Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: 2. Date of General Procurement Notice: June 06, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year July 8, 2016 to July 7, 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1.5 Million 2. NCB (Goods) N/A 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) N/A All 5. (Non-Consultant Services) Above US$ 1.5 Million 6 Individual Consultants for procurement All regardless of the and legal services contract amount 2. Prequalification: N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for GEQIP II Volume 1: Institutional Arrangements, Planning and Monitoring and Evaluation Volume 2: Financial Management Volume 3: Procurement Management Volume 4: School Grant Guidelines 5. Any Other Special Procurement Arrangements: No 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preferenc by Bank US$ e (Prior / million (yes/no) Post) Summary of No - - - There is no works the ICB component in this (Works) project Summary of 140.67 20 Yes Prior the ICB (Goods) Summary of No - - - There is no works the NCB component in this (Works) project Summary of 2.51 8 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 3.10 7 Prior number of contracts that 1.61 31 Post will be let under QCBS Summary of 0.26 6 Prior SSS and number of Selection of IC contracts that will be let 1.28 40 Post under other methods PROCUREMENT Ethiopia : Ethiopia General Education Quality Improvement Project II PLAN General Information Country: Ethiopia Banks Approval Date of the Original Procurement Plan: 2017-03-31 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-05-22 Project ID: P129828 GPN Date: Project Name: Ethiopia General Education Quality Improvement Project II Loan / Credit No: IDA / 53150 Executing Agency(ies): Ministry of Education WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-88/16 / Program Coordination, Procure locally available Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 99,000.00 0.00 2017-04-04 2017-05-30 2017-11-26 Montossori materials for O class Communication Quotations Envelope Implementation pilot program Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-06/13 / Program Coordination, Development, Printing and Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 16,365,299.00 0.00 2016-07-25 2016-07-30 2016-09-10 2016-10-10 2016-11-14 2017-05-13 Distribution of supplementary Communication Envelope Implementation materials for Grade 7-10 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-63/15 / Monitoring and Evaluation, and Single Stage - One Under Printing and Distribution of Grade IDA / 53150 Prior Request for Bids Open - International 5,300,947.00 0.00 2016-03-15 2016-03-20 2016-05-01 2016-05-31 2016-07-05 2017-01-01 Communication Envelope Implementation G1-8 Adapted Mother Tongue Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-61/14 / Program Coordination, Printing and Distribution of Grade Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 6,907,314.00 0.00 2016-03-30 2016-04-04 2016-05-16 2016-06-15 2016-07-20 2017-01-16 3-8 Amharic Textbooks and Communication Envelope Implementation Teachers Guide Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-86/16 / Program Coordination, Supply, Implementation and Monitoring and Evaluation, and Single Stage - One Pending Commissioning of 500 audio IDA / 53150 Prior Request for Bids Open - National 639,065.00 0.00 2017-04-10 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 Communication Envelope Implementation reader for 200 Secondary Management and Capacity Schools Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-95/16 / Program Coordination, Reprinting and Distribution of- Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 1,939,092.00 0.00 2017-04-20 2017-04-25 2017-06-06 2017-07-06 2017-08-10 2018-02-06 Grade 10 Civics and Ethical Communication Envelope Implementation Education Textbooks Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 1 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-106/16 / Program Coordination, Supply 480 tablets with Monitoring and Evaluation, and Single Stage - One Pending educational application (platform) IDA / 53150 Post Request for Bids Open - National 801,250.00 0.00 2017-04-27 2017-05-02 2017-06-13 2017-07-13 2017-08-17 2018-02-13 Communication Envelope Implementation to Six(6) secondary school of Management and Capacity two(2) emerging regions Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-108/16 / Program Coordination, Supply of Computers for Monitoring and Evaluation, and Single Stage - One Pending BOFEDs' and ZOFEDs' to