Annex 4 PROCUREMENT PLAN General 1. Project Information: Nigeria: Transforming Irrigation Management in Nigeria 2. Bank’s approval Date of the Procurement Plan: May 2014 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement Method Prior Threshold Review Procurement Method US$ Threshold ICB (Goods and Non- Equal to and above 1. consulting services) 5,000,000 All Equal to or NCB (Goods and Non- above US$ 2. Consulting Services) Below 5,000,000 1,000,000 Equal to or above 3 ICB (Works) 20,000,000 All Equal to or above 4. NCB (Works) Below 20,000,000 10,000,000 Below US$ Shopping (Goods) 100,000 None Shopping (Vehicles) - Below US$ From 1st line distributors 500,000 None Below US$ 5. Shopping (Works) 200,000 None 2. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 3. Procurement Packages with Methods 1 2 3 4 5 6 7 Re Description Estimat Procure Domes Revie Comme f. ed ment tic w nts No Cost Method Prefer by . US$ ence Bank million (yes/n (Prior o) / Post) 01 Rehabilitation 115 ICB No Prior of Bakalori Dam and Rehabilitation/I mprovement of Bakalori Irrigation Scheme 02 Rehabilitation 85 ICB No Prior and Improvement of Kano Irrigation Scheme 03 Rehabilitation 60 ICB No Prior and Extension of Hadejia Valley Irrigation Scheme 04 Rehabilitation 40 ICB No Prior of 6 No. Dams 05 Supply and 0.6 NCB No Post Installation of Hydrometric Equipment for Sokoto Rima Basin 06 Flood Plain 1.35 NCB No Prior Mapping for EPP (BIP & MRVIP) 07 Bathymetric 0.20 NCB No Post Survey of Goronyo, Zobe and Bakolori Dams 08 Procurement of 0.3 Shopping No Post Field and Operational Vehicles 09 Procurement of 0.1 Shopping No Post Computers 10 Procurement of 0.1 Shopping No Post Office Equipment III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Method Prior Review Threshold (USD) Threshold (USD) 1. Competitive Methods Equal to or above All (Firms); QCBS, QBS, LCS, 300,000 FCS 2. Consultant Qualification Below 300,000 None 3. Single Source Selection N/A All (Firms & Individuals) 4. Individuals N/A Above 100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. Description of Estimat Selecti Review Comments No. Assignment ed on by Bank Cost Metho (Prior / US$ d Post) Million 01 Engineering 2.7 QCBS Prior Supervision of the Rehabilitation of Bakalori Dam and Irrigation Scheme 02 Technical Assistance 2.0 QCBS Prior for Dam Safety Assurance & Training for Dam & Reservoir Dept. and RBDA Staff 03 Dam Safety Panel of 1.0 IC Prior Series of Experts individual consultant contracts on specific aspects of dam 04 Technical Feasibility 2.0 QCBS Prior and detailed Design of Dadin Kowa Irrigation Scheme 05 Engineering 1.5 QCBS Prior Supervision of Rehabilitation and Extension of Kano Rima Irrigation Scheme 06 Engineering 0.65 QCBS Prior Supervision of Rehabilitation and Extension of Hadejia Valley Irrigation Scheme 07 Elaboration of 1.0 QCBS Prior Resettlement Action Plan for Kano River and Hadejia Valley Irrigation Schemes 08 Technical Assistance 1.5 QCBS Prior for WUA in Bakalori and Middle Rima Valley Irrigation Schemes 09 Technical Assistance 1.0 QCBS Prior for WUA in Kano River and Hadejia Valley Irrigation Schemes. 10 Technical Assistance 4.0 QCBS Prior on Farmers-Market Linkages and for the Establishment of FMCs 11 Support to RBDAs; 1.5 QCBS Prior Assessment, capacity Building and Strategic Planning 12 Development of 1.0 QCBS Prior Information Database and information System 13 Development of an 1.0 QCBS Prior Electronic and Document Management System 14 ESIA for Kano River 0.6 QCBS Prior and Hadejia Valley Irrigation Schemes 15 ESIA for Dadin Kowa 0.5 QCBS Prior Irrigation Scheme 16 ESIA for Middle Rima 0.1 IC Prior Valley Irrigation Scheme 17 Development of M&E 0.06 IC Post Manual 18 Development of 0.06 IC Post Financial Management Manual 19 Applied Research 2.3 N/A Prior Grantees Grant on Irrigated will be Agriculture selected competitivel y on the bases of Call for Research Proposals PROCUREMENT Nigeria : Transforming Irrigation Management in Nigeria PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-04-05 2021-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P123112 GPN Date: Project Name: Transforming Irrigation Management in Nigeria Loan / Credit No: IDA / 55060 Transforming Irrigation Management In Nigeria Federal Coordinating Office Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-TRIMING NCO-12728- CW-RFB / River Training Component 1: Water Single Stage - One 4,538,527.0 2020-06- Works in the Hadejia-Jama’are IDA / 55060 Resources Management and Prior Request for Bids Open - National 5,100,000.00 Signed 2017-02-09 2017-06-05 2017-02-09 2017-05-04 2017-05-04 2017-06-19 2017-10-23 2017-07-31 2018-05-24 Envelope 7 29 River Basin Located in Jigawa Dam Operation Improvement. State, Nigeria NG-TRIMING NCO-12726- CW-RFB / Works for Component 1: Water Single Stage - One 125,000,000. 2021-09- Rehabilitation and Expansion IDA / 55060 Resources Management and Prior Request for Bids Open - International 0.00 Canceled 2017-03-23 2017-06-06 2017-03-23 2017-05-18 2017-06-29 2017-07-17 2017-09-13 Envelope 00 06 of Irrigation Scheme in KRIS Dam Operation Improvement. and HVIS NG-TRIMING NCO-14084- Component 2: Irrigation CW-RFB / Works for Single Stage - One 79,920,874.0 110,425,88 2021-03- IDA / 55060 Development and Prior Request for Bids Open - International Signed 2016-02-01 2016-02-23 2016-05-03 2016-05-03 2016-08-06 2017-05-10 2017-03-29 2017-03-29 Rehabilitation and Conversion Envelope 0 3.81 08 Management. of Bakolori Irrigation Scheme NG-TRIMING NCO-19039- CW-RFB / Rehabilitation of Component 4: Institutional Single Stage - One 2016-07- 4Nos Houses for TRIMING IDA / 55060 Development and Project Post Request for Bids Open - National 239,862.00 177,675.51 Signed 2015-11-11 2015-11-11 2015-11-11 2015-12-15 2015-12-09 2016-01-08 2016-02-02 2016-01-18 2017-01-18 Envelope 16 field officers at Bunkure under Management. KRIP in Kano State FMWR/TRIMING/2018/ICB/W/ Component 1: Water 01 / Dam Safety improvement Single Stage - One 96,000,000.0 2022-02- IDA / 55060 Resources Management and Prior Request for Bids Open - International 0.00 Canceled 2018-06-29 2018-07-27 2018-10-05 2018-11-02 2019-01-25 works of Bakolori, Zobe and Envelope 0 25 Dam Operation Improvement. Goronyo dams in two lots FMWR/TRIMING/2018/SH/W/ 01 / Rehabilitation of additional 3 Nos House for Housing of community radio Component 2: Irrigation at Hadejia Valley Irrigation Request for Single Stage - One 2018-10- IDA / 55060 Development and Post Open - National 200,000.00 145,713.04 Completed 2018-03-31 2018-05-04 2018-06-12 Scheme, Dadinkkowa and Quotations Envelope 15 Management. Goronyo Irrigation Schemes and Remodeling of Studio rooms at Bakolori and Kano Scheme FMWR/TRIMING/2018/SH/W/ 02 / Upgrading and Securing of 4nos Agricultural Component 3: Enhancing Request for Single Stage - One 2018-09- Development Projects offices IDA / 55060 Agricultural Productivity and Post Open - National 70,000.00 52,052.92 Completed 2018-04-25 2018-05-28 2018-05-16 Quotations Envelope 12 allocated for TRIMING project Support to Value Chains. Farmers Field and Business School activities FMWR/TRIMING/2018/NCB/W /02 / Construction of Tomato Collection Centers in Kano River Irrigation Scheme to Component 3: Enhancing Single Stage - One 2018-11- support tomato farmers in IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 700,000.00 0.00 Canceled 2018-03-21 2018-03-26 2018-05-02 2018-05-23 2018-07-20 Envelope 17 their productive alliances with Support to Value Chains. Dangote tomato processing company and other offtakers in Nigeria FMWR/TRIMING/2018/SH/W/ 04 / Additional works at Kano River Irrigation Scheme, Hadejia Valley Irrigation Component 2: Irrigation Request for Single Stage - One 2018-09- Scheme and Bakolori Irrigation IDA / 55060 Development and Post Open - National 200,000.00 144,594.80 Completed 2018-03-24 2018-05-03 2018-05-17 Quotations Envelope 24 Scheme including one block, Management. fence, gate houses, landscaping and BTC security wire FMWR/TRIMING/2016/ICB/W/ 002 / Rehabilitation & Expansion of Kano River Component 1: Water Irrigation Scheme (KRIS) and Single Stage - One 125,000,000. 98,110,626. 2022-04- IDA / 55060 Resources Management and Prior Request for Bids Open - International Signed 2017-03-17 2017-03-23 2017-06-29 2017-06-29 2017-12-18 2018-04-18 2018-05-16 2018-07-06 Hadejia Valley Irigation Envelope 00 64 29 Dam Operation Improvement. Scheme (HVIS) and Dam Safety Remedial Works in Kano and Hadejia NG-TRIMING NCO-76567- CW-RFQ / Rehabilitation of Adjourning Structures, Fencing and Landscapping of Component 2: Irrigation Request for Single Stage - One 2018-12- Farmers Meeting Hall, and IDA / 55060 Development and Post Open - National 95,000.00 78,119.81 Completed 2018-09-13 2018-10-17 2018-12-24 Quotations Envelope 16 Provisions of 8 Nos Management. 