Sample Procurement Plan I. General 1. Project Information Project Name: Rain fed Agriculture and Livestock Project (RALP) Country: YEMEN Project ID: P089259 Credit Number : IDA Cr.#4220/Yem 2. Bank's approval date of Procurement Plan Original: Revision 1: July 15, 2009 Revision 2: January 18, 2010 Revision 3: November 20,2010 Revision 4: April 19, 2011 Revision 5: March 10,2012 Revision 6: July 9 , 2012 Revision 7: October 16 , 2012 Bank's approval date : November 19,2012 Revision 8: April 14 , 2013 Bank's approval date April 22 , 2013 Revision 9: June 3,2013 Bank's approval date June 21 , 2013 Revision 10 : October 21,2013 3. Date of General Procurement Notice: 30,September, 2009 issue No. 759 latest update ; UNDB print Edition : issue No .781 , 31-8-2010 Posted online : 3 August 2010 II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Prior Review 1a. Procurement Category Comments Threshold (USD) Goods ≥100000 All ICB, first 3 contracts irrespective of value, and all contracts > 100,000 Works ≥200000 All ICB, first 3 contracts irrespective of value, and all contracts > 200,000 Procurement Method 1b. Procurement Method Threshold (USD) Comments ICB and LIB (Goods) ≥ 300000 NCB (Goods) < 300,000 NS/IS( minimum of three quotations)(Goods) < 25000 <50,000 for contracts under Part C ICB (Works) ≥ 500,000 NCB (Works) < 500,000 (N S) (three quotations)(work) < 25000 <50,000 for contracts under Part C 2. Prequalification. Bidders for Works shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): <30,000 4. Reference to (if any) Project Operational/Procurement Manual: Not Prepared 5. Any Other Special Procurement Arrangements: NA 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet 11/26/2013 1 Prepared by: Ali ashaish PS RALP Project III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review 1a. Procurement Category Comments Threshold (USD) Consulting Firms (Competitive) >100000 Consulting Firms(CQ) and Least Cost Selection (LCS) First 3 contracts under each method of selection Consulting Firms (Single Source) ALL CONTRACTS Individual Consultants (Competitive) >50000 Individual Consultants (Single Source) ALL CONTRACTS Procurement Method Threshold 1b. Procurement Method (USD) Comments QCBS > 100,000 QBS NA FBS NA LCS <100,000 CQS <100,000 To be used if it meets with the requirements of paragraph 3.10 of the Consultant Guidelines for Single Source Selection, Single Source (Firms) < 50,000 with the provisions of paragraphs 3.9 through 3.13 of the Consultant Guidelines. To be used if it meets with the requirements set Individual Consultants (Competitive) forth in paragraphs 5.1 through 5.3 of the Consultant Guidelines. To be used if it meets with the requirements set forth in paragraph 5.4 of the Consultant Individual Consultants (Single Source) Guidelines. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $<=100000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Note: OPCPR list of ceilings can be found here http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet 11/26/2013 2 Prepared by: Ali ashaish PS RALP Project 11/26/2013 3 Prepared by: Ali ashaish PS RALP Project 11/26/2013 4 Prepared by: Ali ashaish PS RALP Project Procurement Plan for Goods/Works/Non-Consulting Services YEMEN P089259 : Rainfed Agriculture and Livestock Project (RALP) IDA Cr.#4220/Yem ** Applicable in case of Bank's prior review Prequalification No Bank’s No No Obj ection Objection Obj ection from Bank Bank’s No to Bid Goods/ Rev iew by from Bank for Bid Bid Contract Name, City, and Country Completion Procurement Domestic Prequalifi Obj ection to SL Package/ Bank for Draft Ev aluatio Preparation of Bid Contract Award Evaulation Contract Contract Expenditure No. Reference No. Description of Goods/ Works Works/ (Prior/ Method Preferenc cation e (yes/no) (yes/no) Prequalific n of Document (Date) Bidding Document Bid Inv itation (Date) Closing Opening Decision (Date) Report and Signed Value Currency Contract No. of Contractor (incl. Zip of Contract incurred to Date Comments NCS Post) ation Prequalifi (Date) (Date) (Date) Code if US) (Date) document cation (Date)** Contract s (Date)** Applicatio Award n (Date)** (Date)** Planned No No NA NA NA NA NA NA NA NA 11-Nov-07 AL-Maktaba Office Supplies P.O. BOX Rev ised 1 RALP/ PSU /G/NS /1 /2007 Suppl y Sta ti ona ry for Project s upport Uni t (PSU ) . Goods Prior NS No No NA NA NA NA NA NA NA NA 621,625 YER RALP/G/1/2007 3134 Sana,a -Republic of Yemen 621,625 Completed Actual No No 23-Jul-07 NA 30-Jul-07 NA 14-Aug-07 01-Oct-07 29-Oct-07 04-Nov-07 25-Nov-07 Planned Procurement of (Computers a nd offi ce a ppl i a nces for (23) Regi ona l No No 03-Nov-07 11-Nov-07 12-Nov-07 12-Dec-07 12-Dec-07 26-Dec-07 02-Jan-08 09-Jan-08 20-Mar-08 ALGWDAH For Trading Co. P.O . BOX Rev ised 2 RALP/G/NCB/02/2007 a gri cul tura l offi ces i n ( 5) Governora tes . (SANA,A, LAHJ, AL-Mhweet Goods Prior NCB No No NA NA NA NA NA NA NA 80,270 USD RALP/G/1/2008 19871 Sana,a -Republic of Yemen 80,270 Completed ,Hodei da ,Ha jja ,a ) Actual No No 01-Nov-07 06-Nov-07 11-Nov-07 12-Dec-07 12-Dec-07 26-Jan-08 17-Feb-08 19-Feb-08 24-Mar-08 Planned No No 18-Nov-07 01-Dec-07 07-Dec-07 06-Jan-08 06-Jan-08 20-Jan-08 27-Jan-08 03-Feb-08 24-May-08 TEHAMA TRADING COMPANY Procurement of Tra ns porta ti on vehi cl e for Project s upport Uni t (PSU ) . Rev ised 3 RALP/G/NCB/03/2007 /Sa na ’a Goods Prior NCB No No NA NA NA NA NA NA NA NA 28,500 USD RALP/G/2/2008 Shmsan street .- P .O. B OX 4422 28,500 Completed HODEIDAH- Republic of Yemen Actual No No 05-Nov-07 01-Dec-07 07-Dec-07 15-Jan-08 15-Jan-08 30-Jan-08 17-Feb-08 24-Feb-08 18-Oct-08 Planned No No 28-Feb-08 15-Mar-08 16-Mar-08 30-Mar-08 30-Mar-08 06-Apr-08 13-Apr-08 20-Apr-08 12-Apr-08 Ard Hemier Trading for office ,house Rev ised 4 RALP/G-NS/O1/2008 Offi ce furni ture Project s upport Uni t (PSU ) . s a na ,a Goods Prior NS No No NA NA NA NA NA NA NA NA 4,835 USD RALP/G/3/2008 ,school Furnture sale P. o . BOX : 20116 4,835 Completed Sana,a -Republic of Yemen Actual No No 01-Mar-08 NA 01-Mar-08 18-Mar-08 18-Mar-10 24-Mar-08 01-Apr-08 05-Apr-08 10-Apr-08 Planned No No 28-Feb-08 13-Mar-08 16-Mar-08 15-Apr-08 15-Apr-08 29-Apr-08 13-May-08 20-May-08 RALP/W/4/2008Adde 10-Feb-09 REHABILITATION OF REGIONAL AGRICULTURAL OFFICES i n (10) di s tri cts ( n.contract 1--2009 Mohammed Hassan Hajib, For Trading Rev ised 5 RALP/ W/NCB/01/2008 3) Governora tes ( Sa na ’a -La hej-Al mhweet) Works Prior NCB No No NA NA NA NA NA NA NA 242,995 USD Amend. contract 2-- & Contracting Sana,a -Republic of Yemen 14-Aug-09 231,791 Completed Actual No No 25-Jun-08 28-Jun-08 01-Jul-08 30-Jul-08 30-Jul-08 12-Aug-08 07-Sep-08 20-Sep-08 2008 01-Aug-09 Planned No No 30-Mar-08 10-Apr-08 15-Apr-08 15-May-08 15-May-08 29-May-08 05-Jun-08 12-Jun-08 11-Dec-08 RALP/W/5/2008/ Mohammed Gay ed Al-Waghdi for Rev ised 6 RALP/ W/NCB/ 02/2008 Reha bi l i ta ti on of GDAR Hea d offi ce Ma i ntena nce /SANA,A Works Prior NCB No No NA NA NA NA NA NA NA NA 7,562,443 YER With Adden. Contract Trading &General contracting P. O. BOX 09-Jan-09 7,562,443 Completed 1-2008 : 11742 Sana,a -Republic of Yemen Actual No No 25-Jun-08 28-Jun-08 01-Jul-08 30-Jul-08 30-Jul-08 09-Sep-08 08-Oct-08 11-Oct-08 01-Dec-08 Planned No No 28-Mar-08 15-Apr-08 16-Apr-08 30-Apr-08 30-Apr-08 10-May-08 25-May-08 08-Jun-08 24-Feb-09 RALP/W/1/2009/ Mohammed Gay ed Al-Waghdi for Reha bi l i ta ti on & Decora ti on of l i bra ry a nd Ha l l Centra l Veteri na ry