IDA / 53150 Post Request for Bids Open - National 294,476.00 0.00 2017-04-03 2017-04-08 2017-05-20 2017-06-19 2017-07-24 2018-01-20 Communication Envelope Implementation implement the IBEX roll out for Management and Capacity GEQIP II Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-110/16 / Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 1,234,000.00 0.00 2017-05-01 2017-05-06 2017-06-17 2017-07-17 2017-08-21 2018-02-17 Procurement of vehicles for MOE Communication Envelope Implementation Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program MOE/GEQIP-2/SH/G-92/16 / School Improvement Plan Translation, Printing and Program Coordination, distribution of 0- class Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 88,140.00 0.00 2017-04-18 2017-06-13 2017-12-10 curriculum materials in 4 local Communication Quotations Envelope Implementation languages of Benishanguel Management and Capacity Gumuze region Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AFAR/GEQIP-2/NCB/G-1/09 / Program Coordination, Provision of student Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 137,200.00 0.00 2017-04-10 2017-04-15 2017-05-27 2017-06-26 2017-07-31 2018-01-27 desk,shelves,blackboards and Communication Envelope Implementation tables and chairs. Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AFAR/GEQIP-2/SH/G-1/09 / For Program Coordination, up-grading level one schools in Monitoring and Evaluation, and Request for Single Stage - One Pending afar Provision of science kits and IDA / 53150 Post Limited 27,000.00 0.00 2017-04-16 2017-06-11 2017-12-08 Communication Quotations Envelope Implementation educational materials for the Management and Capacity targeted 40 schools. Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AFAR/GEQIP-2/SH/G-2/09 / For Monitoring and Evaluation, and Request for Single Stage - One Pending up-grading level one schools in IDA / 53150 Post Limited 25,000.00 0.00 2017-04-13 2017-05-04 2017-10-31 Communication Quotations Envelope Implementation afar Provision of water tanks. Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and AFAR/GEQIP-2/SH/G-4/09 / Inspection Printing and distribution of Teacher Development Program Training material including School Improvement Plan syllabus,school based Program Coordination, management (SBM) Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 9,700.00 0.00 2017-04-18 2017-06-13 2017-12-10 guideline,school improvement Communication Quotations Envelope Implementation framework and guideline, reading Management and Capacity club guideline, Printing of written Building, including EMIS tests for primary school teachers Improving the Quality of Learning and school leaders. and Teaching through the use of Information and Communication Technology (ICT) Page 2 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AFAR/GEQIP-2/SH/G-3/09 / For Program Coordination, up-grading level one schools in Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 15,000.00 0.00 2017-04-17 2017-06-12 2017-12-09 afar Transport of the procured Communication Quotations Envelope Implementation items to beneficiary schools. Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program AFAR/GEQIP-2/SH/G-5/09 / For School Improvement Plan up-grading level one schools in Program Coordination, afar supply reference books and Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 21,200.00 0.00 2017-04-17 2017-06-12 2017-12-09 supplementary reading materials Communication Quotations Envelope Implementation to establish a reading center or Management and Capacity reading corner. Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AFAR/GEQIP-2/SH/G-6/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Procurment of various equipment IDA / 53150 Post Limited 3,500.00 0.00 2017-04-18 2017-06-13 2017-12-10 Communication Quotations Envelope Implementation for communications Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AFAR/GEQIP-2/SH/G-7/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of booklets, brochures IDA / 53150 Post Limited 3,900.00 0.00 2017-04-18 2017-06-13 2017-12-10 Communication Quotations Envelope Implementation and leaflets/fliers Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-142/16 / Program Coordination, Printing and Distribution of Monitoring and Evaluation, and Single Stage - One Under IDA / 53150 Prior Request for Bids Open - International 22,195,991.00 0.00 2017-05-08 2017-05-11 2017-05-13 2017-06-24 2017-07-24 2017-08-28 2018-02-24 English Textbooks and Teachers Communication Envelope Implementation Guide for Grade 1-8 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-141/16 / Program Coordination, Re-Printing and Distribution of Monitoring and Evaluation, and Under IDA / 53150 Prior Direct Selection Direct 3,966,326.00 0.00 2017-04-17 2017-04-22 2017-05-27 2017-11-23 Grade 9-12 TBs and TGs for 13 Communication Implementation Subjects Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-94/16 / Program Coordination, Purchase and supply of 5 Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 528,843.00 0.00 2017-04-13 2017-04-18 2017-05-30 2017-06-29 2017-08-03 2018-01-30 Computers for each 200 Communication Envelope Implementation secondary schools. Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-96/16 / Program Coordination, Developing, printing, and Monitoring and Evaluation, and Single Stage - One Under distributing G5-8, textbooks and IDA / 53150 Prior Request for Bids Open - International 4,362,959.00 0.00 2017-04-04 2017-05-09 2017-04-09 2017-05-16 2017-05-21 2017-06-20 2017-07-25 2018-01-21 Communication Envelope Implementation teachers guide for Oromiya Management and Capacity Region Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 3 Curriculum, Textbooks, Assessment, Examinations and Inspection MOE/GEQIP-2/NCB/G-70/15 / Teacher Development Program Printing and distribution of School Improvement Plan licensing guideline and Program Coordination, regulation documents, English Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 170,000.00 0.00 2017-04-12 2017-04-17 2017-05-29 2017-06-28 2017-08-02 2018-01-29 version teachers and educational Communication Envelope Implementation leaders generic standardes and Management and Capacity (Amharic) content and pedagogic Building, including EMIS standareds Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-15-1/13 / Program Coordination, Printing and Distribution of Grade Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 724,527.00 0.00 2017-04-28 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 1-8Arts, Visual Arts and Physical Communication Envelope Implementation Education Teachers Guide Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-24/13 R / Program Coordination, Supply, installation and Monitoring and Evaluation, and Single Stage - One Under commissioning of Educational IDA / 53150 Prior Request for Bids Open - International 20,255,856.00 0.00 2016-10-18 2016-10-23 2016-12-04 2017-01-03 2017-05-12 2017-02-07 2018-03-04 Communication Envelope Implementation Private Cloud Infrastructure and Management and Capacity services Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-02/13 / Program Coordination, Adaptation and Transcription of Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 5,230,800.00 0.00 2016-09-26 2016-10-01 2016-11-12 2016-12-12 2017-01-16 2017-07-15 Textbooks and Teachers Guide Communication Envelope Implementation in to Braille and Distribution Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-04/13 / Program Coordination, Development, Printing and Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 8,806,550.00 0.00 2015-11-18 2015-11-18 2015-11-18 2015-11-18 2015-12-09 2016-06-06 Distribution of Grade 1- 4 Mother Communication Envelope Implementation Tongue Supplementary materials Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program MOE/GEQIP-2/ICB/G-85/13 / School Improvement Plan Development, Printing, and Program Coordination, Distribution of Grade 1- 4 Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 5,486,262.00 0.00 2016-03-02 2016-03-07 2016-04-18 2016-05-18 2016-06-22 2016-12-19 Supplementary Materials Communication Envelope Implementation Environmental science and Management and Capacity Mathematics Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-60/14 / Program Coordination, Development, Printing and Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 125,000.00 0.00 2016-06-05 2016-06-10 2016-07-22 2016-08-21 2016-09-25 2017-03-24 Distribution of Grade 9-12 Communication Envelope Implementation Somaligna Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AAC/GEQIP-2/SH/G-1/09 / Program Coordination, Printing of written test for Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 12,364.00 0.00 2017-05-27 2017-07-22 2018-01-18 primary school teachers and Communication Quotations Envelope Implementation school leaders 3 times a year Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 4 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AAC/GEQIP-2/SH/G-4/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of 1. Magazines 2. IDA / 53150 Post Limited 7,273.00 0.00 2017-05-20 2017-07-15 2018-01-11 