Solar Resource Mapping in Pakistan MAINTENANCE VISIT REPOR.7 %4"0'. İ August 2016 This report was prepared by CSP Services, under contract to The World Bank. It is one of several outputs from the solar Resource Mapping and Geospatial Planning Pakistan [Project ID: P146140]. This activity is funded and supported by the Energy Sector Management Assistance Program (ESMAP), a multi-donor trust fund administered by The World Bank, under a global initiative on Renewable Energy Resource Mapping. Further details on the initiative can be obtained from the ESMAP website. This document is an interim output from the above-mentioned project. Users are strongly advised to exercise caution when utilizing the information and data contained, as this has not been subject to full peer review. The final, validated, peer reviewed output from this project will be the Pakistan Solar Atlas, which will be published once the project is completed. Copyright © 2016 International Bank for Reconstruction and Development / THE WORLD BANK Washington DC 20433 Telephone: +1-202-473-1000 Internet: www.worldbank.org This work is a product of the consultants listed, and not of World Bank staff. The findings, interpretations, and conclusions expressed in this work do not necessarily reflect the views of The World Bank, its Board of Executive Directors, or the governments they represent. The World Bank does not guarantee the accuracy of the data included in this work and accept no responsibility for any consequence of their use. The boundaries, colors, denominations, and other information shown on any map in this work do not imply any judgment on the part of The World Bank concerning the legal status of any territory or the endorsement or acceptance of such boundaries. The material in this work is subject to copyright. Because The World Bank encourages dissemination of its knowledge, this work may be reproduced, in whole or in part, for non-commercial purposes as long as full attribution to this work is given. Any queries on rights and licenses, including subsidiary rights, should be addressed to World Bank Publications, The World Bank Group, 1818 H Street NW, Washington, DC 20433, USA; fax: +1-202-522-2625; e-mail: pubrights@worldbank.org. Furthermore, the ESMAP Program Manager would appreciate receiving a copy of the publication that uses this publication for its source sent in care of the address above, or to esmap@worldbank.org. CSP Services GmbH, Köln, Germany CSPS Technical Documentation ESMAP Tier2 Meteorological Station Maintenance Report: University of Engineering and Technology, Peshawar, Pakistan Responsible Authors Birk Kraas Muhammad Umer Kamal Roman Affolter Author Contact Information: CSP Services GmbH Friedrich-Ebert-Ufer 30 51143 Köln/Cologne, Germany E-Mail: b.kraas@cspservices.de 02 August 2016 CSP Services GmbH, Köln, Germany CSPS Technical Documentation CSP Services GmbH Office Cologne: Birk Kraas Friedrich-Ebert-Ufer 30, 51143 Cologne, Germany Phone: +49 2203 959003 0 b.kraas@cspservices.de Office Almería: Roman Affolter Paseo de Almería 73 – 2°, 04001 Almería, Spain Phone: +34 950 27 89 92 r.affolter@cspservices.de PITCO: Muhammad Umer Kamal 2nd Floor, Al – Maalik, 19 – Davis Road, Lahore, PAKISTAN umer.kamal@pitcopk.com CSP Services is a Spin-Off company of the German Aerospace Center (DLR), Institute of Solar Research, and makes use of licensed technology and know-how of DLR. The contents of this report are strictly confidential. They are only for the use of our client. The authors have written this report at their best knowledge and it has been rechecked within our quality control system. However, our liability, except in cases of intent, is excluded or limited to the contract conditions. CSP Services GmbH Geschäftsführer Sitz der Gesellschaft: Köln Friedrich-Ebert-Ufer 30 (Managing Directors): Amtsgericht Köln D-51143 Köln · Germany Dr. Klaus Pottler HRB 61644 T: +49 2203 959 0030 Dr.-Ing. Steffen Ulmer USt.-Id (VAT) DE814904840 F: +49 2203 296 9560 www.cspservices.de CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Summary Site Site: University of Enigneering and Technology, Peshawar Coordinates: 34.002°N, 71.485°E Station Type: ESMAP Tier 2 Station Date of installation: 2014-04-10 Date of maintenance visit: 2016-05-19 Serial Numbers Station SN#: CSPS.MT.14.217 Control Box SN#: CSPS.CA.14.209.0003 RSI SN# – Drive, PU: DR.14.0001.0014, MS.14.001.0014 GHI CMP SN#: 140570 Inspection visit staff Inspection performed by (Date, Names and Signatures) Date: 02 August 2016 Muhammad Umer Kamal, PITCO The CSP Services (CSPS) ESMAP Project Tier1 meteorological station CSPS.MT.14.217, operational since Apr. 10th 2015, was inspected and tested for its correct operation by PITCO staff on July 19, 2016. The station is fully functional. The irradiation sensors showed an increase of 3.5% in their irradiation signal upon cleaning of the sensor head. It is recommended to clean the sensors on a weekly basis in order to reduce the influence of sensor soiling on the irradiance data. ESMAP Report 3 Pk-Pesh-160519_Tier2-MaintenanceReport CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Completed Tasks  Foundations checked for integrity.  