RECENT ECONOMIC AND The 12-month food price index was 6.1 percent in SECTORAL December 2011, as compared to 15.2 percent a year ago. The food prices, however, continued being the DEVELOPMENTS major driver for inflation, contributing around 2.9 percentage points to the overall price increase. Price Growth Performance environment remained favorable over the first two months of 2012, with 0.9 percent of monthly The economy has continued to recover in 2011, deflation in February, which brought 12-month led by the mining and agriculture sectors. inflation down to 3.0 percent, as compared to 11.8 Economic growth (in year-on-year terms) picked percent in the same period a year before. up gradually from 2.1 percent in 2010 to 4.6 percent in 2011. Industry contributed more than Figure 2: Inflation returned to the target band half of the economic growth driven mainly by the (Actual inflation and the target bounds, %) mining sector and, to a lesser extent, agro- 14 industries. The industrial output surpassed the level 12 of December 2008 (in the pre crisis period) by 17.5 percent. Agriculture also contributed 8.1 10 percentage points to the growth in the third 8 quarter. Continuing contraction in the construction 6 sector, however, partly offset these achievements. 4 2 Figure 1: Economic growth and sectoral 0 contributions Ja n-08 Ja n-09 Ja n-10 Ja n-11 Ja n-12 Oct-08 Oct-09 Oct-11 Oct-10 Jul-08 Jul-10 Jul-11 Jul-09 Apr-09 Apr-10 Apr-11 Apr-08 (Share in GDP and real GDP growth, %) 20 20.0 Lower bound (2.5%) Upper bound (5.5 %) CPI YoY 15 15.0 10 10.0 5 5.0 0 0.0 Improving the inflation outlook allowed -5 -10 -5.0 -10.0 loosening monetary policy. Along with the -15 -15.0 slowdown of the monthly inflation, the Central -20 -20.0 -25 -25.0 Bank reduced its policy (refinancing) rate by 50 basis 2007Q1 2007Q2 2007Q4 2008Q1 2008Q2 2008Q4 2009Q1 2009Q2 2009Q4 2010Q1 2010Q2 2010Q4 2011Q1 2011Q2 2007Q3 2008Q3 2009Q3 2010Q3 2011Q3 points (to 8 percent) in 2011. The reduction took place in September 2011, when the 12-month Agriculture Construction inflation of 4.1 percent almost reached the target Manufacturing Other industry level (4±1.5 percentage point band). This policy rate Service GDP real growth (%), RHS remained unchanged since then. Downside risks remain given global economic uncertainties. But Russia’s growth and the Figure 3: Lower inflationary pressures allowed sustained inflow of remittances and FDI provide reducing the policy rate some economic stability. The economic outlook (Actual inflation and the policy rate, %) continues to largely depend on the tradable sectors’ ability to recover and expand. 14 9 12 8.5 8 10 7.5 Inflation Developments 7 8 6.5 Inflation returned to the band targeted by the 6 6 Central Bank in the second half of 2011. 4 5.5 Reflecting the slowdown in the rise of food prices in 5 2 the local market, the 12-month inflation declined to 4.5 0 4 4.7 percent in December 2011, within the 4±1.5 Ma y-09 Ma y-10 Ma y-11 Ja n-09 Ja n-10 Ja n-11 Ja n-12 Sep-09 Sep-10 Sep-11 Ma r-09 Ma r-10 Ma r-11 Nov-09 Nov-10 Nov-11 Jul-09 Jul-10 Jul-11 percentage point band set by the Central Bank. The average monthly inflation in 2011 was only 0.4 percent, or twice as low as the respective indicator in CPI YoY CBA policy rate, eop (RHS) 2010. 2 External Sector Performance Figure 5: Net FDI remains moderate (Net FDI, % of GDP) A favorable external environment helped 16 reduce external imbalances. The mining sector 14 and metallic manufacturing production accounted 12 for more than half of merchandise exports. The 10 export of minerals and metallic products follows 8 London Metal Exchange (LME) spot price for 6 copper very closely; decline in prices of base metals 4 may entail contraction of these exports. Metallic 2 minerals go primarily to the European Union 0 (mostly Germany), but the share of EU in total 2008Q1 2008Q3 2009Q1 2009Q3 2010Q1 2010Q2 2010Q3 2010Q4 2011Q1 2011Q2 2011Q3 2008Q2 2008Q4 2009Q2 2009Q4 exports declined slightly in 2011. Exports expanded to relatively new markets, such Further improvement of the business environment as Switzerland and Canada. The share of exports to is necessary to step-up FDI inflows. According to these countries increased by 3.4 percent in 2011. the Doing Business-2012 report, last year Armenia Merchandise exports and imports grew by 27.7 was among the top reformers worldwide improving percent (to US$ 1.3 billion) and 10.7 percent (to its position by six points in the global ranking. US$ 4.2 billion), respectively. Since imports in dollar terms are three times higher than exports, During the first nine months of 2011, the FDI the trade deficit widened by 4.2 percent and inflows into the real sector amounted to US$ 462.5 reached –US$ 2.8 billion. million; about 58 percent of which originated from Russia. Production of base metals, telecom, and Remittances increased by around 20 percent and energy attracted 29.3 percent, 21.5 percent, and reached 12.1 percent of GDP in 2011 contributing 15.1 percent of the total FDI respectively in to the improvement of the current account deficit January-December of 2011. At about 6 to 7 percent by 2.6 percentage points. of GDP, FDI inflows are quite respectable but have sizeable upward potential. Figure 4: Export of minerals reflected the trend of copper prices (Exports of mineral (mln USD) and the LME copper Fiscal Sector Performance price index (2007=100%)) The fiscal deficit improved further from 5 75.0 150.0 percent in 2010 to an estimated 3 percent in 70.0 140.0 2011. After the sharp deterioration from 0.7 65.0 percent of GDP in 2008 to 7.6 percent of GDP in 130.0 60.0 2009, the overall deficit has gradually improved 55.0 120.0 reaching 5.0 percent by the end of 2010. The deficit 50.0 45.0 110.0 shrank further last year to 2.7 percent, due to 40.0 100.0 economic rebound and an ambitious fiscal consolidation plan implemented. Ma y-11 Ja n-11 Feb-11 Sep-11 Ma r-11 Jun-11 Apr-11 Aug-11 Nov-11 Oct-11 Dec-11 Jul-11 Tax collections were in line with the planned Export of minerals and base metals amount, exceeding US$ 2 billion in 2011, though Copper price index (2007=100%), (RHS) the tax/GDP ratio declined to 19.3 percent due to higher-than-expected GDP and VAT refund. The tax collections in January-February are keeping up The medium term outlook for Armenia’s current with the plan, and mild inflationary environment account deficit largely depends on global contributes to the growth of tax revenue in real developments. With exports and remittances highly terms. dependent on international prices for commodities, the Armenian economy might suffer from any The key focus of the fiscal policy in 2011 was the adverse shock to terms of trade from global public finance consolidation on the background of developments. maintaining the share of pro-poor social spending. 3 On the revenue side, the major policy change was Figure 6: Growth in lending was relatively bringing the import of petroleum and diesel under stable around 30 percent, and growth of the general taxation regime, though the VAT rate deposits accelerated during the year. for diesel was set at 0 percent. On the expenditures (Growth of lending and deposits (year-on-year),%) side, the Government managed to protect pensions 50.0 and other priority social spending. In the 2011 45.0 40.0 budget the share of priority social programs 35.0 30.0 increased to 29.6 percent, relative to 29.1 percent in 25.0 the 2010 execution. The allocation to priority social 20.0 15.0 programs also increased as a share of GDP, from 10.0 5.0 7.8 to 8.2 percent over the same period. 0.0 Ma y-11 Ja n-11 Ja n-12 Feb-11 Sep-11 Ma r-11 Jun-11 Apr-11 Aug-11 Nov-11 Oct-11 Dec-11 Jul-11 The 2012 approved budget continued addressing the fiscal consolidation agenda expected to be Loans Deposits driven by the revenue collection efforts. The Government introduced a tax policy reform At end-2011, total banking sector assets amounted package targeted at increasing tax revenues by 100 to US$ 5.4 billion, or 59 percent of GDP. billion AMD. The changes include bringing retail Dollarization remains high. Despite higher risk of fuel under the general taxation regime, weights and provisioning on foreign exchange (FX) introducing more progressive personal income loans, FX credit continues to grow twice as fast as taxation (introduction of additional bracket), dram lending, as banks continued to draw down increasing the minimum level of social excess reserves at the CBA and accessed credit contribution, introducing a new tax on luxury cars lines with International Financial Institutions (IFIs) and premium alcohol, and increasing the and parent banks. To address this dollarization, the presumptive tax for casinos. The priority social Central Bank gradually changed the provisioning spending will continue to be protected, maintaining for the foreign exchange-denominated deposits, the share of about 29 percent in total expenditures. moving from the foreign currency to fully local The share of deficit in GDP is also expected to stay currency-denominated provisioning. Despite this below 3 percent. policy measure, the situation remained almost unchanged, and as of January 2012 the foreign exchange-denominated deposits increased by 36 Financial Sector Developments percent and still accounted for about 70 percent of total deposits. The Armenian banking sector is dominated by foreign banks. The banking system comprises 22 Figure 7: Dollarization remains high banks operating with 432 branches. Fifteen of (Share of foreign currency-denominated deposits, %) them are majority-foreign-owned, accounting for 70.5 about 69 percent of total banking sector assets. The 70.0 banking sector is highly fragmented given the small 69.5 size of the country. The largest bank (ACBA-Credit 69.0 Agricole) held 10.5 percent of assets, 11.6 percent 68.5 of loans, and 7.8 percent of deposits at end-2011. 68.0 The banking sector is small in size, and financial 67.5 penetration remains low, despite rapid credit 67.0 expansion in recent years. 