PROCUREMENT PLAN Version 2.0 – Date: July 29, 2021 PROGRAM TO ACCELERATE AGRARIAN REFORM (ONE MAP PROJECT) A. Project information: Country: Indonesia Borrower: Republic of Indonesia Project ID: P160661 Financing Agreement IBRD Loan 8897-ID Number: Project Implementation Agency(ies): PMU: Ministry of Agrarian and Spatial Planning (ATR/BPN) PIU: Geospatial Information Agency (BIG) B. Key Dates: 1. Procurement Plan: a. Version 1.0 (for June 4, 2018 negotiation) Bank’s Approval to this June 4, 2018 version: Period covered by this June 4, 2018 – December 31, version: 2023 b. Version 1.9 (previous March 5, 2021 version) Bank’s Approval to this March 12, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 c. Version 2.0 (this version) July 22, 2021 Bank’s Approval to this July 29, 2021 version: Period covered by this June 4, 2018 – December 31, version: 2023 d. [next version, if any] [to be updated] 2. General Procurement April 2019 Notice: C. Preamble All Procurement under the Project shall be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers of July 2016, revised November 2017, and the provisions of the Procurement Plan and Project Operations Manual and shall take precedence over any national procurement regulations. In accordance with paragraph 5.9 of the Procurement Regulations, the Bank’s online procurement planning and tracking tools i.e. Systematic Tracking and Exchanges in Procurement (STEP) will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. D. Key Provisions The following conditions apply to all procurement activities in this Procurement Plan. The Bank’s procurement prior review thresholds: The identified procurement risk under this Project is ‘Substantial’. Accordingly, all contracts listed in the Procurement Plan that are at or above the thresholds set out below are subject to the Bank’s prior review. All other contracts are subject to the Bank’s ex-post review. Table 1. Applied Prior Review Threshold Type of procurement Procurement Prior Review Thresholds (US$ millions) Works (including turnkey, supply & installation of 10 plant and equipment, and PPP) Goods, Information Technology and Non- 2 consulting Services Consultants: Firms 1 Consultants: Individuals 0.3 The Bank’s approved selection methods thresholds: The following selection method thresholds shall apply for procurement of goods & information technology, non-consulting services and consulting services of each identified activity. Table 2. Applied Approved Selection Method Threshold Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International Works (including turnkey, supply & installation of plant and equipment, and PPP) (i) Request for Request for at or above $0.2 and at or above $25 Bids (RFB) less than $25 (ii) Request for Quotations less than $0.2 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Goods, Information Technology and Non-consulting services a. For Goods and Information Technology: (i) Request for Request for at or above $0.1 and at or above $2 Bids (RFB) less than $2 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations b. For Non-consulting Services: (i) Request for Request for at or above $0.1 and at or above $10 Bids (RFB) less than $10 (ii) Request for Quotations less than $0.1 N/A (RFQ) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 6.8, 6.9 paragraph 6.8, 6.9 and 6.10 of the and 6.10 of the Procurement Procurement Regulations Regulations Consultants: firms a. For Selection of Consulting Firms (i) Quality Cost Based Shortlist of firms for at or above $0.4 Selection (QCBS), Fixed contracts below $0.4 Budget Based Selection may comprise (FBS), Least Cost Based entirely national Selection (LCS) and firms Quality Based Selection (QBS) (ii) Consultant’s less than $0.3 N/A Qualifications Based Selection (CQS) (iii) Direct Selection On exceptional basis On exceptional basis if justified as per if justified as per paragraph 7.13, 7.14 paragraph 7.13, 7.14 and 7.15 of the and 7.15 of the Procurement Procurement Regulations Regulations b. For Selection of Individual Consultants (i) Open Competitive All, no monetary All, no monetary Selection of Individual threshold threshold Consultants and Limited Competitive Selection of Individual Consultants Type of procurement and Approved Selection Method Thresholds Approved Selection (US$ millions) Method National International (ii) Direct Selection of On exceptional basis On exceptional basis Individual Consultants if justified as per if justified as per paragraph 7.39 of paragraph 7.39 of the Procurement the Procurement Regulations Regulations Standard Procurement Documents (SPD): The Bank’s SPD shall be used when approaching the international market (specifically for international competitive procurement and those contracts shall be as specified in the Procurement Plan tables in STEP. Use of National Procurement Procedures: In accordance with paragraphs 5.3 of the Procurement Regulations, when approaching the national market all contracts to be procured through open national competitive procurement will follow the GoI’s procurement regulation. The procedures applicable to the procurement of goods and non-consulting services awarded on the basis of open national competitive procurement shall be those of the Tender method as set forth in the Peraturan Presiden No. 16/2018 and its subsequent amendment Peraturan Presiden No. 12/2021) provided that such arrangements continue to meet requirements set forth under paragraph 5.4 of these Regulations and the following conditions: 1. The procurement is open to eligible firms from any country. There shall not any restriction to the bidders’ participation including mandatory requirement to form in joint venture; 2. Any gaps between National Procurement Procedures and the Procurement Regulations will be addressed and incorporated in the harmonized bidding documents acceptable by the Bank. Use of National e-Procurement System (SPSE): Unless informed otherwise by the Bank in writing, SPSE e-procurement system may be used only for procurement of works, goods and non-consulting services under Request for Bids (RFB) method through national open competitive procurement method, applying the harmonized model bidding documents for national open competitive procurement agreed by the Bank. For selection of consulting services through QCBS method, only the modified SPSE (termed by LKPP as SPSE-“ICB”) may be used applying the Bank’s Standard Request for Proposal (RFP) document. The Bank has further accepted GOI’s proposal for use of SPSE-ICB for selection of consulting services through CQS method applying a modified Bank’s Standard RFP. Two consulting services activities (contracts) under other Bank-financed project are being performed as pilot use of SPSE-ICB for CQS method to ensure that the system is working as intended. Since at the present time LKPP has not yet developed the