PRIORITIZED ROAD INVESTMENT AND MANAGEMENT ENHANCEMENTS (PRIME) PROJECT Federated States of Micronesia STAKEHOLDER ENGAGEMENT PLAN FINAL Prepared for With Funding from December 2020 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan CONTENTS 1. Introduction ........................................................................................................................ 1 1.1 Environmental and Social Assessment Overview ...................................................................... 1 1.2 Stakeholder Engagement Plan .................................................................................................. 1 2. Project Description ............................................................................................................ 4 2.1 Overview of the ‘PRIME’ Project ............................................................................................... 4 2.2 ‘PRIME’ Investments and Activities ........................................................................................... 4 3. Stakeholder Engagement Objectives and Principles ..................................................... 7 3.1 Definition of ‘Stakeholder’ in ESS10 .......................................................................................... 7 3.2 Stakeholder Engagement Objectives ........................................................................................ 7 3.3 Key Principles of Effective Engagement .................................................................................... 8 3.4 Stakeholder Engagement Considerations ................................................................................. 9 4. Stakeholder Identification and Analysis ........................................................................ 13 4.1 Stakeholder Identification ........................................................................................................ 13 5. Stakeholder Engagement Approach .............................................................................. 18 5.1 Project Preparation Stakeholder Engagement Activities ......................................................... 18 5.2 Ongoing Stakeholder Engagement throughout PRIME Project................................................ 42 5.3 Stakeholder Engagement Tools and Materials ........................................................................ 53 6. Grievance Mechanism ..................................................................................................... 55 6.1 Introduction ............................................................................................................................. 55 6.2 Grievance Redress Process .................................................................................................... 57 6.3 Disclosure of Grievance Mechanism ....................................................................................... 59 6.4 Record Keeping and Reporting of Grievances ........................................................................ 59 7. Resources and Responsibilities for Implementing SEP............................................... 62 7.1 Stakeholder Engagement Resources and Responsibilities...................................................... 62 8. Monitoring and Reporting ............................................................................................... 67 LIST OF TABLES Table 5-1: Project Area of Influence (AOI) delineations and conditions ....................................................... 14 Table 5-1: Stakeholders engaged with in each State during Project Preparation (July to November 2020) ... 20 Table 5-2: Summary of combined key feedback and comments received from stakeholders during Project preparation consultation meetings. ................................................................................................................ 25 Table 5-3: PRIME Project Stakeholder Engagement and Communication Plan ............................................. 44 Table 6-1: PRIME Project Grievance Mechanism Process............................................................................. 57 December 2020 Final ii Federated States of Micronesia PRIME Project Stakeholder Engagement Plan LIST OF FIGURES Figure 7-1: Implementation arrangements for the PRIME Project. ................................................................. 62 APPENDICES Appendix A PRIME Project Summary Document Appendix B Presentations from Project preparation consultation meetings Appendix C Summary of stakeholder engagement activities during Project preparation Appendix D Meeting notes from Project preparation consultation meetings December 2020 Final iii Federated States of Micronesia PRIME Project Stakeholder Engagement Plan ABBREVIATIONS AOI Area of Interest CBO Community Based Organisation CIU DoFA Central Implementation Unit CRRS Climate Resilient Road Strategy DoFA Department of Finance and Administration DoTC&I Department of Transportation, Communications and Infrastructure E&S Environmental and Social ESA Environmental and Social Assessment ESCP Environmental and Social Commitment Plan ESF World Bank Environmental and Social Framework ESMF PRIME Environmental and Social Management Framework ESMP Environmental and Social Management Plan ESS World Bank Environmental and Social Standards FSM Federated States of Micronesia FPIC Free, Prior and Informed Consent GIS Geographic Information Systems GoFSM Government of FSM GM Grievance Mechanism IOL Inventory of Loss NGO Non-Governmental Organisation OHS Occupational Health and Safety PAP Project Affected Person PIU PRIME Project Implementation Unit PMU DoTC&I Project Management Unit PRIME Prioritized Road Investment and Management Enhancements Project PSC Project Steering Committee RF PRIME Resettlement Framework SEP PRIME Stakeholder Engagement Plan (this document) SIDS Small Island Developing States TOR Terms of Reference VA Vulnerability Assessment WB World Bank WHO World Health Organization December 2020 Final iv Federated States of Micronesia PRIME Project Stakeholder Engagement Plan GLOSSARY Cut-off date The eligibility cut-off date is the date of completion of the inventory of loss (IOL) for Project works under Component 2. Assets located within the Component 2 works footprint after this date will not be eligible for entitlements or associated assistance. Gender Mainstreaming The process of ensuring that gender concerns and women’s needs and perspectives are explicitly considered in Projects and programs, and that women participate in the decision-making processes associated with development-based activities. Indigenous Persons WB ESS7: Referring exclusively to a distinct social and cultural group possessing the following characteristics in varying degrees: (i) self- identification as members of a distinct indigenous social and cultural group and recognition of this identity by others; and (ii) collective attachment to geographically distinct habitats, ancestral territories or areas of seasonal use or occupation, as well as to the natural resources in these areas; and (iii) customary cultural, economic, social, or political institutions that are distinct or separate from those of the mainstream society or culture; and (iv) a distinct language or dialect, often different from the official language or languages of the country or region in which they reside. Meaningful WB ESF / ESS10: a two-way process that (a) begins early in the a Consultation project planning process to gather initial views on the project proposal an inform project design; (b) encourages stakeholder feedback, particularly as a way of informing project design and engagement by stakeholders ion the identification and mitigation of environmental and social risks and impacts; (c) continues on an ongoing basis, as risks and impacts arise; (d) is based on the prior disclosure and dissemination of relevant, transparent, objective, meaningful and easily accessible information in a timeframe that enables meaningful consultations with stakeholders, in a culturally appropriate format, in relevant local language(s) and in understandable to stakeholders; € considers and responds to feedback; (f) supports active and inclusive engagement with project-affected parties; (g) is free of external manipulation, interference, coercion, discrimination, and intimidation; and (h) is documented and disclosed by the Borrower. PRIME Roads Roads that will be assessed as part of Technical Assistance (TA) aspects of the PRIME Project, including the Vulnerability Assessment (VA), Climate Resilient Road Strategy (CRRS) and Environmental and Social Assessment (ESA studies, which include the majority of the existing ‘primary roads’ on the main islands of each FSM State, and some additional secondary roads that are considered to be of strategic and/or economic importance by DoTC&I. Only the primary roads identified will be funded under Component 2 of the PRIME Project. Any recommended improvements identified by the VA/CRRS on the secondary roads will not be considered for funding under Component 2 of PRIME, however they may form part of recommended future investment needs for FSM’s road network. December 2020 Final v Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Project Affected Includes any person, households, entity, organizations, firms or private Persons institutions who, on account of changes that result from the Project will have their (i) standard of living adversely affected, (ii) right, title, or interest in any house, land (including residential, commercial, agricultural, forest, plantations, grazing, and/organizing land), water resources, communal fishing grounds, annual or perennial crops and trees, or any other moveable or fixed assets acquired, possessed, restricted, or otherwise adversely affected, in full or in part, permanently or temporarily; and/or (iii) business, occupation, place of work or residence, or habitat adversely affected, permanently or temporarily, with or without displacement. Vulnerable Road Users Road users who are more vulnerable to harm because they are not in a vehicle, including pedestrians, motorcyclists, cyclists, and those on animals or animal drawn carts. December 2020 Final vi Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 1. Introduction 1.1 Environmental and Social Assessment Overview The Government of Federated States of Micronesia (GoFSM) has applied for financing from the World Bank (WB) for the Prioritized Road Investment and Management Enhancements (PRIME) Project to improve the climate resilience of FSM’s road network. Part of the PRIME Project includes the assessment of environmental and social risks including: (i) Environmental and Social Assessment (ESA); (ii) Preparation of environmental and social instruments in accordance with the WB Environmental and Social Framework (ESF); (iii) Support stakeholder consultation activities; and (iv) Provision of technical environmental and social advice as required to the GoFSM as part of Project preparation. The ESA Consultant was engaged by the GoFSM through the Department of Transportation, Communications and Infrastructure (DoTC&I) to undertake the ESA and prepare instruments required for WB appraisal including development of a Stakeholder Engagement Plan (SEP) for the PRIME Project. 1.2 Stakeholder Engagement Plan 1.2.1 Purpose and Scope of the Stakeholder Engagement Plan This SEP presents and describes the stakeholder engagement activities (primarily information acquisition, disclosure and consultations, dissemination of key issues/results and participatory design approaches) proposed for the PRIME Project. Well-planned and executed stakeholder engagement assists in building strong relationships with stakeholders based on mutual respect and trust and increases the likelihood that Projects are well-designed and responsibly implemented. This SEP draws on both the experience of previous stakeholder engagement and an understanding of stakeholder concerns that DoTC&I has gained in relation to the road network within FSM. The SEP is aligned with the provisions of the World Bank (WB) Environmental and Social Standard (ESS) 10: Stakeholder Engagement and Information Disclosure (WB, 2017) 1, as well as other national and international standards (refer Section 3). Key stakeholders are identified that are to be consulted throughout the duration of the Project including relevant Government authorities, traditional authorities, local community, landowners and key road users. This SEP should be considered a dynamic document that DoTC&I will periodically examine and update where relevant with regard to its performance and in relation to the specific annual Project work plans. Works specific or technical assistance (TA) specific Stakeholder Engagement Plans may be prepared based on specific activity or stakeholder needs. 1 WB, 2017. “World Bank Environmental and Social Framework”. World Bank, Washington December 2020 Final 1 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 1.2.1.1 Covid-19 Pandemic On March 11, 2020, the World Health Organization (WHO) declared a global pandemic in response to the global spread of the severely infectious 2019 Novel Coronavirus (SARS- CoV-2, or ‘Covid-19’). FSM is particularly vulnerable to the risk of Covid-19 due to its economic reliance on international travel of residents, tourists, and trade. Although no cases have been reported in the FSM to date (as at 1 December 2020) both international and domestic (i.e. inter- State) travel restrictions have been in place in FSM since March 2020 with strict quarantine requirements for travellers. As a result the core internationally-based ESA consultant team was not able to travel to FSM as part of the preparation of the PRIME Project ESA, instead engaged locally based sub-consultants in each State to undertake the baseline data collection, field survey and stakeholder consultation activities under the direction of the internationally based environmental and social experts. Consultation meetings were facilitated by the State-based ESA consultant team members. While initial efforts were made to allow relevant members of the international ESA consultant team to call into larger meetings via online video conferencing, internet connection was not reliable enough for this approach to be successful in most cases. The FSM-based team was provided with training and consultation material (including presentation, Project Summary, agenda, meeting minutes template and attendee lists) by the international ESA consultant team members prior to consultation meetings. This was undertaken to ensure consistency in the messages being communicated to stakeholders across all four States, to ensure valuable feedback was provided and to manage stakeholder expectations. An internal debrief meeting was then held after the meeting to discuss any issues raised by the stakeholders and learnings from the process. 1.2.2 SEP Objectives The SEP seeks to define a technically and culturally appropriate approach to consultation and disclosure. The goal of this SEP is to improve and facilitate decision making and create an atmosphere of understanding that actively involves Project -affected people and other stakeholders in a timely manner and that these groups are provided sufficient opportunity to voice their opinions and concerns that may influence Project decisions. The SEP is a useful tool for managing communications between DoTC&I and its stakeholders. The key objectives of the SEP for this Project are as follows: • Provide guidance for stakeholder engagement such that it meets the standards of International Best Practice, including adhering to WB ESS10 and ESS7; • Identify key Project stakeholders within each State, including indigenous persons; • Identify the most effective methods and structures through which to disseminate Project information, and to ensure regular, accessible, transparent and appropriate consultation; • Guide DoTC&I to build mutually respectful, beneficial and lasting relationships with stakeholders; • Develop a stakeholder engagement process that provides stakeholders with an opportunity to influence Project planning and design; December 2020 Final 2 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Outline the Grievance Mechanism (GM) for implementation of the PRIME Project; • Identify roles and responsibilities for implementation of the SEP. • Describe means of reporting and disclosure of key information and instruments in a manner that can be readily understood by all key stakeholders (including the community and vulnerable groups); and • Potential communications challenges (e.g. over consultation, confusion with other Projects, etc) and opportunities (e.g. synergies with other consultation activities and facilitators known to the community) will be identified. December 2020 Final 3 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 2. Project Description 2.1 Overview of the ‘PRIME’ Project The Prioritized Road Investment and Management Enhancements (PRIME) Project will provide funds for technical assistance and institutional strengthening to improve the management of the road network in relation to potential climate change impacts for the FSM. In addition, the Project will fund the feasibility, design and construction of physical works on priority road assets to improve resilience to climate-related hazards or events. FSM’s transport network is of critical importance to the country’s economy and economic development through supporting trade and promoting commercial activity by facilitating the movement of goods and services, and providing safe and efficient access to social services including schools and health facilities. Critical climate resilient road, bridge or drainage improvement works to be implemented urgently to maintain a basic level of land transport connectivity in each state will be identified as part of the PRIME Project. The extent of these works are described and shown in thew ESMF 2. While some initial road works have been identified as requiring urgent works (refer Component 2, Section 2.2.2), the design of the required works has not yet been undertaken and the full extent of impacts are not yet known. The additional works that will form the PRIME Project will be identified as part of the VA and CRRS studies. As part of these studies a multi-criteria assessment will be undertaken to prioritize the urgency of works and works that will be funded by PRIME. Environmental and social risk screening will be part of the multi-criteria analysis. A summary of key PRIME Project components are outlined below. Further detail on the scope of the PRIME Project activities is outlined in the ESMF. 2.2 ‘PRIME’ Investments and Activities Project activities will primarily take place within existing primary road corridors, or immediately adjacent to the road to improve erosion protection, drainage or safety features. Some additional secondary roads that are considered to be of strategic and/or economic importance will also form part of the ‘PRIME Roads’, and be assessed under Component 1 below, but recommended improvements on these secondary roads will not be considered for funding under Component 2. The extent of these roads including a definition of ‘PRIME Roads’ in each State are presented in the ESMF. The three key components of the PRIME Project are outlined below. 2.2.1 PRIME Component 1: Spatial and Sector Planning Tools This Component involves technical assistance that will improve the way that climate change is addressed in FSM’s road sector to enable policymakers to make informed decisions based on the most accurate and up-to-date information available. The following activities are proposed under Component 1: a) Vulnerability Assessment (VA) and Climate Resilient Road Strategy (CRRS). Preparation and implementation of a VA and CRRS to assess levels of vulnerability to climate change and severe weather events (e.g. sea-level rise, extreme rainfall, landslide, storm surge, etc.) across FSM’s existing primary road corridors and 2Prioritized Road Investment and Management Enhancements (PRIME) Project, FSM: Environmental and Social Management Framework’, Report prepared for Department of Transportation, Communication and Infrastructure. December 2020 Final 4 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan GoFSM-selected existing strategic secondary road corridors. The VA and CRRS will also identify measures to enhance resilience and prioritize investments to balance vulnerability reduction against cost implication. Training will be provided to relevant national and state officials in the use of VA and CRRS tools. b) Climate-informed road asset management systems. Provision of hardware, software and ancillary tools to establish climate-informed road asset management systems to be used by DoTC&I and State Road Authorities. Training will be provided to relevant National and State officials in the use of these systems. 2.2.2 PRIME Component 2: Climate Resilient Infrastructure Solutions This Component involves feasibility studies, design and construction of identified priority road assets to improve their resilience to climate-related hazards. The integration of climate change considerations into infrastructure activities will help strengthen the resilience of assets and improve functionality of the road network. Component 2 is split into two parts: a) Urgent Priority Works (including design and supervision). Critical climate resilient road, bridge, causeway or drainage improvement works that should be implemented urgently to maintain a basic level of road connectivity in each state. Urgent works proposed for financing under the PRIME Project include: (i) Improving the narrow, low-level Lelu causeway in Kosrae; (ii) Replacing the 12 m Awak bridge in Pohnpei; (iii) Improving the 2.5 km airport to Pou Bay bridge road in Chuuk; and (iv) Replacing two short-span (6 m long) steel and concrete composite bridges in Yap. b) Works informed by the VA and CRRS (including design and supervision). In addition to the urgent priorities under Sub-component 2a, a selection of near, medium and long-term road works would be financed to enhance the resilience of the network in each state to climate change impacts and natural hazards, in accordance with the recommendations from the VA and CRRS undertaken as part of Component 1. Works will be restricted to road networks within the existing primary road corridors. Interventions are expected to include measures to strengthen network resilience, including but not necessarily limited to: (i) Pavement and surface strengthening – periodic maintenance, repairs, rehabilitation or reconstruction of existing road pavement layers and/or surfacing, including provision of sealed shoulders and raising road levels; (ii) Drainage improvements – provision, reinstatement and/or lining of longitudinal drainage, replacement and/or increasing capacity of cross drainage culverts, improving open or covered outfalls, provision of subsoil drainage and cut-off drains; (iii) Spot slope stabilization – widening and/or reducing slope of cuttings and fill embankments to reduce landslip risk, soil bioengineering and biotechnical stabilization techniques, and anchoring of unstable rock slopes; December 2020 Final 5 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan (iv) Rock wall revetment strengthening – for protection of coastal road sections; (v) Improvements to causeways and bridges – repairs or reconstruction of existing crossings and/or provision of new crossings to provide safe, all weather access for vehicles and pedestrians; (vi) Road safety improvements – traffic calming measures, provision of guardrails, line marking and minor realignments to improve sight distance. 2.2.3 PRIME Component 3: Strengthening the Enabling Environment This Component will provide funding to support institutional and regulatory reforms for road sector asset management and maintenance, including measures to strengthen local capacity and to increase the sustainability of climate resilient road sector investments. In addition, this Component will help to strengthen coordination among relevant institutions, will look at ways in which road sector management can be improved, and will address any emerging priority issues that can help support GoFSM in addressing climate change risks. Proposed Sub-components include: a) Institutional and Governance Review. A review of institutional arrangements, key policies, regulations, legislation and roles and responsibilities of principle stakeholders involved in the road sector with recommendations to strengthen such arrangements. b) Project Management. Establishment and maintenance of a Project Implementation Unit (PIU) to support the implementation of the PRIME Project. In addition, this includes operating costs for PRIME-related travel and communications costs. c) Road Safety Program. Provision of technical assistance activities to improve road safety. d) Capacity Building Initiatives. Assess current preventive maintenance techniques and industry capacity. Provide technical trainings to sector agencies and local consultants and contractors to better operate and regulate a more climate resilient road network. e) Gender-informed Driver Licensing Pilot. A pilot program to study and implement activities that address gaps in the possession of a driver’s license. f) Emerging Priority Issues. Providing technical assistance to strengthen the Recipient’s capacity to address emerging priority issues that could have an impact on the Recipient’s ability to manage a climate resilient road network. . December 2020 Final 6 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 3. Stakeholder Engagement Objectives and Principles 3.1 Definition of ‘Stakeholder’ in ESS10 World Banks definition of ‘Stakeholders’, as stated in the ESS10, refers to: “…individuals or groups who: a) Are affected or likely to be affected by the Project (Project -affected parties); and b) May have an interest in the Project (other interested parties).” The ES10 guidance note document provides further definitions for these groups, including: • Project Affected Persons – “includes those likely to be affected by the Project because of actual impacts or potential risks to their physical environment, health, security, cultural practices, well-being, or livelihoods. These stakeholders may include individuals or groups, including local communities”. • Other Interested Parties – “refers to individuals, groups, or organizations with an interest in the Project , which may be because of the Project location, its characteristics, its impacts, or matters related to public interest. For example, these parties may include regulators, government officials, the private sector, the scientific community, academics, unions, women’s organizations, other civil society organizations, and cultural groups”. ESS10 also states that for both groups “special consideration should be given to stakeholders that may be disadvantaged or vulnerable”. 3.2 Stakeholder Engagement Objectives ESS 10 states that the objectives of stakeholder engagement are as follows: • To establish a systematic approach to stakeholder engagement that will help Borrowers identify stakeholders and build and maintain a constructive relationship with them, in particular Project affected parties. • To assess the level of stakeholder interest and support for the Project and to enable stakeholders’ views to be taken into account in Project design and environmental and social performance. • To promote and provide means for effective and inclusive engagement with Project -affected parties throughout the Project life cycle on issues that could potentially affect them. • To ensure that appropriate Project information on environmental and social risks and impacts is disclosed to stakeholders in a timely, understandable, accessible, and appropriate manner and format. • To provide Project -affected parties with accessible and inclusive means to raise issues and grievances, and allow Borrowers to respond to and manage such grievances. The operational objectives of stakeholder engagement for the PRIME Project are: December 2020 Final 7 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Acquire information from key stakeholders to assist in environmental and social risk screening, and the preparation of land procedure documents for the PRIME Project (as described in Section 5); • Ensuring that stakeholders have an understanding of how they might be affected and their potential role in PRIME Project implementation and impact management; • Implementation of a ‘participatory design approach’, whereby between Project designers, respective landowners, road users and communities undertake detailed consultations throughout the design process in order to minimize impacts on land and people; • Provision of opportunities for stakeholders to express their opinions and concerns in relation to the PRIME Project, and for these opinions and concerns to be taken into account in the development of works land access documents and E&S management plans; and • Ensuring that stakeholders understand the PIU’s and the WB’s operational aims and requirements with respects to PRIME Project, and have confidence in the PIU’s ability to manage environmental and social risks in a responsible and transparent manner. Early and ongoing engagement with land owners, local communities, vulnerable groups and their traditional or local leaders will be critical for all stages of the PRIME Project. The design of road improvements will prioritize works within the corridors of existing primary roads and minimize the loss of private property, where technically feasible. There will be an emphasis on ‘participatory design approach’ whereby local communities and affected land owners participate in the decisions related to the design of road improvements that affect them. 3.3 Key Principles of Effective Engagement ESS10 states that stakeholder engagement is: “an inclusive process conducted throughout the Project life cycle. Where properly designed and implemented, it supports the development of strong, constructive, and responsive relationships that are important for successful management of a Project ’s environmental and social risks. Stakeholder engagement is most effective when initiated at an early stage of the Project development process, and is an integral part of early Project decisions and the assessment, management, and monitoring of the Project ’s environmental and social risks and impacts.” Stakeholder engagement is usually informed by a set of principles defining core values underpinning interactions with stakeholders. Common principles based on International Best Practice 3 include the following: • Commitment is demonstrated when the need to understand, engage and identify the community is recognised and acted upon early in the process; • Integrity occurs when engagement is conducted in a manner that fosters mutual respect and trust; 3 IFC, 2007, Stakeholder Engagement: A Good Practice Handbook for Companies Doing Business in Emerging Markets. December 2020 Final 8 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Respect is created when the rights, cultural beliefs, values and interests of stakeholders and affected communities are recognised; • Transparency is demonstrated when community concerns are responded to in a timely, open and effective manner; • Inclusiveness is achieved when broad participation is encouraged and supported by appropriate participation opportunities; and • Trust is achieved through open and meaningful dialogue that respects and upholds a community’s beliefs, values and opinions. 3.4 Stakeholder Engagement Considerations The stakeholder engagement process will be inclusive, participatory and transparent to ensure multiple opportunities for learning about the Project for all affected or interested stakeholder groups. Ensuring informed participation and consultations creating an atmosphere for open dialogue, ensuring the vulnerable are empowered and facilitated to participate and transparency are the principles in the approach to stakeholder engagement. The following considerations will be made when planning for stakeholder engagement 4: • Time and Resources: It takes time to develop and build trust-based relationships with stakeholders. The consensus from practitioners is that from the outset relationships with stakeholders should develop and grow, and that these relationships should be nurtured and not fostered to fade. Additional stakeholders might be identified that also want to be engaged. No willing stakeholder should be excluded from the process of engagement. Some stakeholders will need to be educated about the concept of engagement itself, as well as on the complex issues requiring specialised and technical knowledge. These demands can increase the cost of consultation required to meet external expectations and often this occurs at a time when a Project lacks the internal capacity and resources to implement a broad engagement strategy. • Raises Expectations: Stakeholders can have unrealistically high expectations of benefits that may accrue to them from a Project. As such, DoTC&I as Project proponents must be clear on what they can and cannot do, establishing a clear understanding of their roles and responsibilities. Managing expectations especially from land owners and communities affected will be handled at the outset of the Project. In FSM, the engagement processes should provide DoTC&I with an opportunity to develop relationships with stakeholders and potential Project partners who can assist with implementing corporate social responsibility Projects. • Securing Stakeholder Participation: Cultural norms and values can prevent stakeholders from freely participating in meetings. Often there are conflicting demands within a community and it can be challenging for a Project to identify stakeholders who are representative of common interests. The inclusion of women and vulnerable groups to ensure gender participation and the consideration of the needs and priorities of all sectors of the community will be addressed. An awareness 4 Based on: “Stakeholder Research Associates Canada Inc, 2005, The Stakeholder Engagement Manual Volume 1: The Guide to Practitioners’ Perspectives on Stakeholder Engagement, www.StakeholderResearch.com.” December 2020 Final 9 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan of the local context and implementing structures to support and foster effective stakeholder engagement, will be important. Employing Project State Focal Points (refer Section 8) who are sensitive to local communication (including traditional) structures and power dynamics will assist in fostering effective stakeholder engagement. • Consultation Fatigue: Moreover evidence suggests that stakeholders can easily tire of consultation processes especially when promises are unfulfilled, and their opinions and concerns are not taken into consideration. Often stakeholders feel their lives are not improving as a result of a Project and this can lead to consultation meetings being used as an area to voice complaints and grievances about the lack of development. This might be avoided by coordinating stakeholder engagement during an assessment process and by ensuring practitioners do not make promises to stakeholders but rather use the public consultation process as an opportunity to manage expectations, challenge misconceptions, disseminate accurate Project information and gather stakeholder opinions which are feedback to the client and other Project specialists. • Use of Participatory Approaches: Participatory appraisal tools will be used during consultations to ensure the engagement of all sectors of the community. Participatory tools such as the use of seasonal calendars, time use surveys and ranking of resources used for both income and subsistence livelihoods will address gender, age, traditional barriers and allow everyone to participate. The ‘participatory design approach’ will also be applied to the Project to involve land owners and community in the design and prioritization process to minimize impacts, and resolve uncertainties regarding easement extents. • Information and Communication Access: Information and communication needs of various groups and individuals especially those more disadvantaged or vulnerable including consideration of use of local languages, accessible means of communication, physical accessibility challenges and accessible feedback. To ensure broad participation, consultations are to be undertaken at venues, times and in languages that do not disadvantage any particular groups (e.g. women, or vulnerable households). • Culturally Approach Engagement: It is critical that engagement is inclusive and culturally appropriate, especially in terms of Project Affected Persons (PAPs) and/or communities and indigenous peoples. This could include appropriate forms meeting type, venues, locations, times, language used, materials presented, means of disclosure and involvement of traditional leaders. • Language: Engagement is to be undertaken in a language appropriate for the broadest comprehension by stakeholders possible. While English is widely understood (both written and spoken) throughout FSM (being the official language of FSM), each State has an indigenous culture and their own official languages (e.g. Kosraean, Mehn Pohnpei, Chuukese and Yapese as well as English), which may be more likely to be better understood amongst community stakeholders. Literacy levels amongst stakeholders should also be considered when undertaking engagement. The remaining chapters of this report outline considerations that will assist in overcoming issues with stakeholder engagement and attaining the overarching goal of free, prior and informed consultation. December 2020 Final 10 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 3.4.1 Barriers to Participation 3.4.1.1 Disadvantaged or vulnerable groups Some Project impacts may disproportionately fall on disadvantaged or vulnerable individuals or groups who often do not have a voice to express concerns or understand the impacts of a Project. Some road users may also be more vulnerable to harm because they are not in a vehicle including pedestrians, motorcyclists, cyclists, and those on animals or animal drawn carts. The Project will identify vulnerable or disadvantaged individuals or groups and the limitations they may have in participating and/or in understanding the Project information on an ongoing basis. Currently identified representatives of vulnerable people and groups that require engagement as part of the Project are outlined in Section 4.1.3. The list will be expanded and updated as new groups are identified. 3.4.1.2 Gender, Sexual Exploitation and Abuse (SEA) and Sexual Harassment (SH) Micronesian societies are matrilineal and inheritance of land and other assets is traditionally through women even though the senior male of the lineage, often a woman’s older brother, is generally the manager of landed estate and males exercise most political and economic power. However, gender-based violence (GBV) rates are high in FSM and women are vulnerable to trafficking, illegal sex work, unwanted pregnancies, harassment and violence. Imported and transient workforces such as those required for the construction industry are known to contribute to these issues. For women in FSM there are multiple barriers to having equal opportunities as well as a life free from violence and coercion. Priority areas of the GoFSM national gender planning include addressing female unemployment and a gender-stratified labor market, teenage pregnancy, violence against women and girls and limited access to justice and protection for women. Participation of women at the highest levels of decision making remains very limited and women continue to be highly under-represented at the legislative and executive levels of government. In addition, FSM is one of only three countries worldwide that has zero women in the National Legislature. Sexual Exploitation and Abuse (SEA) and Sexual Harassment (SH) is prevalent in FSM with approximately one in three women (32.8%) having experienced physical and/or sexual violence by an intimate partner in their lifetime. The PRIME Project aims at achieve gender mainstreaming in its design, management and implementation. Early and continuing stakeholder engagement under ESS10 is vital to addressing gender gaps, and gender mainstreaming will ensure that barriers to participation of women are taken into account. Additionally a specific SEA and SH Grievance Mechanism is currently being developed by the DoFA Centralized Implementation Unit (CIU) which will be implemented for the PRIME Project. 