1,000litres Water Tanks and Distribution to Residential Apartments at BIS NG-TRIMING NCO-76571- CW-RFQ / Emergency repairs Component 1: Water Request for Single Stage - One 2018-12- of Goronyo dam Spillway IDA / 55060 Resources Management and Post Open - National 200,000.00 142,581.60 Completed 2018-09-07 2018-10-15 2019-02-14 Quotations Envelope 14 Radial Gate and Gantry Cranes Dam Operation Improvement. (as advised by DPoEs) NG-TRIMING NCO-76533- CW-RFQ / Emergency repairs Component 1: Water Request for Single Stage - One 2018-12- of Goronyo dam Toe Drain IDA / 55060 Resources Management and Post Open - National 150,000.00 122,802.17 Completed 2018-09-20 2018-10-19 2019-02-14 Quotations Envelope 18 Pump House and Pumps (as Dam Operation Improvement. strongly advised by DPoE) Page 1 NG-TRIMING NCO-76528- CW-RFQ / Emergency Rehabilitation of 3No. 3- Component 2: Irrigation Pending Request for Single Stage - One 2018-12- Bedroom Houses and IDA / 55060 Development and Post Open - National 200,000.00 0.00 Implementat 2018-09-07 2018-10-11 Quotations Envelope 10 Construction of Securing Management. ion Fencing at Service Center No. 1 for the Army NG-TRIMING NCO-76583- CW-RFQ / Emergency Rehabilitation of 3No. Junior Component 2: Irrigation Request for Single Stage - One 2018-12- Officers quarters at Yarkofoji IDA / 55060 Development and Post Open - National 150,000.00 109,721.89 Completed 2018-09-25 2018-11-04 2019-02-14 Quotations Envelope 19 and Construction of Securing Management. Fencing at Service Center No. 1 for security personnel. FMWR/TRIMING/2019/ICB/W/ 01 / Rehabilitation and Component 2: Irrigation Single Stage - One 50,000,000.0 29,235,668. 2020-11- expansion of Dadinkowa IDA / 55060 Development and Prior Request for Bids Open - National Signed 2019-04-25 2019-03-21 2019-04-30 2019-04-01 2019-06-11 2019-06-11 2019-07-11 2019-10-31 2019-08-22 2020-01-07 Envelope 0 09 05 Irrigation Scheme (Quick Wins Management. of 2000ha) in Gombe State FMWR/TRIMING/2019/ICB/W/ 02 / Additional construction Component 2: Irrigation Single Stage - One 20,000,000.0 2021-09- works of 1000ha at Bakolori IDA / 55060 Development and Prior Request for Bids Open - International 0.00 Canceled 2019-05-23 2019-06-06 2019-07-18 2019-08-17 2019-09-28 Envelope 0 27 Irrigation Scheme(BIS) and Management. 400ha at Jakaranwa FMWR/TRIMING/2019/RFQ/W /01 / Fencing, lanscaping and Component 4: Institutional Under Request for Single Stage - One 2018-07- securing of schemes radio IDA / 55060 Development and Project Post Open - National 150,000.00 0.00 Implementat 2018-02-25 2018-04-04 Quotations Envelope 03 houses and equipment at Management. ion MRVIS, DKIS, KRIS and HVIS FMWR/TRIMING/2019/ICB/W/ Component 1: Water 03 / Rehabilitation and Single Stage - One 45,000,000.0 2024-05- IDA / 55060 Resources Management and Prior Request for Bids Open - International 0.00 Canceled 2019-03-20 2019-04-03 2019-05-15 2019-06-14 2019-07-22 Improvement works for Envelope 0 30 Dam Operation Improvement. Bakolori and Zobe dams FMWR/TRIMING/2019/ICB/W/ 04 / Rehabilitation and Component 1: Water Single Stage - One 35,000,000.0 2024-06- Improvement works for IDA / 55060 Resources Management and Prior Request for Bids Open - International 0.00 Canceled 2019-03-20 2019-04-03 2019-05-15 2019-06-14 2019-07-26 Envelope 0 20 Goronyo and River Training at Dam Operation Improvement. MRVIS FMWR/TRIMING/2019/NCB/W /01 / Removal of Typa grasses and acquatic weeds Component 1: Water for restoration of Ruwan Single Stage - One 2022-08- IDA / 55060 Resources Management and Prior Request for Bids Open - International 3,000,000.00 0.00 Canceled 2019-04-20 2019-05-04 2019-06-15 2019-07-06 2019-08-13 Kanyan Reservoir and the Envelope 09 Dam Operation Improvement. Hadejia Barrage for optima performance under Dam Safety Improvement FMWR/TRIMING/2019/RFQ/W Component 2: Irrigation /02 / Rehabilitation of 6 nos. Request for Single Stage - One 2019-09- IDA / 55060 Development and Post Limited 120,000.00 97,659.56 Completed 2019-04-15 2019-04-15 2019-05-20 2019-07-17 Project Managers Offices of Quotations Envelope 09 Management. TRIMING intervention Schemes NG-TRIMING NCO-133311- CW-RFQ / Additional rehabilitation and Component 2: Irrigation reconstruction of Request for Single Stage - One 2019-12- IDA / 55060 Development and Post Limited 100,000.00 83,426.25 Completed 2019-09-30 2019-09-16 2019-11-04 2019-10-15 office/residential block, Quotations Envelope 16 Management. fencing and landscaping at DKIS Colony and other works at Bakolori Community radio FMWR/TRIMING/2019/NCB/W /02/01 / Rehabilitation and Component 1: Water Under Improvement Works for Single Stage - One 17,000,000.0 2022-03- IDA / 55060 Resources Management and Prior Request for Bids Open - National 0.00 Implementat 2019-10-31 2020-03-30 2019-11-07 2020-06-09 2019-12-19 2020-07-22 2020-01-30 2021-06-09 2020-03-12 Bakolori and Zobe Dams in Envelope 0 12 Dam Operation Improvement. ion Zamfara and Katsina States, Nigeria FMWR/TRIMING/2019/NCB/W /03/01 / Rehabilitation and Component 1: Water Single Stage - One 15,000,000.0 25,824,410. 2022-03- Improvement works for IDA / 55060 Resources Management and Prior Request for Bids Open - National Signed 2019-10-31 2020-09-08 2019-11-07 2020-09-16 2019-12-19 2020-11-02 2020-01-30 2021-05-21 2020-03-19 2021-08-05 Envelope 0 42 19 Goronyo and River Training at Dam Operation Improvement. MRVIS FMWR/TRIMING/2020/NCB/W /03 / Procurement of Works Component 2: Irrigation for Construction and Single Stage - One 3,543,240.8 2022-02- IDA / 55060 Development and Prior Request for Bids Open - National 6,000,000.00 Signed 2020-04-30 2020-07-06 2020-05-14 2020-07-27 2020-06-25 2020-08-25 2020-07-25 2021-03-18 2020-09-05 2021-05-07 Rehabilitation of Roads in Envelope 6 27 Management. Hadejia Valley Irrigation Scheme (HVIS) FMWR/TRIMING/2020/RFQ/W /010 / Upgrading and Demarcation of Officers Component 4: Institutional Request for Single Stage - One 2020-10- Cubicles in TRIMING Kano IDA / 55060 Development and Project Post Limited 100,000.00 85,491.90 Signed 2020-06-04 2020-11-02 2020-07-23 2020-11-27 Quotations Envelope 21 offices and provision of AC'S Management. for TRIMING Abuja and Kano offices. FMWR/TRIMING/2020/RFQ/W /04 / Furnishing for Additional Security Personnel Residences at Service Centre 1, Reconstruction and Wire Component 2: Irrigation Request for Single Stage - One 2021-01- Fencing of Site Project IDA / 55060 Development and Post Limited 200,000.00 174,317.09 Completed 2020-06-04 2020-06-15 2020-07-16 2020-07-29 Quotations Envelope 12 Manager with two other Management. Assistant Managers Residences in Bakolori Irrigation Scheme, Zamfara State. FMWR/TRIMING/2020/RFQ/W /05 / Provision of Borehole / reticulation and Solar System Component 2: Irrigation Request for Single Stage - One 2020-11- for remaining Security IDA / 55060 Development and Post Limited 150,000.00 129,989.86 Completed 2020-06-20 2020-06-15 2020-08-01 2020-07-29 Quotations Envelope 29 Personnel Residences at Management. Bakolori Irrigation Scheme, Zamfara State. Page 2 FMWR/TRIMING/2020/RFQ/W /011 / Rehabilitation and furnishing of Scheme Level Component 2: Irrigation Staff Offices, WUA Meeting Request for Single Stage - One 2021-03- IDA / 55060 Development and Post Limited 200,000.00 174,655.33 Completed 2020-07-25 2020-06-15 2020-09-05 2020-07-29 Hall in Kano River Irrigation Quotations Envelope 04 Management. Scheme and Connection of Site office to National Grid at Kura in Kano State FMWR/TRIMING/2020/RFQ/W /03 / Rehabilitation and furnishing of Water Users Component 2: Irrigation Request for Single Stage - One 2021-01- Association meeting Hall and IDA / 55060 Development and Post Limited 100,000.00 90,937.57 Completed 2020-06-04 2020-05-04 2020-07-16 2020-06-29 Quotations Envelope 12 offices in Hadejia Valley Management. Irrigation Scheme (HVIS) in Jigawa State. FMWR/TRIMING/2020/NCB/W /01 / Procurement of Works for Construction of Farmers Management Center in Component 3: Enhancing Single Stage - One 5,912,453.7 2021-10- Bakolori, Kano, Hadejia Valley IDA / 55060 Agricultural Productivity and Prior Request for Bids Open - National 6,400,000.00 Signed 2020-09-20 2020-10-26 2020-09-27 2020-10-26 2020-10-25 2020-11-25 2020-12-06 2021-06-07 2021-02-02 2021-08-13 Envelope 1 30 and Middle Rima Valley Support to Value Chains. Irrigation Schemes in Zamfara, Kano, Jigawa and Sokoto States, Nigeria FMWR/TRIMING/2020/RFQ/C W/07 / Protection of 36Nos Component 1: Water Installed hydrolaugical Request for Single Stage - One 2021-02- IDA / 55060 Resources Management and Post Limited 200,000.00 86,718.69 Completed 2020-12-08 2020-11-02 2020-12-29 2020-11-30 stations equipments at Quotations Envelope 27 Dam Operation Improvement. SRRBDA and Provision of dedicated internet GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-11056-GO- RFB / PROCUREMENT OF Component 3: Enhancing SECOND PHASE 25,000 UNITS Single Stage - One IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 240,000.00 199,416.41 Completed 2017-03-27 2017-05-04 2017-04-01 2017-05-01 2017-06-01 2017-05-31 2017-09-05 2017-07-05 2017-09-19 2018-01-01 2017-11-16 TOMATO PLASTIC CRATES TO Envelope Support to Value Chains. ANOTHER 500 TARGETTED FARMERS OF KRIP NG-TRIMING NCO-19047-GO- RFB / Procurement of Component 1: Water Pending customised boats and Single Stage - One IDA / 55060 Resources Management and Post Request for Bids Open - International 830,079.00 0.00 Implementati 