PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – ELECTRICITY ACCESS AND SERVICE EXPANSION (EASE) - P156208 Project Implementation agency: UCM Date of the Procurement Plan: January 2018 Period covered by this Procurement Plan: January 2018 – June 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Electricity Access & Services Expansion (EASE) PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 2020-07-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156208 GPN Date: Project Name: DRC Electricity Access & Services Expansion (EASE) Loan / Credit No: IDA / D1770, IDA / V0350, IDA / 60180 Executing Agency(ies): UNITE DE COORDINATION ET MANAGEMENT DES PROJETS DU MINISTERE WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-UCM-41701-CW-RFB / Network Upgrades and Travaux d'électrification de Access Expansion in Open - Single Stage - One IDA / D1770 A priori Appel d'offres 14,800,000.00 0.00 Annulé 2018-01-16 2018-04-17 2018-01-21 2018-04-26 2018-02-20 2015-12-22 2018-02-25 2018-03-07 2018-09-03 kimbanseke phase 2 (Lot Selected SNEL Service International Envelope 6B) Areas ZR-UCM-42629-CW-DIR / Network Upgrades and M03-Réhabilitation des Passation de Access Expansion in postes Liminga, Lingwala, IDA / D1770 A posteriori marché de gré à Direct 4,100,000.00 0.00 Annulé 2018-01-16 2018-03-30 2018-01-21 2018-02-25 2018-08-24 Selected SNEL Service Mitendi, autres travaux gré Areas dans les injecteurs ZR-UCM-42534-CW-RFB / Network Upgrades and Travaux de réhabilitation de Access Expansion in Open - Single Stage - One IDA / D1770 A priori Appel d'offres 10,700,000.00 0.00 Annulé 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-28 2022-05-12 la centrale de Mobayi- Selected SNEL Service International Envelope Mbongo Areas ZR-UCM-42665-CW-RFB / Network Upgrades and Electrification des poches Access Expansion in Open - Single Stage - One IDA / D1770 A priori Appel d'offres 5,910,000.00 0.00 Annulé 2018-01-30 2018-02-04 2018-03-06 2018-03-11 2018-04-06 2021-03-21 noires de Mpasa, Kinseso et Selected SNEL Service International Envelope Malweka (Lot 7) Areas ZR-UCM-42667-CW-RFB / Travaux de réhabilitation de Network Upgrades and la ligne de transport HT132 Access Expansion in Open - Single Stage - One kV ainsi que la IDA / D1770 A priori Appel d'offres 9,371,000.00 0.00 Annulé 2018-05-17 2018-05-22 2018-07-03 2018-08-02 2018-09-06 2021-08-21 Selected SNEL Service International Envelope réhabilitation et l'extension Areas des réseaux de distribution de Gbadolite Network Upgrades and ZR-UCM-42668-CW-RFB / Access Expansion in Single Stage - One En attente Travaux de réhabilitation du IDA / D1770 A posteriori Appel d'offres Open - National 100,000.00 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2018-09-08 Selected SNEL Service Envelope d'exécution centre d'appels de SNEL Areas ZR-UCM-66587-CW-DIR / Network Upgrades and Passation de Lot 6B - Extension du Access Expansion in 14,778,603.7 IDA / D1770 A priori marché de gré à Direct 14,800,000.00 Signé 2018-03-22 2018-10-11 2018-03-27 2019-05-02 2018-05-01 2018-04-23 2020-01-21 réseau 20/0,4Kv de Selected SNEL Service 2 gré Kimbanseke (Phase 2) Areas ZR-UCM-66603-CW-DIR / Network Upgrades and Lot 7 - Travaux Passation de Access Expansion in d'électrification des poches IDA / D1770 A posteriori marché de gré à Direct 4,950,000.00 4,902,302.03 Signé 2018-03-22 2018-02-05 2018-03-27 2018-02-15 2018-05-04 2018-06-25 2019-09-26 Selected SNEL Service noires à Malweka, Mpasa & gré Areas Kisenso Network Upgrades and ZR-UCM-66597-CW-DIR / Passation de Access Expansion in M03 - Travaux aux postes IDA / D1770 A priori marché de gré à Direct 9,500,000.00 8,795,238.38 Signé 2018-03-22 2018-10-11 2018-03-27 2019-05-02 2018-05-01 2018-06-25 2019-11-22 Selected SNEL Service et sous-stations gré Areas ZR-UCM-72750-CW-RFB / Travaux d'urgence pour la Network Upgrades and fiabilisation du groupe 2 et Access Expansion in Open - Single Stage - One IDA / D1770 A posteriori Appel d'offres 1,631,000.00 0.00 Annulé 2018-08-31 2018-09-05 2018-10-20 2018-11-19 2018-12-24 2019-09-20 des engins de levage de la Selected SNEL Service International Envelope centrale hydroélectrique de Areas Mobayi Mbongo ZR-UCM-76401-CW-RFB / Travaux d'urgence de fiabilisation et remise en Network Upgrades and service du groupe 2 et de Access Expansion in Single Stage - One IDA / D1770 A posteriori Appel d'offres Limited 2,500,000.00 0.00 Annulé 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 2019-07-29 réhabilitation des engins de Selected SNEL Service Envelope levage et de manutention de Areas la Centrale Hydroélectrique de Mobayi Page 1 ZR-UCM-84199-CW-RFB / Travaux de construction de Network Upgrades and l'ouvrage de protection de la Access Expansion in Open - Single Stage - One En attente IDA / D1770 A posteriori Appel d'offres 4,000,000.00 0.00 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-11-03 berge de l'Ubangi à Mobayi Selected SNEL Service International Envelope d'exécution Mbongo au niveau des Areas village Ziamba et Kumbu ZR-UCM-88512-CW-RFB / Travaux de réhabilitation de Network Upgrades and la ligne de transport HT Access Expansion in Open - Single Stage - One En cours 132 kV Mobayi - Gbadolite IDA / D1770 A priori Appel d'offres 9,371,000.00 0.00 2018-11-01 2020-01-16 2018-12-01 2020-03-13 2019-01-30 2019-03-31 2019-05-21 2019-11-17 Selected SNEL Service International Envelope d'exécution ainsi que la réhabilitation Areas et l'extension des réseaux de distribution de Gbadolite ZR-UCM-88614-CW-RFB / Network Upgrades and Travaux de réhabilitation de Access Expansion in Open - Single Stage - One En attente IDA / D1770 A priori Appel d'offres 10,700,000.00 0.00 2019-04-28 2019-05-23 2019-07-22 2019-08-21 2019-10-11 2020-10-05 la centrale hydroélectrique Selected SNEL Service International Envelope d'exécution de Mobayi et des auxiliaires Areas ZR-UCM-88511-CW-RFB / Sélection d'entrepreneurs en charge des Travaux Network Upgrades and d'électrification des poches Access Expansion in Open - Single Stage - One En cours noires, d'assainissement, de IDA / D1770 A priori Appel d'offres 51,460,000.00 0.00 2019-07-15 2019-11-28 2019-09-13 2019-11-12 2020-01-11 2020-03-26 2021-03-21 Selected SNEL Service International Envelope d'exécution réhabilitation et de mise en Areas conformité du réseau de distribution SNEL DKO & DKC ZR-UCM-88500-CW-RFB / Network Upgrades and Travaux de réhabilitation de Access Expansion in Open - Single Stage - One IDA / D1770 A priori Appel d'offres 10,700,000.00 0.00 Annulé 2018-11-01 2018-11-16 2019-01-20 2019-03-21 2019-04-25 2020-04-19 la centrale de Mobayi- Selected SNEL Service International Envelope Mbongo et des auxiliaires Areas ZR-UCM-142770-CW-RFB / Électrification des poches noires, assainissement, Network Upgrades and réhabilitation et mise en Access Expansion in Open - Single Stage - One En cours IDA / D1770 A priori Appel d'offres 19,000,000.00 0.00 2019-11-04 2019-11-22 2019-11-09 2019-12-06 2019-12-21 2020-01-31 2020-01-20 2020-05-26 2020-02-24 2020-08-22 conformité des réseaux de Selected SNEL Service International Envelope d'exécution distribution d’électricité des Areas directions SNEL DKC & DKO ZR-UCM-142777-CW-RFB / Électrification par MALT des poches noires, Network Upgrades and assainissement, Access Expansion in Open - Single Stage - One En cours réhabilitation et mise en IDA / D1770 A priori Appel d'offres 8,000,000.00 5,270,157.02 2019-11-15 2019-11-28 