MIZORAM STATE ROADS II- REGIONAL TRANSPORT CONNECTIVITY PROJECT Project ID: P145778 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 04, 2014 2. Date of General Procurement Notice: May 25, 2013 updated on February 20, 2014 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1. Procurement Thresholds, Methods and Value thresholds for Civil Works Expenditure Value* (Threshold per Procurement Contracts subjected to Prior Category contract) Method Review/Post Review Civil Works (a) Civil Works estimated to Shopping Post review only cost equivalent to US$ (Minimum 3 100,000 or less per contract. quotations) Force Account, if Post review only any (b) Roads (Civil Works) National First NCB works contract estimated to cost more than Competitive regardless of value, and all other the equivalent to US$ Bidding (NCB) contracts above US$ 5 million 100,000 per contract and are subject to prior review. less than US$ 40 Million. (c) Roads (Civil Works) International All ICB contracts >US$ 5 millon estimated to cost more than Competitive value will be subject to prior US$ 40 million. Bidding (ICB) review. * If bids are called concurrently for several contracts in a package and the PIU invites cross discounts, the aggregate value of the total package will form the basis to determine the procurement method as well as the prior review threshold requirements All amendments to prior review contracts > 15% in contract value or time will be subject to prior review March 04, 2014 Table 2. Methods and Value Thresholds for Goods Goods & and Non- Value Threshold Methods Review Arrangements Consulting Services Equipment, (i) US$ 100,000 equivalent or Shopping Post review only Machinery, less per contract. (Minimum 3 Vehicles, Furniture, quotations) IT Systems and Non- (ii) Proprietary equipment; Direct Prior review above Consulting Services software; print, audio or visual Contracting contracts worth US$ etc. educational publications; and 50,000 with other learning resources justifications as per irrespective of value. Guidelines. (iii) Contracts of more than National First contract regardless US$ 100,000 equivalent but Competitive of value and all other less than US$ 3 Million Bidding (NCB) contracts above US$ 0.5 equivalent. million are subject to prior review by the Bank. (iv) Contracts of more than International All ICB contracts >0.5 US$ 3 Million equivalent. Competitive million are subject to Bidding (ICB) Prior review by the Bank. (v) Framework Agreement As per Para 3.6 All FAs are subject to (FA) @ Subject to inclusion of of GL review for acceptance. “FA” as procurement method for specific items in the Procurement Plan. * If bids are called concurrently for several contracts in a package and the PIU invites cross discounts, the aggregate value of the total package will form the basis to determine the procurement method as well as the prior review threshold requirements All amendments to prior review contracts > 15% in contract value or time will be subject to prior review * If a transaction comprises several packages, lots or slices and cross-discounts are invited, the aggregate estimated value of contracts determines the applicable threshold amount. #DGS&D Contracts can be used at par with shopping. However, State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. @If DGS&D rate contracts are used under Framework Agreement (FA) method, the Project would require ensuring the following: • Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods contract package. March 04, 2014 • Before issuing the purchase order, the borrower carries-out a price analysis on the specific goods that is intended to be purchased. If after this due diligence the borrower concludes (and Bank agrees) that the DGS&D rate contract is not suitable, then the borrower will have to use NCB or shopping depending on the value of procurement. • To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: A Procurement and Contracts Management Manual is under preparation by the Implementing Agency. The manual will be reviewed with the Bank and after clearance of the Manual by the Bank all procurement in the project will be done as per procedures described in it and the manual will work as guidance for the contract management. 