PROCUREMENT PLAN (Textual Part) Project information: FYR of Macedonia Project Implementation agency: Ministry of Labor and Social Policy Date of the Procurement Plan: October 2018 Period covered by this Procurement Plan: Duration of the Project Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT North Macedonia : Social Services Improvement Project PLAN General Information Country: North Macedonia Bank’s Approval Date of the Original Procurement Plan: 2018-10-22 2021-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162246 GPN Date: 2018-09-18 Project Name: Social Services Improvement Project Loan / Credit No: / , IBRD / 89020 M Executing Agency(ies): inistry of Labor and Social Policy WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MK-MLSP-72220-CW-RFB- 1. Promoting social 134 / Renovation of MLSP, inclusion through improved Single Stage - One 2020-04- SWCs, Municipalities, NEA and / Prior Request for Bids Open - National 608,000.00 0.00 Canceled 2019-08-01 2019-08-31 2019-10-05 2019-10-22 2019-10-30 access to social benefits and Envelope 27 other institutions included in services the SP system MK-MLSP-96745-CW-RFB- 1. Promoting social Pending Request for Single Stage - One 2019-09- 1313 / Renovation of local IBRD / 89020 inclusion through improved Prior Open - National 220,000.00 0.00 Implementat 2019-02-06 2019-04-03 Quotations Envelope 30 offices access to social benefits and ion services MK-MLSP-122572-CW-RFB- 2. Expanding the access to TRANSFERS-2.1.1 / Civil Single Stage - One 2021-02- IBRD / 89020 and improving of the quality Prior Request for Bids Open - National 1,200,000.00 850,675.56 Signed 2019-07-14 2019-08-01 2019-08-13 2019-09-17 2019-10-04 2019-10-07 2019-12-11 2019-10-29 2020-01-03 works-Kindergarten in Envelope 20 of preschool services Kavadarci MK-MLSP-123252-CW-RFB- 2. Expanding the access to TRANSFERS-2.1.1.2 / Civil Single Stage - One 1,071,451.8 2021-02- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 1,200,000.00 Signed 2019-07-19 2019-09-20 2019-08-18 2019-09-22 2019-11-05 2019-10-12 2019-12-10 2019-11-06 2020-01-02 works-Kindergarten in Envelope 7 28 of preschool services Negotino MK-MLSP-123255-CW-RFB- 2. Expanding the access to Single Stage - One 2021-03- TRANSFERS-2.1.1.3 / Civil IBRD / 89020 and improving of the quality Post Request for Bids Open - National 1,200,000.00 934,707.05 Signed 2019-07-21 2019-10-01 2019-08-20 2019-09-24 2019-11-21 2019-10-14 2019-12-10 2019-11-08 2020-01-03 Envelope 02 works-Kindergarten in Kocani of preschool services MK-MLSP-123257-CW-RFB- 2. Expanding the access to TRANSFERS-2.1.1.4 / Civil Single Stage - One 2019-11- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 800,000.00 698,448.30 Signed 2019-07-25 2019-09-27 2019-08-24 2019-09-28 2019-11-15 2019-10-18 2019-12-09 2019-11-12 2020-01-03 works-Kindergarten in Kisela Envelope 15 of preschool services Voda MK-MLSP-129124-CW-RFQ- 1315 / Renovation of part of 1. Promoting social the Special Institution Demir inclusion through improved Request for Single Stage - One 2019-12- IBRD / 89020 Post Open - National 190,000.00 0.00 Canceled 2019-09-15 2019-10-11 Kapija and part of the Public access to social benefits and Quotations Envelope 20 Institution for rehabilitation of services children and youth MK-MLSP-142028-CW-RFB- 2. Expanding the access to Single Stage - One 2021-06- 2.1.1.5 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 430,000.00 365,321.40 Signed 2019-10-25 2020-07-10 2019-11-14 2019-12-29 2020-08-25 2020-01-18 2020-09-22 2020-03-06 2020-10-20 Envelope 29 Kindergarten in Kriva Palanka of preschool services MK-MLSP-142030-CW-RFB- 2. Expanding the access to Single Stage - One 1,553,358.1 2021-06- 2.1.1.6 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 1,400,000.00 Signed 2019-10-25 2019-10-31 2019-11-14 2019-12-29 2019-12-17 2020-01-18 2019-12-15 2020-03-06 2020-01-13 Envelope 4 29 Kindergarten in Gjorce Petrov of preschool services MK-MLSP-142033-CW-RFQ- 2. Expanding the access to Request for Single Stage - One 2020-08- 2.1.1.7 / Civil works- IBRD / 89020 and improving of the quality Post Open - National 200,000.00 181,276.15 Signed 2019-11-14 2020-02-11 2019-12-17 Quotations Envelope 09 Kindergarten in Bogovinje of preschool services MK-MLSP-142036-CW-RFB- 2. Expanding the access to Single Stage - One 2021-06- 2.1.1.8 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 380,000.00 404,688.09 Signed 2019-10-25 2019-12-13 2019-11-14 2019-12-29 2019-12-16 2020-01-18 2019-12-13 2020-03-06 2020-01-02 Envelope 29 Kindergarten in Resen of preschool services MK-MLSP-142040-CW-RFB- 2. Expanding the access to Single Stage - One 1,945,032.9 2021-06- 2.1.1.9 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 1,800,000.00 Signed 2019-10-25 2019-10-29 2019-11-14 2019-12-29 2019-12-13 2020-01-18 2019-12-11 2020-03-06 2020-01-03 Envelope 7 29 Kindergarten in Strumica of preschool services MK-MLSP-151802-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2021-10- 2.1.1.10 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 910,000.00 0.00 Implementat 2020-02-10 2020-03-01 2020-03-15 2020-03-22 2020-05-09 Envelope 31 Kindergarten in Aracinovo of preschool services ion MK-MLSP-151803-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2021-10- 2.1.1.11 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-02-10 2020-03-01 2020-03-15 2020-03-22 2020-05-09 Envelope 31 Kindergarten in Valandovo of preschool services ion MK-MLSP-151804-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2021-10- 2.1.1.12 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-02-10 2020-03-01 2020-03-15 2020-03-22 2020-05-09 Envelope 31 Kindergarten in Karposh 2 of preschool services ion MK-MLSP-151805-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2021-10- 2.1.1.13 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 480,000.00 0.00 Implementat 2020-02-10 2020-03-01 2020-03-15 2020-03-22 2020-05-09 Envelope 31 Kindergarten in Probistip of preschool services ion MK-MLSP-167801-CW-RFQ- 1.3.15 / Renovation of part of 1. Promoting social the Special Institution Demir inclusion through improved Request for Single Stage - One 2020-12- IBRD / 89020 Post Open - National 190,000.00 240,879.84 Signed 2020-04-11 2020-06-06 2019-11-01 Kapija and part of the Public access to social benefits and Quotations Envelope 03 Institution for rehabilitation of services children and youth MK-MLSP-178969-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2022-02- 2.1.1.16 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 1,100,000.00 0.00 Implementat 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 Envelope 13 Kindergarten in Bitola of preschool services ion MK-MLSP-178973-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2022-02- 2.1.1.17 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 920,000.00 0.00 Implementat 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 Envelope 13 Kindergarten in Lipkovo of preschool services ion MK-MLSP-178976-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2022-02- 2.1.1.18 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 560,000.00 0.00 Implementat 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 Envelope 13 Kindergarten in Gostivar of preschool services ion Page 1 MK-MLSP-178979-CW-RFB- 2. Expanding the access to Pending Single Stage - One 2022-02- 2.1.1.19 / Civil works- IBRD / 89020 and improving of the quality Post Request for Bids Open - National 490,000.00 0.00 Implementat 2020-07-01 2020-07-06 2020-08-17 2020-09-16 2020-10-21 Envelope 13 Kindergarten in Karposh 2 of preschool services ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72180-GO-RFB- 131 / Development of an 1. Promoting social Under integrated social welfare IS inclusion through improved Single Stage - One / Prior Request for Bids Open - International 600,000.00 0.00 Implementati 2019-01-15 2020-12-23 2019-02-14 2020-12-28 2019-03-21 2019-04-07 2019-04-15 2020-04-14 covering both social access to social benefits and Envelope on assistance benefits and services services MK-MLSP-72182-GO-RFB- 1. Promoting social Pending 132 / Hardware equipment inclusion through improved Single Stage - One / Post Request for Bids Open - National 600,000.00 0.00 Implementati 2019-03-01 2019-03-21 2019-04-25 2019-05-05 2019-05-13 2019-11-09 for the MLSP and the social access to social benefits and Envelope on institutions services MK-MLSP-72678-GO-RFB- 2. Expanding the access to Single Stage - One 223 / Training for pre- / and improving of the quality Post Request for Bids Open - National 609,000.00 0.00 Canceled 2019-01-15 2019-02-04 2019-03-11 2019-03-21 2019-03-29 2020-03-28 Envelope primary school program of preschool services MK-MLSP-72679-GO-RFB- 2. Expanding the access to Single Stage - One 224 / In service teacher / and improving of the quality Post Request for Bids Open - National 609,000.00 0.00 Canceled 2019-02-15 2019-03-07 2019-04-11 2019-04-21 2019-04-29 2020-04-28 Envelope training of preschool services MK-MLSP-77087-GO-RFQ- 3. Project Management, Request for Single Stage - One / Post Open - National 68,000.00 26,617.47 Terminated 2019-01-09 2019-02-04 2019-12-10 2019-04-05 3118 / Equipment (4 years ) Monitoring and Evaluation Quotations Envelope MK-MLSP-93096-GO-DIR- 1. Promoting social 1310 / Maintenance and IBRD / 89020 inclusion through improved Prior Direct Selection Direct 198,000.00 0.00 Canceled 2019-01-03 2019-01-08 2019-02-12 2021-01-02 Upgrade of CBMIS access to social benefits and services MK-MLSP-94588-GO-RFQ- 3. Project Management, Request for Single Stage - One 3121 / Camera and Recording IBRD / 89020 Post Open - National 20,000.00 15,750.48 Signed 2019-02-09 2019-03-07 2019-07-22 2019-04-06 Monitoring and Evaluation Quotations Envelope devices MK-MLSP-94585-GO-DIR- 1. Promoting social 1310 / Maintenance and IBRD / 89020 inclusion through improved Prior Direct Selection Direct 198,000.00 358,450.12 Signed 2019-01-21 2019-01-28 2019-01-26 2019-01-30 2019-03-02 2019-02-08 2021-03-01 Upgrade of CBMIS access to social benefits and services MK-MLSP-96729-GO-RFB- 1. Promoting social 1311 / Hardware equipment inclusion through improved Single Stage - One IBRD / 89020 Prior Request for Bids Open - National 240,000.00 192,099.49 Signed 2019-02-01 2019-09-24 2019-03-03 2019-04-07 2019-11-08 2019-04-24 2019-11-21 2019-05-02 2019-12-19 2019-10-29 for the local offices and the access to social benefits and Envelope MLSP services MK-MLSP-96739-GO-RFQ- 1. Promoting social Pending Request for Single Stage - One 1312 / Furniture for the local IBRD / 89020 inclusion through improved Post Open - National 60,000.00 0.00 Implementati 2019-02-10 2019-03-08 2019-09-04 Quotations Envelope offices access to social benefits and on services MK-MLSP-77092-GO-RFQ- 3. Project Management, Request for Single Stage - One / Prior Open - National 49,000.00 0.00 Canceled 2019-02-15 2019-03-18 2019-05-17 326 / Vehicles (2) Monitoring and Evaluation Quotations Envelope MK-MLSP-122570-GO-RFQ- 3. Project Management, Request for Single Stage - One 328 / Procurement of Vehicles IBRD / 89020 Prior Open - National 49,000.00 0.00 Canceled 2019-07-27 2019-09-02 2019-12-01 Monitoring and Evaluation Quotations Envelope (2) MK-MLSP-129121-GO-RFQ- 1. Promoting social Request for Single Stage - One 1314 / Furniture for the IBRD / 89020 inclusion through improved Post Open - National 30,000.00 22,554.84 Signed 2019-09-10 2019-10-24 2019-11-19 2019-12-23 Quotations Envelope Center for Cerebral palsy access to social benefits and services MK-MLSP-129129-GO-DIR- 1. Promoting social 1316 / Upgrade of CBMIS-SSIP IBRD / 89020 inclusion through improved Post Direct Selection Direct 7,000.00 10,079.30 Signed 2019-09-10 2019-10-01 2019-09-15 2019-10-01 2019-09-25 2019-11-25 2020-03-23 Financial module access to social benefits and services MK-MLSP-169710-GO-RFQ- 2.1.1.14 / Furnishing and equipment for the 2. Expanding the access to kindergarten in the Request for Single Stage - One IBRD / 89020 and improving of the quality Post Open - National 113,000.00 97,878.71 Signed 2020-05-06 2020-07-01 2020-08-07 2020-08-30 municipality of Bogovinje Quotations Envelope of preschool services (village of Kamenjane), including outside playground equipment MK-MLSP-173421-GO-RFQ- 2.1.1.15 / Furnishing and equipment for the 2. Expanding the access to Request for Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Open - National 113,000.00 131,723.10 Signed 2020-06-06 2020-08-01 2020-08-04 2020-09-10 Quotations Envelope municipality of Resen , of preschool services including outside playground equipment MK-MLSP-173425-GO-RFQ- 3. Project Management, Request for Single Stage - One IBRD / 89020 Post Open - National 27,000.00 27,217.36 Signed 2020-06-06 2020-08-01 2020-08-07 2020-08-31 3.1.32 / Antivirus licenses Monitoring and Evaluation Quotations Envelope MK-MLSP-173432-GO-RFQ- 3. Project Management, Request for Single Stage - One 3.2.9 / Procurement of IBRD / 89020 Post Open - National 54,130.00 33,581.06 Signed 2020-07-06 2020-08-31 2020-08-24 2020-11-29 Monitoring and Evaluation Quotations Envelope hardware equipment MK-MLSP-178981-GO-RFQ- 2. Expanding the access to Pending 2.2.18 / Printing of age Request for Single Stage - One IBRD / 89020 and improving of the quality Post Open - National 57,000.00 0.00 Implementati 2020-07-06 2020-08-31 2020-09-30 appropriate teaching-learning Quotations Envelope of preschool services on materials MK-MLSP-196377-GO-DIR- 2. Expanding the access to Under 2.2.19 / Distribution of age IBRD / 89020 and improving of the quality Post Direct Selection Direct 8,000.00 0.00 Implementati 2020-09-30 2020-10-06 2020-10-05 2020-10-06 2020-11-09 2020-12-24 appropriate teaching-learning of preschool services on materials Page 2 MK-MLSP-203864-GO-RFB- 2.1.1.1.1 / Furnishing and equipment for the 2. Expanding the access to Pending Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Request for Bids Open - National 169,000.00 0.00 Implementati 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-06-21 Envelope municipality of Kavadarci , of preschool services on including outside playground equipment MK-MLSP-203865-GO-RFB- 2.1.1.2.1 / Furnishing and equipment for the 2. Expanding the access to Pending Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Request for Bids Open - National 169,000.00 0.00 Implementati 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-06-21 Envelope municipality of Negotino , of preschool services on including outside playground equipment MK-MLSP-203867-GO-RFQ- 2.1.1.3.1 / Furnishing and equipment for the 2. Expanding the access to Pending Request for Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Open - National 113,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 Quotations Envelope municipality of Kocani , of preschool services on including outside playground equipment MK-MLSP-203869-GO-RFQ- 2.1.1.4.1 / Furnishing and equipment for the 2. Expanding the access to Pending Request for Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Open - National 107,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 Quotations Envelope municipality of Kisela Voda , of preschool services on including outside playground equipment MK-MLSP-203872-GO-RFQ- 2.1.1.6.1 / Furnishing and equipment for the 2. Expanding the access to Pending Request for Single Stage - One kindergarten in the IBRD / 89020 and improving of the quality Post Open - National 113,000.00 0.00 Implementati 2020-12-06 2021-01-31 2021-05-01 Quotations Envelope municipality of Gjorce Petrov , of preschool services on including outside playground equipment MK-MLSP-226423-GO-RFQ- 2.1.1.2.1.2 / Furnishing and equipment for the kindergarten in the 2. Expanding the access to Pending Request for Single Stage - One municipality of Negotino- IBRD / 89020 and improving of the quality Post Open - National 13,600.00 0.00 Implementati 2021-04-06 2021-06-01 2021-07-01 Quotations Envelope Procurement, delivery and of preschool services on installation of Didactic equipment and Procurement of movable partition panels NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72163-CS-CQS- 1. Promoting social Consultant 112 / Technical assistance for / inclusion through improved Post Qualification Open - National 120,000.00 0.00 Canceled 2019-02-15 2019-02-23 2019-03-20 2019-03-27 2019-04-04 2020-04-03 activation of GMI beneficiaries access to social benefits and Selection services MK-MLSP-72166-CS-CQS- 1. Promoting social 122 / Technical assistance for Consultant inclusion through improved Pending legislative changes regarding / Post Qualification Open - National 120,000.00 0.00 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 access to social benefits and Implementation the implementation of Selection services reformed licensing system MK-MLSP-72168-CS-CQS- 1. Promoting social Consultant 123 / Social service needs / inclusion through improved Post Qualification Open - National 120,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 assessment access to social benefits and Selection services MK-MLSP-72170-CS-CQS- 1. Promoting social 124 / Developing system for Consultant inclusion through improved financing of social services / Post Qualification Open - National 120,000.00 0.00 Canceled 2019-05-01 2019-05-09 2019-06-03 2019-06-10 2019-06-18 2020-06-17 access to social benefits and including determination of Selection services cost of services, MK-MLSP-72172-CS-CQS- 127 / Transformation of the large institutional capacities 1. Promoting social into small group homes, living Consultant inclusion through improved with support, / Post Qualification Open - National 235,000.00 0.00 Canceled 2019-01-15 2019-01-23 2019-02-17 2019-02-24 2019-03-04 2020-03-03 access to social benefits and deinstitutionalization through Selection services foster families and other appropriate forms of protection MK-MLSP-72175-CS-CQS- 1. Promoting social 128 / Outreach activities inclusion through improved Quality And Cost- / Prior Open - National 350,000.00 0.00 Canceled 2019-03-01 2019-03-15 