Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 21, 2016. 2. Date of General Procurement Notice: September 28, 2016. 3. Period covered by this procurement plan: January 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million 3. ICB (Works) Above US$ 10 million 4. NCB (Works) Above US$ 2 million 5. Non-Consultant Services Above US$2 million 6 Consultants (firms) Above US$ 1 million 7. Consultant Individuals Above 0.3 million 2. Prequalification. Not applicable. 4. Any Other Special Procurement Arrangements: Retroactive financing up to 5 million. July 9, 2010 PROCUREMENT Mexico : Energy Efficiency in Public Facilities Project (PRESEMEH) PLAN General Information Country: Mexico Bank’s Approval Date of the Original Procurement Plan: 2016-11-29 2021-10-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149872 GPN Date: 2016-09-28 Project Name: Energy Efficiency in Public Facilities Project (PRESEMEH) Loan / Credit No: IBRD / 85940, IBRD / 88440 S Executing Agency(ies): ecretaria de Energia WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SENER-DGESE-FIDE-LPN-AP- GTO-2017-01 / ALUMBRADO Municipal energy efficiency Solicitud de Single Stage - One 2018-02- IBRD / 85940 Posterior Open - National 7,890,213.00 0.00 Cancelado 2017-09-15 2017-09-21 2017-10-12 2017-11-08 2017-11-27 PUBLICO EN EL MUNICIPIO DE investments ofertas Envelope 23 LEON, GUANAJUATO SENER-DGESE-FIDE-LPN-BA- TLAX-2017-02 / BOMBEO DE Municipal energy efficiency Solicitud de Single Stage - One 2018-06- IBRD / 85940 Posterior Open - National 676,304.00 0.00 Cancelado 2017-10-18 2017-10-23 2017-11-14 2017-11-29 2017-12-27 AGUA EN EL MUNICIPIO DE investments ofertas Envelope 27 HUAMANTLA, TLAXCALA SENER-DGESE-FIDE-LPN-AP- GTO-2017-01-A / ALUMBRADO PUBLICO EN EL Municipal energy efficiency Solicitud de Single Stage - One 3,351,761.0 2018-02- IBRD / 85940 Posterior Open - National 7,890,213.00 Finalizado 2017-09-15 2017-10-12 2017-09-21 2017-10-12 2017-11-14 2017-11-08 2017-12-08 2017-11-27 2017-12-13 MUNICIPIO DE LEON, investments ofertas Envelope 4 23 GUANAJUATO SENER-DGESE- FIDE-LPN-AP-GTO-2017-01 SENER-DGESE-FIDE-LPN-BA- TLAX-2017-02-A / BOMBEO DE AGUA EN EL MUNICIPIO DE Municipal energy efficiency Solicitud de Single Stage - One 2018-10- IBRD / 85940 Posterior Open - National 676,304.00 0.00 En ejecución 2018-03-21 2018-10-01 2018-04-03 2018-05-15 2018-11-26 2018-06-08 2018-12-12 2018-06-29 HUAMANTLA, TLAXCALA investments ofertas Envelope 29 SENER-DGESE-FIDE-LPN-BA- TLAX-2017-02 SENER-DGESE-FIDE-LPN-EM- PUE-2018-01 / PROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One 2018-10- IBRD / 85940 Posterior Open - National 360,000.00 0.00 En ejecución 2018-04-03 2018-04-25 2018-04-17 2018-05-24 2018-06-05 2018-06-11 2018-06-21 2018-07-03 EDIFICACIONES EN EL investments ofertas Envelope 31 MUNICIPIO DE PUEBLA, PUEBLA SENER-DGESE-FIDE-LPN-AP- DMH-2018-02 / PROYECTO Municipal energy efficiency Solicitud de Single Stage - One 3,085,967.8 2018-09- DE ALUMBRADO PUBLICO EN IBRD / 85940 Posterior Open - National 5,698,598.93 Finalizado 2018-04-19 2018-05-02 2018-04-25 2018-05-09 2018-05-30 2018-05-28 2018-06-18 2018-06-16 2018-07-04 investments ofertas Envelope 6 14 LA DELEGACION MIGUEL HIDALGO, CIUDAD DE MEXICO SENER-DGESE-FIDE-LPN-AP- HJUAPAN-2018-04 / SUBPROYECTO DE ALUMBRADO PUBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 1,301,538.0 2019-01- IBRD / 85940 Posterior Open - National 4,000,000.00 Finalizado 2018-07-17 2018-07-31 