PROCUREMENT PLAN (Textual Part) Project information: P164551 - Mozambique Land Administration Project (Terra Segura) Project Implementation agency: FNDS Date of the Procurement Plan: April 8, 2018 Period covered by this Procurement Plan: 12 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The procedures to be followed for NCB shall be those set forth in the “Regulamento de Contratação de Empreitada de Obras Públicas, Fornecimento de Bens e Prestação de Serviços ao Estado” of the Republic of Mozambique of Março 08, 2016 (“the Regulation”), as per Decree No. 5/2016 , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). To be specified Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. To be detailed PROCUREMENT Mozambique : Mozambique Land Administration Project (Terra Segura) PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2018-04-10 2020-03-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164551 GPN Date: Project Name: Mozambique Land Administration Project (Terra Segura) Loan / Credit No: IDA / V1430, IDA / D4010 Executing Agency(ies): MINISTRY OF LAND, ENVIRONMENT AND RURAL DEVELOPMENT - International Funds Management Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 49/MLAND/W/19 / Renovate Institutional Development Pending Single Stage - One the DINAT Data Center IDA / D4010 and Strengthening of the Post Request for Bids Open - National 550,000.00 0.00 Implementati 2020-09-28 2020-10-03 2020-11-14 2020-12-25 2021-01-31 2022-01-31 Envelope premises. Legal Framework on 31/MLANDS/W/18 / Institutional Development Pending Construction of buildings for Single Stage - One IDA / V1430 and Strengthening of the Post Request for Bids Open - National 5,500,000.00 0.00 Implementati 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 2021-12-17 Provincial and Regional Envelope Legal Framework on Offices GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14/MLAND/G/2018 / IT Project Management and Request for Single Stage - One IDA / V1430 Post Limited 40,000.00 42,435.61 Signed 2018-05-22 2018-06-12 2018-07-17 2018-06-27 2019-01-13 equipment Coordination Quotations Envelope Pending 15/MFIP/G/2018 / Office Project Management and Request for Single Stage - One IDA / V1430 Post Limited 50,000.00 0.00 Implementati 2018-06-04 2018-07-30 2019-01-26 equipment - Furniture Coordination Quotations Envelope on 45/MLAND/G/19 / IT Project Management and Request for Single Stage - One IDA / D4010 Post Open - National 30,000.00 21,338.81 Signed 2019-06-25 2019-08-20 2019-09-11 2020-02-17 Equipament Coordination Quotations Envelope Project Management and Single Stage - One 13/MLAND/G/18 / Vehicles IDA / V1430 Post Request for Bids Open - National 350,000.00 138,396.78 Signed 2019-07-05 2019-08-19 2019-07-10 2019-08-21 2019-10-01 2019-09-20 2019-11-04 2019-10-25 2019-11-29 2020-04-22 Coordination Envelope 32/MLAND/W/2018 / Renovation of Data Center Institutional Development premises and purchase and Single Stage - One IDA / V1430 and Strengthening of the Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2020-05-04 2020-05-11 2020-06-22 2020-07-22 2020-08-26 2021-02-22 installation of hardware, Envelope Legal Framework security and licensing for DINAT Data Center 38/MLAND/G/19 / Upgrade the capacity for processing and use of imagery and Pending Systematic Land Single Stage - One base map, purchase IDA / V1430 Post Request for Bids Open - National 350,000.00 0.00 Implementati 2020-02-28 2020-03-04 2020-04-15 2020-05-15 2020-06-19 2020-12-16 Regularization Envelope necessary hardware, software on including field equipment and training of personnel 51/MLAND/G/19 / Purchase Institutional