5. Any Other Special Procurement Arrangements: * If a transaction comprises several packages, lots or slices and cross-discounts are invited, the aggregate estimated value of contracts determines the applicable threshold amount. #DGS&D Contracts can be used at par with shopping. However, State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. @If DGS&D rate contracts are used under Framework Agreement (FA) method, the Project would require ensuring the following: • Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods contract package. • Before issuing the purchase order, the borrower carries-out a price analysis on the specific goods that is intended to be purchased. If after this due diligence the borrower concludes (and Bank agrees) that the DGS&D rate contract is not suitable, then the borrower will have to use NCB or shopping depending on the value of procurement. • To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. March 04, 2014 A. Contracts procured in advance will be financed under retroactive financing within the specified limits, if agreed to in the Credit Agreement. B. National Competitive Bidding (NCB) method for procurement and goods and works as per the above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World Bank Procurement Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the Government of India’s Task Force (and as amended from time to time), shall be used for bidding. ii. Invitations for bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer). vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures. ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) C. The Project Implementing Entity shall: i. establish and maintain throughout the period of implementation of the Project, a fully operational procurement documentation and record keeping system, in a manner and substance acceptable to the Association, including a freely and publicly accessible ,website showing the procurement plans and procurement notices, invitations to bid, bidding documents and requests for proposals, as well as the procurement status of various contracts, including contract awards and the complaints received and the actions taken in respect thereof. The Project March 04, 2014 Implementing Entity shall updates the website on a regular basis throughout the period of implementation of the Project; and ii. establish and maintain throughout the period of implementation of the Project, a system for the handling of procurement complaints, in a manner and substance acceptable to the Association, which system shall include, inter alia: (i) a second tier appeal system; and (ii) a complaint database with an interface (link) to the management information systems, providing free and public access for the submission of complaints electronically. Till electronic system becomes operational, the PIU will implement the strengthened manual Complaint Handling System. Notwithstanding the foregoing, for any procurement done through International Competitive Bidding, the Association’s complaint redress mechanism under the Procurement Guidelines shall apply. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (1 US$ = INR 62.00) SN Description of Works Estimated Method Domestic Cost of Preference (in US$ Procuremen Millions) t 1 Improvement & Upgradation 38.56 NCB Not of Chhumkhum- Chawngte Applicable Road – 41.53 KM 2 Improvement & Upgradation Not of Champhai – Zokhawthar 26.32 NCB Applicable Road – 27.25 KM 3 Improvement & Upgradation Not of Lunglei – Chhumkhum 25 NCB Applicable Road - 22KM III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 3 - Methods and Value thresholds for Consultancy Services Expenditure Value* (Threshold Procurement Method Contracts subjected to Category per contract) Prior Review/Post Review Consultancy (a) More than [i] Quality and Cost Based First Contract of each Services US$300,000 Selection (QCBS) Or method of selection (Firms) equivalent per Quality Based Selection irrespective of value contract. (QBS) and all subsequent [ii] Short-list may contracts valued above comprise entirely national US$ 200,000 will be consultants for contracts subject to Prior Review. below US$ 800,000 All other contracts will March 04, 2014 (b) up to US$300,000 Quality and Cost Based be subject to post equivalent Selection (QCBS) Or review. Quality Based Selection (QBS) Or Selection based on Consultant’s Qualification (CQS) Or Selection based on a Fixed Budget (FBS) Or Selection Based on Least Cost Basis (LCS) (c) Single-Source Selection The single source (SSS) As per paragraphs selection can be used 3.9-3.11 of Guidelines only for the contracts which are included in a procurement plan cleared with the Bank The justifications for all contracts to be issued on the basis of single-source or direct contracting (except for contracts less than US$ 50,000 in value) will be subject to prior review. Individual Competitive Selection Prior Review of all Consultants based on comparison of the contracts valued above relevant overall capacity of $100,000. All other at least 3 qualified contracts will be subject consultants in accordance to post review with Section V of the Guidelines. Single-Source Selection The single source (SSS) as per paragraphs selection can be used 5.6 of Guidelines only for the contracts which are included in a procurement plan cleared with the Bank The justifications for all contracts to be issued on the basis of single- source or direct contracting (except for contracts less than US$ 50,000 in value) will be subject to prior review. * If proposals are called concurrently for several contracts in a package and the PIU invites cross discounts, the aggregate value of the total package will form the basis to determine the procurement method as well as the prior review threshold requirements March 04, 2014 All amendments to prior review contracts > 15% in contract value or time will be subject to prior review 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the World Bank Consultant Guidelines. 