Procurement Plan National Ganga River Basin Project [P119085] I. General Bank’s approval Date of the procurement Plan : Project approval date is May 31, 2011 with effectiveness date of Aug 18, 2011 2. Date of General Procurement Notice: Original date *Not known* but revised Jan 31, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year July 2016 to Mar 31, 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$ 2 million 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million 5. Non-Consultant Services Above US$ 1 million 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project available with the team. 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] ICB / NCB works packages financed under retroactive financing in the early project phase. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) Refer to Procurement Plan in STEP Portal III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 1 million 2. Single Source (Firms) All 3. Individual Above US$300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_800,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule Refer to Procurement Plan in STEP Portal PROCUREMENT India : IN National Ganga River Basin Project PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2016-06-09 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-08-22 Project ID: P119085 GPN Date: Project Name: IN National Ganga River Basin Project Loan / Credit No: IBRD / 80650, IDA / 49550 Executing Agency(ies): National Mission for Clean Ganga WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 29-Ref No. 865/610/57 / WBR 29-Design, Build, and 10 Years Operation and Component One: Institutional Maintenance of STP of 14 mld IBRD / 80650 Development Single Stage - One Capacity including 14 mld Main Prior Request for Bids Open - National 0.00 8,645,587.84 Signed 2014-10-01 2014-10-29 IDA / 49550 Component Two: Priority Envelope Pumping Station, 43 mld Effluent Infrastructure Investments Pumping Station, Appurtenant Structures at Salori, Allahabad, Uttar Pradesh WBR 31-Pkg 02/SE(N)/GAP/KMDA of 14-15 / WBR 31-[i]Design & Build STP of installed cap. 16 MLD including Component One: Institutional all appurtenant structures & Development Single Stage - One allied works;[ii] survey,review IBRD / 80650 Prior Request for Bids Open - International 46,000,000.00 41,534,827.15 Signed 2015-11-10 2015-11-20 Component Two: Priority Envelope designs,redesign where Infrastructure Investments necessary & build new UG sewerage network of about 227 km;[iii] O & M of 10 Yrs in Halisahar, West Bengal WBR 35-NGRBA/PP14- 15/SPMG/JH/W/01 / WBR 35- Component One: Institutional NGRBA/PP14- Development Single Stage - One IBRD / 80650 Prior Request for Bids Open - National 16,500,000.00 20,309,341.81 Signed 2015-10-05 2016-03-04 15/SPMG/JH/W/01: Sewerage Component Two: Priority Envelope Scheme and STP at Sahibganj, Infrastructure Investments Jharkhand WBR 38-Sewer Network-Dist Component One: Institutional C,Allahabad / WBR 38-Sewer Development Single Stage - One IBRD / 80650 Prior Request for Bids Open - National 29,000,000.00 19,416,542.28 Signed 2015-02-20 2015-03-23 Network in District C at Component Two: Priority Envelope Allahabad Infrastructure Investments WBR 40-Sewer Network in Dist A-Allahabad / Survey,Review Designs,Redesign where Necessary,Build New Sewerage Network of About 242 Kms. Component One: Institutional Length,3 Sewage Pumpings IBRD / 80650 Development Single Stage - One Prior Request for Bids Open - International 43,000,000.00 42,556,814.58 Signed 2015-03-27 2015-04-17 Stations Including All IDA / 49550 Component Two: Priority Envelope Appurtenant Infrastructure Investments Structures,Operation and Maintenance of Sewerage Network and Pumping Stations for 10 Yrs-Dist A,Allaha WBR 41-NGRBA/PP14- 15/SPMG/WB/W/01 / WBR 41- NGRBA/PP14- 15/SPMG/WB/W/01-Design & Build of STP Installed Cap 9.3 Component One: Institutional MLD [incl EPS] & All Development Single Stage - One IBRD / 80650 Prior Request for Bids Open - National 0.00 28,576,535.65 Signed 2015-12-02 2016-01-06 Appurtenant Str & Allied Component Two: Priority Envelope Works;Survey,Review Infrastructure Investments Designs,Redesign & Build New U/ground Sew Network;O&M of 10 Yrs Complete STP in Budge Budge, West Bengal WBR 42 - Wastewater Project, Narora, UP / DESIGN AND BUILD SEWAGE TREATMENT PLANTOF INSTALLED CAPACACITY 4.0 MLD S.T.P Component One: Institutional AND ALL APPURTENANT IBRD / 80650 Development Single Stage - One STRUCTURES AND ALLIED Prior Request for Bids Open - National 7,500,000.00 7,066,427.28 Signed 2015-05-03 2015-05-20 IDA / 49550 Component Two: Priority Envelope WORKS;(ii) SURVEY, REVIEW Infrastructure Investments THE DESIGNS, REDESIGN WHERE NECESSARY, AND BUILD NEW UNDERGROUND SEWERAGE NETWORK OF ABOUT 21.03 KM Length. WBR 47 / Survey, Review The Designs, Redesign Where Necessary And Build New Sewerage Network Of About 215 Component One: Institutional Km Length Including Survey, Development Single Stage - One IBRD / 80650 Prior Request for Bids Open - International 0.00 34,131,919.50 Signed 2016-05-05 2016-06-10 Design, Construction Of 2 Nos. Component Two: Priority Envelope Pumping Stations , And Infrastructure Investments Operation & Maintenance Of Sewerage Network in District-B, Allahabad, U.P. WBR No. 52 / O &M of sewage treatment plan, sewerage Component One: Institutional network and pumping stations for Development Single Stage - One a period of 10 years in IBRD / 80650 Prior Request for Bids Open - National 0.00 11,952,621.07 Signed 2015-11-17 2015-12-30 Component Two: Priority Envelope ANUPSHAHAR TOWN OF Infrastructure Investments DISTT. BULANDSHAHAR, UTTAR PRADESH. Page 