modified SPSE for procurement of goods, works and non-consulting services under international open Competitive method, nor for selection of consulting services under QBS, LCS, FBS, and individual consultant selection methods, therefore procurement of all contract packages under these methods shall be carried out through non- electronic process with manual issuance of specific procurement notice (request for expression of interest or invitation for bids/proposals and receipt of bids/proposals), until such time that the modified SPSE has been completed by LKPP and assessed by the Bank to be acceptable. If the Bank determines the modified SPSE to be acceptable for use under the above- mentioned remaining procurement methods, the Bank will confirm through the Bank’s written no objection to LKPP and will also notify in writing to PMU/PIU. Use of National e-Catalogue System. Based on the Bank’s assessment of the national e-catalogue system, the Bank allows the Project Implementing Units (PIUs) under World Bank financed projects to use the national e- catalogue for procurement of small value of goods in lieu of the Request for Quotations (RFQ) method specified in these Regulations within the parameters as below: a) For Goods (other than medicines) with estimated cost not more than USD 15,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods within the above-specified threshold, if such goods are required under the project and specified in the Procurement Plan approved by the Bank. b) Goods (other than medicines) with estimated cost greater than USD 15,000 but less than USD 100,000 equivalent per contract. PIUs may use the national e-catalogue for procuring such items of goods if such goods are required under the project subject to fulfilling the following additional procedural requirement as below: PMU and PIU shall carry out a secondary procurement process through mini competition, by comparing the prices of similar goods offered by at least three different suppliers which available in the national e-catalogue and then selecting the Supplier with the lowest evaluated price on the basis of “as delivered" price at final destination (i.e., including inland transportation, insurance, applicable taxes and any other incidental charges for the delivery of the required quantity of goods at final destination). E. Other Relevant Procurement Information • Project Operations Manual (POM) shall set out the operating procedures for procurement and contract implementation matters under the Project written in Bahasa, which shall be consistent with the procedures and rules specified under the Bank’s Procurement Regulations. In case of any difference of interpretation between the POM and the Bank’s Procurement Regulations, the later shall prevail; • PMU and PIU may use its own forms of contract for goods/non-consulting services procured under Request for Quotations (RFQ) method when approaching to national market, acceptable to the Bank; • Advance procurement may be applied under the project and shall be valid by signing of the Loan Agreement. PMU and PIU may commence the procurement process prior to issuance of the DIPA for any anticipated activity to be procured under the Project, while signing of the contract shall be subject to issuance of the DIPA of the respective activity. All contracts shall not be designed as single-year contract, and therefore procurement process shall continue throughout multiple calendar years without limitation of contract period up to end of the GoI’s fiscal year; • Regardless of the Bank’s review requirement (prior or post), the Bank may review technical aspects of procurement documents and other non- procurement matters (terms of reference, statement of works, technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in question, if needed; • The Bank will continue to provide guidance and support to the PMU and PIU for procurement processing through the STEP. • Project Implementation Support Personnel shall not be included in this Procurement Plan. Their selection and hiring procedures shall continue to apply the GoI’s selection and hiring procedures as further defined in the POM. The Procurement Plan is a living document and can be revised if there are any changes during the implementation of the project. PROCUREMENT Indonesia : Program to Accelerate Agrarian Reform (One Map Project) PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2019-04-12 2021-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160661 GPN Date: Project Name: Program to Accelerate Agrarian Reform (One Map Project) Loan / Credit No: IBRD / 88970, TF / A7044 Ministry of Agrarian and Spatial Planning / National Land Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ID-ATR/BPN-108910-CW- Project Management, Pending Request for Single Stage - One 2019-12- RFB / Renovation of Archive IBRD / 88970 Institutional Development Post Open - National 165,866.00 0.00 Implementat 2019-04-27 2019-06-22 Quotations Envelope 19 Building/Modern Archive and Monitoring ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108911-GO- RFB / Procurement of hardware for strengthening Participatory Mapping and Single Stage - One Land Information System IBRD / 88970 Prior Request for Bids Open - International 6,652,975.00 0.00 Canceled 2019-04-08 2020-02-19 2020-02-14 2020-04-30 2020-03-30 2020-05-19 2020-05-08 2020-06-29 2020-12-26 Agrarian Reform Envelope (Data Center / Disaster Recovery Center infrastructure) ID-ATR/BPN-194098-GO- RFB / Retender: Procurement of Hardware for Strengthening Participatory Mapping and Single Stage - One Land Information System IBRD / 88970 Prior Request for Bids Open - International 6,170,000.00 6,023,182.50 Signed 2020-09-21 2020-10-12 2020-09-26 2020-10-14 2020-11-07 2020-12-07 2020-12-07 2021-01-22 2021-01-11 2021-02-25 2021-04-11 Agrarian Reform Envelope (Data Center/Disaster Recovery Center Infrastructure) ID-ATR/BPN-108912-GO- Project Management, Single Stage - One RFB / Procurement of upgrade IBRD / 88970 Institutional Development Post Request for Bids Open - National 1,990,639.00 0.00 Canceled 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Envelope office equipment (7 Lots) and Monitoring ID-ATR/BPN-228382-GO- Under RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 254,000.00 0.00 Implementati 2021-04-08 2021-04-14 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-09-28 office equipment Jambi Agrarian Reform Envelope on FY2021 ID-ATR/BPN-228383-GO- Under RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 302,431.00 0.00 Implementati 2021-04-08 2021-04-22 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 office equipment West Agrarian Reform Envelope on Kalimantan FY2021 ID-ATR/BPN-228384-GO- Under RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 273,336.00 0.00 Implementati 2021-04-08 2021-04-14 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 