PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Multisectoral Child Nutrition and Health Project - P168756 Project Implementation agency: UGP PDSS Date of the Procurement Plan: April 2019 Period covered by this Procurement Plan: April 2019 – October 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Multisectoral Nutrition and Health Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2019-05-03 2021-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168756 GPN Date: 2019-09-27 Project Name: DRC Multisectoral Nutrition and Health Project Loan / Credit No: / , IDA / 64410, IDA / D4790, IDA / V2420, IDA / V1400 R Executing Agency(ies): DC-MINISTERE DE LA SANTE PUBLIQUE WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-DRC-MSP-104597-CW- Convergence Demonstration Single Stage - One En attente 2020-05- RFQ / Construction et ou / A posteriori Demande de prix Limited 280,000.00 0.00 2019-09-21 2019-11-16 Project Envelope d'exécution 14 réhabilitation des sanitaires ZR-DRC-MSP-105617-CW- RFQ / Construction et Capacity Strengthening and Single Stage - One En attente 2020-03- réhabilitation de structures / A posteriori Demande de prix Limited 280,000.00 0.00 2019-07-20 2019-09-14 Project Management Envelope d'exécution 12 sanitaires dans les provinces d'intervention ZR-DRC-MSP-105624-CW- RFQ / Réhabilitation et Capacity Strengthening and Single Stage - One En attente 2020-01- rafraichissement des locaux / A posteriori Demande de prix Limited 150,000.00 0.00 2019-05-11 2019-07-06 Project Management Envelope d'exécution 02 du PDSS pour abriter le personnel du PMNS ZR-DRC-MSP-196590-CW- RFB / Travaux de Single Stage - One En attente 2021-10- IDA / 64410 CERC A posteriori Appel d'offres Open - National 700,000.00 0.00 2020-12-21 2020-12-26 2021-02-06 2021-03-08 2021-04-12 réhabilitation et d'extension Envelope d'exécution 09 du bâtiment du PRONANUT ZR-DRC-MSP-185062-CW- RFB / Extension/réhabilitation des locaux PDSS pour acquérir Single Stage - One En attente 2021-11- l'équipe PMNS et IDA / 64410 CERC A posteriori Appel d'offres Open - National 550,000.00 0.00 2021-01-15 2021-01-20 2021-03-03 2021-04-02 2021-05-07 Envelope d'exécution 03 Réhabilitation des locaux et du laboratoire d'analyse du PRONANUT ZR-DRC-MSP-220154-CW- RFB / Travaux de construction Single Stage - One En attente 2022-01- IDA / 64410 CERC A posteriori Appel d'offres Open - National 900,000.00 0.00 2021-03-17 2021-03-22 2021-05-03 2021-06-02 2021-07-07 des bâtiments devant abriter Envelope d'exécution 03 les bureaux du PDSS GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-105627-GO- RFQ / Acquisition de cinq (5) Capacity Strengthening and Single Stage - One / A posteriori Demande de prix Limited 250,000.00 225,244.45 Signé 2019-05-18 2020-02-13 2019-07-13 2020-05-04 2020-01-09 véhicules 4x4 pour la Project Management Envelope coordination du projet ZR-DRC-MSP-105628-GO- RFQ / Acquisition en deux lots Capacity Strengthening and Single Stage - One En attente / A posteriori Appel d'offres Open - National 750,000.00 0.00 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-05-02 des mobiliers et équipements Project Management Envelope d'exécution informatiques ZR-DRC-MSP-114486-GO- RFQ / Contractualisation avec Convergence Demonstration Single Stage - One En attente les agences spécialisées dans / A priori Demande de prix Open - National 20,000,000.00 0.00 2019-09-21 2019-11-16 2020-05-14 Project Envelope d'exécution le transfert monétaire des allocations familiales ZR-DRC-MSP-212915-GO- RFQ / Acquisition de matériels Capacity Strengthening and Single Stage - One En attente IDA / 64410 A posteriori Demande de prix Limited 100,000.00 0.00 