Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Services) Above US$ 1,500,000 All 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of NA NA NA NA the ICB (Works) Summary of 6.69 4 No Prior the ICB (Goods) Summary of 3.8 9 No Post All the NCB (Works) Summary of 14.70 14 No Post All the NCB (Goods) Summary of NA NA NA NA the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Commentes 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.35 2 Prior number of contracts that July 9, 2010 will be let under QCBS Summary of 1.4 38 Post LCS/ IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-10-26 2020-03-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58330 Executing Agency(ies): Agence Djiboutienne de Development Social WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/T1/2017 / Travaux d'extension de 5 salles de Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 325,070.00 0.00 2018-02-10 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-12-01 Lycée et réhabilitation du Services and Infrastructure Envelope d'exécution dortoir à Obock COMP1/T3/2017 / Travaux Social and Economic Single Stage - One En attente de raccordement pecherie IDA / 58330 A posteriori Appel d'offres Open - National 450,704.00 0.00 2017-11-20 2017-11-27 2018-01-08 2018-02-07 2018-03-14 2018-09-10 Services and Infrastructure Envelope d'exécution d'Obock COMP1/T8/2017 / construction de locaux Social and Economic Single Stage - One En cours IDA / 58330 A posteriori Demande de prix Limited 101,408.00 0.00 2018-03-17 2018-10-22 2018-05-12 2018-11-08 communautaire/communautair Services and Infrastructure Envelope d'exécution e à Ali addé COMP1/T9/2017 / Réhabilitation du local Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 40,000.00 0.00 2018-02-17 2018-04-14 2018-10-11 communautaire (UNFD) à Services and Infrastructure Envelope d'exécution Holl-Holl COMP2/T1/2017 / rénovation et renforcement Social and Economic Single Stage - One En attente de perimetres existants d'où IDA / 58330 A posteriori Demande de prix Limited 135,211.00 0.00 2017-11-01 2017-12-27 2018-06-25 Services and Infrastructure Envelope d'exécution 5 reservoirs , 5 puits , 5 champs solaires pour Obock DJ-ADDS-29135-CW-RFB / Social and Economic Single Stage - One En attente Travaux extention du centre IDA / 58330 A posteriori Appel d'offres Open - National 399,493.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-02-08 2018-06-08 Services and Infrastructure Envelope d'exécution de santé à Obock DJ-ADDS-29136-CW-RFB / rehabilitation/ extention du Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 436,620.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-08-07 centre de santé Ali addé et Services and Infrastructure Envelope d'exécution Hol Hol en 2 lots séparés DJ-ADDS-29129-CW-DIR / Passation de Travaux d'extension Résau/ Social and Economic En cours IDA / 58330 A priori marché de gré à Direct 1,188,371.09 0.00 2017-09-19 2019-05-14 2017-10-04 2017-10-27 2019-04-25 Electricité d'Obock et Holl- Services and Infrastructure d'exécution gré Holl 004/2017/TVX/IDA- PRDDCA/ADDS / avenant Passation de n°1 au marché des travaux Social and Economic IDA / 58330 A priori marché de gré à Direct 210,936,565.00 0.00 Annulé 2019-02-21 2019-02-26 2019-04-02 2019-09-29 d'électrification Holhol et Services and Infrastructure gré extension réseau electrique d'Obock Page 1 COMP1/T5/2017 / F+P et raccordement des installations électriques des Social and Economic Single Stage - One En cours logements, locaux IDA / 58330 A posteriori Appel d'offres Open - National 241,392.00 0.00 2017-10-31 2018-03-29 2017-11-07 2017-12-07 2018-05-02 2018-01-06 2018-02-10 2018-05-11 Services and Infrastructure Envelope d'exécution commerciaux et établissements publics à Holl- Holl COMP1/T5/2019 / Travaux Social and Economic Single Stage - One En attente de rénovation des locaux de IDA / 58330 A posteriori Appel d'offres Open - National 86,751.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 Services and Infrastructure Envelope d'exécution l'UNFD à Obock COMP4/T1/2019 / Travaux Project Management, and Single Stage - One En cours de construction d'une salle IDA / 58330 A posteriori Appel d'offres Open - National 185,915.00 0.00 2019-09-08 2019-10-21 2019-09-13 2019-10-25 2019-12-11 2019-11-24 2020-01-27 2019-12-29 2020-06-26 Monitoring and Evaluation Envelope d'exécution d'archives COMP1/T7/2017 / Travaux de construction d'une piste Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 662,423.