77307 v4 The Potential of Regional Power Sector Integration Greater Mekong Subregion (GMS) | Transmission & Trading Case Study Submitted to ESMAP by: Economic Consulting Associates January 2010 Economic Consulting Associates Limited 41 Lonsdale Road, London NW6 6RA, UK tel: +44 20 7604 4545, fax: +44 20 7604 4547 email: peter.robinson@eca-uk.com Contents Contents Contents i  Tables, Figures and Boxes iv  Abbreviations and Acronyms vi  Preface ix  1  Executive summary 1  1.1  Motivations/objectives for trade 1  1.2  The trade solution put in place (or attempted) 2  1.3  Progress against targets 3  2  Context for trade 4  2.1  Economic and political context 4  2.1.1  Members of the Greater Mekong Subregion 4  2.1.2  Economic context 5  2.1.3  National power markets 5  2.2  Supply options 8  2.3  Demand 11  2.4  Energy tariffs 14  2.4.1  Retail tariffs 14  2.4.2  Marginal cost comparisons 15  2.4.3  Prices of other fuels 16  3  History of scheme 18  3.1  Overview including timeline/chronology 18  3.1.1  The GMS Program 18  3.1.2  The power market’s stages 21  3.1.3  Other regional power market initiatives 22  3.2  Project concept, objectives, and development 23  Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW i ESMAP Briefing Note 004/10 | June 2010 Contents 3.2.1  Concept and objectives 23  3.2.2  Development 24  3.2.3  “Omittedâ€? areas 25  3.3  Feasibility studies done 25  3.4  Assets built and planned resulting from the scheme 26  3.5  Interconnections and electricity trade 29  3.6  Environmental and social issues 30  3.6.1  Environmental and social impacts 30  3.6.2  Carbon emissions savings 32  4  Institutional arrangements 34  4.1  Organizations to govern and coordinate the scheme 34  4.1.1  Electric Power Forum 34  4.1.2  Regional Power Trade Coordinating Committee 35  4.1.3  Focal Group 36  4.1.4  Planning Working Group 36  4.1.5  Proposed institutions 37  4.2  Role of national governments and regional institutions 37  4.3  Regulatory agencies 38  4.4  Role of outside agencies 38  5  Contractual, financial and pricing arrangements 41  5.1  Contracts 41  5.2  Ownership and finance 44  5.3  Pricing arrangements 45  6  Future plans 46  6.1  Vientiane Plan of Action 46  6.2  Regional Cross Border Trade Road Map 47  6.3  Physical interconnections 49  6.4  Major issues 50  Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW ii ESMAP Briefing Note 004/10 | June 2010 Contents Bibliography 52  A1  National power markets 58  A1.1  Cambodia 58  A1.2  China (Yunnan and Guangxi) 60  A1.3  Lao PDR 62  A1.4  Myanmar 64  A1.5  Thailand 66  A1.6  Vietnam 71  A2  Electricity supply 75  A3  Electricity demand 86  A4  Contracts 89  Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW iii ESMAP Briefing Note 004/10 | June 2010 Tables, Figures and Boxes Tables, Figures and Boxes Tables Table 1 GMS Member Country Economic Data (2007) 5  Table 2 Energy Resources in the GMS 10  Table 3 Summary of Actual, Planned and Proposed GMS Export Projects 27  Table 4 Major Existing Cross-Border GMS Trade Contracts 43  Table 5 Vientiane Plan of Action - Power Market Institutional Activities 46  Table 6 Regional Cross Border Trade Road Map, 2008-12 47  Table 7 Proposed ADB and World Bank-Funded Interconnection Projects 51  Table 8 Thailand Power Generation by Licensee Type 66  Table 9 GMS Current and Planned Installed Capacity 75  Table 10 Existing and Planned GMS Trade Projects 77  Table 11 Electricity Peak Demand in GMS Member Countries 86  Figures Figure 1 The Greater Mekong Subregion 4  Figure 2 GMS Current and Planned Installed Capacity 8  Figure 3 Generation Fuel Mix (2007) 11  Figure 4 GMS Demand Growth 12  Figure 5 Daily Load Curves - Thailand and Vietnam 13  Figure 6 GMS Electricity Tariffs 15  Figure 7 GMS Program Institutional Structure 19  Figure 8 ASEAN Power Grid Interconnections - GMS 23  Figure 9 Export Flows in the GMS – Known Projects 28  Figure 10 Cambodia Transmission Grid 60  Figure 11 Lao PDR Transmission Grid 63  Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW iv ESMAP Briefing Note 004/10 | June 2010 Tables, Figures and Boxes Figure 12 Myanmar Transmission Grid 65  Figure 13 Thailand Transmission Grid 68  Figure 14 Vietnam Transmission Grid 73  Figure 15 Lower Mekong Basin hydro projects 84  Figure 16 Myanmar Hydro Projects 85  Boxes Box 1 Thailand's Power Import MOUs 70  Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW v ESMAP Briefing Note 004/10 | June 2010 Abbreviations and Acronyms Abbreviations and Acronyms ADB Asian Development Bank AfD Agence Française de Développement AMBDC ASEAN – Mekong Basin Development Cooperation AIMS ASEAN Interconnection Master Plan Study ASEAN Association of South-East Asian Nations BCI GMS Biodiversity Conservation Corridors Initiative BOT Build-Operate-Transfer CA Concession Agreement CBP Cost-Based Pool CDM Clean Development Mechanism CEIA Cumulative Environmental Impact Assessment CEP GMS Core Environment Program CfD Contract for Differences CGM Competitive Generation Market CLMV Cambodia, Lao PDR, Myanmar and Vietnam CSG China Southern Power Grid EAC Electricity Authority of Cambodia ECA Economic Consulting Associates EDC Electricité du Cambodge EDL Electricité du Laos EGAT Electricity Generating Authority of Thailand EGP Expert Group on Power Interconnection and Trade EMP Environmental Management Plan EOC GMS Environment Operation Center EPF Subregional Electric Power Forum ERAV Electricity Regulatory Authority of Vietnam ERC Energy Regulatory Commission (Thailand) EVN Electricity of Vietnam FG Focal Group FS Feasibility Study GMS Greater Mekong Subregion HAPUA Heads of ASEAN Power Utilities / Authorities HPP Hydro Power Plant IAI Initiative for ASEAN Integration IGA Inter-Governmental Agreement on Regional Power Trade in the Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW vi ESMAP Briefing Note 004/10 | June 2010 Abbreviations and Acronyms Greater Mekong Subregion (signed November 2002) IPP Independent Power Project ITCC Inter-TSO Compensation Charge Lao PDR Lao Peoples Democratic Republic LRMC Long-Run Marginal Cost MC Management Committee MEA Metropolitan Electricity Authority (Thailand) MEP Ministry of Electric Power (Myanmar) MIME Ministry of Industry, Mines and Energy (Cambodia) MOIT Ministry of Industry and Trade (Vietnam) MOU Memorandum of Understanding MOU #1 Memorandum of Understanding on the Conditions for the Implementation of the RPTOA—Stage 1 (signed July 2005) MOU #2 Memorandum of Understanding on the Road Map for Implementing the Greater Mekong Subregion Cross-Border Power Trading (signed March 2008) MP Master Plan MRC Mekong River Commission n.a. Not available n.k. Not known NDRC National Development and Reform Commission (China) NLDC National Load Dispatch Center (Vietnam) NPTC National Power Transmission Corporation (Vietnam) NRA National Regulatory Agency PC Power Company (Vietnam) PDA Project Development Agreement PDD Project Design Document PDP Power Development Plan PEA Provincial Electricity Authority (Thailand) Plan of Action Plan of Action for the Energy Sector (signed March 2008) PNPCA Procedures for Notification, Consultation and Agreement Policy Statement Policy Statement on Regional Power Trade in the Greater Mekong Subregion (approved January 2000) PPA Power Purchase Agreement PSO Public Service Obligation RMO Regional Market Operator Road Map Road Map for Implementing the Greater Mekong Subregion Cross- Border Power Trading (approved under MOU #2) RPTCC Regional Power Trade Coordination Committee Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW vii ESMAP Briefing Note 004/10 | June 2010 Abbreviations and Acronyms RPTOA Regional Power Trade Operating Agreement PWG Planning Working Group REE Rural Electricity Enterprise (Cambodia) RRA Regional Regulatory Agency RRB Regional Regulatory Board RTC Regional Transaction Coordinator SEA Strategic Environment Assessment SERC State Electricity Regulatory Commission (China) SIDA Swedish International Cooperation Development Agency SPC State Power Corporation (China) TA Technical Assistance TBD To be determined TOR Terms of Reference TSO Transmission System Operator UNFCCC United Nations Framework Convention on Climate Change Vientiane Plan of See Plan of Action Action WGE GMS Working Group on Environment Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW viii ESMAP Briefing Note 004/10 | June 2010 Preface Preface This case study is part of an Energy Sector Management Assistance Program (ESMAP) project on Regional Power System Integration (RPSI). The objective of the project is to facilitate and accelerate RPSI projects in developing countries around the world. The project will draw on international experience and theoretical analysis in this area to provide a framework to assess: ï?¯ the economic, financial and environmental benefits that can accrue to regional power trading; ï?¯ the institutional and regulatory arrangements needed to sustain and optimize regional projects; and ï?¯ the ways in which obstacles to integration have been successfully overcome. The final output of the project will be an umbrella report, Regional Power Sector Integration – Lessons from Global Case Studies and a Literature Review. This review will summarize the 12 case studies and literature review undertaken and analyze common themes on barriers to RPSI and solutions to overcome them. Economic Consulting Associates was contracted to execute the project. In doing so, we are working closely with ESMAP and World Bank staff, as well as government officials, utility, power pool, and regional economic community personnel, and others directly involved in implementing regional power schemes. This and other 11 Case Studies are prepared as clear, factual presentations of the selected projects. The intent is to provide a direct, easily digestible description of each of the selected projects without imposing an analytic framework or making judgments about the degree of success. Such analysis will be undertaken at the global level, considering the entirety of experiences from the Case Studies, in the aforementioned umbrella report. All 12 Case Studies follow a uniform structure to facilitate ease of comparison and reference from one Study to the next. Some sections are longer than others, depending on the specifics of the Study. Additionally, there is some cross-referencing within each Study. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW ix ESMAP Briefing Note 004/10 | June 2010 Executive summary 1 Executive summary 1.1 Motivations/objectives for trade The Greater Mekong Subregion (GMS) comprises Cambodia, Lao PDR, Myanmar, Thailand, Vietnam and the Yunnan Province and Guangxi Zhuang Autonomous Region of China. Since 1992, the countries have been linked through the GMS Economic Cooperation Program. The GMS Program has provided a framework under which the countries have been able to cooperate, with the support of external partners such as the Asian Development Bank (ADB), in developing regional initiatives such as power trade. However, it is not the only such regional initiative. The various countries involved in the GMS Program also cooperate through a range of other institutions, notably the Association of South-East Asian Nations (ASEAN), which includes all the GMS members excepting China, as well as Brunei, Indonesia, the Philippines and Singapore. ASEAN is itself driving various programs of regional integration including, through the ASEAN + 1 format, integration with China. The potential for power trade within the region has been discussed for many years. The rapid economic growth of Thailand during the 1980s and early 1990s, together with the ending of various regional conflicts, led to renewed interest in making use of the abundant hydro potential of Lao PDR and Myanmar as a means of meeting growing electricity demand at low cost and allowing diversification of the generation mix. More recently, Vietnam has emerged as a potential importer to meet demand growth which, in recent years, has averaged 12% annually. Since 1993, Thailand has entered into a series of Memoranda of Understanding (MOUs) with Lao PDR, Myanmar and China for power imports. Currently, under these MOUs, Thailand is committed to importing 10,000 MW from Lao PDR by 2017 and to the development of five major hydro projects in Myanmar (the first two of which would have a combined capacity of 8,200 MW). Two export hydro projects in Lao PDR are already in operation, the 210 MW Theun Hinboun plant—which commissioned in 1998, although development started in 1991, preceding the GMS Program—and the 150 MW Houay Ho plant, which commissioned in 1999. The 1,088 MW Nam Theun 2 plant is due to commission in late 2009. Vietnam has also entered into MOUs with Lao PDR, and imports from the 250 MW Xekaman 3 hydro plant are due to start in 2010. Of the other GMS member countries, Cambodia’s interest in power trade is that it offers a way to reduce current reliance on expensive oil-fired generation. Imports of up to 200 MW from Vietnam over a new interconnector are due to begin shortly, and there are existing imports from Thailand. In the longer term, Cambodia may become an exporter of power from hydro schemes. China is currently a significant exporter of power to Vietnam but may also become an importer in future from Lao PDR and Myanmar in order to meet its own rapid demand growth. Chinese firms are also active in the development of many export projects in the region. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 1 ESMAP Briefing Note 004/10 | June 2010 Executive summary 1.2 The trade solution put in place (or attempted) The objectives for the GMS regional market are established in a Policy Statement issued in 2000. In summary, these are to: ï?¯ Promote the efficient development of the regional power sector and regional power trade in order to aid economic growth. ï?¯ Promote extended cooperation between GMS members in the field of energy. ï?¯ Protect and improve the environment through the use of appropriate technologies and plans. The objectives are supported by a set of guiding principles, including that each GMS member recognizes: ï?¯ International power trade as an integral part of its energy policies. ï?¯ The importance of technical harmonization of transmission standards to facilities interconnection. ï?¯ The desirability of foreign direct investment and private participation in the power sector. A four-stage development of the regional power market has been set out: ï?¯ In the first stage, trade will primarily take the form of bilateral export projects, as at present. The focus during this stage is establishing common minimum standards for bilateral agreements and national codes that will allow harmonization under future regional power trade agreements, and on identifying priority interconnection projects to support expanded power trade. ï?¯ During the second stage, it is expected that links between the interconnectors constructed for export projects will allow trade between any pair of GMS member countries. However, trade will be limited to use of the surplus capacity of export project lines. During these two stages, trade will be conducted by national utilities (single buyers). ï?¯ The third and fourth stages are less well defined and are seen as being some way off. Under the third stage, interconnectors will be developed expressly for power trade, and third parties will be allowed to trade over them. The fourth stage will see the creation of an integrated competitive regional power market. Implementation of these stages is dependent on the restructuring of national power markets to allow competition in these. The GMS Program is managed at the highest level by summits of heads of government. Three such summits have been held to date. Ministerial meetings and meetings of senior officials in the sectors of activity are held about once a year. The development of the regional power market was initially led by the Subregional Electric Power Forum (EPF), established in 1995, located under this overall GMS Program governance structure. In 2002, a Regional Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 2 ESMAP Briefing Note 004/10 | June 2010 Executive summary Power Trade Coordination Committee (RPTCC) was established with responsibility for preparing a Regional Power Trade Operating Agreement (RPTOA) and establishing actions required to achieve the objectives for power trade. In 2005, guidelines for implementation of the RPTOA during Stage 1 of the power market were approved, and two institutions under the RPTCC were established—the Focal Group (FG), which coordinates implementation activities, and the Planning Working Group (PWG), whose responsibilities include identifying priority interconnection projects and establishing common regional performance standards. The RPTCC, FG and PWG are comprised of representatives of national governments and utilities. They have no permanent office or budget. The secretariat is provided by the host country for each meeting and the Asian Development Bank (ADB). The ADB has and continues to manage a number of consultancy projects providing support to the RPTCC, FG and PWG in their work. 1.3 Progress against targets Power trade in the GMS region is expected to rapidly expand in the form of bilateral export projects—almost 60 export generation projects are under construction, planned, or proposed. With regard to regional power trading, in 2008, a Road Map for implementation of power trading was approved at the Vientiane GMS Summit. This identifies a number of actions to complete Stage 1 of the regional market (focused on establishing common minimum standards), which are to be completed by 2010, and a set of actions to be undertaken in preparation for implementation of Stage 2 (focused on regulatory issues related to interconnector access and use), which are to be completed by 2012. At this time, there appears to be no trade resulting from the regional power market itself, but this is understandable given the stage of development and given that even bilateral trade is very limited at present. The concept of the regional market appears to be supported by all participating members and embedded in their own policymaking and planning. But it is only when the market moves to Stage 2, with rules for cross-border power trading and, possibly, the establishment of permanent dedicated institutions, that the market might be expected to begin to have significant impacts on the regional power sector. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 3 ESMAP Briefing Note 004/10 | June 2010 Context for trade 2 Context for trade 2.1 Economic and political context 2.1.1 Members of the Greater Mekong Subregion The Greater Mekong Subregion (GMS) is comprised of the following countries and regions of China: ï?¯ Kingdom of Cambodia ï?¯ Guangxi Zhuang Autonomous Region and Yunnan Province of the People’s Republic of China ï?¯ Lao People’s Democratic Republic (Lao PDR) ï?¯ Union of Myanmar ï?¯ Kingdom of Thailand ï?¯ Socialist Republic of Vietnam Figure 1 The Greater Mekong Subregion Yunnan Guangxi Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 4 ESMAP Briefing Note 004/10 | June 2010 Context for trade Source: Google Maps This section provides an overview of the context within which the GMS power market is being developed. Brief comparative economic data and a summary of major regional relations are provided first. This is followed by a short outline of the power sector in each member country. More detail on demand, supply, and tariffs within each GMS member are provided in subsequent subsections. 2.1.2 Economic context Basic economic data on the GMS countries is provided in Table 1. Noticeable are the high economic growth rates across the region. Although the ongoing global recession has inevitably reduced these, the region as a whole appears generally well-placed for recovery according to the latest IMF forecasts (contained in the April 2009 World Economic Outlook). The notable exception to this pattern is Thailand, whose growth rates have declined very substantially since the Asian financial crisis of 1997 and which also appeared to face a severe economic downturn in 2009. Table 1 GMS Member Country Economic Data (2007) GDP GDP Per Population Average Real GDP Capita Growth US$ bn US$ millions 1987-97 1997-07 Cambodia 9 649 13 5.8% 9.3% China 3,382 3,426 1,321 9.9% 9.6% Lao PDR 4 675 6 6.0% 6.4% Myanmar 20 340 58 3.5% 12.0% Thailand 246 3,743 66 8.4% 3.3% Vietnam 71 835 85 7.6% 7.2% Source: IMF (2009)1 2.1.3 National power markets The national power markets across the GMS member countries differ greatly in size, with the markets of China and Thailand dominating, followed by Vietnam and then the much smaller markets in Cambodia, Lao PDR and Myanmar. The markets are also characterized by their different fuel mixes with hydro and coal dominating in the Yunnan and Guangxi provinces of China, gas in Thailand, coal, gas and hydro in Vietnam, oil in Cambodia, and 1 Sources used are identified in the main text by author and date. Full references are provided in the Bibliography at the end of this report. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 5 ESMAP Briefing Note 004/10 | June 2010 Context for trade hydro in Lao PDR and Myanmar. More detail on the level and mix of generating capacity in the various markets is provided in later subsections. The various markets remain dominated by state-owned utilities, although there is large- scale penetration by independent power producers (IPPs) in all countries except Vietnam (in some cases these IPPs have been developed by entities which themselves are state-owned). Generation, transmission and distribution are vertically integrated in Cambodia, Lao PDR and Vietnam (although substantial IPP capacity also exists in all three countries). In Thailand, generation and transmission are vertically integrated while in Myanmar, transmission and distribution are integrated. None of the countries has introduced competitive power markets, either at the wholesale or retail level. Various concepts for wholesale power market competition have been explored in China, while Vietnam has issued and is implementing a road map to introduce a competitive generation market in 2010, eventually leading to full retail competition by 2024. Thailand considered the potential for introducing a competitive power market during the late 1990s, but has subsequently settled for a single-buyer market model. Cambodia, Lao PDR and Myanmar are too small for competitive power markets to be realistic. National regulatory agencies (NRAs) have been established in Cambodia, China, Thailand and Vietnam. The independence and powers of these regulators varies significantly. That in Cambodia is probably the most independent, with the greatest powers over pricing and planning. The agencies in Thailand and Vietnam oversee planning and have a major role in setting prices but operate within frameworks where final decisions are generally taken by government. The agency in China has largely advisory powers with key decisions being taken by central government. More details on the individual national market structures and governance are provided in Annex A1. The original motivation at the national level for the development of power trade within the GMS region was Thailand’s rapid demand growth in the 1990s alongside its economic growth. During this period, Thailand was concerned about securing access to low-cost energy supplies. Environmental opposition effectively ruled out further large-scale hydro expansion within Thailand,2 making imports of power from hydro projects located in Laos, Myanmar and Yunnan especially attractive. Since 1993, Thailand has entered into a series of intergovernmental memoranda of understanding (MOUs) for power imports from GMS countries: ï?