Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Revision of Updated Procurement Plan, August 2017 2. Date of General Procurement Notice: October 10, 2016 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Category Prior Review Threshold Comments US$ 1. Goods and >= US$2 million All 2. Works >= US$ 10 million All 3. (Non-Consultant Services) >= US$2 million All 2. Prequalification. _Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: At sub-national levels (Commune/Sangkat and Community), provisions of the Project Implementation Manual (PIM) dated March 30, 2016 which has been agreed by the Bank will apply. The PIM provides for processes and procedures for procurement at sub-national levels. 4. Reference to (if any) Project Operational/Procurement Manual: the Project Implementation Manual (PIM) dated March 30, 2016 has been agreed by the Bank. 5. Summary of the Procurement Packages 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) LASE Upgrade 1.5 1 No Post NCB D/NC Earth Road to DDS/ Late-Rite W/NC Roads B/05/1 (106.96Km) 7 LASE Construction 1.3 1 No Post NCB D/NC of Late-Rite DDS/ Roads = W/NC 29km B/03/1 7 LASE Land 2.4 1 No Post NCB D/NC Preparation DDS/ Agriculture- W/NC Bulldozing, B/02/1 Leveling. 7 Total:2,355.5 0Ha LASE Construction 1.1 1 No Post NCB D/NC of 11 small DDS/ dams. W/NC B/06/1 7 LASE Construction 2.86 1 No Post NCB D/NC of earth roads DDS/ (130Km) W/NC B/04/1 7 LASE Household 0.12 1 No Post NCB D/NC Start-Up DDS/ Packages for G/NC Daung 700 B/12/1 HH (Solar 7 lamp, Tent plastic, mat, blanket, water jar, water filter) LASE Office 0.18 1 No Post NCB D/NC equipment DDS/ (computers & G/NC Photocopy B/03/1 Machines) 6 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) >= US$1,000,000 2. Individual >= US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) LASED/N Consulting 0.12 1 Post CQS CDDS/F/3 firm for 5/17 Irrigation Design (8 sites) LASED/N Baseline 0.07 1 Post CQS CDDS/IC/3 Survey in 0/17 year 2017 (Local Firm) LASED/N Impact 0.05 1 Post CQS CDDS/IC/3 Survey for 1/18 2nd year of the project/Mid- term review (Local Firm) LASED/N Final Impact 0.12 1 Post CQS CDDS/IC/3 Survey 2/21 PROCUREMENT Cambodia : KH-Land Allocation for Social and Economic Development Project II PLAN General Information Country: Cambodia Banks Approval Date of the Original Procurement Plan: 2016-08-18 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-12-07 Project ID: P150631 GPN Date: 2016-10-10 Project Name: KH-Land Allocation for Social and Economic Development Project II Loan / Credit No: IDA / 58070 Executing Agency(ies): National Committee for Sub-National Democratic Development Secretariat WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/W/NCB/08/17 / Construction of Health Posts (3 rooms, fense 400m, gate 1, well1, WC 2rooms, pipe culvert Sub-component 1.2: Land Request for Single Stage - One Pending 1, incinerator 1, 200m of laterite IDA / 58070 Preparation and Infrastructure Post Open - National 183,333.33 0.00 2017-02-06 2017-04-03 2018-04-03 Quotations Envelope Implementation road). Da (1 Unit), Thmey (1 Development Unit) Ksach Sar (1 Unit), Chhean Loeung (1 Unit) and Daung (1 Unit). Total 5 Units. COMMUNE NO 01/17 / Repair Sub-component 1.2: Land Request for Single Stage - One Pending Earth Roads for Sambok IDA / 58070 Preparation and Infrastructure Post Open - National 22,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation (6.6km). Total: 6.6Km Development COMMUNE NO 02/17 / Repair Sub-component 1.2: Land Request for Single Stage - One Pending Earth Roads for Changkrang IDA / 58070 Preparation and Infrastructure Post Open - National 22,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation (6.6km) Total: 6.6Km Development COMMUNE NO 03/17 / Repair Sub-component 1.2: Land Request for Single Stage - One Pending Earth Roads for Thmey (4km). IDA / 58070 Preparation and Infrastructure Post Open - National 13,333.33 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation Total: 4Km Development COMMUNE NO 04/17 / Repair Sub-component 1.2: Land Request for Single Stage - One Pending Earth Roads for Dar (7.8km). IDA / 58070 Preparation and Infrastructure Post Open - National 26,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation Total: 7.8 Km Development COMMUNE NO 05/17 / Water Sub-component 1.2: Land Request for Single Stage - One Pending well (Afredes) for Daung. Phase I: IDA / 58070 Preparation and Infrastructure Post Open - National 60,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation Total: 18 Units Development COMMUNE NO 06/17 / Water Sub-component 1.2: Land Request for Single Stage - One Pending well (Afredes) for Daung Phase II: IDA / 58070 Preparation and Infrastructure Post Open - National 56,666.67 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation Total: 17 Units Development Sub-component 1.2: Land COMMUNE NO 07/17 / Water Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 63,333.33 0.00 2017-06-06 2017-08-01 2018-08-01 well (Afredes) for Thmey 19 Units Quotations Envelope Implementation Development COMMUNE NO 08/17 / Water Sub-component 1.2: Land Request for Single Stage - One Pending well (Afredes) for Chambak 6 IDA / 58070 Preparation and Infrastructure Post Open - National 20,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 Quotations Envelope Implementation Units Development COMMUNE NO 09/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Daung QTY 1 Unit COMMUNE NO 10/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Tipo 1 QTY 1 Unit COMMUNE NO 11/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Tipo 2 QTY 1 Unit COMMUNE NO 12/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Choamkravien QTY 1 Unit COMMUNE NO 13/17 / House for Nurses & Teachers (8mx 20m Sub-component 1.2: Land Request for Single Stage - One Pending x4Rooms, each room equipped IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 Quotations Envelope Implementation with internal kitchen & bathroom) Development for Chambak QTY 1 Unit COMMUNE NO 14/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 31,500.00 Signed 2017-07-06 2017-08-31 2017-10-04 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Development W.C & 4 places of kitchend) for Sambok QTY 1 Unit COMMUNE NO 15/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Under IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Changkrang QTY 1 Unit Page 1 COMMUNE NO 16/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Thmey QTY 1 Unit COMMUNE NO 17/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Dar QTY 1 Unit COMMUNE NO 18/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Ksach Sar QTY 1 Unit COMMUNE NO 19/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Sambok Kriel QTY 1 Unit COMMUNE NO 20/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Peam QTY 1 Unit COMMUNE NO 21/17 / House for Nurses & Teachers (8mx 20m Sub-component 1.2: Land Request for Single Stage - One Pending x4Rooms, each room equipped IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 Quotations Envelope Implementation with internal kitchen & bathroom) Development for Chhean Loeung QTY 1 Unit