PROCUREMENT PLAN (Textual Part) Project information: Bosnia and Herzegovina Emergency COVID-19 Project – P173809 Project Implementation agencies: Ministry of Health and Social Welfare of the Republic of Srpska and Federal Ministry of Health (Federation of Bosnia and Herzegovina). Date of the Procurement Plan: December 14, 2020 Period covered by this Procurement Plan: 2020 – 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the arrangements agreed shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Fast-Track Procurement. The proposed procurement approach prioritizes fast-track emergency procurement for the urgently required goods, works and services. Key measures to fast-track procurement include certain flexibilities related to bid and performance securities, advance payment, time for submission of bids/proposals; and standstill period. PROCUREMENT Bosnia and Herzegovina : Bosnia and Herzegovina Emergency COVID-19 Project PLAN General Information Country: Bosnia and Herzegovina Bank’s Approval Date of the Original Procurement Plan: 2021-01-25 2021-09-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173809 GPN Date: 2020-07-29 Project Name: Bosnia and Herzegovina Emergency COVID-19 Project Loan / Credit No: IBRD / 90970 M Executing Agency(ies): inistry of Health and Social Welfare WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA/RS/MOHSW/COVID- Component 1. Responding to 19/GO/DIR/041-21 / IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 613.56 Completed 2021-02-15 2021-02-03 2021-02-20 2021-02-03 2021-03-27 2021-02-03 2021-09-23 2021-02-03 Thermometers - retroactive Republika Srpska financing - PHI RS BA/RS/MOHSW/COVID- Component 1. Responding to 19/GO/DIR/040-21 / Bedding IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 17,336.17 Completed 2021-02-15 2021-02-03 2021-02-20 2021-02-03 2021-03-27 2021-02-03 2021-09-23 2021-02-03 goods - retroactive financing Republika Srpska - SC Nikola Tesla BA-MZSZ RS-217226-GO- Component 1. Responding to DIR / Mattresses - BOTEX - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 3,154.16 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-27 2021-10-07 2021-07-27 retroactive financing - City of Republika Srpska Bijeljina BA-MZSZ RS-217316-GO- Component 1. Responding to DIR / Bedding goods - TEXTIL IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 8,513.28 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-27 2021-10-07 2021-07-27 (02-85-12/20) - retroactive Republika Srpska financing - City of Bijeljina BA-MZSZ RS-217321-GO- Component 1. Responding to DIR / Bedding goods - TEXTIL IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 6,511.27 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-27 2021-10-07 2021-07-27 (02-85-14/20) - retroactive Republika Srpska financing - City of Bijeljina BA-MZSZ RS-217284-GO- Component 1. Responding to DIR / Bedding goods - TEXTIL IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,278.93 Completed 2021-03-01 2021-02-12 2021-03-06 2021-02-12 2021-04-10 2021-02-12 2021-10-07 2021-02-12 (02-85-21/20) retroactive Republika Srpska financing - City of Bijeljina BA-MZSZ RS-217286-GO- Component 1. Responding to DIR / Rapid diagnostics tests IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 28,036.67 Completed 2021-03-01 2021-07-28 2021-03-06 2021-07-28 2021-04-10 2021-07-28 2021-10-07 2021-07-28 - AKO MED - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217467-GO- Component 1. Responding to DIR / Supplies for testing IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,375.83 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 Covid 19 - ANALITIKA (1598) Republika Srpska - retroactive financing - PHI RS BA-MZSZ RS-217287-GO- Component 1. Responding to DIR / Supplies for testing IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,672.22 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 Covid 19 - ANALITIKA (1839) Republika Srpska - retroactive financing - PHI RS BA-MZSZ RS-216990-GO- Component 1. Responding to DIR / Supplies for testing IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,672.22 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 Covid 19 - ANALITIKA (1841) Republika Srpska - retroactive financing - PHI RS BA-MZSZ RS-217288-GO- Component 1. Responding to DIR / Thermal cameras - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 215,944.44 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 ARMS (2389) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217460-GO- Component 1. Responding to DIR / Tests for COVID-19 - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,138.57 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-08 2021-04-10 2021-03-08 2021-10-07 2021-03-08 BIOMEDIKA (1430) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217008-GO- Component 1. Responding to DIR / RT PCR kit for SARS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,496.22 