2018-08-03 2018-09-14 2018-09-13 2018-10-03 2018-10-02 2018-10-29 2018-10-17 EL MUNICIPIO DE HUAJUAPAN investments ofertas Envelope 4 14 DE LEON OAXACA SENER- DGESE-FIDE-LPN-AP- HJUAPAN-2018-04 SENER-DGESE-FIDE-LPN-AP- OAX-2018-05 / SUBPROYECTO DE ALUMBRADO PÚBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 7,349,433.5 2019-05- IBRD / 85940 Previa Open - National 7,600,000.00 En ejecución 2018-11-26 2019-09-30 2018-12-11 2019-09-30 2019-01-01 2019-08-01 2019-02-12 2019-11-21 2019-03-06 2019-10-02 EL MUNICIPIO DE OAXACA DE investments ofertas Envelope 3 20 JUÁREZ SENER-DGESE-FIDE-LPN-AP- OAX-2018-05 SENER-DGESE-FIDE-LPN-AP- COZ-2018-03 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One 2019-02- ALUMBRADO PÚBLICO PARA IBRD / 85940 Posterior Open - National 6,500,000.00 0.00 En ejecución 2018-08-08 2018-11-05 2018-08-23 2018-09-13 2018-10-25 2018-11-20 investments ofertas Envelope 03 EL MUNICIPIO DE COZUMEL SENER-DGESE-FIDE-LPN-AP- COZ-2018-03 SENER-DGESE-FIDE-LPN-AP- COZ-2019-01 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One 2,144,755.2 2020-06- ALUMBRADO PÚBLICO PARA IBRD / 85940 Posterior Open - National 3,250,000.00 Firmado 2019-12-27 2019-11-22 2020-01-12 2020-02-06 2020-03-03 2020-03-07 2020-03-25 2020-04-01 2020-05-20 investments ofertas Envelope 0 30 EL MUNICIPIO DE COZUMEL, SENER-DGESE-FIDE-LPN-AP- COZ-2019-01 SENER-DGESE-FIDE-LPN-AP- COAT-2019-02 / SUBPROYECTO DE ALUMBRADO PÚBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 2,800,514.5 2020-12- IBRD / 85940 Posterior Open - National 4,139,780.00 En ejecución 2020-02-20 2021-03-22 2020-02-25 2020-04-07 2021-04-30 2020-05-07 2021-05-28 2020-06-11 EL MUNICIPIO DE investments ofertas Envelope 2 08 COATZACOALCOS, VERACRUZ, SENER-DGESE-FIDE-LPN-AP- COAT-2019-02 SENER-DGESE-FIDE-LPN-AP- CUL-2018-06 / SUBPROYECTO DE Municipal energy efficiency Solicitud de Single Stage - One 1,931,379.8 2021-05- ALUMBRADO PÚBLICO PARA IBRD / 85940 Posterior Open - National 2,047,099.67 Firmado 2020-06-30 2020-06-29 2020-07-15 2020-08-05 2020-08-12 2020-10-14 2020-09-01 2020-11-13 2020-09-08 investments ofertas Envelope 4 12 EL MUNICIPIO DE CULIACÁN SENER-DGESE-FIDE-LPN-AP- CUL-2018-06 SENER-DGIDTFRH-FIDE-LPN- AP-RIO-2020-02 / SUBPROYECTO DE ALUMBRADO PÚBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 1,710,612.1 2021-05- IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-06-15 2020-09-21 2020-06-30 2020-08-11 2020-11-05 2020-10-20 2020-11-27 2020-11-25 2020-12-15 EL MUNICIPIO DE RÍO investments ofertas Envelope 9 24 GRANDE, ZACATECAS, SENER- DGIDTFRH-FIDE-LPN-AP-RIO- 2020-02 Page 1 SENER-DGIDTFRH-FIDE-LPN- AP-PINOS-2020-03 / SUBPROYECTO DE ALUMBRADO PÚBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 1,656,967.4 2021-06- IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-06-30 2020-12-21 2020-07-15 2020-08-26 2021-02-04 2020-11-04 2021-03-01 2020-12-10 2021-03-19 EL MUNICIPIO DE PINOS, investments ofertas Envelope 9 08 ZACATECAS /SENER- DGIDTFRH-FIDE-LPN-AP- PINOS-2020-03 SENER-DGIDTFRH-FIDE-LPN- AP-XAL-2020-04 / SUBPROYECTO DE ALUMBRADO PÚBLICO PARA Municipal energy efficiency Solicitud de Single Stage - One 2,243,013.7 2021-10- IBRD / 85940 Posterior Open - National 2,177,700.35 Firmado 2020-10-27 2021-03-29 2020-11-11 2020-12-23 2021-05-14 2021-03-03 2021-06-10 2021-04-14 2021-06-22 EL MUNICIPIO DE XALAPA, investments ofertas Envelope 8 11 VERACRUZ / SENER- DGIDTFRH-FIDE-LPN-AP-XAL- 2020-04 SENER-DGIDTFRH-FIDE-LPN- BA-DGO-2020-05 / BOMBEO DE AGUA EN EL MUNICIPIO DE Municipal energy efficiency Solicitud de Single Stage - One Ejecución 2021-09- IBRD / 85940 Posterior Open - National 2,177,700.35 0.00 2020-09-28 2020-10-13 2020-11-24 2021-02-02 2021-03-10 GÓMEZ PALACIO, DURANGO / investments ofertas Envelope pendiente 06 SENER-DGIDTFRH-FIDE-LPN- BA-DGO-2020-05 SENER DGESE-FIDE-LPN-MER- 214640-CW-RFB / Municipal energy efficiency Solicitud de Single Stage - One Ejecución 2021-09- SUBPROYECTO EDIFICACIONES IBRD / 85940 Posterior Open - National 1,548,964.53 0.00 2021-02-22 2021-03-10 2021-04-04 2021-05-04 2021-05-29 investments ofertas Envelope pendiente 30 MUNICIPALES EN LA CIUDAD DE MÉRIDA YUCATÁN SENER-DGESE-FIDE-LPN- PCAR-214655-CW-RFB / SUBPROYECTO ALUMBRADO Municipal energy efficiency Solicitud de Single Stage - One 2,033,501.1 2021-10- IBRD / 85940 Posterior Open - National 2,967,828.74 En ejecución 2021-03-08 2021-03-09 2021-03-24 2021-04-18 2021-04-12 2021-05-18 2021-05-05 2021-06-12 PÚBLICO PARA LA CD. DE investments ofertas Envelope 3 30 PLAYA DEL CARMEN QUINTANA ROO GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-FIDE-LPI-AP- GTO-2016-01 / ALUMBRADO Municipal energy efficiency Solicitud de Single Stage - One IBRD / 85940 Previa Open - International 12,000,000.00 0.00 Cancelado 2017-01-27 2017-02-11 2017-03-28 2017-05-02 2017-05-27 2018-01-02 PUBLICO EN EL MUNICIPIO DE investments ofertas Envelope LEON SENER-DGESE-FIDE-LPN-BA- TLAX-2016-01 / BOMBEO DE Municipal energy efficiency Solicitud de Single Stage - One IBRD / 85940 Previa Open - National 3,600,000.00 0.00 Cancelado 2017-01-13 2017-01-28 2017-02-17 2017-03-19 2017-04-05 2017-10-23 AGUA EN EL MUNICIPIO DE investments ofertas Envelope HUAMANTLA. SENER-DGESE-FIDE-LPN-LH- IMS214669-CW-RFB / SUMINISTRO, INSTALACIÓN Y Public Facility Energy Solicitud de Single Stage - One Ejecución PUESTA EN OPERACIÓN DE IBRD / 88440 Previa Open - National 7,419,571.84 0.00 2021-06-22 2021-06-27 2021-07-27 2021-08-16 2021-09-20 2021-10-31 Efficiency Investments ofertas Envelope pendiente LUMINARIAS EN HOSPITALES DEL INSTITUTO MEXICANO DEL SEGURO SOCIAL (IMSS) MX-SENER-258546-LPN- HOSP- TABASCO-FIDE / Suministro, Instalación y Public Facility Energy Solicitud de Single Stage - One Ejecución IBRD / 88440 Previa Open - National 2,500,000.00 0.00 2021-11-12 2021-11-27 2021-12-27 2022-01-16 2022-02-04 2022-06-04 Puesta en Operación de Bienes Efficiency Investments ofertas Envelope pendiente de Alta Eficiencia Energética en Hospitales de Tabasco. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-CP-S-2016-02 / CAPACITACION POR PARTE DEL BANCO MUNDIAL DIRIGIDA A FUNCIONARIOS DE LA SENER, CONUEE, UREP, Policy development and Solicitud de Single Stage - One Ejecución IBRD / 85940 Posterior Open - National 15,000.00 0.00 2017-01-23 2017-03-19 2017-04-06 MUNICIPIOS Y CONSULTORES, institutional strengthening cotizaciones Envelope pendiente PARA LA HERRAMIENTA CLIMATE ACTION FOR URBAN SUSTAINABILITY (CURB) AL CONTEXTO MEXICANO. SENER-DGESE-CP-S-2016-01 / DISENO, EDICION E IMPRESION DE LOS INFORMES DE RESULTADOS DE 7 Policy development and Solicitud de Single Stage - One Ejecución ESTUDIOS (LEDS; HOSPITALES; IBRD / 85940 Posterior Open - National 50,000.00 0.00 2016-10-31 2016-12-04 2017-02-02 institutional strengthening cotizaciones Envelope pendiente CENTROS DE ACOPIO; ESCUELAS, IMPACTO DEL PROYECTO, HOTELES E IMPORTACIONES). SENER-DGESE-CP-S-2017-01 / LICENCIA DE USO DEL Policy development