COMMUNE NO 22/17 / House for Nurses & Teachers Ceramic Sub-component 1.2: Land tile floor (W=9.2m, L=16.2m, Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,000.00 0.00 2017-07-06 2017-08-31 2018-08-31 H=6.82m, 4 bed room, 4 rooms's Quotations Envelope Implementation Development W.C & 4 places of kitchend) for Raksmey Samaki QTY 1 Unit COMMUNE NO 23/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-07-31 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Dar (1). Total: 1 Unit COMMUNE NO 24/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-07-31 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Thmey (1). Total: 1 Unit COMMUNE NO 25/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-07-31 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Chambak (1). Total: 1 Unit COMMUNE NO 26/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-07-31 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Choamkravien (1). Total: 1 Unit COMMUNE NO 27/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Tipo 2 (1). Total: 1 Unit COMMUNE NO 28/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Daung (1). Total: 1 Unit COMMUNE NO 29/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Peam (1). Total: 1 Unit COMMUNE NO 30/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-31 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Chean Loeung (1). Total: 1 Unit COMMUNE NO 31/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Ksach Sor (1). Total: 1 Unit Page 2 COMMUNE NO 32/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Chum Kreal (1). Total: 1 Unit COMMUNE NO 33/17 / Construction of Community Sub-component 1.2: Land Centre Ceramic tile floor Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 29,000.00 0.00 2017-06-06 2017-08-01 2018-08-01 (W=7.2m, L=17.2m, H=6.62m, Quotations Envelope Implementation Development Warehouse, 2 rooms's W.C) for Prey Thom (1). Total: 1 Unit COMMUNITY NO 01/18 / Concrete Poles and Installation Sub-component 1.2: Land Request for Single Stage - One Pending in Agriculture & Residential IDA / 58070 Preparation and Infrastructure Post Open - National 17,700.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation Lands (0.12x0.12x0.75m) for Development Sambok, Kratie (708 Poles). COMMUNITY NO 02/18 / Concrete Poles in Agriculture & Sub-component 1.2: Land Request for Single Stage - One Pending Residential Lands IDA / 58070 Preparation and Infrastructure Post Open - National 17,500.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation (0.12x0.12x0.75m) for Development Changkrang (700 Poles). COMMUNITY NO 05/18 / Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land Request for Single Stage - One Pending (0.12x0.12x0.75m) = (250 Poles) IDA / 58070 Preparation and Infrastructure Post Open - National 6,950.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation and Concrete Poles in Forestry & Development in SLC Sites (0.3x0.3x0.4x1.5m) for Thmey (10 Poles) COMMUNITY NO 06/18 / Concrete Poles in Agriculture & Sub-component 1.2: Land Request for Single Stage - One Pending Residential Lands IDA / 58070 Preparation and Infrastructure Post Open - National 6,750.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation (0.12x0.12x0.75m) for Chambak Development (270 Poles). COMMUNITY NO 07/18 / 1) Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land (0.12x0.12x0.75m) = (700 Poles) Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 18,900.00 0.00 2018-06-06 2018-08-01 2019-08-01 and 2) Concrete Poles in Quotations Envelope Implementation Development Forestry & in SLC Sites (0.3x 0.3x 0.4x 1.5m) for Sambok Kriel (20 Poles) COMMUNITY NO 08/18 / Concrete Poles in Agriculture & Sub-component 1.2: Land Request for Single Stage - One Pending Residential Lands IDA / 58070 Preparation and Infrastructure Post Open - National 10,000.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation (0.12x0.12x0.75m) for Ksach Sar Development (400 Poles). COMMUNITY NO 09/18 / 1) Concrete Poles in Agriculture & Residential Lands Sub-component 1.2: Land Request for Single Stage - One Pending (0.12x0.12x0.75m) = (400 Poles) IDA / 58070 Preparation and Infrastructure Post Open - National 12,100.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation and Concrete Poles in Forestry & Development in SLC Sites (0.3x0.3x0.4x1.5m) for Peam (30 Poles). COMMUNITY NO 10/18 / 1) Concrete Poles in Forestry & in SLC Sites (0.3x0.3x0.4x1.5m) Sub-component 1.2: Land Request for Single Stage - One Pending (20 Poles) and 2) Concrete Poles IDA / 58070 Preparation and Infrastructure Post Open - National 2,570.00 0.00 2018-06-06 2018-08-01 2019-08-01 Quotations Envelope Implementation in Stream and Canal Development (0.2x0.2x1.5m) for Raksmey Samaki (26 Poles) COMMUNITY NO 11/18 / Sub-component 1.2: Land Concrete Poles in Stream and Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 15,750.00 0.00 2018-06-06 2018-08-01 2019-08-01 Canal (0.2x0.2x1.5m) for Quotations Envelope Implementation Development Chaomkravien (350 Poles). COMMUNITY NO 13/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 7,500.00 0.00 2018-03-06 2018-05-01 2018-10-28 (W5xT0.15xE0.5m). for Sambok Quotations Envelope Implementation Development (6km). COMMUNITY NO 14/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 7,500.00 0.00 2018-03-06 2018-05-01 2018-10-28 (W5xT0.15xE0.5m) for Quotations Envelope Implementation Development Changkrang (6km). COMMUNITY NO 15/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Planting Grass of Earth Roads IDA / 58070 Preparation and Infrastructure Post Open - National 10,000.00 0.00 2018-03-06 2018-05-01 2018-10-28 Quotations Envelope Implementation (W5xT0.15xE0.5m) for Da (8km). Development COMMUNITY NO 16/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 6,250.00 0.00 2018-08-06 2018-10-01 2019-03-30 (W5xT0.15xE0.5m) for Quotations Envelope Implementation Development Choamkravien (5Km) COMMUNITY NO 17/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 18,750.00 0.00 2018-03-06 2018-05-01 2018-10-28 (W5xT0.15xE0.5m) for Tipo 1 Quotations Envelope Implementation Development (15Km) COMMUNITY NO 18/18 / Sub-component 1.2: Land Planting Grass of Earth Roads Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 15,000.00 0.00 2018-03-06 2018-05-01 2018-10-28 (W5xT0.15xE0.5m) for Tipo 2 Quotations Envelope Implementation Development (12Km) COMMUNITY NO 19/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Box Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 16,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (2x3x6m) for Sambok (1) Development COMMUNITY NO 20/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Box Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 16,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (2x3x6m) for Changkrang (1 Unit) Development Page 3 COMMUNITY NO 21/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Box Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 16,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (2x3x6m) for Dar (1 Unit) Development COMMUNITY NO 22/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Box Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 