66.5 Ja n-11 Ja n-12 Ma r-11 Ma y-11 Jun-11 Nov-11 Oct-11 Dec-11 Jul-11 Feb-11 Sep-11 Apr-11 Aug-11 Credit to the private sector grew by around 30 percent in 2011. Before the 2009 crisis, the financial depth indicators in Armenia were low The banking sector loan portfolio grew by about 35 even for developing countries’ standards, with the percent and deposits by 40 percent (net of FX credit-to-GDP ratio standing below 10 percent effects) during 2011. Nevertheless, banking sector while the economy was growing by double-digits. non-performing loans (NPLs) show a stabilizing This was attributed to both a conservative banking trend after reaching a peak in the middle of 2009. system and reliance on remittances rather than on On average, NPLs were 5.32 percent at the end of loans as a source of financing. By 2011, financial 2011, compared to 6.31 percent in 2010 and 6.6 intermediation deepened to 30 percent. percent in 2009. 4 The Armenian banking system remains well Armenia’s recent gains in living standards and capitalized and profitable: aggregate capital poverty reduction have been partly offset by the adequacy ratio (CAR) remained relatively high at financial crisis. Between 1999 and 2008, poverty 19.6 percent and return on equity (ROE) reached incidence was halved, from 56 percent to 27.6 9.8 percent at end-2011. Owing to a rise in percent, lifting over one million Armenians out of economic activity and a rebound in remittance poverty. But in just two years, about 30 percent of flows, the Armenian banking system continued to this reduction has been reversed. The effect of the show signs of recovery in 2011 (including strong crisis on poverty has been dramatic, with 270,000 lending and deposit growth, lower non-performing more people joining the ranks of the poor between loans, and improving profitability). 2008 and 2010, raising the number of the poor in 2010 to around 1.2 million. The poverty headcount Labor Market and Poverty Developments increased from 27.6 percent in 2008 to 35.8 percent in 2010, an increase of 8.2 percentage points. Both In 2011, employment and wage growth were rural and urban areas saw these trends. marginal. Officially, registered unemployment declined from 6.7 percent in January 2011 to 5.9 Figure 9: Changes in rural and urban poverty percent in December 2011. In absolute numbers, in the aftermath of the crisis the reduction in the number of registered (Share of population, %) unemployed people was 10,500 while the increase of employment was only 4,800 people. This suggests that the reduction of the unemployed might have been partially induced by people that had to unregister from the system due to existing limitations on eligibility for unemployment benefits. Furthermore, the official employment figures do not fully capture the real situation of the unemployment, which has been estimated at 19 percent in 2010 based on the International Labor Organization (ILO) methodology. Wages increased by only 0.8 percent in real terms throughout 2011. The increase of wages during 2011 was higher in the public than in the private However, as growth picks up, poverty will likely sector. This partly reflects the automatic start falling. Growth prospects are directly linked to mechanism for wage increases embedded in the the global economic recovery as well as to the government pay system. Another reason might deepening of domestic reforms. Targeted social have been the poor performance of the expenditures and pension increases have supported construction sector. In particular, the monthly incomes of the poor. wages in construction and real estate transactions declined by 3.3 percent and 4.3 percent, respectively. The inflation, although moderate by Public Sector/Governance the end of 2011, largely offset the increase of wages. The civil service system was established in Armenia in 2002 with the adoption of the Law Figure 8: Private sector monthly wage growth on Civil Service. The reform supported the clear lagged behind public sector separation of the administrative and political offices. (Real year-on-year growth of monthly wages in public Several strategic papers were developed to inform and private sectors, %) the public sector reform process. 8.0 6.0 Starting in 2011, the state budget is planned in a 4.0 2.0 program-based budgeting format. Public financial 0.0 management reforms are progressing in several Jan-11 Mar-11 May-11 Jun-11 Nov-11 other areas, in particular internal and external audits, Oct-11 Dec-11 Jul-11 Feb-11 Sep-11 Apr-11 Aug-11 -2.0 -4.0 -6.0 public accounting, public procurement and treasury -8.0 administration. The Public Financial Management -10.0 Strategy was approved by the Government in -12.0 October 2010 to further advance the reforms in this Private Public 5 area. Separate strategies for tax policy and tax various Institutional Development Fund grants. The administration are being updated on rolling bases. ongoing judicial reforms have been supported through the Second Judicial Reform Project and The Law on Public Service adopted in May 2011 Dutch/Japanese Policy and Human Resources rolled out human resource management principles Development (PHRD) co-financing grants. originally introduced in core Civil Service (about 45 civil service bodies) to cover other fragments of public service. The law also introduced common Infrastructure Development rules for conflict of interest management in the public sector. Following the adoption of the Law on Energy Public Service, the Commission on the Ethics of High-Ranking Officials was established in January Armenia’s energy sector has moved from severe 2012 to be in charge of conflict of interest, income crisis to a current state of stability that is more and asset declarations from about 500 highest level characteristic of developed countries than officials from all the branches of power, emerging markets. A combination of policy, legal, independent commissions, and local governments regulatory and institutional reforms has rendered with population above 50,000. remarkable results: improvements in operating efficiency have helped create commercially viable The Government has recently established a special service providers, technical and non-technical line Regulatory Reform Unit to perform a regulatory losses have decreased, while collections have guillotine exercise. The Regulatory Guillotine increased to nearly 100 percent of sales. initiative is a multi-donor project and will support the Armenian Government during the initial round However, Armenia faces three principal challenges of simplifying and streamlining the legal framework in meeting these energy sector objectives: (i) An and regulations. The World Bank is supporting this emerging supply gap: Armenia will need at least through an Institutional Development Fund (IDF) 800 MW of new generating capacity by 2017 as the grant. old, under-maintained energy infrastructure is retired and demand continues to grow steadily; (ii) A significant reform agenda was set in the judicial Maintaining energy supply reliability: Heavy sector with the adoption of the Judicial Code in reliance on imported fuels and underdeveloped 2006. Among the key changes made, it is necessary regional interconnections put Armenia at risk of to highlight that (i) ensuring consistent supply interruptions, price fluctuations, and possible interpretation of laws became the main function of outages. Fuel for more than 90 percent of Armenia’s the Cassation Court, decisions of which are now energy needs is imported. Armenia is dependent on binding for lower instance courts hearing similar the import of hydrocarbons for all of its transport cases, and (ii) the Judicial Department has been fuel, all gas used for heating (whether industrial or established as the main institution responsible for residential) and cooking, and all of the gas used for court administration and the newly introduced generating one-third of the country’s electricity; (iii) professional judicial service at courts. The mid-term Maintaining affordable tariffs: Rising fuel prices priorities of judicial reforms were reflected in the and the need for new, more expensive generating 2009-2011 Judicial Reform Strategy. The 2012-2016 units may jeopardize the affordability of electricity Judicial Reform Strategy with the 2012-2014 Action for low-income consumers. In 2009, Armenian Plan is pending adoption, and will be further households spent roughly 8 percent of their total updated on rolling bases. budgets on electricity and gas. This percentage has already increased because of the increase in energy E-government is an overarching direction in all tariffs and the decline in GDP per capita. public sector reforms supported by the World Bank, European Union and other donors (both the The World Bank’s assistance in this area aims at executive and judicial branches of power have helping Armenia meet the above challenges and introduced their own e-government portals, with build on the current support. The Bank supports growing number of services and information improvement of electricity supply reliability by available on-line). contributing a US$ 39 million IBRD loan to rehabilitate around 230 km section of the electricity The World Bank has been supporting the ongoing transmission network backbone. The Bank is also reforms in the area of public administration in the supporting improvement of energy efficiency of executive branch through the Public Sector social and other public facilities (e.g. schools, Modernization Projects 1 and 2 (PSMP 1-2), kindergartens, hospitals, municipal buildings) Development Policy Operation (DPO) series and through a US$ 1.82 million Global Environmental 6 Facility (GEF) grant. The grant, coupled with US$ 8 allocations for financing the construction, million of Government co-financing, will support rehabilitation and maintenance of the road network. energy efficiency investments in social and other public facilities as well as the creation of enabling Improvement of the road network for rural environment for energy efficiency for the public communities has been one of the key objectives of sector. the Government in the transport sector. These roads are called “lifeline” roads and comprise some The Bank also administers a US$ 1.5 million GEF 3,014 km of Armenia’s 7,704 km non-urban roads. grant that finances investigation works in potential As part of its anti-crisis policy aimed at creating geothermal sites in Armenia. In 2006-2011, the Bank temporary employment through investment in has also been supporting the development of public works, the Government embarked on a renewable energy in Armenia by contributing US$ 8 program to make significant investments in the million (US$ 3 million GEF grant and US$ 5 million improvement of the “lifeline” road network. The IDA credit) to a US$ 25 million multi-lateral World Bank is supporting the Government with the financing package for