and Solicitud de Single Stage - One Ejecución IBRD / 85940 Posterior Limited 268.00 0.00 2017-06-23 2017-07-25 2018-07-25 SISTEMA CONTABLE CONTPAQ institutional strengthening cotizaciones Envelope pendiente i SENER-DGESE-CP-S-2018-01 / LICENCIA DE USO DEL Policy development and Solicitud de Single Stage - One IBRD / 85940 Posterior Limited 270.00 270.87 En ejecución 2018-11-20 2019-09-23 2018-12-22 2019-12-22 SISTEMA CONTABLE institutional strengthening cotizaciones Envelope CONTPAQi CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-SCC-2016-02 / DEFINICION DE LOS Selección basada PARAMETROS A REPORTAR Policy development and IBRD / 85940 Posterior en calificaciones Open - National 150,000.00 0.00 En ejecución 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 PARA EL ESTABLECIMIENTO DE institutional strengthening de consultores UNA LINEA BASE PARA MONITOREO DEL PRESEM SENER-DGESE-SCC-2016-03 / DISENO Y DESARROLLO DE UNA PAGINA WEB PARA DIFUSION DE LOS RESULTADOS Y CASOS DE Selección basada Policy development and Ejecución EXITO DEL PRESEM (SE ESTA IBRD / 85940 Posterior en calificaciones Open - National 45,000.00 0.00 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 institutional strengthening pendiente REVISANDO SI SERA UNA de consultores FIRMA O UN CONSULTOR INDIVIDUAL, DE SER ESTE ULTIMO SE HARA EL AJUSTE CORRESPONDIENTE) SENER-DGESE-SCC-2016-04 / DISENO E IMPARTICION DE 9 TALLERES DE EFICIENCIA Selección basada Policy development and ENERGETICA: 3 PARA LA IBRD / 85940 Posterior en calificaciones Open - National 270,000.00 0.00 Cancelado 2017-01-06 2017-01-10 2017-02-10 2017-02-16 2017-02-27 2017-08-31 institutional strengthening REGION NORTE, 3 PARA LA de consultores REGION CENTRO Y 3 PARA LA REGION SUR SENER-DGESE-SCC-2016-06 Selección basada / EVALUACION DE IMPACTO Policy development and Ejecución IBRD / 85940 Posterior en calificaciones Open - National 150,000.00 0.00 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 DEL ECOCREDITO institutional strengthening pendiente de consultores EMPRESARIAL SENER-DGESE-SCC-2017-01 / DISEÑO DE MECANISMO Selección basada PARA EL APOYO ECONOMICO Policy development and Ejecución IBRD / 85940 Posterior en calificaciones Open - National 45,000.00 0.00 2017-11-24 2017-12-11 2018-01-16 2018-02-15 2018-02-25 2018-05-26 AL CUMPLIMIENTO DE LA NOM- institutional strengthening pendiente de consultores 020-ENER PARA VIVIENDA DE INTERES SOCIAL SENER-DGESE-SCC-2017-02 / DISENO E IMPARTICION DE 3 TALLERES DE EFICIENCIA Selección basada ENERGETICA EN LOS Policy development and IBRD / 85940 Posterior en calificaciones Open - National 80,000.00 0.00 Cancelado 2017-12-11 2018-01-30 2018-02-26 2018-03-05 2018-03-23 2018-05-25 MUNICIPIOS DE MONTERREY institutional strengthening de consultores NUEVO LEON GUADALAJARA JALISCO Y VILLAHERMOSA TABASCO SENER-DGESE-SCC-2016-01 / DESARROLLO DE UNA PLATAFORMA EN LINEA DE Selección basada SEGUIMIENTO DE RESULTADOS Policy development and IBRD / 85940 Posterior en calificaciones Open - National 100,000.00 0.00 Cancelado 2016-11-22 2016-12-06 2016-12-20 2017-01-24 2017-02-01 2017-08-31 DEL PRESEM (DIAGNOSTICOS Y institutional strengthening de consultores EL MONITOREO DE LAS INTERVENCIONES EN MUNICIPIOS) MX-SENER-235627-CS-CQS FIDE-NOM-020 / Estudio sobre las implicaciones energéticas, económicas y Selección basada fiscales de la mejora de Policy development and Ejecución IBRD / 88440 Posterior en calificaciones Open - National 