32,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (2x3x6m) for Thmey (2 Units) Development COMMUNITY NO 23/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 32,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (2x3x6m) for Chambak. Phase 1 Quotations Envelope Implementation Development (2 Units) COMMUNITY NO 24/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 32,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (2x3x6m) for Chambak. Phase 2 Quotations Envelope Implementation Development (2 Units) COMMUNITY NO 25/18 / Sub-component 1.2: Land Construction of Box Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 32,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (2x3x6m) for Chambak. Phase 3 Quotations Envelope Implementation Development (2 Units) COMMUNITY NO 26/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 20,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Sambok, Kratie: 8 Quotations Envelope Implementation Development Units COMMUNITY NO 27/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 20,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Changkrang, Kratie: Quotations Envelope Implementation Development 8 Units COMMUNITY NO 28/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Pipe Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 15,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (H1xL6m) for Dar, Kratie: 6 Units Development COMMUNITY NO 29/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 17,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Thmey, Kratie: 7 Quotations Envelope Implementation Development Units COMMUNITY NO 30/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 10,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Chambak, Kratie: 4 Quotations Envelope Implementation Development Units COMMUNITY NO 31/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 20,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Choamkravien, Kg. Quotations Envelope Implementation Development Cham: 8 Units COMMUNITY NO 32/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Tipo 1 (10), Kg. Quotations Envelope Implementation Development Thom: 11 Units. COMMUNITY NO 33/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Tipo 2 (10), Kg. Quotations Envelope Implementation Development Thom. Total: 11 Units COMMUNITY NO 34/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 25,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Sambok Kriel: 10 Quotations Envelope Implementation Development Units COMMUNITY NO 35/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 37,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Ksach Sar: 15 Quotations Envelope Implementation Development Units COMMUNITY NO 36/18 / Sub-component 1.2: Land Request for Single Stage - One Pending Construction of Pipe Culverts IDA / 58070 Preparation and Infrastructure Post Open - National 12,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation (H1xL6m) for Peam: 5 Units Development COMMUNITY NO 37/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 25,000.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Chhean Loeun: 10 Quotations Envelope Implementation Development Units COMMUNITY NO 38/18 / Sub-component 1.2: Land Construction of Pipe Culverts Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 37,500.00 0.00 2018-06-06 2018-08-01 2019-01-28 (H1xL6m) for Raksmey Samaki: Quotations Envelope Implementation Development 15 Units LASED/NCDDS/W/NCB/01/17 / 1) Concrete Poles in Agriculture & Residential Lands (0.12 x 0.12 x 0.75m) = (5000 Poles), 2) Sub-component 1.2: Land Concrete Poles in Forestry & in Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 160,555.56 0.00 2017-10-07 2017-12-02 2018-05-31 SLC Sites (0.3x0.3x0.4x1.5m) Quotations Envelope Implementation Development (150 Poles) and 3) Concrete Poles in Stream and Canal (0.2x0.2x1.5m) for Daung (200 Poles). LASED/NCDDS/W/NCB/04/17 / Construction Earth Roads(W5xT0.15xE0.5m):LOT1: Sambok(6), Ch.krang(6),Dar(8), Thmey(10km), Sub-component 1.2: Land Chambak(12),Choamkravien- Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 2,860,000.00 0.00 2017-06-01 2017-06-06 2017-07-18 2017-08-17 2017-09-21 2018-03-20 TKM(5), TP1(15), TP2(12). Envelope Implementation Development Total:74km. LOT 2:S.Kriel(14km), Ks.Sar(14), Peam(14), Chh.Loeung(7), Ra.Samaki(7). Total:56km. Grand Total:130Km Page 4 LASED/NCDDS/W/NCB/06/17 / Small Dam(W4xSite Slop1:2, average embankment, length depends on each site,1spill way 20m,water double gates Sub-component 1.2: Land Single Stage - One Pending (2x2m=4m):Lot IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 1,100,000.00 0.00 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 2018-09-19 Envelope Implementation 1:S.bok(1),Ch.krang(1), Development Thmey(1),Chambak(1),TP1(1),TP 2(1)&Daung(1).Lot 2:Sb.Kriel(1),Ks.Sar(1),Peam(1) and R.Samaki(1).Total: 11Unit LASED/NCDDS/W/NCB/02/17 / Land Preparation Agriculture- Buldozing, Leveling:LOT1: S.Kriel(100), Ksa.Sar(126.50),Peam(116.50), Sub-component 1.2: Land Chh.loeung(103), Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 2,355,500.00 0.00 2017-02-01 2017-02-06 2017-03-20 2017-04-19 2017-05-24 2017-11-20 Ra.Samaki(200), TP1(276), TP2 Envelope Implementation Development (226.50), S.bok(100), Ch.Krang(59), Dar(97), Thmey(174)&Chambak(277). LOT2:Daung (500).Grand Total:2,355.50Ha LASED/NCDDS/W/NCB/03/17 / Construction of Lot 1. Late-Rite Sub-component 1.2: Land Roads (W5xT0.15xE0.5m) = Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 1,342,000.00 0.00 2017-12-01 2017-12-06 2018-01-17 2018-02-16 2018-03-23 2018-09-19 22km. Lot 2. Earth Roads Envelope Implementation Development (W5xT0.15xE0.5m) for Daung = 29km LASED/NCDDS/W/SP/09/17 / Build board Construction, Installation and Renew Banner Sub-component 1.2: Land Request for Single Stage - One Pending (New bill board 3 sites at KSP, IDA / 58070 Preparation and Infrastructure Post Open - National 116,666.67 0.00 2017-11-06 2018-01-01 2018-06-30 Quotations Envelope Implementation KPT and KCH) and Renews Development banner for existing bill board 9 sites. LASED/NCDDS/W/NCB/07/17 / Construction of Primary Schools (5Rooms, 4WCs, 1Well, 1Flag Pole) Incl. 250chairs connected Sub-component 1.2: Land with tables, 5Tables & 5Chairs Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 711,111.11 0.00 2017-09-15 2017-09-20 2017-11-01 2017-12-01 2018-01-05 2018-07-04 and Whiteboards for: Tipo1, Envelope Implementation Development Chambak, Sambok, Raksmey Samaki (KSP), Ksach Sar (KCH), Choamkravien and Daung (2units) Total:8Units LASED/NCDDS/W/SP/01/17 / "Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): Main IDA / 58070 Preparation and Infrastructure Post Open - National 158,888.89 0.00 2017-12-20 2018-02-14 2018-08-13 Quotations Envelope Implementation Road, KPT Development Tipo 1 and 2 = 11km. " LASED/NCDDS/W/SP/02/18 / "Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Roads (W4.5mxT0.15m): Main Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 216,666.67 0.00 2018-03-06 2018-05-01 2018-10-28 Road KCH Quotations Envelope Implementation Development