¯ Lao PDR: Thailand signed its first MOU with Lao PDR in 1993 for the import of 1,500 MW of power by 2000. In 1996 a second MOU was signed for the import of a total of 3,000 MW by 2006. A third MOU was signed in 2006, which increased the purchase amount to 5,000 MW by 2015. In December 2007, the quantity to be 2The last major dam built in Thailand was the 136 MW Pak Mun project completed by EGAT in 1994. This project has been widely criticized as having severe negative impacts on local fisheries and requiring large-scale resettlement for little benefit in terms of electricity generated (output has averaged only around 290 GWh, although EGAT has argued the plant was always supposed to operate as peaking capacity). Protests by affected villagers spread to Bangkok and have led to interventions at the cabinet level both to order EGAT to open the dam gates to restore fisheries and to close them as governments have changed. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 6 ESMAP Briefing Note 004/10 | June 2010 Context for trade purchased was further increased to 7,000 MW by 2020. Further amendments to these MOUs mean that currently Thailand is committed to purchasing 1,500 MW by 2010, 7,000 MW by 2015 and 10,000 MW by 2017. ï?¯ Myanmar: An initial MOU was signed in July 1997 for the purchase of 1,500 MW of hydro capacity by 2010. In May 2005, a new MOU was signed for the development of five hydro power projects on the Salween3 river for which the Myanmar government proposed two initial projects with a combined capacity of 8,200 MW. ï?¯ China: In 1998, Thailand signed an MOU with China for the import of 3,000 MW by 2017. Imports would be by interconnectors passing through Lao PDR, making it necessary to agree to transit payments to be made to Lao PDR. At present, no agreement has been reached on these payments, and progress on developing export projects under the MOU remains stalled. Following the Asian financial crisis of 1997, Thailand’s economic growth and energy demand growth have slowed markedly. Despite this, Thailand has continued to remain committed to large-scale future imports. This appears to be partly due to the cost advantages of hydro imports and partly due to a desire to diversify away from the current dependence on natural gas for power generation. Domestic opportunities for such diversification are very limited—further large-scale hydro development is not an option, and attempts to increase coal-fired generation have run into heavy opposition on environmental grounds. Nuclear generation is now being planned but also seems likely to face strong opposition domestically. This demand has provided opportunities for Lao PDR and Myanmar to develop export- oriented hydro projects in the form of IPPs as a means of earning revenues and, through the allocation of part of the resulting capacity to domestic needs, to support electrification. The first export IPP, the 210 MW Theun Hinboun hydro plant in Lao PDR, was commissioned in 1998, followed by the 150 MW Houay Ho hydro plant in 1999. The 1,088 MW Nam Theun 2 hydro plant is due to commission in 2009 and further potential export projects have been identified. Myanmar is less advanced in implementing export projects but also has ambitious plans. Meanwhile, Vietnam’s rapid economic growth since the introduction of the Doi Moi reforms in 1986 has seen the country’s electricity demand expand at double-digit rates. This has driven increasing interest in electricity imports—both to relieve short-term supply constraints, as with current imports from China, and as a means of providing access to long- term, low-cost power supplies, as in the various hydro projects under development in Laos. Vietnam signed an intergovernmental MOU with Laos in 1998 for the import of 2,000 MW of power. A number of project-specific MOUs have been signed. Cambodia’s primary interest at present in increased power trade is the potential this offers to import lower-cost power supplies to replace its existing reliance on expensive diesel generation and to allow expansion of grid electricity services. Cambodia has ambitious plans for the development of a national transmission grid around the various interconnectors 3 The Salween is known as the Nu in China and Thanlwin in Myanmar. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 7 ESMAP Briefing Note 004/10 | June 2010 Context for trade currently being constructed, which will greatly increase the coverage of grid electricity. In the longer term, Cambodia may become a power exporter from its hydro and gas resources and, potentially, through the development of power plants using imported coal and exporting power to Thailand. China’s interest in energy trade appears to derive from a combination of import and export opportunities, including the potential for Chinese firms to develop projects in GMS countries for the regional market. Chinese firms are active in project development in Cambodia, Laos, Myanmar and Vietnam—although not all of these are directed at exports to the regional market. 2.2 Supply options Figure 2 provides a summary of existing installed capacity for GMS members and planned expansion to 2020 according to country master plans. A tabular listing together with source notes is provided in Table 9 in Annex A2. The expansion plans shown include projects developed for export purposes—which explains the large-capacity expansion in Lao PDR and Myanmar, which greatly exceeds expected growth in demand (see following section). Figure 2 GMS Current and Planned Installed Capacity MW 15000 Nuclear 12500 Renewables Hydro 10000 Oil Gas Coal 7500 5000 2500 0 CAM â€? 2007 CAM â€? 2020 LAO â€?2007 LAO â€? 2020 MYA â€? 2007 MYA â€? 2020 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 8 ESMAP Briefing Note 004/10 | June 2010 Context for trade MW 60000 Nuclear 50000 Renewables Hydro 40000 Oil Gas Coal 30000 20000 10000 0 Gua â€? 2007 Yun â€? 2007 THA â€? 2007 THA â€? 2020 VIE â€? 2007 VIE â€? 2020 CAM Cambodia Gua Guangxi Zhuang LAO Lao PDR Autonomous Region (China) MYA Myanmar THA Thailand VIE Vietnam Yun Yunnan Province (China) Different scales are used for Cambodia, Lao PDR, and Myanmar than for China, Thailand, and Vietnam, given the very large differences in size between the electricity industries in these two country groups. Planned capacity for 2020 is not available for China. Sources: See Table 9 in Annex A2. Noticeable is the massive increase in capacity planned in Vietnam, driven by the very rapid expected growth in demand included in the most recent master plan. Installed capacity is planned to increase by over six times in 10 years at an average of almost 8 GW of additions in each year. Even larger proportional increases are projected for Cambodia, Lao PDR and Myanmar, but these represent much smaller absolute capacity additions, due to their very small starting points. Expansion in these three countries is driven by export projects rather than to meet domestic demand. Thailand is planning to add almost 2 GW of domestic generating capacity annually over the period (as well as projects developed in neighboring countries). Available energy resources are shown in Table 2. For hydro and wind power the theoretical potential is shown. The economic potential will be significantly lower than this. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 9 ESMAP Briefing Note 004/10 | June 2010 Context for trade Table 2 Energy Resources in the GMS Coal (Mt) Gas (BCM) Oil (Mt) Hydro Wind (GW) (GW) Cambodia n.k. 43-99 7-14 15 26 China Yunnan 23,580 32 226 150 n/a Guangxi n/a n/a n/a n/a n/a Lao PDR 910 - - 26 182 Myanmar 200-300 160 32 100 n/a Thailand 2,400 943 124 13 152 Vietnam >40,000 144 82 30 513 Source: Baardsen (2008) Unsurprisingly, the two countries with the greatest interest in importing power in the GMS market are those that have the greatest need for new capacity and have most exploited their existing low-cost hydro resources. Thailand’s current installed hydro capacity represents 26% of its theoretical potential, and Vietnam’s is 18%. By contrast, Lao PDR has exploited just 3% of its hydro capacity to date and Myanmar 1%. This difference in available resources is a major driver of the developing regional market The current fuel mix in each country’s generation is shown in Figure 3 (where available). Of particular note is the dependence of Thailand on gas for power generation. Concern over this reliance combined with the levelling-off of gas production from Thailand’s existing fields has been one of the drivers of Thailand’s interest in importing energy, either in the form of coal to be used in Thailand or electricity imports from hydro plants located in Lao PDR and Myanmar. Over the period to 2020, Thailand is likely to remain dependent to a large extent on gas under planned capacity additions. The role of hydro will greatly increase in Cambodia and Myanmar, in large part due to export projects. The biggest shift in fuel mix will take place in Vietnam, where coal will become increasingly dominant in the generation mix under current expansion plans. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 10 ESMAP Briefing Note 004/10 | June 2010 Context for trade Figure 3 Generation Fuel Mix (2007) Cambodia Myanmar Hydro 4% Renewables  0% Coal  7% Gas 36% Hydro 57% Oil 96% Oil 1% Thailand Vietnam Renewables  Purchase (b)  2% 2% Hydro (a) 7% Coal 13% Oil 3% Coal 21% Purchase (b)  27% Gas 27% Hydro 31% Gas 66% Oil 2% a Includes hydro imports from Lao PDR b Imports and purchases from IPPs for which no fuel breakdown is given Sources: Cambodia Electricity Authority of Cambodia (2008) Myanmar Presentation at PWG-5 (2008) Thailand EGAT (2008) Vietnam Trung (2008) 2.3 Demand Figure 4 shows actual demand since 2000 and projected demand to 2020 for the GMS member countries, to the extent this can be determined from published documents. A tabular listing together with source notes is provided in Table 11 in Annex A3. Of particular note is the rapid growth in demand across the region. Since 2000, Cambodia, the Guangxi and Yunnan regions of China, Lao PDR and Vietnam have all recorded double- digit growth in demand. Demand in Thailand has grown around 6% annually on average over this period. Looking ahead, this rapid growth is expected to continue. Cambodia and Lao PDR both project very high growth rates, but from a very low starting base. Demand growth in Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 11 ESMAP Briefing Note 004/10 | June 2010 Context for trade Thailand is expected to slow (and more so following recent revisions to forecasts as a result of the economic recession), but will increase by over 20 GW over the period to 2020. Figure 4 GMS Demand Growth MW 50000 Cambodia (grid) 45000 Lao PDR 40000 Thailand Vietnam 35000 Solid lines  are actual demand.  Dashed  30000 lines are  forecast  demand 25000 20000 15000 10000 5000 0 Annual actual and forecast demand growth data is not available for China and Myanmar. Vietnamese projections are available for 2010, 2015 and 2020 and interpolated for other years. Demand growth rates Cambodia China Lao PDR Myanmar Thailand Vietnam (CSG) 2000-07 16.3% 12.6% 13.3% 4.9% 6.1% 12.0% 2007-20 20.9% n.a. 14.8% n.a. 5.7% 11.7% Sources: See Table 11 in Annex A3. Dominating demand growth in the GMS, though, are southern China and Vietnam. Long- run projections of demand for China are not available. However, if a 10% rate of electricity demand growth was maintained in the Guangxi and Yunnan regions, a rate consistent with historic growth, then the combined peak demand of these regions would grow from 23 GW in 2007 to around 80 GW by 2020 or an increase of 57 GW. Demand in Vietnam is projected to grow by 35 GW by 2020 from its 2007 levels. Together, the Guangxi and Yunnan regions of China, Thailand and Vietnam would, therefore, account for a combined demand increase of around 110 GW to 2020 or 8 to 9 GW annually. While China is likely to be largely self-sufficient, both Thailand and Vietnam will be dependent on imports to meet a large part of this demand (see preceding section). The massive discrepancies in demand levels across the GMS countries are very noticeable. In 2007, demand in the Guangxi and Yunnan regions of China and in Thailand was 110 times Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 12 ESMAP Briefing Note 004/10 | June 2010 Context for trade greater than that in Cambodia and in Vietnam was 50 times greater. Vietnam is projected to become increasingly dominant in the region’s demand. Using the growth rates in the current Master Plan, its demand will exceed that of Thailand by 2020. At present, there appears to be limited potential for opportunity trades even if the necessary interconnectors were in place. The systems in Cambodia, Lao PDR and Myanmar are too small for such trading to be significant. For Thailand and Vietnam, demand peaks at similar times during the day. However, it is possible to envisage seasonal trade developing, with Thailand taking advantage of its lower winter demand relative to summer demand and greater share of thermal capacity to export power to Vietnam, where winter demand tends to be similar to summer demand and reliance on seasonal hydro generation is greater (Figure 5). Figure 5 Daily Load Curves - Thailand and Vietnam Thailand Source: EGAT (2007a) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 13 ESMAP Briefing Note 004/10 | June 2010 Context for trade Vietnam MW 12000 10000 8000 6000 Summer 2007 Winter 2007 4000 2000 0 0 0 0 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 1 0 1 1 1 2 1 3 1 4 1 5 1 6 1 7 1 8 1 9 2 0 2 1 2 2 2 3 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 : 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Source: Trung (2008) 2.4 Energy tariffs 2.4.1 Retail tariffs Figure 6 shows average tariffs across the GMS member countries for different customer types. Data on tariffs for China was not available. The extremely high tariffs in Cambodia are due to the dependence on oil-fired generation. The potential benefits for Cambodia from access to lower-cost imports are clear. Thailand’s relatively high tariffs, which in part result from its dependence on gas-fired generation, also suggest potential benefits from trade with countries with lower-cost hydro resources. It is not clear how cost-reflective the tariffs for Lao PDR, Vietnam and Myanmar are and, therefore, the extent to which the differences between these tariffs and those for other countries reflect differences in the costs of supply.4 4 A tariff study for EDL, released in May 2009, identified a need for a 50% increase in average tariffs between 2009 and 2011, suggesting that current tariffs are significantly below costs. See: “Householders to pay more for electricity from 2009 to 2015,â€? Electricité du Laos, 18 June 2009 (http://www.edl-laos.com/edl_update2.php). Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 14 ESMAP Briefing Note 004/10 | June 2010 Context for trade Figure 6 GMS Electricity Tariffs Small Residential Large Residential Cambodia  Cambodia  9.3 17.2 (Pnh) â€? 2007 (Pnh) â€? 2007 Thailand â€? Thailand â€? 7.0 9.0 2008 2008 Lao PDR â€? Lao PDR â€? 3.0 6.5 2009 2009 Vietnam â€? Vietnam â€? 2.9 6.0 2009 2009 Myanmar â€? Myanmar â€? 2.4 2.3 2007 2007 0.0 5.0 10.0 15.0 0.0 5.0 10.0 15.0 USc/kWh USc/kWh Small Industrial Medium Industrial Cambodia  Cambodia  17.5 16.7 (Pnh) â€? 2007 (Pnh) â€? 2007 Thailand â€? Thailand â€? 9.5 9.2 2008 2008 Lao PDR â€? Lao PDR â€? 6.1 6.1 2009 2009 Vietnam â€? Vietnam â€? 5.3 5.1 2009 2009 Myanmar â€? Myanmar â€? 4.5 4.5 2007 2007 0.0 5.0 10.0 15.0 0.0 5.0 10.0 15.0 USc/kWh USc/kWh A small residential customer is assumed to use 50 kWh/month and a large residential customer 300 kWh/month. A small industrial customer is assumed to be connected at 6 kV to 12 kV (depending on voltage levels in use) and to use 10,000 kWh/month with a peak demand of 40 kW. A large industrial customer is assumed to be connected at 35 kV or 69 kV and to use 100,000 kWh/month with a peak demand of 220 kW. Sources: Cambodia Electricity Authority of Cambodia (2008) Lao PDR Electricitè du Laos website Myanmar Presentation at Franco-ASEAN Seminar (2007) Vietnam Prime Minister Decision No. 21/2009/Q Ã?-TTG Thailand Energy Regulatory Commission (2009) and Provincial Electricity Authority website Conversions are made at current market exchange rates (as reported by the Financial Times for 31 July 2009) excepting Myanmar, where the unofficial market exchange rate is used. 2.4.2 Marginal cost comparisons Only limited recent evidence on long-run marginal costs (LRMCs) for GMS countries is available. A 2006 study for Vietnam by Economic Consulting Associates using data from 2002–2003 estimated the LRMC for industrial customers as approximately USc4.6/kWh (using then-current exchange rates) and for residential customers as approximately USc7.9/kWh. Marginal costs were estimated for Thailand as part of a tariff study conducted in 1999–2000 by PricewaterhouseCoopers. The marginal cost of supply for all customers averaged Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 15 ESMAP Briefing Note 004/10 | June 2010 Context for trade USc6.1/kWh, while for residential customers it was USc6.8/kWh and for medium-sized industrial customers it was USc5.7/kWh. However, these estimates were prepared at a time of very low fuel prices compared to recent levels and of a significant level of overcapacity following the 1997 financial crisis. Analysis as part of the preparation of the World Bank and Asian Development Bank – supported Rural Electrification and Transmission Project for Cambodia estimated the LRMC of supply to customers in Phnom Penh at USc12.3/kWh in the absence of electricity imports and significantly lower with imports. In general, LRMC estimates appear to be below current tariff levels, but this does not necessarily imply current tariffs are excessive relative to the costs of utilities in the region. Given the large increases in fuel prices in recent years and rising investment costs, comparisons of current tariffs with the LRMC estimates must be made with caution. 2.4.3 Prices of other fuels In China and Thailand, prices of (nontransport) fuels are largely liberalized, although some limited government intervention remains.5 Rather than direct control, governments influence prices through, for example, limits on entry into or exit from fuel supply industries, encouragement or discouragement of exports, and so forth. Prices in other GMS countries largely remain regulated. The impacts are probably most significant in Vietnam,6 where coal prices for power generation have been consistently maintained below world levels. Currently, the sales price from the state minerals corporation, Vinacomin, to the state electricity corporation, EVN, is set through negotiations overseen by the Ministry of Industry and Trade and the Ministry of Finance. Based on data reported by the National Load Dispatch Centre (NLDC), the average domestic coal price for power generation in 2008 was $126/t compared to $157/t for imported coal.7 Media reports suggest that the price difference may be much greater, with imported coal prices being given as “twofoldâ€? those of domestic coal.8 The government has committed to gradually increasing coal prices for electricity generation toward export parity levels in line with planned increases in retail electricity tariffs—in early 2009, coal prices rose by 27%. The Vietnamese government has pursued a policy of pricing gas at the cost of production on a field-by-field basis (and below for some users such as fertilizer plants). For earlier gas fields, particularly the associated gas produced from the Nam Con Son basin, this has 5 For example, the Thai government helped the majority state-owned oil and gas company, PTT, which holds a monopoly over sales to the power sector, reach an agreement with the state generation utility, EGAT, whereby the full increase in gas prices during 2008 resulting from their oil indexation was not passed through. In return, gas prices to EGAT have not been lowered as much during 2009 as the fall in world oil prices would require, with the government permitting the higher price to be included in electricity tariffs. 6Insufficient information is available on fuel price regulation in Myanmar to determine whether these are more or less heavily regulated than Vietnam. 7 Assumes a coal calorific value of 6,500 kcal/t. Prices reported in PB Associates (2009). 8 See, for example: “Power investors turn back on Vietnamese coal importers,â€? LookatVietnam, July 2009 (http://www.lookatvietnam.com/2009/07/power-investors-turn-backs-on-vietnamese-coal-importers.html) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 16 ESMAP Briefing Note 004/10 | June 2010 Context for trade resulted in gas prices of around $3.8/mmbtu in 2008. The more recent Ca Mau project has, however, faced much higher gas prices reported by NLDC as around $9.2/mmbtu. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 17 ESMAP Briefing Note 004/10 | June 2010 History of scheme 3 History of scheme 3.1 Overview including timeline/chronology 3.1.1 The GMS Program Regional power trade in the GMS began in 1971 with exports from the Nam Ngum hydropower plant (HPP) in Lao PDR to northeast Thailand. Subsequently, the Theun Hinboun and Houay Ho HPPs have been developed in Lao PDR, exporting to Thailand, along with the soon-to-commission Nam Theun 2 HPP,9 which will also export to Thailand, and the Xekanman 3 HPP exporting to Vietnam. A large number of other hydro power plants are under development or planned for Lao PDR and Myanmar, for export to China, Thailand and Vietnam. A number of high-voltage interconnectors are planned or being developed alongside these exports which, it is hoped, will form the nucleus for both a future Lao national grid and for trade between GMS countries via Lao PDR. While these various projects are gradually leading to the de facto establishment of an interconnected regional electricity grid, the impetus behind the development of a more formal GMS market is the GMS Economic Cooperation Program. The program was initiated in 1992 to implement high-priority subregional projects in transport, energy, telecommunications, environment, human resource development, tourism, trade, private- sector development and agriculture. The ADB has been a major driving force behind the program, although other donors also provide support. A formal institutional structure for the program was agreed upon in 1995. Under this, the highest coordinating body is the GMS Summit attended by prime ministers of participating countries. Policy direction and coordination is generally provided by Ministerial Meetings and, under these, Senior Officials Meetings. A number of Sectoral Working Groups and Fora are responsible for operational matters relating to the implementation of the program. The structure is illustrated in Figure 7. As of mid-2008, there had been three GMS Summits (in 2002, 2005 and 2008) and 14 Ministerial Meetings (or approximately one per year). The Senior Officials Meeting takes place once or twice per year. The GMS Program does not have a formal secretariat. Instead, the ADB acts as a de facto secretariat, facilitates and coordinates meetings and activities, and provides technical, financial, administrative and logistical support to the GMS institutions. 