office equipment South Agrarian Reform Envelope on Kalimantan FY 2021 ID-ATR/BPN-228385-GO- Under RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 322,586.00 0.00 Implementati 2021-04-08 2021-04-14 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 office equipment Central Agrarian Reform Envelope on Kalimantan FY2021 ID-ATR/BPN-228386-GO- Pending RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 250,300.00 0.00 Implementati 2021-04-08 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 office equipment East Agrarian Reform Envelope on Kalimantan FY2021 ID-ATR/BPN-228387-GO- Pending Participatory Mapping and Single Stage - One RFB / Procurement of upgrade IBRD / 88970 Post Request for Bids Open - National 236,432.00 0.00 Implementati 2021-04-08 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 Agrarian Reform Envelope office equipment Riau FY2021 on ID-ATR/BPN-228388-GO- Under RFB / Procurement of upgrade Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 351,490.00 0.00 Implementati 2021-04-08 2021-04-14 2021-04-13 2021-05-25 2021-06-08 2021-07-13 2021-10-11 office equipment South Agrarian Reform Envelope on Sumatera FY2021 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-103258-NC- RFB / Pilot Project Fit For Purpose : Project to Accelerate Agrarian Project Management, Reform in Kalimantan Timur Single Stage - One IBRD / 88970 Institutional Development Post Request for Bids Open - National 383,802.00 233,441.69 Signed 2019-03-15 2019-04-08 2019-03-20 2019-04-10 2019-05-09 2019-04-24 2019-05-17 2019-05-15 2019-06-20 2019-10-12 and Kalimantan Selatan Envelope and Monitoring Province Methods: Participatory Mapping (PM) and Collaborative (CO) PTSL ID-ATR/BPN-106238-NC- RFB / Pilot Project Fit For Project Management, Purpose : Single Stage - One IBRD / 88970 Institutional Development Post Request for Bids Open - National 170,968.00 69,189.96 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-19 2020-01-11 Project to Accelerate Agrarian Envelope and Monitoring Reform in Jambi Province Method: General PTSL Page 1 ID-ATR/BPN-106239-NC- RFB / Pilot Project Fit For Purpose : Project to Accelerate Agrarian Project Management, Single Stage - One Reform in Kalimantan Tengah IBRD / 88970 Institutional Development Post Request for Bids Open - National 426,863.00 233,043.91 Signed 2019-03-25 2019-04-09 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-31 2019-07-15 2019-06-20 2020-01-11 Envelope and Kalimantan Barat Province and Monitoring Methods: Community Driven (CD) and Collaborative (CO) PTSL ID-ATR/BPN-106240-NC- RFB / Pilot Project Fit For Purpose Project to Accelerate Agrarian Project Management, Single Stage - One Reform in Riau and Sumatera IBRD / 88970 Institutional Development Post Request for Bids Open - National 342,880.00 232,948.36 Signed 2019-03-25 2019-04-08 2019-03-30 2019-05-11 2019-05-09 2019-06-10 2019-05-17 2019-07-15 2019-06-18 2020-01-11 Envelope Selatan Province and Monitoring Methods: Participatory Mapping (PM) and Community Driven (CD) PTSL ID-ATR/BPN-108465-NC- RFB / Participatory Mapping with Survey (PTSL): 7 lot Participatory Mapping and Single Stage - One (South Sumatera, Riau, Jambi, IBRD / 88970 Post Request for Bids Open - National 9,356,886.00 5,091,529.00 Signed 2019-06-15 2019-08-13 2019-06-20 2019-08-01 2019-09-30 2019-08-31 2019-10-09 2019-10-05 2020-10-23 2020-03-03 Agrarian Reform Envelope West Kalimantan, Central Kalimantan, East Kalimantan, South Kalimantan) ID-ATR/BPN-108475-NC- RFB / Quality Control for Participatory Mapping with Survey (PTSL): 7 lot (South Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,053,482.00 693,358.15 Signed 2019-06-15 2019-11-01 2019-06-20 2019-08-01 2019-11-29 2019-08-31 2019-12-17 2019-10-05 2020-02-18 2020-04-02 Sumatera, Riau, Jambi, West Agrarian Reform Envelope Kalimantan, South Kalimantan, East Kalimantan, Central Kalimantan) ID-ATR/BPN-108601-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 176,407.00 0.00 Implementati 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Technical Assessment of Agrarian Reform Envelope on Forest Boundary Demarcation ID-ATR/BPN-108603-NC- Pending RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 96,429.00 0.00 Implementati 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-01-25 Technical Assessment of Agrarian Reform Envelope on Document Digitation ID-ATR/BPN-108605-NC- RFB / Procurement of IT Participatory Mapping and Single Stage - One Support for Scanning and IBRD / 88970 Post Request for Bids Open - National 1,060,979.00 767,041.41 Signed 2019-06-01 2019-11-11 2019-06-06 2019-07-18 2019-12-06 2019-08-17 2019-12-11 2019-09-21 2020-02-12 2020-03-19 Agrarian Reform Envelope Digital Filing (Digitalization): 7 lots ID-ATR/BPN-108606-NC- RFB / Event Organizer for Project Management, Single Stage - One Workshop Procurement, IBRD / 88970 Institutional Development Post Request for Bids Open - National 140,601.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Financial Management and and Monitoring Project Management ID-ATR/BPN-108607-NC- RFB / Event Organizer for Project Management, Single Stage - One Workshop International IBRD / 88970 Institutional Development Post Request for Bids Open - National 71,429.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Experience on Single Land and Monitoring Administration ID-ATR/BPN-108628-NC- Project Management, Single Stage - One RFB / Event Organizer for IBRD / 88970 Institutional Development Post Request for Bids Open - National 54,739.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Workshop Geospatial Industry and Monitoring ID-ATR/BPN-108602-NC- Participatory Mapping and Single Stage - One RFB / Forest Boundary IBRD / 88970 Post Request for Bids Open - National 1,505,248.00 1,104,413.53 Signed 2019-06-01 2020-03-09 2020-02-20 2020-03-20 2020-08-06 2020-03-31 2020-08-25 2020-04-27 2020-09-22 2020-10-24 Agrarian Reform Envelope Demarcation: 5 lots ID-ATR/BPN-202001-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 3,100,000.00 2,324,630.07 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-24 2020-12-04 Agrarian Reform Envelope (220.000 parcel with 5 lots) of South Sumatera 2020 ID-ATR/BPN-202002-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,523,222.39 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-28 2020-12-04 Agrarian Reform Envelope (280.000 parcel with 7 lots) of West Kalimantan 2020 ID-ATR/BPN-202003-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 5,000,000.00 3,724,942.67 Signed 2020-04-27 2020-05-04 2020-05-01 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-06 2020-09-11 2020-12-03 Agrarian Reform Envelope (280.000 parcel with 6 lots) of South Kalimantan 2020 ID-ATR/BPN-202004-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Prior Request for Bids Open - National 3,900,000.00 2,815,680.48 Signed 2020-04-27 