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 CoV19 - BIOMEDIKA (2555) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217258-GO- Component 1. Responding to DIR / RT PCR kit for SARS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,496.22 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 CoV1 - BIOMEDIKA (2556) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217262-GO- Component 1. Responding to DIR / RT PCR device - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 34,666.67 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 BIOSISTEMI (1827) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217340-GO- Component 1. Responding to DIR / RT PCR device - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 104,000.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 BIOSISTEMI (2124) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217347-GO- Component 1. Responding to DIR / Virus transportation IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 9,750.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 surfaces - BROMA BEL (1929) Republika Srpska - retroactive financing - PHI RS Page 1 BA-MZSZ RS-217290-GO- Component 1. Responding to DIR / RNA extraction kit - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 99,811.11 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 BROMA BEL (2390) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-216993-GO- Component 1. Responding to DIR / Power generator - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 11,465.03 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 ELEKTRO RACIC (2421) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217270-GO- Component 1. Responding to DIR / Protective suits - EMGEN IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 257,833.33 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 (2134) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217356-GO- Component 1. Responding to DIR / Protective masks FFP2 - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 257,833.33 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 EMGEN (2234) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217350-GO- Component 1. Responding to DIR / PCR filter tips - ENA IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,145.00 Completed 2021-03-01 2021-04-05 2021-03-06 2021-04-05 2021-04-10 2021-04-05 2021-10-07 2021-04-05 (1832) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217373-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 14,797.61 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 GALENFARM (1738) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217358-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 GALENFARM (1975) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217355-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 GALENFARM (1977) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217360-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 GALENFARM (2227) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217374-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,881.67 Completed 2021-03-01 2021-03-31 2021-03-06 2021-03-31 2021-04-10 2021-03-31 2021-10-07 2021-03-31 GALENFARM (2466) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217372-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 (1719) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217264-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 (1720) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217367-GO- Component 1. Responding to DIR / Nitrile gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 (1792) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217297-GO- Component 1. Responding to DIR / Nitrile gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (1793) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217261-GO- Component 1. Responding to DIR / Nitrile gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2005) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217277-GO- Component 1. Responding to DIR / Nitrile gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,708.33 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2006) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217368-GO- Component 1. Responding to DIR / Protective masks - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,094.89 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 MIPEX (2007) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217222-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2151) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-216992-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2152) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217292-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2397) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217294-GO- Component 1. Responding to DIR / Latex gloves - MIPEX IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,744.44 