SFG3865 DRAFT ENVIRONMENT & SOCIAL IMPACT ASSESSMENT & MANAGEMENT PLAN FOR KHUNTI WATER SUPPLY PROJECT November 2017 Jharkhand Urban Infrastructure Development Company Limited (JUIDCO) Jharkhand Municipal Development Project (JMDP) Table of Contents EXECUTIVE SUMMARY ........................................ .........2 1 INTRODUCTION................................................11 1.1 Brief Description of Project ............................... ........ 12 1.2 Objective and Scope of the ESIA Study.............................. 12 1.3 Approach and Methodology............................... ....... 13 1.4 Layout of the Report .................................... ....... 17 2 PROJECT DESCRIPTION ................................... ....... 18 2.1 General ........................................... ....... 18 2.2 Proposed Project ................................... ........ 18 3 ADMINISTRATIVE, REGULATORY FRAMEWORK & PROJECT CATEGORIZATION ........................................ ...... 35 3.1 Applicable National & State Laws and Regulations ............. ....... 35 3.2 World Bank Safeguard Policies .......................... ....... 43 3.3 IFC EHS Guideline.............. .................... ....... 47 4 ANALYSIS OF ALTERNATIVES.............. ................ ....... 52 4.1 No Project scenario ............ . ................... ....... 52 5 ENVIRONMENTAL BASELINE...................................... 55 5.1 Introduction ...............................................55 5.2 Land Environment ................................... ....... 55 5.3 Natural Hazards................ .................... ....... 63 5.4 Air Environment .................................... ........ 64 5.5 Noise Environment ................................... ....... 73 5.6 Water Environment ................................... ....... 75 5.7 Ecology Baseline ............. . ................... ........ 86 6 SOCIAL PROFILE .................... ........................... 87 6.1 Project Impact Area ................................... ....... 87 6.2 Socio Economic Profile................................. .....87 7 PUBLIC CONSULTATIONS AND DISCLOSURE .................. ........ 94 7.1 Identification of Stakeholders and Methods for Consultation ..... ........ 94 7.2 Findings of Public Consultation (Phase 1) .................. ........ 98 7.3 Summary of Public Consultation ( Phase II) .................. ...... 107 8 ENVIRONMENTAL IMPACT ASSESSMENT............................111 8.1 Project Area of Influence ......................................111 8.2 Impacts due to project activity ........................... 115 9 SOCIAL IMPACT ASSESSMENT (SIA) & RESETTLEMENT ACTION PLAN (RAP) 133 9.1 SIA Methodology ..................................... ...... 133 9.2 Findings of Social Impact Assessment .................... .......1 33 9.3 Mitigation Measures................ ................. ...... 135 9.4 Resettlement Action Plan ............. ................. ...... 135 10 ENVIRONMENTAL MANAGEMENT PLAN.............................1 43 10.1 Objectives of the EMP ................................. ...... 143 10.2 Institutional Arrangement for ESMP Implementation ............ ...... 143 10.3 Project Commitments ................................ .......1 46 10.4 Revisions to the ESMP ............................... .......1 47 10.5 Environmental and Social Management Plan .............. ........... 147 10.6 Environmental Monitoring .............................. ...... 168 10.7 Capacity Building and Training .............................. 178 10.8 ESMP Budget ...................................... ....... 180 Annexure 1: Environmental and Social Screening Checklist ............... .......... 187 Annexure II: Aam Sabha Proceedings (Birhu Village) ............................1 99 Annexure III: Minutes of the Consultation held on 30th of May 2017 with Self Help Group of the Khunti Nagar Panchayat to discuss the Water Supply Scheme proposed for World Bank funding....................................................200 Annexure IV: NOC issued by KNP for......................................202 1. Designated Disposal Site For construction waste and sludge at Belahatti .... ....202 2. Land for Labour/construction camps near WTP. .................... ......202 Annexure V: Applicable Environmental Standards ......................... .....204 Annexure VI: Top Soil Management .............................................209 Annexure VII: Labour Camp Site Management Plan................... ...........210 Annexure Vill: Construction Debris and Waste Management Plan........ .... .......220 Annexure IX: Occupational Health and Safety Management Plan........ ..............224 Annexure X: Scheduled Tribe Development Plan....................................229 Annexure Xl: Impacted Households................. ................. .....233 Annexure XII: General Guidelines for Chlorination Plants .........................231 Annexure XII: ESMP Monitoring Report by PIU....................... .........236 Annexure XIII: Environment Impact Assessment Methodology............ ........240 Annexure XIV: Forest NOC Application and Map of pipeline ............... ...........243 Annexure XV: NOC issued under FRA, 2006, Section 3 (2) (for replacement of pipeline in 0.0235 Ha of Forest land) ............................. ..............246 Annexure XVI: Justification of Point No. 5 of Forest NOC .............. ..............247 Annexure XVIl: NO OBJECTION from Water resources department for water withdrawal from existing intake point .................................... ......248 Annexure XVIII: SCOPE OF WORK FOR SAFEGUARDS SUPERVISION ....... .......249 LIST OF FIGURES Figure 1: Components of JMDP .................................. ......11 Figure 2: Overview of methodology followed for conducting the ESIA ...... ..........13 Figure 3: Line Diagram of the Proposed Scheme ...................... .....22 Figure 4: Schematic diagram of proposed project .....................25 Figure 5: Design of WTP Tank.........................................28 Figure 7: Work Execution Schedule................................34 Figure 8: Hydrogeological Map of Khunti Nagar Panchyat ........ ............57 Figure 9: Drainage Map of Khunti District...........................59 Figure 10: Soil Sampling Locations ................................ .....61 Figure 11: Project area marked on Earthquake Hazard Map ......................63 Figure 12: Project area marked on Wind Hazard Map ...................64 Figure 13: Monthly Temperature Variation................................67 Figure 14: Relative Humidity...........................................68 Figure 15: Rainfall Details.............................................68 Figure 16: Air & Noise Monitoring Locations...............................72 Figure 17: Water Sampling Locations....................................77 Figure 18: TDS of sampling locations....................................80 Figure 19: Alkanity of sampling locations.................................80 Figure 20: Organogram of JMDP........................................140 LIST OF TABLES Table 1: Details of Existing Water Supply of KNP............................18 Table 2: Pumping Machinery at Intake....................................19 Table 3: Ra Water from intake to WTP....................................19 Table 4: Clear Water Main from WTP to Sump at ESR.........................19 Table 5: WTP plant details.............................................20 Table 6: Current ESR.................................................20 Table 7: Current Distribution and House Connection.........................20 Table 8: Zone details ................................................21 Table 9: Land Details ................................................23 Table 10: Demand Projection ...... ....................................23 Table I1:Capacity calculation of existing weir & barrage for Khunti WSS ............... 24 Table 12: Proposed WTP Details ........................................27 Table 13: Rising Main Details Clear Water.................................29 Table 14: Details of ESR ......................................................29 Table 15: Statement of Distribution for the proposed scheme..................30 Table 16: Estimation of raw material for construction ........................31 Table 17: Details of Waste generated during construction phase ...............32 Table 18: Applicable Environmental Regulations of Gol and GoJ................36 Table 19: Applicability of WB Safeguard Policies for the Project.................44 Table 20: IFC EHS guideline applicable to project............................47 Table 21: Environmental Categorization of Sub-projects.......................50 Table 22: Social Categorization of Projects.................................46 Table 23: Option Analysis ....................................... ......53 Table 24: Land Use Pattern for the Khunti Nagar Panchayat......... ..........55 Table 25: Soil Sampling Locations ..........................................60 Table 26: Physico-Chemical Characteristics of Soil ..................... ....62 Table 27: Ambient Air Temperature, Relative Humidity, Vapour Pressure and Wind Speed 1S.............R...............................................65 Table 28: Rainfall, Cloud amount and Weather Table ..........................66 Table 29: Wind Direction of Ranchi material.for.constr..........31............ .............69 Table 30: Description of Ambient Air Quality Monitoring Stations ...............69 Table 31: Ambient Air Quality pp i to prje t ...................................Mt g s........................... 70 Table 32: Details of Noise M onitoring Stations ........................................................................ 73 Table 33: Ambient Noise Quality Monitoring Results................................. .............................74 Table 34: Details of Water Sampling Locations .................................................... ......76 Table 35: Ground Water Quality Monitoring Results .........................................................78 Table 36: Primary Water Quality Criteria for Designated-Best-Use-Classes...............81 Table 37: Surface Water Quality Monitoring Results .........................................................82 Table 38: Incom e Profile of the PIA .......................................................................................... 83 Table 39: Distribution of average HH expenditure..............................................................83 Table 40: Working status of Population (% to Total Population of 18-59 years)........84 Table 41: Occupational Pattern of PIA .................................................................................. 85 Table 42 Stakeholders identified and methods used .........................................................95 Table 43: Findings of Community Consultation................................................................. 98 Table 44: Findings of consultation with elected representatives ......................................101 Table 45: Findings of Consultation with Government Officials .........................................103 Table 46: Consultation of Draft ESIA ....................................................................................101 Table 47: Details of influence area of the proposed sub-project components..............112 Table 48: Environmental Impact due to construction and operation phase ..................117 Table 49: Type of Construction of Affected Structure..........................................................127 Table 50: Details of the kiosk affected ......................................................................................127 Table 51: Sum m ary Project Im pacts..........................................................................................134 Table 52: Entitlem ent M atrix ........................................................................................................132 Table 53: Compensation and Assistance for Khunti Water Supply Project ...................136 Table 54: Key institutions for EMP implementation ..............................................................143 Table 55: Environmental and Social Management Plan for Khunti Water Supply S c h e m e ..............................................................................................................................................14 8 Table 56: Monitoring schedule during construction phase ................................................170 Table 57: Environment monitoring schedule in operation phase .....................................173 Table 58: Capacity Building and Training Plan ......................................................................178 Table 59: Indicative Budgetary allocation for EMP implementation .................................180 Table 60: Solid and Hazardous Waste- Construction Phase ..............................................220 ACRONYMS AND ABBREVIATIONS AAQ Ambient Air Quality BIS Bureau