PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-08-06 2021-03-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2900, IDA / V1250 I Executing Agency(ies): nternational Union for Conservation of Nature WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-IUCN-223643-CW-RFQ / Passation de Component 1: Strengthening En attente 2021-10- Travaux d’aménagement IDA / D2900 A posteriori marché de gré à Direct 0.00 2021-05-24 2021-05-29 2021-07-03 Regional Integration d'exécution 31 locaux UICN WACA BAR gré GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-IUCN-71934-GO-RFQ / Component 1: Strengthening Single Stage - One IDA / D2900 A posteriori Demande de prix Limited 40,154.92 Signé 2018-09-06 2019-10-28 2018-11-01 2019-11-29 2019-04-30 UICN - Véhicule Regional Integration Envelope BF-IUCN-116515-GO-RFQ / Component 1: Strengthening Single Stage - One UICN - EQUIPEMENT DE IDA / V1250 A posteriori Demande de prix Limited 7,528.39 Signé 2019-06-04 2019-03-18 2019-07-30 2019-08-27 2020-01-26 Regional Integration Envelope BUREAU (MOBILIER) BF-IUCN-142244-GO-RFQ / Component 1: Strengthening Single Stage - One Equipement informatique IDA / D2900 A posteriori Demande de prix Limited 14,089.97 Résilié 2019-11-08 2020-08-07 2019-12-09 2020-09-08 2020-01-23 Regional Integration Envelope pour la Convention d'Abidjan (ABC) BF-IUCN-142245-GO-RFQ / Materiel et mobilier de bureau Component 1: Strengthening Single Stage - One IDA / D2900 A posteriori Demande de prix Limited 8,377.47 Signé 2019-11-08 2020-07-28 2019-12-09 2020-08-26 2020-01-23 pour la Convention d'Abidjan Regional Integration Envelope (ABC) BF-IUCN-71940-GO-RFQ / Component 1: Strengthening Single Stage - One IDA / D2900 A posteriori Demande de prix Limited 12,014.59 Signé 2018-09-06 2019-03-18 2018-11-01 2019-07-23 2019-04-30 UICN - Matériel informatique Regional Integration Envelope BF-IUCN-187763-GO-RFQ / Component 1: Strengthening Single Stage - One Matériel de vidéoconférence IDA / D2900 A posteriori Demande de prix Limited 5,552.29 Signé 2020-09-01 2021-01-13 2020-10-27 2021-03-11 2021-04-05 Regional Integration Envelope pour le WACA BF-IUCN-223641-GO-RFQ / Impression Supports (2021) Component 1: Strengthening Single Stage - One En attente de communication IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-24 2021-09-18 2022-03-17 Regional Integration Envelope d'exécution complémentaires UICN WACA BAR BF-IUCN-224222-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Supports de communication IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-24 2021-09-18 2022-03-17 Regional Integration Envelope d'exécution supplémentaires ABC BF-IUCN-224228-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Equipements IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-10 2021-09-04 2022-03-03 Regional Integration Envelope d'exécution complémentaires UICN WACA BAR BF-IUCN-224229-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Fournitures Consommables de IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-06-06 2021-08-01 2022-01-28 Regional Integration Envelope d'exécution bureau UICN WACA BAR BF-IUCN-224233-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Acquisition Carburant UICN IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-10 2021-09-04 2022-03-03 Regional Integration Envelope d'exécution WACA BAR BF-IUCN-224234-GO-RFQ / Confection de Masques avec Component 1: Strengthening Single Stage - One En attente IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-04-10 2021-06-05 2021-12-02 graphisme pour UICN WACA Regional Integration Envelope d'exécution BAR BF-IUCN-224235-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Mobilier complémentaires IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-10 