UP Core Road N Development Project– Plan For first Eighteen UP CORE ROAD NETWORK DEVELOPMENT PROJECT– PROCUREMENT PLAN 1. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, Revised November 2017 and August 2018 and applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. 2. A Project Procurement Strategy for Development (PPSD) has been prepared for the project. Extensive market analysis has been carried out for different packages of procurement. Decisions on packages and lots are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the needs assessment, the project has decided to use Government e Marketplace [GeM] for procurement of Goods up to US$ 100,000 and as mentioned under National Procurement Procedures at para 9 below. Based on risk and market analysis, the procurement plan has been prepared to set out the selection methods to be followed by the Borrower during project implementation in the procurement of works, goods, IT system procurement, non-consulting and consulting services financed by the World Bank. 3. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 11) indicated in apply to the initial 18-months of implementation period and are based on the procurement performance of the project; these thresholds may be subsequently modified. Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, supply > 40 million and installation of plant and equipment and PPP) Open national (works – including turnkey, supply and > 100,000 and up to 40 million installation of plant and equipment and PPP) Open international (goods, IT system, and non-consulting > 3 million services) Open national (goods, IT system, and non-consulting > 100,000 and up to 3 million services) National request for quotation (goods and works) Up to 100,000 February 26, 2019 1 UP CORE ROAD NETWORK DEVELOPMENT PROJECT– PROCUREMENT PLAN Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, supply > 40 million and installation of plant and equipment and PPP) Open national (works – including turnkey, supply and > 100,000 and up to 40 million installation of plant and equipment and PPP) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 4. Procurement prior-review thresholds. The World Bank will prior review the following contracts: (a) Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 10 million equivalent (b) Goods and IT system: All contracts more than US$2 million equivalent (c) Non-consulting services: All contracts more than US$2 million equivalent (d) Consultants: All contracts >US$1 million equivalent for firms and >US$300,000 equivalent for individuals 5. The above thresholds are for the initial 18-month implementation period; based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, ToRs shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually (or at any other time if required) and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan, herein below at para 9. February 26, 2019 2 UP CORE ROAD NETWORK DEVELOPMENT PROJECT– PROCUREMENT PLAN 6. Prior review contract. In the case of contracts subject to prior review, the Implementing Agencies will seek the World Bank’s no objection before granting/agreeing to: (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; (c) any variation order or amendment (except in cases of extreme urgency) that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and (d) the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. 7. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: (a) Procurement Plan and its updates; (b) an invitation for bids for procurement of works, goods, IT system procurement and non-consulting services; (c) request for expression of interest for selection/hiring of consulting services; (d) contract awards of works, goods, IT system procurement and non-consulting services procured following international and national procedures; (e) a list of contracts/purchase orders placed following RFQ (Request for Quotation) procedures on a quarterly basis; (f) a list of contracts following direct contracting (DC) on a quarterly basis; (g) an annual financial and physical progress report of all contracts; and (h) an action taken report on the complaints received on a quarterly basis. 8. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: (a) Specific Procurement Notice (i.e. invitation for bids) for procurement of works, goods , IT system procurement and non-consulting services using open international procedures; (b) Requests for Expression of Interests above USD 800,000; (c) contract award details of all procurement of works, goods, IT system procurement and non-consulting services using open international procedure; and(d) a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. February 26, 2019 3 UP CORE ROAD NETWORK DEVELOPMENT PROJECT– PROCUREMENT PLAN 9. National Procurement Procedures : National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: (a) Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. (b) Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. (c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. (d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. (e) Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. (f) At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. (g) Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. (h) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. (i) The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. February 26, 2019 4 UP CORE ROAD NETWORK DEVELOPMENT PROJECT– PROCUREMENT PLAN (j) Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. 10. Domestic preference. The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Name of the Project: Uttar Pradesh Core Road Network Development Project (P147864) Allocated / Sanctioned Amount: Project yet to be negotiated Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. February 26, 2019 5 PROCUREMENT India : Uttar Pradesh Core Road Network Development Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-11-08 2021-10-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147864 GPN Date: Project Name: Uttar Pradesh Core Road Network Development Project Loan / Credit No: / , IBRD / 89400 Uttar Pradesh Public Works Department (PWD) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-UPPWD-14106-CW-RFB / Rebidding- Construction of Single Stage - One 54,431,569.0 2018-02- SH-51 Badaun-Bilsi-Bijnaur / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2017-05-01 2017-05-08 2017-08-17 2017-06-22 2017-07-22 2017-08-26 Envelope 0 22 Road (From Km 58.400 to Km 137.820) IN-UPPWD-14105-CW-RFB / Construction of SH-93 Gola - Single Stage - One 50,951,282.0 2018-02- / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2017-05-01 2017-05-08 2017-08-17 2017-06-22 2017-07-22 2017-08-26 Shahjahanpur Road (from Km Envelope 0 22 1.280 to Km 58.580) IN-UPPWD-14020-CW-RFB / Construction of SH-42 Single Stage - One 48,391,695.0 2018-02- / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2017-05-01 2017-05-08 2017-08-17 2017-06-22 2017-07-22 2017-08-26 Hamirpur-Rath Road (from Envelope 0 22 Km 2.060 to Km 76.500) UPCRNDP/UPG/04/2016 / Single Stage - One 54,431,569.0 2019-04- Construction of SH-51 / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2016-11-08 2016-11-11 2016-11-08 2016-12-24 2017-02-22 2017-04-21 Envelope 0 21 Badayun-Bilsi-Bijnaur Road UPCRNDP/UPG/01/2016 / Single Stage - One 48,391,695.0 2019-04- Construction of SH-42 / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2016-11-08 2016-11-11 2016-11-08 2016-11-24 2016-12-24 2017-01-03 2017-02-22 2017-04-21 Envelope 0 21 Hamirpur-Rath Road UPCRNDP/UPG/03/2016 / Single Stage - One 50,951,282.0 2019-04- Construction of SH-93 Gola- / Network Improvement Prior Request for Bids Open - International 0.00 Canceled 2016-11-08 2016-11-11 2016-11-08 2017-05-03 2016-12-24 2017-02-22 2017-04-21 Envelope 0 21 Shahjahanpur Road IN-UPPWD-48710-CW-RFB / Engineering Procurement and Construction Contract for Up- Single Stage - One 48,800,000.0 48,444,429. 2020-06- gradation and Maintenance of / Network Improvement Prior Request for Bids Open - International Signed 2018-02-15 2018-05-25 2018-02-20 2018-07-20 2018-04-12 2018-08-07 2018-05-15 2018-10-09 2018-06-20 2019-07-05 Envelope 0 96 19 Badaun-Bilsi-Bijnaour section of SH-51, from Km 58.400 to Km 137.820-UPG 04 IN-UPPWD-48718-CW-RFB / Engineering Procurement and Construction Contract for Up- Single Stage - One 51,343,000.0 51,765,918. 2020-06- gradation and Maintenance of / Network Improvement Prior Request for Bids Open - International Signed 2018-02-15 2018-05-25 2018-02-20 2018-07-20 2018-04-12 2018-08-07 2018-05-15 2018-10-09 2018-06-20 2019-06-26 Envelope 0 08 19 Gola-Shahjahanpur section of SH-93, from Km 1.280 to Km 58.580-UPG 03 IN-UPPWD-48722-CW-RFB / Engineering Procurement and Construction Contract for Up- Single Stage - One 45,500,000.0 39,915,583. 