2020-05-04 2020-05-02 2020-06-02 2020-06-29 2020-06-16 2020-08-11 2020-07-07 2020-09-23 2020-12-04 Agrarian Reform Envelope (220.000 parcel with 5 lots) of Central Kalimantan 2020 ID-ATR/BPN-177786-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,670,000.00 1,014,800.07 Signed 2020-03-16 2020-05-06 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-11 2020-10-27 Agrarian Reform Envelope (90.000 parcel with 2 lots) of Riau 2020 ID-ATR/BPN-177794-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,550,000.00 1,103,375.81 Signed 2020-03-16 2020-05-05 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-12 2020-10-27 Agrarian Reform Envelope (110.000 parcel with 3 lots) of Jambi 2020 ID-ATR/BPN-177789-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Fase-3 IBRD / 88970 Post Request for Bids Open - National 1,850,000.00 1,257,319.45 Signed 2020-03-16 2020-05-05 2020-03-21 2020-05-02 2020-06-10 2020-06-01 2020-07-01 2020-06-29 2020-08-04 2020-10-27 Agrarian Reform Envelope (100.000 parcel with 2 lots) of East Kalimantan 2020 Page 2 ID-ATR/BPN-177801-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 258,000.00 170,269.09 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-06-15 2020-07-07 2020-07-06 2020-10-19 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of South Sumatera 2020 ID-ATR/BPN-177796-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 106,000.00 65,220.93 Signed 2020-04-15 2020-06-19 2020-04-20 2020-06-01 2020-07-17 2020-06-15 2020-07-24 2020-07-06 2020-10-21 2020-11-03 Participatory Mapping with Agrarian Reform Envelope Survey (PTSL) of Riau 2020 ID-ATR/BPN-177803-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 130,000.00 89,775.81 Signed 2020-04-15 2020-05-29 2020-04-20 2020-06-01 2020-06-29 2020-06-15 2020-07-07 2020-07-06 2020-08-28 2020-11-03 Participatory Mapping with Agrarian Reform Envelope Survey (PTSL) of Jambi 2020 ID-ATR/BPN-177806-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 348,000.00 229,358.50 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-07-01 2020-07-07 2020-07-29 2020-10-27 2020-11-26 Agrarian Reform Envelope Survey (PTSL) of West Kalimantan 2020 ID-ATR/BPN-177799-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 348,000.00 241,430.00 Signed 2020-04-15 2020-06-03 2020-04-20 2020-06-01 2020-07-01 2020-06-15 2020-07-08 2020-07-06 2020-10-05 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of South Kalimantan 2020 ID-ATR/BPN-177804-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 125,000.00 79,001.42 Signed 2020-04-15 2020-05-29 2020-04-20 2020-06-01 2020-06-29 2020-06-15 2020-07-07 2020-07-06 2020-09-08 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of East Kalimantan 2020 ID-ATR/BPN-177809-NC- RFB / Quality Control for Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 273,000.00 179,830.86 Signed 2020-04-15 2020-05-27 2020-04-20 2020-06-01 2020-06-24 2020-06-15 2020-07-07 2020-07-06 2020-10-13 2020-11-03 Agrarian Reform Envelope Survey (PTSL) of Central Kalimantan 2020 ID-ATR/BPN-192782-NC- Pending RFQ / Event Organizer (EO) for Participatory Mapping and Request for Single Stage - One IBRD / 88970 Post Limited 121,000.00 0.00 Implementati 2020-08-08 2020-09-19 2020-11-18 Forest Boundary Demarcation Agrarian Reform Quotations Envelope on Coordination Meetings ID-ATR/BPN-204226-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-4 IBRD / 88970 Post Request for Bids Open - National 1,689,722.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (140.000 parcel) of Riau 2021 on - (3 Lots) ID-ATR/BPN-204231-NC- RFB / Participatory Mapping Pending Participatory Mapping and Single Stage - One with Survey (PTSL) Phase IBRD / 88970 Post Request for Bids Open - National 1,736,319.00 0.00 Implementati 2020-11-06 2020-11-11 2020-12-23 2021-01-22 2021-02-26 2021-07-26 Agrarian Reform Envelope (110.000 parcel) of East on Kalimantan 2021 - ( 3 Lots) ID-ATR/BPN-203978-NC- RFB / Participatory Mapping Under Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-4 IBRD / 88970 Prior Request for Bids Open - National 3,620,833.00 0.00 Implementati 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-26 Agrarian Reform Envelope (300.000 parcel) of South on Sumatera 2021 - (7 Lots) ID-ATR/BPN-204229-NC- RFB / Participatory Mapping Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-2 IBRD / 88970 Prior Request for Bids Open - National 2,655,277.00 1,889,294.58 Signed 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-02-01 2021-01-22 2021-04-01 2021-02-26 2021-05-31 2021-07-26 Agrarian Reform Envelope (220.000 parcel) of Jambi 2021 - (6 Lots) ID-ATR/BPN-203979-NC- RFB / Participatory Mapping Under Participatory Mapping and Single Stage - One with Survey (PTSL) Phase IBRD / 88970 Prior Request for Bids Open - National 4,735,416.00 0.00 Implementati 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-26 Agrarian Reform Envelope (300.000 parcel) of South on Kalimantan 2021 (8 Lots) ID-ATR/BPN-204232-NC- RFB / Participatory Mapping Under Participatory Mapping and Single Stage - One with Survey (PTSL) phase IBRD / 88970 Prior Request for Bids Open - National 3,472,638.00 552,319.93 Implementati 2020-11-06 2020-12-01 2020-11-11 2020-12-23 2021-01-20 2021-01-22 2021-04-01 2021-02-26 2021-07-26 Agrarian Reform Envelope (220.000 parcel) of Central on Kalimantan 2021 - (5 Lots) ID-ATR/BPN-203977-NC- RFB / Quality Control for Under Participatory Mapping and Single Stage - One Participatory Mapping with IBRD / 88970 Post Request for Bids Open - National 1,979,166.00 0.00 Implementati 2021-01-05 2020-12-10 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-09-24 Agrarian Reform Envelope Survey Phase 4 (PTSL) in 7 on Provinces FY 2021 (7 Lots) ID-ATR/BPN-203975-NC- RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Prior Request for Bids Open - National 2,975,000.00 0.00 Canceled 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-09-19 Digitalization in 7 Provinces Agrarian Reform Envelope FY2021 (7 Lots) ID-ATR/BPN-204227-NC- RFB / Participatory Mapping Under Participatory Mapping and Single Stage - One with Survey (PTSL) Phase-4 IBRD / 88970 Prior Request for Bids Open - National 5,208,958.00 0.00 Implementati 2020-11-23 2020-12-01 2020-11-28 2021-01-09 2021-01-20 2021-02-08 2021-04-01 2021-03-15 2021-08-12 Agrarian Reform Envelope (330.000 parcel) of West on Kalimantan 2021 - (7 Lots) ID-ATR/BPN-213581-NC- RFB / Thematic Map of Land and Spatial in the Context of Project Management, Accelerating Land Single Stage - One IBRD / 88970 Institutional Development Post Request for Bids Open - National 303,936.00 259,657.86 Signed 2021-01-13 2021-01-18 2021-01-18 2021-03-01 2021-02-26 2021-03-31 2021-03-16 2021-04-28 2021-04-19 2021-07-17 Redistribution of Objects for Envelope and Monitoring Agrarian Reform from Forest Area Based on Spatial Planning and Environment (Pilot