Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Bangladesh : Coastal Embankment Improvement Project - Phase I (CEIP-I) PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-06-20 2019-11-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128276 GPN Date: Project Name: Coastal Embankment Improvement Project - Phase I (CEIP-I) Loan / Credit No: IDA / 52800 Executing Agency(ies): Bangladesh Water Development Board WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CEIP-1/W-02 / Rehabilitation / Rehabilitation and Open - Single Stage - One Reconstruction & Upgrading IDA / 52800 Prior Request for Bids 0.00 138,954,189.70 Signed Improvement of Polders International Envelope of Polder 39/2C, 40/2, 41/1, 43/2C, 47/2 and 48 CEIP-1/W-01 / Under Rehabilitation and Upgrading Rehabilitation and Open - Single Stage - One IDA / 52800 Prior Request for Bids 104,276,026.00 0.00 Implementati 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2019-01-25 of Polder 32, 33, 35/1 and Improvement of Polders International Envelope on 35/3 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CEIP-1/G1 / Procurement of Project Management, Motor Vehicles a) 4-WD Technical Assistance, Single Stage - One Jeep/Cross Country (Total 10 IDA / 52800 Post Request for Bids Open - National 1,000,000.00 708,752.66 Completed 2017-09-18 2017-09-18 2017-09-18 2017-09-18 2017-09-18 2017-09-18 Training and Strategic Envelope Nos.) b) Micro Bus-(Total 1 Studies No.) Project Management, CEIP-1/G2 / Procurement of Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 19,231.00 21,986.63 Completed 2017-09-18 2017-09-18 2017-09-18 2017-09-18 2017-09-18 2017-09-18 Motor Cycle- 10 Nos. Training and Strategic Envelope Studies CEIP-1/G4 / Supply of Project Management, Desktop Computer, Laptop, Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 62,000.00 61,134.89 Completed 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 Printer, & UPS with Training and Strategic Envelope Accessories under CEIP-1 Studies CEIP-1/G5 / Procurement of Project Management, Engineering Equipment :a) Technical Assistance, Single Stage - One Levelling instrument with IDA / 52800 Post Request for Bids Open - National 19,880.00 9,710.26 Completed 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 Training and Strategic Envelope accessories -5 & b) Total Studies Station-3 Nos. CEIP-1/G6 / Office Equipment : 1) Multimedia Projector , 2) Air cooler, 3) PABX Intercom System, 4) Project Management, Photocopier, 5) Fax , 6) Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 38,500.00 26,203.25 Completed 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 2017-09-19 Scanner, 7) Spiral Binding Training and Strategic Envelope Machine and 8) Plotter (36" Studies Size) with accessories and related services under CEIP- 1. Page 1 Project Management, Pending CEIP-1/G7 / Procurement of Technical Assistance, Request for Single Stage - One IDA / 52800 Post Open - National 6,387.00 0.00 Implementati 2017-09-19 2017-09-19 2017-09-19 Office Furniture Training and Strategic Quotations Envelope on Studies CEIP-1/G11 / Procurement Project Management, of Computes a ) laptop-5 Technical Assistance, Single Stage - One nos and Desktop 5 nos b) IDA / 52800 Post Request for Bids Open - National 14,607.60 9,447.23 Completed 2017-07-16 2017-07-16 2017-07-25 2017-08-08 2017-09-12 2018-03-11 Training and Strategic Envelope Printer 10 nos c) UPS 5 nos Studies d) IPS 05 nos Project Management, CEIP-1/G8 / Procurement of Pending Technical Assistance, Single Stage - One Motor Vehicle: 4WD Vehicle- IDA / 52800 Post Request for Bids Open - National 385,000.00 0.00 Implementati 2018-07-10 2018-07-12 2018-08-09 2018-08-30 2018-10-04 2018-12-13 Training and Strategic Envelope 5 Nos. on Studies Project Management, Pending CEIP-1/G9 / Procurement of Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 