MUNICIPAL GOVERNANCE AND SERVICES PROJECT Implementation Support Mission: April 23- May 4, 2017 Aide Memoire 1. A World Bank mission1 reviewed the implementation of the Municipal Governance and Services Project (MGSP) during April 23-May 4, 2017. The mission would like to express its appreciation for the cooperation and support received from of the Government of Bangladesh (GoB), including the Secretary and officials of Local Government Division (LGD) as well as officials of the Local Government Engineering Department (LGED) and the Bangladesh Municipal Development Fund (BMDF). The mission is also grateful for the warm reception from mayors, officials and staff of Urban Local Bodies (ULBs) during the field visits. This Aide Memoire presents the key findings of the mission and agreements reached at the wrap up meeting on May 4, 2017 chaired by Mr. Abdul Malek, Secretary, LGD, Ministry of Local Government, Rural Development and Cooperatives. As agreed at the meeting, this Aide Memoire will be classified as a public document under the World Bank’s Access to Information Policy. Key Project Data Board Approval January 14, 2014 Original Ln./Cr. Amount $410M Effectiveness Date April 6, 2014 Revised Ln./Cr. Amount Not applicable Original Closing Date June 30, 2020 Amount Disbursed $85M (21% of IDA) Revised Closing Date Not applicable Summary Ratings Last Now MTR Date June 30, 2017 PDO MU MS IP MU MS Project Overview 2. Achievement of PDO. The project is now making progress towards achieving the PDO targets. Under the improved service delivery objective, as of May 1, 2017 about 654,000 people are estimated to have benefited directly from completed Year 1 and Year 2 sub-projects. The number of beneficiaries is expected to increase substantially in the following two years, as the implementing agencies (IAs) and the ULBs are now pursuing larger infrastructure sub-projects. In terms of improved municipal governance, the February 2017 baseline survey indicated that 21 of the 26 ULBs are likely to meet most of the key performance targets for the first Performance Assessment that will be carried out in July 2017 (also see Section 4.5). The BMDF loan repayment ratio stands at 84 percent, which already represents achievement of the Year 4 target. Annex 1 presents the updated Results Framework. 1 The mission comprised: Christopher T. Pablo (Sr. Urban Specialist and Task Team Leader); Kwabena Amankwah- Ayeh (Sr. Urban Specialist); Balakrishna Menon (Lead Urban Specialist); Reaz Chowdhury (Financial Management Specialist); A.N.M. Mustafizur Rahman (Procurement Specialist); Iqbal Ahmed (Environmental Safeguards Specialist); Md. Akhtar Zaman (Social Development and Safeguards Specialist); M. Akram-ul Aziz (Local Government Specialist); Evangeline Kim Cuenco (Sr. Institutional Development Specialist); Marilyn Tolosa- Martinez (Projects Specialist); Hope Gerochi (M&E Specialist); Santanu Lahiri (Sr. Municipal Engineer), Md. Shehab Uddin (Municipal Engineer); Huraera Jabeen (Urban Specialist), Ishita Alam (Project Analyst); Ahmed-bin Parvez (Project Analyst); Farmin Ahsan Khan (Project Analyst); Shahzeen Hafiz (Project Analyst); Anika Chowdhury (Team Assistant); and Rex Joseph Quiah (Team Assistant). Michelle Chen (Program Assistant) Washington DC. 1 3. Project Restructuring. The project is being restructured to introduce changes to the project design and align it with IA capacity, as well as to take account of implementation difficulties in the first two years. The proposed restructuring includes changes in the administration and utilization of capital (base and performance) grants: participating ULBs will be allowed to pool the annual base grants allocation of five years into a single capital investment program. The governance performance bonus grants will be added to the base grants to expand the capital investment budget envelope. These changes will ensure that ULBs propose and implement fewer, larger and only critical infrastructure investments, instead of pursuing a large number of micro investments (that characterized the earlier MGSP portfolio). The other major changes relate to: administration of the O&M component (largely clarifying the modus operandi in LGED and the participating ULBs); the introduction of project preparation support as an eligible project activity under BMDF; and creation of a dedicated project office in BMDF. 4. Government remains strongly committed to achieving the PDOs, and is closely monitoring execution by the IAs of these actions, including ensuring that critical inputs are procured by June 30, 2017. Implementation pace is being accelerated by LGED as it focuses on better supervision (enabled by hiring of additional PMU staff and consultants, who have improved the documentation of sub-project activities and intensified field monitoring). The quality of subprojects enrolled has also improved (81 bigger CIP sub-projects worth $58.4 million, compared to hundreds of micro investments in the first two years of implementation). LGED is committed to prepare another 74 sub-projects worth $77.7 million by December 31, 2017, and has started to augment DSM consultant complement as well as PMU staffing for the intensified sub-project preparation and appraisal. BMDF is recruiting more staff and has started to build a pipeline of larger CIP sub-projects from six city corporations and four municipalities. It is and processing funding requests from these cities for sub-project preparation. Implementation Progress 5. Considerable progress has been made by both IAs in meeting the agreed critical actions. 5.1. Restructuring. The changes to be introduced in the project were agreed during the December 2016 mission. The changes include: (a) revision of the Results Framework; (b) inclusion of additional disbursement category for operation and maintenance (O&M) expenditures; (c) revision of disbursement estimates; (d) revision of a legal covenant, (i.e., change in proposed date for BMDF to submit a business plan for long-term sustainable operation from December 31, 2016 to December 31, 2017); (e) establishment of a project management unit (PMU) in BMDF to manage day-to-day operation of the MGSP; and (f) change in the definition of “sub-project” [i.e., new definition includes the outputs from the project preparation support (PPS) to be covering, but not limited to, feasibility studies, detailed engineering and other technical studies to facilitate the identification of more strategic and viable sub- project investments that will promote the development of ULBs]. The amendment to the financing agreement that has been countersigned by the Government reflects these changes to the project. 5.2. Changes to the Project Implementation Manuals (PIMs). The following changes will be reflected the in the PIMs: (a) adoption of the revised MGSP Results Framework; (b) updating of the social development and safeguards section to take into account the updated Social Management Framework (SMF); (c) adjustment in the administration of the base allocation, i.e., pooling the annual ULB allocations for the remaining implementation period and utilize the lump-sum amount to program the priority CIP sub-projects of 26 ULBs, instead of allocating it on an annual basis; (d) inclusion of the list of CIP sub-projects as a PIM Annex to ensure that the project only finances the priority infrastructure sub-projects identified through the CIP process; (e) enhancement of sub-project implementation procedures under LGED; (f) adjustment in the administration of performance-based allocation (i.e., revision and refinement in the pre-identified 10 performance indicators, adjustment in the performance 2 rating scale, phasing of performance assessment activities, addition of rehabilitation and maintenance of ULB assets as an eligible activity that can be financed by performance-based grants); (g) provision for separate accounting and reporting for O&M expenses; (h) inclusion of the O&M Quality Assurance Control Manual; (i) provision of PPS to allow qualified BMDF- ULBs to procure consulting services to prepare specific project preparation studies; (j) increase in the maximum amount of BMDF financing by type of ULB; (k) enhancement of sub-project implementation procedures under BMDF; (l) rationalization of training activities and clarification of roles of various training providers; (m) dropping of several technical assistance studies (that are either no longer relevant or will be funded by other projects); (n) focusing of capacity- building support to the LGED and BMDF supported ULBs; (o) augmenting resources for project management; and (p) reallocation of costs across activities under Component 3 without any change in overall costs. The revised PIMs are expected to be finalized and made effective by June 30, 2017. 