Project) ID-ATR/BPN-188254-NC- RFB / PTPR Thematic Map of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,810,803.33 998,589.67 Signed 2020-08-12 2020-09-29 2020-08-17 2020-09-28 2020-10-27 2020-10-28 2020-11-17 2020-11-25 2020-12-16 2020-12-31 Land and Spatial (PTPR) (4 Agrarian Reform Envelope Lots) Page 3 ID-ATR/BPN-222685-NC- RFB / ID-ATR/BPN-203975- Pending NC-RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 375,000.00 0.00 Implementati 2021-03-05 2021-03-10 2021-04-21 2021-05-21 2021-06-25 2021-07-07 Digitalization in South Agrarian Reform Envelope on Sumatera Province FY2021 (7 Lots) ID-ATR/BPN-222924-NC- RFB / ID-ATR/BPN-203975- Under Participatory Mapping and Single Stage - One NC-RFB / Procurement of IBRD / 88970 Post Request for Bids Open - National 375,000.00 0.00 Implementati 2021-03-05 2021-04-14 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Agrarian Reform Envelope Digitalization in South Riau on FY2021 (5 Lots) ID-ATR/BPN-222925-NC- RFB / ID-ATR/BPN-203975- Under NC-RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 458,333.00 0.00 Implementati 2021-03-05 2021-04-14 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Digitalization in East Agrarian Reform Envelope on Kalimantan Province FY2021 (5 Lots) ID-ATR/BPN-222927-NC- RFB / ID-ATR/BPN-203975- Pending NC-RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 375,000.00 0.00 Implementati 2021-03-05 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Digitalization in Central Agrarian Reform Envelope on Kalimantan Province FY2021 (5 Lots) ID-ATR/BPN-222928-NC- RFB / ID-ATR/BPN-203975- Under NC-RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 425,000.00 0.00 Implementati 2021-03-05 2021-03-21 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Digitalization in South Agrarian Reform Envelope on Kalimantan Province FY2021 (6 Lots) ID-ATR/BPN-222930-NC- RFB / ID-ATR/BPN-203975- Pending NC-RFB / Procurement of Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 483,333.00 0.00 Implementati 2021-03-05 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Digitalization in West Agrarian Reform Envelope on Kalimantan Province FY2021 (6 Lots) ID-ATR/BPN-222931-NC- RFB / ID-ATR/BPN-203975- Under Participatory Mapping and Single Stage - One NC-RFB / Procurement of IBRD / 88970 Post Request for Bids Open - National 483,333.00 0.00 Implementati 2021-03-05 2021-04-14 2021-03-10 2021-04-21 2021-05-21 2021-06-18 2021-09-16 Agrarian Reform Envelope Digitalization in Jambi on Province FY2021 (5 Lots) ID-ATR/BPN-203980-NC- Under RFB / Forest Area Boundary Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,433,938.00 0.00 Implementati 2021-01-05 2021-06-10 2021-01-10 2021-02-21 2021-03-23 2021-04-27 2021-07-13 Situation Map FY 2021 (multi Agrarian Reform Envelope on Lots) ID-ATR/BPN-177811-NC- RFB / Procurement of IT Support for Scanning and Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 1,698,472.00 0.00 Canceled 2020-04-27 2020-05-02 2020-06-13 2020-07-13 2020-08-10 2020-12-08 Digital Filing (Digitalization) Agrarian Reform Envelope 2020 7 (seven) Provinces / 7 (seven) Lot ID-ATR/BPN-108631-NC- Project Management, Single Stage - One RFB / Event Organizer for IBRD / 88970 Institutional Development Post Request for Bids Open - National 714,286.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Envelope Public Campaign and Monitoring ID-ATR/BPN-108632-NC- RFB / Event Organizer for Participatory Mapping and Single Stage - One IBRD / 88970 Post Request for Bids Open - National 142,857.00 0.00 Canceled 2019-06-01 2019-06-06 2019-07-18 2019-08-17 2019-09-21 2020-03-19 Implementation Assessment Agrarian Reform Envelope on Pres Decree No. 86/2018 ID-ATR/BPN-232937-NC- Pending RFQ / Event Organizer for Participatory Mapping and Request for Single Stage - One IBRD / 88970 Post Limited 55,918.00 0.00 Implementati 2021-05-09 2021-06-27 2021-08-11 Coordination Meeting Forest Agrarian Reform Quotations Envelope on Area Boundary FY 2021 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-106571-CS- QCBS / Method Analysis and Project Management, Quality And Cost- Under Quality Control of Pilot Project IBRD / 88970 Institutional Development Post Open - National 128,571.00 0.00 2019-06-03 2019-07-10 2019-06-24 2019-08-07 2019-07-10 2019-09-04 2019-07-11 2019-10-04 2019-11-08 2019-12-13 2020-12-12 Based Selection Implementation Fit For Purpose Cadastral and Monitoring Mapping ID-ATR/BPN-108901-CS- QCBS / Consulting Services Participatory Mapping and Quality And Cost- Pending for Development of Land IBRD / 88970 Prior Open - International 2,331,034.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 Agrarian Reform Based Selection Implementation Information System, portal and e-Services ID-ATR/BPN-108902-CS- QCBS / Pilot Project Analysis Project Management, Quality And Cost- Pending Consultant and Data Quality IBRD / 88970 Institutional Development Post Open - National 128,571.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 Based Selection Implementation Control for Participatory and Monitoring Mapping ID-ATR/BPN-108903-CS- Project Management, QCBS / Legal and Institutional Quality And Cost- Pending IBRD / 88970 Institutional Development Post Open - National 85,714.00 0.00 2019-05-01 2019-05-22 2019-07-05 2019-08-02 2019-09-01 2019-10-06 2019-11-10 2020-11-09 Framework Consulting Based Selection Implementation and Monitoring Services ID-ATR/BPN-108907-CS- QCBS / Consulting Services Project Management, Quality And Cost- Pending for Project Management IBRD / 88970 Institutional Development Post Open - National 142,857.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 Based Selection Implementation Information System and Monitoring Development ID-ATR/BPN-108908-CS- Project Management, QCBS / Consulting Services Quality And Cost- Pending IBRD / 88970 Institutional Development Post Open - International 607,143.00 0.00 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 for Communication and Public Based Selection Implementation and Monitoring Relations Page 4 ID-ATR/BPN-116152-CS- Geospatial Data QCBS / Consulting Services Infrastructure for Quality And Cost- Pending TF / A7044 Post Open - National 107,143.00 0.00 2019-06-24 2019-07-15 2019-07-29 2019-08-26 2019-09-02 2019-09-12 2019-10-03 2020-03-31 for Review Geospatial Data Environmental and Natural Based Selection Implementation Infrastructure an Services Resource Management ID-ATR/BPN-219895-CS- Consultant CQS / Preparation of Archive Participatory Mapping and IBRD / 88970 Post Qualification Open - National 8,621.00 0.00 Under Review 2021-02-26 2021-04-30 2021-03-19 2021-04-16 2021-05-16 2021-06-13 2021-09-11 Building/Modern Archive (DED Agrarian Reform Selection - Planning) ID-ATR/BPN-108906-CS- Project Management, QCBS / Vulnerability Mapping, Quality And Cost- IBRD / 88970 Institutional Development Post Open - National 321,429.00 0.00 