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 en pierres taillées (voiries Services and Infrastructure Envelope d'exécution Obock) COMP1/T6/2017 / Travaux de construction de logements Social and Economic Single Stage - One En attente de fonction et réhabilitation IDA / 58330 A posteriori Appel d'offres Open - National 1,616,902.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-05-09 Services and Infrastructure Envelope d'exécution de l’école primaire et collège de Holl Holl. COMP2/T2/2017 / rénovation et renforcement Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 186,183.00 0.00 2017-11-01 2017-12-27 2018-06-25 de perimetres existants Services and Infrastructure Envelope d'exécution pour Holhol COMP2/T3/2017 / rénovation et renforcement de perimetres existants d'où Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 149,000.00 0.00 2017-11-01 2017-12-27 2018-06-25 5 reservoirs , 5 puits, 5 Services and Infrastructure Envelope d'exécution champs solaires pour Ali Addé COMP1/T1/2019 / Travaux Passation de de réhabilitation et Social and Economic En attente IDA / 58330 A posteriori marché de gré à Direct 87,417.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 d'extension du Centre de Services and Infrastructure d'exécution gré Santé de Holl Holl.. COMP1/T6/2019 / petits travaux de raccordement eau Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2019-11-25 2020-01-20 2020-07-18 et électricité pour la Services and Infrastructure Envelope d'exécution pêcherie.. COMP1/T7/2019 / Travaux de rénovation d'électricité Social and Economic Single Stage - One En attente pour la salle d'urgence et IDA / 58330 A posteriori Demande de prix Limited 13,000.00 0.00 2019-11-02 2019-12-28 2020-06-25 Services and Infrastructure Envelope d'exécution salle d'hospitalisation du CMH d'Obock COMP1/T3/2019 / Réalisation à Obock des travaux des conduites Passation de En attente d’adduction d’eau depuis les IDA / 58330 Livelihoods Program A priori marché de gré à Direct 1,156,356.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 d'exécution forages au réservoir ainsi gré que le raccordement de deux nouveau forages.. COMP1/T5/TVX/2019 / Social and Economic Single Stage - One En attente Rénovation des locaux de IDA / 58330 A posteriori Appel d'offres Open - National 107,042.00 0.00 2019-11-19 2019-11-24 2020-01-05 2020-02-04 2020-03-10 2020-09-06 Services and Infrastructure Envelope d'exécution l'UNFD à Obock Page 2 COMPT1/T7/2019 / Fourniture +Pose et raccordement des Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Open - National 164,380.00 0.00 2020-02-09 2020-04-05 2020-07-04 installations électriques des Services and Infrastructure Envelope d'exécution logements, mis en conformité de 200 logements à obock COMPT1/T3/2010 / travaux de raccordement de nouveaux forages, réalisation Passation de Social and Economic En attente de conduite d'adduction IDA / 58330 A posteriori marché de gré à Direct 1,339,674.00 0.00 2020-02-04 2020-02-09 2020-03-15 2020-06-13 Services and Infrastructure d'exécution d'eau et changements des gré conduites vétustes de distribution d'eau à Obock GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/F2/2017 / achat de Matériels informatique pour Social and Economic Single Stage - One En attente les lycées bénéficiaires pour IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2017-10-07 2017-12-02 2018-05-31 Services and Infrastructure Envelope d'exécution le compte de l'Education Informatique COMP1/F4/2017 / Passation de equipements médicaux et Social and Economic En cours IDA / 58330 A priori marché de gré à Direct 1,305,900.00 0.00 2017-10-20 2018-05-31 2017-10-20 2017-12-01 2018-05-30 Mobiliers pour Obock,Ali Services and Infrastructure d'exécution gré Addé et Hol Hol COMP2/F2/2017 / achat de matériels pour périmetres Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 166,667.