Procurement Plan Community Development Program Support Project – Phase III (Programme National de Développement Participatif – Phase III) I. General 1. Bank’s approval Date of the procurement Plan [Original: February 2016]: Revision of Updated Procurement Plan, May 05, 2017 2. Date of General Procurement Notice: February 15, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) None 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million 5. DC (Non-Consultant Services) none 2. Prequalification. Not applicable. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Procurement (works, goods and services) for subprojects of communes, such as small infrastructure, social infrastructure, classrooms, health centers, community halls, , minor works or rehabilitation, will be procured on the basis of community participation in accordance with the clause 3.19 of the World Bank Procurement Guidelines (Community Participation in Procurement), and the Guidelines for Simplified Procurement and Disbursement for Community-Based Investments (March 3, 1998) detailed in the specific manual or guidelines to communes approved by the bank. 4. Reference to (if any) Project Operational/Procurement Manual: Guide des Acteurs intervenant dans le processus de passation et de l’exécution des marchés communaux financés par le PNDP – Juin 2010, révisé en Janvier 2016 5. Any Other Special Procurement Arrangements: 5 ICB works packages will be financed under - retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced May 05, 2017 procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of 2.328 2 No Prior the ICB (Goods) Summary of 0.700 1 No Post 1st contract for the NCB Prior Review (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 500,000 Justification prior reviewed by bank 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review by Expected Comments/ No cost (US$ method the Bank proposals completion equivalent) (prior/post) submission date date For the first 1 Support for the preparation Post year 20,000 IC 21/08/15 of Statutory Instruments 24/09/15 (30 days) 2 Study on the definition of a 40,000 Post CQS 22/04/16 planning methodology at 25/01/16 (03 months) regional level 3 Study on the planning 40,000 CQS Post 25/01/16 22/04/16 process in the communes and (03 months) urban communities May 05, 2017 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review by Expected Comments/ No cost (US$ method the Bank proposals completion equivalent) (prior/post) submission date date 4 Study for the establishment 20,000 IC Post 19/02/16 24/03/16 of local public service in (30 days) communes 5 Study on the sustainability of 40,000 CQS Post 11/04/16 18/07/16 the PNDP (03 months) 6 Evaluation of the 40,000 CQS Post 13/07/16 18/10/16 decentralization process in (03 months) Cameroon/supports to the finalization of the national strategy for decentralization 7 Selection of a consultant to 20,000 IC Post 20/11/15 30/12/15 develop the practitioner's (30 days) manual for the 31 communes 8 Municipal staff training 100,000 SSS Prior NA Service provided by the CEFAM (Convention) 9 Training of procurement 100,000 SSS Prior NA Service commissions provided by ARMP (Convention) 10 Financial Audits of the 150,000 LCS Post 10/03/15 Contract for 2 project for the first 2 years years 11 legal advice 10,000 IC Post 28/12/15 Annual contract 12 Design and development of 90,000 CQS Post 12/02/16 22/08/16 an internet portal on the (06 months) PNDP and communes 13 Translation of documents 90,000 CQS Post 11/05/16 20/08/16 (03 months) 14 Technical audit 80,000 QCBS Post 16/02/16 31/08/16 (06 months) 15 Beneficiary assessment 50,000 QCBS Post 15/11/16 22/05/17 (06 months) 16 Environmental and Social 70,000 QCBS Post 13/12/16 26/06/17 Assessment (06 months) 17 Follow-up of training Service deployment and technical SSS Prior NA provided by 70,000 assistance to Sim_ba AIMF expert software in communes (Convention) 18 IC Post 27/05/15 Annual contract (the current 10,000 contract ends June 30, Insurance advice 2015) 19 Preparation of CDPs for the QCBS Post 01/12/16 16/04/16 80,000 31 communes (06 months) May 05, 2017 May 05, 2017 PROCUREMENT Cameroon : Community Development Program Support Project-Phase III PLAN General Information Country: Cameroon Bank’s Approval Date of the Original Procurement Plan: 2017-05-30 2019-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144637 GPN Date: 2016-09-06 Project Name: Community Development Program Support Project-Phase III Loan / Credit No: IDA / 57180, IDA / D2990 Executing Agency(ies): CELLULE REGIONALE DE COORDONATION - EXTREME NORD WORKS Bid Evaluation Activity Reference No. Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD-8012-CW-RFQ / Petits travaux Single Stage - One d'aménagement des bureaux IDA / 57180 A posteriori Demande de prix Limited 4,722.91 Achevé 2017-03-10 2017-05-05 2017-06-04 Envelope (cloisonnement des bureaux, équipement étagères pour classement, etc...) à la CRC EN CM-CRC EXTREME NORD-8013-CW-RFQ / Construct et équipt d'01 bloc de 02 de sc et d'un bloc de Lt à trois comparts à l'EP de Dogba, au lycée Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 139,405.62 Signé 2017-03-25 2017-05-20 2017-09-17 de Gayack et Construction Envelope de 01 bloc de hangar de 52 pces et d'un bloc de Lt à trois comparts au marché de Papata,Commune de Mra II CM-CRC EXTREME NORD-8016-CW-RFQ / Constructde 6 forages équipés de PMH à Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 68,485.30 Signé 2017-03-25 2017-05-20 2017-08-18 Tchékéhi, Mbokouré, Envelope Magaldao Toupéo, Soukkoungo Galdima, Bourango et Bandalaré, commune de Pétté CM-CRC EXTREME NORD-8035-CW-RFQ / Construct d'un magasin de stockage à Kéné-Kéné, Single Stage - One Construct d'un bloc de 02 IDA / 57180 A posteriori Demande de prix Limited 68,573.26 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope sc équipées à l'EP de Djafgué, et Construct d'un bloc de Lt à l'EP de Djafgué commune de Pétté CM-CRC EXTREME NORD-8036-CW-RFQ / Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Balaza Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 76,928.16 Signé 2017-03-25 2017-05-20 2017-08-18 Lawane (Tchalloudi mango) Envelope et Constr d'un forage pastoral à énergie solaire équipé de 02 abreuvoirs à Kongola Saïd, Cne Maroua 3 CM-CRC EXTREME NORD-8037-CW-RFQ / Construct d'un bloc de 02 sc équipées et d'un bloc de Single Stage - One Lt à trois comparts à l'EP IDA / 57180 A posteriori Demande de prix Limited 0.00 Annulé 2017-03-25 2017-05-20 2017-08-18 Envelope de Mayel Béi, à l'EP de Bao