Communication Quotations Envelope Implementation Brochures 3. Booklets Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AAC/GEQIP-2/SH/G-5/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of leaflets/fliers and IDA / 53150 Post Limited 1,364.00 0.00 2017-05-23 2017-07-18 2018-01-14 Communication Quotations Envelope Implementation various sizes Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AAC/GEQIP-2/SH/G-6/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Procurment of various equipment IDA / 53150 Post Limited 7,924.00 0.00 2017-05-23 2017-07-18 2018-01-14 Communication Quotations Envelope Implementation for communications Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, BEN-G/GEQIP-2/SH/G-2/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Purchasing of training materials IDA / 53150 Post Limited 1,420.00 0.00 2017-05-21 2017-07-16 2018-01-12 Communication Quotations Envelope Implementation and equipments Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, BEN-G/GEQIP-2/SH/G-5/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of 1. Magazines 2. IDA / 53150 Post Limited 4,770.00 0.00 2017-05-29 2017-07-24 2018-01-20 Communication Quotations Envelope Implementation Booklets 3. Brochures Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, BEN-G/GEQIP-2/SH/G-7/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Procurment of various equipment IDA / 53150 Post Limited 3,670.00 0.00 2017-05-30 2017-07-25 2018-01-21 Communication Quotations Envelope Implementation for communications Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, DIRED/GEQIP-2/SH/G-3/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of 1. Magazine 2. IDA / 53150 Post Limited 4,780.00 0.00 2017-06-03 2017-07-29 2018-01-25 Communication Quotations Envelope Implementation Brochures and 3. Booklets Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, DIRED/GEQIP-2/SH/G-4/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of leaflets/fliers and IDA / 53150 Post Limited 680.00 0.00 2017-06-04 2017-07-30 2018-01-26 Communication Quotations Envelope Implementation various sizes Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 5 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, DIRED/GEQIP-2/SH/G-5/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Procurment of various equipment IDA / 53150 Post Limited 3,120.00 0.00 2017-06-05 2017-07-31 2018-01-27 Communication Quotations Envelope Implementation for communications Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, ASAITA/GEQIP-2/SH/G-1/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing entrance exam for the IDA / 53150 Post Limited 1,775.00 0.00 2017-06-04 2017-07-30 2018-01-26 Communication Quotations Envelope Implementation selection of new entrants Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-86/16 / Program Coordination, Supply, Implementation and Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Post Request for Bids Open - National 639,065.00 0.00 2017-05-18 2017-05-23 2017-07-04 2017-08-03 2017-09-07 2018-03-06 Commissioning of 500 audio Communication Envelope Implementation reader Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/NCB/G-80/15 / Program Coordination, Procurement of Computer, Monitoring and Evaluation, and Single Stage - One Pending printer, Laptop, Photocopy IDA / 53150 Post Request for Bids Open - National 623,100.00 0.00 2017-05-26 2017-05-31 2017-07-12 2017-08-11 2017-09-15 2018-03-14 Communication Envelope Implementation Machine and other Office Management and Capacity Equipment Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-114/16 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of newsletters on various IDA / 53150 Post Limited 25,400.00 0.00 2017-05-27 2017-07-22 2018-01-18 Communication Quotations Envelope Implementation general education topics Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-54/15 / Monitoring and Evaluation, and Request for Single Stage - One Pending Procurement of Offfice Supplies IDA / 53150 Post Limited 75,000.00 0.00 2017-02-19 2017-04-16 2017-10-13 Communication Quotations Envelope Implementation (Stationery Materials) Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-141-1/16 / Monitoring and Evaluation, and Under Reprinting and Distribution of IDA / 53150 Prior Direct Selection Direct 654,575.23 0.00 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Communication Implementation grade 9-12 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-141-2/16 / Monitoring and Evaluation, and Under Reprinting and Distribution of IDA / 53150 Prior Direct