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 existants d'où motopompes, Services and Infrastructure Envelope d'exécution brouettes... pour Obock COMP4/F1/2017 / acquisition d'une pick up et Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 124,213.00 0.00 2017-10-02 2017-10-09 2017-11-20 2017-12-20 2018-01-24 2018-07-23 de 2 voitures 4X4. HARD Services and Infrastructure Envelope d'exécution TOP COMP4/F2/2017 / Social and Economic Single Stage - One En attente acquisition de tablettes pour IDA / 58330 A posteriori Demande de prix Limited 30,000.00 0.00 2017-10-09 2017-12-04 2018-06-02 Services and Infrastructure Envelope d'exécution l'enquete COMP4/F4/2017 / acquisition d' équipement Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 84,507.00 0.00 2017-10-03 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 pour le centre de formation Services and Infrastructure Envelope d'exécution de l'ONARS COMP1/F3/2017 / achat de Matériels de SVT et Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 135,201.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-04-09 Physique pour le Ministère Services and Infrastructure Envelope d'exécution de l'Educatioon Nationale COMP2/F3/2017 / achat de matériels pour périmetres Social and Economic Open - Single Stage - One En attente existants d'où motopompes, IDA / 58330 A posteriori Appel d'offres 333,334.00 0.00 2017-10-31 2017-11-07 2017-12-19 2018-01-18 2018-02-22 2018-06-22 Services and Infrastructure International Envelope d'exécution brouettes... pour Ali Addé et HolHol COMP3/F1BIS/2017 / Social and Economic Single Stage - One En attente Acquisition de kits culinaires IDA / 58330 A posteriori Demande de prix Limited 20,000.00 0.00 2017-11-05 2017-12-31 2018-01-20 Services and Infrastructure Envelope d'exécution pour les GEA Page 3 COMP3/F1/2017 / acquisition de matériels et Social and Economic Single Stage - One En attente consommables pour les IDA / 58330 A posteriori Appel d'offres Open - National 180,000.00 0.00 2017-10-31 2017-11-05 2017-12-05 2018-01-04 2018-02-08 2018-04-09 Services and Infrastructure Envelope d'exécution groupements de femmes et jeunes COMP4/F3/2017 / acquisition de logiciel pour Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Demande de prix Limited 25,000.00 0.00 2017-11-17 2018-01-12 2018-07-11 l'analyse des données des Services and Infrastructure Envelope d'exécution enquetes COMP1/F1/2017 / Equipements chauds et Froid pour les lycés techniques d' Social and Economic Open - Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres 428,391.00 0.00 2017-10-05 2017-10-12 2017-11-23 2017-12-23 2018-01-27 2018-07-26 Ali Sabieh et Obock pour Services and Infrastructure International Envelope d'exécution le Ministère de l' Education Nationale COMP1/F4/2019 / acquisition de chambres Project Management, and Single Stage - One IDA / 58330 A posteriori Appel d'offres Open - National 123,944.00 78,248.74 Signé 2019-09-08 2019-06-20 2019-09-13 2019-10-25 2019-08-07 2019-11-24 2019-09-17 2019-12-29 2019-10-03 2020-06-26 froides positives pour la Monitoring and Evaluation Envelope pecherie COMP1/F5/2019 / Regional Support for Acquisition de boutres, et Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 275,000.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 autres matériels etc.. pour Envelope d'exécution Knowledge les pecheurs d'obock COMP1/F6/2019 / Regional Support for Acquisition d'équipements Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 56,338.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pours les dortoirs et Envelope d'exécution Knowledge réfectoires d'Obock COMP1/F1/2019 / Acquisition d'équipements Project Management, and Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 54,995.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pour le collège de Alli Addé Monitoring and Evaluation Envelope d'exécution (tables, chaises,...) COMP1/F2/2019 / Regional Support for Acquisition d'équipements Single Stage - One En attente IDA / 58330 Coordination, Capacity and A posteriori Appel d'offres Open - National 99,000.00 0.00 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 pour l'UNFD à Holhol, Ali Envelope d'exécution Knowledge addé et Obock COMP1/F2/2017 / achat de Matériels informatique pour Social and Economic Single Stage - One En attente IDA / 58330 A posteriori Appel d'offres Open - National 169,000.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 les lycées bénéficiaires/ Services and Infrastructure Envelope d'exécution Education COMP1/F5/2017 / Passation de Social and Economic En attente acquisition de 10 200 foyers IDA / 58330 A priori marché de gré à Direct 229,859.00 0.00 2019-11-15 2019-11-20 2019-12-16 2020-03-15 Services and Infrastructure d'exécution améliorés pour les 3 sites gré NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/NCS1/2019 / séminaire Management de Passation de projets et programmes par Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 12,435.