3.4.1.3 Indigenous Peoples WB ESS7 is relevant as the overwhelming beneficiaries of the Project in each State (Kosraean, Mehn Pohnpei, Chuukese and Yapese) meet several characteristics of indigenous persons as described in the ESF of the WB. Given this, it is considered that the ‘indigenous’ population of FSM is comprehensively represented in all state mechanisms, December 2020 Final 11 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan will not be disproportionately disadvantaged by the Project and, as such, an ‘Indigenous Peoples Plan' is not required under ESS7. Engagement will be undertaken in a culturally appropriate manner and language for the indigenous peoples of each State (e.g. Kosraean, Mehn Pohnpei, Chuukese and Yapese), The Project will assess and document Indigenous Peoples’ natural resource use and land claims, and will be gender inclusive including specifically consider women’s role in the management and use of these resources. December 2020 Final 12 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 4. Stakeholder Identification and Analysis 4.1 Stakeholder Identification 4.1.1 Approach to Stakeholder Identification In order to develop an effective SEP, it is necessary to determine who the stakeholders are, understand their needs and expectations for engagement and their priorities and objectives in relation to the Project. This information can then be used to tailor engagement to each type of stakeholder. As part of this process it is particularly important to identify individuals and groups who may find it more difficult to participate and those who may be differentially or disproportionately affected by the Project because of their marginalised or vulnerable status. It is important to understand stakeholder’s interests and how they may be affected – or perceives they may be affected – so that engagement can be tailored to inform them and understand their views and concerns in an appropriate manner. As part of this process it is particularly important to identify individuals and groups who may find it more difficult to participate and those who may be differentially or disproportionately affected by the Project because of their marginalized or vulnerable status. For the PRIME Project, stakeholders have been and will continue to be identified throughout the duration of the Project on a continuing basis by identifying: • Various stakeholder categories that may be affected by, or be interested in, all aspects of the PRIME Project including technical assistance (e.g. VA/CRSS), physical works and institutional strengthening; and • Specific individuals, groups, and organizations within each of these categories taking into account: o The expected Area of Influence (AOI) of Component 2 works, that is the socio- economic and geographical area over which it may cause impacts (both positive and negative) over its lifetime, and therefore the localities within which people and businesses could be affected, and o The nature of the impacts that could arise and therefore the types of national/local government entities, NGOs, academic and research institutions and other bodies who may have an interest in these issues. The process of identifying stakeholders is continuous. 4.1.2 Project Area of Influence The initial description of the Project’s Area of Influence (AOI) is based on the definition provided in the Guidance Note to ESS1, to which the Project is to comply. Specifically, this Guidance note states that: “….Where the Project involves specifically identified physical elements, aspects, and facilities that are likely to generate impacts, the collection and analysis of environmental and social baseline information and data, at an appropriate level of detail for the Project, are essential to define the Project’s area of influence and describe relevant physical, biological, ecological, socioeconomic, health, and labor conditions, including any changes anticipated to occur in the foreseeable future (including projected variability in climatic and environmental conditions due to December 2020 Final 13 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan potentially significant climate change or that would require adaptation measures that could occur over the life of the Project), along with current and proposed development activities within the general Project area but not directly connected to the Project to be financed…..” The area considered for the identification of stakeholders (the Project AOI) consists of the: • Road corridor adjacent to the ‘PRIME Roads’ (and area of works where it is a bridge or causeway) and immediately adjacent environment either side of the road alignment; • Road users and communities connected to and by the PRIME roads; • Any temporary structures (such as bridges, causeway replacement structure, etc); • Receiving environment downstream (and upstream when considering fish passage) if the works are a bridge (or causeway) or works are related to drainage, culverts etc; • Contractors yards, lay down or stockpile areas, and any other works related facilities; and • Quarry locations and immediate surrounds. Table 4-1 outlines the guidelines that have been followed to determine the AOI for the PRIME Project which is based around a precautionary approach. All data was obtained by desktop study and field survey conducted between July and October 2020. Table 4-1: Project Area of Influence (AOI) delineations and conditions Environment Project AOI Local villages / communities / Adjacent to PRIME Road alignments and works locations. businesses Connected to and by the PRIME Road network. Road users (motorists, cyclists, Users of the road that may have access or transportation restrictions pedestrians and other modes of from the works if they are not adequately managed. transport) Users that will benefit from improved infrastructure. Important species habitat Sensitive ecological areas in close proximity to the PRIME Road alignments and works locations potentially receiving runoff during construction / operation. Streams & inshore waters Assuming a precautionary approach, an area directly adjacent to the (adjacent to coastline) PRIME Road alignments and works locations potentially receiving stormwater runoff during construction / operation. The AOI extent considered in the SEP is broader than the area in which possible physical works/interventions will occur as Component 2 works will only be undertaken along small discrete sections (<10%) of the ‘primary roads’ identified a part of the ‘PRIME Roads’. However all road users that rely on the road networks for work, education, markets, community and social connectivity will potentially be affected by, and benefit from the Project. The broader AOI has been applied for the stakeholder identification in order to ensure the process is inclusive of all anticipated stakeholders. Any site-specific environmental and social assessments to be prepared, if required, are to define the AOI specifically for those works in order to identified works specific stakeholders, December 2020 Final 14 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan based on the works footprint including all ancillary components and potential impacts on environmental, economic and social resources. 4.1.3 Key Stakeholders Identified To date, a large number of potential stakeholders have been identified from: • Contacts that DoTC&I has already made with communities, government departments and other organizations as part of its public consultation, disclosure and government- level interactions; • DoTC&I’s implementation of land acquisition/resettlement and community development consultations; and • Consideration of the AOI insofar as it is currently defined. The stakeholders pertaining to affected communities have been identified by means of the following inputs: • Stakeholders identified and consulted in previous DoTC&I projects for similar schemes in FSM; • Understanding of the key features of the social baseline of the communities in each State including each of the four urgent works locations; and • Inputs and advice from the FSM-based E&S Consultant team members. Non-community stakeholders have been identified by means of the following: • An initial review of the administrative system of FSM; and • Inputs and advice from the FSM-based E&S Consultant team members. Initial stakeholders identified as part of the PRIME Project ESA are outlined below. 4.1.3.1 National-Level Stakeholders The following national level stakeholders have been identified as being appropriate to engage with regarding the PRIME Project: • Project Partners: o Department of Transportation, Communications and Infrastructure (DoTC&I) o Department of Finance and Administration (DoFA) o World Bank Regional Office • Other Government Departments: o Department of Resource and Development (DRD), including  Division of Marine Resources  Division of Land Management o Department of Health and Social Services, including  Division of Youth & Social Affairs  Division of Women’s Affairs December 2020 Final 15 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan o Department of Environment, Climate Change and Emergency Management (DECCEM) o Department of Justice o National Police o Public Information Office o Ministry of Labor • National Agencies / Authorities o National Fisheries Corporation o National Oceanic Resource Management Authority (NORMA) o Telecommunication Regulatory Authority (TRA) o Environmental Protection Authority (EPA) • Non-Governmental Organisations (NGO)/ Community Based Organisations (CBO) o Pacific Adaptation to Climate Change o Micronesia Conservation Trust o Sustainable Fishers Group 4.1.3.2 State-Level Stakeholders The Project Stakeholders identified at the State level for each of the four FSM States (including Kosrae, Pohnpei, Chuuk and Yap) are outlined below: • Government Departments/Authorities: o State Governor’s Office. o State Senators and Legislature. o Department of Resources & Development (including Division of Marine Resources and Division of Land Management). o Land Commission (or State relevant delegated authorities). o Office of Transportation & Infrastructure. o Department of Health. o Department of Education. o Department of Youth and Civic Affairs (including Historical Preservation Office, and Division of Media & Protocol). o Environmental Protection Authorities (EPA) and Kosrae Island Resource Management Authority (KIRMA). o Relevant Municipal Governments. • Communities Groups: o Traditional leaders and/or councils of chiefs. December 2020 Final 16 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan o Project affected villages. o Road users (commercial, private, motorists, pedestrians, cyclists and other modes of transport). o Church leaders and/or groups. o Women’s Council / Associations / groups. o Youth Council / Associations. o Senior Citizens Organizations. o Farmer’s Association. o Private landowners and land users (e.g. PAPs). o Schools. • Public Utilities: o FSM Telecommunications Corporation. o FSMTCC (OAE) Cable Corporation o State Public Utilities Corporation. • Other Groups: o State Chamber of Commerce. o Private Sector / companies / business owners-operators in close proximity to the works. o Relevant NGOs / CBOs. o Any other key stakeholders identified relevant to the works. Further specific stakeholders will be identified once the specific Component 2 works have been defined. December 2020 Final 17 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 5. Stakeholder Engagement Approach 5.1 Project Preparation Stakeholder Engagement Activities For Project preparation, engagement and consultation, activities were led by the ESA consultant (supported by DoTC&I state representatives and the CIU Safeguards Team as appropriate) and specifically related to explaining the components, implementation arrangements and the E&S aspects of the PRIME Project. Consultation activities were undertaken consistent with the cultural and social norms and values of each State. The ESA consultant team included State-based team members in each State to ensure the most appropriate approach for communication and engagement of identified stakeholders was undertaken (including meeting types, language use, materials presented and circulated, consultant times and locations etc). Given the diverse and extensive range of stakeholders identified (refer Section 4.1.3), consultation meetings were held by stakeholder type, and typically included the following: • Joint Government Stakeholder Meetings – included meetings/workshops for each State attended by representatives of various State government departments/offices/agencies/authorities and their relevant subordinate divisions /offices. Note for Pohnpei, national government stakeholders were also included in this meeting. • Joint Public Stakeholder Meetings – included public meeting/workshop attended by representatives of relevant community groups (e.g. traditional leaders, community groups) and other stakeholders (such as public utilities, NGOs, Chamber of Commerce etc). • Separate One-On-One Meetings – undertaken with specific government and public stakeholders where key stakeholders were in attendance in the relevant joint meeting, or for data gathering purposes. The State-based ESA consultant team members contacted stakeholder groups via phone and/or email and sent a formal letter to the key stakeholder representatives (prepared by either DoTC&I, Governors' office or the ESA Consultant, as appropriate) requesting attendance at the joint meetings. An agenda and a Project Summary Document (provided in Appendix A) was also circulated along with invitation letter so that stakeholders understood the purpose of the meeting in advance and were able to prepare. During the joint consultation meetings, a powerpoint presentation communicated information to stakeholders about the scope and nature of the Project and an opportunity was provided for stakeholder feedback for inclusion into the development of the E&S management framework documents. Given English is widely understood (both written and spoken) throughout FSM (being the official language of FSM), presentations and consultation materials were prepared in English. However, presentations were presented in the local State language (e.g. Kosraean, Mehn Pohnpei, Chuukese and Yapese) where appropriate depending on the stakeholders present during the meeting. Two rounds of broad stakeholder consultation activities were undertaken as part of the ESA Project preparation stakeholder engagement activities and various smaller December 2020 Final 18 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan consultation activities were undertaken where specific issues and topics required engagement or discussion. The two broad rounds of stakeholder consultation included: • First round (August to October 2020) – during the baseline assessment phase ESA to: o Inform key Project stakeholders of the upcoming PRIME Project; o Acquire information to develop E&S framework documents; and o Record stakeholder feedback, opinions and concerns to assist in developing the draft environmental and social assessments and instruments. • Second round (November 2020) – undertaken following the development of the Project Appraisal Document and nearing completion of the draft environmental and social risk management instruments to: o Update on the progress, status and timing of the PRIME Project; o Report back on outcomes of the ESA baseline assessment; o Outlining the key principles of E&S framework documents and ‘strategies’ proposed to screen and manage possible environmental and social impacts from any Project works; o Obtain comment and feedback on the strategies for inclusion in the final draft E&S instruments, prior to public disclosure; and o Allow the stakeholders an opportunity to be engaged in the development of these documents and management decisions for the Project. Given Covid-19 travel restrictions (refer Section 1.2.1.1) consultation meetings were facilitated by the State-based ESA consultant team members. While initial efforts were made to allow relevant members of the international ESA consultant team to call into larger meetings via online video conferencing, internet connection was not reliable enough for this approach to be successful in most cases. The FSM-based team was provided with training and consultation material (including presentation, Project Summary, agenda, meeting minutes template and attendee lists) by the international ESA consultant team members prior to the meetings. This was undertaken to ensure consistency in the messages being communicated to stakeholders across all four States, to ensure valuable feedback was provided and to manage stakeholder expectations. An internal debrief meeting was then held after the meeting to discuss any issues raised by the stakeholders and learnings from the process. The presentations used during both the first and second round of Project preparation consultation are provided in Appendix B. Following the consultation activities, meeting notes were prepared with photographs and attendee lists attached which outlined key feedback to be incorporated into the assessments and instruments. These notes also documented comments, suggestions, clarifications and other information collected during meetings. An overview of stakeholders engaged in each State as part of Project preparation are outlined in Table 5-1. December 2020 Final 19 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Table 5-1: Stakeholders engaged with in each State during Project Preparation (July to November 2020) National Stakeholders State Stakeholders Engaged Stakeholder Type Engaged Yap Chuuk Pohnpei Kosrae Department of Office of Planning and Chuuk Governor’s Office Pohnpei Governor’s Office Kosrae Governor’s Office Transportation, Budget Communication & Infrastructure Department of Finance & Department of Youth and Department of Office of Transportation Department of Administration Civic Affairs Transportation & Public and Infrastructure Transportation & Works Infrastructure Environmental Protection Yap State Legislature Environmental Protection Environmental Protection Department of Finance & Agency Agency Agency Administration Department of Resource & Department of Public Chuuk Planning Office Department of Youth and Kosrae Visitors Bureau Development (Division of Works & Transport Civic Affairs (Office of Land Management) Social Affairs) Government Departments / Offices / Department of Resource & Department of Resource & Department of Resource Agencies / Authorities Development (Commerce Development (Land & Economic Affairs (Land & Industry Division) Management Division) Management Division) Department of Resource & Department of Public Department of Resource Development (Land Safety & Economic Affairs Management Division) (Fisheries Department) Chuuk Visitors Bureau Office of Fisheries and Department of Health Aquaculture Department of Agriculture Kitti Municipal Government Department of Education Disaster Coordination Madolenihmw Municipal Kosrae Port Authority Office Government Department of Justice U Municipal Government Kosrae State Legislature (Immigration & Labor Division) December 2020 Final 20 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan National Stakeholders State Stakeholders Engaged Stakeholder Type Engaged Yap Chuuk Pohnpei Kosrae Chuuk Department of Malem Municipal Public Safety Government Department of Marine Lelu Town Municipal Resources Government Land Commission Office Tafunsak Municipal Government Chuuk Public Affairs Utwe Municipal Government Department of Land Court Administrative Services Chuuk Department of Kosrae Island Resource Education Management Authority (KIRMA) Chuuk Department of Division of Historic & Health Services Preservation, KIRMA Chuuk Sanitation Office House of Representatives, Chuuk State Legislature (House of Representatives & Senate) FSM Congress, Northern Nomoneas Region Tonoas Municipal Government Weno Municipal Government Weloy Municipality Weno Traditional Chief/ U Municipality Presidents of Municipal Community Groups Traditional Chief Village Representative Hamlets December 2020 Final 21 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan National Stakeholders State Stakeholders Engaged Stakeholder Type Engaged Yap Chuuk Pohnpei Kosrae Gagil Municipality Chuuk Women’s Council Pohnpei Senior Citizens Kosrae Women’s Traditional Chief Association Association officers Tamil Municipality Chuuk Youth Council Kosrae Youth Traditional Chief Development Association Yap Women’s Association Kosrae Senior Citizens Association Kids of Ruuq Community Civil Society of Kosrae (KORC) Youth Group 10x village chiefs (as part Kosrae Special Parent of Council of Pilung) Network Council of Pastors Malem Church Pastor Lelu Church pastor Walunga Malem Hamlet Community Health Malem Resource Management Committee Lelu Town Resource Management Committee Tafunsak Resource Management Committee Utwe Resource Management Committee Yap State Public Service FSM Telecommunications FSM Telecommunications FSM Telecommunications Public Utilities Corporation Corporations Corporations Corporations December 2020 Final 22 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan National Stakeholders State Stakeholders Engaged Stakeholder Type Engaged Yap Chuuk Pohnpei Kosrae Chuuk Public Utility Corp Pohnpei Utilities Kosrae Utilities Authority Corporation FSMT Cable Corp. Yap Chamber of Chuuk Conservation Kosrae Chamber of Commerce Society Commerce Yap Small Business Gender Based Violence Kosrae Consumers Development Center Program-Inepwinau Organization/lnter-Agency Counselling Center Committee Other Yap Red Cross Chuuk Chamber of Aquaculture Center Commerce (MMME) Adaptation Fund Project Micronesia Red Cross (Kosrae Chapter) December 2020 Final 23 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan A total of 108 separate stakeholder groups were engaged as part of the Project preparation engagement activities across the four States, including: • National – 4 Government; • Kosrae – 17 Government; 15 Communities groups; 7 ‘Other’ stakeholders; • Pohnpei – 10 Government; 2 Communities groups; 2 ‘Other’ stakeholders; • Chuuk – 22 Government; 3 Communities groups; 6 ‘Other’ stakeholders; and • Yap – 4 Government; 12 Communities groups; 4 ‘Other’ stakeholders. Differences in the number of certain types of stakeholders engaged in each State are in part due to how organized and engaged certain stakeholder groups are in each State, and how effective community leaders were in bringing the stakeholders together. Additional effort may be required during Project implementation to engage certain stakeholder groups if they are identified as being potentially impacted by the physical works. A total of 42 consultation meetings were conducted from 30-Jul-2020 to 12-Nov-2020 across all four States. A summary of key feedback and comments received from stakeholders during Project preparation consultation meetings are outlined in Table 5-2 including a response as to how the issues raised are addressed by the Project. A detailed breakdown of stakeholder engagement and consultation activities, including persons, locations and dates, key purpose and outcomes is of meetings provided in Appendix C. Detailed meeting notes from these meetings are provided in Appendix D. December 2020 Final 24 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Table 5-2: Summary of combined key feedback and comments received from stakeholders during Project preparation consultation meetings. Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Kosrae Joint State Kosrae DoT&I; • Accuracy of the Primary Road extent shown, and extent of • Agreed during meeting that KIRMA to provide additional sections to Government Governor’s Office; roads to be assessed as part of the PRIME Project, including ESA Consultant that they thought should be included, and DoTC&I Meeting Infrastructure Planning and Implementation Committee (IPIC) / WB to be consulted and follow up. DoFA; Primary Road Network Map, and Adaption Fund road • The extent of the roads included were determined by DoTC&I in DoREA (Land segment in Malem. Sep-3, 2020 Management & consultation with State stakeholders and WB. Fisheries • What are the types of physical works required to enhance • Physical works proposed to be developed as part of VA/CRRS Development climate resilience in Kosrae? studies. Divisions); • Agreement by stakeholders that improvement of Lelu • Existing resources, data and information will be understood to Kosrae Port Authority; Causeway was the highest priority for Kosrae, and that it was inform prioritization of certain physical works (e.g. Kosrae Shoreline Department of appropriate for this to be identified as an ‘urgent’ work. Management Plan, which identifies coastal erosion areas). Education; • Appreciation of engagement, and readiness for continued • This is the start of the engagement process, and there will be many Department of Health; engagement going forward. more opportunities to be involved throughout the Project duration. Kosrae State Legislature; • Concerns of local capacity to undertake a review of the E&S • Agreed that State stakeholders would be provided an opportunity to documents being reviewed, and whether this responsibility review these documents prior to finalization. Kosrae Visitors should only be left up to national stakeholders, such as • DoTC&I and DoFA CIU to undertake detailed review of documents Bureau; DoTC&I, CIU. on behalf of GoFSM. KIRMA; Historic Preservation; • Reservations about sharing GIS data that local authorities • Agreed during meeting that GIS data needed for the PRIME Project FSMTC; (e.g. KIRMA) have spent a lot of time and effort compiling, was to be shared with the ESA Consultant. and wanting surety that the data would not be shared beyond • GoFSM to remain ultimate owners of the data being compiled and Kosrae Utilities the needs of the Project. Authority; collected. Lelu Mayor’s Office; • Request for compensation for use to data to be raised with DoTC&I for follow up. Malem Mayor’s office; Tafunsak Mayor’s • Distribution of funds provided by WB for the Project, and how • Concern acknowledged during meeting, and stated that this topic office; much would be allocated to Kosrae. General feeling that would be raised with DoTC&I to follow up. Utwe Mayor’s office. Kosrae is often disadvantaged by national Project’s due to the • Respective funding to each State to be based on need of works in size of the State. that State. December 2020 Final 25 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Joint Community Governor’s office; • Accuracy of the Primary Road extent shown, and extent of • Governor and DoT&I Director clarified during the meeting that and ‘Other’ Kosrae State roads to be assessed as part of the PRIME Project, including funding for the Adaption Fund road segment in Malem is already Stakeholder Legislature; inclusion of the Adaption Fund road segment in Malem. secured (i.e. from another source) and will not form part of the Meeting PRIME Project. Malem Church; Kosrae CoC; • Many sections of road in State that are degraded and require • Physical works proposed and prioritized, to be developed as part of Sep-4, 2020 improvement to enhance climate resilience. VA/CRRS studies. Aquaculture Center (MMME); • Road easement clarifications, including i) duration (expiry • Agreed during meeting that DoT&I Director to follow up with Land Civil Society of dates) of existing easements, ii) are the easements valid if Management office on status of easements, and to get a legal Kosrae; current landowners did not sign (i.e. signed by previous land opinion from the Attorney General’s office. Lelu Church; owners). Adaptation Fund • Lelu Causeway discussions, including current and potential • Generally understood that the existing causeway is resulting in Coordinator; environmental and social impacts. environmental impacts currently. This is in part a reason why Lelu Walunga Malem o Water quality and ecological concerns regarding causeway has been identified as an urgent works. Hamlet; current operation of Lelu Causeway, and that • ESIA/ESMPs to be developed and implemented to manage Community Health; improvements are required. potential environmental and social impacts from construction Project Management o Potential environmental impacts on reef adjacent to activities associated with Lelu Causeway improvements. Office; Lelu Causeways due to construction activities during • Acknowledge local sentiment regarding cultural and historical value Kosrae Women improvement, and request for an ESIA to be undertaken of existing causeway. Request for preserving the bridge if possible, Association; prior to commencement of construction. should be considered as part of ‘participatory design approach’ o Lelu Causeway is culturally and historically significant, during preliminary design. Senior Citizens; in part because it was built by local people used local DoT&I; resources. Request for investigation as to whether KIRMA; preserving the bridge if possible, rather than full Council of Pastors; removal, and local signage to identify local significance. Micronesia Red • Provision of GIS data and support undertaking field survey • While support from Red Cross staff was not necessary during field, Cross- Kosrae (Red Cross Society), if required. the offer was acknowledged and appreciated. • Important that different sectors of community are engaged • Comment acknowledged during meeting, and appreciative of throughout the Project, and enthusiasm regarding Project and enthusiasm. future involvement and consultations. • Agreed, hence the reason for the development of a SEP to ensure all key stakeholders (including local communities) are identified and appropriately engaged throughout Project. December 2020 Final 26 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present • Selection process of works in each State to be determined by • A range of stakeholders to be engaged during the VA/CRRS both national and State leadership and representatives, and a process to ensure range of inputs and ideas are considered in range of stakeholders (not just government officials). terms of priorities in each State. Joint meeting with Governor’s office; • Implementation of Physical Works • Comments acknowledged and responses provided during meeting, Government, Department of o Will implementation of the physical works be the same including: Community and Resources & for all four States, or will progress by one or more o Allocation of fund determined by implementation costs. ‘Other’ Economic Affairs States affect the implementation schedule for the other Stakeholders o Project is developing a framework to ensure resettlement (DREA), Division of States. issues are adequately addressed. Fisheries; o Want to ensure that delays in other States will not o An RFP has been issued for Lelu Causeway, with the scope Nov-9, 2020 Department of Health penalize Kosrae in terms of timing of construction. to include identification of costs of undertaking the works. Services; o Consensus that there is a need to improve and build • An email was circulated post-meeting by the ESA consultant Department of climate-resilience in Kosrae, and stakeholders ready to addressing each of these points identified for follow up in more Finance & provide support the Project. detail, including: Administration; o Desire for works Kosrae is keep on track and not miss o Physical works – “There will be a process for selecting, Department of any opportunities for improvements under this Project screening and designing each physical works, which will be Education; due to delays. independent for each State i.e. hold ups in one State will not Department of • Scope of Project Roads result in delays in other States (as long as funding is Transportation & o Again questioned by only part of the Primary road on secured, which is what our work is for), so Kosrae will not be Infrastructure; Kosrae was included under PRIME (e.g. Utwe to disadvantaged in that regard. The urgent works identified FSMTC; Wailung), and that other secondary roads recommended (i.e. Lelu causeway) will be the first works to be assessed, Historic Preservation in 1st meeting were not included. designed and implemented. What I would say though is that (KIRMA); depending on the scale of works proposed further o Desire that even if actual physical works will not be environmental and social assessment may be required (i.e. Kosrae Visitors undertaken on these road sections, they should be an ESIA) prior to any works commencing which can take Bureau; included in the VA/CRRS studies. time. The urgent works in other States are likely to have Project Management o Wanted assurances that concerns raised previously smaller scale impacts than Lelu Causeway, and may move Office (PMO); were actually considered. through the screening, assessment and design phases Overseas • Would the Project budget be allocated evenly amongst the faster, so my be implemented sooner. But it is still too early Development States, or based on respective needs of each State. to have an accurate idea of respective timing”. Assistance (ODA) • How will physical works be determined (i.e. who will decide if o Scope of Project Roads – “The roads identified are the result office; works with high E&S risk is part of Project, i.e. determine that of consultation and negotiation between national and State Malem Mayor; it is ‘essential’ work). governments. The ESA consultant had no part in this. There is only so much funding, and hard decisions will • Will there be budget for resettlement costs? December 2020 Final 27 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Civil Society of • Concern regarding Project timeframe, and whether the have been made at a higher level. Also just because they Kosrae; GoFSM was pursuing other sources of funding for road are not captured under PRIME does not mean they may not Kosrae Utilities improvements in Kosrae. be included under other funding arrangements, as it is Authority; • Stakeholders hoped that physical works would begin earlier understood talks are underway with a number of donors (e.g. than 2022. ADB, China etc) for similar funding arrangements in the Kosrae Youth future. Questions regarding inclusion of road sections from Development the State leadership to be directed to DoTC&I for further Association; discussions”. Kosrae Women • Respective budget in each State to be based on need of works in Association that State, rather than even split. • Prioritization of physical works to be determined as part of a multi- criteria analysis (MCA) which will form part of the VA/CRRS. This MCA will include consideration of E&S risks. • Provision budget is to be set aside for securing land access for works (should it be required). • A thorough process is required in order to ensure robust assessment and design of physical works, including mitigating potential impacts. This takes time. Generally urgent works are expected to be the first project to commence construction (or at least to begin the assessment/design process). Pohnpei Joint meeting with DoTC&I; • Enthusiasm regrading Project, and government to work • Comment acknowledged and enthusiasm appreciated. Government, EPA; collaboratively (including National, State and Municipal) to Community and identify areas of the road network that require improvement Social Affairs Office; ‘Other’ Stakeholders Department of • Options to minimize dredging/mining of reef for construction • Dredging/mining of the reef will not be recommended for the Resources & material. Project. Roading material is to be sourced from appropriately Development; • State Government needs to boost enforcement of licensed quarry sites. Sep-17, 2020 Pohnpei Senior environmental laws and regulations, as most development • Concern regarding enforcement by State government Citizens; projects do no abide by management requirements. acknowledged. FSMTC • WB requires robust mitigation and management measures to be developed, and will ensuring monitoring is undertaken (including provision of adequately resources to manage these aspects of the December 2020 Final 28 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Project). Regular reporting to WB is required, and any issues identified will be followed up and resolved. • Distribution of funds provided by WB for the Project to be split • DoFA CIU responded during meeting that funding as per works evenly across States or as required depending on physical requirements, with works proposed on an ‘as need’ basis on works. primary road in each State starting with identified ‘urgent works’ (e.g. Awak Bridge in Pohnpei). • Knowledge sharing between departments a common issue • Comment acknowledged, and understood that knowledge sharing and challenge, and hopeful that PRIME Project can support between departments and States can be a challenge (as a common standardization of national and State protocols. issue internationally). • Establishment of a Project Implementation Unit (PIU) with resources in each State will ensure that the Project is suitably coordinated and managed, including managing relationships and communication between stakeholders. • Collaboration with Green Climate Fund (GCF) to unify • DoTC&I State focal point (and EPA) responded during meeting that assessment efforts. no reason why the GCF cannot unify with PRIME Project, and worth investigating to include GCF in future assessments. • Can Asian Development Bank (ADB) fill funding gaps for • DoTC&I is already working with ADB and other bi-lateral interventions along transport network. investments in expand physical works needs identified as part of the PRIME VA/CRRS. Joint meeting with DoTC&I; • Will this Project include road markings, as these deteriorates • Road Safety audit to be undertaken which will include assessment Government, T&I; quickly in Pohnpei due to high rainfall. of lighting, road markings and signs. Community and EPA; • Maintenance mechanism already in place for Pohnpei, • Comment and concern regarding seeing actual benefits from ‘Other’ Stakeholders Social Affairs Office; including tax increase to cover this, but haven’t seen any infrastructure projects acknowledged. Department of Public improvements. • This Project is being funded by WB, an international donor, Safety; therefore no tax increases will be required to fund PRIME. Oct-12, 2020 Office of Fisheries • During previous assessment in 2019 was Pehleng bridge • VA/CRRS will assess all bridges and culverts on the primary road and Aquaculture; examined? networks. Kitti Municipal • 2x bridges at Pehleng included in supplementary request from Government; ADB, so unlikely to require funding under WB funded PRIME. December 2020 Final 29 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Madolenihmw • Will hydrology, including rainfall and stream flow be • Yes, VA/CRRS will consider historical rainfall an future trends for Municipal considered as part of assessment of Awak Bridge the road network, including rainfall, seal level rise, landslide prone Government; areas and other climate threads. U Municipal Government; • Public utilities corporation and Telecommunications Corp. • Comment acknowledged. needs to work closely with T&I to ensure no utilities and • Coordination between stakeholders is critical, and FSMTC are a U Municipality; networks are interrupted as a result of