1 IN-NMCG-1877-CW-RFB / Survey, review and designs, redesign where necessary and build new sewerage network of Component Two: Priority Single Stage - One about 180 km length and all IBRD / 80650 Prior Request for Bids Open - International 38,590,000.00 61,829,767.70 Signed 2016-09-23 2016-09-28 2016-11-09 2016-12-09 2016-09-27 2017-01-13 2017-03-30 2017-07-12 Infrastructure Investments Envelope appurtenant structures and Operation and Maintenance of Sewerage network for a period of 10 years at Beur in Patna NGRBA/PP14- 15/SPMG/BH/W/05B / Survey, review and designs, redesign where necessary and build new sewerage network of about 180 Component Two: Priority Single Stage - One IBRD / 80650 Prior Request for Bids Open - International 38,590,000.00 0.00 Canceled 2016-09-19 2016-09-24 2016-11-05 2016-12-05 2016-09-21 2017-01-09 2017-07-08 km length and all appurtenant Infrastructure Investments Envelope structures and Operation and Maintenance of Sewerage network for a period of 10 years at Beur in Patna IN-NMCG-1878-CW-RFB / Survey, review and designs, redesign where necessary and build new sewerage network of Component Two: Priority Single Stage - One Under about 172 km length and all IBRD / 80650 Prior Request for Bids Open - International 44,770,000.00 66,923,168.58 2016-09-23 2016-09-28 2016-11-09 2016-12-09 2016-09-27 2017-01-13 2017-07-12 Infrastructure Investments Envelope Implementation appurtenant structures and Operation and Maintenance of Sewerage network for a period of 10 years at Saidpur in Patna NGRBA/PP14- 15/SPMG/BH/W/07B / Survey, review and designs, redesign where necessary and build new sewerage network of about 172 Component Two: Priority Single Stage - One IBRD / 80650 Prior Request for Bids Open - International 44,770,000.00 0.00 Canceled 2016-09-20 2016-09-25 2016-11-06 2016-12-06 2016-09-21 2017-01-10 2017-07-09 km length and all appurtenant Infrastructure Investments Envelope structures and Operation and Maintenance of Sewerage network for a period of 10 years at Saidpur in Patna IN-NMCG-2984-CW-RFB / Survey, review designs, redesign where necessary & build new sewerage network of 102Km length and Rehabilitation of Component Two: Priority Single Stage - One Under IBRD / 80650 Prior Request for Bids Open - International 56,985,000.00 48,052,961.92 2016-11-04 2016-12-09 2016-11-09 2016-12-22 2016-12-21 2017-02-28 2017-01-20 2017-07-19 2017-02-24 2017-08-23 Existing network of 300km length Infrastructure Investments Envelope Implementation incl. 4No. pumping stations & all appurtenant structures; O&M of complete works in District-1, Kanpur IN-NMCG-2997-CW-RFB / Development of Ganga Data Component Two: Priority Single Stage - One Pending IBRD / 80650 Post Request for Bids Open - National 154,000.00 0.00 2016-12-07 2016-12-12 2017-01-23 2017-02-22 2017-03-29 2017-09-25 Centre at basement of CPCB Infrastructure Investments Envelope Implementation Delhi Office (Several Packages) IN-NMCG-2710-CW-RFB / Design & Build Sewage Treatment Plant of capacity Component Two: Priority Single Stage - One 18MLD & 6MLD; Survey, review IBRD / 80650 Prior Request for Bids Open - International 45,387,000.00 39,138,278.56 Signed 2016-10-20 2016-10-25 2016-12-06 2017-01-05 2016-11-21 2017-02-09 2016-10-26 2017-08-08 Infrastructure Investments Envelope designs, redesign Sewerage Network of 247Km length; O&M of complete works in Barrackpore IN-NMCG-2998-CW-RFB / Component Two: Priority Single Stage - One Under Sewerage Scheme and STP at IBRD / 80650 Prior Request for Bids Open - National 13,626,000.00 0.00 2016-11-09 2016-11-14 2016-12-26 2017-01-25 2017-03-01 2017-08-28 Infrastructure Investments Envelope Implementation Muni-ki-Reti, Dhalwala IN-NMCG-3012-CW-RFB / Component Two: Priority Single Stage - One Pending Haridwar (Phase I & II), Municipal IBRD / 80650 Prior Request for Bids Open - International 53,218,000.00 0.00 2016-11-09 2016-11-14 2016-12-26 2017-01-25 2017-03-01 2017-08-28 Infrastructure Investments Envelope Implementation Waste Water (MWW) IN-NMCG-3015-CW-RFB / River Component Two: Priority Single Stage - One Pending Front Development at Pilot, IBRD / 80650 Post Request for Bids Open - National 1,000,000.00 0.00 2017-02-02 2017-02-07 2017-03-21 2017-04-20 2017-05-25 2017-11-21 Infrastructure Investments Envelope Implementation Uttarakhand IN-NMCG-3027-CW-RFB / Component Two: Priority Single Stage - One Sewerage Treatment Plant ( IBRD / 80650 Prior Request for Bids Open - National 23,600,000.00 0.00 Under Review 2017-01-04 2017-01-09 2017-02-20 2017-03-22 2017-04-26 2017-10-23 Infrastructure Investments Envelope STP) at Pahari, Patna IN-NMCG-3030-CW-RFB / Component Two: Priority Single Stage - One Sewerage Scheme at Pahari IBRD / 80650 Prior Request for Bids Open - National 36,200,000.00 0.00 Under Review 2017-01-04 2017-01-09 2017-02-20 2017-03-22 2017-04-26 2017-10-23 Infrastructure Investments Envelope Zone IVA (S) at Pahari, Patna IN-NMCG-3033-CW-RFB / Component Two: Priority Single Stage - One Under Sewerage Scheme at Pahari IBRD / 80650 Prior Request for Bids Open - National 22,350,000.00 0.00 2017-01-04 2017-08-16 2017-01-09 2017-02-20 2017-03-22 2017-04-26 2017-10-23 Infrastructure Investments Envelope Implementation Zone-V at Pahari, Patna IN-NMCG-3039-CW-RFB / Design and Build Sewage Treatment Plant of capacity 23 MLD and Renovation of existing Component Two: Priority Single Stage - One Pending of 20 MLD STP and all IBRD / 80650 Prior Request for Bids Open - International 12,730,000.00 0.00 2016-11-05 2016-11-10 2016-12-22 2017-01-21 2017-02-25 2017-08-24 Infrastructure Investments Envelope Implementation appurtenant structures and allied works; and