Hosséré II et à l'EP de Palaoudi, commune Maroua 1 CM-CRC EXTREME NORD-8040-CW-RFQ / construction d'un bloc maternel à l'école Single Stage - One Maternelle de Zokok-Laddo IDA / 57180 A posteriori Demande de prix Limited 46,402.62 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope et branchement au réseau d'alimentation en eau potable, commune de Maroua 1 CM-CRC EXTREME NORD-8042-CW-RFQ / Construction de trois Single Stage - One forages équipés de pompe à IDA / 57180 A posteriori Demande de prix Limited 39,964.59 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope motricité humaine à Ouro Dow, Goni Bello et Yoldéo Guiziga, Commune Maroua 1 CM-CRC EXTREME NORD-8043-CW-RFQ / Construction de d'un bloc de 02 salles de classe Single Stage - One équipées et d'un bloc de IDA / 57180 A posteriori Demande de prix Limited 77,069.07 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope latrines à trois compartiments à l'EP Masfaï et au CES de Boula, commune de Mokolo CM-CRC EXTREME NORD-8045-CW-RFQ / Construction de 2 forages Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 30,426.64 Signé 2017-03-25 2017-05-20 2017-08-18 équipés de PMH un à Ouro Envelope Kessoum et à Mounam, commune de Mokolo CM-CRC EXTREME NORD-8047-CW-RFQ / Construction d'un ouvrage Single Stage - One de franchissement et IDA / 57180 A posteriori Demande de prix Limited 81,284.78 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope assainissement(radier-dalot) sur le Mayo Kwayaga, dans la commune de Mogodé Page 1 CM-CRC EXTREME NORD-8050-CW-RFQ / Construction d'un bloc de 02 salles de classe équipées Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 85,878.49 Signé 2017-03-25 2017-05-20 2017-08-18 et d'un bloc de latrines à Envelope trois compartiments à l'EP de Saoudjo et au CES de Madaka, commune de Bogo CM-CRC EXTREME NORD-8053-CW-RFQ / Construction d'un forage Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 28,863.63 Signé 2017-03-25 2017-05-20 2017-08-18 équipé de PMH à Dambaye Envelope et à Bagalaf commune de Bogo CM-CRC EXTREME NORD-8054-CW-RFQ / construction d'un bloc de deux (02) salles de classe equipees et un (01) bloc latrine a trois (03) Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 163,753.46 Signé 2017-03-25 2017-05-20 2017-09-17 compartiments a l'EP de Envelope honkol, a l'EP de darsala, a l'EP de dabanga et l'equipement en meubles a l'ecole maternelle de logone birni CM-CRC EXTREME NORD-8056-CW-RFQ / construction de trois forages équipés de pompe à Single Stage - One motricité humaines: un à IDA / 57180 A posteriori Demande de prix Limited 44,814.24 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope l'EP de Dabanga, un à l'EP de Honkol et un à l'EP de Darsala dans la Commune de Logone Birni CM-CRC EXTREME NORD-8057-CW-RFQ / construction d'un forage pastoral équipé de pompe Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 41,388.95 Signé 2017-03-25 2017-05-20 2017-08-18 immergée à énergie Envelope photovoltaique à Sahaba 1 dans la Commune de Logone Birni CM-CRC EXTREME NORD-8068-CW-RFQ / réhabilitation de la mare artificielle et la construction Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 91,831.58 Signé 2017-03-25 2017-05-20 2017-09-17 d'un forage pastoral à Envelope energie photovoltaique à Mogong dans la commune de Moutourwa CM-CRC EXTREME NORD-8072-CW-RFQ / construction de 2 blocs de deux salles de classe Single Stage - One équipées et de 2 blocs de IDA / 57180 A posteriori Demande de prix Limited 102,090.02 Signé 2017-03-25 2017-05-20 2017-08-18 Envelope latrines à trois compartiments EP NGré et EP Afadé dans la commune de Makary CM-CRC EXTREME NORD-38352-CW-RFB / Travaux de construction d'un forage PMH à Kaliao, Goulmoyo, Mbozo Mofou, Balewa et Manguirdla (Lot Single Stage - One 1), Gadjawai, Guivel, IDA / 57180 A posteriori Appel d'offres Open - National 200,809.46 Signé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-06-17 Envelope Quartier Méri centre, Nguissar et Kilwo-Valta (Lot 2), Moundour Foulbé, Dogba Maliki, Magawa, Houloum et Tchaki djébé (Lot 3) C-MERI CM-CRC EXTREME NORD-38353-CW-RFQ / Travaux de Construction d'un bloc de deux salles de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 36,949.06 Signé 2017-12-02 2018-01-27 2018-04-27 classe équipées et un bloc Envelope de latrines au C.E.S de Manguirdla dans la commune de Meri CM-CRC EXTREME NORD-38354-CW-RFQ / Travaux de construction d'un bloc de deux salles de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 67,277.81 Signé 2017-12-02 2018-01-27 2018-04-27 classe équipées avec Envelope latrines à l'EP de Domo Doukou et à l'EP de Riganda COMMUNE DE YAGOUA CM-CRC EXTREME NORD-38355-CW-RFQ / Travaux de construction d'un bloc de deux salles de Single Stage - One classe équipées et un bloc IDA / 57180 A posteriori Demande de prix Limited 82,938.94 Signé 2017-12-02 2018-01-27 2018-04-27 Envelope de latrines à l'EP de Pitoa- Kolara et à l'EP de Badadji COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD-38356-CW-RFQ / Travaux de construction d'un bloc de deux salles Single Stage - One équipées et un bloc de IDA / 57180 A posteriori Demande de prix Limited 79,132.86 Signé 2017-12-02 2018-01-27 2018-04-27 Envelope latrines à l'EP de Djagalaye et au CES de Hardé COMMUNE DE MAROUA Ier Page 2 CM-CRC EXTREME NORD-38357-CW-RFQ / Travaux de construction d'un bloc de deux salles équipées et un bloc de Single Stage - One latrines CES de Balda et IDA / 57180 A posteriori Demande de prix Limited 82,420.00 Signé 2017-12-02 2018-01-27 2018-04-27 Envelope Construction d'un bloc de deux salles de classe équipées à l'EP de Sedek Ouro-Gabdo COMMUNE DE BOGO CM-CRC EXTREME NORD-38358-CW-RFQ / Travaux de Construction de 01 forage PMH A EM de Ldamtsai, Mandaka Single Stage - One Mpoldok, Camp mission de IDA / 57180 A posteriori Demande de prix Limited 117,088.54 Signé 2017-12-02 2018-01-27 2018-04-27 Envelope Tourou, Koudougour II Loctcha, Katamsa Sikia, Gouldoum Moufou, Houdango Dandi et Ouro Bocki(2lots) dans la commune de Mokolo CM-CRC EXTREME NORD-38359-CW-RFQ / Travaux de construction d' Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 14,057.20 Signé 2017-12-02 2018-01-27 2018-03-28 un forage équipé de PMH Envelope à l'EP de Riganda commune YAGOUA CM-CRC EXTREME NORD-38360-CW-RFQ / Travaux de construction d'un forage équipé de PMH Single Stage - One à l'EP de Badadji, à l'EP IDA / 57180 A posteriori Demande de prix Limited 61,321.88 Signé 2017-12-02 2018-01-27 2018-04-27 Envelope de Pitoa-Kolara, au lycée de Kolara et à Gadjia Padjonré COMMUNE DE MOULVOUDAYE