3. Any Other Special Selection Arrangements: (a) Contracts procured in advance will be financed under retroactive financing within the specified limits, if agreed to in the Credit Agreement. (b) Requests for Expression of Interest (REOI) for assignments expected to cost more than US$ 300,000 shall be advertised in UNDB online in accordance with Para 2.5 of the Consultant Guidelines. Besides, all REOIs prepared by the PIA shall be submitted to the World Bank for publishing them on the Bank’s external website. 4. Consultancy Assignments with Selection Methods and Time Schedule: (1 US$ = INR 62.00) SN Description of Estimated Selection Review Expected Comments Consulting Cost in Methods by the Proposals Services US$ Bank Submission Assignment million Prior/Post Date 1 Project 1.5 Prior Recd. on Evaluation Preparation QCBS Sept 09, Completed Consultant I 2013 2 Project 1.2 Prior Recd. on Evaluation Preparation QCBS Sept 09, Completed Consultant II 2013 3 Construction 2.0 Prior March 10, RFP issued Supervision 2014 QCBS Consultant for Civil Works (3 Contracts) 4 Project Prior May 20, REOI Management 1.5 QCBS 2014 issued Consultant 5. Internal Auditor 0.025 QCBS/QBS Prior - - March 04, 2014 PROCUREMENT India : Mizoram State Roads II- Regional Transport Connectivity Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-12-13 2019-04-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145778 GPN Date: Project Name: Mizoram State Roads II- Regional Transport Connectivity Project Loan / Credit No: IDA / Q8610, IDA / 54250 Executing Agency(ies): Public Works Department, Govt of Mizoram WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PWD/SRP/MZ/CW- 01/NCB/Pkg-I / Improvement and Up-gradation of Single Stage - One Chhumkhum-Chawngte Road IDA / 54250 Prior Request for Bids Open - National 40,877,848.59 Signed Envelope from Km 0.00 to Km 41.53 to 2 lane NH Standard in the State of Mizoram. PWD/SRP/MZ/CW- 03/NCB/Pkg-III / IMPROVEMENT AND UPGRADATION OF TLABUNG- Single Stage - One IDA / 54250 Prior Request for Bids Open - National 11,557,679.01 Signed KAWRPUICHHUAH ROAD Envelope FROM KM 75.50 TO KM 87.35 (11.85 KM) 2 LANE NH STANDARDS IN THE STATE OF MIZORAM PWD/SRP/MZ/CW- 02/NCB/PKG -II / IMPROVEMENT AND UPGRADATION OF CHAMAPHAI- Single Stage - One ZOKHAWTHAR ROAD TO 2 IDA / 54250 Prior Request for Bids Open - National 22,820,997.95 Signed Envelope LANE STANDARD IN THE STATE OF MIZORAM FROM KM 0.00TO KM 27.25 HAVING TOTAL LENGTH 27.25 KM IN-MIZORAM PWD-27344- CW-DIR / Maintenance, repair and re-arrangement of IDA / 54250 Post Direct Selection Direct 3,596.33 Signed 2017-09-14 2017-09-19 2017-09-25 2017-11-24 PIU Office Building at Tuikhuahtlang, Aizawl IN-MIZORAM PWD-92243- CW-DIR / Complementary Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 4,064.92 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Chhumkhum to Chawngte Road : Rangte IN-MIZORAM PWD-92245- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 5,524.59 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Chhumkhum to Chawngte Road : Lungrang Page 1 IN-MIZORAM PWD-92246- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 4,087.82 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Chhumkhum to Chawngte Road : Rualalung IN-MIZORAM PWD-92247- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 2,631.21 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Chhumkhum to Chawngte Road : Lalnutui IN-MIZORAM PWD-92248- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 2,631.21 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Champhai to Zokhawthar Road : Ruantlang IN-MIZORAM PWD-92249- CW-DIR / Compensatory Tree Plantation on MSRIi- IDA / 54250 Post Direct Selection Direct 2,631.21 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Champhai to Zokhawthar : Melbuk IN-MIZORAM PWD-92250- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 1,934.63 Signed 2019-01-07 2019-01-08 2019-01-17 2020-03-31 RTCP Roads - Champhai to Zokhawthar Road : Zokhawthar IN-MIZORAM PWD-92251- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 14,440.62 Signed 2019-01-08 2019-01-09 2019-01-18 2020-03-31 RTCP Roads - Champhai to Zokhawthar Road : Mualkawi IN-MIZORAM PWD-92253- CW-DIR / Compensatory Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 14,440.62 Signed 2019-01-08 2019-01-09 2019-01-18 2020-03-31 RTCP Roads - Champhai to Zokhawthar Road : Zotlang IN-MIZORAM PWD-92254- CW-DIR / Complementary Tree Plantation on MSRII- IDA / 54250 Post Direct Selection Direct 3,994.81 Signed 2019-01-08 2019-01-09 2019-01-18 2020-03-31 RTCP Roads - Tlabung to Kawrpuichhuah Road : Tlabung GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MSRP-II-36-CP-B-G10 / Annual Report of Mizoram Request for Single Stage - One IDA / 54250 Post Limited 4,206.54 Completed 2017-04-27 2017-05-18 2017-11-14 PWD for the 5 years 2015- Quotations Envelope 2020 Page 2 MSRP-II-32-CP-B-G09 / Supply and installation of software based video conferencing solution including hardware, software, Request for Single Stage - One IDA / 54250 Post Open - National 4,287.65 Signed 2017-04-27 2017-04-27 2017-04-27 installation integration with Quotations Envelope the existing system, testing, onsite training along with one year maintenance support services. MSRP-II-33-CP-B-G08 / Supply and installation of video solution for conference room including hardware, Request for Single Stage - One software, installation, IDA / 54250 Post Open - National 15,224.00 Signed 2017-04-27 2017-04-27 2017-04-27 Quotations Envelope integration with the existing system, testing with onsite training along with one year maintenance support services MSRP-II-29-CP-B / Request for Single Stage - One Procurement of Video IDA / 54250 Post Open - National 8,970.89 Signed 2017-04-27 2017-04-27 2017-04-27 Quotations Envelope Conference License IN-MIZORAM PWD-11966- GO-DIR / Dedicated Lease line Internet Connectivity Request for Single Stage - One (4Mbps) for Video IDA / 54250 Post Limited 6,010.03 Signed 2017-05-02 2017-06-13 2020-06-12 Quotations Envelope Conferencing and Procurement Cell of PIU, PWD IN-MIZORAM PWD-22485- GO-RFQ / Office Goods and Request for Single Stage - One personal Protective IDA / 54250 Post Limited 989.40 Signed 2017-09-20 2017-09-24 2017-09-29 Quotations Envelope Equipment (PPE) for PIU Officers & Staffs IN-MIZORAM PWD-82720- Under Request for Single Stage - One GO-RFQ / Procurement of IDA / 54250 Post Limited 0.00 Implementati 2018-12-28 2019-01-06 2019-01-20 Quotations Envelope Non-Nuclear Density Gauge on IN-MIZORAM PWD-92236- Under GO-RFQ / Procurement of Request for Single Stage - One IDA / 54250 Post Limited 0.00 Implementati 2019-01-04 2019-01-10 2019-01-24 Light Weight Deflectometer Quotations Envelope on (LWD) IN-MIZORAM PWD-92239- Under Request for Single Stage - One GO-RFQ / Procurement of IDA / 54250 Post Limited 0.00 Implementati 2019-01-04 2019-01-11 2019-01-25 Quotations Envelope Concrete Scanner on IN-MIZORAM PWD-102771- GO-RFQ / Procurement of IT Under Request for Single Stage - One equipment for Road Fund IDA / 54250 Post Limited 0.00 Implementati 2019-03-03 2019-03-17 2019-03-31 Quotations Envelope Board and Bridge Cell of on PWD, Mizoram. IN-MIZORAM PWD-103204- Under GO-RFQ / Procurement of Request for Single Stage - One IDA / 54250 Post Limited 0.00 Implementati 2019-03-07 2019-03-21 2019-04-04 office furniture for Road Quotations Envelope on Fund Board IN-MIZORAM PWD-103254- GO-DIR / Procurement of Books and Software to IDA / 54250 Post Direct Selection Direct 114.01 Signed 2019-02-28 2019-03-07 2019-03-27 2019-04-10 support Bridge Cell and Design Cell of Mizoram PWD Page 3 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WB 01 / Project Quality And Cost- Open - Preparation Consultant(PPC) IDA / Q8610 Prior 1,427,670.72 Signed Based Selection International Services - I WB 03 / Project Quality And Cost- Open - IDA / 54250 Prior 1,392,555.54 Signed Management Consultants Based Selection International CSC / Consultancy for Quality And Cost- Open - Construction Supervision and IDA / 54250 Prior 3,869,497.53 Signed Based Selection International Contract Administration MSRP-II-20-SBCC-CF- BIO/WBCF5 / Independent EIA, Regional Biodiversity and Cumulative Impact Quality And Cost- IDA / 54250 Post Open - National 104,923.98 Signed 2017-04-27 2017-04-27 2017-04-27 2017-04-27 2017-04-27 2017-04-27 2017-04-27 2017-04-27 Assessment Study for Trade Based Selection Corridor Development in the State of Mizoram for MSR II - RTCP MSRP-II-28-SBPF-CF / Quality And Cost- IDA / 54250 Post Open - National 11,918.53 Signed 2017-04-28 2017-04-28 2017-04-28 2017-04-28 2017-04-28 2017-04-28 2017-04-28 2017-04-28 INTERNAL AUDIT Based Selection IN-MIZORAM PWD-42974- CS-QBS / Consultancy Services for Study and Quality Based Assess the Trade-Related IDA / 54250 Post Open - National 69,996.32 Signed 2018-01-21 2018-01-21 2018-01-21 2018-01-21 2018-01-21 2018-01-30 2018-02-05 2018-05-03 Selection Infrastructural Gaps and Requirements for MSRII-RTCP Project Roads. IN-MIZORAM PWD-94441- CS-CQS / Consulting Service to develop and established a Quality Based Open - IDA / 54250 Prior 0.00 Under Review 2019-01-14 2019-02-04 2019-03-04 2019-04-01 2019-04-15 2019-04-29 2019-05-20 2020-11-10 web and GIS based Road Selection International Asset Management System (RAMS) for Mizoram PWD. INDIVIDUAL CONSULTANTS Page 4