2020-06- gradation and Maintenance of / Network Improvement Prior Request for Bids Open - International Signed 2018-02-15 2018-05-25 2018-02-20 2018-07-20 2018-04-12 2018-08-07 2018-05-15 2018-10-09 2018-06-20 2019-06-19 Envelope 0 46 19 Hamirpur - Rath section of SH- 42, from Km 2.060 to Km 76.500--UPG-01 IN-UPPWD-221202-CW-RFB / Engineering Procurement and Construction Contract for Under Up-gradation and Single Stage - Two 22,000,000.0 2023-08- IBRD / 89400 Network Improvement Prior Request for Bids Open - National 0.00 Implementat 2021-02-23 2021-05-28 2021-03-10 2021-04-21 2021-07-20 2021-08-24 Maintenance of Rath - Envelope 0 24 ion Garautha section of SH-42, from Km 74.550 to Km 110.360 IN-UPPWD-254359-CW-RFB / Engineering Procurement and Construction Contract for Up-gradation and Single Stage - Two Other (with field 45,470,000.0 Under 2024-04- IBRD / 89400 Network Improvement Prior Request for Bids Open - International 0.00 2021-09-30 2021-10-30 2021-12-19 2022-02-23 2022-04-06 Maintenance of Bahraich- Envelope for explanation) 0 Review 05 Gonda-Faizabad section of SH- 30, from Km 0.000 to Km 60.082--UPG-07 IN-UPPWD-254362-CW-RFB / Engineering Procurement and Construction Contract for Up-gradation and Single Stage - Two Other (with field 25,000,000.0 Under 2024-03- IBRD / 89400 Network Improvement Prior Request for Bids Open - National 0.00 2021-09-30 2021-10-30 2021-12-11 2022-02-15 2022-03-29 Maintenance of Bansi- Envelope for explanation) 0 Review 28 Mehdawal-Khalilabad section of SH-88 , from Km 0.000 to Km 28.870--UPG-06 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-UPPWD-3670-CS-QCBS / Consultancy Services for Hiring Services of Independent Quality And Cost- / Network Improvement Post Open - National 71,500.00 0.00 Canceled 2016-11-30 2016-12-19 2017-01-09 2017-02-22 2017-03-24 2017-04-23 2017-06-06 2017-07-04 2020-01-02 Quality Auditor for U.P. Core Based Selection Road Network Development Project IN-UPPWD-14307-CS-QCBS / Consultancy Services for Hiring Services of Independent Quality And Cost- / Network Improvement Post Open - National 71,500.00 0.00 Canceled 2017-05-12 2017-06-11 2017-07-15 2017-08-14 2017-09-01 2017-09-29 2017-10-23 2020-04-22 Quality Auditor for U.P. Core Based Selection Road Network Development Project IN-UPPWD-45830-CS-QCBS / Consultancy Services for Independent Quality Auditor Quality And Cost- / Network Improvement Post Open - National 71,000.00 0.00 Canceled 2018-01-31 2018-02-22 2018-03-15 2018-02-24 2018-05-14 2018-10-12 2018-06-23 2018-12-06 2018-07-23 2019-10-05 2018-08-28 2018-09-27 2021-03-27 for UP Core Road Network Based Selection Development Project proposed from World Bank Loan IN-UPPWD-50016-CS-QCBS / Consultancy Services for Gender Assessment and Quality And Cost- / Network Improvement Post Open - National 100,000.00 143,021.04 Signed 2018-02-21 2017-01-26 2018-02-21 2018-02-21 2018-04-24 2018-03-22 2018-06-04 2018-04-11 2018-08-18 2018-07-28 2019-06-17 2018-08-12 2019-07-18 2019-02-08 Preparation of Gender Action Based Selection Plan for Uttar Pradesh Core Road Network Development Project (UPCRNDP) IN-UPPWD-148146-CS-QCBS / Consultancy Services for Independent Quality Auditor Quality And Cost- IBRD / 89400 Network Improvement Post Open - National 62,000.00 67,826.15 Signed 2019-12-09 2019-12-09 2020-01-10 2019-12-09 2020-02-24 2020-02-26 2020-04-04 2020-05-14 2020-04-24 2020-08-18 2020-05-30 2020-12-30 2020-06-29 2021-01-18 2022-06-29 for UP Core Road Network Based Selection Development Project proposed from World Bank Loan. IN-UPPWD-124129-CS-CQS / Hiring of Accounting Firm in Consultant U.P. Core Road Network IBRD / 89400 Network Improvement Post Qualification Open - National 72,000.00 0.00 Canceled 2019-07-24 2019-07-23 2019-08-24 2019-10-23 2019-12-02 2019-12-22 2020-01-21 2022-01-20 Development Project from Selection World Bank loan. IN-UPPWD-124136-CS-CQS / Hiring services of firm for carrying out base line (first) Consultant Road user /Customer IBRD / 89400 Network Improvement Post Qualification Open - National 58,000.00 0.00 Canceled 2019-07-24 2019-07-23 2019-08-24 2019-10-23 2019-12-02 2019-12-22 2020-01-21 2022-01-20 Satisfaction Survey on Selection designated roads of U.P. Core Road Network Development Project from World Bank loan . IN-UPPWD-181584-CS-QCBS / The objective of the assignment is to provide FM support to the PIU in PWD (Headquarters). The Quality And Cost- IBRD / 89400 Network Improvement Post Open - National 72,000.00 29,988.30 Signed 2020-06-24 2019-07-23 2020-06-24 2020-06-26 2020-07-01 2020-07-26 2020-07-31 2020-08-10 2020-09-15 2020-10-09 2021-01-06 2020-11-08 2021-01-07 2022-11-08 firm will work in close Based Selection association with the PWD officials at Head office and field offices (Divisions/Circles). IN-UPPWD-181587-CS-QCBS / Hiring services of firm for carrying out base line (first) Road user /Customer Quality And Cost- IBRD / 89400 Network Improvement Post Open - National 58,000.00 50,378.74 Signed 2020-06-24 2019-07-23 2020-06-24 2020-06-26 2020-07-01 2020-07-26 2020-07-31 2020-08-10 2020-09-15 2020-10-09 2020-12-30 2020-11-08 2021-01-08 2022-11-08 Satisfaction Survey on Based Selection