Rev ised 7 RALP/ W/NS//03/2008 La bora tory ( CVL) Sa na ’a Works Prior NS No No NA NA NA NA NA NA NA NA 4,744,686 YER With Adden. contract2- Trading &General contracting P. O. BOX 24-May-09 4,744,686 Completed 2009 : 11742 Sana,a -Republic of Yemen Actual No No 28-Mar-08 NA 06-Dec-08 24-Dec-08 24-Dec-08 28-Dec-08 19-Jan-09 24-Jan-09 28-Apr-09 Planned No No 05-Nov-08 15-Nov-08 22-Nov-08 22-Dec-08 22-Dec-08 01-Jan-09 08-Jan-09 15-Jan-09 02-May-09 Sabeha Trading Co. Zubiri street P .O. B RALP/ GDAR / G/NCB/4/ Procurement of (5) vehi cl es 4WD) for publ i c pri va te pa rtners hi p for Rev ised 8 2008 veteri na ry s ervi ces Goods Post NCB No No NA NA NA NA NA NA NA NA 82,500 USD RALP/G/2/2009 OX : 15174 SANA,A 05-Sep-09 82,500 Completed Republic of Yemen Actual No No 06-Nov-08 NA 23-Dec-08 14-Jan-09 14-Jan-09 22-Jan-09 NA 01-Feb-09 25-Aug-09 Planned No No 15-Dec-08 NA 03-Feb-09 05-Mar-09 05-Mar-09 11-Mar-09 NA 23-Mar-09 22-May-09 RALP/G/3/2009 TEHAMA TRADING COMPANY Procurement of ( VAN & pi ck up 4*4 doubl e ca bi n for (Centra l Rev ised 9 RALP/ GDAR/G /NCB/3/2009 Veteri na ry l a bora tory (CVL). Goods Post NCB No No NA NA NA NA NA NA NA NA 37,100 USD with addend.contract Shmsan street .- P .O. B OX 4422 04-Nov-10 37,100 Completed on ( 4/10/2010) HODEIDAH Republic of Yemen Actual No No 31-Dec-08 NA 03-Feb-09 21-Feb-09 21-Feb-09 06-Mar-09 NA 23-Mar-09 17-Oct-10 Planned No No 05-Jan-09 NA 04-Feb-09 07-Mar-09 07-Mar-09 21-Mar-09 NA 28-Mar-09 31-Jul-09 Leaders Technology ,, Maqadisho street RALP/ GDAR/ CVL/G/NCB/ Suppl y a nd i ns ta l l furni ture a nd equi pments for l i bra ry a nd RALP /G/4/2009 / with Rev ised 10 04/2009 conference ha l l ) i n Centra l Veteri na ry La bora tory (CVL ) SANA,A Goods Post NCB No No NA NA NA NA NA NA NA NA 48,060 USD /Adden.contract3-2009 P.O. BOX: 26034 Sana'a - Republic of 31-Aug-09 48,060 Completed Yemen Actual No No 07-Feb-08 NA 14-Feb-09 14-Mar-09 14-Mar-09 13-May-09 NA 01-Jun-09 02-Sep-09 Planned No No 25-May-09 30-May-09 31-May-09 15-Jul-09 15-Jul-09 30-Jul-09 06-Aug-09 13-Aug-09 Brothers INT,L.Co.LTD - S .Ring.RD P. 26-Dec-09 RALP/G/5/2009 with RALP/ GDAH/G/NCB/ Suppl y a nd i ns ta l l Inci nera tor for the Centra l Veteri na ry La bora tory O. BOX ;11482 SANA,A Rev ised 11 07/2009 (CVL ) Sa na ’a Goods Post NCB No No NA NA NA NA NA NA NA NA 41,990 USD addend.cont. no 2/ Republic of Yemen 24-Feb-10 41,738 Completed and Deducted Liquidated Damages 2010 extend period Actual No No 25-May-09 NA 31-May-09 30-Jun-09 30-Jun-09 27-Jul-09 NA 27-Sep-09 20-Mar-10 Planned No No 12-May-09 NA 31-May-09 30-Jun-09 30-Jun-09 15-Jul-09 25-Jul-09 02-Aug-09 Al-Hadha Furnuture &Carpets co. 27-Nov-09 Suppl y offi ce Furni ture for a gri cul tura l offi ces 5 Governora tes (HADFUR) Hadda street P. O. BOX : Rev ised 12 RALP /G/NCB/ 06/2009 (s a na ,a ,l a hj,hodeda h.a l mhweet,ha jja ) Goods Post NCB No No NA NA NA NA NA NA NA NA 27,320 USD RALP/G/6 /2009 3968 SANA,A 11-Jan-10 27,320 Completed Republic of Yemen Actual No No 12-May-09 NA 31-May-09 01-Jul-09 01-Jul-09 12-Aug-09 NA 13-Oct-09 29-Dec-09 Planned No No 15-Oct-09 NA 25-Oct-09 24-Nov-09 24-Nov-09 08-Dec-09 NA 15-Dec-09 Jumaan Trading &Investment Co.(YJSC) 28-Mar-10 AL-Zubairy street P.O. Box: 2765 Suppl y a nd Ins ta l l Genera tor for the Centra l Veteri na ry La bora tory Rev ised 13 RALP/CVL/G/NCB/11/2009 (CVL ) Goods Post NCB No No NA NA NA NA NA NA NA NA 85,850 USD RALP/G/7 /2009 SANA,A 85,850 Completed Republic of Yemen Actual No No 28-Aug-09 NA 06-Sep-09 12-Oct-09 12-Oct-09 10-Nov-09 NA 28-Dec-09 27-Mar-10 Planned No No 05-Sep-09 NA 19-Sep-09 03-Oct-09 03-Oct-09 10-Oct-09 NA 17-Oct-09 Maktabati Stationery Hadda street P. O. 14-Dec-09 BOX ; 19613 SANA,A Rev ised 14 RALP/ PSU /G/NS /1 /2009 Suppl y Sta ti ona ry for Project s upport Uni t (PSU ) . Goods Post NS No No NA NA NA NA NA NA NA NA 4,323 USD RALP/G/8 /2009 Republic of Yemen 4,323 Completed Actual No No 05-Oct-09 NA 17-Oct-09 31-Oct-09 31-Oct-09 04-Nov-09 NA 14-Nov-09 21-Nov-09 Engineering Technologies for Consultant Planned No No 17. Feb. 09 01-Mar-09 08-Mar-09 22-Apr-09 22-Apr-09 06-May-09 20-May-09 27-May-09 Services &Supplies Bait BOS ,50 Sothern 03-Jun-10 RALP/G/1 /2010 ST. Suppl y a nd Ins ta l l La bora tory Benchi ng Equi pments for ( Centra l Rev ised 15 RALP/ GDAH/G/ICB/05/2009 Veteri na ry l a bora tory (CVL) SANA,A Goods Prior ICB No No 28-Jun-09 12-Jul-09 15-Aug-09 29-Sep-09 29-Sep-09 13-Oct-09 20-Oct-09 27-Oct-09 169,936 USD with addend.contract P.0 .BOX 7091 SANAA-Republic of 169,936 Completed no 1/2010 Yemen Actual No No 19-Jul-09 03-Aug-09 15-Sep-09 01-Nov-09 01-Nov-09 04-Jan-10 06-Jan-10 03-Feb-10 31-May-10 Planned Purcha s e of ( 2) vehi cl es (Pi ck up 4*4 doubl e ca bi ns ) for Regi ona l No NO 01-Nov-10 NA 08-Nov-10 08-Dec-10 08-Dec-10 23-Dec-10 NA 07-Jan-11 TEHAMA TRADING COMPANY 26-Feb-11 RALP/ Rev ised 16 RALP/RVL/G/NCB/2/2010 Veteri na ry l a bora tori es .RVL Goods Post NCB No NO 12-Jul-10 NA 24-Jul-10 24-Aug-10 24-Aug-10 24-Aug-10 NA 08-Sep-10 46,400 USD RVL/G/2/2010 Shmsan street .- P .O B OX 4422 46,400 Completed HODEIDAH Republic of Yemen Actual No No 12-Jul-10 NA 24-Jul-10 24-Aug-10 24-Aug-10 24-Oct-10 NA 28-Nov-10 15-Dec-10 Planned No NO 15-Sep-10 NA 22-Sep-10 22-Oct-10 22-Oct-10 06-Nov-10 NA 13-Nov-10 15-Aug-11 Inter Tek Supply AL-Zubairy street Suppl y a nd i ns ta l l Compl ementa ry equi pment for Regi ona l l a b i n Rev ised 17 RALP/ RVL/G/NCB/1 /2011 (Abs ) HAJJA Gov. Goods Post NCB No No 05-Apr-11 NA 12-Apr-11 12-May-11 12-May-11 27-May-11 NA 03-Jun-11 56,198 USD RALP/G/ 1 /2011 P.O. Box: 11192 Sana'a - Republic of 56,198 Completed Yemen Actual No No 05-Jan-11 NA 22-Jan-11 22-Feb-11 22-Feb-11 09-Apr-11 NA 15-May-11 17-Aug-11 Suppl y a nd Ins ta l l Autocl a ve a nd wa s te wa ter trea tment pl a nt the Planned No NO 15-Oct-09 22-Oct-09 29-Oct-09 13-Dec-09 13-Dec-09 27-Dec-09 03-Jan-10 10-Jan-10 AGMIN ITALY s r I Vicolo,Trave4 - 18-Oct-11 Amendment : (Modify the Method and Conditions of P ayment the WB NO objection Letter dated (May 16, 2011)P rior signed the original contract on (May 21,2011 ). Addendum: s ys tem) for Centra l Veteri na ry l a bora tory (CVL) SANA,A 37121Verona (change the Brand &country of origin for tow items included the original contract the WB NO objection Letter to the Addendum dated (October 17, 2011) the Addendum signed on Rev ised 18 RALP/CVL/G/ICB/1 /2010 Goods Prior ICB No NO 25-Oct-10 08-Nov-10 28-Nov-10 12-Jan-11 12-Jan-11 27-Jan-11 03-Feb-11 10-Feb-11 106,893.23 EUR RALP/G/2 /2011 Italy 31-Dec-13 (October 18, 2011). Actual No No 25-Oct-10 08-Nov-10 28-Nov-10 12-Jan-11 12-Jan-11 06-Mar-11 05-Apr-11 21-May-11 Planned Suppl y a nd i ns ta l l offi ce furni ture for centra l epi demi ol ogi ca l uni t i n No No 27-Nov-10 NA 10-Dec-10 24-Dec-10 24-Dec-10 07-Jan-11 NA 14-Jan-11 12-Jul-11 SAM FOR IND.