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 indicateurs, résultats et Monitoring and Evaluation d'exécution gré tableaux de bord Page 4 COMP4/NCS2/2019 / Formation: cycle FI05 intitulé "La passation et l'exécution des marchés selon Passation de Project Management, and En attente les nouvelles procédures IDA / 58330 A posteriori marché de gré à Direct 15,000.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 Monitoring and Evaluation d'exécution nationales et des bailleurs gré (Banque Mondiale, Banque Africaine de Développement, Union Européenne...)" COMP4/CSC3/2019 / Formation de la responsable Passation de gestion financière en gestion Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 15,000.00 0.00 2019-09-24 2019-09-29 2019-11-03 2020-05-01 administrative et financière, Monitoring and Evaluation d'exécution gré la clôture et l'audit des programmes et projets COMP4/NCS4/2019 / formation du chef de projet Passation de en " préparation ala Project Management, and En attente IDA / 58330 A posteriori marché de gré à Direct 15,171.00 0.00 2019-11-17 2019-11-22 2019-12-27 2019-12-30 certification en gestion de Monitoring and Evaluation d'exécution gré projet PMP (project Managment professionnal) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/C1/2017 / Recrutement d'un Bureau d'Etudes et de supervision Sélection fondée Social and Economic En attente pour les travaux d'extension, IDA / 58330 A posteriori sur la qualité et Open - National 252,234.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 Services and Infrastructure d'exécution construction, réhabilitation le coût des établissements scolaires , le local communautaire COMP1/C2/2017 / Recrutement d'un Bureau Sélection fondée d'Etudes pour la supervision Social and Economic sur les En attente IDA / 58330 A posteriori Open - National 83,611.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 des travaux d'extension de Services and Infrastructure qualifications des d'exécution centres de santé pour obock, consultants ali addé et Hol hol COMP1/C3/2017 / Récrutement d'un consultant individuel pour les études et Sélection fondée la supervision les travaux Social and Economic sur les En attente d'installations dans les IDA / 58330 A posteriori Open - National 30,000.00 0.00 2017-10-30 2017-11-20 2018-01-03 2018-02-02 2018-03-09 2018-09-05 Services and Infrastructure qualifications des d'exécution logements, locaux consultants commerciaux et établissement publics à Holl- Holl COMP1/C4/2017 / Sélection fondée Recrutement d'un bureau Social and Economic sur les En attente IDA / 58330 A posteriori Open - National 45,070.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 d'etudes pour raccordement Services and Infrastructure qualifications des d'exécution Pecherie (Obock) consultants COMP1/C5/2017 / Recrutement d'un BE pour Sélection fondée les travaux de forrage de Social and Economic En attente IDA / 58330 A posteriori sur la qualité et Open - National 188,732.00 0.00 2017-12-15 2018-01-05 2018-02-18 2018-03-18 2018-04-17 2018-05-22 2018-06-26 2019-06-26 Hol hol et Ali Addé et du Services and Infrastructure d'exécution le coût reseau d'adduction d'eau à Obock et Holl-Holl Page 5 COMP2/C1/2017 / Sélection fondée Recrutement d'un bureau Social and Economic sur les En attente d'etudes pour la la IDA / 58330 A posteriori Open - National 40,564.00 0.00 2017-10-05 2017-10-26 2017-12-09 2018-01-08 2018-02-12 2018-08-11 Services and Infrastructure qualifications des d'exécution rénovation et renforcement consultants des perimetres existants COMP2/C2/2017 / Recrutement d'un bureau Sélection fondée Social and Economic En attente d'etudes pour l'extension de IDA / 58330 A posteriori sur la qualité et Open - National 152,369.