Sambokreal = 9km and Khsach Sor = 6km. (Total = 15km)" COMMUNE/KPT/W/37/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Roads (W4.5mxT0.15m):, Tipo 1 Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 61,677.78 0.00 2018-08-06 2018-10-01 2019-03-30 (AR3=0.95km, ART=0.71km, Quotations Envelope Implementation Development AR2=1.26km, AR4=1,35) Total= 4.27km. (Package1) COMMUNE/KPT/W/38/18 / Upgrade Earth Road to Late-Rite Roads (W4.5mxT0.15m): Tipo 1 Sub-component 1.2: Land Request for Single Stage - One Pending (AR6=1.30km, AR=14km, IDA / 58070 Preparation and Infrastructure Post Open - National 75,111.11 0.00 2018-08-06 2018-10-01 2019-03-30 Quotations Envelope Implementation AR16=0.85km, AR18=0.46, and Development AA1= 1.42) Total= 5.2km. (Package2) COMMUNE/KPT/W/39/18 / Upgrade Earth Road to Late-Rite Roads (W4.5mxT0.15m): Tipo 2 Sub-component 1.2: Land Request for Single Stage - One Pending (AR01=1.10km, AR02=1.20km, IDA / 58070 Preparation and Infrastructure Post Open - National 84,933.33 0.00 2018-07-07 2018-09-01 2019-02-28 Quotations Envelope Implementation AR03=1.20km, AR04=1.13km, Development ARAR05=1.25km)= Total:5.88km (Package 1) COMMUNE/KPT/W/40/18 / Upgrade Earth Road to Late-Rite Roads (W4.5mxT0.15m): Tipo 2 Sub-component 1.2: Land Request for Single Stage - One Pending (AR06=1.10km, AR07=1.15km, IDA / 58070 Preparation and Infrastructure Post Open - National 67,166.67 0.00 2018-07-07 2018-09-01 2019-02-28 Quotations Envelope Implementation AR08=1.00km, AR09=0.60km, Development AR10=0.80km)= Total:4.65km (Package 2) COMMUNE/KCH/W/41/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Infrastructure Post Open - National 77,133.33 0.00 2018-04-07 2018-06-02 2018-11-29 Quotations Envelope Implementation Sambok Kriel = (URR/7lines = Development 5.34km). (Package 1) COMMUNE/KCH/W/42/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): IDA / 58070 Preparation and Infrastructure Post Open - National 67,311.11 0.00 2018-04-07 2018-06-02 2018-11-29 Quotations Envelope Implementation Sambok Kriel = (URR/5lines = Development 4.66km). (Package 2) COMMUNE/KCH/W/43/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): Ksach IDA / 58070 Preparation and Infrastructure Post Open - National 69,333.33 0.00 2018-04-07 2018-06-02 2018-11-29 Quotations Envelope Implementation Sar = (URR/2lines & UAR/6lines Development = 4.8km). Page 5 COMMUNE/KCH/W/44/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): Peam IDA / 58070 Preparation and Infrastructure Post Open - National 81,900.00 0.00 2018-04-07 2018-06-02 2018-11-29 Quotations Envelope Implementation = (URR/9lines) = 5.67km. Development (Package 1) COMMUNE/KCH/W/45/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m): Peam IDA / 58070 Preparation and Infrastructure Post Open - National 83,344.44 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation = (URR/5lines & UAR/3lines). Development Total = 5.77km. (Package 2) COMMUNE/KCH/W/46/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m):Chhean IDA / 58070 Preparation and Infrastructure Post Open - National 59,944.44 0.00 2018-06-06 2018-08-01 2019-01-28 Quotations Envelope Implementation Loeung = (URR/12lines) = Development 4.15km. (Package 1) COMMUNE/KCH/W/47/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m):Chhean IDA / 58070 Preparation and Infrastructure Post Open - National 63,555.56 0.00 2018-07-07 2018-09-01 2019-02-28 Quotations Envelope Implementation Loeung = (UAR/4lines). Total = Development 4.40km. (Package 2) COMMUNE/KCH/W/48/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Request for Single Stage - One Pending Roads (W4.5mxT0.15m):Chhean IDA / 58070 Preparation and Infrastructure Post Open - National 74,677.78 0.00 2018-07-07 2018-09-01 2019-02-28 Quotations Envelope Implementation Loeung = (UAR/6lines). Total = Development 5.17km. (Package 3) COMMUNE/KSP/W/49/18 / Upgrade Earth Road to Late-Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Raksmey Samaki, KSP = Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 68,611.11 0.00 2018-02-06 2018-04-03 2018-09-30 (Up1=3.40km, Up2=0.30 km, Quotations Envelope Implementation Development Up3=0.15 km, Up4=0.30 km, Up5=0.30 km, and Up6=0.30km) = 4.75km. (Package 1) COMMUNE/KSP/W/50/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Roads (W4.5mxT0.15m): Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 75,833.33 0.00 2018-02-06 2018-04-03 2018-09-30 Raksmey Samaki, KSP = Quotations Envelope Implementation Development (Up7=3.50 km, and Up9=1.75km) = 5.25km. (Package 2) COMMUNE/KSP/W/51/18 / Upgrade Earth Road to Late-Rite Roads (W4.5mxT0.15m): Sub-component 1.2: Land Request for Single Stage - One Pending Raksmey Samaki, KSP = IDA / 58070 Preparation and Infrastructure Post Open - National 74,388.89 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation (Up8=1.65 km, and Development Up10=3.50km) = 5.15km. (Package 3) COMMUNE/KSP/W/52/18 / Upgrade Earth Road to Late-Rite Sub-component 1.2: Land Roads (W4.5mxT0.15m): Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 84,500.00 0.00 2018-03-06 2018-05-01 2018-10-28 Raksmey Samaki, KSP - Main = Quotations Envelope Implementation Development (Up11=5.85km) = 5.85km. (Package 4) LASED/NCDDS/W/NCB/05/17 / Upgrade Earth Road to Late-Rite Roads(W4.5mxT0.15m):LOT 1: Tipo1(9.47km), Tipo2 (10.53km) and Main Road (11km). Total Sub-component 1.2: Land Single Stage - One 31km. LOT 2: S.Kriel(19km), IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 1,544,977.78 0.00 Canceled 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 Envelope K.Sar(10.80km), Development Peam(11.44km), Chh.Loeung(13.72km) & Ra.Samaki(21km). Total: 75.96km. Grand Total 106.96Km GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/G/NCB/07/16 / OfficeFurniture:Nat.+3NewProvi:( 30MeetChr, 28Desks, 58Chr, 4MeetTab, 2Filingcabi,3SlidingCabi,6FilingC abi). 3Distr:(15Des, 45Chr, Component 2: Project Request for Single Stage - One Under IDA / 58070 Post Open - National 40,110.00 37,270.50 2017-02-06 2017-04-03 2018-04-03 3SlidingCabi, 3FilingCabi, Management Quotations Envelope Implementation 3MeetTab) 5NewHP:(10Des,10Char,5Sliding Cabi,5FilingCabi+4Draw, 5Connected 3Cha,10Bed,5WaterFilter) LASED/NCDDS/G/SP/09/17 / 1). Mobile loud speaker (Loud Speaker, Stand, Transmitter and Receiver) for LASED GSSLC, Sub-component 1.3: Agriculture Request for Single Stage - One Pending NCDDS and GDA. Toal: 3 sets. IDA / 58070 Post Limited 11,500.00 0.00 2017-05-06 2017-07-01 2017-12-28 and Livelihood Development Quotations Envelope Implementation 2). Loud Speaker ( Loud Speaker, Microphone, Ampli, Battery and Electrical line) for 12 SLC Community Toal: 14 sets. LASED/NCDDS/G/SP/10/17 / GPS Mapping+Licenses: NCDDS 2, GSSLC 4, GDA 5, Sub-Component 1.1: Social (KCH,KSP,TBM) 3, Total Land Concession Investment GPS:14 units. Concrete Test Planning and Prioritization Request for Single Stage - One Under Hammer for 3 new provinces 3 & IDA / 58070 Post Open - National 44,311.11 0.00 2017-02-06 2017-04-03 2017-09-30 Sub-component 1.2: Land Quotations Envelope Implementation for NCDDS 1. Dynamic Cone Preparation and Infrastructure