construction works. key stakeholder that will be involved in the design process to Pohnpei Utilities minimize the risk of disruption to services, and impacts on the Corporation community. Joint meeting with State Governor’s • Comments by Governor: • Comments acknowledged and discussed during meeting. Government, Office; o Suggested by the Governor, that consultations • Governor to work closely with State partners to ensure communities Community and Department of undertaken for the VA/CRRS to take place in the and land owners are involved in stakeholder consultations, ‘Other’ Finance & respective Municipalities. including locating future meetings in Municipalities to increase Stakeholders Administration; engagement and attendance. o Pohnpei Transportation Authority (PTA) to be Madolenihmw designated entity to lead construction work, with any • Existing work to standardize design to be incorporated and Nov-10, 2020 Municipal other interested/qualified Contractors to go through a considered during PRIME design process. Government; bidding process. • PRIME will involve extensive stakeholder engagement, and EPA; o Some previous road improvements were poorly easement negotiations. Being WB funded means that PRIME will Department of designed (i.e. inadequate drainage and culverts), not be undertaken as per DoTC&I standard practice, as required to Resources & resulting in damage). Work is underway to standardize adhere to WB ESS. Development; roading projects. • E&S risks and impacts will be incorporated into PRIME process Nett District • Comments by Mayor of Madolenihmw Municipal Government: (including planning, design and implementation). Government; o 4x ongoing road improvement projects in Madolenihmw, • DoFA CIU have resources purely to adhere to E&S safeguard Kolonia Town and no stakeholder consultation undertaken for them (by requirements across the donor portfolio of works in FSM. A PIU Government; DoTC&I, T&I or local government); will also be established for PRIME to managed and implement PSQ; o Some of the projects were designed that required road Project. So each State department does not require specific Social Affairs Office; easement negotiation, but that never took place; resources to conduct assessments and consultation. But they will o E&S aspects are often undervalued due to urgent be actively engaged in the process. T&I; projects between donors and State government; • T&I and PTA will be engaged during VA/CRRS prioritization Overseas process to ensure sites they consider to be high priority sites are Development o Municipal governments don’t have means to conduct assessments and consultation, and will require a considered. Assistance (ODA) office. stronger partnership between State and National December 2020 Final 30 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present government departments to ensure smooth • Framework documents to be publicly disclosed and an opportunity implementation, community awareness and cooperation. will be provided for stakeholders to provide comment and feedback o Need to revisit easement laws to ensure they are into the contents of these framework documents. reflected strongly in the development and management • Physical relocation not expected as a result of the Project, and frameworks. impacts to land/assets and communities will be minimized where • Comments by Director of DRD: ever possible. o Important for T&I and PTA to provide their priority projects, so can easily align when donor funds become available; o Important to have own government people involved with people drafting the framework documents, so not committed to something can’t deliver; o Maintenance is the issue with infrastructure. Often lack maintenance plan to sustain roads o Look forward to draft frameworks to make sure they reflect capabilities to implement projects • Comments by Nett District Administrator: o Need to work closely with State Legislature to consider viable and effective resettlement options. Nett and Sokehs Municipalities are close to Kolonia and population is becoming dense. Chuuk Joint meeting with FSM Congress, • Chuuk Conservation Society is interested in understanding • We have been collaborating with NGOs, Chamber of Commerce, Government, Northern Nomoneas the safeguards instruments for this Project, to ensure they are Chuuk Women’s Council and Chuuk Youth Council. Community and Region; consistent with current environmental and social efforts. • NGOs will be engaged going forward. ‘Other’ Weno Municipality; Stakeholders • Scope of Project assessment • Primary roads are the main focus as access to communities still Chuuk Sanitation o Sapuk badly needs road rehabilitation. need a functioning primary road. Office; Aug-28, 2020 o Please assess Mwan to Neauo, and Wichap to Epiupw, • The extent of the roads included under PRIME were determined by as roads badly deteriorated. DoTC&I in consultation with State stakeholders and WB. December 2020 Final 31 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Weno Municipality o Will secondary roads be included under Project Office/Council; assessment. Weno Traditional • Need to ultimately complete the circumferential road around Chief/ Village Weno. Representative. • Clarification regarding engagement/communication process, • ESA consultation starting this process, including an initial survey. and who will be doing the assessments. Will be more focused once the works have been identified. Many of these assessments will be undertaken by PIU/CIU, with support from external S consultants if required. • Are you working with the utility companies? Is there • Yes CPUC and FSMTC are Project stakeholders/partners and will collaboration? be engaged throughout Project. • Please coordinate with CPUC, including possible joint • CPUC and FSMTC have been working closely with ESA consultant negotiation to provide access to water resources in Wichen, to provide utility GIS data. Peniesene. • Other current and proposed projects to be understood and • A number of donor funded projects include utilities (e.g. solar consulted with where appropriate (including both donor and GoFSM array – WB, deep wells – UNDP, water and sanitation – ADB funded projects). etc). • Community support and engagement. • Stakeholders that need to work with are being identified, and will be o Important to get as much community support and refined once works proposed. involvement as possible. This has been a problem with • These type of projects (i.e. WB funded) come with conditions, and if past Projects. stakeholders and communities are not involved or unwilling then o As soon as land owners/community leaders see everyone loses the benefits of these projects. developments starting they put price tags on access to • Important that all stakeholders are involved and engaged, such as their property. this meeting of Chiefs, so that important messages can be explains o Important that we give communities support so they can to communities, including Project benefits. reap long term benefits of these Project’s. • Limited timeframe for this stage of the Project , but there will be o Based on experience with ADB Project , land disputes opportunities for communities to be more directly engaged going are a major issue e.g. CPUC/ADB water resources forward as part of this Project. Project in Peniesene, which has now been side lined as • Understanding community feedback is important as part of the a result. environmental and social assessment, including negative feedback. December 2020 Final 32 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present o This is an opportunity for communities to get development assistance, and the Project depends on community willingness to get involved o Community engagement helps to educate on the importance of collective benefits. o If communities don’t cooperate or aren’t involved, this could prevent engagement for future development projects. • When Weno Project in Mwan was undertaken, • There were recommendations to climate proof the ADB project, but engineers/contractors resulted in environmental problems, funding didn’t allow recommendations to be accommodated (e.g. including impacts on watercourses, stagnant water flooding raising road level, drainage etc) Taro crops. Please consider proper drainage during Project • Term ‘climate resilience’ is important, and all of these considered design, to avoid damage to farmland, taro, and flooding etc. are to be taken into account during design, including drainage, flood, erosion etc). • All the environmental and social data being collected are to identify areas that the designers need to consider. • Is there a time limit for how long easements are in place for? • Easements are only along road reserves that have been agreed upon. Community is to be involved infield surveys and meetings regarding easements. • ESA consultant and State focal points are trying to help Weno communities secure the grant for these improvements. • Different government administrations come and go, but • Main focus is on the primary road around Weno, as this is typically haven’t seen important changes that benefit people. Need to where climate resilience is most required (i.e. coastal) or where key support these types of Projects so that development infrastructure is located. assistance can be provided, for everyone’s benefit. • Road improvements are essential for development, and people need access to resources and services. • Also need assistance on roads into villages, not just primary roads. Joint meeting with • Will the PRIME Project only focus on primary roads, or will • Roads to be included in VA/CRRS are based on economic/strategic Government, secondary roads also be improved. West Pou Road need, and will include West Pou Road. Primary roads are mostly December 2020 Final 33 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Community and Department of (secondary road) needs most improvement, and heavily considered as these are typically where critical infrastructure is ‘Other’ Transport & Public congested. located. Stakeholders Works; • Integration with other infrastructure plans and funding: • IDP has identified road network in Weno as priority, and some Governor’s office; o Infrastructure Development Plan (IDP) currently exists elements (such as conceptual design of circumferential road) has Sep-3, 2020 Commerce & Industry; which considered environmental and social impacts. been completed. It’s just a matter of securing funding for the Land Management; The IDP has not yet been implemented. Will this be works. Chuuk Conservation IDP be considered in terms of upcoming development • Need to scale up concept designs has been identified, and the Society; projects. importance of environmental and social data gathering and o China is currently committed to providing funding for development of framework documents being undertaken under Chuuk Planning PRIME will feed into these designs and will inform other donor Office; Weno road. funded projects. Chuuk Public Utility o IDP is an official document for the State, and any projects should follow the programs identified under • This Project belongs to Chuuk State and FSM, through their Corp.; IDP. respective lead agencies. It is not the ESA consultants role to Chuuk Visitors Office; select priority investments. This is the responsibility of State and o Several projects and sources of funding. These should Chuuk Women’s all be combined/coordinated, with funds allocated for National GoFSM. Council; non-Weno islands. Disaster Coordination o Need consistent clarity on State plans, not just react Office; when opportunities arise. Need a collective and Department of connect interest. Agriculture; • Has there been coordination between national, state • Scoping and consultation has been ongoing over the past year, and FSM Immigration & government and WB when selecting roads the scope of concept design were considered. Labor; Project ? Or is this a foreign initiative disconnected from the • E&S gap analysis highlighted that a lot of information gaps still Chuuk Department of needs to Chuukese people? remain. These gaps need to filled to be eligible for funding. Public Safety; • Chuuk State decided and selected urgent works. Works in Chuuk Department of Marine should have been included in the Chuuk Road Project, but included Resources; under PRIME as funding needed to be provided in each State for EPA; this Project. Land Commission • Project identified by President of FSM, who met with WB to request office; funding. Chuuk Public Affairs; • Funding will be provided under other donor’s for works that will not be funded under PRIME (i.e. ADB, China etc). Coordination is required in order to FSM to accomplish roading needs. December 2020 Final 34 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Department of • Hope to see future development projects spread to other • These projects came from President’s ‘Pave the Nation’ initiative. Administrative islands. Services; • Receiving this feedback is what this engagement is for, so that your o Given PRIME only focuses on Weno, hope that ADB ideas, thoughts and suggestions can be taken into account (and not Chuuk Youth Council; funded works don’t just focus on Weno, as then other just a foreign initiative). Chuuk Department of infrastructure identified in IDP will not be undertaken. • WB maritime project visited other islands in 2018, so WB and Education; o Other islands in Chuuk, outside of Weno, are in DoTC&I have a good understanding of conditions in other islands. Chuuk Department of desperate needs of development. Lack of road • The extent of the roads included under PRIME were determined by Health Services; infrastructure impact peoples access to services, such DoTC&I in consultation with State stakeholders and WB. Gender Based as school. Violence Program- o Concern that Weno is overfunded, as currently multiple Inepwinau infrastructure development projects focused on Weno. Counselling Center; o How does this Project benefit all of Chuuk, if only Chuuk State funding for Weno. Legislature; o Please include Tanoas in the development plans, as Chuuk Chamber of there is a range of infrastructure there that requires Commerce; upgrades (e.g. roads, docks, industry etc). Tonoas Municipality. • There are plans by Department of Commerce and Industry to develop Tanoas, to take pressure of Weno. • CPUC has current funding under ADB for water and sewerage • Comment acknowledged, and extent an prioritization of roads and systems, under disaster risk reduction funding. Are utilities works will form part of VA/CRRS. included are part of the PRIME Project. It would be difficult to complete loop for power utilities right around Weno without road access. The missing section of road should be a State priority • Section of road between Mwan to Neauo should be prioritized as it adds economic benefit (e.g. Tourism, connectivity etc). • Any findings from environmental and social assessment? • Update on E&S baseline study provided during meeting. • ESA to inform the ESMF and other instruments has been completed and has been compiled in a Baseline Resource Report, which is appended to the ESMF. This will be publicly disclosed along with the other E&S instruments. December 2020 Final 35 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present • Need to coordinate our efforts, especially regarding road • Road easement documents along whole primary road in Weno to easements. Chuuk is often identified as being behind in start to be compiled in anticipation of works, so can better terms easement information (e.g. only Tanoas has more than understand gaps for this Project, and for other projects currently 50% of land titles secured). The rest of the islands have a lot focused on Weno. of land documents missing • The planning and designing of works will emphasize participatory design process. Land owners and land users adjacent to proposed works areas as well as community and traditional leaders will be consulted on proposed design options and their feedback incorporated in to preliminary and final design. Any modification to the road footprint along with any displacement of property with associated mitigation should therefore be acceptable to affected persons regardless of degree of completeness of easement agreement documentation. • As part of beautification of Weno project, leaders encouraged • Any structures that will be impacted by the Project will be improving roadside fences. Will this be an issue for impacts relocated/moved at a cost of the Project. on people adjacent to the road near works. Joint meeting with Governor’s office; • Question regarding disclosure of draft E&S framework • Clarified purpose of meeting was to outlined strategies for Government, Commerce & Industry; documents. Request for draft documents to be shared with feedback, prior to completion of draft docs. Draft and final Community and stakeholders by a Project representative when they are ready. framework docs would then be publicly disclosed. Department of Marine ‘Other’ • The more information we provide stakeholders with, the • Agencies were very helpful and we gathered a lot of useful Resources; Stakeholders higher quality feedback that can be obtained during information. Identified that land easements were available along Chuuk Public Utility Corp.; consultation meetings. urgent section of road (Airport to Pou Bay Bridge), but work needed Nov-12, 2020 • Status of baseline survey and data gathering? to scan all documents required from Land Management office. This Land Management; will be critical once all the works have been identified. EPA; • Will West Pou Road be included in the Project? Why I it classified as a secondary road. • Lt Governor answered during the meeting that while it may not be Chuuk Conservation included for physical works under PRIME, assessment of this road Society; • Importance of collaboration between different projects. CPUC will be under the Project, and works on this road may be has 2 projects ongoing, one funded by ADB (water and undertaken under another package of works. sewage facilities) and one funded under WB (solar plant at Mechitiw). Both of these will be affected by PRIME, with the • The E&S assessment completed to date is just the start of a series ADB project commencing next year. of studies under PRIME that will determine the scope of work. • Urgent works (airport to Pou Bay Bridge) to include utilities, • Emphasized the importance of stakeholder meetings and the water and sewerage? ‘participatory design approach’. December 2020 Final 36 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present • Query regarding timeframes (i.e. detailed design within 2 • Clarified during meeting that these projects do take time to years?). Maritime project is approved but will not see any adequately assess, design and mitigate impacts, but project physical work within the next 5 years in Chuuk. Has exact timeframe is limited. start and end point of urgent works established. • Objective of current phase of PRIME is to secure funding. After • Conservation society appreciated being involved. Queried that assessments and works can be undertaken independent of one which of the four States will start works first, or will they be another (i.e. hold ups in Pohnpei should not affect Chuuk). undertaken simultaneously? Will Chuuk be affected by delays • Urgent works determined by earlier scoping by DoTC&I in in other States? consultation with State stakeholders and WB. While other sections • How were the urgent works selected? Why is the Airport to of road may have more economic significance, the selected section Pou Bay Bridge Road limited to less than 2 miles of road? of road fits PRIME’ objective the most (i.e. needed the most climate Due to funding limitations? proofing). Yap Meeting with State Planning Office; • Two urgent works bridges proposed (‘Manta Bay’ bridges) • Comments acknowledged. Council of Pilung EPA; must consider an alternative detour route within Nimar village, • Planning of works will prioritize minimization of property losses. (Chiefs) to avoid commuters needing to go via loop road. Participatory design approaches will ensure that designs along with PMO Resident Engineer; • Request to minimize destruction of gardens and taro patches any property losses and respective mitigation measures are Aug-14, 2020 Chief of Weloy along northern road, and if such resources are destroyed acceptable to affected persons. Municipality; without alternatives then mediation will be required with land owners. Chief of Gagil Municipality; • Request for assistance in relocating waterline that runs under portion of existing Gagil Road before construction taking place Chief of Tomil on northern road i.e. to outside of the ‘gutters’. Municipality. • Request to meet with potential Contractors, and be involved with selection of Contractors. • Would like to choose a member of their own municipalities to be their eyes and ears in the government focal group that is administering the Project for information haring purposes. • Would like to be involved in zoom conferences between government agencies and donors, especially on infrastructure projects that take place in respective municipalities. December 2020 Final 37 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Meeting with State Planning Office; • Bridges to officially be referred to as a) ‘Donoech’ rather than • Comments acknowledged, and renaming of bridge projects to be Chamber of EPA; ‘Manta Bay’ bridge, and ‘Doqmathing’ rather than ‘Waab raised with DoTC&I. Commerce (CoC) Hardware Bridge’, so that local names aren’t neglected. • Suitably qualified and experienced international design engineers Civic Affairs; CoC representatives • Bond requirement on contracts for local companies are will be engaged to undertake design, and manage local surveys Sep-15, 2020 unnecessary as i) local companies are poor and cannot afford and assessments. more restrictions, and ii) local companies are owned by • Assessment and prioritization of works requiring climate resilience Islanders and are never at ‘flight risk’. improvements to be determined as part of the VA/CRRS. • Estimate of northern road needs to be precise, and undertaken by certified engineer. To date DoPW&T hasn’t given a clear indication of costs for resurfacing road, repair and extension to Tamor, Tamil and Gachpat, Gagil. Recommended that government work closely with DoPW&T for a thorough cost of northern road • Product quality to closely consider all parties in relation to use of cement, rather than asphalt, based on experience of northern road not lasting 10 years before deteriorating. • Need more education of public on road easements and law to avoid conflicts and interferences based on lack of knowledge. • Government to seriously consider how local contractors can win bids, even if it means subsidising. • Side walk is a major issue around Colonia and should be seriously considered to ensure pedestrians are safe. • Local artists perspective should be sought in designing new works, in order to retain/capture local taste or image of Yap where possible. • Key sections of primary road needing immediate repair include: o Around lagoon (patching needed, elevation from tides and sidewalk) o PTS to Airport (flooding, cracked pavement, uneven and sewer leakage) December 2020 Final 38 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present o Water dam road (excessive flooding even during light rain) o Ayrach Hill-Yyin, Fanif Road (cracked and deteriorating fast, unsafe for drivers when heading downhill) • Other sections of road needing repair: o Gaanelay School road needs pavement to prevent steep drainage into main road intersection causing pavement cracks, and unsafe for drivers. o Proper drainage issue – most areas on primary road do not have proper drainage and are beginning to break/crack between heavy rain and hot sun heating asphalt o Mochoy Road – Crossing Dugor to Adibweq in Weloy. Neglected before. Runs east to west making commuting more convenient, faster and cost effective. Important for access to essential services (hospital, school etc) o Tamil bridge. Been on table for some time. To connect Colonia to Tamil side over the bay. Easier for shorter commutes, emergency situations, school etc o Yap State highway/freeway. Build an island freeway from North-South with exists into respective communities, downtown etc. Would serves as main road in case of inundation or flooding o Mulroo Bridge. Between Ace’s mart 1 store and Aces’ mart 2 store. Needing excavation to free up debris stuck underneath, as well as elevation to prevent inundation during high tide. o Ganir Bridge. Government to undertake immediate repair and enable yachts to anchor inside lagoon • Government to define Primary and Secondary Roads December 2020 Final 39 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present Meeting with Yap State Planning Office; • Need more education of public on road easements and law to • Comments acknowledged during meeting. State Legislature PMO Resident avoid conflicts and interferences based on lack of knowledge. • The planning and designing of works will emphasize participatory (YSL) Engineer; • Northern Road estimate needs to be precise, and undertaken design process. Land owners and land users adjacent to proposed Planning & Budget; by a certified engineer/agency. A maintenance proposal for works areas as well as community and traditional leaders will be Sep-18, 2020 YSL representatives the Project must be projected on a yearly basis. consulted on proposed design options and their feedback • Project reports and stages to be documented and shared with incorporated in to preliminary and final design. YSL. • Safety and continual flow of traffic to be ensured during implementation of projects that commuters are not impacted. • Division of Land Resources to be made aware of all land- based projects to ensure Project operations do not infringe of private property. • Cultural and customary rights of citizens paramount, and focal group should ensure those rights are maintained in all aspects of Project planning. Meeting with Yap State Planning Office; • YSPSC has a plan showing future underground powerline • Plan has been received by State Focal Point (Planning Office) and State Public EPA; alignment along north-south road and Loop Road. Request has been submitted to the Governor for review. Service that this is taken into account for future road works. Civic Affairs; Corporation • Concern that powerlines near FMI and Sports Complex were (YSPSC) YSPSC representatives laid in a difficult location for maintenance (bushes) to provide more space to these facilities. Will these powerlines now be Oct-20, 2020 in the location here the primary road will be one day? Joint meeting with Civic Affairs; • Recommendation for a working group to work closely with • Plan showing YSPSC has been forwarded to Governor and will be Government, Yap Planning & Budget YSPSC regarding power lines next to FMI and sports complex shared with VA/CRRS and design engineers, once engaged, to Community and Office; (as discussed in previous meeting), to ensure primary road ensure it is suitably considered. ‘Other’ Council of Pilung will coincide with current layout. Otherwise they may need to • Enthusiasm appreciated, and stakeholder engagement will continue Stakeholders (including 10x realign the powerlines back to the existing road. throughout the Project, and as outlined in SEP. Municipal Chiefs) • All 10x chiefs gave their blessing for the Project to proceed as Nov-6, 2020 necessary in order to begin as soon as practicable. December 2020 Final 40 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Discussion Topic, comment, feedback Response / Outcome Meeting Present • Group welcomes any future updates to consider, including community meetings, and each member will take responsibility for conveying messages to their respective communities. Joint meeting with EPA; • Request regarding emphasis on proper drainage and • Drainage is an important aspect of designing climate resilient Community and Civic Affairs; sidewalks, especially during rainy days, as can be hard to roads, and will be factored into design. ‘Other’ Yap Planning Office; walk to/from school. • Extent of ‘PRIME Roads’ to be assessed, and from there various Stakeholders • Ganir Bridge is in very poor condition (recommended to works will be identified and prioritized as part of a MCA process. Yap Red Cross; Government to close bridge for public safety). Not • If works are not undertaken as part of PRIME funding, there may be Yap Women’s Nov-12, 2020 considered? other opportunities for works to be undertaken at a later time Association; Kids of Ruuq • When are the secondary roads to be developed? More and through another source of funding. Community (KORC) more people are travelling on them, due to high number of Youth Group; cars being imported to the island. • When will works actually begin? • Consider elevating lower roads, including drainage that shoots onto Taro patches causing damage. • Need to look at number of vehicles being imported to Yap, as more and more cars are arriving, and old cars not being removed. Impacts on both road network and communities. • How is the soil analysis being done for the Project? Ensure poor design wont damage gardens/taro patches. • Appreciative of engagement. December 2020 Final 41 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 5.2 Ongoing Stakeholder Engagement throughout PRIME Project 5.2.1 Ongoing Stakeholder Engagement Scope Stakeholder engagement is to continue throughout the PRIME Project including planning and design, construction, and post construction phases (i.e. operation) off physical works, for all technical assistance (e.g. VA/CRRS), and institutional strengthening activities. All of the stakeholders identified in Section 4.1.3 are appropriate for consideration throughout the Project although additional stakeholders may be identified once the specific TA have been scoped, annual project work plans prepared and Component 2 works and associated activities have been identified. 5.2.2 Component 2 Physical Works Each Component 2 works will have a discrete list of stakeholders identified and engaged with as part of the land access procedure process which will be specifically focused on: • Land Owners and Occupiers – called Project Affects Persons (PAPs) under ESS5. • Local Communities (including nearby or indirectly affected villages, community interest groups, road users etc). • Relevant Municipal and State Government departments and agencies. • Traditional – customary leaders (including groups classified as indigenous peoples under ESS7). • Others (including NGOs, businesses, utility providers etc). A variety of mechanisms will be utilized to consult with the identified stakeholders throughout the Project including: (i) Village meetings involving women, men and youth from communities; (ii) Specific facilitated meetings with PAPs (e.g. land owners, disrupted businesses etc) and community leaders (e.g. village chiefs), regarding: a. ‘Participatory design approach’ during the design phase, commencing with preliminary design development. b. Confirming land / asset ownership. c. Securing land access. d. Negotiating VLD. e. Confirming and providing entitlements. (iii) Separate meetings with specific interest groups, as required (including women, youth, religious, vulnerable households); (iv) Key informant interviews with relevant government staff (e.g. Land Commission, Land Court, Planning Office) and community/traditional leaders; (v) One-to-one socio-economic household survey of PAPs and affected communities (in the event an Abbreviated Resettlement Plan (ARAP) is required); December 2020 Final 42 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan (vi) Participatory Inventory of Losses (IOL survey); and (vii) Informal conversations with passers-by, transport users and other interested parties near the works site. To ensure broader participation, consultations are to be undertaken at venues, times and in language that do not disadvantage any particular groups (e.g. women, or vulnerable households). Other considerations outlined in Section 3.4 should also be taken into account through the stakeholder engagement process for the Project. Vulnerable groups are to be targeted through representative organisations including women, disability and youth associations. Remote communities which are often low income will be included through their traditional (e.g. chiefs) and formal representatives (e.g. senators). Pedestrians and cyclists and other vulnerable road users will be identified through community consultations and observations / surveys. 5.2.3 Stakeholder Engagement and Communication Plan and Schedule The schedule and scope of engagement with the various stakeholders throughout the PRIME Project is outlined in Table 5-3. This SEP and specifically the Consultation Plan is intended to be a ‘live’ document that is updated throughout the Project’s lifecycle to guide the implementation of the Project’s community engagement and communication strategy and changing Project work plans. Works specific or TA specific SEP may be prepared to support the detailed engagement activities required. Following all meetings, meeting notes are to be prepared with photographs and attendee lists attached (with gender details recorded) which outlined key feedback to be incorporated into the assessments and instruments. These notes also documented comments, suggestions, clarifications and other information collected during these meetings. December 2020 Final 43 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Table 5-3: PRIME Project Stakeholder Engagement and Communication Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives PRIME Component 1: Spatial and Sector Planning National DRD, DHSS, Meeting/workshop to be attended • Outline works • Delivery of draft report. Email; Letter; PIU, CIU, Government DECCEM, DOJ, by representatives of various prioritization and Meeting design Departments PIO, MOL national government optioneering (joint); Video engineer / Agencies / NORMA, TRA, departments/ agencies/ process. conference consultant Authorities EPA authorities, and their relevant • Present proposed subordinate divisions/offices. Project works. (Note: Combined with State • Obtain feedback. government meeting for Pohnpei) State Governor’s Meetings/workshops for each • Outline works • Delivery of draft report. Email; Letter; PIU, CIU, Government Office, State to be attended by prioritization and Meeting design Departments Legislature, DRD, representatives of various State optioneering (joint); Video engineer / Offices / DHSS, DECCEM, government departments/ offices/ process. conference consultant Agencies / DOH, DOE, agencies/ authorities, and their • Present proposed VA / CRRS / Road Authorities DYCA, EPA, relevant subordinate Project works. Safety Audits KIRMA, divisions/offices. Municipal • Obtain feedback. Specific letters of invitation to be Governments emailed to stakeholders. • PRIME road network, and State specific works to be discussed for each State. Other As required. Specific one-on-one meetings • Outline works • During development of Phone; PIU, CIU, Groups Could include with other stakeholders groups, prioritization and draft report (if required). Email; Letter; design public utilities, as required optioneering • Delivery of draft report. Meeting engineer airports, or other process. (one-on- consultant groups that would • Present proposed one); Video assist the Project works. conference prioritisation process. • Obtain feedback. December 2020 Final 44 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives • Obtain information/data. All As required. Follow up correspondence with To be determined, Various (as required) Phone, Email PIU, CIU, various stakeholders as required. based on needs at the design time. engineer consultant PRIME Component 2: Climate Resilient Infrastructure Solutions State Governor’s Meetings/workshops for each • Outline scope of • During (before completion Email; Letter; PIU, CIU Government Office, Road Works to be attended by specific road works of) preliminary design. Meeting Safeguards Departments Legislature, DRD, representatives of various State proposed. (joint); Video Team; design / Offices / DHSS, DECCEM, government departments/ offices/ • Obtain conference engineer Agencies / DOH, DOE, agencies/ authorities, and their information/data. consultant; Authorities DYCA, EPA, relevant subordinate E&S KIRMA, divisions/offices. • Update Project consultant Municipal status and schedule. Meeting notification to be via Governments specific letters of invitation to be • Obtain feedback to emailed to stakeholders. inform preliminary design (participatory Preliminary design). Design for Works; E&S Screening Community Community Public meeting/workshop to be • Outline scope of • During (before completion Newspaper; PIU, CIU groups with attended by representatives of specific road works of) preliminary design. Radio; Email; Safeguards specific interest relevant community groups, and proposed (including Letter; Team; design in Project works other stakeholders. specific likely impact Meeting engineer (including Meeting notification to be on community). (public) consultant; indigenous advertised via radio and • Obtain Video E&S peoples). newspaper (if appropriate). information/data. conference consultant • Update Project status and schedule. • Obtain feedback to inform preliminary December 2020 Final 45 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives design (participatory design). • Identify potential PAPs and vulnerable groups. Landowners and Specific one-on-one meetings • Outline scope of • During (before completion In-person PIU, CIU occupiers may be with specific Project affected specific road works of) preliminary design. meeting/s Safeguards directly affected persons/communities who have proposed (incl. • Prior to finalization of Team; design by the Project the potential to have land/asset specific likely impact preliminary design to engineer works. or access impacts as a result of on obtain agreement. consultant specific works. land/assets/access). • Obtain Note: Could require multiple information/data. (ongoing) meetings/ • Update Project discussions. status and schedule. • Obtain feedback to inform preliminary design (participatory design). • Minimize social impacts. • Reach agreement on preferred design option and mitigation/restorative measures. Vulnerable Could either by a part of • Outline scope of • During (before completion In-person PIU, CIU groups/road community meeting/workshop, or specific road works of) preliminary design. meeting/s Safeguards users who could one-on-one meetings if proposed (incl. Team; design be appropriate (i.e. not present, or specific likely impact engineer disproportionately consultant affected by December 2020 Final 46 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives proposed works. able to voice concerns, in public on land/assets/ Note: Could require multiple Pedestrians, meeting). access). (ongoing) meetings/ elderly, minors, • Obtain discussions. cyclists. information/data. • Update Project status and schedule. • Obtain feedback to inform preliminary design (participatory design). • Minimize social impacts. • Reach agreement on preferred approach and mitigation/restorative measures. Public FSMTC, One-on-one meetings with public • Outline specific • During (before completion Email; Letter; PIU, CIU Utilities FSMTCC, State utility providers who may scope of road works of) preliminary design. in-person Safeguards PUC. potentially have infrastructure proposed (incl. meeting/s; Team; design disturbed by the proposed works. specific likely impact Video engineer Note: Could require multiple conference consultant; on utility). (ongoing) meetings/ E&S • Obtain discussions. information/data. consultant • Update Project status and schedule. • Obtain feedback to inform prelim design (participatory design). December 2020 Final 47 