5.3. Updating of the SMF. LGED and BMDF have updated the SMF to: (a) take into account the potential adverse social impacts of CIP sub-projects and to identify additional mitigation strategies, where necessary; and (b) include management of other social risks associated with contract management, including gender mainstreaming, citizen engagement and labor influx. 5.4. Project re-orientation workshops. In March 2017 the Bank conducted project orientation workshops for LGED-PMU, Design Supervision and Management (DSM) consultants, BMDF-PMU, and PIUs from eight ULBs to: (a) clarify the sub-project implementation process; (b) define the roles and responsibilities of the PMUs, ULBs, and implementation support consultants; (c) further explain Bank fiduciary and safeguards policies and procedures; and (d) prepare the PMU to conduct similar project orientation activities in the remaining 18 ULBs. LGED and BMDF will start the roll out of the orientation course by June 1, 2017. 5.5. Procurement of critical consultants under LGED. Most of the critical consultants had mobilized by April 15, 2017. PMU staff augmentation has begun with the recruitment of additional appraisal staff. Good progress has been achieved by the Municipal Support Unit (MSU), DSM consultants, O&M consultant and the Performance Assessment consultants. 5.6. Base allocation. LGED is now implementing 81 sub-projects at a contract value of $58.4 million: 68 sub-projects are on-going ($45.6 million), 13 sub-projects are under tender ($12.8 million), and 74 sub-projects ($77.7 million) are under preparation. LGED has committed to complete sub-project preparation and tender documents by December 2017 for 74 sub-projects (see Annex 2). 5.7. Performance- based allocation. The 26 ULBs will be able to meet most of the seven indicators for the first Performance Assessment. The CIP and O&M training for 26 ULBs have been completed, and the CIP and O&M plans are being prepared. Asset registries for three ULBs are complete; the rest are underway. However, a majority of the ULBs have not yet settled their power and phone bills, and have been accordingly reminded to do so. The results of the baseline survey also indicate skill gaps and areas where training providers (MSU, DSM and Governance Improvement and Capacity Building or GICB) should focus their efforts to enable ULBs to meet the requirements for the first and second performance assessments. (See Annex 2-2). 5.8. O&M allocation. Substantial progress has been made in addressing the quality of O&M planning. The O&M plans are expected to be completed by May 31, 2017. 5.9. BMDF demand-based financing. BMDF has a fully staffed PMU that has started to: (a) carry out due diligence on ongoing sub-projects that were previously not properly supervised; (b) process requests by major clients (e.g., Dhaka and Khulna); and (c) develop a pipeline of larger sub-projects from six city corporations and four municipalities. The CIP exercise in Chittagong generated a number of potentially 3 transformative investments that BMDF can support. BMDF also plans to conduct CIP in four ULBs. It is estimated that most of the proposed sub-projects would commence in January 2018. The Dhaka South City Corporation (DSCC) and BMDF are about to sign an agreement for $1.8 million to support the detailed design and engineering and tender documents of identified city priorities such as pilot urbanscape activities and “smart city” interventions. The BMDF will recruit a new supervision consultant (and will terminate the contract of the current supervision consultant) and will permit the ULBs (rather than supervision consultants) to certify payments to contractors. 5.10. Capacity- building. Substantial progress has been achieved as all training providers have been recruited. The MSU and DSM consultants have completed most of the governance-related training activities for the 26 ULBs. The DSM staff needs to be augmented to ensure that the project cycle training is carried out without further delay. The mission urged LGED to assess the REAP work plan carefully and take appropriate measures to ensure quality outputs of the GICB consultants. 5.11. M&E. The M&E system is now fully operational at LGED. With the new PMU in place in BMDF, the system will be expanded to cover project activities under BMDF. Key Issues 6. The following remaining actions have been initiated and will be completed by June 30, 2017. 6.1. Mandatory project cycle training. LGED will ensure that: (a) the DSM has sufficient staff to prepare and conduct project cycle training; (b) the PIUs have sufficient staff to carry out project activities; and (c) the PIU reorientation workshops will be rolled out to the to the remaining 18 ULBs. 6.2. Third party monitoring (TPM). LGD will complete the procurement expeditiously so that the selected TPM firm can initiate the work by July 1, 2017. 6.3. Operational audit. LGED will complete the review of the proposals so that the consultant can commence work on June 15, 2017. 6.4. Safeguards compliance review. LGED and BMDF will submit separate reports to the Bank by June 30, 2017 (for review and no objection) on: (a) environmental safeguards compliance; and (b) social development and safeguards compliance. 7. LGED sub-project development and staffing inputs. To ensure the timely preparation and full compliance of all 74 identified sub-projects with project rules and standards, LGED will augment DSM staff by end June 2017. LGED will furnish the overdue work plan for sub-project implementation to the Bank as soon as possible. 8. LGED-PMU appraisal capacity. As the 74 sub-projects in the pipeline need to be prepared by December 2017, the PMU would urgently augment its staffing. As a result of the field visit in Patiya, the mission also urged the LGED- PMU to ensure that all sub-project proposals suggest a complete project (i.e., two-storey building proposal with only two-storey foundations) and should meet the financial and economic viability requirements of the project (see Annex 2, Section 2.5). 9. Mid-term review (MTR). Critical inputs from the project M&E system, the operational audit, TPM, and the performance assessment will be in place by December 2017. The MTR, originally planned for June 2017, will be rescheduled to January – March 2018. 4 Fiduciary Compliance 10. Procurement. LGED should develop a realistic procurement plan and ensure there is ample capacity to carry out procurement for the 74 additional sub-projects. The M&E Wing of LGD, which is managing the TPM component, has indicated that it will need support from LGED in completing the procurement. BMDF is still to submit a report on the progress of its procurement risk mitigation action plan. 11. Financial management. Most of the FM actions agreed during the December 2016 mission are still to be completed. LGED has not yet started the hiring process for the junior consultant at LGED, for which the agreed deadline for completion was February 2017. BMDF has not made any progress in upgrading the accounting software; the agreed deadline was January 2017. The interim unaudited financial reports of both agencies were submitted on time and are acceptable to the Bank. LGED has taken appropriate measures to spend and account for O&M expenses in accordance with the restructured financing percentage. 