Penetrometer(DCP) for new Development provinces 3 and NCDDS 1. Topography Survey for new provinces 3 &NCDDS 1. Page 6 LASED/NCDDS/G/NCB/12/17 / Household Start-Up Packages for Sub-component 1.2: Land Single Stage - One Pending Daung 700 HH (Solar lamp, Tent IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 116,666.67 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Envelope Implementation plastic, mat, blanket, water jar, Development water filter) LASED/NCDDS/G/NCB/01/16 / Sub-component 1.3: Agriculture Single Stage - One Vehicles : 9 Pickup Trucks for IDA / 58070 Post Request for Bids Open - National 270,000.00 243,531.00 Signed 2016-11-14 2016-11-19 2016-12-31 2017-01-12 2017-01-30 2017-02-09 2017-03-06 2017-02-16 2017-09-02 and Livelihood Development Envelope National Level and Sub-National. LASED/NCDDS/G/SP/06/16 / Component 2: Project Request for Single Stage - One Software (GIS, Accounting) for IDA / 58070 Post Open - National 24,200.00 15,760.00 Signed 2016-11-26 2017-01-21 2017-09-15 2018-01-21 Management Quotations Envelope NCDDS, GSSLC & GDA LASED/NCDDS/G/SP/04/16 / Camera Equipment. A) National level: 1) Professional Camera (3 units) and Professional Video Sub-Component 1.1: Social Request for Single Stage - One Pending Camera (3 units) for LASED- IDA / 58070 Land Concession Investment Post Open - National 32,000.00 0.00 2017-01-06 2017-03-03 2018-03-03 Quotations Envelope Implementation GSSLC Communication, LASED- Planning and Prioritization NCDDS & GDA. B) Provincial: 1) Camera (5 units); 2) Aircon (6 units). LASED/NCDDS/G/NCB/02/16 / Motorcycles: for Province(KSP: 10, KCH: 10, TBK: 10), for District: (SMC: 5, OR: 5, PBL:5), Sub-component 1.2: Land Single Stage - One for Communes: (CL:1, PM:1, IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 115,500.00 100,170.00 Signed 2016-12-31 2016-12-26 2017-01-05 2017-02-16 2017-02-02 2017-03-18 2017-03-21 2017-04-22 2017-05-02 2018-04-22 Envelope RSMSK:1, DG:1, KLV:1), for Development NCDDS: 3 Units, GSSLC: 3 Units, GDA: 7 Units. Total 63 Units LASED/NCDDS/G/NCB/03/16 / Computer&Photocopy Machine: Lot 1: Nat.: 37Laptops,3LaserJet Printers, 4Scaners. Provi.: 49Laptops, 5LaserJet Printer & Component 2: Project Single Stage - One 5Scaner. Distr.:14Laptops, IDA / 58070 Post Request for Bids Open - National 177,460.00 191,151.40 Signed 2016-11-30 2017-04-12 2016-12-05 2017-01-16 2017-06-08 2017-02-15 2017-08-08 2017-03-22 2017-09-12 2018-03-22 Management Envelope 7LaserJet Printers.Lot 2: Nat.: 3Photocopy, 4LCD Projector+Screen, Provi.:5Photocopy & 5LCD Projector+Screen LASED/NCDDS/G/NCB/11/17 / Agriculture Start-Up Packages Sub-component 1.2: Land Single Stage - One Pending for Daung 700 HH (Agri kits 8 IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 280,000.00 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-09-20 Envelope Implementation items, rice 200kg/HH, vegetable Development seeds 6 items, plants 5 items) LASED/NCDDS/G/NCB/13/17 / Sub-component 1.2: Land Single Stage - One Pending Shelter Construction Materials IDA / 58070 Preparation and Infrastructure Post Request for Bids Open - National 217,777.78 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-09-20 Envelope Implementation (40 Zincs/HH) for Daung 700HH Development Sub-Component 1.1: Social LASED/NCDDS/G/SP/08/16 / Request for Single Stage - One IDA / 58070 Land Concession Investment Post Limited 2,720.00 0.00 Canceled 2017-02-06 2017-04-03 2017-10-03 Soil Testing Kits (16 kits) Quotations Envelope Planning and Prioritization COMMUNE/G/01/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-09-03 Sambok Kriel (100Ha), Quotations Envelope Implementation Development Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/02/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,138.89 0.00 2018-01-06 2018-03-03 2018-08-30 Ksach Sar (126.50Ha), Quotations Envelope Implementation Development Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/02/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 35,138.89 0.00 2018-01-06 2018-03-03 2018-08-30 Ksach Sar (126.50Ha), Quotations Envelope Implementation Development Kranglovea Commune, Samaki Meanchey District, Kg. Chhnang COMMUNE/G/03/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 32,361.11 0.00 2018-01-06 2018-03-03 2018-08-30 Peam Commune (116.5Ha), Quotations Envelope Implementation Development Samaki Meanchey District, Kg. Chhnang COMMUNE/G/04/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 28,611.11 0.00 2018-01-06 2018-03-03 2018-08-30 Chheanloeurng Commune Quotations Envelope Implementation Development (103Ha), Samaki Meanchey District, Kg. Chhnang COMMUNE/G/05/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Reaksmey Samaki Commune Quotations Envelope Implementation Development (100Ha), Oral District, Kg. Speu (PHASE 1) COMMUNE/G/06/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Reaksmey Samaki Commune Quotations Envelope Implementation Development (100Ha), Oral District, Kg. Speu. (PHASE 2) COMMUNE/G/07/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Tipo 1 (100 Ha) Commune, Quotations Envelope Implementation Development Suntuk District, Kg. Thom. (PHASE 1) Page 7 COMMUNE/G/08/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Tipo 1 (100 Ha) Commune, Quotations Envelope Implementation Development Suntuk District, Kg. Thom. (PHASE 2) COMMUNE/G/09/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 21,111.11 0.00 2018-01-06 2018-03-03 2018-08-30 Tipo 1 (76 Ha), Commune, Quotations Envelope Implementation Development Suntuk District, Kg. Thom. (PHASE 3) COMMUNE/G/10/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 30,694.44 0.00 2018-01-06 2018-03-03 2018-08-30 Tipo 2 (110.5 Ha) Commune, Quotations Envelope Implementation Development Suntuk District, Kg. Thom. (PHASE 1) COMMUNE/G/11/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 32,222.22 0.00 2018-01-06 2018-03-03 2018-08-30 Tipo 2 (116 Ha) Commune, Quotations Envelope Implementation Development Suntuk District, Kg. Thom. (PHASE 2) COMMUNE/G/12/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land Request for Single Stage - One Pending and Seedling for Cover Crop) for IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Quotations Envelope Implementation Sambok Commune (100Ha), Development Chetr Borey, Kratie COMMUNE/G/13/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land Request for Single Stage - One Pending and Seedling for Cover Crop) for IDA / 58070 Preparation and Infrastructure Post Open - National 16,388.89 0.00 2018-01-06 2018-03-03 2018-08-30 Quotations Envelope Implementation Changkrang Commune (59Ha), Development Chetr Borey, Kratie COMMUNE/G/14/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land Request for Single Stage - One Pending and Seedling for Cover Crop) for IDA / 58070 Preparation and Infrastructure Post Open - National 26,944.44 0.00 2018-01-06 2018-03-03 2018-08-30 Quotations Envelope Implementation Dar Commune (97Ha), Chetr Development Borey, Kratie COMMUNE/G/15/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land Request for Single Stage - One Pending and Seedling for Cover