2019-11-30 2019-12-06 2020-01-29 2020-02-14 2020-02-08 2020-04-09 2020-02-22 2021-08-15 Selected SNEL Service International Envelope d'exécution conformité des réseaux de Areas distribution d’électricité des directions SNEL de Kinshasa Centre et Kinshasa Ouest ZR-UCM-160825-CW-RFB / Recrutement d'un Private Sector Based Access Single Stage - One En attente entrepreneur pour la IDA / D1770 A posteriori Appel d'offres Open - National 2,615,000.00 0.00 2020-06-29 2020-07-04 2020-08-15 2020-09-14 2020-10-19 2021-10-14 Expansion Envelope d'exécution construction du bâtiment pour UCM, ARE & ANSER GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-42630-GO-RFQ / Sector Development and Single Stage - One En attente Acquisition de mobilier pour IDA / D1770 A posteriori Demande de prix Limited 70,000.00 0.00 2018-01-31 2018-03-03 2018-04-02 Implementation Support Envelope d'exécution UCM et MERH ZR-UCM-41705-GO-DIR / Passation de Sector Development and Acquisition et installation IDA / D1770 A posteriori marché de gré à Direct 60,000.00 31,130.66 Achevé 2016-12-01 2017-04-07 2016-12-06 2017-06-05 2017-01-10 2017-06-05 2017-07-09 2020-06-29 Implementation Support logiciel TOM2PRO gré ZR-UCM-42669-GO-RFQ / Sector Development and Single Stage - One Acquisition matériels IDA / V0350 A posteriori Demande de prix Limited 23,000.00 22,600.00 Achevé 2018-01-13 2017-12-04 2018-02-17 2018-01-19 2018-03-19 2020-06-29 Implementation Support Envelope informatiques pour UCM ZR-UCM-42670-GO-RFQ / Acquisition fournitures de Sector Development and Single Stage - One bureau, consommables IDA / V0350 A posteriori Demande de prix Limited 38,000.00 23,339.29 Achevé 2018-02-10 2018-09-11 2018-04-07 2019-05-13 2021-03-22 2020-06-29 Implementation Support Envelope informatiques et bureautiques Page 2 ZR-UCM-42671-GO-RFQ / Sector Development and Single Stage - One En attente Complément matériels IDA / D1770 A posteriori Demande de prix Limited 80,000.00 0.00 2018-02-12 2018-04-09 2018-05-09 Implementation Support Envelope d'exécution informatiques pour UCM ZR-UCM-42675-GO-RFB / Logiciel (formation) et Sector Development and Single Stage - One En attente installation des points de IDA / D1770 A posteriori Appel d'offres Open - National 293,690.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Implementation Support Envelope d'exécution vente pour SNEL (DDK et DC) ZR-UCM-42544-GO-RFB / Sector Development and Open - Single Stage - One Progiciel Intégré SNEL issu IDA / D1770 A posteriori Appel d'offres 1,100,000.00 0.00 Annulé 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Implementation Support International Envelope du PMEDE ZR-UCM-67716-GO-DIR / PRONTO-Installation et mise en oeuvre de: (i) un Passation de Sector Development and cloud privé SNEL, (ii) la IDA / D1770 A posteriori marché de gré à Direct 1,102,756.00 0.00 Annulé 2018-06-22 2018-06-27 2018-08-01 2018-08-31 Implementation Support gestion intégrée et (iii) le gré système d'information clientèle intégré ZR-UCM-42673-GO-DIR / Network Upgrades and Passation de Acquisition de véhicule pour Access Expansion in marchés auprès IDA / D1770 A posteriori Direct 425,000.00 499,177.00 Achevé 2018-10-01 2018-11-05 2018-10-06 2018-11-05 2018-11-10 2018-11-05 2019-05-09 2020-06-29 la mise en œuvre du Projet Selected SNEL Service des agences de (UCM, SNEL) Areas l'ONU ZR-UCM-72755-GO-RFQ / Acquisition de quatre Network Upgrades and véhicules pour l'Unité de Access Expansion in Single Stage - One IDA / D1770 A posteriori Demande de prix Limited 175,000.00 195,020.00 Achevé 2018-06-30 2018-07-03 2018-08-25 2018-09-14 2019-02-21 2020-06-29 coordination et de Selected SNEL Service Envelope Management des Projets du Areas Ministère (UCM) ZR-UCM-76562-GO-DIR / Acquisition et installation de kits (systèmes automatisés) de collecte des données pour Passation de Sector Development and le monitoring de la qualité IDA / D1770 A posteriori marché de gré à Direct 480,000.00 348,162.00 Signé 2018-08-31 2019-01-18 2018-09-05 2019-01-21 2018-10-10 2019-05-31 2019-04-08 Implementation Support de la fourniture d'électricité gré dans le cadre du projet EASE auprès de la firme MCT Télécom SPRL ZR-UCM-142721-GO-RFQ / Acquisition de matériels informatiques pour le Sector Development and Single Stage - One En attente Secrétariat Général du IDA / D1770 A posteriori Demande de prix Limited 20,000.00 0.00 2019-11-20 2020-01-15 2020-07-13 Implementation Support Envelope d'exécution Ministère des Ressources hydrauliques et de l'Electricité ZR-UCM-142748-GO-RFQ / Acquisition de mobilier pour le Secrétariat Général du Sector Development and Single Stage - One En attente IDA / D1770 A posteriori Demande de prix Limited 14,000.00 0.00 2019-11-20 2020-01-15 2020-07-13 ministère des Ressources Implementation Support Envelope d'exécution hydrauliques et de l'Electricité ZR-UCM-142753-GO-RFQ / Acquisition et installation de climatiseurs pour les Sector Development and Single Stage - One En attente bureaux du Secrétariat IDA / D1770 A posteriori Demande de prix Limited 10,500.00 0.00 2019-11-20 2020-01-15 2020-07-13 Implementation Support Envelope d'exécution Général du ministère des Ressources hydrauliques et de l'Electricité ZR-UCM-142778-GO-RFB / Network Upgrades and Fourniture de compteurs à Access Expansion in Open - Single Stage - One En cours IDA / D1770 A priori Appel d'offres 3,000,000.00 1,475,951.60 2019-10-31 2019-11-20 2019-11-15 2019-12-06 2020-01-14 2020-01-21 2020-02-13 2020-04-07 2020-03-20 2021-09-11 pré-paiement pour les Selected SNEL Service International Envelope d'exécution réseaux DKO & DKC Areas NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 ZR-UCM-160814-NC-RFP / Sélection de compagnies de distribution et d'installation Private Sector Based Access Demande de Single Stage - One En cours IDA / 60180 A priori Open - National 3,200,000.00 0.00 2020-03-22 2020-06-19 2020-03-27 2020-06-19 2020-05-08 2019-11-19 2020-06-07 2020-07-12 2021-01-08 de kits solaires dans le Expansion propositions Envelope d'exécution cadre de la subvention basée sur les résultats CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-42604-CS-CQS / ONG pour mise en œuvre PAR (i) travaux électrification réseaux SNEL Network Upgrades and Sélection fondée DKO & DKC (ii) travaux Access Expansion in sur les En cours IDA / D1770 A priori Open - National 200,000.00 0.00 2018-02-05 2018-06-11 2018-02-26 2018-10-11 2018-04-11 2018-05-11 2018-06-15 2018-10-13 électrification Kimbanseke Selected SNEL Service qualifications des d'exécution (iii) travaux Areas consultants électrifcationréseaux SNEL Gbadolite et travaux ligne HT 132 kV Mobayi- Gbadolite ZR-UCM-42627-CS-QCBS / Ingénieur conseil pour APD & justification économique et financière, DAO & Network Upgrades and Sélection fondée supervision travaux Access Expansion in Open - En cours IDA / D1770 A priori sur la qualité et 1,284,000.00 0.00 2018-01-22 2018-10-11 2018-02-05 2018-03-05 2018-10-15 2018-04-19 2018-11-07 2018-05-19 2019-09-16 2018-06-23 2020-01-14 2018-07-28 2021-07-12 réhabilitation centrale de Selected SNEL Service International d'exécution le coût Mobayi. APD & justification Areas économique et financière pour l'extension centrale de Mobayi ZR-UCM-41689-CS-CQS / Ingénieur conseil pour (i) contrôle et supervision Network Upgrades and Sélection fondée travaux issus de PMEDE, Access Expansion in sur les Open - IDA / D1770 A priori 2,500,000.00 0.00 Annulé 2018-01-16 2018-02-06 2018-03-06 