2021-03-28 2021-05-23 2021-11-19 et équipements informatiques Project Management Envelope d'exécution pour les bureaux ZR-DRC-MSP-212918-GO- RFQ / Acquisition du matériel informatique, audiovisuel et Capacity Strengthening and Single Stage - One En attente de connexion internet pour IDA / 64410 A posteriori Demande de prix Limited 420,000.00 0.00 2021-03-21 2021-05-16 2021-11-12 Project Management Envelope d'exécution appuyer Minagri/Minpeche , PNSR, EPSP, MINAS & PRONANUT ZR-DRC-MSP-212919-GO- RFQ / Acquisition de tablettes Capacity Strengthening and Single Stage - One En attente IDA / 64410 A posteriori Demande de prix Limited 70,000.00 0.00 2021-03-22 2021-05-17 2021-11-13 et chargeurs solaires pour les Project Management Envelope d'exécution vérificateurs du FBP ZR-DRC-MSP-105647-GO- RFQ / Acquisition des Capacity Strengthening and Single Stage - One En attente matériels de connexion IDA / 64410 A posteriori Demande de prix Limited 200,000.00 0.00 2019-05-27 2019-07-22 2020-01-18 Project Management Envelope d'exécution internet en faveur du Projet (V- SAT et connexes) ZR-DRC-MSP-185114-GO- RFQ / Acquisition des Capacity Strengthening and Single Stage - One IDA / 64410 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2020-08-08 2020-10-03 2021-04-01 équipements essentiels pour Project Management Envelope le PRONANUT NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104562-CS- QCBS / Contractualisation avec une firme pour Sélection fondée Capacity Strengthening and En cours développer et mettre en / A priori sur la qualité et le Open - International 7,000,000.00 0.00 2019-08-12 2020-05-14 2019-09-02 2019-10-16 2019-11-13 2019-12-13 2020-01-17 2020-02-21 2021-02-20 Project Management d'exécution œuvre la stratégie de coût changement des comportements et le changement social ZR-DRC-MSP-104572-CS- CQS / Recrutement d'une Sélection fondée firme pour le ciblage des Convergence Demonstration sur les En attente / A posteriori Open - National 350,000.00 0.00 2019-09-09 2019-09-30 2019-11-13 2019-12-13 2020-01-17 2020-07-15 ménages vulnérables Project qualifications des d'exécution bénéficiaires des allocations consultants financières ZR-DRC-MSP-104595-CS- CQS / Contractualisation avec Sélection fondée opérateur de téléphonie Convergence Demonstration sur les En attente mobile chargé de la / A posteriori Limited 50,000.00 0.00 2019-08-05 2019-08-19 2019-09-18 2019-10-23 2020-04-20 Project qualifications des d'exécution vulgarisation des messages consultants d'alerte en langues nationales au profit des ménages ciblés ZR-DRC-MSP-104546-CS- QCBS / Contractualisation Capacity Strengthening and Sélection fondée IDA / D4790 A priori Open - International 52,000,000.00 0.00 En cours d'examen 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 avec les ONG pour appuyer la Project Management sur la qualité planification familiale ZR-DRC-MSP-104542-CS- QCBS / Recrutement d'ONG Cadres Internationales pour la Capacity Strengthening and Sélection fondée En attente IDA / D4790 A priori Open - International 150,000,000.00 0.00 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-08 2020-01-12 2021-01-11 mise en œuvre de l'approche Project Management sur la qualité d'exécution Nutrition à Assise Communautaire ZR-DRC-MSP-185072-CS- Sélection fondée CQS / Recrutement d'un Capacity Strengthening and sur les En attente consultant firme pour le IDA / 64410 A posteriori Open - National 200,000.00 0.00 2021-05-12 2021-06-02 2021-07-16 2021-08-15 2021-09-19 2022-03-18 Project Management qualifications des d'exécution diagnostic organisationnel du consultants PRONANUT ZR-DRC-MSP-197623-CS- QCBS / Recrutement d’une ONG chargée de la mise en