PROCUREMENT PLAN PERU INTEGRATED WATER RESOURCES MANAGEMENT IN TEN BASINS PROJECT P151851 I. General 1. Bank’s approval Date of the procurement Plan: Original, February 23, 2017 2. Date of General Procurement Notice: February 23, 2017 3. Period covered by this procurement plan: all the procurement process planned II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Below US$ 2 million None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Below US$ 10 million None 2. Project Operational/Procurement Manual: Procurement implementation details activities will be outlined in the Project Operational Manual (POM) 3. Any Other Special Procurement Arrangements: None 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 Description Estimat Packa Domest Review Commen ed ges ic by Bank ts Cost Prefere (Prior / US$ nce Post) million (yes/no ) Summary of the ICB 25.2 5 No Prior (Goods) Summary of the NCB 9.28 5 No Post (Works) Summary of the NCB 3.16 4 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 350,000 All 2. Single Source (Firms) All 3. Individual Key personnel All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 350,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Description of Estimated Package Review Comments Assignment Cost s by Bank US$ million (Prior / Post) Summary of number of 15.95 10 Prior contracts that will be let under QCBS > US$ 350 mil Summary of number of 1.20 5 Post contracts that will be let under QCBS < US$ 350 mil PROCUREMENT Peru : Integrated Water Resources Management in Ten Basins PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 2021-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151851 GPN Date: Project Name: Integrated Water Resources Management in Ten Basins Loan / Credit No: IBRD / 87400 National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA) Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Contract Description Component Review Type Method Document Amount Amount qualification Document / and Signed Contract No. Approach Process n (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Completion Type (US$) (US$) Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned LPN 003 2018 ANA PGIRH BM / PERFORACIÓN E INSTALACIÓN DE 58 Component 1: Consolidating Solicitud de Single Stage - One 2,205,593.0 En 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2019-01- PIEZÓMETROS EN LOS IBRD / 87400 Posterior Open - National 0.00 IWRM at the National Level ofertas Envelope 0 ejecución 26 08 29 28 25 07 27 26 23 ACUÍFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA LPN 007-2018-ANA-PGIRH- BM / PERFORACION E INSTALACION DE 58 PIEZOMETROS EN LOS ACUIFEROS DE ICA Y TACNA Component 1: Consolidating Solicitud de Single Stage - One 1,664,437.0 2,141,562. 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- 2019-04- lote 1 ICA 28 perfotaciones IBRD / 87400 Posterior Open - National Firmado IWRM at the National Level ofertas Envelope 0 01 04 12 07 12 06 21 16 28 05 05 03 metodo diamantina, lote 2 TACNA 8 perforaciones metodo diamantina, lote 3 TACNA 22 perforaciones metodo RC CP 001 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA EJECUCIÒN Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-12- DE PERFORACIÒN E IBRD / 87400 Posterior Limited 21,870.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 21 15 30 INSTALACION DE 28 PIEZOMETROS EN LOS ACUIFEROS DE ICA CP 002 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA EJECUCION Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2018-12- DE PERFORACION E IBRD / 87400 Posterior Limited 13,587.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 21 15 30 INSTALACION DE 30 PIEZOMETROS EN LOS ACUIFEROS DE TACNA CP 003 2018 ANA PGIRH BM / CONSTRUCCION DE Component 1: Consolidating Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- CASETAS DE PROTECCION DE IBRD / 87400 Posterior Limited 55,239.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 07 02 16 30 PIEZOMETROS EN LOS ACUIFEROS DE TACNA LPN 008 2018 ANA PGIRH / Contratación para la Construcción - Obras Civiles para la Implementación de la Infraestructura del Centro de Component 1: Consolidating Solicitud de Single Stage - One 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2020-02- IBRD / 87400 Posterior Open - National 238,806.00 0.00 Cancelado Datos, Laboratorio de IWRM at the National Level ofertas Envelope 24 26 26 31 17 13 Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-126672-CW-RFQ / Perforación y habilitación de Component 1: Consolidating Solicitud de Single Stage - One 2019-09- 2019-10- 2019-09- 2019-12- 18 piezómetros en los IBRD / 87400 Posterior Open - National 180,000.00 225,104.38 Firmado IWRM at the National Level cotizaciones Envelope 21 31 27 15 acuiferos de Ica, Villacurí y Lanchas PE-ANA-121004-CW-RFQ / Obras Civiles para la Implementación del Centro de Datos, Laboratorio de Component 1: Consolidating Solicitud de Single Stage - One 2019-09- 2019-10- 2020-04- IBRD / 87400 Posterior Open - National 238,806.00 0.00 Cancelado Instrumentación, Centro de IWRM at the National Level cotizaciones Envelope 18 26 23 Monitoreo y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-139769-CW-RFB / Obras Civiles para la Implementación del Centro de Datos, Laboratorio de Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2020-02- 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-02- 2020-03- IBRD / 87400 Posterior Open - National 410,326.94 392,098.50 Firmado Instrumentación, Centro de IWRM at the National Level ofertas Envelope 21 25 26 18 07 29 17 20 27 14 26 Monitoreo y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-145138-CW-RFQ / Construcción de subestación y red de media tensión para Component 1: Consolidating Solicitud de Single Stage - One 2019-11- 2020-04- 2019-12- 2020-07- 2020-02- IBRD / 87400 Posterior Limited 58,541.00 62,575.10 Firmado la electrificación del Centro IWRM at the National Level cotizaciones Envelope 22 17 06 31 04 de Procesamiento de Datos Secundarios ICA PE-ANA-165869-NC-RFB / CONSTRUCCIÓN DE 22 Component 1: Consolidating Solicitud de Single Stage - One 2020-05- 2021-01- 2020-07- 2021-01- 2020-09- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 117,848.00 139,961.53 Firmado IWRM at the National Level cotizaciones Envelope 06 05 01 08 29 DE AGUA EN LA REGIÓN TUMBES PE-ANA-165872-NC-RFB / CONSTRUCCIÓN DE 11 Component 1: Consolidating Solicitud de Single Stage - One 2020-05- 2021-01- 2020-07- 2020-11- 2020-08- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 58,924.00 69,812.60 Firmado IWRM at the National Level cotizaciones Envelope 06 04 01 12 30 DE AGUA EN LA REGIÓN MOQUEGUA PE-ANA-165873-NC-RFB / CONSTRUCCIÓN DE 15 Component 1: Consolidating Solicitud de Single Stage - One 2020-05- 2021-01- 2020-07- 2020-11- 2020-08- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 80,351.00 76,073.91 Firmado IWRM at the National Level cotizaciones Envelope 06 05 01 16 30 DE AGUA EN LA REGIÓN TACNA PE-ANA-166008-CW-RFB / CONSTRUCCIÓN DE 73 Component 1: Consolidating Solicitud de Single Stage - One En 2020-05- 2020-12- 2020-05- 2020-12- 2020-06- 2021-01- 2020-07- 2021-01- 2020-08- 2021-01- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 391,041.00 0.00 IWRM at the National Level ofertas Envelope ejecución 01 04 06 21 17 22 17 27 21 18 DE AGUA EN LA REGIÓN ANCASH PE-ANA-166009-CW-RFB / CONSTRUCCIÓN DE 87 Component 1: Consolidating Solicitud de Single Stage - One En 2020-05- 2021-02- 2020-05- 2021-02- 2020-06- 2021-03- 2020-07- 2020-08- 2021-01- IBRD / 87400 Posterior Open - National 466,035.00 0.00 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level ofertas Envelope ejecución 01 06 06 11 17 31 17 21 18 DE AGUA EN LA REGIÓN LIMA PE-ANA-145139-CW-RFQ / Component 1: Consolidating Solicitud de Single Stage - One 2019-11- 2019-12- 2020-01- CONSTRUCCIÓN DE RED IBRD / 87400 Posterior Limited 30,434.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 22 06 20 MATRIZ DE AGUA Y DESAGUE PE-ANA-216706-CW-RFB / CONSTRUCCIÓN DE 73 Component 1: Consolidating Solicitud de Single Stage - One En 2021-02- 2021-02- 2021-02- 2021-02- 2021-03- 2021-03- 2021-03- 2021-05- 2021-04- 2021-10- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 391,041.00 305,112.38 IWRM at the National Level ofertas Envelope ejecución 02 05 07 09 21 30 31 17 05 02 DE AGUA EN LA REGIÓN ANCASH (2da Convocatoria) PE-ANA-165981-CW-RFB / CONSTRUCCIÓN DE 131 Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2021-08- 2022-01- IBRD / 87400 Posterior Open - National 701,729.85 0.00 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level ofertas Envelope for explanation) pendiente 26 23 DE AGUA EN LA REGIÓN PIURA PE-ANA-166005-CW-RFB / CONSTRUCCIÓN DE 95 Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-04- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 508,889.00 0.00 IWRM at the National Level ofertas Envelope for explanation) pendiente 01 06 17 16 21 19 DE AGUA EN LA REGIÓN LAMBAYEQUE PE-ANA-166006-CW-RFB / CONSTRUCCIÓN DE 80 Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2021-08- 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 428,537.31 0.00 IWRM at the National Level ofertas Envelope for explanation) pendiente 02 07 18 18 22 21 DE AGUA EN LA REGIÓN LA LIBERTAD PE-ANA-166011-CW-RFB / CONSTRUCCIÓN DE 107 Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2021-08- 2021-08- 2021-09- 2021-10- 2021-11- 2022-06- IBRD / 87400 Posterior Open - National 573,168.66 0.00 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level ofertas Envelope for explanation) pendiente 02 07 18 18 22 20 DE AGUA EN LA REGIÓN ICA PE-ANA-166012-CW-RFB / CONSTRUCCIÓN DE 190 Component 1: Consolidating Solicitud de Single Stage - One Other (with field 1,017,777.0 Ejecución 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-06- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Open - National 0.00 IWRM at the National Level ofertas Envelope for explanation) 0 pendiente 01 06 17 16 21 18 DE AGUA EN LA REGIÓN AREQUIPA PE-ANA-126678-CW-RFQ / CONSTRUCCIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2019-09- 2019-10- 2019-12- IBRD / 87400 Posterior Open - National 45,000.00 0.00 PROTECCIÓN Y CASETAS EN IWRM at the National Level cotizaciones Envelope for explanation) pendiente 21 31 15 PIEZÓMETROS UBICADOS EN EL ACUÍFERO ICA PE-ANA-235842-CW-RFB / CONSTRUCCIÓN DE ESTRUCTURAS DE Component 1: Consolidating Solicitud de Single Stage - One Other (with field Ejecución 2021-06- 2021-06- 2021-08- 2021-09- 2021-10- 2022-01- IBRD / 87400 Posterior Open - National 90,000.00 0.00 PROTECCIÓN Y CASETAS EN IWRM at the National Level ofertas Envelope for explanation) pendiente 22 27 08 07 12 10 PIEZÓMETROS UBICADOS EN EL ACUÍFERO CAPLINA GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual LPI 003 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DEL Component 1: Consolidating Solicitud de Open - Single Stage - One 2018-07- 2019-05- 2018-07- 2019-06- 2018-09- 2019-09- 2018-09- 2019-10- 2018-10- 2019-11- 2019-01- IBRD / 87400 Previa 5,786,425.49 7,376,638.41 Firmado EQUIPAMIENTO PARA EL IWRM at the National Level ofertas International Envelope 06 30 11 03 13 30 23 28 25 13 03 SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 004 2018 ANA PGIRH / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE LOS Component 1: Consolidating Solicitud de Open - Single Stage - One 2018-07- 2018-07- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Posterior 1,418,283.54 0.00 Cancelado SUBSISTEMAS PARA EL IWRM at the National Level ofertas International Envelope 09 14 16 26 28 11 SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN Page 1 LPN 001 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE EQUIPAMIENTO PARA LA PLATAFORMA TECNOLÓGICA Component 1: Consolidating Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2022-08- 2018-12- 2022-10- PARA LA ADQUISICIÓN, IBRD / 87400 Posterior Open - National 100,250.00 151,040.00 Firmado IWRM at the National Level ofertas Envelope 09 05 14 11 16 05 26 31 25 10 24 DECODIFICACIÓN, INTEGRACIÓN Y DISTRIBUCIÓN DE DATOS DE LAS ESTACIONES AUTOMATICAS CON TELEMETRIA LPN 002 2018 ANA PGIRH BM / ADQUISICIÓN DE CATORCE (14) VEHÍCULOS Component 1: Consolidating Solicitud de Single Stage - One 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- IBRD / 87400 Posterior Open - National 592,732.00 500,888.09 Firmado PARA LA SUPERVISIÓN, SEDE IWRM at the National Level ofertas Envelope 26 22 31 31 17 05 25 20 27 20 CENTRAL Y ADMINISTRACIÓN DE LAS CUENCAS DEL PGIRH LPN 004 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: Consolidating Solicitud de Single Stage - One 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Posterior Open - National 564,000.00 0.00 Cancelado CAPACITACIÓN DE 141 IWRM at the National Level ofertas Envelope 31 06 05 17 04 02 SENSORES CON SISTEMA DE TELEMETRÍA PARA PIEZÓMETROS EN ICA Y TACNA LPI 005 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de Open - Single Stage - One 2018-07- 2018-09- 2018-07- 2018-09- 2018-09- 2018-11- 2018-09- 2018-12- 2018-10- 2018-12- IBRD / 87400 Previa 3,200,000.00 0.00 En ejecución Y CAPACITACIÓN DE IWRM at the National Level ofertas International Envelope 26 07 31 07 14 22 19 14 04 28 INSTRUMENTACIÓN DE PRESAS LPN 006 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN Component 1: Consolidating Solicitud de Single Stage - One 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-12- 2018-10- 2019-01- 2018-11- 2019-03- 2019-02- IBRD / 87400 Posterior Open - National 645,577.00 0.30 Firmado FUNCIONAMIENTO Y IWRM at the National Level ofertas Envelope 13 12 18 12 18 03 21 03 13 25 11 CAPACITACIÓN DE INSTRUMENTACIÓN DE PIEZOMETROS CP 010 2018 ANA PGIRH BM / ADQUISICION DE EQUIPOS INFORMATICOS Y Component 3: General Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- IBRD / 87400 Posterior Limited 45,151.52 6,737.05 Finalizado ACCESORIOS PERIFERICOS Project Adminstration cotizaciones Envelope 21 16 06 19 21 13 PARA LAS COORDINACIONES TECNICAS DE CUENCA CP 011 2018 ANA PGIRH BM Component 3: General Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- / ADQUISICION DE LAP TOP IBRD / 87400 Posterior Limited 14,470.00 16,425.03 Finalizado Project Adminstration cotizaciones Envelope 21 23 06 06 21 28 PARA LA SEDE CENTRAL LPN 002 2019 ANA PGIRH Component 1: Consolidating Solicitud de Single Stage - One 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- BM2 / ADQUISICIÓN DE IBRD / 87400 Posterior Open - National 55,000.00 46,967.58 Firmado IWRM at the National Level ofertas Envelope 08 25 13 26 15 28 25 03 29 24 13 CORRENTOMETROS LPI 001 2019 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- 2019-06- 2019-07- 2020-06- IBRD / 87400 Previa 3,200,000.00 2,709,756.00 Firmado Y CAPACITACIÓN DE LA IWRM at the National Level ofertas International Envelope 24 01 01 01 17 29 24 06 06 12 05 INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS CP 010 B 2018 ANA PGRIH BM / Equipos Informaticos y Component 2: Improving Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-01- Accesorios Perifericos para IBRD / 87400 WRM in Selected Pilot River Posterior Limited 20,121.00 19,216.27 Finalizado cotizaciones Envelope 16 16 04 04 24 15 las Coordinaciones Tecnicas Basins de Cuenca. LPN 009 2018 ANA PGIRH / ADQUISICION E INSTALACION DE EQUIPOS DE TELEMETRIA PARA ESTRUCTURAS DE MEDICION DE AGUA CON Component 1: Consolidating Solicitud de Single Stage - One 2019-02- 2019-03- 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- IBRD / 87400 Posterior Open - National 147,962.00 0.00 Cancelado SENSORES PARA LAS IWRM at the National Level ofertas Envelope 22 08 26 12 28 02 20 20 ADMINISTRACIONES DE LOCAL DE AGUA DE TUMBES, PIURA, LAMBAYEQUE, AREQUIPA PE-ANA-116125-GO-RFB / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE LOS Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Previa 2,000,000.00 2,573,999.07 Firmado SUBSISTEMAS PARA EL IWRM at the National Level ofertas International Envelope 27 30 01 03 13 26 12 20 16 27 14 SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 006 2018 ANA PGIRH BM / ADQUISICIÓN, INSTALACIÓN, CAPACITACIÓN Y PUESTA EN Component 1: Consolidating Solicitud de Open - Single Stage - One 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2020-08- MARCHA DE EQUIPOS DE IBRD / 87400 Previa 3,480,149.89 0.00 Cancelado IWRM at the National Level ofertas International Envelope 10 15 15 17 25 19 10 MEDICIÓN DE AGUA Y TRANSMISIÓN DE DATOS EN LAS CAPTACIONES Y BLOQUES DE RIEGO SELECCIONADOS EN LA COSTA DEL PERU PE-ANA-116523-GO-RFB / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-10- 2020-06- 2019-10- 2020-06- 2019-11- 2020-10- 2019-12- 2021-01- 2020-01- 2022-01- IBRD / 87400 Previa 7,874,768.00 0.00 En ejecución Y CAPACITACIÓN DE 153 IWRM at the National