Selection Direct 1,304,413.18 0.00 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Communication Implementation Grade 9-12 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 6 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-141-3/16 / Monitoring and Evaluation, and Under Reprinting and Distribution of IDA / 53150 Prior Direct Selection Direct 1,475,346.06 0.00 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Communication Implementation Grade 9-12 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-141-4/16 / Monitoring and Evaluation, and Under Reprinting and Distribution of IDA / 53150 Prior Direct Selection Direct 97,187.55 0.00 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Communication Implementation Grade 9-12 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ICB/G-141-5/16 / Monitoring and Evaluation, and Under Reprinting and Distribution of IDA / 53150 Prior Direct Selection Direct 434,804.39 0.00 2017-05-15 2017-05-20 2017-06-24 2017-12-21 Communication Implementation Grade 9-12 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ICB/G-06/13 / Program Coordination, Development, Printing and Monitoring and Evaluation, and Single Stage - One Pending IDA / 53150 Prior Request for Bids Open - International 16,365,299.00 0.00 2016-07-25 2016-07-30 2016-09-10 2016-10-10 2016-11-14 2017-05-13 Distribution of supplementary Communication Envelope Implementation materials for Grade 7-10 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, BEN-G/GEQIP-2/SH/G-6/09 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of leaflets/fliers and IDA / 53150 Post Limited 690.00 0.00 2017-05-30 2017-07-25 2018-01-21 Communication Quotations Envelope Implementation various sizes Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-55/14 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing and distribution of IDA / 53150 Post Limited 8,600.00 0.00 2017-05-28 2017-07-23 2018-01-19 Communication Quotations Envelope Implementation Magazines, Brochures, Leaflets Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/NCB/G-112/16 / Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 30,000.00 0.00 2017-05-29 2017-07-24 2018-01-20 Printing of posters Communication Quotations Envelope Implementation Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-119/16 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of Promotional Year IDA / 53150 Post Limited 66,100.00 0.00 2017-05-30 2017-07-25 2018-01-21 Communication Quotations Envelope Implementation Planners Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 7 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-118/16 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of promotional items for IDA / 53150 Post Limited 22,730.00 0.00 2017-05-30 2017-07-25 2018-01-21 Communication Quotations Envelope Implementation the annual education conference Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/SH/G-122/16 / Program Coordination, Procurement of various Monitoring and Evaluation, and Request for Single Stage - One Pending IDA / 53150 Post Limited 46,760.00 0.00 2017-06-03 2017-07-29 2018-01-25 communications work related Communication Quotations Envelope Implementation hardware and software Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/NCB/G-111/16 / Monitoring and Evaluation, and Request for Single Stage - One Pending Printing of booklets and IDA / 53150 Post Limited 62,100.00 0.00 2017-06-07 2017-08-02 2018-01-29 Communication Quotations Envelope Implementation magazines Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, DIRED/GEQIP-2/SH/G-1/09 / TV Monitoring and Evaluation, and Pending spots/programs/adverts PSAs IDA / 53150 Post Direct Selection Direct 13,640.00 0.00 2017-05-22 2017-05-27 2017-07-01 2017-12-28 Communication Implementation Placement Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AAC/GEQIP-2/SH/G-2/09 / TV Monitoring and Evaluation, and Pending IDA / 53150 Post Direct Selection Direct 34,000.00 0.00 2017-05-17 2017-05-22 2017-06-26 2017-12-23 programs/spots Placement Communication Implementation Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AAC/GEQIP-2/SH/G-3/09 / Monitoring and Evaluation, and Pending Radio - Production and IDA / 53150 Post Direct Selection Direct 25,909.00 0.00 2017-05-18 2017-05-23 2017-06-27 2017-12-24 Communication Implementation Placement Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, BEN-G/GEQIP-2/SH/G-3/09 / Monitoring and Evaluation, and Pending TV spots/programs/adverts PSAs IDA / 53150 Post Direct Selection Direct 12,730.00 0.00 2017-05-22 2017-05-27 2017-07-01 