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives • Reach agreement for mitigation/restorative measures. Other Chamber of Meeting/s with various other • Outline specific • During (before completion Newspaper; PIU, CIU Groups Commerce, Project stakeholders in each scope of roads works of) preliminary design Radio; Email; Safeguards Private Sector, State. proposed (incl. Letter; Team; design State Public meeting/workshop to be specific likely impact Meeting engineer Note: Could require multiple NGOs/CBOs attended by representatives of on stakeholders). (public) consultant; (ongoing) meetings/ (State and other Project stakeholders in • Obtain Video E&S discussions. National), NAC, each State. information/data. conference consultant AFPC, MERIP, Meeting notification to be • Update Project Airports, Schools advertised via radio and status and schedule. etc. newspaper (if appropriate), and • Obtain feedback to specific letters of invitation to be inform prelim design emailed to key Stakeholder (participatory groups. design). Specific one-on-one meetings with other stakeholders groups, as required All As required. Follow up correspondence with To be determined, Various (as required). Phone, Email PIU, CIU various stakeholders as required. based on needs at the Safeguards time. Team; design engineer consultant; E&S consultant Detailed Design State Governor’s Meetings/workshops for each • Outline design of • During (before completion Email; Letter; PIU, CIU for Works / Government Office, Road Works to be attended by specific road works of) detailed design. Meeting Safeguards Departments Legislature, DRD, representatives of various State proposed (incl. • Prior to finalization of (joint); Video Team; design ESIA/ESMP/Land / Offices / DHSS, DECCEM, government departments/ offices/ specific likely impact preliminary design to conference engineer Access Plans Agencies / DOH, DOE, agencies/ authorities, and their on land/ asset/ obtain agreement. consultant; Authorities DYCA, EPA, access). December 2020 Final 48 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives KIRMA, relevant subordinate • Obtain information / • During (before completion E&S Municipal divisions/offices. data and feedback to of) draft ESIA/ ESMP/ consultant Governments. Meeting notification to be via inform detailed Land Access Plan specific letters of invitation to be design (participatory documents. emailed to stakeholders. design) and ESIA/ESMP/Land Note: Could require multiple Access Plan (ongoing) meetings/ development. discussions. • Identify potential PAPs and vulnerable groups. Community Community Public meeting/workshop to be • Outline design of Newspaper; PIU, CIU groups with attended by representatives of specific road works Radio; Email; Safeguards specific interest relevant community groups, and proposed (incl. Letter; Team; design in Project works other stakeholders. specific likely impact Meeting engineer (including Meeting notification to be on land/ asset/ (public) consultant; indigenous advertised via radio and access). Video E&S peoples). newspaper (if appropriate). • Obtain information / conference consultant data and feedback to Landowners and Specific one-on-one meetings In-person PIU, CIU inform detailed occupiers may be with specific Project affected meeting/s Safeguards design (participatory directly affected persons/communities who have Team; design design) and by the Project the potential to have land/asset engineer ESIA/ESMP/Land works. or access impacts as a result of consultant; Access Plan specific works. E&S development. consultant • Reach agreement for Vulnerable Could either by a part of mitigation/restorative In-person PIU, CIU groups/road community meeting/workshop, or measures. meeting/s Safeguards users who could one-on-one meetings if Team; design be appropriate (i.e. not present, or engineer disproportionately able to voice concerns, in public consultant affected by meeting). proposed works. December 2020 Final 49 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives Public FSMTC, One-on-one meetings with public • Outline design • During (before completion Email; Letter; PIU, CIU Utilities FSMTCC, State utility providers who may specific road works of) detailed design. in-person Safeguards PUC. potentially have infrastructure proposed (incl. meeting/s; Team; design disturbed by the proposed works. specific likely impact Video engineer Note: Could require multiple conference consultant on utility provider). (ongoing) meetings/ • Obtain information / discussions. data and feedback to inform mgmt. plan. • Reach agreement for mitigation/restorative measures. Other Chamber of Meeting/s with various other • Outline design • During (before completion Newspaper; PIU, CIU Groups Commerce, Project stakeholders in each specific road works of) detailed design. Radio; Email; Safeguards Private Sector, State. proposed (incl. Letter; Team; E&S State Public meeting/workshop to be specific likely impact Meeting consultant NGOs/CBOs Note: Could require multiple (public) attended by representatives of on utility provider). (State and (ongoing) meetings/ Video other Project stakeholders in • Obtain information / discussions. National), NAC, each State. data and feedback to conference AFPC, MERIP, inform mgmt. plan. Meeting notification to be Airports, Schools advertised via radio and etc newspaper (if appropriate), and specific letters of invitation to be emailed to key Stakeholder groups. Specific one-on-one meetings with other stakeholders groups, as required All As required. Follow up correspondence with To be determined, Various (as required). Phone, Email PIU, CIU various stakeholders as required. based on needs at the Safeguards time. Team; E&S consultant December 2020 Final 50 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives State Land Specific one-on-one meetings • Discuss process for • After completion of Phone; PIU, CIU Government Commission (or with key State government securing land (e.g. detailed design and IOL. Email; Safeguards Departments delegated departments/ offices/ agencies/ VLD, land Meeting Team / Offices / authority); authorities acquisition/ Agencies / Planning Office; valuation) if required, Authorities Land Court; and asset relocation Municipal or assistance from Governments. works impacts. Community Community Specific one-on-one meetings • Reach agreement on • After completion of Phone; PIU, CIU groups with with key relevant community process for securing detailed design and IOL. Email; Safeguards specific interest groups, e.g. community leaders land (e.g. VLD, or Meeting Team Securing land / in Project works, and land owners/ occupiers. land acquisition) if assistance including required, and asset activities indigenous relocation or peoples and land assistance from owners/ works impacts. occupiers. Public FSMTC, Specific one-on-one meetings • Reach agreement on • After completion of Phone; PIU, CIU Utilities FSMTCC, State with key relevant public utility mitigation/restorative detailed design and IOL. Email; Safeguards PUC. providers with assets potentially measures for Meeting Team impacted by the works. impacted utility infrastructure. All As required. Follow up correspondence with To be determined, Various (as required). Phone, Email PIU, CIU various stakeholders as required. based on needs at the Safeguards time. Team Community Owners of land Specific one-on-one meetings • Assessment of land • Prior to preparatory In-person PIU, CIU and/or assets with key relevant community and/or asset prior to construction activities. meeting/s Safeguards that are groups, e.g. community leaders disturbance (i.e. • After completion of Team; Works temporary and land owners/ occupiers, benchmark). construction/reinstatement Contractor Construction acquired/used asset owners. • Acceptance of of land/asset disturbed, or during condition of construction. reinstatement land/or December 2020 Final 51 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Stakeholder Stakeholders Stakeholder Engagement Topic Stakeholder Milestone Engagement Responsibility Component Type / Scope Engagement Type Activities Objectives asset after temporarily acquired / completion of works. used. Public FSMTC, Specific one-on-one meetings • Assessment of utility • Prior to preparatory Phone; PIU, CIU Utilities FSMTCC, State with key relevant public utility infrastructure prior to construction activities. Email; In- Safeguards PUC. providers with assets impacted disturbance (i.e. • After completion of person Team; by the works. benchmark). construction/reinstatement meeting/s Contractor • Acceptance of of land/asset disturbed, or condition of temporarily acquired / reinstatement utility used. infrastructure after completion of works. All All Public notification of works to be • Outline scope and • Prior to preparatory Newspaper; PIU, CIU advertised via radio and design of road construction activities. Radio; notice Safeguards newspaper (if appropriate), and works. • Regular updates board/sign; Team; notice board/signage in the • Project status and throughout construction. letter Contractor vicinity of the Project works. schedule. drop/door knocking. • Outlining grievance mechanism and providing contact details. All All Specific one-on-one meetings • Reach agreement on Various (as required). Phone; PIU, CIU with aggrieved parties on the corrective action Email; Safeguards submission of a Meeting Team; complaint/grievance. Contractor December 2020 Final 52 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 5.2.4 Information Disclosure 5.2.4.1 Project Preparation The final draft of the E&S Instruments were made available by DoTC&I to key stakeholders in each State to review and provide comment prior to the documents being finalized. The ‘final’ E&S Instruments are to be publicly disclosed on the WB website (www.worldbank.org) as well as relevant FSM government websites (www.dofa.gov.fsm). E&S instruments that will be publicly disclosed include: • Environmental and Social Management Framework (ESMF) • Resettlement Framework (RF) • Stakeholder Engagement Plan (SEP) • Environmental and Social Commitment Plan (ESCP) 5.2.4.2 PRIME Component 2: Climate Resilient Infrastructure Solutions All Resettlement Plans, Environmental and Social Impact Assessments, Environmental and Social Management Plans prepared during Project implementation for road works activities under Component 2 are to be publicly disclosed on the WB website (www.worldbank.org) as well as relevant FSM government websites (www.dofa.gov.fsm). Stakeholders are to be regularly informed and updated on the PRIME Project throughout Component 2 by way of consultation meetings and public notices (e.g. radio, newspaper etc, as appropriate) including: (i) Scope of the works proposed; (ii) Schedule and progress of works implementation; (iii) Land access requirements and procedures; (iv) Entitlements for Project affected persons; and (v) Grievance Mechanism process. Signs and/or notice boards are to also be erected at the works site, which should provide the following information: • Name, address and other contact information for the PIU Project Manager, and Contractor; • Contact points for the Grievance Mechanism; • Project information (objectives, technical information, development schedules etc); • Information of venue (village) and date where a consultation meeting will take place; and • Maps showing location of Project infrastructure in relation to villages. 5.3 Stakeholder Engagement Tools and Materials This SEP will be used in conjunction with stakeholder engagement and community relations management tools including: • Project Summary Documents – For each key stage of the PRIME Project, a Project summary document is to be prepared or coordinated by the CIU to inform December 2020 Final 53 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan stakeholders of the stage of the Project and the purpose of upcoming consultation(s). The Project summary document that was used for PRIME Project preparation phase is provided in Appendix A as an example. Where consultation is focused on specific works an overview of the concept/preliminary design, potential environmental and social impacts and works schedule may be appropriate to be included in this document. • Consultation Materials – Prior to consultation meetings agendas will be circulated to key stakeholders and powerpoint presentation should be prepared (where appropriate). Project summary documents will be used to support these materials particularly in the absence of suitable facilities at the consultation meeting venue to allow the use of powerpoint. • Language: Engagement is to be undertaken in a language appropriate for the broadest comprehension by stakeholders possible. While English is the official language and widely understood (both written and spoken) throughout FSM, each State has an indigenous culture and its own official languages (e.g. Kosraean, Mehn Pohnpei, Chuukese and Yapese), which may be more likely to be better understood amongst community stakeholders. Literacy levels amongst stakeholders should also be considered when undertaking engagement. • Engagement/Meeting Notes – To ensure that an accurate and detailed record of information and views are gathered at every stakeholder meeting consultation meeting notes will be prepared after key stakeholder meetings throughout the Project. Photographs and attendee lists will be attached to the meeting notes. • Grievance Mechanism (Section 6) – Provides a mechanism for communities and affected or aggrieved parties to raise complaints and grievances and allows the Project to respond to and resolve the issues in an appropriate manner. A complaints/grievance register has been developed to record all grievances reported. December 2020 Final 54 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 6. Grievance Mechanism 6.1 Introduction 6.1.1 Purpose and Objectives There is a possibility of grievances arising from technical advisory, design, institutional strengthening, construction or operation impacts from activities associated with the PRIME Project. The primary objective of grievance management is to allow those who believe they are impacted by the PRIME Project including those affected by land clearing or land acquisition for the Project, to express concern/issues and seek satisfactory resolution to grievances they may have relating to Project activities, impacts as well as compensation and assistance measures. Other objectives include: • Receive, evaluate and facilitate the resolution of affected people’s concerns, complaints and grievances about the environmental and social performance and gender issues, including gender-based violence. • Provide an accessible, time-bound and transparent mechanism for Aggrieved Party’s (APs) to voice and resolve environmental and social concerns linked to the PRIME Project. • Address concerns promptly and effectively, in a transparent manner that is culturally appropriate and readily accessible to all APs, at no cost and without retribution (confidentially). • Ensure transparency in all dealings with communities and that redress mechanisms for grievances are clearly spelt out. • A feedback system is in place to ensure that all commitments by DoTC&I, State agencies and the construction Contractors are kept. Grievances may include: • Environmental issues – such as excessive dust or noise generation, accidental spills, Contractor malpractices, excessive vegetation clearance. • Social Issues – such as dissatisfaction regarding land and/or asset disturbance entitlements or valuation, temporary or permanent loss of livelihoods, changes to land access and associated issues, damages to infrastructure due to construction related vibrations or transportation of raw material, noise, traffic congestions, disruption of services, insensitive social interactions by Contractor with local populations, gender based violence (GBV) and other social and cultural issues. Should such situation(s) and/or issues arise, there must be a mechanism through which affected parties can resolve such issues in an efficient, unbiased, transparent, confidential timely and cost-effective manner. To achieve this objective, a Grievance Mechanism (GM) has been developed for the PRIME Project. A separate GM will be developed for the specific labor related issues. This process will be set out in the Labor Management Procedure (LMP) which will be prepared for the Project prior to engagement of the Construction contractor. December 2020 Final 55 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan A specific Grievance Mechanism (GM) pathway over and above the GM processes detailed below will be established for Sexual Exploitation and Abuse (SEA) and Sexual Harassment (SH) complaints for the Project to ensure survivor-centered approaches are applied, including the involvement of local GBV service providers. This SEA and SH specific GM requirements are currently being developed by a consultant on another WB FSM project with the results and recommendations integrated by the CIU Safeguards Team into the projects GM and will be finalized prior to the implementation of the PRIME Project. 6.1.2 Grievance Redress Principles Those that have a complaint or that feel aggrieved by the PRIME Project to be allowed to communicate their concerns and/or grievances through an appropriate process. The GM set out below is to be used as part of the PRIME Project and will provide an accessible, rapid, fair and effective response to concerned stakeholders especially any vulnerable group who often lack access to formal legal regimes. While recognizing that many complaints may be resolved immediately, the Complaints Register and GM set out below encourages mutually acceptable resolution of issues as they arise. The GM is based on the following guiding principles: • Simplicity: procedures in filing complaints are understandable to users and easy to recall. • Accessibility: filing complaints is easy through means that are commonly used by stakeholders, especially by the Project-affected people. • Transparency: information about the system is made widely available to all stakeholders and the general public. • Timeliness: grievances are attended to and resolved in a timely manner. • Fairness: feedback or complaints are validated thoroughly and subjects of complaints are given due process and opportunities for appeal. • Confidentiality: the identity of complainants remains confidential. In addition, the GM has been designed to be a legitimate process that allows for trust to be built between stakeholder groups and assures stakeholders that their concerns will be assessed in a confidential, fair and transparent manner. The GM is to also enable continuous learning and improvements to the GM, through continued assessment to reduce potential complaints and grievances arising. 6.1.3 Eligibility Eligibility criteria for the GM is to include: (i) Perceived negative economic, social or environmental impact on an individual and/or group, or concern about the potential to cause an impact; (ii) Clearly specified kind of impact that has occurred or has the potential to occur and explanation of how the Project caused or may cause such impact; and (iii) Individual and/or group filing of a complaint and/or grievance is impacted, or at risk of being impacted; or the individual and/or group filing a complaint and/or grievance demonstrates that it has authority from an individual and or group that have been or may potentially be impacted on to represent their interest. December 2020 Final 56 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Local communities and other interested stakeholders may raise a grievance/complaint at any time to the traditional and government elected officials. Affected local communities should be informed about the GM and how to make a complaint. 6.2 Grievance Redress Process The GM for the PRIME Project is scaled to the risks and adverse impacts anticipated for the Project. If promptly addressed, and using an understandable and transparent process that is gender responsive, culturally appropriate and at no costs and without retribution, the concerns and complaints of potentially affected people will usually be resolved. The GM process is not a substitute for, or meant to impede access to, regular legal process but provides a simpler mechanism for complaint resolution. The GM will as far as practicable, try to resolve complaints and/or grievances on terms that are mutually acceptable to all parties. When making a complaint and/or grievance, all parties must act at all times in good faith and should not attempt to delay and/or hinder any mutually acceptable resolution. If an Aggrieved Person (AP) is not satisfied with, or has a complaint about, an aspect of the Project (e.g. such as the mitigation or assistance provided) they have the right to lodge a grievance. While every effort should be made to resolve conflicts by mutual agreement of the parties involved, in some cases, arbitration and adjudication on disagreements and conflicts by an external mediator will be required. For consistency, the GM for the PRIME Project is in-line with other GM instruments implemented in FSM under WB funded projects. This GM process is set out in Table 6-1 for grievance redress of social and environmental matters relating to the PRIME Project. Table 6-1: PRIME Project Grievance Mechanism Process Step Process Duration 1 The Aggrieved Party (AP) takes their grievance to the PRIME Project Any time Implementation Unit (PIU) State Focal Point, Contractor, or contact through the FSM DoFA website or email. Relevant case information is recorded (e.g. Grievance Form, maps, notes of meetings, photos, etc). All grievances (both construction and non-construction related, and those related to SEA/SH/GBV) are to be forwarded to the PIU State Focal Point for screening and record keeping. 2 Upon receipt of the grievance the PIU State Focal Point is to screen the Within 1 day of grievance to assess whether it is related to the PRIME Project, and grievance environmental and social issues. lodged Non-eligible grievances (i.e. those not Project related) are then to be referred to the relevant agency to follow up, if appropriate. 3 The PIU State Focal Point will endeavor to resolve any complaint/issue Within 2 weeks immediately, both construction and non-construction related grievances. of grievance If satisfactorily resolved the incident and resultant resolution/corrective action lodged will be logged and reported to the PIU Project Manager, and copied to the Centralized Implementation Unit (CIU) (Program Manager and Safeguards Team). 4 If unsuccessful (i.e. AP is not satisfied), the PIU State Focal Point will refer the AP to the PIU Project Manager and the CIU Program Manager and Safeguards Team to address and resolve the complaint. The proposed corrective action is to be reported back to the AP for agreement. December 2020 Final 57 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Step Process Duration 5 Where the complaint has not been resolved, the PIU Project Manager will refer the grievance to the DoTC&I Project Management Unit (PMU) Manager for his/her action/resolution. The PIU Project Manager will log the details of issue and resultant resolution status (copy CIU Program Manager and Safeguards Team). 6 If the matter remains unresolved, or the AP is not satisfied with the outcome, Within 1 month the DoTC&I PMU Manager refers the matter to the Project Steering Committee of grievance (PSC) for a resolution, cc’ing the PIU Project Manager. The PIU Project lodged Manager will log details of issue and resultant resolution status (copy CIU Program Manager and Safeguards Team). 7 Once the agreed corrective actions are implemented, and the PIU Project Within 1 week Manager notifies the claimant of the result in writing. of resolution 8 If it remains unresolved or the complainant is dissatisfied with the outcome Within 3 proposed by the PSC, the AP may refer the matter to the appropriate legal or months of judicial authority. A decision of the Court will be final. grievance lodged (where possible) or otherwise as agreed between parties during the process. Steps 1 to 5 should be undertaken immediately (i.e., as soon practicable). Where the matter is referred to the PIU Project Manager, a resolution should be sought within two weeks. If unsuccessful and the matter is referred to the Project Steering Committee (PSC), this should occur within a month. The PIU Project Manager shall report back the outcome of the resolution to the AP within one week total of the corrective action occurring. The PIU State Focal Point will be the grievance focal point and receive, record and report on Project related concerns. If the complaint/grievance relates to a Contractor activity, the Project will ensure the Contractor remedies any damage, pays compensation for damage or loss, etc. Use of community leaders and customary methods of conflict resolution is encouraged and utilized if and when appropriate – on a case-by-case basis. A complaints register will be maintained and will show the details and nature of the complaint, the complainant’s name, the date and actions taken as a result of the investigation (outlined further below). Any grievance related to corruption, any unethical practice including human trafficking, GBV, prostitution etc needs to be managed confidentially through the following process: (i) The AP take their grievance to the relevant PIU State Focal Point whom will immediately notify and refer the grievance to the Municipal, State and/or National Police and to a service provider who can support the survivor. (ii) The PIU State Focal Point notifies the PIU Project Manager whom notifies the DoTC&I Project Management Unit (PMU) and CIU (Program Manager and Safeguards Team), ensuring that all personal details are anonymous. (iii) If the grievance includes human trafficking, prostitution and other similar illegal activities of this nature the PIU Project Manager will notify the State and National legal offices (e.g. Department or Justice) and report the incidence. December 2020 Final 58 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan (iv) Resolution of these grievances will be the responsibility of the legal systems within each state and or national agencies as dictated by state and national law. In these cases the Project’s grievance mechanism will ensure the above due diligence is enacted and due process is documented with the grievance given a complaint number and recorded. Confidentiality associated with all criminal cases must be compliant and follow State and National laws. The PIU Project Manager will review and amend the GM process, where appropriate and make adjustments to consultations, the GM, community engagement, Project implementation and other aspects as necessary to avoid future complaints and grievances if and when required. 6.3 Disclosure of Grievance Mechanism It is important to ensure that all stakeholders including local authorities and community members in the vicinity of the identified works are informed of the Project ’s GM process throughout the full duration of the PRIME Project including construction and non- construction components such as during preparation of any works specific management/land access plans, and prior commencement of any civil works. This information should include their rights regarding potential land/asset impacts and environmental degradation, the grievance process, and guidance on relevant steps to lodge a complaint. The Grievance Process is to be introduced during all stakeholder engagement activities and on websites including stakeholder consultation meetings to ensure that all relevant stakeholders are aware of this procedure and the specific steps to be taken for lodging a complaint. The GM, along with key E&S documents (such as frameworks, land access plans, management plans, ESIAs) prepared for the Project will be publicly disclosed on relevant websites (www.worldbank.org and www.dofa.gov.fsm), in draft and final. Prior to the start of construction activities, signs will be erected at the work sites (in the appropriate local language) providing the public with updated Project information and summarizing the GM process including contact person details. 6.4 Record Keeping and Reporting of Grievances 6.4.1 Grievance Record Keeping All complaints or grievances submitted will require the completion of a Grievance Claim Form which will include the following information: (i) Name of the complainant; (ii) Address (including village name); (iii) Name of the person filling in the Grievance Claim Form (if not the complainant); (iv) Full description of complaint issue, including background, sketches and maps where appropriate; (v) Description of the requested corrective action; (vi) Date of grievance submission; and December 2020 Final 59 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan (vii) Signature of complainant, the person filling in the form and the person who received the form. If assistance is required, the claimant can request help with a verbal grievance to complete the form from the Contractor or PIU State Focal Point (where appropriate). Grievances claim forms can also be submitted electronically through the FSM DoFA website or email. Personal details can remain anonymous. Each grievance record is to be allocated a unique number, reflecting year and sequence of received complaint (e.g. 2021-01, 2021-02 etc). Complaint records (letter, email, record of conversation) should be stored together electronically or in hard copy. Each complaint/grievance is assigned a specific person responsible for its management and close out. All grievances (both construction and non-construction related, and those related to SEA/SH/GBV) are to be either directly received by the PIU State Focal Point or forwarded to the PIU State Focal Point (i.e., should grievances be received by the Contractor for construction related complaints). Upon receipt of the grievance the PIU State Focal Point is to screen the grievance to assess whether it is related to the PRIME Project or environmental and social issues. Non- eligible grievances (i.e. those not Project related) are then to be referred to the relevant agency to follow up, if appropriate. If the complaint is related to SEA/SH/GBV, the relevant GM (once developed) is to be followed including the involvement of local GBV service providers. Language barriers and insufficient literacy levels shall also not prevent any persons from lodging a complaint. The Grievance Claim Form shall be written in English and the appropriate language for that FSM State, and disclosed during consultation. Complaints or grievances are to be recorded in a Complaints Register held locally by the PIU State Focal Point with a copy also kept centrally by the CIU Safeguards Team. The register is to clearly indicate whether an issue has been resolved or is still outstanding. The following records generated by this procedure will be stored in hard copy at the PIU State Focal Point office and in electronic format: • Grievance Claim Forms; • Letters of request; • Memorandums of field investigations, consultations and meetings; and • Photographs, maps, drawings. If an issue has been resolved, the register will include the following information: • Completed Grievance Resolution Form; • Action taken (including evidence of action taken, i.e. photographs, receipts, etc.); • Date of resolution; and • Signature of complainant and person responsible for issue resolution. December 2020 Final 60 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 6.4.2 Reporting and Evaluation A report on the status of all reported grievances will need to be provided by the PIU Project Manager to the DoTC&I PMU and CIU Safeguards Team on a monthly basis. This information is also to be included in the Project’s regular reporting requirements to the WB. The scope of this regular grievance reporting shall include: • Total number of complaints/grievances received. • Total number resolved. • Total number under investigation/not yet resolved. • Total number not yet resolved and also exceeds the recommended close out time of 1 month or 3 months. • Short paragraph on any significant grievances currently not yet resolved and any risks to Project implementation. If there are more than 30 complaints/grievances recorded, the PIU Project Manager may decide to investigate any patterns or repetition of issues that need addressing. The PIU Project Manager may decide to get an independent consultant to review and provide advice. 6.4.3 Contact Details Anyone can ask for information on the Project, express a concern, make a complaint (grievance) or get in touch with the Project for any reason. Complaints/concerns can be anonymous and are to be treated confidentially. Specific persons and contact details both nationally and at the State level will be identified as the Project develops, communicated where ever the GM is presented and at suitable locations in the vicinity of physical works, and updated accordingly throughout the Project. . December 2020 Final 61 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 7. Resources and Responsibilities for Implementing SEP 7.1 Stakeholder Engagement Resources and Responsibilities The successful implementation of the SEP requires full participation of Project relevant implementing agencies in collaboration with National, State and Municipal Government Officials. The responsibility to implement all commitments in the SEP along with any works specific procedure plans/reports prepared will be distributed between these stakeholders. The relevant institutional structures to be either utilized (for existing institutions) or established for the PRIME Project including roles and responsibilities are outlined in the ESMF and RF and shown in Figure 7-1. Figure 7-1: Implementation arrangements for the PRIME Project. The management, coordination and implementation of the SEP and its integral tasks will be the responsibility of the Project Implementation Unit (PIU) with support from the Centralized Implementation Unit (CIU) Safeguards Team. The proposed organizational structure and management functions for the stakeholder engagement function for the PRIME Project is described below. While the DoTC&I and DoFA may decide to adapt this structure according to its needs and funding, it is emphasised that the various components listed and described below should be represented in the organizational structure in order to successfully implement the SEP: • PIU Project Manager - responsible for overseeing and coordinating all activities associated with stakeholder engagement; December 2020 Final 62 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • PIU Project Officer - to provide assistance and support to the Project Manager. • PIU State Focal Points – responsible for implementing State level stakeholder an community engagement activities including for specific Component 2 works. • PIU Administration - responsible for the management of all database, document control and logistics activities and integration/support/interaction between with other departments/agencies or projects. • CIU Safeguards Team – responsible for preparing and updating stakeholder engagement plans according to Annual Work Plans, preparing TOR for specialist support where required, support to PIU Project Manager to coordinate and deliver stakeholder engagement and public communications about the projects, GM, environmental and social assessments, support for participatory design approaches etc. • Design Team – responsible for incorporating the principles of stakeholder-led design through participatory design approaches. • Technical Advisors – all consultants are required to implement the SEP in relation to their own work program with the support of PIU and CIU. • Civil Works Contractors – responsible for undertaking stakeholder engagement specific related to physical works construction. 7.1.1 PIU Project Manager and Project Officer The PIU will be initially staffed with a PIU Project Manager and Project Officer based in Pohnpei (National Government DoTC&I) with additional PIU support to be recruited (such as State level or administrative support) as required. The PIU Project Manager will be responsible for working collaboratively with all national level stakeholders and overseeing all State level stakeholder consultation activities with support from PIU State Focal Points. The PIU Project Manager will also be responsible for the following tasks in relation to stakeholder engagement, with support from the CIU Safeguards Team as required, depending on appropriate capacity, skill sets and experience: • Approve the content of any future revisions to the SEP or task-specific or works specific SEP; • Implement and monitor all stakeholder engagement strategies/plans for the Project; • Approve prior to release all materials used to provide consultation information for the Project (such as introductory letters, Project summary documents, meeting agendas, Powerpoint materials, brochures etc); • Approve and facilitate (with support from the CIU Safeguards Team and/or external consultants as required) all stakeholder engagement events and disclosure of material to support stakeholder engagement events in Pohnpei; • Participate either themselves, or coordinate State Focal Points during all face-to- face stakeholder meetings; • Review and sign-off minutes of all engagement events; and December 2020 Final 63 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Oversee the maintenance the stakeholder database. Efforts are to be made to keep stakeholders informed on Project progress including establishing a direct line of communication between to the PIU Project Manager as the key stakeholder contact points. The PIU Project Manager can then direct stakeholder contact to any other appropriate Project implementation groups (e.g. PIU State Focal Point, CIU Safeguards Team, design consultants, E&S consultant and Contractor/s) as appropriate. This direct line of contact to the PIU Project Manager will allow for on-going updates and discussions outside of formal consultation activities and allow for stakeholder concerns and suggestions to be taken into account as they arise. The Project Officer is to provide assistance and support to the Project Manager on the above. 7.1.2 PIU State Focal Points A focal point in each State will be appointed by the PIU to work on and manage day-to-day activities for the PRIME Project including stakeholder engagement such as coordinating implementation of specific Component 2 works. The PIU State Focal Point is likely to be appointed from within the State Department of Transport and Infrastructure (or Department of Transport and Public Works’ in Chuuk and Yap). The PIU State Focal Point will report directly to the PIU Project Manager, and act as the key contact person for stakeholder enquires in each State with oversight from the PIU Project Manager, and CIU Safeguards Team, as appropriate. Any PIU State Focal Points appointed should be suitably qualified with good communication skills to undertake a range of stakeholder engagement activities and be appropriately trained in the needs of the Project. The PIU State Focal Point will also be responsible for the following tasks: • Implement all State level stakeholder engagement related activities for the Project, under the supervision of the PIU Project Manager and CIU Safeguards Team; • Manage the grievance mechanism at the State level, including receiving, screening, resolving for forwarding grievances (e.g. to PIU Project Manager, CIU Safeguards Team or others), as appropriate; • Interact with related and complementary support activities that require ad hoc or intensive stakeholder engagement (community development and land acquisition/resettlement planning and implementation); • Act as mediator between the Contractor and stakeholders; and • Proactively identify stakeholders, Project risks and opportunities, with support from the CIU Safeguards Team, and inform the PIU Project Manager to ensure that the necessary planning can be done to either mitigate risk or exploit opportunities. 