2019-04-26 2019-05-01 2019-05-09 2019-05-22 2019-05-30 2020-05-29 includeing Citizen access to social benefits and Based Selection Angegement activities services MK-MLSP-72676-CS-CQS- 2. Expanding the access to Consultant 222 / Developing a new / and improving of the quality Post Qualification Open - National 122,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 capitation formula of preschool services Selection MK-MLSP-77086-CS-LCS- 3. Project Management, Least Cost IBRD / 89020 Prior Open - National 49,000.00 28,373.17 Signed 2019-01-01 2020-02-26 2019-01-15 2019-02-26 2020-03-23 2019-03-03 2020-05-05 2019-03-11 2020-06-05 2019-03-24 2020-06-18 2019-04-01 2020-07-10 2024-03-30 3117 / Project Audit Monitoring and Evaluation Selection MK-MLSP-77089-CS-CQS- 321 / Operational and Consultant Performance Audit of the 3. Project Management, / Post Qualification Open - National 60,000.00 78,345.50 Signed 2019-02-01 2020-02-18 2019-02-09 2019-03-06 2020-04-23 2019-03-13 2020-06-03 2019-03-21 2020-06-09 2024-02-17 implementation of the ECDE Monitoring and Evaluation Selection Grant program for infrastructure projects Page 3 MK-MLSP-77090-CS-CQS- 322 / Operational and Performance Audit for the Consultant implementation of the grant 3. Project Management, / Post Qualification Open - National 60,000.00 78,536.61 Signed 2019-02-01 2020-02-18 2019-02-09 2019-03-06 2020-04-23 2019-03-13 2020-06-03 2019-03-21 2020-06-09 2024-02-17 mechanism that will promote Monitoring and Evaluation Selection development of (non- institutional) social services at local level MK-MLSP-77091-CS-CQS- Consultant 323 / Baseline and Follow up 3. Project Management, / Post Qualification Open - National 61,000.00 188,037.85 Signed 2019-02-01 2019-10-10 2019-02-09 2019-03-06 2019-12-06 2019-03-13 2019-12-25 2019-03-21 2019-12-30 2024-02-17 Institutional Assessment of Monitoring and Evaluation Selection the preschool quality process MK-MLSP-72681-CS-QCBS- 2. Expanding the access to 225 / Developing a system Quality And Cost- IBRD / 89020 and improving of the quality Post Open - International 366,000.00 0.00 Canceled 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 for evaluation of quality in the Based Selection of preschool services preschool education system MK-MLSP-72232-CS-QCBS- 2. Expanding the access to 221 / Developing of age Quality And Cost- Pending IBRD / 89020 and improving of the quality Post Open - International 365,000.00 0.00 2019-04-01 2019-04-09 2019-05-16 2019-05-21 2019-05-26 2019-06-05 2019-06-13 2020-06-12 appropriate teaching-learning Based Selection Implementation of preschool services materials MK-MLSP-72229-CS-QCBS- 2. Expanding the access to Quality And Cost- 212 / Project designs for IBRD / 89020 and improving of the quality Prior Open - International 1,220,000.00 0.00 Canceled 2019-01-01 2019-01-15 2019-02-26 2019-03-03 2019-03-11 2019-03-24 2019-04-01 2023-12-31 Based Selection kindergartens of preschool services MK-MLSP-72682-CS-QCBS- 226 / Training of ECED administrators and other 2. Expanding the access to Quality And Cost- decision makers to improve IBRD / 89020 and improving of the quality Post Open - International 430,000.00 0.00 Canceled 2019-01-15 2019-01-23 2019-03-01 2019-03-06 2019-03-11 2019-03-21 2019-03-29 2020-03-28 Based Selection capacity and development of of preschool services monitoring programs and tools MK-MLSP-76978-CS-QCBS- 2. Expanding the access to 227 / Outreach activities Quality And Cost- IBRD / 89020 and improving of the quality Post Open - International 365,000.00 0.00 Canceled 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 including Citizen Engagement Based Selection of preschool services activities MK-MLSP-71874-CS-CQS- 1. Promoting social Consultant 111 / Technical assistance for inclusion through improved / Prior Qualification Open - National 120,000.00 0.00 Canceled 2019-01-15 2019-01-29 2019-02-28 2019-03-10 2019-03-18 2020-03-17 legislative changes regarding access to social benefits and Selection the implementation of GMI services MK-MLSP-72164-CS-CQS- 1. Promoting social 121 / Technical assistance for Consultant inclusion through improved legislative changes regarding / Post Qualification Open - National 180,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 access to social benefits and the implementation of social Selection services services reform MK-MLSP-72171-CS-CQS- 125 / Development of quality 1. Promoting social Consultant standards including licensing inclusion through improved / Post Qualification Open - National 120,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 and accreditation and system access to social benefits and Selection for monitoring for their services achievement MK-MLSP-95692-CS-CQS- Consultant 327 / Outreach activities 3. Project Management, IBRD / 89020 Post Qualification Open - National 150,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 including Citizen Engagement Monitoring and Evaluation Selection activities MK-MLSP-98479-CS-CQS- Consultant 327 / Outreach activities 3. Project Management, IBRD / 89020 Post Qualification Open - National 150,000.00 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 including Citizen Engagement Monitoring and Evaluation Selection activities MK-MLSP-99426-CS-CQS- 1. Promoting social Consultant 114 / Counselling and inclusion through improved IBRD / 89020 Prior Qualification Open - National 100,000.00 0.00 Canceled 2019-02-07 2019-02-07 2019-02-28 2019-04-13 2019-05-13 2019-06-17 2020-06-16 Motivation for activation of access to social benefits and Selection GMA beneficiaries services MK-MLSP-115906-CS-CQS- 1. Promoting social Consultant 1213 / Social service needs IBRD / 89020 inclusion through improved Post Qualification Open - National 120,000.00 61,155.24 Signed 2019-06-03 2019-06-11 2019-06-11 2019-07-06 2019-07-11 2019-07-13 2019-07-25 2019-07-21 2019-07-25 2020-01-17 assessment access to social benefits and Selection services MK-MLSP-115916-CS-CQS- Consultant 324 / Public campaign 