Procurement Plan for Project of Integrated Urban and Tourism Development I. General 1. Bank’s approval Date of the procurement Plan [Original: July 15,2016]: Revision 1 of Updated Procurement Plan, May 2017 2. Date of General Procurement Notice: April 26, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to October 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Expenditure Contract Procurement Method Bank Prior Review Category Value (USD) >= 5,000,000 ICB All >/=US$10 million contracts < 5,000,000 NCB First contract Civil Works <200,000 Shopping First contract NA DC US$60,000 >= 1,000,000 ICB All >/=US$1million contracts Goods <1,000,000 NCB First contract <100,000 Shopping First contract NA DC US$60,000 4. Reference to (if any) Project Operational/Procurement Manual: Project Operational Manual for World Bank Loan Project P155875 PIUDT issued by Albanian Development Fund on 24.04.2017 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 Review Domestic Preference Ref. No. Description Packages by Bank Comments (yes/no) (Prior/Post) Summary of the 2 No ICB (Works) AL- Berat Town of ADF15547- integrated Urban Prior CW-RFB upgrading Saranda tourism C1W-S3 No Prior gateway integrated urban upgrading Summary of the 14 No Post NCB (Works) AL- Saranda staircase ADF15534- rehabilitation No Post CW-RFB Project Urban Regeneration of AL- the existing ADF15536- No Post promenade CW-RFB “Naim Frasheri” in Saranda Ali Pasha AL- historic trail and ADF15538- slopes No Post CW-RFB stabilization – Gjirokastra AL- Street lightening ADF15539- historic center – No Post CW-RFB Gjirokstra AL- Bazaar coble ADF15540- stone roads No Post CW-RFB rehabilitation Gjirokastra AL- museum city ADF15541- No Post integrated urban CW-RFB upgrading Upgrading the AL- renovation of ADF15536- No Post systems of CW-RFB museums Rehabilitation of AL- Cobblestone ADF28554- road “Mihal No Prior CW-RFB Komneno”, Berat castle Upgrading to AL- vehicle access ADF15545- road “Muzak No Post CW-RFB Topia”, Berat Castle Visual upgrading No AL- of selected ADF15542- Post heritage CW-RFB landscape AL- Street lightening ADF15548- No Post – Permet CW-RFB AL- Permet ADF15549- integrated urban No Post CW-RFB upgrading Integrated AL- upgrading of ADF15550- No Post selected touristic CW-RFB area AL- Tourism Product ADF15551- development in 4 No Post CW-RFB municipalities Summary of the 6 No Post NCB (Goods) Solid waste AL-ADF- equipment for 15581-GO- No Prior Himara transfer RFB station Solid W collection AL-ADF- equipment(Gjirok 15582-GO- No Post astra/other as RFB needed Financial AL-ADF- Management 15583-GO- No Post Equipment for 4 RFB municipalities Asset AL-ADF- Management 15609-GO- No Post Equipment for 4 RFB municipalities AL-ADF- GIS equipment 15584-GO- and licenses for No Post RFB 4 municipalities Equipment for tourism AL-ADF- information 15586-GO- No Post management and RFB statistic improvement Summary of the 4 No Post SH (Goods) Equipment for AL-ADF- local destination 15585-GO- No Prior management RFB entities Office AL-ADF- equipment and 15588-GO- licenses for No Post RFB project implementation Purchase of AL-ADF- additional 44382-GO- accessories for No Post RFB smart board of ADF AL-ADF- 44382-GO- Vehicles No Post RFB III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Consultant QCBS, QBS, FBS, >/= USD 500,000 ; NA Services LCS and CQS* >=US$200,000 for IC and NA SSS >/=US$5,000 for SSS NA IC 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Review Ref. No. Description of Assignment Packages by Bank Comments (Prior/ Post) Summary of QCBS 8 AL-ADF- Concept, Design and Supervision of 44317-CS- Post Saranda Urban Upgrading (line 3) QCBS AL-ADF- Concept, Design and Supervision Urban 39736-CS- Post Upgrading Gjirokastra (line 7) QCBS AL-ADF- Concept, Design and Supervision of the 31055-CS- Berat and Permet Integrated Urban Post QCBS Upgrading (line 12 and14) AL-ADF- Site Management, Detailed design and 15563-CS- construction supervision for Infrastructure Prior QCBS of IUTS AL-ADF- Market Research & Development 15567-CS- Strategy for the South of Albania & four Post QCBS municipalities AL-ADF- Market Development for the South of 15568-CS- Albania (Tourism products promotion, Prior QCBS line 16 and component 2 works) AL-ADF- Tourism Product and value chain 15570-CS- development in selected municipalities Prior QCBS (line 16) AL-ADF- 44317-CS- Guesthouse branding and market delivery Prior QCBS Summary of CQS 9 Post AL-ADF- Design and Supervision Gjirokastra 15556-CS- Post system of museums (line 8) CQS AL-ADF- Supervision of fast truck subproject Berat 37871-CS- Post & Permet CQS AL-ADF- Supervision of fast truck subproject 37532-CS- Post Gjirokastra & Saranda CQS AL-ADF- Detailed design and construction 15562-CS- supervision for Infrastructure for Post CQS Viewpoints along the touristic circuit AL-ADF- Asset Management system - assessment 15565-CS- and technical specification for goods (line Post CQS 43) AL-ADF- Geographic Information Systems - 15566-CS- assessment and technical specification for Post CQS goods (line 44) AL-ADF- Tourism Information Management system 15574-CS- Post and Statistics Improvement - assessment CQS and technical specification of goods (line 46) AL-ADF- 15580-CS- Results Assessment (M&E) Post INDV AL-ADF- Design and urban regeneration of the 15557-CS- existing promenade “Naim Frasheri”, Post CQS Sarande Summary of IC 7 Post AL-ADF- International expert on conservation and 15559-CS- structural restoration of monuments and Post INDV historic buildings. (line 4) AL-ADF- Financial Management Systems - 15566-CS- assessment and technical specifications Post INDV for goods. (line 42) AL-ADF- Project Coordinator - Urban Specialist 15576-CS- Prior PCU INDV AL-ADF- 15576-CS- Tourism Specialist - PCU Prior INDV AL-ADF- 15577-CS- Architect - PCU Prior INDV AL-ADF- 15578-CS- Cultural Heritage Consultant Post INDV AL-ADF- 15579-CS- Site Management Consultant Post INDV PROCUREMENT Albania : Project for Integrated Urban and Tourism Development (PIUTD) PLAN General Information Country: Albania Bank’s Approval Date of the Original Procurement Plan: 2017-05-22 2019-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155875 GPN Date: 2017-05-23 Project Name: Project for Integrated Urban and Tourism Development (PIUTD) Loan / Credit No: IBRD / 86560 Executing Agency(ies): Albanian Development Fund WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15534-CW-RFB / Component 1: Urban Under Single Stage - One Saranda Staircase IBRD / 86560 Upgrading and Post Request for Bids Open - National 894,776.70 Implementati 2017-05-19 2017-05-24 2017-07-05 2017-08-04 2017-09-08 2018-02-08 Envelope Rehabilitation Project Infrastructure Improvement on AL-ADF-15543-CW-RFB / Component 1: Urban Rehabilitation of Cobblestone Single Stage - One IBRD / 86560 Upgrading and Prior Request for Bids Open - National 0.00 Canceled 2017-05-18 2017-05-23 2017-07-04 2017-08-03 2017-09-07 2018-02-07 Road "Mihal Komneno" to Envelope Infrastructure Improvement Berat castle AL-ADF-16753-CW-RFB / Component 1: Urban Rehabilitation of Cobblestone Single Stage - One IBRD / 86560 Upgrading and Prior Request for Bids Open - National 0.00 Canceled 2017-06-02 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Road "Mihal Komneno" to Envelope Infrastructure Improvement Berat castle AL-ADF-28554-CW-RFB / Component 1: Urban Under Rehabilitimi i rrugës hyrëse Single Stage - One IBRD / 86560 Upgrading and Prior Request for Bids Open - National 