16,093.00 0.00 Implementati 2018-07-10 2018-07-12 2018-08-02 2018-08-16 2018-09-20 2018-11-08 Motor Cycle- 10 Nos. Training and Strategic Envelope on Studies CEIP-1/G12 / Procurement Project Management, Pending of a) Levelling Instrument - Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 41,000.00 0.00 Implementati 2019-02-03 2019-02-05 2019-02-26 2019-03-12 2019-04-16 2019-05-21 5 Nos. and b) Total Station Training and Strategic Envelope on - 2 Nos Studies CEIP-1/G13 / Procurement of a) Multimedia Projector- 2 Project Management, Nos, b) Air cooler- 5 Nos, c) Pending Technical Assistance, Single Stage - One Photocopier- 5 Nos, d) Fax-6 IDA / 52800 Post Request for Bids Open - National 23,000.00 0.00 Implementati 2019-02-03 2019-02-05 2019-02-26 2019-03-12 2019-04-16 2019-05-21 Training and Strategic Envelope Nos, e) Scanner-2 Nos, f) on Studies Spiral Binding Machine- 2 Nos Project Management, Pending CEIP-1/G14 / Procurement Technical Assistance, Single Stage - One IDA / 52800 Post Request for Bids Open - National 56,410.00 0.00 Implementati 2018-07-10 2018-07-12 2018-08-09 2018-09-08 2018-10-12 2018-12-21 of Micro Bus- 1 No. Training and Strategic Envelope on Studies Project Management, CEIP-1/G3 / Procurement of Pending Technical Assistance, Single Stage - One Speed Boat with engine & IDA / 52800 Post Request for Bids Open - National 61,897.00 0.00 Implementati 2018-09-02 2018-09-06 2018-09-27 2018-10-11 2018-11-15 2019-01-03 Training and Strategic Envelope other accessories- 5 Nos. on Studies Project Management, CEIP-1/G10 / Procurement Pending Technical Assistance, Single Stage - One of Speed Boat with engine IDA / 52800 Post Request for Bids Open - National 49,517.00 0.00 Implementati 2019-09-01 2019-09-05 2019-09-26 2019-10-10 2019-11-14 2020-01-02 Training and Strategic Envelope & other accessories : 4 Nos on Studies NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CEIP-I/C2/S3 / Third Party Monitoring & Evaluation Rehabilitation and Quality Based Open - IDA / 52800 Prior 0.00 3,475,453.58 Signed (M&E) of overall project Improvement of Polders Selection International implementation Page 2 CEIP-1/B2/B3/C1/S2 / Consultancy services for Construction Supervision, Detailed Design, Project Monitoring and Quality Based Open - Under IDA / 52800 Prior 17,182,672.00 0.00 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2020-12-31 Construction Supervision, Evaluation, and Coastal Selection International Implementation and Project Management Zone Monitoring Support CEIP-1/C3/S4 / Long Term Monitoring, Research and Analysis of Bangladesh Construction Supervision, Coastal Zone (Sustainable Project Monitoring and Quality Based Open - IDA / 52800 Prior 14,506,030.00 13,799,657.32 Signed 2018-01-25 2018-01-25 2018-01-25 2018-01-25 2018-01-25 2018-01-25 2018-04-20 2020-06-30 Polder Adapted to Coastal Evaluation, and Coastal Selection International Dynamics) under Coastal Zone Monitoring Embankment Improvement Project, Phase-1 (CEIP-1) CEIP-1/A2 AND B1/S1-A / Consultancy service to Implement (a) social action plan (incl. setting up Implementation of Social Consultant WMOs),(b) Social and Environmental IDA / 52800 Post Qualification Open - National 531,232.00 441,591.25 Signed 2018-02-22 2018-02-22 2018-05-20 2018-06-10 2018-07-08 2020-06-30 afforestation and c) Management Frameworks Selection Integrated Pest Management and Plans (IPM) Plan for Polder No.32 & Polder No. 33 in Khulna District. CEIP-1/A2 AND B1/S1-B / Consultancy service to Implement (a) social action plan (incl. setting up Implementation of Social Consultant WMOs),(b) Social and Environmental IDA / 52800 Post Qualification Open - National 619,489.00 533,092.35 Signed 2018-04-26 2018-04-26 2018-05-20 2018-06-10 2018-07-08 2020-06-30 afforestation and c) Management Frameworks Selection