PROCUREMENT PLAN Project information: Iraq - Social Fund for Development, P163108 Project Implementation agency: Ministry of Planning Date of the Procurement Plan: January 9, 2019 Period covered by this Procurement Plan: 2018-2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT Iraq : Iraq Social Fund for Development PLAN General Information Country: Iraq Bank’s Approval Date of the Original Procurement Plan: 2019-07-22 2019-07-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163108 GPN Date: Project Name: Iraq Social Fund for Development Loan / Credit No: IBRD / 88270 Executing Agency(ies): Ministry of planning-Poverty Reduction Strategy WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SAL.01-2 / Construction water network in AL- Kanogah village, rehabilitation irrigation project in AL-Owainat Pending Single Stage - One village, construction water IBRD / 88270 Post Request for Bids Open - National 0.00 Implementati 2019-07-28 2019-07-31 2019-08-25 2019-09-15 2019-10-07 2020-04-04 Envelope drainge station and 1.5 Km on conveyor tube, and rehabilitation drinking water station in Azeez Balad village SAL.01-4 / ConstructionHCU in four villages ( AL-Arab AL- Pending Single Stage - One Kabeer, and AL- IBRD / 88270 Post Request for Bids Open - National 0.00 Implementati 2019-07-28 2019-07-31 2019-08-27 2019-09-16 2019-10-10 2020-06-06 Envelope Khuzaify,Jowaizat and Azeez on Balad), and Construction school (6 class) in Khanogah SAL.01-5 / Construction Pending Request for Single Stage - One school (6 class) in Albu IBRD / 88270 Post Limited 0.00 Implementati 2019-07-24 2019-09-15 2020-05-12 Quotations Envelope Tumaa village on SAL.01-6 / Construction Pending Request for Single Stage - One school (6 class) in Albu IBRD / 88270 Post Limited 0.00 Implementati 2019-07-24 2019-09-15 2020-05-12 Quotations Envelope Dalaf village on SAL.01-3 / Paving main streets 2 Km in 4 villages (AL-Ahbab & Albu Sharan,AL-Owainat,AL-Arab Pending Single Stage - One AL-Kabeer), construction IBRD / 88270 Post Request for Bids Open - National 0.00 Implementati 2019-07-28 2019-07-31 2019-08-21 2019-09-09 2019-10-03 2020-05-30 Envelope arch and paving street 2 on Km in AL-Juwaizat village, and paving street 2.4 Km in AL-Kuzaify village GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 SAL.01-1 / supply and installation generator 750 kV, trasformer 600 kV in Pending Albu Sharan irrigation Single Stage - One IBRD / 88270 Post Request for Bids Open - National 0.00 Implementati 2019-07-28 2019-07-31 2019-08-19 2019-09-08 2019-10-01 2020-03-29 station, and rehabilitation Envelope on electricity network in three villages (Albu Tumaa, Albu Dalaf, AL-Ahbaab) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant NGO/SAL/01 / NGO for Pending IBRD / 88270 Post Qualification Open - National 0.00 2018-05-02 2018-05-23 2018-07-06 2018-08-05 2018-09-09 2019-03-08 Salah Deen Implementation Selection Consultant NGO/MUT/01 / NGO for Pending IBRD / 88270 Post Qualification Open - National 0.00 2018-05-02 2018-05-23 2018-07-06 2018-08-05 2018-09-09 2019-03-08 Muthana Implementation Selection PMT/CS/02 / External Least Cost Open - Pending IBRD / 88270 Post 0.00 2019-04-15 2019-05-06 2019-06-19 2019-07-17 2019-08-16 2019-09-20 2019-10-25 2020-10-24 auditor Selection International Implementation INDIVIDUAL CONSULTANTS Page 2