of Indian Standard BMTPC Building Materials & Technology Promotion Council CGWA Central Ground Water Authority CGWB Central Ground Water Board+C26 CTE Consent to Establish DEM Digital Elevation Model DG Diesel Generator EHS Environmental Health Safety EPC Engineering Procurement Construction ESMP Environmental Social Management Plan HSSE Health Safety Social Environment IFC International Finance Corporation JSEB Jharkhand State Electricity Board JSPCB Jharkhand State Pollution Control Board JUIDCO Jharkhand Urban Infrastructure Development Company Limited KII Key Informants Interview KNP Khunti Nagar Panchayat NH National Highway OF Out Fall OP Operating Procedure PM Particulate Matter PVC Polyvinyl Chloride RCC Reinforced Cement Concrete RoW Right of Way UDHD Urban Development and Housing Department ULB Urban Local Body JMDP Jharkhand Municipal Development Project JUIDCO Jharkhand Urban Infrastructure Development Company Ltd. WB World Bank ESMF Environmental and Social Management Framework ESIA Environment and Social Impact Assessments GoJ Government of Jharkhand ToR Terms of Reference ESR Elevated Storage Reservoir WTP Water Treatment Plant EMP Environment Management Plant WSS Water Supply Scheme SES Socio-Economic Survey PIA Project Impact Area Col Corridor of Impact PAPs Project Affected Persons RAP Resettlement Action Plan SIA Social Impact Assessment JSEB Jharkhand State Electricity Board GRC Grievance and Redressal Committee 1| Page EXECUTIVE SUMMARY Introduction The Urban Development and Housing Department (UDHD), Government of Jharkhand has designed the Jharkhand Municipal Development Project (JMDP) with an objective to improve urban service delivery and urban management capacities in selected Urban Local Bodies (ULBs). JMDP entails planning and implementation of multiple sub-projects across districts in Jharkhand. The Government of Jharkhand has identified the Jharkhand Urban Infrastructure Development Company Ltd. (JUIDCO Ltd.) as the primary implementing agency for executing the JMDP. The Government of Jharkhand is seeking financial support from the World Bank towards the cost of the JMDP. An Environmental and Social Management Framework (ESMF) has been prepared by JUIDCO for the JMDP with the following objectives: to assess and manage the potential environmental and social risks and impacts that may come up during implementation and throughout the project cycle; to ensure the social and environmental sustainability of investments; and to ensure compliance with national environmental and social legislation and World Bank safeguard policies. As required by the ESMF, screening, and categorisation, an Environment and Social Impact Assessments (ESIA) and management plan has been conducted for the Khunti Water Supply sub-project by consultants independent of DPR consultants, following the requirements of Bank OP 4.01 Category A project. WBG EHS Guidelines, and Industry Sector Guidelines for Water and Sanitation have been used to identify impacts and recommend suitable mitigation measures. About the Khunti Water Supply Sub-Project The Khunti Water Supply Scheme in Khunti Nagar Panchyat is one of the sub-projects for implementation under JMDP and this document is the ESIA and ESMP of this sub-project. The current Water Supply Scheme supplies 0.9 MLD of water and covers partially 30 percent of the urban area. It was first constructed in the year 1982 with a 3m weir, distribution network, an intake well, and one ESR. A pumping facility from the intake well and WTP were upgraded later in the year 2006 after which regular piped water supply system was commissioned. The proposed sub- project will augment the existing system by expanding to 13.54 MLD of water till the ultimate design year i.e. 2048. 21 Page The existing intake well, on Tajna River will serve as source of water for the project. For this purpose, the Water Resources Department, Government of Jharkhand has issued a no objection certificate for drawing of the increased amount of water from the intake, based on a water balance calculation conducted as part of the DPR, and the departments own investigations. The current raw water main pipeline connecting the intake and proposed new WTP will be replaced with a new 500mm dia and 1650m length. The existing WTP will be decommissioned and a new 16 MLD capacity WTP will be developed, and connected with 4 ESRs (3 New & 1 refurbished) and about 8.7 kms of rising mains; and 122 km new distribution lines will be laid under this project to supply 100 percent household (8350) connections with automated meters. The entire project is divided into 4 zones, distribution consists of new DI pipes replacing old PVC, HDPE and Cl pipes. Operations and Maintenance will be supported for 5 years' post implementation of the project Applicable Environmental and Social Policies The key environment and social laws and legislation applicable for Khunti water supply project, are Water (Prevention And Control of Pollution) Act, 1974; The Water (Prevention And Control of Pollution) Act, 2012; Air (Prevention and Control of Pollution) Act 1981, The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006; Construction and Demolition Waste Management Rules, 2016, The Noise Pollution (Regulation and Control) Rules, 2000 Country Labour laws' and Street Vendors (Protection of Livelihood and Regulation of Steet Vending) Act, 2014. In addition, a set of operational policies laid down by the World Bank will also be applicable to the project, which are OP 4.01 Environmental Assessment; OP 4.36 Forests; OP 4.12 Involuntary Resettlement; OP 4.10 Indigenous People; and World Bank Policy on Access to Information and Disclosure. The project shall also follow WBG EHS Guidelines, and WBG Industry Sector Guidelines on Water and Sanitation. Public and Stakeholder Consultations As a part of environmental and social impact assessment, two rounds of public/stakeholder consultations were organized in Khunti to seek inputs into the project design and 1 Contract labour (Regulation and Abolition) Act 1970; Sexual Harassment of Women at the Workplace (Prevention, Prohibition and Redressal) Act, 2013; Employees P.F and Miscellaneous Provision Act, 1952; Child labour (Prohibition and Regulation) Act 1986; Inter-State Migrant Workmen's (Regulation of employment and Conditions of service) Act, 1979; The Building and Other Construction Works (Regulation of Employment and Conditions of Service) Act 1996; Minimum Wages Act 1948; Equal Remuneration Act 1976; Weekly Holidays Act 1942; Employer's Liability Act 1938; Bonded Labour System (Abolition) Act 1976 etc. 31 Page development of the ESIA in January 2017, and on an advanced draft of the ESIA in October 2017. Furthermore, information pertaining to the sub-project including work schedule, procedures involved, finalization of project components with identification of impacts, entitled persons, mitigation measures and grievance redressal mechanisms was discussed and disseminated. Stakeholders such as the public, the ULB, the Land Revenue Department, National Highway Authority of India (NHAI), Water Resources Department etc. were also involved in the consultations. The suggestions arising from the consultations were incorporated, as appropriate, in the designs and mitigation plans. The summary of public consultation inputs, undertaken as part of ESIA is detailed below: i. The project does not require any land acquisition or any permanent impact to structures. ii. Impacts are limited to non-title holders. The structure of only 2 non-title holder will be affected due to the project. There will be temporary loss of income of 35 PAPs for approximate 20 days during the actual construction process. There is only one Schedule Tribe household to be affected. iii. Assistance will be provided for the temporary impacts. The relevant provisions of the Entitlement Matrix were made known to the public and a Hindi version of the same would be distributed before mobilization of the contractor. Locals were also informed of skill development training. iv. People have raised the issue of noise and air pollution that would be generated during the construction phase and have requested for implementation of suitable mitigation measures. v. Water pipelines should be separated from the roadside drainage to avoid any possible contamination. vi. Free water points for public use need to be considered. vii. As informed by people, the contractor should keep a provision for employment of local persons (mainly women), in the project. Screening, Categorisation and Assessment of Impacts Screening of the subproject was carried out in line with the checklist attached in Annexure I. Khunti Urban Water Supply Project is categorized under environment as E-1. As per the ESMF guidance, all project involving sensitive environmental areas, including forests would qualify for El categorisation. The proposed sub- project will involve replacement of 233 m of pipeline within protected forest area. 41 Page The key positive impacts due to the sub-project are (a) improved water quality and quantity; (b) increase in employment opportunities for locals; (c) reduction in groundwater abstraction (d) improved living standards and hygiene within the project area; and (e) improved institutional capacity of the ULB to manage the sustainability of the water supply infrastructure. This ESIA identifies the environmental and social impacts that may occur because of the implementation of the sub-project in all its phases; design, construction and operation. The sub -project will be implemented on similar alignments as the old water supply scheme and all infrastructure components proposed under the subproject are located within the town and its surroundings. The expected environmental impacts during construction phase include (a) waste and construction debris generation from decommissioning of the old water supply scheme [old WTP, and ESR, and disposal of old distribution lines] (b) excavation activities causing impacts on soil erosion, vegetation and increased risks of accident and injury (c) increase in dust, air, noise pollution and with the town and disruptions in traffic/ pedestrian movement flow (especially where pipelines cross major roads). Impacts will be site specific, and in most cases mitigatory measures are standard. The ULB has designated a landfill site which has the requisite capacity to accommodate for debris and waste, in addition a site for setting up the contractors labour camp has been designated over 1 acre near the existing WTP where 50-60 migrant workers will be accommodated. The project will not affect any physical cultural resources adversely, and there are no historic and archaeological significant sites in the town of Khunti. No land acquisition will be undertaken for the project. Land for three ESRs and intake well is already in possession. Around 1650 m of pipeline will be upgraded and 130.758 km will be newly laid, The newly laid pipe will be within the RoW and there is no change in the character of land. The project involves loss of two structures of two non-titleholders within the road Right of Way (RoW). Also at the time of laying of pipes is likely to cause loss of income for 35 street vendors temporarily. As per ESMF categorisation criteria, Khunti Water Supply Project is categorised as S-2. A separate ARAP is prepared to meet the requirement of country legislations and World Bank's Operational Policy 4.12 on Involuntary Resettlement. The existing Raw Water pipeline of 300mm, would need to be replaced by 500mm pipeline. The current alignment of 233 m of raw water pipeline is located on forest land (for which 0.02 Ha area would be utilized) also a Scheduled V area. A clearance for this has been granted by the Divisional Forest Officer, Khunti, under section 3 (2) of The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006. As this is a 5 1 Page government legally designated protected forest, the ESMP will follow all recommendations given in the clearance, no trees will be cut and consent of the forest dwelling community in the Gram Sabha has been taken as per the procedure of clearance under the applicable Act. An Scheduled Tribe Participation Plan (STPP) has also been prepared to ensure community participation throughout the sub project cycle to fulfil the requirement of World Bank's policy 4.10 on Indigenous Peoples and OP 4.36 on Forests. The ESMP also specifies all precautionary measures not to damage I disturb the sensitive areas, and to avoid any impacts. Operation phase impacts are minor, the ESIA has put in place effective mechanisms and mitigation for occupational health and safety risks for the WTP operators and adequate treatment and disposal of sludge from the WTP during operation phase. Since back water is recovered and re-circulated in the WTP, no wastewater will be generated from water treatment process. A sewerage scheme is being planned for Khunti Nagar Panchayat (KNP) area, and will be fully operational in the next 4-5 years. Environment and Social Management Plan An Environment and Social Management Plan (ESMP), which elaborate on the identified mitigation measures, and the means of their implementation, the monitoring plan and the costs involved have been prepared along with ESIA. The ESMP has a budgetary requirement of INR. 29.22 lakhs for the construction phase, and INR 25.4 lakhs for O&M phase comprising of 5 years. The cost for the ESH training, mitigation, waste disposal and labour camp have been included in the Project cost. The costs for environmental quality monitoring, personal protective equipment for labour have been provided. The Management Plan also covers operation and maintenance phase has also been prepared with special emphasis on water quality monitoring and sludge management. Abbreviated Resettlement Action Plan (ARAP) proposes a budget of INR 7.74 lakhs. However, no separate budget has been provisioned under Scheduled Tribe Participation Plan (STPP) as the implementation arrangements for ensuring participation of the forest dwellers remains the same as ESMP and ARAP. This has been included in the overall sub- project costs. 