Level ofertas International Envelope 10 26 19 26 23 05 08 21 04 03 ESTACIONES HIDROLÓGICAS CON 33 EHCA LPI 001 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- IBRD / 87400 Previa 7,874,768.00 0.00 Cancelado Y CAPACITACIÓN DE 153 IWRM at the National Level ofertas International Envelope 05 14 16 07 31 30 ESTACIONES HIDROLÓGICAS CON 33 EHCA PE-ANA-121041-GO-RFP / Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2019-10- 2019-11- 2019-12- ADQUISICIÓN DE PLOTTERS E IBRD / 87400 Posterior Open - National 36,882.35 0.00 IWRM at the National Level cotizaciones Envelope pendiente 06 18 18 IMPRESORAS LPN 005 2018 ANA PGIRH BM / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: Consolidating Solicitud de Single Stage - One 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-07- IBRD / 87400 Posterior Open - National 1,418,283.54 0.00 Cancelado CAPACITACIÓN DE LOS IWRM at the National Level ofertas Envelope 01 02 02 13 03 02 SUBSISTEMAS PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2019 ANA PGIRH BM / EQUIPAMIENTO PARA LA IMPLEMENTACIÓN DE LAS SALAS DE MONITOREO Component 2: Improving Solicitud de Single Stage - One 2019-10- 2020-07- 2019-10- 2019-11- 2020-09- 2019-12- 2020-10- 2020-01- 2020-10- 2020-03- HÍDRICO EN LOS IBRD / 87400 WRM in Selected Pilot River Posterior Open - National 850,000.00 870,755.10 Firmado ofertas Envelope 01 24 09 25 04 05 05 06 30 06 COORDINACIÓN DE Basins RECURSOS HÍDRICOS DE LAS CUENCAS DE LA VERTIENTE DEL ATLÁNTICO PE-ANA-134184-GO-RFQ / ADQUISICION DE SOFTWARE Component 1: Consolidating Solicitud de Single Stage - One 2019-09- 2019-11- 2019-10- 2019-12- 2019-10- IBRD / 87400 Posterior Limited 32,613.00 37,219.02 Firmado (INC. LICENCIA) DISEÑO DE IWRM at the National Level cotizaciones Envelope 18 25 07 20 22 PROCESOS PE-ANA-155600-GO-RFQ / ADQUISICIÓN DE EQUIPOS DEMOSTRATIVOS: CUATRO Component 1: Consolidating Solicitud de Single Stage - One 2020-01- 2020-02- 2020-11- 2020-03- IBRD / 87400 Posterior Open - National 13,134.00 8,703.10 Firmado DE MEDICIÓN DE AGUA Y IWRM at the National Level cotizaciones Envelope 28 04 05 05 CUATRO DE TRANSMISIÓN DE DATOS. PE-ANA-158249-GO-RFB / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE Component 1: Consolidating Solicitud de Open - Single Stage - One 2020-03- 2020-10- 2020-03- 2020-11- 2020-05- 2021-03- 2020-05- 2021-06- 2020-06- 2021-10- IBRD / 87400 Previa 3,822,975.00 0.00 En ejecución INSTRUMENTACIÓN PARA LA IWRM at the National Level ofertas International Envelope 17 20 22 03 06 05 26 03 30 23 MEDICIÓN DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO EN LA COSTA DEL PERÚ PE-ANA-155601-GO-RFQ / ADQUISICIÓN DE Component 1: Consolidating Solicitud de Single Stage - One 2020-01- 2020-03- 2020-02- 2020-02- 2020-04- ACCESORIOS PARA IBRD / 87400 Posterior Open - National 5,970.00 5,448.45 Firmado IWRM at the National Level cotizaciones Envelope 28 12 04 27 06 CORRENTOMETROS ELECTROMAGNÉTICOS (BARRA CONCENTRICA HERES) LPI 002 ANA PGIRH / SUMINISTRO INSTALACION PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-04- 2019-04- 2019-06- 2019-07- 2019-07- 2020-07- IBRD / 87400 Previa 3,190,000.00 0.00 Cancelado Y CAPACITACION DE 110 IWRM at the National Level ofertas International Envelope 05 19 20 06 21 20 SISTEMA MECANIZADOS DE AFOROS PE-ANA-161081-GO-RFQ / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE 121 SISTEMAS MECANIZADOS DE AFOROS, 05 PASARELAS Component 1: Consolidating Solicitud de Open - Single Stage - One 2020-03- 2020-07- 2020-03- 2020-07- 2020-05- 2020-10- 2020-06- 2020-11- 2020-07- 2020-12- 2021-12- IBRD / 87400 Previa 3,500,000.00 5,377,304.00 Firmado METÁLICAS PARA AFOROS Y IWRM at the National Level ofertas International Envelope 16 15 21 16 02 23 01 13 06 23 28 WINCHES PARA AFOROS EN SECCIONES DE CONTROL DE ESTACIONES HIDROLÓGICAS PARA FINES DE GESTIÓN DE RECURSOS HÍDRICOS PE-ANA-164500-GO-RFQ / Component 1: Consolidating Solicitud de Single Stage - One 2020-03- 2021-01- 2020-04- 2020-11- 2020-06- compra de flujometros IBRD / 87400 Posterior Open - National 26,000.00 32,139.47 Firmado IWRM at the National Level cotizaciones Envelope 27 13 03 19 04 ultrasonicos portátiles PE-ANA-164501-GO-RFB / ADQUISICIÓN DE UNA Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-04- 2020-04- 2020-05- COMPRESORA PARA IBRD / 87400 Posterior Open - National 35,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 06 20 30 MONITOREO DE AGUAS SUBTERRANEAS PE-ANA-165163-GO-RFQ / ADQUISICIÓN DE MOBILIARIO Component 3: General Solicitud de Single Stage - One Ejecución 2020-04- 2020-05- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 0.00 PARA LAS OFICINAS DEL Project Adminstration cotizaciones Envelope pendiente 19 14 29 PGIRH PE-ANA-165181-GO-RFQ / ADQUISICION DE Component 1: Consolidating Solicitud de Single Stage - One 2020-06- 2020-11- 2020-08- 2020-11- 2021-02- EQUIPAMIENTO PARA IBRD / 87400 Posterior Limited 23,000.00 7,198.79 Firmado IWRM at the National Level cotizaciones Envelope 19 10 14 25 10 ANALISIS HIDROBIOLOGICO EN LAS CUATRO CUENCAS PE-ANA-165894-GO-RFQ / ADQUISICIÓN DE 03 NIVELES Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-05- 2020-07- IBRD / 87400 Posterior Limited 2,687.00 0.00 En ejecución DE INGENIERO, INCLUIDO IWRM at the National Level cotizaciones Envelope 22 08 07 ACCESORIOS PE-ANA-186823-GO-RFQ / ADQUISICIÓN E INSTALACIÓN Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-10- 2020-10- 2020-11- 2020-12- DE BASES ANTI SÍSMICAS IBRD / 87400 Posterior Limited 18,000.00 23,490.72 Firmado IWRM at the National Level cotizaciones Envelope 18 29 06 18 05 PARA EL SISTEMA ELÉCTRICO DEL CENTRO DE DATOS Page 2 PE-ANA-116126-GO-RFB / ADQUISICIÓN DE EQUIPOS DE MEDICIÓN Y TRANSMISIÓN DE Component 1: Consolidating Solicitud de Open - Single Stage - One 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-06- IBRD / 87400 Previa 3,822,971.00 0.00 Cancelado DATOS PARA EL CONTROL IWRM at the National Level ofertas International Envelope 27 01 13 12 16 12 DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO PE-ANA-164478-GO-RFB / ADQUISICIÓN DE EQUIPOS DE Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-04- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 87400 Posterior Open - National 247,100.00 0.00 Cancelado MEDICIÓN DE CAUDAL - TIPO IWRM at the National Level ofertas Envelope 20 25 06 06 10 06 ADCP PE-ANA-167427-GO-RFQ / Adquisición de equipos de Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-05- 2020-05- 2020-07- 2020-06- medición de caudal y IBRD / 87400 Posterior Limited 37,500.00 61,518.14 Firmado IWRM at the National Level cotizaciones Envelope 15 29 05 10 19 medición de calidad de agua en campo PE-ANA-163933-GO-RFB / ADQUISICIÓN DE EQUIPOS MULTIPARÁMETROS Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-10- 2020-04- 2020-11- 2020-05- 2020-11- 2020-06- 2020-11- 2020-07- 2020-09- IBRD / 87400 Posterior Open - National 755,000.00 0.00 En ejecución PORTÁTILES PARA MEDICIÓN IWRM at the National Level ofertas Envelope 01 19 06 25 18 23 17 23 22 20 DE CALIDAD DE AGUA SUPERFICIAL PE-ANA-190562-GO-RFQ / ADQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-10- 2020-10- 2020-12- MUESTREO Y EQUIPOS IBRD / 87400 Posterior Limited 38,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 02 26 25 MULTIPARAMETROS PARA AGUAS SUBTERRANEAS PE-ANA-190602-GO-RFQ / Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-10- 2020-12- ADQUISICION DE EQUIPOS DE IBRD / 87400 Posterior Limited 43,000.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 29 29 28 PROSPECCION GEOFISICA PE-ANA-190604-GO-RFQ / ADQUISICION DE SONDA DE Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-10- 2020-12- IBRD / 87400 Posterior Open - National 43,000.00 0.00 Cancelado RESONANCIA MAGNETICA IWRM at the National Level cotizaciones Envelope 30 26 25 NUCLEAR PE-ANA-190605-GO-RFQ / ADQUISICION DE EQUIPOS DE Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-11- 2021-01- IBRD / 87400 Posterior Limited 30,000.00 0.00 Cancelado PERFILAJE GEOFISICO Y DE IWRM at the National Level cotizaciones Envelope 30 04 03 CAUDAL DE POZOS PE-ANA-190610-GO-RFQ / ADQUISICION DE EQUIPOS Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-11- 2021-01- IBRD / 87400 Posterior Limited 40,000.00 0.00 Cancelado SISTEMA CMT PARA SEIS IWRM at the National Level cotizaciones Envelope 29 03 02 PIEZOMETROS PE-ANA-194534-GO-RFB / ADQUISICIÓN DE CAMIONETAS PARA LA Component 1: Consolidating Solicitud de Single Stage - One 2020-10- 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- IBRD / 87400 Posterior Open - National 183,000.00 0.00 En ejecución SUPERVISION - EQUIPO IWRM at the National Level ofertas Envelope 12 17 28 08 05 04 TECNICO COORDINADO DE EHA- SMA PE-ANA-199721-GO-RFQ / Impresoras Multifuncional Monocromática para la Component 2: Improving Implementación de las Salas Solicitud de Single Stage - One 2020-10- 2020-11- 2020-10- 2020-11- 2021-02- IBRD / 87400 WRM in Selected Pilot River Posterior Limited 50,000.00 38,366.78 Firmado de Monitoreo Hídrico en las cotizaciones Envelope 18 02 28 16 25 Basins Coordinaciones de Recursos Hídricos de las Cuencas de la Vertiente PE-ANA-202827-GO-RFQ / Suministro, instalación y puesta en funcionamiento de Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2020-11- 2021-01- 2020-12- 2021-05- transmisión de datos via el IBRD / 87400 Posterior Limited 50,000.00 49,857.20 Firmado IWRM at the National Level cotizaciones Envelope 06 19 31 01 01 satélite GOES de la instrumentación de presas poechos y san Lorenzo PE-ANA-202829-GO-RFB / Suministro, instalación y puesta en funcionamiento de sensor de nivel de agua del Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-02- 2020-12- 2021-03- 2021-03- 2021-06- embalse y pluviómetro y del IBRD / 87400 Posterior Open - National 190,000.00 318,318.01 Firmado IWRM at the National Level ofertas Envelope 01 12 06 25 17 17 16 28 23 29 21 sistema de transmisión de datos via satélite GOES de la instrumentación en las siete presas priorizadas del PGIRH PE-ANA-206763-GO-RFQ / Adquisición de 01 Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- correntómetro para aforos de IBRD / 87400 Posterior Limited 12,000.00 13,228.32 Firmado IWRM at the National Level cotizaciones Envelope 16 15 20 12 21 bajos caudales en campo Cuenca piloto Mayo PE-ANA-208164-GO-RFB / Adquisición de Equipos Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2020-12- 2021-01- 2021-01- 2021-02- 2021-02- 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- Multiparámetros Portátiles IBRD / 87400 Posterior Open - National 755,000.00 426,427.39 Firmado IWRM at the National Level ofertas Envelope 30 18 04 05 15 12 17 09 21 03 20 para Medición de Calidad de Agua Superficial PE-ANA-212984-GO-RFQ / Adquisición de 2 equipos Component 1: Consolidating Solicitud de Single Stage - One 2021-01- 2021-02- 2021-03- 2021-06- para Capacitación, Pruebas y IBRD / 87400 Posterior Open - National 36,320.00 25,390.02 Firmado IWRM at the National Level cotizaciones Envelope 30 28 16 28 Operación de Sistemas Mecanizados de Aforos PE-ANA-161084-GO-RFQ / SUMINISTRO DE EQUIPOS E Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2021-02- 2020-04- 2021-02- 2020-05- 2021-04- 2020-06- 2020-07- 2020-10- INSTRUMENTACIÓN PARA LA IBRD / 87400 Posterior Open - National 1,200,000.00 0.00 En ejecución IWRM at the National Level ofertas Envelope 12 16 17 24 29 21 18 23 31 OPERACIÓN DE SISTEMAS MECANIZADOS DE AFORO PE-ANA-190607-GO-RFQ / ADQUISICIÓN SOFTWARES Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-08- 2021-11- IBRD / 87400 Posterior Open - National 20,000.00 0.00 PARA AGUAS SUBTERRÁNEAS IWRM at the National Level cotizaciones Envelope pendiente 05 13 11 Y CAPACITACIÓN. PE-ANA-236203-GO-RFB / ADQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de Single Stage - One 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- IBRD / 87400 Posterior Open - National 60,000.00 0.00 Cancelado MEDICION DE CAUDAL EN IWRM at the National Level ofertas Envelope 26 01 12 11 16 14 POZOS (SPINNER) + WINCHE PE-ANA-236204-GO-RFB / ADQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de Single Stage - One 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- MEDICION DE CAUDAL EN IBRD / 87400 Posterior Open - National 60,000.00 0.00 Cancelado IWRM at the National Level ofertas Envelope 03 08 19 18 23 21 POZOS (PULSO DE CALOR) + WINCHE PE-ANA-161126-GO-RFQ / SUMINISTRO, INSTALACIÓN Component 1: Consolidating Solicitud de Single Stage - One 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2022-03- DE FLUJÓMETROS Y IBRD / 87400 Posterior Open - National 456,716.00 0.00 Cancelado IWRM at the National Level ofertas Envelope 06 11 23 22 26 25 SISTEMAS DE TELEMETRÍA EN LOS ÁMBITOS DE ICA Y TACNA. PE-ANA-240307-GO-RFB / SUMINISTRO, INSTALACION Component 1: Consolidating Solicitud de Open - Single Stage - One Ejecución 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- DE FLUJOMETROS Y SISTEMAS IBRD / 87400 Previa 2,000,000.00 0.00 IWRM at the National Level ofertas International Envelope pendiente 11 16 27 16 11 19 DE TELEMETRIA EN LOS AMBITOS DE ICA Y TACNA. PE-ANA-241743-GO-RFQ / ADQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-09- 2022-03- IBRD / 87400 Posterior Limited 50,000.00 0.00 MEDICION DE CAUDAL EN IWRM at the National Level cotizaciones Envelope pendiente 17 11 10 POZOS (SPINNER) + WINCHE PE-ANA-241746-GO-RFQ / ADQUISICION DE EQUIPO DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-09- 2022-03- MEDICION DE CAUDAL EN IBRD / 87400 Posterior Limited 50,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 17 11 10 POZOS (PULSO DE CALOR) + WINCHE NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalificatio Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Description Component Review Type Method qualification Document / and Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Documents Justification Recommendation for Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PlannedAwardActual Planned Actual Planned Actual CP 004 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de Single Stage - One 2018-12- 2018-10- 2019-01- 2019-02- 2019-03- / SERVICIO DE NIVELACION Y IBRD / 87400 Posterior Limited 38,044.00 39,072.17 Rescindido IWRM at the National Level cotizaciones Envelope 23 31 17 11 03 MONUMENTACION ICA CP 005 2018 ANA PGIRH BM Component 1: Consolidating Solicitud de Single Stage - One 2018-12- 2018-10- 2019-01- 2019-02- 2019-03- / SERVICIO DE NIVELACION Y IBRD / 87400 Posterior Limited 40,760.00 44,281.79 Rescindido IWRM at the National Level cotizaciones Envelope 22 31 16 11 02 MONUMENTACION TACNA CP 008 2018 ANA PGIRH BM / ADQUISICION DE DOS Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2018-10- 2018-11- 2018-12- IBRD / 87400 Posterior Limited 29,892.00 0.00 CAUDALIMETROS IWRM at the National Level cotizaciones Envelope pendiente 21 06 21 ULTRASONICOS CP 009 2018 ANA PGIRH BM / ADQUISICION DE UNA Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-12- IBRD / 87400 Posterior Limited 29,629.00 0.00 En ejecución CAMARA DE INSPECCION DE IWRM at the National Level cotizaciones Envelope 21 06 21 POZOS CP 014 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION DE NIVEL DE AGUA EN BLOQUES DE RIEGO DE LOS Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- VALLES DE ALGARROBO - IBRD / 87400 Posterior Limited 28,528.00 129,635.34 Firmado IWRM at the National Level cotizaciones Envelope 28 19 20 16 14 VALLE HERMOSO - HUALTACO I - II - IV - SOMATE ALTO - SOMATE BAJO - VALLE LOS INCAS - CHIPILLICO BAJO -M - MALINGAS CP 015 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 25,934.00 207,452.42 Firmado BLOQUES DE RIEGO DE LOS IWRM at the National Level cotizaciones Envelope 28 19 20 16 13 VALLES DE QUIROZ PAMPAS- SAN ISIDRO I-II-TEJEDORES- TG-MALINGAS-YUSCAY- TABLAZO ALTO CP 016 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 12,550.00 57,574.33 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 21 25 16 07 BLOQUES DE RIEGO DE LOS VALLES DE PRAXADES-SANTA MARCELA CP 017 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 28,485.00 26,918.23 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 12 25 16 18 BLOQUES DE RIEGO DEL VALLE DE CASCAJAL-ANITAS- ILLIMO CP 018 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 25,990.00 131,662.63 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 28 12 20 16 10 BLOQUES DE RIEGO DEL VALLE DE MARGEN DERECHA Page 3 CP 019 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2019-08- 2018-11- 2019-09- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 23,103.00 20,790.00 Firmado IWRM at the National Level cotizaciones Envelope 28 11 20 25 08 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE MIGUEL CHECA CP 020 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 