3. Project Management, IBRD / 89020 Post Qualification Open - National 330,000.00 0.00 Canceled 2019-06-03 2019-06-11 2019-07-06 2019-07-13 2019-07-21 2023-12-31 including Citizen Engagement Monitoring and Evaluation Selection activities MK-MLSP-119370-CS-QCBS- 325 / Public campaign 3. Project Management, Quality And Cost- IBRD / 89020 Prior Open - National 570,000.00 415,933.50 Signed 2019-06-17 2019-07-15 2019-07-01 2019-07-16 2019-08-12 2019-11-12 2019-08-17 2019-12-03 2019-08-25 2019-12-06 2019-09-09 2020-02-21 2019-09-22 2020-03-11 2024-06-30 including Citizen Engagement Monitoring and Evaluation Based Selection activities MK-MLSP-122574-CS-CQS- 2121 / Project designs for 2. Expanding the access to Consultant new kindergartens in IBRD / 89020 and improving of the quality Prior Qualification Open - National 85,000.00 93,887.86 Signed 2019-07-15 2019-07-26 2019-07-29 2019-08-23 2020-02-05 2019-09-07 2020-04-07 2019-09-15 2019-11-08 2020-01-13 Arachinovo, Bitola, Lipkovo of preschool services Selection and Valandovo MK-MLSP-122578-CS-CQS- 2123 / Revision of basic Project designs for 2. Expanding the access to Consultant kindergartens in Arachinovo, IBRD / 89020 and improving of the quality Post Qualification Open - National 17,000.00 12,335.25 Signed 2019-08-01 2019-08-07 2019-08-15 2019-09-14 2019-12-23 2019-09-24 2020-01-02 2019-10-05 2020-01-08 2020-04-02 Bitola, Lipkovo, Valandovo of preschool services Selection ,Probishtip, Gostivar, Karposh 1 and Karposh 2 MK-MLSP-122576-CS-CQS- 2122 / Project designs for 2. Expanding the access to Consultant upgrades of kindergartens in IBRD / 89020 and improving of the quality Post Qualification Open - National 28,000.00 74,081.25 Signed 2019-07-30 2019-08-01 2019-08-13 2019-09-12 2019-10-10 2019-09-22 2019-10-30 2019-10-06 2019-11-08 2020-01-04 Probishtip, Gostivar, Karposh of preschool services Selection 1 and Karposh 2 MK-MLSP-129132-CS-CQS- 2. Expanding the access to Consultant 213 / Supervision of works for IBRD / 89020 and improving of the quality Post Qualification Open - National 70,000.00 31,454.12 Signed 2019-09-09 2019-09-24 2019-09-17 2019-10-12 2019-12-05 2019-10-19 2019-12-25 2019-10-27 2019-12-30 2021-03-10 construction of kindergartens of preschool services Selection in Negotino and Kavadarci Page 4 MK-MLSP-129133-CS-CQS- 2. Expanding the access to Consultant 214 / Supervision of works for IBRD / 89020 and improving of the quality Post Qualification Open - National 55,000.00 25,130.45 Signed 2019-09-09 2019-11-12 2019-09-17 2019-10-12 2019-12-06 2019-10-19 2019-12-27 2019-10-27 2019-12-30 2019-12-16 construction of kindergartens of preschool services Selection in Kocani and Kisela Voda MK-MLSP-129135-CS-CQS- 215 / Project for interior 2. Expanding the access to Consultant design for Kindergardens in IBRD / 89020 and improving of the quality Post Qualification Open - National 55,000.00 39,061.04 Signed 2019-09-09 2020-01-24 2019-09-17 2019-10-12 2020-02-25 2019-10-19 2020-03-16 2019-10-27 2020-03-27 2020-01-25 Kocani, Negotino, Kisela Voda, of preschool services Selection Kavadarci and Bogovinje MK-MLSP-129136-CS-CQS- 216 / Project for interior 2. Expanding the access to Consultant design for Kindergartens in IBRD / 89020 and improving of the quality Post Qualification Open - National 50,000.00 41,802.26 Signed 2019-09-09 2020-01-24 2019-09-17 2019-10-12 2020-02-27 2019-10-19 2020-03-16 2019-10-27 2020-03-20 2020-01-25 Gjorce Petrov, Resen, Kriva of preschool services Selection Palanka and Strumica MK-MLSP-135022-CS-CQS- 1214 / Company for 1. Promoting social providing support to the Consultant inclusion through improved municipalities/ potential IBRD / 89020 Post Qualification Open - National 100,000.00 127,667.71 Signed 2019-09-20 2019-09-27 2019-10-04 2019-10-14 2019-12-02 2019-10-17 2019-12-25 2019-10-23 2019-12-30 2023-07-04 access to social benefits and service providers in Selection services preparation of application documents including the project proposals MK-MLSP-146042-CS-CQS- 2.1.7 / Supervision of works for construction of 2. Expanding the access to Consultant kindergartens in the IBRD / 89020 and improving of the quality Post Qualification Open - National 130,000.00 55,893.58 Signed 2019-11-20 2019-11-19 2019-11-28 2019-12-23 2019-12-23 2019-12-30 2019-12-27 2020-02-03 2020-01-02 2021-10-25 municipalities of Strumica, of preschool services Selection Resen, Gjorce Petrov, Bogovinje and Kriva Palanka MK-MLSP-147511-CS-CQS- 2.2.16 / Consultants' firm 2. Expanding the access to Consultant delivering services for IBRD / 89020 and improving of the quality Post Qualification Open - National 180,000.00 99,693.98 Signed 2019-11-29 2019-12-13 2019-12-13 2020-01-01 2019-12-20 2020-01-06 2020-02-21 2020-02-01 2020-02-24 2021-01-31 supporting the process of of preschool services Selection improving the quality of preschool system MK-MLSP-201117-CS-CQS- 2.1.8 / Supervision of works 2. Expanding the access to Consultant Under for construction of IBRD / 89020 and improving of the quality Post Qualification Open - National 47,000.00 0.00 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2023-03-31 Implementation kindergartens in Probishtip, of preschool services Selection Lipkovo, Bitola and Valandovo MK-MLSP-201118-CS-CQS- 2.1.9 / Supervision of works 2. Expanding the access to Consultant Under for construction of IBRD / 89020 and improving of the quality Post Qualification Open - National 30,000.00 0.00 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2023-03-31 Implementation kindergartens in Gostivar, of preschool services Selection Arachinovo and Karposh MK-MLSP-201119-CS-CQS- 2.1.10 / Project for interior 2. Expanding the access to Consultant Under design for Kindergartens in IBRD / 89020 and improving of the quality Post Qualification Open - National 46,600.00 0.00 2020-12-01 2020-10-27 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2023-03-31 Implementation Lipkovo, Aracinovo and of preschool services Selection Valandovo MK-MLSP-201120-CS-CQS- 