61 Page Grievance Redressal mechanism A GRC will be set up at the state and ULB level. The objective is to receive and resolve the affected communities concerns, queries, complaints and grievances about the environmental and social aspects of the Project that could be encountered during implementation as well as to address other social issues pertaining to social cohesion and integration once the sub- projects implemented. Some means of communicating information on JUIDCO's GRM includes the following: Distribution of leaflets to the public places Notice boards JUIDCO's website Telecommunication Tools The Deputy Project Director (JUIDCO, PMU) will be responsible for ensuring that each sub- project establishes an effective multi-level GRM to handle all grievances related to sub- project activities. The GRM will function at 2 levels: at the community level, where every effort will be made to resolve the issue; and at the sub-project level where,a GRC will be established and as an appeal mechanism at state level. the sub-project level GRC shall be constituted with following Members. One from the ULB/executing agency Any one elected representative (local project area; preferably female) Representative of a community-based group of women such as Mahila Samakhya/Mahila Mandal A person who is publicly known and accepted by the locals (in the project area) to speak on their behalf (to be identified by the elected representatives of the ULB) Community development officer from PlU Medical officer Officer from concerned department such as police, transport and labour ULB-level community organiser or Chief Municipal Officer's representative The PAP will have to clarify the area of grievance. The GRC will entertain only grievances related to construction activities affecting the livelihood or loss of property/utility or restriction of access, labour community conflict, construction site management and quality of service during the O&M period. Grievances related to corruption will only be dealt under the anti- corruption laws of the Jharkhand. 71 Page The PAP (or his/her representative) may submit his/her complaint in by either written letter, phone, or email to the GRC or, alternatively, raise his/her voice in a public or individual meeting with project staff. A very simple grievance form in local language will also be available at each project site to be filled in by the complainant. Also complaint boxes shall be placed at ULB office, PIU office and Contractors campsite/office. One person in PIU and Khunti contractor office will be designated as complaint officer responsible for reciving all the grievances (oral or written) and maintaining the log of such complaints and action taken. This complaint officer shall facilitate filling the grievance form in case of illiterate complainants. NGO engaged for ARAP implementation shall act as facilitator in ensuring that all the complaints/suggestions reach the attention of PIU head especially of the PAPs and local community. The effectiveness of the GRM shall be tracked through progress report of Construction Supervision and Quality Consultants (CSQC) and NGO facilitating ARAP implementation. The contact details of the registering complaints/suggestions at state level is given below: Grievance Redressal Cell Jharkhand infrastructure Development Company Limited 3rd Floor,Pragati Sadan, Kutchery Chowk Ranchi-834001, Jharkhand Phone No: 651 2243203 Email: grc.jmdp.juidco@gmail.com The GRC will meet to try and resolve the matter at community level and make a recommendation usually within 7-10 working days from receipt of complaint. If there is no decision after 10 days, the PAP or any other aggrieved person can refer the complaint to the Deputy Project Director (JUIDCO, World Bank PMU). The Deputy Project Director (JUIDCO, World Bank PMU) will chair an Appeals Committee, which will then examine and address the complaint within 20 days. It is recognised that some complaints may take longer to resolve due to their complexity, for example, those related to land disputes. In such cases, the greived party shall be communicated the possibility of delays with reasons and next actions within 20 days, All submitted complaints and grievances will be registered at the sub-project level and added to a database of JUIDCO-JMDP PIU, which will be monitored regularly by designated JUIDCO-JMDP staff.In addition to the mechanism explained above, PAPs have the right to approach the judiciary of the country. 81 Page Gender Issues, Action Plan and Monitoring Indicators The main gender issues in the project are inequality in accessibility to urban infrastructure and services, safety and security of the women, inequality in participation of women workforce and awareness of women about their rights. The project will ensure easy accessibility to improved urban infrastructure and services through 24x7 domestic water supply for households and better roads. Proper street lighting will increase the safety and security of women. There will also be a provision for the contractor to employ local people, preferably women. The implementing consultant/NGO would increase the awareness among the women regarding their rights and opportunities available from the project. The monitoring indicators are the number of connections of water supply points to the vulnerable population particularly women headed households in the sub-project area, contractor's progress report shall include number of women employed and their wages and monthly status of the grievance redressal mechanism(GRM). Institutional and Implementation arrangement for ESMP Supervision The State PMU in Ranchi at JUIDCO will be overall responsible for addressing environmental and social safeguard measures. An environmental and social specialist is already in place in the PMU. The PMU will be supported by a Project Implementation Unit (PIU) at Khunti, responsible for day-to-day implementation of ESMP, ARAP and STPP. The PMU specialists will also train and strengthen the capacities of specialists in the PlUs and other implementing entities. The project shall hire qualified civil society organisations/NGOs for the implementation of ARAP and other social mobilisation/IEC activities under the Khunti Water Supply Project. Construction Supervision and Quality Control Consultants are also in the process of being hired, and will contain a dedicated Environment, Social, Health and Safety Officer to verify compliance with ESMP, labour management, occupational health and safety requirements, and waste management procedures. The Project Management Consultants (PMC) shall provide additional support of Social and environment specialists to the PMU and PIU to coordinate, review, support and monitor all respective safeguards aspects of the Khunti Water Supply Project. 91 Page The compliance of the ESMP, labour management and OHS management by the contractor shall be monitored and assessed during construction by the PlU and CSQC consultant, and formal inspections by the PMU staff. There will also be a safeguard audit of the works which shall be carried out by an independent consultant. 10 | P a g e 1 INTRODUCTION 1. The Urban Development and Housing Department (UDHD), Government of Jharkhand (GoJ), has created the Jharkhand Municipal Development Project (JMDP) with an objective to improve urban service delivery and urban management capacities in selected Urban Local Bodies (ULBs). The Government of Jharkhand (GoJ) has sought financial support from the World Bank (WB) towards the cost of the JMDP. Jharkhand Urban Infrastructure Development Company Ltd. (JUIDCO Ltd.) has been identified as the primary implementing agency for the JMDP. "JUIDCO" is a company created under the administrative control of Urban Development Department, Government of Jharkhand for formulation, implementation and monitoring of various central/state sponsored urban infrastructure development schemes in the state of Jharkhand. JUIDCO has been undertaking implementation of water supply projects in the urban areas across the State of Jharkhand, besides 2. The JMDP encompasses upgradation of municipal infrastructure (expansion of coverage, and construction and rehabilitation of basic infrastructure systems, such as, water supply, roads, municipal buildings, etc.) and associated operation and maintenance support. The JMDP primarily has three components, as shown in Figure-1 below. Figure 1: Components of JMDP ...........I Companents of JMDP , Urban Infrastructure Improvement Polkcy and institutional Support * Project Management and Implementation Support 3. These components entail planning and design of multiple sub-projects, across different districts in Jharkhand. The priority sub-projects have been identified by the Government of Jharkhand based on technical, environmental, social and financial sustainability of the investments. 4. An Environmental and Social Management Framework (ESMF) has been prepared by JUIDCO for the JMDP with the following objectives: to assess and manage the potential 11| P a g e environmental and social risks and impacts that may come up during implementation and throughout the project cycle; to ensure the social and environmental sustainability of investments; and to ensure compliance with national environmental and social legislation. As per World Bank policy 4.01, an ESMF is an instrument that examines the issues and associated impacts when a project consists of a program and/or series of sub-projects, and the impacts cannot be determined until the program or sub-project details have been identified. The ESMF sets out the principles, rules, guidelines and procedures to assess the environmental and social impacts. It contains measures and plans to reduce, mitigate and/or offset adverse impacts and enhance positive impacts, besides provisions for estimating and budgeting the costs of such measures, and information on the agency or agencies responsible for addressing project impacts. 5. As required by the ESMF, Environment and Social Impact Assessments (ESIAs) are being conducted for the selected priority sub-projects. 1.1 Brief Description of Project 6. The Khunti Nagar Panchayat (KNP), an urban area in the state of Jharkhand, is partially receiving water from the existing water supply scheme commissioned in year 1982 and upgraded in 2006. At present, only 14% of the total households of Khunti Nagar Panchayat, spread across 10 wards out of the 16 wards, have water connections. The remaining areas depend entirely on ground water for meeting their daily needs. The proposed sub-project, called the Khunti Urban Water Supply Scheme (Khunti-UWSS), is aimed at 100% coverage of piped potable water supply on 24x7 basis in KNP. The proposed source for the Khunti- UWSS is the Tajna River - a left bank tributary of the Swarnrekha river in Swarnrekha basin in the Khunti district. The following activities are to be taken up under the proposed sub- project: the existing 300 mm of pipeline from intake well will be replaced by 500 mm DI pipe; a new 16 MLD WTP will be developed; three ESRs will be constructed; one existing ESR will also be rehabilitated and used; 100% household connections with automated meters will be provided. 1.2 Objective of the ESIA Study 7. The objectives of the ESIA is a) Identification of the project activities b) Description of existing environment and social conditions of the area c) Assessment of potential impacts associated with the project activities 12 | Page d) Mitigation and monitoring measures proposed for impacts identified and e) Incorproation of stakeholder suggestions and feedback f) Preparation of an environment and social management plan which includes implmementation arrnagements for supervision. 