St. Petersburg Economic Development Project PROCUREMENT PLAN for 2019-20 Works Contract Procurement Bid Contract Contract Description IBRD review BD Issue Bids received Evaluation number method signed completion Report 1 2 4 5 6 7 8 9 10 Sub-Component 2a (Rehabilitation of Cultural Assets) EDP-RM-W Phase 1 Mikhailovsky Palace Inner Courtyards Rehabilitation, ICB prior Jun-18 Aug-18 Sep-18 Nov-18 Mar-20 including preparation of Working Drawings ICB-International Competitive Bidding St. Petersburg Economic Development Project PROCUREMENT PLAN for 2019-20 Consultants (Firms) Contract Description Procurement IBRD review issue of REI Submission of Issue RFP Proposals Technical Final Draft Contract signed Contract numer method applications received Evaluation Evaluation Contract completion 1 2 4 5 6 7 8 9 10 11 12 13 14 Sub-Component 2d (Project rmplementation) EDP-RM-E Technical Supervision over Phase 1 Mikhailovsky Palace Inner QCBS post May-IS Jun-IS Aug-18 Sep-IS N/A N/A N/A Nov-I Mar-20 Courtyards Rehabilitation Works EDP-RMPF Architectural Supervision and Scientific Guidance during execution o 55S post N/A N/A Aug-iS Sep-IS N/A N/A N/A Jan-19 Mar-20 the Phase I Mikhailovsky Palace Inner Courtyards Rehabilitation EDP - EV St. Petersburg Economic Development Project Evaluation QCBS post Jul-18 Aug-18 Sep-18 Oct-18 N/A N/A N/A Apr-19 Mar-20 EDP-IN Engeneering Survey for Mariinsky Theater Historic Building 888 post N/A N/A Jun-18 Jun-IS N/A N/A N/A Jun-18 Aug-iS Rehabilitation State Expertize Appraisal of updated design documents for EDP-SE rehabilitation of the Mariinsky Theater Historic Building SSS N/A N/A N/A Aug-18 Aug-I8 N/A N/A N/A Mar-19 Jun-19 QCBS - Quality-and Cost-Based Selection SSS - Single Source Selection St. Petersburg Economic Development Project PROCUREMENT PLAN for 2019-20 Individual Consultants IBRD Evaluation Draft NOL to Contract Contract # Contract number Description iw TOR eauton nDrat Draft Cona c on review Report Contract Cotat signed completion Contract 1 2 3 5 6 7 8 9 10 11 Sub-Component 2d (Project Implementation) 1 IC-EDP/ 2016 Contract with Consultant-Coordinator Post Jan-16 - Jan-16 Jan-16 Dec-15 Apr-20 Preparation of prequalification and technical part of bidding documents for selection of contractor for rehabilitation of the State Russian Museum Mikhailovsky Palace Inner Courtyards 2 IC-EDP/RM- A Contract with Architect-Restorer Post Dee- 17 Jan-18 Jan-18 N/A Jan-18 Aug-18 3 IC-EDP/RM- B Contract with Expert in BOQ Post Dec-17 Jan-18 Jan-18 N/A Jan-18 Aug-18 4 IC-EDP/RM- E Contract with Expert in Electrical networks and Post Dee-17 Jan-18 Jan-18 N/A Jan-18 Aug-18 IC-EDP/RM- E facilities 5 IC-EDP/RM- L Contract with the Group Leader Post Dec-17 Jan-18 Jan-18 N/A Jan-18 Aug-18 6 IC-EDP/RM- N Contract with Expert in Utility Networks and Post Dee-17 Jan-18 Jan-18 N/A Jan-IS Aug-18 6___ IC-EDP/RM-_____ N Facilities 7 IC-EDP/RM- W Contract with Expert in General Construction Works Post Dec-17 Jan-18 Jan-18 N/A Jan-18 Aug-18 Rehabilitation of the State Academic Mariinsky Theater historic building. Analysis of design solutions, development of recommendations for their updating and project support 8 IC-EDP/MAR- 1Contract with Expert in stage machiner and its Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 control systems 9 IC-EDP/MAR- 2 Contract with Expert in stage lighting Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 10 IC-EDP/MAR- 3 Contract with Expert in sound amplification, public Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 address, voice alarm and intercom systems Contract with Expert in production management system; cue light system; video projection and multimedia system; closed circuit TV system;video 11 IC-EDP/MAR- 4 recordia system; cal cablestelepho Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 recording and archiving system; local cable telephone network, cable and broadcast television; stage equipment complex power supply system 12 IC-EDP/MAR- Contract with Expert in cost estimate of the stage Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 complex including rehearsal halls and foyer 13 IC-EDP/MAR- 6 Contract with Expert in architectural solutions Post Aug-17 Sep-17 Sep-17 N/A Oct-17 Jun-19 Contract with Expert in structural solutions 14 IC-EDP/MAR- 7 (enfrce concrt structur s Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 (reinforced concrete structures) 15 IC-EDP/MAR- 8 Contract with Expert in structural solutions (metal Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 structures) Contract with Expert in engineering solutions 16 IC-EDP/MAR- 9 (electrical power supply, electrical equipment and Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 electric lighting) Contract with Expert in engineering solutions 17 IC-EDP/MAR- 10 (automation and supervisory control of the building Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 services); low power networks and systems I -___ I I I Contract with Expert in engineering solutions 18 IC-EDP/MAR- 1 (hea1ti Eiltin nir oin Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 (heating, ventilation and air conditioning) 19 IC-EDP/MAR- 12 Contract with Expert in fire safety measures Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 Contract with Expert in general construction works 20 IC-EDP/MAR- 13 estimates Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 21 IC-EDP/MAR- 14 Contract with Expert in restoration works estimates Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 22 IC-EDP/MAR- 15 Contract with Expert in huildings services and utility Post Aug-17 Sep-17 Sep-17 N/A Sep-17 Jun-19 networks estimates