2016-03-08 2016-03-17 2016-04-16 2016-08-16 2016-12-07 2017-12-02 associated equipment for Envelope Dam Operation Improvement. on bathymetric survey of Nigeria dams & reservoirs NG-TRIMING NCO-19040-GO- RFB / Procurement of various Component 4: Institutional Under office equipment and Single Stage - One IDA / 55060 Development and Project Post Request for Bids Open - National 315,000.00 0.00 Implementati 2017-07-20 2017-10-05 2017-07-25 2017-09-05 2017-11-02 2017-09-19 2018-04-12 2017-10-10 2018-01-08 furniture for office and Envelope Management. on residential appartments for 12nos houses in BIS, Zamfara State. NG-TRIMING NCO-18975-GO- RFQ / Procurement of personal protective equipment Component 2: Irrigation Request for Single Stage - One for the Project site and safe IDA / 55060 Development and Post Open - National 40,000.00 28,415.69 Completed 2017-08-01 2017-08-18 2017-11-09 2017-09-11 2017-12-04 Quotations Envelope use of chemicals e.g (Nose Management. mask, Safety boots, glooves e.t.c) Phase 3 NG-TRIMING NCO-18966-GO- RFB / Procurement of Component 3: Enhancing Single Stage - One agricultural equipment to IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 400,000.00 0.00 Canceled 2017-03-03 2017-03-07 2017-04-04 2017-05-15 2017-07-14 2017-10-12 Envelope support farmers organisation Support to Value Chains. on technology transfer NG-TRIMING NCO-18964-GO- RFQ / Procurement of additional 6nos Field and Component 4: Institutional Operational Vehicles for Request for Single Stage - One IDA / 55060 Development and Project Post Open - National 400,000.00 330,351.26 Completed 2017-10-25 2017-11-29 2017-09-18 2017-12-27 2017-09-20 Project Management logistics Quotations Envelope Management. (1nos -18 seaters bus, 2nos Salon cars and 3nos 4WD for Project Managers). NG-TRIMING NCO-19034-GO- RFB / Procurement of various office equipment and furniture for office and Component 4: Institutional Pending Single Stage - One residential apartments for BIS, IDA / 55060 Development and Project Post Request for Bids Open - National 600,000.00 0.00 Implementati 2017-08-31 2017-09-05 2017-11-02 2017-11-16 2017-12-15 2018-03-15 Envelope DIS, HVIS and and Goronyo in Management. on Zamfara, Gombe, Jigawa and Sokoto State respectively under the TRIMING project (in lots) NG-TRIMING NCO-14025-GO- RFB / Procurement and Installation of Electronic Component 4: Institutional Single Stage - One Records & Documents IDA / 55060 Development and Project Prior Request for Bids Open - International 2,000,000.00 0.00 Canceled 2018-01-30 2018-03-07 2018-02-20 2018-04-09 2018-04-03 2018-05-03 2018-06-19 2019-04-23 Envelope Management System (ERDMS) Management. Equipment and Associated Services FMWR/TRIMING/2018/NCB/G /03 / Procurement of 20T Low Component 1: Water Bed trailer with Crane and Single Stage - One IDA / 55060 Resources Management and Post Request for Bids Open - National 480,000.00 461,094.27 Signed 2018-04-02 2018-11-30 2018-04-07 2018-04-30 2018-12-28 2018-05-14 2019-04-30 2018-06-18 2020-01-31 2018-12-15 3,000litres Mobil fuel dump Envelope Dam Operation Improvement. for use by National Water Resources Institute FMWR/TRIMING/2018/SH/G/0 1 / Procurement of personal Component 2: Irrigation protective equipment and Request for Single Stage - One IDA / 55060 Development and Post Open - National 50,000.00 40,943.47 Completed 2018-03-05 2018-04-03 2018-05-11 2018-05-03 2018-06-08 integrated pest management Quotations Envelope Management. and safe use of chemical commodities Phase 4 Page 3 FMWR/TRIMING/2018/NCB/G /02 / Procurement of 65,000nos Additional Plastic Crates to Kano mRiver Component 3: Enhancing Irrigation Scheme Tomato Single Stage - One IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 950,000.00 0.00 Canceled 2018-04-16 2018-04-21 2018-05-19 2018-06-09 2018-07-21 2019-01-17 Farmers Association and other Envelope Support to Value Chains. Beneficiaries along Tomato Value Chains and Productive Alliance in all TRIMING project Schemes FMWR/TRIMING/2018/NCB/G /01 / Additional Procurement of Agricultural Technology Land Leveling and other Component 3: Enhancing Single Stage - One Agricultural Equipment for IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 750,000.00 0.00 Canceled 2018-03-19 2018-03-19 2018-04-16 2018-04-23 2018-05-28 2018-10-16 Envelope Introduction to Farmers and Support to Value Chains. others Beneficiaries towards establishment of Farmers Management Centers FMWR/TRIMING/2018/SH/G/0 3 / Procurement of Protective Riding Gears and High way Component 3: Enhancing Request for Single Stage - One Code for Motorcycle/Vehicles IDA / 55060 Agricultural Productivity and Post Open - National 90,000.00 0.00 Canceled 2018-02-05 2018-04-02 2018-09-29 Quotations Envelope for Extension officers and sign Support to Value Chains. post for TRIMING Farmers Field and Business School FMWR/TRIMING/2018/SH/G/0 4 / Procurement and Installation of Solar Panels Component 4: Institutional and Inverters for TRIMING Request for Single Stage - One IDA / 55060 Development and Project Post Open - National 95,000.00 80,156.92 Completed 2018-03-07 2018-04-09 2018-04-13 2018-05-09 2018-05-11 project Office/Residencies in Quotations Envelope Management. Kano and three (3nos) field offices at Auyo, Dadin Kowa and Goronyo FMWR/TRIMING/2018/SH/G/0 5 / Procurement of Laptops, Component 4: Institutional Request for Single Stage - One Deskstops, Scanners and IDA / 55060 Development and Project Post Open - National 90,000.00 74,197.20 Completed 2018-04-07 2018-05-08 2018-06-15 2018-06-07 2018-08-02 Quotations Envelope printers for PMU Kano and Management. Abuja Offices FMWR/TRIMING/2018/SH/G/0 6 / Support to FMWR Component 4: Institutional Pending (Irrigation & Drainage Request for Single Stage - One IDA / 55060 Development and Project Post Open - National 50,000.00 0.00 Implementati 2018-04-07 2018-05-04 2018-06-04 Department) through Quotations Envelope Management. on procurement of required ICT Equipment. FMWR/TRIMING/2018/SH/G/0 7 / Procurement of various office equipment and Component 2: Irrigation Pending Request for Single Stage - One furniture for office and IDA / 55060 Development and Post Open - National 100,000.00 0.00 Implementati 2018-02-17 2018-04-07 2018-05-07 Quotations Envelope residential apartments for Management. on Bunkure, Kano River Irrigation Scheme in Kano State FMWR/TRIMING/2018/SH/G/0 8 / Procurement of 350nos Component 3: Enhancing Request for Single Stage - One signpost for Farmers Field and IDA / 55060 Agricultural Productivity and Post Open - National 50,000.00 32,975.94 Completed 2018-02-12 2018-03-16 2018-03-28 2018-04-30 2018-05-17 Quotations Envelope Business School Training Support to Value Chains. school FMWR/TRIMING/2018/NCB/G /04 / Procurement of services provider for provision of Component 3: Enhancing Single Stage - One Famers Field Business School IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 400,000.00 299,619.48 Completed 2018-02-26 2018-04-27 2018-03-03 2018-03-17 2018-05-25 2018-03-24 2018-07-02 2018-04-05 2018-07-31 2018-10-02 2018-12-14 Envelope training materials and Support to Value Chains. agricultural inputs for running of FFS FMWR/TRIMING/2018/SH/G/1 1 / Furnishing of four (4) no. Component 3: Enhancing Request for Single Stage - One Agricultural Development IDA / 55060 Agricultural Productivity and Post Open - National 100,000.00 71,032.84 Completed 2018-04-28 2018-05-29 2018-11-19 2018-06-28 2018-12-06 Quotations Envelope Project offices allocated for Support to Value Chains. TRIMING Project activities NG-TRIMING NCO-54492-GO- RFB / Procurement and Installation of Hydrometric Component 1: Water Single Stage - One Equipment and Related IDA / 55060 Resources Management and Prior Request for Bids Open - International 4,500,000.00 4,785,928.19 Signed 2018-03-19 2018-03-19 2018-03-19 2017-11-30 2018-04-06 2018-03-27 2018-05-11 2018-05-31 2021-04-25 Envelope Services for Sokoto Rima and Dam Operation Improvement. Hadejia Jama'are Basin for Hydrometric Improvement FMWR/TRIMING/2016/ICB/G/ 001 / Procurement and Installation of Hydromet Component 1: Water Equipment and Provision of Single Stage - One IDA / 55060 Resources Management and Prior Request for Bids Open - International 4,500,000.00 0.00 Canceled 2017-10-12 2017-10-12 2017-11-30 2018-02-28 2018-04-20 2021-04-04 Related Services at Sokoto Envelope Dam Operation Improvement. Rima and Hadejia Jama’are River Basins for Hydrometric Improvement FMWR/TRIMING/2018/SS/G/0 1 / Bathymetric Survey of Component 1: Water Under Tiga, Ruwankayan, Hadejia, IDA / 55060 Resources Management and Post Direct Selection Direct 2,000,000.00 0.00 Implementati 2018-06-11 2018-06-16 2018-07-21 2019-01-17 Goronyo, Zobe, Dadin-0Kowa, Dam Operation Improvement. on Challawa Dams/Reservoirs NG-TRIMING NCO-76576-GO- RFQ / Support to FMWR Component 4: Institutional (Department of Dams & Request for Single Stage - One IDA / 55060 Development and Project Post Open - National 50,000.00 41,125.17 Completed 2018-09-15 2018-10-27 2018-11-15 2018-11-26 2018-12-12 Reservoir Operations) through Quotations Envelope Management. procurement of required ICT Equipment. NG-TRIMING NCO-76525-GO- RFQ / Purchase of 4 No Generators for TRIMING Component 1: Water Request for Single Stage - One Project Sites at the Four IDA / 55060 Resources Management and Post Open - National 100,000.00 82,495.88 Signed 2018-09-15 2018-10-19 2018-09-18 2018-11-18 Quotations Envelope Schems (BIS- 100KVA, HVIS - Dam Operation Improvement. 