1.3 Approach and Methodology 8. This section of the report details the step by step approach followed for conducting the ESIA of Khunti-UWSS with respect to the proposed sub-project as illustrated in the Figure-2 below. Figure 2: Overview of methodology followed for conducting the ESIA 1. Preparatory Activities - Reviewed and compiled secondary data - Conducted field visit to identify environment and social receptors - Identified primary and secondary stakeholders 2. Analysis of alternatives D - Compared feasible alternatives to the proposed project site, technology, design, and operation in terms of their potential environmental impacts 3. Collection of Environment and Social Baseline Data - Monitored data for ambient air quality, water quality, soil quality, ambient noise quality - Conducted Socio -Economic Survey (SES)/Census Survey to collect socio -economic data - Conducted stakeholder consultation to collect first hand information from the beneficiaries and Project Affected People (PAP) 4. Impact Assessment - Compared feasible alternatives to the proposed project site, technology, design, and operation in terms of their potential environmental impacts 5. Development of ESMP and other mitigation Plans - Developed ESMP Developed ARAP and STPP (a). Preparatory Activities 13 | Page 9. Preparatory activities included team mobilisation and compilation of existing secondary information pertaining to the project area. Field visits were planned and conducted during February 2017 with the following objectives: Assessing existing environmental conditions Identifying potential environmental and social impacts Identifying potential mitigation measure Identifying interested and affected individuals or parties Preparation of a strategy for the Process Public Participation (PPP) (b). Analysis of Alternatives 10. The feasible alternatives to the proposed project site, technology, design, and operation were analysed in terms of their potential environmental and social impacts. (c). Collection of Environmental and Social Baseline Data 11. This section details the methodology adopted for establishing the environmental and social baseline. A. Environmental Baseline 12. The baseline environmental status is important to understand the existing physical and biological characteristics along with cultural and social status of residing community. The data presented in this section is based on field surveys, monitoring, stakeholders consultations and secondary data collection ( drainage, topography, climate, flora and fauna). The information on the baseline environmental conditions (Water/Air/Noise quality and Soil monitoring), forms the basis to analyse the probable impacts of the proposed project vis-6-vis the present background environmental quality of the core study area. In case of environmental baseline, sampling of air quality, water quality (surface and ground), soil quality, and noise levels was undertaken in the first week of March, 2017. The sampling locations for monitoring of air, water, soil, and noise quality were identified based on the following: Existing topography Sensitive environmental areas and receptors Location of water bodies Wind direction and location of village/towns/sensitive areas Accessibility, power availability and security of monitoring equipment 13. The details of the parameters monitored have been presented below: 14 | Page Ambient Air Quality: Ambient air quality was monitored at four locations for parameters including Particulate Matter (PM<10 micron, PM<2.5 micron), SOx and NOx. Water Quality: Information on water quality was generated by collecting and analysing samples from three surface water bodies and five ground water locations. Soil Quality: Soil quality was assessed by collecting six soil samples from four locations. Further, the collected soil samples were analysed for the physical and chemical parameters. Ambient Noise Quality: Ambient noise quality was monitored for 24 hour at four locations within the study area. Land Environment: Information regarding topography, geology, seismicity, ecology and land use pattern was collected through various field visits, secondary research and information available with the project proponent. B. Social Baseline 14. As the first step, data from the secondary documents such as Census, ULB records etc. was reviewed for collecting basic socio-economic information. As the next step, a census survey was conducted with an objective of gathering first-hand information on the following: Inventory of affected assets Categorization and measurements of potential loss Physical measurements of the affected assets/structures Identification of trees and crops Household characteristics, including social, economic and demographic profile Identification of non-titleholders Assessment of potential economic impact, including temporary loss 15. The census survey covered 100% structures affected within the proposed Right of Way (ROW) as per the Corridor of Impact (Col) of the DPR and drawings provided. Structures considered are permanent (pukka), semi-permanent (semi-pukka) and temporary (kutcha). In addition to census survey, a series of public consultations were conducted during January, March and June 2017 after finalisation of the methodology, protocol and communication strategy by JUIDCO. The stakeholder consultations were conducted through focus group discussions, individual interviews and formal as well as informal meetings. The vulnerable sections of Project Affected Persons (PAPs) were also included in the 15 | P a g e consultation process in the ward level meetings. The public consultation helped in ensuring people participation in the planning and implementation phase and further facilitated in disclosure of the project details to the would be PAPs and beneficiaries. In conformance to the World Bank principles of consultation and disclosure, the project activity was disclosed across the selected locations with the following key objectives: Understand the community concerns and issues Disclose environmental issues that may arise due to the project and discuss suggestions for mitigation measures Assess the present-day project site's characteristics and definitive social, livelihood, and environmental impacts Consult with affected communities and/or entities on the proposed project alternatives in order to minimize adverse impacts and enhance beneficial ones Obtain a consensus on the proposed activity, potential impacts and suggested mitigation measures (d). Impact Assessment and Management Plan 16. Primary and secondary data collected for establishing the baseline, were analysed for identification of potential environmental and social impacts that may occur during different phases of the project. For each of the identified impacts, measures to avoid and/or mitigate these have been recommended in the Environment and Social Management Plan (ESMP) and Abbreviated Resettlement Action Plan (ARAP) and Scheduled Tribe Participation Plan (STPP). A relevant monitoring plan has been proposed to ensure effectiveness of the management measures. 17. The sub-steps followed for conducting impact assessment and developing management plan are given below: Reviewed literature related to the project Conducted field visits to the project area Conducted stakeholders consultations with PAPs, ULB and other local community members about the project Established environmental and social baseline of the project area Identified potential environmental and social impacts, considering the characteristics of the project and the biophysical and socioeconomic characteristics of the area Developed recommendations on mitigation measures to be implemented to mitigate the negative environmental and social impacts due to the project activity 16 | P a g e 1.4 Layout of the Report 18. The ESIA report has been organized into the following sections: Section 1: Introduction - This section provides a brief introduction to the project, scope of the ESIA and methodology followed for developing the ESIA. Section 2: Project Description- The project details in terms of location and components have been presented in this section. Section 3: Legal and Regulatory Framework-This section details out the acts, policies and regulations rolled out by the Government of India at central and state level, which are applicable to the proposed project. Further, this section also reviews the applicability of World Bank's safeguard policies to the project activities. Section 4: Analysis of Alternatives- This section presents two scenarios, 'with project' scenario and 'no project' scenario. Section 5: Environmental Baseline Profile- The findings of baseline studies conducted and secondary information collated have been presented in this section. Section 6: Social Profile of the StatelDistrict and PIA - The socio-economic profile of the state, district and the PIA have been presented in this section. Section 7: Public Consultations and Disclosure - This section presents the summary of the public consultations including key informant interviews and in-depth interviews with primary and secondary stakeholders. Section 8: Environmental Impact Assessment - This section presents the environmental impact assessment and environmental impacts identified during various phases of the project. The mitigation measures for the impacts have also been presented. Section 9: Social Impact Assessment (SIA) and Mitigation Plans - This section presents the social impacts that may occur due to the project activity and summary of relevant mitigation Plans prepared. Section 10: Environmental And Social Management Plan- The measures to avoid and mitigate environmental and social impacts across different phases of the project cycle with allocation of responsibilities and monitoring plan for reviewing effectiveness of the measures have been presented in this section. The cost of implementation of EMP has also been presented here. 17 | P a g e 2 PROJECT DESCRIPTION 2.1 General 19. The Khunti Nagar Panchayat (KNP) receives water from the existing water supply scheme which was commissioned in the year 1982 and upgraded in 2006.. At present, a total of 1001 numbers of water connections are in place i.e. is only 14% of the total HHs in KNP. 30% geographically covered (partially in ten wards out of 15). The remaining area depends on ground water for meeting their daily needs. The quantity being supplied in Khunti is 65 Ipcd approximately. The final per capita supply is calculated after deducting 20% of non-revenue water. Average water losses during the transmission and distribution are about 20 % in Khunti.The proposed sub-project is aimed at 100% coverage of piped potable water supply on 24x7 basis in KNP. 2.2 Proposed Project 2.2.1 Site Setting 20. The proposed sub-project is situated in Khunti town, located in Khunti district which is the newest district of Jharkhand situated at 611 meters above sea level and located along National Highway 23 at latitude 23.080 North and longitude 85.280 East located in south central part of the state. 21. Khunti is surrounded by Ranchi and Gumla districts in the north, Chaibasa and Seraikela districts in the south, Ranchi and Seraikela districts in the east, Gumla and Simdega districts in the west. The proposed source for Khunti Urban Water Supply Scheme is Tajna River - a left bank tributary of Swarnrekha River in Swarnrekha basin in the Khunti district. River Tajna/Karkari (Perennial River) is the only surface water supply source for Khunti flowing through the north-eastern boundary of Khunti town. 2.2.2 Current Scenario 22. The existing surface water supply scheme includes an intake well, a 3-m weir (located downstream of the intake), a WTP, 1 ESR and the distribution network. The details of the existing water supply scheme are tabulated below. Table 1: Details of Existing Water Supply of KNP S.No Component Details 1 Total Water Supply 0.9 MLD 2 Name of Source Tajna/Karkari River with existing weir 3 Type of Source Perennial River2 4 HFL 606.72 5 DBL 602.84 6 Present Water Level(m) 604.94 7 Weir Stone Masonry, 3m 2 A Hydrological test/monitoring conducted by the Water Resource Department, GoJ in regular interval, accordingly perennial river is decided. 18 | P a g e 87 Location of Intake Near Mukti Dham adjoining NH23 8 Intake Well Dia & Depth Diameter: 6 m & Depth :6 m 9 Intake Capacity >12.37 MLD 10 Gangway Length & Width Length: 20m & Width:3m 11 Pumps available at Intake 30 HP & 30 HP (Stand by) 12 Head 35 m 13 Pipe Material DI 14 Dia & Length of pipe material Diameter:300 mm; Length :1350m Source: DPR Pumping machinery at intake 23. The current pumping machinery at the intake wells have been presented in Table 2. Table 2: Pumping Machinery at Intake S.No Project Component Details 1 Pumps available at Intake 1. 30 HP 2. 30 HP (Stand By) 2 Head 35 m 3 Discharge 2400 Ipm 4 Transformer 200Kva 5 HT Line Availability Yes (Through Village Feeder) 6 Pumping Hours 10-12 hours a day 7 Power Supply 10 Hours (Poor & Intermittent) 8 Age (Year of Installation) 2006 (9 Years Old) Source: DPR provided by JUIDCO Raw Water from Intake to WTP 24. The current raw water from intake to WTP has been presented in Table 3. Table 3: Raw Water from intake to WTP S.No Project Component Details 1 Pipe material DI 2 Diameter 300 mm 3 Length 1350 m 4 Age 2006 Source: DPR Clear Water Main from WTP to Sump at ESR 25. The details of the current clear water main from WTP to sump at ESR is presented in Table 4. Table 4: Clear Water Main from WTP to Sump at ESR S.No Project Component Details I Pipe material DI 2 Diameter 250 mm 3 Length 34000 m 4 Age 2006 Source: DPR WTP 26. Currently, the raw water is treated through a conventional process at the existing treatment plant. 