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2398) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-216991-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 PERFECT CLEAN (1707) - Republika Srpska retroactive financing - PHI RS Page 2 BA-MZSZ RS-217457-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 PERFECT CLEAN (1877) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217299-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 PERFECT CLEAN (1936) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217458-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 PERFECT CLEAN (1961) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217224-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 PERFECT CLEAN (1983) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217300-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 PERFECT CLEAN (2016) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217342-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,073.33 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 PERFECT CLEAN (2039) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217359-GO- Component 1. Responding to DIR / Disinfection supplies - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 24,440.00 Completed 2021-03-01 2021-03-30 2021-03-06 2021-03-30 2021-04-10 2021-03-30 2021-10-07 2021-03-30 PERFECT CLEAN (2217) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217223-GO- Component 1. Responding to DIR / Protective masks FFP2 - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,600.00 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 PERFECT CLEAN (2257) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217003-GO- Component 1. Responding to DIR / Protective masks FFP2 - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,600.00 Completed 2021-03-01 2021-03-29 2021-03-06 2021-03-29 2021-04-10 2021-03-29 2021-10-07 2021-03-29 PERFECT CLEAN (2258) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217006-GO- Component 1. Responding to DIR / Protective suits - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 433,333.33 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 PREVENT (2153) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217303-GO- Component 1. Responding to DIR / Protective surgical IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 505,555.55 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 masks - SANITEKS (2129) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217276-GO- Component 1. Responding to DIR / Protective caps - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 515.70 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 SAVINA (1356) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217279-GO- Component 1. Responding to DIR / Protective caps - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,870.55 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 SAVINA (1889) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217305-GO- Component 1. Responding to DIR / Protective caps - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,603.33 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 SAVINA (2259) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217010-GO- DIR / Portable ultrasound Component 1. Responding to color Doppler devices - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 40,242.22 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 SHIMADZU (2127) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217308-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1534) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217319-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1535) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217007-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 1,993.33 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1582) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217112-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1635) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217318-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,491.67 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1636) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217225-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-17 2021-10-07 2021-03-17 (1799-2) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217001-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (1799-4) - retroactive Republika Srpska financing - PHI RS Page 3 BA-MZSZ RS-217309-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-17 2021-10-07 2021-03-17 (1800) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217231-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 3,213.89 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-17 2021-10-07 2021-03-17 (1801) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217232-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (1997) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217253-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-17 