& TRADING Aldairi Rev ised 19 RALP/GDAH/G/NS/1 /2011 (Di rectora te Genera l of Ani ma l Hea l th a nd Veteri na ry Qua ra nti ne Goods Post NS No No 02-Apr-11 NA 10-Apr-11 24-Apr-11 24-Apr-11 01-May-11 NA 08-May-11 851,000 YER RALP /G/3/2011 street P.O . BOX 2736 Sana'a - Republic 851,000 Completed of Yemen (DGAH&VQ). Actual No No 27-Apr-11 NA 07-May-11 21-May-11 21-May-11 30-May-11 NA 12-Jun-11 26-Jun-11 Planned No No 09-Jul-11 NA 19-Jul-11 03-Aug-11 03-Aug-11 13-Aug-11 NA 28-Aug-11 19-Jul-11 Leaders Technology ,, Maqadisho street Rev ised Procurement of (5)computer s ets (i ncl udi ng one des i gned for da ta No No NA NA NA NA NA NA NA NA 20 RALP/GDAD/G/NS/2/2011 ma na gement ) &offi ce a ppl i a nces for (Di rectora te Genera l of Ani ma l Goods Post NS 8,148 USD RALP /G/4 /2011 P.O. BOX: 26034 Sana'a - Republic of 8,148 Completed Yemen Actual Devel opment (DGAD). No No 07-May-11 NA 09-May-11 23-May-11 23-May-11 30-May-11 NA 19-Jun-11 10-Jul-11 Planned No No NA NA 30-Sep-09 15-Oct-09 20-Oct-09 20-Nov-09 20-Nov-09 20-Dec-09 30-Dec-09 14-Jan-10 30-Jun-11 The contract awarded through avian influenza Prevention &Control Project (AIPCP) , The orginal contract Value is ( USD M / S .C STYRCOOL for Reform and Improvement AI lab in new building central No No 01-Nov-10 20-Nov-10 27-Nov-10 27-Dec-10 27-Dec-10 03-Jan-11 07-Feb-11 12-Feb-11 31-Dec-12 250464 ) only (USD 142915.95 paid from the influenza Prevention &Control Project (AIPCP). . Rev ised 21 AI /W/NCB/ 01/2010 Works Prior NCB NA NA 107,548.05 USD AI/W/1/2011 Industry, A/C &Contracting 88,532 Veterinary Laboratory (CVL) SANA,A YEM EN The remaining amount of contract ( USD 107548.05 ) will be paid from RALP due to the closing date of AI Project in addition to Actual No No NA NA 01-Nov-10 20-Nov-10 27-Nov-10 27-Dec-10 27-Dec-10 25-Jan-11 07-Feb-11 19-Feb-11 31-Dec-12 the delay happened to complete this contract due to unpaid the direct payments .as agreed during cairo mission march 2012 . Planned No No NA NA 30-Aug-09 NA 30-Jun-09 14-Aug-09 14-Aug-09 01-Nov-09 28-Oct-09 12-Nov-09 24-M ay-11 The contract awarded through avian influenza Prevention &Control Project (AIPCP) but unpaid due to the Procurement of Mobi l e GIS uni ts for profes s i ona l GIS ma ppi ng Rev ised 22 AI/ G/NS / 2/2011 a ppl i ca ti ons uni t (2) for moni tori ng i n (DGAHVQ) Goods Post NS No No NA NA 15-M ar-11 NA 19-M ar-11 02-Apr-11 02-Apr-11 07-Apr-11 NA 14-Apr-11 6,800 USD AI/G/4/2011 Leaders Technology yemen 6,800 closing date of AI project, so ALL the contract Value paid from RALP Project.as agreed during cairo Actual No No NA NA 15-M ar-11 NA 19-M ar-11 02-Apr-11 02-Apr-11 05-Apr-11 NA 24-Apr-11 29-M ay-11 mission march 2012 Planned No No NA NA 30-Jan-09 03-M ar-09 30-Aug-09 14-Oct-09 14-Oct-09 30-Dec-09 28-Dec-09 12-Jan-10 11-M ay-11 The contract awarded financed through avian influenza Prevention &Control Project (AIPCP) but unpaid Procurement of equi pments for i mprovement s urvei l l a nce network & Rev ised 23 AI/ G/NS / 3/2011 tra i ni ng regi ona l centers (s ta ff) i n CVL Goods Post NS No No NA NA 09-Feb-11 NA 16-Feb-11 02-M ar-11 02-M ar-11 07-M ar-11 14-M ar-11 14-M ar-11 18,540 USD AI/G/3/2011 Leaders Technology yemen 18540 due to the closing date of AI project, so ALL the contract Value paid from RALP Project.as agreed during Actual No No NA NA 09-Feb-11 NA 16-Feb-11 02-M ar-11 02-M ar-11 21-M ar-11 NA 11-Apr-11 14-M ay-11 cairo mission march 2012 Planned No No 29-Jul-09 15-Aug-09 22-Aug-09 06-Oct-09 06-Oct-09 05-Nov-09 15-Dec-09 12-Jan-10 22-Feb-14 Rev ised 1 No No 01-Apr-10 20-Apr-10 02-M ay-10 16-Jun-10 16-Jun-10 31-Jul-10 30-Aug-10 29-Sep-10 4,481,783 23-May-14 Rev ised 2 Yes Yes 20-Nov-10 09-Jan-11 15-Jan-11 22-Jan-11 29-Jan-11 12-M ar-11 12-M ar-11 26-Apr-11 26-M ay-11 02-Jun-11 Mr. 'Ali Moh'd Hamood Al-Wadei The contract amount increased from USD 3797969 to USD 4481783 The Construction works of AL- Mocha quarantine at Al -mocha district in RALP/AQF/PW/ICB/ Rev ised 3 24 RALP/AQF/PW/ICB/01/2012 Taiz Governorate. Works Prior ICB Yes No 31-M ar-11 20-Apr-11 07-M ay-11 22-Jun-11 22-Jun-11 16-Jul-11 23-Jul-11 30-Jul-11 USD 01/2012 f or Architectural and Construction 2,165,044 addendum amount is US$ 683814 and the contract period extended from 450 Contracting - Sana,a Y EMEN Rev ised 4 Yes No 20-Jun-12 09-Jul-12 16-Jul-12 27-Aug-12 27-Aug-12 10-Oct-12 10-Nov-12 10-Dec-12 days to 540days NOL dated on (21/9/2013 - 1/10/2013 ). Rev ised 5 Yes No 20-Jun-12 09-Jul-12 16-Jul-12 27-Aug-12 27-Aug-12 10-Oct-12 10-Nov-12 15-Nov-12 Actual Yes No 14-Jun-12 24-Jun-12 30-Jun-12 14-Aug-12 ######## 29-Sep-12 08-Oct-12 14-Nov-12 Planned NCB No No 03-Nov-13 NA 17-Nov-13 17-Dec-13 ######## 31-Dec-13 NA 14-Jan-14 14-May-14 Supply and install Incinerator for AL- Mocha quarantine at Al -mocha district in Rev ised 25 RALP/AQF/G/NCB/01/2013 Taiz Governorate. Goods Post Actual 11/26/2013 5 Prepared by: Ali ashaish PS RALP Project 11/26/2013 6 Prepared by: Ali ashaish PS RALP Project Procurement Plan for Consultant Services YEMEN P089259 : Rainfed Agriculture and Livestock Project (RALP) IDA Cr.#4220/Yem In some contracts, one or more of these ** Applicable in case of Bank's prior review approvals may be contained in one Bank 98 communication. No Objection No Objection No RFP Final No by the Bank by the Bank Review Type of Advertisin TOR/Shortli No Objection Objection Proposal SL Draft to be Objection to the (Technical/ Contract Services Expenses by Bank Consultant Method of g for Short st to be from Bank from Bank RFP Issued Submissio Contract Contract Name, City, and Country of No. Package/ Reference No. Description of Services (Prior/ (Firm/ Selection listing Finalised forwarded from Bank for Shortlist for Final (Date) n Deadline Technical #Combined/ Signed Value Currency Contract No. Contractor (incl. Zip Code if US) Completion Incurred to Comments to the Bank for TOR Evaluation Draft Contract/ (Date) (Date) Date Post) Individual) (Date) (Date) (Date)** RFP (Date) (Date) (Date)** Report Final Contract) (Date)** (Date)** (Date)** Planned NA NA NA NA NA NA NA NA 28-Jun-08 01-Jan-08 GENERAL SEEDS MULTIPLICATION 31-Dec-08 Coordinate, communicate, Follow-up identification/collection of CORPORATION (GSMC) West of Gym Revised 1 RALP/CS/1/2008 priority crops and land races. Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 30,000 USD RALP/CS/1/2008 stadium P.O.BOX: 87282 Dhammar 30,000 Completed Governorate . Actual NA NA NA NA NA NA 01-Jan-08 NA 28-Jun-08 01-Jan-08 Republic of Yemen 27-Mar-09 Planned Civil Engineer for (Rehabilitation and maintenance) of agriculture NA NA NA NA NA NA NA NA NA NA 30-Apr-08 SALAH ADDIN NASSIR (MR.)Sana'a - Revised 2 RALP/CS/ 2/2008 offices) (11 districts )and Designing & supervision for additional works Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 3,800 USD RALP/CS/2/ 2008 Republic of Yemen 3,800 Completed of agriculture extension offices Actual NA NA NA 30-Sep-07 NA NA NA 17-Dec-07 17-Dec-07 05-Jan-08 09-Jun-09 Planned NA NA NA NA NA NA NA NA NA NA 10-May-08 Civil engineer for GDAR Head office Maintenance (designing ) and Eng Ahmed S. Al-Hammadi Sana'a - Revised 3 RALP/CS/3/2008 supervision Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 1,600 USD RALP/CS/3/2008 Republic of Yemen 15-Feb-09 1,600 Completed Actual NA NA NA NA NA NA NA 16-Apr-08 27-Apr-08 20-Apr-08 1-Dec-08 Planned 22-Mar-08 30-Apr-08 NA 10-May-08 NA NA NA NA 10-Aug-08 30-Aug-08 23-Feb-08 Dr.Unger Herman, w - Lebsaftgasses 3 A- Revised 4 RALP/CS/4/2008 Laboratory equipment specialist ( international ). Post Individual IC NA NA NA NA NA NA NA NA NA NA NA 15,876 USD RALP/CS/4/2008 3400 Klosterneuburg Germany NA 14,837 Completed Actual 22-Mar-08 8-Jan-08 NA 8-Jan-08 NA NA NA NA NA NA 9-Feb-08 20-Jul-09 Planned 6-Sep-07 20-Sep-07 NA NA NA NA NA NA NA 27-Sep-07 04-Oct-07 15-Jun-09 Completed The contract extended the WB NO objection Letter to extend the contract dated on Dr.Mustafa H.Abdul Sattar P.O BOX: 4415 Revised 5 RALP/PT/002/2007 MONITORING AND EVALUATION OFFICER Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 10,000 USD RALP/CS/5/2008 Crater Aden Republic of Yemen 15-Jun-10 10,000 (December 27,2009 ) the extension contract signed on ( December 27,2009) the period extended to ( June 15,2010 ) and the amount of extension contract (USD 5000 ) . Actual 6-Sep-07 13-Jan-08 NA NA NA NA NA NA 16-Jan-08 24-May-08 15-Jun-08 21-Oct-10 Planned NA NA NA NA NA NA NA NA 25-Jul-08 01-Jul-08 GENERAL SEEDS MULTIPLICATION 30-Jun-09 CORPORATION (GSMC) West of Gym Revised 6 RALP/CS/ 6/2008 Enhancement of Seeds Production and Maintenance of varieties. Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 50,000 USD RALP/CS/6/2008 stadium P.O.BOX: 87282 Dhammar NA 50,000 Completed Governorate . Actual NA NA NA NA NA NA NA NA 29-Jul-08 01-Jul-08 Republic of Yemen 10-Sep-09 Planned NA NA NA NA 25-May-08 17-Apr-08 15-May-08 10-Jul-08 25-Jul-08 30-Jul-08 30-Jun-09 Yemeni Veterinary Medicine Association Revised 7 RALP/CS/7/2008 Training of CAHWs &Veterinary Technicians and Assistants - (1) Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 36,462,500 YER RALP/CS/7/2008 (YVMA), Almithaq Street, P.O: BOX: 14846, NA 36,462,500 Completed Sana'a - Republic of Yemen Actual NA NA NA NA NA NA NA NA 4-Nov-08 1-Jul-08 3-Feb-10 Planned NA NA NA NA NA NA NA NA NA 01-Aug-08 31-Jul-09 Collection, characterization, evaluation, participatory improvement and ADEN UNIVERSITY - NASSER FACULTY Revised 8 RALP/CS/8/2008 conservation of landraces (Lahej governorate) 2008-2009 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/8/2008 OF AGRICULTURAL SCIENCES Alhwta 24,000 Completed P.O BOX: 10044 Lahi Republic of Yemen Actual NA NA NA NA NA NA NA NA 29-Nov-08 01-Aug-08 07-Dec-09 Planned NA NA NA NA NA NA NA NA NA 01-Aug-08 31-Jul-09 Collection, characterization, evaluation, participatory improvement and SANA'A UNIVERSITY - FACULTY OF Revised 9 RALP/CS /9/2008 conservation of landraces ( SANAA governorate ) 2008-2009 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/9/2008 AGRICULTURE Ring Road]. Street P.o 24,000 Completed BOX 13945 Sana'a - Republic of Yemen Actual NA NA NA NA NA NA NA NA 29-Nov-08 01-Aug-08 08-Dec-09 AGRICULTURAL RESEARCH AND Planned NA NA NA NA NA NA NA NA NA 01-Aug-08 EXTENSION AUTHORITY (AREA) Sana'a 31-Jul-09 Collection, characterization, evaluation, participatory improvement and 10 Road, P.O. BOX 87148 Dammar Revised RALP/CS/10/2008 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/10/2008 30-Dec-09 24,000 Completed conservation of landraces ( Hodeidah governorate). 2008-2009 Governorate . Actual NA NA NA NA NA NA NA NA 17-Dec-08 01-Aug-08 Republic of Yemen 15-May-10 AGRICULTURAL RESEARCH AND Planned NA NA NA NA NA NA NA NA NA 01-Aug-08 EXTENSION AUTHORITY (AREA) Sana'a 31-Jul-09 Collection, characterization, evaluation, participatory improvement and Revised 11 RALP/CS/11/2008 conservation of landraces ( HAJJA GOV.) 2008-2009 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/11/2008 Road, P.O. BOX 87148 Dammar Governorate . 30-Dec-09 24,000 Completed Actual NA NA NA NA NA NA NA NA 17-Dec-08 01-Aug-08 Republic of Yemen 15-May-10 AGRICULTURAL RESEARCH AND Planned NA NA NA NA NA NA NA NA NA 01-Aug-08 EXTENSION AUTHORITY (AREA) Sana'a 31-Jul-09 Collection, characterization, evaluation, participatory improvement and 12 Road, P.O. BOX 87148 Dammar Revised RALP/CS/12/2008 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/12/2008 30-Dec-09 24,000 Completed conservation of landraces ( AL-Mahweet governorate ) . 2008-2009 Governorate . Actual NA NA NA NA NA NA NA NA 17-Dec-08 01-Aug-08 Republic of Yemen 15-May-10 Planned NA NA 07-Aug-07 NA NA NA NA NA 22-Aug-07 29-Aug-07 30-Dec-12 Consultancy Services on Capacity Building and Technical Backstopping for the Following International Centre for Agriculture Research The contract expired on 31 December 2012 and the remaining and some new Revised 13 RALP/CS/ 13/2008 Project First comp. (Sub-Components: (1.1) Landrace Improvement and Maintenance; (1.2) Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 369,944 USD RALP/CS/13/2008 in the Dry Areas (ICARDA) P.O. Box: 5466 330,012 activities shifted to the new contract in 2013. Promotion of Seed Producer Groups; - (2) Aleppo- Syria Actual NA NA 29-Aug-07 NA NA NA NA NA 03-Aug-08 25-Aug-08 31-Dec-12 Planned 10-Feb-08 24-Feb-08 2-Mar-08 NA NA 16-Mar-08 23-Mar-08 22-Apr-08 6-May-08 14-May-08 28-May-08 4-Nov-11 Completed / Amendment : ( Staffing ,terms of payments and Reports NOL dated on ( M ay 24 INTERNATIONAL CONSULTANCY SERVICES FOR CENTRAL VETERINARY International Projects Partnership (IPP) ,2010 ) and amendment (1) signed on ( M ay 30,2010 ) addendum (1) : (The contract amount of Revised 14 RALP/CS/ QCBS/ 2/ 2008 LABORATOYR (CVL), SANA'A ( 3 Experts) Prior Firm QCBS NA NA NA NA NA NA NA NA NA NA NA 222,352 USD RALP/CS/14/2008 Consultants 30 bis rue du Vieil Abruvoir 217,850 the Original contract increased from US$189000 US$ to US$ 222352 due to the addition of local 78100 St Germain-en-Laye France taxes estimated US$ 33352 The NOL dated on ( December28,2010) and the amendment signed on Actual 1-Feb-08 1-Apr-08 26-Apr-08 NA 23-Apr-08 7-May-08 10-May-08 11-Jun-08 7-Jul-08 2-Sep-08 20-Sep-08 5-Sep-12 (January 3 , 2011). Planned NA NA NA NA NA NA NA NA NA NA NA Civil engineer for Designing & Redesigning and supervision of the avian Amendment contract no (4/2011) dated on ( 15/ 2/ 2011 ) the orginal contract Anwar Ahmed Alhaboob Sana'a - Republic of Revised 15 RALP/CS/ 14/2008 influenza laboratory within the new building of the new CVL. Post Individual IC NA 07-Jan-11 NA NA NA NA NA NA NA NA NA 12,500 USD RALP/CS/15/2008 Yemen 30-Jun-11 12,500 amount increased from US$ 7500 toUS$ 12500 due to Redesigning and supervision Completed Actual NA NA NA NA NA NA NA NA NA 24-Nov-08 29-Dec-12 Addendum(1) : ( (T he contract amount increased from Euro268860 to Euro 302860 due to Append Planned INTERNATIONAL EXPERTISE SERVICES FOR GENERAL DIRECTORATE OF 31-Dec-07 14-Jan-08 14-Jan-08 NA NA 16-Jan-08 25-Jan-08 7-May-08 7-Jun-08 25-Jun-08 30-Jun-08 6-Feb-14 activity (local legal expert) for 12 months estimated (34000Euro ) & period of contract reduced ICON INSTITUT PUBLIC SECTOR GMBH- 16 EUR from (60 months )to (39 months ) NOL dated on ( July 25.2010 ) the addendum signed on( August Revised RALP/CS/ QCBS /1/ 2008 ANIMAL RESOURCES (GDAR) Prior Firm QCBS NA NA NA NA NA NA NA NA NA NA NA 356,305 RALP/CS/1/2009 Von – Groote – Strasse 28, 50968 – 30-Apr-12 351 610 1,2010) - Amendment : ( substitute key staff ) on (October 16,2010) and the NOL dated on ( (5 Experts ). Cologne, Germany November 6,2010 ). Addendum(2) : ( T he contract amount increased from (302860 Euro ) to ( Actual 1-Feb-08 NA 7-May-08 NA NA 19-May-08 24-May-08 9-Jul-08 1-Sep-08 26-Jan-09 07-Feb-09 18-Mar-13 356305 Euro ) due to the addition of local taxes estimated ( 53445 Euro) NOL dated on ( December Technical expertise for quarantines development.