19 P a g e Table 5: WTP plant details S. No. Component Details 1 Capacity 2.25 MLD 2 Working Hours 10-12 Hours/Day 3 Type Conventional 4 Age (Year of Installation) 1982 5 Clear Water Sump 337500 Litres 6 Transformer 200 KVA Source: DPR 27. The following units are present in the current WTP: Aeration fountain Flash Mixer Flocculator Clarifier Rapid Sand Filter Chlorination Arrangement Elevated Storage Resavoir (ESR) 28. The details of the current ESR under the WSS has been provided in Table 6. Table 6: Current ESR S.No. Component Details 1 Location Behind Police campus 2 Age (Year of Installation) 2007 3 Condition Structurally Safe 4 Total Capacity 450000 Litres 5 Staircase Iron Ladder with railings Source: DPR Distribution and House Connections 29. The details of current distribution and house connections in Table 7 Table 7: Current Distribution and House Connection S.No Component Details 1 Type of Pipe DI, PVC, HDPE 2 Diameter DI K7 300 - 1100m Di k7 250 - 112m DI K7 200 - 600m PVC 175 - 400m PVC 150 - 5966m PVC 125 - 6000m DI K7 100 - 15960 HDPE 80 - 678 3 Age (Year of Installation) DI is 9 years Old 4 Coverage 30% (-30.81 KM) 5 Connections 1002 Source: DPR 20 Pa g e 2.2.3 Proposed Scheme 30. The existing intake well will serve as source of water for the project. The capacity of water withdrawal will be increased by replacing the current 300 mm pipe with 500 mm pipe. The distance from the intake well to the proposed WTP is 1650 m. The proposed WTP will be of 16 MLD capacity and will be connected with 4 ESRs. (3 New & 1 existing which will be refurbished) 31. Considering the topology, the entire project has been divided into 4 zones. Wards falling under the four zones have been provided in Table 8. Table 8: Zone details S. No Zones Ward Number 1 Zone - 1 Ward no. 1 & 2 2 Zone - 2 Ward no. 3,4,5,6,7 & 8 3 Zone - 3 Ward no. 9,10,11,12 & 13 4 Zone - 4 Ward no. 14,15 & 16 Source: DPR 32. Three (3) ESRs and reuse of one existing ESR is proposed under the project. Currently there is one abandon ESR in existing Zone -111, which will be demolished and new ESR of 1050 KI will be constructed. The project proposed 100% household connection with automated meters. Line diagram of the proposed scheme has been presented in Figure 3. 21| P a g e Figure 3: Line Diagram of the Proposed Scheme * - I i e - s IIe. I Source: DPR 22|Page Land Requirement for the Project 33. The total land required under the proposed scheme is 8.33 acre. The land break up details of the different components have been provided in Table 9. Table 9: Land Details S. No. Name of Location of Land Required Area Type of structure Land 1. Replacement Existing Intake structure Existing Intake Under WRD of pumps and rising mains 2. Pipeline Raw Forest land and RoW of 0.0235 Ha Forest land Water roads Govt Land pumping and Private main of 500 land mm dia. DI for a length of 3.81 Km. from intake to WTP 3. WTP Near Existing WTP. 4.88 Acre Govt. Land 4. ESR-1 (Ward No-2) Near Khunti Existing ESR Govt. Land Thana 5. ESR-2 Kadama (Ward No-4) 1.30 Acre Govt. Land 6. ESR-3 Dahugutu (Ward No-10) 2.05 Acre Govt. Land 7. ESR-4 (Ward No-14) Near Bus 0.10 Acre Govt. Land Stand 8. Clear Water In ROW of roads and 2.0 acre Govt.Land Transmission government land in System which ESR will be (-8.5 Km) constructed. Source: DPR Demand Projection 34. Proposed water supply system has been designed based on the design criteria and demand projections. The demand projection worked out as the design criteria for the project horizon has been indicated below Table 10. Table 10: Demand Projection S. No Description 2018 2033 2048 1. Population 42353 56546 74921 2. Rate of Water Supply (in Ipcd) 155.25 155.25 155.25 3. Water Demand in Litres 65,75,303 87,78,767 116,31,485 4. Water Demand in KLD 6,575.30 8,778.77 11,631.49 5. Water Demand including 7.435 9.772 12.774 firefighting and floating population in MLD 6. Total Water Demand including 7.881 10.358 13.540 Institutional demand (6%) in MLD 7. Rate of Water Supply (including 186.075 183.184 180.728 23 | Page Firefighting, floating & Institutional Demand) (in Ipcd) Source: DPR Source of water 35. River Tajna/Karkari (a perennial river) flowing through the north-eastern boundary of Khunti is its only surface water supply source. As per the DPR prepared for the sub-project; the water balance analysis conducted by JUIDCO; in consultations with the Water Resources Department (WRD) and ULB; and sustainability certificate received from the WRD, it is estimated that the source will be sufficient to cater the required demand of 13.54 MLD water till the ultimate design year i.e. 2048. The capacity calculation of existing weir and barrage has been provided in Table: IlError! Reference source not found.. A schematic diagram of the proposed project has been presented in Figure 4. Table 11:Capacity calculation of existing weir & barrage for Khunti WSS Water Demand in Base Year 7.881 MLD 7.881 X 1000 7880 cum /day In intermediate year 10.358 MLD 10.385 X 1000 10358 cum/day In Ultimate Year 13.540 MLD 13.540X1 000 13540 cum/day Quantity of water at weir site 325584 cu m Quantity of water at Barrage site 484227 cu m Total 809811 cu m Hence storage water will feed (a) In base year 809811 cu m /7880 cum 103 days (b) In intermediate year 809811 cu m/ 10358 cu m 78 days (c) In Ultimate Year 809811 cu m/1350 cu m 60 days 1 Calculation for Quantity of water at weir site Length of submergence 912 m Width at the top 280 m Height of Water (3+0)/2 1.5 m Hence Quantity 24 P a g e 918 x 280 x 1.5 383040 cum (A) Assume 85 % in current shape 325584 cu m 2 Quantity of water at barrage site Length 1415 m Width 330 m Height of Water (2.44+0)/2 1.22 m Hence Quantity 1415 x330 x 1.22 569679 cu m (B) Assume 85 % in current shape 484227 cu m Total Quantity (A+B) 809811 cu m Figure 4: Schematic diagram of proposed project 25 P a g e TaM6A W L - 60494 HFL406.72 1'A INTAKEKPIN th.C tooAV W~ Mld P"VNN RON V-M PIN'!- UNI MVNNN 10umlt Uriban Water Suepply Schere a hf- nn s.nag o .N ape * Pes a P r aowl I ga as mkgaaa t.istuean 3 h Pr opse Wate T 36. The proposed WTP will be of 16 MLD. The proposed treatment is Rapid Sand Filtration (RSF) and chlorination. The WTP will consist of a chlorination unit, aeration fountain, venturi flume, flash mixer, flocculator, clarifier, rapid sand filter with filter house, chemical storage house, pure water sump and pump house, pure water sump, pump house and post chlorination unit. Land for new WTP has been identified near the existing WTP. 26| g I age ,q*I 0E Lo E E -E . c CO - c . E - 0E o o 0 i G L - 7 u .E a CE "C c: - o 2 o. E m m 0 EEcc o 0 0 a) c o jo U) 0 4-- 0 0 - VO - E . M> 0 0 0 m D O m ) 0 (D o oc og a o E- - o oæs a E ~ o -0 . - E c : e ~ ~~ D c =o.E5_o e œ > (D a~ = - 0 E (D ti>å .9 æe E-C8 3 o-9E _* . æ>. oEg O. c toen - Eæ 0 m o -!-- - -3 Lo 0 a -oEc. · E E E E o O- O ~ ~ ~ ~ ~ ~ ( m E -o0 ~oE9 35o n 0 Ø D - E > o E ~ ~ ~ C (D cn 0 ~ r ~* ~ 0 0 c. 4- _. E o 3 U) 0 - ø E,m 0 *o 0 4- 0 ( a * o 5 o 0'¯'-o.2*c2o o o y o < o g .. o o0 o 0) -= 0 c (D 0- = (n 0 a , w * L- ~:) E- -o - . . .o g o- = r-- o 3 O N - a 0- 00 . 3)0o - ~ U o -ø (o o -o _oa 0- E > × N E 2 LO 0 m ' ION) EEE EEøEv>O- 0)e 0 (n .E - oo c 7 LD c 0 iG- o -0 æ . ti E G> / (0c,o u æ--2 C . C) M æ ~-00 0 ø o 5 E o i 0~' O l 0 co- CE- C E _u E 0 0 L0 0E j ~( c- Lý (o E - E E =-ýr-N00 (u~- C)- 3- x ( 0 0000U na (D E m0 - D m E U) 0 ~ 0E~ c< > LL LLO a_ CO 00 z m ~~ U' 0 0 0 Proposed system for waste water and sludge disposal: 37. System for recycling of wastewater: It is estimated that the backwash water will be about 5% of the daily production (i.e. about 0.52 MLD considering a production of at least 10.38 MLD up to the year 2033). The proposed system of recycling this water will be using a series of RCC sedimentation tanks that will allow sufficient time for the sludge and particles to settle down and the remaining clarified water will be reused by directing it to the channel of raw water inlet to flash mixer via a small pump. This arrangement will avoid pollution and minimize wastage of water. 38. The size of the tanks has been designed considering 5% of the disposal of the daily production (i.e. about 0.52 MLD considering a production of at least 10.38 MLD up to the year 2033). Figure below presents the design of the tanks. Figure 5: Design of WTP Tank L - I.- - - L SECTION ONXA - - -- -- Source: DPR 28 P a g e System for disposal of sludge: 39. An estimated 5.2 MT of sludge will be produced per day when total water demand will be 10.36 MLD (Intermediate Year). 40. The sludge will be collected from the tanks mechanically and will be allowed to dry in sludge drying bed for 24 hours, then stabilised and then will be disposed to the designated municipal landfill site at Belahatti. The sludge is not suitable to be re-used. The proposed landfill site is a new landfill proposed for Khunti Solid Waste Management project and the ULB has provided its NOC for the use of land for sludge disposal. Rising Main Details - Clear Water 41. The details of the proposed clear water piping details have been provided in Table 13. Table 13: Rising Main Details Clear Water SI. No Diameter Length (in meters) 1 500 mm (WTP to JN. A) 2830 2 400 mm (Jn. A to Jn. B) 780 3 350 mm (Jn. B to Jn. C) 430 4 300 mm (Jn. A to ESR 3 - 1175 m & Jn. C to ESR 2065 5 250 mm (Jn. C to ESR 4) 2140 6 200 mm (Jn. B to Ex. ESR 4) 475 Source: DPR Storage Capacity 42. About 40%-50% of the daily requirements of water, is proposed to be stored at various locations in the system to cater to the fluctuating needs of the system. About 35%-40% of the demand requirements are proposed to be stored in the service reservoirs. The balance 10% -15% is proposed to be stored in ground level tanks near the treatment plant areas. Three new ESR's s are being proposed to be built under this project. One existing ESR of 450 KI will be re-used for storing water. Details of all the ESR under the project have been provided in the Table 14. Table 14: Details of ESR SI.No. Details of ESR ESR-1 ESR-2 ESR-3 ESR-4 existing) 1. Capacity of the ESR in KL 450 1380 1050 780 2. Staging of the ESR in m 18 24 21 22 3. RL of GL at ESR in m 648.24 638.96 646.58 625.96 Source: DPR 29 | P a g e Clear Water Transmission System 43. The entire project area has been further divided into 4 different zones and different command area of the treatment plant based on the topography, physical boundaries, and reuse of existing ESR 1. The existing clear water transmission main was laid about 6 years back and the supply pattern is not uniform and pipes are found to be inadequate size with many tapings, hence existing transmission main is discarded completely. Local Distribution Scheme 44. The distribution system network is divided into 4 zones for the equitable distribution of water. The command of the existing ESR and its pressure at the tail end points were analysed, accordingly the requirement of additional reservoirs was designed. 4 zones have been formed for the equitable distribution of water. Each zone is proposed to be fed with a service reservoir. The summary of the distribution pipe network is provided in Table 15. Table 15: Statement of Distribution for the proposed scheme S.No Diameter Length ( in meters) 1 100 mm 80081 2 150 mm 11893 3 200 mm 13596 4 250 mm 42 5 300 mm 13178 6 400 mm 2424 7 500 mm 482 8 600 mm 342 Source: DPR provided by JUIDCO Design period 45. As per Central Public Health and Environmental Engineering Organisation (CPHEEO) Manual on water supply, following design periods have been adopted for different components of water supply system: Water Treatment Plant - 15 years Infiltration works (intake) - 30 yearsRaw and Clear Water main pipelines - 30 years Distribution system - 30 years Clear water ground/over - head tanks 15 years Pump house buildings - 30 years Pumping equipment (E&M) - 15 years 2.2.1 Labour accommodation 46. The construction phase of the proposed project is expected to continue for 24 months and approximate skilled and unskilled labour required for the project is projected to be 350. About 15% (approx 55 nos.) of skilled and unskilled labour may come from outside the Khunti district. Labour camp for 55 workers will be set up near proposed WTP and the 30 | P a g e remaining will be employed from nearby villages. The construction cum labour camps will be set up on an area of approximately 1 acre. Approximately 10-15 toilets are proposed to be provided at the labour camp3, the final number will depend on the number of labour residing within the camps. The toilets will be connected to septic tanks as per BIS 2470-1 (1985). Guidelines that will be followed for the siting, setting up of facilities required in the labour camp would be provided as per the specifications in Annexure VII. In addition, mobile toilets, hand washing facilities and drinking water tanks would be set up at site specific locations where labour would be working during the day. 2.2.2 Water Requirement 47. As per the detailed project report, average water requirement during construction phase for the project will be approximately 5000 ki. Water required for construction will be sourced through water tankers from government approved sources. 