œuvre des activités de Sélection fondée prévention et réponse aux Capacity Strengthening and IDA / D4790 A posteriori sur la qualité et le Open - National 200,000.00 0.00 Annulé 2021-01-22 2020-10-01 2021-02-12 2021-03-28 2021-04-25 2021-05-25 2021-06-29 2021-08-03 2022-08-03 Violences Basées sur le Genre Project Management coût (VBG), y compris l’exploitation et les abus sexuels (EAS) et le harcèlement sexuel (HS), dans le cadre du PMNS ZR-DRC-MSP-185113-CS- Sélection fondée CQS / Recrutement d'une sur les IDA / 64410 CERC A posteriori Open - National 45,000.00 0.00 Annulé 2020-10-02 2020-10-23 2020-12-06 2021-01-05 2021-02-09 2021-08-08 firme pour le renforcement qualifications des des capacités de PRONANUT consultants ZR-DRC-MSP-212841-CS- CQS / Recrutement d’une Sélection fondée agence chargée de la sur les En attente IDA / 64410 CERC A posteriori Open - National 150,000.00 0.00 2021-03-24 2021-04-14 2021-05-28 2021-06-27 2021-08-01 2022-01-28 communication qualifications des d'exécution institutionnelle du projet consultants (lancement, supports…) ZR-DRC-MSP-212852-CS- QCBS / Recrutement des ONG Sélection fondée En attente pour la mise en œuvre de IDA / 64410 CERC A priori sur la qualité et le Open - National 150,000,000.00 0.00 2021-02-17 2021-03-10 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 d'exécution l’approche Nutrition à Assise coût Communautaire ZR-DRC-MSP-209258-CS- CQS / Recrutement et Sélection fondée financement des ONG pour la sur les IDA / 64410 CERC A posteriori Open - National 50,000.00 0.00 Annulé 2020-12-23 2021-01-13 2021-02-26 2021-03-28 2021-05-02 2021-10-29 mise en œuvre de l'approche qualifications des nutrition à assise consultants communautaire(NAC) ZR-DRC-MSP-212860-CS- QCBS / Contractualisation Sélection fondée Capacity Strengthening and avec les ONG (Acteurs non IDA / D4790 A priori sur la qualité et le Open - National 52,000,000.00 0.00 En cours d'examen 2021-02-17 2021-03-10 2021-04-23 2021-05-21 2021-06-20 2021-07-25 2021-08-29 2022-08-29 Project Management Etatiques) pour appuyer la coût planification familiale ZR-DRC-MSP-212875-CS- QBS / Recrutement d’agences Sélection fondée En attente spécialisées dans les IDA / 64410 CERC A priori Open - National 20,000,000.00 0.00 2021-03-29 2021-04-19 2021-06-02 2021-06-30 2021-07-30 2021-08-29 2021-10-03 2022-10-03 sur la qualité d'exécution transferts de monétaires (Cash Transfert) ZR-DRC-MSP-185059-CS- Sélection fondée QCBS / Recrutement d'un Capacity Strengthening and IDA / 64410 A posteriori sur la qualité et le Open - National 60,000.00 0.00 Annulé 2020-10-26 2020-11-16 2020-12-30 2021-01-27 2021-02-26 2021-04-02 2021-05-07 2022-05-07 cabinet pour l'audit externe Project Management coût du projet PMNS ZR-DRC-MSP-204745-CS- QCBS / Recrutement d'une ONG chargée de la mise en œuvre des activités de Sélection fondée prévention et réponse aux Capacity Strengthening and IDA / D4790 A priori sur la qualité et le Open - National 4,000,000.00 0.00 Annulé 2020-12-21 2021-01-11 2021-02-24 2021-03-24 2021-04-23 2021-05-28 2021-07-02 2022-07-02 Violences Basées sur le Genre Project Management coût (VBG), y compris l'exploitation et les abus sexuels (EAS) et le harcèlement sexuel (HS), dans le cadre de la mise en œuvre Page 2 ZR-DRC-MSP-196582-CS- CQS / Recrutement d'un Sélection fondée consultant chargé des études, Capacity Strengthening and sur les contrôles et surveillances des IDA / 64410 A posteriori Open - National 100,000.00 0.00 Annulé 2020-10-12 2020-10-01 2020-11-02 2020-12-16 2021-01-15 2021-02-19 2021-08-18 Project Management qualifications des travaux de réhabilitation et consultants extension du bâtiment du PRONANUT