12. External audit reports of both LGED and BMDF for the financial year 2015-2016 were submitted to the Bank on time. The auditors have expressed an unqualified audit opinion in both the cases; however, there were 14 audit observations in the case of LGED and 15 on BMDF. The Bank has asked LGED and BMDF to take appropriate actions on the material audit observations by May 31, 2017. Safeguards Compliance 13. Environmental Safeguards. Both LGED and BMDF have recruited separate environmental safeguards specialists in their PMUs to review and ensure environmental safeguards compliance. With assistance from the DSM consultant, LGED has completed the environmental screening and assessment reports of all 83 on-going sub-projects (41 in Year 1 and 42 in Year 2). The quality of the environmental screening and assessment reports has gradually improved in terms of capturing the critical environment risks associated with each sub-project. There has also been some improvement in the implementation of environmental management plans (EMPs). 14. BMDF needs to share with the Bank the environmental screening results and the Environmental Assessment (EA) reports of the on-going 38 sub-projects. It was agreed that: (a) LGED will submit the environmental compliance report covering the December 2016 to April 2017 period by June 30, 2017; (b) BMDF will share all EA reports by June 30, 2017; (c) BMDF will share the overall environmental compliance report by June 30, 2017; and (d) LGED and BMDF will submit the training plan on environmental management to the Bank by May 31, 2017 and subsequently roll out the safeguards training by June 15, 2017. 15. Social development and safeguards. ULB capacity in the management of social development and safeguards compliance has improved. However, some ULBs lack the necessary skills to adopt the SMF in the sub-project cycle and require additional training on social development and safeguards. LGED reported that the social safeguards compliance review of all completed and on-going subprojects is underway and agreed to submit the report to the Bank by June 30, 2017. LGED and BMDF will develop a social development and safeguards training program and will submit it for Bank review by May 15, 2017. LGED and BMDF will share the social screening reports and social management plans for sub-projects with involuntary resettlement issues, voluntary donation of land, and/or other acts involving land acquisition by June 30, 2017. M&E 5 16. Since the last mission, there has been significant progress to create an M&E system for the project. This includes finalization of the various M&E monitoring and reporting templates and the geographical mapping of LGED sub-projects (with related embedded information) using Google Earth. BMDF sub-projects will be added once BMDF’s M&E system is finalized on June 15, 2017. LGED will consolidate project-level information, particularly those related to the MGSP results framework. LGED will also take the lead in developing the semi-annual and MTR report required for submission to the World Bank. The M&E specialists of the IAs should agree on a working arrangement to ensure consistent and seamless reporting of project-level information. LGED will mount an M&E training for all ULBs as soon as possible. Key Agreed Actions 17. Table 1 below lists the key actions agreed at the end of the mission. The full list of agreed actions during this mission and the status of agreed actions during the last mission are in Annex 3. Table 1: Key Agreed Actions Agreed Actions Responsible Unit Agreed Date 1. Complete project restructuring LGED and BMDF May 31, 2017 (delayed, expected before June 30, 2017) 2. Submit revised PIMs for Bank concurrence LGED and BMDF May 31, 2017 (completed) 3. Complete actions to augment DSM subproject LGED and DSM June 30, 2017 preparation staffing 4. Complete preparation of 74 subprojects LGED December 31, 2017 5. Submit Work and Financial Plan LGED and BMDF BMDF (completed) LGED (May 15, 2017) 6. Augment PMU appraisal consultant support LGED June 15, 2017 7. Conduct first performance assessment LGED July 1, 2017 8. Recruit additional staff to prepare and conduct LGED and DSM June 15, 2017 mandatory project cycle training 9. Ensure PIUs have sufficient staff to carry out project LGED and BMDF June 1, 2017 activities 10. Initiate project cycle training LGED June 1, 2017 11. Complete procurement of TPM consultant LGD June 15, 2017 12. Commence work by Operational Audit consultant LGED June 15, 2017 13. Complete signing of Sub-credit Agreement between BMDF May 15, 2017 BMDF and DSCC 14. Complete social and environmental safeguards LGED & BMDF June 30, 2017 compliance review of completed and on-going sub projects and submit the report to the Bank for review 15. Complete appropriate actions on audit observations LGED and BMDF May 31, 2017 16. Establish functional M&E system BMDF June 15, 2017 Next Mission 18. The next mission is scheduled for August 2017. 6 Annex 1 Results Framework A. Update on Original Results Framework Project Outcome Indicators Unit of Baseline Cumulative Target Actual Remarks Measure Values Achievement Y4 EOP (5/1/2017) PDO Indicators 1. Number of people in urban areas provided with Number (in 0 1,243 3,430 654 Achieved 52.6% of the Year 4 target improved basic services thousands) Of which female Percentage 0 45 45 46% 2. Percentage of ULBs (among 26 ULBs) demonstrating Percentage 0 - 80 - The baseline survey conducted in improvement in the annual performance assessment February 2017 indicated that 21 of the 26 ULBs are likely to meet most of the key performance targets for the first Performance Assessment that will be carried in July 2017. 3. Contingent emergency appropriation Number n/a n/a n/a n/a Not triggered. Intermediate Indicators 1. Percentage of participating ULBs with arrangements Number 0 40 100 - Twenty six (26) ULBs have been for O&M established trained on O&M plan preparation. The PIUs of LGED ULBs are expect to complete their O&M plans by May 2017. This indicator is proposed to be dropped and replaced as it needs to be clarified what O&M “arrangements” would need to be established. This will be confirmed in the restructuring paper. 2. Loan repayment ratio Percentage 80 84 90 84 Achieved. This indicator is proposed to be revised to state that this specific to BMDF ULBs and reflected as a PDO Indicator as it captures improvement in ULB creditworthiness and fiduciary governance, and BMDF institutional sustainability (measures of improved governance). This will be confirmed in the restructuring paper. 7 3. Number of ULBs with with improved financial and Number 0 59 100 - Twenty six ULBs have already investment planning conducted CIP workshops, and have prepared the CIP document. LGED- PMU is currently reviewing the CIPs. This indicator reflects two performance improvement areas. To make it more specific and targeted, the indicator is proposed to be dropped and replaced by indicators that relate to the two aspects (financial areas and investment planning). This will be confirmed in the restructuring paper. 4. Percentage of participating ULBs with a municipal Percentage 0 40 100 - No data. This indicator is proposed to tax collection rate of 80% of invoiced tax bills be dropped and replaced with the preparation, adoption and disclosure of ULB Revenue Enhancement Action Plan (REAP). The plan will include actions to improve municipal taxation. This will be confirmed in the restructuring paper. 5. BMDF incremental operating costs covered by own Percentage 25 40 100 - No data yet. OSCB study is ongoing. source revenue 6. Number of ULB staff trained including community Number (in 0 100 144 2.492 Targets will be reduced by 89% (i.e., people trained by LGED and BMDF (thousands) thousands) the end-of-project will be set to 16,000) as training for Ward Level Coordination Committee (WLCC) members and district level officials of LGED will no longer be pursued from Years 4 to 7. Only ULB staff will be trained for the succeeding years. This will be confirmed in the restructuring paper. 2 As of end-March 2017. To be updated. 