(AL-MoKha -Taiz)-Al- Planned 15-May-08 NA NA NA NA NA NA NA 28 Jan. 09 10 Feb. 09 20-Feb-10 mukla -hadrmot) DAVID E. FLEMING (DR.) P.O BOX : 661 The contract terminated NOL recived from WB Revised 17 RALP /CS/2/2009 International expert Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 56,430 USD RALP/CS/2/2009 31,660 Locust Grove USA on (July 26,2012) Actual NA NA NA NA NA NA NA 27-Jan-09 NA 21-Feb-09 26-Jul-12 Planned Technical expertise for quarantines development NA NA NA NA NA NA 15-May-08 7-Jun-08 25-Jun-08 30-Jun-08 20-Feb-10 (AL-MoKha -Taiz)-Al-mukla -hadrmot) Dr Khalid Mohammed saeed P.o Box 4123 - Revised 18 RALP /CS/2009 national expert Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 3,750 USD RALP/CS/3/-2009 HODEIDAH - Republic of Yemen 3,750 Completed Actual NA NA NA NA NA NA NA NA 5-Apr-09 11-Apr-09 18-Sep-10 Planned NA NA NA NA NA NA NA NA NA NA 29-May-09 Haleem hasnain/ House 13 Street:6, Sector Revised 19 RALP /CS/4/2009 Yemen Veterinary Association Support expert(International expert) Post Individual IC NA NA NA NA NA NA NA NA NA NA NA 25,922 USD RALP/CS /4/2009 :F-8/3 Islamabad 44000 Pa kistan 25,411 Completed Actual NA NA NA NA NA NA NA NA 14-Apr-09 18-Jun-09 Prepared by: Ali ashaish 11/26/2013 7 PS RALP Project Procurement Plan for Consultant Services YEMEN P089259 : Rainfed Agriculture and Livestock Project (RALP) IDA Cr.#4220/Yem In some contracts, one or more of these ** Applicable in case of Bank's prior review approvals may be contained in one Bank 98 communication. No Objection No Objection No RFP Final No by the Bank by the Bank Review Type of Advertisin TOR/Shortli No Objection Objection Proposal SL Draft to be Objection to the (Technical/ Contract Services Expenses by Bank Consultant Method of g for Short st to be from Bank from Bank RFP Issued Submissio Contract Contract Name, City, and Country of No. Package/ Reference No. Description of Services (Prior/ (Firm/ Selection listing Finalised forwarded from Bank for Shortlist for Final (Date) n Deadline Technical #Combined/ Signed Value Currency Contract No. Contractor (incl. Zip Code if US) Completion Incurred to Comments to the Bank for TOR Evaluation Draft Contract/ (Date) (Date) Date Post) Individual) (Date) (Date) (Date)** RFP (Date) (Date) (Date)** Report Final Contract) (Date)** (Date)** (Date)** Planned 25-Mar-09 24-Apr-09 NA NA NA NA NA NA NA 27-Jun-09 28-Jun-09 31-Dec-11 ALI MOHAMMED ASHAISH Sana'a - The contract extended by MAI and Amendment to the orginal Revised 20 RALP /PSU/1/2009 Procurement Officer Post Individual IC 25-Mar-09 24-Apr-09 NA NA NA NA NA NA NA NA NA 89,728 USD RALP/CS /5/2009 Republic of Yemen 31-May-14 59,094 contract increased salary by MOPIC Actual NA NA NA NA NA NA NA NA NA 27-Jun-09 28-Jun-09 Planned 25-Mar-09 24-Apr-09 NA NA NA NA NA NA NA 27-Jun-09 28-Jun-09 31-Dec-11 NAGEEB ABDULLAH AL-HASHEDI Sana'a - The contract extended by MAI and Amendment to the orginal Revised 21 RALP /PSU/1/2009 Procurement Assistant Post Individual IC 25-Mar-09 24-Apr-09 NA NA NA NA NA NA NA 68,356 USD RALP/CS /6/2009 Republic of Yemen 31-Dec-14 52,261 contract increased salary by MOPIC Actual NA NA NA NA NA NA NA NA NA 27-Jun-09 28-Jun-09 Planned 11-May-09 NA 17-May-09 NA NA NA NA NA 20-May-09 01-Jun-09 GENERAL SEEDS MULTIPLICATION 31-Dec-09 Coordinate, communicate, Follow-up identification/collection of CORPORATION (GSMC) West of Gym Revised 22 RALP /CS/ 5/2009 priority crops and land races Prior Firm SS NA NA NA NA NA NA NA NA NA 34,000 USD RALP/CS/7/2009 stadium P.O.BOX: 87282 Dhammar 34,000 Completed Governorate . Actual NA NA NA NA NA NA NA NA 17-May-09 06-Jul-09 Republic of Yemen 06-Apr-10 Planned NA NA NA NA NA NA NA NA NA NA 23-Mar-10 The contract amended (the contract amount increased from ($12500) to( Consultant Services for Design of Al-Mokha Quarantine Building in TAIZ YAHIYA MOHAMMED NO'MAN HAMIM P.O $20000) and extend the end period from (March 23,2010) to (July Revised 23 RALP /CS/ 3/2009 gov. Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 20,000 USD RALP/CS/ 8/2009 BOX : 19217 Sana'a - Republic of Yemen 31-Jul-10 20,000 31,2010) NOL dated on( July 25,2010 ) the Addendum signed on ( July Actual NA NA NA NA NA NA NA 10-Jun-09 14-Dec-09 15-Dec-09 8-Aug-10 27,2010). Planned 12-Oct-09 NA 25-Oct-09 NA NA NA NA NA 10-Nov-09 15-Nov-09 GENERAL SEEDS MULTIPLICATION 13-Jun-10 First Amendment : ( Amended TOR ) amendment signed on (June 5,2010 ) NOL Establishment of Seed Producers Groups and Sites and Communities CORPORATION (GSMC) West of Gym dated on (June 2,2010 ) Second amendment : ( Extend Completion (Date) from (June Revised 24 RALP /CS/1/2010 Selection Prior Firm SSS NA 20-Mar-10 NA NA NA NA NA NA NA 36,800 USD RALP/CS/1/2010 - stadium P.O.BOX: 87282 Dhammar 31-Aug-10 36,562 13,2010 ) to (August 31,2010 ) NOL dated on ( August 2,2010 ) Deducted Liquidated Governorate . Damages Actual 6-Mar-10 NA NA NA NA NA NA NA 15-Mar-10 15-Mar-10 Republic of Yemen 18-Oct-10 Planned 20-Jul-09 NA 1-Aug-09 NA NA NA NA NA 10-Aug-09 20-Aug-09 GENERAL SEEDS MULTIPLICATION 31-Dec-10 CORPORATION (GSMC) West of Gym Revised 25 RALP /CS/ 2/2010 Enhancing on farm - seed production Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 49,170 USD RALP/CS/2/2010 stadium P.O.BOX: 87282 Dhammar NA 49,170 Completed Governorate . Actual 6-Mar-10 NA NA NA NA NA NA NA 15-Mar-10 15-Mar-10 Republic of Yemen 21-Feb-11 Planned 02-Feb-10 NA NA NA NA NA NA NA 16-Feb-10 23-Feb-10 31-Dec-11 Ms.Dunya Mohammed AL-Dubai Sana'a - Revised 26 RALP /PSU/1 /2010 Recruiting a Secretary for RALP &Avian Flue project Post Individual IC NA NA NA NA NA NA NA NA NA NA NA 23,772 USD RALP/PSU/1/-2010 Republic of Yemen 31-Dec-14 19,364 Actual 03-Mar-10 NA NA NA NA NA NA NA 24-Mar-10 03-Apr-10 Planned 02-Jan-10 NA NA NA NA NA NA NA 1-Feb-10 16-Feb-10 04-Apr-11 Veterinary Institute training program (Vet. Technicians training Yemeni Veterinary Medicine Association Revised 27 RALP /CS/ 3/2010 program &Vet. Assistants training program) (11) students .) 2010 Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 12,084,505 USD RALP/CS/3/2010 (YVMA), Almithaq Street, P.O: BOX: 14846, NA 11,912,605 Completed Sana'a - Republic of Yemen Actual 17-Feb-10 NA NA NA NA NA NA NA 30-Mar-10 4-Apr-10 19-Apr-11 Planned 9-Sep-09 2-Sep-09 NA 16-Sep-09 NA NA NA NA NA 17-Oct-09 20-Oct-09 28-Feb-11 Completed First amendment :The period of contract extended up to 30-4-2011 (NOL dated on ( February 1,2011) and the amendment signed on ( February 2,2011 ) -The addendum (1) (increase ABDO BAKRI AHMED FAKIRA (DR.) P.O: Revised 28 RALP /CS/4/2010 Research Contract in Animal Fodders Prior Individual IC NA NA NA NA NA NA NA NA NA NA 01-Jan-10 49,339.68 USD RALP/CS/4/2010 BOX: 14898 Sana'a - Republic of Yemen 31-May-11 37,342.51 the contract amount from (48340US$ ) TO (49340 US$ ) and the completion period of contract extended to (May 31,2011) instead of (April30,2011) NOL dated on (June19,2011 ) and the addendum Actual NA 13-Sep-09 NA 7-Oct-09 NA NA NA NA NA 11-Apr-10 12-Apr-10 04-Jul-11 signed on(June20,2011 ) Planned 28-Feb-10 NA 7-Mar-10 NA NA NA NA NA 15-Mar-10 22-Mar-10 10-Nov-10 National Coordinator for RALP to implement farmer based system of Dr. Mohamed Ali Hassan Farea P.O . BOX Revised 29 RALP /CS/5/2010 seed improvement and management Prior Individual IC NA NA NA NA NA NA NA NA NA NA NA 12,000 USD RALP/CS/5/2010 87148 Dhamar - Republic of Yemen 12,000 First mission (6 months ). Actual 5-Mar-10 NA 30-Mar-10 NA NA NA NA NA 8-May-10 10-May-10 10-Nov-10 Planned 10-Aug-09 NA 15-Aug-09 NA NA NA NA NA 25-Aug-09 02-Sep-09 31-Dec-10 Collection, characterization, evaluation, participatory improvement and SANA'A UNIVERSITY - FACULTY OF Revised 30 RALP /CS/ 6/2010 conservation of landraces ( SANAA governorate (Renew) 2010 Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 30,000 USD RALP/CS/6/2010 AGRICULTURE Ring Road]. Street P.o 30,000 Completed BOX 13945 Sana'a - Republic of Yemen Actual 24-Apr-10 NA NA NA NA NA NA NA 