Canceled 2019-05-05 2019-05-26 2019-07-09 2019-08-06 2019-09-05 2019-10-10 2019-11-14 2020-11-13 social monitoring and impact Based Selection and Monitoring assessment INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ID-ATR/BPN-108914-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Open 37,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Advisor and Monitoring Selection ID-ATR/BPN-108917-CS- Project Management, Individual Pending INDV / Safeguards IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-108918-CS- Project Management, Individual Pending INDV / Monitoring and IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Evaluation Specialist and Monitoring Selection ID-ATR/BPN-108919-CS- Project Management, Individual Pending INDV / Communication IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-108920-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 22,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / ICT specialist Implementation and Monitoring Selection ID-ATR/BPN-108921-CS- Project Management, Individual Pending INDV / Legal expert ( IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation consultant on land law policy) and Monitoring Selection Project Management, Individual ID-ATR/BPN-108922-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 56,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Liasion PCC Implementation and Monitoring Selection ID-ATR/BPN-108923-CS- Project Management, Individual Pending INDV / Strategic Planning IBRD / 88970 Institutional Development Post Consultant Open 125,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist (International) and Monitoring Selection ID-ATR/BPN-108924-CS- Project Management, Individual INDV / Social and Pending IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Environmental Specialist for Implementation and Monitoring Selection Pilot Participatory Mapping Project Management, Individual ID-ATR/BPN-108925-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / FM Assistant Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-108926-CS- IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 Under Review 2019-04-24 2019-05-01 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Procurement Assistant and Monitoring Selection ID-ATR/BPN-108927-CS- Project Management, Individual INDV / Junior Public IBRD / 88970 Institutional Development Post Consultant Open 12,500.00 0.00 Under Review 2019-04-24 2019-05-01 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Awareness Specilaist and Monitoring Selection ID-ATR/BPN-108928-CS- Project Management, Individual Pending INDV / Junior Public IBRD / 88970 Institutional Development Post Consultant Open 52,500.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Awareness Specilaist and Monitoring Selection ID-ATR/BPN-108929-CS- Project Management, Individual Pending INDV / Regional Project IBRD / 88970 Institutional Development Post Consultant Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Technical Advisor and Monitoring Selection ID-ATR/BPN-108930-CS- Project Management, Individual Pending INDV / Regional Project IBRD / 88970 Institutional Development Post Consultant Open 140,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Operations Advisor and Monitoring Selection Project Management, Individual ID-ATR/BPN-108931-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 20,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Project Administrator Implementation and Monitoring Selection ID-ATR/BPN-108915-CS- Project Management, Individual Pending INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 Implementation Specialist and Monitoring Selection ID-ATR/BPN-116146-CS- Project Management, Individual Under INDV / Project Management TF / A7044 Institutional Development Post Consultant Open 26,786.00 0.00 2018-12-03 2018-10-01 2018-12-22 2018-12-24 2019-01-01 2019-05-31 Implementation Advisor and Monitoring Selection ID-ATR/BPN-116153-CS- Project Management, Individual Under INDV / Communication TF / A7044 Institutional Development Post Consultant Open 14,286.00 0.00 2019-02-01 2019-01-23 2019-02-23 2019-03-02 2019-03-15 2019-05-31 Implementation Specialist and Monitoring Selection ID-ATR/BPN-116154-CS- Project Management, Individual Pending INDV / Safeguards TF / A7044 Institutional Development Post Consultant Open 8,571.00 0.00 2019-01-02 2019-01-19 2019-01-22 2019-02-01 2019-05-31 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-116151-CS- Project Management, Individual Pending INDV / Monitoring & TF / A7044 Institutional Development Post Consultant Open 7,500.00 0.00 2019-02-18 2019-02-26 2019-02-27 2019-03-01 2019-05-31 Implementation Evaluation Specilaist and Monitoring Selection Page 5 ID-ATR/BPN-116145-CS- Project Management, Individual Pending INDV / Junior Public TF / A7044 Institutional Development Post Consultant Open 6,429.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 Implementation Awareness Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-116148-CS- Pending TF / A7044 Institutional Development Post Consultant Open 10,714.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 INDV / PCC Liaison Officer Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-116147-CS- Pending TF / A7044 Institutional Development Post Consultant Open 12,857.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-07 INDV / Legal Advisor Implementation and Monitoring Selection ID-ATR/BPN-116150-CS- Project Management, Individual Pending INDV / Survey and Mapping TF / A7044 Institutional Development Post Consultant Open 12,429.00 0.00 2019-05-24 2019-06-04 2019-06-06 2019-06-10 2019-12-31 Implementation Specialist for Pilot Project and Monitoring Selection ID-ATR/BPN-116149-CS- Project Management, Individual Pending INDV / Assistant Safeguard TF / A7044 Institutional Development Post Consultant Open 3,750.00 0.00 2019-05-24 2019-06-07 2019-06-09 2019-06-13 2019-11-30 Implementation Coordinator and Monitoring Selection Project Management, Individual ID-ATR/BPN-108916-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 30,000.00 0.00 2019-04-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 INDV / Procurement Specialist Implementation and Monitoring Selection ID-ATR/BPN-177827-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Direct 59,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Advisor and Monitoring Selection ID-ATR/BPN-177834-CS- Project Management, Individual Pending INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Direct 37,250.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-177837-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 45,500.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Procurement Specialist Implementation and Monitoring Selection ID-ATR/BPN-178294-CS- Project Management, Individual Pending INDV / Monitoring and IBRD / 88970 Institutional Development Post Consultant Direct 28,200.