8 B. Update on Proposed Results Framework Project Outcome Indicators Unit of Baseline Cumulative Target Actual Remarks Measure Values Achievement Y4 EOP (5/1/2017) PDO Indicators PDO 1a: Improve municipal governance 4. Number of ULBs achieving an aggregate rating of at Number 0 At least 26 - The baseline survey conducted in least 60 percent in the project's performance 13 ULBs February 2017 indicated that 21 of the assessment on municipal planning, social 26 ULBs are likely to meet most of the accountability, public financial management and key performance targets for the first public revenues Performance Assessment that will be carried in July 2017. 5. Loan repayment ratio from ULBs borrowing from Percentage 80 84 90 84 Achieved. BMDF PDO 1b: Improve basic services 6. Direct project beneficiaries Number (in 0 1,243 3,430 654 Achieved 52.6% of the Year 4 target thousands) Of which female Percentage 0 45 45 46% 7. Beneficiaries satisfied with basic services under the Percentage 0 - 80 - Procurement of consultant to carry out project TPM activities is ongoing. Female beneficiaries satisfied with basic services Percentage 0 - 80 - Same as above. under the project PDO 2: Improve the recipient’s capacity to respond promptly to an eligible crisis or emergency 8. Number of people benefitting from local Number n/a n/a n/a n/a Not triggered. infrastructure that are rehabilitated or reconstructed as a result of a crisis or calamity. Intermediate Indicators Intermediate Indicators related to municipal planning 7. Number of ULBs with approved CIPs Number 0 At least 26 - All 26 ULBs have already conducted 13 ULBs CIP workshops, and have prepared the CIP document. LGED-PMU is currently reviewing the CIPs. 8. Number of ULBs with approved O&M plans Number 0 At least 26 - All 26 ULBs have been trained on 13 ULBs O&M plan preparation. The rest of the PIUs expect to complete their O&M plans by May 2017. 9 Intermediate indicators related to social accountability 9. Number of GRC formed and functional Number 0 At least 26 - All GRCs have undergone capacity- 13 strengthening through the MSU. Intermediate indicators related to public FM and public revenues 10. Number of ULBs with revenue enhancement action Number 0 13 78 - plans or REAP Intermediate indicator related to BMDF 11. BMDF incremental operating costs covered by own Percentage 25 40 100 - No data yet. OSCB study is ongoing. source revenue Intermediate indicator related to improvement of basic services 12. Length of roads constructed/ rehabilitated under the Kilometers 0 TBD 640 267 LGED and BMDF will take on larger project projects in their current pipeline. It is expected that progress towards the achievement of the target will pick-up in the remaining implementation years. Targets will be revisited at mid-term. 13. Length of drainage constructed/ rehabilitated under Kilometers 0 TBD 300 70 See above. the project 14. Number of revenue- generating facilities constructed/ Number 0 TBD 70 10 See above. rehabilitated under the project 15. Other local facilities constructed/ rehabilitated under Number 0 TBD 45 4 See above. the project Intermediate indicator for capacity building to improve governance and implementation of subprojects 16. Number of ULB staff trained including community Number (in 0 12 16 2.493 On track. Training preparations are people trained by LGED and BMDF (thousands) thousands) underway, particularly on the subproject cycle. 3 As of end-March 2017. To be updated. 10 Annex 2 Technical Notes Component 1: Municipal Governance and Basic Urban Services Improvement 1. Base allocation. LGED is now implementing 81 subprojects worth $ 58.42 million: 68 subprojects are ongoing ($45.6 million), 13 subprojects are under tender ($12.8 million), and 74 subprojects worth $ 77.7 million are under preparation. Since the mission in December 2016, LGED has contracted additional 13 subprojects worth 12.8 million. The mission noted that no additional ongoing subprojects were completed since December 2016. As of December 2016 As of April 2017 Number Total Amount Number Total Amount BDT lac $ million BDT lac $ million Part 1. Year 1& 2 Subprojects 1. Completed 167 11,974.8 15.2 119* 12,146.3 15.4 2. Ongoing construction 68 6,153.4 7.8 40* 5,981.9 7.6 Sub-total 235 18,128.2 23 159 18,128.2 23.0 Part 2. Years 3-6 (CIP) Subprojects 3. Ongoing construction 23 1,995.9 25.3 28 28,023.5 35.5 4. Under tender process 10 1,287.4 16.3 13 10,143.6 12.8 5. Firm pipeline 80 32,864 41.6 74 61,383 77.7 Sub-total 113 36,147.3 83.1 116 99,550.1 126.0 6. Soft pipeline 141 7,819.9 9.9 24 19,530 24.7 Sub-total 141 17,640.9 22.3 24 19,530 24.7 Notes: Year 1 & 2 subprojects refer to the micro-subprojects or schemes. These are largely roads and drains. The average length of a road subproject is one (1) kilometer. The average length of a drain subproject is 0.7 kilometer. Most of the subprojects can be considered as maintenance work. *Number of completed and on-going subprojects in April 2017 differ from December 2016 as a result of rectifying the understanding of PMU on “subprojects”, schemes, and “subproject packages”. Schemes/ packages were consolidated to form a subproject (not otherwise). 1.1. Year 1 and 2 subprojects. Seven (7) road and drain subprojects prepared in Years 1 and 2 have encountered delays in completion. These are as follows: 11 Name of the Subproject Package Length Contract Contracted Contracted ULB Type Number amount ($ Start Date end date million) Bhairab Road & Drain W02 3360 m 0.4 7 April 2015 20 June 2016 Bhaluka Road & Drain W01 5380 m 0.6 5 May 2015 16 July 2016 Chakoria Road W01 6600 m 0.63 12 April 2015 14 April 2016 Chandina Road & Drain W01 5378 m 0.36 2 Feb 2016 30 Nov 2016 Chowddagram Road & Drain W01 6279 m 0.55 15 Dec 2015 16 Dec 2016 Madhabpur Road & Drain W01 3540 m 0.45 22 Feb 2015 5 May 2016 Sylhet Road & Drain W01 3856 1.11 10 Nov 2015 3 Nov 2016 1.2. Pipeline of CIP subprojects. LGED has identified 74 additional subprojects (worth $77.7 million) for preparation until December 2017. Among those, almost 21 subprojects involve building design, which requires additional preparation time compared to that for roads and drain subproject. The mission notes that the average time required for subproject preparation to commence construction for roads and drain subproject requires approximately six months. Further, LGED has yet to complete preparation of only one building subproject (a community center) among 189 subprojects completed and committed during the three of project implementation. The mission notes the building design mostly mixed-use function in nature will require significant inputs. 1.3. Need to augment DSM preparation and PMU appraisal capacities. Considering the sheer number of subprojects to complete preparation by December 31, 2017, the mission strongly recommends augmenting the DSM subproject preparation capacity, particularly for building design. It was agreed that the DSM consultant would need to increase staffing by June 15, 2017. Likewise, given that 74 large and complex subprojects will be prepared in next eight (8) months, PMU would need to appraise an average of 10 subprojects per month, mission again raises the need to further beef up PMU capacity to carry out appropriate quality appraisal work. The mission also stresses the need to increase staffing for social and environmental safeguards. To allow to better program activities in the next eight (8) months, it was agreed that LGED will submit its work and financial plan covering the period May- December 2017 by May 15, 2015. 1.4. Social and environmental safeguards compliance review. LGED-PMU reported that they have completed safeguards compliance review all subprojects, a concern that was highlighted during December 2016 mission. It was agreed that LGED will submit the report by June 15, 2017. 