2021-09-04 2022-03-03 Regional Integration Envelope d'exécution pour ABC BF-IUCN-224236-GO-RFQ / Component 1: Strengthening Single Stage - One En attente Acquisition consommables IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-07-17 2021-09-11 2022-03-10 Regional Integration Envelope d'exécution pour ABC BF-IUCN-142244BIS-GO-RFQ / RELANCE ACQUISITION Component 1: Strengthening Single Stage - One En attente EQUIPEMENTS IDA / D2900 A posteriori Demande de prix Limited 0.00 2021-06-23 2021-07-24 2021-09-07 Regional Integration Envelope d'exécution INFORMATIQUES CONVENTION ABC NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-IUCN-142246-CS-CQS / Production audio-visuelle Component 1: Strengthening Single Stage - One En cours IDA / D2900 A posteriori Demande de prix Limited 0.00 2020-05-09 2020-06-11 2020-07-11 pour la Convention d'Abidjan Regional Integration Envelope d'exécution (ABC) Page 1 BF-IUCN-143209-NC-DIR / Passation de Logiciel de programmation et Component 1: Strengthening IDA / D2900 A posteriori marché de gré à Direct 27,541.38 Signé 2019-12-16 2020-04-01 2020-01-05 2020-04-03 2020-01-30 2020-05-28 2024-02-11 de suivi-évaluation Regional Integration gré multiprojet BF-IUCN-187753-NC-RFQ / Impression de supports de Component 1: Strengthening Single Stage - One IDA / D2900 A posteriori Demande de prix Limited 10,063.40 Signé 2020-09-08 2020-09-30 2020-11-03 2020-10-28 2021-05-02 communication pour WACA Regional Integration Envelope BAR BF-IUCN-223642-NC-DIR / Passation de Component 1: Strengthening En attente Architecte pour aménagement IDA / D2900 A posteriori marché de gré à Direct 0.00 2021-04-15 2021-04-20 2021-05-25 2021-11-21 Regional Integration d'exécution bureaux du WACA BAR gré CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sélection fondée BF-IUCN-71915-CS-QCBS / Component 1: Strengthening sur les Sélection d'un cabinet pour le IDA / D2900 A posteriori Open - International 24,949.18 Signé 2018-08-08 2018-09-09 2018-08-29 2018-10-12 2018-10-12 2018-11-11 2018-08-26 2018-12-16 2018-09-29 2019-06-14 Regional Integration qualifications des recrutement du staff du projet consultants Sélection fondée BF-IUCN-71913-CS-CQS / Component 1: Strengthening sur les Manuel de Suivi & Évaluation IDA / D2900 A posteriori Open - National 15,950.00 Signé 2018-09-04 2018-09-04 2018-09-04 2018-06-27 2018-09-04 2018-08-27 2018-09-04 2018-08-27 2018-10-31 Regional Integration qualifications des Version 1 (régional, national). consultants BF-IUCN-69234-CS-CQS / Manuel Régional de Mise en Œuvre (Regional Project Sélection fondée Implementation Manual), y Component 1: Strengthening sur les IDA / D2900 A posteriori Open - National 57,587.07 Signé 2018-09-04 2018-05-21 2018-09-04 2018-09-04 2018-05-25 2018-09-04 2018-08-25 2018-09-04 2018-06-27 2018-11-30 inclus les manuels des Regional Integration qualifications des procédures administratives, consultants financières et comptables, et de passation des marchés. BF-IUCN-71938-CS-QCBS / Assistance technique pour Sélection fondée Component 1: Strengthening préparer l'investissement des IDA / D2900 A posteriori sur la qualité et le Open - International 0.00 Annulé 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2020-05-12 Regional Integration nouveaux pays WACA (MSIP coût pour 3 pays) BF-IUCN-71937-CS-LCS / Mise en œuvre des Sélection fondée Component 1: Strengthening Campagnes de IDA / D2900 A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-01-10 2019-01-31 2019-03-16 2019-04-13 2019-05-13 2019-06-17 2019-07-22 2023-12-28 Regional Integration Communication tout au long coût de la durée du projet BF-IUCN-71936-CS-LCS / AT Sélection fondée pour les Audits – audits Component 1: Strengthening sur