A. WORKS 1 USD = Rs. 50.00 Ref. No. Contract Description (length) Contract Price in Modified Price in Contract / Bid Procureme Review by Bid-Opening Comments ₹ ₹ Price (USD nt Method Bank Date million) (Prior / Post) PHASE I Rehabilitation WB/PSRSP/RH/1/NCB Rehabilitation of Ferozepur-Zira Road (34.46 441,421,339 427,282,620 8.55 NCB Prior 19.10.06 Km) Work Completed WB/PSRSP/RH/2/NCB Rehabilitation of Chandigarh-Landran-Chunni- 439,182,400 439,182,400 8.78 NCB Prior 20.10.06 Sirhind (37.27 Km) Work Completed WB/PSRSP/RH/3/NCB Rehabilitation of Phillaur-Aur-Rahon-Nagar 468,556,883 523,629,156 10.47 NCB Post 18.10.06 (33.51 km) Work Completed WB/PSRSP/RH/4/ICB Rehabilitation of Kapurthala-Tarn Taran (47.20 546,953,628 545,595,268 10.91 ICB Prior 22.11.06 km) Work Completed WB/PSRSP/RH/5/NCB Rehabilitation of Zira Dharamkot Road (24.70 347,308,823 369,674,767 7.39 NCB Prior 23.10.06 km) Work Completed WB/PSRSP/RH/6/NCB Rehabilitation of Sirhind-Patiala (28.30 km) 242,837,229 249,376,928 4.99 NCB Post 06.08.07 Work Completed Total 2,486,260,302 2,554,741,139 51.09 Upgradation WB/PSRSP/UG/1/ICB Upgradation of Kharar-Landran-Banur-Tepla 1,089,842,533 1,089,842,533 21.80 ICB Prior 30.11.06 As recommended by the Chief (39.53 Km) Engineers’ Committee to investigate regarding non fulfilment of various obligations by various party(s) involved in the execution of UG/1 and rectification measures for UG/1, the rectification of defects has been done by the Contractor. WB/PSRSP/UG/2/ICB Upgradation of Ludhiana-Malerkotla-Sangrur 2,260,383,808 2,260,383,808 45.21 ICB Prior 1.12.06 Work Completed (71.92 Km) WB/PSRSP/UG/3/NCB Upgradation of Attari-Chabbal – Taran Tarn Rd. 452,819,208 449,503,857 8.99 NCB Prior 24.10.06 Work Completed (including Junction at Tarntaran) (40.50 Km) Total 3,803,045,549 3,799,730,198 75.99 Ref. No. Contract Description (length) Contract Price in Modified Price in Contract / Bid Procureme Review by Bid-Opening Comments ₹ ₹ Price (USD nt Method Bank Date million) (Prior / Post) PHASE IMaintenance Periodic WB/PSRSP/PM/1/NCB Periodic Maintenance of Ajnala Ramdass 1.05 NCB Prior 7.08.06 Work Completed Cheharta Dhand Bir Road 52,615,950 52,615,950 Chehrata Dand Bir road 7.08.06 Work Completed WB/PSRSP/PM/2/NCB Periodic Maintenance of Gurdaspur Sri 96,961,910 96,961,910 1.94 NCB Prior 10.08.06 Work Completed Hargobindpur road WB/PSRSP/PM/3/NCB Periodic Maintenance of Longowal Sunam, road 33,743,221 33,743,221 0.67 NCB Prior 27.07.06 Work Completed Badbar Longowal Pakhokey Tappa 30,573,404 30,573,404 0.61 NCB 27.07.06 Work Completed WB/PSRSP/PM/4/NCB Periodic Maintenance of Khanna Samrala 128,590,060 128,590,060 2.57 NCB Post 1.12.06 Work Completed Nawanshahar Garhshankar road WB/PSRSP/PM/5/NCB Periodic Maintenance of Kapurthala Tashpur, 52,227,571 52,227,571 1.04 NCB Prior 2.11.06 Work Completed Sultanpur dalla & Dadwindi Sultanpur road WB/PSRSP/PM/6/NCB Periodic Maintenance i of Sitogana Dabwali road 34,494,279 34,494,279 0.69 NCB Prior 17.08.06 Work Completed WB/PSRSP/PM/7/NCB Periodic Maintenance of Faridkot to Ferozepur 44,175,882 44,175,882 0.88 NCB Prior 22.08.06 Work Completed road WB/PSRSP/PM/10/NCB Periodic Maintenance of BaghaPurana Bhagta 73,470,745 73,470,745 1.47 NCB Prior 31.07.06 Work Completed Bhucho road WB/PSRSP/PM/11/NCB Periodic Maintenance of Sri Hargobindpur Batala 79,000,148 79,000,148 1.58 NCB Prior 14.08.06 Work Completed Dera Baba Nanak Road Total 625,853,170 625,853,170 12.52 PHASE II Upgradation & Rehabilitation--OPRC (Phase 2) PSRSP/WB/OPRC/1/ICB Output and Performance based Road Contract for Improvement, Rehabilitation, Resurfacing & Routine Maintenance Works of Roads of a) Package I: Sangrur-Mansa-Bathinda Contract 110.44 ICB Prior 26.04.12 M/s Patel Infrastructure Pvt. Ltd. Area