Integrated Pest Management and Plans (IPM) Plan for Polder No.35/1 & Polder No.35/3 in Bagerhat District . CEIP-1/A2 AND B1/S1-C / Consultancy service to Implement (a) Social action Implementation of Social Consultant plan (incl. setting up WMOs) and Environmental IDA / 52800 Post Qualification Open - National 459,287.00 355,046.36 Signed 2018-02-22 2018-02-22 2018-05-20 2018-06-10 2018-07-08 2020-06-30 and c),(b) Social afforestation Management Frameworks Selection Integrated Pest Management and Plans (IPM) Plan for Polder No. 39/2C in Pirojpur District CEIP-1/A2 AND B1/S1-D / Consultancy service to Implement (a) Social afforestation , (b) social Implementation of Social Consultant action plan (incl. setting up and Environmental IDA / 52800 Post Qualification Open - National 457,830.00 358,898.95 Signed 2018-04-18 2018-04-18 2018-05-20 2018-06-10 2018-07-08 2020-06-30 WMOs) and c) Integrated Management Frameworks Selection Pest Management (IPM) and Plans Plan for Polder No.40/2 & Polder No.41/1 in Barguna District. CEIP-1/A2 AND B1/S1-E / Consultancy service to Implement (a) social action plan (incl. setting up WMOs) Implementation of Social Consultant (b) Social afforestation and and Environmental IDA / 52800 Post Qualification Open - National 398,992.00 335,961.59 Signed 2018-04-18 2018-05-31 2018-07-01 2018-07-22 2018-08-19 2020-06-30 c) Integrated Pest Management Frameworks Selection Management (IPM) Plan for and Plans Polder No.43/2C, Polder No. 47/2 and Polder No. 48 in Patuakhali District. Page 3 CEIP-1/ D3/S23 / Consultancy Services for Project Management, Feasibility Studies and Technical Assistance, Quality Based Open - Pending IDA / 52800 Prior 5,270,000.00 0.00 2018-08-26 2018-09-16 2018-10-31 2018-12-12 2019-01-11 2019-02-01 2019-03-31 2020-06-30 Preparation of Detailed Training and Strategic Selection International Implementation Design for the following Studies Phases of CEIP (CEIP II ) CEIP-1/D1/S26 / Consultancy Services for Project Management, Conducting Internal Audit of Technical Assistance, Quality Based Under IDA / 52800 Post Open - National 13,800.00 0.00 2019-07-07 2019-07-21 2019-09-05 2019-10-03 2019-10-24 2019-11-23 2019-12-14 2020-02-12 Coastal Embankment Training and Strategic Selection Implementation Improvement Project, Phase- Studies 1 (CEIP-1) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual CEIP-I/D1/S13 / Senior Rehabilitation and IDA / 52800 Prior Consultant Open 0.00 99,906.32 Canceled Communication Officer Improvement of Polders Selection CEIP-I/D1/S7-A / Individual Rehabilitation and Procurement Expert IDA / 52800 Prior Consultant Open 0.00 132,867.15 Signed Improvement of Polders (National) Selection No: WDB/CEIP/S-10/440 Dated 19-10-2014 / Request for Expressions of Interest Individual (EOI) for Senior Rehabilitation and IDA / 52800 Prior Consultant Open 0.00 124,044.93 Canceled Environmental Specialist Improvement of Polders Selection (SES) under PMU , CEIP-1, BWDB, Dhaka; Contract Package No. CEIP-1/D1/S10 No: WDB/CEIP/S-9/461 dated 02-11-2014 / Fresh Request for Expressions of Individual Rehabilitation and Interest (EOI) for Financial IDA / 52800 Prior Consultant Open 0.00 117,573.02 Signed Improvement of Polders Management Specialist Selection (FMS) under PMU,CEIP-1, BWDB, Dhaka, Bangladesh CEIP=1/D1/S21 / Individual CEIP=1/D1/S21: Rehabilitation and IDA / 52800 Prior Consultant Open 164,470.00 160,400.95 Signed Environment, Water Improvement of Polders Selection Management and Polder Expert Project Management, CEIP-1/D1/S6 / Individual Technical Assistance, International Technical IDA / 52800 Prior Consultant Open 1,104,590.00 0.00 Canceled 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2018-03-31 Training and Strategic Expert (Panel) Selection Studies CEIP-1/D1/S17 / Independent Panel of Expert (IPoE) for Project