150,000.00 0.00 2021-06-21 2021-07-05 2021-07-30 2021-08-29 2021-09-18 2021-10-31 aislamiento térmico en el institutional strengthening pendiente de consultores sector residencial (por zona climática) para facilitar la implementación de la NOM- 020-ENER-2011 MX-SENER-235646-CS-CQS- FIDE-NOM-08 / Actualización Selección basada de la NOM aplicable a Policy development and Ejecución IBRD / 88440 Posterior en calificaciones Open - National 150,000.00 0.00 2021-06-21 2021-07-12 2021-08-05 2021-09-04 2021-09-28 2021-10-18 envolvente de edificios institutional strengthening pendiente de consultores comerciales (NOM-008-ENER- 2001) MX-SENER-235658-CS-CQS- FIDE-NOM-13 ENER / Selección basada Actualización de la NOM-013- Policy development and Ejecución IBRD / 88440 Posterior en calificaciones Open - National 150,000.00 0.00 2021-06-24 2021-07-14 2021-08-17 2021-09-01 2021-09-12 2021-10-05 ENER-2013 sobre la Eficiencia institutional strengthening pendiente de consultores Energética de Sistemas de Alumbrado en Vialidades MX-SENER-235659-CS-CQS- FIDE-CAP-EE-HOSP / DISEÑO Selección basada E IMPARTICIÓN DE CURSO DE Policy development and Ejecución IBRD / 88440 Posterior en calificaciones Open - National 200,000.00 0.00 2021-06-29 2021-07-20 2021-08-18 2021-09-02 2021-09-18 2021-10-31 EFICIENCIA ENERGÉTICA EN institutional strengthening pendiente de consultores HOSPITALES INTERACTIVO EN LÍNEA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SENER-DGESE-CI-3CV-2016- 02 / EJECUTIVO DE GESTION Policy development and FINANCIERA DE LA UNIDAD IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-11-03 2016-11-13 2016-12-02 2016-11-20 2016-12-01 2021-10-31 institutional strengthening RESPONSABLE EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 03 / ASISTENTE CONTABLE DE Policy development and Ejecución LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 99,157.26 0.00 2017-02-13 2017-02-28 2017-03-07 2017-03-17 2021-10-31 institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 04 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-10-24 2016-10-25 2016-12-01 2016-10-26 2016-11-01 2021-10-31 UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) Page 3 SENER-DGESE-CI-3CV-2016- 05 / ASISTENTE EN ADQUISICIONES DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 99,157.26 0.00 2017-02-24 2017-03-01 2017-03-22 2017-04-26 2021-10-31 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- 08 / ESPECIALISTA TECNICO Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 99,157.26 20,357.60 Finalizado 2016-11-21 2018-03-07 2016-12-06 2017-03-24 2016-12-20 2018-03-07 2017-01-02 2018-03-06 2021-10-31 2019-02-28 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2016- Policy development and 12 / GESTOR MUNICIPAL IBRD / 85940 Previa Individual Limited 271,446.48 0.00 Cancelado 2016-10-21 2016-10-22 2016-10-23 2016-11-01 2021-10-31 institutional strengthening REGION NORTE SENER-DGESE-CI-3CV-2016- Policy development and 13 / GESTOR MUNICIPAL IBRD / 85940 Previa Individual Limited 271,446.48 0.00 En ejecución 2016-10-21 2016-10-22 2016-10-23 2016-11-21 2021-10-31 institutional strengthening REGION SUR SENER-DGESE-CI-3CV-2016- 09 / EJECUTIVO EN NORMATIVIDAD Y Policy development and IBRD / 85940 Posterior Individual Limited 155,913.90 10,136.40 Finalizado 2016-03-16 2016-06-03 2016-03-21 2016-05-09 2016-05-24 2016-06-03 2016-05-31 2016-05-31 2021-10-31 2017-06-30 SEGUIMIENTO DE LA UNIDAD institutional strengthening RESPONSABLE