22-May-10 29-May-10 27-Jan-11 Planned 10-Aug-09 NA 15-Aug-09 NA NA NA NA NA 25-Aug-09 02-Sep-09 31-Dec-10 Collection, characterization, evaluation, participatory improvement ADEN UNIVERSITY - NASSER FACULTY Revised 31 RALP /CS/ 7/2010 and conservation of landraces ( Lahej governorate (Renew) 2010 Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 30,000 USD RALP/CS/7/2010 OF AGRICULTURAL SCIENCES Alhwta 30,000 Completed P.O BOX: 10044 Lahi Republic of Yemen Actual 24-Apr-10 NA NA NA NA NA NA 22-May-10 29-May-10 03-Jan-11 Planned 20-Jul-09 NA 30-Jul-09 NA NA NA NA NA 10-Aug-09 20-Aug-09 GENERAL SEEDS MULTIPLICATION 31-Dec-10 CORPORATION (GSMC) West of Gym Revised 32 RALP /CS/ 8/2010 variety maintenance Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 50,000 USD RALP/CS/8/2010 stadium P.O.BOX: 87282 Dhammar 49,924 Completed Governorate . Actual 24-May-10 NA NA NA NA NA NA NA 08-Jun-10 09-Jun-10 Republic of Yemen 21-Feb-11 Planned 20-Jul-09 NA 1-Aug-09 NA NA NA NA NA 10-Aug-09 15-Oct-09 GENERAL SEEDS MULTIPLICATION 31-Dec-10 The contract terminated the Project notified GSMC on (Jan31,2011) that the contract CORPORATION (GSMC) West of Gym should terminate as WB Mission suggested (January3-18,2011) and GSMC should Revised 33 RALP /CS/9 /2010 Seed quality control Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 25,000 USD RALP/CS/ 9 /2010 stadium P.O.BOX: 87282 Dhammar NA 0 return the advance payment (paid ) . The GSMC agreed and returned the advance Governorate . paid on ( April 18,2011) . the no objection to Terminate the contract received on Actual 18-May-10 NA NA NA NA NA NA NA 20-Jun-10 22-Jun-10 Republic of Yemen 31-Jan-11 (June 19,2011). AGRICULTURAL RESEARCH AND Planned 10-Aug-09 NA 15-Aug-09 NA NA NA NA NA 25-Aug-09 02-Sep-09 EXTENSION AUTHORITY (AREA) Sana'a 15-Jun-11 Collection, characterization, evaluation, participatory improvement and Revised 34 RALP /CS/10 /2010 conservation of landraces (Hodeidah governorate ) (Renew) 2010 Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 30,000 USD RALP/CS/ 10/2010 Road, P.O. BOX 87148 Dammar Governorate . NA 30,000 Completed Actual 15-Apr-10 NA NA NA NA NA NA NA 23-Jun-10 26-Jun-10 Republic of Yemen 09-Jul-12 AGRICULTURAL RESEARCH AND Planned 10-Aug-09 NA 15-Aug-09 NA NA NA NA NA 25-Aug-09 02-Sep-09 EXTENSION AUTHORITY (AREA) Sana'a 15-Jun-11 Collection, characterization, evaluation, participatory improvement and 35 Road, P.O. BOX 87148 Dammar Revised RALP /CS/11/2010 Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 30,000 USD RALP/CS/ 11 /2010 NA 30,000 Completed conservation of landraces (HAJJA governorate (Renew) 2010 Governorate . Actual 15-Apr-10 NA NA NA NA NA NA NA 23-Jun-10 26-Jun-10 Republic of Yemen 09-Jul-12 AGRICULTURAL RESEARCH AND Planned 10-Aug-09 NA 15-Aug-09 NA NA NA NA NA 25-Aug-09 02-Sep-09 EXTENSION AUTHORITY (AREA) Sana'a 15-Jun-11 Collection, characterization, evaluation, participatory improvement and Revised 36 RALP /CS/12 /2010 conservation of landraces ( AL-Mahweet governorate .(Renew) 2010 Prior Firm SSS NA 1-Jan-10 NA NA NA NA NA NA NA 16-Jan-10 30-Jan-10 30,000 USD RALP/CS/ 12 /2010 Road, P.O. BOX 87148 Dammar Governorate . 30,000 Completed Actual 15-Apr-10 NA NA NA NA NA NA NA 23-Jun-10 26-Jun-10 Republic of Yemen 09-Jul-12 Planned NA NA NA NA NA NA NA NA NA 01-Nov-10 12-Nov-10 10-May-11 The Value of the orginal contract was (USD14000) the contract National Coordinator to Implement Farmer-Based System of Seed Dr. Mohamed Ali Hassan Farea P.O . BOX extended during 2011 the NOL dated on ( May16,2011) the Addendum (1) Revised 37 RALP /CS/2010 Improvement and Management (FBSSIM) - 2nd contract Prior Individual SS NA NA NA NA NA NA NA NA NA NA NA 26,000 USD RALP/CS/13 /2010 87148 Dhamar - Republic of Yemen 30-Nov-11 25,099 signed on (June 1,2011) the amount of addendum(1) is USD(12000). The Actual NA NA NA NA NA NA NA NA NA 06-Nov-10 10-Nov-10 30-Nov-11 Value of contract increased to USD (26000 ). Planned 18-Sep-10 2-Oct-10 NA NA NA NA NA NA NA NA 1-Dec-10 30-Nov-11 The contract terminated Eng. Jamil A. Al baddani P.O. BOX :12079 Revised 38 RALP/ PSU/CS/WB Recruiting MONITORING AND EVALUATION OFFICER Post Individual IC 30-Nov-10 14-Dec-10 NA NA NA NA NA NA NA NA NA 14,400 USD RALP/CS/ 14 /2010 Sana'a - Republic of Yemen 12,000 Actual 31-Aug-10 4-Oct-10 NA NA NA NA NA NA NA NA 1-Dec-10 30-Sep-11 Planned 25-Nov-10 NA NA NA NA NA NA NA 18-Dec-10 25-Dec-10 24-Jan-11 Consultant Services for Redesigning of Al-Mokha Quarantine Building - YAHIYA MOHAMMED NO'MAN HAMIM Revised 39 RALP /CS/WB 2nd contract . - ( 3 ) Prior Individual SS NA NA NA NA NA NA NA NA NA NA NA 15,000 USD RALP/CS/ 15 /2010 P.O. BOX : 19217 Sana'a - Republic of 15,000 Completed Yemen Actual 4-Sep-10 NA NA NA NA 4-Oct-10 12-Dec-10 NA 25-Dec-10 25-Dec-10 1-Oct-11 Planned 10-Sep-09 NA 15-Sep-09 NA NA NA NA NA 27-Sep-09 03-Oct-09 17-Nov-11 Completed -The period of contract extended up to February 28, Revised 40 RALP/CS/1/2011 Survey of Seed Demand and Market Analysis Prior Individual IC NA 20-Nov-10 NA 10-Dec-10 NA NA 28-Dec-10 04-Jan-11 14-Jan-11 21-Jan-11 28-Jan-11 53,700 USD RALP/CS/ 1 /2011 Eng. ABDUL HAFEZ AL-HAKIMI P.O. BOX: 12492 Sana'a - Republic of Yemen 28-Feb-12 53,700 2012 NOL dated on (March 26,2012 ) the amendment signed on (March 26,2012) Actual 7-Jul-10 NA 13-Jul-10 NA NA 13-Feb-11 27-Feb-11 26-Dec-10 09-May-11 10-May-11 14-Jul-12 Planned 20-Mar-11 NA 27-Mar-11 NA NA 1-Apr-11 11-Apr-11 NA 18-Apr-11 6-May-11 17-May-12 Collection, characterization, participatory improvement of landraces in ADEN UNIVERSITY - NASSER FACULTY Revised 41 RALP/CS/2/2011 (Lahej governorate) 2011 Prior Firm SSS NA 5-Mar-11 NA NA NA NA 7-May-11 14-May-11 NA 19-May-11 20-May-11 30,000 USD RALP/CS/ 2 /2011 OF AGRICULTURAL SCIENCES Alhwta 30,000 Completed P.O. BOX: 10044 Lahi Republic of Yemen Actual 5-Mar-11 NA NA NA NA 7-May-11 8-May-11 NA 19-May-11 19-May-11 4-Jun-12 Planned 20-Mar-11 NA 27-Mar-11 NA NA 1-Apr-11 11-Apr-11 NA 18-Apr-11 6-May-11 17-May-12 Collection, characterization, participatory improvement of landraces in SANA'A UNIVERSITY - FACULTY OF Revised 42 RALP/CS/3/2011 ( SANAA governorate)(Renew) 2011 Prior Firm SSS NA 5-Mar-11 NA NA NA NA 7-May-11 14-May-11 NA 19-May-11 20-May-11 34,475 USD RALP/CS/ 3 /2011 AGRICULTURE Ring Road]. Street P.o. 34,475 Completed BOX 13945 Sana'a - Republic of Yemen Actual 5-Mar-11 NA NA NA NA 7-May-11 8-May-11 NA 19-May-11 19-May-11 23-Jul-12 Planned 20-Mar-11 NA 27-Mar-11 NA NA 1-Apr-11 15-Apr-11 NA 20-Apr-11 27-Apr-11 1-Jun-12 Veterinary Institute training program (Technicians &Vocational Yemeni Veterinary Medicine Association Revised 43 RALP/CS/4/2011 students) (14) students .) 2011 /2012 Prior Firm SSS NA 20-Mar-11 NA NA NA NA 3-Apr-11 17-Apr-11 NA 24-Apr-11 1-May-11 13,006,606 YER RALP/CS/ 4 /2011 (YVMA), Almithaq Street, P.O. BOX: 14846, 12,990,594 Completed Sana'a - Republic of Yemen Actual 10-Mar-11 NA NA NA NA 16-Mar-11 13-May-11 NA 14-Jun-11 14-Jun-11 6-Nov-12 Planned NA 08-Mar-12 NA 12-Mar-12 NA NA NA NA NA NA 18-Mar-12 31-Mar-12 Dr. Khalid Ibrahim Hariri Republic of Revised 44 RALP/CS/44 Updating the EA/EMP of the Al-Mokha Quarantine Post Individual IC NA NA NA NA NA NA NA NA NA NA NA 5,882 USD RALP/CS/44 Yemen 5,431 Completed Actual NA 07-Mar-12 NA 10-Mar-12 NA NA NA NA NA NA 21-Mar-12 23-Apr-12 Planned 16-May-11 NA 21-May-11 NA NA 26-May-11 9-Jun-11 NA 19-Jun-11 3-Jul-11 GENERAL SEEDS MULTIPLICATION 30-Apr-12 Seed maintenance and stocks Security of the improved landraces from CORPORATION (GSMC) West of Gym Completed / IDA's no-objection to the retroactive signing and processing Revised 45 RALP/CS/45 the SPGs( 2011/2012 ). Prior Firm SSS NA 28-Mar-12 NA NA NA NA 4-Apr-12 18-Apr-12 NA 28-Apr-12 5-May-12 50,000 USD RALP/CS/45 stadium Dhammar Governorate . 