1.5. Field visit in Patiya. The mission visited Patiya, one of the 26 ULBs receiving funding from LGED. The municipality is currently implementing drainage improvement in the main street that also forms part of the highway connecting Chittagong with Cox’s Bazar. The ULB has few more subprojects in the pipeline including kitchen market, community center and drainage improvements. The mission observed poor workmanship and over designed drain subproject. There were insufficient storm drains. It was agreed that the PIU engineer will work closely with the DSM consultant and the contractor for rectification measures. Moreover, the mission noted that the PIU is inadequately staffed (i.e., no environmental and social safeguards, and M&E focal points). The mission urged the LGED to ensure that all 26 ULBs are sufficiently staffed prior to the roll out of the project cycle training. The mission also noted that management of temporary impacts resulting from the drain construction should be incorporated in the SMP. The mission also visited the site for the proposed kitchen market. The ULB is proposing to build a two storey kitchen market with a foundation of five stories. The mayor informed that the municipal council agreed to propose such arrangements with the intention to build additional floors with their own resources right after completion of the first two stories with MGSP funding. The mission, however, expressed that such proposal may not be economically viable; and that it may not be wise use of resources considering that the ULB has other priority infrastructure proposals. The mission advised the ULB to revise the proposal to suggest a complete project, i.e., two-storey building proposal with only 12 two-storey foundations. LGED- PMU will review the design and economic appraisal of this subproject and ensure that this meets the financial/economic viability requirements of the project. 2. Performance- based allocation. The performance assessment consultants conducted the baseline survey of the 26 ULBs from February 12-April 11, 2017. The summary findings are attached in Annex 2- 1. The results indicate existing skills gaps and areas where training providers [MSU, DSM and Governance Improvement and Capacity- building GICB) consultants] should target their training activities in order to assist the ULBs to meet the requirements under the first and second Performance Assessments. Accordingly, the mission organized a joint meeting with the Performance Assessment consultants and training providers (MSU, DSM and GICB) to discuss the implications of the survey results for the respective programs. 2.1. First Performance Assessment (July 2017). Based on the results of the baseline survey, it appears that the 26 ULBs will able to meet most, of the seven (7) indicators for the first Performance Assessment. These indicators pertain to the following; CIP, O&M plan, asset registry, social accountability (TLCC, CDCC and GRC), settlement of bills and inclusive budgeting. Most of the training activities under the social accountability category has been delivered by the MSU. The O&M training for 26 ULBs has been completed by the DSM and the O&M Plans are currently being prepared. Asset registries for three ULBs are completed. The rest are underway. However, majority of the ULBs have not yet settled their power and phone bills. Follow up is needed to remind them to settle their accounts ahead of the assessment. In addition, training on participatory budgeting by GICB has not yet started; the training module has still to be developed. The schedule for conducting the performance assessment was moved from April- May 2017 to July 2017 to allow ULBs to complete remaining requirements (e.g., O&M plan preparation). 2.2. Second Performance Assessment (April –June 2018). The 26 ULBs will be assessed using the seven (7) indicators under the first performance assessment and three more indicators pertaining to public financial management and public revenues [i.e., computerization of the municipal accounting system, property assessment and the Revenue Enhancement Action Plan (REAP)]. The baseline survey indicated the weakest area was the lack of ULB capacity to prepare the REAP. Training on the computerization of the accounting system is almost complete (MSU). However, development of a training program on property assessment and the REAP (GICB) has not yet started. Without the REAP, ULBs will not be able to meet the requirements under the second Performance Assessment. The Bank is preparing detailed comments on the GICB inception report. During the meeting, the lead performance assessment consultants shared the survey questionnaire for the first and second Performance Assessments with the training providers so they can take these into account in their programming of the training activities. A follow up (virtual) meeting between the performance assessment consultants and training providers (MSU, DSM and GICB) will be organized on July 9, 2017 (Sunday) to discuss the results of the assessment and their implications for the programming of the training activities. 3. O&M allocation. The LGED PMU informed that the total amount spent from the O&M IDA funds has been $ 7.95 million, will be documented as 100 percent IDA expenditure. According to the LGED PMU, the ULBs are already informed about the revised percentages of IDA and ULB contribution from FY 17 until the end of the project. In terms of O&M planning, positive steps have been taken by the DSM- O&M consultant and the LGED-PMU to address the quality of O&M planning and preparing for the first performance assessment. Training on O&M were provided by LGED to 26 ULBs in five (5) batches from March 19- April 5, 2017, focusing on establishing asset registry system and preparing rolling O&M plans. LGED PMU expects to receive all rolling O&M plans from 26 ULBs in phases by May 31, 2017. The task team suggested that the ULBs need to prepare the O&M plans before the first performance assessment in order to receive the first tranche of the performance grants. It was agreed that all O&M plans will be completed by May 31, 2017. The LGED PMU will review all O&M plans to decide on eligibility to advance the O&M funds for FY18. The DSM O&M consultant will also assist the 13 ULBs in preparing work plans for implementation in accordance with the O&M plans, including preparation of pipeline for rehabilitation work utilizing performance grants. 4. BMDF demand- based financing. 4.1. PMU work plan. The newly formed BMDF-PMU has been very proactive in developing a work plan for the period from June 2017- June 2018, and the mission expressed its appreciation to the strong commitment of the PMU members. The work plan will cover the implementation of ongoing Years 1 and 2 subprojects as well as planning for BMDF pipeline of subprojects. There are 78 ongoing subprojects and of them 64 are expected to be completed by June 30, 2017 while 12 are expected to be completed by October 31, 2017. The PMU is expecting to prepare completion and monitoring report of Years 1 and 2 subprojects by December 31, 2017. 4.2. Update on Years 1 and 2 subprojects. Out of the 78 ongoing subprojects, PMU identified 14 to be missing social appraisal reports, 15 to be missing environmental appraisal reports and 6 to be missing technical appraisal reports, which they are planning to complete by May 31, 2017. Furthermore, implementation of two subprojects in Taherpur and Khagrachori have been discontinued due to outstanding land issues. An individual is making a claim on part of the project site. The M&S consultants were assigned to prepare social, environmental and technical appraisal reports. But since they failed to complete these reports, the PMU instead be will be completing those reports. It was agreed with BMDF that earlier the payment to the M&S consultant for those assignments will be deducted from future payments to the M&S consultant. Also, PMU (Social and M&E specialists) will follow up on the status of the land dispute and explore possibilities of advising the ULBs on options for negotiation. Also BMDF needs to remind the mayors of the two ULBs that if the works continue without resolution of land dispute, they will be responsible for the payments for those works. In addition, it was agreed that BMDF will immediately inform the M&S consultants of the termination of their contract by the end of June 2017 because of poor performance. BMDF will procure individual consultants to supervise the remaining 14 subprojects (12 and the 2 with land dispute) before a new Construction Supervision Consultant firm is hired. 