2018-03-20 2018-04-08 2021-03-23 (ii) validation études du Selected SNEL Service qualifications des International tracé Kimbanseke et (iii) Areas consultants audit technique marchés issus de PMEDE Network Upgrades and ZR-UCM-42626-CS-LCS / Access Expansion in Sélection au Open - Auditeur du contrat de IDA / D1770 A posteriori 313,000.00 0.00 Annulé 2017-01-10 2017-01-24 2017-04-08 2017-06-07 2017-07-07 2017-08-16 2018-01-14 2018-08-22 Selected SNEL Service moindre coût International service Areas ZR-UCM-42543-CS-LCS / ONG pour (i) campagne de Network Upgrades and communication adaptée au Access Expansion in Sélection au genre et (ii) prise en IDA / D1770 A posteriori Open - National 100,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-08-22 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2018-12-07 Selected SNEL Service moindre coût compte des aspects sociaux Areas dans les travaux de Kinshasa ZR-UCM-41695-CS-LCS / ONG pour (i) campagne de Network Upgrades and communication adaptée au Access Expansion in Sélection au genre et (ii) prise en IDA / D1770 A posteriori Open - National 200,000.00 0.00 Annulé 2018-02-05 2018-02-26 2018-08-22 2018-04-11 2018-05-09 2018-06-08 2018-07-13 2018-08-17 2018-12-07 Selected SNEL Service moindre coût compte des aspects sociaux Areas dans les travaux de Gbadolite & Mobayi ZR-UCM-42621-CS-QCBS / Sélection fondée Recrutement consultant Private Sector Based Access Open - IDA / D1770 A priori sur la qualité et 500,000.00 0.00 Annulé 2018-06-19 2018-07-10 2018-08-23 2018-09-20 2018-10-20 2018-11-24 2018-12-29 2021-12-13 vérificateur indépendant Expansion International le coût (intermédiation financière) ZR-UCM-41665-CS-QCBS / Consultant pour (i) études architecturales, (ii) Sélection fondée Sector Development and En attente élaboration DAO (iii) IDA / D1770 A posteriori sur la qualité et Open - National 360,000.00 0.00 2018-03-20 2018-04-10 2018-05-24 2018-06-21 2018-07-21 2018-08-25 2018-09-29 2020-09-28 Implementation Support d'exécution supervision travaux de le coût rénovation bâtiment UCM, ARE & ANSER ZR-UCM-41654-CS-CQS / Consultant pour les études Sélection fondée de (i) préfaisabilité Sector Development and sur les Open - électrification 12 chefs-lieux IDA / D1770 A priori 900,000.00 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-12 2018-06-16 2018-12-13 Implementation Support qualifications des International de province et (ii) faisabilité consultants et Dao pour 2 à 3 chefs- lieux Page 4 ZR-UCM-41727-CS-CQS / Sélection fondée Consultant pour la Sector Development and sur les Open - préparation du projet de IDA / D1770 A priori 700,000.00 0.00 Annulé 2018-03-06 2018-03-27 2018-05-10 2018-06-09 2018-07-14 2018-11-11 Implementation Support qualifications des International financement additionnel à consultants EASE ZR-UCM-41713-CS-CQS / Consultant pour la coordination et la mise en cohérence (i) de l'étude Sélection fondée géospatiale, (ii) de la Sector Development and sur les Open - IDA / D1770 A priori 700,000.00 0.00 Annulé 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-11-25 préparation projet Implementation Support qualifications des International financement additionnel, (iii) consultants préfaisabilité d'électrification (iv) études développement midsize ZR-UCM-42623-CS-CQS / Préparation nouveau projet d'interconnexion (i) APS, (iià Sélection fondée APD, (iii) justification Sector Development and sur les Open - économique et financière, IDA / D1770 A priori 600,000.00 0.00 Annulé 2018-02-06 2018-02-27 2018-04-12 2018-05-12 2018-06-16 2018-11-11 Implementation Support qualifications des International (iv) DAO lignes de transport consultants et réseaux de distribution pour 8 localités en RDC et 9 en RCA ZR-UCM-42659-CS-QBS / Ingénieur conseil pour le contrôle et la surveillance des travaux d'électrification Network Upgrades and des poches noires er Access Expansion in Sélection fondée Open - En cours IDA / D1770 A priori 821,000.00 0.00 2018-02-13 2018-12-14 2018-03-06 2019-01-21 2018-04-19 2019-11-04 2018-05-17 2019-12-13 2018-06-16 2018-07-16 2018-08-20 2021-08-04 réhabilitation et de Selected SNEL Service sur la qualité International d'exécution conformisation réseaux Areas SNEL Gbadolite ainsi que ligne HT 132 kV Mobayi- Gbadolite ZR-UCM-42660-CS-QCBS / Consultant chargé de l'analyse des dossiers Sélection fondée Private Sector Based Access Open - En cours techniques devant bénéficier IDA / D1770 A priori sur la qualité et 500,000.00 0.00 2018-06-19 2018-07-10 2018-08-23 2018-09-20 2018-10-20 2018-11-24 2018-12-29 2021-12-13 Expansion International d'exécution des lignes de crédit (EDC, le coût ENK & VIRUNGA SARL)- Intermédiation financière ZR-UCM-42818-CS-CQS / Sélection fondée Consultant chargé du Sector Development and sur les Open - IDA / V0350 A posteriori 27,900.00 29,500.00 Achevé 2017-04-14 2017-04-14 2017-04-28 2019-06-03 2017-05-12 2017-05-23 2017-05-17 2017-06-13 2017-06-13 2017-06-13 2017-08-07 2020-06-29 recrutement du personnel Implementation Support qualifications des International d'UCM consultants ZR-UCM-41687-CS-LCS / Audit financier et comptable Sector Development and Sélection au Open - En cours des comptes annuels ainsi IDA / D1770 A posteriori 100,000.00 0.00 2018-01-08 2017-05-30 2018-01-29 2019-06-01 2018-03-14 2017-12-15 2018-04-11 2018-01-30 2018-05-11 2018-03-06 2018-06-15 2018-03-26 2018-07-20 2021-07-13 Implementation Support moindre coût International d'exécution que des procédures de passation des marchés ZR-UCM-42887-CS-QCBS / Cabinet pour (i) l'assistance technique en vue de renforcement des capacités Sélection fondée Sector Development and Open - En attente institutionnelles MERH, IDA / D1770 A posteriori sur la qualité et 194,000.00 0.00 2019-02-01 2019-02-22 2019-04-07 2019-05-05 2019-06-04 2019-07-09 2019-08-13 2020-08-12 Implementation Support International d'exécution ARE, ANSER & CSPP, (ii) le coût mise en œuvre plan de formation financé par le projet PAGASE ZR-UCM-42589-CS-QCBS / Ingénieur conseil pour le contrôle et la surveillance Network Upgrades and Sélection fondée des travaux d'élecrrification Access Expansion in Open - IDA / D1770 A priori sur la qualité et 3,286,000.00 1,636,139.03 Signé 2018-02-02 2018-10-11 2018-02-23 2018-11-21 2018-04-08 2019-10-21 2018-05-06 2019-11-14 2018-06-05 2020-02-13 2018-07-10 2020-04-15 2018-08-14 2020-05-05 2021-07-29 des poches noires, Selected SNEL Service International le coût assainissement, Areas conformisation réseaux SNEL DKO & DKC ZR-UCM-69853-CS-QCBS / Etudes de préfaisabilité, faisabilité, APD et DAO pour l'électrification des localités en RDC partant de Sélection fondée la CHE Mobayi, et études Sector Development and Open - En attente IDA / D1770 A priori sur la qualité et 950,000.00 0.00 2018-08-20 2018-09-10 2018-10-24 2018-11-21 2018-12-21 2019-01-25 2019-03-01 2019-07-20 de planification du Implementation Support International d'exécution le coût développement de sites hydroélectriques pour l'électrification des mêmes localités au Nord et Sud Ubangi Page 5 ZR-UCM-69858-CS-QCBS / Ingénieur conseil chargé du Network Upgrades and Sélection fondée contrôle et de la Access Expansion in Open - En cours IDA / D1770 A priori sur la qualité et 1,700,000.00 0.00 2018-08-09 2018-12-11 2018-08-30 2019-01-21 2018-10-13 2019-10-21 2018-11-10 2019-11-29 2018-12-10 2020-02-05 2019-01-14 2020-06-20 2019-02-18 2020-07-12 surveillance de la phase 2 Selected SNEL Service International