PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: CASA 1000 Community Support Project Total Finance ($): $10.0 million (IDA) $1.0 million (CASA1000-MDTF) Project Number: P163592 Project Implementation agency ARIS Date of the Procurement Plan February 1, 2018 Period covered by this Procurement February 1, 2018 - 2023 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 N 182, December 10, 2016 N 195, February 14, 2017 N 25, May 30, 2017 N 93, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. • The Bidding process shall not be cancelled sole on the reason that minimum bid price is larger than the amount allocated by procuring entity for this procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of ready available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable Other Relevant Procurement Information. The CDD approach and procurement by the communities will follow Procurement Regulations paragraph 6.52 and Annex XII - Selection Methods, paragraphs 6.9 and 6.10. The procurement arrangements at the community level (including procurement responsibilities, procedures, disclosure requirements and sample documentation) and the oversight mechanisms described in Subcomponent 2B will be detailed in the POM. Community procurement will follow the Community Procurement Handbook and the Guidance Note for Design and Management of Procurement Responsibilities in Community Driven Development Projects (March 15, 2012). PROCUREMENT Central Asia : CASA1000 Community Support Project - Kyrgyz Republic PLAN General Information Country: Central Asia Bank’s Approval Date of the Original Procurement Plan: 2020-04-09 2021-07-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163592 GPN Date: 2020-09-10 Project Name: CASA1000 Community Support Project - Kyrgyz Republic Loan / Credit No: IDA / D2940, IDA / 62190, IDA / 67560 C Executing Agency(ies): ommunity Development and Investment Agency WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CASA-CSP-GOODS-20- 1 / procurement of personal Project management, and Request for Single Stage - One IDA / 62190 Post Limited 99,800.00 0.00 Canceled 2020-04-22 2020-05-22 2020-06-05 protective equipment for the monitoring and evaluation Quotations Envelope south regions ARIS-CASA-CSP-GOODS-20- Support for community-led 2/1 / Procurement of IDA / 62190 investments in social and Post Direct Selection Direct 4,100.00 4,000.80 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-10 2020-06-01 2020-06-30 2020-06-02 personal protective equipment economic infrastructure for the south regions ARIS-CASA-CSP-GOODS-20- Support for community-led 2/2 / Supply of Personal IDA / 62190 investments in social and Post Direct Selection Direct 18,065.00 17,627.20 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-02 2020-06-28 2020-06-21 Protective Equipment economic infrastructure ARIS-CASA-CSP-GOODS-20- Support for community-led 2/3 / Supply of Personal IDA / 62190 investments in social and Post Direct Selection Direct 11,735.00 11,449.44 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-02 2020-06-28 2020-07-02 Protective Equipment for the economic infrastructure South Regions ARIS-CASA-CSP-GOODS-20- Support for community-led 2/4 / Procurement of IDA / 62190 investments in social and Post Direct Selection Direct 16,000.00 15,612.88 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-02 2020-06-28 2020-07-21 personal protective equipment economic infrastructure for the south regions ARIS-CASA-CSP-GOODS-20- Support for community-led 2/5 / Procurement of IDA / 62190 investments in social and Post Direct Selection Direct 40,900.00 39,910.41 Completed 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-08 2020-06-02 2020-06-28 2020-06-20 personal protective equipment economic infrastructure for the south regions ARIS-CASA-CSP-GOODS-20- Support for community-led 2/6 / Procurement of IDA / 62190 investments in social and Post Direct Selection Direct 9,000.00 8,782.24 Terminated 2020-06-05 2020-06-01 2020-06-05 2020-06-01 2020-06-07 2020-06-02 2020-06-27 personal protective equipment economic infrastructure for the south regions ARIS-CASA-CSP-GOODS-RFB- Support for community-led 2020-01 / Procurement of Single Stage - One IDA / D2940 investments in social and Post Request for Bids Open - International 300,000.00 0.00 Canceled 2020-11-22 2020-11-24 2020-11-27 2020-12-17 2021-01-08 2021-01-12 2021-03-09 2021-02-05 2021-04-13 2021-07-12 special machinery for electric Envelope economic infrastructure companies ARIS-CASA-CSP-GOODS-RFB- 2020-01-RETENDER / Support for community-led Single Stage - One Procurement of special IDA / D2940 investments in social and Post Request for Bids Open - International 300,000.00 0.00 Canceled 2021-02-22 2021-02-19 2021-02-27 2021-02-18 2021-04-12 2021-04-02 2021-06-11 2021-04-14 2021-07-16 2021-10-14 Envelope machinery for energy economic infrastructure companies ARIS-CASA-CSP-GOODS-RFB- 20-01-RETENDER-2 / Support for community-led Under Single Stage - One Procurement of special IDA / D2940 investments in social and