2017-12-28 Communication Implementation Placement Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 8 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/SH/G-123/16 / Monitoring and Evaluation, and Pending TV Spots Placement/broadcast IDA / 53150 Post Direct Selection Direct 45,800.00 0.00 2017-05-24 2017-05-29 2017-07-03 2017-12-30 Communication Implementation for media-1 Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/QCBS/C-103/16 Program Coordination, / Procurement of consultancy Monitoring and Evaluation, and Quality And Cost- Pending Service for GEQIP-2 IDA / 53150 Prior Open - International 1,000,000.00 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-15 2017-07-15 2017-08-19 2017-09-23 2018-09-23 Communication Based Selection Implementation Comprehensive Evaluation (Mid Management and Capacity and Exit Evaluation) Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ QCBS /C- Program Coordination, 102/16 / Consultancy service to Monitoring and Evaluation, and Quality And Cost- Under develop an Ethiopian-relevant ICT IDA / 53150 Post Open - International 390,640.00 0.00 2017-03-28 2017-04-03 2017-04-18 2017-06-01 2017-06-29 2017-07-29 2017-09-02 2017-10-07 2018-10-07 Communication Based Selection Implementation competency framework for Management and Capacity teachers Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/QCBS/C-90/16 / Program Coordination, Consulting Firm for Adaptation Monitoring and Evaluation, and Quality And Cost- Pending and Translation of Grade 1-8 IDA / 53150 Post Open - National 100,000.00 0.00 2017-04-28 2017-05-19 2017-07-02 2017-07-30 2017-08-29 2017-10-03 2017-11-07 2018-11-07 Communication Based Selection Implementation Arts, Visual Arts and Physical Management and Capacity Education Teachers Guide Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program MOE/GEQIP-2/QCBS/C-89/16 / School Improvement Plan A consulting firm for assessing Program Coordination, the status of textbook student Monitoring and Evaluation, and Quality And Cost- IDA / 53150 Prior Open - International 264,422.00 0.00 Under Review 2017-04-25 2017-05-16 2017-06-29 2017-07-27 2017-08-26 2017-09-30 2017-11-04 2018-11-04 ratio by regions ,subject grade Communication Based Selection level and textbook utlization in Management and Capacity REBs Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/ CQS/C-111/16 / Consultant Monitoring and Evaluation, and Under Development of Inspection data IDA / 53150 Post Qualification Open - National 22,124.00 0.00 2017-04-19 2017-05-10 2017-06-23 2017-07-23 2017-08-27 2018-02-23 Communication Implementation utilization software Selection Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/ QCBS /C- Program Coordination, 102/16 / Consultancy service to Monitoring and Evaluation, and Quality And Cost- Pending IDA / 53150 Post Open - National 390,640.00 0.00 2017-05-24 2017-06-14 2017-07-28 2017-08-25 2017-09-24 2017-10-29 2017-12-03 2018-12-03 develop an Ethiopian-relevant ICT Communication Based Selection Implementation competency framework Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 9 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/QCBS/C-40/13 / Monitoring and Evaluation, and Quality And Cost- Pending GEQIP II Annual Independent IDA / 53150 Prior Open - International 205,128.00 0.00 2016-03-22 2016-04-12 2016-05-26 2016-06-23 2016-07-23 2016-08-27 2016-10-01 2017-10-01 Communication Based Selection Implementation Procurement Audit Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan BEN-G/GEQIP-2/QCBS/C-1/09 / Program Coordination, Consultant Selection of consulting firm for Monitoring and Evaluation, and Pending IDA / 53150 Post Qualification Open - National 300,000.00 0.00 2017-05-16 2017-06-06 2017-07-20 2017-08-19 2017-09-23 2018-03-22 the preparation of TV Communication Implementation Selection programs/spots production Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan DIRED/GEQIP-2/QCBS/C-1/09 / Program Coordination, Consultant Selection of consulting firm for Monitoring and Evaluation, and Pending IDA / 53150 Post Qualification Open - National 300,000.00 0.00 2017-05-15 2017-06-05 2017-07-19 2017-08-18 2017-09-22 2018-03-21 perparation of TV programs/spots Communication Implementation Selection production Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AAC/GEQIP-2/QCBS/C-1/09 / Program Coordination, Consultant Selection of consulting firm for Monitoring and Evaluation, and Pending IDA / 53150 Post Qualification Open - National 21,590.00 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-22 2017-09-26 2018-03-25 