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Evaluation Consultant and Monitoring Selection ID-ATR/BPN-177842-CS- Project Management, Individual Pending INDV / Safeguards IBRD / 88970 Institutional Development Post Consultant Direct 24,900.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Coordinator and Monitoring Selection ID-ATR/BPN-177843-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 1 (Sumsel) and Monitoring Selection ID-ATR/BPN-178145-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 2 (Jambi) and Monitoring Selection ID-ATR/BPN-178144-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 3 (Riau) and Monitoring Selection ID-ATR/BPN-178143-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 4 (Kalbar) and Monitoring Selection ID-ATR/BPN-178122-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 5 (Kalteng) and Monitoring Selection ID-ATR/BPN-178140-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 6 (Kaltim) and Monitoring Selection ID-ATR/BPN-178141-CS- Project Management, Individual Pending INDV / Public Awareness IBRD / 88970 Institutional Development Post Consultant Direct 16,600.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist 7 (Kalsel) and Monitoring Selection ID-ATR/BPN-178299-CS- Project Management, Individual INDV / Program Officer (5 Pending IBRD / 88970 Institutional Development Post Consultant Direct 40,000.00 0.00 2020-01-15 2020-01-18 2020-01-19 2020-01-27 2020-12-31 Person) and Access Reform Implementation and Monitoring Selection Officer (1 Person) Project Management, Individual ID-ATR/BPN-178296-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 33,100.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / PCC Liaison Adviser Implementation and Monitoring Selection ID-ATR/BPN-177840-CS- Project Management, Individual Pending INDV / Communication IBRD / 88970 Institutional Development Post Consultant Direct 29,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-178302-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / PCC liaison Officer Implementation and Monitoring Selection ID-ATR/BPN-177836-CS- Project Management, Individual INDV / Financial Management IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 Under Review 2019-12-20 2019-05-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 Assistant and Monitoring Selection Project Management, Individual ID-ATR/BPN-177839-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 21,000.00 0.00 2019-12-20 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Procurement Assistant Implementation and Monitoring Selection Project Management, Individual ID-ATR/BPN-178148-CS- IBRD / 88970 Institutional Development Post Consultant Direct 12,500.00 0.00 Under Review 2019-12-20 2019-08-01 2019-12-23 2019-12-24 2020-01-01 2020-12-31 INDV / Graphic Designer and Monitoring Selection ID-ATR/BPN-177831-CS- Project Management, Individual Pending INDV / Project Management IBRD / 88970 Institutional Development Post Consultant Open 13,800.00 0.00 2019-12-20 2020-02-07 2020-02-28 2020-03-27 2020-12-31 Implementation Assistant and Monitoring Selection Page 6 Project Management, Individual ID-ATR/BPN-178119-CS- Pending IBRD / 88970 Institutional Development Post Consultant Direct 37,250.00 0.00 2019-12-20 2019-12-26 2019-12-28 2020-01-02 2020-12-31 INDV / Legal Specialist Implementation and Monitoring Selection ID-ATR/BPN-181543-CS- Project Management, Individual Pending INDV / Survey and Mapping IBRD / 88970 Institutional Development Post Consultant Open 11,750.00 0.00 2020-07-01 2020-08-04 2020-08-11 2020-09-01 2021-02-28 Implementation Specialist and Monitoring Selection ID-ATR/BPN-178301-CS- Project Management, Individual Pending INDV / Transformation Digital IBRD / 88970 Institutional Development Post Consultant Direct 6,200.00 0.00 2020-01-15 2020-01-18 2020-01-19 2020-01-27 2020-07-25 Implementation Specialist [National] and Monitoring Selection ID-ATR/BPN-178298-CS- Project Management, Individual Pending INDV / Land Tenure Expert IBRD / 88970 Institutional Development Post Consultant Open 10,400.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation (National) and Monitoring Selection ID-ATR/BPN-178297-CS- Project Management, Individual Pending INDV / Land Tenure Expert IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation (International ) and Monitoring Selection ID-ATR/BPN-178150-CS- Project Management, Individual INDV / Knowledge IBRD / 88970 Institutional Development Post Consultant Open 10,400.00 0.00 Under Review 2020-01-15 2020-03-02 2020-03-04 2020-03-18 2020-04-08 2020-12-31 Management & Data Officer and Monitoring Selection ID-ATR/BPN-187783-CS- Project Management, Individual Pending INDV / Spatial Analyst for IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-15 2020-12-31 Implementation Land Parcels Sp. and Monitoring Selection ID-ATR/BPN-178295-CS- Project Management, Individual Pending INDV / Transformation Digital IBRD / 88970 Institutional Development Post Consultant Open 51,800.00 0.00 2020-01-15 2020-03-04 2020-03-18 2020-04-22 2020-10-19 Implementation Specialist [International] and Monitoring Selection ID-ATR/BPN-178300-CS- Project Management, Individual Pending INDV / Capacity Building IBRD / 88970 Institutional Development Post Consultant Open 2,800.00 0.00 2020-06-05 2020-07-24 2020-08-07 2020-09-11 2020-10-01 Implementation Specialist and Monitoring Selection Project Management, Individual ID-ATR/BPN-181544-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 21,000.00 0.00 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2020-08-28 INDV / Consultant 3D Implementation and Monitoring Selection ID-ATR/BPN-187781-CS- Project Management, Individual INDV / Legal Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187780-CS- Project Management, Individual INDV / Financial Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187777-CS- Project Management, Individual INDV / IT Specialist Pending IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 2020-08-03 2020-09-21 2020-10-05 2020-11-02 2020-12-31 (Supporting for Implementation and Monitoring Selection Transformation digital) ID-ATR/BPN-187797-CS- Project Management, Individual INDV / Feedback and Pending IBRD / 88970 Institutional Development Post Consultant Open 8,333.00 0.00 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2020-12-31 Grievance Redress Mechanism Implementation and Monitoring Selection (FGRM) Officer ID-ATR/BPN-187776-CS- INDV / Project Planning and Project Management, Individual Management Specialist IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187772-CS- INDV / Project Risk Project Management, Individual Management Specialist IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187770-CS- INDV / Land Information Project Management, Individual System Development IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 