Operation and Maintenance of complete works at Beur, Patna IN-NMCG-3041-CW-RFB / Design and Build Sewage Treatment Plant of capacity 37 MLD including main pumping Component Two: Priority Single Stage - One Pending stations(58 MLD) and all IBRD / 80650 Prior Request for Bids Open - International 14,400,000.00 0.00 2016-11-05 2016-11-10 2016-12-22 2017-01-21 2017-02-25 2017-08-24 Infrastructure Investments Envelope Implementation appurtenant structures and allied works; and Operation and Maintenance of complete works at Karmalichak, Patna Page 2 IN-NMCG-3045-CW-RFB / Survey, review the designs, redesign where necessary and build new sewerage network of Component Two: Priority Single Stage - One Under about 97 km length and all IBRD / 80650 Prior Request for Bids Open - National 28,600,000.00 0.00 2016-11-04 2017-02-22 2016-11-09 2017-04-06 2016-12-21 2017-08-10 2017-01-20 2017-02-24 2017-08-23 Infrastructure Investments Envelope Implementation appurtenant structures and Operation and Maintenance of Sewerage network for a period of 10 years at Karmalichak in Patna IN-NMCG-3053-CW-RFB / (i) Design & Build Sewage Treatment Plant of capacity 60MLD; (ii) Survey, review designs, redesign where Component Two: Priority Single Stage - One Pending IBRD / 80650 Prior Request for Bids Open - International 32,540,000.00 0.00 2016-11-05 2016-11-10 2016-12-22 2017-01-21 2017-02-25 2017-08-24 necessary & build new sewerage Infrastructure Investments Envelope Implementation network of 55Km length & all appurtenant structures; (iii) O&M of complete works in Saidpur, Patna IN-NMCG-3056-CW-RFB / River Component Two: Priority Single Stage - One Pending IBRD / 80650 Prior Request for Bids Open - National 17,270,000.00 0.00 2016-11-05 2016-11-10 2016-12-22 2017-01-21 2017-02-25 2017-08-24 Front Development at Buxar Infrastructure Investments Envelope Implementation IN-NMCG-3222-CW-RFB / Survey, Soil testing, Design, Supply, Construction, Testing And Commissioning of Sewerage Component Two: Priority Single Stage - One Under IBRD / 80650 Prior Request for Bids Open - National 21,515,151.00 0.00 2016-11-11 2016-11-16 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Works in Sewerage District E of Infrastructure Investments Envelope Implementation Allahabad, excluding Operation & Maintenance, Retro- Allahabad Dist. E IN-NMCG-2990-CW-RFQ / Civil and Electrical Works in Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 33,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Instrumentation Lab for CPCB Development Quotations Envelope Implementation Delhi IN-NMCG-2991-CW-RFQ / Supply, Installation, Testing and Component One: Institutional Request for Single Stage - One Pending Commissioning of 21 HP VRF Air IBRD / 80650 Post Open - National 23,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Development Quotations Envelope Implementation Conditioning for Instrumentation Lab for CPCB Delhi IN-NMCG-2992-CW-RFQ / Supply, Installation, Testing and Component One: Institutional Request for Single Stage - One Pending Commissioning of Laboratory IBRD / 80650 Post Open - National 40,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Development Quotations Envelope Implementation furniture for Instrumentation Lab for CPCB Delhi IN-NMCG-2993-CW-RFQ / Supply, Installation, Testing and Commissioning of Modular Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 19,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Seating furniture for Development Quotations Envelope Implementation Instrumentation Lab for CPCB Delhi IN-NMCG-2994-CW-RFQ / Supply, Installation, Testing and Component One: Institutional Request for Single Stage - One Pending Commissioning of Fume Hoods IBRD / 80650 Post Open - National 21,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Development Quotations Envelope Implementation for Instrumentation Lab for CPCB Delhi IN-NMCG-2995-CW-RFQ / Supply, Installation, Testing and Component One: Institutional Request for Single Stage - One Pending Commissioning of Gas Pipeline IBRD / 80650 Post Open - National 21,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Development Quotations Envelope Implementation System for Instrumentation Lab for CPCB Delhi IN-NMCG-2996-CW-RFQ / Supply, Installation, Testing and Component One: Institutional Request for Single Stage - One Pending Commissioning of 25 KVA UPS IBRD / 80650 Post Open - National 12,000.00 0.00 2016-12-07 2017-02-01 2017-07-31 Development Quotations Envelope Implementation for Instrumentation Lab for CPCB Delhi IN-NMCG-3013-CW-RFQ / Office Component One: Institutional Request for Single Stage - One Pending Interior Works at New SPMG IBRD / 80650 Post Open - National 70,000.00 0.00 2017-01-09 2017-03-06 2017-09-02 Development Quotations Envelope Implementation Office, Uttarakhand IN-NMCG-1982-CW-RFB / (i) Design & Build Sewage Treatment Plant of capacity 2.6MLD; (ii) Survey, review designs, redesign where Component Two: Priority Single Stage - One Under IBRD / 80650 Prior Request for Bids Open - National 9,182,000.00 0.00 2016-09-28 2016-10-03 2016-11-14 2016-12-14 2017-01-18 2017-07-17 necessary & build new sewerage Infrastructure Investments Envelope Implementation network of 32Km length incl. 2No. pumping stations &all appurtenant structures; (iii) O&M of complete works in Bithoor IN-NMCG-3057-CW-RFB / Solid Component Two: Priority Single Stage - One Pending Waste Management at IBRD / 80650 Prior Request for Bids Open - National 23,477,000.00 0.00 2016-11-11 2016-11-16 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Infrastructure Investments Envelope Implementation Sahebganj and Rajmahal IN-NMCG-9157-CW-RFB / Component Two: Priority