ZR-DRC-MSP-212823-CS- Sélection fondée CQS / Contractualisation avec sur les En attente une firme pour le IDA / 64410 CERC A posteriori Open - National 45,000.00 0.00 2021-04-06 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 qualifications des d'exécution renforcement des capacités consultants du PRONANUT ZR-DRC-MSP-212871-CS- CQS / Recrutement d'une ONG chargée de la mise en ŒUVRE des activités de prevention et Sélection fondée reponse aux violences basées Capacity Strengthening and sur les En attente IDA / D4790 A priori Open - National 536,000.00 0.00 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 sur le genre(VBG), y compris Project Management qualifications des d'exécution l'exploitation et les abus consultants sexuels (EAS) et le harcelement sexuel dans le cadre du PMNS INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-DRC-MSP-104560-CS- CDS / Contractualisation avec Sélection de Convergence Demonstration En cours Harvest Plus pour la / A priori consultants par Direct 12,000,000.00 0.00 2019-07-15 2020-05-05 2019-07-25 2019-09-28 2020-03-26 Project d'exécution production de semences bio entente directe fortifiées ZR-DRC-MSP-104569-CS- Sélection de CDS / Contractualisation avec Capacity Strengthening and En cours / A priori consultants par Direct 4,000,000.00 0.00 2019-08-28 2020-11-24 2019-09-07 2019-11-11 2020-05-09 l'UNICEF pour l'appui Project Management d'exécution entente directe technique et logistique ZR-DRC-MSP-104592-CS- Sélection de CDS / Contractualisation avec Convergence Demonstration En attente / A posteriori consultants par Direct 100,000.00 0.00 2019-08-20 2019-08-30 2019-11-03 2020-05-01 SENASEM pour la production Project d'exécution entente directe de semences bio fortifiées ZR-DRC-MSP-104593-CS- INDV / Recrutement d'un consultant individuel pour les Capacity Strengthening and En attente études de faisabilité et de / A posteriori Individuel Limited 50,000.00 0.00 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Project Management d'exécution conception des infrastructures d'eau hygiène et assainissement ZR-DRC-MSP-105637-CS- INDV / Recrutement d'un Capacity Strengthening and En cours / A priori Individuel Open 216,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-05-22 2019-07-22 2019-08-16 2019-08-26 2020-02-22 Spécialiste en Passation des Project Management d'exécution Marchés ZR-DRC-MSP-105641-CS- INDV / Responsable d'un Capacity Strengthening and En cours / A priori Individuel Open 216,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 responsable suivi et Project Management d'exécution évaluation ZR-DRC-MSP-105643-CS- Capacity Strengthening and INDV / Recrutement d'un Chef IDA / 64410 A priori Individuel Open 288,000.00 156,000.00 Signé 2019-05-13 2019-09-16 2019-07-01 2020-04-16 2019-07-22 2020-10-27 2019-08-26 2020-08-26 2020-02-22 Project Management de Projet ZR-DRC-MSP-105646-CS- Capacity Strengthening and En cours INDV / Recrutement de deux / A priori Individuel Open 240,000.00 0.00 2019-05-13 2019-05-14 2019-07-01 2019-05-21 2019-07-22 2019-12-03 2019-08-26 2020-02-22 Project Management d'exécution comptables ZR-DRC-MSP-105650-CS- INDV / Recrutement d'un Improving the Delivery of En attente consultant pour faire l'état des / Community Interventions and A priori Individuel Limited 350,000.00 0.00 2019-05-23 2019-05-28 2019-06-18 2019-07-23 2020-01-19 d'exécution lieux des FOSA dans les cinq Social and Behavioral Change provinces ciblées ZR-DRC-MSP-104548-CS- CDS / Contractualisation avec Sélection de Convergence Demonstration la FAO pour la mise à / A priori consultants par Direct 14,000,000.00 0.00 En cours d'examen 2019-07-22 2020-04-30 2019-08-01 2020-08-04 