EJECUTORA DEL PROYECTO (UREP). SENER-DGESE-CI-3CV-2016- 06 / ASISTENTE Policy development and IBRD / 85940 Posterior Individual Limited 61,039.42 11,320.14 Finalizado 2016-03-07 2016-05-17 2016-03-12 2016-05-17 2016-05-17 2016-05-17 2016-05-20 2016-05-20 2021-10-31 2017-06-30 ADMINISTRATIVO Y DE institutional strengthening SISTEMAS DE LA UREP SENER-DGESE-CI-3CV-2016- 01 / COORDINADOR GENERAL Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Previa Individual Limited 460,207.73 0.00 En ejecución 2016-03-07 2016-03-12 2016-05-02 2016-05-11 2016-05-17 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2016- 07 / COORDINADOR TECNICO Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Previa Individual Limited 210,869.01 0.00 En ejecución 2016-03-14 2016-03-19 2016-03-16 2016-04-09 2016-05-17 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2016- 14 / COORDINADOR GENERAL Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 32,253.46 0.00 En ejecución 2017-01-13 2017-01-18 2017-01-20 2017-01-23 2017-02-06 2017-08-05 institutional strengthening EJECUTORA DEL PROYECTO UREP/PRESEM. SENER-DGESE-CI-3CV-2016- Policy development and 22 / ESPECIALISTA EN IBRD / 85940 Posterior Individual Limited 33,000.00 0.00 En ejecución 2017-01-16 2017-01-21 2017-01-24 2017-02-13 2018-02-13 institutional strengthening COMUNICACION DEL PRESEM SENER-DGESE-CI-3CV-2017- 01 / ASISTENTE ADMINISTRATIVO DE LA Policy development and IBRD / 85940 Posterior Individual Limited 70,363.42 13,221.06 Finalizado 2017-06-23 2017-07-26 2017-06-26 2017-07-26 2017-07-11 2017-07-26 2017-08-01 2017-08-01 2021-10-29 2018-11-30 UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-3CV-2017- 02 / EJECUTIVO EN NORMATIVIDAD Y Policy development and SEGUIMIENTO DE ACUERDOS IBRD / 85940 Posterior Individual Limited 120,298.96 5,653.51 Finalizado 2017-06-23 2018-05-18 2017-06-26 2018-05-18 2017-07-17 2018-05-18 2017-08-01 2018-06-01 2021-10-29 2020-05-30 institutional strengthening DE LA UNIDAD RESPONSABLE EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CF-SD-2017- 01 / TALLER DE CAPACITACION EN EL MANEJO Policy development and Selección directa Ejecución Y ENSEÑANZA DE LA IBRD / 85940 Posterior Direct 9,000.00 0.00 2017-09-14 2017-09-18 2017-09-29 2017-11-22 institutional strengthening de consultores pendiente HERRAMIENTA CLIMATE ACTION FOR URBAN SUSTAINABILITY (CURB) SENER-DGESE-CI-CD-2016- 1 / CONSULTOR ESPECIALISTA EN EL MANEJO Y ENSENANZA Policy development and Selección directa IBRD / 85940 Posterior Direct 8,000.00 0.00 Cancelado 2017-02-01 2017-02-11 2017-02-27 2017-03-06 DE LA HERRAMIENTA CLIMATE institutional strengthening de consultores ACTION FOR URBAN SUSTAINABILITY (CURB) SENER-DGESE-CI-CD-2017- 01 / COORDINADOR GENERAL Policy development and Ejecución DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Direct 260,668.61 0.00 2017-11-23 2017-11-23 2017-11-24 2017-12-01 2021-10-29 institutional strengthening pendiente EJECUTORA DEL PROYECTO 2 (UREP/PRESEM) SENER-DGESE-CF-SD-2016- Policy development and Selección directa 01 / AUDITORIA DEL IBRD / 85940 Posterior Direct 100,000.00 0.00 Cancelado 2017-02-15 2017-02-15 2017-03-09 2017-06-07 institutional strengthening de consultores PROYECTO SENER-DGESE-CI-3CV-2018- 02 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 127,326.24 0.00 2018-02-23 2018-02-28 2018-03-21 2018-04-25 2021-10-31 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEM) SENER-DGESE-CI-CD-2018- Policy