60KVS, DKIS - 30KVA, & MRVIS - 50KVA) Page 4 NG-TRIMING NCO-76524-GO- RFQ / Purchase of 3 No 4WD Component 2: Irrigation Request for Single Stage - One Utility vehicle for Consultant IDA / 55060 Development and Post Open - National 250,000.00 207,574.26 Completed 2018-09-30 2018-11-03 2018-09-21 2018-12-03 2018-10-15 Quotations Envelope Field Operation for Bakolori Management. Irrigation Civil Works NG-TRIMING NCO-76529-GO- RFQ / Modest furnishing and Component 2: Irrigation provision of Solar Pannels and Request for Single Stage - One IDA / 55060 Development and Post Open - National 100,000.00 73,465.63 Completed 2018-09-04 2018-10-30 2018-12-24 2018-11-29 2019-12-18 Inverters for the newly Quotations Envelope Management. renovated Houses for Security Agencies covering BIS NG-TRIMING NCO-76530-GO- RFQ / Procurement of microsoft office applications Component 4: Institutional Pending Request for Single Stage - One and other relevant software IDA / 55060 Development and Project Post Open - National 65,000.00 0.00 Implementati 2018-10-05 2018-11-08 2018-12-08 Quotations Envelope for PMU, TRIMING project MIS Management. on Centers at FMWR, RBDAs and TRIMING Schemes NG-TRIMING NCO-76522-GO- Component 4: Institutional RFQ / Support to FPFMD Request for Single Stage - One IDA / 55060 Development and Project Post Open - National 50,000.00 36,398.75 Completed 2018-09-15 2018-10-10 2018-09-21 2018-10-24 2018-09-25 through procurement of Quotations Envelope Management. required ICT Equipment. NG-TRIMING NCO-91445-GO- RFQ / Procurement and installation of communication Component 2: Irrigation Request for Single Stage - One Gadgets on vehicles and for IDA / 55060 Development and Post Limited 100,000.00 72,848.69 Completed 2018-12-19 2018-12-04 2019-01-16 2018-12-28 2019-01-30 2019-04-30 Quotations Envelope field works in TRIMING Management. intervention sites as securities measures (BIS) FMWR/TRIMING/2019/NCB/G /02 / Procurement of Agricultural Technology Equipment for the Component 3: Enhancing Single Stage - One Establishment and IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 950,000.00 0.00 Canceled 2019-04-24 2019-05-01 2019-05-29 2019-06-19 2019-07-31 2020-01-27 Envelope Development of Support to Value Chains. Mechanization in the FMCs at BIS, HVIS, KRIS and MRVIS. - LOT 1 FMWR/TRIMING/2019/NCB/G /04 / Procurement and Installation of Solar Panels, Inverters, Hybrid Batteries Component 1: Water Single Stage - One with solar inverters for IDA / 55060 Resources Management and Post Request for Bids Open - National 195,000.00 137,226.88 Signed 2019-03-11 2019-09-19 2019-03-16 2019-09-19 2019-04-13 2019-10-24 2019-04-27 2020-02-20 2019-06-04 2020-08-10 2019-10-02 Envelope TRIMING Project Dam Operation Improvement. Office/Residences and Hydrometry observation stations FMWR/TRIMING/2019/NCB/0 5 / Procurement of Services Provider for provision of Component 3: Enhancing Famers Field Business School Single Stage - One IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 750,000.00 736,090.58 Completed 2019-02-20 2019-03-20 2019-02-27 2019-03-27 2019-04-14 2019-04-17 2019-05-13 2019-05-22 2019-06-11 2021-05-21 2020-12-23 (FFSBS) Training Materials for Envelope Support to Value Chains. Running of FFBS in Wet and Dry Season for 2019/2020 and 2020/2021 FMWR/TRIMING/2019/NCB/G /06 / Procurement and Installation, commissioning Component 1: Water Single Stage - One and Training of flow IDA / 55060 Resources Management and Post Request for Bids Open - National 500,000.00 300,109.36 Signed 2019-03-10 2019-10-10 2019-03-17 2019-10-10 2019-04-14 2019-11-07 2019-05-05 2020-02-05 2019-06-16 2020-07-15 2019-10-14 Envelope measurment devices in the Dam Operation Improvement. irrigation supply canal of TRIMING dams and reservoirs FMWR/TRIMING/2019/ICB/G/ 01 / Procurement and Component 1: Water Installation of Hydrometric Single Stage - One IDA / 55060 Resources Management and Prior Request for Bids Open - International 2,800,000.00 0.00 Canceled 2019-06-27 2019-07-11 2019-08-22 2019-09-21 2019-11-02 2021-11-01 Equipment and Related Envelope Dam Operation Improvement. services for Upper Benue River Basin FMWR/TRIMING/2019/RFQ/G/ 07 / Procurement of 6Nos. Operational field vehicles for Component 4: Institutional use by TRIMING Project Request for Single Stage - One IDA / 55060 Development and Project Post Limited 450,000.00 379,267.45 Completed 2019-04-04 2019-04-19 2019-05-09 2019-05-27 2019-06-08 2019-06-11 Managers, Basin Level Quotations Envelope Management. Coordinators and for FMCs takeoff operation at BIS,HVIS,KRIS and MRVIS FMWR/TRIMING/2019/NCB/G /08 / Procurement and Installations of ICT equipment & related services as Additional Support to Component 4: Institutional Single Stage - One Irrigation & Drainage IDA / 55060 Development and Project Post Request for Bids Open - National 300,000.00 0.00 Canceled 2019-05-30 2019-10-10 2019-06-06 2019-10-10 2019-07-04 2019-07-25 2019-09-05 2019-12-04 Envelope Department, Dam & Management. Reservoirs Operations Dept., Honourable Minister Office and the Project Change Management Committee FMWR/TRIMING/2019/RFQ/G/ 02 / Procurement and installtion of communication Component 2: Irrigation Request for Single Stage - One Gadgets on vechiles and for IDA / 55060 Development and Post Limited 100,000.00 73,575.79 Completed 2019-02-20 2019-09-02 2019-03-27 2019-10-02 2019-04-26 2019-11-18 Quotations Envelope field works in TRIMING Management. intervention sites as securities measures (KRIS & HVIS) FMWR/TRIMING/2019/NCB/G /09 / Supply and Installations Component 4: Institutional including provision of base Single Stage - One IDA / 55060 Development and Project Post Request for Bids Open - National 140,000.00 90,205.56 Completed 2019-05-09 2019-09-19 2019-05-14 2019-09-19 2019-06-11 2019-10-17 2019-06-25 2020-01-30 2019-07-30 2020-03-24 2019-10-28 2020-05-27 platform for the 5Nos Envelope Management. Generators (60KVA) in 5Nos Radio Houses Page 5 FMWR/TRIMING/2019/NCB/G /10 / Procurement of Large Multipurpose Printers and GIS for use by the PMU and for the Component 4: Institutional Single Stage - One establishment of GIS Units in IDA / 55060 Development and Project Post Request for Bids Open - National 190,000.00 70,846.38 Completed 2019-05-20 2019-10-10 2019-05-27 2019-10-10 2019-06-24 2019-11-07 2019-07-15 2020-01-15 2019-08-26 2020-03-18 2019-12-24 2020-06-09 Envelope I & D-FMWR, TRIMING head Management. offices in Abuja & Kano, TRIMING RBDA headquarters, and TRIMING scheme offices FMWR/TRIMING/2019/RFQ/G/ 03 / Purchase of personal protective equipment and Component 3: Enhancing integrated pest management Request for Single Stage - One IDA / 55060 Agricultural Productivity and Post Limited 60,000.00 49,899.05 Completed 2019-09-25 2019-08-21 2019-10-30 2019-09-16 2019-11-29 2019-10-09 and safe use of chemical Quotations Envelope Support to Value Chains. commodity and Waste Seperation and Segregation Containers for TRIMING use FMWR/TRIMING/2019/RFQ/G/ 04 / Furnishing of 6nos Component 4: Institutional Request for Single Stage - One Project Managers offices at all IDA / 55060 Development and Project Post Limited 100,000.00 82,190.46 Completed 2019-10-07 2019-07-26 2019-11-11 2019-08-29 2019-12-11 2019-11-08 Quotations Envelope TRIMING Project Schemes and Management. TRIMING Library office in Kano FMWR/TRIMING/2019/NCB/G /01 / Provision of Office Component 3: Enhancing Single Stage - One Furniture and Equipment for IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 250,000.00 0.00 Canceled 2019-03-18 2019-03-25 2019-04-22 2019-05-13 2019-06-24 2019-09-22 Envelope the FMCs at BIS, KRIS and Support to Value Chains. MRVIS. FMWR/TRIMING/2020/RFQ/G/ 07 / Procurement of 6Nos Component 4: Institutional Request for Single Stage - One field operational vehicles for IDA / 55060 Development and Project Post Limited 485,000.00 8,790,905.26 Completed 2020-04-25 2020-05-04 2020-05-26 2020-06-01 2020-06-25 2020-06-25 Quotations Envelope monitoring and supervision of Management. construction activities FMWR/TRIMING/2020/RFQ/G/ 04 / Procurement and Component 2: Irrigation furnishing of Water Users Request for Single Stage - One IDA / 55060 Development and Post Limited 100,000.00 80,885.33 Completed 2020-04-25 2020-03-02 2020-06-06 2020-06-03 2020-07-18 2020-08-03 Associations meeting halls at Quotations Envelope Management. Bakolori and Middle Rima Valley Irrigation Schemes FMWR/TRIMING/2020/G/RFQ/ 01 / Procurement of Component 3: Enhancing Request for Single Stage - One Protective riding gears, 25Nos IDA / 55060 Agricultural Productivity and Post Limited 100,000.00 73,233.21 Completed 2020-04-25 2020-03-02 2020-05-30 2020-06-03 2020-06-29 2020-06-16 Quotations Envelope motor cycles and generators Support to Value Chains. for extension services delivery FMWR/TRIMING/2020/RFQ/G/ 02 / Purchase of personal protective equipment Component 3: Enhancing Request for Single Stage - One (commodity) to support the IDA / 55060 Agricultural Productivity and Post Limited 70,000.00 61,040.73 Completed 2020-04-25 2020-06-03 2020-05-30 2020-06-25 2020-06-29 2020-07-23 Quotations Envelope integrated pest management Support to Value Chains. and safe use of chemical approach FMWR/TRIMING/2020/NCB/G /07 / Procurement and Component 1: Water Installation of Hydrometric Single Stage - One IDA / 55060 Resources Management and Prior Request for Bids Open - National 2,800,000.00 0.00 Canceled 2020-06-30 2020-07-14 2020-08-12 2020-09-11 2020-10-23 2022-04-16 Equipment and Related Envelope Dam Operation Improvement. Activities for Upper Benue River Basin FMWR/TRIMING/2020/NCB/G /03 / Procurement and Component 4: Institutional Installation of FM Radio Single Stage - One IDA / 55060 Development and Project Post Request for Bids Open - National 800,000.00 0.00 Canceled 2020-09-30 2020-10-07 2020-11-04 2020-12-04 2021-01-15 2021-05-15 Equipment and Associated Envelope Management. furnishing for TRIMING project schemes FMWR/TRIMING/2019/NCB/G /03 / Procurement and Installation of (FM Radio) Component 3: Enhancing Single Stage - One Equipment and associated IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 400,000.00 0.00 Canceled 2019-05-01 2019-05-08 2019-06-05 2019-06-26 2019-08-07 2019-11-05 Envelope furnishing for TRIMING Project Support to Value Chains. FM stations at BIS, HVIS, KRIS and MRVIS. FMWR/TRIMING/2020/RFQ/G/ 05 / Procurement Improvement/Expansion of Component 4: Institutional Request for Single Stage - One Communication Coverage IDA / 55060 Development and Project Post Limited 100,000.00 85,608.97 Completed 2020-05-05 2020-07-06 2020-06-03 2020-08-17 2020-08-02 2020-09-30 Quotations Envelope with Gadgets within Kano Management. River and Hadejia Valley Irrigation Schemes (Phase II) FMWR/TRIMING/2020/RFQ/G/ 06 / Provision of Communication Gadgets Component 4: Institutional Request for Single Stage - One (including masts and IDA / 55060 Development and Project Post Limited 100,000.00 87,384.32 Completed 2020-05-05 2020-05-18 2020-06-05 2020-06-27 2020-08-04 2020-08-07 Quotations Envelope independent power supply in Management. Dadin Kowa Irrigation Scheme, Gombe State FMWR/TRIMING/2020/NCB/G /04 / Procurement of additional service provider for Component 3: Enhancing the provision of agricultural Single Stage - One IDA / 55060 Agricultural Productivity and Post Request for Bids Open - National 350,000.00 267,803.63 Signed 2020-04-30 2020-06-10 2020-05-14 2020-06-11 2020-06-11 2020-07-08 2020-07-23 2020-08-18 2020-09-03 2020-10-15 2021-12-31 inputs, training materials and Envelope Support to Value Chains. furniture for use by relevant Agricuretural Development Programmes FMWR/TRIMING/2020/RFQ/G/ 08 / Provision and Installations of solar power Component 4: Institutional Including Batteries and Request for Single Stage - One IDA / 55060 Development and Project Post Limited 100,000.00 77,970.40 Completed 2020-05-20 2020-02-24 2020-07-01 2020-06-03 2020-08-30 2020-08-03 Inverters systems for Quotations Envelope Management. Residences and offices at Dadinkowa Irrigation Scheme (DKIS) Page 6 FMWR/TRIMING/2020/NCB/G /01 / Procurement and Installation of Electronic Component 4: Institutional Single Stage - One Records and Documents IDA / 55060 Development and Project Prior Request for Bids Open - National 1,650,000.00 1,467,421.98 Signed 2020-07-30 2020-07-28 2020-08-13 2020-08-04 2020-09-24 2020-09-02 2020-10-24 2021-03-31 2020-11-21 2021-06-22 2021-06-19 Envelope Management System (ERDMS) Management. Equipment and Associated Services FMWR/TRIMING/2020/RFQ/G O/010 / Purchase of ICT equipment for use by APEX Component 2: Irrigation and Sectors WUA Offices, Request for Single Stage - One IDA / 55060 Development and Post Limited 100,000.00 87,243.38 Completed 2020-12-08 2020-11-16 2020-12-29 2020-12-09 2021-01-28 2020-12-22 Basin Levels Coordinator Quotations Envelope Management. (BLCs), Site Contract Coordinators SCCs, at HJRBDA including New PMU NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14028-NC- Component 2: Irrigation Under RFB / Detailed aerial Single Stage - One IDA / 55060 Development and Post Request for Bids Open - International 1,173,600.00 0.00 Implementati 2016-04-14 2016-04-14 2016-05-26 2016-05-26 2016-06-25 2017-06-06 2017-03-03 2017-10-29 topograhical survey of Dadin- Envelope Management. on Kowa and Guyuk CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14068-CS- QCBS / Technical Assistance on Farmers -Market Component 3: Enhancing Quality And Cost- Linkages,value chain IDA / 55060 Agricultural Productivity and Prior Open - International 5,179,190.00 4,732,203.54 Signed 2015-06-09 2015-06-09 2016-03-07 2016-04-25 2016-07-21 2017-04-28 2017-06-08 2017-05-19 2017-06-30 2021-04-28 Based Selection development and for the Support to Value Chains. establishment of FMC in 4 irrigation schemes NG-TRIMING NCO-14090-CS- QCBS / Design and Component 2: Irrigation Construction Supervision of Quality And Cost- IDA / 55060 Development and Prior Open - International 4,029,884.00 3,964,523.32 Signed 2015-04-10 2015-04-17 2015-12-08 2016-09-09 2016-09-09 2016-10-09 2017-05-05 2017-06-19 2017-06-16 2017-07-10 2020-09-28 Dadin Kowa Irrigation Scheme Based Selection Management. and feasibility studies of Guyuk Irrigation Scheme NG-TRIMING NCO-14034-CS- QCBS / Consultancy Service for Construction Supervision for Rehabilitation and Component 1: Water Expansion of Kano River Quality And Cost- IDA / 55060 Resources Management and Prior Open - International 5,000,000.00 5,275,353.25 Terminated 2016-08-03 2016-08-10 2017-05-25 2017-09-18 2017-07-06 2017-10-30 2017-08-05 2018-01-09 2017-09-09 2018-07-24 2017-10-14 2018-08-09 2022-09-18 Irrigation Scheme (KRIS) And Based Selection Dam Operation Improvement. Hadejia Valley Irrigation Scheme (HVIS), Dam Safety / River Training Works in The Hadejia-Jama’are Basin. NG-TRIMING NCO-14022-CS- QCBS / Engineering Component 2: Irrigation Quality And Cost- Supervision of the IDA / 55060 Development and Prior Open - International 4,043,083.00 3,442,767.00 Signed 2015-04-17 2015-04-17 2016-07-15 2016-09-09 2016-05-13 2016-10-19 2017-04-28 2017-05-10 2017-06-02 2017-03-08 2020-09-30 Based Selection Rehabilitation/conversion area Management. of Bakolori Irrigation Scheme NG-TRIMING NCO-14031-CS- Component 1: Water Quality And Cost- QCBS / Technical Assistance IDA / 55060 Resources Management and Prior Open - International 2,500,000.00 5,128,736.58 Signed 2016-02-09 2016-03-01 2016-10-28 2016-12-23 2017-05-08 2017-07-30 2017-06-12 2018-11-12 2017-07-17 2018-01-11 2020-07-01 Based Selection for WUA in KRIS and HVIS Dam Operation Improvement. NG-TRIMING NCO-14076-CS- QCBS / Technical Assistance Component 1: Water for Dam Safety Assurance & Quality And Cost- IDA / 55060 Resources Management and Prior Open - International 1,421,626.00 1,398,283.30 Signed 2015-04-17 2015-04-17 2015-12-16 2016-02-10 2016-02-16 2016-05-06 2016-07-21 2017-06-06 2016-09-21 2016-09-21 2019-09-06 Training for Dam and Based Selection Dam Operation Improvement. Reservoir Dept. and RBDA staff NG-TRIMING NCO-14092-CS- QCBS / Consulting services Component 1: Water Quality And Cost- for dams safety, improved IDA / 55060 Resources Management and Prior Open - International 1,500,000.00 0.00 Canceled 2016-10-04 2016-10-11 2017-06-08 2017-07-20 2017-08-19 2017-09-16 2017-10-21 2019-04-14 Based Selection hydrometry and IWRM Dadin Dam Operation Improvement. Kowa Irrigation Scheme NG-TRIMING NCO-19048-CS- CQS / Consultancy Services Component 2: Irrigation Consultant Pending for preparation of ESIA for IDA / 55060 Development and Post Qualification Open - National 286,040.00 0.00 2014-09-23 2014-10-14 2014-11-27 2014-12-27 2015-01-31 2015-07-30 Implementation MRVIS with Goronyo Dam in Management. Selection Sokoto State NG-TRIMING NCO-19044-CS- CQS / Consultancy Services Component 2: Irrigation Consultant Pending for Preparation of IDA / 55060 Development and Post Qualification Open - National 127,700.00 0.00 2016-03-18 2016-04-08 2016-05-22 2016-06-21 2016-07-26 2017-01-22 Implementation Environmental and Social Management. Selection Assessment for Zobe Dam NG-TRIMING NCO-18972-CS- Component 2: Irrigation Consultant Under CQS / Elaboration of RAP for IDA / 55060 Development and Post Qualification Open - International 222,240.00 0.00 2016-02-01 2016-02-01 2016-02-09 2016-06-03 2016-06-21 2016-08-19 2017-01-20 Implementation KRIS Management. Selection NG-TRIMING NCO-19043-CS- Component 2: Irrigation Consultant Under CQS / Elaboration of RAP for IDA / 55060 Development and Post Qualification Open - National 245,300.00 0.00 2016-02-09 2016-02-01 2016-03-01 2016-04-14 2016-06-17 2016-08-19 2017-02-15 Implementation HVIS Management. Selection NG-TRIMING NCO-18962-CS- Component 2: Irrigation Consultant Pending CQS / ESIA Dadin Kowa IDA / 55060 Development and Post Qualification Open - National 271,899.00 0.00 2016-04-08 2016-10-07 2017-03-02 2017-04-27 2017-06-23 2018-03-12 Implementation Irrigation Scheme Management. Selection Page 