25,636.00 20,942.09 Firmado IWRM at the National Level cotizaciones Envelope 28 12 20 16 10 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE CASARANA CP 021 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 19,167.00 14,735.72 Firmado IWRM at the National Level cotizaciones Envelope 28 13 20 17 03 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN ANDRES CP 022 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-01- 2018-12- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Limited 42,727.00 31,139.78 Firmado IWRM at the National Level cotizaciones Envelope 02 09 25 30 28 BLOQUES DE RIEGO DE LOS VALLES DE CAPOTE-LA RAMADA-CHONGOYAOPE- PITIPO CP 023 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- IBRD / 87400 Posterior Limited 28,485.00 85,114.40 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 09 25 12 18 BLOQUES DE RIEGO DE LOS VALLES DE PUCALA TUMAN- POMALCA CP 024 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 19,939.00 66,347.73 Firmado IWRM at the National Level cotizaciones Envelope 02 15 25 01 10 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE LAMBAYEQUE CP 025 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-02- 2018-11- 2019-03- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 37,030.00 19,450.38 Firmado IWRM at the National Level cotizaciones Envelope 02 08 25 22 19 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE TALAMBO CP 013 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 39,879.00 20,893.44 Firmado IWRM at the National Level cotizaciones Envelope 28 23 20 16 20 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE CP 026 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 42,342.00 37,500.33 Firmado IWRM at the National Level cotizaciones Envelope 02 07 25 14 28 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN PEDRO CP 027 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 36,697.00 33,668.21 Firmado IWRM at the National Level cotizaciones Envelope 02 07 25 13 19 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN JOSÉ CP 028 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Posterior Limited 14,243.00 0.00 Cancelado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 25 07 BLOQUES DE RIEGO DEL VALLE DE SAN MIGUEL CP 029 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 19,940.00 20,805.11 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 14 25 30 10 BLOQUES DE RIEGO DEL VALLE DE SAYAN CP 030 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 28,485.00 83,611.18 Firmado IWRM at the National Level cotizaciones Envelope 02 05 25 16 18 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE LLAMACHUPAN CP 031 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 25,636.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 02 25 15 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE HUARICANGA CP 032 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 22,788.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 02 25 13 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE NARANJAL CP 033 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-08- 2018-12- 2019-09- 2018-12- IBRD / 87400 Posterior Limited 28,485.00 29,951.43 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 11 05 25 28 BLOQUES DE RIEGO DE LOS VALLES DE MACASH-POCOS CP 034 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 8,546.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 02 25 04 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE RINCONADA CP 035 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Posterior Limited 17,091.00 0.00 Cancelado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 25 08 BLOQUES DE RIEGO DE LOS VALLES DE LATERAL 4, 5 Y 6 CP 036 2018 ANA PGIRH BM / ADECUACION DE Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2019-02- 2018-11- 2019-03- 2018-12- ESTRUCTURA DE MEDICION IBRD / 87400 Posterior Limited 37,030.00 33,424.63 Firmado IWRM at the National Level cotizaciones Envelope 02 24 25 22 19 DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE EL CHOLOQUE CP 038 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Posterior Limited 22,788.00 38,281.31 Firmado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 28 23 20 16 08 BLOQUES DE RIEGO DE LOS VALLES DE MALA MUERTE- CHICAMITA CP 006 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Consolidating Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- MONUMENTACION ICA IBRD / 87400 Posterior Limited 43,479.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 07 02 16 (POZOS RED CONTROL GLOBAL ALA, AAA, DCERH) CP 007 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Consolidating Solicitud de Single Stage - One 2019-04- 2019-05- 2019-06- MONUMENTACION TACNA IBRD / 87400 Posterior Limited 24,457.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 07 02 16 (POZOS RED CONTROL GLOBAL ALA, AAA, DCERH) CP 012 2018 ANA PGIRH BM / CONTRATACION DE Component 3: General Solicitud de Single Stage - One 2019-04- 2019-04- 2019-06- IBRD / 87400 Posterior Limited 25,000.00 0.00 Cancelado AGENCIA PARA PUBLICACION Project Adminstration cotizaciones Envelope 07 21 14 DE AVISOS EN DIARIOS CP 037 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION Component 1: Consolidating Solicitud de Single Stage - One 2018-11- 2018-11- 2018-12- IBRD / 87400 Posterior Limited 17,091.00 0.00 Cancelado DE NIVEL DE AGUA EN IWRM at the National Level cotizaciones Envelope 02 25 08 BLOQUES DE RIEGO DE LOS VALLES DE MORO- VICHANZAO PE-ANA-126675-NC-RFQ / SERVICIO DE EJECUCIÓN DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2019-09- 2019-10- 2019-11- SIETE PRUEBAS DE BOMBEO IBRD / 87400 Posterior Open - National 45,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 21 31 30 EN PIEZÓMETROS UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-130327-NC-RFQ / SERVICIO DE ELABORACIÓN DEL PLAN DE MONITOREO ARQUEOLÓGICO PARA Component 1: Consolidating Solicitud de Single Stage - One 2019-09- 2019-09- 2019-10- 2019-10- 2020-02- IBRD / 87400 Posterior Limited 32,915.00 31,674.21 Firmado ADECUACIÓN DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 20 26 07 21 04 DE AGUA EN BLOQUES DE RIEGO EN LA ZONA SUR DE LA COSTA PE-ANA-133579-NC-RFB / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2019-12- IBRD / 87400 Posterior Limited 8,000.00 114.45 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 03 06 14 22 13 GRUPO 10 SECTORES HIDRÁULICOS CASMA, HUARMEY PE-ANA-133581-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2020-01- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Limited 12,000.00 98.48 Firmado IWRM at the National Level cotizaciones Envelope 03 06 14 22 12 ESTRUCTURAS DE MEDICIÓN GRUPO 3 SECTORES HIDRÁULICOS MyBP, SECHURA PE-ANA-133582-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2020-01- IBRD / 87400 Posterior Limited 12,000.00 92.63 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 03 30 14 22 12 GRUPO 5 SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-133583-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2020-01- 2020-01- IBRD / 87400 Posterior Limited 12,000.00 78.52 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 03 05 14 14 10 GRUPO 8 SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-133584-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2019-10- 2019-10- 2020-02- IBRD / 87400 Posterior Limited 16,000.00 0.00 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope pendiente 03 14 09 GRUPO 12 SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-133585-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2019-10- 2019-11- 2020-01- IBRD / 87400 Posterior Limited 12,000.00 95.39 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 03 06 14 22 12 GRUPO 13 SECTORES HIDRÁULICOS SAN JUAN, PISCO Page 4 PE-ANA-133586-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2019-12- IBRD / 87400 Posterior Limited 8,000.00 3,297.84 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 03 30 14 25 13 GRUPO 14 SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-133587-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2020-01- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Limited 12,000.00 111.79 Firmado IWRM at the National Level cotizaciones Envelope 03 01 14 22 12 GRUPO 18 SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR YURA PE-ANA-133588-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-10- 2019-10- 2019-11- 2019-12- IBRD / 87400 Posterior Limited 8,000.00 6,790.53 Firmado GRUPO 20 SECTORES IWRM at the National Level cotizaciones Envelope 03 30 14 22 13 HIDRÁULICOS IRRIG. EMM, PTA DE BOMBOM, MOQUEGUA, TORATA, LOCUMBA, SAMA, UCHUSUMA, BAJO CAPLINA PE-ANA-136558-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-02- 2019-11- 2020-03- 2020-01- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Limited 32,740.00 29,723.68 Firmado IWRM at the National Level cotizaciones Envelope 19 18 17 05 16 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR CAÑETE PE-ANA-136561-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-03- 2019-11- 2020-08- 2020-01- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Limited 35,680.00 28,030.30 Firmado IWRM at the National Level cotizaciones Envelope 19 13 17 24 03 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO I PE-ANA-137039-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-03- 2019-11- 2020-08- 2019-12- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Limited 28,312.00 23,487.57 Firmado IWRM at the National Level cotizaciones Envelope 19 13 17 24 27 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO II PE-ANA-137046-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-06- 2019-11- 2020-08- 2020-01- IBRD / 87400 Posterior Limited 23,452.00 36,147.55 Firmado BLOQUES DE RIEGO EN LOS IWRM at the National Level cotizaciones Envelope 19 23 17 24 16 SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN PE-ANA-137047-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-07- 2019-11- 2020-09- 2020-01- IBRD / 87400 Posterior Limited 43,598.00 27,065.09 Firmado BLOQUES DE RIEGO EN EL IWRM at the National Level cotizaciones Envelope 19 10 17 02 27 SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-137048-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-07- 2019-11- 2020-09- 2020-02- IBRD / 87400 Posterior Limited 40,110.00 29,982.46 Firmado BLOQUES DE RIEGO EN EL IWRM at the National Level cotizaciones Envelope 19 29 17 02 03 SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-137049-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-09- 2019-11- 2020-11- 2020-02- BLOQUES DE RIEGO EN EL IBRD / 87400 Posterior Limited 22,399.00 13,241.97 Firmado IWRM at the National Level cotizaciones Envelope 19 18 17 03 03 SECTOR HIDRÁULICO MENOR IRRIGACIÓN ENSENADA-MEJIA- MOLLENDO Y PUNTA DE BOMBOM PE-ANA-137051-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2020-09- 2019-11- 2020-11- 2020-02- BLOQUES DE RIEGO EN LOS IBRD / 87400 Posterior Limited 44,793.00 33,679.65 Firmado IWRM at the National Level cotizaciones Envelope 19 29 17 03 03 SECTORES HIDRÁULICOS MENOR MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-137052-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2019-11- 2020-01- 2020-02- DE AGUA EN BLOQUES DE IBRD / 87400 Posterior Limited 36,795.00 24,051.35 Firmado IWRM at the National Level cotizaciones Envelope 19 20 17 09 03 RIEGO EN EL SECTOR HIDRÁULICO MENOR MOTUPE- OLMOS-LA LECHE PE-ANA-139771-NC-RFQ / Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2020-05- SERVICIO PARA EJECUTAR 11 IBRD / 87400 Posterior Open - National 26,268.66 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 26 24 02 PERFILAJES GEOFISICOS PE-ANA-139772-NC-RFQ / SERVICIO PARA LA Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- INSTALACIÓN Y IBRD / 87400 Posterior Open - National 35,820.90 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 26 24 23 CONSTRUCCIÓN DE CASETAS PRE FABRICADAS TACNA PE-ANA-139773-NC-RFQ / SERVICIO PARA LA Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- INSTALACIÓN Y IBRD / 87400 Posterior Open - National 33,433.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 26 24 23 CONSTRUCCIÓN DE CASETAS PRE FABRICADAS ICA PE-ANA-139774-NC-RFQ / SERVICIO DE ADAPTACIÓN, SEGURIDAD PARA LA INSTRUMENTACIÓN DE 27 Component 1: Consolidating Solicitud de Single Stage - One 2019-10- 2019-11- 2020-01- POZOS Y PIEZOMETROS EN IBRD / 87400 Posterior Open - National 29,553.00 0.00 Cancelado IWRM at the National Level cotizaciones Envelope 26 24 23 ESTADO UTILIZABLE Y 15 EN ESTADO UTILIZADO EN EL ACUIFERO DE ICA, VILLACURI Y LANCHAS PE-ANA-152835-NC-RFQ / SERVICIO DE ALOJAMIENTO Component 1: Consolidating Solicitud de Single Stage - One 2020-01- 2020-01- 2020-02- 2020-01- 2020-07- DE INFRAESTRUCTURA IBRD / 87400 Posterior Limited 30,000.00 60,749.10 Firmado IWRM at the National Level cotizaciones Envelope 25 13 21 20 20 TECNOLÓGICA DE DATA CENTER PE-ANA-154274-NC-RFQ / SERVICIO DE ALOJAMIENTO Y ALIMENTACIÓN PARA LOS Component 1: Consolidating Solicitud de Single Stage - One 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- PARTICIPANTES DEL TALLER IBRD / 87400 Posterior Limited 50,000.00 53,878.72 Firmado IWRM at the National Level cotizaciones Envelope 18 21 26 23 02 DE CAPACITACIÓN PARA ESPECIALISTAS DE CALIDAD DE RECURSOS HIDRICOS PE-ANA-155598-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-03- 2020-04- PARA LA CONSTRUCCIÓN DE IBRD / 87400 Posterior Open - National 8,597.00 9,632.19 Firmado IWRM at the National Level cotizaciones Envelope 09 19 02 04 ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS VALLE DE MAJES Y VALLE SIGUAS QUILCA. PE-ANA-155595-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-04- PARA LA CONSTRUCCIÓN DE IBRD / 87400 Posterior Open - National 6,179.00 10,075.32 Firmado IWRM at the National Level cotizaciones Envelope 09 19 28 04 ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR ALTO PIURA. PE-ANA-155594-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- IBRD / 87400 Posterior Open - National 9,134.00 6,815.66 Firmado PARA LA CONSTRUCCIÓN DE IWRM at the National Level cotizaciones Envelope 09 19 28 20 ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR CHIRA. PE-ANA-155596-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- PARA LA CONSTRUCCIÓN DE IBRD / 87400 Posterior Open - National 8,597.00 9,329.13 Firmado IWRM at the National Level cotizaciones Envelope 09 19 28 30 ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ZAÑA Y JEQUETEPEQUE PE-ANA-155599-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PARA LA CONSTRUCCIÓN DE Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-03- 2020-03- IBRD / 87400 Posterior Open - National 5,373.00 4,212.49 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 09 19 02 20 DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-155597-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PARA LA CONSTRUCCIÓN DE Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- IBRD / 87400 Posterior Open - National 9,134.00 7,134.04 Firmado ESTRUCTURAS DE MEDICIÓN IWRM at the National Level cotizaciones Envelope 09 19 28 25 DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS PALPA, NASCA, ACARI, BELLA UNIÓN, CHAPARRA, Y YAUCA. Page 5 PE-ANA-158210-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-03- 2020-06- funcionamiento y IBRD / 87400 Posterior Limited 38,500.00 38,925.20 Firmado IWRM at the National Level cotizaciones Envelope 20 20 29 02 13 Capacitación de la Instrumentación para la Seguridad de las presas Poechos, San Lorenzo, Tinajones y Gallito Ciego. PE-ANA-158215-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-09- 2020-03- 2020-09- 2020-06- funcionamiento y IBRD / 87400 Posterior Limited 23,500.00 14,775.32 Firmado IWRM at the National Level cotizaciones Envelope 21 23 01 29 19 Capacitación de la Instrumentación para la Seguridad de las presas del Sur Condoroma, El Frayle, Sutunta y Pasto Grande. PE-ANA-159315-NC-RFQ / SERVICIO DE LIMPIEZA, TALA Component 1: Consolidating Solicitud de Single Stage - One 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- Y DESBROCE, Y TRASLADO DE IBRD / 87400 Posterior Limited 23,000.00 20,343.08 Firmado IWRM at the National Level cotizaciones Envelope 21 18 28 21 30 MATERIAL ELIMINADO EN LA PRESA POECHOS PE-ANA-161087-NC-RFQ / SERVICIO DE ALOJAMIENTO, ALIMENTACIÓN Y SALAS EQUIPADAS PARA EL TALLER Component 1: Consolidating Solicitud de Single Stage - One 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- NACIONAL: IBRD / 87400 Posterior Limited 50,000.00 40,733.54 Firmado IWRM at the National Level cotizaciones Envelope 02 02 05 03 07 FORTALECIMIENTO DE LAS JUNTAS USUARIAS Y SU ROL EN EL DESARROLLO PRODUCTIVO AGRARIO PE-ANA-161131-NC-RFQ / SERVICIOS DE LIMPIEZA Y ADAPTACIÓN DE 15 POZOS Component 1: Consolidating Solicitud de Single Stage - One 2020-03- 2020-04- 2020-07- IBRD / 87400 Posterior Limited 14,925.00 0.00 Cancelado UBICADO EN LOS ACUÍFEROS IWRM at the National Level cotizaciones Envelope 18 04 03 DE ICA, VILLACURI Y LANCHAS. PE-ANA-164268-NC-DIR / SERVICIO DE ARRENDAMIENTO DE Component 3: General Adquisición 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-06- 2022-12- INMUEBLE 2 PARA EL IBRD / 87400 Posterior Direct 84,500.00 55,200.00 Firmado Project Adminstration directa 23 09 30 16 01 30 31 PROYECTO GESTIÓN INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS PE-ANA-164313-NC-RFQ / SERVICIO DE ELABORACIÓN Component 1: Consolidating Solicitud de Single Stage - One 2020-03- 2020-05- 2020-11- IBRD / 87400 Posterior Open - National 10,448.00 0.00 Cancelado DE CARTELES DE IWRM at the National Level cotizaciones Envelope 31 26 22 IDENTIFICACIÓN POZOS PE-ANA-164550-NC-RFQ / SERVICIO DE AGENCIAMIENTO Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-04- 2020-05- 2021-01- DE PASAJES AÉREOS IBRD / 87400 Posterior Open - National 29,851.