Development Pending Single Stage - One of generators for provincial IDA / D4010 and Strengthening of the Post Request for Bids Open - National 400,000.00 0.00 Implementati 2021-09-29 2021-10-14 2021-11-25 2021-12-27 2022-02-02 2022-08-02 Envelope and regional offices. Legal Framework on Page 1 Institutional Development Pending 44/MLAND/G/20 / UN Agencies IDA / V1430 and Strengthening of the Post Direct 480,000.00 0.00 Implementati 2020-09-30 2020-10-05 2020-11-09 2021-05-08 Acquisition of vehicles (Direct) Legal Framework on Pending 13/MLAND/G/2020-1 / Project Management and Request for Single Stage - One IDA / V1430 Post Limited 75,000.00 0.00 Implementati 2020-04-20 2020-06-15 2020-12-12 Acquisition of one vehicle. Coordination Quotations Envelope on 22/MLAND/G/2018 / Institutional Development Pending Purchase furniture for Single Stage - One IDA / V1430 and Strengthening of the Post Request for Bids Open - National 900,000.00 0.00 Implementati 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 2023-04-03 Provincial and Regional Envelope Legal Framework on offices 20/MLAND/G/18 / ICT equipment and network Pending Systematic Land Open - Single Stage - One installation and maintenance IDA / V1430 Prior Request for Bids 2,000,000.00 0.00 Implementati 2022-03-16 2022-03-21 2022-05-02 2022-06-01 2022-07-06 2023-01-02 Regularization International Envelope for the new provincial and on regional offices NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 18/MLAND/NCS/2018 / Upgrade a capacity for processing and use of imagery and base map, purchase necessary Systematic Land Single Stage - One IDA / V1430 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2019-03-12 2019-03-17 2019-04-28 2019-05-28 2019-07-02 2019-12-29 hardware, software including Regularization Envelope field equipment and training of personnel and development of QAQC procedures 24/MLAND/NCS/2018 / Densification of existing Systematic Land Single Stage - One IDA / V1430 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-10-15 2019-10-21 2019-12-02 2020-01-01 2020-02-05 2020-08-03 Geodetic Network for Regularization Envelope selected project areas 57/MLAND/NCS/19 / Delimitation of communities and basic land use planning Pending and land regularization, Systematic Land Open - Single Stage - One IDA / D4010 Prior Request for Bids 31,200,000.00 0.00 Implementati 2021-04-01 2021-04-16 2021-05-28 2021-06-27 2021-08-02 2022-08-02 parcels demarcation, Regularization International Envelope on boundaries survey, preparation and issuance of DUATs - Phase II 19/MLAND/NCS/2018 / CORS Network design, Institutional Development Pending Single Stage - One Upgrade establishment IDA / V1430 and Strengthening of the Post Request for Bids Open - National 1,800,000.00 0.00 Implementati 2020-03-09 2020-03-14 2020-04-25 2020-05-25 2020-06-29 2020-12-26 Envelope capacity building during the Legal Framework on project time 54/MLAND/NCS/19 / Implementation of the new version of the Land Institutional Development Pending Information Management Open - Single Stage - One IDA / D4010 and Strengthening of the Prior Request for Bids 4,200,000.00 0.00 Implementati 2020-12-16 2020-12-21 2021-02-01 2021-03-03 2021-04-07 2022-09-29 System (SiGIT), including International Envelope Legal Framework on web portal, mobile app, interoperability, quality control and maintenance Page 2 29/MLAND/NCS/2018 / Delimitation of communities and basic land use planning Pending and land regularization, Systematic Land Open - Single Stage - One IDA / V1430 Prior Request for Bids 12,500,000.00 0.00 Implementati 2020-03-18 2020-03-23 2020-05-04 2020-06-03 