Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: February 11, 2010]: Revision of Updated Procurement Plan, February 2017 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: 18 months after effectiveness II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P106975 08/25/2014 issued by PEEDU 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary of the ICB (Works) Summary 65 11 No Prior of the ICB (Goods) Summary 4.7 1 No Post of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Packages Review Comments July 9, 2010 Description Estimate by Bank of d (Prior / Assignment Cost Post) US$ million Summary 2.4 3 Prior of number of contracts that will be let under QCBS Summary 0. 3 3 Post CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Congo, Republic of : Rep. of Congo - Water, Electricity & Urban Development SIL (LEN) PLAN General Information Country: Congo, Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-07-27 2021-01-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P106975 GPN Date: Project Name: Rep. of Congo - Water, Electricity & Urban Development SIL (LEN) Loan / Credit No: IBRD / 84450, IDA / 55410, IDA / 47010 CG-Water, Electricity and Urban Developement Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-33-T-SED / REPARATION DES DEGATS Passation de Urban Infrastructure and 2019-07- 2018- ENVIRONNEMENTAUX SUR LA IDA / 47010 A posteriori marché de gré à Direct 142,375.79 Achevé 2018-12-05 2017-01-18 2018-12-10 2017-09-15 2019-01-14 2017-09-15 Services 13 05-08 PROPRIETE DE LA FAMILLE gré BOLAMIGNELE GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-001-F-AOI-17 / Fournitures 50 postes et lignes - Fournitures et Electricity Sector Reform, construction de 50 postes de Single Stage - One IBRD / 84450 Commercial and Electricity A priori Appel d'offres Open - International 0.00 Annulé 2017-10-19 2018-03-13 2017-10-24 2017-12-05 2018-01-04 2018-02-08 2019-02-08 transformation électriques Envelope Supply Systems Upgrade. MT/BT et lignes MT associées du réseau électrique à BZV et PNR (2 lots) CG-PEEDU-007-F-AOI / Réhabilitation 40 postes- Electricity Sector Reform, Single Stage - One Fournitures réhabilitation de IBRD / 84450 Commercial and Electricity A priori Appel d'offres Open - International 11,187,608.93 Signé 2017-02-09 2017-02-14 2017-03-28 2017-08-10 2018-01-31 2017-12-29 2017-12-13 2018-11-24 Envelope 40 postes et lignes MT/BT Bzv Supply Systems Upgrade. et Pnr CG-PEEDU-22-F-AON / Acquisition d'un véhicule Electricity Sector Reform, laboratoire et de deux valises Single Stage - One IBRD / 84450 Commercial and Electricity A posteriori Appel d'offres Open - National 0.00 Annulé 2018-04-26 2018-05-31 2018-05-01 2018-06-06 2018-06-12 2018-07-12 2018-08-16 2019-02-12 de détection des défauts pour Envelope Supply Systems Upgrade. la société nationale d'électricité (SNE) CG-PEEDU-23-F-AON / Acquisition des équipements médicaux des centres de Urban Infrastructure and Single Stage - One IDA / 47010 A posteriori Appel d'offres Open - National 274,706.17 Achevé 2018-05-07 2018-05-29 2018-05-12 2018-06-06 2018-06-23 2018-07-11 2018-07-23 2018-08-05 2018-08-27 2018-09-19 2019-02-23 2018-12-04 santé intégrés (Indzouli à Services Envelope Brazzaville, Siafoumou et Saint Joseph à Pointe-Noire) CG-PEEDU-026-F-AOI / FOURNITURE ET TRAVAUX DE CONSTRUCTION DE 20 Electricity Sector Reform, Single Stage - One NOUVEAUX POSTES DE IBRD / 84450 Commercial and Electricity A priori Appel d'offres Open - International 5,056,039.10 Achevé 2018-05-15 2018-07-07 2018-05-20 2018-07-18 2018-07-01 2018-09-25 2018-07-31 2018-12-14 2018-09-04 