with approx. length of 204.0 km has been allotted this work and LOA has been issued on 20th Oct, 2012. The Contractor has commenced its services from 5th Dec, 2012 and the Contract Agreement has been signed on 10th Dec, 2012. Total 110.44 Additional Works (Phase II) Ref. No. Contract Description (length) Contract Price in Modified Price in Contract / Bid Procureme Review by Bid-Opening Comments ₹ ₹ Price (USD nt Method Bank Date million) (Prior / Post) PHASE I WB/PSRSP/RS/1/NCB Road Safety Measures on Phase I roads 2.19 NCB Prior 01.09.10 Work Completed. Construction of Dhelon By Pass (UG/2) 15.00 NCB Prior - Field surveys have been completed and Preparation of DPR is in process. Improvement of identified black spots on the core 11.92 NCB Prior - The Consultant M/s IMaCS is road network being issued a variation order for including the study of Black Spots in its ongoing consultancy, Development of Road Safety Strategy and Generating Awareness on Traffic and Road Safety Additional crust for increasing the structural 3.00 NCB Prior - Preparation of DPR is under adequacy of pavement structure on UG/1 process Total 32.11 B. GOODS Ref. Contract Description Contract Price Procurement Prequalification Domestic Review by Bid-Opening Comments No. (USD million) Method (yes/no) Preference Bank (Yes / Date (Yes/No) No) 1 Asset Management 0.5 ICB No No Prior Jan-09 ROMDAS (Profilometer) Equipment(Profilometer and falling procured under OPRC weight deflectometer etc) Consultancy. 2 Road Safety Goods (including 0.25 procurement of GPS); several packages but no individual package to exceed 50,000 USD. a) Procurement of GPS (400 units) 0.042 Shopping No No Post 24 Feb 2009 GPS units received on 8th (GPS Units ) July 09. b) Procurement of LCD projectors (7 0.005 Shopping No No Post 23/Jun/08 LCD projectors received on nos) 24th Oct 09. c) Procurement of DVD players, Shopping 26/Aug/09 Dropped projection screens, amplifier & speakers 3 HIV/AIDS – Dispensing Machines Shopping No No Post - Dropped 4 Procurement of Digital maps, Satellite 0.10 Direct No No Post Sep-07 In progress from Survey of Images Contacting India (SoI Sheets). 9 Sheets pending 5 Procurement of equipment for GIS 0.04 Shopping/ No No Post Jan-09 Hardware shall be procured NCB after completion of Digitization of Road Network. However, ArcGIS available with PRBDB was upgraded to current version. 0.89 C. SERVICES award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status Phase I Package 1 Part A Feasibility, environmental and social 21-Aug-07 10-Jun-05 studies for 1698 km of prioritized roads M/s CES (India) Pvt. Ltd., New with the option of assigning technical ₹ 23,688,151 Delhi 12-May-05 9-May-05 advisory services for the overall project QCBS implementation. - - Prior Services Completed Package 1 Part B Technical Advisory Services for overall Not Assigned Not Assigned project implementation. Detailed Project Report for ₹ 11,163,451 30-Nov-06 Package 2 29-Jul-05 rehabilitation of 205 km with the option 24,249 M/s Intercontinental Consultants & of assigning quality assurance and Services Completed $ Technocrats Pvt. Ltd. , New Delhi technical support services during 18-Jul-05 22-Jul-05 construction QCBS Prior ₹ 10,901,148 26-Mar-07 30-Apr-08 M/s Intercontinental Consultants & Package 2 Part B - - Technocrats Pvt. Ltd. , New Delhi Quality assurance and Technical Support Services during Services Completed Construction.