2.2.2 Power Requirement 48. The power requirement during the construction phase will be met through temporary electric connection from Jharkhand State Electricity Board (JSEB), and further supplemented with DG sets for back up will be used during power outage. 49. The construction phase will require a maximum of 30,000 litres of diesel. On-site fuel requirement will be met from nearby fuel stations. On-site diesel is proposed to be stored in 100 litres drums and will be kept in a designated storage area with all safety precautions. 2.2.3 Raw Material Requirement 50. For the construction of the entire project complex, raw materials like steel, sand, stone and cement will be required which will be met through government licenced quarries. No new quarries will be eatblished for the sub project. The approximate estimated quantities for the raw materials, their source and mode of transport are provided in Table 16. Table 16: Estimation of raw material for construction List of Average Source of Material Mode of Construction Quantity transportation materials and storage site Cement 782.76 MT Government Authorized Truck agency/ suppliers Gravel 110 cu m Govt. Approved local Truck quarry/suppliers Steel 221.59 MT Government Authorized Truck suppliers Sand 1,253.55 cu.m. Govt. Approved local Truck quarry/suppliers Good Earth 200 cu m Govt. Approved local Truck quarry/suppliers/nearby under construction site Bricks 222,077.60 nos. Government approved Brick Truck 3As per Worker's accommodation standard guidance note by IFC and EBRD 31 P a g e Klin Ready Mixed 1.385 CUM Mini mobile batching plant Truck/Tractor M-25 grade (transportation concrete to construction area) Source: DPR 2.2.4 Wastewater Disposal from labour camps 51. The sewage generated at the construction site will be collected in septic tanks. 1septic tanks catering to 55 users will be provided at the labour camp as per specifications given in BIS 2470 1985 Part 1. Septic tank and soak pits will be provided (as per specifications given in IS 2470 1995 Part I and Part II) onsite and at labour camp 2.2.5 Waste Generation 52. The solid waste generated by the project will consist of labour camp waste, garbage waste, metal scrap, and construction debris. The main types of waste that will be generated and sources during construction phase are detailed in Table 17. Table 17: Details of Waste generated during construction phase SI.No Waste Type Source Estimated Method of Disposal Quantity Non-hazardous waste 1. Domestic solid Labour 75 kg per day Waste will be segregated waste activities onsite and disposed through municipal corporation to Belahatti landfill site. NOC has been provided in Annex IV 2. Construction Excavation 3-5 tonnes Excavated materials to be Debris and earth work per day used for backfilling and levelling 3. Packaging waste Packing 20 tonnes Sold to recyclers containing wood, material and per year cardboard and accessories other recyclables 4. Concrete ESR and old 126.945 To be used as back WTP CUM filling and levelling. Hazardous waste 1. Waste oil and oil DG set 0.5-1 ton per Collected and disposed contaminated rags ,construction annum through CPCB/JSPCB machinery approved recyclers Bituminous Waste From road 190.4175 Re-use as back filling and A_ cutting CUM levelling Source: DPR 2.2.6 Implementation (Construction and O&M) Schedule 53. The implementation schedule of the sub-project after the tender process is presented in Figure 6. 32 | Page 33 | P a g e b) co Ln~ mm rl c-i aj ej 1n '- r. - 4 r3 0 Ln 0 . xi W rm > >1 0 uC toj D). C L'" LL - o -a ra L r] 0 9 > - o -CL eje E aj0 m m - +- m m cu U-j 5 E9 .w u n b E - c 3: 1 - - OJe o OJ a w - zd - j - 5 1- >*k Ti f -=q Cr c uJ c OJ c. % u o .aaj E r o c OJCO 00 2~~C r-l ~ I, Ii' 0r 3 ADMINISTRATIVE, REGULATORY FRAMEWORK & PROJECT CATEGORIZATION 54. This chapter details out the policy, legal and institutional framework under the ambit of which the ESIA was undertaken. It reviews the national and state laws of Jharkhand relevant to the scope of activities under the sub-project, and, discusses the implications for the sub- project design and implementation 3.1 Applicable National & State Laws and Regulations 55. An overview of the applicable environmental laws and regulations relevant to this sub- project is provided in Table 18. 35 | P a g e QJ 助 円 CL の m QJ 助 円 CL ト m QJ 助 円 CL co m QJ 助 円 CL の m QJ 助 门 C匕 O 寸 QJ 助 门 C匕 ,叫 寸 劊: 3.2 World Bank Safeguard Policies 56. The objective of the World Bank's environmental and social safeguard policies is to prevent and mitigate undue harm to people and their environment during the development process. These policies provide guidelines for bank and borrower staff in identification, preparation, and implementation of programs and projects. Safeguard policies provides a platform for participation of stakeholders in project design, and are an important instrument for building ownership among local populations (World Bank, 2006). The triggered safeguard policies are presented in Table 19. 43 1 Page 圓: 皿: Q) buo =3 0 CO 0 Q) 0 0 to 0 0 (D E CO > t 0 'o cn CO ø -0 E ø > ý0 LL 0 0 0 cu cg U) 3.3 IFC EHS Guideline 57. Table 20 presents the IFC EHS guideline applicable for the project Table 20: IFC EHS guideline applicable to project Safeguard Policies Objective Applicability Safeguard IFC: General EHS The (EHS) guidelines Applicable, as the sub- The sub-project Guidelines contain performance level projects will involve will adhere to and measures on construction, the performance environmental, occupational operational and de- level and health and safety for commissioning measures construction, community activities, provided in the health and safety to be lFC general followed during the EHS construction, operation and guidelinesin decommissioning phases. Annexure V Mitigation measures proposed including OHS management plan (Annex IX) has been prepred using the EHS gudelines,and to provide the contractor with the guidance in implementing the required measures. IFC Industry Sector This industry sector EHS The guidelines for water The sub-project Guidelines for Water guideline is to be used and sanitation include had made use and Sanitation together with the general information relevant to of these EHS guidelines document, the O&M of (i) potable industry specific which provides guidance on water treatment and guidelines for EHS issues potentially distribution systems, reccomendin applicable to Water and and (ii) collection of mititgation and sanitation. sewage in centralised management Recommendations for the systems (such as piped measures in management of EHS issues sewer collection O&M phase of associated with construction networks) or the water supply activities as would typically decentralized systems project. apply to these types of civil (such as septic tanks works are provided in the subsequently serviced general EHS guidelines by pump trucks) and treatment of collected sewage at centralized facilities. IFC Industry Sector The guideline document The guidelines for The sub-project Guidelines for Waste provides a summary of the waste management will had made use 47 1 P a g e Management most significant EHS issues cover facilities or of these Facilities associated with waste projects dedicated to industry specific Management, which occur municipal sewage guidelines as during the operational and management. applicable. decommissioning phases, along with recommendations for mitigating these impacts. IFC Workers' This Guidance Note Applicable, as the sub- The plan to be Accommodation: addresses the processes projects will involve followed for Processes and and standards that should setting up of labour setting up of the Standards: Guidance be applied to the provision camp during labour camp Note of workers' accommodation construction phase. has been provided in Annexure VI I. This plan is prepared in reference to the Workers accommodation processes and standards (A guidance note by lFC and EBRD). The objective of this plan in Annex VII is to provide guidance to the contractor or other agency involved in setting up of the construction and labour camp for keeping the health & Safety of workers and impacts of setting up such camps on the local community in consideration while developing and establishing such camp. 48 i P a g e 49 | P a g e Project Categorization 58. As per the preliminary screening conducted in Annex 1, the Khunti Urban Water Supply Project is categorized as E-1 and S-2 (shown in table 21). AS per ESMF catgeorisation, category E-1 corresponds to Bank Category A project. Hence the requirements of Catgeory A project as per OP 4.01 have been followed under the ESIA for Khunti water Supply, including OP 4.01 Annex B Contents of ESIA for Category A project. Table 21: Environmental Categorization of Khunti Water supply as per the ESMF Category Description Type Action Environmental E-1 Significant Significant adverse The proposed sub- project will involve adverse impacts that are replacement of 233 m within 235 environmental sensitive, diverse, sq.m. of protected forest land. impacts over or unprecedented, Though, there is no need for the lifetime of or that affect an compulsory land acquisition or the project; area broader than diversion of forest land However likely need for the sites or replacement of the existing raw water significant facilities subject to main of 300mm with 500mm would mitigation. physical works. involve working within the forest area iain Birhu Thana village under Khunti ects it at Nagar Panchayat. There will be no sensitive,dvre environmental change in the character of land, no etrees will be cut, and the necessary Pompjents vlvn precautions in the construction activity thestes nolvi have been integrated in the ESMP. sa t de The activity does not affect the rights miteyde and wefare of the forest rights holders. diiencues The project needs to ensure that the Projecs. forest rights holders along the raw Pnroetaqirn wat er pipe alignment support the cevronmenal e project and and their interests are EIA notification of protected. MoEF&CC All impacts, environmental and social concerns associated with proposed water supply project have been addressed in the ESIA, and the appropriate mitigation and monitoring measures have been provided in ESMP, ARAP and STPP. JUIPCO has engaged an independent a agency different from DPR consultant 'Projects impacting sensitive environmental components include protected areas, forest areas. 50 1 P a g e Category Description Type Action to carry out a full comprehensive ESIA for Khunti Water Supply project, to meet the requirements of OP 4.01 Category A project. The development of the ESIA involved two rounds of stakeholder and public consultantations. The first, seeking inputs into the development of the ESIA and understanding the social and environmetnal issues of the project area, and the second on the advanced draft of the ESIA and ESMP. Social S-2 Moderate with If impacts are of The project activity will also lead to minim ised minor nature or permanent impact of loss of livelihood social impacts less than 200 for 2 PAPs and temporary impact of persons or about loss of livelihood for 35 PAPs, all of 50 households are whom are non-title holders. affected. JUIDCO has prepared an Abbreviated Resettlement Action Plan (ARAP) by a separate consultant. The draft ARAP will be disclosed after approval from World Bank E & S permissions required 59. Planning Stage NOC from WRD for withdrawal of water for water supply scheme (obtained and presented in Annex-XVII). 60. Pre-construction stage NOC from the Forest Department for replacement of 233 m of pipelines in forest land under Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 (obtained- see annex- XIV) NOC/ Consent from Urban Local body for designated site at Belahatti for disposal of construction waste (obtained- see annex IV) NOC for WTP sludge disposal at Belahatti from urban local body .(obtained- see annex IV) NOC from urban local body for establishment of labour camp near WTP .(obtained- see annex IV) 51| P a g e 61. Construction stage CTE & CTO from JSPCB for batching (concrete mix) plant and DG set (greater than 15 kVA). Labour license from Department of Labour. Contractor who employs or who employed five or more Inter-State migrant workmen need to obtain registration of interstate workmen migrant license from labour commissioner. Approval from ULB for withdrawal of water for construction purpose from surface water source PUC for construction vehicles from Department of Transport, Government of Jharkhand. 