Post Request for Bids Open - International 300,000.00 0.00 Implementati 2021-05-15 2021-05-02 2021-05-22 2021-05-06 2021-07-03 2021-06-18 2021-08-02 2021-08-16 2021-11-14 Envelope machinery for energy economic infrastructure on companies ARIS-CSP-GOODS-RFB-2021- 02 / Electric equipment for Support for community-led Under Single Stage - One energy companies to conduct IDA / D2940 investments in social and Post Request for Bids Open - International 1,560,000.00 0.00 Implementati 2021-05-23 2021-05-14 2021-05-30 2021-05-17 2021-07-11 2021-06-25 2021-08-10 2021-07-15 2021-09-16 2021-12-15 Envelope the repair of electric economic infrastructure on distribution networks ARIS-CSP-GOODS-RFB-2021- 03 / Electric equipment for Support for community-led Under Single Stage - One energy companies to conduct IDA / D2940 investments in social and Post Request for Bids Open - International 300,000.00 0.00 Implementati 2021-06-10 2021-06-11 2021-06-15 2021-06-11 2021-07-27 2021-07-23 2021-08-26 2021-10-02 2021-12-31 Envelope the repair of electric economic infrastructure on distribution networks NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ARIS-CSP-CQ-20-2 / Development and Support for community Consultant implementation of mobilization, youth IDA / D2940 Post Qualification Open - National 52,428.00 47,473.65 Signed 2020-05-21 2020-05-29 2020-05-22 2020-06-22 2020-06-19 2020-08-05 2020-06-26 2020-08-25 2020-07-10 2020-09-08 2021-04-06 information campaign of the engagement and Selection Communities Support Project communications CASA1000 Page 1 Consultant IDA-ARIS-CSP-AFCSP-CQ-21- Project management, and IDA / 62190 Post Qualification Open - National 100,000.00 71,654.94 Signed 2021-03-12 2021-03-10 2021-03-27 2021-03-10 2021-04-26 2021-04-06 2021-05-11 2021-04-23 2021-05-25 2021-05-11 2022-02-19 4 / Baseline survey monitoring and evaluation Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-CASA-IC-CDSO-2020-1 Support for community / Community Development Individual mobilization, youth and Support Officer for IDA / D2940 Post Consultant Limited 23,077.00 6,950.32 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 engagement and Suuzak rayon Djalal-Abad Selection communications oblast (1). IDA-CASA-IC-CDSO-2020-2 Support for community / Community Development Individual mobilization, youth and Support Officer for IDA / D2940 Post Consultant Limited 23,077.00 7,089.01 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 engagement and Suuzak rayon Djalal-Abad Selection communications oblast (2). IDA-CASA-IC-CDSO-2020-3 Support for community / Community Development Individual mobilization, youth and Support Officer for IDA / D2940 Post Consultant Limited 23,077.00 8,823.99 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-06 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 engagement and Suuzak rayon Djalal-Abad Selection communications oblast (3). IDA-CASA-IC-CDSO-2020-4 Support for community Individual / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 8,490.69 Completed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 2021-06-23 and Support Officer for Ozgon engagement and Selection rayon Osh oblast (1). communications IDA-CASA-IC-CDSO-2020-5 Support for community Individual / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 8,539.34 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-05 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for Ozgon engagement and Selection rayon Osh oblast (2). communications IDA-CASA-IC-CDSO-2020-6 Support for community Individual / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 7,638.05 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-31 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for Kara- engagement and Selection Suu rayon Osh oblast. communications IDA-CASA-IC-CDSO-2020-7 Support for community Individual / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 8,679.75 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for engagement and Selection Nookat rayon Osh oblast (1). communications IDA-CASA-IC-CDSO-2020-8 Support for community Individual / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 7,901.54 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-04 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for engagement and Selection Nookat rayon Osh oblast (2). communications IDA-CASA-IC-CDSO-2020-9 Support for community / Community Development Individual mobilization, youth and Support Officer for IDA / D2940 Post Consultant Limited 23,077.00 7,628.07 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 engagement and Kadamjay rayon Batken oblast Selection communications (1). IDA-CASA-IC-CDSO-2020- Support for community 10 / Community Development Individual mobilization, youth and Support Officer for IDA / D2940 Post Consultant Limited 23,077.00 7,979.