0.00 Implementati 2017-09-14 2017-09-19 2017-10-31 2017-11-30 2018-01-04 2018-07-03 "Mihal Komneno" për në Envelope Infrastructure Improvement on Kala dhe Tabja AL-ADF-15545-CW-RFB / Component 1: Urban Under Upgrading of vehicle access Single Stage - One IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2018-03-01 2018-03-06 2018-04-17 2018-05-17 2018-06-21 2019-01-19 road "Muzak Topia" to Berat Envelope Infrastructure Improvement on castle AL-ADF-15540-CW-RFB / Component 1: Urban Single Stage - One Bazaar cobble stone roads IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2019-05-20 Envelope rehabilitation Infrastructure Improvement Component 1: Urban AL-ADF-15548-CW-RFB / Single Stage - One IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Canceled 2018-03-29 2018-04-03 2018-05-15 2018-06-14 2018-07-19 2018-10-18 Street lighting - Permet Envelope Infrastructure Improvement AL-ADF-15550-CW-RFB / Pending Component 2: Touristic Single Stage - One Integrated upgrading of IBRD / 86560 Post Request for Bids Open - National 0.00 Implementati 2019-04-16 2019-04-21 2019-06-02 2019-07-02 2019-08-06 2021-02-02 Sites Upgrading Envelope selected touristic sites. on AL-ADF-62551-CW-RFB / Component 1: Urban Under Single Stage - One Bazaar cobblestone roads IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 Envelope rehabilitation Infrastructure Improvement on Component 1: Urban Pending AL-ADF-63100-CW-RFQ / Request for Single Stage - One IBRD / 86560 Upgrading and Post Limited 0.00 Implementati 2018-06-04 2018-07-30 2019-01-26 Street lighting - Permet Quotations Envelope Infrastructure Improvement on AL-ADF-15538-CW-RFB / Component 1: Urban Pending Ali Pasha historic trail and Single Stage - One IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2019-07-12 2019-07-17 2019-08-28 2019-09-27 2019-11-01 2020-06-02 slopes stabilization - Envelope Infrastructure Improvement on Gjirokastra Page 1 AL-ADF-15541-CW-RFB / Component 1: Urban Pending Single Stage - One Gjirokastra Museum City IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2020-01-06 2020-01-11 2020-02-22 2020-03-23 2020-04-27 2021-12-26 Envelope Integrated Urban Upgrading Infrastructure Improvement on AL-ADF-15539-CW-RFB / Component 1: Urban Pending Single Stage - One Street lighting historic IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2019-05-30 2019-06-04 2019-07-16 2019-08-15 2019-09-19 2020-02-19 Envelope center - Gjirokastra Infrastructure Improvement on AL-ADF-15542-CW-RFB / Component 1: Urban Pending Single Stage - One Upgrading and renovation of IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2021-05-07 Envelope system of museums Infrastructure Improvement on AL-ADF-15546-CW-RFB / Component 1: Urban Pending Single Stage - One Visual Upgrading of selected IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2019-09-09 2019-09-14 2019-10-26 2019-11-25 2019-12-30 2020-04-30 Envelope heritage landscape Infrastructure Improvement on AL-ADF-15549-CW-RFB / Component 1: Urban Pending Single Stage - One Permet integrated urban IBRD / 86560 Upgrading and Post Request for Bids Open - National 0.00 Implementati 2019-10-07 2019-10-12 2019-11-23 2019-12-23 2020-01-27 2021-05-28 Envelope upgraded Infrastructure Improvement on AL-ADF-15551-CW-RFB / Component 3:Tourism Pending Tourism Product Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-01-06 2020-01-11 2020-02-22 2020-03-23 2020-04-27 2021-12-18 development in 4 Envelope Development on municpalities Pending AL-ADF-51671-CW-RFB / Component 2: Touristic Single Stage - One IBRD / 86560 Post Request for Bids Open - National 0.00 Implementati 2020-01-15 2020-01-20 2020-03-02 2020-04-01 2020-05-06 2020-11-02 Construction of viewpoints Sites Upgrading Envelope