les IDA / D2900 A posteriori Open - National 0.00 Annulé 2019-01-10 2019-01-31 2019-03-16 2019-04-15 2019-05-20 2023-12-20 annuels des comptes du Regional Integration qualifications des projet à l’UICN consultants BF-IUCN-71932-CS-CQS / Sélection fondée Développement de Plan de Component 1: Strengthening sur les IDA / D2900 A posteriori Open - National 0.00 Annulé 2018-12-03 2018-12-13 2019-01-26 2019-02-25 2019-04-01 2019-05-16 Communication au début du Regional Integration qualifications des projet consultants Sélection fondée BF-IUCN-71939-CS-CQS / Component 1: Strengthening sur les Notes d'orientation technique IDA / D2900 A posteriori Open - National 0.00 Annulé 2018-12-03 2018-12-24 2019-02-06 2019-03-08 2019-03-28 2019-05-27 Regional Integration qualifications des (Comment fonctionne WACA?) consultants Sélection fondée BF-IUCN-142252-CS-CQS / Component 1: Strengthening sur les Production outils de IDA / D2900 A posteriori Open - International 0.00 Annulé 2020-05-04 2020-05-18 2020-06-01 2020-06-08 2020-06-18 2020-07-18 Regional Integration qualifications des communication (WACA-BAR) consultants BF-IUCN-223328-CS-CQS / Sélection fondée Firme pour la formation du Component 1: Strengthening sur les En attente personnel et des partenaires IDA / D2900 A posteriori Open - National 0.00 2021-04-27 2021-05-18 2021-07-01 2021-07-31 2021-09-04 2022-03-03 Regional Integration qualifications des d'exécution du WACA Resip et du WACA consultants BAR INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-IUCN-71928-CS-CDS / Sélection de Component 1: Strengthening En cours Contrat avec la Convention IDA / D2900 A priori consultants par Direct 0.00 2018-07-30 2018-08-09 2018-10-13 2019-04-11 Regional Integration d'exécution d’Abidjan entente directe BF-IUCN-71930-CS-CDS / Sélection de Component 1: Strengthening Contrat avec le Centre de Suivi- IDA / D2900 A priori consultants par Direct 1,462,252.50 Signé 2018-07-30 2019-05-15 2018-08-09 2019-04-30 2018-10-13 2019-09-14 2019-04-11 Regional Integration Ecologique (CSE) entente directe BF-IUCN-71916-CS-QCBS / Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 252,198.00 Signé 2018-08-09 2018-06-25 2018-09-27 2018-10-22 2018-10-18 2018-10-31 2018-11-22 2018-10-31 2019-05-21 Regional WACA Coordinator Regional Integration BF-IUCN-71924-CS-QCBS / Component 1: Strengthening Regional WACA M&E and IDA / D2900 A posteriori Individuel Open 55,283.07 Signé 2018-08-13 2019-05-09 2018-11-12 2019-03-07 2018-11-17 2019-06-15 2018-11-26 2019-06-15 2019-11-26 Regional Integration Reporting Specialist BF-IUCN-71923-CS-QCBS / Regional WACA Financial Component 1: Strengthening Management Support IDA / D2900 A posteriori Individuel Open 53,278.77 Signé 2018-08-13 2019-05-09 2018-11-12 2019-07-17 2018-11-17 2019-08-15 2018-11-26 2020-08-15 2019-11-26 Regional Integration Specialist (and accountant for RISU) BF-IUCN-71926-CS-QCBS / Component 1: Strengthening Regional WACA Leadership IDA / D2900 A posteriori Individuel Open 38,509.88 Signé 2018-08-13 2019-05-09 2018-11-12 2019-05-20 2018-11-17 2019-06-07 2018-11-26 2020-06-15 2019-11-26 Regional Integration Development Specialist Page 2 BF-IUCN-142258-CS-INDV / Consultant court termes 6 Component 1: Strengthening mois spécialiste IDA / D2900 A posteriori Individuel Limited 0.00 Annulé 2020-01-06 2020-01-11 2020-01-23 2020-01-27 2020-07-25 Regional Integration développement & sauvegardes sociales BF-IUCN-142259-CS-INDV / Component 1: Strengthening En cours Spécialiste développement & IDA / D2900 A posteriori Individuel Open 0.00 2020-01-06 2020-03-30 2020-02-26 2020-03-12 2020-03-26 2021-03-26 Regional Integration d'exécution sauvegardes sociales BF-IUCN-142265-CS-INDV / Consult individuel Etat de Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 0.03 Signé 2019-12-16 2020-08-04 2020-01-19 2020-09-29 2020-01-29 2020-10-20 2020-03-05 2020-10-20 2020-05-04 référence pour la Convention Regional Integration d'Abidjan (ABC) BF-IUCN-142266-CS-INDV / Consultant Régional en droit Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 37,820.56 Signé 2019-11-11 2019-01-05 2019-12-15 2020-07-30 2019-12-22 2020-08-07 2020-01-03 2020-08-18 2020-03-03 de l'environnement pour la Regional Integration Convention d'Abidjan (ABC) BF-IUCN-142267-CS-INDV / Consultant Communication Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 15,246.72 Signé 2019-12-16 2020-08-02 2020-01-20 2020-10-27 2020-01-25 2020-11-03 2020-03-05 2020-11-05 2020-05-04 pour la Convention d'Abidjan Regional Integration (ABC) BF-IUCN-142272-CS-INDV / Expert coordonnateur de Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 47,502.42 Signé 2019-11-04 2020-05-03 2019-12-07 2019-02-14 2019-12-17 2019-05-15 2019-12-22 2019-05-15 2020-12-21 projet (Consultant) pour la Regional Integration Convention d'Abidjan (ABC) BF-IUCN-71921-CS-QCBS / Regional WACA Procurement Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 54,016.52 Signé 2018-08-13 2019-05-09 2020-01-06 2020-04-15 2020-01-11 2020-06-01 2020-01-20 2020-04-30 2021-01-19 Support Specialist (and Proc Regional Integration Spec for RISU) BF-IUCN-142254-CS-CDS / Appuyer les pays dans la mise Sélection de Component 1: Strengthening En cours en place et la gestion des IDA / D2900 A posteriori consultants par Direct 0.00 2020-01-15 2021-01-27 2020-01-25 2020-03-11 2020-12-31 Regional Integration d'exécution Aires Marines Protégées - entente directe RAMPAO BF-IUCN-142253-CS-CDS / Sélection de Assistance technique en Component 1: Strengthening IDA / D2900 A posteriori consultants par Direct 112,270.00 Signé 2019-11-04 2020-06-15 2019-11-10 2020-01-06 2019-11-15 2020-06-05 2020-05-13 ingénierie et planification Regional Integration entente directe côtière aux UGP - CEREMA BF-IUCN-73868-CS-INDV / Component 1: Strengthening Regional WACA Env Support IDA / D2900 A posteriori Individuel Open 58,441.68 Signé 2018-08-14 2019-05-09 2018-10-01 2020-04-17 2018-10-06 2019-06-15 2018-10-12 2019-06-15 2019-10-12 Regional Integration Specialist BF-IUCN-71925-CS-QCBS / Regional WACA Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 46,162.89 Signé 2018-08-13 2019-05-09 2018-09-30 2020-01-29 2018-10-05 2020-04-16 2018-10-11 2020-04-16 2019-10-11 Communication Support Regional Integration Specialist BF-IUCN-187249-CS-INDV / Consultant pour design de Component 1: Strengthening IDA / D2900 A posteriori Individuel Limited 7,263.60 Signé 2020-08-12 2020-09-25 2020-08-17 2020-11-13 2020-09-07 2020-12-09 2020-10-12 2020-12-14 2021-02-09 supports de communications Regional Integration WACA BAR. BF-IUCN-71927-CS-QCBS / Component 1: Strengthening IDA / D2900 A priori Individuel Open 0.00 Annulé 2018-08-13 2018-09-30 2018-10-05 2018-10-11 2019-10-11 Chauffeur Regional Integration BF-IUCN-142263-CS-INDV / Expertise individuelle Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-07 2021-06-14 2021-07-16 2021-07-26 2022-04-07 Commission UICN - Activités Regional Integration d'exécution génératrices de revenus BF-IUCN-223175-CS-INDV / Consultant en sauvegardes Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-05-31 2021-06-05 2021-06-26 2021-07-31 2022-01-27 sociales court terme WACA Regional Integration d'exécution BAR pour 6 mois BF-IUCN-223635-CS-INDV / Consultant pour la formation Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-05-24 2021-05-29 2021-06-19 2021-07-24 2021-12-21 des spécialistes en Regional Integration d'exécution communication BF-IUCN-223639-CS-INDV / Consultant Community Component 