2020-07-08 2021-01-04 parcels demarcation, Regularization International Envelope on boundaries survey, preparation and issuance of DUATs - Phase I 23/MLAND/NCS/2018 / Pending Acquisition of high resolution Systematic Land Open - Single Stage - One IDA / V1430 Prior Request for Bids 5,300,000.00 0.00 Implementati 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 2020-12-19 orthorectified imagery (base Regularization International Envelope on map) 28/MLAND/CS/2018 / Public Pending Systematic Land Single Stage - One Information and Sensitization IDA / V1430 Post Request for Bids Open - National 1,800,000.00 0.00 Implementati 2020-05-31 2020-06-07 2020-07-19 2020-08-18 2020-10-01 2021-10-01 Regularization Envelope campaign on 24/MLAND/NCS/2020 / Institutional Development Pending Single Stage - One Purchase of satelite imagery IDA / V1430 and Strengthening of the Post Request for Bids Open - National 200,000.00 0.00 Implementati 2020-04-30 2020-05-05 2020-06-16 2020-07-16 2020-08-20 2021-02-16 Envelope and training Legal Framework on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 11/MLAND/CS/2018 / Land Consultant Open - Information System (SIGIT) IDA / V1430 Post Qualification 150,000.00 0.00 Canceled 2018-06-06 2018-04-27 2018-06-27 2018-08-10 2018-09-09 2018-10-14 2019-04-12 International Technical Review Selection 16/MLAND/CS/18 / Land Consultant Open - Under information System (SIGIT) IDA / V1430 Post Qualification 150,000.00 0.00 2018-06-15 2018-04-18 2018-06-29 2018-08-13 2018-07-26 2018-09-12 2018-11-07 2018-10-17 2019-04-15 International Implementation technical review Selection 17/MLAND/CS/18 / Institutional Development Consultant Open - Infrastructure needs IDA / V1430 and Strengthening of the Post Qualification 100,000.00 109,305.37 Signed 2018-06-20 2018-07-24 2018-07-11 2018-08-24 2018-07-24 2018-09-24 2018-08-31 2018-10-29 2018-09-21 2019-04-27 International assessment Legal Framework Selection 10/MLAND/CS/2018 / Revision of the Land Systematic Land Quality And Cost- Open - Under Legislation and land use IDA / V1430 Post 500,000.00 0.00 2018-12-10 2018-12-06 2018-12-31 2019-01-14 2019-02-13 2019-03-13 2019-04-12 2019-05-17 2019-06-21 2020-06-20 Regularization Based Selection International Implementation planning (including consultations) 44/MLAND/CS/19 / Communities delimitation Systematic Land Quality And Cost- and land regularization IDA / D4010 Post Open - National 400,000.00 0.00 Canceled 2019-11-28 2019-12-19 2020-02-01 2020-02-29 2020-03-30 2020-05-04 2020-06-08 2021-06-08 Regularization Based Selection quality assurance and quality control 26/MLAND/CS/2018 / Institutional Development Consultant Interoperability of SiGIT and IDA / V1430 and Strengthening of the Post Qualification Open - National 250,000.00 0.00 Canceled 2019-07-02 2019-07-23 2019-09-05 2019-10-05 2019-11-09 2020-05-07 e-Government integration Legal Framework Selection 27/MLAND/CS/2018 / Institutional Development Consultant Redesign and upgrade of IDA / V1430 and Strengthening of the Post Qualification Open - National 200,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2020-08-20 SIGIT web-portal Legal Framework Selection 09/MLAND/CS/18 / Institutional Assessment and Consultant Consolidation Business Plan IDA / V1430 Post Qualification Open - National 150,000.00 0.00 Canceled 2018-05-31 2018-06-21 2018-08-04 2018-09-03 2018-10-08 2019-04-06 (1. Management / 2. Selection Capacity building) Page 3 39/MLAND/CS/19 / Institutional Development Consultant Development of a business IDA / D4010 and Strengthening of the Post Qualification Open - National 200,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 