development and Selección directa Ejecución IBRD / 85940 Posterior Direct 180,968.32 0.00 2018-06-27 2018-06-27 2018-07-02 2021-10-29 01 / GESTOR MUNICIPAL institutional strengthening de consultores pendiente SENER-DGESE-CI-3CV-2018- 01 / COORDINADOR GENERAL Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 260,668.61 0.00 En ejecución 2018-02-28 2018-07-18 2018-03-05 2018-03-26 2018-04-30 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEM) Page 4 SENER-DGESE-CI-3CV-2018- 03 / COORDINADOR TECNICO Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 119,415.00 35,842.17 Finalizado 2018-08-08 2018-09-06 2018-08-13 2018-09-06 2018-08-23 2018-09-06 2018-09-10 2018-09-06 2021-10-31 2019-03-30 institutional strengthening EJECUTORA DEL PROYECTO (UREP) SENER-DGESE-CI-3CV-2019- 03 / EJECUTIVO DE ADQUISICIONES DE LA Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 66,081.96 0.00 2019-12-27 2019-12-27 2020-01-17 2020-02-21 2021-10-31 UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2019- 01 / COORDINADOR TECNICO Policy development and DE LA UNIDAD RESPONSABLE IBRD / 85940 Posterior Individual Limited 66,081.96 29,868.47 Firmado 2019-12-27 2020-02-28 2020-01-01 2020-02-28 2020-01-22 2020-02-28 2020-02-26 2020-03-01 2021-10-31 institutional strengthening EJECUTORA DEL PROYECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2020- 01 / EJECUTIVO DE GESTION Policy development and Ejecución FINANCIERA DE LA UNIDAD IBRD / 85940 Posterior Individual Limited 64,873.60 0.00 2020-02-14 2020-02-18 2020-02-21 2020-03-01 2021-10-31 institutional strengthening pendiente RESPONSABLE EJECUTORA DEL PROYECTO (UREP/PRESEMEH) SENER-DGESE-CI-3CV-2016- 24 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO UREP/PRESEM 2 SENER-DGESE-CI-3CV-2016- 25 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-24 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO UREP/PRESEM 3 SENER-DGESE-CI-3CV-2016- 23 / ASISTENTE TECNICO EN EFICIENCIA ENERGETICA DE LA Policy development and IBRD / 85940 Posterior Individual Limited 6,079.63 0.00 Cancelado 2017-04-10 2017-04-15 2017-04-26 2017-05-08 2017-11-04 UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO UREP/PRESEM 1 SENER-DGESE-CI-3CV-2016- 15 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-10-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 1 SENER-DGESE-CI-3CV-2016- 16 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 2 SENER-DGESE-CI-3CV-2016- 17 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 3 SENER-DGESE-CI-3CV-2016- 18 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 4 SENER-DGESE-CI-3CV-2016- 19 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 5 SENER-DGESE-CI-3CV-2016- 20 / EVALUACION Policy development and IBRD / 85940 Posterior Individual Limited 12,500.00 0.00 Cancelado 2017-04-28 2017-05-03 2017-05-12 2017-05-24 2017-11-24 ENERGETICA URBANA EN EL institutional strengthening MUNICIPIO 6 SENER-DGESE-CI-3CV-2016- 11 / CONSULTOR PARA LA ADAPTACION DEL "MANUAL Policy development and PARA LA IMPLEMENTACION DE IBRD / 85940 Previa Individual Limited 124,257.89 0.00 Cancelado 2017-01-20 2017-02-03 2017-02-20 2017-03-02 2021-03-01 institutional strengthening UN SISTEMA DE GESTION DE LA ENERGIA DE LA CONUEE" EN MUNICIPIOS. SENER-DGESE-CI-3CV-2016- 21 / DESARROLLO DE GUIA DE Policy development and IBRD / 85940 Posterior Individual Limited 25,000.00 0.00 Cancelado 2017-03-10 2017-03-15 2017-03-23 2017-04-05 2017-10-02 APOYOS FINANCIEROS A institutional