9 This is the subject of a separate case study. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 18 ESMAP Briefing Note 004/10 | June 2010 History of scheme Figure 7 GMS Program Institutional Structure GMS Summit GMS Ministerial Meeting National ADB Coordinator Senior Officials’ Meeting (SOM) Sectoral Working Groups / Fora Source: ADB (http://www.adb.org/Documents/Others/GMS/Program/institutional-arrangements.pdf, accessed 6 May 2009) The concept of a GMS power market has existed for many years. During the 1950s, Thailand and the newly independent states of French Indochina and Myanmar (then known as Burma) were cooperating on initiatives to develop the Mekong River. The first regional power project, the Nam Ngum plant in Lao PDR, began operations in 1971. However, the various wars and border tensions that followed during the 1970s and 1980s prevented any significant progress until the 1990s. At the time of the formation of the GMS Program in 1992, regional power integration was identified as one of the areas of cooperation between members. Export projects were already being explored by this date—the Lao PDR government had begun studies on potential projects during 1991, of which the first result was the Theun Hinboun HPP.10 Major dates in the development of the GMS electricity market under the GMS Program are: ï?¯ April 1995: The Subregional Electric Power Forum (EPF) was formally inaugurated at a meeting in Yangon, Myanmar. Establishment of the EPF was agreed at the Fourth Conference on Subregional Economic Cooperation (Ministerial Meeting) held in Chiang Mai, Thailand, in September 1994. ï?¯ January 1998: The Expert’s Group on Power Interconnection and Trade (EGP) was established to provide recommendations on regional power issues in the GMS. 10 http://www.adb.org/Projects/Theunhinboun/Pcr/project_description.asp Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 19 ESMAP Briefing Note 004/10 | June 2010 History of scheme ï?¯ January 2000: At the Ninth GMS Ministerial Meeting in Manila, ministers endorsed the Policy Statement on Regional Power Trade in the Greater Mekong Subregion (the Policy Statement). This establishes the objectives and principles for power trade among the GMS member countries. It also provided for an intergovernmental agreement on regional power trade to be prepared, which would provide the framework to implement the policy statement. ï?¯ November 2002: The Inter-Governmental Agreement on Regional Power Trade in the Greater Mekong Subregion (the Inter-Governmental Agreement, IGA) was signed in Phnom Penh. The IGA provided for the establishment of a Regional Power Trade Coordination Committee (RPTCC) and required the RPTCC to establish a plan for: ï?¯ Preparing a draft Regional Power Trade Operating Agreement (RPTOA) specifying the rules for regional power trade. ï?¯ Recommending the arrangements for policymaking and day-to-day management of regional power trade, including the necessary coordination bodies. ï?¯ Establishing the short, medium and long-term actions required to achieve the objectives for regional power trade. ï?¯ Identifying the necessary implementation steps, including financing arrangements. ï?¯ July 2005: A Memorandum of Understanding on the Guidelines for the Implementation of the RPTOA – Stage #1 (MOU #1) was signed in Kunming. This approved the draft RPTOA11 issued by the third RPTCC meeting (April 2005) as guidelines for Stage 1 of the regional power market. It also established two new institutions to support the work of the RPTCC: ï?¯ The Focal Group (FG) was established to coordinate implementation activities in each GMS country. MOU 1 provides that this may subsequently evolve into a technical secretariat. ï?¯ The Planning Working Group (PWG) was established to fulfil the functions of the operational and system planning working groups identified in the draft RPTOA. These include preparing a regional interconnection plan, participating in developing regional performance standards, and creating a regional database. ï?¯ March 2008: A Memorandum of Understanding on the Road Map for Implementing the Greater Mekong Subregion Cross-Border Power Trading (MOU 2) was signed in Vientiane. The Road Map contains actions and an indicative timeline up to 2012 required to implement Stage 1 of regional power trading and prepare for Stage 2. Activities identified are: 11Formally, MOU #2 approved guidelines for implementation of the RPTOA during Stage 1. For conciseness, in this report we refer to these guidelines as the approved RPTOA. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 20 ESMAP Briefing Note 004/10 | June 2010 History of scheme ï?¯ Completion of the studies on performance standards, transmission regulations, a priority interconnection plan, standard metering and communications arrangements and power trade rules by 2009–2010 for implementation of Stage 1. ï?¯ Completion of studies on a GMS grid code, expanded transmission regulations and identification of regulatory barriers to the development of power trade by 2012 in readiness for Stage 2. This second MOU was signed alongside the most recent GMS Summit (prime ministerial level) which was held in Vientiane 30–31 March 2008. The summit endorsed a Plan of Action for GMS Development, including the Road Map for the energy sector set out in MOU #2. The various agreements and the role, composition and administration of the institutions created under these are discussed later in this case study as part of the descriptions of institutional arrangements and contracts. 3.1.2 The power market’s stages The regional power market is planned to evolve through a number of stages. Stage 1 is defined in the RPTOA approved under MOU #1 in July 2005. Stage 2 is briefly defined in MOU #2 signed in March 2008. The definitions of each stage as used in these agreements are provided below: Stage 1 corresponds to the initial period when only country-to-country power transactions are possible, before a regional transmission network is established to enable power trading between any pair of member countries. During this period, the existing cross-border transmission lines are mostly associated with Power Purchase Agreements between the Parties or an Independent Power Producer located in any one Party country selling power to a National Power Utility in a neighbouring country. The cross border trading in Stage 1 refers to opportunity exchange of power between National Power Utilities of the Parties using the excess capacity of existing cross border transmission lines over and above the transmission capacity required for power transfers associated with Power Purchase Agreements. Stage 2 corresponds to the moment when trading will be possible between any pair of GMS countries, eventually using transmission facilities of a third regional country. However, in this stage the available cross border capacity is limited and based on surplus capacity of lines linked to Power Purchase Agreements. In effect, Stage 1 represents the existing situation where power trade is almost entirely conducted under bilateral contracts, although the definition also provides scope for opportunity trades between national utilities, using any spare interconnection capacity developed for bilateral exchanges. Under Stage 2, it is expected that some transit trade will develop, but this will continue to largely use interconnector capacity constructed under bilateral arrangements. Two further stages have been outlined. Under Stage 3, interconnectors will be developed expressly for cross-border power trading, and third parties (other than national utilities) will be permitted to begin trading over these. Under Stage 4, a competitive regional power market would be established. A precondition for this would be the establishment of multi- seller, multi-buyer power markets in member countries. The timing of Stages 3 and 4 is Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 21 ESMAP Briefing Note 004/10 | June 2010 History of scheme uncertain, and different countries may move to these stages at different times, depending on the extent of liberalization of their national electricity market. 3.1.3 Other regional power market initiatives Most of the GMS members, with the exception of the Yunnan Province and Guangxi Zhuang Autonomous Region of China, are also members of the Association of South-East Asian Nations (ASEAN). ASEAN has its own set of regional initiatives promoting economic cooperation and linkages in a number of sectors, including energy. In June 1996, ASEAN members and China signed the Basic Framework of ASEAN-Mekong Basin Development Cooperation (AMBDC) in Kuala Lumpur.12 The Framework’s objectives include strengthening interconnections between ASEAN and Mekong riparian countries, including in energy. However, there do not appear to have been substantial actions in the energy sector emerging out of this Framework. The minutes of the most recent Ministerial Meeting, held in Singapore on 29 August 2008, identified only the Singapore-Kunming Rail Link Project as a significant infrastructure project under the AMBDC framework.13 ASEAN has also established the Initiative for ASEAN Integration (IAI), which is intended to assist the economic development of the poorer ASEAN members, Cambodia, Lao PDR, Myanmar and Vietnam (collectively referred to as CLMV). The most recent workplan under the IAI, covering 2009–2012, includes support for projects building CLMV capacity to participate in the ASEAN Power Grid.14 The Power Grid concept is derived from an ASEAN Interconnection Master Plan Study (AIMS) completed in March 2003, which identified 11 priority interconnection projects for ASEAN for implementation between 2007 and 2020. Of these, a number fall within the GMS as illustrated in Figure 8. It appears to have been agreed that further action on those interconnections planned for the GMS will be undertaken in the context of the GMS Program. 12 http://www.aseansec.org/6353.htm. At the time the Framework was signed, Cambodia, Lao PDR and Myanmar were not members of ASEAN, but all subsequently joined, leaving China as the only non-ASEAN signatory to the Framework. 13 http://www.aseansec.org/22363.htm 14 http://www.aseansec.org/22325.pdf Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 22 ESMAP Briefing Note 004/10 | June 2010 History of scheme Figure 8 ASEAN Power Grid Interconnections - GMS Project Type Capacity (MW) Year Thailand – Lao PDR HVAC 1578 / 2015 2008 / 2010 Thailand – Myanmar HVAC 1500 2013 Thailand – Cambodia HVAC 80 / 300 2004 / 2016 Vietnam – Lao PDR HVAC 1887 2007-2016 Cambodia - Vietnam HVAC 80 / 120 2003-2006 Source: HAPUA (2008) 3.2 Project concept, objectives, and development 3.2.1 Concept and objectives The objectives for the regional power market, as identified by the GMS Program countries participating countries, are set out in the Policy Statement issued in January 2000: (a) To promote the efficient development of the electric power sector in the GMS with the objective of aiding economic growth; (b) To promote opportunities for extended economic cooperation between Members in the field of energy; (c) To facilitate the implementation of priority electric power projects; (d) To address technical, economic, financial and institutional issues relevant to GMS electric power development; (e) To promote electric power trade, where economic, to further these objectives; and (f) To protect and improve the environment through the adoption of appropriate technologies and plans. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 23 ESMAP Briefing Note 004/10 | June 2010 History of scheme These objectives are supported by a set of guiding principles, also contained in the Policy Statement: (a) Each Member recognises and endorses international trading in electric power to be an integral part of its policies to strengthen its electricity sector; (b) Each Member recognises the importance of technical harmonisation of electric power transmission parameters and practices with eventual interconnection in mind; (c) Each Member recognises the desirability of foreign direct investment on reasonable terms in its electric power sector in order to speed economic development in the GMS; (d) Each Member recognises that, for private-sector participation in the electric power sector on reasonable terms, certain “best practiceâ€? guiding principles should be recognised as generally indicated in Annex 1 hereto [see the full Policy Statement for this Annex]; (e) Each Member recognises the importance of open communication and the sharing of information in order to promote the efficient development and supply of electric power; and (f) Each Member recognises the need to protect and improve the environment through the adoption of appropriate technologies and plans. 3.2.2 Development Regional power trade has become part of the long-term power development planning of all GMS member countries. The initial impetus appears to have come from Thailand with its signing of MOUs for imports with Lao PDR and Myanmar. This has led all three countries to include projects for export from Lao PDR and Myanmar to Thailand in their own national power development plans. More recently, both Cambodia and Vietnam have included regional projects in their national power planning. The main driver for the development of regional power trade appears to continue to be Thailand’s desire for imports of power, which Lao PDR, Myanmar and now Cambodia are all enthusiastic to supply. Trade is being largely driven by the benefits offered in the form of lower-cost power for Thailand and revenue-generating opportunities for exporting countries. Vietnam’s increasing interest in imports may lead to some shifts in the future. Meanwhile, China’s involvement to a great extent appears to be in participating in export projects in regional countries—Chinese developers are promoting projects in Cambodia, Lao PDR and Myanmar. The ongoing development of a regional market framework has been more in response to these developing power trades than in leading them. The framework builds on the cross- border interconnections being developed to support export projects and the bilateral power purchase agreements (PPAs) underlying these, as is clear from the description of Stage 1 of the market. At no time do possible alternatives such as moving rapidly to a regional power pool appear to have been seriously considered given the massive political, legal and technical barriers to such a market. The creation of a separate institutional, legal and regulatory framework for the regional market seems in large part to be due to its inclusion in the general move to greater Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 24 ESMAP Briefing Note 004/10 | June 2010 History of scheme integration of regional activities under the GMS Program to which ministers in the participating countries have committed themselves. The actual design of the power trading framework has largely been handled by utility experts working through the various groups set up for this purpose, with very extensive support from IFIs and their consultants. In many cases, it seems IFIs and their consultants have taken the lead in developing draft documentation to provide a basis around which representatives of the member countries can build consensus. Separate from the arrangements for the regional power market, the GMS Program is now pursuing a similar strategy to the development of a regional action plan for energy integration covering nonpower energy trade and renewable energy sources in particular. A Subregional Energy Forum (SEF) has been established and has held two meetings to date to agree upon a draft Energy Action Plan for presentation to the GMS Ministerial Meeting. 3.2.3 “Omittedâ€? areas The regional market’s focus is currently on facilitating trade using transmission facilities already being developed, particularly for bilateral export projects. While priority interconnection projects are being identified through a regional planning process, at present the market institutions do not seem to be directly involved in the structuring, financing or implementation of these. In general, the regional market is being developed in very much a gradualist manner. The scope of activities reflect this, with initial focus being on establishing a minimal set of rules and standards which can be used by national system operators in trading power over spare interconnector capacity and in developing national-level documents which are consistent with those in other GMS countries. Initial work on the design of regional transmission tariffs and regulatory arrangements is beginning, but introduction of these is some way off. 3.3 Feasibility studies done While feasibility studies have been undertaken for specific power projects being developed for export purposes within the GMS, we are not aware of any feasibility studies of the GMS power market itself. External agencies, notably the Asian Development Bank (ADB), World Bank and ESMAP, have supported a number of studies looking at the potential gains from increased regional power trade and major barriers to achieving this. Most recent of these is the ADB-supported strategy, Building a Sustainable Energy Future: The Greater Mekong Subregion, issued in June 2009. This estimates that the present value of electricity costs across the GMS over the period 2005–2025 would be some US$213 billion lower if the regional energy market was to be fully integrated, representing a reduction of around 15% in costs. The ADB and other financing institutions and donors have also been active in funding consultancies to support the various studies being undertaken to implement the GMS Regional Power Market (as identified in the IGA, MOU #1 and MOU #2). This support is described further in Section 4.4. These studies include an indicative regional master plan which, while not a feasibility study, does identify priority projects for development to support regional power trade. The initial version of this master plan issued in 2004 provided Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 25 ESMAP Briefing Note 004/10 | June 2010 History of scheme estimates of total generation and transmission costs for GMS countries if only existing and committed interconnections were developed and under an extended cooperation scenario under which all economic projects identified in existing MOUs were completed. Total cost savings to 2020 from extended cooperation in power trade were estimated at US$914 million (present value in 2001, discounted at 12%) or around 2% of total costs.15 3.4 Assets built and planned resulting from the scheme Table 10 in Annex A1 provides a list of generation projects and international interconnectors currently in place or under development among GMS countries. A summary of the identified projects is provided in Table 3. Projects are organized by the host country rather than by importing country. The status of many of these projects is difficult to ascertain, and this list should not, therefore, be regarded as definitive. The list of interconnectors ignores trades conducted at medium voltages (there are a number of cross-border purchases by isolated areas in Cambodia and Lao PDR from the neighboring Thai and Vietnamese systems at medium voltage). It also does not include interconnectors constructed for the purposes of transmitting power from export projects and which are owned by the associated project companies and national utilities. 15 Table 6-16 in Norconsult (2004), Indicative Master Plan on Power Interconnection in GMS Countries. Reported in Garrett (2004). Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 26 ESMAP Briefing Note 004/10 | June 2010 History of scheme Table 3 Summary of Actual, Planned and Proposed GMS Export Projects Exporter Generation Projects Interconnector Projects No Capacity (MW) No Capacity (MW) Cambodia 8 8,630 0 0 China (Guangxi and 1 n.k. 7 2,610 Yunnan) Lao PDR 38 19,582 3 n.k. Myanmar 12 29,070 1 n.k. Thailand 0 0 2 n.k. Vietnam 0 0 2 240 Sources: See Table 10 in Annex A2. Figure 9 provides a summary of current and imports and exports between GMS member countries, the possible level by 2020, and the total potential level based on identified projects. Decisions on project status used in preparing this summary are inevitably somewhat arbitrary but, in general, only projects included in both the importing and exporting countries’ current power master plans are assumed to proceed by 2020. The main potential power flows are from Cambodia and Lao PDR to Vietnam, from Lao PDR and Myanmar to Thailand, and from Myanmar to China. The major flows which appear most likely to be in place by 2020 are from Lao PDR to Thailand and Vietnam and from China to Vietnam. There will also be small-scale exports and imports involving Cambodia. The various planned projects are not the result of any comprehensive regional planning exercise. Instead, they have been identified at a national level, although in some cases the impetus has been agreements for exports to neighboring countries which have incorporated planned projects into their own national master plans. The indicative regional master plan prepared under ADB funding also provides a set of projections of future energy trade between GMS member countries, based on optimizing flows within the region. These show a rather different pattern of expansion from that under the existing national plans. By 2021, the indicative plan projects the major export flows as being from China to Thailand via Lao PDR, from Cambodia, Lao PDR and Myanmar to Thailand, and from Vietnam to China and Thailand. By 2028, it projects Lao PDR and Myanmar to be major exporters to Thailand, reduced flows from China to Thailand, much reduced flows from Cambodia to Thailand, and relatively small flows from Myanmar to China, Cambodia to Vietnam and China to Vietnam. Most noticeable compared to national plans is the expectation from the regional plan that Vietnam will be an exporter, not importer, for at least part of the period,16 and that exports from Myanmar to Thailand will start more rapidly than is reflected in Thailand’s own national planning. 