designated roads of U.P. Core Road Network Development Project from World Bank loan . IN-UPPWD-204673-CS-QCBS / The hiring of Authority Engineer for Phase-II Roads of UPCRNDP for Construction Quality And Cost- Under Supervision in conformity and IBRD / 89400 Network Improvement Prior Open - International 3,000,000.00 0.00 2020-11-24 2021-02-26 2020-12-15 2021-03-15 2021-02-03 2021-03-15 2021-04-14 2021-05-28 2021-07-02 2025-06-30 Based Selection Implementation quality of the works and the existence and the compliance with the relevant procedures of contractual documents. IN-UPPWD-223702-CS-QCBS Quality And Cost- Under / Hiring services of Internal IBRD / 89400 Network Improvement Post Open - National 50,000.00 0.00 2021-03-18 2021-06-08 2021-04-27 2021-06-10 2021-06-10 2021-07-10 2021-08-09 2021-09-13 2021-10-18 2023-10-18 Based Selection Implementation Auditing (Finance) Firm. IN-UPPWD-225450-CS-QCBS / Project Management Consultancy Services for Road Safety Activities to be Quality And Cost- Under IBRD / 89400 Network Improvement Prior Open - International 1,278,000.00 0.00 2021-03-26 2021-05-18 2021-04-16 2021-06-10 2021-05-30 2021-06-27 2021-07-27 2021-08-31 2021-10-05 2024-10-04 implemented by UPPWD under Based Selection Implementation Uttar Pradesh Core Road Network Development Program (UPCRNDP). IN-UPPWD-228530-CS-QCBS / HIRING OF NGO SERVICES FOR IMPLEMENTATION OF RESETTLEMENT ACTION PLAN Quality And Cost- Under IBRD / 89400 Network Improvement Post Open - National 200,000.00 0.00 2021-04-13 2021-05-27 2021-05-23 2021-06-10 2021-07-06 2021-08-10 2021-09-09 2021-10-14 2021-11-18 2024-11-17 IN PHASE II OF UTTAR Based Selection Implementation PRADESH CORE ROAD NETWORK DEVELOPMENT PROJECT (UPCRNDP). IN-UPPWD-257594-CS-QCBS / Hiring of External Evaluation Consultant for Evaluation of Quality And Cost- IBRD / 89400 Network Improvement Post Open - National 50,000.00 0.00 Under Review 2021-10-11 2021-10-20 2021-11-01 2021-12-15 2022-01-12 2022-02-11 2022-03-18 2022-04-22 2022-10-19 Implementation of the Based Selection Resettlement Action Plan under UPCRNDP. Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-UPPWD-5827-CS-INDV / Qualified individual consultant with expertise in relevant environmental field, who will Individual work as a member of / Network Improvement Post Consultant Open 58,600.00 0.00 Canceled 2017-03-21 2017-05-02 2017-05-23 2017-06-13 2017-07-18 2020-07-17 Environmental and Social Selection Development Cell (ESDC) of PMU to support the activities of ESDC. IN-UPPWD-5834-CS-INDV / Qualified individual consultant with expertise in relevant Individual social field, who will work as a / Network Improvement Post Consultant Open 58,600.00 0.00 Canceled 2017-03-21 2017-05-02 2017-05-23 2017-06-13 2017-07-18 2020-07-17 member of Environmental and Selection Social Development Cell (ESDC) of PMU to support the activities of ESDC. IN-UPPWD-61318-CS-INDV / Individual Consultant (IC) for the Consultancy Services to Individual support the Environmental / Network Improvement Post Consultant Open 80,000.00 85,562.05 Signed 2018-05-15 2018-05-14 2018-08-11 2019-11-21 2018-09-01 2020-02-24 2018-10-06 2020-05-06 2021-10-05 component under Selection Environment and Social Development Cell (ESDC). IN-UPPWD-5834-CS-INDV-2 / Individual Consultant (IC) for Individual the Consultancy Services to / Network Improvement Post Consultant Open 80,000.00 66,548.26 Signed 2018-05-15 2018-05-14 2018-08-11 2019-11-21 2018-09-01 2020-02-24 2018-10-06 2020-05-05 2021-10-05 support the Social component Selection under Environment and Social Development Cell (ESDC). IN-UPPWD-196119-CS-CDS / The hiring of NGO services to undertake balance activities for implementation of the IBRD / 89400 Network Improvement Post Direct Selection Direct 14,212.63 14,323.03 Signed 2020-09-24 2020-10-01 2020-09-26 2020-10-06 2020-10-01 2020-10-21 2021-03-30 Resettlement Action Plan in Phase I roads under the World Bank aided UPCRNDP. IN-UPPWD-233588-CS-INDV / Consultancy Services for Road Asset Management Individual System support to the UPPWD IBRD / 89400 Network Improvement Post Consultant Open 218,000.00 0.00 Canceled 2021-05-27 2021-05-18 2021-08-15 2021-09-24 2021-10-29 2024-10-28 under Uttar Pradesh Core Selection Road Network Development Program (UPCRNDP) (Individual) IN-UPPWD-260271-CS-INDV / Consultancy Services for Road Asset Management Individual System support to the UPPWD Pending IBRD / 89400 Network Improvement Post Consultant Open 218,000.00 0.00 2021-10-30 2022-01-18 2022-02-27 2022-04-03 2047-06-06 under Uttar Pradesh Core Implementation Selection Road Network Development Program (UPCRNDP) (Individual) Page 3