2021-03-06 2021-03-17 2021-04-10 2021-03-17 2021-10-07 2021-03-17 (2200) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217338-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-07-27 2021-10-07 2021-07-27 (2202) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-216988-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-26 2021-03-06 2021-03-26 2021-04-10 2021-03-26 2021-10-07 2021-03-26 (2203) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217257-GO- Component 1. Responding to DIR / Surgical masks - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 26,000.00 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 STEPMED (1717) - retroactive Republika Srpska financing - PHI RS BA-MZSZ RS-217310-GO- Component 1. Responding to DIR / Volumetric infusion IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,816.67 Completed 2021-03-01 2021-04-06 2021-03-06 2021-04-06 2021-04-10 2021-04-06 2021-10-07 2021-04-06 pumps - STEPMED (2004) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-217255-GO- DIR / Beds and mattresses - Component 1. Responding to VIGMELT (02-85-13/20) - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 6,843.06 Completed 2021-03-01 2020-04-06 2021-03-06 2020-04-08 2021-04-10 2020-04-08 2021-10-07 2020-04-29 retroactive financing - City of Republika Srpska Bijeljina BA-MZSZ RS-214134-GO- Component 1. Responding to Request for Single Stage - One RFQ / Supplies for laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 Quotations Envelope - PCR attachments Republika Srpska BA-MZSZ RS-214544-GO- Component 1. Responding to Request for Single Stage - One RFQ / Supplies for laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 Quotations Envelope - optical tubes Republika Srpska BA-MZSZ RS-214542-GO- Component 1. Responding to Request for Single Stage - One RFQ / Supplies for laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 Quotations Envelope - pipettes Republika Srpska BA-MZSZ RS-214541-GO- Component 1. Responding to Request for Single Stage - One RFQ / Supplies for laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 Quotations Envelope - test tubes Republika Srpska BA-MZSZ RS-214072-GO- Component 1. Responding to Request for Single Stage - One RFQ / Supplies for laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-03-06 2021-05-01 2021-10-28 Quotations Envelope - HEPA filters Republika Srpska BA-MZSZ RS-217366-GO- DIR / Respiratory medical Component 1. Responding to masks KN95 - PROKONTROL IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 249,166.67 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (2078) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217344-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1998) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-216987-GO- Component 1. Responding to DIR / Surgical masks - SINEKS IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 4,285.18 Completed 2021-03-01 2021-03-09 2021-03-06 2021-03-09 2021-04-10 2021-03-09 2021-10-07 2021-03-09 (1999) - retroactive financing Republika Srpska - PHI RS BA-MZSZ RS-217291-GO- Component 1. Responding to DIR / RT PCR device - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-03-01 2021-03-06 2021-04-10 2021-10-07 BIOSISTEMI (2408) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-214079-GO- Component 1. Responding to Request for Single Stage - One RFQ / Volumetry - Automatic IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 Quotations Envelope pipettes Republika Srpska Component 1. Responding to BA-MZSZ RS-214180-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 RFQ / Hygiene products Quotations Envelope Republika Srpska BA-MZSZ RS-214074-GO- Component 1. Responding to RFQ / Measuring systems Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 devices (social welfare Quotations Envelope Republika Srpska institutions) Component 1. Responding to BA-MZSZ RS-214466-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-06-12 2021-08-07 2022-02-03 RFQ / Disinfectants Quotations Envelope Republika Srpska BA/RS/MOHSW/COVID- 19/GO/DIR/039-21 / Component 1. Responding to Washing machines - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 43,333.00 Completed 2021-03-01 2021-03-08 2021-03-06 2021-03-08 2021-04-10 2021-03-08 2021-10-07 2021-03-08 retroactive financing - SC Republika Srpska Nikola Tesla Page 4 BA-MZSZ RS-219489-GO- Component 3. Project Request for Single Stage - One RFQ / Procurement of office IBRD / 90970 Post Open - National 12,809.33 Completed 2021-03-06 2021-05-01 2021-04-21 2021-10-28 2021-05-25 Management Quotations Envelope furniture for MoHSW BA-MZSZ RS-214071-GO- Component 3. Project Request for Single Stage - One RFQ / Office and computer IBRD / 90970 Post Open - National 72,876.73 Signed 2021-03-06 2021-05-01 2021-03-22 