7.1.3 PIU Project Assistant The PIU will require a Project Assistant to be recruited to provide support to the Project by ensuring all administrative requirements are managed effectively. Main responsibilities are to include: • Document management, including capture and filing (physical and electronic) of stakeholder documents and records. December 2020 Final 64 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Database management, including: o Continuously update stakeholder information (contact details, organizational details, designation, engagement activities); and o Continuously update grievance information (grievance records, grievance database, agreements, meeting registers). • Logistics management; • Support with arranging accommodation and traveling where required; and • Assist with printing of materials to be used during stakeholder meetings (posters, pamphlets, Project Summary Documents, letters, attendance registers, maps, newsletters etc). 7.1.4 CIU E&S Safeguards Support The CIU Safeguards Team currently undertakes a range of stakeholder engagement activities as part of its WB portfolio responsibilities, and has existing relationships with a many of stakeholders in each State which will be important to utilize for the PRIME Project. In relation to implementation of the SEP, the PIU will require support from the CIU Safeguards Team in particular, for capacity building and E&S technical support throughout the Project and to ensure the SEP is implemented and updated appropriately and is consistent with the requirements of ESS10. The CIU Safeguards Team is to also ensure that vulnerable and disadvantaged, women and those without access to technology (e.g. websites, social media and radio) are also engaged as part of the Project. The CIU Safeguards Team will be responsible for storing data (including grievance records), collating and interpreting stakeholder feedback and providing details to the design team. The CIU Safeguards Team are responsible for reviewing, updating and monitoring the implementation of the SEP, including preparation and oversight of task specific and works specific SEP. The CIU Safeguards Team may need additional social and environmental safeguard support to implement the growing WB portfolio in FSM including the PRIME Project. This could either be by way of engaging external E&S consultants or recruiting State level support (either to support or supplement the PIU State Focal Points). The CIU Safeguards Team will also support with outreach and public communications. 7.1.5 Designers and Technical Consultants These specialists will be responsible for implementing the SEP for their scope of work, and working with the PIU and CIU to ensure the right stakeholders are identified and involved in their work program. They will assist in preparing task specific SEP. Design teams will be involved in participatory design approaches using Good International Industry Practice for stakeholder engagement. 7.1.6 Civil Works Contractors The Contractor engaged to undertake road works construction will be responsible for undertaking stakeholder engagement related to construction of the specific physical works. The scope of stakeholder engagement will be documented in the CESMP and is to include: December 2020 Final 65 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan • Support the PIU State Focal Points in engaging with stakeholders relating to communicating the scope and timing of works (either by attendance at meetings, installation of notice boards, door knocks/letter drops, etc.); • Negotiation with landowners/users in relation to temporary use of land required for construction relation activities (e.g. laydown and storage/stockpile areas, amenities, etc.), and assessment of temporarily used land after reinstatement/restoration to a condition acceptable to the land owner; • Negotiation with landowners regarding relating/reinstalling physical assets (such as fences, walls etc) located directly within the Project footprint; and • Receiving complaints and grievances by stakeholders and forwarding to the PIU State Focal Point during works construction, and resolution of grievances if they are related to the Contractor (in coordination with the PIU). December 2020 Final 66 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan 8. Monitoring and Reporting 8.1.1 Monitoring and Evaluation Monitoring and evaluation is essential to ensure successful implementation of the consultation program as outlined in this SEP and allow the Project to respond to identified issues and alter the schedule and nature of engagement activities to make them more effective. The PIU, with support from the CIU Safeguards Team, will be responsible for establishing a monitoring program that will monitor, measure, and assess the implementation and overall effectiveness of stakeholder consultation and participation activities. The PIU will maintain a database of stakeholder engagement activities including public consultation, disclosure and grievances throughout the Project which is to be made available for public review on request. The following data will be used to monitoring the implementation of the SEP: • Issues and management responses linked to minutes of meetings; • Monthly reports; • Informal feedback from key stakeholder groups; and • Complaints/Grievance Register. The success of the SEP is to be measured by how well it can achieve the overall objective of meaningful and inclusive engagement and consultation with all Project stakeholders. In addition the following key indicators are also to be evaluated: • Level of understanding of the Project stakeholders; • Annual grievances received and how they have been addressed and time taken to resolve; and • Level of involvement of PAPs and vulnerable groups. 8.1.2 Internal Reporting Internal monitoring is to be reported monthly for the separate physical works, consolidated and summarized as part of quarterly monitoring for the PRIME Project. The following stakeholder engagement activities are to be recorded as part of the monthly monitoring report. • Stakeholder engagement activities conducted during each month; • Public outreach activities (meetings with stakeholders and newsletters); • Entries to the grievance register; • New stakeholder groups (where relevant); and • Stakeholder engagement activities planned for the next month, and beyond (where appropriate). . December 2020 Final 67 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Appendix A PRIME Project Summary Document December 2020 Final FSM PRIME Project: E&S Assessment & Instruments Consultation Project Summary Document PRIORITISED ROAD INVESTMENT AND MANAGEMENT ENHANCEMENT (PRIME) PROJECT Environmental & Social Assessment – Summary Document Introduction implementation have not yet been determined. Key initial documents will include: The Prioritised Road Investment and Management Enhancement (PRIME) Project is a World Bank (WB) • E&S Management Framework funded project that will enhance the resilience of the • Resettlement Framework primary road network in FSM to potential climate- • Labor Management Procedures related impacts and natural hazards or events. • Stakeholder Engagement Plan The Project will fund the feasibility, design and construction of a range of physical works on priority • Other documents (e.g. Generic ESMP, E&S Commitment Plan etc). road assets. The scope of works has not yet been determined, but works are expected to largely be The methodology for the E&S Assessment includes: within the existing road corridor, and may include: • Identifying gaps in knowledge and information; • Road improvements and resurfacing; • Filling gaps based on sourcing existing data and • Bridge, crossing and causeway improvements or field data collection in each State; replacement; • Initial Stakeholder Engagement and • Drainage improvements; Consultation to introduce the PRIME Project; • Coastal protection and slope stabilisation; • Develop labour management procedures; • Vegetation and scour protection etc • Prepare the draft E&S Instrument (framework) documents; The initial stage of the PRIME Project is an Environmental and Social Assessment, which will be • Undertake a second round of consultation to present the draft E&S framework documents; undertaken by Argo Environmental Ltd (ARGO). • Finalise and publicly disclose the E&S The next stages will include a Climate Resilient Road framework documents. Strategy (CRSS) and Vulnerability Assessment (VA) which will determine the specific physical works to be Purpose of Initial Consultation undertaken, followed by concept and design for each • Inform key stakeholders of the PRIME Project; sub-project, and site-specific E&S management plans. These studies will be undertaken throughout • Acquire information to develop E&S framework 2020/2021 by other consultants engaged by DTC&I. documents; and • Provide stakeholders an opportunity to express Environment & Social Assessment opinions/concerns, and for these to be taken into account in developing the E&S documents, and Argo Environmental Ltd (ARGO) has been engaged DTC&I management decisions. by DTC&I to undertake the Environmental & Social (E&S) Assessment, and prepare E&S Instruments for Regular engagement with stakeholders by DTC&I WB appraisal. ARGO’s focus is on preparing key and their consultants will be undertaken throughout E&S ‘framework’ documents, as the specific sites for the full duration of the PRIME Project, including specific sub-projects (once known). Version: Rev0 (August 2020) Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Appendix B Presentations from Project preparation consultation meetings December 2020 Final FSM PRIME PROJECT: Environmental & Social Safeguards Assessment and Instruments Initial Stakeholder Consultation Meeting – Sep 2020 Overview of Meeting Agenda » Welcome & Introductions » PRIME Project Overview » E&S Assessment – Purpose and Scope » E&S Assessment – Approach & Methodology » Stakeholder Engagement & Consultation » Next Steps and Timing » Other Matters 2 FSM PRIME Project - Overview » Prioritised Road Investment and Management Enhancement (PRIME) Project is World Bank (WB) funded aimed at enhancing the resilience of the primary road network to potential climate-related impacts and natural hazards or events in all four FSM States (incl. Kosrae, Pohnpei, Chuuk and Yap). » Project will fund the feasibility, design and construction of a range of physical works on priority road assets - expected to largely be within the existing road corridor. » Scope of works has not yet been determined. The following are examples of the types of works expected: • Road improvements and resurfacing/resealing etc; • Bridge, crossing and causeway improvements or replacement; • Coastal protection, slope stabilization, vegetation and scour protection; • Drainage improvements etc » The initial stage of the Project is an Environmental & Social assessment being undertaken by Argo Environmental Ltd » Next stages of PRIME Project will include: • Climate Resilient Road Strategy (CRSS) and Vulnerability Assessment (VA) to determine the specific physical works • Design work for each sub-project (i.e. sites of physical works) • Site-specific E&S management plans to be prepared for discrete sub-projects (once known) » These other studies will be undertaken throughout 2020/2021 by other consultants engaged by DTC&I. 3 E&S Assessment – Scope and Methodology » Argo Environmental Ltd (ARGO), a NZ-based international environmental consultancy has been engaged by DTC&I to undertake to prepare E&S Instruments for WB appraisal. » ARGO’s focus will be on preparing key E&S ‘framework’ documents as the specific sites for implementation have not yet been determined. Key initial documents will include: • E&S Management Framework • Resettlement Framework • Labor Management Procedures • Stakeholder Engagement Plan (incl. Grievance Mechanism) » The methodology for the E&S Assessment includes: • Identifying gaps in knowledge and information • Filling gaps based on:  Sourcing existing data, reports and information  Field survey to collect baseline data  Feedback during stakeholder engagement and consultation • Initial Stakeholder Engagement and Consultation to introduce the PRIME Project • Prepare the draft E&S Instrument (framework) documents; • Undertake a second round of consultation to present the draft E&S framework documents; • Finalise and publicly disclose the E&S framework documents. 4 E&S Assessment – Data Requirements » Currently acquiring data for primary road network including: • General spatial (GIS) data (e.g. road network, topography, basemaps, infrastructure etc) • Environmental and ecological data (including freshwater, coastal/marine and terrestrial habitats & land cover) • Social data (including settlements, land use, sensitive receptors, cultural sites, vulnerable groups, high risk traffic areas) • Legal road easement and land tenure information • Natural hazard & soil and erosion data • Assets or properties encroaching on road easement; land acquisition requirements • Aggregate sources (e.g. quarries) & potential waste material dump sites • Hazardous material or potentially contaminated sites • Stakeholder engagement requirements » We are getting in touch with relevant groups who hold much of this existing data » Where the data doesn’t exist in a usable format, we will be filling gaps during the field survey » A database of the compiled data will be prepared as part of this Project 5 Initial Stakeholder Consultation » Purpose of this initial round of stakeholder consultation • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. » Regular engagement with stakeholders by DTC&I and their consultants will be undertaken throughout the PRIME Projectincluding specific sub-projects (once known) » Draft E&S Framework documents will be presented to stakeholders during consultation in Oct 2020 (TBC) » A grievance mechanism is being developed which provides a mechanism for complaints, issues or disputes to be addressed and resolved. 6 Kosrae – Scope of PRIME Project » The road extent to be considered under the PRIME Project includes: • Primary Road Network + Roads of Strategic Importance » Key initial questions / considerations: • Are there sections of the road where you expect improvements are needed to improve resilience to climate related impacts? • Any other known issues / considerations along the primary road network? 7 Initial Priority Sub-Project (Lelu Improvement) » Initial priority ‘sub-projects’ have been identified by DTC&I (1x in each state) that are likely to be party of the scope of works » For Kosrae this is improving the Lelu Causeway » Any known issues / considerations you would like to raise regarding this causeway? 8 Pohnpei – Scope of PRIME Project » The road extent to be considered under the PRIME Project includes: • Primary Road Network + Roads of Strategic Importance » Key initial questions / considerations: • Are there sections of the road where you expect improvements are needed to improve resilience to climate related impacts? • Any other known issues / considerations along the primary road network? 9 Initial Priority Sub-Project (Awak Bridge replacement) » Initial priority ‘sub-projects’ have been identified by DTC&I (1x in each state) that are likely to be party of the scope of works » For Pohnpei this is replacing Awak Bridge » Any known issues / considerations you would like to raise regarding the replacement of this bridge? 10 Chuuk (Weno) – Scope of PRIME Project » The road extent to be considered under the PRIME Project includes: • Primary Road Network + Roads of Strategic Importance » Key initial questions / considerations: • Are there sections of the road where you expect improvements are needed to improve resilience to climate related impacts? • Any other known issues / considerations along the primary road network? 11 Initial Priority Sub-Project (Airport to Pou Bay Bridge Road Improvement) » Initial priority ‘sub-projects’ have been identified by DTC&I (1x in each state) that are likely to be party of the scope of works » For Chuuk this is improving the Airport to Pou Bay Bridge Road » Any known issues / considerations along this section of road you would like to raise? 12 Yap – Scope of PRIME Project » The road extent to be considered under the PRIME Project includes: • Primary Road Network + Roads of Strategic Importance » Key initial questions / considerations: • Are there sections of the road where you expect improvements are needed to improve resilience to climate related impacts? • Any other known issues / considerations along the primary road network? 13 Initial Priority Sub-Project (Manta Bay Bridges) » Initial priority ‘sub-projects’ have been identified by DTC&I (1x in each state) that are likely to be party of the scope of works » For Yap this is improving/replacing the Manta Bay Bridges » Any known issues / considerations you would like to raise regarding these upgrades to these bridges? 14 Thank You Thank You / Questions? Questions / Comments / Feedback? FSM PRIME PROJECT: Environmental & Social Assessment and Instruments Stakeholder Consultation Meeting – November 2020 Overview of Meeting Agenda » Welcome & Introductions » Brief PRIME Project Overview (Refresh & Update) » Key Outcomes of E&S Baseline Assessment » Overview of Environmental & Social Management Framework » Overview of Resettlement Framework » Stakeholder Engagement and Consultation » Next Steps and Indicative Schedule » Questions / Feedback Purpose of Meeting » To provide an update on progress, scope and timing of the PRIME Project. » To outline proposed key principles of E&S framework documents and ‘strategies’ to screen and manage possible environmental and social impacts from any Project works (once they are identified). » To receive comment and feedback from stakeholders, in order to complete draft E&S framework documents. » To engage stakeholders in the development of these documents and management decisions for the Project. 2 FSM PRIME Project - Overview » Prioritized Road Investment and Management Enhancement (PRIME) Project will provide funds for technical assistance and institutional strengthening to improve the management of the road network in relation to potential climate change impacts anticipated for the FSM. » The World Bank (WB) funded Project will fund feasibility, design and construction of physical works to enhance the resilience of the primary road network to potential climate-related impacts and natural hazards / events in all four FSM States (including Kosrae, Pohnpei, Chuuk and Yap). » The three key components of the PRIME Project include: 1. Spatial and Sector Planning Tools (incl. Climate Resilient Road Strategy (CRSS) and Vulnerability Assessment (VA), road asset management systems). 2. Climate Resilient Infrastructure Solutions (incl. Urgent Priority Works (e.g. Lelu Causeway, Awak Bridge, Airport to Pou Bay Road & Manta Bay Bridges) and other physical works informed by the VA/CRRS studies 3. Strengthening the Enabling Environment (e.g. E&S Frameworks, institutional strengthening, regulatory reforms, capacity building etc) 3 Expected Scope of PRIME Project » Project activities will primarily take place within existing primary road corridors, or immediately adjacent to the road (e.g. improve erosion protection, drainage or safety features). » Both primary roads and some additional secondary roads (of strategic and/or economic importance) will be assessed for climate vulnerability. » Extent of roads included, determined by DoTC&I, in consultation with key State stakeholders & WB » Only works on the primary roads will be funded under the PRIME Project. VA/CRSS improvement recommendations on secondary roads to form part of future packages of work. Yap Chuuk Pohnpei Kosrae 4 Expected Scope of PRIME Project » Scope of physical works are expected to incl. (but not limited to): • Pavement and surface strengthening  Maintenance, repair, rehabilitation or reconstruction of existing road pavement (incl. sealed shoulders and raising road levels) • Drainage improvements  Longitudinal drainage, cross-drainage culverts, outfalls, subsoil drainage and cut-off drains • Spot slope stabilization  Modifications to cutting slope and fill embankments to reduce landslip risk, soil bioengineering and biotechnical stabilization techniques and anchoring of unstable rock slopes • Rock wall revetment strengthening  For protection of coastal road sections • Improvements to causeways and bridges  Repairs/reconstruction of crossings to provide safe, all weather access for vehicles and pedestrians • Road safety improvements  Traffic calming measures, guardrails, line marking and minor realignments 5 E&S Baseline Assessment – Scope and Methodology » The methodology for the E&S Baseline Assessment undertaken by ARGO included: • Identifying gaps in knowledge and information • Filling gaps based on:  Sourcing existing data, reports and information  Field survey to collect baseline data  Feedback during initial stakeholder engagement and consultation (Aug/Sep 2020) » E&S baseline assessment undertaken from Aug-Oct 2020 (now complete) » The following E&S data (either existing data or field survey) has been acquired to inform the PRIME Project, to inform the development of the ESMF: • General spatial (GIS) data (e.g. road network, topography, basemaps, infrastructure etc) • Environmental and ecological data (including coastal/marine and terrestrial habitats & land cover) • Social data (incl. settlements, land use, sensitive receptors, cultural sites, vulnerable groups, etc) • Legal road easement and land tenure information • Natural hazard, soil and erosion data • Key assets or properties encroaching on road easement; land acquisition requirements • Aggregate sources (e.g. quarries) & potential waste material dump sites » A number gaps still exist in the data which have been identified. » A database of the compiled data is being developed to assist with assessing E&S risk. 6 E&S Constraints Mapping (Kosrae) » Data & info collected during baseline resource assessment, informed the development of an E&S constraints mapping exercise for each State. » E&S Constraints mapping identified E&S sensitive receptors (e.g. buildings, structures, infrastructure, protected areas etc) in close proximity to primary road corridor. » Where there are particularly sensitive sites these were identified as part of a risk assessment, in order to inform the VA/CRRS & design » Note: these locations are indicative only and further investigation will be undertaken in the vicinity of specific works sites. 7 E&S Constraints Mapping (Pohnpei) » Data & info collected during baseline resource assessment, informed the development of an E&S constraints mapping exercise for each State. » E&S Constraints mapping identified E&S sensitive receptors (e.g. buildings, structures, infrastructure, protected areas etc) in close proximity to primary road corridor. » Where there are particularly sensitive sites these were identified as part of a risk assessment, in order to inform the VA/CRRS & design » Note: these locations are indicative only and further investigation will be undertaken in the vicinity of specific works sites. 8 E&S Constraints Mapping (Chuuk) » Data & info collected during baseline resource assessment, informed the development of an E&S constraints mapping exercise for each State. » E&S Constraints mapping identified E&S sensitive receptors (e.g. buildings, structures, infrastructure, protected areas etc) in close proximity to primary road corridor. » Where there are particularly sensitive sites these were identified as part of a risk assessment, in order to inform the VA/CRRS & design » Note: these locations are indicative only and further investigation will be undertaken in the vicinity of specific works sites. 9 E&S Constraints Mapping (Yap) » Data & info collected during baseline resource assessment, informed the development of an E&S constraints mapping exercise for each State. » E&S Constraints mapping identified E&S sensitive receptors (e.g. buildings, structures, infrastructure, protected areas etc) in close proximity to primary road corridor. » Where there are particularly sensitive sites these were identified as part of a risk assessment, in order to inform the VA/CRRS & design » Note: these locations are indicative only and further investigation will be undertaken in the vicinity of specific works sites. 10 Anticipated E&S Impacts and Mitigation » Potential General Construction Impacts associated with possible physical works - • Physical and Ecological Environment incl.  water quality & sediment (e.g. as a result of uncontrolled discharges)  terrestrial ecology (e.g. loss of biodiversity & habitat in construction footprints)  freshwater & coastal marine ecology (e.g. loss of biodiversity & habitat in works footprints and from uncontrolled discharges)  air & noise quality (e.g. due to noise from machinery/equipment, dust generation)  hazardous substances and waste management (e.g. uncontrolled use and storage, disposal of used roading material)  aggregate & asphalt suppliers (e.g. ensuring aggregate is sustainably sourced) • Socio-Economic and Cultural Environment incl.  land and asset loss (e.g. within the works footprint – a ‘participatory design approach’ to be adopted, discussed later)  pedestrian & vehicular traffic (e.g. increased traffic movements)  temporary disruption to existing essential services (e.g. power, water, telecom utilities)  potential disruption to archaeology and cultural heritage resources (e.g. within the works footprint – ‘participatory design approach’)  worker / community health & safety » Potential General Operational Impacts associated with possible physical works - • Potential benefits – more resilient roads to climatic events, improved connectivity, more reliable access, reduced travel time, enhanced safety of road users, etc » Environmental & Social Impacts – typical road related impacts (e.g. stormwater, traffic, safety etc) » Specific potential impacts will be identified and assessed, and mitigation measures developed, once the physical works have been identified. 11 Environmental & Social Management Framework » Purpose of ESMF is: • To examine the risks and impacts of a project when it consists of a program of works (i.e. the risks cannot be determined until the works have been identified). • Once the VA/CRSS studies have defined the physical works, the framework will guide development of E&S mgmt. plans and impact assessments for the specific works. » The key elements of the ESMF include: • Baseline resource assessment and E&S constraints mapping • E&S impact and risk assessment • E&S screening process for prioritization of works, inform design, and determine what ESIAs/ESMPs are required for each works » Works with ‘High’ E&S risks (that require costly/intensive management and mitigation) may be evaluated as being a lower priority for inclusion under the PRIME Project (i.e. may not be included unless essential). » Project emphasis on ‘participatory design approach’ to minimize E&S impacts. • Involves detailed consultations with communities and landowners during design phases (iterative process). • Communities and landowners presented with objectives of road improvements (e.g. water drainage issues), general design options and implications/impacts, for feedback, preferences and acceptance. 12 E&S Risk Screening - ESMF 1. Initial E&S Risk Screening • identifies potential high-level E&S risks and impacts 2. Detailed E&S Screening • preparation of ‘E&S Screening Report’ as part of the preliminary design process. 3. Further redesign of the works • to avoid/minimize E&S impacts, land and/or asset loss, where practical. 4. Implementation of a Generic ESMP • minor E&S impacts with works largely within the existing road easement. 5. Preparation and implementation of a works specific ESIA and ESMP • moderate or high E&S impacts are expected, and not suitably captured in Generic ESMP. 13 Resettlement Framework » Purpose of Resettlement Framework is: • To ensure Project Affected Person (PAPs) are provided with suitable assistance to maintain (or improve) their pre-Project living standards, livelihood, and income earning capacity. • Once the VA/CRSS studies have defined the physical works, the framework will guide development of land access plans for the specific works. » The key elements of the RF include: • Outline principles to address any land/asset/livelihood impacts • E&S screening process for prioritization of works, inform design, and determine what Land Access Plans/Reports are required for each works • PAP eligibility and entitlements • Process for securing land (if required) • Outline complaints and grievance process to resolve disputes and complaints from PAPs 14 Resettlement Framework – Key Project Principles » Minimization of impacts: • Works kept to existing primary road corridors however some minor realignments of existing roads or road assets (e.g. bridges, causeways) may be included if technically required. There will be no new alignments to roads. • Severe land/asset/livelihood impacts will not be included (e.g. relocation of housing, permanent severe livelihood impacts/land acquisition etc) • Design of prioritize works that have temporary impacts that can be easily mitigated. • Works will adopt a ‘participatory design approach’ with the respective landowners, users and communities to minimize social impacts. • Disruption to businesses will be avoided, and access maintained, where ever possible. » Securing land access for Project works outside of road easement will be through either voluntary land donation agreement/negotiation or land acquisition (e.g. for minor road adjustment or works such as installation of new culverts or drainage improvements). » Physical assets/structures will be relocated and/or reinstalled, where ever possible (e.g. fences, walls, minor structures etc). If not possible/viable, a like-for-like replacement or compensation at replacement cost will be provided (e.g. fruit trees, crops etc). » Consultations and public participation will be ongoing throughout PRIME Project (e.g. planning, design, implementation, construction and post-project etc). Affected people and communities in the vicinity of works will be given advance notice of planned works schedules. 15 E&S Risk Screening – Resettlement Framework 1. Initial E&S Risk Screening • identifies potential high-level E&S risks and impacts 2. Detailed E&S Screening • preparation of ‘E&S Screening Report’ as part of the preliminary design process. 3. Further redesign of the works • to avoid/minimize E&S impacts, land and/or asset loss, where practical. 4. Preparation of either: • Land Access Due Diligence Report – in the event of no anticipated land/asset impacts, OR • Voluntary Land Donation Report – impacts to land/assets but donation agreement/negotiation reached, OR • Resettlement Plan – impacts to land/assets and compensation required. 16 Stakeholder Engagement and Consultation » Regular engagement with stakeholders throughout the full life of the PRIME Project • Undertaking by Project team (incl. DoTC&I, DoFA, State representatives, Consultants) • Will include both overarching, and works specific, consultation » Emphasis on ‘participatory design approach’ • Local communities / affected landowners participate in design decisions related to road improvements that affect them. • Road improvement designs will prioritize works within the corridors of existing primary roads, and minimize the loss of private property, where technically feasible. » Stakeholder Engagement Plan: • Presents and describes the stakeholder engagement activities to be undertaken throughout the full duration of the PRIME Project including outlining the ‘participatory design approach’. • Is a dynamic document that will be periodically examined and updated where relevant throughout the Project. » Grievance Mechanism : • Outlines a process for addressing and resolving complaints/grievances raised throughout the Project. » Key Project documents, including E&S Framework documents (currently under preparation), will be publicly disclosed (both draft and final versions). » There will be lot of opportunities to be involved in this Project, and to express opinions, concerns etc (we are only starting this process!) 17 Next steps and Indicative Schedule Project Stage Responsibility Approx. Timing Initial stakeholder consultation, E&S baseline assessment, and development of GoFSM / ARGO 2020 (nearing E&S Framework documents (ARGO) completion) Public disclosure of Draft E&S Framework documents (WB/GoFSM) GoFSM / WB Dec 2020 Public disclosure of Final E&S Framework documents (WB/GoFSM) GoFSM / WB Early 2021 VA/CRRS studies to determine specific physical works proposed under PRIME GoFSM / Early-mid 2021 Consultant (TBC) Preliminary design work for each physical works, including ‘participatory design’ GoFSM / Late 2021-2022 consultations Consultant (TBC) E&S screening and management plans prepared for physical works GoFSM Late 2021-2022 Detailed design for each physical works GoFSM / ~2022 (TBC) Consultant (TBC) Commencement of construction activities GoFSM / TBC Consultant (TBC) Stakeholder engagement and consultation throughout Project GoFSM / Ongoing Consultant (TBC) 18 Thank Thank You / Questions? You Questions / Comments / Feedback? Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Appendix C Summary of stakeholder engagement activities during Project preparation December 2020 Final PRIME Project Preparation (ESA) CONSULTATION SUMMARY – KOSRAE Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation KIRMA Administrator, Mr. Meeting with KIRMA to KIRMA Administrator, Mr. Telephone One-on-one July 30, KIRMA Maps Submitted to Blair Charley discuss maps and GIS data Blair Charley & Andy meeting 2020 Office E&S Consultant requested by Argo. George KIRMA Administrator, Mr. Meeting to go over gap KIRMA Administrator, Mr. Telephone One-on-one August 21, KIRMA KIRMA agrees to Blair Charley table and discuss need to Blair Charley & Andy meeting 2020 Office compile available access existing GIS data George GIS data but soon from KIRMA to emphasize the support the PRIME project. need to protect these data and not use them for any other purpose State other than the Government PRIME project. Departments Andy George, State focal Meeting to discuss first Andy George, Osamu Email & Team meeting August 26, Governor’s Team agreed to / Offices / points, Director Livaie, & round of consultation Nedlic, Betty Sigrah, telephone 2020 Chief of have the governor Agencies / Governor’s Chief of Staff meetings with state and Director Livaie, & Nena Staff’s sign off on the Authorities Mr. Nena William community leadership and William office invite letters to all support for field survey. stakeholders and provide venue for the meeting. Andy George, State focal Meeting to finalize plans for Andy George, Osamu Email & Team meeting September Governor’s Official invite letter points, Director Livaie, & first round of consultations Nedlic, Betty Sigrah, telephone 01, 2020 Chief of for state and Governor’s Chief of Staff and approve draft agenda, Director Livaie, & Nena Staff’s community Mr. Nena William go over presentation, William office leadership along finalize logistics for both with Agenda meeting days (Thursday drafted and and Friday), and review approved by team primary road network map FSM PRIME_Consultation Summary_Kosrae 131120 Page 1 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation for Kosrae provided by ARGO in the presentation Office of the Governor, First round of consultation Governor’s office, Lt. Official Invite Meeting - September Governor’s Refer Meeting Office of the Lt. Governor, with State government Governor, KIRMA, letter from (Govt. joint) 03, 2020 Conference Notes Department of leadership to: Historic Preservation, the Room Transportation & • Inform key Kosrae Visitors Bureau, Governor’s Infrastructure, Department stakeholders of the PRIME Fisheries Development, office of Finance & Project Department of Health, Administration, Department Kosrae State Legislature, • Acquire of Resource & Economic Department of Finance & information to develop E&S Affairs with the divisions of Administration, FSMTC, framework documents Land Management & Malem Municipal Mayor, Fisheries Development, • Provide Lelu Town Mayor, Kosrae Port Authority, stakeholders an opportunity Tafunsak Municipal Department of Education, to express Mayor, Department of Department of Health, opinions/concerns to be Education Kosrae State Legislature, addressed in developing Kosrae Visitors Bureau, the E&S documents and DTC&I management KIRMA, Historic decisions. Preservation, FSMTC, Kosrae Utilities Authority, Office of the Lelu Mayor, Office of the Malem Mayor, Office of the Tafunsak Mayor, Office of the Utwe Mayor, Andy George and Blair Meeting to again Blair & Andy Telephone One-one-one September KIRMA Blair commits to Charley emphasize the need to 23, 2020 office start compiling access the GIS data from information this week and share. FSM PRIME_Consultation Summary_Kosrae 131120 Page 2 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation KIRMA soon as dateline is First Zip folder approaching. received. Land Court Staff Meeting to receive copies of Land Court Clerk of Telephone One-on-One September Kosrae Standard Rules of the Land Court Standard Court and secretary 24th, 2020 Land Court Procedures Rules of Procedures for received. land acquisition, registration, and adjudication and inform the Land Court staff about the PRIME project Andy George & Lupalik Meeting to inquire about Andy & Lupalik Telephone One-on-one September Land Copy of a Wesley (Division of Land road easement and 24th, 2020 Manageme document Management, DREA) potentially get copies of the nt office “Government easement Access Use Right”. A request has been sent to the AG’s office to draft a letter to show that the document is a legally-binding document. Director Hairom Livaie, Meeting to discuss the Director Hairom Livaie, telephone One-on-one October DT&I Office Email sent to Department of location, size of quarry (i.e., Department of meeting 16, 2020 ARGO indicating Transportation & extractable volume, Transportation & Mr. Bruce Infrastructure and Mr. Bruce infrastructure available (i.e., Infrastructure and Mr. Howell’s Howell, Project crushers, sorters, etc), Bruce Howell, Project assessment of the Management Office grade of material (can it be Management Office grade and quality of local aggregates. Basically, his FSM PRIME_Consultation Summary_Kosrae 131120 Page 3 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation used as roading assessment is that aggregate?) local aggregates are not suitable for roading aggregates & aggregates used in past road paving projects were imported from Asia. Docs and photos of Puk Quarry, the only quarry in Kosrae that has a rock crushing machine and sorter were shared with ARGO. KIRMA Administrator, Mr. Meeting to discuss number KIRMA Administrator, Mr. telephone One-on-one October KIRMA A Map and table Blair Charley of existing quarry sites in Blair Charley & Andy meeting 16, 2020 Office showing permitted Kosrae that have George quarry sites in Development permits. Kosrae submitted to Argo . State focal point Mr. Osamu Meeting to discuss the 2nd Andy George, Osamu Email & Team meeting October DT&I Office Team agreed to Nedlic, State Focal Point round of stakeholder Nedlic, & Director Livaie. telephone 22, 2020 have one meeting Ms. Betty Sigrah, and consultation meeting in for all Director Livaie Kosrae, particularly on stakeholders. The whether to hold separate meeting is meetings for state and tentatively FSM PRIME_Consultation Summary_Kosrae 131120 Page 4 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation community leadership as in scheduled for the 1st round. November 4th, 2020. Director Livaie agreed to confirm the date with Governor Sigrah. The team also agreed to hold off