d'exécution le coût des travaux transférés de Areas PMEDE à EASE ZR-UCM-69859-CS-QCBS / Etudes de: (i) préfaisabilité pour électrification par système solaire de 9 chefs-lieux de Sélection fondée Sector Development and Open - province et 66 autres IDA / D1770 A priori sur la qualité et 900,000.00 830,961.08 Signé 2018-08-13 2018-10-11 2018-09-03 2018-11-21 2018-10-17 2019-08-09 2018-11-14 2019-10-07 2018-12-14 2019-11-22 2019-01-18 2019-12-18 2019-02-22 2020-04-06 2019-10-31 Implementation Support International agglomérations non le coût desservies ou insuffisamment alimentés en électricité (ii) faisabilité, APD et DAO pour 3 chefs-lieux ZR-UCM-42625-CS-CQS / Consultant pour études du plan national géospatiale Sélection fondée d'électrification au moindre Sector Development and sur les Open - IDA / D1770 A priori 1,500,000.00 0.00 Annulé 2018-02-20 2018-03-06 2018-04-03 2018-05-03 2018-06-07 2018-12-04 coût à l'horizon 2040 assorti Implementation Support qualifications des International d'une stratégie de mise en consultants œuvre et de prospectus d'investissement ZR-UCM-69884-CS-QCBS / Consultant pour la coordination et la mise en cohérence de: 1) l'étude géospatiale Sélection fondée 2) la préparation du projet Sector Development and Open - En attente IDA / D1770 A priori sur la qualité et 700,000.00 0.00 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 de financement additionnel Implementation Support International d'exécution le coût 3) l'étude de préfaisabilité de l'électrification par énergie solaire 4) des études de développement des Midsizes ZR-UCM-69885-CS-QCBS / Consultant pour les études du Plan National Géo- spatial d'électrification au moindre coût (PNGS) à Sélection fondée Sector Development and Open - l'horizon 2040, assorti IDA / D1770 A priori sur la qualité et 1,500,000.00 1,210,765.00 Signé 2018-07-23 2018-09-27 2018-08-13 2018-10-11 2018-09-26 2019-10-03 2018-10-24 2019-11-14 2018-11-23 2020-02-05 2018-12-28 2020-04-14 2019-02-01 2020-04-29 2019-07-31 Implementation Support International d'une stratégie de mise en le coût oeuvre et de prospectus d'investissement (analyse des réseaux dans les agglomérations) ZR-UCM-69898-CS-QCBS / Consultant pour la Sélection fondée Sector Development and Open - En attente préparation du projet de IDA / D1770 A priori sur la qualité et 700,000.00 0.00 2018-09-18 2018-10-09 2018-11-22 2018-12-20 2019-01-19 2019-02-23 2019-03-30 2019-07-28 Implementation Support International d'exécution financement additionnel à le coût EASE ZR-UCM-72635-CS-CQS / Sélection fondée Consultant pour l'élaboration Sector Development and Open - En attente IDA / D1770 A posteriori sur la qualité et 200,000.00 0.00 2018-08-29 2018-09-19 2018-11-02 2018-11-30 2018-12-30 2019-02-03 2019-03-10 2019-07-08 du plan de communication Implementation Support International d'exécution le coût d'UCM ZR-UCM-72677-CS-QCBS / Consultant pour les études Sélection fondée Sector Development and Open - En attente environnementales et IDA / D1770 A posteriori sur la qualité et 250,000.00 0.00 2018-08-15 2018-09-05 2018-10-19 2018-11-16 2018-12-16 2019-01-20 2019-02-24 2019-06-04 Implementation Support International d'exécution sociales des travaux de le coût construction de digue ZR-UCM-72727-CS-CQS / Network Upgrades and Sélection fondée Consultant pour l'audit Access Expansion in sur les Open - technique marchés des IDA / D1770 A posteriori 150,000.00 194,585.00 Signé 2018-08-08 2018-09-14 2018-08-24 2019-01-21 2018-10-08 2019-08-30 2018-11-07 2019-10-02 2018-12-12 2019-10-07 2019-02-10 Selected SNEL Service qualifications des International travaux transférés de Areas consultants PMEDE ZR-UCM-72753-CS-QCBS / Consultant pour l'élaboration des études de faisabilité et élaboration de l'APD et Sélection fondée Sector Development and Open - En attente DAO pour l'électrification de IDA / D1770 A priori sur la qualité et 600,000.00 0.00 2018-11-18 2018-12-09 2019-01-22 2019-02-19 2019-03-21 2019-04-25 2019-05-30 2019-11-26 Implementation Support International d'exécution la ville de Mbandaka à le coût partir du réseau de la République du Congo Brazzaville (Imboulou) Page 6 ZR-UCM-72749-CS-CQS / Consultant chargé de Network Upgrades and Sélection fondée dresser l'état des lieux du Access Expansion in sur les Open - passif environnemental et IDA / D1770 A posteriori 200,000.00 0.00 Annulé 2018-08-06 2018-08-27 2018-10-10 2018-11-09 2018-12-14 2019-06-12 Selected SNEL Service qualifications des International social des travaux de Areas consultants construction de la centrale de Mobayi Mbongo ZR-UCM-73112-CS-CQS / Consultant pour le Sélection fondée recrutement du personnel Sector Development and sur les Open - additionnel d'UCM en IDA / D1770 A posteriori 50,000.00 0.00 Annulé 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-04-11 Implementation Support qualifications des International rapport avec le Projet consultants d'électrification transfrontalière ZR-UCM-84205-CS-QCBS / Ingénieur conseil pour les études des travaux de Network Upgrades and construction de l'ouvrage de Sélection fondée Access Expansion in Open - protection des berges de IDA / D1770 A priori sur la qualité et 1,500,000.00 0.00 Annulé 2018-11-05 2018-11-26 2019-01-09 2019-02-06 2019-03-08 2019-04-12 2019-05-17 2020-05-16 Selected SNEL Service International l'Ubangi au niveau des le coût Areas villages ZIAMBA et KUMBU ainsi que la supervision et surveillance des travaux ZR-UCM-78835-CS-CQS / Consultant (ONG) pour : (i) campagne de communication Network Upgrades and Sélection fondée et de sensibilisation adaptée Access Expansion in sur les IDA / D1770 A posteriori Open - National 200,000.00 247,635.00 Signé 2018-02-05 2018-04-26 2018-02-26 2019-03-05 2018-04-11 2019-03-28 2018-05-11 2019-06-07 2018-06-15 2019-06-19 2018-12-12 2020-06-29 au genre, (ii) prise en Selected SNEL Service qualifications des compte des aspects sociaux Areas consultants dans les travaux de GBADOLITE ZR-UCM-78834-CS-CQS / Consultant (ONG) pour : (i) campagne de communication Network Upgrades and Sélection fondée et de sensibilisation adaptée Access Expansion in sur les IDA / D1770 A posteriori Open - National 100,000.00 289,150.69 Signé 2018-02-05 2018-04-26 2018-02-26 2019-03-04 2018-04-11 2019-03-28 2018-05-11 2019-06-07 2018-06-15 2019-06-19 2018-12-12 2020-06-29 au genre, (ii) prise en Selected SNEL Service qualifications des compte des aspects sociaux Areas consultants dans les travaux de KINSHASA ZR-UCM-80600-CS-CQS / Sélection fondée Consultant chargé de Sector Development and sur les En attente IDA / D1770 A posteriori Open - National 195,000.00 0.00 2018-10-15 2018-11-05 2018-12-19 2019-01-18 2019-02-22 2019-08-21 l'élaboration du plan de Implementation Support qualifications des d'exécution communication d'UCM consultants ZR-UCM-72639-CS-QCBS / Consultant pour (i) les études de la digue de protection des berges au Network Upgrades and Sélection fondée large des villages Ziamba et Access Expansion in Open - En cours IDA / D1770 A priori sur la qualité et 1,600,000.00 0.00 2019-01-10 2019-04-03 2019-01-31 2019-08-13 2019-03-23 2019-04-20 2019-05-20 2019-07-01 2019-08-05 2021-03-27 Kumbu (Mobayi Mbongo), Selected SNEL Service International d'examen le coût (ii) élaboration du DAO et Areas (iii) surveillance des travaux de construction de la digue de protection ZR-UCM-88596-CS-CQS / Network Upgrades and Sélection fondée Consultant firme pour le Access Expansion in sur