plan for land administration Legal Framework Selection institution 55/MLAND/CS/19 / Institutional Assessment and Institutional Development Quality And Cost- Pending Development of Business IDA / D4010 and Strengthening of the Post Open - National 365,000.00 0.00 2020-06-17 2020-07-08 2020-08-21 2020-09-18 2020-10-18 2020-11-23 2020-12-28 2021-06-26 Based Selection Implementation Plan for a Land Legal Framework Administration Institution 33/MLAND/IC/2018 / Development of DINAT's ICT Institutional Development Consultant Pending strategy and enterprise IDA / D4010 and Strengthening of the Post Qualification Open - National 125,000.00 0.00 2021-04-30 2021-05-21 2021-07-04 2021-08-03 2021-09-07 2022-03-06 Implementation architecture towards the Legal Framework Selection centralized system 43/MLAND/CS/19 / External Project Management and Least Cost Pending IDA / D4010 Post Open - National 40,000.00 0.00 2021-06-30 2021-07-21 2021-09-03 2021-10-01 2021-11-01 2021-12-06 2022-01-10 2022-04-10 Audits Coordination Selection Implementation 41/MLAND/CS/19 / Design Institutional Development Consultant Pending the operationalization plan of IDA / D4010 and Strengthening of the Post Qualification Open - National 150,000.00 0.00 2021-02-28 2021-03-21 2021-05-06 2021-06-05 2021-07-10 2022-01-06 Implementation the land tax system Legal Framework Selection 05/MLAND/CS/2020 / Institutional Development Consultant Design and supervision of Pending IDA / V1430 and Strengthening of the Post Qualification Open - National 75,000.00 0.00 2020-09-30 2020-10-21 2020-12-04 2021-01-03 2021-02-07 2021-08-06 Renovation of DINAT Data Implementation Legal Framework Selection Center 38/MFIP/CS/18 / Redesign of Land Information Systematic Land Quality And Cost- Pending Management System (SiGIT), IDA / V1430 Post Open - National 300,000.00 0.00 2020-03-03 2020-03-24 2020-05-07 2020-06-04 2020-07-04 2020-08-08 2020-09-12 2021-09-12 Regularization Based Selection Implementation including technical specifications 25/MLAND/CS/2018 / Consolidation, maintenance and upgrade of SiGIT software toward a Institutional Development Quality And Cost- Open - centralized system IDA / V1430 and Strengthening of the Prior 3,800,000.00 0.00 Canceled 2019-10-01 2019-10-22 2019-12-05 2020-01-02 2020-02-03 2020-03-09 2020-04-13 2020-10-10 Based Selection International architecture (data quality, Legal Framework increased volume data, high availability, communication and licenses cost) 42/MLAND/CS/19 / Independent Process Quality Assurance Entity (support of conflict resolution Systematic Land Quality And Cost- IDA / D4010 Post Open - National 493,750.00 0.00 Canceled 2020-06-30 2020-07-21 2020-09-03 2020-10-01 2020-10-31 2020-12-05 2021-01-09 2022-01-09 mechanism, training of Regularization Based Selection authorities, safeguard monitoring in communities (social impact) 21/MLAND/CS/2018 / Institutional Development Design and supervision Quality And Cost- Open - Pending IDA / V1430 and Strengthening of the Post 885,000.00 0.00 2020-09-02 2020-09-23 2020-11-06 2020-12-04 2021-01-03 2021-02-07 2021-03-14 2022-03-14 works of buildings offices Based Selection International Implementation Legal Framework (Regional & Provincial) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional Development Individual 02/MLAND/IC/18 / Social Under IDA / V1430 and Strengthening of the Post Consultant Open 75,000.00 0.00 2018-04-26 2018-05-25 2018-06-14 2018-07-05 2018-08-09 2019-02-05 Analysis Implementation Legal Framework Selection Page 4 Institutional Development Individual 03/MLAND/IC/2018 / IDA / V1430 and Strengthening of the Post