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 13 04 12 NACIONALES Y INTERNACIONALES PE-ANA-164552-NC-RFQ / SERVICIO DE PUBLICIDAD DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-04- 2020-05- 2021-01- AVISOS RELACIONADOS A LAS IBRD / 87400 Posterior Open - National 17,910.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 13 04 12 CONVOCATORIAS DEL PROYECTO PE-ANA-164985-NC-DIR / SERVICIO DE ARRENDAMIENTO DE INMUEBLE PARA LA SEDE Component 3: General Adquisición 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2022-12- PRINCIPAL DEL PGIRH DE LA IBRD / 87400 Posterior Direct 239,415.00 174,120.00 Firmado Project Adminstration directa 18 16 25 16 05 31 31 UNIDAD EJECUTORA N°002 MODERNIZACION DE LA GESTION DE LOS RECURSOS HIDRICOS PE-ANA-165161-NC-RFQ / SERVICIO DE CABLEADO DE Component 3: General Solicitud de Single Stage - One 2020-04- 2020-04- 2020-08- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 29,483.43 Firmado VOZ Y DATA PARA LOCAL Project Adminstration cotizaciones Envelope 16 26 13 11 DEL PGIRH PE-ANA-165867-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-06- 2020-09- IBRD / 87400 Posterior Limited 42,728.00 0.00 Cancelado DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope 25 20 18 HIDRÁULICOS MENORES COMPRENDIDOS DESDE CHICAMA HASTA SANTA PE-ANA-165868-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-04- 2020-06- 2020-08- IBRD / 87400 Posterior Limited 26,192.00 0.00 DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope pendiente 25 20 19 HIDRÁULICOS MENORES COMPRENDIDOS DESDE FORTALEZA HASTA LURÍN PE-ANA-165877-NC-RFQ / ALQUILER DE CAMIONETA Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-04- 2020-04- 2020-06- IBRD / 87400 Posterior Limited 9,242.00 0.00 PARA VERIFICACIÓN DE IWRM at the National Level cotizaciones Envelope pendiente 21 30 29 COBERTURA DE TRANSMISIÓN PE-ANA-165652-GO-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2020-06- 2020-06- 2020-08- 2020-08- 2020-09- 2020-12- IBRD / 87400 Posterior Open - National 130,401.14 0.00 Cancelado DE AGUA EN LOS SECTORES IWRM at the National Level ofertas Envelope 15 20 01 21 25 24 HIDRÁULICOS MENORES COMPRENDIDOS DESDE TUMBES HASTA JEQUETEPEQUE PE-ANA-187094-NC-RFQ / SERVICIO DE TELEFONIA MOVIL PARA EL PERSONAL Component 3: General Solicitud de Single Stage - One 2020-09- 2020-10- 2020-10- 2020-11- 2021-10- IBRD / 87400 Posterior Limited 20,000.00 14,423.97 Firmado DEL PROYECTO DE GESTION Project Adminstration cotizaciones Envelope 17 16 01 20 01 INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS PE-ANA-187470-NC-RFQ / ELABORACION E Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-09- 2020-10- 2020-11- 2021-03- IMPLEMENTACION DE PLANES IBRD / 87400 Posterior Limited 50,000.00 49,055.79 Firmado IWRM at the National Level cotizaciones Envelope 17 21 08 04 07 DE MONITOREO ARQUEOLÓGICO - PMA. PE-ANA-164575-NC-RFB / SERVICIO DE ANÁLISIS DE Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-11- 2020-04- 2020-12- 2020-05- 2021-01- 2020-06- 2021-02- 2020-07- 2021-03- 2020-12- IBRD / 87400 Posterior Open - National 477,650.00 248,246.81 Firmado LABORATORIO PARA IWRM at the National Level ofertas Envelope 06 22 11 21 23 13 22 12 27 04 24 MUESTRAS DE AGUA NATURAL PE-ANA-165874-NC-RFB / ELABORAR E IMPLEMENTAR Component 1: Consolidating Solicitud de Single Stage - One 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- ONCE (11) PLANES DE IBRD / 87400 Posterior Open - National 59,702.00 0.00 Cancelado IWRM at the National Level ofertas Envelope 30 05 16 16 20 17 MONITOREO ARQUEOLÓGICO- PMA PE-ANA-191481-NC-RFQ / SERVICIO DE INTERNET PARA EL CENTRO DE Component 1: Consolidating Solicitud de Single Stage - One 2020-09- 2020-09- 2020-10- 2020-10- 2021-01- PROCESAMIENTO DE DATOS IBRD / 87400 Posterior Limited 40,000.00 17,122.15 Firmado IWRM at the National Level cotizaciones Envelope 17 23 01 23 29 SECUNDARIO DE LA AUTORIDAD NACIONAL DEL AGUA PE-ANA-187303-NC-RFQ / SERVICIO DE Component 3: General Solicitud de Single Stage - One Ejecución 2020-09- 2020-10- 2021-10- INFRAESTRUCTURA Y IBRD / 87400 Posterior Limited 32,500.00 0.00 Project Adminstration cotizaciones Envelope pendiente 27 22 22 PLATAFORMA EN LA NUBE PARA EL PROYECTO PGIRH PE-ANA-202872-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-11- 2020-12- 2021-01- IBRD / 87400 Posterior Limited 40,900.00 0.00 DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope pendiente 22 01 30 HIDRÁULICOS MENORES COMPRENDIDOS DESDE CHICAMA HASTA SANTA PE-ANA-202873-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2020-11- 2021-02- 2020-12- 2021-03- 2021-01- IBRD / 87400 Posterior Limited 25,100.00 31,352.14 Firmado DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope 22 16 01 15 30 HIDRÁULICOS MENORES COMPRENDIDOS DESDE FORTALEZA HASTA LURÍN PE-ANA-202823-NC-RFQ / Conductor 02 de camioneta Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-12- 2021-02- 2022-08- IBRD / 87400 Posterior Limited 33,906.00 0.00 para la supervisión de EHA - IWRM at the National Level cotizaciones Envelope pendiente 27 21 15 SMA PE-ANA-202818-NC-RFQ / Conductor 01 de camioneta Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-12- 2021-02- 2022-08- IBRD / 87400 Posterior Limited 33,906.00 0.00 para la supervisión de EHA - IWRM at the National Level cotizaciones Envelope pendiente 27 21 15 SMA PE-ANA-202824-NC-RFQ / Conductor 03 de camioneta Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-12- 2021-02- 2022-08- IBRD / 87400 Posterior Limited 33,906.00 0.00 para la supervisión de EHA - IWRM at the National Level cotizaciones Envelope pendiente 27 21 15 SMA PE-ANA-202826-NC-RFQ / Conductor 04 de camioneta Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2020-12- 2021-02- 2022-08- IBRD / 87400 Posterior Limited 33,906.00 0.00 para la supervisión de EHA - IWRM at the National Level cotizaciones Envelope pendiente 27 21 15 SMA PE-ANA-206762-NC-RFQ / SERVICIOS COMPLEMENTARIOS PARA EL Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2020-12- 2020-12- IBRD / 87400 Posterior Limited 28,000.00 21,878.55 Firmado CENTRO DE PROCESAMIENTO IWRM at the National Level cotizaciones Envelope 16 18 20 23 21 SECUNDARIO DEL MONITOREO DEL RECURSO HÍDRICO - ICA PE-ANA-208167-NC-RFQ / SEGURO VEHICULAR ANUAL Component 3: General Solicitud de Single Stage - One 2020-12- 2020-12- 2020-12- 2020-12- 2020-12- IBRD / 87400 Posterior Limited 37,350.00 21,521.29 Firmado PARA LOS VEHICULOS DEL Project Adminstration cotizaciones Envelope 13 11 17 18 18 PGIRH PE-ANA-208190-NC-RFQ / SERVICIO DE ADUANA PARA LA IMPORTACION DE Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- IBRD / 87400 Posterior Limited 40,000.00 35,148.56 Firmado ESTACIONES AUTOMATICAS IWRM at the National Level cotizaciones Envelope 16 18 26 06 27 (HIDROLOGICAS E HIDROMETEOROLOGICAS) Page 6 PE-ANA-208191-NC-RFQ / SERVICIO DE ADUANA PARA LA IMPORTACION DE Component 1: Consolidating Solicitud de Single Stage - One 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- SISTEMAS MECANIZADOS DE IBRD / 87400 Posterior Limited 40,000.00 26,899.18 Firmado IWRM at the National Level cotizaciones Envelope 16 15 20 06 21 AFORO, PASARELAS METALICAS DE AFOROS Y WINCHES PARA AFOROS PE-ANA-203041-NC-RFQ / ALQUILER DE CAMIONETA 4 X 4 PARA ACTIVIDADES DE INSPECCION AL SERVICIO DE Component 1: Consolidating Solicitud de Single Stage - One 2021-02- 2021-01- 2021-02- 2021-02- 2021-06- IBRD / 87400 Posterior Limited 21,000.00 20,459.53 Firmado SUMINISTRO INSTALACION IWRM at the National Level cotizaciones Envelope 02 22 12 24 27 PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS EN PIURA PE-ANA-213295-NC-RFQ / SERVICIO DE ALQUILER DE CAMIONETA 4X4 PARA ACTIVIDADES DE INSPECCION Component 1: Consolidating Solicitud de Single Stage - One 2021-01- 2021-01- 2021-02- 2021-02- 2021-04- AL SERVICIO DE SUMINISTRO, IBRD / 87400 Posterior Limited 9,334.00 9,093.12 Firmado IWRM at the National Level cotizaciones Envelope 21 22 01 24 02 INSTALACION, PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS GALLITO CIEGO - CAJAMARCA PE-ANA-213296-NC-RFQ / SERVICIO DE ALQUILER DE CAMIONETA 4X4 PARA ACTIVIDADES DE INSPECCION AL SERVICIO DE SUMINISTRO, Component 1: Consolidating Solicitud de Single Stage - One 2021-01- 2021-01- 2021-02- 2021-02- 2021-04- IBRD / 87400 Posterior Limited 9,167.00 8,930.75 Firmado INSTALACION, PUESTA EN IWRM at the National Level cotizaciones Envelope 21 22 01 24 02 FUNCIONAMIENTO Y CAPACITACION DE PRESAS - PRESA TINAJONES EN CHILCAYO - GRUPO II PE-ANA-213297-NC-RFQ / SERVICIO DE ALQUILER DE 02 CAMIONETAS 4X4 PARA ACTIVIDADES DE INSPECCION Component 1: Consolidating Solicitud de Single Stage - One 2021-01- 2021-01- 2021-01- 2021-02- 2021-04- AL SERVICIO DE SUMINISTRO, IBRD / 87400 Posterior Limited 18,667.00 18,186.25 Firmado IWRM at the National Level cotizaciones Envelope 21 22 31 24 01 INSTALACION, PUESTA EN FUNCIONAMIENTO Y CAPACITACION DE PRESAS DEL SUR PE-ANA-213485-NC-RFQ / SERVICIO DE DISEÑO, DIAGRAMACIÓN Y Component 3: General Solicitud de Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2022-12- IBRD / 87400 Posterior Limited 26,000.00 26,134.23 Firmado CORRECCIÓN DE ESTILO DE Project Adminstration cotizaciones Envelope 25 29 15 03 30 11 BOLETINES DIGITALES DEL PGIRH (2021-2022) PE-ANA-221551-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2021-03- 2021-05- 2021-04- 2021-06- IBRD / 87400 Posterior Limited 49,000.00 46,889.86 En ejecución DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope 13 07 06 22 HIDRÁULICOS MENORES COMPRENDIDOS DESDE TUMBES HASTA ALTO PIURA PE-ANA-221560-NC-RFQ / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Solicitud de Single Stage - One 2021-03- 2021-03- 2021-04- 2021-05- 2021-06- IBRD / 87400 Posterior Limited 41,500.00 51,703.66 Firmado DE AGUA EN LOS SECTORES IWRM at the National Level cotizaciones Envelope 13 08 06 07 30 HIDRÁULICOS MENORES COMPRENDIDOS DESDE OLMOS HASTA JEQUETEPEQUE PE-ANA-229523-NC-RFQ / Elaboración de Planes de Component 1: Consolidating Solicitud de Single Stage - One 2021-04- 2021-04- 2021-05- 2021-05- 2021-10- IBRD / 87400 Posterior Limited 50,000.00 10,051.39 Firmado Monitoreo Arqueológico para IWRM at the National Level cotizaciones Envelope 21 26 07 03 04 Estaciones Hidrometricas PE-ANA-235377-NC-RFQ / Servicio de movilidad para la supervisión de la culminación de la adecuación de las Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-06- 2021-06- 2021-09- IBRD / 87400 Posterior Limited 7,200.00 0.00 estructuras de medición de IWRM at the National Level cotizaciones Envelope pendiente 06 28 28 agua en sectores hidráulicos desde Tumbes hasta Alto Piura PE-ANA-235381-NC-RFQ / Servicio de movilidad para la supervisión de la culminación Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-08- 2021-10- de la adecuación de las IBRD / 87400 Posterior Limited 6,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 20 11 26 estructuras de medición de agua en sectores hidráulicos desde Chicama hasta Santa PE-ANA-202887-NC-RFB / SERVICIO DE COMUNICACIÓN DE DATOS DE ESTRUCTURAS Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-10- 2021-10- 2021-11- 2021-12- 2021-12- 2022-12- DE MEDICIÓN DE AGUA EN IBRD / 87400 Posterior Open - National 142,900.00 0.00 IWRM at the National Level ofertas Envelope pendiente 01 06 17 02 22 27 BLOQUES DE RIEGO A PLATAFORMA DEL SNIRH, CON TECNOLOGÍA GPRS/GSM- SMS PE-ANA-236174-NC-RFQ / SERVICIO DE IMPLEMENTACIÓN DE EJEMPLOS PILOTO DE MEDICIÓN DE CONSUMO DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-05- 2021-06- 2021-06- IBRD / 87400 Posterior Limited 31,000.00 0.00 AGUA EN POZOS DE IWRM at the National Level cotizaciones Envelope pendiente 28 15 16 PRODUCCIÓN UBICADOS EN EL ÁMBITO DE ICA A TRAVÉS FLUJÓMETROSELECTROMÁGN ETICOS Y DE TURBINA. PE-ANA-236175-NC-RFQ / SERVICIO DE IMPLEMENTACIÓN DE EJEMPLOS PILOTO DE MEDICIÓN DE CONSUMO DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-05- 2021-06- 2021-06- AGUA EN POZOS DE IBRD / 87400 Posterior Limited 15,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 28 15 17 PRODUCCIÓN UBICADOS EN EL ÁMBITO DE TACNA A TRAVÉS FLUJÓMETROSELECTROMÁGN ETICOS Y DE TURBINA PE-ANA-236180-NC-RFB / SERVICIO PARA EJECUTAR Component 1: Consolidating Solicitud de Single Stage - One 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2021-09- PERFILES GAMMA RAY, CE Y T IBRD / 87400 Posterior Open - National 80,000.00 0.00 Cancelado IWRM at the National Level ofertas Envelope 11 16 28 17 11 17 EN PIEZOMETROS CULMINADOS EN ICA PE-ANA-236181-NC-RFQ / NIVELACIÓN PRECISIÓN DE 47 Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-05- 2021-06- 2021-06- IBRD / 87400 Posterior Limited 10,000.00 0.00 PIEZÓMETROS UBICADOS EN IWRM at the National Level cotizaciones Envelope pendiente 28 15 17 EL ÁMBITO DE TACNA PE-ANA-236182-NC-RFQ / NIVELACIÓN DE PRECISIÓN DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-05- 2021-06- 2021-06- IBRD / 87400 Posterior Limited 20,000.00 0.00 99 POZOS EN LOS ÁMBITOS IWRM at the National Level cotizaciones Envelope pendiente 28 15 17 DE ICA VILLACURÍ Y LANCHAS PE-ANA-236190-NC-RFQ / SERVICIO DE INSTALACION DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-06- 2021-08- 2021-10- CARTELES DE IBRD / 87400 Posterior Limited 3,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 12 07 06 IDENTIFICACION EN POZOS Y PIEZOMETROS AMBITO ICA (I- V-L) PE-ANA-236191-NC-RFQ / SERVICIO DE INSTALACION DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-06- 2021-08- 2021-09- CARTELES DE IBRD / 87400 Posterior Limited 3,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 12 07 06 IDENTIFICACION EN POZOS Y PIEZOMETROS AMBITO TACNA PE-ANA-236194-NC-RFB / SERVICIO DE PERFILAJE E INTERPRETACION A TRAVES Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-07- 2021-08- 2021-09- 2021-10- 2022-01- DE SONDAS DE RESONANCIA IBRD / 87400 Posterior Open - National 200,000.00 0.00 IWRM at the National Level ofertas Envelope pendiente 05 10 21 20 25 23 MAGNETIA NUCLEAR (NMR) EN PIEZOMETROS EN EL AMBITO TACNA PE-ANA-161129-NC-RFQ / SERVICIO DE ADAPTACIÓN DE Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-06- 2021-06- 2021-07- 2021-08- 2021-09- 2021-11- ÁRBOLES DE DESCARGA EN IBRD / 87400 Posterior Open - National 94,030.00 0.00 IWRM at the National Level ofertas Envelope pendiente 04 09 21 10 14 13 POZOS UBICADOS EN EL ÁMBITO DE TACNA PE-ANA-241748-NC-RFQ / SERVICIO PARA EJECUTAR Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-09- 2022-03- PERFILES GAMMA RAY, CE Y T IBRD / 87400 Posterior Limited 40,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 20 14 13 EN PIEZOMETROS CULMINADOS EN ICA PE-ANA-241755-NC-RFQ / SERVICIO PARA EJECUTAR Component 1: Consolidating Solicitud de Single Stage - One Ejecución 2021-07- 2021-09- 2022-03- PERFILES GAMMA RAY, CE Y T IBRD / 87400 Posterior Limited 30,000.00 0.00 IWRM at the National Level cotizaciones Envelope pendiente 20 14 13 EN PIEZOMETROS CULMINADOS EN TACNA CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SBCC 002 ANA MGRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TECNICOS PARA CONSTRUCCION DE 200 Component 1: Consolidating Selección basada 2018-06- 2018-06- 2018-06- 2018-06- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-07- 2018-10- ESTRUCTURAS DE CONTROL Y IBRD / 87400 Posterior Open - National 125,000.00 0.00 Cancelado 2018-06-01 IWRM at the National Level en calidad y costo 13 08 18 23 10 08 12 11 26 13 31 14 MEDICION DE AGUA EN BLOQUES DE RIEGO EN DIECIOCHO SECTORES HIDRAULICO DE LA ZONA CENTRO DE LA COSTA DEL PERU SBCC 003 2018 ANA PGIRH / CONSULTORÍA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA CONSTRUCCIÓN DE 274 Component 1: Consolidating