technical assistance to remove improvement of the rural road network through the institutional and regulatory barriers to small scale Lifeline Roads Improvement Project and two additional renewable projects, and for on-lending for small investments with total Bank financing of US$ 101.6 hydropower and wind power projects. million. The World Bank also supported Armenia in The Bank also provides technical assistance to increasing access to safe, clean, and affordable gas- strengthen the in-house technical capacity of the based heating in urban multi-apartment buildings Armenian Roads Directorate, upgrade the road and schools through a US$ 15 million IDA credit. construction standards, improve the road safety, enhance the sustainability of road financing and Transmission line supporting a newly management and adopt new road design and constructed hydro power plant in Garni area, maintenance technologies and approaches. Kotayk region The Lifeline Roads Improvement Project has reconnected Armenia’s isolated rural communities to their urban centers. Roads The road network is essential for the country’s sustainable economic development, since Water Armenia is a land-locked country with limited transport routes. The road transport network has Over the past decade, the Government has significant impact on the country’s economic strived to improve access, reliability and quality competitiveness, and to a large degree determines of the drinking water and its infrastructure. the success of the export orientation of the Considerable progress has been made in reforming economy. the sector. However, non-revenue water remains high and is still a concern. Cost recovery is the long- The Government has prioritized the rehabilitation term development issue of the drinking water and reconstruction of 7,704 km of roads as reflected system. Currently drinking water and sanitation in the Transport Sector Strategy and the Sustainable tariffs do not cover the costs, and in all areas except Development Program. In the past five years the Yerevan, they do not even cover the recurrent costs. Government significantly increased the state budget 7 Affordability is the main reason for not switching to continue the reforms started in the sector and place cost recovery tariffs. larger focus on water management issues, including wider use of modern irrigation techniques and more In recognition of the water sector’s strong potential efficient use of water. This may help reduce water and the vital role it plays in the social safety net, the delivery costs and increase sustainability of the World Bank has attached special attention to irrigation sector. reforms in the sector. The Bank has supported Armenia’s efforts to provide safe and constant water The World Bank supports Armenia’s I&D sector supply and reduce environmental pollution through through the Irrigation Rehabilitation Emergency Project water and wastewater management projects (US$ 50 (IREP) and its Additional Financing effective since million for Yerevan and US$ 58 for the areas outside December 2011. Yerevan). Over 332,000 households in Yerevan and 264,000 households in the regions have benefitted Temporary employment under IREP generated from improvements in the duration of water supply an estimated US$ 5.4 million in wages. and water quality. The use of Public Private Partnerships (PPP) in the water and wastewater sector in Armenia has been an example of progressive sector development. While recognizing that the main reason for the poor water services was the management of the available water resources, the World Bank and the Government of Armenia introduced an example of a performance- based management contract for Yerevan. Building on the success of this, the Government opted for increased private sector participation – a lease contract for ten years, supported by the second IDA project in Yerevan. Later a PPP model for urban areas outside Yerevan was introduced, covering about 33 percent of the population. Upon completion of the management contract in 2013, the Government plans a lease contract for the Armenia Water Sewage Company. Figure 10 Irrigation and Drainage Key Achieved and Expected Results The Government is working towards increasing irrigated areas, and consequently rural incomes, by rehabilitating the country’s irrigation and drainage (I&D) infrastructure. Agriculture is an important source of livelihood, employing 40 percent of the population and contributing about 20 percent of the GDP. More than 80 percent of agricultural GDP is generated from irrigated lands. Thus, deterioration of the irrigation infrastructure threatens rural employment and rural incomes. Rural poverty, at 34.9 percent1, is higher than in urban areas. The Irrigation and Drainage sector continues to be a major development challenge for the Government. While much has been achieved, the needs for irrigation rehabilitation investments in Armenia remain high. Future irrigation projects should 1 According to the recent Poverty Update (March 2011), rural poverty is estimated at 40 percent at the end of 1st half of 2010. 8 Agriculture in 2008. Also, the role of SMEs is crucial in ensuring Due to weather vulnerability and marketing the high level of employment in the economy. In challenges, agriculture growth rates fluctuated 2010, the SME sector employment as percent of considerably over the last decade, contrary to the total employment was slightly increased to 42.2 steady growth pattern of the whole economy. percent and remained almost at the same level in However, agriculture has maintained its central 2010. importance to employment and rural incomes, as well as to domestic food supply, and as a source for Figure 11 expansion of exports in food products. Share of SME sector in GDP (%) Some 335,000 households are involved in the sector, 50% with an average landholding of around 1.4 hectares 40% per household and a diversified production system involving both crops and livestock. The Agro- 30% % of GDP processing sub-sector is the main employer in rural areas. 20% The economic downturn increased the vulnerability 10% of small-scale operators, by making them more dependent on livestock and natural resources for 0% their livelihoods. Besides, the livestock sector is 2002 2003 2004 2005 2006 2007 2008 2009 2010 facing serious challenges such as unsustainable pasture management and underutilization, persistent livestock diseases, processing and marketing The World Bank supports SME development constraints, and reduced productivity. Additionally, through providing financial resources to the banking there are huge fluctuations in supply of dairy system. The Bank’s Access to Finance for SMEs products, with most milk produced in the summer (AFSME) Project makes available additional months and almost no production in winter and resources for banks to lend to SMEs. Since the spring. launch of the AFSME project in April 2009, AMD 21.3 billion have been disbursed cumulatively (as of These challenges limit Armenia’s capacity to exploit end-2011); about 60 percent of this is addressed to opportunities stemming from increasing domestic widening access to finance for SMEs in the regions. demand. Imported meat now accounts for half of national meat consumption due to low livestock sector productivity, and an unreliable supply of meat ICT sector and innovation and milk. The dairy and meat sectors are competitive on the domestic markets. However Information Technology (IT) has become one there is scope for strengthening their competitive of the important sectors of the Armenian position through addressing productivity and supply economy, contributing to the technological constraints. innovation and productivity growth in the country. In 2008, the Government adopted the IT The Bank’s portfolio includes Community Agriculture sector development strategy, which aims to expand Resource Management and Competitiveness Project telecommunications and business incubation (CARMAC) effective since July 2011. infrastructure, improving the productivity and expanding support and financing mechanisms for Information and Communication Technology (ICT) Private Sector Development start‐ups. In 2010, the turnover of the Armenian software and services sector reached around US$ The Small and Medium Enterprise (SME) sector 150 million resulting in 25 percent Compound continues to be one of the major development Annual Growth Rate (CAGR) during 1998‐2010. issues for the Government, as SMEs play an This turnover figure constitutes 1.7 percent of important role in the economy of Armenia. Armenia’s nominal GDP. According to the calculations of the Development National Center (DNC) in 2010, SMEs contributed about 43 percent of the country’s GDP, in comparison to 42.5 percent in 2009 and 41.7 percent 9 Figure 12 contributed to the establishment and strengthening Armenian IT industry turnover of the necessary infrastructure for the ongoing reforms. The current project contributes to aligning the Higher Education System to the Bologna requirements by establishing and strengthening the National Education Quality Assurance System and developing a tertiary education management information system (TEMIS). Other important aspects of the project include supporting improvements in the quality of education through improved in-service teacher training and The World Bank is supporting the development of professional development, including training of the ICT sector under the E-Society and Innovation for school principals in effective leadership and Competitiveness (EIC) Project through improvement of management; supporting the implementation of the ICT infrastructure and enabling enterprise high school reform by providing computer literacy innovation on the basis of a competitive national training to librarians of 107 high schools, as well as IT/knowledge-intensive industry and an ICT- reforming pre-service teacher education through the equipped and adequately skilled society, including university academic partnership program between citizens, businesses and government. the Armenian State Pedagogical University and University of Oulu of Finland. In addition, the Bank helps facilitate one year Human Development preschool education for four-and-a-half to five-and- a-half year-old children to promote school readiness Education and equal opportunities at the start of general education. The project strengthens the quality and Quality is a lynchpin of education reforms, and finance