4.3. BMDF pipeline. Both Dhaka South City Corporation (DSCC) and Dhaka North City Corporation (DNCC) applied for Project Preparation Support (PPS) from BMDF. The BMDF-PMU completed financial and technical appraisal of DSCC’s application to determine their creditworthiness as well as the viability of the proposed subprojects. BMDF have informed DSCC about their approved credit line and advised to progress with the necessary actions to sign Sub-credit agreement for PPS. BMDF also gave clearance to DSCC for the TOR of hiring design consultant for Urbanscape Improvement subproject, accordingly DSCC has requested for technical and financial proposal from the consultant. BMDF is waiting for some additional document from DNCC to progress with the appraisal and signing Sub-credit Agreement for PPS. 4.4. The PMU is planning to extend the PPS to other city corporations, i.e., Chittagong City Corporation (CCC) and Khulna City Corporation (KCC) and Rajshahi City Corporation (RCC). BMDF conducted a successful CIP preparation workshop for CCC during the mission which recommended a number of good subprojects the city can propose for investments. BMDF is planning to conduct the same for RCC by May 31, 2017. KCC has applied for PPS to prepare for subprojects from the CIP they conducted earlier, BMDF will appraise their application to target preparation of subproject proposal by end of November 2017. However, completion of procurement and implementation of those subprojects is expected to continue also after December 31, 2017. 4.5. The PMU has identified 38 subprojects from 27 ULBs that already signed Sub- credit Agreement with BMDF, but whose investments were suspended. Of the 27, four (4) ULBs have completed CIP while 14 BMDF is planning to organize CIP workshop for ULBs whose proposed subprojects are larger in scale and revenue generating. These ULBs will need to prepare their REAP before processing their subprojects. 4.6. Subproject prototypes. It was agreed that BMDF-PMU will work towards preparing prototype design options for subprojects commonly proposed by ULBs, such as kitchen markets, slaughter houses and bus terminals. This will allow BMDF to shorten project preparation time, and incorporate better standards for planning and design. The architect of the PMU will take a lead in developing the prototype design options and guidelines. 4.7. PMU support (logistics, office, administrative staffing, etc.). BMDF prepared a disbursement projection from April to June 2017 including disbursement to ULBs and their operating costs. The ongoing and and planned disbursement to the ULBs is expected to account for $21.2 million, while $23.8 million is budgeted for project management, logistics and equipment costs. The renovation of the BMDF office is now being pursued and works are expected by July 1, 2017. 5. Component 3: Capacity Building and Project Implementation Support 5.1. MSU consultant. The MSU reported that training on the computerization of the municipal accounting system and community mobilization (for the TLCCs and GRCs) for the 26 ULBs are almost complete. The latter is one of the indicators under the first Assessment which starts on July 1, 2017. Orientation for newly elected mayors and councilors is underway. MSU indicated that the length of training can vary between 1-5 days depending on the field of training. The mission noted that the 5-day class room-type training for mayors may not be ideal nor productive. The consultants were therefore urged to consider shortening the duration of training for mayors, and for LGED to explore arranging study visits for mayors to neighboring countries. Annex 2-2 provides details on the training activities of the MSU. The mission urged the consultants to consult BMDF when they expand the training courses to BMDF ULBs. It was noted that the project has provision for funding a number of consultant services to support project implementation for both LGED and BMDF. 5.2. GICB consultant. Under the revised capacity building arrangements, GICB consultants are responsible for providing training on the preparation of revenue enhancement action plan (REAP), municipal budget and property assessment. A group of individual consultants has been hired to develop modules and deliver training to 26 LGED ULBs and 52 BMDF ULBs. The consultants submitted an inception report and presented their work plan to the mission. The mission noted with concern that the consultants could not fully appreciate the requirements of a REAP and, as a result, the methodology put forward lacked the vision and processes required for preparation of a REAP. The mission recommended that LGED should assess the work plan carefully and take appropriate measures to remedy the short comings. 5.3. DSM consultant. The DSM consultant, in addition to providing project supervision support, is responsible for providing capacity building training to the ULBs for preparation of CIP and O&M Plan for all 26 ULBs. The CIP and O&M Plans are required to access the PBG grants. In addition, they will also develop the training material for the project cycle module which will be delivered with assistance from the MSU. To-date, all 26 ULBs have submitted CIPs to the LGED for review. Additionally, the DSM consultant has completed O&M training for all 26 ULBs. The ULBs will now prepare their O&M plan as per the O&M Planning Manual. The DSM consultant is also translating the Manual into Bengali which will be distributed to the ULBs as a reference source. The DSM consultant is also assisting ULBs in the preparation of their infrastructure asset registry, of which three have been completed to-date. The DSM consultant submitted copies of the O&M training module to the Bank. It was noted that, as agreed during the December 2016 mission, the training materials developed to-date included both a participant profile which will be incorporated in the general participant database and a course evaluation form. 15 5.4. As previously agreed, MSU has set up a participant database using the participant profile format provided by the Bank. The mission requested the MSU to share a hard copy of the populated database so far developed by May 31, 2017. All other training providers are also asked to follow the same format so that they can be easily incorporated into this common participant database. The MSU will be responsible for managing and maintaining this database. (a) The mission has asked the training providers to submit a hard and soft copy of all final (and cleared) training modules. The MSU will serve as a repository of these training materials. (b) As previously agreed, all training activities will include a course evaluation at the end of each event using the guidelines provided by the Bank. The Bank requested the MSU and the DSM consultant to provide a report on the evaluation results from the training activities conducted by end-May 2017. (c) The mission urged the DSM consultant to start the project cycle training as soon as all 26 ULBs have completed their infrastructure asset registries, as required in the first Performance Assessment. 5.5. GIS-based Urban Property and Infrastructure Assets Management Systems (GIS-PAMS) consultant: The objective of this consultancy is to develop and deploy a GIS-based Property and Infrastructure Asset Management System (GIS-PIAMS) to improve local revenue mobilization and more effectively optimize the performance of infrastructure assets from a technical and economic point of view. The GIS-PIAMS will be piloted in two (2) of the pre-identified 26 ULBs under MGSP. LGED has submitted a draft contract for hiring a firm for the job to the Bank. 5.6. Operational Audit consultant: This assignment aims to independently and systematically review and evaluate the processes, procedures and preliminary results of Municipal Governance and Basic urban services as well as BMDF Demand-based Financing for basic Urban services components of the project to improve implementation efficiency and effectiveness, and ensure the economy and sustainability of project outcomes. The mission noted that LGED has received RFPs from the short-listed consultant on April 10, 2017. The mission recommends that LGED should expeditiously complete review of the proposals so that the consultant may be on board by June 15, 2017. 