Kenya - Third Nairobi Water Supply Project (English)

Overall this project is rated as unsatisfactory: a strategic opportunity to achieve significant institutional and commercial gains was wasted. Water production and waste water treatment capacities were not balanced by corresponding water distribution and waste water collection capacities; the project has not changed significantly the provision of water supply service to lower income communities nor the ambient water quality of the Nairobi river; and...