of higher education through the the Government has already made considerable establishment of a Competitive Innovation Fund to progress by addressing structural reform needs. promote implementation of innovative and The establishment of a fully functional Assessment enhancement projects, thus improving the capacity and Testing Center (ATC) allowed the introduction of higher education institutions. Expansion of of a centrally-administered unified examination access to preschool education is critical for system, which resulted in a more equitable and enhancing pro-poor outcomes in the sector. As of transparent system for university entrance. The February 2012, 83 preschool facilities operated in education reforms also included the new National different communities throughout Armenia. The Curriculum, school-based assessment, use of project will contribute to creating preschool classes Information and Communication Technology (ICT) in 170 communities. in schools, and effective in-service training system. Such approach to quality reforms provided some Health early improvement of learning outcomes. The Trends in International Mathematics and Science The Government is in the midst of major Study-2007 (TIMSS-2007) showed that the quality healthcare reforms focusing on strengthening of the education system had increased – Armenia Primary Health Care (PHC), optimizing the was the only country in Europe and Central Asia extensive health services networks, enhancing region that obtained significantly better scores in all the health system governance and improving four categories in comparison to the results of 2003. the provider payment methods. The ultimate goal The World Bank supports the education sector is to improve the key health indicators of the through the Education Quality and Relevance Projects population, in which important steps have been (APL 1-2, US$ 44 million) and DPO. The first phase taken but further progress is needed. of the Education Quality and Relevance (EQR) Project supported the design of a new Curriculum The high level of private expenditures on health and Assessment system, provided teachers with remains a challenge. 50 percent of expenditures on training on new trends and changes in teaching health (year 2009) are out-of-pocket payments. This methodology and using ICT in education, as well as is partly caused by low public expenditures on 10 health, which accounted for only 1.4 percent of access to a qualified and well-motivated family GDP in 2010. doctor and nurse of his/her choice; (ii) consolidating the hospital sector to minimize waste The Bank supports the health sector through three of scarce resources and improve quality of care; and Heath System Modernization Projects (APL 1-2 and AF (iii) strengthening the Government’s competencies for APL 2, in the total amount of US$ 60 million), for effective stewardship in policy making, with the objectives of providing more accessible, regulation, oversight and public accountability to high quality and sustainable health care services to ensure targeted use of public resources in the population. The second phase of APL 2 accordance with the healthcare needs of the continues supporting the Government in: (i) population. completing the family-medicine based PHC reform to ensure that every Armenian citizen will have 11 IRRIGATION REHABILITATION EMERGENCY PROJECT - ADDITIONAL FINANCING Approved: October 25, 2011 Effective: December 13, 2011 Closing: June 30, 2013 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IBRD Loan 18.00 6.90 11.10 Government 3.40 of Armenia Beneficiaries 0.20 Total 21.60 6.90 11.10 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The Bank has been supporting the rehabilitation of the irrigation and drainage (I&D) infrastructure and institutional development process in the subsector in Armenia since 1995. While much has been achieved, irrigation rehabilitation investments in Armenia remain important and currently the Bank is the only donor in the sector. Project Objective The project is aimed at improving water-use efficiency in the selected irrigation schemes while also fostering immediate rural employment. These objectives can be achieved by rehabilitating around 50 km of main and secondary canal sections and another 63 km of tertiary networks to reduce water losses and, at the same time, providing limited assistance to strengthen the institutions managing the irrigation infrastructure. Key Achieved and Expected Results: Key Achieved and Expected Results in Graph 50 km of all identified sections of the selected main and secondary canals in Aragatsotn, Kotayk, Shirak, Lori, Ararat, Meters and Armavir regions to be rehabilitated. As a result, water rehabilitated losses between primary intake and on-farm system will be reduced by 34.4 million cubic meters improving irrigation on about 52,000 hectares (ha) of land. Water losses 3 (million m ) 63 km of tertiary networks in 19 communities of Lori, Shirak, Gegharkunik, and Armavir regions to be rehabilitated. As a result, water losses will be reduced by 9.9 million cubic meters improving existing irrigation water services on over 2,500 ha of land.  In total, the project rehabilitation activities will generate 7,000 person-months of temporary jobs. The value of wages generated by this temporary employment is estimated to be in the range of US$ 3.7. About 2,100 agricultural jobs are estimated to be created in two years after project completion when higher-value crops will replace low-value crops. It is estimated that the total area returned to irrigation as a result of project interventions may reach about 6,500 ha. Key partners The World Bank team had developed a long-standing partnership with the Millennium Challenge Corporation (MCC), since the Bank assisted MCC’s efforts to enter the Irrigation and Drainage (I&D) sector by providing plans, analyses and other documents that had been developed under an earlier irrigation project. But due to increase of costs of construction materials and labor, MCC could not finance the rehabilitation of all systems for which it had prepared the technical designs, and re-scoped its program in November 2008. MCC shared the technical designs with the Bank, which formed the basis for the project. 12 LIFELINE ROADS IMPROVEMENT PROJECT Key Dates: LRIP Approval: February 24, 2009 LRIP Closing: December 31, 2010 LRIP Additional Financing I Closing: December 31, 2011 LRIP Additional Financing II Closing: December 31, 2013 Financing in million US dollars: Financier Financing Disbursed* Undisbursed IDA Credit 25.00 24.99 0.001 IBRD Loans 76.60 59.33 17.27 Government 24.48 of Armenia Total 126.08 84.32 17.271 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The accessibility of roads connecting the rural settlements to the major road networks is limited, reducing the economic and social development opportunities of rural communities. Thus, the Government of Armenia decided that each community should have at least one “lifeline road” connected to an interstate highway. The total length of the lifeline road network is 3,014 km, and over 60 percent of those roads are in poor condition. Moreover, the recent crisis resulted in a significant increase of unemployment in rural areas, where a handful of industrial companies scaled back their operations, thus necessitating the Government’s intervention to create rural jobs. Project Objective The Lifeline Roads Improvement Project aimed at rehabilitating a total of 430 km of lifeline roads in 12 regions of Armenia in order to reduce the time required for travelling on those roads, and to generate local employment through use of labor-intensive construction technologies. The project used cost-effective designs in accordance with actual traffic needs to ensure that longer lengths of roads can be rehabilitated without compromising technical integrities. Key Results  A total of 290 km of lifeline roads with lengths of 1 to 14 km rehabilitated.  Over 27,000 person-months of employment created.  Transfer of knowledge and technologies. The local contractors gained experience in designing and rehabilitating low-volume rural roads in accordance with international standards for such roads.  Improved road safety. All roads passing through residential areas were provided with sidewalks and designs to allow the use of facilities by disabled people. Key Partners The Bank team works closely with the (i) Ministry of Transport and Communication (MoTC), which is responsible for overall policy setting and for overall implementation of the Project; (ii) Transport Project Implementation Unit State Institution (Transport PIU), charged with coordination and management of implementation activities on a day- to-day basis; and (iii) Armenian Roads Directorate State Non-Commercial Organization (ARD), which is responsible for the technical aspects of the project implementation. Key Development Partner includes the Asian Development Bank (ADB), which is implementing a similar project and with whom the Bank team coordinated closely on policy issues. 13 MUNICIPAL WATER PROJECT Approved: February 21, 2012 Effective: Expected end-March, 2012 Closing: June 30, 2015 Financing in million US Dollars: Financier Financing Undisbursed* IBRD Loan 15.00 Government of Armenia 3.00 Total 18.00 18.00 *World Bank disbursements as of March, 2012. Challenge For many years after the collapse of the Soviet Union, most of the water supply and sanitation systems in Armenia were in a serious state of disrepair. Despite an abundance of water in the country, water was available only a few hours a day in most cities and villages and at low pressure. Over the past decade, GoA has succeeded in improving access, reliability and quality of drinking water service with increased use of public-private partnerships (PPP), which has brought about higher efficiency and improvements in quality of service to customers. Considerable progress has been made in the delivery of water services in small and medium-sized towns in Armenia. Despite such improvements, the sector is still facing some challenges. Project Objective The Project Development Objective is to support improvement of the quality and availability of water supply in selected service areas of the Armenian Water and Sewerage Company (AWSC). Key Expected Results: International Development Agency (IDA) Core Indicators:  Increase weighted average daily supply of drinking water service in selected areas from 12.30 hours daily to 16.60 Expected in 2015: hours daily.  