The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Angola Statistics Project (P157671) AFRICA EAST | Angola | Poverty and Equity Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 9 | ARCHIVED on 30-Aug-2021 | ISR47809 | Implementing Agencies: National Institute for Statistics of Angola (INE), Ministry of Finance Key Dates Key Project Dates Bank Approval Date: 07-Dec-2016 Effectiveness Date: 31-May-2017 Planned Mid Term Review Date: 30-Jul-2019 Actual Mid-Term Review Date: 06-Dec-2019 Original Closing Date: 30-Nov-2021 Revised Closing Date: 30-Nov-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to strengthen the capacity of the National Institute for Statistics to fill data gaps, improve statistical production and enhance statistical dissemination practices. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional Reform and Capacity:(Cost $3.50 M) Data Production and Dissemination:(Cost $56.35 M) Project Management:(Cost $2.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Angola Statistics Project was approved by the Board of the World Bank on December 7, 2016, followed by the signing of the project on March 02, 2017. The effectiveness date of the project was May 31, 2017. The Instituto Nacional de Estadística (INE) is implementing the project that is organized into three components: Institutional and Human Capacity; Data Production and Dissemination; and Project Management. This ISR is based on the virtual implementation support mission that took place in May 2021, on continuous follow-up implementation support supervision activities held by the Bank's team during the period February to June 2021. In general, the project implementation is performing Moderately Unsatisfactory mainly due to fiduciary issues referred to in the procurement and financial management sections. 8/30/2021 Page 1 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Although the rapid escalation of the spread of COVID-19 in Angola and measures to contain the spread significantly delayed the data collection activities for both the agricultural and the economic censuses, all preparation activities and data collection resumed and were successfully completed. The project has been facing fiduciary issues related to the expenses during the extended fieldwork that affect its rating. In order to address these fiduciary challenges and mitigate associated risks, INE and the World Bank have agreed to the following steps: 1. Weekly project overview meetings between INE and the World Bank, with participation of the Debt management Unit of the Ministry of Finance. 2. Weekly procurement meetings with the participation of the PIU, including its procurement staff, and the World Bank procurement team. 3. A supervision mission during the last two weeks of September to assess the progress made and prepare final inputs for the consideration of a potential extension, which depends on project performance as well as availability of project budget Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Low Low Low Institutional Capacity for Implementation and Substantial Moderate Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Low Low Low Stakeholders Low Low Low Other -- Substantial Substantial Overall Substantial Moderate Moderate Results PDO Indicators by Objectives / Outcomes Increase the national statistical capacity of Angola IN01025982 ►Increase in the Statistical Capacity Index (SCI) score (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target 8/30/2021 Page 2 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) Value 42.20 48.90 45.60 60.00 Date 31-May-2017 18-Dec-2020 30-Jul-2021 31-Dec-2021 Data gaps on agriculture, welfare, employment and business covered surveys or censuses implemented IN01025983 ►Number of agriculture, welfare, employment and business surveys or censuses implemented (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4.00 5.00 12.00 Date 31-May-2018 18-Dec-2020 30-Jul-2021 30-Dec-2021 The October value of 9 is a mistake, it should be 0 instead of 9. Comments: Improved national accounts IN01025984 ►Improved national accounts (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 40.00 45.00 100.00 Date 31-May-2017 06-Jul-2020 30-Jul-2020 31-Dec-2021 Increase metadata and microdata dissemination IN01025985 ►Number of INE downloads of statistical materials and micro-datasets (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 6.00 150.00 Date 29-Apr-2016 06-Jul-2020 30-Jul-2020 30-Nov-2021 The WB team is counting all downloads from the INE catalog, considering all datasets in the catalog (11). The new statistical operations under the Statcap will start uploading soon. We are counting all downloads because through the Statcap we are improving data dissemination. However, we are resetting the score of Comments: this indicator to Zero "0" because it should reflect only the dissemination of datasets produced under the Statcap project. The Household Survey (IDREA) is already published and there are 5,672 views (July 2021). Overall Comments PDO The WB team is counting all downloads from the INE catalog, considering all datasets in the catalog (11). The new statistical operations under the Statcap will start uploading soon. We are counting all downloads because through the Statcap we are improving data dissemination. However, we are resetting the score of this indicator to Zero "0" because it should reflect only the dissemination of datasets produced under the Statcap project. 8/30/2021 Page 3 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) The Household Survey (IDREA) is already published and there are 5,672 views (July 2021). Intermediate Results Indicators by Components Project Management IN01025986 ►FM and procurement plan complied (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 70.00 70.00 100.00 Date 31-May-2017 06-Jul-2020 06-Jul-2020 31-Dec-2021 Data Production and Dissemination IN01025987 ►Number of published quarterly GDP statistics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 14.00 15.00 10.00 Date 29-Apr-2016 18-Dec-2020 30-Jul-2021 30-Nov-2021 IN01025989 ►Number of survey and census micro-datasets available online (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 11.00 11.00 21.00 Date 29-Apr-2016 18-Dec-2020 18-Dec-2020 30-Nov-2021 The INE microdata catalog is open online. There are 11 datasets available to consult and download; however, the statistical projects produced under the Statcap project are uploaded and published only 1 Comments: dataset in the Catalogue. Institutional Reform and Capacity IN01025988 ►Number of statistical reports funded by the project available online, disaggregated by availability of gendered statistics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6.00 7.00 6.00 Date 29-Apr-2016 18-Dec-2020 30-Jul-2021 30-Nov-2021 Examples of statistical reports available online: Quick info sheet inquiry approved building permits Comments: (ILACE), GDP press release (quarterly reports), quick information sheet of foreign trade statistics, industrial production index quick datasheet, (IPI), quick export and import price index information sheet 8/30/2021 Page 4 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) (IPEI), quick employment and unemployment information sheet (IEA) and economic environment; COVID impact from Labor Survey (IEA), Household Survey (IDREA) available through the NADA Cataolog. IN01025990 ►The number of staff who have achieved improvements in skill/knowledge compared to a pre-training baseline (measured by test results and disaggregated by gender) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 227.00 227.00 750.00 Date 29-Apr-2016 18-Dec-2020 30-Jul-2021 30-Nov-2021 Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P157671 IBRD-86690 Effective USD 62.00 62.00 0.00 49.26 12.74 79% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P157671 IBRD-86690 Effective 07-Dec-2016 02-Mar-2017 31-May-2017 30-Nov-2021 30-Nov-2021 Cumulative Disbursements 8/30/2021 Page 5 of 6 The World Bank Implementation Status & Results Report Angola Statistics Project (P157671) PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 8/30/2021 Page 6 of 6