2021-10-28 Management Quotations Envelope equipment for MoHSW Component 1. Responding to Pending BA-MZSZ RS-214073-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-09-18 2021-11-13 2021-12-28 RFQ / Sterilization devices Quotations Envelope Republika Srpska on BA-MZSZ RS-217263-GO- Component 1. Responding to DIR / RT PCR device - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-03-01 2021-03-06 2021-04-10 2021-10-07 BIOSISTEMI (2408) - Republika Srpska retroactive financing - PHI RS BA-MZSZ RS-214075-GO- Component 1. Responding to Request for Single Stage - One RFQ / Medical Equipment - IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Pulse oximeter Republika Srpska BA-MZSZ RS-214100-GO- RFQ / Stirring and shaking Component 1. Responding to Pending Request for Single Stage - One systems - Shakers and IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-21 2021-10-16 2021-12-15 Quotations Envelope Separation Republika Srpska on system/Centrifugation Component 1. Responding to Pending BA-MZSZ RS-214105-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-10-09 2021-12-04 2022-01-26 RFQ / Laboratory inventory Quotations Envelope Republika Srpska on BA-MZSZ RS-214121-GO- RFQ / Thermostatic devices - Component 1. Responding to Pending Request for Single Stage - One Refrigerating units IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-28 2021-10-23 2021-12-22 Quotations Envelope (Laboratory refrigerators and Republika Srpska on freezers) and Temperature controllers BA-MZSZ RS-228236-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Communication IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-18 2021-10-13 2022-04-11 Quotations Envelope equipment Republika Srpska on BA-MZSZ RS-214129-GO- Component 1. Responding to RFQ / Equipment for Social Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 509,467.15 Completed 2021-03-06 2021-07-28 2021-06-01 2021-05-05 2021-11-28 2021-07-06 welfare institutions for Quotations Envelope Republika Srpska accomodation BA-MZSZ RS-214502-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Volumetry - Dispenser IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-10-02 2021-11-27 2022-05-26 Quotations Envelope and pipettes Republika Srpska on BA-MZSZ RS-214077-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Specific laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-09-04 2021-10-30 2021-12-14 Quotations Envelope equipment - Flow Cabinets Republika Srpska on BA-MZSZ RS-214453-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Measuring systems IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-09-11 2021-11-06 2021-12-29 Quotations Envelope devices Republika Srpska on BA-MZSZ RS-214142-GO- Component 1. Responding to Request for Single Stage - One RFQ / Medical Equipment - IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Patient monitor Republika Srpska BA-MZSZ RS-214522-GO- Component 1. Responding to Single Stage - One RFB / Medical Equipment - IBRD / 90970 the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 Envelope Radiography Republika Srpska Component 1. Responding to Pending BA-MZSZ RS-214539-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-10-16 2021-12-11 2022-06-09 RFQ / Supplies for laboratory Quotations Envelope Republika Srpska on BA-MZSZ RS-214523-GO- Component 1. Responding to Request for Single Stage - One RFQ / Medical Equipment - IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Canceled 2021-04-03 2021-05-29 2021-11-25 Quotations Envelope Ultrasound device Republika Srpska BA-MZSZ RS-214503-GO- Component 1. Responding to RFB / Medical Equipment - Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 Computerized Tomography - Envelope Republika Srpska Mobile CT device BA-MZSZ RS-214140-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Sample preparation - IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-14 2021-10-09 2021-12-01 Quotations Envelope Sample extraction - extractors Republika Srpska on BA-MZSZ RS-214185-GO- Component 1. Responding to Pending RFQ / Analysis of laboratory Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-07 2021-10-02 2021-11-24 samples - Molecular Quotations Envelope Republika Srpska on diagnostic instruments BA-MZSZ RS-214532-GO- Component 1. Responding to Pending RFB / Hardware and software Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Implementati 2021-11-01 2021-11-06 2021-12-18 2022-01-17 2022-02-21 2022-04-13 for microbiology and Envelope Republika Srpska on epidemiology BA-MZSZ RS-214124-CS- Component 1. Responding to Pending Request for Single Stage - One CQS / Promotional campaign IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-09-14 2021-11-09 2021-12-09 Quotations Envelope (leaflets) Republika Srpska on Component 1. Responding to Under BA-MZSZ RS-242813-GO- Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Implementati 2021-08-15 2021-09-06 2021-08-20 