All parts and sensors of the station examined for damage, dust or condensed humidity, current status recorded and equipment cleaned where necessary.  Vertical alignment of wind mast checked, wind mast anchorage and wind mast guying ropes checked for stability, secure fixation to the ground and tightness.  Rotating Shadowband Pyranometer (RSI) and CMP10 pyranometer alignment ad- justed and fine-tuned, no perceptible influence on the irradiance data stated.  Solar irradiation sensors checked for proper operation and functionality; sensors cleaned, impact of cleaning on data recorded.  Batteries Box and solar panel inspected and correct operation of 12 VDC circuit verified.  Mounting structure stability checked.  Datalogger program correct operation verified.  Measured quantities checked for proper operation and correct values.  Cleaning inspection button checked for proper functioning.  Fuses, electrical components and wiring checked. Pending Tasks / Recommended Tasks for next Maintenance Visit None Maintenance Checklist Checked/ Component Work item approved Comments yes no Foundations and anchors intact X Founda- Fence and door intact X No fence, controlled roof area tions, fence Lock on door intact and usable X No fence, controlled roof area Support Firmly installed X structure Grounding cable connected X with control box All bolts tightened X Visual examination X Fuses ok X PV Power cable connected X Wiring, ca- bles Electrical connection X PV Panel(s) visual examination X Cleaned Supply Voltage X Power Sup- ply Batteries ok and charging X All sensors connected X All cables orderly fixed X ESMAP Report 4 Pk-Pesh-160519_Tier2-MaintenanceReport CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Checked/ Component Work item approved Comments yes no Barometric Sensor Serial No. X Model: Setra 278 SN#:5949006 Pressure Sensor Visual examination, operability X Irradiation shield visual examination X Sensor probe and chip examination X Tamb / RH Filter cap examination X Cleaned Sensor Serial No. X Model: CS215 SN#: E12259 Visual examination, operability X Dirty on diffuser disc, cleaned Drive Unit X SN: DR.14.001.0014 PU Unit X SN: MS.14.001.0014 RSI Diffuser disc / LI-COR sensor(s) X Shadow band X Horizontal leveling X Slightly adjusted Thermopile Irradiation Pyranometer GHI X SN# : 140570, cleaned Sensor Alignment Horizontal leveling X Slightly adjusted Visual examination, alignment X Tightened Wind tower, Wind direction sensor serial No. X Model: NRG#200 SN#: N/A wind speed Wind speed sensor serial No. X Model: NRG#40C SN#: 1795-00229367 and direc- tion sensors North Orientation of WD sensor X Operability of sensors X SIM card X Provider / number: Telenor APN: internet Modem APN, username, password of SIM X Username: Telenor Password: Telenor LED blinking code X Operation system installed X Version: Std.27 Datalogger configuration saved X File name: Pk-Pesh_2015-04-10.xml IP visible in logger configuration X IP: dynamic Correct sensor constants in program X Correct coordinates in program X Datalogger Program name: Pk-Pesh-2015-04-03.CR1 Datalogger program installed X Subroutines: ESMAP-Pakistan-MDI-Su- broutines-2014-08-19_str_Enc.CR1 Program set to “Run always” X Local standard time, no daylight saving Datalogger clock correct X time: UTC+5 Logger time shift detected: 0 s ESMAP Report 5 Pk-Pesh-160519_Tier2-MaintenanceReport CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Photographic documentation Figure 1: MDI stand with solar panel and sensor Figure 2: MDI Stand with control box (front mounts (back side, from South) side, from North) Figure 3: CMP10 close-up Figure 4: CMP10 level ESMAP Report 6 Pk-Pesh-160519_Tier2-MaintenanceReport CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Figure 5: Temperature sensor in protection cap Figure 6: Control box interior Figure 7: RSI Pyranometer unit Figure 8: RSI Pyranometer unit with water level ESMAP Report 7 Pk-Pesh-160519_Tier2-MaintenanceReport CSPS CSPS Tier2 Maintenance Report Concentrating Solar Power Services Figure 9: Wind tower foot Figure 10: Station overview with wind tower (from South) ESMAP Report 8 Pk-Pesh-160519_Tier2-MaintenanceReport