The number of piped household water  Decrease weighted average non-revenue water in selected connections benefiting from the rehabilitation areas from 83.50 percent to 70 percent. works undertaken by the project is 33,609.  Increase ratio of billing and collection from 93.50 percent to  The number of people in rural areas provided with 98 percent. access to improved water sources under the  Decrease annual electricity consumption from 0.23 to 0.17 project comprises 33,328 people. KW/m3.  The number of people in urban areas provided  Decrease amount of water production from 752 l/c/d to with access to improved water sources under the 489 l/c/d. project reaches 99,263 people. Key Partners: The Bank team works closely with the (i) State Committee on Water Economy (SCWE) and the Ministry of Territorial Administration. SCWE reports to the Ministry and is responsible for overall policy setting in water and irrigation sectors; and (ii) Armenia Water and Sewerage Company, a water utility outside the Yerevan service area, which covers about 33 percent of the country’s population, and implementer of the MWP. Key Development Partners included the Asian Development Bank (ADB), KfW, and USAID. The Bank coordinates with ADB on the water sector reforms, particularly on exchange of information on mutual efforts in AWSC service area. EBRD invests in five treatment plants in Sevan region. KfW is financing water supply investments in the cities of Armavir, Vanadzor and Gyumri. The Bank works closely with many donors to coordinate investments in the water and wastewater sector, and these efforts bode well for significant future improvement of the sector. 14 MUNICIPAL WATER AND WASTEWATER PROJECT- ADDITIONAL FINANCING Key Dates: Approved: October 30, 2008 Effective: April 20, 2009 Closing: February 28, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 20.00 19.84 0.04 Government 6.80 of Armenia Total 26.80 19.84 0.04 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The water supply system in Armenia suffered from systemic problems, associated with the poor condition of water and wastewater networks, limited institutional capacity, and weak financial performance of water supply and sanitation utilities. Over the past decade, the Government of Armenia has strived to improve access, reliability and quality of the drinking water and its infrastructure. Considerable progress has been made in reforming the sector. Nevertheless, most of the water supply and sanitation systems in Armenia are still in a state of disrepair. Although the water resource balance in many parts of the country has improved since the 1980s, and despite the progress in improving water supply in the areas supported by private sector participation, the institutional framework for sustainable water supply delivery in most parts of Armenia remains poor. Project Objective The project objective is to improve the quality of water and wastewater services in the Armenia Water and Wastewater Company (AWSC) Service Area by providing efficient and sustainable water and wastewater services and strengthening the capacity and sustainability of AWSC. Key Results:  The average number of daily hours of drinking water service increased significantly, from the average 6 hours/day in 2004 to 15 hours/day (end of project target met).  Percentage of cities with minimal daily hours of water supply service increased from 68 percent at baseline to 94 percent now (end of project target is 90 percent).  AWSC and its branches improved financial sustainability; revenue collection increased significantly (from 47.9 percent in 2004 to over 100 percent in February, 2012).  Percentage of individual subscribers billed on the basis of metered consumption increased from 40 percent at baseline to 82.2 percent now (end of project target is 77 percent).  The bacteriological safety compliance increased from 93 percent at baseline to 98.2 percent now (end of project target met). Key Partners The Bank team works closely with the (i) SCWE and the Ministry of Territorial Administration. SCWE reports to the Ministry and is responsible for overall policy setting in water and irrigation sectors; (ii) Armenia Water and Sewerage Company, a water utility outside the Yerevan service area, which covers about 33 percent of the country’s population, and implementer of the MWW Project; (iii) Water Sector Development and Institutional Improvements Project Management Unit, charged with monitoring of the Management Contract and coordination of implementation activities and procurement and financial management of the MWW Project. Key Development Partners included the Asian Development Bank (ADB), KfW, EBRD and USAID. The Bank coordinates with ADB on the water sector reforms, particularly on exchange of information on mutual efforts in AWSC service area. EBRD invests in five treatment plants in the Sevan region. KfW is financing water supply investments in cities of Armavir, Vanadzor and Gyumri. 15 ELECTRICITY SUPPLY RELIABILITY PROJECT Key Dates: Approved: May 26, 2011 Effective: By Sep. 29, 2011 (estimated) Closing: June 30, 2016 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IBRD Loan 39.00 0.75 38.25 Government 13.00 of Armenia Total 52.00 0.75 38.25 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge Armenia’s power transmission infrastructure is old and under-maintained. The average age of transmission assets is 45 years. Some sections of the 220 kilovolt power transmission backbone are in urgent need of rehabilitation. The Government’s Energy Sector Strategy and the Sustainable Development Program recognize this challenge. Thus, increase of the power supply reliability is among the key strategic objectives of the sector. Therefore, the Government prioritizes the replacement of a section of the power transmission backbone, the transmission line connecting two key generation centers in the central part of the country (Hrazdan Thermal Power Plant) and in the South (Vorotan Cascade of hydro power plants), and serving large electricity consumers in the Central-Eastern part of the country. Replacement of the targeted section of the transmission line is critical since it is in extreme disrepair and jeopardizes reliability of power supply and overall network stability. The line was constructed in 1956-1958 and has been in service since then. Conductors, pylons, insulators and other key pieces of infrastructure are obsolete and need replacement. Project Objective The project development objective is to increase the reliability and capacity of the transmission network. Key Results The project became effective in November 2011. The procurement of the contractor for design, supply and installation of the targeted section of the transmission line is underway and expected to be completed by the end of June 2012. Key Partners The Bank team works closely with the (i) High Voltage Electric Networks of Armenia, the power transmission company responsible for construction, operation and maintenance of the high-voltage power transmission network of the country; (ii) Ministry of Energy and Natural Resources, which is responsible for overall policy setting. 16 COMMUNITY AGRICULTURAL RESOURCE MANAGEMENT AND COMPETITIVENESS PROJECT Key Dates: Approved: March 22, 2011 Effective: July 26, 2011 Closing: September 30, 2016 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 16.00 6.97 9.03 Government of 5.33 Armenia Total 21.33 6.97 9.03 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The livestock sector in Armenia faces serious challenges such as unsustainable pasture management and underutilization, persistent livestock diseases, processing and marketing constraints, and reduced productivity. This project builds on the World Bank experience and successes in agriculture, rural development, pastures and livestock management, and participatory community development to help Armenia address these urgent challenges and provide investment support. Project Objective The project development objective is to improve productivity and sustainability of pasture/livestock livelihood systems in selected communities. This would be evidenced by: (i) increased livestock productivity as measured by milk productivity and increase in daily animal weight gain; (ii) increased efficiency of communal pasture management, as measured by increased communal budgetary revenues from lease of pastures; (iii) increased farm sales from livestock; and (iv) increased pasture management effectiveness. Key Achieved and Expected Results:  Supporting services for farmers involved in livestock production are being improved and as a result livestock productivity measured by milk productivity and by growth rates of animals will increase.  Efficient and sustainable community-managed pasture/fodder-based livestock production systems are introduced in selected mountainous communities through establishing farmers associations and leasing pastures and grasslands. 38 Pasture Users Associations (PUAs) out of an expected 55 have been established and registered. Preparation of 21 pasture management plans has been completed and development of 17 is underway. Community funds for the implementation of these plans are being established.  Community animal health services are being improved through the mobilization of veterinarians with the provision of training. Disease control strategies are being implemented.  Activities for the Technology Assessment Program (TAP) are making good progress: 32 topics were selected, of which 31 have been completed successfully, with the other TAP terminated due to unfavorable weather conditions.  The first call for the Competitive Grant Program (CGP) proposals was made, and a total of 37 applications were submitted and eight were approved and received funding. In the second round, a total of 41 applications were received and nine were approved. Key Partners The Bank works closely with the Ministry of Agriculture, Ministry of Territorial Administration, Regional Governors, as well as Village Mayors and farmer groups. The Project is coordinated and implemented in close collaboration with a similar project – Rural Areas Development (RAD) financed by IFAD. The analytical work for the preparation of the Project served as the main basis for developing the Millennium Challenge Corporation (MCC) Program’s Water-to-Market Component. 