Crop) for IDA / 58070 Preparation and Infrastructure Post Open - National 24,166.67 0.00 2018-01-06 2018-03-03 2018-08-30 Quotations Envelope Implementation Thmey Commune (87Ha), Chetr Development Borey, Kratie. (PHASE 1) COMMUNE/G/16/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land Request for Single Stage - One Pending and Seedling for Cover Crop) for IDA / 58070 Preparation and Infrastructure Post Open - National 24,166.67 0.00 2018-01-06 2018-03-03 2018-08-30 Quotations Envelope Implementation Thmey Commune (87Ha), Chetr Development Borey, Kratie. (PHASE 2) COMMUNE/G/17/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Chambak Commune, Prek Quotations Envelope Implementation Development Prasab, Kratie (PHASE 1)-100Ha of (277Ha) COMMUNE/G/18/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Chambak Commune, Prek Quotations Envelope Implementation Development Prasab, Kratie (PHASE 2)-100Ha of (277Ha) COMMUNE/G/19/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 21,388.89 0.00 2018-01-06 2018-03-03 2018-08-30 Chambak Commune, Prek Quotations Envelope Implementation Development Prasab, Kratie (PHASE 3)-77Ha of (277Ha) COMMUNE/G/20/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Daung Commune, Prasad Quotations Envelope Implementation Development Balang, Kg. Thom. PHASE 1 (110Ha) of 500Ha COMMUNE/G/21/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Daung Commune, Prasad Quotations Envelope Implementation Development Balang, Kg. Thom. PHASE 2 (100Ha) of 500Ha COMMUNE/G/22/16 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Daung Commune, Prasad Quotations Envelope Implementation Development Balang, Kg. Thom. PHASE 3 (100Ha) of 500Ha COMMUNE/G/23/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Daung Commune, Prasad Quotations Envelope Implementation Development Balang, Kg. Thom. PHASE 4 (100Ha) of 500Ha COMMUNE/G/24/18 / Planting in Agriculture Land (Ploughing Sub-component 1.2: Land and Seedling for Cover Crop) for Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 27,777.78 0.00 2018-01-06 2018-03-03 2018-08-30 Daung Commune (500Ha), Quotations Envelope Implementation Development Prasad Balang, Kg. Thom. PHASE 5 (100Ha) of 500Ha Page 8 COMMUNITY 01G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 2,777.78 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Sambok Kriel Development (100Ha) COMMUNITY 02G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 3,513.89 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Ksach Sar Development (126.50Ha) COMMUNITY 03G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 3,236.11 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Peam Development (116.50Ha) COMMUNITY 04G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 2,861.11 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Chheanloeung Development (103Ha) COMMUNITY 05G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 5,555.56 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Raksmey Development Samaki (200Ha) COMMUNITY 06G/18 / Planting Sub-component 1.2: Land in Agriculture Land (Sowing Seed Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 7,666.67 0.00 2018-02-06 2018-04-03 2018-09-30 or Planting Seedling cover crop) Quotations Envelope Implementation Development for community in Tipo 1 (276Ha) COMMUNITY 07G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 6,291.67 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Tipo 2 Development (226.50Ha) COMMUNITY 08G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 2,777.78 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Sambok Development (100Ha) COMMUNITY 09G/18 / Planting in Agriculture Land (Sowing Seed Sub-component 1.2: Land Request for Single Stage - One Pending or Planting Seedling cover crop) IDA / 58070 Preparation and Infrastructure Post Open - National 1,638.89 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation for community in Changkrang Development (59Ha) COMMUNITY 10G/18 / Planting Sub-component 1.2: Land in Agriculture Land (Sowing Seed Request for Single Stage - One Pending IDA / 58070 Preparation and Infrastructure Post Open - National 2,694.44 0.00 2018-02-06 2018-04-03 2018-09-30 or Planting Seedling cover crop) Quotations Envelope Implementation Development for community in Dar (97Ha) COMMUNITY 011G/18 / Planting in Agriculture Land Sub-component 1.2: Land Request for Single Stage - One Pending (Sowing Seed or Planting IDA / 58070 Preparation and Infrastructure Post Open - National 4,833.33 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation Seedling cover crop) for Development community in Thmey (174Ha) COMMUNITY 012G/18 / Planting in Agriculture Land Sub-component 1.2: Land Request for Single Stage - One Pending (Sowing Seed or Planting IDA / 58070 Preparation and Infrastructure Post Open - National 7,694.44 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation Seedling cover crop) for Development community in Chambak (277Ha) COMMUNITY 013G/18 / Planting in Agriculture Land Sub-component 1.2: Land Request for Single Stage - One Pending (Sowing Seed or Planting IDA / 58070 Preparation and Infrastructure Post Open - National 13,888.89 0.00 2018-02-06 2018-04-03 2018-09-30 Quotations Envelope Implementation Seedling cover crop) for Development community in Daung (500Ha) LASED/NCDDS/G/SP/01A/17 / Sub-component 1.3: Agriculture Request for Single Stage - One Under 1 Pickup Trucks for National IDA / 58070 Post Open - National 30,000.00 0.00 2017-10-06 2017-12-01 2018-04-03 and Livelihood Development Quotations Envelope Implementation Level. LASED/NCDDS/G/SP/05A/16 / Building new networking data center for LASED-NCDDS (1 Component 2: Project Request for Single Stage - One Pending server, Back up Storage 4TB, IDA / 58070 Post Open - National 48,650.00 0.00 2017-12-06 2018-01-31 2018-05-01 Management Quotations Envelope Implementation UPS, Other Software license, Internet service 4 years) and Android Tablet (50 Tablets) LASED/NCDDS/G/SP/05/16 / Building new networking data center for LASED-NCDDS (1 Component 2: Project Request for Single Stage - One IDA / 58070 Post Open - National 36,000.00 0.00 Canceled 2016-12-06 2017-01-31 2018-01-31 server machine, fiber optic cable, Management Quotations Envelope and network accessory) and Internet Service Provider NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/35/17 / Insurance (Group Personal Accident and Health Insurance Component 2: Project Single Stage - One Pending IDA / 58070 Post Request for Bids Open - National 108,900.00 0.00 2017-03-01 2017-03-06 2017-04-17 2017-05-17 2017-06-21 2021-12-31 and Vehicle Insurance (Third Management Envelope Implementation Party Liability Driver and Passenger) CONSULTING FIRMS Page 9 Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/30/17 / Sub-Component 1.1: Social Consultant Pending Baseline Survey in year 2017 IDA / 58070 Land Concession Investment Post Qualification Open - National 70,000.00 0.00 2017-01-31 2017-02-21 2017-04-06 2017-05-06 2017-06-10 2018-06-10 Implementation (Local Firm) Planning and Prioritization Selection LASED/NCDDS/IC/31/18 / Sub-Component 1.1: Social Consultant Impact Survey for 2nd year of the Pending IDA / 58070 Land Concession Investment Post Qualification Open - National 50,000.00 0.00 2017-12-31 2018-01-21 2018-03-06 2018-04-05 2018-05-10 2019-05-10 project/Mid-term review (Local Implementation Planning and Prioritization Selection Firm) LASED/NCDDS/IC/34/17 / Service Provider for Sub-component 1.3: Agriculture Quality Based Pending IDA / 58070 Post Open - International 514,100.00 0.00 2017-02-01 2017-02-22 2017-04-07 2017-05-05 2017-06-04 2017-07-04 2017-08-08 2021-12-31 Implementation Community and Livelihood Development Selection Implementation Development Fund (for 5 years) Sub-component 1.2: Land Consultant LASED/NCDDS/IC/32/21 / Final Pending IDA / 58070 Preparation and Infrastructure Post Qualification Open - International 90,000.00 0.00 2021-01-01 2021-01-22 2021-03-07 2021-04-06 2021-05-11 2021-12-31 Impact Survey Implementation Development Selection LASED/NCDDS/F/35/17 / Sub-Component 1.1: Social Consultant Pending Consulting firm for Irrigation IDA / 58070 Land Concession Investment Post Qualification Open - National 120,000.00 0.00 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2018-01-23 2018-06-12 Implementation Design (8 sites) Planning and Prioritization Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LASED/NCDDS/IC/10/17 / Component 2: Project Individual Consultant Pending Admin and Finance Assistant at IDA / 58070 Post Open 56,470.59 0.00 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Selection Implementation NCDDS LASED/NCDDS/IC/11/17 / Component 2: Project Individual Consultant Pending Admin and Finance Assistant at IDA / 58070 Post Open 56,470.59 0.00 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Selection Implementation GDA-MAFF LASED/NCDDS/IC/12/17 / Component 2: Project Individual Consultant Pending Admin and Finance Assistant at IDA / 58070 Post Open 56,470.59 0.00 2017-01-01 2017-02-19 2017-03-12 2017-04-16 2021-12-31 Management Selection Implementation GSSLC LASED/NCDDS/IC/04/16 / Sub-component 1.2: Land Individual Consultant Project Finance Consultant at IDA / 58070 Preparation and Infrastructure Prior Open 148,235.29 0.00 Canceled 2016-09-01 2016-09-16 2016-10-20 2016-11-10 2016-12-15 2021-08-31 Selection GSSLC & GDA Development LASED/NCDDS/IC/01/16 / Sub-component 1.2: Land Individual Consultant National Operation and M&E IDA / 58070 Preparation and Infrastructure Prior Open 148,235.29 0.00 Canceled 2016-08-16 2016-10-04 2016-10-25 2016-11-29 2021-08-31 Selection Advisor at NCDDS Development LASED/NCDDS/IC/05/16 / Sub-component 1.2: Land Individual Consultant National Infrastructure Advisor at IDA / 58070 Preparation and Infrastructure Prior Open 118,588.24 0.00 Canceled 2016-09-01 2016-10-03 2016-10-20 2016-11-10 2016-12-15 2020-11-30 Selection GSSLC Development LASED/NCDDS/IC/06/16 / Sub-component 1.2: Land Individual Consultant National Operation and M&E IDA / 58070 Preparation and Infrastructure Prior Open 148,235.29 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2021-08-31 Selection Advisor at GSSLC Development LASED/NCDDS/IC/07/16 / National Agriculture & Rural Sub-component 1.3: Agriculture Individual Consultant IDA / 58070 Prior Open 148,235.29 0.00 Canceled 2016-09-01 2016-09-19 2016-10-20 2016-11-10 2016-12-15 2021-08-31 Development Advisor at GDA - and Livelihood Development Selection MAFF LASED/NCDDS/IC/08/16 / Sub-component 1.2: Land Individual Consultant National Communication & IDA / 58070 Preparation and Infrastructure Prior Open 118,588.24 0.00 Canceled 2016-12-01 2017-01-19 2017-02-09 2017-03-16 2020-11-30 Selection Strategy Advisor at NCDDS Development LASED/NCDDS/IC/13/17 / One Sub-Component 1.1: Social Provincial GIS, Safeguard and Individual Consultant Pending IDA / 58070 Land Concession Investment Post Open 101,647.06 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Environemental Advisor at Selection Implementation Planning and Prioritization LASED Kratie LASED/NCDDS/IC/14/17 / One Provincial GIS, Safeguard and Sub-Component 1.1: Social Individual Consultant Pending Environemental Advisor for IDA / 58070 Land Concession Investment Post Open 101,647.06 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Selection Implementation LASED Kg. Thom and Thbong Planning and Prioritization Khmum LASED/NCDDS/IC/15/17 / One Provincial GIS, Safeguard and Sub-Component 1.1: Social Individual Consultant Pending Environmental Advisor for LASED IDA / 58070 Land Concession Investment Post Open 101,647.06 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-04-15 Selection Implementation Kampong Speu and Kampong Planning and Prioritization Chhnang. LASED/NCDDS/IC/16/17 / Sub-component 1.2: Land Individual Consultant Pending Provincial Operation Advisor for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Selection Implementation LASED Kratie. Development LASED/NCDDS/IC/17/17 / Sub-component 1.2: Land Individual Consultant Pending Provincial Operation Advisor for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Selection Implementation LASED Tbong Khmum. Development LASED/NCDDS/IC/18/17 / Sub-component 1.2: Land Individual Consultant Pending Provincial Operation Advisor for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Selection Implementation LASED Kg. Thom. Development LASED/NCDDS/IC/19/17 / Sub-component 1.2: Land Individual Consultant Pending Provincial Operation Advisor for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Selection Implementation LASED Kg. Speu. Development LASED/NCDDS/IC/20/17 / Sub-component 1.2: Land Individual Consultant Pending Provincial Operation Advisor for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-12-31 2017-02-18 2017-03-11 2017-04-15 2021-12-31 Selection Implementation LASED Kg. Chhnang. Development Page 10 LASED/NCDDS/IC/21/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Finance Consultant for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation LASED Kratie. Development LASED/NCDDS/IC/22/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Finance Consultant for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation LASED Thbong Khmum. Development LASED/NCDDS/IC/23/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Finance Consultant for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation LASED Kg. Thom. Development LASED/NCDDS/IC/24/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Finance Consultant for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation LASED Kg. Speu. Development LASED/NCDDS/IC/25/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Finance Consultant for IDA / 58070 Preparation and Infrastructure Post Open 109,411.76 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation LASED Kg. Chhnang. Development LASED/NCDDS/IC/01A/16 / Sub-component 1.2: Land Individual Consultant Under Senior Sub-National Project IDA / 58070 Preparation and Infrastructure Post Open 155,294.12 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation Management Advisor at NCDDS Development LASED/NCDDS/IC/05A/16 / Sub-component 1.2: Land Individual Consultant Under Senior National Infrastructure