on distributing or announcing meeting until the presentation from ARGO is received. Andy George, State focal Meeting to with the project Andy George, Osamu Email & Team meeting October DT&I Office Agenda revised points, Director Livaie, & team to finalize plans for Nedlic, & Director Livaie. telephone 28, 2020 and the team Governor’s Chief of Staff 2nd consultation and to agreed to have the Mr. Nena William review agenda and sample official invite letter invite letter from AGRO. come from the Governor’s office. The copy of the Agenda & sample invite letter was shared with Gov’s Chief of staff. Governor’s Chief of Staff Briefly met to discuss the Governor’s Chief of Staff Telephone One-on-one November Governor’s Final Invite letter invite letters for and Andy George 4th, 2020 Conference drafted and shared stakeholders and to make Room with ARGO sure the letters are FSM PRIME_Consultation Summary_Kosrae 131120 Page 5 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation distributed soonest possible. Governor Sigrah, Lt. Joined Director Livaie to Governor Sigrah, Lt. Email Group November Governor’s Both Gov. & Lt. Governor Nena, Director update the Governor and Gov. Nena, Director meeting 6th, 2020 Office Gov agreed to Livaie, Andy George Lt. Governor on the status Livaie, and Andy George attend the g 2nd of PRIME project prior to consultation the actual meeting on meeting on Monday. Monday. Office of the Governor, 2nd round of consultation Governor Sigrah, Lt. Official Invite Joint Meeting November Governor’s Refer Meeting Office of the Lt. Governor, with State government and Governor Nena, letter from of government 9th, 2020 Conference Notes Department of community representatives. Department of the and Room Transportation & The meeting was intended: Resources & Economic Governor’s community Infrastructure, Department Affairs (DREA), Division office stakeholders • To provide an of Finance & of Fisheries update on Administration, Department Development (DREA), progress, scope of Resource & Economic Department of Health and timing of the Affairs with the divisions of Services, Department of PRIME Project. Land Management & Finance & • To outline Fisheries Development, Administration, proposed key Kosrae Port Authority, principles of E&S Department of Department of Education, framework Education, Department Department of Health documents and of Transportation & Services, Kosrae State ‘strategies’ to Infrastructure, FSMTC, Legislature, PMO, Kosrae screen and Historic Preservation, Visitors Bureau, KIRMA, manage possible Kosrae Visitors Bureau, Historic Preservation, environmental Project Management Kosrae Land Court, and social Office (PMO), Overseas FSMTC, Kosrae Utilities impacts from any Development Assistance Authority, Office of the Lelu Project works (ODA office), Malem Mayor, Office of the Malem (once they are Mayor, Civil Society of Mayor, Office of the identified). Kosrae, Kosrae Utilities Tafunsak Mayor, Office of Authority, Kosrae Youth FSM PRIME_Consultation Summary_Kosrae 131120 Page 6 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation the Utwe Mayor, Senior • To receive Development Citizens officers, KWA comment and Association, Kosrae officers, KYDA officers, Civil feedback from Women Association Society of Kosrae officers, stakeholders, in Kosrae Consumers order to complete Organization/lnter-Agency draft E&S Committee, Chamber of framework Commerce, Kosrae Special documents. Parent Network (KSPN), • To engage MMME, Adaptation Fund stakeholders in Project Coordinator, RMC the development (Lelu, Malem, Tafunsak, of these Utwe), Council of Pastors, documents and Presidents of Municipal management Hamlets decisions for the Project Senior Citizens officers, First round of consultation Governor’s office, Lt. Official Invite Meeting - September Governor’s Refer Meeting KWA officers, KYDA with community leadership Governor’s office, Kosrae letter from (community 04, 2020 Conference Notes officers, Civil Society of to: State Legislature, Pastor the leaderships Room Kosrae officers, Kosrae • Inform key Malem Church, Kosrae Governor’s joint) Consumers stakeholders of the PRIME Chamber of Commerce, office Organization/lnter-Agency Project Aquaculture Committee, Chamber of Center(MMME), Civil • Acquire Community Commerce, Kosrae Special Society of Kosrae, Pastor information to develop E&S Groups Parent Network (KSPN), Lelu Church, Adaptation framework documents MMME, Adaptation Fund Fund Coordinator, • Provide Walunga Malem Hamlet, Project Coordinator, RMC stakeholders an opportunity Community Health, (Lelu, Malem, Tafunsak, to express Project Management Utwe), Council of Pastors, opinions/concerns to be Presidents of Municipal Office, Kosrae Women addressed in developing Association, Senior Hamlets the E&S documents and Citizens, DT&I, KIRMA, Council of Pastor, FSM PRIME_Consultation Summary_Kosrae 131120 Page 7 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Kosrae Key feedback/ Stakeholder Consultation Stakeholders Invited Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type Type consultation DTC&I management Micronesia Red Cross- decisions. Kosrae Chapter, Youth (DREA) Andy George, Director Meeting to request for Greg Ribauw (KUA), Email One-on-one August 26, KUA Office GIS coordinates of Livaie, Mr. Fred Skilling updated data on electric Director Livaie, & Andy 2020 electric poles Public Utilities (KUA Manager) poles and other GIS data George provided by KUA available with KUA FSM PRIME_Consultation Summary_Kosrae 131120 Page 8 PRIME Project Preparation (ESA) CONSULTATION SUMMARY – POHNPEI Stakeholders Invited Consultation Purpose Stakeholder Notification Consultation Date Location Key feedback/ Stakeholder Attended Type outcome of Type consultation Governor’s office • Outline/Introduce Governor’s office; Request for On-on-One Sept 2, Governor’s Full support and PRIME Project EPA Appointment Briefing 2020 Office recommends E&S • Discuss potential team work closely physical works on Primary with TC&I. EPA Road Network (incl. Lelu EPA; DoFA Email Pohnpei team Sept. EPA Office Consolidate data and Causeway) meeting 02,2020 information required. • Outline intended Preparations for programme of work stakeholder meeting FSM • Identify gaps to be FSM Invitation Social event Sept. 15, Hide Away Will work with both State Telecommunications filled Telecommunications 2020 Restaurant DTC&I and T&I Government Corporations • Obtain feedback on Corporations during planning Departments / Project phase. Offices / Agencies / Office of Social Affairs Office of Social Email; 1st Sept.17, Governor’s Refer to meeting Authorities; Resource & Affairs Official Stakeholder 2020 Conference notes Development; Resource & invitation meeting Room Community Groups and Pohnpei Senior Development; ‘Other’ Citizens Pohnpei Senior Stakeholders Citizens Office of T&I Request for One-on-One Oct. 1, T&I Office T&I also conducting Transportation and Appointment Briefing 2020 their assessments. Infrastructure (T&I) E&S assessment needs to go along T&I assessment U Municipal U Municipal Phone Call One-on-One September Lunch Supports the project Government Government Briefing 22, 2020 Meeting and will work T&I during planning phase FSM PRIME_Consultation Summary_Pohnpei 131120 Page 1 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Pohnpei Stakeholders Invited Consultation Purpose Stakeholder Notification Consultation Date Location Key feedback/ Stakeholder Attended Type outcome of Type consultation FSM DTC&I; FSM DTC&I; Email; 2nd October Governor’s Refer to meeting Governor’s Office Governor’s Office; Official Stakeholder 12, 2020 Conference notes. invitation meeting Room T&I; ODO; Department of Public T&I; Safety; Department of Office of Fisheries Public Safety; and Aquaculture; Office of Fisheries Kitti Municipal and Aquaculture; Government; Kitti Municipal Madolenihmw Government; Municipal Madolenihmw Government; Municipal U Municipal Government; Government; U Municipal U Municipality; Government; Pohnpei Utilities U Municipality; Corporation Pohnpei Utilities Corporation State Governor’s • To provide an update State Governor’s Email; 3rd November Governor’s Refer to meeting Office; on progress, scope and timing Office; Official Stakeholder 10, 2020 Conference notes. Department of of the PRIME Project. Department of invitation meeting Room Finance & • » To outline proposed Finance & Administration; key principles of E&S Administration; Madolenihmw framework documents and Madolenihmw Municipal ‘strategies’ to screen and Municipal Government; manage Government; EPA; • possible EPA; environmental and social impacts from any Project FSM PRIME_Consultation Summary_Pohnpei 131120 Page 2 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Pohnpei Stakeholders Invited Consultation Purpose Stakeholder Notification Consultation Date Location Key feedback/ Stakeholder Attended Type outcome of Type consultation Department of works (once they are Department of Resources & identified). Resources & Development; • » To receive Development; Nett District comment and feedback from Nett District Government; stakeholders, in order to Government; Kolonia Town complete draft E&S Kolonia Town Government; framework documents. Government; PSQ; • » To engage PSQ; stakeholders in the Social Affairs Office; development of these Social Affairs Office; T&I; documents and management T&I; Overseas decisions for the Project Overseas Development Development Assistance (ODA) Assistance (ODA) office. office. FSM PRIME_Consultation Summary_Pohnpei 131120 Page 3 PRIME Project Preparation (ESA) CONSULTATION SUMMARY – CHUUK Key feedback/ Consultation Stakeholder Type Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type consultation Initial Stakeholders Meeting to: FSM Telecommunications Request for One-on-One 21-Aug- FSMTC Refer to Meeting • Outline/Introduce PRIME Corporation Appointment Meeting 2020 Notes Project Chuuk Public Utility Corp. Request for One-on-One 24-Aug- CPUC Refer to Meeting • Discuss potential physical Appointment; Meeting 2020 Notes works on Primary Road Network (incl. Email Lelu Causeway) Governor’s Office, Request for One-on-One 25-Aug- Governor’s Refer to Meeting • Outline intended Appointment Meeting 2020 Office Notes programme of work • Identify gaps to be filled/ DT&PW Request for One-on-One 25-Aug- DT&PW Refer to Data Request for data Appointment, Meeting 2020 Gathered/ Email • Obtain feedback on Project Email regarding previous road survey by State Government DT&PW Departments / Offices / Agencies / Authorities/ EPA Request for One-on-One 26-Aug- EPA Refer to Data NGOs / Community Appointment, Meeting 2020 Gathered/ GIS Info Representatives Email on Hazard SItes, Contour data FSM Congress, Northern Request for Weno Aug. 28, Weno Refer to Meeting Nomoneas Region; Attendance Stakeholders 2020 Municipality Notes Weno Municipality; Meeting Chamber Chuuk Sanitation Office; Weno Municipality Office/Council; Weno Traditional Chief/ Village Representative. FSMT Cable Corp. Email Email 29-Aug- n/a Refer to Email/ Data 2020 Gathered/ As-Build FSM PRIME_Consultation Summary_Chuuk 131120 Page 1 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Chuuk Key feedback/ Consultation Stakeholder Type Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type consultation for Fronthaul route- road crossing Chief, Elisius Akapito Request for One-on-One 31-Aug- Chuuk Refer to Meeting Appointment, Meeting 2020 Planning Notes Email Office • Identify gaps to be filled/ Chief, Peter Aten Email One-on-One Sept. 16, C&I Building Scheduling Request for data Meeting 2020 Scanning of Road Easement Documents Initial Stakeholders Meeting to: Department of Transport Email; Request Joint Sept. 03, Governor’s Refer to Meeting • Outline/Introduce PRIME & Public Works; for Attendance; Stakeholders 2020 Auditorium Notes Project Governor’s office; Letter Invitation Meeting • Discuss potential physical Commerce & Industry; works on Primary Road Network (incl. Land Management; Lelu Causeway) Chuuk Conservation • Outline intended Society; programme of work Chuuk Planning Office; • Identify gaps to be filled Chuuk Public Utility • Obtain feedback on Project Corp.; Chuuk Visitors Office; Chuuk Women’s Council; Disaster Coordination Office; Department of Agriculture; FSM Immigration & Labor; FSM PRIME_Consultation Summary_Chuuk 131120 Page 2 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Chuuk Key feedback/ Consultation Stakeholder Type Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type consultation Chuuk Department of Public Safety; Department of Marine Resources; EPA; Land Commission office; Chuuk Public Affairs; Department of Administrative Services; Chuuk Youth Council; Chuuk Department of Education; Chuuk Department of Health Services; Gender Based Violence Program-Inepwinau Counselling Center; Chuuk State Legislature; Chuuk Chamber of Commerce; Tonoas Municipality. • To provide an update on Governor’s office; Email; Request Joint November Governor’s Refer to Meeting progress, scope and timing of the Commerce & Industry; for Attendance; Stakeholders 12, 2020 Auditorium Notes PRIME Project. Letter Invitation Meeting Department of Marine • To outline proposed key Resources; principles of E&S framework Chuuk Public Utility documents and ‘strategies’ to screen and manage possible Corp.; environmental and social impacts Land Management; FSM PRIME_Consultation Summary_Chuuk 131120 Page 3 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Chuuk Key feedback/ Consultation Stakeholder Type Consultation Purpose Stakeholder Attended Notification Date Location outcome of Type consultation from any Project works (once they EPA; are identified). Chuuk Conservation • To receive comment and Society; feedback from stakeholders, in order to complete draft E&S framework documents. • To engage stakeholders in the development of these documents and management decisions for the Project FSM PRIME_Consultation Summary_Chuuk 131120 Page 4 PRIME Project Preparation (ESA) CONSULTATION SUMMARY – YAP Consultation Purpose Stakeholder Attended Notification Consultation Date Location Key feedback/ Stakeholder Type outcome of Type consultation • Outline/Introduce PRIME Project Chief Weloy Municipality Phone Calls Meeting (joint) 15-Aug- Ganir Restaurant Refer Meeting • Discuss potential physical works Chief Gagil Municipality 2020 Notes on Primary Road Network (incl. Domathing Chief Tamil Municipality & Doenoch Bridges) Yap Chamber of Commerce Email; Meeting (joint) 15-Sept- Small Business Refer Meeting • Outline intended programme of Chairman Letters 2020 Development Notes work Center-Colonia, • Identify gaps to be filled Yap. • Obtain feedback on Project Yap State Legislature Phone Calls Meeting (joint) 18-Sept- Yap State Refer Meeting 2020 Legislature- Notes State Chamber Room Government Departments / Yap State Public Service Phone Calls Meeting ( 20-Oct- YSPSC Refer Meeting Offices / Corporation joint) 2020 Conference Notes Agencies / Room Authorities / Community • To provide an update on Civic Affairs; Email; Meeting (joint) Nov-6, Refer Meeting Groups / Public progress, scope and timing of the PRIME Yap Planning & Budget Office; Letters; 2020 Notes Utilities Project. Phone calls Council of Pilung (including 10x • To outline proposed key Municipal Chiefs) principles of E&S framework documents and ‘strategies’ to screen and manage possible environmental and social impacts from any Project works (once they are identified). • To receive comment and feedback from stakeholders, in order to complete draft E&S framework documents. FSM PRIME_Consultation Summary_Yap 131120 Page 1 Federated States of Micronesia PRIME Project: Project Preparation (ESA) Consultation Summary - Yap Consultation Purpose Stakeholder Attended Notification Consultation Date Location Key feedback/ Stakeholder Type outcome of Type consultation • To engage stakeholders in the development of these documents and management decisions for the Project EPA; Email; Meeting (joint) Nov-12, Refer Meeting Civic Affairs; Letters; 2020 Notes Yap Planning Office; Yap Red Cross; Yap Women’s Association; Kids of Ruuq Community (KORC) Youth Group; FSM PRIME_Consultation Summary_Yap 131120 Page 2 Federated States of Micronesia PRIME Project Stakeholder Engagement Plan Appendix D Meeting notes from Project preparation consultation meetings December 2020 Final Kosrae Meeting Notes MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Conference Room Date: September 3rd, 2020 Time: 10:00 am Andy George, Betty Sigrah, and Osamu Chairperson: Andy George Recorder: Nedlic Attendees: Argo Environmental Ltd – Andy George DoTC&I State Reps – Director Hairom Livaie, Kosrae DT&I Osamu Nedlic – government E&S focal point Betty Sigrah – government E&S focal point Note: Refer to attached attendance list for stakeholder attendees PURPOSE • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions Opening Prayer – Minister Kiobu Luey 1 Director Hairom Livaie opened with a welcoming remark followed by a special remark by Honourable Governor Carson Sigrah. The honourable governor highlighted in his remark the importance for Kosrae leadership to understand the purpose of the PRIMME project and to offer its fullest support and endorsement on the project. [Agenda Item #1: Kosrae Primary Road] The leadership questioned the accuracy of Kosrae Primary Road network map that was presented during the presentation. The leadership questioned how the map was developed and who was in charge of developing the primary road network map. The consensus was that the map is missing at least four road segments and they should be included. These missing segments are in Tafunsak, Lelu, and Utwe. The leadership requested KIRMA to update the map to show the missing segments and share with ARGO. The leadership also discussed the IPIC’s (Infrastructure Planning and Implementation Committee) own Primary Road Network Map. They indicated that the IPIC map shows proposed roads in Kosrae particularly the Adaptation Fund road from Malem to Utwe and the proposed cross-island road from Innem to Okat as part of the Kosrae Primary Road Network. Thus, the leadership inquired about the possibility for WB to allow Kosrae 2 to include these proposed new roads in the WB Primary Road Network Map. The discussion regarding sections of the primary road network that needed improvement to enhance resilience to climate related impacts identified several road segments that are currently impacted by coastal erosion and coastal flooding as well as road segments that have poorly designed drainage system, culverts, and bridges. These road sections extend from Tafunsak to Utwe. After a lengthy discussion on all these different road sections, KIRMA advised the local team to reference the Kosrae Shoreline Management Plan as it should identify all the coastal areas in Kosrae that are clearly affected by coastal erosion. The governor emphasized that the Lelu Causeway remains Kosrae’s priority for the PRIME project. The leadership agreed that the causeway is in bad shape and improvement is urgently needed. The culvert that was once situated in middle of the causeway is now covered and blocked up therefore affecting the water flow in the area. The leadership claimed that the culverts near both ends of the causeway are eating away the FSM PRIME_Meeting Notes_Kosrae_Government Leaders_Sep 3 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Sep 3 2020 No. Agenda Item / Discussion sandy beach on the ocean front side and therefore should be relocated or removed. The consensus from the leadership was to hold off on further discussions on the causeway road design until designing phase. Other issues raised during the causeway discussion included the swimming dock/platform attached to side of the causeway and the newly designated Lelu MPA, which is currently under review by the Kosrae State legislature to be included in the Kosrae Protected Area System Act. The leadership was informed by KIRMA during the meeting of the status of the Lelu MPA application with the state government. The leadership wanted to make sure that when designing the new causeway the project takes the swimming dock and the Lelu MPA into account. [Agenda Item #2: Consultation & Data Collection] The leadership expressed appreciation for this engagement and readiness for the 2nd round of consultation. The one concern raised by the leadership regarding the 2nd round of consultation had to do with local capacity to do in depth review of E&S Framework documents. The leadership questioned whether the review of framework documents is something the FSM national government should do or something for the state. The understanding at the end of the discussion was that the state leadership and all relevant stakeholders should be afforded the opportunity to review these documents during the 2nd round of consultation. 3 The leadership emphasized the need to protect our raw data and make sure data in only used for this purpose. The issue of compensation for the use of GIS data came up too as KIRMA claimed to have spent tremendous amount of money in order to collect the data over the years. The consensus from the leadership was to seek clarification form ARGO or WB if Kosrae will be compensated for sharing available data with consultants. The governor requested that available GIS data with KIRMA and other relevant government agencies that are needed for the E&S safeguard assessment be shared with ARGO and the local team. KIRMA agreed to continue compiling their data to share with the local team in the next few weeks. Other Matters The leadership sought clarification on the process and amount of project funds to be disbursed by WB. The question is whether disbursement of funds depends on how soon the required social and environmental 4 safeguard requirements are completed or is there a distribution formula in place to determine how much each state is receiving for this project. The concern that Kosrae is always victimized by its size when it comes to distribution of funds to support the four states of FSM was also raised. The overall hope from the Kosrae leadership is that the WB funds are not distributed based on the size of the state. 5 Meeting closed at 12:30 pm ACTIONS No. Action Item Responsibility Due Update Primary Road Network Map to show missing road segments Local Team September 1 with KIRMA 11th, 2020 Kosrae Next Steering Request submitted to Project steering committee to consider the sate that Steering 2 committee Committee completes all its requirements to receive funding first. member, meeting Director Livaie 3 GIS data to be compiled and shared with ARGO consultant & local team KIRMA September week of 14th. FSM PRIME_Meeting Notes_Kosrae_Government Leaders_Sep 3 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Sep 3 2020 MEETING PHOTOGRAPHS FSM PRIME_Meeting Notes_Kosrae_Government Leaders_Sep 3 2020 3 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Conference Room Date: September 4th, 2020 Time: 10:00 am Andy George, Betty Sigrah, and Osamu Chairperson: Andy George Recorder: Nedlic Attendees: Argo Environmental Ltd – Andy George DoTC&I State Reps – Director Hairom Livaie, Kosrae DT&I Osamu Nedlic – Government E&S focal point Betty Sigrah – Government E&S focal point Note: Refer attached attendance list for stakeholder attendees PURPOSE • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions Opening Prayer – Senior Pastor and chairman of the Kosrae Congregational Church Council of Pastor opened the meeting with an opening prayer. Director Hairom Livaie gave the welcoming remark and acknowledged presence of key stakeholders from the 1 communities. He also acknowledged presence of the three state senators who accompanied their community leaders to the meeting. The Honourable Governor Carson Sigrah followed Director Livaie with a remark to highlight the importance of the PRIME project and the need for the communities to be aware of and support development projects that will take place in their communities. The governor stated in his brief remark that the priority phase I for Kosrae in this project is to improve the resilience of the Lelu Causeway. Phase II will be to improve other sections of the road in Kosrae’s primary road network. [Agenda Item #1: Kosrae Primary Road] The community leadership agreed with discussed missing road segments from the primary road network map. In addition to the four missing road segments discussed by the state leadership, a new segment (Adaptation Fund road) in Malem was also discussed particularly by community leaders from Malem. The discussion was really seeking clarification on whether the AF road (at least the existing portion of the AF road) should be considered part of the primary road network and therefore should be surveyed by ARGO. The response from the Governor and Director Livaie made it clear that the AF road is not part of the PRIME project and funding 2 for the AF road segment is already secured. The community leaders also discussed and highlighted several sections of the primary road network that need to be improved. A comment from one of the elders suggested that the entire primary road system in Kosrae actually needs improvement and enhancement in order to withstand the changes in climate as well as frequency in natural disaster. Everyone seemed to agree that the entire road system needs some improvement. The community leadership also inquired about the Road Easement, particularly on the terms and duration of the easement. The leadership sought clarifications on the following: a) How long before the existing easement will expire? FSM PRIME_Meeting Notes_Kosrae_Community Leaders_Sep 4 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Sep 4 2020 No. Agenda Item / Discussion b) Is the easement valid even if the current landowners did not sign it? The question came up because some original landowners who signed off on the easement have sold their properties. After much discussion on the easement, Director Livaie agreed to follow up with the office of Land Management under the Department of Resources and Economic Affairs on the status of the easement. He also agreed to get legal opinion from the Attorney General’s office on the validity of the easement especially when some properties have been sold to new landowners. Another key concern raised during the discussion was the blockage of the Insrefusr mangrove channel and the culvert in the middle of the causeway, which contributes greatly to the poor circulation of water in that area. The community leadership agreed that the poor quality of water in the area can be improved with the PRIME project. Another issue raise was on the potential environmental impacts to the reefs near the causeway area if and when improvement/construction works begin. The community leadership, particularly from Lelu, requested that an environmental impact assessment be carried out before any construction begins. Finally, another key point made by the community leadership is the cultural and historical aspects and significance of the Lelu Causeway to the people of Kosrae. The leadership realized that the causeway was built by our own people with their own resources. The design, although not professional, was done by our own people too. Therefore, the leadership requested that WB looks into the option of preserving the causeway by building a suspension bridge over it rather than destroying something of sentimental value to Kosraeans. However, the community leadership also noted that if a suspension bridge is not possible then at least the project or the government should put up signage to that will highlight the cultural and historical significance of the causeway. [Agenda Item #2: Consultation & Data Collection] The community leadership agreed that GIS data needed for the E&S safeguard assessment is available with the state government and they hope that the data available can be shared with the team. The Micronesia RedCross Society Kosrae Chapter volunteered to help with field data collection if the need arises. Furthermore, 3 the leadership also highlighted that it is very significant that PRIME project engages the different sectors at this stage of the project and they look forward to participating in future consultations. They agreed that the improvement to the primary road system will significantly help in improving the delivery of goods and services throughout the island. Other Matters The Youth representative in the meeting inquired about the selection process for subprojects in each state. 4 The concern from the youth rep was that priority subprojects selected by each state be discussed and agreed with by both state and community leaderships and/or representatives. The idea is to allow all sectors to have a say in the process and not just a few people in the government. 5 Meeting closed at 12:30 pm ACTIONS No. Action Item Responsibility Due Follow up with Land Management of the current Road Easement Director Livaie, September 1 DT&I 14th, 2020 Director Livaie, September 2 Get legal opinion from AG on validity of road easement DT&I 9th, 2020 FSM PRIME_Meeting Notes_Kosrae_Community Leaders_Sep 4 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Sep 4 2020 MEETING PHOTOGRAPHS FSM PRIME_Meeting Notes_Kosrae_Community Leaders_Sep 4 2020 3 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Conference Room Date: November 9th, 2020 Time: 10:00 am Andy George, Betty Sigrah, and Osamu Chairperson: Andy George Recorder: Nedlic Attendees: Argo Environmental Ltd – Andy George DoTC&I State Reps – Director Hairom Livaie, Kosrae DT&I Osamu Nedlic – government E&S focal point Betty Sigrah – government E&S focal point Note: Refer attached attendance list for stakeholder attendees. PURPOSE . • To provide an update on progress, scope and timing of the PRIME Project. • To outline proposed key principles of E&S framework documents and ‘strategies’ to screen and manage possible environmental and social impacts from any Project works (once they are identified). • To receive comment and feedback from stakeholders, in order to complete draft E&S framework documents. • To engage stakeholders in the development of these documents and management decisions for the Project PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions Opening Prayer – Director Rensley Sigrah, Department of Finance & Administration 1 Director Hairom Livaie opened the meeting to welcome stakeholders and leadership from both government and community who were able to make it to the meeting despite the last minute arrangements. The Honourable Governor Carson Sigrah also delivered a special remark to highlight the importance of engaging stakeholders in the planning and implementation of projects such as the PRIME project. He expressed his appreciation for the good turnout of participants and encouraged everyone’s participation in the meeting. [Agenda Item #1: Implementation of Physical Works in the States] The leadership questioned whether implementation schedule for the actual physical works would be the same for all four states and/or would progress or lack of progress by one or more states can affect the implementation schedule for the other states. The stakeholders/leadership wanted to be sure that hold ups and delays in other states does not penalize or affect Kosrae’s chances to begin necessary construction and physical works on the primary road on time. Discussions highlighted that there is a great need to improve and build climate- 2 resilient road infrastructures in Kosrae and therefore stakeholders expressed readiness to provide necessary support to move the project forward. Stakeholders, with the blessings of the leadership, emphasized the need for Director Livaie, PRIME Project Steering committee from Kosrae, and the state focal points to bring up the issue with the FSM national government DTC&I and the steering committee. Stakeholders also emphasized the need for Kosrae to keep on track and make sure to work within timeframe to ensure that Kosrae does not lose out on the opportunity to improve Kosrae primary road network. FSM PRIME_Meeting Notes_Kosrae_Joint Stakeholders_Nov 9 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Nov 9 2020 No. Agenda Item / Discussion [Agenda Item #2: Kosrae Primary Road] The stakeholders and key state leaders in the meeting again and sought clarification on why the rest of Kosrae primary road is still included, as recommended in the 1st consultation meeting, into the PRIME project scope of work particularly the road sections around Lelu Island and from Utwe to Walung. The consensus from the Kosrae stakeholders is that missing road sections around Lelu island and from Utwe to Walung be incorporated into the scope as highlighted and discussed in detail during the 1st consultation meeting. The Honourable Lt. Governor Nena again advised Kosrae’s representative on the PRIME project Steering Committee to raise the concern of the Kosrae stakeholders to the committee and to DTC&I and to push for the inclusion of these 3 missing primary road segments into the PRIME project. The stakeholders agreed that even if actual physical works will not be done on these primary road segments, they should be included in the VA/CRRS studies that will be conducted as part of PRIME project. Stakeholders wanted to be sure that concerns raised by the state leadership and stakeholders during consultations are actually addressed. Stakeholders questioned the status of the field surveys. On behalf of ARGO, I informed stakeholders that field survey has been completed and survey was done on segment of the road as shown n the Map. The project team took the opportunity to thank the focal points for their exceptional collaboration and KIRMA and other government agencies for sharing necessary data requested by ARGO. Other Matters 1. A question was raised regarding the WB budget for the project and how funds are to be distributed to the states. The question sought clarification on whether WB funds would be divided equally amongst the states or would it be based on the needs and costs of physical works in each state. 2. Stakeholders also sought clarifications as to how sub-projects/physical works will be determined for each state? Who will decide if physical work with high E&S risks can be part of the project because it is essential? The project team could only say that funds going to the states will most likely depend on the implementation costs. The remaining questions were not answered but the project team agreed to bring this up to DTC&I. 4 3. A brief question was raised on whether there is indeed budget Resettlement costs? The responses what that the project is developing a framework to ensure that resettlement issues are addressed properly 4. Bruce Howell briefed the stakeholders that an RFP for the Lelu causeway design has been issued. The purpose is to help identify costs of improving the causeway. 