7 FWMR/TRIMING/2018/CQ/CS /01 / Elaboration and Component 2: Irrigation Consultant implementation of IDA / 55060 Development and Post Qualification Open - National 200,000.00 0.00 Canceled 2018-07-03 2018-07-24 2018-08-10 2018-08-14 2018-08-28 2019-02-24 resettlement action plan (RAP) Management. Selection for Jankarawa Irrigation and other Projects. FMWR/TRIMING/2018/QCBS/ CS/01 / Supervision of Dam Component 1: Water Quality And Cost- Under safety improvement works at IDA / 55060 Resources Management and Prior Open - International 7,000,000.00 0.00 2018-04-10 2019-09-10 2018-05-01 2019-09-13 2018-06-14 2020-07-20 2018-07-05 2020-08-18 2018-07-12 2021-05-18 2018-08-14 2018-10-19 2022-02-22 Based Selection Implementation Bakolori, Zobe and Goronyo Dam Operation Improvement. dams FWMR/TRIMING/2018/CQ/CS /02 / TA for review of existing studies and identification of development Component 2: Irrigation Consultant options for Zobe Irrigation IDA / 55060 Development and Post Qualification Open - National 295,000.00 0.00 Canceled 2018-04-05 2018-04-19 2018-06-02 2018-07-02 2018-08-06 2018-12-28 Scheme and prefeasibility Management. Selection studies of Dutse and Mairuwa Dams for the development of gravity irrigation potentials in Katsina State. FWMR/TRIMING/2018/CQ/CS /03 / Elaboration and Implementation of Component 2: Irrigation Consultant Under Resettlement Action Plan IDA / 55060 Development and Post Qualification Open - National 200,000.00 0.00 2018-04-05 2019-03-10 2018-04-26 2018-06-09 2018-07-09 2018-08-13 2019-02-09 Implementation (RAP) for the Middle Rima Management. Selection Valley Irrigation Scheme, Sokoto State FMWR/TRIMING/2018/CS/CQ /04 / Review and Upgrade of Component 2: Irrigation Consultant feasibility studies on Hadejia IDA / 55060 Development and Post Qualification Open - National 295,000.00 0.00 Canceled 2018-02-13 2018-03-06 2018-04-19 2018-05-19 2018-06-23 2018-12-20 Valley Irrigation Project, Phase Management. Selection 1 stage 2 NG-TRIMING NCO-76564-CS- CQS / Recruitment of Scheme Component 4: Institutional Consultant Safeguards Officer in Bakolori IDA / 55060 Development and Project Post Qualification Open - National 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-09-27 2018-10-11 2018-10-25 2018-11-08 2019-11-03 irrigation Project (BIP) (Social Management. Selection Safeguards) FMWR/TRIMING/2019/QCBS/ CS/01 / Consultancy contract Component 2: Irrigation for works supervision of Quality And Cost- IDA / 55060 Development and Prior Open - National 1,000,000.00 0.00 Canceled 2019-03-18 2019-04-01 2019-04-29 2019-05-27 2019-06-17 2019-07-08 2019-08-12 2022-08-11 additional works (1400ha) at Based Selection Management. Bakolori Irrigation Scheme (BIS) including Jankarawa FMWR/TRIMING/2019/CQS/C S/02 / Feasibility studies and technical specification for Component 1: Water Consultant removal of aquatic weeds IDA / 55060 Resources Management and Post Qualification Open - National 295,000.00 0.00 Canceled 2019-03-18 2019-06-03 2019-04-01 2019-05-06 2019-05-20 2019-06-17 2019-12-14 from TRIMING dams and Dam Operation Improvement. Selection Reservoirs in Ruwan Kanya and Hadejia Barrage FMWR/TRIMING/2019/QCBS/ CS/02 / Consultancy Service Component 1: Water for the Review and Quality And Cost- IDA / 55060 Resources Management and Prior Open - International 900,000.00 0.00 Canceled 2019-03-18 2019-04-01 2019-05-06 2019-05-20 2019-06-03 2019-07-01 2019-07-29 2021-07-28 Completion of the Catchment Based Selection Dam Operation Improvement. Management Area (CMA) in Hydrological Area 1. (Sokoto Rima Basin FMWR/TRIMING/2019/CQS/C S/03 / Consultancy Services Component 1: Water Consultant for improved hydrometry and IDA / 55060 Resources Management and Post Qualification Open - National 290,000.00 0.00 Canceled 2019-03-30 2019-06-03 2019-04-13 2019-05-18 2019-06-01 2019-06-22 2019-12-19 IWRM of the Gongola sub- Dam Operation Improvement. Selection Basin in the Upper Benue Basin. FMWR/TRIMING/2019/CQS/C S/04 / Technical Assistance on Integrated Pest Component 3: Enhancing Consultant Management and safe use of IDA / 55060 Agricultural Productivity and Post Qualification Open - National 150,000.00 123,623.50 Completed 2019-02-28 2019-02-26 2019-03-14 2019-04-18 2019-04-10 2019-05-02 2019-06-03 2019-05-30 2019-06-03 2019-11-26 2019-12-06 chemicals for the Farmers Support to Value Chains. Selection Field Business School facilitators and step down trainings for farmer facilitators FMWR/TRIMING/2018/QCBS/ Component 4: Institutional CS/02 / Periodic M & E data Quality And Cost- IDA / 55060 Development and Project Prior Open - International 350,000.00 0.00 Canceled 2018-02-20 2018-03-13 2018-04-26 2018-05-24 2018-06-23 2018-07-28 2018-09-01 2019-09-01 collection and midterm Impact Based Selection Management. evaluation FMWR/TRIMING/2019/CQS/C S/01 / Gender Based Violence Component 2: Irrigation Consultant mapping of TRIMING Project IDA / 55060 Development and Prior Qualification Open - National 120,000.00 0.00 Canceled 2019-03-28 2019-03-13 2019-04-11 2019-03-18 2019-05-16 2019-05-30 2019-06-16 2019-10-14 participating schemes and Management. Selection development of a proactive prevention response plan NG-TRIMING NCO-114549- CS-QCBS / Consultancy Component 4: Institutional Services for Periodic M&E Data Quality And Cost- IDA / 55060 Development and Project Prior Open - International 900,000.00 883,208.30 Signed 2019-05-30 2019-07-18 2019-06-13 2019-07-30 2019-07-11 2020-02-29 2019-08-08 2020-04-14 2019-08-22 2020-07-15 2019-09-19 2020-08-25 2019-10-17 2020-09-11 2022-03-31 Collection, Impact Evaluations Based Selection Management. and Completion Report for the TRIMING Project NG-TRIMING NCO-19031-CS- QCBS / Technical Assistance Component 2: Irrigation Quality And Cost- for WUA in Bakolori Irrigation IDA / 55060 Development and Prior Open - International 2,156,440.00 0.00 Canceled 2014-12-12 2015-01-30 2015-04-14 2015-05-12 2015-07-11 2016-02-02 2018-03-05 2016-03-08 2019-06-19 Based Selection Schemes and Middle Rima Management. valley Irrigation Scheme FMWR/TRIMING/2020/QCBS/ CS/01 / TA Emergency Preparedness Plan and Action Component 1: Water Plan Framework and detailed Quality And Cost- IDA / 55060 Resources Management and Prior Open - International 1,500,000.00 0.00 Canceled 2020-04-23 2020-05-07 2020-06-11 2020-07-09 2020-07-23 2020-08-20 2020-09-17 2021-11-11 studies of the effect of Dam Based Selection Dam Operation Improvement. Break on Downstream settlement for TRIMING Project Dams Page 8 FMWR/TRIMING/2020/CQS/C S/01 / Gender Based Violence Component 2: Irrigation Consultant mapping of TRIMING Project IDA / 55060 Development and Post Qualification Open - National 290,000.00 258,070.09 Signed 2020-05-30 2020-05-06 2020-06-06 2020-06-17 2020-07-11 2020-10-06 2020-08-10 2020-11-12 2020-08-31 2020-12-04 2020-11-29 participating schemes and Management. Selection development of a proactive prevention response plan FMWR/TRIMING/QCBS/14/00 2 / Regularization of Contract for Consultancy Services for Technical Assistance for Water Component 2: Irrigation Users Associations and Quality And Cost- IDA / 55060 Development and Prior Open - International 2,156,445.00 1,629,867.50 Signed 2017-05-30 2017-06-20 2017-08-03 2020-05-18 2017-08-31 2015-05-28 2017-09-30 2020-06-16 2017-10-28 2020-06-28 2017-12-02 2016-03-09 2020-02-02 Scheme Management Based Selection Management. Development at Bakolori (BIS) and Middle Rima (MRVIS) Irrigation Schemes under TRIMING Project FMWR/TRIMING/2020/CQS/C S/03 / Technical Assistance on Integrated Pest Component 3: Enhancing Consultant Under Management and safe use of IDA / 55060 Agricultural Productivity and Post Qualification Open - National 150,000.00 0.00 2020-04-30 2020-05-06 2020-05-21 2020-06-04 2020-07-02 2020-07-23 2020-08-20 2021-02-16 Implementation chemicals on the use of Support to Value Chains. Selection scouting sheets, record keeping and data storage FMWR/TRIMING/QCBS/2015/ 01 / Regularization of subsisting Contract for Component 2: Irrigation Quality And Cost- Construction Supervision for IDA / 55060 Development and Prior Open - International 4,043,083.00 3,264,780.12 Signed 2015-01-04 2015-03-19 2016-03-09 2016-03-13 2016-09-12 2017-02-14 2020-09-10 2017-03-08 2017-03-08 2022-04-11 Based Selection Bakolori Irrigation Scheme Management. Rehabilitation and Reconversion FMWR/TRIMING/2020/QCBS/ CS/02 / Consultancy Services Component 2: Irrigation for Engagement of Security Quality And Cost- Under IDA / 55060 Development and Prior Open - International 1,800,000.00 0.00 2020-09-01 2020-08-28 2020-09-08 2020-09-01 2020-09-29 2021-01-08 2020-10-27 2021-02-10 2020-11-03 2021-07-31 2020-11-24 2020-12-15 2021-12-15 Management Firm at Bakolori, Based Selection Implementation Management. Kano, Hadejia and Dadin- Kowa Irrigation Schemes NG-TRIMING NCO-60760-CS- QCBS / Consultancy Services for Construction Supervision Component 1: Water of Kano River and Hadejia Quality And Cost- IDA / 55060 Resources Management and Prior Open - International 5,000,000.00 0.00 Canceled 2016-08-10 2018-04-27 2016-08-10 2017-08-18 2018-05-01 2017-10-30 2017-10-30 2018-04-26 2018-05-17 2018-05-31 2022-05-31 