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2019-04-13 Services and Infrastructure d'exécution la centrale solaire et le le coût forage d'Ali-Addé COMP4/C10/2017 / Social and Economic Sélection au En attente recrutement d 'un cabinet IDA / 58330 A posteriori Open - National 10,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-03 2018-02-02 2018-03-09 2018-04-13 2018-10-10 Services and Infrastructure moindre coût d'exécution pour l'Audit Financier COMP4/C11/2017 / Recrutement d'un consultant Sélection fondée pour la collecte de donnée Social and Economic sur les En attente IDA / 58330 A posteriori Open - National 8,000.00 0.00 2017-10-02 2017-10-23 2017-12-06 2018-01-05 2018-02-09 2018-08-08 administratives de toutes les Services and Infrastructure qualifications des d'exécution infrastructures sociales de consultants base COMP1/C2/2019 / Recrutement d'un cabinet Sélection fondée Social and Economic En attente pour l'étude topographique IDA / 58330 A posteriori sur la qualité et Open - National 30,000.00 0.00 2019-09-23 2019-10-14 2019-11-27 2019-12-25 2020-01-24 2020-02-28 2020-04-03 2021-04-03 Services and Infrastructure d'exécution de l'adduction d'eau potable le coût a partir d'Ali sabieh COMP1/C5/2017 / Recrutement d'un BE pour Sélection fondée Social and Economic Open - En attente les travaux de raccordements IDA / 58330 A posteriori sur la qualité et 500,000.00 0.00 2020-02-20 2020-03-12 2020-04-25 2020-05-23 2020-06-22 2020-07-27 2020-08-31 2021-08-31 Services and Infrastructure International d'exécution de Hol hol et Ali Addé au le coût reservoir d'eau d'Ali-Sabieh INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/C1/2017 / Social and Economic En cours IDA / 58330 A posteriori Individuel Open 30,000.00 0.00 2017-10-02 2016-10-25 2017-11-20 2017-12-11 2018-01-15 2018-07-14 coordinateur de projet Services and Infrastructure d'exécution COMP4/C2/2017 / Social and Economic En attente recrutement d'ingénieur en IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 Services and Infrastructure d'exécution Infrastructures COMP4/C3/2017 / recrutement de 4 techniciens Social and Economic En attente IDA / 58330 A posteriori Individuel Open 62,400.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 supérieurs pour les régions Services and Infrastructure d'exécution et Djibouti ville COMP4/C5/2017 / recrutement d'un spécialiste Social and Economic En attente IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 en sauvegardes Services and Infrastructure d'exécution environnementales et sociales COMP4/C6/2017 / Social and Economic En attente recrutement d'un responsable IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 Services and Infrastructure d'exécution Suivi evaluation COMP4/C7/2017 / Social and Economic En attente IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 recrutement d'un comptable Services and Infrastructure d'exécution Page 6 COMP4/C8/2017 / Social and Economic En attente recrutement d'un assistant IDA / 58330 A posteriori Individuel Open 12,000.00 0.00 2017-11-05 2017-12-24 2018-01-14 2018-02-18 2018-08-17 Services and Infrastructure d'exécution de projet COMP4/C9/2017 / Social and Economic En attente recrutement d'un spécialiste IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-05 2017-11-23 2017-12-14 2018-01-18 2018-07-17 Services and Infrastructure d'exécution Passation des marchés COMP4/C12/2017 / Sélection de Social and Economic En attente Enquette sur les migrants à IDA / 58330 A priori consultants par Direct 71,967.00 0.00 2017-10-02 2017-10-07 2017-11-11 2018-05-10 Services and Infrastructure d'exécution Balbala et à Djibouti-Ville entente directe COMP4/C16/2017 / Récrutement d'un expert Social and Economic En attente international pour la IDA / 58330 A posteriori Individuel Open 30,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 Services and Infrastructure d'exécution préparation de la stratégie de l'ONARS COMP4/C17/2017 / Récrutement d'un consultant individuel pour l'appui de Social and Economic En attente IDA / 58330 A posteriori Individuel Open 11,268.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2018-07-14 l'expert en charge de la Services and Infrastructure d'exécution préparation de la stratégie de l'ONARS COMP4/C17/2017_1 / recrutement d'un expert Social and Economic En attente IDA / 58330 A posteriori Individuel Open 85,000.00 0.00 2017-11-15 2018-01-03 2018-01-24 2018-02-28 2018-08-27 international en manuel de Services and Infrastructure d'exécution procédures ONARS COMP4/C4/2017 / Social and Economic En attente recrutement d'un spécialiste IDA / 58330 A posteriori Individuel Open 24,000.00 0.00 2017-10-02 2017-11-20 2017-12-11 2018-01-15 2019-01-15 Services and Infrastructure d'exécution en agriculture COMP4/C13/2017 / recrutement d'un consultant Social and Economic En attente IDA / 58330 A posteriori Individuel Open 29,734.