(TAC) 30-Jun-09 1-Jul-08 The Consultant M/s BCEOM M/s Egis Bceom International, provided TAC services as France variation to Package 3 services. award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status Phase I ₹ 13,214,270 16-Sep-05 15-Jun-06 Package 3 Preparation of detailed Project Reports 191,128 for upgradation of 152 km length & Services Completed € Construction supervision services 16-Sep-05 9-Sep-05 QCBS M/s Egis Bceom International, Prior France Package 3 Part ₹ 66,910,996 30-Jun-09 23-Jul-07 Construction Supervision Services Services of Consultant terminated on (CSC) for Upgradation works during - - B 31st March 2011. construction. ₹ 16,406,988 30-Nov-07 28-Mar-06 10-Apr-06 17-Apr-06 Package 4 139,261 QCBS Institutional development studies and M/s PricewaterhouseCoopers Pvt. Prior Services Completed $ development of appropriate action plan. Ltd., New Delhi ₹ 2,196,048 13-Apr-06 21-Apr-06 21-Apr-06 19-Sep-06 Package 5 Independent review of the environment CQS M/s Lea Associates, New Delhi - - Post Services Completed and social assessments Post Review ₹ 3,989,062 31-May-09 11-Dec-06 13-Dec-06 Package 6 M/s Development Institute for QCBS Implementation of RAPs on Phase I Systems Alternatives (DISA), - - Post Services Completed works Lucknow award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status I Phase II Phase Preparation of detailed Project Reports Package 1 for rehabilitation & upgradation of 258 Consultancy called off. km length, including construction supervision as the case may be. 1,195,038 NZD ₹ 18,324,682 Time Extension to the Consultant was 22-Nov-09 Package 2 7-Aug-08 10-Jul-08 24-Jul-08 Devising a program for Output and M/s Opus International Consultants granted till 30th June, 2012. Some tasks QBS Performance based contracts for Road ``` Ltd, New Zealand are still pending contractually to be 1,589,419 Network of about 600 Km completed by the Consultant. RM ₹ 13,096,000 19-Nov-07 18-Nov-11 18-Dec-07 Package 3 9-Nov-07 QCBS HIV/AIDS Awareness M/s Advantage India, New Delhi - - Post Services Completed Package 4 Reclassification of Road Network Consultancy called off. To be done through PWD Single Source Single Source ₹ 1,932,000 24-Jan-08 25-Jul-07 25-Jul-07 Preparation of GIS maps for Road - - Post - Services completed Network in Punjab Package 5 M/s CCE, Punjab Engineering College, Chandigarh ₹ 1,085,000 During a meeting with Consultant in the 11-Apr-10 12-Oct-09 12-Oct-09 Collection of field data for major first week of Dec, the Consultant was highways and bridges [Supplementary - - Post - again directed to carry out all the tasks of Contract Agreement] the Consultancy as per the TOR. award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status Phase I 163,418 Final Report has been submitted by the ₹ 18,213,110 $ 11-Aug-09 25-Aug-09 Package 6 30/Jun/11 20-Jul-09 Consultant the comments on which have Integrated Transport Policy and Strategy M/s Ecorys Nederlands BV; The QBS Prior been forwarded to the Consultant. and Strategic Investment Plans Study Netherlands Services likely to finish by end April, 292,240 2013. € The Consultant has submitted Awareness Generation Plan (AGP) with draft ₹ 18,854,008 campaign material. Services likely to 18-Oct-10 Package 7 1-May-12 1-Nov-10 5-Oct-10 Development of Road Safety Strategy QCBS M/s ICRA Management Consulting finish by 16th Aug, 2013. The work for and Generating Awareness on Traffic - - Prior Services Limited, Noida Black Spot assessment and improvement and Road Safety. study on core road network in Punjab is being additionally added to the scope of services through a variation order. QBS Setting up of Road Fund Secretariat - - - - Prior - - - - Package 8 This Consultancy has been dropped in the restructured Loan Agreement. b) Procurement of Experts(s) & support SS staff for guidance on RMF Secretariat - - - - - - - - establishment Package 10 Package 9 QCBS Asset Management Software Consultancy planned to begin after GIS - - - - Post - - - - development and training digitization Training ( IT, Contract management, CQ/SS Quality Control & Procurement) ; - - - - Post - - - - Completed several packages Post Review ₹ 7,888,607 Package 11 29-May-08 28-May-12 6-Jun-08 M/s IDMA Foundation for The Final Environmental Monitoring for Environment Management Plan CQS Sustainable Development, - - Post Q-IV, 2012 has been completed. Training and Pollution Monitoring Chandigarh Services likely to finish by March, 2013. award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status Phase I Package 12 CQ/SS Training (Financial Management); - - - - Post - - - - Completed several packages Road Safety Database, training CQS etc.