2.1.11 / Project for interior 2. Expanding the access to Consultant Under design for Kindergartens in IBRD / 89020 and improving of the quality Post Qualification Open - National 35,000.00 0.00 2020-12-01 2020-10-30 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2023-03-31 Implementation Probishtip, Bitola, Gostivar of preschool services Selection and Karposh INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72221-CS-CDS- 1. Promoting social 135 / Actuary in the Unit for inclusion through improved IBRD / 89020 Prior Direct Selection Direct 161,000.00 79,664.25 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 Analysis, Evaluation and access to social benefits and Monitoring services MK-MLSP-72223-CS-CDS- 1. Promoting social Individual 136 / IT in the Unit for inclusion through improved IBRD / 89020 Prior Consultant Open 161,000.00 65,337.88 Signed 2019-01-01 2018-10-25 2019-01-29 2018-11-23 2019-02-08 2018-11-28 2019-02-16 2018-11-29 2024-02-15 Analysis, Evaluation and access to social benefits and Selection Monitoring services MK-MLSP-72225-CS-CDS- 1. Promoting social 137 / Researcher in the Unit inclusion through improved IBRD / 89020 Prior Direct Selection Direct 103,000.00 75,392.24 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 for Analysis, Evaluation and access to social benefits and Monitoring services MK-MLSP-72228-CS-CDS- 1. Promoting social 139 / Legal Advisor in the inclusion through improved IBRD / 89020 Prior Direct Selection Direct 103,000.00 197,332.13 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 Unit for Analysis, Evaluation access to social benefits and and Monitoring services MK-MLSP-76981-CS-INDV- 228 / Capacity building of 2. Expanding the access to Individual local architects and engineers IBRD / 89020 and improving of the quality Post Consultant Open 85,300.00 84,037.50 Signed 2019-03-01 2019-02-04 2019-03-24 2019-03-29 2019-03-31 2019-05-10 2019-04-08 2019-05-10 2019-10-05 for such innovative and highly of preschool services Selection energy-efficient infrastructure MK-MLSP-77005-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 183,000.00 221,782.58 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 311 / Project Manager Monitoring and Evaluation MK-MLSP-77006-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 169,000.00 188,548.95 Signed 2019-01-01 2018-11-12 2019-01-21 2019-02-08 2018-10-02 2024-02-07 312 / Procurement manager Monitoring and Evaluation Individual MK-MLSP-77007-CS-INDV- 3. Project Management, / Prior Consultant Open 110,000.00 0.00 Canceled 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-13 313 / Coordinator for ECDE Monitoring and Evaluation Selection MK-MLSP-77008-CS-INDV- Individual 3. Project Management, 314 / Coordinator for Social IBRD / 89020 Prior Consultant Open 110,000.00 177,444.70 Signed 2019-01-01 2019-05-15 2019-01-29 2019-05-31 2019-02-08 2019-06-03 2019-02-16 2019-05-31 2024-02-15 Monitoring and Evaluation services development Selection Page 5 MK-MLSP-77009-CS-INDV- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 161,000.00 175,079.26 Signed 2019-01-01 2018-11-12 2019-01-21 2018-10-01 2019-02-08 2018-10-02 2024-02-07 315 / IT manager Monitoring and Evaluation MK-MLSP-77010-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 121,000.00 175,923.56 Signed 2019-01-01 2018-11-12 2019-01-21 2019-02-08 2018-10-02 2024-02-07 316 / Financial manager Monitoring and Evaluation MK-MLSP-77016-CS-INDV- Individual 3. Project Management, 3111 / Environmental/social IBRD / 89020 Prior Consultant Open 110,000.00 79,853.27 Signed 2019-01-01 2019-01-24 2019-01-29 2019-03-18 2019-02-08 2019-03-26 2019-02-16 2019-03-29 2024-02-15 Monitoring and Evaluation safeguards specialist Selection MK-MLSP-72227-CS-CDS- 1. Promoting social 138 / Social Consultant in the inclusion through improved IBRD / 89020 Prior Direct Selection Direct 72,000.00 117,990.67 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-04 2024-06-30 Unit for Analysis, Evaluation access to social benefits and and Monitoring services MK-MLSP-77011-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 95,000.00 53,314.64 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 317 / Civil engineer/architect Monitoring and Evaluation MK-MLSP-77012-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 55,000.00 67,944.00 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 318 / Civil engineer/architect Monitoring and Evaluation MK-MLSP-77013-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 81,000.00 52,145.31 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 319 / Civil engineer/architect Monitoring and Evaluation MK-MLSP-77014-CS-CDS- 3. Project Management, 3110 / Civil IBRD / 89020 Prior Direct Selection Direct 81,000.00 155,023.10 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 Monitoring and Evaluation engineer/architect MK-MLSP-77022-CS-CDS- Individual 3. Project Management, Pending 3114 / Grant application IBRD / 89020 Prior Consultant Open 75,000.00 0.00 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-06-30 Monitoring and Evaluation Implementation officer Selection Individual MK-MLSP-77083-CS-INDV- 3. Project Management, IBRD / 89020 Prior Consultant Open 73,000.00 150,188.17 Completed 2019-01-01 2019-11-19 2019-01-24 2019-12-07 2019-01-31 2019-12-10 2019-02-08 2019-12-11 2024-06-30 2019-12-31 3115 / M&E Officer Monitoring and Evaluation Selection MK-MLSP-77018-CS-CDS- 3. Project Management, 31112 / Grant Administrative IBRD / 89020 Prior Direct Selection Direct 95,000.00 178,697.43 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 Monitoring and Evaluation Coordinator MK-MLSP-77020-CS-CDS- 3. Project Management, 3113 / Financial and IBRD / 89020 Prior Direct Selection Direct 75,000.00 88,621.61 Signed 2018-10-24 2018-11-12 2018-11-08 2018-10-01 2018-11-23 2018-10-02 2024-06-30 Monitoring and Evaluation administrative officer Individual MK-MLSP-77085-CS-CDS- 3. Project Management, Under IBRD / 89020 Prior Consultant Open 73,000.00 0.00 