2019-01-22 2019-09-04 2020-09-01 Envelope TRANSFORMATION Supply Systems Upgrade. ÉLECTRIQUE MT/BT ET LIGNES A BRAZZAVILLE CG-PEEDU-029-F-AOI / Spéc ifications techniques : Ø Véhicule la localisation de défauts sur câbles MT/BT sout errains Electricity Sector Reform, Ø 2 valises la localisation de Single Stage - One IBRD / 84450 Commercial and Electricity A posteriori Demande de prix Limited 522,838.32 Achevé 2018-07-29 2018-08-31 2018-09-23 2018-12-24 2019-03-22 2019-11-22 défauts sur câbles MT/BT sout Envelope Supply Systems Upgrade. errains - Camions laboratoire de re cherche de défaut électrique - Accessibles à tous endroit s. Electricity Sector Reform, Passation de CG-PEEDU-31-F-SED / MISE IBRD / 84450 Commercial and Electricity A posteriori marché de gré à Direct 13,432.06 Achevé 2018-09-13 2018-08-07 2018-09-18 2018-08-13 2018-10-23 2018-10-30 2019-04-21 2018-11-12 A JOUR TOM2 PRO VERSION 2 Supply Systems Upgrade. gré CG-PEEDU-34-T-SED / ENTENTE DIRECTE AVEC LE BCBTP POUR LES TRAVAUX DE GENIE CIVIL EQUIPEMENT Passation de HYDROMECANIQUE ET IDA / 47010 Urban Water Supply A posteriori marché de gré à Direct 765,749.03 Achevé 2019-02-08 2019-02-22 2019-02-13 2019-03-01 2019-03-20 2019-05-11 2019-09-16 2020-09-21 ELECTRIQUE DES FORAGES FP1 gré TCHIMAGNI ET FP2 KM8 LOUSSALA POUR LA SNDE A POINTE-NOIRE CG-PEEDU-41-F-ED / acquisition du matériel de réserve pour le Electricity Sector Reform, Passation de fonctionnement des 9 feeders IBRD / 84450 Commercial and Electricity A posteriori marché de gré à Direct 505,157.41 Achevé 2020-01-30 2020-01-31 2020-02-04 2020-02-06 2020-03-10 2020-03-19 2020-09-06 2020-10-24 souterrains 20 KV construits à Supply Systems Upgrade. gré Pointe Noire au titre du PEEDU à partir du poste source MGK1 CG-PEEDU-177654-GO-RFQ Electricity Sector Reform, / Acquisition de cent (100) Single Stage - One IBRD / 84450 Commercial and Electricity A posteriori Demande de prix Limited 53,669.38 Achevé 2020-06-17 2020-06-23 2020-08-12 2020-07-17 2021-02-08 2020-07-17 tablettes au profit de La Envelope Supply Systems Upgrade. Congolaise Des Eaux (LCDE) CG-PEEDU-178188-GO-DIR Passation de Urban Infrastructure and / Fourniture des plans IBRD / 84450 A posteriori marché de gré à Direct 157,081.11 Résilié 2020-06-16 2020-06-18 2020-06-21 2020-06-19 2020-07-26 2020-06-30 2021-01-22 Services cadastraux au profit de LCDE gré Page 1 CG-PEEDU-186301-GO-RFQ Single Stage - One / Acquisition du mobilier de IBRD / 84450 Urban Water Supply A posteriori Demande de prix Limited 0.00 Annulé 2020-08-15 2020-08-18 2020-10-10 2021-04-08 Envelope bureau (Appui à l'ORSE) CG-PEEDU-186304-GO-RFQ Single Stage - One / Acquisition du matériel IBRD / 84450 Urban Water Supply A posteriori Demande de prix Limited 40,693.76 Achevé 2020-08-15 2020-08-18 2020-10-10 2020-09-21 2021-04-08 2020-09-30 Envelope informatique (Appui à l'ORSE) CG-PEEDU-212484-CW-DIR / Marché par Entente directe avec le groupement MBTP- CELEC pour l'achèvement du Electricity Sector Reform, Passation de marché des fournitures et En attente IDA / 55410 Commercial and Electricity A priori marché de gré à Direct 0.00 2021-01-26 2021-01-31 2021-03-07 2021-09-03 travaux de réhabilitation des d'exécution Supply Systems Upgrade. gré 25 postes de transformation électrique et lignes MT/BT et réseaux BT associés à Brazzaville CG-PEEDU-212491-CW-DIR / Marché par Entente directe avec le groupement MBTP- CELEC pour l'achèvement des Electricity Sector Reform, Passation de En attente fournitures et travaux de IDA / 55410 Commercial and Electricity A priori marché de gré à Direct 0.00 2021-01-26 