4 ANALYSIS OF ALTERNATIVES 4.1 No Project scenario 62. River Tajna/Karkari (Perennial River) is the only surface water supply source for Khunti Nagar Panchayat (KNP) flowing through the north-eastern boundary of the town. The present surface water supply scheme includes a WTP and intake well that were constructed in the year 1982. Water pumping facility from the intake well and WTP were upgraded in late 2006 after which regular piped water supply system was commissioned. 63. With the current scheme, 1001 water connections have been provided, which account for 14% of the total HHs in KNP. At present, 65 Ipcd of water is being supplied through intermittent water supply adding up to a total duration of about 1.5 hours per day. The population is forecasted to increase to 74921 by 2048 from the present population of 36390 and the water demand is expected to be around 13.540 MLD. 64. The key issues with the current water supply are: Incomplete coverage (reaching only 14% of the households) Inadequate supply (at 65 Ipcd) No metering of the water supply resulting in huge wastage by consumers Low water pressure Poor water quality (as the WTP is more than 25 years old and in a dilapidated condition) Poor Maintaince of current WTP which has resulted in dilapidated condition 65. The sub-project will lead to the following benefits: 52 | Page 100% coverage of the households in KNP Reduction in water wastage due to 100% household connections and metering Improved water quality supplied to consumers thereby reducing the burden of water borne disease. Reduction in drudgery, and savings in time for women who travel long distances to collect water from a dediated point. General hygiene in the served area could improve through use of acceptable water quality and enhanced availability (from 65 Ipcd to 155 Ipcd). 66. The no-project scenario will lead to the following negative and long term impacts: Increased exposure to health risks/ water borne diseases due to consumption of water with little or no treatment. Loss of time and energy, especially for women and girl children, due to fetching water from public water points. Groundwater depletion due to over extraction through tube wells. Table 22: Option Analysis Options Scenario Remarks Option-I Proposed raw water main from The increase water supply can be existing intake well to WTP site achieved by changing the existing 300 through a mix of Forest, mm pipeline from intake to WTP with Government, Private and National a 500-mm pipeline. Highway lands. Highay lnds.Around 233 m length of the existing 300 mm pipeline passes through Use f oly exstin ES ou of forest land. NOC has been obtained Use of only 1 existing ESRo from the Forest Department for 2 existing ESRsreplacement of the pipeline. Use of Rapid Sand Filter ESR of Zone - will continue to be in operation. Option-Il A new existing intake well at the Construction of a new intake well will upstream of Tajna Barrage disturb the riverine environment and connecting to the proposed WTP the fresh construction activity may through the Toyatoli Village, lead to river pollution. crossinge FoeestnDeparimertand The alignment of the pipeline from intake point to the WTP is being proposed in government land, which is currently under cultivation. Laying of pipelines will lead to livelihood loss. There are boulders present along this 53 t Phargoe Use of all (2) existing ESRs alignment, which have to be removed through use of explosives that entail Use of Slow Sand Filtersaeyrk. safety risks. Two structures will be permanently impacted because of the alignment of pipeline from intake well to WTP. There is community resistance to this alignment. The ESR in zone - 3 is defunct for long period of time and the current structure has been observed to be structurally not safe. Use of slow sand filter will require 50 times more area than rapid sand filter 67. As per the table presented above, Option-I has been considered in the proposed sub- project to ensure the following: Avoid impacts on river Tajna Minimise loss of livelihood Avoid water quality and reduced noise and vibration impacts of establishing new intake structures Minimise permanent impact on properties Avoid resistance of community 68. The Environment and Social Impact Assessment (ESIA) has been conducted based on the sub-project components considered in Option-I. 54 | P a g e 5 ENVIRONMENTAL BASELINE 5.1 Introduction 69. This section presents the existing environmental baseline status of the study area, covering an area of 500 m radius from the sub-project site. 5.2 Land Environment 5.2.1 Land use 70. The land use pattern for the Khunti Nagar Panchayat is provided in Table 23. Table 23: Land Use Pattern for the Khunti Nagar Panchayat Land use Area (Ha) Percentage Coverage Residential 478.33 4.941% Commercial 6.43 0.066% Industrial & Manufacturing 46.09 0.476% Public & Semi Public 61.76 0.638% Traffic & Transportation 95.88 0.990% Recreational 6.19 0.064% Agriculture 7722.97 79.778% Water Body 201.39 2.080% Vacant land 1061.27 10.963% Protected Forest 6 0.235 0.002% Total 9680.545 Source: Master plan, Khunti 5.2.2 Topography 71. The Tajna (Karkari) river is the major water body flowing through northern part of the town forming its north-eastern boundary (ward number 9). River Karkari is the tributary of River Subarnarekha. The highest elevation point is 633 m along the Ranchi-Chibasa road (NH 75). General slope is towards southern side of the town. The city is highly undulating with a difference of 15-20m. 5.2.3 Geomorphology 72. The northernmost and southernmost parts of the district are covered with hillocks and forests. Altitude of the area varies from 500 m to 700 m above mean sea level in general. There are many hillocks throughout the district having an altitude of 700 m above mean sea level. The district is the part of Chota Nagpur plateau. 5.2.4 Geology 73. The major landforms of the area are granite gneiss. Undulating erosional surface with interrupting dykes, ridges and inselbergs are prominent features. These are developed over granite gneiss. It consists of boulders, cobbles, pebbles, gravels, sandy silt and clays. 5 Pipe will be upgraded in this patch, overall forest area in KNP is 9 Ha. 55 | P a g e 5.2.5 Hydrogeology 74. The Khunti district has varied hydrogeological characteristics due to which the ground water potential differs from one region to another. It is underlain by Chota Nagpur granite gneiss of pre-Cambrian age in three-fourths of its area. 75. Aquifer system: Two types of aquifers are found. Weathered aquifer and fractured aquifers. Thickness of weathered aquifers varies from 10-25 m in granite terrain and 30-60 m in lateritic terrain. In weathered aquifer ground water occurs in unconfined condition, while in fractured aquifer ground water occurs in semi confined to confined condition. Shallow Aquifer: The shallow aquifers are being tapped through dug wells, dug cum bore wells and hand pumps. The thickness of weathered mantle varies from 5 to 20 mbgl. In lateritic terrain, many dug wells dry up during summer months. Hand pumps generally tap first fracture zones, with a depth of 30-40 mbgl. Deeper Aquifer: In granite gneiss terrain area first fracture occurs between 50-70 m and second fracture is found between 100-120 m depth. The hydrogeological map of Khunti district is available, showing the project area which has been presented in Figure 7. 56 | P a g e Figure 7: Hyd『ogeofogical Map of Khunti DIStrict 긔 SㅇUrCe.& CGVVB 57 1 P a g e 5.2.6 Ground Water Status 76. The overall stage of ground water development in Khunti district is 28.26 percent indicating sufficient scope of development. All the blocks in Khunti are classified as failing in the 'safe zone'. However, the long-term water level trend (2003-2012) was observed to be declining by about 0.41 m/year in Khunti block. In terms of the water quality, the water in the phreatic aquifers is alkaline in nature. 5.2.7 Surface Water Status 77. The major rivers draining the Khunti district are Tajna , Banai, Chata and Karo The Tajna river is a left bank tributary of Swarnrekha river in Swarnrekha basin and is the major water body flowing throughout the northern part of KNP forming its north eastern boundary.The drainage map of Khunti district showing the project area has been presented in Figure 8. 58 1 P a g e Figure 8: Drainage Map of Khunti District FIG-2 DRAINAGE MAP OF KHUNT DISTRICT Souce CGWBRst -At -~-A 5.2.8 Soil 78. Soil samples were collected from study area at six locations during February 2017. The details of the soil sampling locations are described in Table 24 and presented in Figure 9. 59|1P a ge Table 24: Soil Sampling Locations Sampling Location S.No. Locations Code Geographical Coordinates Remarks Presents soil quality 1 Kadma S-1 23.05783 N, 85.28803 E near proposed pipeline Presents soil quality 2 Dahuphuttu S-2 23.0852 N, 85.285867 E near proposed pipeline Presents soil quality 3 Ward No. 4 S-3 23.07281 N, 85.274244 E near proposed ESR-2 Presents soil quality 4 WTP S-4 23.105667 N, 85.278883 E near existing WTP Presents soil quality Proposed Labour near proposed labour 5 camp S-5 23.10699 N, 85.27961 E camp Subhas chowk - Presents soil quality 6 sensitive area, S-6 23.07603 N, 85.27887 E near proposed pipeline Note: The soil samples at each location were collected from different depths of 0 to 15 cm (D-1), 15 to 30 cm (D-2), 30 to 60-cm (D-3) and 60 to 100cm (D-4) at each location. 79. Soil sampling locations were chosen based on a reconnaissance survey of the area and prevailing activities within 100 m study area. Samples were collected by hand driven sampling augers from the surface and different depths. 80. The samples were packed in dependable, waterproof containers and analysed as per ASTM, USEPA IS: 2720, M.L. Jackson (Soil Chemical Analysis). 60 | P a g e QJ 助 门 C匕 ,叫 口 ‘创 Table 25: Physio- hernical Characteristics of Soil Sampling Lo ation SI. Parameter & Method Unit S1 S2 S3 S4 S5 S6 No. Unit Coarse % 58.3 49.2 17.5 65.4 51.5 24.4 Gravels International % 30.1 21.8 14.3 17.3 19.7 23.2 1. Texture Fine - pipette method % 9.3 10.6 19.7 8.7 8.3 15.8 Clay + % 2.3 18.4 48.5 8.6 20.5 36.6 Isilt 2. Porosity Stochastics % 27.5 30.2 29.6 30.5 28.6 30.2 method I 1 1 3. Bulk Density Weighing bottle g/CM3 2.5 2.14 2.49 2.61 1.57 1.84 method 4. Water holding Saturation capacity moisture % 97.5 92.6 64.5 78.9 85.8 57.0 percentag 5. pH Electrometric 6.68 6.04 4.95 5.55 5.67 7.03 method 6. Conductivity Electrometric mho/cm 28 50 38 37 86 222 method 7. Magnesium Titrimetric meq/1 OOgm 5.6 6.8 7.9 3.5 4.6 7.9 method 8. Calcium Titrimetric mq/100gm 3.2 2.5 5.7 8.9 3.5 4.8 method 9. Alkalinity Titrimetric % 12 4 4 8 4 8 method I I 10. Chloride Mohr's titration mg/I 9.78 19.57 2.0 2.0 2.0 7.83 method 11. Sodium Direct air 39.4 45.7 42.1 63.4 32.8 32.6 acetylene flame ppm method 12. Potassium Direct air 2.9 3.8 4.1 5.8 3.1 3.8 acetylene flame ppm method 13. Organic carbon Walkely & black % 0.25 0.56 0.37 0.28 0.74 0.28 method 14. SAR Specific mq/1 8.63 8.92 6.11 9.37 8.03 4.98 absorption rate 15. Nitrogen Alkaline 275 289 158 313 271 195 permanganate Kg/ha method 16. Salinity Electrometric Kg/ha 57.3 83.5 39.1 75.3 21.5 method 81. Soil in the study corridor was found to be mostly clayey. The pH of the soil ranged between 4.95 - 7.03 and hence was mostly acidic in nature. Electrical conductivity (EC) was low, generally varying between 23-222 pmhos/cm. Sodium level (32.6 - 63.4 ppm) in the soil samples was also found low and therefore making the soil good for agricultural purpose. In 62 1 P a g e comparison to sodium, potassium level (2.9 - 5.8ppm) was found to be high. Nitrogen level (158 - 313 kg/ha) was found to be moderate. Organic matter content (organic carbon 0.25 - 0.74%) was high indicating good vegetative potential of the soil. 5.3 Natural Hazards 5.3.1 Seismicity 82. As per the earthquake hazard map of India provided in the Vulnerability Atlas prepared by Building Materials and Technology Promotion Council (BMTPC), the Khunti district lies in Zone II which is the 'Low Damage Risk Zone' and is vulnerable to earthquakes of intensity MSK VI or less. 5.3.2 Wind Hazard 83. According to Wind Hazard Map of Jharkhand prepared by BMTPC, the sub-project area falls in Moderate Damage Risk Zone - B (Vb=39m/s). The seismicity, and wind hazard of the study area has been presented below in Figure 10 & Figure 11 respectively. Figure 10: Project area marked on Earthquake Hazard Map JHARKHAND /Amupake Hamrd Map hu4g fau*c OVhuM and eathqse oI marudo a) Proj t rea - 63|Page Figure 11: Project area marked on Wind Hazard Map M*ARMAND Project Area 5.3.3 Floods 84. As per the Flood Hazard Map of India by Building Materials & Technology Promotion Council (BMTPC), the sub-project site does not fall under area liable to floods. 