Selección basada 2018-06- 2018-06- 2018-07- 2018-08- 2018-08- 2018-10- 2018-11- 2019-02- IBRD / 87400 Posterior Open - National 148,931.00 0.00 Cancelado 2018-06-15 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level en calidad y costo 25 20 23 07 16 29 16 14 DE AGUA EN BLOQUES DE RIEGO EN DOCE (12) SECTORES HIDRÁULICOS DE LA ZONA NORTE DE LA COSTA DEL PERÚ SBCC 001 ANA PGIRH / FORMULACIÓN DE LOS Component 2: Improving Selección basada Open - 2018-08- 2018-06- 2018-07- 2018-10- 2018-10- 2018-10- 2018-11- 2020-11- PLANES DE GESTIÓN DE IBRD / 87400 WRM in Selected Pilot River Previa 5,955,217.00 0.00 Cancelado 2018-06-01 en calidad y costo International 08 06 11 08 19 26 27 26 RECURSOS HDRICOS EN Basins CUATRO CUENCAS Page 7 SBCC 004 2018 ANA PGIRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA CONSTRUCCIÓN DE 337 Component 1: Consolidating Selección basada 2018-07- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2019-01- IBRD / 87400 Posterior Open - National 155,680.00 0.00 Cancelado 2018-07-05 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level en calidad y costo 17 11 08 15 12 19 27 05 03 DE AGUA EN BLOQUES DE RIEGO EN TREINTA (30) SECTORES HIDRÁULICOS DE LA ZONA SUR DE LA COSTA DEL PERÚ SBC 001 2018 ANA PGIRH BM / ESTUDIO DE LÍNEA BASE Component 3: General Selección basada 2018-08- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2018-12- DEL PIP 302961 GESTIÓN IBRD / 87400 Posterior Open - National 88,459.00 99,407.20 Firmado 2018-07-23 Project Adminstration en calidad 08 25 12 22 11 24 14 05 17 18 28 19 27 INTEGRADA DE LOS RECURSOS HÍDRICOS EN DIEZ CUENCAS SBCC 005 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE Component 2: Improving Selección basada Open - 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2019-07- 2020-11- RECURSOS HÍ DRICOS EN DOS IBRD / 87400 WRM in Selected Pilot River Previa 1,809,400.00 2,537,766.50 Firmado 2018-08-22 en calidad y costo International 03 06 11 16 06 16 08 21 09 24 24 13 26 02 CUENCAS PILOTO DE LA Basins VERTIENTE DEL ATLÁNTICO: MAYO Y MANTARO SBCC 006 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE Component 2: Improving RECURSOS HIDRICOS EN DOS Selección basada Open - 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2020-05- IBRD / 87400 WRM in Selected Pilot River Previa 2,151,920.00 0.00 En ejecución 2018-08-22 CUENCAS PILOTO DE LA en calidad y costo International 03 06 11 16 06 16 08 21 09 24 24 13 06 Basins VERTIENTE DEL ATLÁNTICO: PAMPAS-APURIMAC Y URUBAMBA-VILCANOTA SBCC 007 2018 ANA PGIRH BM / SUPERVISIÓN DE LA PERFORACIÓN E Component 1: Consolidating Selección basada 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2018-11- 2019-03- INSTALACIÓN DE 58 IBRD / 87400 Posterior Open - National 236,142.00 0.00 Cancelado 2018-09-07 IWRM at the National Level en calidad y costo 08 12 25 23 26 30 15 14 PIEZOMETROS EN LOS ACUIFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA SCC 001 2018 ANA PGIRH BM / SERVICIO DE ASESORÍA Selección basada Component 1: Consolidating 2019-01- 2019-02- 2019-03- 2019-05- EN LA EJECUCIÓN DE LAS IBRD / 87400 Posterior en calificaciones Limited 190,000.00 0.00 Cancelado 2019-01-04 IWRM at the National Level 18 17 24 08 PERFORACIONES EN LA de consultores REGIÓN DE ICA Y TACNA SBCC 001 2019 ANA PGIRH BM / SUPERVISION PARA EL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating Selección basada 2019-04- 2019-02- 2019-04- 2019-03- 2019-07- 2019-04- 2019-08- 2019-05- 2019-08- 2019-05- 2019-08- 2019-06- 2020-01- PUESTA EN FUNCIONAMIENTO IBRD / 87400 Posterior Open - National 326,071.00 0.00 En ejecución 2019-02-11 IWRM at the National Level en calidad y costo 05 16 05 31 03 28 02 08 09 18 19 13 09 Y CAPACITACIÓN DE LA INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS SCC 001 2019 ANA PGIRH BM / SERVICIO DE Component 2: Improving Selección basada Ejecución 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- CONSULTORIA PARA LA IBRD / 87400 WRM in Selected Pilot River Posterior en calificaciones Open - National 164,180.00 0.00 2019-04-05 pendiente 26 09 09 13 12 IMPLEMENTACIÓN DEL PLAN Basins de consultores DE DESARROLLO DE CAPACIDADES SBCC 003 2019 ANA PGIRH BM / SERVICIO DE Component 1: Consolidating Selección basada 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-11- CONSULTORIA PARA LA IBRD / 87400 Posterior Open - National 126,453.73 0.00 En ejecución 2019-04-01 IWRM at the National Level en calidad y costo 17 15 06 27 11 25 17 14 IMPLEMENTACION DE LA FASE 0 - GOBIERNO DE DATOS PE-ANA-121030-CS-QCBS / SERVICIO DE CONSULTORÍA PARA LA PROMOCIÓN E IMPLEMENTACIÓN DE Component 2: Improving MECANISMOS DE Selección basada 2019-09- 2019-09- 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2022-03- IBRD / 87400 WRM in Selected Pilot River Posterior Open - National 1,399,406.25 0.00 En ejecución 2019-09-19 FINANCIAMIENTO DE en calidad y costo 20 24 21 20 29 13 23 12 Basins PROGRAMAS Y PROYECTOS DE LOS PLANES DE GESTIÓN INTEGRADA DE RECURSOS HÍDRICOS DE CUENCA PE-ANA-161088-CS-QCBS / SUPERVISION DEL SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Selección basada Open - 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2021-10- Y CAPACITACIÓN DE IBRD / 87400 Posterior 500,000.00 0.00 Cancelado 2020-04-12 IWRM at the National Level en calidad y costo International 03 16 14 13 17 22 22 SISTEMAS MECANIZADOS DE AFOROS, PASARELAS DE AFOROS Y WINCHAS DE AFOROS PE-ANA-165654-CS-CQS / SUPERVISIÓN DE LA Selección basada Component 1: Consolidating Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- CONSTRUCCIÓN DE 131 IBRD / 87400 Posterior en calificaciones Open - National 80,600.00 0.00 2020-11-02 IWRM at the National Level pendiente 23 06 05 12 09 ESTRUCTURAS DE MEDICIÓN de consultores DE AGUA EN LA REGIÓN PIURA PE-ANA-165655-CS-CQS / SUPERVISIÓN DE LA Selección basada CONSTRUCCIÓN DE 95 Component 1: Consolidating Ejecución 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Posterior en calificaciones Open - National 58,449.43 0.00 2020-06-01 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level pendiente 22 05 04 09 08 de consultores DE AGUA EN LA REGIÓN LAMBAYEQUE PE-ANA-165656-CS-CQS / SUPERVISIÓN DE LA Selección basada CONSTRUCCIÓN DE 80 Component 1: Consolidating Ejecución 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Posterior en calificaciones Open - National 49,220.57 0.00 2020-06-01 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level pendiente 22 05 04 09 08 de consultores DE AGUA EN LA REGIÓN LA LIBERTAD PE-ANA-165657-CS-CQS / SUPERVISIÓN DE LA Selección basada CONSTRUCCIÓN DE 73 Component 1: Consolidating 2021-03- 2020-05- 2021-03- 2020-07- 2021-05- 2020-08- 2020-09- 2021-02- IBRD / 87400 Posterior en calificaciones Open - National 44,913.77 0.00 En ejecución 2020-05-01 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 23 22 25 05 12 04 08 05 de consultores DE AGUA EN LA REGIÓN ANCASH PE-ANA-165658-CS-CQS / SUPERVISIÓN DE LA Selección basada CONSTRUCCIÓN DE 73 Component 1: Consolidating 2020-05- 2020-07- 2020-08- 2020-09- 2021-02- IBRD / 87400 Posterior en calificaciones Open - National 44,913.77 0.00 Cancelado 2020-05-01 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 22 05 04 08 05 de consultores DE AGUA EN LA REGIÓN ANCASH PE-ANA-165659-CS-CQS / SUPERVISIÓN DE LA Selección basada Component 1: Consolidating 2021-04- 2020-05- 2021-04- 2020-07- 2020-08- 2020-09- 2021-02- CONSTRUCCIÓN DE 87 IBRD / 87400 Posterior en calificaciones Open - National 53,527.37 0.00 En ejecución 2020-05-01 IWRM at the National Level 15 22 26 05 04 08 05 ESTRUCTURAS DE MEDICIÓN de consultores DE AGUA EN LA REGIÓN LIMA PE-ANA-165660-CS-CQS / SUPERVISIÓN DE LA Selección basada Component 1: Consolidating Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- CONSTRUCCIÓN DE 107 IBRD / 87400 Posterior en calificaciones Open - National 65,832.51 0.00 2020-11-02 IWRM at the National Level pendiente 23 06 05 12 09 ESTRUCTURAS DE MEDICIÓN de consultores DE AGUA EN LA REGIÓN ICA PE-ANA-165661-CS-CQS / SUPERVISIÓN DE LA Selección basada CONSTRUCCIÓN DE 190 Component 1: Consolidating Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 87400 Posterior en calificaciones Open - National 116,898.86 0.00 2020-11-02 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level pendiente 23 06 05 12 08 de consultores DE AGUA EN LA REGIÓN AREQUIPA SBCC 002 2019 ANA PGIRH BM / SUPERVISIÓN PARA EL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating Selección basada 2019-02- 2019-04- 2019-05- 2019-05- 2019-06- 2019-07- 2021-01- PUESTA EN FUNCIONAMIENTO IBRD / 87400 Previa Open - National 629,981.44 0.00 Cancelado 2019-02-22 IWRM at the National Level en calidad y costo 27 08 08 13 05 06 03 Y CAPACITACIÓN DE 153 ESTACIONES HIDROLÓGICAS CON 33 EHCA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCI-001 / III Administración Component 3: General 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2018-04- 2018-10- General del Proyecto IBRD / 87400 Previa Individual Open 360,000.00 324,000.00 Firmado 2017-12-28 Project Adminstration 31 12 12 15 24 18 06 15 III.a Director Ejecutivo SCI 003 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2022-11- IBRD / 87400 Previa Individual Limited 202,500.00 0.00 Cancelado 2018-05-22 Especialista en Adquisiciones Project Adminstration 30 23 29 31 06 SCI 004 ANA PGIRH / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 Previa Individual Limited 192,000.00 0.00 Cancelado 2018-05-25 RECURSOS HÍDRICOS - Project Adminstration 01 08 12 22 COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 005 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-05- ESPECIALISTA EN AGUA IBRD / 87400 Posterior Individual Limited 192,000.00 13,730.67 Firmado 2018-05-28 Project Adminstration 28 04 27 11 29 13 29 23 SUBTERRÁNEAS SCI 009 ANA PGIRH / Component 3: General 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2021-05- IBRD / 87400 Posterior Individual Limited 72,000.00 7,292.52 Firmado 2018-05-28 GEOGRAFO - SIG Project Adminstration 09 04 11 11 14 13 29 28 SCI 010 ANA PGIRH / Component 3: General 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- IBRD / 87400 Posterior Individual Limited 71,460.00 5,955.00 Firmado 2018-05-25 ASISTENTE TECNICO Project Adminstration 25 01 26 08 01 12 01 27 TALLERES SCI 011 ANA PGIRH / Component 2: Improving 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 19,664.33 Firmado 2018-05-28 15 04 18 11 06 13 06 23 CUENCA PILOTO URUBAMBA Basins SCI 012 ANA PGIRH / Component 2: Improving 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- 2018-10- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 19,664.33 Finalizado 2018-05-28 15 04 18 11 06 13 06 23 04 CUENCA PILOTO MAYO Basins SCI 013 ANA PGIRH / Component 2: Improving 2018-07- 2018-06- 2018-07- 2018-06- 2018-07- 2018-06- 2018-07- 2022-11- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 15,489.35 Firmado 2018-05-28 16 04 20 11 25 13 30 19 CUENCA PILOTO PAMPAS Basins SCI 014 ANA PGIRH / Component 2: Improving 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 184,140.00 17,105.99 Firmado 2018-05-28 15 04 18 11 05 13 06 23 CUENCA PILOTO MANTARO Basins SCI 017 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,772.45 Firmado 2018-06-04 RECURSOS HIDRICOS 27 11 27 19 01 22 11 01 Basins CUENCA PILOTO MAYO SCI 016 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,630.53 Firmado 2018-06-04 RECURSOS HIDRICOS 14 11 14 19 20 22 11 01 Basins CUENCA PILOTO PAMPAS SCI 018 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-06- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,763.15 Firmado 2018-06-04 RECURSOS HIDRICOS 14 11 14 19 24 22 11 01 Basins CUENCA PILOTO MANTARO Page 8 SCI 024 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,681.43 Firmado 2018-06-04 AMBIENTAL CUENCA PILOTO 27 11 27 19 02 22 11 28 Basins MAYO SCI 025 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,681.43 Firmado 2018-06-04 AMBIENTAL CUENCA PILOTO 22 11 22 19 25 22 11 28 Basins PAMPAS SCI 026 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,434.04 Firmado 2018-06-04 AMBIENTAL CUENCA PILOTO 22 11 22 19 25 22 11 28 Basins MANTARO SCI 027 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-11- ASESOR EN GESTIÓN DE IBRD / 87400 Posterior Individual Limited 286,200.00 0.00 Cancelado 2018-05-25 Project Adminstration 01 08 12 18 RECURSOS HÍDRICOS SCI 029 ANA PGIRH / Component 3: General 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 64,800.00 4,119.20 Firmado 2018-05-29 SECRETARIA DE LA JEFATURA Project Adminstration 29 06 02 13 08 15 29 21 SCI 031 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 54,000.00 3,432.67 Firmado 2018-05-29 CHOFER DE JEFATURA Project Adminstration 29 06 15 13 24 15 29 21 SCI 035 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2021-05- IBRD / 87400 Posterior Individual Limited 36,000.00 2,747.18 Firmado 2018-05-29 ASISTENTE SOPORTE Project Adminstration 29 06 13 13 14 15 28 30 TECNICO SCI 036 ANA PGIRH / Component 3: General 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-10- 2022-11- SECRETARIA DE IBRD / 87400 Posterior Individual Limited 54,000.00 2,574.50 Firmado 2018-05-29 Project Adminstration 20 06 26 13 28 15 01 21 ADMINISTRACION Y FINANZAS SCI 037 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- CHOFER DE ADMINISTRACIÓN IBRD / 87400 Posterior Individual Limited 48,600.00 3,139.64 Firmado 2018-05-29 Project Adminstration 29 06 30 13 08 15 29 21 Y FINANZAS SCI 038 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 103,500.00 8,625.00 Firmado 2018-05-29 Project Adminstration 29 06 26 13 01 15 01 30 ADQUISICIONES 1 SCI 040 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- IBRD / 87400 Posterior Individual Limited 48,600.00 2,354.73 Firmado 2018-05-29 CHOFER DE ADQUISICIONES Project Adminstration 29 06 23 13 07 15 24 21 SCI 042 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-08- 2018-06- 2018-09- 2018-06- 2018-09- 2021-05- IBRD / 87400 Posterior Individual Limited 67,500.00 6,059.71 Firmado 2018-05-28 ASISTENTE DE CONTABILIDAD Project Adminstration 28 04 24 11 04 13 17 28 SCI 043 ANA PGIRH / Component 3: General 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- IBRD / 87400 Posterior Individual Limited 155,250.00 7,607.80 Firmado 2018-05-28 ESPECIALISTA FINANCIERO Project Adminstration 17 04 18 11 26 13 28 19 SCI 044 ANA PGIRH / Component 3: General 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2022-11- IBRD / 87400 Posterior Individual Limited 194,076.00 12,680.56 Firmado 2018-05-28 ESPECIALISTA EN TESORERIA Project Adminstration 24 04 24 11 29 13 29 19 SCI 045 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-07- 2018-06- 2018-08- 2018-06- 2018-08- 2021-05- IBRD / 87400 Posterior Individual Limited 67,500.00 6,802.54 Firmado 2018-05-29 ASISTENTE DE TESORERIA Project Adminstration 29 06 30 13 08 15 29 30 SCI 033 ANA PGIRH / Component 3: General 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2018-06- 2018-09- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 155,250.00 7,378.62 Firmado 2018-06-04 Project Adminstration 11 11 13 18 24 22 24 28 PRESUPUESTO SCI 002 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2018-11- Especialista en IBRD / 87400 Previa Individual Limited 243,000.00 0.00 Cancelado 2018-05-22 Project Adminstration 29 23 29 31 09 Administración y Finanzas SCI 053 ANA PGIRH / Component 3: General 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- ESPECIALISTA EN IBRD / 87400 Previa Individual Open 243,000.00 13,500.00 Firmado 2018-06-14 Project Adminstration 21 02 22 02 09 03 10 30 ADMINISTRACIÓN Y FINANZAS SCI 054 2018 ANA PGIRH / Component 3: General 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- ESPECIALISTA EN IBRD / 87400 Previa Individual Open 202,500.00 9,125.00 Firmado 2018-06-14 Project Adminstration 21 02 03 02 22 03 22 30 ADQUISICIONES SCI 007-ANA-PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 Posterior Individual Direct 192,000.00 0.00 Cancelado 2018-05-25 ESPECIALISTA AMBIENTAL Project Adminstration 04 06 08 18 SCI 028 2018 ANA PGIRH BM Component 3: General 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 13,687.88 Firmado 2018-07-19 / ESPECIALISTA AMBIENTAL Project Adminstration 08 20 10 30 19 31 29 30 SCI 030 2018 ANA PGIRH BM / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado 2018-07-19 RECURSOS HÍDRICOS - Project Adminstration 20 25 30 01 31 01 30 COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 006 2018 ANA PGIRH BM Component 3: General 2018-08- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2022-12- / ASESOR EN GESTIÓN DE IBRD / 87400 Previa Individual Limited 286,200.00 0.00 En ejecución 2018-07-19 Project Adminstration 02 20 07 30 03 31 30 RECURSOS HÍDRICOS SCI 008 2018 ANA PGIRH BM Component 3: General 