(several packages, but no package to - - - - Post - - - - exceed 0.05 USD million ) Package 13 The training for the operation of the software has been imparted in 13 out of 23 districts. The balance districts shall be ₹ 525,000 17-Oct-08 17-Oct-08 16-Jan-09 Consultancy Services for creation of covered by May, 2013. Post SS online road safety database management M/s ArriveSafe, Chandigarh - - Post system Post Review ₹ 8,009,979 16-Apr-12 10-Oct-08 17-Oct-08 M/s Operations Research Group Pvt. Services in progress and likely to be CQS Road User Satisfaction Survey - - Post Ltd., New Delhi completed by May, 2013. Package 14 24-04-2011 (Phase I) ₹ 29,781,000 The Final Report of the mid-term surveys 17-Jan-11 24-Jan-11 6-Jan-11 b) Surveys (Average network speed, QCBS M/s CES (India) Pvt. Ltd., New has been submitted and approved by the vehicle operating cost, road roughness - - Prior Delhi Review Committee. End Term Surveys and road condition survey) to be taken up in April - May, 2013. Package 15 Feasibility studies & advisory services QBS - - - - Prior - - - - Not to be undertaken. for Preparation of PPP The draft RFP/ Bidding Document as ₹ 5,683,059 Package 16 19-May-10 Appointment of Project Management 20-Sep-10 4-Oct-10 3-Jan-13 QCBS well as other Phase I deliverables have Consultant for Assistance in M/s Wipro Limited Infotech Group, - - Prior been forwarded to the World Bank for Procurement of Main Computerization Chandigarh the issuance of 'No Objection' on draft Consultancy Services RFP/ BD. Package 17 QCBS Computerization of PWD B&R - - - - Prior - - - - - award of Contract Name of currency Date of Award of Completion Date Contract Cost of Review by Bank Date of Start of Contract Price other currency WB NO to the Procurement Name of the Assignment Description Consultant (Yes / No) Contract Contract Ref. No. Method Status DPR Consultancy for Rehabilitation of Phase I Consultancy called off. affected reaches of PM/6 CQS/SS Services of Internal Auditor for PSRSP (several packages but no package to - - - Post - - - - exceed 0.05 USD million) ₹ 123,596 13-Sep-07 13-Sep-07 12-Sep-08 1) Internal Auditor for Financial Year M/s S.K. Bhasin & Associates, CQS Post - - Post Services completed. 2007-08 Chandigarh Package 18 24-Nov-09 ₹ 249,440 24-Feb-09 24-Feb-09 M/s S.K. Bhasin & Associates, Post SS 2) Internal Auditor for year 2008-09 - - Post Services completed. Chandigarh ₹ 707,663 9-Aug-10 28-Jul-10 8-Feb-13 M/s Agarwal A Kumar Associates, CQS Post 3) Internal Auditor for 2009-12 - - Post Services in Progress. Chandigarh ₹ 1,460,000 Package 19 14-Nov-08 14-Nov-08 Evaluation) 01-07-2011 (End Term M/s Consultant for Rural Area External Evaluation of Implementation Post SS Development Linked Economy - - Post Services completed. of Resettlement Action Plan (CRADLE) Package 20 External Evaluation of HIV/AIDS CQS - - - - Post - - - - Services completed. awareness The World Bank has accorded its 'No Package 21 Monitoring consultant for the Output Objection' to the draft shortlist of the QCBS and Performance based Road Contracts - - - - Prior - - - - Consultants. The draft RFP document of 'Sangrur- Mansa- Bathinda' network has been forwarded to the World Bank in Punjab for the issuance of 'NO'.