Single Stage - One Under Sewage Treatment Plant with 15 IBRD / 80650 Prior Request for Bids Open - International 40,961,000.00 0.00 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 Infrastructure Investments Envelope Implementation years O&M at Haridwar IN-NMCG-8712-CW-RFB / Municipal Wastewater Project, Component Two: Priority Single Stage - One Under Haridwar (Interception & IBRD / 80650 Prior Request for Bids Open - National 17,471,000.00 0.00 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 Infrastructure Investments Envelope Implementation Diversion of Nalas and Treatment Works) IN-NMCG-20828-CW-RFB / Sewage Treatment Plant with 15 Component Two: Priority Single Stage - One Under years O&M at Muni-Ki-Reti & IBRD / 80650 Prior Request for Bids Open - National 10,085,000.00 0.00 2017-07-21 2017-07-26 2017-09-06 2017-10-06 2017-11-10 2018-05-09 Infrastructure Investments Envelope Implementation Dhalwala (Tehri Garhwal) in Uttarakhand IN-NMCG-3058-CW-RFB / Component Two: Priority Single Stage - One Sewerage Scheme and STP at IBRD / 80650 Prior Request for Bids Open - National 9,057,000.00 0.00 Canceled 2016-11-11 2016-11-16 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Infrastructure Investments Envelope Rajmahal, Jharkhand Page 3 IN-NMCG-17880-CW-RFB / Design and Build One STP of 3.5MLD and appurtenant structures, Survery Review Design and build new UG Component Two: Priority Single Stage - One Under IBRD / 80650 Post Request for Bids Open - National 7,300,000.00 0.00 2017-06-21 2017-06-26 2017-08-07 2017-09-06 2017-10-11 2018-04-09 Sewerage Network of about Infrastructure Investments Envelope Implementation 34.21km, including O&M of complete works of 10 years at Rajmahal Town, District Sahibganj, Jharkhand IN-NMCG-19836-CW-RFB / Interception & Diversion of Nalas Component One: Institutional Single Stage - One IBRD / 80650 Post Request for Bids Open - National 5,868,000.00 0.00 Canceled 2017-07-14 2017-07-19 2017-08-30 2017-09-29 2017-11-03 2018-05-02 including 1 year O&M in Development Envelope Rishikesh, Uttarakhand IN-NMCG-24434-CW-RFB / A. Interception & Diversion of Nalas including 1 year O&M in Rishikesh, Uttarakhand. Component Two: Priority Single Stage - One Under B. DBOT of Sewage Treatment IBRD / 80650 Prior Request for Bids Open - National 21,868,000.00 0.00 2017-08-31 2017-08-18 2017-09-05 2017-10-17 2017-11-16 2017-12-21 2018-06-19 Infrastructure Investments Envelope Implementation Plant of 26 MLD capacity including 15 yrs O&M in Lakkarghat, Rishikesh, Uttarakhand. IN-NMCG-17756-CW-RFB / DBOT of Sewage Treatment Plant of 26 MLD capacity Component Two: Priority Single Stage - One IBRD / 80650 Prior Request for Bids Open - National 16,000,000.00 0.00 Canceled 2017-06-16 2017-08-01 2017-06-21 2017-08-02 2017-09-01 2017-10-06 2018-04-04 including 15 years O &M in Infrastructure Investments Envelope Lakkarghat , Rishikesh, Uttarakhand IN-NMCG-25686-CW-RFB / I&D and STP Works including O&M of 1 year for I&D Works and 15 Component Two: Priority Single Stage - One Pending IBRD / 80650 Prior Request for Bids Open - National 12,549,000.00 0.00 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 years for STP at Muni-Ki-Reti & Infrastructure Investments Envelope Implementation Dhalwala (Tehri Garhwal) in Uttarakhand GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-NMCG-3085-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Information Systems Equipment IBRD / 80650 Post Open - National 10,000.00 0.00 2017-01-18 2017-03-15 2017-09-11 Development Quotations Envelope Implementation (Server) for West Bengal SPMG IN-NMCG-3090-GO-RFQ / Infrastructure - Vehicle Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 70,000.00 0.00 2016-12-27 2017-02-21 2017-08-20 (Monitoring/ Exhibition) for Development Quotations Envelope Implementation SPMG, Jharkhand IN-NMCG-3091-GO-RFQ / Data Computerisation/ data sets (incl. legacy data computerization, Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 15,000.00 0.00 2016-12-27 2017-02-21 2017-08-20 digitization, geolocation, of Development Quotations Envelope Implementation polluting industries etc.) at SPMG Jharkhand IN-NMCG-3094-GO-RFQ / Information system equipment (IT hardware including Desktops, Component One: Institutional Request for Single Stage - One Pending Laptops, Services, Media, LCD IBRD / 80650 Post Open - National 60,000.00 0.00 2016-12-27 2017-02-21 2017-08-20 Development Quotations Envelope Implementation Projectors, Video/Audio Conferencing, UPS) for SPMG, Jharkhand IN-NMCG-3067-GO-RFQ / Specialized software such as Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 46,000.00 0.00 2017-01-10 2017-03-07 2017-09-03 Google Professional, ARC info & Development Quotations Envelope Implementation allied software & maps for CPCB IN-NMCG-3069-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Computers & Printers (10 nos.) IBRD / 80650 Post Open - National 13,000.00 0.00 2017-01-10 2017-03-07 2017-09-03 Development Quotations Envelope Implementation for CPCB IN-NMCG-3071-GO-RFQ / Information Systems Equipment Component One: Institutional Request for Single Stage - One Pending (IT hardware, including desktops, IBRD / 80650 Post Open - National 10,000.00 0.00 2016-12-13 2017-02-07 2017-08-06 Development Quotations Envelope Implementation laptops, servers, media, LCD, UPS) for Uttarakhand SPMG IN-NMCG-3072-GO-RFQ / Officer refurbishing furniture, Air Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 22,000.00 0.00 2016-12-13 2017-02-07 2017-08-06 conditioners and other equipment Development Quotations Envelope Implementation at Uttarakhand SPMG Office IN-NMCG-3074-GO-RFQ / Information system