50,000 of payment of the contract in reference. Republic of Yemen 30-Apr-12 Actual 21-May-11 NA NA NA NA 22-May-11 19-Jun-11 NA 30-Aug-12 30-Apr-11 Planned NA 16-May-11 NA NA NA NA 23-May-11 6-Jun-11 NA NA 13-Jun-11 Dr. Abbas Ahmed Abdlrahman Bawazir 18-May-13 Having it is principal office located at: Revised 1 Preparing drafting legislation & regulations of Seed Quality Control . NA 28-Mar-12 NA NA NA NA NA NA NA NA 14-Apr-12 46 Khormaksar, Aden Revised 2 RALP/CS/46 (national consultant) Post Individual IC NA 30-Jun-12 NA NA NA NA NA NA NA NA 16-Jul-12 15,760 USD RALP/CS/46 Republic of Yemen 15,760 Completed Email: abbawazir@hotmail.com Actual NA 18-Jul-12 NA NA NA NA NA NA NA NA 9-Feb-13 11-Jun-13 Planned NA 14-Mar-12 NA NA NA NA NA NA NA NA 31-Mar-12 29-Jul-12 Revised 47 RALP/CS/47 Recruitment of a MONITORING AND EVALUATION OFFICER(New ) Post Individual IC NA 30-Jun-12 NA NA NA NA NA NA NA NA 16-Jul-12 30-Jun-14 shifted to ACAP Project Actual NA 01-Aug-12 NA NA NA NA NA NA NA NA AGRICULTURAL RESEARCH AND Planned 16-May-11 NA 21-May-11 NA NA 26-May-11 9-Jun-11 NA 19-Jun-11 3-Jul-11 EXTENSION AUTHORITY (AREA) Sana'a 1-Sep-13 Collection, characterization, evaluation, participatory improvement and 48 Road, P.O. BOX 87148 Dammar The completion date extended from Sep 1, 2013 to December 31, 2013 NOL on 22/8/2013 Revised RALP/CS/48 Prior Firm SSS NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 30,000 USD RALP/CS/48 31-Dec-13 21,000 conservation of landraces ( Hodeidah governorate (Renew) 2012/2013 Governorate . and the amendment of the contract signed on 25/8/2013 Actual 15-Jul-12 NA NA NA NA 16-Jul-12 1-Aug-12 NA 27-Aug-12 1-Sep-12 Republic of Yemen Planned 16-May-11 NA 21-May-11 NA NA 26-May-11 9-Jun-11 NA 19-Jun-11 3-Jul-11 AGRICULTURAL RESEARCH AND 1-Sep-13 Collection, characterization, evaluation, participatory improvement and EXTENSION AUTHORITY (AREA) Sana'a 49 The completion date extended from Sep 1, 2013 to December 31, 2013 NOL on 22/8/2013 and Revised RALP/CS/49 Prior Firm SSS NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 30,000 USD RALP/CS/49 Road, Dammar Governorate . 31-Dec-13 21,000 conservation of landraces (Hajja governorate )(Renew) 2012/2013 the amendment of the contract signed on 25/8/2013 Republic of Yemen Actual 15-Jul-12 NA NA NA NA 16-Jul-12 1-Aug-12 NA 27-Aug-12 1-Sep-12 Planned 16-May-11 NA 21-May-11 NA NA 26-May-11 9-Jun-11 NA 19-Jun-11 3-Jul-11 AGRICULTURAL RESEARCH AND 1-Sep-13 EXTENSION AUTHORITY (AREA) Sana'a Landraces Participatory improvement in (AL-Mahweet governorate ( 50 The completion date extended from Sep 1, 2013 to December 31, 2013 NOL on 22/8/2013 and Revised RALP/CS/50 Prior Firm SSS NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 20,000 USD RALP/CS/50 Road, Dammar Governorate . 31-Dec-13 14,000 the amendment of the contract signed on 25/8/2013 2012/2013 ). Republic of Yemen Actual 15-Jul-12 NA NA NA NA 16-Jul-12 1-Aug-12 NA 27-Aug-12 1-Sep-12 Planned NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 30-Jul-13 ADEN UNIVERSITY - NASSER FACULTY Collection, characterization, evaluation, participatory improvement and Revised 51 RALP/CS/51 conservation of landraces (Lahej governorate).( 2012/2013 ). Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 35,000 USD RALP/CS/51 OF AGRICULTURAL SCIENCES Alhwta 35,000 Completed P.O. BOX: 10044 Lahi Republic of Yemen Actual NA 08-Jul-12 NA NA NA NA 9-Jul-12 16-Jul-12 NA 26-Jul-12 28-Jul-12 24-Jun-13 Planned NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 30-Jul-13 SANA'A UNIVERSITY - FACULTY OF Landraces participatory improvement SANA, A Governorate (2012 Revised 52 RALP/CS/52 /2013) Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 34,025 USD RALP/CS/52 AGRICULTURE Ring Road]. Street P.o. 21,250 Completed BOX 13945 Sana'a - Republic of Yemen Actual NA 08-Jul-12 NA NA NA NA 9-Jul-12 25-Jul-12 NA 29-Jul-12 30-Jul-12 GENERAL SEEDS MULTIPLICATION Planned NA 30-Jun-12 NA NA NA NA 7-Jul-12 14-Jul-12 NA 23-Jul-12 30-Jul-12 30-Jul-13 Seed maintenance and stocks Security of the improved landraces from CORPORATION (GSMC) West of Gym Revised 53 RALP/CS/53 the SPGs.( 2012/2013 ). Prior Firm SSS NA NA NA NA NA NA NA NA NA NA NA 50,000 USD RALP/CS/53 stadium P.O.BOX: 87282 Dhammar 50,000 Completed Governorate . Actual NA 08-Jul-12 NA NA NA NA 9-Jul-12 18-Jul-12 NA 28-Jul-12 29-Jul-12 23-Jul-13 Republic of Yemen Planned NA 20-Mar-09 NA NA NA NA 3-Apr-09 17-Apr-09 NA NA 01-May-09 31-Mar-14 Revised 1 22-Feb-11 8-Mar-11 15-Mar-11 NA NA 29-Mar-11 5-Apr-11 20-May-11 25-May-11 30-May-11 06-Jun-11 QCBS Addendum(1) : ( (The contract amount increased from (USD 122,065) to 15-Mar-11 29-Mar-11 5-Apr-11 NA NA 19-Apr-11 26-Apr-11 10-Jun-11 20-Jun-11 25-Jun-11 30-Jul-11 Al-Amidah Consult (AMICON) P.O. Box 1661 Revised 2 Construction Supervision of AL- Mocha quarantine at Al -mocha district (USD140,271.7) due to Append activity (Doing and Implementing Survey & Revised 3 54 RALP/CS/54 in Taiz Governorate Prior Firm 14-Aug-12 28-Aug-12 8-Sep-12 NA NA 22-Sep-12 29-Sep-12 31-Oct-12 7-Nov-12 26-Nov-12 10-Dec-12 140,271.7 USD RALP/CS/54 Al -Qiadeh Street Sana'a Republic of Yemen 90,869 Design works for the new Site Project General Location)) for estimated ( 18,206.7) Including Local Tax,NOL dated on Feb 28,2013 ) the amendment signed on (March 2,2013) Revised 4 CQS NA 16-Oct-12 NA NA NA NA NA NA 15-Nov-12 22-Nov-12 29-Nov-12 Actual NA 17-Oct-12 NA 21-Oct-12 NA NA NA NA 18-Nov-12 3-Dec-12 04-Dec-12 Planned National coordinator to implement NA 01-Jan-12 NA NA NA NA NA NA NA 15-Jan-12 22-Jan-12 1-Oct-13 RALP, S First component (Farmer - based system of seed improvement 55 Dr. Mohamed Ali Hassan Farea P.O . BOX Revised RALP/CS/55 Prior Individual SSS NA NA NA NA NA NA NA NA NA NA NA 24,000 USD RALP/CS/55 24,000 Completed and management) 2012/2013 87148 Dhamar - Republic of Yemen Actual NA 18-Jul-12 NA NA NA NA NA NA NA 27-Sep-12 1-Oct-12 1-Oct-13 Planned IC NA 01-Dec-12 NA NA NA NA NA NA NA NA 31-Dec-12 14-Feb-13 Revised 56 RALP/CS/56 Communication Officer Post Individual 31-Dec-13 Actual David Fleming, DVM Locust Grove, OK Planned NA 20-Feb-14 NA 06-Mar-14 NA NA NA NA NA NA 21-Apr-14 74352 10-Oct-13 Technical Expertise for Preparation of Operation and Management Phone: +1918 479-5496 Bus. Revised 57 RALP/CS/57 Arrangements for New Al-Mukha Quarantine for Live Animals Post Individual IC 32,868 USD RALP/CS/57 Mobile: +1918 260-5170 Fax: +1918 479-8543 Actual NA 25-May-13 NA 29-May-13 NA NA 18-Jun-13 27-Jul-13 NA NA 14-Aug-13 E-mail: davidthevet@gmail.com Planned Consultancy Services on Capacity Building and Technical Backstopping NA NA NA NA NA NA NA 5-Jan-13 NA 30-Jan-13 3-Feb-13 31-Dec-13 International Centre for Agriculture Research for the Following Project First comp. (Sub-Components: (1.1) Landrace The orginal contract expired on 31 December 2012 and the remaining Revised 58 RALP/CS/58 Improvement and Maintenance; (1.2) Promotion of Seed Producer Prior Firm SSS NA NA NN NA NA NA NA NA NA NA NA 58,824 USD RALP/CS/58 in the Dry Areas (ICARDA) P.O. Box: 5466 17,647 & new activities shifted to this new contract