17 ARMENIA GEOTHERMAL ENERGY PROJECT Key Dates: Approved: February 26, 2009 Effective: April 28, 2009 Closing: April 30, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed GEF Grant 1.5 0.63 0.87 Government 0.3 of Armenia Total 1.8 0.63 0.87 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The Republic of Armenia has limited energy resources to satisfy its needs and does not have fossil fuel reserves. Thermal and nuclear power generation account for about 70 percent of the total electricity generation and the country imports all of the fuel required for the operation of thermal and nuclear plants. Thus, the government prioritizes development of indigenous renewable energy resources as a means to increase energy diversification and achieve a higher degree of energy security. Armenia has an estimated 740 megawatt (MW) of small hydropower, wind and geothermal resources. The results of studies to estimate geothermal potential of the country suggest a high likelihood of the existence of geothermal resources, which could be used for electricity generation purposes. The optimism is justified by the broad presence of young volcanic areas, numerous outcrops of mineral waters and the activity of tectonic-magmatic processes with relatively small geological age. While the above-mentioned preliminary studies are encouraging regarding the overall potential of the country for development of geothermal resources, actual field investigations of specific sites either have not been undertaken or have been very limited in scope. Therefore, because of the lack of thorough site investigation works and no confirmed deposits, the private sector’s interest in the development of geothermal energy resources in Armenia has been very limited to date. The following prospective sites for further comprehensive field investigation works were proposed: (1) Karkar site, located on the Syunik plateau in the South Eastern part of Armenia, and (2) Gridzor site, located on the Gegham mountain plateau along the Western shore of Lake Sevan. Project Objective The project development objective is to assess the feasibility of exploratory drilling of one geothermal site with the estimated highest geothermal potential through comprehensive field investigation works. Key Result  Karkar was identified as the prospective geothermal site based on the results of the geological field investigation works and the magneto-telluric sounding works for Gridzor and Karkar sites.  A sophisticated three-dimensional magneto-telluric sounding study was conducted for Karkar site, which provided additional information and data on the potential geothermal resource. The results of this study will be used for assessment of economic and financial viability of the site, which combined with the results of the above study, will help to assess feasibility of exploratory drilling. Key Partners The Bank team works closely with the (i) Ministry of Energy and Natural Resources, which is responsible for overall policy setting; and (ii) Renewable Resources and Energy Efficiency Fund, which is in charge of the implementation of the project. 18 ACCESS TO FINANCE FOR SMALL AND MEDIUM ENTERPRISES PROJECT Key Dates: Approved : February 24, 2009 Effective: April 16, 2009 Closing: December 30, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IBRD Loan 50.00 45.12 4.88 Total 50.00 45.12 4.88 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The financial crisis and the resulting global liquidity squeeze have effectively blocked external borrowing for banks in many emerging markets, including Armenia. Foreign banks operating in Armenia did not continue funding their subsidiaries at prior levels. Many internationally-active banks were in the process of re-building capital and liquidity in their home markets. The loss of access to funds has reduced the ability of Armenia to sustain growth. As a result, domestic banks have become more reluctant to lend to Small and Medium Enterprises (SMEs). The rationale for advancing this wholesale credit line operation to SMEs is centered on strengthening their access to finance and improving the resilience of both Armenia’s private and financial sectors in the face of the impacts of the global financial crisis, declining economic growth and a sharp decline in remittances. Project Objective The project's development objective is to maintain or increase access to medium-term finance for Armenian small and medium enterprises. The project will positively impact SMEs and participating banks both during and beyond the implementation period (2009-2012). As a revolving facility with an initial five-year maturity, Participating Financial Institutions (PFIs) may recycle loans to additional SMEs before repayment to the Central Bank of Armenia (CBA). This will enable PFIs to finance a large number of sub-loans through the life of the AFSME facility. Key Results  The project implementation to date suggests that the objective to maintain SME access to medium-term finance through providing local currency denominated lending is being met. During the 2009 crisis, this credit line facility helped local banks maintain comfortable liquidity cushions with the share of liquid assets to total assets at 34 percent at end-2009 (29.5 percent and 28 percent as of end-2010 and end-2011, respectively). The AFSME project provided medium-term financial resources in Armenian Drams that allowed keeping dram-denominated lending at the same level during 2010, and the increase of it by 25 percent in 2011 made lending available to SMEs with more acceptable terms.  As of end-2011 loans have been provided cumulatively to about 3,830 SMEs across all regions and operating in trade, agricultural, production, and services sectors for both investment and working capital needs.  From the beginning of the Project, SMEs have received cumulatively more than US$ 55 million equivalent in local currency loans.  More than 60 percent of SMEs financed are from regions, or outside the capital city, with about 79 percent of total amount lent to small and micro borrowers (loan size less than AMD 33 mln).  The SME share in GDP has increased by 0.8 percent during the 2009 crisis to 42.5 percent and reached 43 percent in 2010. Key Partners The Bank team works closely with the (i) Central Bank of Armenia, which is responsible for overall policy setting in financial sector, (ii) German-Armenian Fund (GAF), the project implementation unit, and (iii) ten participating financial institutions. Key Development Partners included the USAID Financial Sector Deepening Project (FSDP) that supported the Project at the early stages during due-diligence of banks and providing a series of trainings on SME lending to the participant banks. 19 E-SOCIETY AND INNOVATION FOR COMPETITIVENESS (EIC) PROJECT Key Dates: Approved: November 30, 2010 Effective: May 18, 2011 Closing: December 31, 2014 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IBRD Loan 24.00 0.57 23.43 Government 6.00 of Armenia Total 30.00 0.57 23.43 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge While much has been achieved, the main challenge in the sector remains the lack of coordination of Information and Communication Technology (ICT) development efforts. Low level of Internet and PC penetration is still an issue for Armenia, causing major inequalities in access to modern ICTs between the capital city and rural areas. From the sector development prospective, the main constrains for the ICT business development and innovations generation are still the lack of adequate infrastructure for business incubation and low access to credit and commercial investments, particularly in the regions of Armenia. Project Objective The Project Development Objective is to address the constraints to competitive e-Society and enterprise innovation in Armenia by strengthening the underlying infrastructure and enabling environment. E-Society in the context of this project is defined as a society with greater access to ICTs (computers, broadband), improved enterprise-level ICT skills, growing and more competitive local knowledge and technology intensive industry. Key Expected Results:  Increased access to affordable broadband services for citizens, businesses and public institutions.  Citizens and businesses equipped with a tool for identification and authentication for electronic transactions.  Increased access to affordable computers, content and e-services for citizens.  Support innovation and technology start-ups through improved access to finance.  Gyumri Technology Center (GTC) established and contributing to the region’s enterprise innovation.  Enhanced capacity and growth of the IT/Knowledge-intensive sector. Key partners The World Bank team works closely with the Ministry of Economy and the PIUs - Enterprise Incubator Foundation (EIF), E-Governance Infrastructure Project Implementation Unit (EKENG), Foreign Financed Projects Management Center (FFPMC), National Competitiveness Foundation of Armenia (NCFA), which are responsible for implementation of the project. Key development partners Other donors currently do not have major specific projects in these areas but some of their projects have an indirect relation to the mentioned area, such as cluster development, SME development, improving regulatory environment, community building, etc. Particularly, the USAID-funded Competitive Armenian Private Sector (CAPS) Project that was completed recently supported the IT industry, as one of the identified competitive clusters, with a series of trainings, consultancy and other capacity-building activities. 20 SECOND JUDICIAL REFORM PROJECT Key Dates: Approved : March 8, 2007 Effective: July 5, 2007 Closing: December 31, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 23.48 23.17 0.30 PHRD co- 3.00 financing Grant Dutch co- 4. 84 financing Grant Government of 7.60 Armenia Total 38.92 23.17 0.30 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge While much has been achieved in the area of court administration, sustaining the introduced innovations is critical. To do so, the Republic of Armenia needs to invest necessary resources for the maintenance and service of the introduced systems and infrastructure. Nevertheless, the biggest challenge is still the change of mentality and improved capacity of judges to make the courts more efficient and transparent. Project Objective The project objectives are to improve the efficiency, reliability and transparency of judicial operations and services, and to further improve awareness of judicial services and access to legal and judicial information. Key Results in Graph (monthly statistics) Key Results  About 45 times more people have on-line access to the Armenian legislation through ARLIS legal database.  