2019-10-05 2020-04-02 Project disposition de kits agricoles et entente directe petits élevages ZR-DRC-MSP-159573-CS- INDV / Recrutement d'un Spécialiste en Santé Publique, Capacity Strengthening and chargé du Suivi et Evaluation, IDA / 64410 A priori Individuel Open 240,000.00 57,600.00 Signé 2020-02-17 2020-03-06 2020-04-06 2020-08-04 2020-04-27 2020-09-16 2020-06-01 2020-09-29 2020-11-28 Project Management pour le compte du Programme Multisectoriel de Nutrition et de Santé ZR-DRC-MSP-159577-CS- INDV / Recrutement d'un Spécialiste en Sauvegarde Capacity Strengthening and IDA / 64410 A priori Individuel Open 250,000.00 57,600.00 Signé 2020-02-17 2020-03-06 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-09-30 2020-11-28 Sociale, pour le compte du Project Management Projet Multisectoriel de Nutrition et de Santé ZR-DRC-MSP-159578-CS- INDV / Recrutement d'un Spécialiste en Sauvegarde Capacity Strengthening and Environnementale, pour le IDA / 64410 A priori Individuel Open 250,000.00 45,000.00 Signé 2020-02-17 2020-03-16 2020-04-06 2020-08-05 2020-04-27 2020-09-16 2020-06-01 2020-09-29 2020-11-28 Project Management compte du Programme Multisectoriel de Nutrition et de Santé ZR-DRC-MSP-179043-CS- INDV / RECRUTEMENT D´UN Capacity Strengthening and En cours SPECIALISTE VIOLENCE BASE IDA / 64410 A priori Individuel Open 228,000.00 0.00 2020-06-15 2020-07-17 2020-08-03 2020-12-23 2020-08-24 2021-01-19 2020-09-28 2021-03-27 Project Management d'exécution SUR LE GENRE AU SEIN DE DU PROJET PMNS Page 3 ZR-DRC-MSP-182812-CS- CDS / Contractualisation en entente directe avec Sélection de YOUSSOUF CISSE, consultant Capacity Strengthening and IDA / V2420 A posteriori consultants par Direct 6,000.00 5,860.00 Signé 2020-07-08 2020-07-13 2020-07-18 2020-08-06 2020-09-21 2020-08-07 2021-03-20 chargé de l'élaboration du Project Management entente directe manuel de mise en oeuvre opérationnel des activités du PMNS ZR-DRC-MSP-104563-CS- CDS / Contractualisation avec Improving the Delivery of Sélection de BLUESQUARE pour développer / Community Interventions and A priori consultants par Direct 900,000.00 0.00 Annulé 2019-08-22 2019-09-01 2019-11-05 2020-05-03 et tester un système de la Social and Behavioral Change entente directe vérification base sur les risques ZR-DRC-MSP-185078-CS- INDV / Recrutement d'un auditeur interne pour le Capacity Strengthening and En attente IDA / 64410 A priori Individuel Open 240,000.00 0.00 2020-08-27 2020-10-15 2020-11-05 2020-12-10 2021-06-08 respect des procédures des Project Management d'exécution gestions administratives et financières du PMNS ZR-DRC-MSP-196577-CS- INDV / Recrutement d'un Capacity Strengthening and En cours IDA / V1400 A priori Individuel Open 216,000.00 0.00 2020-09-30 2020-11-16 2020-11-18 2020-12-09 2021-01-13 2021-07-12 assistant technique volet Project Management d'exécution agricole en appui au PMNS ZR-DRC-MSP-185076-CS- INDV / Recrutement des trois En cours IDA / 64410 CERC A posteriori Individuel Open 151,200.00 0.00 2020-12-14 2020-12-01 2021-02-01 2021-02-22 2021-03-29 2021-09-25 (3) chauffeurs pour le compte d'exécution du PMNS ZR-DRC-MSP-197616-CS- INDV / Recrutement d'un Consultant Individuel chargé Capacity Strengthening and IDA / V2420 A posteriori Individuel Open 80,000.00 0.00 Annulé 2021-01-20 2020-10-02 2021-03-10 2021-03-31 2021-05-05 2021-11-01 de la Cartographie Générique Project Management Violence Basée sur le Genre pour PMNS ZR-DRC-MSP-105638-CS- INDV / Recrutement d'un Capacity Strengthening and / A priori Individuel Open 216,000.00 0.00 Annulé 2019-05-13 2019-05-14 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Responsable Administratif et Project Management