5.7. TPM consultant: The objective of the TPM is to basically enable LGED and BMDF to identify and manage project social accountability risks to improve implementation performance, and therefore project effectiveness. The M&E Wing of the Local Government Division, independent from the two implementing agencies, is responsible for implementing this activity. The RFP has now been issued to short-listed firms. The mission recommends that all processes should be completed expeditiously so that the selected firm can be on board by July 1, 2017. 5.8. Operation Support and Capacity Building (OSCB) consultant: The objective of this consultancy, is to develop a detailed business plan that would focus on the potential market for BMDF financing; and financial projections of BMDF over the next 5 years; and an action plan to implement the business. The firm engaged for the job submitted the draft final report to BMDF on April 30, 2017, the last date of its contract. BMDF informed the mission that the firm requested an extension of its contract up to June 30, 2017 to finalize the report. The mission responded by saying that the Bank will review the report carefully and share the results of the Bank evaluation. BMDF could consider the Bank comments in its review of the consultant request for extension. 6. Social Safeguards. ULB capacity in management of social development and safeguards compliance in subproject cycle have improved. They are now largely able to provide necessary information and carry out social screening in preparation of subprojects. Social screening reports have been included in most of the subproject proposals; but few of the subproject proposals are missing this report. The ULBs are preparing social screening reports for all new subprojects. However, some of the 16 ULBs are lacking the necessary skills and orientation for adopting the SMF in subproject cycle. Grievance redress mechanism (GRM) has been established through formation of Grievance redress committees (GRC) at ULB level. A GRM website has been developed and demonstrated before the mission. The mission advised the consultant to open the website to the community and other external stakeholders for producing their complaints and suggestions and also review statuses of those. Mission reiterated its position on the Taherpur and Khagrachari ULBs of no Bank finance in disputed lands. LGED and BMDF will review social safeguards compliance issues of all completed and ongoing subprojects and produce the Social Safeguards Compliance Report to the Bank for review and no objection. The report will identify any lapse and pending issue with actions planned for mitigation and management following the project SMF. The SMF will however, be updated within June 2017 to accommodate the approach and requirements commensurate to the restructure of the project. The Social Specialists with LGED and BMDF will be visiting the sites regularly. LGED and BMDF agreed with the mission on the following:  Complete social safeguards compliance review of all completed and ongoing subprojects and produce the report to the Bank for review and no objection by June 30, 2017;  The Social Specialists of LGED and BMDF will develop SMF training program for the ULBs and share with the Bank for review and no objection by May 31, 2017;  The LGED and BMDF will share the social screening reports and social management plans for subprojects with issues of involuntary resettlement, voluntary donation of land and other acts of using additional land for any subproject along with the subproject appraisal reports. 7. The project SMF will be updated commensurate to the requirements of the restructured project and shared with the Bank by June 15, 2017. 8. M&E. Since the last mission, there has been significant progress in putting in place an M&E system for the project. Progress includes finalizing the various M&E monitoring and report templates and the geographical mapping of LGED subprojects (with related information imbedded) using google earth. It is expected that the BMDF subprojects will be added as soon as BMDF’s M&E system is finalized by June 15, 2017. It was agreed that LGED will consolidate project-level information particularly those related to the MGSP results framework. LGED will also take the lead in developing the semi-annual and medium term report that are required to be submitted to the World Bank. The mission recommended that the M&E specialists of the implementing agencies agree on a working arrangement that will ensure consistent and seamless reporting of project-level information. 9. The revised MGSP Results Framework (RF) has been agreed on by both implementing agencies as part of the restructuring of the project. The project’s RF was revised to specifically refine existing indicators to better capture the contribution of the project on improving municipal governance, and access and quality of basic services. Both LGED and BMDF have started to populate their respective RF indicators. Annex 1-2 of this Aide Memoire presents the revised RF reflecting progress on the indicators as of May 22, 2017. 10. LGED. Significant progress has been made by LGED in terms of developing an M&E manual which will be used to train the M&E focal persons of PIUs and the DSM to facilitate data collection and monitoring on the ground. According to the LGED M&E team organogram which was finalized last mission, the PIU M&E focal point will work on obtaining data and information with the help of DSM consultants to work closely in populating the relevant M&E templates. They will report directly to the Sub Assistant Engineers. The Sub- assistant Engineer will then collect and review the information gathered in the form of various reports and inform directly to the M&E Specialist at the PMU as well as the Senior Assistant Engineers. A revised draft of M&E Manual has been submitted to the Bank for final review and is expected to form part of the LGED PIM. The M&E training is expected to be delivered by June 30, 2017. 17 11. BMDF. A new PMU has recently been mobilized, and thus, it may require some time to put in place a reliable M&E system. The new BMDF M&E specialist is currently working on finalizing the M&E workflow and arrangement for data management and reporting system. With 52 ULBs on its Years 1 and 2 portfolio, the BMDF PMU would need to think through how the M&E activities can be managed after the contract of its M&S consultants ends in June 2017. The mission requested the PMU to propose an organogram reflecting the current M&E arrangement (with implementation support consultants) and the arrangement after June 2017. A draft organogram and workflow has been submitted to the WB for review. BMDF is expected to prepare and submit the M&E manual, which will form part of the BMDF- PIM by May 31, 2017. 18 Annex 2-1 Brief Presentation of Baseline Assessment Results See separate pdf file. 19 Annex 2-2 Updated List of Trainings Conducted by MSU ULBs under LGED ULBs under BMDF Completed till March 28, 2017 Completed till March 28, 2017 Target number of ULBs Target number of ULBs Target Completion date Target Completion date Training themes and types Remaining Remaining Municipal Support Unit (MSU) Theme: Participation and social accountability 1 TLCC formation and March 31, 2017 26 22 4 March 11, 50 50 0 operation 2017 2 GRC formation and March 31, 2017 26 24 2 April 1, 2017 50 46 4 operation 3 Orientation for elected officials a. For Mayors May 31, 2017 22 0 22 May 31, 2017 50 0 50 b. For Councilors June 30, 2018 22 0 22 June 30, 2019 50 0 50 Theme: Computerized financial management system 4 Installation and operation of Holding Tax Billing software a. New March 31, 2017 5 5 0 May 13, 2017 13 7 6 b. Refresher March 31, 2017 21 21 0 May 20, 2017 37 20 17 5 Installation and operation of Municipal Accounting System a. New March 31, 2017 5 5 0 April 15, 2017 13 7 6 b. Refresher March 31, 2017 21 21 0 May 20, 2017 37 15 22 6 Installation and operation of Municipal Trade License Management software a. New March 31, 2017 5 5 0 May 27, 2017 13 0 13 b. Refresher March 31, 2017 21 21 0 May 20, 2017 37 15 22 7 Installation and operation of Water billing software a. New March 31, 2017 4 4 0 May 6, 2017 2 0 2 b. Refresher March 31, 2017 8 8 0 May 20, 2017 25 10 15 20 Annex 3 Agreed Actions A. Agreed Actions for May 2017 Mission Agreed Action Responsible Agreed Date Status Unit 1. Complete project restructuring a. Send concurrence on BMDF December 31, Delayed, new deadline: restructuring proposal to 2016 (completed) June 30, 2017. LGED b. Send to ERD agreed WB February 15, restructuring proposal for 2017 GoB clearance c. Send restructuring ERD February 21, request to WB 2017 d. Process GoB WB March 15, 2017 restructuring request e. Submit revised Project LGED/BMDF March 31, 2017 Completed on May 31, Implementation Manual 2017. 