on AL-ADF-15537-CW-RFB / Component 1: Urban Pending Open - Single Stage - Two Saranda Tourism Gateway IBRD / 86560 Upgrading and Post Request for Bids 0.00 Implementati 2020-01-15 2020-01-20 2020-03-02 2020-05-15 2020-06-19 2022-02-17 International Envelope Integrated Urban Upgrading. Infrastructure Improvement on AL-ADF-15547-CW-RFB / Component 1: Urban Pending Open - Single Stage - Two Berat Town of Integrated IBRD / 86560 Upgrading and Post Request for Bids 0.00 Implementati 2019-09-16 2019-09-21 2019-11-02 2020-01-15 2020-02-19 2021-09-19 International Envelope Urban Upgrading Infrastructure Improvement on AL-ADF-15536-CW-RFB / Component 1: Urban Under Urban Regeneration of the Open - Single Stage - One IBRD / 86560 Upgrading and Post Request for Bids 0.00 Implementati 2019-05-28 2019-06-02 2019-07-14 2019-08-13 2019-09-17 2020-03-15 Existing Promenade "Naim International Envelope Infrastructure Improvement on Frasheri" in Saranda GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15581-GO-RFB / Component 3:Tourism Single Stage - One Solid waste equipment for IBRD / 86560 Market and Product Prior Request for Bids Open - National 0.00 Canceled 2017-05-30 2017-06-04 2017-07-16 2017-08-15 2017-09-19 2018-01-19 Envelope Himara transfer station Development Under AL-ADF-15589-GO-RFQ / Component 4: Request for Single Stage - One IBRD / 86560 Post Open - National 131,517.71 Implementati 2017-07-05 2017-08-30 2017-11-30 Vehicles Implementation Support Quotations Envelope on AL-ADF-44382-GO-RFQ / Pending Purchase of additional Component 4: Request for Single Stage - One IBRD / 86560 Post Open - National 0.00 Implementati 2018-01-24 2018-03-21 2018-09-17 accessories for smart board Implementation Support Quotations Envelope on of ADF's meeting room Page 2 AL-ADF-54729-GO-RFB / Component 3:Tourism Under Single Stage - One Solid waste equipment for IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2018-04-10 2018-04-15 2018-05-27 2018-06-26 2018-07-31 2019-01-27 Envelope Himara transfer station Development on AL-ADF-15582-GO-RFB / Component 3:Tourism Pending Solid W collection Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-10 2020-02-15 2020-03-28 2020-04-27 2020-06-01 2020-10-30 equipment(Gjirokastra/other Envelope Development on as needed) AL-ADF-15586-GO-RFB / Component 3:Tourism Pending Equipment for tourism Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2019-11-18 2019-11-23 2020-01-04 2020-02-03 2020-03-09 2020-07-10 information management and Envelope Development on statistic improvement AL-ADF-15588-GO-RFQ / Under Office equipment and Component 4: Request for Single Stage - One IBRD / 86560 Post Open - National 0.00 Implementati 2018-03-25 2018-05-20 2018-08-20 licenses for project Implementation Support Quotations Envelope on implementation AL-ADF-15584-GO-RFB / Component 3:Tourism Pending Single Stage - One GIS equipment and licenses IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-17 2020-02-22 2020-04-04 2020-05-04 2020-06-08 2020-12-06 Envelope for 4 municipalities Development on AL-ADF-15583-GO-RFB / Component 3:Tourism Pending Financial Management Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 2020-11-22 Equipment for 4 Envelope Development on municipalities AL-ADF-15609-GO-RFB / Component 3:Tourism Pending Asset Management Single Stage - One IBRD / 86560 Market and Product Post Request for Bids Open - National 0.00 Implementati 2020-02-06 2020-02-11 2020-03-24 2020-04-23 2020-05-28 2020-12-26 Equipment for 4 Envelope Development on municipalities AL-ADF-111910-GO-RFQ / Component 3:Tourism Pending Equipment for local Request for Single Stage - One IBRD / 86560 Market and Product Post Open - National 0.00 Implementati 2019-10-19 2019-12-14 2020-03-13 