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2022-12- / ESPECIALISTA EN GESTIÓN IBRD / 87400 Posterior Individual Limited 192,000.00 14,155.09 Firmado 2018-07-19 Project Adminstration 25 20 25 30 29 31 29 30 DE RECURSOS HÍDRICOS SCI 060 2018 ANA PGIRH / Component 2: Improving ESPECIALISTA EN SISTEMAS 2018-09- 2018-07- 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,434.04 Firmado 2018-07-19 DE INFORMACIÓN CUENCA 14 20 14 30 25 31 11 30 Basins PILOTO MANTARO SCI 061 2018 ANA PGIRH BM Component 2: Improving / ESPECIALISTA EN SISTEMAS 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,339.10 Firmado 2018-07-19 DE INFORMACIÓN CUENCA 25 20 25 30 01 31 12 30 Basins PILOTO PAMPAS SCI 062 2018 ANA PGIRH BM Component 2: Improving / ESPECIALISTA EN SISTEMAS 2018-09- 2018-07- 2020-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 151,200.00 6,101.27 Firmado 2018-07-19 DE INFORMACIÓN CUENCA 28 20 28 30 05 31 12 30 Basins PILOTO MAYO SCI 063 2018 ANA PGIRH BM Component 2: Improving / ASISTENTE TÉCNICO EN 2018-10- 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-11- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 2,887.04 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 23 20 23 30 25 31 09 30 Basins CUENCA PILOTO URUBAMBA SCI 064 2018 ANA PGIRH BM Component 2: Improving / ASISTENTE TÉCNICO EN 2018-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,348.05 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 19 20 28 30 05 31 16 30 Basins CUENCA PILOTO MANTARO SCI 065 2018 ANA PGIRH BM Component 2: Improving / ASISTENTE TÉCNICO EN 2018-07- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,576.89 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 19 20 28 30 02 31 11 30 Basins CUENCA PILOTO MAYO SCI 034 2018 ANA PGIRH BM Component 2: Improving / ASISTENTE TÉCNICO EN 2018-09- 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 96,000.00 4,198.58 Firmado 2018-07-19 SISTEMAS DE INFORMACIÓN 18 20 25 30 02 31 12 30 Basins CUENCA PILOTO PAMPAS SBCC 066 2018 ANA PGIRH Component 1: Consolidating 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2022-12- 2018 / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado 2018-08-28 IWRM at the National Level 28 30 07 01 28 05 28 30 HIDROMETRIA SCI 015 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2020-02- 2019-02- 2020-02- 2019-02- 2020-03- 2019-02- 2020-03- 2020-02- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 7,099.38 Firmado 2019-02-08 RECURSOS HIDRICOS 20 15 24 20 02 28 02 28 Basins CUENCA PILOTO URUBAMBA SCI 056 2018 ANA PGIRH BM Component 2: Improving 2019-04- 2019-02- 2019-04- 2019-02- 2019-04- 2019-02- 2019-06- 2020-02- / COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 40,920.00 5,904.71 Firmado 2019-02-08 17 15 24 20 29 28 28 28 CUENCA URUBAMBA Basins SCI 057 2018 ANA PGIRH BM Component 2: Improving 2019-07- 2019-02- 2019-07- 2019-02- 2019-07- 2019-02- 2019-07- 2020-02- / COORDINADOR TÉCNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 40,920.00 5,511.15 Firmado 2019-02-08 12 15 18 20 24 28 31 28 CUENCA MAYO Basins SCI 023 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2020-02- 2019-04- 2020-02- 2019-04- 2020-03- 2019-04- 2020-03- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-04-05 AMBIENTAL CUENCA PILOTO 18 15 24 20 02 30 02 29 Basins URUBAMBA SCI 046 ANA PGIRH / Component 3: General Ejecución 2019-04- 2019-04- 2019-04- 2020-04- ESPECIALISTA EN CONTROL IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-04-05 Project Adminstration pendiente 15 20 30 29 PATRIMONIAL Y ALMACEN SCI 055 2018 ANA PGIRH BM Component 3: General 2019-09- 2019-05- 2020-01- 2019-05- 2019-05- 2020-05- / ESPECIALISTA EN IBRD / 87400 Posterior Individual Open 54,000.00 0.00 En ejecución 2019-04-05 Project Adminstration 20 15 15 20 31 24 ADMINISTRACIÓN Y FINANZAS SCI 071 2018 ANA PGIRH BM Component 3: General 2019-09- 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 87400 Previa Individual Open 55,880.63 0.00 Bajo Revision 2019-04-05 / JEFE DE PROYECTO Project Adminstration 20 20 25 09 08 SCI 059 2018 ANA PGIRH / Component 2: Improving ESPECIALISTA EN SISTEMAS 2020-02- 2019-04- 2020-02- 2019-04- 2020-03- 2019-05- 2020-03- 2020-05- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-04-05 DE INFORMACIÓN CUENCA 17 20 21 25 02 05 02 04 Basins PILOTO URUBAMBA SCI 058 2018 ANA PGIRH BM / CONSULTOR EN SEGURIDAD Component 1: Consolidating 2019-04- 2019-04- 2019-04- 2019-05- IBRD / 87400 Posterior Individual Limited 6,000.00 0.00 Cancelado 2019-04-05 DE PRESAS -SALVAGUARDAS IWRM at the National Level 15 20 30 30 BANCO MUNDIAL PE-ANA-116127-CS-INDV / ESTUDIO DE INGENIERÍA DE DETALLE DE TELECOMUNICACIONES PARA Component 1: Consolidating 2019-07- 2019-08- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 13,433.00 0.00 Cancelado 2019-05-31 LA TRANSMISIÓN DE DATOS IWRM at the National Level 19 09 13 12 DE 396 PUNTOS DE MEDICIÓN DE NIVEL EN BLOQUES DE RIEGO PE-ANA-121010-CS-INDV / SUPERVISIÓN DE LA CONTRATACIÓN - OBRAS CIVILES PARA LA IMPLEMENTACIÓN DEL CENTRO DE DATOS, Component 1: Consolidating 2020-02- 2019-11- 2020-02- 2019-11- 2020-02- 2019-12- 2020-02- 2020-06- LABORATORIO DE IBRD / 87400 Posterior Individual Open 23,880.00 24,349.99 Firmado 2019-10-01 IWRM at the National Level 04 20 03 25 26 05 26 02 INSTRUMENTACIÓN, CENTRO DE MONITOREO Y MODELAMIENTO DE RECURSOS HÍDRICOS DE LA AUTORIDAD NACIONAL DEL AGUA PE-ANA-122155-CS-INDV / Component 2: Improving ASISTENTE DE 2020-02- 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,099.38 Firmado 2019-10-01 COMUNICACIONES CUENCA 17 06 20 21 27 31 02 30 Basins URUBAMBA PE-ANA-122156-CS-INDV / Component 2: Improving ASISTENTE DE 2020-02- 2019-10- 2020-01- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,099.38 Firmado 2019-10-01 COMUNICACIONES CUENCA 18 06 29 21 02 31 02 30 Basins MAYO Page 9 PE-ANA-122157-CS-INDV / Component 2: Improving 2020-02- 2019-10- 2020-01- 2019-10- 2020-02- 2019-10- 2020-03- 2020-10- ESPECIALISTA SOCIAL IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,231.08 Firmado 2019-10-01 18 06 30 21 28 31 02 30 AMBIENTAL CUENCA MAYO Basins PE-ANA-122158-CS-INDV / Component 2: Improving 2020-02- 2019-10- 2020-01- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- ESPECIALISTA SISTEMA DE IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 33,600.00 9,939.13 Firmado 2019-10-01 18 06 29 21 02 31 02 30 INFORMACIÓN CUENCA Basins MAYO PE-ANA-122159-CS-INDV / Component 2: Improving ASISTENTE DE 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,101.30 Firmado 2019-10-01 COMUNICACIÓN CUENCA 18 06 21 21 02 31 03 30 Basins PAMPAS PE-ANA-122160-CS-INDV / Component 2: Improving 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- COORDINADOR TÉCNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 134,220.00 12,107.93 Firmado 2019-10-01 18 06 21 21 02 31 02 30 CUENCA MANTARO Basins PE-ANA-122161-CS-INDV / Component 2: Improving ASISTENTE DE 2020-02- 2019-10- 2020-02- 2019-10- 2020-03- 2019-10- 2020-03- 2020-10- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 7,101.30 Firmado 2019-10-01 COMUNICACIÓN CUENCA 18 06 21 21 02 31 02 30 Basins MANTARO SCI 047 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 TECNICO DE ARCHIVO Project Adminstration 15 20 30 29 SCI 048 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE EN SERVICIOS IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 GENERALES Y ARCHIVO SCI 069 2018 ANA PGIRH BM Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- / TECNICO ADMINISTRATIVO IBRD / 87400 Posterior Individual Limited 8,400.00 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 DE JEFATURA SCI 049 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE ADMINISTRATIVO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO URUBAMBA Basins SCI 050 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE ADMINISTRATIVO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO MAYO Basins SCI 051 ANA PGIRH / Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE ADMINISTRATIVO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO PAMPAS Basins SCI 052 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- ASISTENTE ADMINISTRATIVO IBRD / 87400 Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 CUENCA PILOTO MANTARO SCI 020 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 CULTURA DEL AGUA CUENCA 15 20 30 29 Basins PILOTO MAYO SCI 021 ANA PGIRH / Component 2: Improving ASISTENTE TÉCNICO 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 CULTURA DEL AGUA CUENCA 15 20 30 29 Basins PILOTO PAMPAS SCI 019 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 CULTURA DEL AGUA CUENCA 15 20 30 29 Basins PILOTO URUBAMBA SCI 022 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 CULTURA DEL AGUA CUENCA 15 20 30 29 Basins PILOTO MANTARO SCI 070 2018 ANA PGIRH BM Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- / ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 INFORMATICA PE-ANA-122164-CS-INDV / Component 3: General Ejecución 2019-10- 2019-10- 2019-10- 2020-10- ESPECIALISTA EN SISTEMAS IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-10-01 Project Adminstration pendiente 16 21 31 30 DE INFORMACIÓN SCI 067 2018 ANA PGIRH BM / Supervision de la Contratación - Obras Civiles para la Implementación de la Infraestructura del Centro de Component 1: Consolidating 2019-04- 2019-04- 2019-04- 2019-10- IBRD / 87400 Posterior Individual Limited 19,387.61 0.00 Cancelado 2019-04-05 Datos, Laboratorio de IWRM at the National Level 15 20 30 27 Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-130323-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Posterior Individual Limited 14,330.00 8,180.28 Firmado 2019-09-18 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 23 23 26 26 07 30 14 28 DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130324-CS-INDV / SUPERVISOR 02 DE LA ELABORACIÓN DE EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Posterior Individual Limited 14,330.00 8,137.40 Firmado 2019-09-18 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 23 23 03 26 07 30 14 28 DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130325-CS-INDV / SUPERVISOR 03 DE LA ELABORACIÓN DE EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-11- 2020-01- IBRD / 87400 Posterior Individual Limited 14,330.00 6,259.54 Firmado 2019-09-18 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 23 23 23 26 07 30 04 28 DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130326-CS-INDV / SUPERVISOR 04 DE LA ELABORACIÓN DE EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Posterior Individual Limited 14,330.00 8,235.45 Firmado 2019-09-18 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 23 23 04 26 01 30 14 28 DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130328-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 01 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 38,059.71 0.00 Bajo Revision 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 13 12 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS TUMBES, SAN LORENZO PE-ANA-130329-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 03 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-09- IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 14 ESTRUCTURAS DE MEDICIÓN SECTOR HIDRÁULICOS MyBP, SECHURA PE-ANA-130330-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 05 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 11 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-130331-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 06 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Open 50,746.27 10,296.71 Firmado 2019-09-05 IWRM at the National Level 22 10 11 11 30 13 30 11 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CHANCAY-LAMBAYEQUE, CHICAMA PE-ANA-130334-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 10 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 34,925.38 7,758.27 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 12 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CASMA HUARMEY PE-ANA-130335-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 11 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Open 38,059.71 7,736.16 Firmado 2019-09-05 IWRM at the National Level 22 10 11 11 10 13 10 12 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS FORTALEZA, PATIVILCA, SUPE, HUAURA, CH-HUARAL PE-ANA-130336-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 12 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-02- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Open 11,641.80 10,344.36 Firmado 2019-09-05 IWRM at the National Level 22 10 11 11 27 13 27 10 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-130337-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 13 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Posterior Individual Open 46,567.17 10,344.36 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 11 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS SAN JUAN, PISCO PE-ANA-130338-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 14 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-08- 2019-10- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 34,925.38 7,736.16 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 15 11 01 10 30 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-130339-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 16 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 38,059.71 7,692.31 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 12 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OCOÑA, CAMANÁ Page 10 PE-ANA-132925-CS-INDV / CONSULTORES INDIVIDUALES GRUPO 20 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 34,925.38 5,157.44 Firmado 2019-09-09 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 22 14 11 15 10 17 10 16 SECTORES HIDRÁULICOS Irrig. EMM, Pta de Bombón, Moquegua, Torata, Locumba, Sama, Uchusuma, Bajo Caplina PE-ANA-132943-CS-INDV / ESPECIALISTA EN Component 1: Consolidating 2019-09- 2019-09- 2019-10- 2019-09- 2019-10- 2019-09- 2019-10- 2020-01- IBRD / 87400 Posterior Individual Limited 44,118.00 5,345.12 Firmado 2019-09-18 SENSIBILIZACIÓN Y IWRM at the National Level 23 23 01 26 01 30 11 28 CAPACITACIÓN 01 PE-ANA-132945-CS-INDV / ESPECIALISTA EN Component 1: Consolidating 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Posterior Individual Limited 44,118.00 0.00 En ejecución 2019-09-18 SENSIBILIZACIÓN Y IWRM at the National Level 23 23 26 30 28 CAPACITACIÓN 02 PE-ANA-120995-CS-INDV / ESPECIALISTA EN Component 1: Consolidating 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 SENSIBILIZACIÓN Y IWRM at the National Level 20 25 05 04 CAPACITACIÓN 01 PE-ANA-120996-CS-INDV / ESPECIALISTA EN Component 1: Consolidating 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 SENSIBILIZACION Y IWRM at the National Level 20 25 05 04 CAPACITACIÓN 02 PE-ANA-130340-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 18 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 IWRM at the National Level 22 10 11 11 10 13 10 11 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR, YURA PE-ANA-130332-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 08 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Open 46,567.17 10,314.88 Firmado 2019-09-05 IWRM at the National Level 22 10 11 11 02 13 10 11 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-130333-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 09 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2019-07- 2019-09- 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Posterior Individual Open 38,059.71 7,736.16 Firmado 2019-09-05 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 22 10 11 11 10 13 10 12 ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS SANTA, NEPEÑA, IRCHIM PE-ANA-135207-CS-INDV / Component 3: General 2021-05- 2019-10- 2019-10- 2019-10- 2020-10- ESPECIALISTA EN IBRD / 87400 Previa Individual Open 45,000.00 0.00 Bajo Revision 2019-09-20 Project Adminstration 19 06 11 14 13 ADQUISICIONES PE-ANA-139763-CS-INDV / Contratación de Consultor Internacional para apoyo Component 1: Consolidating 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-11- 2019-10- 2019-11- IBRD / 87400 Posterior Individual Direct 11,842.00 11,842.00 Firmado 2019-10-21 técnico al Taller Análisis de IWRM at the National Level 21 28 23 02 23 09 29 27 Modos de fallo potenciales de la presa Poechos PE-ANA-152038-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 17 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2020-01- 2020-01- 2020-01- 2020-01- 2020-05- IBRD / 87400 Posterior Individual Direct 50,000.00 0.00 Bajo Revision 2020-01-02 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 10 12 17 27 26 DE AGUA EN LOS SECTORES HIDRÁULICOS MENOR VALLE DE MAJES Y