les Open - En attente recrutement interne du IDA / D1770 A posteriori 100,000.00 0.00 2019-01-14 2019-02-04 2019-04-05 2019-05-05 2019-06-09 2019-12-06 Selected SNEL Service qualifications des International d'exécution personnel SNEL aux postes Areas consultants vacants laissés par MHI ZR-UCM-88599-CS-QCBS / Consultant pour: (i) Etudes de faisabilité, (ii) APD, (iii) justification économique et financière (iv) élaboration Sélection fondée Sector Development and Open - En attente DAO des lignes de IDA / D1770 A priori sur la qualité et 1,000,000.00 0.00 2019-01-23 2019-02-13 2019-04-05 2019-06-04 2019-07-04 2019-08-08 2019-09-28 2020-09-27 Implementation Support International d'exécution transport à partir de la le coût CHE de Mobayi et du site de l'ile des éléphants pour électrification 14 centres en RDC ZR-UCM-88498-CS-LCS / Sélection des banques Private Sector Based Access Sélection au En attente commerciales pour la IDA / D1770 A priori Open - National 10,000,000.00 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2019-11-09 Expansion moindre coût d'exécution gestion des fonds destinés à la ligne de crédit ZR-UCM-42601-CS-LCS / EIES , PGES & PAR pour Sector Development and Sélection au Open - IDA / D1770 A posteriori 250,000.00 0.00 Annulé 2018-03-13 2018-04-03 2018-05-17 2018-06-14 2018-07-14 2018-08-18 2018-09-22 2019-05-20 le nouveau projet Implementation Support moindre coût International d'interconnexion Page 7 ZR-UCM-106938-CS-CQS / Consultant chargé de la mise en oeuvre des PAR Network Upgrades and Sélection fondée pour les travaux:(i) Access Expansion in sur les d'électrification des poches IDA / D1770 A posteriori Open - National 200,000.00 248,165.00 Signé 2019-03-19 2018-04-18 2019-04-09 2019-05-23 2019-05-28 2019-06-22 2019-06-23 2019-07-27 2019-06-20 2019-11-24 Selected SNEL Service qualifications des noires DKC & DKO, (ii) de Areas consultants réhabilitation de la CHE de Mobayi et (iii) d'extension du réseau de Kimbanseke ZR-UCM-122294-CS-CQS / ONG chargée de la mise en Network Upgrades and Sélection fondée œuvre des mesures de Access Expansion in sur les En cours prévention et réponse aux IDA / D1770 A posteriori Open - National 295,000.00 0.00 2019-07-22 2019-11-01 2019-08-12 2020-01-13 2019-09-14 2019-10-14 2019-11-18 2020-05-16 Selected SNEL Service qualifications des d'exécution VBG dans le cadre des Areas consultants activités du projet EASE à Kinshasa ZR-UCM-122295-CS-CQS / Network Upgrades and Sélection fondée Firme pour l’actualisation Access Expansion in sur les En cours des cadres IDA / D1770 A posteriori Open - National 250,000.00 0.00 2019-07-23 2019-12-19 2019-08-13 2019-10-03 2019-11-02 2019-12-07 2020-06-04 Selected SNEL Service qualifications des d'examen environnementaux CGES, Areas consultants CPR, CPPA du projet EASE ZR-UCM-142660-CS-QCBS / Etude (i) d'une structure tarifaire et de la fiscalité Network Upgrades and Sélection fondée applicable au secteur de Access Expansion in sur les Open - En cours l'électricité, (ii) de la IDA / D1770 A priori 510,000.00 0.00 2019-11-15 2020-02-18 2019-12-06 2020-06-06 2020-01-19 2020-02-18 2020-03-24 2020-09-20 Selected SNEL Service qualifications des International d'examen structuration de la dette de Areas consultants SNEL vis-à-vis de sa clinetèle privée, (iii) de la restructuration de la SNEL ZR-UCM-142799-CS-CQS / ONG chargée de la mise en Network Upgrades and Sélection fondée œuvre des mesures de Access Expansion in sur les En cours prévention et réponse aux IDA / D1770 A posteriori Open - National 350,000.00 0.00 2019-11-15 2019-11-14 2019-12-06 2020-01-13 2020-01-26 2020-02-25 2020-03-31 2020-09-27 Selected SNEL Service qualifications des d'exécution VBG dans le cadre des Areas consultants activités du projet EASE à Gbadolite ZR-UCM-143154-CS-QCBS / Ingénieur conseil pour APD & justification économique et financière, DAO & Network Upgrades and Sélection fondée supervision des travaux de Access Expansion in Open - En cours IDA / D1770 A priori sur la qualité et 1,284,000.00 0.00 2019-10-28 2019-11-04 2019-11-18 2019-11-07 2020-01-01 2019-11-11 2020-01-29 2018-11-07 2020-02-28 2019-11-13 2020-04-03 2020-05-08 2021-05-08 réhabilitation de la CHE de Selected SNEL Service International d'exécution le coût Mobayi. Réalisation APD & Areas justification économique et financière pour l'extension centrale de Mobayi ZR-UCM-152815-CS-QCBS / Sélection fondée Sector Development and Open - En attente Etude des axes de IDA / D1770 A priori sur la qualité et 810,000.00 0.00 2020-03-23 2020-04-13 2020-06-12 2020-08-11 2020-09-10 2020-10-15 2020-11-19 2021-11-19 Implementation Support International d'exécution restructuration de SNEL le coût ZR-UCM-150803-CS-CQS / Consultant (Firme) chargé d'assister UCM dans le contrôle des activités réalisées par les opérateurs Sélection fondée de réseaux et les Private Sector Based Access sur les Open - En attente IDA / D1770 A posteriori 300,000.00 0.00 2020-01-31 2020-02-21 2020-04-05 2020-05-05 2020-06-09 2020-12-06 entreprises sélectionnées Expansion qualifications des International d'exécution dans le cadre du fonds consultants d'électrification du Projet EASE pour la distribution et 'installation de kits solaires ZR-UCM-152794-CS-CQS / Consultant chargé de Sélection fondée l'analyse des dossiers Private Sector Based Access sur les En attente IDA / D1770 A posteriori Open - National 150,000.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-05 2020-07-10 2020-07-13 techniques devant bénéficier Expansion qualifications des d'exécution des lignes de crédit (EDC, consultants ENK & VIRUNGA SARL) ZR-UCM-160466-CS-CQS / Sélection d'un cabinet de Sélection fondée vérification indépendante des Private Sector Based Access sur les Open - En attente IDA / D1770 A posteriori 200,000.00 0.00 2020-03-01 2020-03-22 2020-05-05 2020-06-04 2020-07-09 2021-01-05 réalisation des opérateurs Expansion qualifications des International d'exécution réseaux et compagnies consultants solaires Page 8 ZR-UCM-160788-CS-LCS / Recrutement d'un cabinet Sector Development and Sélection au En attente d'audit financier et IDA / D1770 A posteriori Open - National 100,000.00 0.00 2020-03-20 2020-04-10 2020-05-24 2020-06-21 2020-07-21 2020-08-25 2020-09-29 2021-03-28 Implementation Support moindre coût d'exécution comptable pour les audits externes annuels du projet ZR-UCM-167931-CS-QCBS / Recrutement d'un cabinet Sélection fondée Sector Development and Open - En cours pour l'Etude tarifaire et la IDA / D1770 A priori sur la qualité et 510,000.00 0.00 2020-04-07 2020-06-19 2020-04-28 2020-06-20 2020-06-11 2020-07-09 2020-08-08 2020-09-12 2020-10-17 2021-10-17 Implementation Support International d'examen fiscalité du secteur de le coût l'électricité ZR-UCM-154442-CS-CQS / Consultant pour (i) élaboration structure tarifaire applicable au Sélection fondée secteur de l’électricité, (ii) Sector Development and sur les Open - IDA / D1770 A posteriori 350,000.00 0.00 Annulé 2020-01-18 2020-02-08 2020-03-23 2020-04-22 2020-05-27 2020-11-23 proposition régime fiscal et Implementation Support qualifications des International parafiscal incitatif spécifique consultants au secteur (iii) élaboration d’une grille tarifaire propre au cas de la SNEL ZR-UCM-174906-CS-QCBS / Sélection fondée Recrutement d'un cabinet Sector Development and En attente IDA / D1770 A posteriori sur la qualité et Open - National 80,000.00 0.00 2020-05-29 2020-06-19 2020-08-02 2020-08-30 2020-09-29 