Financier ZR-DRC-MSP-105631-CS- INDV / Recrutement d'un Capacity Strengthening and / A priori Individuel Open 216,000.00 0.00 Annulé 2019-06-17 2019-12-19 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Assistant Technique en appui Project Management au Volet agriculture ZR-DRC-MSP-212818-CS- INDV / Recrutement d' un Capacity Strengthening and En attente IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 2021-02-15 2021-04-05 2021-04-26 2021-05-31 2021-11-27 Assistant Technique en appui Project Management d'exécution au volet Education ZR-DRC-MSP-105635-CS- INDV / Recrutement d'un Capacity Strengthening and / A priori Individuel Open 216,000.00 0.00 Annulé 2019-05-13 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Assistant Technique en appui Project Management au Volet Education ZR-DRC-MSP-212819-CS- INDV / Recrutement d' un Capacity Strengthening and En attente IDA / 64410 A posteriori Individuel Open 54,000.00 0.00 2021-02-23 2021-04-13 2021-05-04 2021-06-08 2021-12-05 Assistant Technique en appui Project Management d'exécution au volet Protection Sociale ZR-DRC-MSP-105634-CS- INDV / Recrutement d'un Capacity Strengthening and / A priori Individuel Open 216,000.00 0.00 Annulé 2019-06-17 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Assistant Technique en appui Project Management au Volet protection sociale ZR-DRC-MSP-212824-CS- INDV / Recrutement d'un Consultant pour Capacity Strengthening and En attente l’identification et l'estimation IDA / 64410 A posteriori Individuel 15,000.00 0.00 2021-03-24 2021-03-29 2021-04-19 2021-05-24 2021-11-20 Project Management d'exécution des besoins d’amélioration du laboratoire d'analyse du Pronanut ZR-DRC-MSP-212829-CS- INDV / Recrutement d’un Consultant (ou groupe de consultants) pour la détermination d’un taux de Capacity Strengthening and En attente IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 2021-02-25 2021-04-15 2021-05-06 2021-06-10 2021-12-07 paiement conforme à la Project Management d'exécution situation socio-économique dans les zones ciblées pour les participants aux activités de « cash Transfer » ZR-DRC-MSP-212839-CS- Capacity Strengthening and En attente INDV / Recrutement d’un IDA / 64410 A posteriori Individuel Open 160,000.00 0.00 2021-03-17 2021-05-05 2021-05-26 2021-06-30 2021-12-27 Project Management d'exécution contrôleur de gestion ZR-DRC-MSP-212845-CS- Sélection de CDS / Contractualisation avec Convergence Demonstration En attente IDA / 64410 A priori consultants par Direct 24,000,000.00 0.00 2021-03-24 2021-04-03 2021-06-07 2021-12-04 les EUPs pour l’achat Project d'exécution entente directe stratégique ZR-DRC-MSP-212846-CS- CDS / Contractualisation avec Sélection de Capacity Strengthening and En attente une agence de contre- IDA / D4790 A priori consultants par Direct 2,000,000.00 0.00 2021-04-05 2021-04-15 2021-06-19 2021-12-16 Project Management d'exécution vérification (GINGER CREDES) entente directe de l’achat stratégique ZR-DRC-MSP-182814-CS- CDS / Contractualisation en Sélection de entente directe avec l'agence Capacity Strengthening and IDA / D4790 A priori consultants par Direct 2,000,000.00 0.00 Annulé 2020-07-13 2020-08-25 2020-07-23 2020-09-26 2021-03-25 de contre vérification externe Project Management entente directe (CREDES) pour l'achat stratégique Page 4 ZR-DRC-MSP-212849-CS- CDS / Contractualisation avec CCP/JHU pour développer et Sélection de En cours mettre en œuvre la stratégie IDA / 64410 CERC A priori consultants par Direct 10,000,000.00 0.00 2021-02-24 2021-02-23 2021-03-06 2021-05-10 2021-11-06 d'exécution de changement de entente directe comportement et de changement social ZR-DRC-MSP-197607-CS- INDV / Consultant Capacity Strengthening and En attente International chargé de IDA / V2420 A posteriori Individuel Open 50,000.00 0.00 2021-02-02 2021-03-23 2021-04-13 2021-05-18 2021-11-14 Project Management d'exécution l'élaboration du plan stratégique du PNSA ZR-DRC-MSP-212880-CS- INDV / Recrutement d'un Capacity Strengthening and En attente Consultant international pour IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 2021-03-16 2021-05-04 2021-05-25 2021-06-29 2021-12-26 Project Management d'exécution l'élaboration du plan stratégique du PNSR ZR-DRC-MSP-212883-CS- INDV / Recrutement d' un Consultant individuel pour évaluer les besoins en appui et proposer un plan de Capacity Strengthening and En attente renforcement des capacités IDA / 64410 A posteriori Individuel Open 50,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 Project Management d'exécution des Directions et Services techniques des Ministères de l’Agriculture et de Pêche et Elevage qui interviennent dans la mise en œuv ZR-DRC-MSP-212885-CS- INDV / Recrutement d' un Consultant individuel pour évaluer les besoins en appui en termes de renforcement des capacités techniques, Capacity Strengthening and En attente IDA / 64410 A posteriori Individuel Open 15,000.00 0.00 2021-03-26 2021-05-14 2021-06-04 2021-07-09 2022-01-05 opérationnelles et Project Management d'exécution managériales au CAPSA Benalongo pour contribuer efficacement dans la production et la diffusion des semences ZR-DRC-MSP-212887-CS- Improving the Delivery of En attente INDV / Recrutement d'un AT IDA / 64410 Community Interventions and A posteriori Individuel Open 54,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 d'exécution en appui au PRONANUT Social and Behavioral Change ZR-DRC-MSP-185071-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2021-01-05 2020-11-12 2021-02-23 2021-03-16 2021-04-20 2021-10-17 assistant technique en appui Social and Behavioral Change au PRONANUT ZR-DRC-MSP-212889-CS- En attente INDV / Recrutement d'une IDA / 64410 CERC A posteriori Individuel Open 30,000.00 0.00 2021-03-23 2021-05-11 2021-06-01 2021-07-06 2022-01-02 d'exécution assistante de programme ZR-DRC-MSP-212894-CS- INDV / Recrutement d'un AT En attente IDA / 64410 CERC A posteriori Individuel Open 54,000.00 0.00 2021-03-23 2021-05-11 2021-06-01 2021-07-06 2022-01-02 chargé du suivi des activités d'exécution du PMNS dans le Sud Kivu ZR-DRC-MSP-185103-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 assistant technique en appui Social and Behavioral Change au PMNS dans le KASAI ZR-DRC-MSP-185099-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 assistant technique en appui Social and Behavioral Change au PMNS dans le Kasai- Central ZR-DRC-MSP-185101-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 assistant technique en appui Social and Behavioral Change au PMNS dans le KWILU ZR-DRC-MSP-209302-CS- CDS / Contractualisation par entente directe avec Médecin d'Afrique (MEDA), pour l' Sélection de En attente Etude de base sur les IDA / 64410 CERC A posteriori consultants par Direct 210,000.00 0.00 2021-02-17 2021-02-27 2021-05-03 2021-10-30 d'exécution indicateurs nutritionnels dans entente directe les provinces d'intervention du PMNS dans le cadre de l'étude d'impact du PDSS ZR-DRC-MSP-185096-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 216,000.00 0.00 Annulé 2020-11-16 2021-01-04 2021-01-25 2021-03-01 2021-08-28 assistant technique en appui Social and Behavioral Change au PMNS dans le Sud-Kivu ZR-DRC-MSP-197611-CS- Improving the Delivery of INDV / Recrutement d'un IDA / 64410 Community Interventions and A priori Individuel Open 240,000.00 0.00 Annulé 2020-11-18 