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 pour l'enquête quantitative Services and Infrastructure d'exécution ménage COMP4/C14/2017 / recrutement d'un consultant Social and Economic En attente pour l'enquête quantitative IDA / 58330 A posteriori Individuel Open 26,133.00 0.00 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 Services and Infrastructure d'exécution jeunes femmes et périmètres agro pastoraux COMP4/C16/2017 / Recrutement d'un consultant Social and Economic En attente IDA / 58330 A posteriori Individuel Limited 34,000.00 0.00 2018-03-14 2018-03-19 2018-04-09 2018-05-14 2018-06-28 pour l'enquête de suivi des Services and Infrastructure d'exécution indicateurs DJ-ADDS-54279-CS-INDV / recrutement d'un consultantpour la Social and Economic En attente IDA / 58330 A posteriori Individuel Limited 20,000.00 0.00 2017-10-05 2017-10-10 2017-10-31 2017-12-05 2018-06-03 sensibilisation,étude de Services and Infrastructure d'exécution marchés, mise a jour du listing COMP4/C17/2017_2 / Social and Economic En attente recrutement d'un consultant IDA / 58330 A posteriori Individuel Limited 80,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-06-29 Services and Infrastructure d'exécution pour l'enquete de référence 40000 / recrutement d'un Social and Economic En attente consultant pour la IDA / 58330 A posteriori Individuel Limited 40,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Services and Infrastructure d'exécution communication COMP3/C1/2017 / recrutement d'un consultant Social and Economic En attente IDA / 58330 A posteriori Individuel Limited 20,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 pour l'analyse Services and Infrastructure d'exécution complémentaire de l'enquete Page 7 022/2018/CO/IDA- PRDDCA/ADDS / Sélection de En attente recrutement d'une chargée IDA / 58330 Livelihoods Program A posteriori consultants par Direct 8,400.00 0.00 2019-01-16 2019-01-26 2019-04-01 2019-09-28 d'exécution des GEA pour la rgion entente directe OBOCK 023/2018/CO/IDA- PRDDCA/ADDS / Sélection de En attente recrutement d'une chargée IDA / 58330 Livelihoods Program A posteriori consultants par Direct 8,400.00 0.00 2019-01-16 2019-01-26 2019-04-01 2019-09-28 d'exécution des GEA pour la région entente directe d'Ali sabieh 024/2018/CO/IDA- PRDDCA/ADDS / Sélection de Recrutement d'une En attente IDA / 58330 Livelihoods Program A posteriori consultants par Direct 7,200.00 0.00 2019-01-30 2019-02-09 2019-04-15 2019-10-12 facilitatrice du programme d'exécution entente directe de moyens de subsistance des jeunes. 004/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'un facilitateur Sélection de à Holl-Holl pour le Project Management, and En attente IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Renforcement de capacités Monitoring and Evaluation d'exécution entente directe des jeunes et pour la Préparation au concours de Microprojets 005/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'une Sélection de facilitatrice à Holl-Holl pour Project Management, and En attente IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 le Renforcement de Monitoring and Evaluation d'exécution entente directe capacités des jeunes et pour la Préparation au concours de Microprojets. 006/2019/CO/IDA- PRDDCA/ADDS / Recrutement d'une Sélection de facilitatrice à Holl-Holl pour Project Management, and En attente IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 le Renforcement de Monitoring and Evaluation d'exécution entente directe capacités des jeunes et pour la Préparation au concours de Microprojets. 007/2019/CO/IDA- PRDDCA/ADDS / Recrutement d’un facilitateur Sélection de à Ali-Addeh pour le Project Management, and En attente IDA / 58330 A posteriori consultants par Direct 7,200.00 0.00 2019-02-05 2019-02-15 2019-04-21 2019-10-18 Renforcement de capacités Monitoring and Evaluation d'exécution entente directe des jeunes et pour la Préparation au concours de Microprojets. 020/2019/CO/IDA- PRDDCA/ADDS / Sélection de Project Management, and En attente recrutement d'un consultant IDA / 58330 A posteriori consultants par Direct 4,250.00 0.00 2019-04-02 2019-04-12 2019-06-16 2019-12-13 Monitoring and Evaluation d'exécution pour l'actualisation des entente directe indicateurs DRIPDIP COMP4/C19/2019 / Project Management, and En cours recrutement d'un consultant IDA / 58330 A posteriori Individuel Open 15,000.00 0.00 2019-07-15 2019-06-09 2019-09-02 2019-09-23 2019-10-28 2020-04-25 Monitoring and Evaluation d'exécution pour la revue mi-parcours COMP4/C20/2019 / Sélection de recrutement d'un Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 30,000.