2021-09-06 2021-10-01 2021-10-31 2021-12-05 2022-02-03 RFQ / Ambulances Envelope Republika Srpska on BA-MZSZ RS-214534-GO- Component 1. Responding to Single Stage - One RFB / Hardware and software IBRD / 90970 the COVID-19 Pandemic in Post Request for Bids Open - National 0.00 Canceled 2021-06-21 2021-06-26 2021-08-07 2021-09-06 2021-10-11 2022-04-09 Envelope for hospitals networking Republika Srpska Component 1. Responding to Pending BA-MZSZ RS-242806-GO- Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Prior Request for Bids Open - International 0.00 Implementati 2021-09-01 2021-09-06 2021-10-18 2021-11-17 2021-12-22 2022-02-20 RFB / Medical Equipment Envelope Republika Srpska on Page 5 BA-MZSZ RS-214456-GO- Component 1. Responding to Under Request for Single Stage - One RFQ / Diagnostic Supplies - IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-21 2021-09-20 2021-10-16 2022-04-14 Quotations Envelope Test kits and Reagents Republika Srpska on Component 1. Responding to BA-MZSZ RS-214487-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 16,201.48 Signed 2021-08-21 2021-08-10 2021-10-16 2021-09-10 2022-04-14 RFQ / Protective Equipment Quotations Envelope Republika Srpska BA-MZSZ RS-214445-GO- Component 1. Responding to Pending Request for Single Stage - One RFQ / Specific laboratory IBRD / 90970 the COVID-19 Pandemic in Post Open - National 0.00 Implementati 2021-08-21 2021-10-16 2022-04-14 Quotations Envelope equipment - Microscopes Republika Srpska on Component 1. Responding to BA-MZSZ RS-214525-GO- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 23,195.51 Signed 2021-08-21 2021-09-20 2021-10-16 2021-09-15 2022-04-14 RFQ / Field vehicle Quotations Envelope Republika Srpska NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-MZSZ RS-217273-NC- DIR / Laundry services - MAX Component 1. Responding to FRESH (02-85-15/20) - IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 925.93 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-27 2021-10-07 2021-07-27 retroactive financing - City of Republika Srpska Bijeljina Component 1. Responding to BA-MZSZ RS-214070-NC- Request for Single Stage - One IBRD / 90970 the COVID-19 Pandemic in Post Open - National 17.33 Signed 2021-03-06 2021-05-01 2021-03-01 2021-10-28 RFQ / Translation services Quotations Envelope Republika Srpska BA-MZSZ RS-217333-NC- DIR / Cleaning services - Component 1. Responding to BINGO CLEAN (02-85-20/20) IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 2,592.60 Completed 2021-03-01 2021-07-27 2021-03-06 2021-07-27 2021-04-10 2021-07-27 2021-10-07 2021-07-27 - retroactive financing - City Republika Srpska of Bijeljina BA-MZSZ RS-254525-NC- Pending Component 3. Project DIR / COVID-19 related Media IBRD / 90970 Post Direct Selection Direct 0.00 Implementati 2021-09-27 2021-10-02 2021-11-06 2022-05-05 Management monitoring on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BA-MZSZ RS-214126-CS- Component 1. Responding to Consultant CQS / Public information IBRD / 90970 the COVID-19 Pandemic in Post Qualification Open - National 0.00 Canceled 2021-06-14 2021-07-05 2021-08-18 2021-09-17 2021-10-22 2022-04-20 campaigns Republika Srpska Selection BA-MZSZ RS-242791-CS- Component 1. Responding to Consultant CQS / Education of Covid19 Pending IBRD / 90970 the COVID-19 Pandemic in Post Qualification Open - National 0.00 2021-10-03 2021-10-24 2021-12-07 2022-01-06 2022-02-10 2022-03-12 Treatment Health Care Implementation Republika Srpska Selection Workers BA-MZSZ RS-214128-CS- Component 1. Responding to Consultant Pending CQS / Development of plans IBRD / 90970 the COVID-19 Pandemic in Post Qualification Open - National 0.00 2021-09-20 2021-10-11 2021-11-24 2021-12-24 2022-01-28 2022-07-27 Implementation and strategies Republika Srpska Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Responding to Individual BA-MZSZ RS-214183-CS- IBRD / 90970 the COVID-19 Pandemic in Post Consultant Open 14,974.47 Signed 2021-03-01 2021-04-05 2021-04-19 2021-05-10 2021-05-10 2021-05-21 2021-06-14 2021-05-26 2022-06-30 INDV / Consultant for ESM Republika Srpska Selection BA-MZSZ RS-214076-CS- Component 1. Responding to Individual INDV / Consultant for M&E IBRD / 90970 the COVID-19 Pandemic in Post Consultant Open 14,974.47 Signed 2021-03-01 2021-04-05 2021-04-19 2021-05-18 2021-05-10 2021-05-26 2021-06-14 2021-05-26 2022-06-30 and SEP Republika Srpska Selection Component 1. Responding to Individual BA-MZSZ RS-242796-CS- Under IBRD / 90970 the COVID-19 Pandemic in Post Consultant Direct 0.00 2021-08-13 2021-07-29 2021-08-23 2021-09-06 2021-09-13 2021-09-17 2021-10-18 2022-06-30 INDV / Procurement Specialist Implementation Republika Srpska Selection Component 1. Responding to BA-MZSZ RS-244832-CS- IBRD / 90970 the COVID-19 Pandemic in Post Direct Selection Direct 0.00 Canceled 2021-08-16 2021-08-26 2021-10-30 2022-07-17 CDS / Press Clipping Republika Srpska Page 6