destination management Quotations Envelope Development on entities NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15552-CS-QCBS / Component 1: Urban Concept, Design and Quality And Cost- Open - IBRD / 86560 Upgrading and Prior 0.00 Canceled 2017-05-30 2017-06-20 2017-08-03 2017-08-31 2017-09-30 2017-11-04 2017-12-09 2020-07-09 Supervision of Saranda Based Selection International Infrastructure Improvement Urban Upgrading (line 3) AL-ADF-15557-CS-CQS / Design of Urban Component 1: Urban Consultant Under Regeneration of the Existing IBRD / 86560 Upgrading and Post Qualification Open - National 0.00 2017-07-11 2017-08-01 2017-09-14 2017-10-14 2017-11-18 2018-05-20 Implementation Promenade "Naim Frasheri" Infrastructure Improvement Selection in Saranda. (line 2) Page 3 AL-ADF-15562-CS-CQS / Detailed design and Consultant Component 2: Touristic Open - Under construction supervision for IBRD / 86560 Post Qualification 0.00 2017-05-29 2017-06-19 2017-08-02 2017-09-01 2017-10-06 2019-05-06 Sites Upgrading International Implementation Infrastructure for Viewpoints Selection along the touristic circuit AL-ADF-15567-CS-QCBS / Market Research & Component 3:Tourism Quality And Cost- Open - Under Development Strategy for IBRD / 86560 Market and Product Post 324,092.59 2017-05-26 2017-06-16 2017-07-30 2017-08-27 2017-09-26 2017-10-31 2017-12-05 2018-07-05 Based Selection International Implementation the South of Albania & four Development municipalities Consultant AL-ADF-15580-CS-INDV / Component 4: IBRD / 86560 Post Qualification Open - National 0.00 Canceled 2019-03-12 2019-03-26 2019-05-21 2019-06-25 2022-06-25 Results Assessment (M&E) Implementation Support Selection AL-ADF-15561-CS-CQS / Component 1: Urban Consultant Supervision of fast truck Open - IBRD / 86560 Upgrading and Post Qualification 0.00 Canceled 2017-05-31 2017-06-21 2017-08-04 2017-09-03 2017-10-08 2019-02-08 subproject ( line International Infrastructure Improvement Selection 1,2,4,5,6,9,10,13) AL-ADF-15555-CS-QCBS / Concept, Design and Component 1: Urban Quality And Cost- Open - Supervision of the Berat and IBRD / 86560 Upgrading and Prior 0.00 Canceled 2017-05-31 2017-06-21 2017-08-04 2017-09-01 2017-10-01 2017-11-05 2017-12-10 2020-06-09 Based Selection International Permet Integrated Urban Infrastructure Improvement Upgrading ( line 12 and14) AL-ADF-31055-CS-QCBS / Concept, Detail Designs and Component 1: Urban supervision for Integrated Quality And Cost- Open - Under IBRD / 86560 Upgrading and Post 1,119,945.08 2017-10-04 2017-10-25 2017-12-08 2018-01-05 2018-02-04 2018-03-11 2018-04-15 2019-04-15 Urban Upgrading Based Selection International Implementation Infrastructure Improvement Municipalities of Berati and Përmeti AL-ADF-21339-CS-QBS / Component 1: Urban Supervision of fast truck sub- Quality Based IBRD / 86560 Upgrading and Post Open - National 0.00 Canceled 2017-07-20 2017-08-10 2017-09-23 2017-10-21 2017-11-20 2017-12-20 2018-01-24 2019-01-24 project (Saranda and Selection Infrastructure Improvement Gjirokastra) AL-ADF-37532-CS-CQS / Component 1: Urban Consultant Supervision of fast truck Pending IBRD / 86560 Upgrading and Post Qualification Open - National 0.00 2017-11-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2018-09-26 subproject (Saranda and Implementation Infrastructure Improvement Selection Gjirokastra) AL-ADF-21342-CS-QBS / Component 1: Urban Quality Based Supervision of fast truck sub- IBRD / 86560 Upgrading and Post Open - National 0.00 Canceled 2017-07-21 2017-08-11 2017-09-24 2017-10-22 2017-11-21 2017-12-21 2018-01-25 2019-01-25 Selection project (Berat and Permet) Infrastructure Improvement AL-ADF-37871-CS-CQS / Supervision services for fast- Component 1: Urban Consultant truck sub-project