Consultant Open 50,000.00 62,517.14 Signed 2018-04-25 2018-05-25 2018-06-13 2018-06-08 2018-07-04 2018-06-10 2018-08-08 2018-06-21 2019-02-04 Environment analysis Legal Framework Selection 04/MFIP/IC/2018 / Institutional Development Individual Cadastral Survey and IDA / V1430 and Strengthening of the Post Consultant Open 65,000.00 71,523.00 Signed 2018-05-24 2018-04-24 2018-07-12 2018-06-22 2018-08-02 2018-06-21 2018-09-06 2018-06-29 2019-03-05 Mapping needs assessment Legal Framework Selection 06/MLAND/IC/18 / Economic Institutional Development Individual and Financial Analysis IDA / V1430 and Strengthening of the Post Consultant Open 50,000.00 73,532.15 Signed 2018-06-12 2018-05-01 2018-07-31 2018-07-27 2018-08-21 2018-07-27 2018-09-25 2018-07-31 2019-03-24 (EFA) Legal Framework Selection 07/MLANDS/IC/208 / Design Individual the Communication Strategy IDA / V1430 Post Consultant Open 50,000.00 0.00 Canceled 2018-06-20 2018-08-08 2018-08-29 2018-10-03 2019-04-01 and Awareness Campaign Selection 01/MLAND/IC/18 / Individual Infrastructure Needs IDA / V1430 Post Consultant Open 100,000.00 0.00 Canceled 2018-05-23 2018-03-23 2018-07-11 2018-08-01 2018-09-05 2019-03-04 Assessment Selection 07/MLAND/CS/2018-2 / Design the Communication Systematic Land IDA / V1430 Post Direct Selection Direct 50,000.00 23,649.34 Signed 2018-12-10 2019-01-08 2018-12-20 2019-05-16 2019-02-23 2019-07-23 2019-08-22 Strategy and Awareness Regularization Campaign 05/MFIP/IC/2018 / Project Individual Implementation Manual IDA / V1430 Post Consultant Open 50,000.00 0.00 Canceled 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 (PIM) Selection 36/MLAND/IC/2018 / Individual Technical Assistanceto Systematic Land IDA / V1430 Post Consultant Open 40,000.00 0.00 Canceled 2019-01-09 2019-02-27 2019-03-20 2019-04-24 2019-10-21 develop RFBids for Regularization Selection Orthorectified imagery 30/MLAND/IC/2018 / Individual Technical Assistance to Systematic Land IDA / V1430 Post Consultant Open 40,000.00 49,512.50 Signed 2019-04-30 2019-02-28 2019-06-18 2019-07-16 2019-07-09 2019-07-16 2019-08-13 2019-07-16 2020-02-09 develop Request for Bids for Regularization Selection DELCOM/LTR contracts 08/MLAND/IC/2018 / E- Individual Government Legal IDA / V1430 Post Consultant Open 25,000.00 0.00 Canceled 2018-05-24 2018-07-12 2018-08-02 2018-09-06 2019-03-05 Framework Assessment Selection 35/MLAND/IC/2018 / Individual Technical Assistance to Systematic Land IDA / V1430 Post Consultant Open 40,000.00 0.00 Canceled 2018-12-17 2019-03-01 2019-02-04 2019-02-25 2019-04-01 2019-09-28 Develop Request forFBids for Regularization Selection the DELCOM/LTR Contracts Individual 48/MLAND/IC/19 / Project Management and Under IDA / V1430 Prior Consultant Open 72,000.00 0.00 2019-11-29 2019-12-10 2020-01-17 2020-02-07 2020-03-13 2021-03-13 Procurement Specialist Coordination Implementation Selection Individual 37/MLAND/IC/19 / Project Management and IDA / V1430 Prior Consultant Open 96,000.00 0.00 Canceled 2019-03-29 2019-04-05 2019-06-03 2019-06-24 2019-07-29 2020-07-28 Procurement Specialist Coordination Selection 40/MLAND/IC/19 / Gender- Individual Based Violence (GBV) Project Management and Pending IDA / D4010 Post Consultant Open 15,000.00 0.00 2020-05-31 2020-07-19 2020-08-09 2020-09-13 2020-11-12 Assessment as part of Coordination Implementation Selection safeguards implementation. 50/MLAND/IC/19 / Individual Development of QAQC Systematic Land Pending IDA / D4010 Post Consultant Open 100,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 procedures for CENACARTA, Regularization Implementation Selection including training. Page 5