14 courthouses totaling 19,000 sq/m area have been rehabilitated under JRP-2.  30 public information kiosks providing access to judicial services and information were installed in Yerevan courts and selected administrative buildings. An additional 50 kiosks for the regions are procured and are being installed at additional locations. Since the introduction of the Datalex portal in late 2010 all relevant usage statistics (visits, users and pages viewed) grew more than 8 times. Key Partners The Bank team works closely with the (i) Ministry of Justice of the Republic of Armenia, which is responsible for overall policy setting, and its subordinate Enforcement Service Department (ESD) benefiting from the capacity building for enforcing judicial decisions; (ii) Council of Justice (CoJ) and Judicial Department (JD), main recipients of credit resources respectively in charge of judicial career and resource administration; and (iii) Judicial School (JS to be reorganized to Academy of Justice), charged with training of judges and judicial servants, etc. Key Development Partners included Governments of Japan and Netherlands who co-financed the project, and the EU, EC and USAID, with whom the Bank Team coordinated closely on activities supported under separate project components. 21 SECOND PUBLIC SECTOR MODERNIZATION PROJECT Key Dates:* Approved: March 16, 2010 Effective: July 26, 2010 Closing: July 31, 2015 Financing in million US Dollars: Financier Financing Disbursed** Undisbursed IBRD Loan 9.00 1.37 7.63 Government 2.54 of Armenia Total 11.54 1.37 7.63 * Information refers to PSMP II. First PSMP was closed on February 28, 2011 ** World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The basic challenge has been the change management. Civil service management became possible only due to strong government ownership, further progress towards introduction of work planning and performance and information management systems. The low level of public salaries remains the major challenge that will hinder the efficiency gains from introducing performance appraisal and pay systems. Project Objective The objective of the Project is to enhance the performance of public sector management for better service delivery by: i) strengthening institutional capacity in policy formulation; ii) maximizing the efficiency of human capital; and iii) developing information systems for internal work flow and external communication. Key Results Towards paperless office At the current stage of project implementation the most visible results include:  The Commission on Ethics of High-Ranking Officials was established in January 2012 as part of policy dialogue on conflict of interest management reform.  Automated Information Retrieval System in Traffic Police Service will be launched in April 2012.  Activities are to start on the introduction of an archiving system for the electronic document management system (Mulberry) operational in all ministries, all Governors offices, and in other public administration bodies (total 50 entities). Key Partners The Bank team is working closely with the (i) Office of the Government of the Republic of Armenia, which is the main project counterpart and has been leading the policy on public administration reforms; (ii) Civil Service Council of the Republic of Armenia (CSC) in charge of civil service reform and administration; (iii) Commission on Ethics of High-Ranking Officials, and (iv) Ministry of Territorial Administration, Ministry of Justice, Ministry of Foreign Affairs, Ministry of Energy and Natural Resources, selected service delivery units of Police where project will support functional reviews and business process reengineering. The ongoing PSMP II is rolling-out the main achievements under the first Project with greater emphasis on policy analyses and formulation. Key Development Partners include the EU (including advisory group), UNDP and USAID, which support related activities in the areas of electronic government, civil service reform, and regulatory guillotine. 22 SOCIAL INVESTMENT FUND III Key Dates: Approved: October 26, 2006 Closing: June 30, 2011 First Additional Financing Closing: June 30, 2011 Second Additional Financing Closing: March 31, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 25.00 26.12 0.00 IDA Credit 8.00 8.08 0.00 IBRD Loan 7.00 5.76 1.26 Government 6.67 of Armenia Communities 1.50 Sponsors 0.13 Total 48.3 39.96 1.26 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The Armenia Social Investment Fund (ASIF) III project was designed to support the Government in its continuing commitment to raise the living standards of the poor and vulnerable groups and fill up the major infrastructure gaps in order to have the poor receive the benefits from economic growth. Despite the strong economic growth before the crisis, Armenia was facing several critical vulnerabilities stemming from the global economic and financial crisis. To help respond to it, the authorities requested urgent support for small-scale infrastructure that would help generate employment. The Bank proposed to address the Government’s request to help mitigate the impact of the cris is by supporting activities that can be quickly and effectively scaled-up and implemented under the existing ASIF III Project. Project Objective The aim of the Project is to support the Government’s policy to raise living standards of poor and vulnerable groups through: i) Improving the quality and access, and increasing the coverage of community services and infrastructure in poor communities; ii) Promoting complementary institutional capacity building at the community and municipal level so as to improve the quality and sustainability of community investments and service delivery, increase accountability, and enhance greater stakeholder empowerment at the local level; and (iii) Creating employment associated with the provision of community infrastructure and services. Key Results  236 community infrastructure micro-projects (MPs) are completed, and another 29 are on-going. The completed and ongoing MPs and furniture production have so far created 519,000 job days of employment and US$ 8.7 million wage income. The total number of beneficiaries of completed MPs is estimated at about 1,062,974.  4,676 local community members (334 communities) received training on investment planning and management, 515 municipal officials from 105 communities received training on financial management.  Poverty mapping and ranking were last updated for 911 communities (871 rural and 47 urban) in December 2011. Key Partners The Bank team works closely with the (i) Ministry of Territorial Administration responsible for overall policy setting and providing implementation support; (ii) Ministry of Finance contributing to policy dialogue and ensuring the proper flow of funds and carries out financial monitoring of project activities; (iii) Ministry of Labor and Social Issues involved in policy dialogue and providing implementation support. Key Development Partners included UNHCR, All Armenian Fund, Armenian General Benevolent Union (AGBU), Aznavour pour l’Armenie (APA), IFAD, Kniths of Vardan (KoF), which have been involved under both matching fund arrangements and partial or full financing of community contributions. 23 HEALTH SYSTEM MODERNIZATION PROJECT APL 2 Key Dates: Approved: March 08 , 2007 Effective: June 06, 2007 Closing: December 31, 2012 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 22.0 22,64 0.3 Government of 7.17 Armenian communities 0.15 Yerevan State Medical 0.30 University Total 29.62 22,64 0.3 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenges There is a concern that people may postpone seeking medical care and use of services because of lack of resources, high out-of-pocket payments and perceived low quality of care, especially in rural areas. The main challenges in the health system are to ensure better access to health services, particularly for poor groups and regions, reallocation of the health budget towards Primary Health Care (PHC) and health service rationalization, including optimizing excess capacity in the hospital sector. Project Objective The APL2 of HSMP is focused on completing the family-medicine based PHC reform (launched in 1996) to ensure that every Armenian citizen will have access to a qualified and well-motivated family doctor and nurse of his/her choice; consolidating the hospital sector to minimize waste of scarce resources and improve quality of care; strengthening the Government’s competencies for effective stewardship in policy making, regulation, oversight and public accountability. Key Results  1,433 physicians were re-trained as family physicians. 1,592 nurses were re-trained as family nurses. About 90 percent of the population is covered with re-trained family medicine providers.  Infrastructure of 70 PHC facilities was improved (26 new constructions and 44 renovations) in rural areas.  200 PHC facilities were provided with a standard set of medical equipment, supplies, furniture and IT equipment.  Space vacated as a result of modernization in Yerevan hospitals is 15,577 sq/m, in regional hospitals – 13,303 sq/m.  726 managers of hospital facilities participated in management training courses. As a result, 48 regional hospitals have trained key management personnel.  7 regional Medical Centers (MCs) - Kotayk region Hrazdan MC (105,300 population), Tavush region Ijevan MC (49,200 population), Armavir region Armavir MC (121,500 population), Ararat region Ararat MC (95,300 population), Syunik region Goris MC (44,700 population), Aragatsotn region Aparan MC (22,300 population) and Gegհarkunik region Gavar MC (57,800 population) were renovated and provided with modern medical equipment and furniture. Also the Lori region Alaverdi MC (47,600 population) was provided with modern medical equipment and furniture. Civil works are currently in process in Shirak region Gyumri new Medical Center (146,000 population). Key Partners The Bank team works closely with the (i) Ministry of Health responsible for overall policy setting as well as for the implementation of the Bank financed projects; (ii) Ministry of Territorial Administration responsible for the programs on regional developments; local authorities and (iii) Ministry of Finance responsible for the Poverty Reduction Strategy/Sustainable Development Program as well as for mid-term expenditures projections and programmatic budgeting. Key Development Partners: The HSMP APL project team successfully collaborates with the USAID-funded project in the area of performance-based contracting for the Primary Health Care providers, improvement of Health Financing Management Information System (HFMIS) and quality assurance mechanisms. With the WHO, the project team collaborates in the development of Health Care Performance Assessment reports and co-payment strategy. UNICEF is a traditional partner in supporting the Mother and Child Health (MCH) programs. 24 SECOND EDUCATION QUALITY AND RELEVANCE PROJECT Key Dates: Approved: May 12, 2009 Effective: October 2, 2009 Closing: November 30, 2014 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 25.00 5.53 19.47 Government 6.26 of Armenia Total 31.26 5.53 19.47 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge Education has been a priority sector for public investment in Armenia since the late 1990s. The government has aimed to reduce poverty by increasing access to and improving quality of general secondary education, and boosting public spending on that sub- sector. The focused investment has contributed considerably to the development of general secondary education, but has also resulted in the relative neglect of other sub-sectors, i.e., preschool and tertiary education. The challenge the project addresses is to sustain and extend the accomplishments in general secondary education, which had been achieved under the first APL phase, through second- generation quality-oriented reforms, at the same time addressing equity and quality concerns in both preschool and tertiary education. Project Objective The second phase of the Education Quality and Relevance Project (EQRP) continues focusing on the reforms of the general secondary education system, also addressing key policy issues in both higher education and preschool education through: (i) enhancing school learning in general education and improving the school readiness of children entering primary education; and (ii) supporting the integration of the Armenian tertiary education system into the European Higher Education Area. More specifically, the project will support the increase in preschool enrollment for equal primary education start; improve quality of education through improved teacher education and professional development and continued integration of ICT in education; complete transfer to 12-year general education; establish and strengthen national quality assurance system for tertiary education; develop tertiary education management information system and strengthen the capacity to implement a sustainable higher education financing system. Key Results  Throughout 2010, 41 preschool micro-projects were established and made operational benefiting 1,250 students. During 2011, 83 additional preschool micro-projects have been signed with the potential of benefiting 1,300 additional students.  The project has supported the efforts to extend the existing school computer network to include 459 new schools in remote areas.  International Competitive Bidding (ICB) procurement has been conducted for the provision of hardware to the total of 1,360 schools, and results of ICB have been approved by the World Bank and the Government during 2011.  The project supported the Ministry of Education and Science in undertaking training of 6,000 teachers during 2011.  In June 2011, the Government adopted the higher education financing strategy designed with the technical support from the Project.  The need analysis of the Tertiary Education Management Information System (TEMIS), together with technical specifications for hardware equipment and software packages has been completed.  The Government decided to move forward with the implementation of the Competitive Innovation Fund (CIFT) designed under the project.  A long-term twinning arrangement has been made between the Armenia State Pedagogical University (and the Consortium of Pedagogical Institutes, including Yerevan State University) and the Oulu University from Finland for Technical Assistance for reforming pre-services teacher education in Armenia. Key Partners The Bank team works closely with the (i) Ministry of Education and Science responsible for overall policy setting as well as for the implementation of the Bank-financed Projects; (ii) Ministry of Finance responsible for deepening policy dialogue on financial implications of the proposed project as well as for ensuring the proper flow of funds and financial monitoring of project activities. Key Development Partners included UNICEF, which financially contributed to the project through preschool teachers’ training; Open Society Institute Armenia Foundation (OSIAF), which supported the Project's focusing on integration of ICT in teaching and learning. 25 SOCIAL PROTECTION ADMINISTRATION PROJECT Key Dates: Approved: June 10, 2004 Closing: May 31, 2013 Additional Financing: Approved February 25, 2010 Closing: May 31, 2013 Financing in million US Dollars: Financier Financing Disbursed* Undisbursed IDA Credit 5.15 5.53 - Government 0.56 of Armenia 5.00 IBRD Loan 1.10 0.45 4.55 Government of Armenia Total 11.81 5.98 4.45 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenge The main challenge is the creation of a modern social protection administration, which will provide not only effective administration and management of public social programs, but also become a basis for improved social services delivery to poor families and population groups. Project Objective The development objective is to improve the effectiveness (including quality, efficiency, user satisfaction, and financial viability) of the public employment, pension and social assistance systems through introduction of improved business processes, administrative procedures and techniques designed to enhance the social protection of the poor and vulnerable population groups. Key Results:  Social assistance benefits and pensions are paid in a timelier manner reaching accordingly 95.8 and 97.9 percents of recipients (2011 survey data).  Targeting of social assistance benefits and services is improved.  The Gyumri Center for the Disabled is functional.  Overall satisfaction of beneficiaries with social service and benefits is improved reaching to 94.8 percent (2011 survey data.  27.5 percent of system participants (pensioners) are aware of their rights and 29.4 percent - of their responsibilities.  Development of a structural-functional model of Integrated Social Service (ISS) centers, and rehabilitation of facilities is underway.  Better performance by the public employment, pension and social assistance agencies in providing services to the population. Key Partners The World Bank team closely collaborates with the (i) Ministry of Labor and Social Issues; (ii) State Employment Service; (iii) State Social Security Services; State Revenue Committee (SRC); and (iv) Foreign Financing Project Management Center (FFPMC), which is responsible for the implementation of the project. Key Development Partners The project collaborates with the USAID-funded project in the area of pension reforms and employment generation, and with UNICEF in the development of integrated social services. 26 PROGRAMMATIC DEVELOPMENT POLICY OPERATION Key Dates: DPO-I Approved: July2, 2009 DPO-II Approved: January 11, 2011 DPO-III Approved: February 14, 2012 Financing in million US Dollars: DPO I (2009) II (2011.) III (2012e) IDA Credit 60 21 50 IBRD Loan 4 30 Total ($165mln) 60 25 80 Financier Financing Disbursed Undisbursed* (DPO III) IDA Credit 50 - IBRD Loan 30 - Total 80 - 80.4 *World Bank disbursements as of March, 2012. Note: Disbursements may differ from financing due to exchange rate fluctuations at the time of disbursement. Challenges The global economic crisis revealed the vulnerabilities of the Armenian economy and posed several challenges needing an immediate response of a more structured nature, to be addressed throughout the medium- to long-term period. Project Objective The budget support operation – DPO supports the Government’s three strategic objectives of: (i) mitigating the social impact and Armenia’s vulnerability to external shocks; (ii) strengthening competitiveness for post- crisis recovery and growth over the medium term, and (iii) furthering institutional reforms to improve the quality of public decision making and governance. Key Results To mitigate the social impact, the operation supported:  Maintaining a sound macro-fiscal framework while protecting the poor by securing safety-net funding;  Improving the management of education, health, and social protection programs. To strengthen competitiveness for recovery and growth, the operation supported:  Strengthening the State Competition Committee to enhance economic competition;  Improving the business climate by modernizing inspection practices (including customs) and setting up one stop shops;  Streamlining tax procedures and re-engineering business processes in the tax administration;  Strengthening the regulatory environment in infrastructure;  Revamping the legal framework for the mining sector. To advance institutional reforms, the operation supported:  Improving public-sector efficiency and effectiveness by introducing regulation on conflict of interest and public service;  Improving public financial management by introducing Public Investment Appraisal System and enhancing the linkage between budgeting and strategic planning. Key Partners The Bank team worked closely with the (i) Ministry of Finance, which was responsible for ensuring sound macro-fiscal policies and monitoring of the expected outcomes. Line Ministries and public agencies, including (ii) Ministry of Economy, State Revenue Committee, State Economic Competition Promotion Committee, Social Ministries, Ministry of Energy and Natural Resources, Ministry of Transport and the Public Services Regulatory Commission , took primary responsibility for implementation of envisaged reform actions in their respective fields. Key Development Partners included the IMF (monitoring of macro-fiscal and debt performance), EBRD (monitoring of private sector development), IFC (introduction of risk-based inspection system), and USAID (tax administration), with whom the Bank Team coordinated closely on policy, implementation and monitoring issues. 27