2021-01-31 2021-03-07 2021-09-03 d'exécution réhabilitation des 15 postes Supply Systems Upgrade. gré de transformation électrique MT/BT et réseaux BT associés à Pointe Noire NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-003 BIS-C-SFQC / Supervision 16 feeders et 40 postes - Firme pour contrôle Electricity Sector Reform, Sélection fondée et supervision des fournitures IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 1,318,640.75 Signé 2015-04-11 2015-11-26 2016-07-26 2017-05-03 2017-05-25 2017-06-19 2017-11-11 2017-07-19 2017-07-19 2018-12-11 et travaux de construction de Supply Systems Upgrade. coût 16 feeders souterrains et Réhabilitation de 40 postes et lignes MT-BT à BZV et PNR CG-PEEDU-008 BIS-C-QC / Sélection fondée Electricity Sector Reform, Enquête Satisfaction SNE - sur les IBRD / 84450 Commercial and Electricity A posteriori Open - International 165,909.46 Achevé 2017-05-04 2017-05-17 2017-07-17 2017-08-28 2017-09-06 2017-09-08 2017-09-08 2017-09-08 2017-12-07 2018-01-18 Enquête de satisfaction de qualifications des Supply Systems Upgrade. base de la clientèle SNE consultants CG-PEEDU-29275-CS-CQS / Réalisation d'une notice Sélection fondée d'impact environnemental et Urban Infrastructure and sur les IBRD / 84450 A priori Open - International 204,477.74 Achevé 2017-02-23 2017-03-16 2017-04-29 2017-05-29 2017-11-11 2017-07-03 2017-04-07 2017-12-30 2017-09-01 social (NIES) pour la Services qualifications des construction de 7 feeders à consultants Brazzaville CG-PEEDU-003-C-SFQC-17 / Supervision 16 feeders et 40 postes - Firme pour contrôle Electricity Sector Reform, Sélection fondée et supervision des fournitures IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 0.00 Annulé 2017-07-26 2017-08-16 2017-09-29 2017-10-27 2017-05-03 2017-11-26 2017-12-31 2018-02-04 2019-02-04 et travaux de construction de Supply Systems Upgrade. coût 16 feeders souterrains et Réhabilitation de 40 postes et lignes MT-BT à BZV et PNR CG-PEEDU-008-C-QC / Sélection fondée Electricity Sector Reform, Enquête Satisfaction SNE - sur les IBRD / 84450 Commercial and Electricity A posteriori Open - International 0.00 Annulé 2017-05-04 2017-07-12 2017-09-04 2017-10-04 2017-11-09 2018-05-08 Enquête de satisfaction de qualifications des Supply Systems Upgrade. base de la clientèle SNE consultants CG-PEEDU-003-BIS-C-SFQC / Supervision 16 feeders et 40 postes-Supervision et Electricity Sector Reform, Sélection fondée Contrôle des fournitures et IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 0.00 Annulé 2015-12-17 2016-01-16 2016-08-13 2016-12-11 2017-06-07 2017-07-12 2017-08-16 2018-08-16 construction de 16 feeders Supply Systems Upgrade. coût etvréhabilitation de 40 postes et lignes MB/BT à BZV et PNR CG-PEEDU-002-C-SFQC-17 / supervision 50 postes et lignes - Contrôle et Electricity Sector Reform, Sélection fondée supervision des travaux de IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 0.00 Annulé 2017-10-27 2018-01-11 2017-11-17 2018-01-31 2017-12-31 2018-03-29 2018-01-28 2018-02-27 2018-04-03 2018-05-08 2019-06-07 50 postes de transformation Supply Systems Upgrade. coût électriques MT/BT et lignes MT associées du réseau électrique à BZV et PNR CG-PEEDU-016-C-QC-18 / Notice d'impact Sélection fondée Electricity Sector Reform, environnemental et social sur les IBRD / 84450 Commercial and Electricity A posteriori Open - International 0.00 Annulé 2014-12-31 2015-12-31 2016-12-23 2017-02-15 2017-04-07 2017-10-04 (NIES) pour la construction de qualifications des Supply Systems Upgrade. neuf feeders souterrains 20 consultants kV à Pointe Noire