2019-01-01 2019-02-05 2019-01-29 2019-02-08 2019-02-16 2024-06-30 3116 / IT officer Monitoring and Evaluation Implementation Selection MK-MLSP-94587-CS-INDV- Individual 3. Project Management, 3120 / Environmental/social IBRD / 89020 Post Consultant Open 72,000.00 10,139.92 Signed 2019-03-01 2020-05-20 2019-03-24 2020-06-09 2019-03-31 2020-06-29 2019-04-08 2020-07-01 2024-04-06 Monitoring and Evaluation safeguards assistance Selection Individual MK-MLSP-94589-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 72,000.00 153,586.85 Signed 2019-03-01 2019-02-07 2019-03-24 2019-04-12 2019-03-31 2019-04-15 2019-04-08 2019-04-16 2024-04-06 3122 / Interior Designer Monitoring and Evaluation Selection Individual MK-MLSP-94590-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 130,000.00 29,590.53 Signed 2019-02-01 2019-02-24 2019-03-18 2019-03-03 2019-04-01 2019-03-11 2019-04-05 2024-03-09 3123 / Business Analyst Monitoring and Evaluation Selection MK-MLSP-94593-CS-INDV- 1. Promoting social Individual 113 / Social Safety Net IBRD / 89020 inclusion through improved Post Consultant Open 100,000.00 96,631.92 Signed 2019-02-01 2019-02-04 2019-02-24 2019-03-29 2019-03-03 2019-04-09 2019-03-11 2019-05-15 2024-03-09 Specialist access to social benefits and Selection services MK-MLSP-94594-CS-INDV- 129 / Development of norms 1. Promoting social Individual and standards for inclusion through improved IBRD / 89020 Post Consultant Open 120,000.00 13,459.20 Signed 2019-03-01 2019-02-06 2019-03-24 2019-04-15 2019-03-31 2019-05-20 2019-04-08 2019-05-23 2020-04-07 establishing of social services access to social benefits and Selection and for ensuring quality in the services service delivery MK-MLSP-94596-CS-INDV- 1210 / Support for 1. Promoting social Development of norms and Individual inclusion through improved standards for establishing of IBRD / 89020 Post Consultant Open 60,000.00 8,335.63 Signed 2019-03-01 2019-02-06 2019-03-24 2019-04-15 2019-03-31 2019-05-22 2019-04-08 2019-05-28 2020-04-07 access to social benefits and social services and for Selection services ensuring quality in the service delivery MK-MLSP-94598-CS-INDV- 1. Promoting social Individual 1211 / Developing a system inclusion through improved Pending IBRD / 89020 Post Consultant Open 100,000.00 0.00 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2020-04-07 for evaluation of quality in the access to social benefits and Implementation Selection social services delivery system services MK-MLSP-95684-CS-INDV- 1. Promoting social 1212 / Preparation of Cost Individual inclusion through improved Methodology for Establishing IBRD / 89020 Post Consultant Open 120,000.00 22,275.54 Signed 2019-02-01 2019-02-06 2019-02-24 2019-04-17 2019-03-03 2019-05-27 2019-03-11 2019-05-27 2019-09-07 access to social benefits and of Social Services including Selection services pricing list MK-MLSP-95686-CS-INDV- 2. Expanding the access to Individual 229 / Developing a new IBRD / 89020 and improving of the quality Post Consultant Open 120,000.00 7,761.25 Signed 2019-05-01 2019-10-18 2019-05-24 2019-12-04 2019-05-31 2019-12-17 2019-06-08 2019-12-18 2019-12-05 capitation formula of preschool services Selection MK-MLSP-96725-CS-INDV- Individual 3. Project Management, 3124 / Business Analyst IBRD / 89020 Post Consultant Direct 85,000.00 0.00 Canceled 2019-02-01 2019-01-30 2019-02-14 2019-04-01 2019-02-24 2019-04-08 2019-03-04 2024-03-02 Monitoring and Evaluation Assistant Selection MK-MLSP-97638-CS-CDS- 1. Promoting social 114 / Counselling and inclusion through improved IBRD / 89020 Prior Direct Selection Direct 215,000.00 0.00 Canceled 2019-02-01 2019-02-11 2019-04-17 2020-04-16 Motivation for activation of access to social benefits and GMA beneficiaries services MK-MLSP-119013-CS-INDV- Individual 3. Project Management, 3125 / Business Analyst IBRD / 89020 Post Consultant Limited 85,000.00 102,630.85 Signed 2019-06-13 2019-01-30 2019-06-23 2019-04-01 2019-06-30 2019-04-04 2019-07-08 2019-04-11 2020-01-04 Monitoring and Evaluation Assistant Selection Page 6 Individual MK-MLSP-129139-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 130,000.00 117,305.19 Signed 2019-09-09 2019-12-03 2019-10-02 2019-12-28 2019-10-09 2019-12-30 2019-10-24 2019-12-31 2024-07-29 3126 / Civil engineer Monitoring and Evaluation Selection Individual MK-MLSP-129140-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 130,000.00 76,936.38 Signed 2019-09-09 2020-10-27 2019-10-02 2021-01-08 2019-10-09 2021-01-12 2019-10-24 2021-01-14 2024-07-29 3127 / Civil engineer/arhitect Monitoring and Evaluation Selection Individual MK-MLSP-129143-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 65,000.00 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3128 / Electrical engineer Monitoring and Evaluation Implementation Selection Individual MK-MLSP-129144-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 65,000.00 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3129 / Mechanical engineer Monitoring and Evaluation Implementation Selection MK-MLSP-129624-CS-INDV- 1. Promoting social Individual 1317 / Economist in the Unit inclusion through improved IBRD / 89020 Post Consultant Limited 170,000.00 157,335.13 Signed 2019-08-29 2019-09-13 2019-09-06 2019-09-17 2019-09-11 2019-09-17 2019-10-10 2019-09-18 2024-08-14 for Analysis, Evaluation and access to social benefits and Selection Monitoring services Individual MK-MLSP-129625-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 130,000.00 112,906.32 Signed 2019-09-18 2019-09-19 2019-10-11 2019-10-18 2019-10-26 2019-10-20 2019-11-03 2019-10-21 2020-05-01 3130 / Procurement officer Monitoring and Evaluation Selection 2. Expanding the access to Individual MK-MLSP-135381-CS-INDV- IBRD / 89020 and improving of the quality Post Consultant Open 120,000.00 109,940.00 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-04 2019-10-26 2020-01-20 2019-11-12 2020-01-21 2024-06-18 1.2.10 / Principal Investigator of preschool services Selection MK-MLSP-135385-CS-INDV- 