equipment (IT hardware including desktops, Component One: Institutional Request for Single Stage - One Pending laptops servers, media, LCD/DLP IBRD / 80650 Post Open - National 76,000.00 0.00 2017-01-04 2017-03-01 2017-08-28 Development Quotations Envelope Implementation projectors, Video/Audio Conferencing Ups etc.) for UPSPMG. IN-NMCG-3077-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 38,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 Furniture for UPSPMG office Development Quotations Envelope Implementation IN-NMCG-3081-GO-RFQ / Information Systems Equipment Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 10,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 (Computers, printers, UPS) for Development Quotations Envelope Implementation West Bengal SPMG IN-NMCG-3082-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Software for computers for West IBRD / 80650 Post Open - National 10,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 Development Quotations Envelope Implementation Bengal SPMG Page 4 IN-NMCG-3084-GO-RFQ / Information Systems Equipment Component One: Institutional Request for Single Stage - One Pending (media, LCD/DLP projectors, IBRD / 80650 Post Open - National 10,000.00 0.00 2016-12-21 2017-02-15 2017-08-14 Development Quotations Envelope Implementation video/audio conferencing) for West Bengal SPMG IN-NMCG-3086-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Workstation for West Bengal IBRD / 80650 Post Open - National 10,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 Development Quotations Envelope Implementation SPMG staff IN-NMCG-3088-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Information System Equipment IBRD / 80650 Post Open - National 75,000.00 0.00 2016-12-27 2017-02-21 2017-08-20 Development Quotations Envelope Implementation for SPMG, Jharkhand IN-NMCG-3066-GO-RFB / IT Component One: Institutional Single Stage - One Pending IBRD / 80650 Post Request for Bids Open - National 109,000.00 0.00 2016-12-08 2016-12-13 2017-01-24 2017-02-23 2017-03-30 2017-09-26 Hardware for CPCB Development Envelope Implementation IN-NMCG-3068-GO-RFB / Data Computerization/ Data Set for CPCB (Legacy data computerization, Component One: Institutional Single Stage - One Pending digitization, geolocation of IBRD / 80650 Post Request for Bids Open - National 600,000.00 0.00 2016-12-08 2016-12-13 2017-01-24 2017-02-23 2017-03-30 2017-09-26 Development Envelope Implementation polluting industries, Advance GPS tracking devices, specific softwares/ hardwares and networking facilities etc.) IN-NMCG-3070-GO-RFB / Real Time Quality Monitoring Component Two: Priority Single Stage - One Pending Equipment at inlet and outlet IBRD / 80650 Post Request for Bids Open - National 121,000.00 0.00 2016-12-09 2016-12-14 2017-01-25 2017-02-24 2017-03-31 2017-09-27 Infrastructure Investments Envelope Implementation channel of STP at Allahabad as pilot project by CPCB IN-NMCG-3073-GO-RFB / Component One: Institutional Single Stage - One Pending Information system Equipment IBRD / 80650 Post Request for Bids Open - National 227,000.00 0.00 2017-01-20 2017-01-25 2017-03-08 2017-04-07 2017-05-12 2017-11-08 Development Envelope Implementation for UPPCB IN-NMCG-3076-GO-RFB / Specialized Software including Component One: Institutional Single Stage - One Pending for GIS database Modeling and IBRD / 80650 Post Request for Bids Open - National 152,000.00 0.00 2016-12-02 2016-12-07 2017-01-18 2017-02-17 2017-03-24 2017-09-20 Development Envelope Implementation Communication etc. for UPSPMG IN-NMCG-3078-GO-RFB / Laboratory equipment (Lab Component One: Institutional Single Stage - One Pending IBRD / 80650 Post Request for Bids Open - National 1,179,000.00 0.00 2016-12-23 2016-12-28 2017-02-08 2017-03-10 2017-04-14 2017-10-11 safety, processing & Development Envelope Implementation preservation) for UPPCB IN-NMCG-3079-GO-RFB / Component One: Institutional Single Stage - One Pending Laboratory equipment IBRD / 80650 Post Request for Bids Open - National 1,330,000.00 0.00 2017-01-20 2017-01-25 2017-03-08 2017-04-07 2017-05-12 2017-11-08 Development Envelope Implementation Instrumentation for UPPCB IN-NMCG-3080-GO-RFB / Information Systems Equipment (IT hardware, including desktops, Component One: Institutional Single Stage - One Pending laptops, servers, media, IBRD / 80650 Post Request for Bids Open - National 250,000.00 0.00 2016-12-01 2016-12-06 2017-01-17 2017-02-16 2017-03-23 2017-09-19 Development Envelope Implementation LCD/DLP projectors, video/audio conferencing, UPS) for Bihar SPMG IN-NMCG-3092-GO-RFB / Office Component One: Institutional Single Stage - One Pending automation equipment for IBRD / 80650 Post Request for Bids Open - National 200,000.00 0.00 2016-11-24 2016-11-29 2017-01-10 2017-02-09 2017-03-16 2017-09-12 Development Envelope Implementation ULB/SPCB, Jharkhand IN-NMCG-3059-GO-RFB / Information Systems Equipment (IT hardware, including desktops, Component One: Institutional Single Stage - One Pending laptops, servers, media, IBRD / 80650 Post Request for Bids Open - National 136,000.00 0.00 2016-11-23 2016-11-28 2017-01-09 2017-02-08 2017-03-15 2017-09-11 Development Envelope Implementation LCD/DLP projectors, video/audio conferencing, UPS) for NGRBA PMG IN-NMCG-3060-GO-RFB / IT Component Two: Priority Single Stage - One Pending IBRD / 80650 Post Request for Bids Open - National 150,000.00 0.00 2017-02-03 2017-02-08 2017-03-22 2017-04-21 2017-05-26 2017-11-22 Hardware and Software (GKC) Infrastructure Investments Envelope Implementation IN-NMCG-3064-GO-RFB / Procurement of instruments/equipment's for Component One: Institutional Single Stage - One Pending water quality monitoring and IBRD / 80650 Post Request for Bids Open - National 128,000.00 0.00 2016-11-11 2016-11-16 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Development Envelope Implementation testing for CPCB at New Delhi as well as Zonal offices level (Several Packages) IN-NMCG-3061-GO-RFQ / Component Two: Priority Request for Single Stage - One Pending IBRD / 80650 Post Open - National 83,000.00 0.00 2017-03-08 2017-05-03 2017-10-30 Remote Sensing Data, GKC Infrastructure Investments Quotations Envelope Implementation IN-NMCG-3062-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Books/Journal/Library/E- IBRD / 80650 Post Open - National 40,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 Development Quotations Envelope Implementation Resources (GKC) IN-NMCG-3063-GO-RFQ / Component One: Institutional Request for Single Stage - One Pending Portable Water Quality IBRD / 80650 Post Open - National 30,000.00 0.00 2016-12-14 2017-02-08 2017-08-07 Development Quotations Envelope Implementation Monitoring kits for CPCB IN-NMCG-3065-GO-RFQ / Microscopes for Bio-monitoring Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 60,000.00 0.00 2017-01-10 2017-03-07 2017-09-03 laboratory for CPCB Delhi office Development Quotations Envelope Implementation and for Zonal office IN-NMCG-25563-GO-RFQ / Procurement of Samsung Component One: Institutional Request for Single Stage - One Pending IBRD / 80650 Post Open - National 11,000.00 0.00 2017-09-05 2017-10-31 2018-04-29 MagicInfo Premium Software Development Quotations Envelope Implementation (iPlayer) for CPCB NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 Component One: Institutional WBR No. 49 / Procurement of Development Single Stage - One continuous real time water IBRD / 80650 Prior Request for Bids Open - International 0.00 4,081,312.50 Signed 2016-03-01 2016-07-11 Component Two: Priority Envelope quality monitoring data Infrastructure Investments IN-NMCG-2987-NC-RFB / Procurement of continuous real Component Two: Priority Single Stage - One Pending IBRD / 80650 Prior Request for Bids Open - International 4,200,000.00 0.00 2016-11-24 2016-11-29 2017-01-10 2017-02-09 2017-03-16 2017-09-12 time water quality monitoring Infrastructure Investments Envelope Implementation data (2nd Phase) IN-NMCG-4716-NC-DIR / Exhibition on Ganga in Component One: Institutional IBRD / 80650 Post Direct Selection Direct 221,000.00 0.00 Canceled 2016-12-20 2016-12-17 2016-12-26 2017-01-02 2017-01-30 2017-07-29 Collaboration with National Development Museum CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 34-NGRBA/PP14- 15/SPMG/UK/C/02 / WBR 34- Component One: Institutional RFP No. NGRBA/PP14- IBRD / 80650 Development Quality And Cost- 15/SPMG/UK/C/02-Consultancy Prior Open - International 140,000.00 129,904.64 Signed 2015-08-30 2015-09-04 IDA / 49550 Component Two: Priority Based Selection Services for Rishikesh Municipal Infrastructure Investments Waste Water-RFP for DPR Preparation NGRBA/PP14- 15/SPMG/WB/C/05 / Consulting Services for Profiling and Component Two: Priority Quality And Cost- Under Preparation of DPRs for IBRD / 80650 Prior Open - National 600,000.00 0.00 2016-09-20 2016-10-11 2016-11-24 2016-12-22 2017-01-21 2016-11-04 2017-02-25 2017-04-01 2018-04-01 Infrastructure Investments Based Selection Implementation Demonstration Investments for Riverfront Development in Kolkata Metropolitan Area IN-NMCG-2983-CS-QCBS / Consultancy Services for CPCB Component One: Institutional Quality And Cost- Under IBRD / 80650 Prior Open - International 1,960,000.00 0.00 2016-11-04 2016-11-25 2017-01-08 2017-02-05 2016-10-31 2017-03-07 2017-04-11 2017-05-16 2018-05-16 for Real Time Data Qualification Development Based Selection Implementation Services Contractor (Consultant) IN-NMCG-5718-CS-QCBS / Consultancy Services for Component One: Institutional Quality And Cost- Under Strategic Environmental, IBRD / 80650 Post Open - National 736,000.00 0.00 2017-01-23 2017-01-19 2017-02-13 2017-03-01 2017-03-29 2017-04-26 2017-05-26 2017-06-30 2017-08-04 2018-08-04 Development Based Selection Implementation Economic and Social Assessment (SEESA) IN-NMCG-3102-CS-QCBS / Consultancy Services for Design & Supervision of RFD for Greater Rishikesh including Component Two: Priority Quality And Cost- IBRD / 80650 Prior Open - National 1,000,000.00 0.00 Canceled 2016-11-18 2016-12-09 2017-01-22 2017-02-19 2017-03-21 2017-04-25 2017-05-30 2018-05-30 Laxmanjhula, Ramjhula, Infrastructure Investments Based Selection Tapowan, Munikereti, Swargashram and interlinked Gram Panchayats, Uttarakhand IN-NMCG-2685-CS-QCBS / Consulting Services for Collection, Conveyance, Treatment and Disposal of Component Two: Priority Quality And Cost- Under IBRD / 80650 Prior Open - International 500,000.00 0.00 2016-10-19 2016-11-09 2016-12-23 2017-01-20 2017-02-19 2016-11-29 2017-03-26 2017-06-27 2017-04-30 2018-04-30 Wastewater from Drainage Infrastructure Investments Based Selection Implementation basins in Borough V,IX and XV of Kolkata Municipal Corporation, Kolkata, West Bengal IN-NMCG-3097-CS-QCBS / Consultancy Service for CPCB to Component One: Institutional Quality And Cost- Pending conduct a comprehensive IBRD / 80650 Prior Open - National 606,000.00 0.00 2016-11-18 2016-12-09 2017-01-22 2017-02-19 2017-03-21 2017-04-25 2017-05-30 2018-05-30 Development Based Selection Implementation pollution Inventory including research and training activities IN-NMCG-3099-CS-QCBS / Consultancy on Development of sustainable water quality Component One: Institutional Quality And Cost- Pending monitoring design aids and IBRD / 80650 Post Open - National 