CM-CRC EXTREME NORD-38361-CW-RFQ / Travaux de construction d'un forage équipé de PMH Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 35,012.75 Signé 2017-12-02 2018-01-27 2018-04-27 à l'EP de Yamdjidjing, à Envelope l'EP de Djagalaye et à Zébé COMMUNE DE MAROUA Ier CM-CRC EXTREME NORD-38362-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à motricité humaine à l'EP de Sedek Ouro Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 67,323.39 Signé 2017-12-02 2018-01-27 2018-04-27 Gabdo à Ardo Foulbé Envelope Tankirou à Gagnéri Kourdaya à Guinlaye Guizigaré et Guinlaye Moufouré dans la commune BOGO CM-CRC EXTREME NORD-38386-CW-RFQ / Travaux de construction d'un bloc de deux salles de classe équipées avec latrines à l'EP de Single Stage - One IDA / 57180 A posteriori Appel d'offres Open - National 213,978.48 Signé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-06-17 Mouftoum et à l'Ecole Envelope Bilingue de Rhoumzou (Lot 1), au lycée de SIR et à l'EPB de Kwashimalda (Lot 2) , au CES de Goura (Lot 3) dans la commune de Mogode CM-CRC EXTREME NORD-38387-CW-RFB / Travaux de construction d'un bloc de deux salles équipées et un bloc de latrines à l'EP de Ldamang Single Stage - One IDA / 57180 A posteriori Appel d'offres Open - National 193,465.09 Signé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-06-17 et à l'EP de Ndrock Tourou Envelope (Lot 1), l'EP de Moufou- sud et à l'EP de Zili Yolel (Lot 2),au CES de Mandaka (Lot 3) dans la commune de MokolO CM-CRC EXTREME NORD-38388-CW-RFB / Travaux de construction Single Stage - One d'un radier de 12 ml sur IDA / 57180 A posteriori Appel d'offres Open - National 27,858.87 Signé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-06-17 Envelope le mayo Teki dans la localité de Teki, dans la commune de Mogode CM-CRC EXTREME NORD-58606-CW-RFQ / Travaux de Construct d'un bloc de 02 sc équipées et Single Stage - One IDA / 57180 A posteriori Demande de prix Open - National 73,189.11 Signé 2017-10-08 2017-12-03 2018-03-03 d'un bloc de Lt à trois Envelope comparts à l'EP de Mayel Béi, et à l'EP de Palaoudi l cmne Maroua 1 CM-CRC EXTREME NORD-58541-CW-RFQ / Travaux de construction d'un forage productif équipé Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 42,885.41 Signé 2018-05-06 2018-07-08 2018-10-06 de pompe manuelle à EP Envelope Louguéré à EP Ouro Nangué à Fakalao à Hodango CM-CRC EXTREME NORD-58600-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées et Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 67,400.34 Signé 2018-05-06 2018-07-01 2018-09-29 construction d'un bloc de Envelope latrines à trois compartiment à EP de WOUYANG et à l'EP de GONOZO Page 3 CM-CRC EXTREME NORD-58693-CW-RFQ / Travaux de Construction d'un atelier de maçonnerie Single Stage - One au CETIC de Loulou et'un IDA / 57180 A posteriori Demande de prix Limited 43,242.06 Signé 2018-05-06 2018-07-08 2018-11-05 Envelope bloc de latrines à trois compartiments au CETIC de Loulou COMMUNE DE NDOUKOULA CM-CRC EXTREME NORD-58296-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées et d'un Single Stage - One bloc de latrines à trois IDA / 57180 A posteriori Demande de prix Limited 118,724.87 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope compartiments à l'EP de GUIRIOU CENTRE, (lot 01) au Lycée de DOM PYA, à la SAR/SM de Gobo(lot02) dans la cmne de GOBO CM-CRC EXTREME NORD-58490-CW-RFQ / Travaux de construction d'un bloc de latrines a Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 18,969.07 Signé 2018-05-06 2018-07-08 2018-10-06 quatre (04) compartiments Envelope au marché de GOBO et de NOULDAINA dans la cmne de GOBO CM-CRC EXTREME NORD-58375-CW-RFQ / Travaux de construction Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 13,046.69 Signé 2018-05-06 2018-07-08 2018-08-07 d'un forage équipé de PMH Envelope à l'EP de GUIRIOU CENTRE CM-CRC EXTREME NORD-58689-CW-RFQ / Travaux de construction d'un bloc de 02 salles de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 35,806.95 Signé 2018-05-06 2018-07-08 2018-10-06 classe équipées et d'un Envelope bloc de latrines à trois compartiments au CES de Doukroye CM-CRC EXTREME NORD-58628-CW-RFQ / Travaux de construction Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 10,491.33 Signé 2018-05-06 2018-07-08 2018-10-06 d'un forage équipé de PMH Envelope à l'EP de Daloa (Doukroye) dans la cmne de KAIKAI CM-CRC EXTREME NORD-58637-CW-RFQ / Travaux d'achevement de la Construction des ouvrages annexes d'embarquement Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 15,519.74 Signé 2018-05-06 2018-07-08 2018-09-06 (quaie dembarquement et Envelope hangar d'abris)des pirogues à LOUGOUANG MASSOUANG dans la cmne de Kaikai CM-CRC EXTREME NORD-58605-CW-RFQ / Travaux de construction d'un bloc de 02 salles de Single Stage - One classe équipées et d'un IDA / 57180 A posteriori Demande de prix Limited 73,407.18 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope bloc de latrines à trois compartiments à EP de Balane au CES de Sirlawé dans la cmne de KAR-HAY CM-CRC EXTREME NORD-58552-CW-RFQ / Travaux de construction d'un forage équipé de PMH Single Stage - One à l'EP de Damdama à IDA / 57180 A posteriori Demande de prix Limited 65,668.07 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope l'EP de Gouloulou à l'EP Balane à l'EP de REY- FOULAYE à l'EP de Sadielle au CES de Sirlawe CM-CRC EXTREME NORD-58690-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées et d'un Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 73,038.97 Signé 2018-05-06 2018-07-08 2018-10-06 bloc de latrines à trois Envelope compartiments à l'EP de Bihoré à l'EP de Troké dans la, commue de Tchatibali. CM-CRC EXTREME NORD-58610-CW-RFQ / Travaux de construction Single Stage - One d'un forage équipé de PMH IDA / 57180 A posteriori Demande de prix Limited 33,727.68 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope à l'EP Saouringwa, à Kada 'a et Glonheme dans la cmne de Tchatibali CM-CRC EXTREME NORD-58611-CW-RFQ / Travaux de construction Single Stage - One d'un forage équipé de PMH IDA / 57180 A posteriori Demande de prix Limited 35,580.80 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope à Bibalé -Gambour à Goubara à Kassilé dans la commue de Kaele CM-CRC EXTREME NORD-58489-CW-RFQ / Travaux de réhabilitation de la mare de Garey Kaélé, Construction d'un forage Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 47,962.28 Signé 2018-05-06 2018-07-08 2018-10-06 pastoral à énergie solaire Envelope Garey Kaélé et construction d'un forage équipé de PMH à Kassilé dans la