in 2013. Aleppo- Syria Actual Groups; - (2) (2013) NA NA NA NA NA NA NA 4-Mar-13 NA 16-Apr-13 20-Apr-13 Mr. Christopher Ward Planned Consultancy Services on Technical Assistance to MAI - Preparation of a NA 15-Mar-13 NA NA NA NA NA NA NA 1-Apr-13 5-Apr-13 The Old Vicarage 30-Jun-13 proposal Revised 59 RALP/CS/59 for the Global Agriculture and Food Security Program (GAFSP) Prior Individual SSS NA NA NN NA NA NA NA NA NA NA NA 18,913 USD RALP/CS/592013 Hennock Devon TQ13 9QD 18,913 Completed England Actual NA 29-Mar-13 NA NA NA NA NA NA NA 17-Apr-13 17-Apr-13 10-Jun-13 International Consultant support to stakeholder consultations on Mrs. Helen Lackner 42 Marston Street, Planned NA 25-Apr-13 NA 26-Apr-13 NA NA NA NA NA 26-Apr-13 26-Apr-13 17-May-13 Yemen’s agriculture and food security strategy and associated Oxford OX4 1JU, UK Revised 60 RALP/CS/60 investment plan Prior Individual SSS 26,235 USD RALP/CS/61/2013 Phone/fax: 44 (0) 1865 242260 E-mail: helenlackner@yahoo.com 26,235 Completed on Yemen’s 2013 project proposal for GAFSP financing mobile: +44 (0)77 9626 5787 Prepared by: Ali ashaish 11/26/2013 8 PS RALP Project Procurement Plan for Consultant Services YEMEN P089259 : Rainfed Agriculture and Livestock Project (RALP) IDA Cr.#4220/Yem In some contracts, one or more of these ** Applicable in case of Bank's prior review approvals may be contained in one Bank 98 communication. No Objection No Objection No RFP Final No by the Bank by the Bank Review Type of Advertisin TOR/Shortli No Objection Objection Proposal SL Draft to be Objection to the (Technical/ Contract Services Expenses by Bank Consultant Method of g for Short st to be from Bank from Bank RFP Issued Submissio Contract Contract Name, City, and Country of No. Package/ Reference No. Description of Services (Prior/ (Firm/ Selection listing Finalised forwarded from Bank for Shortlist for Final (Date) n Deadline Technical #Combined/ Signed Value Currency Contract No. Contractor (incl. Zip Code if US) Completion Incurred to Comments to the Bank for TOR Evaluation Draft Contract/ (Date) (Date) Date International Consultant support to stakeholder consultations on Post) Individual) (Date) (Date) (Date)** RFP (Date) Mrs. Helen Lackner 42 Marston Street, (Date) (Date)** Report Final Contract) Yemen’s agriculture and food security strategy and associated (Date)** Oxford OX4 1JU, UK (Date)** (Date)** 60 Phone/fax: 44 (0) 1865 242260 RALP/CS/60 investment plan Prior Individual SSS 26,235 USD RALP/CS/61/2013 E-mail: helenlackner@yahoo.com 26,235 Completed on Yemen’s 2013 project proposal for GAFSP financing mobile: +44 (0)77 9626 5787 Actual NA 25-Apr-13 NA 26-Apr-13 NA NA NA NA NA 26-Apr-13 27-Apr-13 29-May-13 Prof. Dr. Eng. Omar Hassan Al-Sakaf P. O. Planned National Consultant support to stakeholder consultations on Yemen’s NA 25-Apr-13 NA 26-Apr-13 NA NA NA NA NA 26-Apr-13 26-Apr-13 Box 1669 - Sana'a, Yemen 27-May-13 agriculture and food security strategy and associated investment plan Telefax: 01- 575289 Revised 61 RALP/CS/61 on Yemen’s 2013 project proposal for GAFSP financing Prior Individual SSS 6,900 USD RALP/CS/62/2013 Mobile: 733 77 23 28 6,900 Completed e-mail: oalsakaf@gmail.com Actual NA 25-Apr-13 NA 26-Apr-13 NA NA NA NA NA 26-Apr-13 27-Apr-13 oalsakaf@yahoo.com 25-May-13 Prepared by: Ali ashaish 11/26/2013 9 PS RALP Project Procurement Plan for Consultant Services YEMEN P089259 : Rainfed Agriculture and Livestock Project (RALP) IDA Cr.#4220/Yem In some contracts, one or more of these ** Applicable in case of Bank's prior review approvals may be contained in one Bank 98 communication. No Objection No Objection No RFP Final No by the Bank by the Bank Review Type of Advertisin TOR/Shortli No Objection Objection Proposal SL Draft to be Objection to the (Technical/ Contract Services Expenses by Bank Consultant Method of g for Short st to be from Bank from Bank RFP Issued Submissio Contract Contract Name, City, and Country of No. Package/ Reference No. Description of Services (Prior/ (Firm/ Selection listing Finalised forwarded from Bank for Shortlist for Final (Date) n Deadline Technical #Combined/ Signed Value Currency Contract No. Contractor (incl. Zip Code if US) Completion Incurred to Comments to the Bank for TOR Evaluation Draft Contract/ (Date) (Date) Date Post) Individual) (Date) (Date) (Date)** RFP (Date) (Date) (Date)** Report Final Contract) (Date)** (Date)** (Date)** Exceptional cases : N# Description -1 YVMA AGREEMENT was even mentioned in project (PAD) ICARDA IS the only research center specialized on such activities Moreover this agreement was even -2 mentioned in pad project (PAD) Tasks are continuation of previous work that consultant has carried out and the consultant was -3 selected competitively NOTE: All SSS shall be initiated only after specific clearance from the Bank Prepared by: Ali ashaish 11/26/2013 10 PS RALP Project Prepared by: Ali ashaish 11/26/2013 11 PS RALP Project Prepared by: Ali ashaish 11/26/2013 12 PS RALP Project Prepared by: Ali ashaish 11/26/2013 13 PS RALP Project Prepared by: Ali ashaish 11/26/2013 14 PS RALP Project Procurement Plan for Capacity Building Activities YEMEN P089259 : Rainfed Agricuture and Livestock Project (RALP) IDA Cr.#4220/Yem SL No. Expected Outcome/ Activity Description Estimated Duration Start Date Completion Date Remarks 1 Annual Conference for Animal Genetic Resources 5days 26-Jan-09 30-Jan-09 Romme-Italy done 2 77th General Session international committee of the OIE ( 2009) 7 days 24-May-09 29-May-09 Paris -France done 3 78 General Session of the OIE -( 2010) 7 days 23-May-10 28-May-10 Paris -France done Codex Alimentations ( Committee in contaminants in foods )-2010 4 (1 person ). 7days 26-Apr-10 30-Apr-10 Azmir -Turkey done 5 Workshop on policies and regulations 3 day 15-Feb-09 18-Feb-09 Sanaa done TAIZ-Hodiedah-Hajjah 6 Workshop on animal production(trainer trainsPRA ) Taiz 3days 17-May-09 20-May-09 GOV. done 7 Workshop on epidemiosurveillance PADZI - TAIZ 2 days 21-Apr-09 22-Apr-09 TAIZ done 8 Workshop on animal production(trainer trainsPRA ) 3days 19-Jul-10 22-Jul-10 (sanaa,amran,dhmar,mareb) done 9 Workshop on epidemiosurveillance 3days 17-Jul-11 19-Jul-11 Sanaa 10 Workshop on policies and regulations 2days 07-Dec-10 08-Dec-10 Sanaa done 11 English courses for technical staff for CVL 10 Persons 12 months 20-Feb-10 20-Feb-11 Exceed language centre / Sana,a done English training ( 2)Techical staff at AL-Mocha Quarantine Modern American Language 12 Dr.derhim shmsan &Dr.mohammed AL-mohamadi 12 months 01-Dec-10 01-Dec-11 institute (MALI ) Taiz on going GHANA INSTITUTE OF Training Program for (procurement assistant) on (Works 13 Procurement Management Course ) 18 DAYS 05-Jul-10 23-Jul-10 MANAGEMENT AND PUPLIC done ADMINISTRATION (GIMPA)) International Training Centre of Training Program for (procurement specialist) on (Selection and 14 Recruitment of Consultants in World Bank -Funded Projects 7 days 15-Nov-10 19-Nov-10 the ILO done Turin - Italy Stockholder consultation & workshops in support of the updating Yemen's 15 agriculture &food security, associated investment plans & preparation of 10 days 08-May-13 18-May-13 several workshops 2013 GAFSP proposal 16 81 General Session of the OIE 2013 7 days 26-May-13 31-May-13 Paris -France done 17 Study tour to Visit Djibouti quarantine 5 Days 30-Apr-13 04-May-13 The Minister & Yasser done Prepared by : Ali ashaish 11/26/2013 15 PS RALP Project