1: Strengthening En attente manager pour l'animation IDA / D2900 A posteriori Individuel 0.00 2021-04-15 2021-04-20 2021-05-11 2021-06-15 2021-11-12 Regional Integration d'exécution d'un webinaire avec les bloggueurs et influenceurs de bloggeurs BF-IUCN-224091-CS-INDV / Consultant pour la mise en Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-05-31 2021-06-05 2021-06-26 2021-07-31 2022-01-27 œuvre du plan de Regional Integration d'exécution communication ABC BF-IUCN-224142-CS-INDV / Consultant pour la mise à jour Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 stratégie de développement Regional Integration d'exécution institutionnel ABC BF-IUCN-224185-CS-INDV / Consultant en appui au Ghana Component 1: Strengthening En attente pour les documents de IDA / D2900 A posteriori Individuel Limited 0.00 2021-05-10 2021-05-15 2021-06-05 2021-07-10 2022-01-06 Regional Integration d'exécution présentation des protocoles ABC pour Ratification BF-IUCN-224218-CS-INDV / Consultant en appui au Component 1: Strengthening En attente Nigeria pour les documents IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Regional Integration d'exécution de présentation des protocoles ABC pour Ratification BF-IUCN-224220-CS-INDV / Consultant en appui à Sao Component 1: Strengthening En attente Tomé pour documents de IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-30 2021-07-05 2021-07-26 2021-08-30 2022-02-26 Regional Integration d'exécution présentation des protocoles ABC pour Ratification Page 3 BF-IUCN-142264-CS-INDV / Expertise individuelle Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-21 2021-06-26 2021-07-16 2021-08-09 2022-04-21 Commission UICN - Solutions Regional Integration d'exécution basées sur la nature BF-IUCN-142273-CS-INDV / Component 1: Strengthening En attente Assistant coordonnateur pour IDA / D2900 A posteriori Individuel Open 0.00 2021-06-17 2021-07-22 2021-08-22 2021-09-15 2022-09-14 Regional Integration d'exécution la Convention d'Abidjan (ABC) BF-IUCN-142262-CS-INDV / Component 1: Strengthening En attente Expertise individuelle IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-21 2021-06-28 2021-07-26 2021-08-09 2022-04-21 Regional Integration d'exécution Commission UICN - Mangrove BF-IUCN-142271-CS-INDV / Consultant pour le Component 1: Strengthening développement du centre de IDA / D2900 A posteriori Individuel Open 0.00 Annulé 2019-12-16 2020-01-20 2020-02-10 2020-03-05 2020-05-04 Regional Integration ressources de la Convention d'Abidjan (ABC) BF-IUCN-142268-CS-INDV / Consultant Développement Component 1: Strengthening IDA / D2900 A posteriori Individuel Open 0.00 Annulé 2019-12-16 2020-02-13 2020-02-20 2020-03-05 2020-05-04 institutionnel pour la Regional Integration Convention d'Abidjan (ABC) BF-IUCN-187757-CS-INDV / Consultants pour services Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-01 2021-06-06 2021-06-27 2021-08-01 2022-08-01 d'interprète en portugaise Regional Integration d'exécution pour ABC et WACA BF-IUCN-187755-CS-INDV / Consultant pour services Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-01 2021-06-06 2021-06-27 2021-08-01 2022-08-01 d'interprète en anglais pour Regional Integration d'exécution ABC et WACA BF-IUCN-187751-CS-INDV / Consultant pour services de Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-01 2021-06-06 2021-06-27 2021-08-01 2022-08-01 traduction en portugais pour Regional Integration d'exécution ABC et WACA BF-IUCN-187750-CS-INDV / Consultant pour services de Component 1: Strengthening En attente IDA / D2900 A posteriori Individuel Limited 0.00 2021-06-01 2021-06-06 2021-06-27 2021-08-01 2022-08-01 traduction dans la langue Regional Integration d'exécution anglaise pour ABC et WACA Page 4