strengthening MUNICIPIOS SENER-DGESE-CI-3CV-2016- 10 / CONSULTOR EXPERTO PARA SUPERVISAR LOS Policy development and DIAGNOSTICOS MUNICIPALES IBRD / 85940 Previa Individual Limited 253,042.81 0.00 Cancelado 2017-04-28 2017-05-13 2017-05-21 2017-06-01 2021-05-31 institutional strengthening EN EFICIENCIA ENERGETICA Y ANALISIS DE RESULTADOS DEL PRESEM SENER-DGESE-CI-3CV-CG- 214705-CS-INDV / COORDINADOR GENERAL DE Policy development and IBRD / 85940 Posterior Individual Limited 34,392.05 0.00 En ejecución 2021-03-01 2021-03-06 2021-03-16 2021-04-01 2021-10-31 LA UNIDAD RESPONSABLE institutional strengthening EJECUTORA DEL PROYECTO (UREP / PRESEM) SENER-DGESE-CI.3CV-EGF- 215029-CS-INDV / Policy development and “EJECUTIVO DE GESTIÓN IBRD / 85940 Posterior Individual Limited 20,564.29 0.00 Bajo Revision 2021-03-01 2021-06-29 2021-03-06 2021-03-14 2021-04-01 2021-10-31 institutional strengthening FINANCIERA DE LA UREP/PRESEMEH” SENER-DGESE-CI-3CV-2016- Policy development and 12-30-06-2018 / GESTOR IBRD / 85940 Posterior Individual Limited 271,446.48 0.00 En ejecución 2021-06-21 2021-06-26 2021-07-17 2021-08-21 2021-10-31 institutional strengthening MUNICIPAL REGION NORTE Page 5 MX-SENER-235661-CS-INDV- Policy development and DGIDTFRH / Gestor Municipal IBRD / 85940 Posterior Individual Limited 8,538.42 0.00 Bajo Revision 2021-06-25 2021-08-04 2021-06-30 2021-07-21 2021-09-01 2021-10-31 institutional strengthening PRESEMH-UREP MX-SENER-250381-CS-INDV / Ejecutivo en Normatividad y Seguimiento de Acuerdos de Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 2,769.54 0.00 2021-09-03 2021-09-06 2021-09-13 2021-09-16 2021-11-07 la Unidad Responsable institutional strengthening pendiente Ejecutora del Proyecto (UREP / PRESEM)” MX-SENER-254879-CS-INDV Policy development and Ejecución DGIDTFRH-2021-2 / Gestor IBRD / 85940 Posterior Individual Direct 4,251.77 0.00 2021-09-27 2021-09-27 2021-09-28 2021-09-30 2021-10-31 institutional strengthening pendiente Municipal PRESEMH/UREP MX-SENER-258557-3CV-CI- CS-INDV-DGIDTFRH / Ejecutivo en Normatividad y Policy development and Ejecución Seguimiento de Acuerdos de IBRD / 85940 Posterior Individual Limited 32,733.17 0.00 2021-10-22 2021-10-22 2021-10-25 2021-11-01 2023-04-30 institutional strengthening pendiente la Unidad Responsable Ejecutora del Proyecto (UREP / PRESEM) ” MX-SENER-258560-REC-CS- INDV- DGIDTFRH / Ejecutivo Policy development and Ejecución IBRD / 85940 Posterior Individual Direct 51,880.53 0.00 2021-10-22 2021-10-22 2021-10-27 2021-11-01 2023-04-30 de Gestión Financiera de la institutional strengthening pendiente UREP/PRESEMEH MX-SENER-258561-REC-CS- Policy development and Ejecución INDV-DGIDTFRH / Gestor IBRD / 85940 Posterior Individual Direct 74,397.52 0.00 2021-10-22 2021-10-22 2021-10-27 2021-11-01 2023-04-30 institutional strengthening pendiente Municipal PRESEMH / UREP MX-SENER-258564-REC-CS- INDV-DGIDTFRH / COORDINADOR TÉCNICO DE Policy development and Ejecución IBRD / 85940 Posterior Individual Direct 51,880.53 0.00 2021-10-22 2021-10-22 2021-10-27 2021-11-01 2023-04-30 LA UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP / PRESEMEH) MX-SENER-258567-3-CV-CI- CS-INDV-DGIDTFRH / COORDINADOR GENERAL DE Policy development and Ejecución IBRD / 85940 Posterior Individual Limited 77,120.11 0.00 2021-11-15 2021-11-20 2021-11-30 2022-01-03 2023-04-30 LA UNIDAD RESPONSABLE institutional strengthening pendiente EJECUTORA DEL PROYECTO (UREP / PRESEM) Page 6