commue de Kaele Page 4 CM-CRC EXTREME NORD-58682-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc Single Stage - One latrines a trois IDA / 57180 A posteriori Demande de prix Limited 154,981.86 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope compartiments à l'EP de Badjafe, à l'EP de Zouana, (lot 01 )à l'EP de Tchabeyel et EP de Goudjouing (lot 02) cmne de Kaele. CM-CRC EXTREME NORD-58614-CW-RFQ / Travaux de construction d'un bloc de 02 salles de classe équipées d'un bloc de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 72,592.86 Signé 2018-05-06 2018-07-08 2018-10-06 latrines à EP Mayel - Envelope Guinadj et un bloc de 02 salles de classe équipées à l'EP de KALAF cmne de Moutourwa. CM-CRC EXTREME NORD-58527-CW-RFQ / Travaux de construction de 01 forage équipé de PMH à Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 54,374.28 Signé 2018-05-06 2018-07-08 2018-10-06 Ganaha, à EP de Dourloum Envelope à EP de KALAF et EP de Mayel-guinadji dans la cmne de moutourwa CM-CRC EXTREME NORD-58849-CW-RFQ / Single Stage - One construction d'un forage IDA / 57180 A posteriori Demande de prix Limited 30,049.09 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope équipé de PMH à EM Moskota et à l'EP GOKORO CM-CRC EXTREME NORD-58676-CW-RFQ / Travaux de Construction d'un bloc de deux salles de classe équipées et d'un bloc Single Stage - One latrines a trois IDA / 57180 A posteriori Demande de prix Limited 124,030.36 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope compartiments au CES de Mazaya à EP ZELE (Soulédé) (lot01) à EP de Doumbéré(lot02) cmne de ROUA CM-CRC EXTREME NORD-58267-CW-RFQ / Travaux de construction Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 23,886.66 Signé 2018-05-06 2018-07-08 2018-10-06 d'un forage équipé de PMH Envelope à Koulang à Mangavé cmne de MORA CM-CRC EXTREME NORD-58524-CW-RFQ / Travaux de construction de 01 magasin de stockage à Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 2,421.57 Signé 2018-05-06 2018-07-08 2018-11-05 cereale à Sera -Idoumda et Envelope un magasin de conservation d'oignon à Kourgui cmne de MORA CM-CRC EXTREME NORD-58623-CW-RFQ / Travaux de Construction d'un forage équipé de PMH Single Stage - One à l'EP GANCE au CES IDA / 57180 A posteriori Demande de prix Limited 63,149.41 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope Toltomari et Réalisation d’un forage solaire avec borne fontaine à Kolofata cmne de Kolofata CM-CRC EXTREME NORD-58445-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de Single Stage - One classe équipées s à EP IDA / 57180 A posteriori Demande de prix Limited 110,625.81 Signé 2018-05-06 2018-07-08 2018-11-05 Envelope Chéoulew, au CES de Makalingaï (lot01)à EP Tazang (lot02) cmne de Tokombere CM-CRC EXTREME NORD-58679-CW-RFQ / Travaux de Construction de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 35,355.26 Signé 2018-05-06 2018-07-08 2018-09-06 01 forage équipé de PMH à Envelope Baka-Fourwa et à Djaltar dans la cmne de Tokombere CM-CRC EXTREME NORD-59466-CW-RFQ / TRAVAUX DE REHABILILATION DU Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 81,782.22 Signé 2018-05-06 2018-07-08 2019-01-04 TRONCON HOTEL LE Envelope SAHEL-MAYO-KALIAO (0,7 KM) cmne DE MAROUA Ier CM-CRC EXTREME NORD-58513-CW-RFQ / TRAVAUX DE Single Stage - One REHABILILATION DE LA IDA / 57180 A posteriori Demande de prix Limited 74,376.67 Signé 2018-05-06 2018-07-01 2018-12-28 Envelope PISTE SOUKOUDJO- BAGRISSE-FARARE (28 KM) CM-CRC EXTREME NORD-58707-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES Single Stage - One DE CLASSE EQUIPE ET IDA / 57180 A posteriori Demande de prix Limited 45,015.45 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP KOUTOULA DANS LA CMNE DE BLANGOUA Page 5 CM-CRC EXTREME NORD-58839-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 68,084.66 Signé 2018-05-06 2018-07-08 2018-11-05 GUICHETS, 04 Envelope MAGASINS, D’UN HANGAR D’ATTENTE ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 130 m A BLANGOUA CM-CRC EXTREME NORD-58514-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Single Stage - One FORAGE EQUIPE DE IDA / 57180 A posteriori Demande de prix Limited 21,590.55 Signé 2018-05-06 2018-07-08 2018-09-06 Envelope PMH A la gare routiere de BLANGOUA ET A L'EP DE KOUTOULA DANS LA CMNE DE BLANGOUA CM-CRC EXTREME NORD-58434-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE Single Stage - One MINI AEP PASTORAL IDA / 57180 A posteriori Demande de prix Limited 36,812.80 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope EQUIPE DE DEUX ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A MAGALAKABIR, DANS LA CMNE DE DARAK CM-CRC EXTREME NORD-58286-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Single Stage - One FORAGE PASTORAL A IDA / 57180 A posteriori Demande de prix Limited 75,327.58 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope ENERGIE SOLAIRE A KARENA ET A NAGA DANS LA CMNE DE DARAK CM-CRC EXTREME NORD-58688-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES DE CLASSE EQUIPE ET D'UN BLOC DE Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 76,025.47 Signé 2018-05-06 2018-07-08 2018-10-06 LATRINES A TROIS Envelope COMPARTIMENTS A L’EP HILELLE (LOT01) ET CONSTRUCTION D'UN HANGAR AU MARCHE DE GOULFEY GANA (LOT02) cmne DE GOULFEY CM-CRC EXTREME NORD-58840-CW-RFQ / TRAVAUX D’AMENAGEMENT D’UNE GARE ROUTIERE PAR LA CONSTRUCTION DE 04 GUICHETS, 04 MAGASINS, Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 69,011.44 Signé 2018-05-06 2018-07-08 2018-11-05 D’UN HANGAR Envelope D’ATTENTE, 02 BOUTIQUES ET D’UN BLOC LATRINE AVEC UN MUR D’ENCEINTE DE 90 m A GOULFEY cmne DE GOULFEY CM-CRC EXTREME NORD-58451-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPES DE Single Stage - One POMPE A MOTRICITE IDA / 57180 A posteriori Demande de prix Limited 40,595.78 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope HUMAINE A MOUGALAM, A TAWOULWEBE, A GARE ROUTIERE ET A L'EP HILELE COMMUNE DE GOULFEY CM-CRC EXTREME NORD-58554-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 46,481.65 Signé 2018-05-06 2018-07-01 2018-09-29 DE CLASSE EQUIPE ET Envelope D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L’EP GONONI CM-CRC EXTREME NORD-58671-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGE EQUIPE DE Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 21,590.55 Signé 2018-05-06 2018-07-08 2018-10-06 POMPE A MOTRICITE Envelope HUMAINE A MAFOULSO III, A FAMARE ET A L'EP DE GONONI commune DE HILE ALIFA CM-CRC EXTREME NORD-58631-CW-RFQ / TRAVAUX DE CONSTRUCTION TRAVAUX DE CONSTRUCTION