Management, Coastal, Estuarine and River Individual Technical Assistance, Morphology & IDA / 52800 Prior Consultant Open 181,600.00 0.00 Canceled 2017-08-14 2017-10-26 2017-11-22 2017-12-31 2020-06-30 Training and Strategic Sediment/ Tidal River Selection Studies Management Expert Under PMU, CEIP-1, BWDB, Dhaka, Bangladesh Page 4 CEIP-1/D1/S18 / Procurement of Independent Project Management, Panel of Expert (IPoE) For Individual Technical Assistance, Hydrodynamic and Coastal IDA / 52800 Prior Consultant Open 181,600.00 0.00 Canceled 2017-08-15 2017-10-26 2017-11-22 2017-12-31 2020-06-30 Training and Strategic Modelling Expert Selection Studies Under PMU, CEIP-1, BWDB, Dhaka, Bangladesh CEIP-1/D1/S19 / Procurement of Independent Panel of Expert (IPoE) For Project Management, Individual Design Expert in Technical Assistance, IDA / 52800 Prior Consultant Open 165,000.00 0.00 Canceled 2017-08-15 2017-10-26 2017-11-22 2017-12-31 2020-06-30 Embankment and Hydraulic Training and Strategic Selection Structures Studies Under PMU, CEIP-1, BWDB, Dhaka, Bangladesh Project Management, CEIP-1/D1/S11 / Individual Individual Technical Assistance, Under Consultant as Sr. Social IDA / 52800 Prior Consultant Open 212,000.00 0.00 2017-11-03 2017-11-03 2017-11-03 2017-11-03 2019-08-01 Training and Strategic Implementation Specialist (PMU/Dhaka) Selection Studies Project Management, CEIP-1/D1/S20 / Individual Technical Assistance, Independent Panel of Expert IDA / 52800 Post Consultant Limited 154,617.48 119,620.73 Signed 2017-07-16 2017-07-16 2017-07-16 2017-08-14 2020-06-30 Training and Strategic (IPoE) for Social Expert Selection Studies CEIP-1/D1/S15 / Individual Project Management, Individual Consultant as Social Technical Assistance, IDA / 52800 Post Consultant Open 217,875.71 55,968.68 Signed 2017-07-17 2017-07-17 2017-07-17 2017-08-14 2019-07-19 Specialist / Economist Training and Strategic Selection (PMU/Field) Studies Project Management, CEIP-1/D1/S5 / Individual Technical Assistance, International Technical IDA / 52800 Prior Consultant Open 1,104,590.00 0.00 Canceled 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-07-30 Training and Strategic Expert (Panel) Selection Studies CEIP-1/D1/S14-A / Project Management, Individual Individual Consultant as Technical Assistance, IDA / 52800 Post Consultant Direct 131,000.00 61,538.46 Completed 2017-11-03 2017-11-03 2017-11-03 2017-11-15 2018-06-22 Senior Revenue Officer Training and Strategic Selection (PMU/Dhaka) Studies CEIP-1/D1/S9 / Procurement Project Management, Individual of Individual Consultant as Technical Assistance, IDA / 52800 Prior Consultant Open 247,000.00 98,565.48 Signed 2018-01-06 2018-01-06 2018-01-06 2018-01-06 2019-10-23 Financial Management Training and Strategic Selection Specialist (National) Studies Project Management, CEIP-1/D1/S8-A / Individual Individual Technical Assistance, Consultant as Procurement IDA / 52800 Post Consultant Direct 63,928.00 52,118.80 Signed 2018-01-30 2018-01-30 2018-01-30 2018-01-30 2018-01-30 Training and Strategic Specialist PMU (National) Selection Studies Project Management, CEIP-1/D1/S8-B / Individual Individual Technical Assistance, Consultant as Procurement IDA / 52800 Post Consultant Direct 50,390.00 49,495.30 Signed 2018-01-31 2018-01-31 2018-02-21 2018-03-11 2018-10-31 Training and Strategic Specialist PMU (National) Selection Studies Project Management, CEIP-1/D1/S8 / Individual Individual Technical Assistance, Consultant as Procurement IDA / 52800 Prior Consultant Open 384,295.00 0.00 Canceled 2017-07-30 2017-07-30 2017-07-30 2017-07-30 2017-10-31 Training and Strategic Specialist PMU (National) Selection Studies CEIP-1/D1/S13 / Individual Project Management, Individual Consultant as Technical Assistance, IDA / 52800 Post Consultant Limited 97,561.00 89,864.99 Completed 2018-04-19 2018-04-19 