151,000.00 0.00 2016-11-17 2016-12-08 2017-01-21 2017-02-18 2017-03-20 2017-04-24 2017-05-29 2018-05-29 Development Based Selection Implementation customization of design aids for water quality planning and management for CPCB IN-NMCG-3104-CS-CQS / Consultant Consultancy services for Component One: Institutional Pending IBRD / 80650 Post Qualification Open - National 10,000.00 0.00 2017-02-16 2017-03-09 2017-04-22 2017-05-22 2017-06-26 2017-12-23 Preparation of DPR for RFD pilot Development Implementation Selection project at Rishikesh, Uttarakhand IN-NMCG-3105-CS-QCBS / Supervision consultancy services Component Two: Priority Quality And Cost- Pending IBRD / 80650 Prior Open - National 545,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 for Muni ki Reti sewerage project, Infrastructure Investments Based Selection Implementation Uttarakhand IN-NMCG-3107-CS-CQS / Consultant Consultancy services for Component One: Institutional Pending IBRD / 80650 Post Qualification Open - National 10,000.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-14 2017-03-21 2017-09-17 communication and outreach Development Implementation Selection services, Uttarakhand IN-NMCG-3108-CS-CQS / Specialized Consultancies for Consultant UPPCB to develop an integrated Component One: Institutional Pending IBRD / 80650 Post Qualification Open - National 30,000.00 0.00 2016-12-21 2017-01-11 2017-02-24 2017-03-26 2017-04-30 2017-10-27 on-line information system for Development Implementation Selection water quality management monitoring IN-NMCG-3109-CS-CQS / Consultancy Services to Uttar Consultant Pradesh State Program Component One: Institutional Pending IBRD / 80650 Post Qualification Open - National 37,000.00 0.00 2017-01-06 2017-01-27 2017-03-12 2017-04-11 2017-05-16 2017-11-12 Management Group for social Development Implementation Selection audit of state level NGRBA activities Page 6 IN-NMCG-3114-CS-CQS / Consultancy Service for Consultant Component One: Institutional Pending architectural design and detailing IBRD / 80650 Post Qualification Open - National 50,000.00 0.00 2017-02-03 2017-02-24 2017-04-09 2017-05-09 2017-06-13 2017-12-10 Development Implementation for Varanasi Demonstration DPR, Selection Uttar Pradesh IN-NMCG-3115-CS-QCBS / IEC Activities and social & Component One: Institutional Quality And Cost- Pending IBRD / 80650 Post Open - National 168,000.00 0.00 2016-12-02 2016-12-23 2017-02-05 2017-03-05 2017-04-04 2017-05-09 2017-06-13 2018-06-13 Environmental management plan, Development Based Selection Implementation Bihar IN-NMCG-3117-CS-CQS / Social Consultant Component One: Institutional Pending Audit of state level NGRBA IBRD / 80650 Post Qualification Open - National 30,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-14 2017-04-18 2017-10-15 Development Implementation activities, West Bengal Selection IN-NMCG-3118-CS-QCBS / Engagement of Third Party Component Two: Priority Quality And Cost- Pending IBRD / 80650 Post Open - National 100,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 Inspection (TPI) Agency, West Infrastructure Investments Based Selection Implementation Bengal IN-NMCG-3120-CS-CQS / Engagement of agency for Consultant Component One: Institutional Pending Communications and Public IBRD / 80650 Post Qualification Open - National 15,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-14 2017-04-18 2017-10-15 Development Implementation Outreach programme, West Selection Bengal IN-NMCG-3122-CS-QCBS / Specialist consultancy services Component One: Institutional Quality And Cost- Pending to state programme management IBRD / 80650 Prior Open - National 250,000.00 0.00 2016-12-23 2017-01-13 2017-02-26 2017-03-26 2017-04-25 2017-05-30 2017-07-04 2018-07-04 Development Based Selection Implementation group for various projects, Jharkhand IN-NMCG-3123-CS-QCBS / Technical assistance for ULBs Component One: Institutional Quality And Cost- Pending IBRD / 80650 Post Open - National 75,000.00 0.00 2016-12-23 2017-01-13 2017-02-26 2017-03-26 2017-04-25 2017-05-30 2017-07-04 2018-07-04 (Tech/Operating & Business Development Based Selection Implementation process outsourcing), Jharkhand IN-NMCG-3096-CS-QCBS / Component One: Institutional Quality And Cost- Pending IBRD / 80650 Post Open - National 22,500.00 0.00 2016-11-07 2016-11-28 2017-01-11 2017-02-08 2017-03-10 2017-04-14 2017-05-19 2018-05-19 Internal Audit for NMCG Development Based Selection Implementation IN-NMCG-3098-CS-QCBS / Consultancy for pilot project on Component One: Institutional Quality And Cost- Pending UAV (Unmanned Aerial Vehicle) IBRD / 80650 Post Open - National 30,000.00 0.00 2016-12-21 2017-01-11 2017-02-24 2017-03-24 2017-04-23 2017-05-28 2017-07-02 2018-07-02 Development Based Selection Implementation surveillance in polluted stretch of River Ganga for CPCB IN-NMCG-3101-CS-CQS / Consultant Consultancy service for Component One: Institutional Pending IBRD / 80650 Post Qualification Open - National 82,000.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-14 2017-03-21 2017-09-17 Institutional support to NGRBA Development Implementation Selection cell to CPCB (4 Consultant) IN-NMCG-3103-CS-FBS / Consultancy Services for Third Component Two: Priority Fixed Budget Pending IBRD / 80650 Post Open - National 30,000.