16 From examination of the report, it appears that this may be due to an assumption that domestic coal and gas prices in Vietnam will remain below export parity levels for an extended period, making it economic to develop thermal generating capacity in Vietnam’s North region to export to China. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 27 ESMAP Briefing Note 004/10 | June 2010 History of scheme The analysis in the ADB’s regional strategy, Building a Sustainable Energy Future, shows the largest projected trade as being from Myanmar to Thailand with significant trade also from Lao PDR and Cambodia to Thailand, Vietnam and China. Thailand would be the largest importing country. Figure 9 Export Flows in the GMS – Known Projects Current (mid-2009) Possible (to 2020) 795 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 28 ESMAP Briefing Note 004/10 | June 2010 History of scheme Potential (all identified projects) 4940 Numerical values represent maximum potential flows in MW Sources: As for Table 3. 3.5 Interconnections and electricity trade Current interconnections fall into two groups: ï?¯ Cross-border interconnections for electricity trade between China and Vietnam, Vietnam and Cambodia, and Thailand and Cambodia. ï?¯ Interconnectors dedicated to transporting output from export projects located in Lao PDR to Thailand and, in the near future, to Vietnam. The major existing interconnectors that are not associated with export projects are: ï?¯ A 115 kV interconnector between Thailand and Cambodia commissioned in 2007 which exports power from Thailand’s grid to the northwest region of Cambodia, serving the provincial capitals of Bantey Meanchay, Siem Reap and Battambang. ï?¯ A 220 kV interconnector between Vietnam and Cambodia which is due to commission imminently to serve the Phnom Penh region. ï?¯ A 110 kV interconnector between Vietnam and Cambodia and a 115 kV interconnector between southern Lao PDR and Cambodia which are both due to commission in 2010. ï?¯ Vietnam has imported significant quantities of power from China since 2004 in order to meet its rapidly growing demand. Initially imports were at 110 kV, but Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 29 ESMAP Briefing Note 004/10 | June 2010 History of scheme new interconnectors at 220 kV were commissioned in 2007 and a 500 kV interconnector is planned. There are also small-scale exports from Vietnam and Thailand to Cambodia, from Thailand to Lao PDR, and from Lao PDR to Vietnam to serve border communities which are distant from the national network. These exchanges are generally at medium voltage. While not a power trade as such, Thailand has also been importing gas from Myanmar since 1998 to supply the Ratchaburi CCGT plant. The dedicated interconnectors associated with export projects are controlled by the dispatch centers of the importing country. Exports over the existing interconnector between Thailand and Cambodia are treated as any other high-voltage customer of PEA. Exports from Vietnam to Cambodia will be controlled by the respective system operators. Commissioning of this line will mark the start of interconnected grid operation for Cambodia. The Cambodia system will be operated synchronously with that of Vietnam. Exports from China to Vietnam are controlled by the respective dispatch centers. The Chinese system and that of Vietnam are not synchronized, and areas supplied from China are isolated as an electrical “island.â€? 3.6 Environmental and social issues 3.6.1 Environmental and social impacts The expectation is that the GMS will encourage and support the exploitation of lower-cost hydro resources across the region. There are obviously very significant environmental and social issues associated with the development of each individual hydro plant which are addressed through national environmental and social impact assessments, approvals and mitigation requirements. Rather than repeat the issues arising with respect to each individual project, the reader is referred to the separate case study on the Nam Theun 2 hydro project, which provides an example of how environmental and social issues arising from the development of hydro projects are being managed. Cross-border interconnectors developed to facilitate power trade are subject to environmental and social impact assessments under national requirements and also the requirements of external funding agencies, such as the World Bank and the Asian Development Bank, where these are involved. There are two main regional coordinating agencies for assessing and managing environmental impacts arising out of the development of the various hydro projects along the Mekong River in particular. These are: ï?¯ The Mekong River Commission (MRC), based in Vientiane, Lao PDR. ï?¯ The GMS Environment Operations Center (EOC), based in Bangkok. Both agencies are engaged, in particular, in the assessment and awareness-raising of potential wider environmental impacts from regional projects in order to assist national governments in incorporating these into their own environmental impact assessments. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 30 ESMAP Briefing Note 004/10 | June 2010 History of scheme At present, there is no regional organization overseeing management and use of the Salween River. A joint technical committee was established in 1989 bringing together representatives of Myanmar and Thailand’s power utilities. There is no direct coordination between the planning undertaken by this committee and China’s own planned developments. Mekong River Commission The main coordinating mechanism among countries along the Mekong for the management of its resources is the Agreement on the Cooperation for the Sustainable Development of the Mekong River Basin, signed in April 1995. Signatories to the agreement are Cambodia, Lao PDR, Thailand and Vietnam. As well as the four signatories to the agreement, China and Myanmar are dialogue partners. The agreement requires rules to be developed governing water utilization and requires that each country avoid creating substantial environmental damage to other countries from their use of the Mekong. A coordinating body, the MRC, is established under the agreement. This succeeded the Mekong Committee, which was set up in 1957 under UN auspices to help manage use of the Mekong. The process of environmental and social impact assessment and approval continues to be conducted at the national level for individual projects located on the Mekong and its tributaries. However, the MRC has established Procedures for Notification, Prior Consultation and Agreement (PNPCA). These require the member countries to notify and consult in advance on the possible impacts of developments on the Mekong mainstream and its tributaries and, if necessary, to reach an agreement on managing or compensating impacts facilitated by the MRC. Under the Procedures for Maintenance of Flows on the Mainstream, member countries are obliged to maintain minimum monthly dry season flows at an acceptable level, to enable the reversal of flows on the Tonle Sap to take place during the wet season, and to prevent water releases leading to peak flows in the flood season in excess of natural levels. Many of the planned hydro export projects are located on the major tributaries of the Mekong or on the Mekong itself. The MRC has identified eight existing or planned dams along the Upper Mekong in China, 11 planned dams along the Lower Mekong through Lao PDR and Cambodia, and 94 existing and planned dams on tributaries of the Mekong— although not all are export projects. Development on this scale can be expected to have very large bio-physical impacts throughout the Mekong basin as well as impacts on the livelihoods of many millions of people. The MRC is currently conducting a Strategic Environmental Assessment (SEA) of Proposed Hydropower Development on the Mekong Mainstream in the Lower Mekong Basin. The SEA is intended to inform decision-making at the regional and national levels on the development of mainstream hydro projects, provide an initial baseline and framework for the assessment of the environmental impacts of individual projects, and provide inputs to the development of the Basin Development Plan by the MRC. It is one of two studies planned by the MRC. The second will consider the macroeconomic and fiscal impacts of the planned developments, including the regional distribution of costs and benefits and their impacts on social equity. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 31 ESMAP Briefing Note 004/10 | June 2010 History of scheme The SEA is not a legal requirement but is supported by the individual MRC member countries as a means of helping identify the environmental and social impacts of the planned developments. As the MRC has no legal authority in this area, it has publicly noted the need to ensure that the SEA does not appear to contradict decisions reached through national-level planning and environmental assessment processes. Environment Operations Center The EOC was established in April 2006 following on from the endorsement of the GMS Core Environment Program (CEP) at the second GMS Summit in July 2005. Its main tasks are: ï?¯ Managing GMS environmental information. ï?¯ Managing the GMS Core Environment Program, setting the framework of environmental safeguards and codes of practice for development sectors, preparing the GMS environment action plan, and managing the Biodiversity Conservation Corridors Initiative (BCI). ï?¯ Performing SEAs of sectors, contributing to the sustainability of development projects and carrying out environmental reviews of strategies and plans. ï?¯ Convening regular consultative meetings of development partners and stakeholders and nurturing the GMS environmental partnership. ï?¯ Serving as secretariat of the Working Group on Environment (WGE). The WGE is one of the nine sector-based working groups under the GMS Program. It was originally established in 1995, and its 15th Annual Meeting was held in July 2009. The WGE facilitates the implementation of priority GMS environmental projects, ensures that environmental issues are properly addressed in other GMS sectors, particularly transport and energy, and helps harmonize national environmental legislation. The EOC conducted an SEA in 2007–2008 on the hydropower aspects of the most recent national power development plan in Vietnam (Master Plan VI). A second SEA on eight dams located on the Mekong mainstream in Lao PDR is being undertaken. 3.6.2 Carbon emissions savings The development of the regional power market should generally be expected to reduce emissions across the region—primarily through the substitution of gas-fired generation in Thailand and coal and gas-fired generation in Vietnam with hydro power generated in Cambodia, Lao PDR and Myanmar. Interconnection can also be expected to reduce emissions substantially in Cambodia in particular, given its current reliance on diesel generation which can be replaced by imported power, but the small size of the Cambodian system means that the impacts of this in regional terms will be minor. Although not currently envisaged, in the longer term it may allow for expanded development of the region’s renewable energy resources—e.g., wind generation in Vietnam—relative to what individual countries could achieve. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 32 ESMAP Briefing Note 004/10 | June 2010 History of scheme However, there are also potentially offsetting effects. Large hydro power plants will release methane from the rotting vegetable matter submerged at the time of flooding the reservoir, and this can have substantial global warming impacts. At least two of the major proposed export projects to Thailand (the 3,600 MW Koh Kong project in Cambodia and the 1,800 MW Hong Sa project in Lao PDR) are coal-fired. The ADB’s analysis of regional market benefits (presented in Building a Sustainable Energy Future) estimates that emissions over the period to 2025 would be around 36 MtCO2e lower with a fully integrated regional energy market. This represents a saving of around 3% in emissions compared to the base case—suggesting that integration alone will deliver relatively small reductions in emissions without major actions to promote energy efficiency and the use of renewable energy technologies at national levels. To date, only one project associated with the GMS market has applied for certification under the Clean Development Mechanism (CDM). This is the 220 kV interconnector between Vietnam and the Phnom Penh area in Cambodia. A Project Design Document (PDD) together with a proposed new methodology for the calculation of emissions savings resulting from a cross-border project of this type was submitted to the Methodology Panel of the United Nations Framework Convention on Climate Change (UNFCCC) in May 2008. As of the date of this case study, the Methodology Panel has not reached a decision on the validity of the proposed methodology, and the application is, therefore, still pending. The PDD estimates the annual savings in emissions resulting from the replacement of fuel oil and diesel generation in Cambodia with electricity generated using the Vietnamese capacity mix at an average of 53,616 tCO2e annually over the requested 10-year crediting period. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 33 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements 4 Institutional arrangements 4.1 Organizations to govern and coordinate the scheme The coordinating institutions for the regional power market sit underneath the GMS Program institutions, as described in Section 3.1.1 and illustrated in Figure 7. There are four institutions specific to the GMS power market: ï?¯ The Subregional Electric Power Forum inaugurated in April 1995. ï?¯ The Regional Power Trade Coordinating Committee established by the November 2002 Inter-Governmental Agreement. ï?¯ The Focal Group and Planning Working Group established under MOU #1, which are under the RPTCC. The role, membership, powers and governance of each of these institutions is described in the sections that follow. None of the institutions has a permanent base or secretariat. Instead, meetings rotate between member countries. The role of secretariat is fulfilled by government or utility staff in the host country for the meeting and the ADB. Minutes of meetings are generally posted on the website of the ADB. 4.1.1 Electric Power Forum The EPF serves as an advisory body to the GMS Ministerial Meetings on subregional power issues. Its objectives, as set out in its Terms of Reference (TOR) are to: ï?¯ Act as a cooperative link among government agencies and related institutions directly involved in power supply and power system development in the subregion. ï?¯ Act as a promotional and advisory organization for the development of efficient power systems in the subregion. ï?¯ Identify and promote opportunities for mutually beneficial subregional cooperation projects in the power sector. ï?¯ Promote financing by government, utilities, donors and the private sector of priority projects related to the development of subregional power systems. ï?¯ Provide a forum for discussing software issues, such as planning tools and pricing principles, related to subregional cooperation in power projects. ï?¯ Provide and disseminate information to participating countries and cooperate with regional and international organizations. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 34 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements ï?¯ Facilitate training and other human resource activities to support the development of power systems. Each GMS country is represented on the EPF by two members. One is a senior official from the ministry or other government agency responsible for power sector policy and planning and the other is a senior manager from the key power utility in the country.17 The EPF has been supplanted by the establishment of the RPTCC, which has the same membership. 4.1.2 Regional Power Trade Coordinating Committee The RPTCC was established under Article 4 of the IGA. Its role, as defined in the IGA, is to “…actively coordinate for successful implementation of regional trade and to represent the countries involved in regional power trade.â€? The RPTCC reports to the GMS Ministerial Meeting. The IGA defined the first task of the RPTCC as being to establish and implement regional trade arrangements for endorsement by member countries. The specific requirements were given as the preparation of a plan to: ï?¯ Provide to the parties a final draft of the RPTOA, which will specify the rules of regional power trade. ï?¯ Provide to the parties a recommendation for the overall policy and day-to-day management of regional power trade, including the necessary bodies for coordination. ï?¯ Establish the short-, medium- and longer-term initiatives which need to be pursued on a priority basis in order to achieve the objectives of regional power trade within a specified timetable. ï?¯ Identify necessary steps for implementation of regional trade, including means for financing. The RPTCC is now responsible for the implementation of the Road Map agreed for implementation of Stage 1 and in preparation for Stage 2 under MOU #2 in March 2008. The membership of the RPTCC is the same as that of the EPF.18 The first meeting of the RPTCC was held in June 2004. To date, seven meetings of the RPTCC have been held, with the latestbeing in Ho Chi Minh City in Vietnam in November 2008. 17 China and Thailand have multiple major government-owned utilities. In each case, they are represented by the utility responsible for the operation and ownership of the transmission system—China Southern Power Grid (CSG) and EGAT, respectively. 18 Other participants may attend meetings of the RPTCC, FG and PWG, including representatives of IFIs and donors and of government and utilities in member countries. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 35 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements 4.1.3 Focal Group The FG is described in the RPTOA and was set up in January 2006 following agreement on its establishment in MOU #1, signed in July 2005. It is primarily responsible for implementation of the RPTOA. The FG’s membership comprises a group of middle managers from each country who are associated with the planning and operation of regional interconnections. As described in the RPTOA, its role is “…to implement the decisions of the RPTCC on a day-to-day basis in their respective countries and to act as the coordinating body of the RPTCC work program in each GMS member country.â€? It reports to the RPTCC. The RPTOA envisages that the FG may evolve into a technical secretariat if the RPTCC decides this is required. Since its establishment, seven meetings of the FG have been held. These are generally held concurrently with meetings of the RPTCC, although separate meetings are held where required. 4.1.4 Planning Working Group The PWG is also described in the RPTOA, and its establishment was approved in MOU #1. It was set up in June 2006 with responsibility for carrying out priority activities assigned to the RPTCC. The PWG’s membership comprises a senior level representative from each member country’s transmission system operator with responsibility for national transmission planning. Its main objectives during Stage 1 of the regional power market are: ï?¯ Preparing a plan for developing a regional network with facilities that are dedicated to cross-border transactions but are not linked to specific PPAs. ï?¯ Planning and prioritizing the addition of new transmission capacity, including recommendations regarding ownership and financing. ï?¯ Defining excess transmission capacity that is available on a non-firm basis to support short-term opportunity exchanges of power. ï?¯ Preparing plans for augmenting the capacity of existing cross-border transmission facilities and reinforcements required in national transmission systems to facilitate cross-border power trading. ï?¯ Participate in developing performance standards regarding safety-security, reliability and quality of service. ï?¯ Create and maintain the regional database on power trading with due regard to the confidentiality aspects of PPAs with private parties. The PWG’s work is coordinated by the FG on a day-to-day basis. Six meetings of the PWG have been held to date. These are generally held concurrently with RPTCC and FG meetings. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 36 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements 4.1.5 Proposed institutions While only the previously mentioned institutions are currently in existence, a number of other proposed institutions have been identified in the consultant reports issued as part of the development of the draft RPTOA, but have not been established as yet. These proposed institutions would be located under the RPTCC and comprise the: ï?¯ Management Committee (MC). This would be established in Stage 2 and be an executive group within the RPTCC responsible for day-to-day interactions with other regional institutions. The MC would have a permanent office and staff and regular funding (either by budgetary contributions or a levy on cross-border energy flows). ï?¯ Regional Regulatory Board (RRB). According to the reports, this was to be established during Stage 1 but is not included in current agreements covering this stage. It would be responsible for promoting regional power trade, including encouraging consistency in regulation and removal of inhibiting national regulations, promoting common regional performance standards, approving tariffs and conducting market surveillance. From Stage 2, the RRB would have a permanent office and staff and regular funding (initially its membership would comprise national representatives who would cover their own costs). At Stage 3, the RRB would become a Regional Regulatory Agency (RRA). ï?¯ Regional Transaction Co-Ordinator (RTC). This would be established during Stage 2, at which time it would determine the availability of cross-border transmission capacity and match offers and bids for cross-border trade. It would also monitor the regional market’s operations and develop maintenance programs and operating plans for regional transmission facilities (together with an operational planning group under the PWG). The RTC would have a permanent office and staff and regular funding. At Stage 3, the RTC would become a Regional Market Operator (RMO). 4.2 Role of national governments and regional institutions The GMS power market has emerged from agreements among national governments in the region to cooperate in a range of sectors, one of which is energy. However, the form that the evolving market is taking is largely a response to developments in power trade on a bilateral basis. The existing regional energy sector institutions are building on bilateral arrangements as an initial step to a more integrated regional power market rather than designing or creating a market. The emphasis on the role of national government and agencies rather than regional institutions is shown in the absence of a formal regional secretariat and the composition of existing regional institutions—whose membership consists of representatives of national utilities and government agencies. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 37 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements 4.3 Regulatory agencies National regulatory agencies (NRAs) exist in Cambodia, China, Thailand and Vietnam, although with varying levels of independence (see Annex A1 for more information). Regulatory agencies have not yet been established in Lao PDR and Myanmar, where regulatory responsibilities continue to be undertaken by ministries and utilities. Currently, NRAs have no direct responsibility for regional electricity trade—their responsibilities end at national borders. However, representatives of at least some NRAs participate in regional activities—as an example, the Vietnamese regulator was co-organizer of the most recent meetings of the RPTCC, FG and PWG. It is difficult to determine to what extent decisions on domestic regulatory matters by the NRAs are influenced by the regional power market. However, it does appear that the NRAs take account of requirements established or to-be-established under the various regional agreements. The NRAs in both Thailand and Vietnam have, for example, in personal communications, stated the need for ongoing revisions to their national Grid Codes to conform to the regional GMS performance standards that are under development. 4.4 Role of outside agencies Outside agencies are playing a critical role in the development of the regional power market. Most significant is probably the contribution of the ADB, which is the main external agency supporting the GMS Program as a whole as well as the regional power market in particular. The ADB has helped provide impetus to the establishment of the regional market through its own efforts and through the management of a number of technical assistance (TA) studies on the regional market (funded by the ADB and by bilateral donor agencies). These include the following: ï?¯ RETA 5920: Regional Indicative Master Plan on Power Interconnection in the Greater Mekong Subregion.19 This TA commenced in November 2000 and was completed in December 2003. It prepared the first version of the regional indicative master plan, which is used to identify priority interconnection projects to support regional power trade. ï?¯ RETA 6100: Study for a Regional Power Trade Operating Agreement in the Greater Mekong Subregion.20 This TA commenced in October 2003 and was completed in October 2007. Activities undertaken included: ï?¯ Defining the stages for the development of the GMS market. ï?¯ Drafting the RPTOA. 19 The ADB website for this project is http://www.adb.org/Projects/project.asp?id=34092 20 The ADB website for this project is http://www.adb.org/Projects/project.asp?id=36035 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 38 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements ï?¯ Laying the basis for the signing of MOU #1. ï?¯ RETA 6304: GMS Regional Power Trade Coordination and Development.21 This TA commenced in April 2006 and is financed by Agence Fançaise de Développement (AfD). As of mid-2009, the TA is effectively completed. Activities undertaken include: ï?¯ Preparing the action plan subsequently approved under MOU #2. ï?¯ Supporting the FG and PWG. ï?¯ Updating the regional indicative master plan. ï?¯ Initiating work on a regional database and trading website. ï?¯ Drafting regional performance standards. ï?¯ RETA 6440: Facilitating Regional Power Trading and Environmentally Sustainable Development of Electricity Infrastructure in the Greater Mekong Subregion.22 This TA commenced in late 2008 and is financed using funds from the Swedish International Cooperation Development Agency (SIDA). The purpose is to assist in completing the action plan activities identified for implementation of Stage 1 of the regional market as well as supporting preparation for Stage 2. Specific activities include: ï?¯ Reviewing and, where necessary, assisting in preparing national power development plans in order to update the regional indicative master plan as well as identifying the need for additional studies for priority interconnection projects. ï?¯ Estimating the costs and benefits of power trading and how these can be shared between participating countries. ï?¯ Assessing measures required to prepare national regulatory frameworks for the introduction of competitive power markets as well as advising on the regulatory frameworks required at each stage of the regional market’s development. ï?¯ Providing capacity-building in the use of cumulative environmental impact assessments (CEIAs), SEAs and environmental management plans (EMPs), including undertaking pilot strategic and cumulative impact assessments for river basins in GMS countries. The project team is investigating opportunities to coordinate with EOC in this. ESMAP has published two studies providing analyses and recommendations on the development of the GMS power market. An initial study published in December 2001 21 The ADB website for this project is http://www.adb.org/Projects/project.asp?id=39594 22The ADB website for this project is http://www.adb.org/Projects/project.asp?id=41018. A project website has been established at http://www.gms-powertrade.net/. However, little material is publicly accessible. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 39 ESMAP Briefing Note 004/10 | June 2010 Institutional arrangements identified constraints to the development of a regional power market. In December 2006, a further study was published providing an overview of market design options. This set out a phased market development program with the aim of achieving a unified regional market over a 15-year period. The ADB and World Bank are also helping with the physical development of regional interconnectors through financial support and technical assistance. The ADB is planning support to interconnectors between southern Lao PDR, Cambodia, Thailand and Vietnam as well as the upgrading of existing MV interconnectors between northern Lao PDR and Thailand to 115 kV. Under the GMS Power Interconnection Project Phase 1, ADB had planned to develop a 500 kV interconnection between Thailand and Vietnam via the southern provinces of Lao PDR. Following concerns expressed by EGAT over the stability of an interconnection with the Vietnamese system at this time, separate interconnectors with Thailand and Vietnam are currently being developed. The World Bank and ADB are jointly financing the interconnector between Vietnam and Phnom Penh in Cambodia. The World Bank is also planning to finance further 115 kV transmission lines within Cambodia and Lao PDR which will allow cross-border trade between these countries and southern Vietnam and allow future links between Thailand, Lao PDR and Cambodia. In addition, further support to the establishment of the GMS power market is being considered. A listing of ADB and World Bank–supported interconnection projects is provided in Table 7 at the end of Section 6. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 40 ESMAP Briefing Note 004/10 | June 2010 Contractual, financial and pricing arrangements 5 Contractual, financial and pricing arrangements 5.1 Contracts Higher-level agreements on the regional power market include the IGA, MOU #1, and MOU #2, described in Section 3.1. The only regional operating contract or agreement currently in place is the RPTOA, approved as guidelines for implementation of bilateral projects under MOU #1.23 Cross-border sales from export projects or across existing interconnectors are covered under bilateral agreements. Draft guidelines covering common regional performance standards have been developed by the PWG with consultant assistance (see Section 4.4). These are to be finalized by 2010 under the Road Map approved by MOU #2. Regional Power Trade Operating Agreement The RPTOA, in its current form, sets out guidelines for bilateral cross-border agreements, creating minimum common standards to facilitate future regional trade. The main features of these guidelines are as follows: ï?¯ Minimum communications and coordination protocols are established. However, details of scheduling and operation procedures and processes are left to bilateral agreements. ï?¯ The concerned transmission system operators (TSOs) are required to maintain a database of transactions suitable for future incorporation into a planned regional database. ï?¯ The contracting parties agree whether a transmission tariff (transit charge) should apply during Stage 1 of the regional market. ï?¯ Billing is to be monthly on the basis of energy sold. ï?¯ A phased dispute resolution process is established: ï?¯ Initially, the general managers of the concerned control centers seek amicable agreement. ï?¯ If this is not successful, then the dispute is referred to higher levels of the concerned TSOs. These initially appoint representatives for formal amicable discussions. ï?¯ If the dispute relates to a technical matter, then the TSOs may agree on an independent expert to provide an opinion. ï?¯ If an amicable resolution cannot be reached, the dispute is referred to arbitration. A three-member panel is appointed operating under 23 Formally, MOU #1 approved guidelines for the implementation of the RPTOA. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 41 ESMAP Briefing Note 004/10 | June 2010 Contractual, financial and pricing arrangements UNCITRAL rules. Arbitration hearings are to be held in a neutral country and conducted in English. The decision of the panel is final and no appeal is allowed to the courts. The RPTOA also defines the first two stages of the regional power market and the composition and roles of the FG and PWG. Regional performance standards The draft regional performance standards are developed from the draft regional grid code prepared as part of the consultant support to the drafting of the RPTOA. As well as the performance standards themselves they also comprise methodologies for interconnection studies, guidelines for the design of new transmission facilities associated with bilateral export projects, and guidelines on the design of transmission (transit) tariffs for application in Stage 1. Major features of the draft guidelines for performance standards are as follows: ï?¯ The PWG will define and prepare and keep updated a model of the Regional Transmission Network used for cross-border transactions. ï?¯ Transmission systems should be designed to perform in accordance with the regional standards. The PWG is responsible for developing a Transmission Design Code with standards no less strict than those currently in force in GMS member countries. The PWG in consultation with TSOs can propose modifications to the standards while the RPTCC can order changes. ï?¯ TSOs are responsible for operating their national systems to meet regional standards. Initially, TSOs are responsible for providing their own reserves. Once the regional market is established, primary reserve requirements can be shared between all member countries.24 The PWG is responsible for defining this reserve requirement and its allocation (based on energy generated) between countries. The need for country-level studies to determine the current ability to comply with the regional performance standards is identified in the report containing the draft guidelines. The report also proposes interim standards to apply in the power systems of Cambodia, Lao PDR and Myanmar which do not currently have Grid Codes (a Grid Code for Cambodia has been almost finalized in anticipation of the interconnection of its 115 kV system to Vietnam). The guidelines for the design of new export transmission facilities require that studies are undertaken to confirm that these comply with the regional performance standards and do not degrade the performance of the respective national transmission systems to which the facilities are connected. The guidelines for transit tariffs note that there is currently no open access on national transmission systems and that any use of transmission lines owned by third parties for transit (e.g., from China to Thailand) is expected to be negotiated on a case-by-case basis. 24 Primary reserve is set equal to the largest single generating unit plus a margin. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 42 ESMAP Briefing Note 004/10 | June 2010 Contractual, financial and pricing arrangements Therefore, an Inter-TSO Compensation Charges (ITCC) mechanism will only be required for Stage 2 onwards of the regional market. Given this, the guidelines only establish a few basic design principles for the ITCC, primarily that: ï?¯ Charges should be linked to the energy injected to and withdrawn from the regional transmission network. Charges will give access rights to the network as a whole. ï?¯ In Stage 2, charges should only recover the variable costs associated with incremental losses arising from transit flows. Optionally, a contribution to fixed costs might be included, but the assumption is that the regional network initially is comprised of networks built to serve national demand and paid for by national users. ï?¯ The exception to this is assets specifically constructed for regional trade, for which standard unit costs set by the RPTCC should be used to calculate costs to be recovered. These costs are allocated between users of the assets in proportion to their share in flows over those assets. Bilateral contracts Basic information on existing bilateral contracts is provided in Table 4. This excludes the soon-to-commission Nam Theun 2 hydro power project, which will export from Lao PDR to Thailand. That project is the subject of a separate case study to which readers are referred for more information. Table 4 Major Existing Cross-Border GMS Trade Contracts Project Date Trade Contract Volumes Contract Contract Price Commenced Term Lao PDR to Thailand Theun 1998 Must-take for 95% of 25 years $0.0484/kWh in Year 1. Hinboun available output. Indexed at 1% pa hydro 1999-2002 sales project averaged 1,465 GWh pa Houay Ho 1999 126 MW minimum 30 years n.k. hydro capacity project 394.2 GWh annual energy China to Vietnam 220 kV (Ha 2007 Up to 200 MW 44 months n.k. Giang) 700 GWh in Year 1 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 43 ESMAP Briefing Note 004/10 | June 2010 Contractual, financial and pricing arrangements Project Date Trade Contract Volumes Contract Contract Price Commenced Term 1,000 GWh in Year 2 220 kV (Lao 2007 Up to 250-300 MW n.k. n.k. Cai) 1,100-1,300 GWh pa Thailand to Cambodia 115 kV 2007 Up to 80 MW n.k. Supplied at applicable PEA (Banteay tariff. Average for 2007 was Mean Chey) 13.8 GWh (Nov-Dec Bt 2.82/kWh (approx. 2007 only) $0.08/kWh) Vietnam to Cambodia 220 kV August 2009 TBD n.k. Under negotiation. Original (Phnom (expected) PPA was for TOU tariff Penh) averaging $0.062/kWh in dry and $0.056/kWh in wet seasons Sources: Lao PDR to Thailand Department of Energy Promotion and Development (2009) and http://www.poweringprogress.org/index.php?option=com_content&view=article&id=79&Itemid=10 8 China to Vietnam Trung (2008) Thailand to Cambodia Electricity Authority of Cambodia (2008) Vietnam to Cambodia World Bank (2003) and personal communication with Electricity Authority of Cambodia 5.2 Ownership and finance At this stage of the regional market’s development, no assets have been specifically developed for cross-border electricity trade as part of the market (i.e., for use by third parties and for transit). While a number of export projects and interconnectors have been or are being constructed, these have been developed on a bilateral basis. Export generator projects in Lao PDR have been developed as independent power projects (IPPs). Interconnector facilities are generally owned by the transmission utility in the country in which they are located, with the exception of transmission lines in Lao PDR, which are owned by the related project company. Financing for export projects in Lao PDR is from a mix of national utilities, international developers, commercial banks and IFIs. For an example financing arrangement, see the Nam Theun 2 case study. Of the interconnectors not associated with export projects from Lao PDR, the World Bank and ADB are jointly financing the majority of the costs of the Vietnam–Cambodia interconnector and are looking at opportunities to finance other interconnectors. The cost of the Vietnam–Cambodia interconnector, including a national control center for Cambodia, is US$95 million, of which US$16 million is being funded by the World Bank under an IDA Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 44 ESMAP Briefing Note 004/10 | June 2010 Contractual, financial and pricing arrangements credit, US$44 million by an ADB loan, US$11 million by the Nordic Development Fund and the remainder by the government of Cambodia. 5.3 Pricing arrangements At present, prices for bilateral cross-border trade are set under negotiated PPAs on a case- by-case basis. A summary of current contracts is provided in Table 4. No transit (wheeling) charges are currently in place. While not explicitly ruled out under Stage 1, the general expectation is that no significant transit transactions will occur at this stage and, therefore, transit tariffs will not be required. This is reflected in the existing RPTOA, which allows contracting parties to mutually determine whether to apply transit charges, and in the draft guidelines on transit charges which do not envisage these being applied during Stage 1. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 45 ESMAP Briefing Note 004/10 | June 2010 Future plans 6 Future plans The key document setting out future plans for the GMS power market is the Plan of Action for the Energy Sector adopted at the Third GMS Summit held in Vientiane in March 2008. More detailed steps in the development of the institutional and contractual arrangements for the regional power market are contained in the Regional Cross Border Trade Road Map, which was approved by MOU #2 signed at the same summit. These two documents are described in the section that follows. 6.1 Vientiane Plan of Action The Vientiane Plan of Action identifies four strategic thrusts for the development of the GMS energy sector (including the regional power market): ï?¯ Strategic Thrust I: Broadening GMS energy cooperation through enhanced efficiency and security and sustainable development of energy resources. ï?¯ Strategic Thrust II: Regional power trade development: Building capacity for power trade operation, coordination and grid interconnection. ï?¯ Strategic Thrust III: Regional power trade development: Implementing key GMS interconnection projects for Stage 1 power trading. ï?¯ Strategic Thrust IV: Regional power trade development: Developing generation projects for power exports under Stage 1. A total of 32 projects and activities are identified as part of the Plan of Action, extending out to 2014. These are separated into three groups: ï?¯ Group 1: Ongoing projects or projects for immediate implementation with identified financing. ï?¯ Group 2: Projects for implementation later within the plan period and/or projects requiring financing. ï?¯ Group 3: Projects with no definite timeline and/or cost estimate and financing. The power market–related activities identified under Strategic Thrusts I and II, which relate to institutional issues, are listed in Table 5. Under Strategic Thrusts III and IV, the Plan of Action identifies a number of priority interconnection and export projects. These are identified as part of Table 10, which lists planned and proposed interconnectors and export projects in the GMS. Table 5 Vientiane Plan of Action - Power Market Institutional Activities Activity Indicative Estimated Remarks Timeline Cost (US$m) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 46 ESMAP Briefing Note 004/10 | June 2010 Future plans Strategic Thrust I – Broadening GMS energy cooperation Group 1 – Ongoing activities and activities for immediate implementation Promoting greater interaction 2008-12 0.05 Included in the EOC between the EPF / RPTCC and work program WGE / EOC Group 2 – Activities for later implementation Facilitating sustainable 2010-12 2.00 To be financed by ADB environmentally friendly regional power trading phase 2 Strategic Thrust II – Building capacity for regional power trade Group 1 – Ongoing activities and activities for immediate implementation Regional power trade Completing 1.30 Ongoing. Financed by coordination and development in 2008 AFD (ADB RETA 6304) Establishment of regional 2007-10 0.10 Included in the RPTCC power database and website work program Facilitating sustainable 2008-10 5.00 Ongoing. Financed by environmentally friendly SIDA (ADB RETA 6440) regional power trading Group 2 – Activities for later implementation Developing the Regional 2010-12 1.00 To be financed by AFD Transmission and Regulatory Authoritya a The consultant reports prepared for the draft RPTOA identified the need to establish a Regional Regulatory Board and a Regional Transaction Coordinator. From the Vientiane Plan of Action, it is unclear whether the Regional Transmission and Regulatory Authority will be a single combined entity replacing these two proposed separate entities. 