5. Another concern was raised on the PRIME project timeline. The concern was directed to the state government leadership on whether the government is pursuing other sources of funding for road improvement in Kosrae. The fact that physical work implementation under the PRIME project may happen in 2022 or thereafter was a surprise to most stakeholders as they would rather see the actual work begins soon. 5 Meeting closed at 12:30 pm ACTIONS No. Action Item Responsibility Due Follow up with FSM DTC&I and Steering committee on implementation 1 Director Livaie Soonest possible schedule for each state Follow up with FSM DTC&I and Steering committee on the Primary Road Network Map for Kosrae and push to incorporate missing road 2 segments (Lelu Island and Utwe-Walung) Director Livaie Soonest possible 3 Share E&S framework documents with stakeholders DT&I December 2020. FSM PRIME_Meeting Notes_Kosrae_Joint Stakeholders_Nov 9 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Kosrae, Nov 9 2020 MEETING PHOTOGRAPHS FSM PRIME_Meeting Notes_Kosrae_Joint Stakeholders_Nov 9 2020 3 Pohnpei Meeting Notes MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Conference Hall Date: September 17, 2020 Time: 10am Chairperson: Henry Susaia Recorder: Ms.Lululeen Santos Attendees: Argo Environmental Ltd – Mr. Eugene Joseph DoFA CIU – Mr. Wilmer Kilmete EPA – Mr. Henry Susaia (DoTC&I State Focal Point) Social Affairs Office – Ms. Lululeen Santos (DoTC&I State Focal Point) Note: Refer attached attendance list for stakeholder attendees PURPOSE Pohnpei State Stakeholder Consultation Meeting (Government Leadership) • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. PROCEEDINGS No. Agenda Item / Discussion Welcoming and introductions: 1 Henry Susuaia, Focal Point: Brief general history of PRIME project. Opening Remarks: Hon. Reed Oliver, Pohnpei State Governor: • Excited to see progress on road improvement. • Will continue to work with Finance Department to develop management mechanism for vehicle 2. registration tax (additional tax for road maintenance). • T&I will soon commence assessments in collaboration with local municipal governments to identify areas of improvement to road network. • Although vehicle registration tax may not be enough to fix all our road network, we are blessed to have big investment projects such as PRIME to help. PRIME Project Presentation: 3. Eugene Joseph, Argo Environmental Contractor. Q&A: Lt. Governor Felciano Perman: • Any other options to minimize dredging/coral mining for construction material? • State government needs to boost enforcement on environmental laws and regulations. Most development projects does not abide with regulations and management criteria, but nothing been 4. done to correct it. Governor Oliver: • Will the total funding of $40M be distributed equally between the four states or by recommendations by the assessments? FSM PRIME_Meeting Notes_Pohnpei_Meeting 1_Sep 17 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Pohnpei, Sep 17 2020 No. Agenda Item / Discussion [Response] Mr. Wilmer Kilmete: • At this stage, we are only focusing on the assessment. If not mistaken, a small percentage of the total funding will be used towards the priority areas (Awak bridge) and the bigger percentage will be for the primary road network. [Comment] Director Yubert Yamada, Department of Resources and Development: • Aware of PRIME Project in previous office at the national government. Also aware of local project team are just limited to priority area. • DTC&I and FSM Finance should attend this meeting to clarify the initial phases including our requirements to secure this kind of investment projects from WB. • Initial scoping has been completed in the previous administration and there was no formal hand over of information for the current administration to carry on with deliverables. • However, since all these information gaps seem to be internal challenges, R&D looks forward to the E&S assessment report and hopefully look into how we can standardize national and state protocols. [Question] Shirley Ligohr, External Affairs Officer: • Is there a way FSM DTC&I can work with Green Climate Fund (GCF) to unify their efforts in this kind of assessment? • Can Asian Development Bank (ADB) match the funding gaps to include all road networks? [Response] Henry Susaia – Focal Point: • There is no reason why GCF cannot unify with WB. However, since this project scoping was already in progress during GCF initial stage, we just had to follow WB criteria and guidelines. Perhaps, something worth looking into the future to include GCF in future assessments. • DTC&I is already working ADB and other bi-lateral investments to expand the project. For example, China Embassy is working on Kahmar bridge and secondary road networks in Madolenihmw. Other Matters 9 None. 10 Meeting closed at [11:15] ACTIONS No. Action Item Responsibility Due Reach out to DTC&I PMU Mr. Robert Goodwin and someone from FSM Finance Dept. to join 2nd stakeholder meeting. Eugene & 1 Mid Sept. Wilmer FSM PRIME_Meeting Notes_Pohnpei_Meeting 1_Sep 17 2020 2 PRIME 2nd Stakeholder Meeting Pohnpei State October 12, 2020 Opening and Welcoming – Henry Susaia, Director of Pohnpei EPA. • Introduction of participants. • Review of agenda. • Project Overview by Mr Goodwin, DTC&I. • Presentation by Eugene Joseph, Argo Environment • Questions • Next Steps Project Overview by Robert Goodwin, DTC&I. • One of the good things about World Bank is that they put a lot of emphasis on stakeholder engagement and involvement in all of their project investments. DTC&I and T&I have been criticized heavily in the past for we do not engage with stakeholders in our projects. The China-Madolenihmw project is a good example where we got the money and start the project without any consultations creating conflicts and complicates the communities. WB is also developing a complain mechanism. • Where we are right now in developing this project and how we are going to implement it and decision on which segments of the road network required for improvement. It is a critical part of the process to develop the project for WB. WB puts a lot of emphasis on Stakeholders to be involved and have a role in any of their development and implementation. Basically, the E&S assessment is to see what kind of impact the project will have on the environment and on the local communities. Also, to be able to develop safeguards or things that we need to do to make sure the project doesn’t have any bad effects on the environment or the communities. • WB has promised us $40M US dollars as a first step in what we hope will be a major investment for the road network for the whole FSM. We know it will not be a whole lot of money because our rough estimate to cover the entire FSM road network improvements is around $400 million. We try also make sure that this first step to be able to set up planning tools to enable us to prioritize. DTC&I are also talking to Asian Development Bank (ADB) with hopes we can get another $40M, we’ve been working with People’s Republic of China (PRC) and they’ve just completed the Kahmar bridge and now working in Madolenihmw with hopes they will extend their support to Chuuk. President Panuelo is talking with the Prime Minister of Australia to look into also support. So, hopefully within the next five years we may see of lot of these investments to be able to upgrade our road networks, which we all know haven’t been maintained for over 20 years now. PRIME project will give us a fresh start on what we hope to be a major investment to improving our road networks throughout the FSM. • We haven’t taken any decisions yet regarding which sections of the road network will be done. The reason being is that we don’t have the whole information. We know that most of the sections are in very poor conditions, but what we were able to do as a first step is identifying priority areas. • In addition to this E&S assessment, we are now on the verge to hire another international consulting firm to undertake Vulnerability Assessment and Road Strategy (VARS). The VA will look at the whole primary road network in the FSM looking at those sections that are most vulnerable in terms of faster deterioration due to heavy rainfall, erosion or landslide. The VA will provide us a priority matrix (bridges and culverts) and 70% of the $40M will target those sections. • Why Awak bridge a priority? WB processes are very slow (studies and hiring of consulting and engineering firms), therefore, we wanted something to get started early or as soon as agreement is signed in 2021. Therefore, DTC&I selected 4 priority sites, one from each state, that will not cost too much money. DTC&I worked with T&I and surveyed key areas and Awak was selected due to bad condition it is in now. Awak bridge is critical as it links Madolenihmw and other municipalities. We have already prepared the TOR to hire a design firm to be advertised in October. • In terms of how decisions are to be made? We will set up a project steering committee of high-level people, people with strong authority within the government. That committee with then decide on which segment of the road network will be prioritized for the remaining 70% of the $40M based on recommendations from the VARS. • Just to mention that the project is not going to be only about improving infrastructure, will also focus on maintenance capabilities (drainage and potholes). We hope to also use this investment to help re-establish our maintenance capabilities further guiding each state on how to create a maintenance fund so infrastructure entities can have the set up to carry out maintenance rather than depending upon outside investments. [Question]Patrick Carl, Director of Department of Public Safety: • Will this project also include road markings? As we all know, Pohnpei rains a lot therefore most of the road markings deteriorates quickly. [Response] Mr. Goodwin: • We are in the process of hiring a consultant to conduct a Road Safety Audit for safety standards to all FSM road networks. The consultant will also look into designs including lightings, markings and signs. [Question] Mr. Tony Sarapio, Mayor, Kitti Municipal Government: • Pohnpei already have a maintenance mechanism in place. There is a new increase in vehicle registration tax dedicated just for road maintenance, but we haven’t seen anything to fix our roads. When you did your prior assessment last year, did your team ever examined the bridges in Pehleng? There are two bridges next to each other and both are also in critical stage of failing. I’ve invited our local engineer, Mr. Daniel Isaac, to assess the bridges and he also concluded that both bridges need immediate actions. [Response] Mr. Goodwin: • As mentioned earlier, the VARS component of the project will definitely look into all the bridges and culverts on the primary road networks. [Question] Mr. Bejay Obispo, Councilmen, U Municipal Government: • Since Pohhnpei rains a lot, will the designing phase of Awak bridge factor in amount of rainfall fall and stream flow measurements of the particular or adjoining rivers? [Response] Mr. Goodwin: • The company that will be conducting the VARS will be looking into historical rainfall as well as trends into the future and see what sections of the road network will be affected. They will be looking at rainfall, sea level rise, landslide prone areas and other climate change threads. FSM PRIME Presentation by Eugene J, Argo Environment • FSM PRIME Project Presentation. Questions and Answers: [Question] Tony Sarapio, Kitti Municipal Mayor: • I strongly believe the cost of renovating Awak bridge may not reach $1million. Is it possible to include Pehleng bridge into the priority sites? [Response] John Adolph, Administrator, Pohnpei T&I: • To my recollection, the assessment of the priority site was conducted the very same day of the joint inauguration of FSM President and Congress. T&I team along with the partners assessed all the bridges including Pehleng. I trust that Pehleng bridge was equally assessed resulting in the selection of Awak bridge. • As Mr. Goodwin also stated, 2 bridges at Pehleng are included in the supplementary request for Asian Development Bank (ADB). Ways Forward: Mr. Henry Susaia, Pohnpei State EPA. • We all heard from Mr. Goodwin on the phasis of the FSM PRIME project. We are at the tail-end of the E&A assessment and will be looking forward to the VARS phase. However the VARS will be conducted, we (EPA, T&I, and relevant partners) will keep you informed and engaged. Closing: Felciano Perman, Lieutenant Governor, Pohnpei State: • I believe it is time for our government to work with T&I along with relevant entities to prioritize on our very own VA (vulnerable assessment). We all see how our bridges are becoming degraded, poor drainage system, and outdated culverts. It’s great to seek support from outside such as these big investment projects, however, we all know how slow the processes. • We also need to find alternate routes so when something goes wrong with the primary road networks, people can still be able to move. • We can also take advantage of the renegotiation of the Compact of Free Association (CoFA) and look MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Conference Room Date: November 10, 2020 Time: 10am-11:30am Chairperson: Henry Susaia, EPA Recorder: Eugene J. Attendees: Argo Environmental Ltd – Eugene Joseph DoFA CIU – Wilmer Kilmete Note: Refer attached attendance list for stakeholder attendees PURPOSE • To provide an update on progress, scope and timing of the PRIME Project. • To outline proposed key principles of E&S framework documents and ‘strategies’ to screen and manage possible environmental and social impacts from any Project works (once they are identified). • To receive comment and feedback from stakeholders, in order to complete draft E&S framework documents. • To engage stakeholders in the development of these documents and management decisions for the Project PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions: Hon. Reed Oliver, Governor – Pohnpei State Governor. • It is critical to hold stakeholder meetings with all municipal government represented. We will 1 have record for all the PRIME stakeholder meetings and when the project kicks off, non- participating municipalities will always question why weren’t they involved. Therefore, if possible, the consultations for the upcoming phases such as Vulnerability Assessment (VA) and others should rather take place at the Municipalities. 2 Presentation – Argo Rep: Eugene Joseph Discussion: Governor Oliver: • Pohnpei Transportation Authority (PTA) will be the designated entity to lead construction work. 3 Any other interested and qualified contractors will have to go through bidding process with the office of Transportation and Infrastructure (T&I). • There are many secondary road improvement projects that were funded by FSM Congress in the past that doesn’t meet T&I’s requirements. Most of the FSM Congress funded road projects have impacted T&I’s primary road improvement by poor designing of drainage and culverts. This administration is working closely with DTC&I to standardise our projects. Discussion: Lt. Governor Perman: 4 • As we address climate proofing for our primary road, we should also consider redesigning to accommodate traffic. FSM PRIME_Meeting Notes_Pohnpei_Meeting 3_Nov 10 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Pohnpei, Nov 10 2020 No. Agenda Item / Discussion Discussion: Mayor Rensle, Madolenihmw Municipal Government: • There are 4 ongoing projects for secondary road improvement in Madolenihmw. There was no stakeholder consultation by DTC&I, T&I and local government. This project has exceeded it’s timeline due to some resistance from the communities. Some of the roads were redesigned in 5 a way that will require renegotiation for road easement, but that never took in effect. • E&S are often undervalued due to urgent deliverables of road improvement projects between donors and state government. • Municipal governments don’t have the means to conduct assessments and consultations, therefore will require stronger partnership with state and national governments to make sure development projects are implemented smoothly with community awareness and cooperation. Discussion: 6 Governor Oliver Discussion: 7 Director Henry Susaia - EPA: Discussion: Mr. Hubert Yamada, Director – Division of Resources and Development: • It is important for T&I and PTA to provide their priority projects. This way, when funding coming from outside, we can easily align them with our priority projects. • When we talk about frameworks, it is important to have our own people working in parallel with 8 whoever will draft the framework. There could be many areas we may find ourselves difficult to follow. We need to know what the conditions are so we don’t commit to something we cannot deliver. • The issue with our infrastructure is maintenance. Frameworks are very critical to help with this issue. We lack putting in the necessary maintenance plan to sustain it. • We look forward to the draft frameworks to make sure it reflects our capabilities to implement these infrastructure projects. Other Matters • Madolenihmw Municipal Mayor: The need to revisit our easement laws to make sure it is reflected strongly in the development and management frameworks. 9 • Nett District Administrator: We need to work closely with State Legislature to consider viable and effective options for resettlement. Nett and Sokehs Municipalities are closest to Kolonia Town central and population is becoming dense as we speak. 10 Meeting closed at 11:25 ACTIONS No. Action Item Responsibility Due Governor Oliver: DTC&I to work closely with state partners in the upcoming March 1 phases and make sure grass roots and landowners are involved in DTC&I 2021 stakeholder consultations. FSM PRIME_Meeting Notes_Pohnpei_Meeting 3_Nov 10 2020 2 Chuuk Meeting Notes MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Environmental Project: and Social Safeguards Assessment and Preparation of Instruments Venue: FSMTC, Chuuk Station Date: August 21, 2020 Time: 11:45am Chairperson: N/A Recorder: N/A Attendees: Argo Environmental Ltd - Donsean Mori FSMTC, VP/ Chuuk Station Manager - Minoru Mori PURPOSE Initial Consultation Meeting/ Baseline data collection PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions Consultant with ARGO Environmental, engaged by FSM National Gov to undertake the E&S Impact Assessment for the Road Improvement projects throughout the FSM, including all 4 states 1 PURPOSE OF MEETING: Inform key stakeholders of ongoing PRIME Project Acquire information, baseline data to develop E&S framework Feedback Project Outline Part of boarder PRIME Projects: Prioritized Road Investment and Management Enhancement - Includes the feasibility, design & construction of physical works on the priority road assets to improve the roads resilience to climate-related hazards or events in each state - Types of physical works could include: bridges & crossing improvements/ replace coastal protection, slope stabilisation - Scope of work is still unknown until Vulnerability Assessment & Climate Resilient Road Strategy work completed ARGO engaged in understanding the E&S Assessment in order to prepare instruments for WB appraisal 2 - E&S Management Framework - Resettlement Framework - Labor Management Procedures - Stakeholder Engagement Plan - Other docs. include Generic ESMP & Priority Projects are no longer a key focus, overall primary road will be assessed as priority investments have not been finalized Program of Work Data Gathering- Gov. Departments/ Agencies, Secondary Reports, Field Survey 3 Series of Consultation Meetings- FSM PRIME_Chuuk Meeting Notes_FSMTC_August 21 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, FSMTC, August 21 2020 Obtain required Data GIS Data DM requested any GIS data on the FSMTC communications network. MM stated FSMTC doesn’t have GIS data on existing copper line telephone landline grid and for their aerial fiber optic grid. FSMTC does not own any utility poles, leases CPUC’s utility poles instead. FSMTC a few years back provided composite utility poles to supplement CPUC utility poles but ownership was transferred to CPUC. MM suggested that Argo requests GIS data from CPUC as they have recently surveyed all existing utility infrastructure. Other FSMTC Infrastructure along primary road 4 -Pedestals for underground phone lines, these exist along the roadside from 1.) Seletiw to Nantaku 2.) Sefin, mwan -Cellular/ Data Towers at: 1.) Chuuk State Hospital 2.) Xavier High School 3.) Penia Elementary School (near primary road) 4.) Mwan (Typhoon resistant cellular monopoles 5.) Wichap (near primary road) 6.) Tonachaw (secondary road access) - Underground conduit at the intersection near V6AK radio station -Fiber optic distribution box enclosures alongside primary road (nothing underground, aerial lines to enclosures) MM mentioned that underground telephones and copper telephone network grid will be obsolete as FSMTC is switching telephone network to fiber optic network Feedback on the Project MM commented that the road needs rehabilitation; Not only an inconvenience but a hazard during emergency and disasters. If the roads were to be compared on the same standards as FSMTC, the road would have been shut down years ago. 5 MM further commented that FSMTC repairs the roads near their infrastructure just so they can maintain access. The poor quality of the road impacts their maintenance and repair work, any improvements on the road will impact FSMTC and its clients. 6 Meeting closed at 12:15pm FSM PRIME_Chuuk Meeting Notes_FSMTC_August 21 2020 2 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Department of Transportation & Public Works Date: August 24, 2020 Time: 2:30 Chairperson: N/A Recorder: No Attendees: Argo Environmental Ltd - Donsean Mori CPUC, CFO, Lei Shirai Purpose: Initial Consultation Meeting/ Baseline data collection Proceedings: No. Agenda Item / Discussion Welcome & Introductions Consultant with ARGO Environmental, contracted by FSM National Gov to undertake the E&S Impact Assessment for the Road Improvement projects throughout the FSM, including all 4 states 1 PURPOSE OF MEETING: Inform key stakeholders of ongoing PRIME Project Acquire information, baseline data to develop E&S framework Feedback: opinions & concerns Project Outline Part of boarder PRIME Projects: Prioritized Road Investment and Management Enhancement - Includes the feasibility, design & construction of physical works on the priority road assets to improve the roads resilience to climate-related hazards or events in each state - Types of physical works could include: bridges & crossing improvements/ replace coastal protection, slope stabilization - Scope of work is still unknown until Vulnerability Assessment & Climate Resilient Road Strategy work completed 2 ARGO engaged in understanding the E&S Assessment in order to prepare instruments for WB appraisal - E&S Management Framework - Resettlement Framework - Labor Management Procedures - Stakeholder Engagement Plan - Other docs. include Generic ESMP & Priority Projects are no longer a key focus Program of Work Data Gathering- Agencies, Secondary Reports, Field Survey 3 Series of Consultation Meetings- Obtain required Data 4 DM requested for GIS data on CPUC utility. Lei commented that CPUC power was recently rehabilitated and all their power utility infrastructure was surveyed, so GIS is available. She will follow up with their GIS specialist and forward any data. FSM PRIME_Chuuk Meeting Notes_CPUC_August 24 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, CPUC, August 24 2020] A good portion of the Water and Sewage utility lines are from the TTPI era. Lei will follow up with CPUC advisor Mr. Howell for data and will forward info. CPUC has data on their water sources (deepwells, tanks etc.) will forward info as well. 5 tanks in total: 1) Peniesene 2.) Wichap 3.) Sapuk (Xavier) 4.) Nantaku (Nefo) 5.) Nantaku (Pink Apt. location), of those 5 tanks only 3 are currently in use; 1.) Sapuk (Xavier) 2.) Nantaku (Nefo) 3.) Nantaku (Pink Apt. location) Feedback on the Project Other CPUC infrastructure in Chuuk include: 1.) Weno, Mechitiw Solar Array, which is funded by WB. Location identified but project has not started. Planned 1.5 MW solar plant 2.) Weno, Airport solar plant., which is connected to the Weno power grid 3.) Chuuk high solar plant, also connected to Weno power grid 4.) CPUC power plant solar array, connected to Weno power grid 5.) Mini solar grid on Udot & Satawal 6.) Standalone systems on schools & dispensaries. 5 UNDP recently provided a recent grant to rehabilitate the deepwells. ADB will be providing funding for the CPUC water and sanitation system. Will provide new pipes for water and water storage and rehabilitate existing infrastructure. 6 Meeting closed at 3:20pm ACTIONS No. Action Item Responsibility Due GIS data on power grid and any data on water utility infrastructures 1 CPUC 08/24-25 FSM PRIME_Chuuk Meeting Notes_CPUC_August 24 2020 2 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Environmental Project: and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Office Date: August 25, 2020 Time: 2:00pm Chairperson: N/A Recorder: Yes (Chuukese) Attendees: Argo Environmental Ltd - Donsean Mori Chuuk State Governor - Gov. Johnson Elimo Purpose: Initial Consultation Meeting/ Baseline data collection Proceedings: No. Agenda Item / Discussion Welcome & Introductions Consultant with ARGO Environmental, contracted by FSM National Gov to undertake the E&S Impact Assessment for the Road Improvement projects throughout the FSM, including all 4 states 1 PURPOSE OF MEETING: Inform key stakeholders of ongoing PRIME Project Acquire information, baseline data to develop E&S framework Feedback: opinions & concerns Project Outline Part of boarder PRIME Projects: Prioritized Road Investment and Management Enhancement - Includes the feasibility, design & construction of physical works on the priority road assets to improve the roads resilience to climate-related hazards or events in each state - Types of physical works could include: bridges & crossing improvements/ replace coastal protection, slope stabilisation - Scope of work is still unknown until Vulnerability Assessment & Climate Resilient Road Strategy work completed 2 ARGO engaged in understanding the E&S Assessment in order to prepare instruments for WB appraisal - E&S Management Framework - Resettlement Framework - Labor Management Procedures - Stakeholder Engagement Plan - Other docs. include Generic ESMP & Priority Projects are no longer a key focus Program of Work 3 Data Gathering- Gov. Departments/ Agencies, Secondary Reports, Field Survey Series of Consultation Meetings- Obtain required Data Gov. commented that it's critical that you meet with the communities because they will provide the most useful 4 feedback on how these projects will impact their social lives and their environment. Also, understand the challenges from all aspects; you will realize that land issues and the rights of passage through the people’s land is going to come up often. FSM PRIME_Chuuk Meeting Notes_Governor_August 25 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, Governor, August 25 2020 Feedback on the Project Gov. commented that the Weno circumferential road is exposed to heavy climate impacts. Sapuk, Epinupw and 5 if you look at the road section from Peniesene (Winiasas) to Penia, you’ll find a lateral line of potholes/damages to the road. Water movement from mountain side & exposure to sea eroding road sub-base. Miscellaneous Gov suggested that Argo invite as many stakeholders and meet with them at the Governor’s auditorium. DM confirmed that he will follow up with the chief of staff to reserve the facility. 6 DM requested that the Gov. issue a memo to all department heads informing them of the ongoing assessment and to request departments cooperation in providing critical data to the project. Gov. confirmed that he will send out a memo to department heads right away. 10 Meeting closed at 2:30pm ACTIONS No. Action Item Responsibility Due 1 Gov. Asap Memo to Department heads 2 DM to reserve Auditorium for Stakeholders meeting DM Asap FSM PRIME_Chuuk Meeting Notes_Governor_August 25 2020 2 MEETING NOTES FSM Prioritized Road Investment and Management Enhancements (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Weno Municipality Chamber Date: August 28, 2020 Chairperson: Donsean Mori Recorder: Donsean Mori Attendees: Refer attached attendance list Purpose: • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. Proceedings: No. Agenda Item / Discussion 1 Welcome & Introductions 2 Presentation provided by Argo Environment Ltd (Donsean Mori) Discussion [1st Speaker] Ichkumi: From Iras, Kurassa, Mechitiw, Tunnuk (Based on current condition of roads) [2nd Speaker] If they can continue the road in Sapuk. The current road construction (funded by FSM Congress) will only end at the Mormon Chuuk at Sapuk. Sapuk badly needs rehabilitation of its roads 3 [3rd Speaker] Question: Aren’t you doing the assessment? *Response* Yes [3rd Speaker] FSM PRIME_Chuuk Meeting Notes_August 28 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, August 28 2020 You should conduct the assessment and based on the assessment, we should all meet again and discuss the results. Right now our roads are deteriorated. How do we do our partnership? Who is going to do the feasibility studies? *Response* There will be more groups in the coming months that will conduct the feasibility studies. Just to clarify, we are at the initial stage of the FSM Prime Projects, we are conducting the assessment by collecting baseline data available with the State. We will survey the roads for missing data. We will also engage stakeholders to gain feedback. This is the purpose of the meeting; start awareness and start discussion of potential prioritized investments. [3rd Speaker] Thank you [4th Speaker] Road from Mwan to Neauo is deteriorating. We won't even mention Wichap and Epinupw, that road has deteriorated beyond recognition. If there will be any assessments of the road, please come visit these villages. Thank you [5th Speaker] You mentioned the scope of the assessment is on the primary road. Will this assessment extend to the secondary roads? [Congressman Victor Gouland] If we look at our islands, it's all primary roads. The existing roads we have should all be considered primary access roads because it's the only access road to most communities. We should treat the assessment in the same way. We should assist EPA and Argo in getting all the information they need for this assessment. These FSM Prime new roads will include utilities as well. For instance, the new roads at Sapuk were not planned well. They don’t include utilities. I encourage all the village representatives to cooperate with the teams that will be conducting the assessment so this project can continue without issues. We need to complete the circumferential road around Weno. [3rd Speaker, Finater] Are you working with the utility companies? Is there collaboration between your assessments and these entities? *Response* Yes, CPUC and FSMTC are project partners and have been working closely with our team in providing relevant data for our studies, GIS data of existing utility infrastructures, both water and sewer. [Finater] [Congress Victor Gouland] I think the importance of this assessment is to get as much community support as possible. Community involvement. Give the men access to your communities so they can conduct a thorough assessment. These are usually the problems with past projects. As soon as land owners/ community leaders see developments starting, they put price tags on access to their properties. It's really important that we give them our community support to complete these assessments so we can reap the long term benefits. FSM PRIME_Chuuk Meeting Notes_August 28 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, August 28 2020 *Response* When we were doing the scoping for these projects, these concerns were brought up. Some utilities may require access to properties that are outside the easements. Of course we have the primary road easements already secure but we are also identifying other stakeholders that we’d need to work with. [Finater] Just from our experience with the ADB water project that CPUC is spearheading, Land disputes is a major issue that comes up. We invite you to coordinate with CPUC and possibly joint our negotiations to provide access to water sources at Wichen, Peniesene [Congress Gouland] This is an opportunity for our communities to get development assistance.This project depends on the community willingness to get involved or not. This is why assessment is important, it provides opportunity for communities to provide feedback and data for these projects to consider. Community involvement; help educate our communities on the importance of the collective benefits. For instance, we should all learn from Peniesene: as soon as CPUC engaged the community on possible usage of their water resources, they already started putting dollar signs and blocked off access. Now, this project has been sidelined. We need to educate our communities on the importance of collective benefits. Thank you. *Response* I am glad our congressman touched on those topics. These types of projects comes with conditions, if we don’t have stakeholders involvement or if communities are unwilling then we will lose the benefits of these projects. [Mayor Stephen] I want to talk about the whole section of the village of Mwan. This was completed during the first phase of the Weno project. The engineers that completed this road also brought unintentional problems/issues. They built the roads but they forgot to consider the natural movement of water or water courses. Taro patches have been damaged by stagnant water. During heavy rainfall, new areas are now prone to flooding. We hope this can be considered as part of the priority roads, proper drainage to accompany new roads. So waterflow from the mountains can easily drain out to the sea without damaging farmlands and taro patches and without causing flooding in certain communities. [Brad Mori] Thank you for your comment. We recommended climate proofing the project. However because the project funding for the 1st phase couldn’t accommodate our recommendations, which were to raise the existing road elevations and provide proper drainage, we are now experiencing these issues today. This is the importance of the term “Climate Resilience”, all these should be factored into the project; Drainage, Flooding and Mountain slides, Coastal Erosions. All the data we are gathering; Maps and GIS data will help identify these areas so when the designers come these will be considered. [Weno Municipality, Chief of Staff, Marcellus] We’ve had 2 major assessments this year: 1.) ADB water project 2.) WB FSM Prime. The first one has been approved all because of the communities willingness to cooperate with assessments that accompanied the projects. Just like the previous one, this assessment will also require cooperation from all the villages of Weno in order to get approval. FSM PRIME_Chuuk Meeting Notes_August 28 2020 3 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, August 28 2020 [Victor Gouland] Just to add to the discussion, if communities don't cooperate or get involved in these assessments. This could stop our communities from getting access to these developmental assistance. [Mayor Stephen] This is why it was so important that I called the meeting of Chiefs. So the chiefs can relay these important messages to the people in their respective communities and explain the benefits. Also, there will be a timeframe for the Argo team to visit communities. Chiefs can facilitate the team when they visit the communities, point them in the right direction on who to meet and where to go. If they hold stakeholders meetings in your communities, invite landlords, community members so everyone can understand the project. [Brad Mori] It is also part of our responsibilities through the social and environmental assessment to understand all feedback from the communities, even negative feedback. For instance, if the FSM Prime project will block any activities or if the proposed prioritized investments are part of a significant cultural site or family cemeteries. These are information that we can only get from the communities. [4th Speaker] Aren’t the easements for Weno already complete? What is the situation with our easements? Do they end or have a limit? I thought they were forever. [Victor Gouland] Easements are only for the road reserve areas that have been agreed upon. I believe our role as the community is to guarantee these easements. Show community involvement and participation in the meetings and field surveys Agro and the state focal points, through this assessment, are trying to help the weno communities secure the grant available to us. Even if these easements are already complete, our communities need to guarantee these easements through their involvement and participation in these engagement meetings and field surveys. [Mayor] We need to understand how long it has taken to realize the development we need. Different government administrations in Chuuk come in and go, yet we haven’t seen/realized the important changes that will truly benefit the people. We need to support these types of assessments/projects that will bring the development assistance we need. This is for our own benefit. We should do this for our kids, our students that need road access. Road improvements are essential for development. People need access to essential resources. We need assistance not only for our primary road in town but also for the roads that lead into our villages and communities. [Brad Mori] As far as we are concerned, our single circumferential road is our primary road, no secondary roads. [Filater] When do you expect to visit the village communities? FSM PRIME_Chuuk Meeting Notes_August 28 2020 4 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, August 28 2020 **response** Our field surveys will start last week of August throughout September. We needed to inform all of the Weno communities first before conducting field surveys. While we are on this subject, we kindly request your assistance in allowing safe passage for our men as they conduct the field surveys around Weno. [Congressman Gouland] It’s really in our benefit to assist the work they will be doing. [Sanitation] What is your time frame for your community stakeholders meetings or second round of consultations? **Response** Second round of consultations will be in October. [Sanitation] Can you inform Weno municipality and council of the schedule for your second round of consultations, especially if they will be with the communities? Just to add a comment, it's better to schedule a community meeting on weekends, that's when all community members are available to attend and participate. [Marcelus] Do we know the value of the FSM Prime projects? **response** At the moment, No. Hopefully if it's approved in November, WB can appraise the value of this project. 4 Meeting closed FSM PRIME_Chuuk Meeting Notes_August 28 2020 5 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, August 28 2020 Meeting Photographs: FSM PRIME_Chuuk Meeting Notes_August 28 2020 6 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Environmental Project: and Social Safeguards Assessment and Preparation of Instruments Venue: FSMTC, Chuuk Station Date: August 31, 2020 Time: 10:00am Chairperson: N/A Recorder: N/A Attendees: Argo Environmental Ltd - Donsean Mori Chuuk State Planning- Chief Akapito PURPOSE Initial Consultation Meeting/ Baseline data collection PROCEEDINGS No. Agenda Item / Discussion Welcome & Introductions Consultant with ARGO Environmental, contracted by FSM National Gov to undertake the E&S Impact Assessment for the Road Improvement projects throughout the FSM, including all 4 states 1 PURPOSE OF MEETING: Inform key stakeholders of ongoing PRIME Project Acquire information, baseline data to develop E&S framework Feedback: opinions & concerns Project Outline Part of boarder PRIME Projects: Prioritized Road Investment and Management Enhancement - Includes the feasibility, design & construction of physical works on the priority road assets to improve the roads resilience to climate-related hazards or events in each state - Types of physical works could include: bridges & crossing improvements/ replace coastal protection, slope stabilization - Scope of work is still unknown until Vulnerability Assessment & Climate Resilient Road Strategy work completed 2 ARGO engaged in understanding the E&S Assessment in order to prepare instruments for WB appraisal - E&S Management Framework - Resettlement Framework - Labor Management Procedures - Stakeholder Engagement Plan - Other docs. include Generic ESMP & Priority Projects are no longer a key focus Program of Work 3 Data Gathering- Gov. Departments/ Agencies, Secondary Reports, Field Survey Series of Consultation Meetings- Obtain required Data 4 Chief Akapito commented that Chuuk Planning Office/Chuuk State has not yet received any plans or as-builts from FSM National government as the 1st phase of the road has not been officially turned over FSM PRIME_Chuuk Meeting Notes_Planning_August 31 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, Planning Department, August 31 2020] Chuuk Planning has been working with the Chinese government on the possibility of having a Chinese funded road. Not only for secondary roads but all roads on Weno will be included. They have already completed the Weno road conceptual design. DM requested a copy of the conceptual design. CA will have his engineers provide documents Chuuk Planning has also identified locations of possible cross drainages on the circumferential road around Weno. DM requested that set of data. CA will have his engineers provide documents. [Upon followed up, I was told by Engineer Dave that no coordinates on possible locations of cross-drainage] Most recent projects for the Planning Office on the road were the Penia Peniesene Bridge and the Causeway Bridge. DM requested for As-Builts. CA will have his engineers provide documents. [Upon follow up, only project plans and specifications could be provided] Feedback on the Project CA inquired whether the FSM Prime assessment documents could be used for other road projects. DM is not 5 sure on other project requirements but any data gathered for E&S Impact assessment will be available with DTC&I. No reason to believe this will not be available to state agencies. Miscellaneous 6 CA emphasized collaboration between agencies to avoid double works and efforts. 7 Meeting closed ACTIONS No. Action Item Responsibility Due Planning to provide Conceptual Design for Weno road, As-Builts for recently built bridges and coordinates of possible locations of cross 1 Chuuk Planning 09/03 drainage throughout Weno Roads. [Only plants and specifications for bridges were provided. Planning hasn’t followed through or replied on followup regarding conceptual design and cross drainages.] 2 FSM PRIME_Chuuk Meeting Notes_Planning_August 31 2020 2 MEETING NOTES FSM Prioritized Road Investment and Management Enhancements (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Auditorium Date: September 3, 2020 Chairperson: Donsean Mori Recorder: Donsean Mori Attendees: Refer attached attendance list Purpose: • Inform key stakeholders of the PRIME Project • Acquire information to develop E&S framework documents • Provide stakeholders an opportunity to express opinions/concerns to be addressed in developing the E&S documents and DTC&I management decisions. Proceedings: No. Agenda Item / Discussion Welcome & Introductions [Lt. Governor] State has two major projects that will be funded by the World Bank; Road and Marine port, our dock. Introducing Argo Environmental and roles in the project. 1 EPA,critical focal point on the FSM PRIME. Other focal points, Department of Transportation & Public Works, State Planning Office. All are gathered here because they are important to the project, key stakeholders such as those present, CPUC and Chamber of Commerce. Our Governor's office is thankful for the collaborative efforts between our national government and the World Bank making these important projects possible for the state government. In order for this project to move through, we kindly request that all stakeholders and their respective offices collaborate with Agro and the state focal points. 2 Presentation provided by Argo Environment Ltd (Donsean Mori) Discussion Are there sections of the road where you’d expect improvements are needed to improve resilience to climate related impacts? 