VALLE SIGUAS QUILCA PE-ANA-157004-CS-INDV / Contratación de un Especialista Internacional Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- para el diagnóstico de IBRD / 87400 Posterior Individual Direct 66,823.00 66,382.18 Firmado 2020-01-31 IWRM at the National Level 03 02 03 02 04 02 03 17 situación y análisis de la seguridad de la presa Poechos recrecida, durante el llenado del embalse PE-ANA-155010-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-04- IBRD / 87400 Posterior Individual Direct 7,165.00 6,259.54 Firmado 2020-02-06 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 04 08 04 09 06 13 07 13 DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERU PE-ANA-155004-CS-INDV / GRUPO 19 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- ESTRUCTURAS DE MEDICIÓN IBRD / 87400 Posterior Individual Direct 34,925.00 0.00 Bajo Revision 2020-02-06 IWRM at the National Level 04 08 09 13 13 DE AGUA EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-154991-CS-INDV / GRUPO 07 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Posterior Individual Direct 33,134.00 0.00 Bajo Revision 2020-02-06 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 04 08 09 14 15 DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-155862-CS-INDV / GRUPO 02 - PARA ELABORACIÓN DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Posterior Individual Direct 38,059.00 0.00 Bajo Revision 2020-02-06 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 04 08 09 13 13 ESTRUCTURAS DE MEDICIÓN DE AGUA. PE-ANA-155863-CS-INDV / GRUPO 15 PARA ELABORACIÓN DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-06- IBRD / 87400 Posterior Individual Direct 46,566.00 0.00 Bajo Revision 2020-02-06 EXPEDIENTES TÉCNICOS DE IWRM at the National Level 04 08 09 13 12 ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-154996-CS-INDV / GRUPO 04 PARA LA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Consolidating 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Posterior Individual Direct 38,060.00 0.00 Bajo Revision 2020-02-06 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 04 08 09 13 13 DE AGUA EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO PE-ANA-160683-CS-INDV / CONSULTORES ADICIONALES AL GRUPO 07 PARA LA ELABORACIÓN DE LOS Component 1: Consolidating 2020-03- 2020-03- 2020-03- 2020-03- 2020-06- EXPEDIENTES TÉCNICOS DE IBRD / 87400 Posterior Individual Direct 18,400.00 0.00 Bajo Revision 2020-03-16 IWRM at the National Level 03 18 19 24 08 ESTRUCTURAS DE MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-161048-CS-INDV / Component 2: Improving 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2023-01- ESPECIALISTA SOCIAL IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 93,170.00 8,353.32 En ejecución 2020-03-02 17 09 21 16 13 27 01 AMBIENTAL CUENCA PAMPAS Basins PE-ANA-161050-CS-INDV / Component 2: Improving 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2022-12- ASISTENTE DE RECURSOS IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 93,170.00 6,151.37 Firmado 2020-03-02 02 09 10 16 10 27 13 30 HIDRICOS CUENCA PAMPAS Basins PE-ANA-161052-CS-INDV / Component 2: Improving 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2022-12- COORDINADOR TÉCNICO IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 113,469.00 8,970.73 Firmado 2020-03-02 02 09 10 16 31 24 31 30 CUENCA URUBAMBA Basins PE-ANA-163778-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Ejecución 2020-03- 2020-03- 2020-03- 2020-05- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Individual Limited 4,776.00 0.00 2020-03-16 IWRM at the National Level pendiente 17 24 25 25 BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN. PE-ANA-163779-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating 2020-08- 2020-03- 2020-08- 2020-03- 2020-09- 2020-03- 2020-09- 2020-06- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Individual Limited 5,970.00 7,694.18 Firmado 2020-03-16 IWRM at the National Level 10 17 26 24 15 25 15 08 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR IRRIGACION MAJES, VALLE DE MAJES, CAMANA PE-ANA-164551-CS-INDV / APOYO AL ANÁLISIS DE LA SEGURIDAD DE LA PRESA Component 1: Consolidating 2020-01- 2020-04- 2020-04- 2020-04- 2020-05- IBRD / 87400 Posterior Individual Direct 6,500.00 0.00 En ejecución 2020-04-01 POECHOS RECRECIDA, IWRM at the National Level 29 08 13 20 08 DURANTE EL LLENADO DEL EMBALSE PE-ANA-164570-CS-INDV / SERVICIO DE COORDINADOR Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-07- 2020-12- IBRD / 87400 Posterior Individual Limited 30,600.00 26,133.61 Firmado 2020-04-19 DE CALIDAD DE RECURSOS IWRM at the National Level 21 24 21 15 12 19 06 31 HIDRICOS PGIRH PE-ANA-164571-CS-INDV / SERVICIO DE ESPECIALISTA DE Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-04- 2020-05- 2020-05- 2020-12- CALIDAD DE AGUA IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 En ejecución 2020-03-29 IWRM at the National Level 30 03 11 18 29 03 31 SUPERFICIAL CUENCA URUBAMBA PE-ANA-164572-CS-INDV / SERVICIO DE ESPECIALISTA DE Component 1: Consolidating 2020-03- 2020-04- 2020-05- 2020-04- 2020-05- 2020-05- 2020-12- IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 En ejecución 2020-03-29 CALIDAD DE AGUA IWRM at the National Level 30 03 11 18 29 03 31 SUPERFICIAL CUENCA PAMPAS PE-ANA-164573-CS-INDV / SERVICIO DE ESPECIALISTA DE Component 1: Consolidating 2020-04- 2020-04- 2021-05- 2020-04- 2020-05- 2020-05- 2020-06- 2020-12- IBRD / 87400 Posterior Individual Limited 19,600.00 13,367.93 Firmado 2020-03-29 CALIDAD DE AGUA IWRM at the National Level 30 03 11 18 29 03 05 31 SUPERFICIAL CUENCA MAYO PE-ANA-164574-CS-INDV / SERVICIO DE ESPECIALISTA EN Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-12- GESTION DE CALIDAD DE IBRD / 87400 Posterior Individual Limited 19,600.00 19,084.99 En ejecución 2020-03-29 IWRM at the National Level 13 03 24 18 08 03 31 RECURSOS HIDRICOS CUENCA MANTARO Page 11 PE-ANA-164991-CS-INDV / SERVICIO DE APOYO EN PROCESAMIENTO DE INFORMACION DE Component 1: Consolidating 2020-04- 2020-04- 2020-06- 2020-04- 2020-07- 2020-05- 2020-07- 2020-12- IBRD / 87400 Posterior Individual Limited 16,000.00 9,694.36 Firmado 2020-04-01 ACTIVIDADES DEL IWRM at the National Level 01 06 24 21 02 06 02 31 COMPONENTE DE CALIDAD DE RECURSOS HIDRICOS EN LA CUENCA MANTARO PE-ANA-164992-CS-INDV / SERVICIO DE APOYO EN GESTIONES Y MONITOREO DE EJECUCION DE ACTIVIDADES Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- 2020-12- IBRD / 87400 Posterior Individual Limited 11,000.00 10,394.88 Firmado 2020-04-01 DEL COMPONENTE DE IWRM at the National Level 06 06 24 11 08 21 06 31 MONITOREO DE LA CALIDAD DE LOS RECURSOS HIDRICOS PGIRH PE-ANA-165879-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating 2020-08- 2020-05- 2020-08- 2020-05- 2020-09- 2020-05- 2020-09- 2020-07- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Individual Limited 5,672.00 5,134.37 Firmado 2020-05-20 IWRM at the National Level 10 21 26 28 15 29 15 27 BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN PE-ANA-165880-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating Ejecución 2020-05- 2020-05- 2020-05- 2020-08- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Individual Limited 7,090.00 0.00 2020-05-20 IWRM at the National Level pendiente 21 28 29 12 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-165881-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating 2020-08- 2020-06- 2020-08- 2020-06- 2020-09- 2020-06- 2020-09- 2020-09- DE NIVEL DE AGUA EN IBRD / 87400 Posterior Individual Limited 7,090.00 7,701.56 Firmado 2020-06-19 IWRM at the National Level 10 22 26 29 15 30 15 14 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-165883-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN BLOQUES DE RIEGO EN EL Component 1: Consolidating 2020-09- 2020-06- 2020-09- 2020-06- 2020-10- 2020-06- 2020-10- 2020-08- IBRD / 87400 Posterior Individual Limited 5,672.00 6,417.96 Firmado 2020-06-19 SECTOR HIDRÁULICO MENOR IWRM at the National Level 22 22 25 29 30 30 30 28 IRRIGACIÓN ENSENADA-MEJIA- MOLLENDO, PUNTA DE BOMBOM, MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-165889-CS-INDV / BACHILLER 01 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-04- 2020-05- 2020-06- 2022-11- IBRD / 87400 Posterior Individual Limited 38,955.00 0.00 Cancelado 2020-04-20 EN ESTRUCTURAS DE IWRM at the National Level 27 18 22 09 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165890-CS-INDV / BACHILLER 02 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-04- 2020-05- 2020-06- 2022-11- IBRD / 87400 Posterior Individual Limited 38,955.00 0.00 Cancelado 2020-04-20 EN ESTRUCTURAS DE IWRM at the National Level 27 18 22 09 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165891-CS-INDV / PROFESIONAL ESPECIALISTA Component 1: Consolidating 2020-03- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- 2020-07- 2021-02- PARA ADECUACIÓN DE IBRD / 87400 Posterior Individual Limited 26,269.00 8,562.53 Firmado 2020-04-20 IWRM at the National Level 30 27 01 18 13 22 06 17 ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165964-CS-INDV / TÉCNICO 01: Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Posterior Individual Limited 14,300.00 0.00 Cancelado 2020-04-19 IWRM at the National Level 24 29 14 10 CAPACITACIÓN EN SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165971-CS-INDV / TÉCNICO 02: Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Posterior Individual Limited 14,300.00 0.00 Cancelado 2020-04-19 IWRM at the National Level 24 29 14 10 CAPACITACIÓN EN SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165979-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS 01 Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Posterior Individual Limited 4,030.00 3,633.92 Firmado 2020-04-20 PARA ESTANDARIZACIÓN E IWRM at the National Level 20 25 22 30 08 15 08 13 INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165984-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS 02 Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Posterior Individual Limited 4,030.00 3,633.92 Firmado 2020-04-20 PARA ESTANDARIZACIÓN E IWRM at the National Level 20 25 22 30 08 06 08 04 INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165985-CS-INDV / PROFESIONAL ESPECIALISTA Component 1: Consolidating 2020-03- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2022-01- EN EJECUCIÓN DE OBRAS DE IBRD / 87400 Posterior Individual Limited 81,493.00 28,070.18 Firmado 2020-04-20 IWRM at the National Level 30 25 02 30 01 06 22 26 ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165987-CS-INDV / PROFESIONAL ASISTENTE EN Component 1: Consolidating 2020-03- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2022-01- EJECUCIÓN DE OBRAS DE IBRD / 87400 Posterior Individual Limited 59,553.00 20,512.82 Firmado 2020-04-20 IWRM at the National Level 30 25 02 30 01 06 22 26 ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165989-CS-INDV / SUPERVISIÓN DE LA CONSTRUCCIÓN DE 22 Component 1: Consolidating 2020-09- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2021-02- 2020-08- IBRD / 87400 Posterior Individual Limited 14,142.00 14,011.42 Firmado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 16 25 17 30 02 15 10 13 DE AGUA EN LA REGIÓN TUMBES PE-ANA-165990-CS-INDV / SUPERVISIÓN DE LA CONSTRUCCIÓN DE 11 Component 1: Consolidating 2020-09- 2020-04- 2020-11- 2020-04- 2020-11- 2020-05- 2020-11- 2020-05- IBRD / 87400 Posterior Individual Limited 7,071.00 8,118.86 Firmado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 16 25 04 30 09 15 18 21 DE AGUA EN LA REGIÓN MOQUEGUA PE-ANA-165991-CS-INDV / SUPERVISIÓN DE LA CONSTRUCCIÓN DE 15 Component 1: Consolidating 2020-09- 2020-04- 2020-09- 2020-04- 2020-10- 2020-05- 2020-11- 2020-07- IBRD / 87400 Posterior Individual Limited 9,643.00 9,705.99 Firmado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 16 25 11 30 02 15 02 14 DE AGUA EN LA REGIÓN TACNA PE-ANA-165993-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN Component 1: Consolidating 2020-07- 2020-04- 2020-07- 2020-04- 2020-07- 2020-05- 2020-07- IBRD / 87400 Posterior Individual Limited 5,672.00 4,917.82 En ejecución 2020-04-20 DE NIVEL DE AGUA EN IWRM at the National Level 10 25 09 30 29 15 14 BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO PE-ANA-165994-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-08- IBRD / 87400 Posterior Individual Limited 8,508.00 0.00 Cancelado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 25 30 15 13 DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE TUMBES HASTA JEQUETEPEQUE PE-ANA-165998-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Posterior Individual Limited 5,672.00 0.00 Cancelado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 25 30 15 14 DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE CHICAMA HASTA SANTA PE-ANA-165999-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Posterior Individual Limited 5,672.00 0.00 Cancelado 2020-04-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 25 30 15 14 DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-166000-CS-INDV / TÉCNICO 01 PARA SUPERVISIÓN DEL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2021-05- IBRD / 87400 Posterior Individual Limited 25,075.00 0.00 Cancelado 2020-04-20 PUESTA EN MARCHA Y IWRM at the National Level 25 30 15 10 CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-166002-CS-INDV / TÉCNICO 02 PARA SUPERVISIÓN DEL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2021-05- IBRD / 87400 Posterior Individual Limited 25,075.00 0.00 Cancelado 2020-04-20 PUESTA EN MARCHA Y IWRM at the National Level 25 30 15 10 CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-171096-CS-INDV / TECNICO EN AUTOCAD 01 Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 PARA ESTANDARIZACION E IWRM at the National Level 20 29 22 04 08 05 08 03 INTEGRACION DE PLANOS PE-ANA-171097-CS-INDV / TECNICO EN AUTOCAD 02 Component 1: Consolidating 2020-04- 2020-04- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 PARA ESTANDARIZACION E IWRM at the National Level 20 29 22 04 08 05 08 03 INTEGRACION DE PLANOS PE-ANA-171099-CS-INDV / TECNICO EN AUTOCAD 03 Component 1: Consolidating 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- IBRD / 87400 Posterior Individual Limited 4,030.00 3,648.11 Firmado 2020-04-27 PARA ESTANDARIZACION E IWRM at the National Level 20 29 22 04 08 05 08 03 INTEGRACION DE PLANOS PE-ANA-165886-CS-INDV / PROFESIONAL 01 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-05- 2020-06- 2020-07- 2022-11- IBRD / 87400 Posterior Individual Limited 51,940.00 0.00 Cancelado 2020-05-08 EN ESTRUCTURAS DE IWRM at the National Level 15 05 10 27 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165888-CS-INDV / PROFESIONAL 02 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-05- 2020-06- 2020-07- 2022-11- IBRD / 87400 Posterior Individual Limited 51,940.00 0.00 Cancelado 2020-05-08 EN ESTRUCTURAS DE IWRM at the National Level 15 05 10 27 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ Page 12 PE-ANA-171926-CS-INDV / PROFESIONAL 01 PARA Component 1: Consolidating 2020-04- 2020-05- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Posterior Individual Limited 8,400.00 7,671.60 Firmado 2020-05-03 IWRM at the National Level 14 13 22 16 02 20 02 18 INTEGRACIÓN DE EXPEDIENTES TÉCNICOS PE-ANA-171929-CS-INDV / PROFESIONAL 02 PARA Component 1: Consolidating 2020-04- 2020-05- 2020-04- 2020-05- 2020-06- 2020-05- 2020-06- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Posterior Individual Limited 8,400.00 7,671.60 Firmado 2020-05-03 IWRM at the National Level 14 08 22 11 02 14 02 12 INTEGRACIÓN DE EXPEDIENTES TÉCNICOS PE-ANA-182711-CS-INDV / PROFESIONAL SENIOR PARA Component 1: Consolidating 2020-06- 2020-07- 2020-06- 2020-07- 2020-07- 2020-07- 2020-07- 2020-11- ACTUALIZAR LA POLITICA Y IBRD / 87400 Posterior Individual Direct 21,000.00 19,411.82 Firmado 2020-06-30 IWRM at the National Level 30 02 30 07 02 13 02 10 ESTRATEGIA NACIONAL DE RECURSOS HÍDRICOS. PE-ANA-187092-CS-INDV / Component 2: Improving ESPECIALISTA SOCIAL 2020-09- 2020-09- 2020-09- 2020-09- 2020-10- 2020-10- 2020-10- 2022-12- IBRD / 87400 WRM in Selected Pilot River Posterior Individual Limited 73,500.00 7,416.42 Firmado 2020-09-21 AMBIENTAL CUENCA MAYO - 23 26 24 28 02 01 02 31 Basins PGIRH PE-ANA-190830-NC-RFQ / Component 1: Consolidating 2020-10- 2020-10- 2020-11- 2020-12- Estudio Geológico del IBRD / 87400 Posterior Individual Limited 35,000.00 0.00 Cancelado 2020-09-28 IWRM at the National Level 03 13 08 08 acuífero Caplina PE-ANA-190831-NC-RFQ / Estudio de prospección Component 1: Consolidating Ejecución 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Posterior Individual Limited 13,000.00 