6.2 Regional Cross Border Trade Road Map The next steps in the completion of Stage 1 of the GMS power market and in preparing for Stage 2 are set out in the Road Map approved under MOU #2 in March 2008. The Road Map provides further detail on the regional power market–related activities to be undertaken under Strategic Thrusts I and II of the Vientiane Plan of Action. The Road Map is reproduced in Table 6. Support will be provided to the GMS countries in undertaking these activities under the ongoing SIDA-funded TA project (ADB RETA 6440). In its business plan for the GMS for 2009–2011, the ADB has also provisionally allocated funding in 2010 for support to the development of the Regulation Regulatory Board and the Regional TransmissionCoordinator (see Section 4.1.5). This is identified as an activity under the Vientiane Plan of Action, but is not included in the Road Map. Table 6 Regional Cross Border Trade Road Map, 2008-12 Milestone Activities Schedule Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 47 ESMAP Briefing Note 004/10 | June 2010 Future plans Milestone Activities Schedule Timelines to fully achieve Stage 1 Complete the GMS indicative master plan 2008 for power development Select priority interconnection projects Complete the indicative 2008-10 identified in the master plan power interconnection Master Plan Develop feasibility studies of selected 2009 onwards priority projects Every two to Update the regional indicative Master Plan three years Complete the study on GMS Performance Standards and consider for adoption the suggested GMS Performance Standards on 2010 new regional interconnections and for the Complete the study on GMS synchronized operation of interconnected Performance Standards grids Consider for adoption the proposed transitional arrangements to achieve GMS 2010 Performance Standards Complete the study on Transmission Regulations and consider for adoption the Complete the study on findings of the study to coordinate the 2010 Transmission Regulations operation and power flow control in grid- to-grid interconnection synchronization and operation Complete the study on standard regional metering arrangements and communications systems in grid-to-grid 2010 interconnection for implementation during Complete the studies on Stage 1 and consider for adoption the standard regional metering findings of the study arrangements and power Complete the study on power trade rules, trade rules including resolution mechanisms for disputes outside existing PPAs for 2010 implementation during Stage 1, and consider for adoption the findings of the study Timelines to prepare for Stage 2 Undertake the study to Complete the study to identify the identify the regulatory regulatory barriers to development of barriers to the development power trade and consider for adoption the 2012 of power trade and measures and institutional arrangements implementation of next stages to address regulatory barriers Complete the study on a GMS Complete the study on a GMS Grid Code Grid Code (operational and consider for adoption the findings of 2010-12 procedures) the study, which includes: Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 48 ESMAP Briefing Note 004/10 | June 2010 Future plans Milestone Activities Schedule ï?± GMS Performance Standards ï?± Coordination procedures between System Operators to schedule and control cross-border flows, management of deviations ï?± Metering and communications ï?± Sharing of power reserves and support during emergencies Complete the study on Stage 2 Transmission Regulations and consider for adoption the findings of the study to include development of payment After 2012 Complete the study on Stage agreements / tariffs for third-party use, to 2 Transmission Regulations to compensate countries that host flows allow third-party access in linked to third parties’ trading interconnections, giving priority to contracts / PPAs, Develop and consider for adoption power including Stage 2 power trade trade rules for short-term cross-border By 2012 rules and dispute resolution trading mechanism Develop and consider for adoption power trade rules for settlement of deviations to By 2012 scheduled power trade in grid-to-grid interconnections 6.3 Physical interconnections As regards physical development of the regional network, a large number of bilateral projects are proposed or under development, the vast majority of which are export projects located in Lao PDR and Myanmar. Interconnectors between China and Vietnam for bilateral trade are also planned. The ADB and World Bank have identified a number of interconnection projects for funding specifically as part of the development of the regional network to support power trade in the GMS. These are included in the Vientiane Plan of Action. These projects are listed in Table 7. Of these, perhaps the most interesting in terms of GMS power market development is the Nabong-Udon Thani interconnection project. This will construct a 500 kV transmission line which will be owned as a joint venture by EGAT and EDL for the purposes of transmitting electricity from four export hydro projects located in Lao PDR to Thailand, for which wheeling charges will apply. As such, it is a first step in the creation of regional interconnectors which are not dedicated to an individual project or user but will have multiple users. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 49 ESMAP Briefing Note 004/10 | June 2010 Future plans 6.4 Major issues The major issue facing the GMS market appears to be whether and when to move ahead to Stage 2, at which time the market will become “formalizedâ€? with permanent institutions in place alongside a formal Grid Code, transit tariffs, and rules for short-term cross-border power trading. Currently, under Stage 1, trade is almost wholly in the form of bilateral agreements between national utilities (or national utilities and IPPs located in neighboring countries). As such, GMS member countries remain free to determine the conditions of trade and when trade will take place. Existing institutions do not have permanent offices or staff and largely act as a means of coordinating the activities of national utilities in developing mechanisms that can form the basis for a future regional market. While the GMS countries have committed to the Road Map, which includes activities to prepare for Stage 2, there is, as yet, no formal agreement committing to the implementation of this stage by a given date. The Vientiane Plan of Action refers only to projects related to Stage 1 of the regional power market, with dates for the commissioning of these projects extending out to 2014. A move to Stages 3 and 4 appears a long way off, particularly given the implied need to restructure and liberalize national electricity markets before these stages can be implemented. Of the two major GMS importing countries, Vietnam has issued a road map for such liberalization. However, Thailand has ruled out liberalization for the present and intends to maintain a national single-buyer structure. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 50 ESMAP Briefing Note 004/10 | June 2010 Future plans Table 7 Proposed ADB and World Bank-Funded Interconnection Projects Project Country Year Cost (US$m) Funding (US$M) Sponsor Co-financing Government ADB-sponsored GMS Northern Power Transmission Lao PDR 2009 53.5 20.0 30.0 3.5 GMS Nam Ngiep 1 Hydropower Project Lao PDR 2009 35.0 35.0 0.0 0.0 GMS Nabong – Udon Thani Power Transmission and Interconnection Lao PDR 2009 84.0 74.0 0.0 10.0 GMS Nam Ngum 3 Project Lao PDR 2009 52.0 47.0 0.0 5.0 Lao-Vietnam Power Interconnection (Ban Sok – Pleiku) Lao PDR 2010 150.0 25.0 117.0 8.0 Lao-Vietnam Power Interconnection (Ban Sok – Pleiku) Vietnam 2010 120.0 30.0 70.0 20.0 World Bank-sponsored 115 kV transmission: Vietnam – Kampong Cham Cambodia n.k. n.k. n.k. n.k. n.k. 115 kV transmission: Lao PDR border – Stung Treng Cambodia n.k. n.k. n.k. n.k. n.k. 115 kV transmission: Ban Hat – Lao PDR border Lao PDR n.k. n.k. n.k. n.k. n.k. 115 kV transmission: Xeset – Saravan Lao PDR n.k. n.k. n.k. n.k. n.k. All the above projects are included in the Vientiane Plan of Action as Group 1 projects under Strategic Thrust III (see Section 6.1 for a description of these categories). Sources: World Bank and ADB (2008) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 51 ESMAP Briefing Note 004/10 | June 2010 Bibliography Bibliography Major documents and websites consulted in the preparation of this case study are listed below. These are organized as follows: ï?¯ Documents published by or prepared for the GMS Program. ï?¯ Documents published by or prepared for other international organizations. ï?¯ Documents published by or prepared for national governments and utilities and their staff, organized by country. ï?¯ Other documents. ï?¯ Websites consulted. Where documents are publicly available on websites, a link is provided in parentheses following the document listing. Websites consulted on a single occasion are referenced at appropriate locations in the main text. GMS Program documents Policy Statement on Regional Power Trade in the Greater Mekong Subregion, January 2000 (http://www.adb.org/Documents/Others/GMS/Sector-Activities/Regional-Power-Trade- IGAandMOU.pdf - also contains the Inter-Governmental Agreement and MOU #1) Inter-Governmental Agreement on Regional Power Trade in the Greater Mekong Subregion, 3 November 2003, Phnom Penh (http://www.adb.org/Documents/Others/GMS/Sector- Activities/Regional-Power-Trade-IGAandMOU.pdf - also contains the Policy Statement and MOU #1) Memorandum of Understanding on the Conditions for the Implementation of the RPTOA – Stage #1, 5 July 2005, Kunming (http://www.adb.org/Documents/Others/GMS/Sector- Activities/Regional-Power-Trade-IGAandMOU.pdf - also contains the Policy Statement and Inter-Governmental Agreement) Memorandum of Understanding on the Road Map for Implementing the Greater Mekong Subregion Cross-Border Power Trading, 31 March 2008, Vientiane (http://www.adb.org/Documents/Events/Mekong/Proceedings/FG6-Appendix3.pdf) Vientiane Plan of Action for GMS Development 2008-2012, March 2008, Vientiane (http://www.adb.org/Documents/Events/2008/3rd-GMS-Summit/POA-Vientiane2008- 2012.pdf) Electric Power Forum Terms of Reference (http://www.adb.org/Documents/Others/GMS/Sector-Activities/TOR-Energy.pdf) Regional Power Trade Coordinating Committee Terms of Reference (http://www.adb.org/Documents/Others/GMS/Sector-Activities/TOR-RPTCC.pdf) Soluziona & Mercados (2008, February): Long-Run Indicative Master Plan for the GMS Region: Final Report. Report prepared for the Asian Development Bank. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 52 ESMAP Briefing Note 004/10 | June 2010 Bibliography Soluziona & Mercados (2008, October ): Regional Performance Standards: Final Report. Report prepared for the Asian Development Bank. Other international organizations documents Asian Development Bank (ADB) ADB (2008, September): Regional Cooperation Operations Business Plan: Greater Mekong Subregion 2009-11 (http://www.adb.org/Documents/CPSs/GMS/2008/RCOBP-GMS-2009- 2011.pdf) ADB (2009, June): Building a Sustainable Energy Future: The Greater Mekong Subregion (http://www.adb.org/Documents/Books/GMS-Sustainable-Energy-Future/GMS- Sustainable-Energy-Future.pdf) Baardsen, E. (2008): “Power Interconnection in the GMS Region.â€? ASIA 2008, 9 March 2008, Da Nang (http://www.adb.org/Documents/Presentations/VRM/GMS-Presentation-Asia- 2008.pdf) Association of South-East Asian Nations (ASEAN) Heads of ASEAN Power Utilities / Authorities (HAPUA) (2006, Otober): “HAPUA and the ASEAN Power Grid for Optimum Use of Energy Resources.â€? Regional Energy Policy and Planning in ASEAN for Sustainable Development. Bangkok, Thailand. 10-11 October 2006. (http://www.asean-sustainable- energy.net/documents/libraries/001/HAPUASecretary%20akhir%20Bangkok%206-10- 06.pdf) Energy Sector Management Assistance Program (ESMAP) ESMAP (2001): Development of a Regional Power Market in the Greater Mekong Subregion. ESMAP Technical Paper 015 (http://www.esmap.org/filez/pubs/86200760022_GMS23874.pdf) ESMAP (2006): Options for the Structure of the GMS Power Trade Market: A First Overview of Issues and Possible Options. ESMAP Technical Paper 108/06 (http://www.esmap.org/filez/pubs/4162007110526_GreaterMekongOptions.pdf) Greater Mekong Subregion Environment Operations Center (GMS EOC) Lefevre T. 2009. “ADB GMS RETA 6440: Project Status and Potential Links with GMS EOC and MRCâ€?. WGE 15th Annual Meeting. Bangkok, Thailand. 2-3 July 2009 (http://www.gms- eoc.org/WGE/Meeting/docs/15-AM-WGE/RETA6440_PotentialLinkages.pdf) Stockholm Environment Institute (2008, July): Strategic Environment Assessment for Hydropower in Vietnam: Policy Summary. Report prepared for Ministry of Industry and Trade and Asian Development Bank (http://www.gms- eoc.org/CEP/Comp1/docs/Vietnam/Hydropower/PolicySummary.pdf) International Monetary Fund (IMF) World Economic Outlook (2009, April):(http://www.imf.org/external/pubs/ft/weo/2009/01/index.htm) Mekong River Commission (MRC) Agreement on the Cooperation for the Sustainable Development of the Mekong River Basin (1995, 5 April): (http://www.mrcmekong.org/agreement_95/agreement_95.htm) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 53 ESMAP Briefing Note 004/10 | June 2010 Bibliography Procedures for Notification, Prior Consultation and Agreement (2003, 30 November): Phnom Penh (http://www.mrcmekong.org/download/programmes/PNPCA.pdf) Procedures for the Maintenance of Flows on the Mainstream (2006, 22 June): Ho Chi Minh City (http://www.mrcmekong.org/download/programmes/FlowsProcedure.pdf) Soussan, J. (2009, June): Phase 1: Background Scoping Paper for a Strategic Environmental Assessment of Proposed Hydropower Developments on the Mekong Mainstream in the Lower Mekong Basin (http://www.mrcmekong.org/ish/SEA_Phase_1_Paper_Final.pdf) United Nations Framework Convention on Climate Change (UNFCCC) Cambodia – Rural Electrification and Transmission Project (RETP) – 220 kV Interconnection between Cambodia and Vietnam, Project Design Document (http://cdm.unfccc.int/UserManagement/FileStorage/L8AHLLI9H94AMYZYARZ64E4XJ3 SLL7) World Bank World Bank (2003, November): Cambodia Rural Electrification and Transmission Project: Project Appraisal Document. Report No. 27015-KH (http://web.worldbank.org/external/projects/main?menuPK=51447259&pagePK=5135100 7&piPK=64675967&theSitePK=40941&menuPK=64187510&searchMenuPK=51351213&theSi tePK=40941&entityID=000012009_20031126114127&searchMenuPK=51351213&theSitePK=4 0941) World Bank. n.k. Greater Mekong Subregion Electricity Market Project (http://siteresources.worldbank.org/INTTHAILAND/Resources/333200- 1211794042917/5033487-1211794196043/gms-regional-power-trade-program.pdf) National documents Cambodia Electricity Authority of Cambodia (2008): Report on Power Sector for the Kingdom of Cambodia for the Year 2007 (http://www.eac.gov.kh/pdf/reports/Report%20On%20Power%20Sector%20For%20The% 20Year%202007.en.pdf) Ministry of Industry, Mines and Energy (2008): “Cambodian Power Development Plans.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5-Appendix4.1.pdf) Wasizawa, T. (2009): Overview on Power Sectors in Cambodia. Report prepared for MIME and JICA. China Berrah, N. (2009, July): Reforming China’s Power Sector: In the Middle of the River (http://scid.stanford.edu/publicationsprofile/1991) China Southern Power Grid Co Ltd. (2008): “Update for CSG Grid Planning and International Cooperation Projects.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5- Appendix4.2.pdf) Lao PDR Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 54 ESMAP Briefing Note 004/10 | June 2010 Bibliography Unknown (2008): “Lao PDR.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5- Appendix4.3.pdf) Department of Energy Promotion and Development. May (2009, May) Power Projects in Lao PDR (http://www.poweringprogress.com/download/Electric%20Power%20Plants%20in%20La os%20%20as%20of%20May%202008.pdf) Maunsell and Lahmeyer International (2004, August): Power System Development Plan: Final Report (http://www.poweringprogress.com/index.php?option=com_jotloader&cid=11&Itemid=97 ) Somvichith, S. (2008): “Hydro Power in Lao PDR and Power Development Plan.â€? Executive Seminar on EDL and Laos Hydro Power Development. Vientiane, 21 November 2008 (http://www.edl- laos.com/download/Presentation%20to%20EDL%20executive%20seminar%20(21- Nov%202008)-Sanhya.ppt) Myanmar Unknown (2007): “Country Report of Myanmar.â€? Franco-ASEAN Seminar on Power ASEAN: Technology and Policy Options. Bangkok, 6-7 September 2007 (http://www.burmalibrary.org/docs2/MMpresentation.pdf) Unknown (2008): “Country Report on Progress of Power Development Plans and Transmission Interconnection Projects: Myanmar.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5-Appendix4.4.pdf) Wolf, A., and J. Newton (2007): Case Study of Transboundary Dispute Resolution: Salween River (http://www.transboundarywaters.orst.edu/research/case_studies/Documents/salween.p df) Thailand EGAT (2007a): Power System Control and Operation. EGAT (2007b): Thailand Power Development Plan. Approved by Cabinet, 19 June 2007. EGAT (2008): “Updated Status of Thailand Power System.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5-Appendix4.5.pdf) Energy Regulatory Commission (2009): Thailand Regulatory Developments 2009 (http://www.erc.or.th/Doc/thailand.pdf) Energy Industry Act 2007 (http://www.erc.or.th/Doc/Energy%20Industry%20Act%202007%20-%20actual%20- %20En.pdf) PricewaterhouseCoopers (2000, January): Review of Electric Power Tariffs. Report prepared for the Energy Policy and Planning Office (http://www.pea.co.th/th/eng/page.php?name=ElectricityTariffs) Provincial Electricity Authority tariffs (http://www.pea.co.th/th/eng/page.php?name=ElectricityTariffs) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 55 ESMAP Briefing Note 004/10 | June 2010 Bibliography Vietnam Establishment and Stipulation of Functions, Duties, Authorities and Organization of the Electricity Regulatory Authority under the Ministry of Industry, Decision of the Prime Minister No. 258/2005/QÄ?-TTg dated 19 October 2005. Approval of the Roadmap, the Conditions to Establish and Develop the Levels of the Power Market in Vietnam, Decision of the Prime Minister No. 26/2006/QÄ?-TTg dated 26 January 2006. Master Plan for National Power Development for 2006-15 with a Perspective to 2025 (Master Plan VI), Decision of the Prime Minister No. 110/2007/QÄ?-TTg dated 18 July 2007. Tariffs for 2009 and Market Tariff Mechanism for 2010-2012, Decision of the Prime Minister No. 21/2009/QÄ?-TTg dated 12 February 2009. Economic Consulting Associates (2006, October): Bulk Power, Distribution Margin, Retail Tariff Design and Development of an Independent Creditors Model: Final Report. Report prepared for Electricity of Vietnam and World Bank. Electricity Regulatory Authority of Vietnam (2007, June): Vietnam Power System. Internal presentation. Institute of Energy (2008): “Progress of Vietnam Power Development and Interconnection Projects.â€? Fifth Meeting of the Planning Working Group (PWG-5). Vientiane, 17 June 2008 (www.adb.org/Documents/Events/Mekong/Proceedings/PWG5-Appendix4.6.pdf) PB Associates (2009, February): Analysis and Implementation of Water Valuation in Vietnam: Interim Report. Report prepared for the National Load Dispatch Center and World Bank. Trung, N. Q. (2008): Introduction to the Electric Power System of Vietnam. Presentation by National Load Dispatch Center. Other documents Garrett, B. (2004): Comments on Indicative Master Plan on Power Interconnection in GMS Countries (http://palangthai.org/docs/CommentsADBMasterPlanGMSPowerGrid.pdf) Garrett, B. (2005): Comments on Study for a Regional Power Trade Operating Agreement in the Greater Mekong Subregion (http://www.palangthai.org/docs/CommentsRPTOA.pdf) Major websites Asian Development Bank: http://www.adb.org Asian Development Bank– Greater Mekong Subregion: http://www.adb.org/gms/ China Southern Grid Power Company Limited: http://eng.csg.cn/ Department of Energy Promotion and Development (Lao PDR): http://www.poweringprogress.com/ Electricité du Cambodge (EDC): http://www.edc.com.kh/ Electricité du Laos (EDL): http://www.edl-laos.com/ Electricity Authority of Cambodia (EAC): http://www.eac.gov.kh/ Electricity Generating Authority of Thailand (EGAT): http://www.egat.co.th/ Electricity of Vietnam (EVN): http://www.evn.com.vn/ Energy Regulatory Commission (ERC, Thailand): http://www.erc.or.th/ Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 56 ESMAP Briefing Note 004/10 | June 2010 Bibliography GMS Environment Operations Center: http://www.gms-eoc.org/ Mekong River Commission: http://www.mrcmekong.org/ World Bank: http://www.worldbank.org Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 57 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets A1 National power markets A1.1 Cambodia Existing market The electricity industry in Cambodia is small and electrification levels are very low, at around 16% to 20%. There are two existing isolated 115 kV transmission systems—one around the capital, Phnom Penh, and the other in the northwest connecting Bantey Meanchay, Siem Reap and Battambang. Elsewhere, supply is in the form of isolated MV systems around the main provincial towns, notably Siem Reap, border areas and along the main national roads and individual isolated mini-grids. The government has set targets of electrifying 100% of villages by 2020, including through battery charging stations, and of providing grid-quality electricity supplies to 70% of households by 2030. Demand has grown quickly in recent years, along with the rapid expansion of Cambodia’s economy. Capacity on the Phnom Penh system, at 188 MW, is already inadequate to meet unconstrained peak demand, which was estimated at 206 MW in 2007. The dominant entity is Electricité du Cambodge (EDC), the state-owned vertically integrated electricity utility which supplies Phnom Penh and major provincial towns. In 2007, EDC supplied 1,221 GWh to 286,660 customers, accounting for 90%of total national sales and 70% of total national customer numbers. Elsewhere, supply is by a large number of rural electricity enterprises (REEs), some of which are connected to MV grids and others which operate isolated mini-grids using diesel generators. The REEs vary greatly in size, with the largest isolated system having sales of 3,04 MWh in 2007 to 1,241 customers. By contrast, the smallest had sales of just 3.2 MWh in 2007 serving 240 customers. The largest grid-connected system had annual sales of 31,532 MWh and served 6,300 customers—still far below those of EDC. The vast majority of electricity supplied in Cambodia is generated from fuel oil and diesel plants. There is a small amount of hydro generation and, in the northwestern grid and in border areas, imports from Thailand and Vietnam (in 2007 totalling around 155 GWh or 10% of total national energy generated and imported). EDC has some generating capacity and also relies heavily on purchases from independent power producers (IPPs). The various REEs in most cases generate their own supplies but, in some cases, purchase from EDC, IPPs or imports. Electricity tariffs are not uniform and are very high in Cambodia by international standards, due to the dependence on oil-fired generation. To this are added the high unit costs resulting from the small and dispersed loads in rural areas. Tariffs vary greatly between the Phnom Penh system, other urban areas and rural areas. The vast majority of REEs charge tariffs of 2,000 Riels/kWh (approximately 50 USc/kWh) or above. The primary legislation governing the electricity industry is the Electricity Law 2001. This establishes the Electricity Authority of Cambodia (EAC) as the regulatory body for the Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 58 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets industry and creates a licensing framework under which all power suppliers are required to hold a license issued by EAC. The law also gives EAC power to regulate tariffs and technical and performance standards of licensees. The Ministry of Industry, Mines and Energy (MIME) is identified as the entity responsible for setting and administrating policies, strategies and planning in the power sector. A substantial amount of secondary legislation has been issued detailing various aspects of the Law. Much of this is available from EAC’s website (www.eac.gov.kh). Other than state-owned licensees, no licensee may own more than one licence or have a direct financing interest in another licensee. Future developments The major ongoing development in the Cambodian electricity industry is the development of a national transmission network. Initially this is taking the form of a number of HV transmission lines connecting to neighboring countries of Vietnam and Thailand, followed later by cross-border connections to Lao PDR. This will allow the import of lower-priced power to the northwestern grid and a new southern grid. Over time, these lines are expected to be extended to create a single interconnected national grid. The major interconnectors in operation or under development are as follows: ï?