Valley Irrigation Schemes, Based Selection Dam Operation Improvement. Dams Safety and Rivers Training in Hadejia-Jama’are River Basins FMWR/TRIMING/QCBS/2016/ 01 / TA for Construction Supervision of Kano River and Component 1: Water Quality And Cost- Hadejia Valley Irrigation IDA / 55060 Resources Management and Prior Open - International 5,000,000.00 0.00 Canceled 2016-08-10 2016-08-10 2017-08-18 2017-10-30 2017-10-30 2018-04-13 2018-05-17 2018-06-07 2022-06-07 Based Selection Schemes, Dams Safety and Dam Operation Improvement. Rivers Training in Hadejia- Jama’are River Basins FMWR/TRIMING/2020/QCBS/ CS/03 / Consultancy Services for Feasibility Studies and Detailed Design of Benue Component 1: Water Quality And Cost- Under River Basin Water Resources IDA / 55060 Resources Management and Prior Open - International 4,550,000.00 0.00 2020-11-30 2021-01-12 2020-12-07 2021-01-19 2021-02-08 2021-03-08 2021-04-07 2021-05-12 2021-06-09 2022-12-01 Based Selection Implementation Development and Dam Operation Improvement. Management Program for Formulation of TRIMING Project II FMWR/TRIMING/2020/CQS/C S/03/01 / Consultancy Services for Preparation of an Environmental and Social Component 2: Irrigation Consultant Management Plan (ESMP) for Under IDA / 55060 Development and Post Qualification Open - National 150,000.00 0.00 2020-12-05 2020-12-10 2020-12-10 2020-12-21 2021-01-07 2021-03-12 2021-01-21 2021-02-02 2021-05-03 Intervention to Support Implementation Management. Selection Livelihood Options for the Maradun Community Affected During the Bakolori Dam Construction FWMR/TRIMING/2021/CQS/C S/01 / Consultancy Services for the Preparation of an Component 2: Irrigation Consultant Environmental and Social Under IDA / 55060 Development and Post Qualification Open - National 200,000.00 0.00 2021-08-23 2021-08-12 2021-08-30 2021-09-27 2021-10-11 2021-11-08 2022-02-06 Safeguards Audit for the Implementation Management. Selection Transforming Irrigation Management in Nigeria (TRIMING) Project FWMR/TRIMING/2021/CQS/C S/02/01 / Consultancy Component 2: Irrigation Consultant Services for Preparation and Under IDA / 55060 Development and Post Qualification Open - National 295,000.00 0.00 2021-08-16 2021-08-12 2021-08-23 2021-08-17 2021-09-20 2021-10-04 2021-10-18 2023-04-11 Implementation of a Implementation Management. Selection Resettlement Action Plan for Jankarawa interventions INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-TRIMING NCO-14061-CS- CDS / Supervision of ADP on Component 3: Enhancing Extension service delivery in IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 450,000.00 447,571.03 Completed 2016-11-11 2016-12-14 2016-09-23 2017-05-26 2017-10-10 2018-01-21 2019-03-21 all TRIMING Project Schemes Support to Value Chains. by IFDC NG-TRIMING NCO-19036-CS- CDS / Technical Assistance on Quality Assuarance and Component 2: Irrigation Quality Control of aerial(LiDar) IDA / 55060 Development and Post Direct Selection Direct 90,000.00 75,000.00 Completed 2017-06-20 2017-02-12 2017-07-01 2017-06-02 2017-07-14 2017-06-20 2018-03-11 2019-07-10 survey for Dadin-Kowa and Management. Guyuk proposed scheme (Gongola Sub-Basin) Page 9 NG-TRIMING NCO-19809-CS- CDS / Third phase of Technical Assistance and Capacity Building on Integrated Pest Management Component 3: Enhancing and Safe use of Chemicals IDA / 55060 Agricultural Productivity and Post Direct Selection Direct 100,000.00 71,372.25 Completed 2017-09-29 2017-11-22 2017-10-09 2017-11-24 2017-12-13 2018-01-18 2018-06-11 2018-07-23 targeted at the staffs of the Support to Value Chains. proposed consultancy on the Establishment of Farmers Management Service Centers and retraining of the ADPs FWMR/TRIMING/2018/IC/CS/ 01 / Preparation of site- Component 2: Irrigation Individual specific Environmental & IDA / 55060 Development and Post Consultant Open 100,000.00 0.00 Canceled 2018-07-03 2018-08-21 2018-09-11 2018-10-16 2019-04-14 Social Management Plan Management. Selection (ESMP) for Jankarawa Irrigation and other Projects. FWMR/TRIMING/2018/SS/CS/ 01 / Consultancy services for Component 3: Enhancing demonstration of small laser IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-04-28 2018-05-08 2018-07-12 2018-09-18 leveling equipment/Technique Support to Value Chains. for farm irrigation practices for TRIMING project sites. FWMR/TRIMING/2018/SS/CS/ 02 / 4th phase of TA and Capacity Building on Integrated Pest Management Component 3: Enhancing and Safe use of Chemicals IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-09-05 2018-09-15 2018-10-31 2019-04-29 targeted at the staffs of the Support to Value Chains. proposed consultancy on the Establishment of Farmers Management Service Centers and retraining of the ADPs FWMR/TRIMING/2018/SS/CS/ 03 / Consultancy Services for Component 4: Institutional computerized Accounting IDA / 55060 Development and Project Post Direct Selection Direct 35,000.00 0.00 Canceled 2018-10-01 2018-10-11 2018-12-15 2019-06-13 software upgrade for TRIMING Management. project stores FWMR/TRIMING/2018/IC/CS/ 02 / Technical backstop Component 4: Institutional Individual services for the IDA / 55060 Development and Project Post Consultant Open 90,000.00 0.00 Canceled 2018-06-13 2018-07-18 2018-08-01 2018-08-29 2019-02-25 implementation of TRIMING Management. Selection M&E system FWMR/TRIMING/2018/SS/CS/ Component 4: Institutional 04 / Consultancy Services for Pending IDA / 55060 Development and Project Post Direct Selection Direct 95,000.00 0.00 2018-04-23 2018-05-07 2018-06-25 2018-08-24 Training of FMWR/PMU on Implementation Management. FIDIC contract management FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual 03 / Techanical Assistance IDA / 55060 Development and Project Post Consultant Open 100,000.00 299,585.32 Signed 2018-03-12 2019-03-18 2018-04-30 2019-07-16 2018-05-21 2019-07-24 2018-06-25 2019-11-10 2018-12-22 _Irrigation Specialist Management. Selection FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual 04 / Techanical IDA / 55060 Development and Project Post Consultant Open 100,000.00 127,150.09 Signed 2018-03-12 2019-03-18 2018-04-09 2019-07-16 2018-04-13 2019-07-23 2018-04-27 2019-11-06 2019-04-27 Assistance_Dam Safety Management. Selection Specialist FWMR/TRIMING/2018/IC/CS/ Component 4: Institutional Individual 05 / Techanical IDA / 55060 Development and Project Post Consultant Open - National 100,000.00 126,962.63 Signed 2018-03-12 2019-03-18 2018-04-09 2019-07-16 2018-04-12 2019-10-15 2018-04-23 2019-11-01 2019-04-23 Assistance_Contract Management. Selection Management Specialist FMWR/TRIMING/2018/IC/CS/ 06 / Engagement of IT Component 4: Institutional Individual Consultant for the supervision IDA / 55060 Development and Project Post Consultant Limited 100,000.00 79,641.06 Signed 2018-06-15 2020-08-10 2018-06-20 2020-08-14 2018-07-11 2020-09-14 2018-08-15 2020-12-21 2019-02-11 of ERDMS Management. Selection Implementation/Roll out NG-TRIMING NCO-75569-CS- CDS / Innovative Research and Development on Participatory Soil Salinity/Sodicity Component 3: Enhancing Management for Sustainable IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 400,000.00 327,263.92 Signed 2018-09-12 2018-12-12 2018-09-22 2018-02-06 2018-10-07 2019-03-07 2021-09-21 Crop Productivity under Support to Value Chains. Irrigation and Improved Livelihood in Kano River Irrigation Scheme (KRIS) NG-TRIMING NCO-76575-CS- CDS / Addendun No. 1 to Component 3: Enhancing Supervision of ADP on IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 495,000.00 1,363,377.36 Signed 2018-09-23 2018-10-14 2018-11-07 2018-11-18 2019-03-25 2019-11-13 Extension service delivery in Support to Value Chains. all TRIMING Project Schemes by IFDC NG-TRIMING NCO-76531-CS- INDV / Recruitment of Component 4: Institutional Individual Scheme Safeguards Officer in IDA / 55060 Development and Project Post Consultant Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 Hadejia Jamare sub Basin with Management. Selection KRIS and HVIS (Social Safeguards) NG-TRIMING NCO-76569-CS- INDV / Recruitment of Scheme Component 4: Institutional Individual Safeguards Officer in Hadejia IDA / 55060 Development and Project Post Consultant Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 Valley irrigation Project (HVIP) Management. Selection (Social Safeguards) NG-TRIMING NCO-76582-CS- INDV / Recruitment of Component 4: Institutional Individual Scheme Safeguards Officer in IDA / 55060 Development and Project Post Consultant Open 20,000.00 0.00 Canceled 2018-09-20 2018-09-10 2018-10-11 2018-10-25 2018-11-08 2019-11-03 dadinkowa Irrigation Scheme Management. Selection (Social Safeguards) Page 10 NG-TRIMING NCO-76584-CS- CDS / Addendum No. 1 - TA for Dam Safety Assurance- Emergency Preparedness Plan Component 1: Water and Action Plan Framework IDA / 55060 Resources Management and Prior Direct Selection Direct 1,200,000.00 0.00 Canceled 2018-09-30 2018-10-21 2018-12-16 2020-12-05 and detailed studies of the Dam Operation Improvement. effect of Dam Break on Downstream settlement for TRIMING Project Dams (7. Nos) NG-TRIMING NCO-76532-CS- Component 1: Water INDV / Technical Assistance IDA / 55060 Resources Management and Prior Direct Selection Direct 100,000.00 0.00 Canceled 2018-09-25 2019-02-21 2018-10-14 2018-12-09 2020-11-28 for Implementation Support of Dam Operation Improvement. WUA regulations NG-TRIMING NCO-75571-CS- CDS / Innovative Research and Development for Identification and Implementation of Land Component 3: Enhancing Administration and IDA / 55060 Agricultural Productivity and Prior Direct Selection Direct 400,000.00 295,044.17 Signed 2018-09-12 2018-09-22 2018-02-08 2018-10-07 2019-03-07 2021-09-21 Consolidation Approaches for Support to Value Chains. Sustainable Development of Dadin-Kowa Irrigation Project (DKIP) NG-TRIMING NCO-77750-CS- CDS / Additional Studies and Component 2: Irrigation Design for the Jankarawa IDA / 55060 Development and Prior Direct Selection Direct 300,000.00 240,321.94 Signed 2018-11-20 2018-11-06 2018-12-11 2018-03-22 2019-01-08 2019-02-18 2019-09-05 Intervention as Part of the Management. Bakolori Irrigation Scheme NG-TRIMING NCO-83840-CS- CDS / Consultancy Services Component 4: Institutional for Periodic M & E data IDA / 55060 Development and Project Prior Direct Selection Direct 250,000.00 0.00 Canceled 2018-10-31 2018-11-15 2018-11-28 2019-01-09 2019-04-17 collection and Mid -Term Management. Impact Evaluation Review NG-TRIMING NCO-88280-CS- INDV / Recruitment of Component 4: Institutional Individual TRIMING Project Secretary IDA / 55060 Development and Project Post Consultant Open 20,000.00 0.00 Canceled 2018-12-10 2018-11-27 2019-01-14 2019-01-21 2019-02-04 2020-02-04 with particular focus to the Management. Selection Project Coordinator’s Office NG-TRIMING NCO-88279-CS- Component 4: Institutional Individual INDV / Recruitment of IDA / 55060 Development and Project Post Consultant Open 20,000.00 0.00 Canceled 2018-12-10 2018-11-27 2019-01-21 2019-01-28 2019-02-11 2020-02-11 TRIMING Project Front Desk Management. Selection Officer / Receptionist NG-TRIMING NCO-91462-CS- Component 2: Irrigation Individual INDV / TRIMING Security IDA / 55060 Development and Post Consultant Limited 100,000.00 0.00 Canceled 2018-12-14 2019-03-06 2018-12-19 2018-12-26 2019-01-09 2020-01-09 Coordinator for BIS Management. Selection FMWR/TRIMING/2019/INDV/C S/01 / Elaboration and Component 2: Irrigation Individual implementation of IDA / 55060 Development and Post Consultant Limited 50,000.00 0.00 Canceled 2019-03-28 2019-04-11 2019-04-25 2019-05-16 2019-11-12 Resettlement Action Plan For Management. Selection additional works in Bakolori Irrigation Scheme FMWR/TRIMING/2019/INV/CS /02 / Engagement of TRIMING Component 2: Irrigation Individual Security Coordinator for BIS IDA / 55060 Development and Post Consultant Limited 100,000.00 0.00 Canceled 2019-02-25 2019-03-02 2019-03-09 2019-04-06 2021-04-05 for initial period of two (2) Management. Selection years FMWR/TRIMING/2019/INV/CS /03 / TA on Mentoring of SRBDA staff attached to Component 1: Water Individual Bakolori dam on dam safety IDA / 55060 Resources Management and Post Consultant Limited 100,000.00 39,177.30 Signed 2019-02-25 2019-08-23 2019-03-11 2020-07-03 2019-03-25 2020-09-22 2019-04-29 2020-11-01 2021-04-28 operations and Dam Operation Improvement. Selection instrumentation for two (2) years FMWR/TRIMING/2019/INV/CS /04 / TA on Mentoring of UBRDA staff attached to Dadin Component 1: Water Individual Kowa dam on dam safety IDA / 55060 Resources Management and Post Consultant Limited 100,000.00 39,177.30 Signed 2019-02-25 2019-08-23 2019-03-04 2020-07-03 2019-03-18 2020-09-22 2019-04-15 2020-11-01 2021-04-14 operations and Dam Operation Improvement. Selection instrumentation for two (2) years FMWR/TRIMING/2019/INDV/C Component 4: Institutional Individual S/02 / Engagement of two IDA / 55060 Development and Project Post Consultant Limited 20,000.00 0.00 Canceled 2019-04-15 2019-04-29 2019-05-13 2019-06-10 2020-06-09 (2Nos) Procurement Asssitant Management. Selection NG-TRIMING NCO-102152- CS-CDS / TA for Consultancy Component 1: Water Services for Dam Safety of IDA / 55060 Resources Management and Prior Direct Selection Direct 350,000.00 311,431.74 Signed 2019-03-15 2019-07-22 2019-04-08 2019-08-05 2019-05-13 2020-05-20 2019-11-09 Dadinkowa Irrigation Scheme Dam Operation Improvement. (DKIS) in upper Benue River Basin FMWR/TRIMING/2019/CDS/C S/01 / Consultancy Services for engagement of PSC-1 Component 2: Irrigation Secuirty firm for Provision of IDA / 55060 Development and Prior Direct Selection Direct 1,200,000.00 1,683,091.17 Terminated 2019-08-10 2019-07-24 2019-08-24 2019-07-25 2019-10-05 2019-11-01 2020-10-04 Project Risk Manager (PRM) Management. and Security Coordinators at BIS, KRIS, HVIS and DKIS at TRIMING sites NG-TRIMING NCO-129623- CS-INDV / Upgrade of the Monitoring and Evaluation Component 4: Institutional Individual (M&E) Application of the IDA / 55060 Development and Project Post Consultant Limited 80,000.00 33,416.44 Signed 2019-09-25 2019-09-05 2019-10-02 2019-09-24 2019-10-16 2020-08-14 2019-11-13 2020-08-20 2020-05-11 Transforming Irrigation Management. Selection Management in Nigeria (TRIMING) Project NG-TRIMING NCO-101098- CS-CDS / Engagement of Component 2: Irrigation Third Party NGO through an IDA / 55060 Development and Prior Direct Selection Direct 50,000.00 0.00 Canceled 2019-03-18 2019-04-15 2019-05-13 2021-05-02 MOU (RAP Implementation) for Management. Hadejia Valley Irrigation Scheme (HVIS) Page 11 NG-TRIMING NCO-101094- CS-CDS / Engagement of Component 2: Irrigation Third Party NGO through an IDA / 55060 Development and Prior Direct Selection Direct 50,000.00 0.00 Canceled 2019-03-18 2019-04-15 2019-05-13 2022-04-27 MOU (RAP Implementation) for Management. Bakolori Irrigation Scheme (BIS) NG-TRIMING NCO-76523-CS- CDS / Engagement of Third Component 2: Irrigation Party NGO through an MOU IDA / 55060 Development and Prior Direct Selection Direct 65,000.00 0.00 Canceled 2018-09-15 2018-09-25 2018-10-06 2021-09-20 (RAP Implementation) for Management. Kano River Irrigation Scheme (KRIS) NG-TRIMING NCO-76566-CS- CDS / Engagement of Third Component 2: Irrigation Party NGO through an MOU IDA / 55060 Development and Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-09-15 2018-10-25 2018-09-27 2018-10-14 2021-09-28 (RAP Implementation) for Management. Bakolori Irrigation Scheme (BIS) NG-TRIMING NCO-76526-CS- CDS / Engagement of Third Component 2: Irrigation Party NGO through an MOU IDA / 55060 Development and Post Direct Selection Direct 50,000.00 0.00 Canceled 2018-09-15 2018-10-25 2018-09-27 2018-10-14 2020-10-03 (RAP Implementation) for Management. Hadejia Valley Irrigation Scheme (HVIS) FMWR/TRIMING/2020/INDV/C S/01 / Technical Assistance Component 3: Enhancing Individual for the training of farmer IDA / 55060 Agricultural Productivity and Post Consultant Limited 25,000.00 21,912.10 Completed 2020-04-20 2020-03-12 2020-04-27 2020-03-16 2020-05-18 2020-07-01 2020-06-08 2020-09-11 2020-08-07 2020-12-29 facilitators on farmer field and Support to Value Chains. Selection business school (FFBS) and on rice production FMWR/TRIMING/2020/INDV/C S/02 / Technical Assistance Component 4: Institutional Individual for GIS-Based Cataloguing Pending IDA / 55060 Development and Project Post Consultant Limited 100,000.00 0.00 2020-06-30 2020-07-14 2020-08-04 2020-09-01 2021-08-27 and Indexing of Irrigation Implementation Management. Selection Infrastructure Assets of all the five (5) TRIMING Schemes FMWR/TRIMING/2020/CDS/C S/02/01 / TA for Construction Supervision of Kano River and Component 1: Water Hadejia Valley Irrigation IDA / 55060 Resources Management and Prior Direct Selection Direct 2,793,651.00 2,710,686.36 Signed 2020-12-10 2021-01-25 2020-12-22 2021-02-01 2021-01-19 2021-08-03 2022-04-30 Schemes, Dams Safety and Dam Operation Improvement. Rivers Training in Hadejia- Jama’are River Basins works through direct selection FWMR/TRIMING/2021/CDS/C S/01/01 / Consultancy Services for Upscaling of Component 3: Enhancing Pending Research on the Utilization of IDA / 55060 Agricultural Productivity and Post Direct Selection Direct 200,000.00 0.00 2021-08-16 2021-08-26 2021-09-23 2023-03-17 Implementation Tpypa for Biogas and Animal Support to Value Chains. Feed Production in Hadejia Valley Irrigation Scheme (HVIS) FWMR/TRIMING/2021/CDS/C S/02/01 / Consultancy Services for Upscaling of research on Applying Component 3: Enhancing Innovation System Approach Pending IDA / 55060 Agricultural Productivity and Post Direct Selection Direct 200,000.00 0.00 2021-08-16 2021-08-26 2021-09-23 2023-03-17 in Rice Value Chain Analysis Implementation Support to Value Chains. and Development for Competitive Market in Bakolori Irrigation Scheme (BIS) FWMR/TRIMING/2021/CDS/C S/03/01 / Consultancy Services Upscaling of Research on Testing and Promotion of System of Rice Component 3: Enhancing Pending Intensification (SRI) Practices IDA / 55060 Agricultural Productivity and Post Direct Selection Direct 300,000.00 0.00 2021-08-16 2021-08-26 2021-09-23 2023-03-17 Implementation for sustainable Rice Support to Value Chains. Production in Middle Rima Valley Irrigation Scheme (MRVIS) and Dadinkowa Irrigation Scheme (DKIS) Page 12