2. Expanding the access to Individual 2211 / Local Support to the IBRD / 89020 and improving of the quality Post Consultant Open 60,000.00 70,345.79 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-11 2019-10-31 2019-12-14 2019-11-22 2019-12-18 2024-06-28 Principal Investigator of preschool services Selection MK-MLSP-135386-CS-INDV- 2. Expanding the access to Individual 2.2.12 / National Coordinator IBRD / 89020 and improving of the quality Post Consultant Open 60,000.00 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-18 2024-06-14 for Measuring Early Learning of preschool services Selection Environment (MELE) MK-MLSP-135387-CS-INDV- 2.2.13 / National Coordinator 2. Expanding the access to Individual for Measurement of IBRD / 89020 and improving of the quality Post Consultant Open 60,000.00 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-18 2024-06-14 Development and Early of preschool services Selection Learning (MODEL) MK-MLSP-135389-CS-INDV- 2.2.14 / Local Consultant for 2. Expanding the access to Individual strengthening the preschool IBRD / 89020 and improving of the quality Post Consultant Open 60,000.00 55,651.68 Signed 2019-10-01 2019-10-10 2019-10-24 2019-12-03 2019-10-31 2019-12-14 2019-11-08 2019-12-18 2024-06-14 system for pre-service and in- of preschool services Selection service teacher training MK-MLSP-147510-CS-INDV- 2. Expanding the access to Individual 2.2.15 / International Teacher IBRD / 89020 and improving of the quality Post Consultant Open 105,000.00 52,793.46 Signed 2019-11-27 2019-12-10 2019-12-14 2019-12-13 2019-12-19 2020-02-21 2020-01-16 2020-02-24 2024-06-23 Training and Program Design of preschool services Selection Expert Consultant MK-MLSP-173423-CS-INDV- 2. Expanding the access to Individual Under 2.2.17 / Developing a new IBRD / 89020 and improving of the quality Post Consultant Open 34,000.00 0.00 2020-06-01 2020-08-18 2020-07-20 2021-01-22 2020-08-10 2020-09-14 2021-01-12 Implementation capitation formula of preschool services Selection Individual MK-MLSP-173424-CS-INDV- 3. Project Management, IBRD / 89020 Prior Consultant Limited 104,000.00 119,029.21 Signed 2020-05-15 2020-05-29 2020-05-20 2020-06-01 2020-06-10 2020-06-15 2020-07-15 2020-06-16 2024-06-30 3.1.31 / System administrator Monitoring and Evaluation Selection MK-MLSP-173426-CS-INDV- Individual 3. Project Management, 3.1.33 / Assistant Civil IBRD / 89020 Prior Consultant Limited 52,000.00 57,131.68 Signed 2020-05-15 2020-05-20 2020-05-20 2020-06-08 2020-06-10 2020-06-26 2020-07-15 2020-07-01 2024-06-30 Monitoring and Evaluation engineer Selection MK-MLSP-201109-CS-INDV- 1. Promoting social Individual 1.3.18 / Researcher/Analyst inclusion through improved Under IBRD / 89020 Prior Consultant Open 105,000.00 0.00 2020-11-18 2020-11-09 2021-01-06 2021-01-27 2021-03-03 2024-06-30 in the Unit for Analysis, access to social benefits and Implementation Selection Evaluation and Monitoring services Individual MK-MLSP-201121-CS-INDV- 3. Project Management, Pending IBRD / 89020 Prior Consultant Open 105,000.00 0.00 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2024-06-30 3.1.34 / Interior Designer Monitoring and Evaluation Implementation Selection MK-MLSP-201123-CS-INDV- Individual 3. Project Management, 3.1.35 / Civil IBRD / 89020 Prior Consultant Open 105,000.00 76,755.50 Signed 2020-12-01 2020-10-28 2021-01-19 2021-01-08 2021-02-09 2021-01-12 2021-03-16 2021-01-14 2024-06-30 Monitoring and Evaluation engineer/architect Selection MK-MLSP-201124-CS-INDV- Individual 3. Project Management, 3.1.36 / Assistant IBRD / 89020 Prior Consultant Open 105,000.00 61,306.83 Signed 2020-12-01 2020-11-09 2021-01-19 2020-12-29 2021-02-09 2021-01-11 2021-03-16 2021-01-13 2024-06-30 Monitoring and Evaluation Coordinator for ECDE Selection MK-MLSP-201125-CS-INDV- Individual 3.1.37 / Assistant 3. Project Management, IBRD / 89020 Prior Consultant Open 105,000.00 76,755.50 Signed 2020-12-01 2020-11-09 2021-01-19 2020-12-22 2021-02-09 2020-12-30 2021-03-16 2020-12-31 2024-06-30 Coordinator for Social services Monitoring and Evaluation Selection development MK-MLSP-201126-CS-INDV- Individual 3. Project Management, 3.1.38 / Civil IBRD / 89020 Prior Consultant Open 105,000.00 55,615.21 Signed 2020-12-01 2020-10-28 2021-01-19 2021-01-11 2021-02-09 2021-01-12 2021-03-16 2021-01-14 2024-06-30 Monitoring and Evaluation engineer/architect Selection MK-MLSP-203846-CS-INDV- 1. Promoting social Individual 1.3.19 / Legal Advisor in the inclusion through improved Under IBRD / 89020 Prior Consultant Open 105,000.00 0.00 2020-11-18 2020-11-16 2021-01-06 2021-01-27 2021-03-03 2024-06-30 Unit for Analysis, Evaluation access to social benefits and Implementation Selection and Monitoring services MK-MLSP-203854-CS-INDV- Individual 3.1.39 / Junior Assistant 3. Project Management, IBRD / 89020 Prior Consultant Open 105,000.00 76,034.50 Signed 2020-11-15 2020-11-16 2021-01-03 2020-12-22 2021-01-24 2020-12-31 2021-02-28 2020-12-31 2024-06-30 Coordinator for Social Services Monitoring and Evaluation Selection Development MK-MLSP-203861-CS-INDV- 1. Promoting social Individual 1.2.15 / Methodology for IBRD / 89020 inclusion through improved Post Consultant Open 12,000.00 218.21 Signed 2020-11-15 2020-11-13 2021-01-03 2020-11-30 2021-01-24 2020-12-03 2021-02-28 2020-12-09 2021-04-29 pricing social services access to social benefits and Selection services Page 7 MK-MLSP-212355-CS-INDV- 2. Expanding the access to Individual 2.2.20 / Local Consultant for Under IBRD / 89020 and improving of the quality Post Consultant Open 11,200.00 0.00 2021-01-07 2021-01-22 2021-02-25 2021-03-18 2021-04-22 2022-04-22 Developing a new capitation Implementation of preschool services Selection formula Individual MK-MLSP-219384-CS-INDV- 3. Project Management, Under IBRD / 89020 Prior Consultant Limited 93,200.00 0.00 2021-02-17 2021-02-17 2021-02-22 2021-02-22 2021-03-15 2021-03-02 2021-04-19 2024-06-30 3.1.40 / IT officer Monitoring and Evaluation Implementation Selection Page 8