in urban Pending IBRD / 86560 Upgrading and Post Qualification Open - National 0.00 2017-11-22 2017-12-13 2018-01-26 2018-02-25 2018-04-01 2018-09-28 upgrading and infrastructure Implementation Infrastructure Improvement Selection improvement (Berat and Permet) AL-ADF-15553-CS-QCBS / Concept, Design and Component 1: Urban Quality And Cost- Open - Supervision Urban IBRD / 86560 Upgrading and Prior 0.00 Canceled 2017-06-30 2017-07-21 2017-09-03 2017-10-01 2017-10-31 2017-12-05 2018-01-09 2020-07-09 Based Selection International Upgrading Gjirokastra (line Infrastructure Improvement 7) AL-ADF-44317-CS-QCBS / Municipality of Saranda - Detailed Designs and Component 2: Touristic Quality And Cost- Open - Under IBRD / 86560 Post 785,770.71 2018-01-17 2018-02-07 2018-03-23 2018-04-20 2018-05-20 2018-06-24 2018-07-29 2019-07-29 Construction Supervision for Sites Upgrading Based Selection International Implementation Saranda Tourism Gateway Integrated Urban Upgrading Page 4 AL-ADF-39736-CS-QCBS / Concept, Design and Component 1: Urban Quality And Cost- Open - Under Supervision Urban IBRD / 86560 Upgrading and Post 458,168.07 2017-12-07 2017-12-28 2018-02-28 2018-03-28 2018-04-27 2018-06-01 2018-07-06 2019-07-06 Based Selection International Implementation Upgrading Gjirokastra (line Infrastructure Improvement 7) AL-ADF-15556-CS-CQS / Component 1: Urban Consultant Design and Supervision Under IBRD / 86560 Upgrading and Post Qualification Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2020-08-21 Gjirokastra system of Implementation Infrastructure Improvement Selection museums (line 8) AL-ADF-62578-CS-CQS / Primary Data Collection, Development of Mid-Term Consultant Component 4: Under and End Follow up Surveys, IBRD / 86560 Post Qualification Open - National 0.00 2018-05-14 2018-05-16 2018-06-29 2018-07-29 2018-09-02 2019-03-01 Implementation Support Implementation Assessment of PDO findings Selection achievement in the framework of PIUTD AL-ADF-15563-CS-QCBS / Site Management, Detailed Component 2: Touristic Quality And Cost- Open - Pending design and construction IBRD / 86560 Post 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-01 2018-07-31 2018-09-04 2018-10-09 2020-06-07 Sites Upgrading Based Selection International Implementation supervision for Infrastructure of IUTS AL-ADF-67670-CS-CQS / Site management, Consultant interpretive and visitor Component 2: Touristic Open - Under IBRD / 86560 Post Qualification 0.00 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 experience plans for Zvernec Sites Upgrading International Implementation Selection - Narta & Benja thermal waters touristic sites AL-ADF-15565-CS-CQS / Asset Management system - Component 3:Tourism Consultant Pending assessment and technical IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-09-21 Implementation specification for goods (line Development Selection 43) AL-ADF-15566-CS-CQS / Geographic Information Component 3:Tourism Consultant Pending Systems - assessment and IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-10-30 2019-11-20 2020-01-03 2020-02-02 2020-03-08 2020-09-07 Implementation technical specification for Development Selection goods (line 44) AL-ADF-15568-CS-QCBS / Market Development for the Component 3:Tourism Quality And Cost- Open - Pending South of Albania (Tourism IBRD / 86560 Market and Product Post 0.00 2019-05-16 2019-06-06 2019-07-20 2019-08-17 2019-09-16 2019-10-21 2019-11-25 2022-09-24 Based Selection International Implementation products promotion, line 16 Development and component 2 works) AL-ADF-15573-CS-QCBS / Component 3:Tourism Quality And Cost- Open - Pending Guesthouse branding and IBRD / 86560 Market and Product Post 0.00 2019-10-31 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2023-07-12 