2020-11-03 2020-12-08 2021-12-08 pour l'audit interne Implementation Support d'exécution le coût trimestriel du projet ZR-UCM-160802-CS-CQS / Consultant (Cabinet) pour la Sélection fondée vulgarisation de la loi n° Sector Development and sur les En attente 14/011 du 17 juin 2014 IDA / D1770 A posteriori Open - National 150,000.00 0.00 2020-06-29 2020-07-20 2020-09-02 2020-10-02 2020-11-06 2021-05-05 Implementation Support qualifications des d'exécution relative au secteur de consultants l'électricité en RDC et des mesures d'application INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-UCM-41709-CS-CDS / APD & DAO pour électrification poches noires, Network Upgrades and Sélection de assainissement, Access Expansion in IDA / D1770 A priori consultants par Direct 563,500.00 488,849.00 Signé 2017-07-07 2018-04-17 2017-07-17 2017-07-20 2017-09-20 2017-10-10 2018-06-17 réhabilitation et conformité Selected SNEL Service entente directe réseaux SNEL DKO &DKC Areas ainsi que Gbadolite et ligne HT 132 kV Gbadolite- Mobayi ZR-UCM-42540-CS-INDV / Etude d'une architecture de Network Upgrades and réseau MALT et triphasé Access Expansion in IDA / D1770 A posteriori Individuel Limited 130,000.00 0.00 Annulé 2017-06-26 2017-06-26 2017-07-01 2018-01-17 2018-02-05 2018-04-09 avec transformateur sur Selected SNEL Service poteau à Kinshasa et Areas Gbadolite ZR-UCM-41691-CS-CDS / Elaboration EIES & PAR pour électrification poches noires, assainissement, Network Upgrades and Sélection de réhabilitation et conformité Access Expansion in IDA / D1770 A priori consultants par Direct 200,000.00 573,500.00 Signé 2018-01-08 2018-10-11 2018-01-18 2018-07-07 2018-03-08 2018-02-27 2018-05-24 réseaux SNEL DKO &DKC. Selected SNEL Service entente directe Actualisation PGES et PAR Areas des travaux d'électrification de Kimbanseke phase 2 (Lot 6B du PMEDE) ZR-UCM-42537-CS-CDS / Elaboration du CPR pour Network Upgrades and Sélection de l'amélioration de l'accès à Access Expansion in IDA / V0350 A posteriori consultants par Direct 37,500.00 37,500.00 Signé 2016-02-24 2016-08-15 2016-04-09 2016-10-16 2016-10-14 2016-10-14 2017-02-28 2020-06-29 l'électricité à travers Selected SNEL Service entente directe SNELet les promoteurs Areas privés ZR-UCM-42539-CS-CDS / Elaboration des cadres de Network Upgrades and CGES, CPPA pour Sélection de Access Expansion in l'accroissement et IDA / V0350 A posteriori consultants par Direct 89,000.00 84,150.00 Signé 2016-02-24 2016-08-09 2016-03-23 2016-10-11 2016-10-14 2016-10-14 2017-02-28 2020-06-29 Selected SNEL Service l'amélioration de l'accès à entente directe Areas l'électricité à travers SNEL & les promoteurs privés Page 9 ZR-UCM-41723-CS-CDS / Network Upgrades and Validation TDR et cadres Sélection de Access Expansion in En cours (CGES, CPR & CPA) par IDA / V0350 A posteriori consultants par Direct 15,500.00 0.00 2016-08-05 2017-01-02 2017-03-08 2017-03-16 Selected SNEL Service d'exécution l'Agence Congolaise de entente directe Areas l'Environnement (ACE) ZR-UCM-41712-CS-CDS / Network Upgrades and Sélection de Validation TDR et cadres Access Expansion in En cours IDA / D1770 A posteriori consultants par Direct 104,500.00 0.00 2018-01-25 2018-02-04 2018-04-10 2021-03-25 (CGES, CPR & CPA) par Selected SNEL Service d'exécution entente directe ACE Areas ZR-UCM-41725-CS-CDS / Network Upgrades and Sélection de Contrat de service Access Expansion in En cours IDA / D1770 A priori consultants par Direct 4,200,000.00 0.00 2018-01-23 2018-10-11 2018-02-02 2018-02-17 2018-06-27 MANITOBA HYDRO Selected SNEL Service d'exécution entente directe INTERNATIONAL Areas ZR-UCM-42567-CS-CDS / Sélection de EIES et PAR des travaux Sector Development and En attente IDA / D1770 A posteriori consultants par Direct 25,000.00 0.00 2018-08-28 2018-09-22 2018-11-09 2018-12-09 de rénovation du bâtiment Implementation Support d'exécution entente directe UCM,ARE & ANSER ZR-UCM-42547-CS-INDV / Sector Development and En cours IDA / D1770 A priori Individuel Open 270,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Spécialiste en production Implementation Support d'exécution ZR-UCM-42535-CS-INDV / Sector Development and En cours Spécialiste en énergies IDA / D1770 A priori Individuel Open 246,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Implementation Support d'exécution renouvelables ZR-UCM-41681-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 Chargée de suivi évaluation Implementation Support ZR-UCM-41683-CS-INDV / Sector Development and En cours Spécialiste en question IDA / D1770 A priori Individuel Open 258,000.00 0.00 2017-02-13 2018-10-11 2017-04-03 2017-04-13 2017-05-02 2018-04-30 Implementation Support d'exécution environnementales ZR-UCM-42546-CS-INDV / Sector Development and En cours Spécialiste en développement IDA / D1770 A priori Individuel Open 276,000.00 0.00 2017-02-13 2018-10-11 2017-04-03 2017-04-24 2017-09-29 2018-12-14 Implementation Support d'exécution sociale ZR-UCM-42541-CS-INDV / Responsable des questions Sector Development and En cours IDA / D1770 A priori Individuel Open 336,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-09-30 juridiques et Implementation Support d'exécution transactionnelles ZR-UCM-41696-CS-INDV / Sector Development and En cours Responsable de la passation IDA / D1770 A priori Individuel Open 258,000.00 0.00 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-09-29 2018-10-17 Implementation Support d'exécution de marchés ZR-UCM-41686-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-16 2018-10-11 2017-08-04 2017-08-25 2017-11-09 2018-11-08 Comptable Implementation Support ZR-UCM-42558-CS-INDV / Responsable de la Sector Development and En cours IDA / D1770 A priori Individuel Open 324,000.00 0.00 2018-01-05 2018-10-11 2018-02-23 2018-03-16 2018-03-31 2018-09-30 planification et gestion Implementation Support d'exécution technique ZR-UCM-42562-CS-INDV / Sector Development and En cours Responsable Administratif et IDA / D1770 A priori Individuel Open 258,000.00 0.00 2018-01-05 2018-10-11 2018-02-23 2018-03-16 2018-03-31 2018-09-30 Implementation Support d'exécution Financier ZR-UCM-42533-CS-CDS / Elaboration EIES, PGES & Network Upgrades and PAR des travaux de Sélection de Access Expansion in réhabilitation centrale de IDA / D1770 A posteriori consultants par Direct 145,000.00 141,515.00 Signé 2018-01-08 2018-01-08 2018-01-18 2018-08-10 2018-03-08 2018-02-27 2018-05-17 2020-06-29 Selected SNEL Service Mobayi, ligne HT 132 kV entente directe Areas Mobayi-Gbadolite et réseaux Gbadolite ZR-UCM-42862-CS-INDV / Assistant technique Sector Development and IDA / D1770 A posteriori Individuel Open 196,000.00 155,800.00 Signé 2018-01-10 2017-10-23 2018-02-28 2017-12-12 2018-03-21 2018-01-12 2018-04-25 2018-04-11 2018-12-21 2020-06-29 spécialiste de passation de Implementation Support marchés Network Upgrades and Sélection de ZR-UCM-67725-CS-CDS / Access Expansion in En attente IDA / D1770 A posteriori consultants par Direct 313,000.00 0.00 2018-06-24 2018-07-04 2018-09-07 2019-03-06 Audit du Contrat de Service Selected SNEL Service d'exécution entente directe Areas Page 10 ZR-UCM-69854-CS-CDS / Ingénieur conseil chargé du contrôle et de la Network Upgrades and Sélection de surveillance de la phase 1 Access Expansion in IDA / D1770 A priori consultants par Direct 1,068,000.00 1,525,930.00 Signé 2018-08-08 2018-08-29 2018-08-27 2018-09-07 2018-10-31 2018-11-09 2019-10-26 des travaux transférés