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-07-30 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 engagement and Kadamjay rayon Batken oblast Selection communications (2). IDA-CASA-IC-CDSO-2020- Support for community Individual 11 / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 7,933.73 Completed 2020-03-18 2020-02-28 2020-03-23 2020-07-29 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 2021-05-24 and Support Officer for Batken engagement and Selection rayon Batken oblast. communications IDA-CASA-IC-CDSO-2020- Support for community Individual 12 / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 8,010.45 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for Leylek engagement and Selection rayon Batken oblast (1). communications IDA-CASA-IC-CDSO-2020- Support for community Individual 13 / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 23,077.00 7,462.43 Signed 2020-03-18 2020-02-28 2020-03-23 2020-08-03 2020-04-13 2020-08-10 2020-05-18 2020-08-10 2023-08-31 and Support Officer for Leylek engagement and Selection rayon Batken oblast (2). communications IDA-CASA-IC-CDSO-2020- Support for community Individual 14 / Community Development mobilization, youth IDA / D2940 Post Consultant Limited 21,428.00 7,301.51 Completed 2020-06-24 2020-02-28 2020-06-29 2020-08-06 2020-07-20 2020-08-10 2020-08-24 2020-08-10 2021-02-20 2021-06-30 and Support Officer for Suzak engagement and Selection rayon Dzhalal-Abad oblast. communications IDA-CASA-IC-2020-15 / Consultant to design the Updated Project Operational Manual, training modules, Support for community Individual informational materials on mobilization, youth IDA / 62190 Post Consultant Limited 11,000.00 9,855.86 Completed 2020-08-26 2020-08-27 2020-08-31 2020-09-02 2020-09-21 2020-09-03 2020-10-26 2020-09-03 2021-04-24 2021-04-05 scopes, tasks and CSP engagement and Selection implementation mechanisms communications to account for the CSP additional financing in the context of COVID-19 IDA/CASA-1000/CSP/AF/IC- 2021-2 / Community and Support for community Individual Technology Expert for Kara- mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,140.85 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 Suu rayon. engagement and Selection Kyzyl-Suu, Kashkar-Kyshtak & communications Savay AAs IDA/CASA-1000/CSP/AF/IC- Support for community 2021-3 / Community and Individual mobilization, youth Technology Expert for Kara- IDA / 67560 Post Consultant Open 8,000.00 3,404.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 engagement and Suu rayon. Selection communications Papan & Mady AAs Page 2 IDA/CASA-1000/CSP/AF/IC- 2021-4 / Community and Support for community Individual Technology Expert for Ozgon mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,490.41 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Kyzyl-Too, Zerger & Kara- communications Tash AAs. IDA/CASA-1000/CSP/AF/IC- 2021-5 / Community and Support for community Individual Technology Expert for Ozgon mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,429.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Altyn-Bulak, Salam-Alik & communications Kolduk AAs. IDA/CASA-1000/CSP/AF/IC- 2021-6 / Community and Support for community Individual Technology Expert for Ozgon mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,513.33 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Iyri-Suu, Changet & Jylaldy communications AAs. IDA/CASA-1000/CSP/AF/IC- 2021-7 / Community and Support for community Individual Technology Expert for Nookat mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,618.25 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Isanov, Kok-Bel and Kenesh communications AAs. IDA/CASA-1000/CSP/AF/IC- 2021-8 / Community and Support for community Individual Technology Expert for Nookat mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,371.30 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Kara-Tash, T. Zulpuev & communications Kyrgyz-Ata AAs. IDA/CASA-1000/CSP/AF/IC- 2021-9 / Community and Support for community Individual Technology Expert for Nookat mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,542.75 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 rayon. engagement and Selection Bel, Jany-Nookat & Nayman communications AAs. IDA/CASA-1000/CSP/AF/IC- 2021-10 / Community and Support for community Individual Technology Expert for Bazar- mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 3,762.39 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 Korgon rayon. engagement and Implementation Selection Kyzyl-Unkur, Arstanbap and communications Talduu-Bulak AAs. IDA/CASA-1000/CSP/AF/IC- 2021-11 / Community and Support for community Individual Technology Expert for Bazar- mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 3,765.62 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 Korgon rayon. engagement and Implementation Selection Kenesh, Seidykum & Beshik- communications Jon AAs. IDA/CASA-1000/CSP/AF/IC- 2021-12 / Community and Support for community Individual Technology Expert for Bazar- mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 3,832.73 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 Korgon/Suzak rayon. engagement and Implementation Selection Akman, Kara-Darya & Saipidin- communications Atabek AAs. IDA/CASA-1000/CSP/AF/IC- 2021-13 / Community and Support for community Individual Technology Expert for Suzak mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 3,856.98 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 rayon. engagement and Implementation Selection Kegart, Kara-Alma & communications Kurmanbek AAs. IDA/CASA-1000/CSP/AF/IC- 2021-14 / Community and Support for community Individual Technology Expert for Nooken mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 3,727.63 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 rayon. engagement and Implementation Selection Burgondu, Sakaldy, Dostuk & communications Mombekov AAs. IDA/CASA-1000/CSP/AF/IC- 2021-15 / Community and Support for community Individual Technology Expert for Nooken mobilization, youth Under IDA / 67560 Post Consultant Open 8,000.00 4,141.06 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-12-31 rayon. engagement and Implementation Selection Nooken, Shaydan, Masy & Aral communications AAs. IDA/CASA-1000/CSP/AF/IC- 2021-16 / Community and Support for community Individual Technology Expert for mobilization, youth IDA / 67560 Post Consultant Open 8,000.00 3,641.51 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 Kadamjay rayon. engagement and Selection Birlik, Chauvay & Orozbekov communications AAs. IDA/CASA-1000/CSP/AF/IC- Support for community 2021-17 / Community and Individual mobilization, youth Technology Expert for Leilek IDA / 67560 Post Consultant Open 8,000.00 3,787.57 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 engagement and rayon. Selection communications Margun & Beshkent AAs. IDA/CASA-1000/CSP/AF/IC- Support for community 2021-18 / Community and Individual mobilization, youth Technology Expert for Leilek IDA / 67560 Post Consultant Open 8,000.00 3,397.76 Signed 2021-02-28 2021-03-04 2021-05-01 2021-04-26 2021-05-05 2021-04-26 2021-05-23 2021-05-20 2021-12-31 engagement and rayon. Selection communications Ak-Suu & Katran AAs. ARIS-CSP-IC-19-2 / Support for community Individual Consultant for Design of mobilization, youth Under IDA / D2940 Post Consultant Limited 20,000.00 0.00 2021-05-03 2021-05-04 2021-05-31 2021-06-23 2021-07-07 2021-07-05 2021-08-11 2022-02-07 technical specifications for engagement and Implementation Selection Subcomponent 1A communications ARIS-CSP-IC-21-33 / Support for community Consultant for Design of Individual mobilization, youth Under technical specifications for IDA / D2940 Post Consultant Limited 14,000.00 0.00 2021-05-20 2021-05-15 2021-06-17 2021-07-08 2021-07-24 2021-08-28 2022-02-24 engagement and Implementation Subcomponent 1A for Osh, Selection communications Batken abd Jalal-Abad oblasts Page 3 IDA-CASA-CSP-IC-CDSO- Support for community 2021-16 / Community Individual mobilization, youth Development and Support IDA / D2940 Post Consultant Limited 12,430.00 0.00 Under Review 2021-07-30 2021-07-26 2021-08-13 2021-09-12 2021-09-29 2021-12-31 engagement and Officer for Suzak rayon Djalal- Selection communications Abad oblast (CDSO) IDA-CASA-CSP-IC-CDSO- Support for community 2021-17 / Community Individual mobilization, youth Development and Support IDA / D2940 Post Consultant Limited 12,430.00 0.00 Under Review 2021-07-30 2021-07-26 2021-08-13 2021-09-12 2021-09-29 2021-12-31 engagement and Officer for Batken rayon Selection communications Batken oblast (CDSO) IDA-CASA-CSP-IC-CDSO- Support for community 2021-18 / Community Individual mobilization, youth Development and Support IDA / D2940 Post Consultant Limited 12,430.00 0.00 Under Review 2021-07-30 2021-07-26 2021-08-13 2021-09-12 2021-09-29 2021-12-31 engagement and Officer for Ozgon rayon Osh Selection communications oblast (CDSO) IDA-CASA-AF-CSP-IC-2021- Support for community 19 / Community and Individual mobilization, youth Under Technology Expert for Uzgen IDA / 67560 Post Consultant Limited 8,000.00 0.00 2021-07-30 2021-07-26 2021-08-27 2021-09-26 2021-10-31 2021-12-31 engagement and Implementation rayon Salam-Alik, Kolduk, Selection communications Altyn-Bulak AAs. IDA-CASA-AF-CSP-IC-2021- Support for community 21 / Community and Individual mobilization, youth Technology Expert for Bazar- IDA / 67560 Post Consultant Limited 8,000.00 0.00 Under Review 2021-07-30 2021-07-26 2021-08-27 2021-09-26 2021-10-31 2021-12-31 engagement and Korgon rayon Kenesh & Selection communications AkmanAAs. IDA-CASA--AF-CSP-IC-2021- Support for community 22 / Community and Individual mobilization, youth Technology Expert for Nooken IDA / 67560 Post Consultant Limited 8,000.00 0.00 Under Review 2021-07-30 2021-07-26 2021-08-27 2021-09-26 2021-10-31 2021-12-31 engagement and rayon Masy, Dostuk & Sakaldy Selection communications AAs. IDA-CASA-CSP-IC-2021-19 Support for community Individual / Consultant on Local self- mobilization, youth Pending IDA / 62190 Post Consultant Limited 7,458.00 0.00 2021-07-30 2021-09-03 2021-09-17 2021-09-24 2022-03-23 governance and municipal engagement and Implementation Selection property. communications Page 4