CG-PEEDU-004-C-SFQC / Assistance comptable SNDE - Sélection fondée Assistance technique IBRD / 84450 Urban Water Supply A posteriori sur la qualité et le Open - International 0.00 Annulé 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-24 financière et comptable coût auprès de la SNDE CG-PEEDU-005-C-SMC / Sélection au Patrimoine SNDE - Audit du IBRD / 84450 Urban Water Supply A priori Open - International 0.00 Annulé 2017-04-21 2017-09-12 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2018-08-09 moindre coût patrimoine de la SNDE Page 2 CG-PEEDU-006-C-SMC / Electricity Sector Reform, Sélection au Patrimoine SNE-Audit du IBRD / 84450 Commercial and Electricity A priori Open - International 0.00 Annulé 2017-04-21 2017-09-14 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2018-08-09 moindre coût patrimoine de la SNE Supply Systems Upgrade. CG-PEEDU-20-CS-SFQC / Inventaire physique des immobilisations et Sélection fondée présentation d'une situation IBRD / 84450 Urban Water Supply A priori sur la qualité et le Open - International 534,095.10 Signé 2018-03-28 2018-04-16 2018-04-18 2018-04-24 2018-06-01 2018-08-20 2018-06-29 2018-10-25 2018-07-29 2018-11-12 2018-09-02 2019-01-21 2018-10-07 2019-01-22 2019-10-07 bilancielle auditée et corrigée coût de la SNDE au 31 décembre 2017 CG-PEEDU-21-CS-SFQC / Inventaire physique des immobilisations et Electricity Sector Reform, Sélection fondée présentation d'une situation IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 437,610.60 Signé 2018-03-28 2018-04-05 2018-04-18 2018-04-12 2018-06-01 2018-08-20 2018-06-29 2018-09-28 2018-07-29 2018-11-12 2018-09-02 2019-01-21 2018-10-07 2019-01-22 2019-10-07 bilancielle auditée et corrigée Supply Systems Upgrade. coût de la SNE au 31 décembre 2017 CG-PEEDU-24-CS-SFQC / Elaboration du fichier des Sélection fondée abonnés de la société IBRD / 84450 Urban Water Supply A priori sur la qualité et le Open - International 1,131,306.93 Signé 2018-05-10 2018-06-12 2018-05-31 2018-06-21 2018-07-14 2018-11-12 2018-08-11 2019-01-11 2018-09-10 2019-04-26 2018-10-15 2019-06-25 2018-11-19 2019-07-15 2019-11-19 nationale de distribution d'eau coût (SNDE) CG-PEEDU-027-C-SFQC / CONTRÔLE ET SUPERVISION DES FOURNITURES ET Electricity Sector Reform, Sélection fondée TRAVAUX DE CONSTRUCTION IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 387,062.12 Signé 2018-05-15 2018-05-31 2018-06-05 2018-07-19 2018-06-08 2018-08-16 2018-07-18 2018-09-15 2018-08-17 2018-10-20 2018-09-20 2018-11-24 2018-10-15 2019-12-24 DE 20 NOUVEAUX POSTES DE Supply Systems Upgrade. coût TRANSFORMATION ÉLECTRIQUE MT/BT ET LIGNES A BRAZZAVILLE CG-PEEDU-30-CS-SFQC / ELABORATION DU MODELE Sélection fondée ECONOMIQUE ET FINANCIER IBRD / 84450 Urban Water Supply A posteriori sur la qualité et le Open - International 128,556.90 Signé 2018-09-17 2018-09-14 2018-10-08 2018-09-18 2018-11-21 2018-11-23 2018-12-19 2019-01-04 2019-01-18 2019-02-08 2019-02-22 2019-03-12 2019-03-29 2019-04-22 2020-03-28 DU SECTEUR DE L coût HYDRAULIQUE URBAINE CG-PEEDU-32-CS-SFQC / Electricity Sector Reform, Sélection fondée APPUI A LA REFORME DU IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-27 2019-01-26 2019-03-02 2019-04-06 2020-04-05 SECTEUR DE L'ELECTRICITE AU Supply Systems Upgrade. coût CONGO CG-PEEDU-004-C-QC-17 / NIES 7 feeders Bzv - Sélection fondée Réalisation d'une notice Electricity Sector Reform, sur les d'impact environnemental et IBRD / 84450 Commercial and Electricity A priori Open - International 0.00 Annulé 2016-02-23 2016-03-15 2016-04-28 2016-05-28 2017-08-03 2017-11-01 qualifications