33,058.25 Signed 2020-08-03 2020-08-24 2020-08-13 2020-06-24 2020-08-27 2020-09-10 2020-09-24 2020-09-11 2020-12-31 Specialist (Supporting for and Monitoring Selection Transformation Digital) ID-ATR/BPN-187774-CS- Project Management, Individual INDV / Digital Communication Under IBRD / 88970 Institutional Development Post Consultant Direct 52,083.00 0.00 2020-08-03 2020-08-24 2020-08-13 2020-08-27 2020-09-24 2020-12-31 Specialist (Supporting for Implementation and Monitoring Selection Transformation Digital) ID-ATR/BPN-187799-CS- Project Management, Individual Pending INDV / Administrator Support IBRD / 88970 Institutional Development Post Consultant Open 21,875.00 0.00 2020-08-07 2020-09-25 2020-10-09 2020-11-06 2020-12-31 Implementation at 7 Provinces (7 Packages) and Monitoring Selection Project Management, Individual ID-ATR/BPN-201161-CS- Pending TF / A7044 Institutional Development Post Consultant Direct 6,944.00 0.00 2020-10-25 2020-11-02 2020-11-07 2020-11-15 2020-12-30 INDV / Risk Screening Support Implementation and Monitoring Selection ID-ATR/BPN-203395-CS- Project Management, Individual INDV / Project Manager for IBRD / 88970 Institutional Development Post Consultant Open 10,417.00 0.00 Under Review 2020-09-01 2020-09-01 2020-09-27 2020-10-04 2020-10-25 2020-12-31 PMO Digital Transformation and Monitoring Selection ID-ATR/BPN-203397-CS- Project Management, Individual INDV / Safeguard Specialist IBRD / 88970 Institutional Development Post Consultant Open 3,125.00 0.00 Canceled 2020-09-01 2021-03-04 2020-09-27 2020-10-11 2020-11-01 2020-12-31 for Pilot Project Land and Monitoring Selection Redistribution ID-ATR/BPN-203401-CS- Project Management, Individual INDV / Project Management Under IBRD / 88970 Institutional Development Post Consultant Open 3,160.00 0.00 2020-09-01 2021-03-04 2020-09-27 2020-10-11 2020-11-01 2020-12-31 Assistant for Pilot Project Land Implementation and Monitoring Selection Redistribution Page 7 ID-ATR/BPN-203400-CS- Project Management, Individual INDV / Communication Pending IBRD / 88970 Institutional Development Post Consultant Open 3,125.00 0.00 2020-09-01 2020-09-27 2020-10-11 2020-11-01 2020-12-31 Specialit for Pilot Project Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-203402-CS- Project Management, Individual INDV / Procurement Assistant- IBRD / 88970 Institutional Development Post Consultant Open 3,472.00 1,750.00 Signed 2020-10-01 2020-11-27 2020-10-27 2020-12-16 2020-11-10 2020-12-21 2020-12-01 2021-01-04 2020-12-31 2 (short term) and Monitoring Selection Project Management, Individual ID-ATR/BPN-204256-CS- Pending IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2020-11-13 2021-01-01 2021-01-15 2021-02-05 2021-12-22 INDV / Stategic Planner (PMU) Implementation and Monitoring Selection ID-ATR/BPN-204250-CS- Project Management, Individual INDV / Community Under IBRD / 88970 Institutional Development Post Consultant Open 8,160.00 0.00 2021-01-05 2021-03-04 2021-02-23 2021-03-09 2021-04-06 2021-09-03 Empowerment Consultant for Implementation and Monitoring Selection Land Redistribution ID-ATR/BPN-204251-CS- Project Management, Individual INDV / Social Safeguard and Under IBRD / 88970 Institutional Development Post Consultant Open 4,896.00 0.00 2021-01-05 2020-11-05 2021-02-23 2021-03-09 2021-03-30 2021-06-28 Complaint Handling for Land Implementation and Monitoring Selection Redistribution ID-ATR/BPN-204246-CS- Project Management, Individual INDV / TORA Potential IBRD / 88970 Institutional Development Post Consultant Open 114,236.00 0.00 Canceled 2020-12-01 2021-01-19 2021-02-02 2021-02-23 2021-12-20 Analysis Consultant for Land and Monitoring Selection Redistribution (7 Consultants) ID-ATR/BPN-204244-CS- Project Management, Individual INDV / Bilingual Secretary for IBRD / 88970 Institutional Development Post Consultant Open 5,347.00 0.00 Canceled 2021-01-05 2021-03-04 2021-02-23 2021-03-16 2021-04-20 2021-11-16 Land Redistribution and Monitoring Selection ID-ATR/BPN-204254-CS- Project Management, Individual INDV / Supporting Staffs for Under IBRD / 88970 Institutional Development Post Consultant Open 7,778.00 0.00 2021-01-05 2021-03-04 2021-02-23 2021-03-09 2021-03-30 2021-10-26 Land Redistribution (2 Implementation and Monitoring Selection Consultants) ID-ATR/BPN-219903-CS- Individual INDV / QC Renovation of Participatory Mapping and Pending IBRD / 88970 Post Consultant Open 5,172.00 0.00 2021-02-19 2021-03-24 2021-04-07 2021-05-05 2021-11-01 Archive Building/Modern Agrarian Reform Implementation Selection Archive ID-ATR/BPN-204257-CS- Project Management, Individual Under INDV / Strategic Program IBRD / 88970 Institutional Development Post Consultant Open 25,000.00 0.00 2021-03-23 2021-02-01 2021-04-25 2021-05-09 2021-05-16 2021-08-14 Implementation Officer (2 person) and Monitoring Selection ID-ATR/BPN-243281-CS- Individual Participatory Mapping and Pending INDV / SPIP Facilitator (4 IBRD / 88970 Post Consultant Direct 66,200.00 0.00 2021-07-13 2021-07-23 2021-08-06 2021-09-03 2022-03-02 Agrarian Reform Implementation Positions) Selection ID-ATR/BPN-243285-CS- Individual Participatory Mapping and Pending INDV / SPIP Coordinator (1 IBRD / 88970 Post Consultant Direct 20,600.00 0.00 2021-07-13 2021-07-23 2021-08-06 2021-09-03 2022-03-02 Agrarian Reform Implementation Position) Selection ID-ATR/BPN-243302-CS- INDV / Governance, Forestry Individual Participatory Mapping and Pending and Environmental Policy IBRD / 88970 Post Consultant Open 8,100.00 0.00 2021-07-13 2021-08-31 2021-09-21 2021-10-26 2022-03-25 Agrarian Reform Implementation Consultant for Land Selection Redistribution ID-ATR/BPN-243312-CS- INDV / Data Management Individual Participatory Mapping and Pending Consultant and IBRD / 88970 Post Consultant Open 7,500.00 0.00 2021-07-13 2021-08-31 2021-09-21 2021-10-26 2022-03-25 Agrarian Reform Implementation Reporting for Pilot Project Selection Land Redistribution ID-ATR/BPN-204249-CS- Project Management, Individual INDV / Business Process and Pending IBRD / 88970 Institutional Development Post Consultant Open 8,000.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-04-06 2021-11-02 Regulation Consultant for Implementation and Monitoring Selection Land Redistribution ID-ATR/BPN-204248-CS- Project Management, Individual INDV / Land Use Planning Pending IBRD / 88970 Institutional Development Post Consultant Open 32,400.00 0.00 2021-01-05 2021-02-23 2021-03-09 2021-03-30 2021-06-28 Consultant for Land Implementation and Monitoring Selection Redistribution (4 Positions) ID-ATR/BPN-204245-CS- INDV / Agrarian Reform Project Management, Individual Pending Assessment Consultant for IBRD / 88970 Institutional Development Post Consultant Open 32,400.00 0.00 2020-12-01 2021-01-19 2021-02-02 2021-02-23 2021-12-20 Implementation Land Redistribution (4 and Monitoring Selection Consultants) Page 8