3 [Roger Arnold] Thank you to the focals points and representatives of the FSM PRIME Project, this project is essential for our future livelihood as it will work to counter the impacts of climate change, which has recently proven to be a real life threat to all the island states. To answer your question, I feel West pou road needs most improvement. Possibly a conflict of interest because I live there but this leads to my question: Is this project just based on primary roads or are we looking at secondary roads to improve as well. Any improvements will benefit Chuuk but even the newly paved primary roads are experiencing FSM PRIME_Chuuk Meeting Notes_September 3 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, September 3 2020 heavy congestion. Before congestion was only during peak hours and holidays but now we are experiencing traffic on a regular basis. This is why I'm asking about secondary roads. Improvements on these secondary roads could relieve congestion on primary roads. [Response] No definitive labels for primary road and secondary roads. Existing road, paved or unpaved, is mostly considered a primary road as it is still the only road for many to access critical infrastructure and resources on the island. So even the Pou road is a primary road for all the residents there. Although priority road investment has been identified from Airport to Pou Bridge or Pou Causeway. West Pou can still be considered for improvements under FSM Prime project. [Nelson Steven, Acting President of the Senate, Chuuk State Legislature] *Opening Remarks* Within our institutions; both state and national governments, there is already an existing Infrastructure Development Plan with data that considers social and environmental impacts. The implementation of this IDP has been long overdue in our system. I wonder if the WB doesn't need this data anymore? Are state and national governments still considering these plans as they related to incoming development projects? [Elisius Akapito, Chief of Planning, Chuuk State Government] IDP has identified the road network on Weno as a priority. To add to that, the conceptual design for the circumferential road including primary roads and secondary roads has already been completed. It's just a matter of securing funding for these works. This E&S assessment will add depth to our plans, but as far as the conceptual design that has been closed. I hope Argo and the WB are aware of China's commitment to the Weno road, which is already in its third phase. Chuuk state’s proposed concept to China is for the whole Weno road. I hope the WB FSM PRIME projects and proposed ADB roads don’t just focus on Weno. If this happens then other critical road infrastructure on other islands throughout Chuuk, as already identified in the IDP, will remain overdue. Other regions might never see development. [Response] During consultation with WB and Argo, it has been identified in the gap analysis the need to secure and scale up these existing conceptual designs. This is the importance of the social and environmental data gathering works that Argo and its state partners have been undertaking, to add and feed into these designs. The data we are gathering and other frameworks will be needed to support these conceptual designs when presenting our proposals to donor partners. [Mars Akapito, Director of Chuuk Conservation Society] *Opening Remarks* I understand there is the IDP that identifies key road infrastructure that require development. This was developed a while ago by the local and state governments. Where did the idea to have WB develop our roads in Chuuk come from? Has there been coordination between the state government, TC&I (national government) and WB? Or was this idea concocted somewhere foreign and you are just here to explain the concept to the Chuukese people? [Response from Bradford Mori, Director of EPA] It's already been a year since scoping and consultation works started, the existing concept designs were considered but after developing the initial gap analysis through these assessments, we realized that a lot of data/ information is still missing. We need these key informations to be eligible for these fundings. Key Stakeholder from Chuuk understood that the FSM PRIME should have started from Phase 2 of the Chuuk road project, but due to the funding being divided among all four states, we had to select FSM PRIME_Chuuk Meeting Notes_September 3 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, September 3 2020 Priority Road Investments that were guaranteed to be eligible for this specific WB funding. State decided and selected these Priory Road Investments. [Tos Nakayama, Director of Transportation & Public Works] Adding to this discussion, this road project started from the President of the FSM. He met with the heads from WB and requested that during his administration a number of road projects should kick in. The total funding for this FSM PRIME project could be at the upwards of $40M. Chuuk was the only state that identified road improvements as one of its priorities. Other states prioritized bridges . ADB offered additional funding for sections of the road, approx. another $40M. So we are looking at around $80M of funding for our FSM roads. Chief Akapito is now mentioning the China roads improvements. I also understand that there is $18M of approved funding from CPUC to improve its water and sewage systems. All these different projects will lead to road improvements. So, coordination is critical so there will be no duplication of work. The more we coordinate our efforts, the more we can accomplish with our roads. To answer your initial question on what sections of the road where I’d expect most improvements are needed: Mwan to Blue Lagoon or the section where the 1st Phase ended near the Mormon Church all the way to Blue Lagoon Resort. This is for the tourists. [as the tourism industry is still one of Chuuk’s lead investments] Thank you very much. [Roger Arnold, Chuuk Economist] To add to what the director of transportation was saying, I think in the past there were things that were taking place and perhaps it was not well coordinated for all to work together. If I understand correctly, the concept design for the Weno circumferential road was part of a ODA priority project that was submitted 2 years ago. I think this is where it was highlighted and given the fact that the second phase of what was supposed to be the road project for Chuuk state was no longer possible to be carried out under the funding from the Compact of Free Association funding. This is where all came into place. This project on the resilience, it was well discussed during the green climate fund symposium and which was emphasised. I think these discussions might have sprung the concept of assisting Chuuk in these areas. What Tos said is very critical, coordination is key. We need to work together. Given these kinds of funding we are about to receive or are in the pipelines for us to tap. Why not, work with them, work together so we can really build up our infrastructure as needed that has been far being neglected over the years. Thank you. [Brad Mori, Director of EPA] Just to go back to what Director Tos talked about, during the consultations with the WB, the issue with the water and sewage systems and its possible funding from ADB did come up as they weren’t aware of ongoing projects or of what has been funded. It is our wish to coordinate with existing projects/ upcoming projects so we can have a better turnout [Graceful Enlet, Director of Education] *Opening Remarks* Our other islands in Chuuk, outside of Weno, are in desperate need of development. Students walk long distances just to get to school, some have to swim and literally climb mountains just because of the lack of road infrastructure. These are the road investments that are prioritized by other municipalities outside of Weno. I hope that since Weno is getting a majority of these fundings [China Road, ADB, etc], we can see some of these development projects spread to other islands/municipalities outside of Weno. Thank you. [Nelson Steven] Thank you to Director of Transportation, Tos Nakayama, for clarifying that the idea for these projects came from the FSM President. I was with President on his field trip to Ichimantong, Tonoas and his commitments sounded too good to be true. Its true coordination is paramount to fend off other political FSM PRIME_Chuuk Meeting Notes_September 3 2020 3 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, September 3 2020 disparities. There are only a few months left with this current administration, I hope this is picked up by the next administration through the efforts of the current state partners and Argo From a political standpoint, public policy making, to me unifying resources is important. [Mars Akapito, CSS] I asked the question, where did this project come from? Because from listening in to the discussion, it sounds like some of these projects are not coordinated with each other. As we’ve already learned from the Chief of Planning, the China Roads are already in its 3rd Phase. I hope these projects can complement each other, add onto existing plans so that the resulting roads can fit together instead of fighting who will get precedence. I also think the Director of Education’s concerns are taken into consideration. I’m worried these road improvements will come in and just focus on Weno. When are we going to see development on other islands/municipalities? This is why I asked where did these ideas come from? Did someone carve this idea up somewhere and expect us to be content with it? If we want these roads to be most beneficial to Chuukese, when we must start these ideas/plans from within, from our stakeholders and not rely on others recommendations. I’m glad to know that these ideas came from our FSM President. These priority roads should come from our planning and preparations and not from outside where they just come in and expect us to agree. [Response] Yes, these ideas came from the President’s initiative to Pave the Nation. This is the importance of what we are trying to do, engaging with stakeholders so their ideas, thoughts and suggestions can be taken into consideration and not just some foreign idea brought in. [Lei Shirai, CPUC, CFO] When CPUC was visited by PMO and TC&I back in January, this was when the scope was only from Airport to Causeway. One of the reasons they met with CPUC was because they mentioned the WB roads will include utilities; Sewer, Water or any assets CPUC has along the way will be include. Now we are talking about additional priority road investments. Are utilities still included? Considering CPUC now has ADB funding for the water and sewage systems. Or still under discussion now that CPUC has ADB. $4M funded by ADB disaster risk reduction. All four states working together to identify what projects to be funded under that project. (1) Complete the loop for power utilities around Weno. Problem, no more old roads, it would be difficult to install poles and utility lines without any road to access those areas. (This section of road should be considered a state priority road investment, Epinuk to Sapuk) [Elisius Akapito] Thankful for the president's road initiative. Many projects directed to funding the road infrastructure in Chuuk, however, were not coordinated. IPC, Infrastructure Planning Committee? Our IDP is an official document for our nation. Any projects that come in should follow the programs identified in IDP. I have to agree with Director Tos Nakayama to prioritize that Section from Mwan to Neauo because it adds economic benefits to the islands [Tourism, Road leads to resorts & attractions]. We can worry about traffic congestions but these should be secondary, we need to consider the overall economic benefits for Chuuk. IDP should be followed. Different focal point/ lead departments shouldn’t stray from the plans set forth in the IDP. CPUC shouldn’t take initiatives on ADB projects, Argo on WB projects, Planning Office already finished their part on the China Road project. All these projects should be combined, coordinated, so there is other funding for road projects on other islands in Chuuk. [Mars Akapito, Chuuk Conservation Society] It's important to stress that we need fidelity to our existing plans. We cannot react when opportunities pop up. We need to stand our ground on existing plans so it doesn’t seem like we are operating in different departments. We need connectivity of interest. FSM PRIME_Chuuk Meeting Notes_September 3 2020 4 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, September 3 2020 **Clarication** This project belongs to Chuuk state and the FSM, through their respective lead agencies. Argo is just present to conduct the social and environmental impact assessment on behalf of those agencies. Argo will not select or take initiative on the selection of priority investments, state and national will. [Roger Arnold] Collective interest is important. Any findings yet from Agro on Environmental and Social Impact assessment? Beginning stage? **Response** Yes, early stage. Data gathering efforts, Field Survey and Stakeholders consultation. Once draft framework assessment completed will return to stakeholders for feedback [Mars Akapito, Chuuk Conservation] Chuuk Conservation Society is interested in understanding the social safeguards instruments for this project. Encouraging key players to avail these instruments to independent parties and to make sure that they are in compliance to our environmental and social conservation efforts. **Response** We have been collaborating with other NGO, Chamber of Commerce, Chuuk Women’s Council and Chuuk Youth Council, however we are not sure why they didn’t send their representatives today. We will reach out to these more NGOs during our next stage of consultations. [Tos Nakayama] We need to collaborate our efforts, especially on the road easements. Every time we work with other states, they always single out Chuuk as being behind. We need to prove to them that the Chuuk now is different from the Chuuk them. We need to make sure we provide all relevant information to support these projects so they can continue without issue. [Atson Nakayama] Regarding easements for this project. Lets not just focus on providing relevant documents on easement for the prioritized sections already identified. We should start compiling all relevant easement documents for the whole priority road on Weno. Just a comment on road development on other islands and road projects being centered on Weno. Secure those road easements. From my understanding, all only tonoas as more than 50% of their land titles secured. The rest have a lot of land documents missing. [Mars Akapito, Chuuk Conservation Society] Just a clarification, I agree with the completion of the road in Weno. The road projects should just not end in Weno. I am concerned that the scope of the assessments are focused on Weno. [Tos Nakayama] 2 years ago, when WB initially sent their representatives to scope out the marine projects. We sent them to Tonoas, Fefan and Udot. I think they have a good picture of the conditions of all our roads in Chuuk, including neighboring islands. So yes, these are in the pipeline. In fact, I requested. FSM PRIME_Chuuk Meeting Notes_September 3 2020 5 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, September 3 2020 [Graceful Enlet] Multiple road development projects directed towards Weno, is there are possibility that maybe the road is overfunded? Just for your information, Faichuk region already has an infrastructure development plan. These should be considered as well. [Urumai] Mixed feelings on this project. I’m excited that this project aims to complete the Weno roads. But equally concerned that these projects might end in Weno. How does this benefit Chuuk as a whole, when other islands or municipalities aren’t getting their developmental needs, such as road infrastructure developments. We have road paths on Tonoas that connect all villages throughout the islands. We have vehicles that travel those roads. We have docks. We have ongoing economic development projects such as the coconut processing plant. My concern is because I heard from the FSM President himself stating his hopes to develop tonoas roads. I have no questions, just a request that you include tonoas in on these developments plans. If there is anything, development assistance for roads, priority roads investments, please consider tonoas. [Lei Shirai] Part of the beautification of Chuuk project, leaders encouraged improving roadside fences. Some are not already built with concrete. What's the plan there? Will there be any displacement of people? You might not have an answer now but do you think this might be an issue? We have a draft regulation regarding these concrete fences that are already built. Any fence, concrete or what not, that encroach the road easements will be removed at the cost of the builder. When applying for permits, those are considered in our guidelines. Don’t block utilities, don’t encroad government easements [Roger Arnold] Just to add to the request for more development on Tonoas. Since you are focused on the social and environmental impacts for these road projects. There are works in place with Commerce & Industry identifying tonoas as a site for development to take away stresses or pressure of economic development being focused on Weno. 4 Meeting closed FSM PRIME_Chuuk Meeting Notes_September 3 2020 6 MEETING NOTES FSM Prioritized Road Investment and Management Enhancement (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: C&I, Conference room Date: Sept 24, 2020 Time: 11:30am Chairperson: N/A Recorder: N/A Attendees: Argo Environmental Ltd - Donsean Mori C&I, Division Chief - Peter Aten Purpose: Baseline data collection/ Standard Operating Procedures (or Similar) for Land Management on how land acquisition/ compensation is to be undertaken. Proceedings: No. Agenda Item / Discussion Land Easement Scanning Works Apologies from Chief Aten for such a busy week. Mr Tasuo William from Land Management had a funeral and has been out of office since Tuesday, 09/22/2020. There was also another state funeral yesterday that Chief Aten had to attend and that was the reason he could not reassign anyone on Wednesday, 09/23/20. 1 Chief Aten acknowledges that Dino Aliven is correct that Tasuo William is the main person assigned to the vault and that it would be best to wait for his availability. Per Chief Aten, Tasuo William should be back in office this Friday, 09/25/20. If Mr. William is available then, scanning works can start right away, if not then scanning works should be scheduled for early next week before the Sept 30th deadline. Stop by the office Friday at 10am. 1.) Standard Operating Procedures (or Similar) for Land Management on how land acquisition/ compensation is to be undertaken. 2.) Standard compensation rates document for land/assets/crops etc. Chief Aten stated that the Land Management office has been working with a land acquisition schedule that was based off of one from Asian Development Bank from 12-13 years ago. Standard compensation rates range from $15-$50 per square meter. Compensation rate is based on distance from high value land areas, mainly port areas (Seaport and Airport), which receive the highest compensation rate of $50 per square meter. Chief Aten notes that technically by law the compensation rates are expired as land valuation should be reassessed every 10 years. However, due to limited funding there has never been a valuation assessment 2 since. Land Management is still using those rates. Chief Aten further notes that CPUC has adopted the state’s land acquisition rates for their most recent projects (ADB & WB funded) but with a 1% annual increase in those rates. Chuuk State has not increased rates since its adoption more than 12-13 years ago. Chief Aten mentioned that Dino Aliven from Land Management is the right person to get a copy of the Land Acquisition Schedule document from. Dino Aliven is aware of Argo Environmental efforts to compile all these documents so it is best to schedule a meeting with him. Dino Aliven is currently out in the field but if you schedule an appointment with him via email, he should be able to provide a copy of the document. 3 Meeting closed at 12:00pm FSM PRIME_Chuuk Meeting Notes_C&I_September 24 2020 1 MEETING NOTES FSM Prioritized Road Investment and Management Enhancements (PRIME) Project: Project: Environmental and Social Safeguards Assessment and Preparation of Instruments Venue: Governor’s Auditorium Date: November 12, 2020 Chairperson: Donsean Mori Recorder: Donsean Mori Attendees: Refer attached attendance list Purpose: • To provide an update on progress, scope and timing of the PRIME Project. • To outline proposed key principles of E&S framework documents and ‘strategies’ to screen and manage possible environmental and social impacts from any Project works (once they are identified). • To receive comment and feedback from stakeholders, in order to complete draft E&S framework documents. • To engage stakeholders in the development of these documents and management decisions for the Project Proceedings: No. Agenda Item / Discussion Welcome & Introductions [Lt. Governor] 1 Stressed the importance of collaboration between government stakeholders and consultants; when relevant government stakeholders are needed, whether it's for information needed or for consultation meetings, everyone should work together because the FSM Prime project is for the benefit of all. Everyone present has a stake in the project. 2 Presentation provided by Argo Environment Ltd (Donsean Mori) Discussion First concern that was brought up was regarding the disclosure of the draft framework documents. Discussed this extensively within group and clarified the purpose of this round of consultation and the timeline for the disclosure of the draft and final E&S framework documents. In the end, everyone in the room still requested that a FSM PRIME representative shares these documents with all interested stakeholders when they are made available. The more information that can be shared with the stakeholders, the more they can provide quality contribution to the consultation meetings/project. 3 Chief of Commerce and Industry asked whether all the relevant information that has been gathered for the baseline assessment was completed. *Response* Replied that all the agencies were very helpful and that we did receive a lot of useful information from their agencies. Mentioned that we identified land easements that were available particularly for the road sections from the Airport to the Pou bay causeway and although I did scan a good portion of those easements, more works still need to be done by the Land Management office to organize all existing FSM PRIME_Chuuk Meeting Notes_November 12 2020 1 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, November 12 2020 easements. This would be very critical once any other physical works are identified along the primary road. West Pou Road was brought up. Will it be included in the project? Why was it classified as a secondary road? *Response* Lt. Governor assisted in answering that question as he's been periodically updated by Robert Goodwin from PMO. He mentioned that although it might not be included in the Physical works for this round, including the road section in the climate vulnerability studies is critical in getting works in these areas started. CPUC stressed the importance of collaboration between different projects. The local utility corporation has 2 projects in works, one funded by ADB for water and sewage facilities and one funded by WB for a solar plant at Mechitiw. Both these projects will be affected by the FSM PRIME. ADB can start as early as next year. CPUC also stated that it was their understanding (from TC&I during scoping) that the FSM PRIME road from Airport to the causeway will include all utilities; water and sewage. Mentioned that the assessment we completed is just the beginning of a series of studies that will be taken to determine what will be included and what will not. Continued to stress the importance of stakeholders meetings and the whole Participatory Design Approach that's integrated into the FSM PRIME. Question regarding our timeframe. It seemed a bit too promising considering it was stated that we could see detailed designs for the physical works within 2 years. In comparison, the WB Marine Project in Chuuk, which is already approved, is not seeing any physical works within the next 5 years. Mentioned that these projects take time, as all these impacts have to be taken into consideration to avoid, minimize and mitigate. However, my knowledge on the construction timeline is limited. These projects might not even make it that far which is probably why that is still TBA. Chuuk Conservation Society stated their appreciation for their organization's inclusion during these stakeholders meetings. They also asked a similar question to what Kosrae leadership asked; Which of the four state’s physical works will start first? Will they all start simultaneously? Will any of Chuuk’s physical works be affected by delays or complications for other states? Stated that I will take note of this question and will not make too many assumptions but I do understand that one of the objectives of our work is to secure the funding for this project. Once funding is secured, further studies and works in each state should be independent of one another. Hold ups in Pohnpei should not result in delays in other states. Lt. Governor asked if the exact starting and ending points of the Prioritized work in Chuuk is already established? Again, mentioned that while my personal knowledge on this is still limited I will take note of the question. However the whole primary road was assessed and will be further assessed during the VA/CRRS studies and that depending on the results of studies, we can still see modification to the prioritized works. The Governor’s economic advisor and the Chief of C&I asked how the prioritized road was selected. Why was it limited to less than 2 miles of road? Was this due to limitations in funding? *Response* Mentioned that the prioritized section was determined by earlier scoping missions by DTC&I, in consultation with key state stakeholders along with WB. Solicited EPA’s assistance considering they were present during these early missions. EPA mentioned that the scoping missions were based on FSM PRIME_Chuuk Meeting Notes_November 12 2020 2 FSM PRIME: E&S Safeguards Assessment and Instruments Chuuk, November 12 2020 preliminary environmental assessments. Although other road sections may have more economic significance, the selected prioritized road fit the PRIMES objective the most, whereas it needed the most climate proofing solutions as compared to other road sections. EPA clarified that although they were present, they were not part of the selection process. Lt. Governor ended the meeting with comments regarding a similar project that is in the works for Chuuk that will be funded by ADB. Collaboration between all projects is critical if we want to rehabilitate our roads in its entirety. 4 Meeting closed FSM PRIME_Chuuk Meeting Notes_November 12 2020 3 Yap Meeting Notes FSM PRIME - Consultation presentation Meeting Date: Friday, 14Aug 2020 @ 12pm Venue: Ganir Restaurant- Yap State Stakeholder: Council of Pilung (Chiefs) Presenter(s): -Johnathan Fathal-State Planning Chief, -Jacob Falan-EPA Acting-Exec Director & -William Domingo-PMO Resident Engineer Individual Stakeholders: -James Manguwon, Chief of Weloy Municipality -Francis Fithingmow, Chief of Gagil Municipality -Steven Mar, Chief of Tomil Municipality Highlighted points 1. Chief of Weloy noted that the two primary bridges being considered for reconstruction must have an alternative detour route within the village of Nimar so that commuters do not have to go around the loop road to get into town. 2. Chief of Tomil wanted to minimize the destruction of gardens and taro patches along the northern road and if such resources are to be destroyed without alternatives then he should be contacted to mediate with the land owners. 3. Chief of Gagil seeks assistance in relocating the waterline that runs under a portion of the existing Gagil road before any construction of the Northern Road takes effect. He suggests that the waterline be relocated outside the gutter areas. 4. The Chiefs asked that they be allowed to meet with potential contractors and that they be involved in the selection of contractors once the project solicits contractor proposals. 5. Once the E&S assessments are done, the Chiefs would like to choose a member of their own individual municipalities to be their eyes and ears in the government focal group that is administering the project for information-sharing purposes 6. The Council of Pilung would like to be considered in Zoom conferences between government agencies and outside donors, especially on infrastructure projects that takes place in the different municipalities of Yap State. FSM PRIME - Consultation presentation Meeting Date: Tuesday, 15SEPT 2020 @ 1pm Venue: Yap Chamber of Commerce Conference Rm-SBDC Bldg Stakeholder: YCC Key Members and others Presenter(s): -Jonathan Fathal-State Planning Chief, -Jacob Falan-EPA Acting-Exec Director & -Sebastian Tamagken-Civic Affairs. Highlighted points: 1. Name of Bridges to be officially referred to as in A) Donoech instead of Manta Ray Bridge; B) Doqmathing instead of Waab Hardware Bridge. This was embraced by the members as a way to ensure local names aren’t neglected or driven away by local government projects. 2. Bond requirement on contracts for the local companies are an unnecessary requirement in many forms as; 1. Local Companies are poor and cannot afford more restrictions in order to win bids. 2. Local Companies are owned by Islanders and are never at flight risk or others. 3. Northern Road estimate needs to be precise by a certified engineering agent/agency. To date Public Works & Transportation-Dept hasn’t given any clear picture what the costs are for the resurfacing of existing road, repair and/or extension to Tamor, Tamil and Gachpar, Gagil. 4. Recommended to the government to closely work with PW&T for a thorough cost on the Northern primary road and to consider using “Cement” than “Asphalt” for many good reasons in the future. 5. Product Quality to closely consider by all parties related to No. 4. This is based on past experience on the existing road (Northern) not lasting over 10 years before deterioration begin. 6. Road Easement Law—Needing more Public Education to the community in order to avoid conflictions and interferences based on lack of education/information on what Road-Easement is. 7. Government to seriously consider how Local-Contractors can win bids if it means supplementing other means rather than spending local money to the outside world. 8. Side-Walk; this is a major issue around the Capital (Colonia-Town) and shall be seriously considered to ensure pedestrians are always safe on the road at all time. 9. Involving “Local-Artists” perspective on the designing of any projects especially infrastructure to retain/capture the local-taste or image of Yap State where possible. 10. Primary Road needing immediate repair as well; *Around the Lagoon-Needing patching, elevation from tides, sidewalk. * PTS to International Airport Road (flooding, cracked-pave, uneven, sewer leakage). *Water Dam Road-Excessive flooding during rain even light-rains. *Ayrach Hill—Yyin, Fanif Road; cracked and deteriorating fast, unsafe to drivers heading downhill. 11. Gaanelay School Road—Needing pavement to prevent steep drainage into main-road intersection causing cracks on pavement, unsafe for drivers and etc. 12. Proper Drainage Issue—Most areas on the Primary Road do not have proper drainage thus most of the areas are beginning to break/crack between heavy rains and hot sun heating asphalts. 13. Mochoy Road—Crossing Dugor to Adibweq in Weloy Municipality is a Primary Road that was neglected before. This road runs across East-West making commuting more convenient, faster and cost effective. It helps in emergency situation for people on West-Side to reach the Hospital faster and students reaching to Bael-School on a daily basis. 14. Tamil Bridge—This has been on the table for some time in the past. Connecting Colonia to Tamil Side over the bay. Easier and shorter for commuters, emergency situation, school access and etc. 15. Yap State Hi-Way or Freeway—Build an Island Freeway from North-South with exits into respective communities, down-town and etc. Serves as main road in case of inundation or floods during heavy storms. 16. Government to define Primary Road and Secondary Roads. 17. Mulroo Bridge—Between Ace’s Mart 1 Store and Ace’s Mart 2 Store. Needing excavation to free up debris stuck underneath as well as elevation to prevent submerging during high tides. 18. Ganir Bridge—Government to do immediate repair and enable yachts to anchor inside Lagoon and etc. Meeting Photographs FSM PRIME - Consultation presentation Meeting Date: Friday, 18SEPT 2020 @ 10am Venue: Yap State Legislature Chamber Stakeholder: Yap State Legislature members Presenter(s): -Johnathan Fathal-State Planning Chief, -Victor Bamog- Director of Planning & Budget -Theo Thinnifel- Director of Public Works Individual Stakeholders: -Jerry Fagolmul- YSL Floor Leader -John Maswemai- YSL Vice Speaker -Jesse Ragilmar-YSL Committee on Gov’t, Health, & Welfare Highlighted Points • Road Easement Law—Needing more Public Education to the community in order to avoid conflictions and interferences based on lack of education/information on what Road-Easement is. • Northern Road estimate needs to be precise by a certified engineering agent/agency. A maintenance proposal for the project must be projected on a yearly basis. • Any reports or stages of the project that is documented must be shared with the Yap State Legislature. • Safety and continual flow of traffic must be ensured during the implementation of the project so that commuters will not be hampered in any way. • The Division of Land Resources must be made aware of all land-based projects to ensure that project operations do not infringe on private property. • The cultural and customary rights of the citizens of Yap must take paramount during the implementation of the project and that the focal group should ensure those rights in all aspects of planning. FSM PRIME - Consultation presentation Meeting Date: Tuesday, 20OCT 2020 @ 1pm Venue: YSPSC (Yap State Public Service Corporation) Conference Room Stakeholder: YSPSC General Mgr, Asst. Mgr, Division Heads and others Presenter(s): -Jonathan Fathal-State Planning Chief, -Jacob Falan-EPA Acting-Exec Director & -Sebastian Tamagken-Civic Affairs. Highlighted points: 1. According to the General Manager-Mr. Faustino Yangmog and Assistant Manager-Mr. Victor Nabeyan, YSPSC has submitted its underground power-line layout to the state for consideration in the future. It is their hope to have this plan be part of the state future plan where the shoulder(s) of the primary road be reserved for YSPSC’s Underground Power-Line. This plan is considering north-south primary road and the Loop road. According to Chief of Planning-Mr. Jonathan Fathal the plan has been received by his office and submitted to the Governor for review and funding consideration. 2. Concern by YSPSC regarding northern road extension plans namely at the end-of-pave next to the FMI and Sports Complex compounds leading to Gagil Municipality. (Please refer to FMI-Sports Complex Simulating map pic). Based on instructions by the government in the past (Public Works & Transportation-Dept) the main road around that particular area will be relocated to give more space to the FMI (Fishery & Maritime Institute) Campus and the Sports Complex space for expansion. Thus the power lines near those areas have been laid in the bushes supposedly where the primary-road will be one day. This is a question whether or not this is what the state is still planning on doing as currently this sits as a challenge to the power company having to drive in bushes for regular maintenance and emergency repair. These are the two major points by the YSPSC. Aside from that they are very keen and supportive of the Prime-Road project for the nation and states. Further, they continue to extend their supports on anything they can do to help in terms of locations of power line, sewer & water lines and etc. Note: Please note on FMI-Sports Complex Simulating map as a rough sketch by us (civic affairs) and YSPSC will assist in providing the actual GIS plot-map, if required. Meeting Photographs FSM PRIME - Consultation presentation Meeting Date: Friday, 06 November 2020 @ 3pm Venue: Council Of Pilung Meeting Room Stakeholder: 10 Municipal Chiefs and others Presenter(s): -Jonathan Fathal-State Planning Chief, -Victor Bamog-Director of Office Planning and Budget & -Sebastian Tamagken-Civic Affairs. Highlighted points: 1. Chiefs were given opportunity on the presentation with not much concern. 2. They were also briefed on other Stakeholders’ meetings taken place with their approvals and blessings to continue work with other stakeholders for more public comments. 3. Tamil Chief-Steven Mar recommended to the working group to work closely with YSPSC regarding their power-lines next to FMI and Sports Complex (as highlighted during YSPSC’s meeting report on October 20, 2020) to ensure that the primary road will coincide with their current layout otherwise they might need to realign back to existing road, should they choose to be next to main road. Otherwise, the choice is entirely up to YSPSC’s how they layout their power poles around that area without any objection by Tamil Chief Mar. 4. All 10 Chiefs made light comments on the presentation as an indication that they are in one accord with the current plan(s). They gave their full blessings to proceed on every phase necessary for the project to begin as soon as practicable for the state. 5. Chairman of the Council-Chief Bruno Tharngan thanked the group and welcome any future updates there may be for the council to consider. Lastly, the council is welcoming community meetings should the group feel necessary. Otherwise, each of the 10 Chiefs will take full responsibility in conveying the message to each of their respective communities. Meeting Photographs FSM PRIME - Consultation presentation Meeting Date: Thursday, 12NOV 2020 @ 12pm Venue: Media & Protocol Div., Conference Room Stakeholder: Yap Women’s Association (YWA) & Kids of Ruuq Community (KORC) Youth Group Presenter(s): -Jonathan Fathal-State Planning Chief, -Jacob Falan-EPA Acting-Exec Director & -Sebastian Tamagken-Civic Affairs. Highlighted points: 1. Youths emphasis on proper drainage and sidewalk especially during rainy days and hard to walk before/after school. 2. YWA Chairwoman-Laura T. Ngaden inquiring of Ganir Bridge as the most condemned bridge yet not being considered under this phase. 3. YWA recommending to the government closure of the Ganir bridge for public safety as it deem obviously necessary to prevent any possible injury in the future. 4. When is the Secondary Roads to be developed as more and more people are traveling on them due to enormous numbers of vehicles being imported on to the island. 5. When is the PRIME actual work should begin? 6. IOM Manager—Philip Raffilipiy: With regards to the Climate Change, elevation of the lower roads should be considered including drainage that shoots out to the taro patches causing taro patches damages. 7. Number of vehicles imported to the island should be seriously looked at as more and more cars are coming in while no exit for broken ones causing more issues not only on existing primary road, but environmental impacts in communities. 8. How is the soil analysis being done for both primary and secondary roads? This is to ensure that there won’t be any poor plans to leave other side properties damaged such as gardens/taro patches. 9. Everyone is happy to have learned the information and will pass it on to both the Yap Women’s Association respective members as well as other Youths’ groups around the island for information and comments as well. 10. Note: Because of school day and during lunch hour; Lunch packets were arranged for refreshments which turned out perfect as it gave energy for more discussions. Meeting Photographs