¯ The 115 kV northwestern grid of 203 km in length connecting Thailand to Bantey Meanchay, Siem Reap and Battambang. This entered service in 2007. The line was financed and is operated by Cambodia Power Transmission Co Ltd (CPTL) under a 30-year BOT agreement with EDC. The import capacity is 80 MW. ï?¯ A new 230 kV line of 110 km connecting Vietnam to Takeo and Phnom Penh. This line is expected to commission shortly. The import capacity is 220 MW. The line will be extended to Kampot and Sihanoukville in 2010 and 2011, respectively. ï?¯ A new 110 kV25 line of 68 km connecting Vietnam to Kampong Cham, due to commission in 2010. The import capacity is 20 MW. ï?¯ A new 115 kV line of 56 km connecting southern Lao PDR to Stung Treng, due to commission in 2010. The import capacity is 20 MW. Figure 10 shows the various existing and planned lines. 25 This is a nonstandard transmission voltage in Cambodia and will require interface transformers. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 59 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Figure 10 Cambodia Transmission Grid Source: Wasizawa (2009) The other major development in the industry is the introduction of new hydro and coal-fired IPPs, initially allowing the replacement of existing oil-fired IPPs and, in time, allowing Cambodia to move from an importer of electricity to an exporter. Motivation for power trade Cambodia’s immediate motivation for engaging in power trade is to obtain supplies to border regions currently not served and to obtain power supplies for the Phnom Penh region at lower costs than the existing fuel oil–fired IPPs. Existing and planned interconnectors are related to these requirements. However, in the longer term there is potential for Cambodia to become a significant exporter to Thailand and possibly Vietnam. As well as hydro projects, this might include export projects using offshore gas from recently discovered reserves and imported coal (in part as a means of bypassing the limitations on developing large-scale coal projects in Thailand). A1.2 China (Yunnan and Guangxi) Existing market China’s electricity market is both massive in size and highly complex in organization. The Chinese members of the GMS, Yunnan province and Guangxi autonomous region, are two of five provinces served by the transmission network owned and operated by the central Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 60 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets government-owned China Southern Power Grid Co Ltd (CSG), which also covers Guangdong, Guizhou and Hainan provinces. CSG was formed in 2002 as part of the reorganization of the former State Power Corporation (SPC), which itself had been established in 1997 following the abolition of the former Ministry of Electric Power, which had been both policymaker and the main utility in the power sector. Also formed at the same time were the State Grid Corporation, which owns and operates the transmission network in provinces outside the region served by CSG, and five state-owned generating companies. While these five ex-SPC generating companies remain the largest generators in China, their combined capacity accounts for only 40% of the country total. The remainder is owned by a mix of central and provincial government- owned generating companies and by state and private enterprises. CSG is structured into the Extra High Voltage power transmission company, which operates inter-province lines, five provincial transmission companies, a power generating company (with 4.3 GW of mainly pumped storage capacity), a power exchange, a load dispatch center and various other affiliated and subsidiary companies. Its total service area is around 1 million km2, supplying 33.3 million customers in a region with 230 million inhabitants. Total sales in 2008 were 483 TWh and the region’s installed capacity was 140 GW. The Yunnan provincial transmission company alone supplies 1.4 million customers, with a network at 110 kV and above of 25,500 km. The Guangxi transmission company supplies 1.75 million customers with a network of 17,800 km. It remains a feature in much of China that provinces are relatively weakly interconnected, and provincial markets are to some extent autonomous—although this is changing with the ongoing West-East Transmission Project, of which the Southern Corridor is contained in CSG’s service area. Currently, the transmission corridor contains twelve 500 kV lines (eight AC and four DC), with a total transmission capacity of over 18 GW. These are used to transmit power from Yunnan, Ghuizhou and Guangxi provinces and regions to Guangdong province. In 2007, Yunnan province had an installed capacity of 22.2 GW (around 17% of the total within CSG’s area in that year) relative to a peak demand of 11.4 GW. Total generation was around 90 TWh or 16% of the regional total while consumption was around 75 TWh or 13% of the regional total. The difference was largely exported to Guangdong. Guangxi autonomous region had an installed capacity of 19.8 GW (15% of the CSG total), a peak demand of 11.5 GW, total generation of 68 TWh and total consumption of a similar level. CSG’s grid is interconnected with that of Vietnam at both 220 kV and 110 kV. There are also 11 interconnectors to the Hong Kong grid and three with the Macau grid. During 2007, CSG exported 2.8 TWh to Vietnam, 4.0 TWh to Hong Kong and 1.7 TWh to Macau. Outside China, CSG is represented by its wholly owned subsidiary, CSG International. Currently, within the GMS region, in addition to its power exports to Vietnam, CSG is developing the Vinh Tan 1 coal plant in Vietnam, the Nam Tha I hydro project in Lao PDR, the Sambor hydro project in Cambodia and 10 hydro projects along the Thalwan river in Myanmar. Although a national regulatory agency, the State Electricity Regulatory Commission (SERC), was established in 2003, power sector regulation continues to largely be undertaken by the central government through the National Development and Reform Commission (NDRC). It Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 61 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets is NDRC that takes decisions on electricity tariffs (although SERC can make proposals), power planning and project approvals. However, in practice, it can be difficult for NDRC to enforce decisions where provincial governments are opposed to these. Motivation for power trade China’s interest in energy trade appears to derive from a combination of import and export opportunities, including the potential for Chinese firms to develop projects in GMS countries for the regional market. Chinese firms are active in project development in Cambodia, Lao PDR, Myanmar and Vietnam—although not all of these are directed at exports to the regional market. A1.3 Lao PDR Existing market The main electricity utility in Lao PDR is Electricité du Laos (EDL), the state-owned vertically integrated generation, transmission and distribution utility. However, the majority of generating capacity in the country is owned by two IPPs, the Theun Hinboun and Houay Ho hydro projects, with a combined capacity of 360 MW as compared to the 309 MW of hydro capacity owned by EDL and small amounts of capacity owned by provincial governments. EDL is a partner in both IPPs, owning 60% of the Theun Hinboun project and 20% of the Houay Ho project. The Theun Hinboun and Houay Ho projects are primarily intended for export to Thailand. The 1,088 MW Nam Theun 2 hydro IPP is due to commission during 2009 and, of its capacity, 75 MW will be made available to EDL. Currently, there is no national grid in Lao PDR. A small number of 230 kV lines exist for export from IPPs. The northern-central area extending out from Vientiane is served by a 115 kV grid supplied from EDL-owned generation and imports from Thailand, and accounts for around 60% of total national electricity sales of 1,300 GWh. Three small isolated grids in the southern-central and the southern regions are supplied by imports from Thailand at 115 kV, and there are also a number of MV interconnections with Thailand (Figure 11). Electricity coverage is growing rapidly, with household electrification rates increasing from 43% in 2003 to 59% by 2007 with 40% of villages connected to electricity supplies. The government has set targets to achieve 70% household electrification by 2010 and 90% by 2020, largely by expansion of the 115 kV grid. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 62 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Figure 11 Lao PDR Transmission Grid EXISTING POWER PLANTS AND TRANSMISSIONS Source: Somvichith (2008) Future developments Alongside the electrification program, there are plans to establish a national transmission grid in Lao PDR. This would be achieved by interconnecting existing and new EDL-owned lines with transmission lines developed for export projects and, potentially, with interconnectors developed to allow trade between China, Thailand and Vietnam via Lao PDR. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 63 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets A major expansion of generating capacity is also planned. EDL is planning to develop a total capacity of 324 MW in the form of hydro generation projects with a further 882 MW to be developed as IPPs for the domestic market and 548 MW to be made available as EDL’s share in the capacity of new export projects. Motivation for power trade The government of Lao PDR views export hydro projects as a major source of social and economic development, particularly given the limited industrial potential of the country. Export hydro projects provide a means of earning revenues and of developing electricity capacity to meet domestic needs. The government has been very active in promoting export projects, opening up the power sector to private and foreign investment in 1993 and with the first IPP commissioning in 1998. A1.4 Myanmar Existing market The Ministry of Electric Power (MEP) was established in 1997 as policymaker and owner for the power sector. In May 2006, the ministry was separated into two entities: ï?¯ Ministry of Electric Power (1), responsible for planning, construction and operation of hydro power projects as well as Myanmar’s existing coal plant. ï?¯ Ministry of Electric Power (2), responsible for transmission system planning, investment and operation, distribution and supply of electricity purchased from MEP (1) and operation of existing gas, oil and diesel-fired generating plants. Larger hydro power projects are being developed on an IPP basis in partnerships between MEP (1) and Chinese and Thai companies. The Ministry of Agriculture and Irrigation is also involved in one of the smaller projects under development. There is no separate regulatory agency. Figure 12 shows the existing transmission grid. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 64 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Figure 12 Myanmar Transmission Grid Source: Presentation at PWG-5 (2008) Future developments Myanmar has ambitious plans for the expansion of its hydro generating capacity to meet domestic demand and for export. The latter are discussed later in this case study. A total of 14 hydro projects with a combined capacity of 10,772 MW are identified as under implementation with another 13 with a combined capacity of 23,645 MW identified for implementation in the near future. Of these, 12 projects totalling 23,930 MW have agreements in some form with foreign investors, including Yunnan Power Development and CPI, both of China, and MDX Group and EGAT of Thailand. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 65 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Alongside this, there are plans for major expansion of the existing 230 kV transmission network. This is currently 918 miles in length, with an additional 995 miles under construction and plans for a further 3,265 miles of line. Future plans also include the development of a 500 kV grid of 1,795 miles in length. Motivation for power trade Similar to Lao PDR, the driving motivation for power trade in Myanmar appears to be the potential for export earning. Myanmar has large unexploited hydro resources which are proving of interest to Chinese and Thai developers. A1.5 Thailand Existing market The Thai power sector has three main state-owned entities: ï?¯ The Electricity Generating Authority of Thailand (EGAT), which undertakes generation and owns and operates the national transmission grid. ï?¯ The Metropolitan Electricity Authority (MEA), which undertakes distribution and supply in Bangkok and surrounding provinces. ï?¯ The Provincial Electricity Authority (PEA), which undertakes distribution and supply in the remainder of Thailand. There are also a number of IPPs, small power producers (SPPs) and very small power producers (VSPPs). The latter two are smaller IPPs which meet specific requirements for technology and fuel (renewable energy sources or combined heat and power producers). These are entitled to standard contract arrangements and premiums above the standard feed-in tariff paid by EGAT. Previously they were accepted on a must-take basis, but recently accepted projects have been limited to those using renewable energy. Larger IPPs have been procured through two competitive tendering rounds, the first in the mid-1990s and a second, for 4,400 MW of capacity, completed in December 2007 with projects commissioning in 2011–2013. EGAT operates as a single buyer, purchasing all output from IPPs and SPPs and onselling this, together with output from its own generators, to MEA and PEA at a bulk supply tariff. Output from VSPPs is purchased by MEA and PEA. As of early 2009, there were 28 licensed generators owned by EGAT, two generators previously owned by EGAT but which were partially privatized, seven IPPs, 60 SPPs and 118 VSPPs. The mix of each licensee type in power generation in 2007 and planned for 2021 is shown in Table 8. Table 8 Thailand Power Generation by Licensee Type Licensee Type Share (2007 actual) Share (2021 planned) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 66 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Licensee Type Share (2007 actual) Share (2021 planned) EGAT 45% 39% IPP 42% 20% SPP 10% 7% VSPP <1% 2% Import 3% 17% Source: Energy Regulatory Commission (2009) An Energy Regulatory Commission (ERC) was established under the Energy Industry Act of 2007. The ERC is responsible for licensing, reviewing power development plans, approving technical codes and setting tariffs in conformity with tariff policies set by the National Energy Policy Council and the Cabinet. Thailand follows a policy of a uniform national tariff. Since the costs of electricity provision of PEA are much higher than those of MEA, lump sum financial transfers are made from MEA to PEA to subsidize rural electrification. This subsidy amounted to around 10 billion baht (or around US$315 million) in 2008. In 2009, the subsidy arrangements were changed to also require EGAT to transfer US$81 million to PEA given EGAT’s higher allowed financial return compared to that of MEA and PEA. New subsidy arrangements are expected to be implemented through a Power Development Fund financed by an industry levy from 2010. These will take the form of payments for delivery of defined Public Service Obligations (PSO). Currently power purchased from neighboring countries amounts to 640 MW, which accounts for just over 2% of demand. In the northeast, Thailand has five lines already supplying power from Lao PDR, with a further two lines under construction and four more planned for the future. In the south, two lines are operating between Malaysia and Thailand. At MV level, additional interconnectors exist between Thailand and Cambodia and Lao PDR. The grid is shown in Figure 13. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 67 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Figure 13 Thailand Transmission Grid Source: EGAT (2007b) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 68 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Future developments During the 1990s, Thailand investigated the possibility of introducing a power pool. Concerns over security of supply, particularly following the 2001 California problems, led to the rejection of this option and a cabinet-level decision that an enhanced single-buyer model would be adopted as the future industry structure. Under this, EGAT will continue as a generator, transmission system owner and the single buyer but will establish an independent system operator function (although ownership would remain with EGAT). During the run-up to the second IPP round, there was discussion as to whether EGAT’s share of new generation capacity should be limited in order to promote private investment. In practice, EGAT seems likely to continue to dominate generation in the future with limits on its share of future capacity being rejected (under current plans, its share of total generation in Thailand will remain steady at around 45%, although its share in overall supply will fall due to rising imports). An attempt to corporatize and partially privatize EGAT during 2005 and 2006 met heavy political opposition and was eventually ruled illegal by the courts due to a failure to fully comply with legal requirements for corporatization of state enterprises. Subsequently, privatization of EGAT and other state-owned energy enterprises appears to have been abandoned. Overall, therefore, little change in the existing industry and market structure is expected in the short to medium term. Motivation for power trade The original motivation at the national level for the development of power trade within the GMS was Thailand’s rapid demand growth in the 1990s alongside its economic growth. During this period, Thailand was concerned about securing access to low-cost energy supplies. Environmental opposition effectively ruled out further large-scale hydro expansion within Thailand,26 making imports of power from hydro projects located in Lao PDR, Myanmar and Yunnan especially attractive. A summary of the various intergovernmental Memoranda of Understanding (MOUs) entered into by Thailand for power import from GMS countries during the 1990s is provided in Box 1. Following the Asian financial crisis of 1997, Thailand’s economic growth and energy demand growth have slowed markedly. Despite this, Thailand has continued to remain committed to large-scale future imports. This appears to be partly due to the cost advantages of hydro imports and partly due to a desire to diversify away from the current dependence on natural gas for power generation. Domestic opportunities for such diversification are very limited—large-scale hydro development and increased coal-fired 26 The last major dam built in Thailand was the 136 MW Pak Mun project completed by EGAT in 1994. This project has been widely criticized as having severe negative impacts on local fisheries and requiring large-scale resettlement for little benefit in terms of electricity generated (output has averaged only around 290 GWh, although EGAT has argued the plant was always supposed to operate as peaking capacity). Protests by affected villagers spread to Bangkok and have led to interventions at the cabinet level both to order EGAT to open the dam gates to restore fisheries and to close them as governments have changed. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 69 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets generation face very strong opposition on environmental grounds. Nuclear generation is now being planned but also seems likely to face strong opposition domestically. Box 1 Thailand's Power Import MOUs Lao PDR Thailand signed its first MOU with Lao PDR in 1993 for the import of 1,500 MW of power by 2000. In 1996 a second MOU was signed for the import of a total of 3,000 MW by 2006. A third MOU was signed in 2006, which increased the purchase amount to 5,000 MW by 2015. In December 2007, the quantity to be purchased was further increased to 7,000 MW by 2020, including the Hong Sa lignite-fired project. Further amendments to these MOUs mean that currently Thailand is committed to purchasing 1,500 MW by 2010, 7,000 MW by 2015 and 10,000 MW by 2017. To date, two hydro projects with a combined capacity of 340 MW are operating under the MOU with a further two, including Nam Theun 2, with a capacity of 1,535 MW, under construction and due to commission in 2009–2010. As part of recent revisions to the national Power Development Plan to accommodate reduced demand growth forecasts, Thailand intends to postpone the planned date of a number of future import projects by one to two years. However, no cancellations are proposed. This is in line with the experience of the slowdown in Thai demand post-1997 when projects were postponed but not cancelled. Myanmar An initial MOU was signed in July 1997 for the purchase of 1,500 MW of hydro capacity by 2010. In May 2005, a new MOU was signed for the development of five hydro power projects on the Salween River for which the Myanmar government proposed two initial projects with a combined capacity of 8,200 MW. There appears to be some ambivalence in the Thai government’s attitude toward this MOU. In June 2007 the energy minister in the then military-installed government, Dr Piyasavasti Amarand, was reported to have said that Thailand was not looking to buy any power from Myanmar.27 In part this appears to have been a response to concerns that the MOU resulted from what were seen as excessively close links between the former prime minister, Thaksin Shinawatra, and the Myanmar government. However, in March 2009, EGAT was hopeful of shortly signing an MOU for the Hutgyi project on the Salween River, one of the plants covered under the second intergovernmental MOU.28 China In 1998, Thailand signed an MOU with China for the import of 3,000 MW by 2017. Imports would be by interconnectors passing through Lao PDR, making it necessary to agree to transit payments to be made to Lao PDR. At present, no agreement has been reached on these payments, and progress on developing export projects under the MOU remains stalled. 