de Selected SNEL Service entente directe PMEDE à EASE et de la Areas validation des études du tracé Kimbanseke ZR-UCM-69902-CS-INDV / Consultant individuel pour l'actualisation des études d'impacts environnementaux Sector Development and En attente IDA / D1770 A priori Individuel Open 200,000.00 0.00 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-03-14 et sociaux (PGES) et plan Implementation Support d'exécution d'action de relocalisation des populations pour les réseaux d'électrification en RCA ZR-UCM-75550-CS-INDV / Consultant individuel chargé de dresser l'état des lieux Network Upgrades and du passif environnemental Access Expansion in IDA / D1770 A posteriori Individuel Limited 95,000.00 79,300.00 Achevé 2018-08-25 2018-07-07 2018-08-30 2018-08-21 2018-09-09 2018-09-14 2018-10-07 2018-09-18 2018-11-08 2020-06-29 et social des travaux de Selected SNEL Service construction de la Centrale Areas hydroélectrique de Mobayi- Mbongo ZR-UCM-76476-CS-INDV / Network Upgrades and Audit environnemental et Access Expansion in IDA / D1770 A posteriori Individuel Limited 190,000.00 145,000.00 Signé 2018-08-01 2018-12-12 2018-08-06 2019-01-22 2018-08-27 2019-05-27 2018-10-01 2019-05-27 2018-11-30 2020-06-29 social des travaux transférés Selected SNEL Service du projet PMEDE à EASE Areas ZR-UCM-41653-CS-CDS / Sélection de Sector Development and Prestataire pour l'entretien IDA / D1770 A posteriori consultants par Direct 12,000.00 0.00 Annulé 2018-10-01 2018-10-11 2018-12-15 2021-11-29 Implementation Support des bureaux entente directe ZR-UCM-78836-CS-INDV / Remplacement du Spécialiste Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 45,000.00 0.00 2018-06-01 2018-06-28 2018-06-06 2018-06-27 2018-08-01 2019-01-28 en questions Implementation Support d'exécution environnementales ZR-UCM-76561-CS-CDS / Institution supérieure technique (Institut Supérieur de Techniques Appliquées- Sélection de Sector Development and En cours ISTA) pour le monitoring de IDA / D1770 A posteriori consultants par Direct 350,000.00 0.00 2018-08-31 2019-10-30 2018-09-10 2018-11-14 2020-05-07 Implementation Support d'exécution la qualité de la fourniture entente directe d'électricité dans les zones d'intervention du projet EASE ZR-UCM-42557-CS-INDV / Sector Development and En cours Auditeur interne (Personnel IDA / D1770 A priori Individuel Open 276,000.00 0.00 2017-06-16 2019-06-18 2017-08-04 2017-08-25 2017-09-29 2018-11-30 Implementation Support d'exécution UCM) ZR-UCM-78824-CS-INDV / Sector Development and Recrutement d'un Spécialiste IDA / D1770 A priori Individuel Open 240,000.00 60,000.00 Signé 2018-10-01 2019-01-23 2018-11-19 2020-03-19 2018-12-10 2020-04-09 2019-01-14 2020-05-15 2020-01-09 Implementation Support en passation des marchés ZR-UCM-88515-CS-INDV / Consultant individuel pour apprécier et examiner (i) Network Upgrades and la pertinence de la Access Expansion in En attente poursuite de la mission IDA / D1770 A priori Individuel Limited 210,000.00 0.00 2018-11-01 2018-11-22 2019-01-06 2019-02-21 2019-08-20 Selected SNEL Service d'exécution d'assistance technique à Areas SNEL ainsi que (ii) les conditions et dispositions y relatives ZR-UCM-88767-CS-CDS / Recrutement du consultant Khaled HAMMOU pour Network Upgrades and Sélection de l'étude d'une architecture de Access Expansion in IDA / D1770 A posteriori consultants par Direct 135,000.00 131,050.00 Signé 2017-06-01 2018-06-25 2017-07-11 2018-02-23 2017-09-14 2018-03-08 2018-03-13 2020-06-29 réseau MALT et triphasé Selected SNEL Service entente directe avec transformateur sur Areas poteau à Kinshasa et Gbadolite Page 11 ZR-UCM-89499-CS-CDS / Recrutement du consultant Khaled HAMMOU pour la Network Upgrades and poursuite et l'achèvement de Sélection de Access Expansion in l'étude d'une architecture de IDA / D1770 A posteriori consultants par Direct 70,000.00 49,900.00 Achevé 2018-12-09 2018-12-20 2019-02-17 2019-05-31 2019-04-23 2019-04-27 2019-10-20 2020-06-29 Selected SNEL Service réseau MALT et triphasé entente directe Areas avec transformateur sur poteau à Kinshasa et Gbadolite ZR-UCM-89561-CS-INDV / Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 84,000.00 0.00 2019-01-14 2019-01-30 2019-01-29 2019-02-28 2019-04-20 2019-10-17 Recrutement d'un chauffeur Implementation Support d'exécution ZR-UCM-88607-CS-INDV / Consultant individuel chargé de l'analyse technique des dossiers des Private Sector Based Access En attente opérateurs privés avant IDA / D1770 A priori Individuel Open 1,000,000.00 0.00 2019-01-27 2019-04-03 2019-04-24 2019-05-29 2019-11-25 Expansion d'exécution octroi de prêts et subvention sur la ligne de crédit et le fonds d'électrification ZR-UCM-97541-CS-INDV / Vérificateur technique (agent UCM) de la mise en oeuvre Sector Development and En cours IDA / D1770 A priori Individuel Open 216,000.00 0.00 2019-01-30 2019-04-10 2019-05-01 2019-06-05 2019-12-02 des activités de la Implementation Support d'exécution composante 2 du Projet EASE ZR-UCM-97545-CS-CDS / Sélection de Convention de subvention Private Sector Based Access En cours IDA / D1770 A priori consultants par Direct 14,469,262.00 0.00 2019-01-30 2019-03-07 2019-03-11 2019-05-15 2019-11-11 d'investissement avec Expansion d'exécution entente directe VIRUNGA SARL ZR-UCM-97558-CS-CDS / Sélection de Private Sector Based Access En cours Convention de subvention IDA / D1770 A priori consultants par Direct 8,256,393.00 0.00 2019-01-30 2019-03-11 2019-05-15 2019-11-11 Expansion d'exécution d'investissement avec EDC entente directe ZR-UCM-97561-CS-CDS / Sélection de Private Sector Based Access En attente Convention de subvention IDA / D1770 A priori consultants par Direct 7,967,008.00 0.00 2019-01-30 2019-03-11 2019-05-15 2019-11-11 Expansion d'exécution avec ENK entente directe ZR-UCM-97562-CS-CDS / Network Upgrades and Sélection de Protocole d'accord de Access Expansion in IDA / D1770 A posteriori consultants par Direct 103,670.00 92,950.00 Signé 2019-01-30 2019-01-29 2019-03-11 2019-02-19 2019-05-15 2019-03-26 2019-11-11 2020-06-29 collaboration entre UCM et Selected SNEL Service entente directe COPIREP Areas ZR-UCM-104709-CS-CDS / consultant individuel chargé d'élaborer le Plan de Réparation des dommages et Network Upgrades and Sélection de de Réinstallation Sociale Access Expansion in En cours IDA / D1770 A posteriori consultants par Direct 100,000.00 0.00 2019-03-15 2019-04-08 2019-04-24 2019-06-28 2019-12-25 dans le cadre du règlement Selected SNEL Service d'exécution entente directe du passif environnemental Areas et social des travaux de construction de la Centrale hydroélectrique de Mobayi ZR-UCM-104712-CS-INDV / Sector Development and En cours Deuxième chauffeur pour IDA / D1770 A posteriori Individuel Limited 84,000.00 0.00 2019-03-20 2019-01-30 2019-04-19 2019-03-21 2019-05-19 2019-07-09 2020-07-03 Implementation Support d'exécution UCM ZR-UCM-104716-CS-CDS / Protocole d'Accord de Network Upgrades and collaboration entre UCM et Sélection de Access Expansion in En attente COPIREP pour les IDA / D1770 A posteriori consultants par Direct 180,000.00 0.00 2019-06-03 2019-08-02 2019-10-06 2020-04-03 Selected SNEL Service d'exécution prestations de COPIREP entente directe Areas dans la nouvelle assistance technique ZR-UCM-41693-CS-CDS / Sélection de Elaboration du manuel Sector Development and En cours IDA / D1770 A posteriori consultants par Direct 60,000.00 0.00 2017-07-14 2017-06-16 2017-07-23 2017-08-02 2018-03-30 