des social (NIES) pour la Supply Systems Upgrade. consultants construction de 7 feeders à Brazzaville CG-PEEDU-35-SFQC / Recrutement d’une firme chargée du renforcement des capacités du personnel des acteurs institutionnels du Electricity Sector Reform, Sélection fondée secteur de l’électricité ( IBRD / 84450 Commercial and Electricity A priori sur la qualité et le Open - International 211,550.55 Signé 2019-07-16 2019-06-25 2019-08-06 2019-07-12 2019-09-19 2019-10-23 2019-10-17 2019-12-02 2019-11-16 2020-03-10 2019-12-21 2020-07-20 2020-01-25 2020-08-04 2021-01-24 (direction générale de Supply Systems Upgrade. coût l’Energie, agence de régulation du secteur de l’électricité, agence nationale de l’électricité ---) CG-PEEDU-36-SFQC / Recrutement d’une firme Electricity Sector Reform, Sélection fondée chargée de l’élaboration des IBRD / 84450 Commercial and Electricity A posteriori sur la qualité et le Open - International 512,666.22 Signé 2019-07-22 2019-08-09 2019-08-12 2019-08-30 2019-09-25 2019-11-06 2019-10-23 2019-12-06 2019-11-22 2019-12-30 2019-12-27 2020-02-27 2020-01-31 2020-06-03 2021-01-30 codes réseaux du système Supply Systems Upgrade. coût électrique congolais CG-PEEDU-37-QC / Recrutement d’une firme chargée de cartographie des Sélection fondée auto producteurs d’eau et sur les IBRD / 84450 Urban Water Supply A posteriori Open - International 297,280.94 Signé 2019-06-27 2019-07-11 2019-07-18 2019-07-25 2019-08-31 2019-09-27 2019-09-30 2019-12-16 2019-11-04 2020-01-15 2020-05-02 mise en place d’un système qualifications des de suivi et contrôle de leur consultants activité dans la ville de pointe noire CG-PEEDU-38-CS-SMC / 1. Recrutement d’une firme Electricity Sector Reform, Sélection fondée chargée de la realisation des IBRD / 84450 Commercial and Electricity A posteriori sur la qualité et le Open - International 25,752.45 Signé 2019-08-12 2019-09-19 2019-09-02 2019-10-15 2019-10-16 2019-12-03 2019-11-13 2020-01-07 2019-12-13 2020-01-31 2020-01-17 2020-02-27 2020-02-21 2020-03-26 2021-02-20 audits externes financiers et Supply Systems Upgrade. coût comptables, exercices 2019 et 2020 du peedu INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PEEDU-013-C-CI / Recrutement d'un assistant en Electricity Sector Reform, passation des marchés au sein IDA / 55410 Commercial and Electricity A posteriori Individuel Open 2,203.08 Achevé 2018-01-18 2018-01-23 2018-03-08 2018-03-21 2018-03-29 2018-04-01 2018-05-03 2018-04-09 2018-10-30 2019-01-02 de l'unité de coordination du Supply Systems Upgrade. PEEDU. CG-PEEDU-010-C-CI / Etude technique et dossiers d'appels d'offres pour la fourniture et Electricity Sector Reform, l'installation du programme IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 0.00 Annulé 2018-02-05 2018-01-30 2018-03-26 2018-04-16 2018-05-21 2018-11-17 de protection des revenus à la Supply Systems Upgrade. SNE, supervision et contrôle de la mise en oeuvre du PPR. CG-PEEDU-015-C-ED-18 / Prestations additionnelles à Electricity Sector Reform, Sélection de l'étude de la demande et de la IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 8,922,731.60 Signé 2015-11-10 2016-05-31 2015-11-20 2016-08-24 2016-01-24 2017-01-04 2016-07-22 tarification de l'électricité au Supply Systems Upgrade. entente directe Congo Page 3 CG-PEEDU-013-C-ED-18 / NIES 25 postes BZV- Notice d'Impact Environnemental et Electricity Sector Reform, Sélection de Social pour réhabilitation de IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 82,143.25 Achevé 2017-10-25 2017-11-02 2017-11-07 2017-11-03 2017-11-10 2017-11-10 2018-02-28 