preparation of TV programs/spots Communication Implementation Selection production Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan BEN-G/GEQIP-2/SH/G-4/09 / Program Coordination, Consultant Radio - Production and Monitoring and Evaluation, and Pending IDA / 53150 Post Qualification Open - National 8,180.00 0.00 2017-05-22 2017-06-12 2017-07-26 2017-08-25 2017-09-29 2018-03-28 Placement of short Communication Implementation Selection messages/programs/spots Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/SH/G-126/16 / Program Coordination, Selection of consulting firm for Consultant Monitoring and Evaluation, and Pending preparation of TV Programs IDA / 53150 Post Qualification Open - National 286,900.00 0.00 2017-05-24 2017-06-14 2017-07-28 2017-08-27 2017-10-01 2018-03-30 Communication Implementation Production and Placement for Selection Management and Capacity media-1 Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, MOE/GEQIP-2/QCBS/C-86/16 / Monitoring and Evaluation, and Individual Consultant Pending Hiring Consultants for the IDA / 53150 Post Open 1,700.00 0.00 2017-03-23 2017-05-11 2017-06-01 2017-07-06 2018-01-02 Communication Selection Implementation Preparation of Technical Drawing Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 10 Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/SSS/C-97/16 / Program Coordination, Hiring a firm for development of Monitoring and Evaluation, and Under written tests for primary and IDA / 53150 Prior Direct Selection Direct 53,942.00 0.00 2017-03-15 2017-04-25 2017-03-25 2017-05-29 2017-11-25 Communication Implementation secondary school teachers and Management and Capacity school leaders Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AFAR/GEQIP-2/IC/C-1/09 / Program Coordination, Translation and adaptation about Monitoring and Evaluation, and Individual Consultant Pending IDA / 53150 Post Open 450.00 0.00 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 evidence based decision making Communication Selection Implementation and planning in to Afar language Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AFAR/GEQIP-2/IC/C-2/09 / Monitoring and Evaluation, and Individual Consultant Pending Translation of school based IDA / 53150 Post Open 710.00 0.00 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Communication Selection Implementation management (SBM) guideline Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan AFAR/GEQIP-2/IC/C-3/09 / Program Coordination, Translation of the revised school Monitoring and Evaluation, and Individual Consultant Pending improvement framework and IDA / 53150 Post Open 885.00 0.00 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Communication Selection Implementation guideline to meet the needs of Management and Capacity ABEs. Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan Program Coordination, AFAR/GEQIP-2/IC/C-4/09 / Monitoring and Evaluation, and Individual Consultant Pending Translation and adaptation of IDA / 53150 Post Open 177.00 0.00 2017-04-12 2017-05-31 2017-06-21 2017-07-26 2018-01-22 Communication Selection Implementation reading club guideline. Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/IC/C-67/15 / Program Coordination, Selction of consultant for Monitoring and Evaluation, and Individual Consultant Under IDA / 53150 Post Open 50,000.00 0.00 2017-04-13 2017-06-01 2017-06-22 2017-07-27 2018-01-23 developing 10 modules for PGDT Communication Selection Implementation program Management and Capacity Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/QCBS/C-95/16 / Program Coordination, Procurement of consulting firm Monitoring and Evaluation, and Individual Consultant Pending that undertake SIP IDA / 53150 Post Open 110,176.00 0.00 2017-04-17 2017-06-05 2017-06-26 2017-07-31 2018-01-27 Communication Selection Implementation implementation & school grant Management and Capacity utilization evaluation Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Curriculum, Textbooks, Assessment, Examinations and Inspection Teacher Development Program School Improvement Plan MOE/GEQIP-2/IC/C-51/15 / Program Coordination, Selecting Consultant for module Monitoring and Evaluation, and Individual Consultant Under development of 8 courses for IDA / 53150 Post Open 60,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 Communication Selection Implementation primary and secondary schools Management and Capacity supervisors training. Building, including EMIS Improving the Quality of Learning and Teaching through the use of Information and Communication Technology (ICT) Page 11