d'exécution du projet et du Implementation Support d'exécution entente directe manuel de procédures ZR-UCM-104711-CS-CQS / consultant chargé de l'analyse technique des dossiers des opérateurs Private Sector Based Access En attente IDA / D1770 A priori Individuel Limited 250,000.00 0.00 2019-07-10 2019-07-25 2019-08-29 2019-10-24 2022-10-08 privés avant octroi de prêts Expansion d'exécution et subvention sur la ligne de crédit et le fonds d'électrification Page 12 ZR-UCM-111601-CS-INDV / Sector Development and IDA / D1770 A posteriori Individuel Open 180,000.00 28,800.00 Signé 2019-04-23 2017-02-16 2019-06-11 2017-10-26 2019-07-02 2017-10-31 2019-08-06 2017-11-09 2020-02-02 Comptable Implementation Support ZR-UCM-111602-CS-INDV / Sector Development and En cours IDA / D1770 A priori Individuel Open 220,000.00 0.00 2019-04-23 2019-06-18 2019-06-11 2019-07-02 2019-08-06 2020-08-06 Chargé de suivi-évaluation Implementation Support d'exécution ZR-UCM-99465-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Limited 210,000.00 0.00 Annulé 2019-02-12 2019-06-19 2019-02-22 2019-05-03 2019-03-15 2019-04-19 2022-02-22 Implementation Support Coordonnateur ZR-UCM-88514-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Open 210,000.00 0.00 Annulé 2018-11-01 2019-02-02 2019-01-06 2019-02-05 2019-03-19 2020-03-13 Implementation Support Coordonnateur ZR-UCM-98164-CS-INDV / Sector Development and Assistant technique du IDA / D1770 A priori Individuel Limited 240,000.00 0.00 Annulé 2019-02-01 2019-03-07 2019-03-08 2019-02-07 2019-04-12 2019-05-17 2022-05-01 Implementation Support Coordonnateur ZR-UCM-122292-CS-INDV / Sector Development and En cours ASSISTANT TECHNIQUE IDA / D1770 A priori Individuel Limited 240,000.00 0.00 2019-07-10 2019-08-04 2019-07-15 2019-08-19 2019-08-05 2019-09-26 2019-09-09 2020-03-07 Implementation Support d'exécution DU COORDONNATEUR ZR-UCM-122296-CS-INDV / Consultant individuel pour la réalisation de l’audit Network Upgrades and environnemental et social de Access Expansion in En attente IDA / D1770 A posteriori Individuel Limited 180,000.00 0.00 2019-07-29 2019-08-03 2019-08-24 2019-09-28 2020-03-26 la deuxième ligne Inga- Selected SNEL Service d'exécution Kinshasa sur le tronçon Areas Kimwenza-poste de Kimbanseke ZR-UCM-142584-CS-INDV / Consultant individuel à Sector Development and En attente IDA / D1770 A posteriori Individuel Open 138,000.00 0.00 2019-11-15 2020-01-13 2020-02-03 2020-03-09 2023-02-22 temps partiel assumant la Implementation Support d'exécution fonction d'auditeur Interne ZR-UCM-142674-CS-CDS / Consultant staff assumant Sector Development and En cours IDA / D1770 A posteriori Individuel Limited 138,000.00 0.00 2019-11-15 2019-11-19 2019-11-20 2019-12-11 2020-01-15 2022-12-30 la fonction de Contrôleur Implementation Support d'exécution financier pour UCM ZR-UCM-142676-CS-INDV / Consultant pour (i) la Vulgarisation de la loi n° Sector Development and En attente 14/011 et des mesures IDA / D1770 A posteriori Individuel Limited 160,000.00 0.00 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2020-07-13 Implementation Support d'exécution d'application ainsi que (ii) l'élaboration des procédures et mesures d'application ZR-UCM-142685-CS-INDV / Vérificateur technique des Sector Development and En attente raccordements réalisés par IDA / D1770 A posteriori Individuel Limited 138,000.00 0.00 2019-11-15 2019-11-20 2019-12-11 2020-01-15 2022-12-30 Implementation Support d'exécution les opérateurs privés des mini-réseaux électriques ZR-UCM-142688-CS-INDV / Premier Vérificateur des Private Sector Based Access En attente IDA / D1770 A posteriori Individuel Open 138,000.00 0.00 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2023-02-12 systèmes et kits solaires Expansion d'exécution individuels ZR-UCM-142691-CS-INDV / Private Sector Based Access En attente Deuxième Vérificateur des IDA / D1770 A posteriori Individuel Open 48,000.00 0.00 2019-11-15 2020-01-03 2020-01-24 2020-02-28 2023-02-12 Expansion d'exécution systèmes et kits solaires ZR-UCM-142694-CS-INDV / Consultant individuel à temps partiel chargé de la Sector Development and En cours géolocalisation des IDA / D1770 A posteriori Individuel Limited 36,000.00 0.00 2019-11-15 2019-11-30 2019-11-20 2019-12-11 2020-01-15 2022-12-30 Implementation Support d'exécution branchements/kits solaires et travaux/équipement du Projet EASE ZR-UCM-143149-CS-CDS / Sélection de Consultant pour le Sector Development and En attente IDA / D1770 A posteriori consultants par Direct 45,000.00 0.00 2019-11-15 2019-12-05 2020-02-08 2020-08-06 développement du site Implementation Support d'exécution entente directe Internet d'ARE ZR-UCM-142763-CS-INDV / Consultant chargé de la Private Sector Based Access En attente IDA / D1770 A posteriori Individuel Open 75,000.00 0.00 2019-11-15 2020-01-12 2020-02-02 2020-03-08 2022-02-26 ligne de crédit et des Expansion d'exécution subventions réseaux/solaires Page 13 ZR-UCM-142767-CS-INDV / Cabinet pour la mise à jour Sector Development and En attente IDA / D1770 A posteriori Individuel Limited 30,000.00 0.00 2019-11-15 2019-11-29 2019-12-20 2020-01-24 2020-07-22 du site Internet et la Implementation Support d'exécution messagerie d'UCM ZR-UCM-152802-CS-INDV / Consultant individuel à temps partiel chargé de la Private Sector Based Access En attente géolocalisation des IDA / D1770 A posteriori Individuel Direct 40,000.00 0.00 2020-01-15 2020-01-25 2020-02-15 2020-03-21 2020-11-16 Expansion d'exécution branchements/kits solaires et travaux/équipement du Projet EASE ZR-UCM-152806-CS-CDS / Sélection de Private Sector Based Access En attente Intermédiation financière IDA / 60180 A priori consultants par Direct 10,000,000.00 0.00 2020-03-20 2020-03-30 2020-06-03 2020-07-09 Expansion d'exécution UCM-BCC entente directe ZR-UCM-153482-CS-CDS / Network Upgrades and Consultant (Afrika German Sélection de Access Expansion in En attente Consult) chargé de l'analyse IDA / D1770 A posteriori consultants par Direct 180,000.00 0.00 2020-01-31 2020-02-10 2020-04-15 2020-10-12 Selected SNEL Service d'exécution des indicateurs de l'objectif entente directe Areas de développement du Projet ZR-UCM-154949-CS-INDV / Consultant individuel (M. Georges BAKALY) pour la coordination des études Sector Development and En attente IDA / D1770 A posteriori Individuel Direct 50,000.00 0.00 2020-01-22 2020-02-01 2020-02-22 2020-03-28 2020-05-03 visant le renforcement et Implementation Support d'exécution l'amélioration de la gouvernance du secteur de l'électricité ZR-UCM-41684-CS-INDV / Sector Development and IDA / D1770 A priori Individuel Open 552,000.00 0.00 Annulé 2017-02-13 2018-10-11 2017-02-28 2017-03-05 2017-03-11 2018-02-28 Coordonnateur UCM Implementation Support ZR-UCM-174915-CS-CDS / Groupement ARTELIA-SHER Consultant chargé de la revue de l'étude de pré Sélection de faisabilité relative à Sector Development and En attente IDA / D1770 A posteriori consultants par Direct 150,000.00 0.00 2020-05-24 2020-06-03 2020-08-07 2021-02-03 l'aménagement Implementation Support d'exécution entente directe hydroélectrique sur la rivière Ubangi dans le cadre de l'interconnexion électrique entre la RDC et la RCA ZR-UCM-178594-CS-INDV / Sector Development and En attente Renouvellement du contrat IDA / D1770 A priori Individuel Direct 220,800.00 0.00 2020-06-15 2020-06-25 2020-07-16 2020-08-20 2021-02-16 Implementation Support d'exécution du Coordonnateur d'UCM Page 14