2018-04-19 2018-05-10 2020-05-09 Communication officer Training and Strategic Selection (PMU/Dhaka) Studies Page 5 CEIP-1/D1/S14-B / Project Management, Individual Individual Consultant as Technical Assistance, IDA / 52800 Post Consultant Direct 68,480.00 92,258.58 Signed 2018-06-05 2018-07-19 2018-07-19 2018-07-30 2020-06-30 Senior Revenue Specialist Training and Strategic Selection (PMU/Dhaka) Studies CEIP-1/D1/S10-A / Project Management, Individual Individual Consultant as Technical Assistance, IDA / 52800 Post Consultant Direct 79,520.00 0.00 Canceled 2018-06-06 2018-07-19 2018-07-19 2018-07-30 2020-06-30 Senior Environment Training and Strategic Selection Specialist (PMU/Dhaka) Studies Project Management, CEIP-1/D1/S12 / Individual Individual Technical Assistance, Consultant as Sr. Forestry IDA / 52800 Post Consultant Open 212,000.00 115,740.62 Signed 2017-11-03 2017-11-03 2017-11-03 2017-11-03 2020-06-30 Training and Strategic Specialist (PMU/Dhaka) Selection Studies CEIP-1/D1/S-17 / Independent Panel of Expert(IPoE) for Coastal, Project Management, Individual Estuarine and River Technical Assistance, Under IDA / 52800 Post Consultant Open 181,600.00 0.00 2018-08-13 2018-09-20 2018-10-11 2018-11-15 2020-06-30 Morphology & Sediment/ Training and Strategic Implementation Selection Tidal River Management Studies Expert under PMU, CEIP-1, BWDB, Dhaka, Bangladesh CEIP-1/D1/S-18 / Procurement of Independent Project Management, Panel of Expert ( IPoE ) Individual Technical Assistance, Under For Hydrodynamic and IDA / 52800 Post Consultant Open 181,600.00 0.00 2018-08-13 2018-09-20 2018-10-11 2018-11-15 2020-06-30 Training and Strategic Implementation Coastal Modelling Expert Selection Studies Under PMU, CEIP-1, BWDB, Dhaka CEIP-1/D1/S-19 / Procurement of Independent Project Management, Panel Expert ( IPoE ) For Individual Technical Assistance, Under Design Expert in IDA / 52800 Post Consultant Open 165,000.00 0.00 2018-08-13 2018-09-20 2018-10-11 2018-11-15 2020-06-30 Training and Strategic Implementation Embankment and Hydraulic Selection Studies Structures Under PMU, CEIP-1, BWDB, Dhaka Project Management, CEIP-1/D1/S16 / Individual Individual Technical Assistance, Consultant as Environment IDA / 52800 Post Consultant Limited 131,000.00 46,331.57 Signed 2018-08-14 2018-08-14 2018-08-14 2018-08-14 2020-06-30 Training and Strategic Specialist (PMU/Field) Selection Studies CEIP-1/D1/S10A / Project Management, Individual Individual Consultant as Sr. Technical Assistance, IDA / 52800 Post Consultant Open 105,000.00 55,068.48 Signed 2018-11-08 2018-12-29 2019-01-16 2019-02-01 2020-06-30 Environment Specialist Training and Strategic Selection (PMU/Dhaka) Studies Project Management, CEIP-1/D1/S8-C / Individual Individual Technical Assistance, Consultant as Procurement IDA / 52800 Post Consultant Direct 91,463.00 80,119.14 Signed 2019-01-17 2019-01-17 2019-01-17 2019-01-17 2020-06-30 Training and Strategic Specialist PMU ( National) Selection Studies CEIP-1/D1/S11-A / Project Management, Individual Consultant as Sr. Technical Assistance, IDA / 52800 Post Direct Selection Direct 41,000.00 30,476.03 Signed 2019-07-03 2019-07-22 2019-08-11 2020-06-30 Social Specialist Training and Strategic (PMU/Dhaka) Studies CEIP-1/D1/S9-A / Individual Project Management, Consultant as Financial Technical Assistance, IDA / 52800 Post Direct Selection Direct 45,000.00 0.00 Canceled 2019-08-18 2019-09-12 2019-10-17 2020-06-30 Management Specialist ( Training and Strategic PMU/Dhaka) Studies CEIP-1/D1/S9A / Individual Project Management, Individual Consultant as Financial Technical Assistance, Pending IDA / 52800 Post Consultant Limited 45,000.00 0.00 2019-10-29 2019-11-17 2019-11-28 2019-12-15 2020-06-30 Management Specialist ( Training and Strategic Implementation Selection PMU/ Dhaka) Studies Page 6