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 coordinateur pour la Monitoring and Evaluation d'exécution entente directe composante III Page 8 COMP4/C21/2019 / Sélection de Project Management, and En cours recrutement d'un expert IDA / 58330 A posteriori consultants par Direct 24,000.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 Monitoring and Evaluation d'exécution micro entreprise entente directe COMP4/C22/2019 / Sélection de recrutement d'une assistante Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 pour le coordinateur du Monitoring and Evaluation d'exécution entente directe projet COMP4/C23/2019 / Sélection de recrutement d'une assistante Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 pour le coordinateur de la Monitoring and Evaluation d'exécution entente directe composante III COMP4/C24/2019 / Sélection de recrutement d'une Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 4,733.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 facilitatrice communautaire Monitoring and Evaluation d'exécution entente directe des femmes à Holhol COMP4/C25/2019 / Sélection de recrutement d'une Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 facilitatrice communautaire Monitoring and Evaluation d'exécution entente directe pour les femmes à obock COMP4/C26/2019 / Sélection de recrutement d'une Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 facilitatrice communautaire Monitoring and Evaluation d'exécution entente directe pour les femmes a Obock COMP4/C27/2019 / Sélection de recrutement d'une Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 facilitatrice communautaire Monitoring and Evaluation d'exécution entente directe pour les femmes a Obock COMP4/C28/2019 / Sélection de recrutement d'une Project Management, and En cours IDA / 58330 A posteriori consultants par Direct 6,915.00 0.00 2019-07-15 2019-07-15 2019-07-25 2019-09-28 2020-03-26 facilitatrice communautaire Monitoring and Evaluation d'exécution entente directe pour les femmes a Obock COMP4/C11/2019 / Mise a Regional Support for Sélection de En attente jour du logiciel de gestion IDA / 58330 Coordination, Capacity and A posteriori consultants par Direct 94,000.00 0.00 2019-09-08 2019-09-18 2019-11-22 2020-05-20 d'exécution du projet Knowledge entente directe COMP1/C1/2019 / Regional Support for Recrutement d'un consultant En attente IDA / 58330 Coordination, Capacity and A posteriori Individuel Limited 32,000.00 0.00 2019-11-12 2019-11-17 2019-12-08 2020-01-12 2020-02-26 pour l'étude topographique d'exécution Knowledge dédiée a la DHR... COMP3/C4/2019 / recrutement d'un spécialiste Project Management, and En cours IDA / 58330 A posteriori Individuel Limited 15,000.00 0.00 2019-11-26 2019-10-09 2019-12-01 2019-12-22 2020-01-26 2020-01-30 en développement Monitoring and Evaluation d'exécution agropastorale COMP4/C15/2017 / recrutement d'un consultant Social and Economic En attente IDA / 58330 A posteriori Individuel Open - National 50,000.00 0.00 2017-10-31 2017-11-28 2017-12-12 2017-12-26 2018-02-24 pour l'enquete qualitatif Services and Infrastructure d'exécution (focus groupe) .. COMP3/C3/2019 / Recrutement de deux consultant hydrolaugue et Project Management, and En attente IDA / 58330 A posteriori Individuel Limited 30,000.00 0.00 2019-11-12 2019-11-17 2019-12-08 2020-01-12 2020-02-26 énergeticien pour la la Monitoring and Evaluation d'exécution renovation/renforcement des perimetres existants Page 9 COMPR1/C2/2019 / Recrutement d'un consultant individuel pour la supervision les travaux Social and Economic En attente IDA / 58330 A posteriori Individuel Limited 27,000.00 0.00 2020-02-05 2020-02-10 2020-03-02 2020-04-06 2020-06-05 d'installations dans les Services and Infrastructure d'exécution logements et mis en conformité de 200 logment à obock COMP4/C2/2017 / expert Project Management, and En attente international en manuel de IDA / 58330 A posteriori Individuel Limited 85,000.00 0.00 2020-02-04 2020-02-09 2020-03-01 2020-04-05 2020-07-04 Monitoring and Evaluation d'exécution procédures /ONARS (3) Page 10