D’UNE MINI AEP PASTORAL Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 21,447.83 Signé 2018-05-06 2018-07-08 2018-10-06 EQUIPE DE DEUX Envelope ABREUVOIRS, D’UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A ABASSOUNI, A DOLE BADA cmne DE HILE ALIFA Page 6 CM-CRC EXTREME NORD-58426-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES Single Stage - One DE CLASSE EQUIPE ET IDA / 57180 A posteriori Demande de prix Limited 43,152.31 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS AU CES D'ADJAÏNE cmne DE KOUSSERI CM-CRC EXTREME NORD-58417-CW-RFQ / CONSTRUCTION D'UN FORAGE EQUIPE DE POMPE A MOTRICITE HUMAINE AU CES D'ADJAINE ET D'UNE Single Stage - One MINI AEP PASTORAL IDA / 57180 A posteriori Demande de prix Limited 82,972.82 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope EQUIPE DE DEUX ABREUVOIRS, D'UNE POMPE IMMERGEE A ENERGIE PHOTOVOLTAÏQUE A LACTA 1, ET A MASSAKI COMMUNE DE KOUSSERI CM-CRC EXTREME NORD-58510-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN FORAGES EQUIPES DE Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 40,954.43 Signé 2018-05-06 2018-07-08 2018-10-06 POMPE A MOTRICITE Envelope HUMAINE A MASSIO- GOURGOURA, A NAGA NDIGUINI, A EP MALTAM. cmne DE MAKARI CM-CRC EXTREME NORD-58677-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN Single Stage - One IDA / 57180 A posteriori Demande de prix Open - National 40,757.69 Signé 2018-05-06 2018-07-01 2018-09-29 HANGAR AVEC BLOC Envelope LATRINE AU MARCHE DE BIAMO, cmne DE MAKARI CM-CRC EXTREME NORD-58398-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX SALLES Single Stage - One DE CLASSE EQUIPE ET IDA / 57180 A posteriori Demande de prix Limited 43,675.84 Signé 2018-05-06 2018-07-08 2018-10-06 Envelope D'UN BLOC DE LATRINES A TROIS COMPARTIMENTS A L'EP DE MALTAM cmne DE MAKARI CM-CRC EXTREME NORD-58564-CW-RFQ / Travaux des MP D'INSTALLATION D'ECLAIRAGE PUBLIC (10 Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 0.00 Annulé 2018-05-06 2018-07-08 2018-09-06 KITS)AVEC ENERGIE Envelope SOLAIRE DE L'AXE MAIRIE DE HILE ALIFA- BRIGADE DE GENDARMERIE DE HILE CM-CRC EXTREME NORD-58697-CW-RFB / TRAVAUX DE CONSTRUCTION DE DEUX SALLES DE CLASSES EQUIPEES ET DE LATRINES AU CETIC DE OUZAL (LOT N°1), Single Stage - Two IDA / 57180 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-05-01 2018-05-06 2018-06-17 2018-08-30 2018-10-04 2019-02-01 CONSTRUCTION DE Envelope DEUX SALLES DE CLASSES EQUIPEES A L'EP DE KORSAMBA ET L'EP DE KARAZAWA (LOT N°2), CONSTRUCTION D'UN BLOC MATERNEL L'EM DE MOZOGO CM-CRC EXTREME NORD-58498-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe équipées à EP de Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 0.00 Annulé 2018-05-06 2018-07-08 2018-10-06 Gance et d'un bloc de Envelope latrines à trois compartiments à L'EP TOLKOMARI cmne de Kolofata CM-CRC EXTREME NORD-58260-CW-RFQ / TRAVAUX DE CONSTRUCTION D'UN BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES A EP DE Single Stage - One En attente GANCE ET D'UN BLOC IDA / 57180 A posteriori Demande de prix Limited 0.00 2018-05-06 2018-07-08 2018-10-06 Envelope d'exécution DE LATRINES A L'EP TOLKOMARI ( LOT 01) CONSTRUCTION DE DEUX BLOC DE DEUX (02) SALLES DE CLASSE EQUIPEES CES TOLkomari CM-CRC EXTREME NORD-111329-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 classe équipé et d'un bloc Envelope d'exécution de latrines au CETIC de Tchévi dans la commune de Bourha Page 7 CM-CRC EXTREME NORD-111255-CW-RFQ / Travaux de Travaux de Construction d'un forage Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 PMH au CETIC de Tchévi, Envelope d'exécution à Zouvou- yolde à DOUVA et à ZEU dans la commune de Bourha CM-CRC EXTREME NORD-111381-CW-RFQ / Travaux de Construction des caniveaux en BA à Single Stage - One En attente Bourha (axe Hamadou -ZRA- IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution Bello Hayatou) (lot 01) et à Boukoula face commissariat (lot 02) dans la Commune de Bourha CM-CRC EXTREME NORD-111363-CW-RFB / Travaux de Construction de deux (02) blocs de dix (10) boutiques au marché de HINA cote A lot (01) et Single Stage - One En attente IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-11-19 Travaux de Construction de Envelope d'exécution deux (02) blocs de dix (10) boutique et un bloc latrines vip au marché de HINA cote B lot (02), commune de HINA. CM-CRC EXTREME NORD-111379-CW-RFQ / Travaux d'extension du reseau electrique de Single Stage - One En attente IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-11-19 Dargala centre-Roufirde, Envelope d'exécution Roufirde-Gassayel, Gassayel- Guertogalwo dans la commune de Dargala CM-CRC EXTREME NORD-111386-CW-RFQ / Travaux de Construction d'un CSI équipé avec case Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 d'astreinte, un incinérateur Envelope d'exécution et un bloc de latrines au CSI Djiddeo Garre, dans la commune de Maroua 3 CM-CRC EXTREME NORD-111394-CW-RFQ / Travaux de Construction d’un forage à énergie Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 solaire avec château au Envelope d'exécution centre de santé de Djiddéo, dans la commune de Maroua 3 CM-CRC EXTREME NORD-111324-CW-RFQ / Travaux de Construction de 01 forage à PMH à Yoldé- Single Stage - One En attente Naggué, à Tchakamadjé, IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 Envelope d'exécution Yaga djibiwo, à Bakourebi (Abba wollo) Toukou mayel(Ouro-Bedem) et à MAYA ,commune de Pétté CM-CRC EXTREME NORD-111354-CW-RFQ / Travaux de Construction d'un mini adduction d'eau à Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 energie photovoltaique Envelope d'exécution pour usage agricole a fadare dans la commune de pette CM-CRC EXTREME NORD-111372-CW-RFQ / Travaux de Construction de Single Stage - One En attente 01 forage à PMH à EP IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution lobokri et à dahounga gholonguini, dans la Commune de Dziguilao CM-CRC EXTREME NORD-111360-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe équipées et d'un bloc Single Stage - One En attente de latrines à trois IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-11-19 Envelope d'exécution compartiments à EP REBEDE EP LOBOKRI, (lot1) EP MBITOU et CES SOUEYE (lot2) dans la Commune de Dziguilao CM-CRC EXTREME NORD-111319-CW-RFQ / Travaux de Construction d'un bloc de deux salles de Single Stage - One En attente classe équipées et d'un bloc IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution latrine à trois compartiments à l'EP de Ligazang, commune de Mindif CM-CRC EXTREME NORD-111254-CW-RFQ / Travaux de Construction et équipement d'un centre de Single Stage - One En attente santé intégré avec IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 Envelope d'exécution incinerateur et un bloc de latrines à trois compartiments à MATFAI, dans la commune de Mindif CM-CRC EXTREME NORD-111382-CW-RFQ / Travaux de Construction Single Stage - One En attente d'un forage pastoral a IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution energie photovoltaique au marché à bétail à Moulvoudaye Page 8 CM-CRC EXTREME NORD-111373-CW-RFB / Travaux d'aménagement du marché à bétail en contruisant un parc à betail Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 une cloture un quai Envelope d'exécution d'embarquement et un bloc latrine a trois compartiments dans la Commune de Moulvoudaye. CM-CRC EXTREME NORD-111380-CW-RFB / Travaux de Construction de 02 sdc et 3 latriness à EP KAOSSERE, à l'EP Ticheeo Kolandi, à l'EP Single Stage - One En attente IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-10-20 Tchoura-Bizili L1 et de 02 Envelope d'exécution SDC EPB Touloum L2 et DE 2 SDC avec BUREAUX A L’EPP SAOTSAI L3 Cune de Touloum CM-CRC EXTREME NORD-111358-CW-RFQ / Travaux de Construction Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 d'un forage équipé de PMH Envelope d'exécution à lycee bilingue dans la commue de Kaele CM-CRC EXTREME NORD-111384-CW-RFQ / Travaux de Construction de Single Stage - One En attente 01 forage à PMH à Gai IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution gai, à EP Golonpoui et à EP Kankwa, dans la commune de Datcheka CM-CRC EXTREME NORD-111395-CW-RFQ / Travaux de Construction d'un bloc de 02 salles de classe équipées et avec un Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 bloc de latrines à trois Envelope d'exécution compartiments à EP Golonpoui , EP Kankrwa et EP Guidima , dans la commune de Datcheka CM-CRC EXTREME NORD-111378-CW-RFQ / Travaux de Construction d'un bloc de deux salles de Single Stage - One En attente classe équipées au CETIC IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution de Vélé, au CES de Widigue , au CES de Dabaye et au CES d'Agolla, dans la commune de Guémé CM-CRC EXTREME NORD-111369-CW-RFQ / Travaux de Construction d'un hangar 52 places au Single Stage - One En attente marché de Gabaraye et IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution Travaux de Construction d'un bloc de latrines au marché de Gabaraye, commune de Guémé CM-CRC EXTREME NORD-111362-CW-RFQ / Travaux de Construction d'un centre de santé Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 intégré équipé et un bloc Envelope d'exécution de latrines au CSI à Nguéring, commune de Gueré CM-CRC EXTREME NORD-111396-CW-RFQ / Single Stage - One En attente Construction d'un bloc de IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution 05 boutiques au marché d'Ardaf Commune de Guere CM-CRC EXTREME NORD-111388-CW-RFQ / Travaux de Construction Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 d'un forage équipé de PMH Envelope d'exécution à l'EP de DAMA Djougong, commune de Kai kai CM-CRC EXTREME NORD-111390-CW-RFQ / CONSTRUCTION DEUX Single Stage - One En attente BLOCS DE CINQ (05) IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution BOUTIQUES AU MARCHÉ DE KALFOU, DANS LA COMMUNE DE KALFOU CM-CRC EXTREME NORD-111371-CW-RFQ / Travaux de Construction d'un forage équipé de pompe à motricité humaine Single Stage - One En attente à Gandou Golopo, au CES IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution de Zaria, à Djada, réhabilitation d'un forage PMH à Delta Guibéré et Mandara, dans la commune de Kalfou CM-CRC EXTREME NORD-111398-CW-RFQ / Single Stage - One En attente Équipement en matériel IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 Envelope d'exécution médicaux au CSI de Takreo yoldeo Commune Kar Hay CM-CRC EXTREME NORD-111387-CW-RFQ / Single Stage - One En attente Travaux de construction IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 Envelope d'exécution d'un forage pmh à l'EP Dolgaye Commune Kar Hay Page 9 CM-CRC EXTREME NORD-111260-CW-RFQ / Electrification du nouveau Single Stage - One En attente marché de Guirvidig (lot IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 Envelope d'exécution 01) et de la localité de Yangah (lot 02) , dans la commune de Maga CM-CRC EXTREME NORD-111368-CW-RFQ / Travaux de Construction Single Stage - One En attente d'un forage équipé de IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 Envelope d'exécution pompe à motricité humaine à Bindiriel Danghou, commue de Tchatibali CM-CRC EXTREME NORD-111259-CW-RFB / Travaux de Construction d'un bloc de 02 salles de classe équipées et d'un bloc de latrines à Single Stage - One En attente IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-11-19 troiscompartiments au CES Envelope d'exécution Kamargui, à EP Goulourgou (lot 02), EP Bigi, EP de Djenreng (lot 02)et EP Waimou (lot 03) COMMUNE DE WINA CM-CRC EXTREME NORD-111383-CW-RFQ / Travaux de Construction D’UN BLOC DE DEUX Single Stage - One En attente SALLES DE CLASSE IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 Envelope d'exécution AVEC BUREAUX EQUIPES au CES de DJOGOIDI et au lycee de Vounaloum Commune de yagoua CM-CRC EXTREME NORD-111331-CW-RFQ / Travaux de Construction Single Stage - One En attente d'un forage équipé de IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 Envelope d'exécution pompe à motricité humaine a Djafgadjie, commue de yagoua CM-CRC EXTREME NORD-111365-CW-RFQ / Travaux de Construction Single Stage - One En attente d'un hangar de 28 places IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-09-29 Envelope d'exécution et d'une boucherie au marché de Velé, dans la commune de Guémé CM-CRC EXTREME NORD-111374-CW-RFQ / Travaux de Construction de Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 01 forage à énergie solaire Envelope d'exécution à CSI de Bosgoye, dans la commune de Wina CM-CRC EXTREME NORD-111433-CW-RFQ / Single Stage - One En attente réalisation d'un parc à IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-09-07 2019-11-02 2020-04-30 Envelope d'exécution bétail dans la commune de Wina (GP) CM-CRC EXTREME NORD-111389-CW-RFQ / Travaux de Construction de 2 salles de classe et de latrines à l'EP de BIJE ( lot 01) , Construction de 2 Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 salles de classes à EPPB Envelope d'exécution de TOKOMBERE et equipement en table bancs et bureaux au CES de makilingai (lot 02) dans la commune de Tokombere CM-CRC EXTREME