2. Complete procurement of remaining critical consultancy services a. Sub-project appraisal LGED January 31, 2017 Completed. Additional (social & environmental appraisal specialists safeguards specialists) needed considering number of sub-projects to be prepared by December 2017. b. Training coordinator LGED February 28, Completed. 2017 c. BMDF- PMU specialists BMDF January 31, 2017 Completed. d. Operational Audit LGED February 28, Delayed: new deadline 2017 June 15, 2017 e. Third Party Monitoring LGD February 28, Delayed: new deadline 2017 3. Workshop to reorient PMUs, LGED, February 28, PMUs (completed) MGSP consultants and BMDF and 2017 LGED ULBs (8 are participating ULBs on WB completed; roll out to 18 enhanced project specialists ULBs will start by June implementation procedures 1, 2017) 4. Complete governance- LGED March 15, 2017 related training prior to first performance assessment a. CIP LGED- DSM March 31, 2017 Completed b. O&M LGED- DSM March 31, 2017 Completed 21 c. TLCC strengthening LGED- MSU March 31, 2017 Completed d. Grievance Redress LGED- MSU March 31, 2017 Completed Committee Strengthening e. Inclusive budgeting LGED- MSU March 31, 2017 Delayed. GICB consultant mobilized just recently. 5. Initiate mandatory project LGED- DSM March 31, 2017 Delayed. New date to cycle training initiate training is June 1, 2017. 6. Conduct operational audit LGED- March 31, 2017 Delayed. Procurement of BMDF consultant will be completed by June 30, 2017. 7. Conduct Third Party LGD March 31, 2017 Delayed. Procurement of Monitoring activities consultant will be completed by June 30, 2017. 8. Complete BMDF Roadmap BMDF May 31, 2017 Delayed. Conduct of study Study ongoing. 9. Carry out safeguards LGED March 31, 2017 Delayed. Conduct of compliance review of activities ongoing. completed and ongoing sub- projects and devise corrective measures to comply with the revised SMF in a manner satisfactory to the Bank B.Status Agreed Actions During the 2017 Mission Agreed Action Responsible Agreed Date Status Unit 10. Complete project restructuring f. Send concurrence on BMDF December 31, Delayed, new deadline: restructuring proposal to 2016 (completed) May 31, 2017. LGED g. Send to ERD agreed WB February 15, restructuring proposal for 2017 GoB clearance h. Send restructuring ERD February 21, request to WB 2017 i. Process GoB WB March 15, 2017 restructuring request j. Submit revised Project LGED/BMDF March 31, 2017 Delayed, new deadline: Implementation Manual May 31, 2017. 11. Complete procurement of remaining critical consultancy services 22 f. Subproject appraisal LGED January 31, 2017 Completed. Additional (social & environmental appraisal specialists safeguards specialists) needed considering number of subprojects to be prepared by December 2017. g. Training coordinator LGED February 28, Completed. 2017 h. BMDF- PMU specialists BMDF January 31, 2017 Completed. i. Operational Audit LGED February 28, Delayed: new deadline 2017 June 15, 2017 j. Third Party Monitoring LGD February 28, Delayed: new deadline 2017 12. Workshop to reorient PMUs, LGED, February 28, MGSP consultants and BMDF and 2017 participating ULBs on WB enhanced project specialists implementation procedures 13. Complete governance- LGED March 15, 2017 related training prior to first performance assessment f. CIP LGED- DSM March 31, 2017 g. O&M LGED- DSM March 31, 2017 h. TLCC strengthening LGED- MSU March 31, 2017 i. Grievance Redress LGED- MSU March 31, 2017 Committee Strengthening j. Inclusive budgeting LGED- MSU March 31, 2017 14. Initiate mandatory project LGED- DSM March 31, 2017 cycle training 15. Conduct operational audit LGED- March 31, 2017 BMDF 16. Conduct Third Party LGD March 31, 2017 Monitoring activities 17. Complete BMDF Roadmap BMDF May 31, 2017 Study 18. Carry out safeguards LGED March 31, 2017 compliance review of completed and ongoing subprojects and devise corrective measures to comply with the revised SMF in a manner satisfactory to the Bank 23 Annex 4 List of Persons Met Sl. Name Designation No. Local Government Division 1 Mr. Abdul Malek Secretary 2 Mr. A S M Mahbubul Alam Director General (M&E Wing) 3 Mr. Mahbub Hossain Additional Secretary (Urban) 4 Mr. Liakat Ali Joint Chief (Planning) 5 Mr. Mashud Ahmed Joint Secretary (M&E Wing) 6 Mr. Mohammad Zahirul Islam Sr. Assistant Secretary, (M&E Wing) Local Government Engineering Department 1 Mr. Shyma Prasad Adhikari Chief Engineer 2 Mr. Iftekhar Ahmed Additional Chief Engineer 3 Mr. Shfiqul Islam Director, MSU 4 Mr.Shaikh Muzakka Zaher Project Director, MGSP 5 Mr. Md. Monjur Ali Deputy Project Director, MGSP 6 Mr. A SM M Kabir Deputy Project Director, MGSP 7 Mr. Md. Firoz Alam Talukder Sr. Asst. Engineer, PMU, MGSP 8 Ms. Sonia Nowrin Sr. Asst. Engineer, PMU, MGSP 9 Mr. Md. Abdul Gaffar Team Leader, MSU, MGSP 10 Mr. Syed Abu Yusuf Financial Specialist, MGSP 11 Mr. Md. Abul Kalam Azad Deputy Team Leader, DSM, MGSP 12 Mr. Md. Wahadur Rahman SA Engineer, MGSP 13 Mr. Md. Abdur Razzaq Accounts Officer, MGSP 14 Mr. Qazi Anwarul Haq PMU, MGSP 15 Mr. Mohammed Tapan Sarker Sociologist, PMU, MGSP 16 Mr. Swapan Kumar Saha Public Finance Consultant, MGSP 17 Mr. Md. Sarowar Hossain Khan Community Development Specialist, MGSP 18 Mr. Abdus Samad Training Coordinator, GICB, MGSP 19 Mr. Sajjad Ahmed Khan Sr. Municipal Finance Specialist, GICB, MGSP 20 Mr. Francisco Cordeiro Team Leader, DSM, MGSP 21 Mr. Ahmed Nawaz Deputy Team Leader, DSM, MGSP 22 Mr. Gholam Zakaria M&E Specialist, MGSP 23 Ms. Hasina Akhtaer Architect, DSM, MGSP 24 Mr. Nazmul Haque Structural Engineer, DSM, MGSP 25 Mr. Noorul Amin Talukder O&M Specialist, DSM, MGSP 26 Mr. Md. Mustafizur Rahman Traffic Management Specialist, DSM, MGSP 27 Mr. Nazmul Haque Architect, DSM, MGS 8 Mr. A.B.M. Nazrul Islam Municipal Design Engineer. , HIFAB, MGSP 29 Mr. Md. Mahbubur Rahman Environment Specialist, DSM, MGSP 30 Dr. M. Moniruzzaman Social Management Specialist, DSM, MGSP 31 Mr. Md. Monzurul Islam Pavement Design Engineer, DSM , MGSP 32 Mr.A.F.M. Gholam Sharfuddin Water Supply & Sanitation Engr., DSM, MGSP 33 Mr.Mohammed Amin Forhad Computer Specialist, DSM, MGSP 34 Mr.Emdadul Haque Social Safeguard Specialist, DSM, MGSP 35 Mr. Ranajit Kumar Paul Sr. Municipal Engineer. DSM, MGSP 24 36 Dr. Akter Mahmud Urban Planner, Performance Assessment Team Bangladesh Municipal Development Fund 1 Mr. Syed Hasinur Rahman Managing Director 2 Dr. A. K.M Kamruzzaman Project Manager, MGSP 3 Mr. Md. Lokman Hossain Social Safeguard Specialists, PMU, MGSP 4 Mr. Abdul Ghani Environment Specialist, PMU, MGSP 5 Mr. G. M. Mohsin Financial Specialist, PMU, MGSP 6 Mr. Mustafizur Rahman Procurement Specialist, PMU, MGSP 7 Mr. Md. Ashrafuzzaman Civil Engineer, PMU, MGSP 8 Mr. Md. Abdur Rakib Khan Urban Development Specialist, MGSP 9 Mr. Mustassim Khan Architect, PMU, MGSP 10 Ms. Sheila Ahmed Economist, MGSP, BMDF 11 Mr. Amar Krishna Baidya M&E Specialist, PMU, MGSP Chittagong City Corporation 1 Mr. A J M Nasiruddin Mayor 2 Mr. Mohammad Shamsuddoha Chief Executive Officer 3 Mr. Rafiqul Islam Manik Superintending Engineer 4 Mr. Abu Saleh Superintending Engineer 5 Mr. Anwar Hossain Superintending Engineer 6 Mr. Abul Hossain Secretary Patiya Pourashava 1 Prof. Md. Harunur Rashid Mayor 2 Mr. Mohammad Mohsin Secretary 3 Mr. Mizanur Rahman Assistant Engineer 4 Mr. Mohammed Shahajahan Sub-Assistant Engineer 5 Mr. Rupak Kumar Sen Councilor 6 Mr. Khorshed Ghani Councilor 7 Mr. Sheikh Saiful Islam Councilor 8 Mr. Abu Sayed Councilor 9 Mr. Gofran Rana Councilor 10 Mr. M A Mannan Councilor 11 Ms. Ferdous Ara Begum Councilor 12 Ms. Yesmin Akhter Councilor 13 Mr. Abdul Mannan Councilor 25