0.00 2020-09-28 geofísica reubicación IWRM at the National Level pendiente 03 13 08 08 piezómetros PE-ANA-190616-NC-RFQ / Estudio Geológico de los Component 1: Consolidating 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Posterior Individual Limited 35,000.00 0.00 Cancelado 2020-09-28 acuíferos de Ica, Villacurí y IWRM at the National Level 03 13 08 08 Lanchas PE-ANA-199722-CS-INDV / Profesional especialista para Component 1: Consolidating 2020-11- 2020-10- 2020-11- 2020-10- 2020-11- 2020-10- 2020-11- 2022-12- la instrumentación de las IBRD / 87400 Posterior Individual Limited 72,500.00 65,708.42 Firmado 2020-10-20 IWRM at the National Level 02 22 05 27 13 31 25 31 estructuras de Medición de agua en bloques de riego PE-ANA-199657-CS-INDV / Component 3: General 2020-08- 2020-10- 2020-10- 2020-10- 2020-11- 2020-10- 2020-11- 2022-12- Especialista en IBRD / 87400 Posterior Individual Direct 103,000.00 53,604.25 Firmado 2020-10-14 Project Adminstration 28 18 05 23 11 31 11 30 Administración y Finanzas del Proyecto PGIRH PE-ANA-202833-CS-INDV / TÉCNICO 01: Component 1: Consolidating 2021-01- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-02- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Posterior Individual Limited 20,600.00 15,062.30 Firmado 2020-11-20 IWRM at the National Level 15 23 15 25 20 01 01 31 CAPACITACIÓN EN SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-202851-CS-INDV / TÉCNICO 02: Component 1: Consolidating 2021-01- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-02- 2021-03- SENSIBILIZACIÓN Y IBRD / 87400 Posterior Individual Limited 20,600.00 15,058.18 Firmado 2020-11-20 IWRM at the National Level 12 23 15 25 20 01 02 31 CAPACITACIÓN EN SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-202855-CS-INDV / PROFESIONAL PARA ESTANDARIZACIÓN E Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- IBRD / 87400 Posterior Individual Limited 8,200.00 7,828.59 Firmado 2020-11-09 INTEGRACIÓN DE IWRM at the National Level 28 14 11 19 24 01 26 01 EXPEDIENTES TÉCNICOS, REGIÓN ICA PE-ANA-202860-CS-INDV / TÉCNICO EN AUTOCAD 01 Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- PARA ESTANDARIZACIÓN E IBRD / 87400 Posterior Individual Limited 3,900.00 3,704.16 Firmado 2020-11-09 IWRM at the National Level 28 14 11 19 23 01 26 01 INTEGRACIÓN DE PLANOS, REGIÓN ICA PE-ANA-202861-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS 01 Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- PARA ESTANDARIZACIÓN E IBRD / 87400 Posterior Individual Limited 3,900.00 3,704.16 Firmado 2020-11-09 IWRM at the National Level 28 14 11 19 23 01 26 01 INTEGRACIÓN DE EXPEDIENTES TÉCNICOS, REGIÓN ICA PE-ANA-202862-CS-INDV / PROFESIONAL PARA ESTANDARIZACIÓN E Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- INTEGRACIÓN DE IBRD / 87400 Posterior Individual Limited 13,600.00 13,054.83 Firmado 2020-11-09 IWRM at the National Level 28 14 11 19 23 01 26 30 EXPEDIENTES TÉCNICOS, REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202863-CS-INDV / TÉCNICO EN AUTOCAD 01 PARA ESTANDARIZACIÓN E Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- IBRD / 87400 Posterior Individual Limited 6,500.00 6,180.47 Firmado 2020-11-09 INTEGRACIÓN DE PLANOS, IWRM at the National Level 28 14 11 19 23 01 26 30 REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202864-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y PRESUPUESTOS 01 PARA ESTANDARIZACIÓN E Component 1: Consolidating 2020-10- 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-04- IBRD / 87400 Posterior Individual Limited 6,500.00 6,173.60 Firmado 2020-11-09 INTEGRACIÓN DE IWRM at the National Level 28 14 11 19 23 01 26 30 EXPEDIENTES TÉCNICOS, REGIONES PIURA, LAMBAYEQUE Y LA LIBERTAD PE-ANA-202869-CS-INDV / TÉCNICO 01 PARA SUPERVISIÓN DEL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2021-03- 2020-11- 2020-11- 2020-12- 2022-07- IBRD / 87400 Posterior Individual Limited 40,000.00 0.00 En ejecución 2020-11-20 PUESTA EN MARCHA Y IWRM at the National Level 03 22 25 01 24 CAPACITACIÓN EN INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-202870-CS-INDV / TÉCNICO 02 PARA SUPERVISIÓN DEL SUMINISTRO, INSTALACIÓN, Component 1: Consolidating 2021-03- 2020-11- 2020-11- 2020-12- 2022-07- IBRD / 87400 Posterior Individual Limited 40,000.00 0.00 En ejecución 2020-11-20 PUESTA EN MARCHA Y IWRM at the National Level 03 23 26 01 24 CAPACITACIÓN EN INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-202874-CS-INDV / SUPERVISIÓN PARA CULMINACIÓN DE ADECUACIÓN DE Component 1: Consolidating Ejecución 2020-11- 2020-11- 2020-12- 2021-02- IBRD / 87400 Posterior Individual Limited 9,300.00 0.00 2020-11-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level pendiente 22 25 01 14 DE AGUA EN SECTORES HIDRAULICOS DESDE CHICAMA HASTA SANTA PE-ANA-202875-CS-INDV / SERVICIO DE SUPERVISIÓN PARA CULMINACIÓN DE ADECUACIÓN DE Component 1: Consolidating 2020-11- 2020-11- 2020-12- 2021-02- IBRD / 87400 Posterior Individual Limited 9,300.00 0.00 En ejecución 2020-11-20 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 22 25 01 14 DE AGUA EN SECTORES HIDRAULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-202876-CS-INDV / PROFESIONAL 01 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Posterior Individual Limited 30,900.00 19,706.59 Firmado 2020-11-20 EN ESTRUCTURAS DE IWRM at the National Level 17 22 18 25 02 01 13 25 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202877-CS-INDV / PROFESIONAL 02 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-12- 2020-11- 2021-01- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Posterior Individual Limited 30,900.00 19,706.59 Firmado 2020-11-20 EN ESTRUCTURAS DE IWRM at the National Level 17 23 18 26 02 01 13 25 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202878-CS-INDV / BACHILLER 01 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Posterior Individual Limited 20,600.00 13,137.73 Firmado 2020-11-20 EN ESTRUCTURAS DE IWRM at the National Level 17 22 18 25 05 01 13 25 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-202879-CS-INDV / BACHILLER 02 PARA TRABAJOS DE HIDROMETRÍA Component 1: Consolidating 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-01- 2022-05- IBRD / 87400 Posterior Individual Limited 20,600.00 12,553.94 Firmado 2020-11-20 EN ESTRUCTURAS DE IWRM at the National Level 17 22 18 25 05 01 13 25 MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-204399-CS-CDS / Component 3: General Selección directa 2020-07- 2020-11- 2020-11- 2020-11- 2020-11- 2022-12- IBRD / 87400 Posterior Direct 156,000.00 78,870.15 Firmado 2020-11-16 DIRECTOR EJECUTIVO Project Adminstration de consultores 10 22 10 25 11 30 PE-ANA-202802-CS-INDV / Component 1: Consolidating Ejecución 2020-12- 2021-01- 2021-02- 2022-08- Responsable Jefe Supervisión IBRD / 87400 Posterior Individual Limited 81,274.00 0.00 2020-12-22 IWRM at the National Level pendiente 27 17 21 15 EHA-SMA PE-ANA-202817-CS-INDV / Component 1: Consolidating Ejecución 2020-12- 2021-01- 2021-02- 2022-08- Coordinador Administrativo IBRD / 87400 Posterior Individual Limited 56,343.00 0.00 2020-12-22 IWRM at the National Level pendiente 27 17 21 15 EHA - SMA PE-ANA-202807-CS-INDV / Component 1: Consolidating Ejecución 2020-12- 2021-01- 2021-02- 2022-08- Asistente Supervisión EHA- IBRD / 87400 Posterior Individual Limited 71,302.00 0.00 2020-12-22 IWRM at the National Level pendiente 27 17 21 15 SMA PE-ANA-202808-CS-INDV / Component 1: Consolidating 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2021-05- 2022-08- Supervisor 1 - Obras Civiles IBRD / 87400 Posterior Individual Limited 66,316.00 64,002.99 Firmado 2020-12-22 IWRM at the National Level 11 27 17 17 28 21 07 15 EHA - SMA PE-ANA-202814-CS-INDV / Component 1: Consolidating 2021-05- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 En ejecución 2020-12-22 Supervisor 2 - Montaje EHA IWRM at the National Level 07 27 17 21 15 PE-ANA-202810-CS-INDV / Component 1: Consolidating 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- 2022-08- Supervisor 2 - Obras Civiles IBRD / 87400 Posterior Individual Limited 66,316.00 43,029.89 Firmado 2020-12-22 IWRM at the National Level 11 27 17 17 30 21 30 15 EHA -SMA PE-ANA-202811-CS-INDV / Component 1: Consolidating 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2020-12- 2022-08- Supervisor 3 - Obras Civiles IBRD / 87400 Posterior Individual Limited 66,316.00 43,029.89 Firmado 2020-12-22 IWRM at the National Level 11 27 17 17 30 21 30 15 EHA - SMA PE-ANA-202813-CS-INDV / Component 1: Consolidating 2021-05- 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 En ejecución 2020-12-22 Supervisor 1 - Montaje EHA IWRM at the National Level 07 27 17 21 15 PE-ANA-202815-CS-INDV / Component 1: Consolidating Ejecución 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 2020-12-22 Supervisor 3 - Montaje SMA IWRM at the National Level pendiente 27 17 21 15 PE-ANA-202816-CS-INDV / Component 1: Consolidating Ejecución 2020-12- 2021-01- 2021-02- 2022-08- IBRD / 87400 Posterior Individual Limited 66,316.00 0.00 2020-12-22 Supervisor 4 - Montaje SMA IWRM at the National Level pendiente 27 17 21 15 PE-ANA-211979-CS-INDV / ESPECIALISTA DE CALIDAD DE AGUA PARA EL MONITOREO Component 1: Consolidating Ejecución 2021-01- 2021-01- 2021-02- 2022-02- DE LA INSTALACION DE IBRD / 87400 Posterior Individual Limited 27,000.00 0.00 2021-01-18 IWRM at the National Level pendiente 20 25 01 01 SENSORES DE CALIDAD DE AGUA SUPERFICIAL EN EL AMBITO DEL PGIRH Page 13 PE-ANA-212242-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUA PARA LA SUPERVISIÓN DE LA ELABORACIÓN DE LOS Component 1: Consolidating Ejecución 2021-01- 2021-01- 2021-01- 2022-01- IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 2021-01-15 DIAGNÓSTICOS DE LA IWRM at the National Level pendiente 17 22 29 29 CALIDAD DE LOS RECURSOS HÍDRICOS SUPERFICIALES DEL ÁMBITO DEL PGIRH PE-ANA-212246-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUAPARA LA SUPERVISIÓN DEL REGISTRO DE DATOS DE LAS ACTIVIDADES DE Component 1: Consolidating Ejecución 2021-01- 2021-01- 2021-01- 2022-01- VIGILANCIA DE LA CALIDAD IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 2021-01-15 IWRM at the National Level pendiente 17 22 29 29 DE LOS RECURSOS HÍDRICOS SUPERFICIALES DEL PERIODO 2010 A 2020 EN LA PLATAFORMA DEL SNIRH/DCERH EN 25 U.H. PE-ANA-212247-CS-INDV / ESPECIALISTA EN CALIDAD DE AGUA PARA LA SUPEVISION DEL REGISTRO DE DATOS DE LAS ACTIVIDADES DE Component 1: Consolidating Ejecución 2021-01- 2021-01- 2021-01- 2022-01- VIGILANCIA DE LA CALIDAD IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 2021-01-15 IWRM at the National Level pendiente 17 22 29 29 DE LOS RECURSOS HIDRICOS SUPERFICIALES DEL PERIODO 2010 A 2020 EM LA PLATAFORMA DEL SNIRH/DCERH EN 17 U.H PE-ANA-212248-CS-INDV / ESPECIALISTA PARA EL GEOPROCESAMIENTO DE INFORMACION PARA LA SUPERVISION Y ELABORACION DE DIAGNOSTICOS DE LA Component 1: Consolidating Ejecución 2021-01- 2021-01- 2021-01- 2022-01- IBRD / 87400 Posterior Individual Limited 27,000.00 0.00 2021-01-15 CALIDAD DE LOS RECURSOS IWRM at the National Level pendiente 17 22 29 29 HIDRICOS SUPERFICIALES Y REGISTRO DE INFORMACION DE LA PLATAFORMA DEL SNIRH/DCERH DE LA ANA DEL AMBITO NACIONAL PE-ANA-212257-CS-INDV / Component 3: General 2021-02- 2021-01- 2021-03- 2021-01- 2021-03- 2021-02- 2021-03- 2022-12- ASISTENTE EN IBRD / 87400 Posterior Individual Limited 68,000.00 26,623.28 Firmado 2021-01-18 Project Adminstration 05 25 16 28 30 02 31 31 ADQUISICIONES 2 PE-ANA-212262-CS-INDV / Component 3: General Ejecución 2021-02- 2021-02- 2021-02- 2022-12- IBRD / 87400 Posterior Individual Limited 76,000.00 0.00 2021-02-13 ASESOR LEGAL - PGIRH Project Adminstration pendiente 20 23 28 31 PE-ANA-212264-CS-INDV / Component 3: General Ejecución 2021-02- 2021-02- 2021-03- 2021-05- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 76,500.00 0.00 2021-02-15 Project Adminstration pendiente 22 27 03 08 CONTABILIDAD SCI 039 ANA PGIRH / Component 3: General 2019-02- 2019-02- 2019-02- 2020-02- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado 2019-02-08 Project Adminstration 15 20 28 28 ADQUISICIONES 2 SCI 068 2018 ANA PGIRH BM Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 Cancelado 2019-04-05 / ASESOR LEGAL Project Adminstration 15 20 30 29 PE-ANA-214176-CS-INDV / ESPECIALISTA EN Component 3: General 2021-02- 2021-02- 2021-02- 2021-02- 2021-02- 2021-03- 2021-03- 2022-12- IBRD / 87400 Posterior Individual Limited 92,000.00 40,594.30 Firmado 2021-02-15 PLANIFICACION, Project Adminstration 18 22 22 27 26 03 05 30 PRESUPUESTO Y EVALUACION SCI 032 ANA PGIRH / ESPECIALISTA EN Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 48,000.00 0.00 Cancelado 2019-04-05 PLANIFICACION, Project Adminstration 15 20 30 29 PRESUPUESTO Y EVALUACIÓN PE-ANA-122163-CS-INDV / Component 3: General Ejecución 2021-02- 2021-02- 2021-03- 2022-12- IBRD / 87400 Posterior Individual Limited 58,000.00 0.00 2021-02-15 ASISTENTE DE CONTABILIDAD Project Adminstration pendiente 22 27 03 30 SCI 041 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 194,076.00 0.00 Cancelado 2018-05-28 Project Adminstration 04 11 13 19 CONTABILIDAD PE-ANA-122162-CS-INDV / Component 3: General 2021-02- 2021-02- 2021-03- 2021-02- 2021-03- 2021-03- 2021-03- 2022-12- ASISTENTE DE MONITOREO Y IBRD / 87400 Posterior Individual Limited 58,000.00 22,992.83 Firmado 2021-02-15 Project Adminstration 26 22 11 27 26 03 31 30 EVALUACIÓN PE-ANA-216395-CS-INDV / Component 3: General 2021-02- 2021-02- 2021-02- 2021-02- 2022-01- Especialista Financiero del IBRD / 87400 Posterior Individual Limited 33,600.00 0.00 Bajo Revision 2021-02-08 Project Adminstration 04 13 18 23 24 Proyecto PE-ANA-221587-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Consolidating 2021-05- 2021-03- 2021-03- 2021-04- 2021-07- IBRD / 87400 Posterior Individual Limited 8,000.00 0.00 En ejecución 2021-03-15 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 18 20 25 09 10 DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE TUMBES HASTA ALTO PIURA PE-ANA-221592-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Consolidating 2021-03- 2021-03- 2021-04- 2021-03- 2021-04- 2021-04- 2021-05- 2021-07- IBRD / 87400 Posterior Individual Limited 8,750.00 10,020.77 Firmado 2021-03-15 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level 11 20 12 25 27 09 11 18 DE AGUA EN LOS SECTORES HIDRÁULICOS DESDE OLMOS HASTA JEQUETEPEQUE PE-ANA-234084-CS-INDV / PROFESIONAL 01 PARA EL SEGUIMIENTO Y CONTROL DE Component 1: Consolidating 2021-06- 2021-06- 2021-06- 2022-06- IBRD / 87400 Posterior Individual Limited 36,000.00 0.00 Bajo Revision 2021-05-28 LA EJECUCION DE OBRAS DE IWRM at the National Level 02 03 10 05 ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234087-CS-INDV / PROFESIONAL 02 PARA EL SEGUIMIENTO Y CONTROL DE Component 1: Consolidating 2021-06- 2021-06- 2021-06- 2021-06- 2022-06- IBRD / 87400 Posterior Individual Limited 36,000.00 0.00 En ejecución 2021-05-28 LA EJECUCION DE OBRAS DE IWRM at the National Level 04 02 03 09 04 ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-234089-CS-INDV / TECNICO EN AUTOCAD, METRADOS, COSTOS Y PRESUPUESTO PARA EL Component 1: Consolidating 2021-06- 2021-06- 2021-06- 2021-06- 2022-01- IBRD / 87400 Posterior Individual Limited 15,000.00 0.00 En ejecución 2021-05-28 SEGUIMIENTO Y CONTROL DE IWRM at the National Level 04 02 03 10 06 LA EJECUCION DE OBRAS DE ESTRUCTURAS DE MEDICION DE AGUA PE-ANA-165885-CS-INDV / DESARROLLO E IMPLEMENTACIÓN DE CURSO Component 1: Consolidating Ejecución 2021-10- 2021-10- 2021-12- 2022-03- IBRD / 87400 Posterior Individual Limited 9,851.00 0.00 2021-10-01 VIRTUAL: MEDICIÓN DEL IWRM at the National Level pendiente 08 29 03 05 AGUA EN SISTEMAS HIDRÁULICOS COMUNES PE-ANA-235103-CS-INDV / PROFESIONAL PARA LA ELABORACION DE 20 Component 1: Consolidating Ejecución 2021-07- 2021-07- 2021-07- 2021-09- IBRD / 87400 Posterior Individual Limited 22,000.00 0.00 2021-07-01 EXPEDIENTES TECNICOS EN IWRM at the National Level pendiente 06 16 28 26 LOS SECTORES DE MEDIO Y BAJO PIURA Y SECHURA PE-ANA-235582-CS-INDV / TECNICO 01 PAAR SUPERVISION DEL SUMINISTRO, INSTALACION , Component 1: Consolidating 2021-07- 2021-07- 2021-07- 2022-05- IBRD / 87400 Posterior Individual Limited 17,000.00 0.00 Cancelado 2021-07-01 PUESTA EN MARCHA Y IWRM at the National Level 06 13 26 22 CAPACITACION DE INSTRUMENTACION PARA LA MEDICION PE-ANA-235586-CS-INDV / TECNICO 02 PARA SUPERVISION DEL SUMINISTRO, INSTALACION, Component 1: Consolidating 2021-07- 2021-07- 2021-07- 2022-05- IBRD / 87400 Posterior Individual Limited 17,000.00 0.00 Cancelado 2021-07-01 PUESTA EN MARCHA Y IWRM at the National Level 06 13 26 22 CAPACITACION DE INSTRUMENTACION PARA LA MEDICION Page 14