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-12 2017-03-14 2017-04-18 2017-05-23 2018-05-23 party inspection of ongoing Infrastructure Investments Selection Implementation projects, Uttarakhand IN-NMCG-3116-CS-QCBS / Specialist consultancy services Component Two: Priority Quality And Cost- to state programme management IBRD / 80650 Prior Open - National 300,000.00 0.00 Canceled 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 Infrastructure Investments Based Selection group (PMC) for various projects, Bihar IN-NMCG-3239-CS-QCBS / Specialist consultancy services Component One: Institutional Quality And Cost- Pending to state programme management IBRD / 80650 Post Open - National 300,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 Development Based Selection Implementation group (PMC) for various projects, Bihar IN-NMCG-3124-CS-QCBS / Project Management Consultancy services for Component Two: Priority Quality And Cost- IBRD / 80650 Prior Open - National 1,000,000.00 0.00 Canceled 2016-12-23 2017-01-13 2017-02-26 2017-03-26 2017-04-25 2017-05-30 2017-07-04 2018-07-04 sewerage, RFD & Solid waste Infrastructure Investments Based Selection project in Sahibgunj & Rajmahal, Jharkhand IN-NMCG-3240-CS-QCBS / Project Management Consultancy services for Component One: Institutional Quality And Cost- Pending IBRD / 80650 Post Open - National 990,000.00 0.00 2016-11-17 2016-12-08 2017-01-21 2017-02-18 2017-03-20 2017-04-24 2017-05-29 2018-05-29 sewerage, RFD & Solid waste Development Based Selection Implementation project in Sahibgunj & Rajmahal, Jharkhand IN-NMCG-3119-CS-QCBS / Setting up of Project Component Two: Priority Quality And Cost- IBRD / 80650 Prior Open - National 1,000,000.00 0.00 Canceled 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 Management Consultancy, West Infrastructure Investments Based Selection Bengal IN-NMCG-3241-CS-QCBS / Setting up of Project Component One: Institutional Quality And Cost- Pending IBRD / 80650 Post Open - National 990,000.00 0.00 2016-12-09 2016-12-30 2017-02-12 2017-03-12 2017-04-11 2017-05-16 2017-06-20 2018-06-20 Management Consultancy, West Development Based Selection Implementation Bengal IN-NMCG-3242-CS-QCBS / Consultancy Services for Design & Supervision of RFD for Greater Component One: Institutional Quality And Cost- Pending Rishikesh including Laxmanjhula, IBRD / 80650 Post Open - National 990,000.00 0.00 2016-11-18 2016-12-09 2017-01-22 2017-02-19 2017-03-21 2017-04-25 2017-05-30 2018-05-30 Development Based Selection Implementation Ramjhula, Tapowan, Munikereti, Swargashram and interlinked Gram Panchayats, Uttarakhand IN-NMCG-3245-CS-QCBS / Component One: Institutional Quality And Cost- Pending Internal Audit for Uttar Pradesh IBRD / 80650 Post Open - National 22,500.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-12 2017-03-14 2017-04-18 2017-05-23 2018-05-23 Development Based Selection Implementation SPMG IN-NMCG-3246-CS-QCBS / Component One: Institutional Quality And Cost- Pending Internal Audit for Bihar and IBRD / 80650 Post Open - National 22,500.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-12 2017-03-14 2017-04-18 2017-05-23 2018-05-23 Development Based Selection Implementation Jharkhand SPMG IN-NMCG-3244-CS-QCBS / Component One: Institutional Quality And Cost- Pending Internal Audit for Uttarakhand IBRD / 80650 Post Open - National 22,500.00 0.00 2016-11-11 2016-12-02 2017-01-15 2017-02-12 2017-03-14 2017-04-18 2017-05-23 2018-05-23 Development Based Selection Implementation SPMG Page 7 NGRBA/PP-14- 15/SPMG/WB/C/03 / Component Two: Priority Quality And Cost- Pending Consultancy Services for DPR IBRD / 80650 Prior Open - National 500,000.00 0.00 2017-04-03 2017-04-24 2017-06-07 2017-07-05 2017-08-04 2017-09-08 2017-10-13 2018-10-13 Infrastructure Investments Based Selection Implementation preparation for Tolly's Nullah Clean Up IN-NMCG-7480-CS-QCBS / Component Two: Priority Quality And Cost- Annual Audit for Environment and IBRD / 80650 Prior Open - National 1,000,000.00 0.00 Canceled 2017-02-17 2017-03-29 2017-03-10 2017-04-23 2017-05-21 2017-06-20 2017-07-25 2017-08-29 2018-08-29 Infrastructure Investments Based Selection Social under NGRBA IN-NMCG-18031-CS-CQS / Consultant Component One: Institutional Pending Engagement of PR Agency for IBRD / 80650 Post Qualification Open - National 186,000.00 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-26 2017-10-31 2018-04-29 Development Implementation NMCG Selection IN-NMCG-18033-CS-QCBS / Component Two: Priority Quality And Cost- Pending Environment and Social Audit for IBRD / 80650 Post Open - National 77,500.00 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-24 2017-10-24 2017-11-28 2018-01-02 2019-01-02 Infrastructure Investments Based Selection Implementation NGRBA Projects INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 30- Heritage Mapping / Component One: Institutional Heritage mapping, River profiling IBRD / 80650 Development Under Prior Direct Selection Direct 0.00 64,957.81 2014-10-31 and visitor flow assessment of IDA / 49550 Component Two: Priority Implementation greater Rishikesh' Infrastructure Investments IN-NMCG-3111-CS-CDS / Consultancy Service for third Party inspection for Sewerage Component Two: Priority Pending IBRD / 80650 Post Direct Selection Direct 15,000.00 0.00 2017-02-03 2017-02-13 2017-04-19 2017-10-16 Works of District-B & Additional Infrastructure Investments Implementation sewer network District-E Allahabad, Uttar Pradesh IN-NMCG-3112-CS-CDS / Consultancy Service for third Component Two: Priority Pending Party inspection for Sewerage IBRD / 80650 Post Direct Selection Direct 15,000.00 0.00 2016-12-16 2016-12-26 2017-03-01 2017-08-28 Infrastructure Investments Implementation Scheme for Anupshahar & Narora, Uttar Pradesh IN-NMCG-5593-CS-CDS / Exhibition on Ganga in Component One: Institutional Under IBRD / 80650 Prior Direct Selection Direct 195,000.00 0.00 2017-01-12 2017-01-14 2017-01-22 2017-03-28 2017-09-24 Collaboration with National Development Implementation Museum Page 8