Based Selection International Implementation market delivery Development AL-ADF-15574-CS-CQS / Tourism Information Management system and Component 3:Tourism Consultant Pending Statistics Improvement - IBRD / 86560 Market and Product Post Qualification Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-03 2019-09-07 2020-04-08 Implementation assessment and technical Development Selection specification of goods (line 46) AL-ADF-15570-CS-QCBS / Tourism Product and value Component 3:Tourism Quality And Cost- Open - Pending chain development in IBRD / 86560 Market and Product Prior 0.00 2019-12-02 2019-12-23 2020-02-05 2020-03-04 2020-04-03 2020-05-08 2020-06-12 2023-07-13 Based Selection International Implementation selected municipalities (line Development 16) Page 5 AL-ADF-123249-CS-CQS / “Identification, Design of prioritized measures to Component 1: Urban Consultant Open - Pending address urgent safety IBRD / 86560 Upgrading and Post Qualification 0.00 2019-07-28 2019-08-18 2019-10-01 2019-10-31 2019-12-05 2020-06-02 International Implementation concerns and prevent loss of Infrastructure Improvement Selection heritage structures in the castle of Gjirokastra INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AL-ADF-15172-CS-INDV / Individual Component 4: Under Project Coordinator - Urban IBRD / 86560 Prior Consultant Open 0.00 2017-05-13 2017-07-01 2017-07-22 2017-08-26 2022-09-26 Implementation Support Implementation Specialist PCU Selection Individual AL-ADF-15576-CS-INDV / Component 4: Under IBRD / 86560 Prior Consultant Open 0.00 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2022-10-01 Tourism Specialist - PCU Implementation Support Implementation Selection Individual AL-ADF-15577-CS-INDV / Component 4: Under IBRD / 86560 Prior Consultant Open 0.00 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2022-10-01 Architect - PCU Implementation Support Implementation Selection AL-ADF-15559-CS-INDV / International expert on Component 1: Urban Individual conservation and structural Under IBRD / 86560 Upgrading and Post Consultant Open 0.00 2017-05-29 2017-07-17 2017-08-07 2018-03-07 2018-04-06 restoration of monuments Implementation Infrastructure Improvement Selection and historic buildings. (line 4) AL-ADF-67092-CS-INDV / Individual Consultant for Preparation of a Property Evaluation Report of Project Individual Component 4: Under Affected Persons due to the IBRD / 86560 Post Consultant Open 0.00 2018-06-29 2018-08-17 2018-09-07 2018-10-12 2019-04-10 Implementation Support Implementation planned implementation of Selection subproject "Upgrading of the vehicle road segment Muzak Topia to Berat Castle" AL-ADF-95814-CS-INDV / Assessment of social impact Individual at proposed Blue Eye Component 4: Under IBRD / 86560 Post Consultant Limited 0.00 2019-01-22 2019-01-27 2019-02-17 2019-03-24 2019-04-13 touristic site Implementation Support Implementation Selection Project for Integrated Tourism Development AL-ADF-15564-CS-INDV / Financial Management Component 3:Tourism Individual Pending Systems - assessment and IBRD / 86560 Market and Product Post Consultant Open 0.00 2019-09-18 2019-11-06 2019-11-27 2020-01-01 2020-05-31 Implementation technical specifications for Development Selection goods. (line 42) Individual AL-ADF-15578-CS-INDV / Component 4: Pending IBRD / 86560 Post Consultant Open 0.00 2019-09-10 2019-10-29 2019-11-19 2019-12-24 2024-11-23 Cultural Heritage Consultant Implementation Support Implementation Selection Individual AL-ADF-15579-CS-INDV / Component 4: Pending IBRD / 86560 Post Consultant Open 0.00 2019-12-16 2020-02-03 2020-02-24 2020-03-30 2025-02-28 Site Management Consultant Implementation Support Implementation Selection Page 6