27 http://www.bernama.com/bernama/v3/news_lite.php?id=266639 (accessed 7 May 2009) 28 http://www.nationmultimedia.com/search/read.php?newsid=30098476&keyword=burma+hydro+mou (accessed 7 May 2009) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 70 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets A1.6 Vietnam Existing market Economic development in Vietnam has driven strong growth in electricity demand, with the system barely being able to keep pace. Since 1990, power generation increased about fourfold from 17.7 TWh in 1998 to 65.9 TWh in 2008. See Figure 14. Vietnam’s power sector is currently dominated by Electricity of Vietnam (EVN). EVN was established following completion of the first 500 kV interconnector between North, Central and South Vietnam, allowing integrated operation of a national grid. At its establishment, EVN absorbed the existing generation, transmission and distribution assets of the three regional power companies (PCs) to form a national vertically integrated monopoly utility. In recent years, EVN and the sector structure have undergone a series of reforms. New generators have entered in the form of IPPs developed by other state-owned entities29 and private investors. EVN has also been carrying out a process of equitizing many of its own generators. This involves the establishment of these generators as independent legal entities and the subsequent sale of minority shareholdings through IPOs and to employees with EVN retaining a majority stake. With the recent sharp fall in Vietnam’s stock markets, the equitization process is effectively on hold at present. EVN directly and through its equitized subsidiaries currently owns around 70% of installed generating capacity, other state entities own around 16.4% in the form of IPPs, and foreign- invested build-operate-transfer (BOT) projects own around 13.2%. EVN itself has been corporatized and transformed into a holding entity for a large number of subsidiaries. In addition to its generating subsidiaries, these include the new National Power Transmission Corporation (NPTC), which operates the high-voltage 500 kV and 220 kV transmission network and the National Load Dispatch Center (NLDC), which schedules and dispatches the high-voltage transmission network and generators greater than 30 MW. A new single buyer unit has also been established within EVN—allowing it to take advantage of EVN’s government backing. Operation of the low-voltage transmission network and distribution is undertaken by 11 power companies (PCs). These include the historic three regional PCs, which now largely serve rural areas, as well as an additional eight PCs serving major urban centers. All but one are wholly owned by EVN. The exception is Khanh Hoa Joint Stock Power Company, which has been equitized but in which EVN remains the largest shareholder. The power sector is facing severe challenges in meeting investment needs resulting from the rapid demand growth. Lack of funds has led to many projects being delayed by up to three years. Installed capacity has been growing more slowly than demand, leading to a narrowing reserve margin. While the 2008 reserve margin remained close to 20%, this is insufficient in a hydro-dependent system with wide seasonal fluctuations in output. Load 29 These include Vietnam Coal and Minerals Corporation (Vinacomin), Petro Vietnam (PVN), Lilama (the state- owned manufacturer of generating equipment and other heavy machinery) and the Song Da Construction Corporation (the main hydro power plant construction firm). Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 71 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets shedding has been experienced since 2004 and became very significant in 2008 when drier- than-normal conditions were experienced. To meet the urgent investment requirements, Vietnam is pursuing a strategy of gradual opening of the power market to external investors, accompanied by measures to facilitate private investment. Central to the strategy is the Electricity Law, which came into effect on 1 July 2005. The Electricity Law establishes a new framework for the power sector, comprising: ï?¯ A continuing mandatory central planning process at national and provincial levels for the purposes of identifying new investments. ï?¯ The introduction of a competitive generation market and its gradual extension to wholesale and retail competition. ï?¯ The establishment of a new regulatory agency, the Electricity Regulatory Authority of Vietnam (ERAV), under the Ministry of Trade and Industry (MOIT). Under Prime Minister Decision #26/2006/QÄ?-TTg, a road map for the introduction of the competitive power market has been approved. A three-phase process is envisaged, in each case split into a pilot and full step: ï?¯ Phase 1 (2005–2014): Competitive Generation Market (CGM). This initially comprises an internal power pool within EVN followed by establishment of the full market from 2010. All power will be sold to a single buyer who will onsell to PCs which retain their regional monopolies. ï?¯ Phase 2 (2015–2022): Wholesale Competitive Market. Selected large customers will initially be able to purchase directly from generators, with this right gradually being extended. ï?¯ Phase 3 (from 2024): Retail Competitive Market. Small customers in some provinces will be allowed to choose this supplier, with this right being subsequently extended to all customers. ERAV is responsible for overseeing the power planning process, approving the selection of developers of generation projects, licensing of electricity entities, overseeing implementation of the power market, proposing electricity retail tariffs for approval by the prime minister, and monitoring the competitive power market. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 72 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets Figure 14 Vietnam Transmission Grid CHIN A Thac Ba L ai Chau Vie t Tri So c Son So n L a PhLai Uong BiQuang N inh Chem a Ha Dong Mai Dong Hai Phong HOA BIN H T huong T in Din N hoh Quan Ninh Binh Thanh Hoa LAO P DR Vinh Ha T inh Nam Theun 2 THAILAND Dong Hoi 500kV Line (~2020) Quang T ri 500kV Line (~2010) 500kV Lines (existing) 220kV Lines (existing) Da N ang Sub. 500kV (- 2020) Sub. 500kV (- 2010) Substation 500kV exist. Ban So k Do c Soi Substation 220kV exist. Yaly HPPs exist. Vinh Son TPPs exist. P le i Ku Quy Nhon Sam Bo r CAMBODIA Krong Buk SongHinh D. N ai3&4 N ha T rang Di L inh Da Nhim Thac Mo T an Dinh Tri An Bao Loc Hoc Mon So ng May N uclear P P P hu L am N ho n Trach P hu My N ha Be O B Ria Cai Lay Mo Rach n TrNoc Gia a a Source: Electricity Regulatory Authority of Vietnam (2007) Future developments ERAV is leading the development and implementation of the full CGM, which will come into operation in 2010 in accordance with the approved road map. The general design Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 73 ESMAP Briefing Note 004/10 | June 2010 Annex: National power markets selected for the CGM is a cost-based power pool (CBP). Participation in the CBP will be mandatory for all generators with a capacity in excess of 30 MW except for existing foreign- invested BOTs, which hold long-term PPAs for their full capacity. To enable recovery of fixed costs, a capacity adder in the form of a Capacity Add-On payment will be paid during hours when the system is short of capacity. This payment will be calculated as the difference between the costs of a Best New Entrant generator and the revenues that this generator is projected to earn in the coming year from the CBP. Generators (other than foreign-invested BOTs) will also hold standard contracts for differences (CfDs) which provide greater revenue certainty for these generators and the single buyer. Alongside the introduction of the CGM, ERAV is leading a reform of existing electricity tariff regulation in order to create a market-oriented tariff system. Major changes to the existing tariff structure were introduced in February 2009 which increased average retail tariffs from March 2009 by 9% and sets out plans for gradual elimination of existing cross- subsidies from industrial and commercial to residential customers over a five- to six-year period. Current distinctions between urban and rural residential customer tariffs will also be removed and, from 2010, PCs will be allowed to negotiate tariffs below the regulated level with industrial and commercial customers, introducing an initial element of competitive pressure. Motivation for power trade Vietnam’s rapid economic growth since the introduction of the Doi Moi reforms in 1986 has seen the country’s electricity demand expand at double-digit rates. This has driven increasing interest in electricity imports—both to relieve short-term supply constraints, as with current imports from China, and as a means of providing access to long-term, low-cost power supplies, as in the various hydro projects under development in Lao PDR. Vietnam signed an intergovernmental MOU with Lao PDR in 1998 for the import of 2,000 MW of power. A number of project-specific MOUs have been signed. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 74 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply A2 Electricity supply Table 9 GMS Current and Planned Installed Capacity MW Coal Gas Oil Hydro Renewables Nuclear Total Cambodia 2007 actual - - 297 13 5 - 315 2020 planned 1,300 - - 1,955 5 - 3,230 China Guangxi 2007 11,113 - - 8,734 - - 19,847 actual Yunnan 2007 actual 9,858 - - 10,402 - - 20,260 2020 planned Not available Lao PDR 2007 actual - - 17 673 - - 690 2020 planned 1,800 - - 7,747 - - 9,547 Myanmar 2007 actual 120 726 70 803 - - 1,718 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 75 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply MW Coal Gas Oil Hydro Renewables Nuclear Total 2020 planned 120 726 70 11,539 - - 12,455 Thailand 2007 actual 4,117 14,594 4,735a 3,424 279 - 27,149 2020 planned 5,570 31,228 3,962a 3,424 2,140 2,000 48,324 Vietnam 2009 actual 2,980 6,139 814a 6,086 - - 16,019 2020 planned 18,350 16,151b - 17,195 1,717 2,000 55,413 a Capacity with dual oil/gas firing is shown as oil. b Includes a small amount of oil-fired capacity Sources: Compiled by ECA from country documents Cambodia Electricity Authority of Cambodia (2008), Ministry of Mines and Energy (2008) and Wasizawa (2009) China China Southern Power Grid (2008) Lao PDR Department of Energy Promotion and Development (2009) and Somvichith (2008) Myanmar Presentation at Franco-ASEAN Seminar (2007) and Presentation at PWG-5 (2008) Thailand EGAT (2007) and EGAT (2008) Vietnam Prime Minister Decision No. 110/2007/QD-TTg, Institute of Energy (2008), PB Associates (2009) and personal communication with the Electricity Regulatory Authority of Vietnam Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 76 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Table 10 Existing and Planned GMS Trade Projects Project Market Type Capacity Status Date Notes (MW) Cambodia Group 2 project under the Vientiane Lower Sesan 1 Vietnam? Hydro 90 n.k. 2012 Plan of Action Included in Vietnam MP (2014-15). Lower Sesan 2 + Vietnam Hydro 420 MOU for FS signed 2016 Group 3 project under the Vientiane Lower Srepok 2 Plan of Action (2014) MOU for pre-FS Sesan 3 Vietnam Hydro 375 2017 Included in Vietnam MP (2017) signed Sambor Vietnam? Hydro 2,600 MOU for FS signed 2019 Lower Srepok 3 Vietnam? Hydro 330 MOU for FS signed TBD Lower Srepok 4 Vietnam? Hydro 235 MOU for FS signed TBD Stung Treng Vietnam? Hydro 980 MOU for FS signed TBD Koh Kong Thailand Coal 3,600 Suspended? TBD China 110 kV Vietnam Interconnector 60 In service 2006 220 kV (Lao Cai) Vietnam Interconnector 250 In service 2006 220 kV (Ha Giang) Vietnam Interconnector 200 In service 2007 Group 1 project under the Vientiane Jinghong n.k. Hydro n.k. Under construction? 2009 Plan of Action (2009) 500 kV Vietnam Interconnector 700 FS underway 2017 Included in Vietnam MP (2017). Group 1 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 77 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) project under the Vientiane Plan of Action (2011) Included in Vietnam MP entering in 500 kV Vietnam Interconnector 700 FS underway 2018 2018 (earlier in Vientiane Plan of Action) Included in Vietnam MP entering in 500 kV Vietnam Interconnector 700 FS underway 2019 2019 (earlier in Vientiane Plan of Action) Lao PDR + Discussions Group 3 project under the Vientiane 500 kV Interconnector n.k. TBD Thailand suspended Plan of Action (2013) Lao PDR Lao PDR + Nam Ngum 1 Hydro 155 In service 1971 Not included in export totalsa Thailand Lao PDR + Se Xet 1 Hydro 45 In service 1990 Not included in export totalsa Thailand Lao PDR + Nam Leuk Hydro 60 In service 2000 Not included in export totalsa Thailand Lao PDR + Nam Mang 3 Hydro 40 In service 2004 Not included in export totalsa Thailand Lao PDR + Se Xet 2 Hydro 76 Under construction 2009 Not included in export totalsa Thailand Theun Hinboun Thailand Hydro 210 In service 1998 Houay Ho Thailand Hydro 150 In service 1999 Included in Thailand MP entering in Nam Theun 2 Thailand Hydro 1,088 Under construction 2009 2009 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 78 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) Included in Thailand MP entering in Nam Ngum 2 Thailand Hydro 615 Under construction 2013 2011 Ban Hat – Stung Group 1 project under the Vientiane Cambodia Interconnector 20 n.k. 2010 Treng Plan of Action (2011) Nabong – Udon Group 1 project under the Vientiane Thailand Interconnector n.k. n.k. 2010 Thani Plan of Action Group 3 project under the Vientiane Nam Mo – Ban Mai Vietnam Interconnector n.k. n.k. n.k. Plan of Action (2013) Included in Vietnam MP (2010). Group 1 Xekaman 3 Lao PDR + Vietnam Hydro 250 Under construction 2010 project under the Vientiane Plan of Action (2009) Included in Thailand MP entering in Nam Ngum 3 Thailand Hydro 440 Under construction 2014 2013. Group 1 project under the Vientiane Plan of Action (2013) Lao PDR + Under negotiation Included in Thailand MP starting in Hong Sa Coal 1,800 2015 Thailand (CA/PPA) 2013–2014 Included in Thailand MP (2014). Group Lao PDR + Under negotiation Nam Ngiep 1 Hydro 278 2015 3 project under the Vientiane Plan of Thailand (CA/PPA) Action (2014) Included in Thailand MP (2012). Group Theun Hinboun Lao PDR + Under negotiation Hydro 280 2012 3 project under the Vientiane Plan of expansion Thailand (CA) Action (2014) Included in Thailand MP (2014). Group Lao PDR + Under negotiation Nam Theun 1 Hydro 523 2014 3 project under the Vientiane Plan of Thailand (CA/PPA) Action (2013) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 79 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) Group 2 project under the Vientiane Xepian-Xemanmoy Thailand Hydro 390 MOU signed 2015 Plan of Action (2010) Included in Vietnam MP (2014). Group 3 Thailand or Xekong 4 Hydro 600 MOU signed TBD project under the Vientiane Plan of Vietnam Action (2012) Included in Vietnam MP (2016). Group 3 Thailand or Nam Kong 1 Hydro 150 MOU signed TBD project under the Vientiane Plan of Vietnam Action (2012) Included in Vietnam MP (2016). Group 3 Thailand or Xekong 5 Hydro 400 MOU signed TBD project under the Vientiane Plan of Vietnam Action (2013) Nam Bak 1 Thailand Hydro 80 MOU signed TBD Included in Thailand MP entering in 2013- Nam Ou China or Thailand Hydro 1,100 PDA signed 2014 / Included in Vietnam MP entering 16 in 2019 Don Sahong Thailand Hydro n.k. PDA signed 2015 Dak E Mule Vietnam Hydro 130 MOU signed TBD Xekaman 4 Vietnam Hydro 155 MOU signed TBD Lao PDR + Nam Ngiep 2 Hydro 155 Suspended? TBD Thailand Included in Vietnam MP (2012). Group 3 Nam Mo Vietnam Hydro 150 PDA signed 2014 project under the Vientiane Plan of Action (2013) Xekaman 1 Lao PDR + Vietnam Hydro 322 PDA signed 2013 Included in Vietnam MP (2013). Group 1 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 80 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) project under the Vientiane Plan of Action (2011) Lao PDR + Pak Lay Hydro 1,320 MOU signed TBD Thailand Luang Prabang Lao PDR + Vietnam Hydro 1,410 MOU signed TBD Lao PDR + Xayaboury Hydro 1,260 MOU signed TBD Thailand Lao PDR + China + Pakbeng Hydro 1,300 MOU signed TBD Thailand Lao PDR + China + Sanakham Hydro 500 MOU signed TBD Thailand Xekong 3 Lao PDR + Vietnam Hydro 150 MOU signed TBD Lao PDR + Ban Koum Hydro 2,330 MOU signed TBD Thailand Nam Ngum 4A Lao PDR + Vietnam Hydro 60 MOU signed TBD Nam Ngum 4B Lao PDR + Vietnam Hydro 60 MOU signed TBD Nam Xam Lao PDR + Vietnam Hydro 750 MOU signed TBD Lao PDR + Lat Sua Hydro 800 MOU signed TBD Thailand Myanmar Lower Ta Sang Thailand Hydro 200 PDA? signed 2010 Ta Sang 1 Thailand Hydro 2,133 PDA? signed 2016 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 81 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) Ta Sang 2 China + Thailand Hydro 4,977 PDA? signed 2022 Hutgyi Thailand Hydro 1,200 MOU signed 2012 Ta Pein 1 China Hydro 240 n.k. 2010 Group 3 project under the Vientiane Shweli 1 - Yunnan China Interconnector n.k. n.k. 2011 Plan of Action Shweli 2 China Hydro 460 MOU signed TBD Shweli 3 China Hydro 360 MOU signed TBD Tanintharyi Thailand Hydro 600 MOU signed TBD Upper Thanlwin Thailand Hydro 4,000 n.k. TBD Lower Thanlwin Thailand Hydro 500 n.k. TBD Ywathit Thailand Hydro 800 n.k. TBD Maykha Basin China Hydro 13,600 MOU signed TBD Thailand 115 kV (Banteay Cambodia Interconnector 80 In service 2007 Mean Chey) Lao PDR Northern Group 1 project under the Vientiane Transmission Lao PDR Interconnector n.k. n.k. 2010 Plan of Action Project Vietnam 220 kV (Phnom Construction Cambodia Interconnector 220b 2009 Penh) complete? Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 82 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Project Market Type Capacity Status Date Notes (MW) 110 kV (Kampong Group 1 project under the Vientiane Cambodia Interconnector 20 Under construction? 2010 Cham) Plan of Action Shaded projects are those identified in the Vientiane Plan of Action (see Section 6 for definition of the groups used). Projects that form part of the Plan of Action or are identified for funding by IFIs, but which lie only within one country, are not included. Projects such as the Lao PDR Northern Transmission Project, which will facilitate imports from Thailand to northern Lao PDR, are shown as an export project for Thailand although most investments will be made in Lao PDR. a These projects only export surplus power. They are primarily used to supply domestic demand b Initial exports are likely to be significantly lower due to capacity constraints CA Concession Agreement FS Feasibility Study MP Master Plan MOU Memorandum of Understanding n.k. Not known PDA Project Development Agreement PPA Power Purchase Agreement TBD To be determined Sources: Compiled by ECA from country documents Cambodia Electricity Authority of Cambodia (2008), Ministry of Mines and Energy (2008) and Wasizawa (2009) China China Southern Power Grid (2008) Lao PDR Department of Energy Promotion and Development (2009) and Somvichith (2008) Myanmar Presentation at Franco-ASEAN Seminar (2007) and Presentation at PWG-5 (2008) Thailand EGAT (2007) and EGAT (2008) Vietnam Prime Minister Decision No. 110/2007/QD-TTg and Institute of Energy (2008) Where different dates or capacities are given in documents for the importing and exporting countries concerned, those in the exporting country documentation have been used. Other dates are shown in parantheses in the Notes column. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 83 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Figure 15 Lower Mekong Basin hydro projects Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 84 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity supply Figure 16 Myanmar Hydro Projects Source: Presentation at PWG-5 (2008) Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 85 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity demand A3 Electricity demand Table 11 Electricity Peak Demand in GMS Member Countries All in MW Cambodia China (China China Lao PDR Myanmar Thailand Vietnam (grid) Southern (Yunnan and Grid) Guangxi) 2000 70 37,890 173 14,918 4,893 2001 78 192 16,126 5,655 2002 88 198 16,681 6,552 2003 101 232 18,121 7,408 2004 116 271 19,326 8,283 2005 133 69,590 328 20,538 9,299 2006 165 349 21,064 10,187 2007 205 87,000 22,900 416 22,586 11,290 2008 240 621 22,568 12,640 2009 318 808 25,225 2010 432 114,030 945 26,635 19,117 Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 86 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity demand All in MW Cambodia China (China China Lao PDR Myanmar Thailand Vietnam (grid) Southern (Yunnan and Grid) Guangxi) 2011 546 1,195 27,996 2012 768 1,690 29,625 2013 931 1,927 31,384 2014 1,160 2,176 33,216 2015 1,349 2,223 35,251 31,495 2016 1,546 2,267 37,382 2017 1,746 2,314 39,560 2018 1,937 2,365 41,795 2019 2,148 2,422 44,082 2020 2,401 2,494 46,481 47,607 Average annual growth in demand 2000-07 16.5% 12.6% 13.3% 4.9%a 6.1% 12.0% 2007-20 20.9% 14.8% 5.7% 11.7% Shaded cells are actual data. Blanks indicate data unavailable a 2000-08. Calculated using generation data Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 87 ESMAP Briefing Note 004/10 | June 2010 Annex: Electricity demand Sources: Compiled by ECA from various country documents. Cambodia Electricity Authority of Cambodia (2008), Ministry of Mines and Energy (2008) and Wasizawa (2009). Historic demand to 2007 is for EDC’s Phnom Penh system only. Forecast demand is updated demand forecast prepared by Ministry of Industry, Mining and Energy. China China Southern Power Grid (2008). Growth in peak demand is for China Southern Grid as a whole. Lao PDR Somvichith (2008) Myanmar Historic demand growth is for generation. 2000 data is from ASEAN Energy Centre. (http://www.aseanenergy.org/energy_sector/electricity/myanmar/electricity_prod_sales_00.htm). 2008 data is from Myanmar Central Statistical Organisation (http://www.csostat.gov.mm/S10MA02.asp, accessed 8 May 2009). Myanmar adopts a year from April to March of the successive year for statistical purposes. Hence, data for 2000 represent April 1999 to March 2000. Thailand EGAT (2007). As a result of the economic downturn, a revised PDP was approved by Cabinet in March 2009. The details are not publicly available in English but reports indicate that consumption by the end of the planning period (2021) is forecast to be 11% below that in the 2007 PDP, and further adjustments to the demand forecasts for the 2016-21 period are possible. (see http://pepei.pennnet.com/display_article/355679/6/ARTCL/none/none/1/Thailand-scales-back-long-term-power-consumption-forecast-by-11-per- cent/). Vietnam Electricity Regulatory Authority of Vietnam (2007), Institute of Energy (2008) and Trung (2008) Where multiple forecasts are provided, the base case is shown. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 88 ESMAP Briefing Note 004/10 | June 2010 Annex: Contracts A4 Contracts Copies of GMS agreements (IGA, MOU #1, MOU #2, the Vientiane Plan of Action, the Road Map and the RPTOA) are available from websites. Please refer to the Bibliography for locations where these agreements can be downloaded. Greater Mekong Subregion (GMS) Case Study REGIONAL POWER SECTOR INTEGRATION: LESSONS FROM GLOBAL CASE STUDIES AND A LITERATURE REVIEW 89 ESMAP Briefing Note 004/10 | June 2010