IDA / 58070 Preparation and Infrastructure Post Open 118,588.24 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Selection Implementation Advisor at GSSLC Development LASED/NCDDS/IC/06A/16 / Sub-component 1.2: Land Individual Consultant Under Senior National Operation and IDA / 58070 Preparation and Infrastructure Post Open 176,470.59 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Selection Implementation M&E Advisor at GSSLC Development LASED/NCDDS/IC/07A/16 / Senior National Agriculture & Sub-component 1.3: Agriculture Individual Consultant Under IDA / 58070 Post Open 148,235.29 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-12-31 Rural Development Advisor at and Livelihood Development Selection Implementation GDA - MAFF LASED/NCDDS/IC/08A/16 / Sub-component 1.2: Land Individual Consultant Pending National Communication & IDA / 58070 Preparation and Infrastructure Post Open 118,588.24 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Selection Implementation Strategy Advisor at NCDDS Development LASED/NCDDS/IC/26/16 / Sub-component 1.2: Land Individual Consultant Pending Provincial Infrastructure Engineer IDA / 58070 Preparation and Infrastructure Post Open 87,529.41 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 Selection Implementation at LASED Kratie Development LASED/NCDDS/IC/27/16 / Sub-component 1.2: Land Provincial Infrastructure Engineer Individual Consultant Pending IDA / 58070 Preparation and Infrastructure Post Open 87,529.41 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 for LASED Kg. Thom and Thbong Selection Implementation Development Khmum LASED/NCDDS/IC/28/16 / Sub-component 1.2: Land Provincial Infrastructure Engineer Individual Consultant Pending IDA / 58070 Preparation and Infrastructure Post Open 87,529.41 0.00 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2021-03-15 for LASED Kampong Speu and Selection Implementation Development Kampong Chhnang. LASED/NCDDS/IC/29/17 / Sub-Component 1.1: Social International Short-Term Individual Consultant Pending IDA / 58070 Land Concession Investment Post Open 100,000.00 0.00 2017-03-31 2017-05-19 2017-06-09 2017-07-14 2018-01-10 Consultant for Internal Review Selection Implementation Planning and Prioritization and Report (1month x 6times) LASED/NCDDS/IC/33/21 / Sub-Component 1.1: Social Individual Consultant Pending National Consultant for Preparing IDA / 58070 Land Concession Investment Post Open 65,000.00 0.00 2020-12-31 2021-02-18 2021-03-11 2021-04-15 2021-12-31 Selection Implementation Project Completion Report. Planning and Prioritization LASED/NCDDS/IC/37/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation Sambok, KRT LASED/NCDDS/IC/38/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation ChangKrang, KRT LASED/NCDDS/IC/39/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Da, and Livelihood Development Selection Implementation KRT LASED/NCDDS/IC/40/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Thmey, and Livelihood Development Selection Implementation KRT LASED/NCDDS/IC/41/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation Chambak, KRT LASED/NCDDS/IC/42/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation Choamkravien, TKM LASED/NCDDS/IC/43/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Tipo, and Livelihood Development Selection Implementation KPT LASED/NCDDS/IC/44/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Dong, and Livelihood Development Selection Implementation KPT LASED/NCDDS/IC/45/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Kraing and Livelihood Development Selection Implementation Lavea, KCH Page 11 LASED/NCDDS/IC/46/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation Chheanloeung, KCH LASED/NCDDS/IC/47/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for Peam, and Livelihood Development Selection Implementation KCH LASED/NCDDS/IC/48/17 / Community Development and Sub-component 1.3: Agriculture Individual Consultant Pending IDA / 58070 Post Open 48,000.00 0.00 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2021-12-31 Agriculture Facilitator for and Livelihood Development Selection Implementation Raksmeysamaki, Oral, KSP LASED/NCDDS/IC/09/16 / Sub-component 1.2: Land Procurement and Contract Individual Consultant IDA / 58070 Preparation and Infrastructure Prior Open 104,470.59 0.00 Canceled 2016-08-22 2016-09-02 2016-10-10 2016-10-31 2016-12-05 2021-07-31 Management Assistant at Selection Development NCDDS LASED/NCDDS/IC/02/16 / Sub-component 1.2: Land National Procurement and Individual Consultant IDA / 58070 Preparation and Infrastructure Prior Open 158,117.65 0.00 Canceled 2016-08-22 2016-09-01 2016-10-10 2016-10-31 2016-12-05 2020-07-31 Contract Management Advisor at Selection Development NCDDS LASED/NCDDS/IC/03/16 / Sub-component 1.2: Land Individual Consultant Project Finance Consultant at IDA / 58070 Preparation and Infrastructure Prior Open 148,235.29 0.00 Canceled 2016-09-01 2016-09-16 2016-10-20 2016-11-10 2016-12-15 2021-08-31 Selection NCDDS Development LASED-NCDDS-IC-02A-16 / Sub-component 1.2: Land Senior National Procurement and Individual Consultant IDA / 58070 Preparation and Infrastructure Post Open 158,117.65 158,258.00 Signed 2016-08-31 2016-09-02 2016-10-19 2017-07-12 2016-11-09 2017-07-25 2016-12-14 2017-07-27 2020-12-13 Contract Management Advisor at Selection Development NCDDS LASED-NCDDS-IC-03A-16 / Sub-component 1.2: Land Senior National Project Financial Individual Consultant IDA / 58070 Preparation and Infrastructure Post Open 176,470.59 70,400.00 Signed 2016-09-11 2016-09-16 2016-12-07 2016-12-28 2017-02-01 2017-05-25 2021-12-31 Management Consultant at Selection Development NCDDS, GSSLC and GDA LASED-NCDDS-IC-09A-16 / Sub-component 1.2: Land Procurement and Contract Individual Consultant IDA / 58070 Preparation and Infrastructure Post Open 104,470.59 66,375.00 Signed 2016-09-01 2016-09-01 2016-10-20 2017-01-18 2016-11-10 2016-12-15 2017-02-06 2021-12-31 Management Assistant at Selection Development NCDDS LASED/NCDDS/IC/36A/17 / One Consultant for Develop and Component 2: Project Individual Consultant Pending Upgrade of Management IDA / 58070 Post Open 86,000.00 0.00 2017-08-28 2017-10-16 2017-11-06 2017-12-11 2019-02-04 Management Selection Implementation Information System (MIS) for District LASED/NCDDS/IC/49/17 / IT Component 2: Project Individual Consultant Pending IDA / 58070 Post Open 90,352.94 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2021-12-31 Adviser Management Selection Implementation LASED/NCDDS/IC/36/17 / One Consultant for Develop and Component 2: Project Individual Consultant Upgrade of Management IDA / 58070 Post Open 40,000.00 0.00 Canceled 2017-05-31 2017-07-19 2017-08-09 2017-09-13 2019-05-13 Management Selection Information System (MIS) for District LASED/NCDDS/IC/50/17 / One Sub-Component 1.1: Social Individual Consultant Under Consultant for Annual Progress IDA / 58070 Land Concession Investment Post Open 23,760.00 0.00 2017-11-01 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2021-12-31 Selection Implementation Survey Planning and Prioritization Page 12