2018-06-30 25 postes et construction de Supply Systems Upgrade. entente directe 30 nouveaux postes de transformation à Brazzaville CG-PEEDU-014-C-ED-18 / PAR 25 postes-BZV- Plan d'Action et de Réinstallation Electricity Sector Reform, pour la construction de 30 IBRD / 84450 Commercial and Electricity A posteriori Individuel Direct 83,670.90 Achevé 2017-10-25 2017-11-02 2017-11-04 2017-11-03 2017-11-09 2017-11-10 2017-11-10 2017-11-10 2018-05-09 2018-04-30 postes de transformation et la Supply Systems Upgrade. réhabilitation de 25 postes à brazzaville CG-PEEDU-011-C-CI / Consultant pour l'élaboration Electricity Sector Reform, des TDR et dossiers d'appel IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 0.00 Annulé 2018-04-27 2018-06-15 2018-07-06 2018-08-10 2019-02-06 d'offres pour la mise en Supply Systems Upgrade. oeuvre des diligences pour la réforme du secteur de l'eau. CG-PEEDU-012-C-CI / Consultant pour l'élaboration des TDR et dossiers d'appel Electricity Sector Reform, d'offres pour la mise en IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 0.00 Annulé 2018-04-27 2018-06-15 2018-07-06 2018-08-10 2019-02-06 oeuvre des diligences pour la Supply Systems Upgrade. réforme du secteur de l'électricité CG-PEEDU-025-C-SED / Consultant individuel chargé d'appuyer la mise en place Electricity Sector Reform, d'un programme de IBRD / 84450 Commercial and Electricity A posteriori Individuel Direct 79,860.00 Résilié 2018-04-23 2018-05-23 2018-05-03 2018-05-29 2018-05-24 2018-06-27 2018-06-28 2018-06-30 2018-12-25 protection de revenus (PPR) au Supply Systems Upgrade. sein de la Société Nationale d'Electricité (SNE) CG-PEEDU-39-CS-INDV / Electricity Sector Reform, Cartographie des activités IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 23,584.42 Signé 2020-02-20 2020-02-04 2020-04-09 2020-04-17 2020-04-30 2020-04-28 2020-06-04 2020-06-30 2020-12-01 réalisées par le PEEDU Supply Systems Upgrade. CG-PEEDU-43-CS-IND / Electricity Sector Reform, Recrutement du consultant IBRD / 84450 Commercial and Electricity A posteriori Individuel Open 62,933.68 Signé 2020-03-10 2020-02-11 2020-04-28 2020-04-16 2020-05-19 2020-06-27 2020-06-23 2020-06-27 2020-12-20 pour élaborer le rapport Supply Systems Upgrade. d'achèvement du PEEDU CG-PEEDU-40-CS-ED / Notice d'impact Electricity Sector Reform, Sélection de environnement et social des IDA / 55410 Commercial and Electricity A posteriori consultants par Direct 60,855.32 Achevé 2020-01-20 2020-02-03 2020-01-30 2020-02-03 2020-04-04 2020-02-08 2020-10-01 2020-05-31 liaisons des 20 nouveaux Supply Systems Upgrade. entente directe postes de transformation électrique à Brazzaville CG-PEEDU-185431-CS-CDS / Entente Directe pour le renouvellement du contrat avec le consultant AFRIKA Electricity Sector Reform, Sélection de GERMAN CONSULT pour le IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 266,068.04 Signé 2020-08-03 2020-09-04 2020-08-13 2020-09-09 2020-10-17 2020-09-21 2021-04-15 contrôle et la supervision des Supply Systems Upgrade. entente directe fournitures et travaux de réhabilitation de 40 postes de transformation électrique à Brazzaville et Pointe Noire CG-PEEDU-203876-CS-CDS / Recrutement d'un consultant pour l'inventaire physique et Electricity Sector Reform, Sélection de la valorisation des ouvrages et IBRD / 84450 Commercial and Electricity A posteriori consultants par Direct 86,460.22 Signé 2020-11-11 2020-11-02 2020-11-21 2020-11-14 2021-01-25 2020-11-17 2021-07-24 installation de la centrale Supply Systems Upgrade. entente directe électrique à gaz de Djeno (CED) à Pointe Noire Page 4