2021-01-06 2021-01-27 2021-03-03 2021-08-30 Spécialiste en Nutrition pour Social and Behavioral Change le PMNS ZR-DRC-MSP-185075-CS- INDV / Recrutement d'une IDA / 64410 CERC A posteriori Individuel Open 128,000.00 0.00 Annulé 2020-12-23 2021-02-10 2021-03-03 2021-04-07 2021-10-04 assistante de programme ZR-DRC-MSP-204735-CS- CDS / Contractualisation par entente directe avec Center for Communication Programms (CCP)/ John Sélection de HOPKINS University pour une IDA / 64410 CERC A priori consultants par Direct 2,500,000.00 0.00 Annulé 2020-11-16 2020-11-26 2021-01-30 2021-07-29 Recherche Formative et le entente directe développement de la stratégie de communication pour le changement social et comportements Page 5 ZR-DRC-MSP-217495-CS- INDV / Recrutement d'un Consultant Individuel chargé de la Réalisation des Etudes Capacity Strengthening and En attente Techniques et surveillance des IDA / 64410 A posteriori Individuel Open 100,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 Project Management d'exécution travaux de Réhabilitation, extension des Bureaux et Laboratoires du PRONANUT à Kinshasa/Gombe ZR-DRC-MSP-212834-CS- INDV / Recrutement d’un Capacity Strengthening and En attente Assistant Technique en IDA / 64410 A priori Individuel Open 360,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 Project Management d'exécution gestion financière et comptable ZR-DRC-MSP-212898-CS- Improving the Delivery of INDV / Recrutement d'un AT En attente IDA / 64410 Community Interventions and A posteriori Individuel Open 162,000.00 0.00 2021-03-30 2021-05-18 2021-06-08 2021-07-13 2022-01-09 chargé du suivi des activités d'exécution Social and Behavioral Change du PMNS dans le Kwilu ZR-DRC-MSP-212910-CS- Improving the Delivery of INDV / Recrutement d'un En attente IDA / 64410 Community Interventions and A posteriori Individuel Open 54,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 Consultant spécialiste en d'exécution Social and Behavioral Change Nutrition pour le PRONANUT ZR-DRC-MSP-212882-CS- INDV / Recrutement d'un Capacity Strengthening and En attente Consultant national pour IDA / 64410 A posteriori Individuel Open 20,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 Project Management d'exécution l'élaboration du plan strategique du PNSR ZR-DRC-MSP-212914-CS- INDV / Recrutement d'un Capacity Strengthening and En attente IDA / V1400 A priori Individuel Open 272,000.00 0.00 2021-03-31 2021-05-19 2021-06-09 2021-07-14 2022-01-10 Consultant spécialiste en Project Management d'exécution Nutrition pour le PMNS ZR-DRC-MSP-185053-CS- INDV / Recrutement d'un Capacity Strengthening and En attente consultant national pour IDA / V2420 A posteriori Individuel Open 20,000.00 0.00 2021-04-15 2021-06-03 2021-06-24 2021-07-29 2022-01-25 Project Management d'exécution l'élaboration d'un plan stratégique du PNSA ZR-DRC-MSP-212896-CS- INDV / Recrutement d'un AT En attente IDA / 64410 CERC A posteriori Individuel Open 162,000.00 0.00 2021-03-23 2021-05-11 2021-06-01 2021-07-06 2022-01-02 chargé du suivi des activités d'exécution du PMNS dans le Kasai ZR-DRC-MSP-212895-CS- INDV / Recrutement d'un AT En attente IDA / 64410 CERC A posteriori Individuel Open 162,000.00 0.00 2021-03-25 2021-05-13 2021-06-03 2021-07-08 2022-01-04 chargé du suivi des activités d'exécution du PMNS dans le Kasai Central ZR-DRC-MSP-220149-CS- CDS / Contractualisation avec Sélection de Capacity Strengthening and En attente l'UNICEF pour l'acquisition des IDA / 64410 A priori consultants par Direct 25,000,000.00 0.00 2021-03-17 2021-03-27 2021-05-31 2021-11-27 Project Management d'exécution intrants nutritionnels pour le entente directe compte du PMNS Page 6