NORD-111392-CW-RFQ / Travaux de Construction Single Stage - One En attente d'un bloc de deux salle de IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution classe équipés et d'un bloc latrines à Magala Djamene dans la commune de Darak CM-CRC EXTREME NORD-111385-CW-RFQ / Travaux de Construction de Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 01 forage PMH à Magala Envelope d'exécution Djamene, dans la commune de Darak CM-CRC EXTREME NORD-111325-CW-RFB / Travaux de Construction d'un bloc de deux salles de classe équipées et d'un bloc Single Stage - One En attente de latrines à trois IDA / 57180 A posteriori Appel d'offres Open - National 0.00 2019-04-01 2019-04-06 2019-05-18 2019-06-17 2019-07-22 2019-11-19 Envelope d'exécution compartiments à EP GADAFAI, au Lycée de Fotokol à EP Magadji et à EP de GUEGUERI, commune de Fotokol CM-CRC EXTREME NORD-111261-CW-RFQ / Single Stage - One En attente Travaux de Construction IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution d'un magasin de stockage à Goulfey CM-CRC EXTREME NORD-111367-CW-RFQ / Travaux de Construction Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 d'une mini AEP pastorale à Envelope d'exécution énergie solaire à fadja commune de Hilé Alifa Page 10 CM-CRC EXTREME NORD-111320-CW-RFQ / Travaux de Construction de Single Stage - One En attente 01 forage PMH à Michiska IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 Envelope d'exécution Mousgoum, OUNANGARE et NGADA 1, dans la commune de Logone Birni CM-CRC EXTREME NORD-111327-CW-RFB / Travaux de Construction Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 d'un magasin de stockage à Envelope d'exécution zigague, dans la commune de Waza CM-CRC EXTREME NORD-111322-CW-RFQ / Travaux de Construction Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-08-30 d'un forage PMH à malia, Envelope d'exécution NDIGUINA et MADA dans la commune de Waza GOODS Bid Evaluation Activity Reference No. Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD-7991-GO-RFQ / Acquisition des fournitures de bureaux du matériels Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 8,556.39 Signé 2017-03-10 2017-05-05 2017-05-19 d'entretien et des Envelope fournitures diverses à la CRC, Région de l'Extrême- Nord CM-CRC EXTREME NORD-8000-GO-RFQ / Acquisition des consomables Informatiques (Encres, clés Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 5,074.65 Signé 2017-03-10 2017-05-05 2017-05-19 internet, CD, 2 disques Envelope durs externes Tera, 9 clés USB, antivirus) à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD-8001-GO-RFQ / Acquisition des fournitures pour véhicules ((5pneusX3véh), 3 boîtes à Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 0.00 Annulé 2017-03-10 2017-05-05 2017-05-19 pharmacie, 3 extincteurs,3 Envelope pelles, 6 paires de gants, 3machettes, 3manteaux...) à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD-8003-GO-RFQ / Single Stage - One acquisition, aménagement et IDA / 57180 A posteriori Demande de prix Limited 4,880.26 Achevé 2017-03-10 2017-05-05 2017-07-04 Envelope équipement de 2 conteneurs de 40 pieds CM-CRC EXTREME NORD-8006-GO-RFQ / Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 5,492.69 Achevé 2017-03-10 2017-05-05 2017-06-04 aquisition et installation de Envelope 10 splits CM-CRC EXTREME NORD-8008-GO-RFQ / acquisition du kit à outils Single Stage - One du CCI(scléromètre, IDA / 57180 A posteriori Demande de prix Limited 0.00 Annulé 2017-03-10 2017-05-05 2017-06-04 Envelope lazermètre, odomètre, pi à coulisse électronique, EPI, Gilets de sauvetage CM-CRC EXTREME NORD-8009-GO-RFQ / fourniture des services de maintenance électrique, Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 2,176.75 Signé 2017-03-10 2017-05-05 2018-05-05 climatiseurs, groupe Envelope électrogène, plolmberie et menuiserie à la CRC, Région de l'Extrême-Nord CM-CRC EXTREME NORD-38389-GO-RFQ / Equipement en table bancs, tables et chaise pour Enseignants et armoires au Single Stage - One IDA / 57180 A posteriori Demande de prix Limited 12,882.93 Signé 2017-12-02 2018-01-27 2018-04-27 CETIC de Mogodé, à l'EP Envelope de SIR, à l'EPB de Rhoumsiki et à l'EP de Tchanawa dans la commune de Mogode CM-CRC EXTREME NORD-58709-GO-RFQ / Acquisition des consomables Informatiques (Encres, clés Single Stage - One internet, CD, 2 disques IDA / 57180 A posteriori Demande de prix Limited 1,816.76 Signé 2017-10-08 2017-12-03 2017-12-17 Envelope durs externes Tera, 9 clés USB, antivirus) à la CRC, Région de l'Extrême-Nord VAGUE 2 CM-CRC EXTREME NORD-58529-GO-RFP / Fourniture d' une pirogue à moteur 30CV type E40GMHL (avec coque en Single Stage - One fibre de verre) et des IDA / 57180 A posteriori Demande de prix Limited 25,881.80 Signé 2018-05-06 2018-07-01 2018-08-30 Envelope équipements annexes: portes tout tricycle tractable, pagaies, gilets de sauvetage, panneaux de labelisation) dans la cmne de KAIKAI Page 11 CM-CRC EXTREME NORD-111400-GO-RFQ / Fourniture en mobilier et petit materiel sanitaire de Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-04-06 2019-06-01 2019-07-31 CSI de Mindif, de Envelope d'exécution Modjombodi, de Maoudine et de Mogom dans la commune de Mindif. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD-111430-NC-RFQ / Selection d'une agence d'edition pour la production Single Stage - One En attente IDA / 57180 A posteriori Demande de prix Open - National 0.00 2019-06-09 2019-08-04 2020-08-03 d'un bulletin trimestriel Envelope d'exécution d'informations communales(47 communes) dans la region de l'Extreme- nord CONSULTING FIRMS Activity Reference No. Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Actual Amount Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-CRC EXTREME NORD-8076-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 55,623.04 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 pour l'actualisation du PCD qualifications des de la commune de Guéré, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-8082-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 22,183.49 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 pour l'actualisation du PCD qualifications des de la commune de Kalfou, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-8088-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 49,888.95 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 pour l'actualisation du PCD qualifications des de la commune de Mindif, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-8094-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 44,697.93 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 pour l'actualisation du PCD qualifications des de la commune de Gazawa., consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-8093-CS-CQS / Sélection fondée Sélection d'un consultant sur les pour l'actualisation du PCD IDA / 57180 A posteriori Open - National 29,601.16 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 qualifications des de la commune de consultants Guidiguis, Région de l'Extrême-Nord CM-CRC EXTREME NORD-8097-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 50,722.45 Signé 2017-03-10 2017-03-31 2017-05-14 2017-06-13 2017-07-18 2018-05-14 pour l'actualisation du PCD qualifications des de la commune de Dargala, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29268-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 23,876.36 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de WINA, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29270-CS-CQS / Sélection fondée Sélection d'un consultant sur les pour l'actualisation du PCD IDA / 57180 A posteriori Open - National 29,798.62 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 qualifications des de la commune de consultants BOURHA, Région de l'Extrême-Nord CM-CRC EXTREME NORD-29272-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 23,663.61 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Hina, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29273-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 27,173.71 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Koza, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29274-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 37,441.16 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Mozogo., consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29276-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 0.00 Annulé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Kolofata, consultants Région de l'Extrême-Nord Page 12 CM-CRC EXTREME NORD-29277-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 0.00 Annulé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Kolofata, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29280-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 0.00 Annulé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Goulfey, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29281-CS-CQS / Sélection fondée Sélection d'un consultant sur les pour l'actualisation du PCD IDA / 57180 A posteriori Open - National 47,055.60 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 qualifications des de la commune de consultants FOTOKOL, Région de l'Extrême-Nord CM-CRC EXTREME NORD-29282-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 35,172.82 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de consultants Blangoua, Région de l'Extrême-Nord CM-CRC EXTREME NORD-29284-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 31,593.26 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-11-24 pour l'actualisation du PCD qualifications des de la commune de Darak, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-8089-CS-CQS / Sélection fondée sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 19,922.77 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 pour l'actualisation du PCD qualifications des de la commune de consultants Datcheka, Région de l'Extrême-Nord CM-CRC EXTREME NORD-29269-CS-CQS / Sélection fondée Sélection d'un consultant sur les pour l'actualisation du PCD IDA / 57180 A posteriori Open - National 18,485.99 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 qualifications des de la commune de consultants TCHATIBALI, Région de l'Extrême-Nord CM-CRC EXTREME NORD-29278-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 18,318.08 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 pour l'actualisation du PCD qualifications des de la commune de Waza, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-29285-CS-CQS / Sélection fondée Sélection d'un consultant sur les pour l'actualisation du PCD IDA / 57180 A posteriori Open - National 32,024.61 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 qualifications des de la commune deHILE- consultants ALIFA., Région de l'Extrême-Nord CM-CRC EXTREME NORD-58613-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 68,824.87 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 pour l'actualisation du PCD qualifications des de la cmne de Goulfey, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-58629-CS-CQS / Sélection fondée Sélection d'un consultant sur les IDA / 57180 A posteriori Open - National 28,958.86 Signé 2018-06-15 2018-07-06 2018-08-19 2018-09-18 2018-10-23 2019-08-19 pour l'actualisation du PCD qualifications des de la cmne de Kolofata, consultants Région de l'Extrême-Nord CM-CRC EXTREME NORD-58563-CS-CQS / Sélection de deux Sélection fondée consultants (OAL) pour la sur les IDA / 57180 A posteriori Open - National 546,754.14 Signé 2017-04-05 2017-04-26 2017-06-09 2017-07-09 2017-08-13 2017-11-11 collecte et la saisie des qualifications des données du score cadre consultants deans 21 cmnes , Région de l'Extrême-Nord CM-CRC EXTREME NORD-111124-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants BOGO CM-CRC EXTREME NORD-111121-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants NDOUKOULA CM-CRC EXTREME NORD-111122-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants MOGODE CM-CRC EXTREME NORD-111231-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants MAKARY CM-CRC EXTREME NORD-111232-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2019-11-08 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants LOGONE BIRNI Page 13 CM-CRC EXTREME NORD-111118-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2021-05-31 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants YAGOUA CM-CRC EXTREME NORD-111119-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / D2990 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants KAI KAI CM-CRC EXTREME NORD-111123-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants KAELE CM-CRC EXTREME NORD-111120-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants MOUTOURWA CM-CRC EXTREME NORD-111218-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants TOKOMBERE CM-CRC EXTREME NORD-111230-CS-CQS / Sélection fondée Sélection d'un OAL pour sur les En attente IDA / 57180 A posteriori Open - National 0.00 2019-06-01 2019-06-22 2019-08-05 2019-09-04 2019-10-09 2020-08-04 l'actualisation légère du qualifications des d'exécution PCD de la commune de consultants MOKOLO INDIVIDUAL CONSULTANTS Page 14