5.4 Air Environment 5.4.1 Climate and Micro-meteorology of the study area 85. The climate of the study area is classified as tropical monsoon climate with following four main seasons: Winter season: January and February Pre-monsoon season: March to May Monsoon season: June to September Post monsoon Season: October to December a) IMD Meteorological Data 86. The secondary data on ambient temperature, atmospheric pressure, relative humidity and wind speed has been analysed based on Indian Meteorological Department (IMD) data from Ranchi (A)6 observatory. The same has been summarised in Table 26. The rainfall data for Ranchi (A) has been summarised in Table 27. 6 The nearest IMD observatory is at Ranchi which is 50 km from Khunti 64 | P a g e Table 26: Ambient Air Temperature, Relative Humidity, Vapour Pressure and Wind Speed Month Temperature (Mean daily in *C) Relative Vapour Wind Humidity in % Pressure (hPa) Speed Highest Max Min Lowest 8:30 17:30 8:30 17:30 In Daily Daily hrs hrs hrs hrs km/hr Jan 22.7 26.7 10 5.9 62 42 10.4 9.8 7.2 Feb 25.4 30.5 12.4 7.6 55 36 11.0 10.1 8.3 Mar 31.1 35.6 16.9 12.2 41 27 11.4 10.0 9.1 April 35.4 39.1 21.3 16.9 40 27 14.7 12.3 9.5 May 36.8 41.1 23.3 18.6 50 36 19.8 16.1 10 June 33.3 39.3 23.5 20.0 71 62 25.5 24 10.8 July 29.2 32.6 22.5 21.0 87 82 27.8 28.0 10.6 Aug 28.5 31.1 22.2 20.9 88 83 27.4 27.8 10.7 Sept 28.8 31.3 21.6 19.7 83 78 26.2 26.0 9.9 Oct 28.3 30.9 18.6 15.1 70 61 20.5 19.5 7.6 Nov 25.7 28.7 14.1 10.5 60 51 14.2 13.7 7.3 Dec 22.9 26.1 10.1 6.4 62 47 11.1 10.7 7.1 Avg. 29.0 41.3 18.0 5.6 64 53 18.3 17.3 9 65 P a g e ―내 「 5.4.2 Temperature 87. The monthly temperature variation is shown in Figure 12. As per the data recorded at meteorological station, Ranchi, the temperature begins to increase from March till May. April and May are the hottest months with highest temperature of 36.8'C, recorded in the month of May. The lowest temperature of 5.9'C was recorded in month of January. The daily mean minimum temperature varies from 10. 1 *C in December to 23.5'C in June, whereas the daily mean maximum temperature varies from 26.1 'C in December to 41. 1 OC in May. Figure 12: Monthly Temperature Variation SO 10 jan Fe 2 March April May June july August S ept 01t Noy Dt c Mondi Max Daily Lowest -4-1-lighost -47- Mi rh Daily 5.4.3 Relative Humidity 88. The mean relative humidity in different months during 1961-1990 is shown in Figure 13. The relative humidity is generally high in monsoon from June to October. It is about 64% during morning hours and 53% during evening hours. The minimum humidity is observed in April and maximum relative humidity is observed in August. Figure 14 presents the average monthly rainfall observed in Ranchi. The annual average rainfall in the region is about 1418.4 mm spreading over 77.8 days. Maximum rainfall occurs during month of July (353.2 mm) and minimum during the month of December (9.6 mm). 67 1 P a g e Figure 13: Relative Humidity 100 90 80 70 60 c 50 40 30 20 10 0 Jan Feb March April May June July August Sept Oct Nov Dec Avg Month -8:30hrs -17:30hrs Figure 14: Rainfall Details 400 350 300 E 250 E = 200 150 100 50 Jan Feb March April May June July August Sept Oct Nov Dec Month Monthly Mean - Max -24 hourly 5.4.4 Cloud Cover 89. The highest cloud cover of 6.7 okta is recorded during the month of August. 5.4.5 Wind Speed/Direction 90. The mean wind speed is recorded to be highest in the month of June at 10.8 kmph and lowest in the month of December at 7.1 kmph. The predominant wind direction is observed from East and West during the summer season (March-May), West during the monsoon season (June - September), East. during the other seasons wind direction details as recorded at Ranchi meteorological station is presented in Table 28. 68 | P a g e Table 28: Wind Direction of Ranchi Morning Time Predominant Wind Evening Ti e Predominant Wind Month I II III I II Ill January East Calm North Calm East West East February East Calm West Calm East West March East West Calm East Calm West April East West Calm East Calm West May East West Calm East Calm West June East West Calm East West Calm July East West Calm West Calm East August East West Calm East Calm West September East West Calm Calm East West October East Calm North Calm East West West November East Calm North Calm East North East East December East Calm North Calm East North East East 5.4.6 Ambient Air Quality 91. A total of ambient air quality four (4) monitoring locations representing residential, industrial, high traffic zone and commercial setup were selected to determine air quality levels within the study area. The locations of the monitoring stations were based on preliminary analysis of the meteorological conditions. Logistical considerations such as accessibility, security, and availability of reliable power supply etc. were also considered while finalizing the locations of AAQM stations. Details of the AAQM stations are summarized in Table 29. Table 29: Description of Ambient Air Quality Monitoring Stations Station SI.No. Code Coordinates Location Description Remarks Represents air quality 23 06 25.18N, Proposed labour camp near Proposed 1 AAQ1 85 16 46.59E site near proposed WTP Construction Camp 23 04 33.71N, Represents air quality 2 AAQ2 85 16 43.93E Subhash chowk near proposed pipeline Represents air quality 23 03 27.51 N, Proposed ESR camp near proposed ESR 3 AAQ3 85 17 17.22E area, Kadma camp area 23 06 20.99N, Represents air quality 4 AAQ4 85 16 42.61 E Existing WTP area near existing WTP 92. The ambient air quality monitoring (AAQM) was conducted from 26th February 2017 to 28th February 2017 for each of the locations on a 24-hour schedule. The equipment was kept 69 | P a g e in open space, away from vegetation and the height of samplers monitoring was kept in range of 3 - 5 m. Monitoring was done as per the Guidelines for Ambient Air Quality Monitoring, National Ambient Air Quality Series NAAQMS/25/2003-04 for the following parameters: Respirable Suspended Particulate Matter (RSPM/ PMjo) Fine particulate Matter (FPM/ PM2.5) Sulphur Dioxide (SO2) Nitrogen Dioxide (NO2) 93. For the collection of samples for PMjo, S02 and NO2, Respirable Dust Samplers (RDS - APM 460 BL, Envirotech) along with gaseous sampling impingers were used. For the collection of PM2.5, Fine Particulate Sampler (Model APM 151, Envirotech) was used. Sulphur Dioxide (SO2) was collected by drawing air through absorbing solution of sodium tetrachloromercurate (EPA modified West & Gaeke Method) and NO2 was collected by drawing air through the mixture of absorbing solutions of sodium hydroxide and sodium arsenite (Na-Arsenite modified Jacobs & Hochheiser Method). The measurement for both SO2 and NO2 was done colorimetrically. 94. Results of AAQM are presented in Table 30. Table 30: Ambient Air Quality Monitoring Results Monitoring Station & Category ESR Existing NAAQS IFC Parameters Construction Subhash camp WTP Guideline Guideline camp site chowk area, Kadma PM1o 70.30 133.69 142.31 180.61 100 50 PM2.5 30.83 75.00 56.58 87.07 60 25 SOx 5.42 12.63 7.30 9.21 80 20 200 NOx 17.19 21.42 18.47 18.29 80 (hu (1 hour) Results: 1. The value of PM,o was observed to be higher than the norms of CPCB (100 pg/M3) at existing WTP area (180.61 pg/M3) due to the presence of a crusher unit, stone mining/quarrying and industry about 500 meters from the existing WTP. II. High value of PM,o was observed at ESR camp area at Kadma. This is due to congestion at Khunti bus stand and presence of brick industries nearby. 70 | P a g e Ill. Subhash Chowk is the centre of the city with high population and dense traffic, which is one of the contributing factors for the high air pollution level. 95. The findings indicate the importance of dust control and emission control measures during the construction activity. 71| P a g e QJ 助 円 CL N ト ‘囲 5.5 Noise Environment 96. To assess the background noise levels in the study area, ambient noise monitoring was conducted. Total 4 locations within the study corridor (as indicated in Table 31) were selected for measurement of present status of ambient noise levels. Table 31: Details of Noise Monitoring Stations S.No. Location Coordinates Location Description Remarks Code 1 N 1 23 03 29.16N, ESR near Kadma area Represents noise 85 17 17.22E levels near to Proposed ESR -2 2 N 2 23 06 22.90N, Existing WTP Represents noise levels 85 16 46.50E near proposed pipeline 3 N 3 23 06 25.OON, Proposed labour camp Represents noise levels 85 16 47.32E area near proposed labour camp area 4 N 4 23 04 35. 1 ON, Subhash Chowk Represents noise levels 85 16 43.60E near to existing WTP 97. The summarized noise level data, as recorded, is presented in Table 32. 73 1 Page 씹 「 98. The day time equivalent noise level reckoned from 0600 to 2200 hours (Leq day) varied from 54.9 to 68.9 dB(A) while night time equivalent noise level reckoned from 2200 to 0600 hours varied from 51.2 to 57.2 dB(A). The day time equivalent noise levels (Leq Day) and night time equivalent noise levels (Leq Night) monitored at all the locations were found to be higher at N-1, N-2 & N-3 than the prescribed norms of CPCB [Day time 06:00-22:00 - 55 dB(A) and Night time 22:00-06:00 - 45 Db(A)]. 5.6 Water Environment 99. The water quality assessment was undertaken to understand the baseline water quality (both groundwater and surface water) in the study area. The sampled locations have been presented in Table 33. 75 1 P a g e c c c c E E E E E E E E E o 0 o 0 0 o o o o o æ 0 - 0 0 0 x æO .EO O " "O c c . EE =3 2 =3 = c t" tu O o . . .m o m m o '0. m 0 L- 0 &- 0 %-=3 SM . o . M C O CO El- 0000G G c c> . (c; a) (0 C) M 00 c: cý CR LIý (R (ý6 C\j m N CD N (11) (0 c:) 0 0 cm r- (o 00 00 LO cei oo M N 00 (c; clý C\i 06 C! 0 q* 00 N L£) L£) c:) C) C\] C) L£) C) 00 00 m C,4 r- Ci r-ý (Zi (V) Lo C\j Lo c:) c:) C) LL C) m m Cl) C) c:) C\i C) ir) 0 c:) CD cý M m C) CYO <100 CL M CL CL C) J2 Le) LO Lø - - - - - - - LO C\] (N4 cq LO W) W) m m LO LO < m < < < CD c:) c:) C) C) < m c:) CD < < 1: z: x m m m m m M Cr) X Z: + a- 0 CO U) cf) U) U) < 2 ýý) D < x < < L < Z < E 0 :ZZ :Zz :Zz Zz ::z =L E E E E E E E E E E E E =3 U) U) 0) E 0 75 cn -9 c 0 cu o 2) ý5 o Q CO z LL c; C) U) Z C\] m (0 l- CO M 0 o c cc c L - - - - O O - CD E Lo 0 C) o o o 0 o o o o o C> C) SZ Z 6 Z dZ dZ - Z 0m z d z z z z z z z c; v E .9 0 o O - O - O O OO o Z 0 Z Z Z Z Z Z Z v E o oo oo o 0LC) 0 0L 0 0 0 L z 6s z z z z z z 6 c v E E o~c; 000 0 z zzzc 0 ( Ei E cn NJ o 0 0 000 mv E mæ m~ m m m m mæm 0 0 Z x x x x x x x 0- < < < LO < < < < < < < E 0 00 4).O ±:0C 1 N 1 00 0 E cl <) -i 0 cl> l :s o o C> m 't L' ( CIJ N I N \N ENN 5.6.1 Groundwater Quality The pH for all the groundwater samples was found within the drinking water limits (6.5 to 8.5) as promulgated by Bureau of Indian Standards (IS: 10500) as observed from Table 34. 100. Total Dissolve Solid (TDS) was normal at all the sampling locations except GW-1. This may be because of longer contact time with the underlying rocks and sediments. The TDS observed at different sampling locations have been presented in Figure 17. 81| P a g e Figure 17: TDS of sampling locations 3500 3000 2500 2000 E DiF 1500 1000 500 GW1 GW2 GW3 GW4 GW5 Monitoring Location Seriesl - IS: 10500, 2012 Acceptable Limit 101. Total Alkalinity ranged between 34 mg/I (DW-1) to 126 mg/I (at GW-4). Total alkalinity at GW-1 was observed to be above the acceptable limit, but, it was within the permissible limit at GW-1 (528 mg/1). Figure 18: Alkanity of sampling locations 700 600 500 400 ~300 S200 100 GW1 GW2 GW3 GW4 GW5 Monitoring Location Series1 - IS: 10500, 2012 Acceptable Limit 102. Total hardness at GW-1 was observed to be above the permissible limit which may be attributed to presence of calcium and magnesium, but were observed to be within acceptable limit at all other monitoring locations. 103. Iron has been observed to be more in GW-1 & GW-5 than the permissible limit. 5.6.2 Surface water Quality 104. Parameters for analysis of surface water quality was selected based on the utility of the particular source of water as per MoEFCC guidelines. The quality of surface water was compared with IS: 10500-2012 for drinking purposes and also against water quality criteria as per CPCB guidelines for aquatic resources (Table 35). The surface water quality analysis of the samples in the study area is given below Table 36. 82 | Page Table 35: Primary Water Quality Criteria for Designated-Best-Use-Classes Designated-Best-Use Class Criteria Drinking Water Source without A Total Coliforms Organism MPN/100ml conventional treatment, but after shall be 50 or less. disinfection. pH between 6.5 and 8.5 Dissolved Oxygen 6mg/I or more Biochemical Oxygen Demand 5 days 200C 2mg/I or less. Outdoor bathing (Organized) B Total Coliforms Organism MPN/100ml shall be 500 or less. pH between 6.5 and 8.5 Dissolved Oxygen 5mg/I or more Biochemical Oxygen Demand 5 days 200C 3mg/ or less. Drinking water source after C Total Coliforms Organism MPN/100ml conventional treatment and shall be 5000 or less. disinfection pH between 6 to 9 Dissolved Oxygen 4mg/I or more Biochemical Oxygen Demand 5 days 200C 3mg/I or less. Propagation of Wild life and D pH between 6.5 to 8.5 Fisheries Dissolved Oxygen 4mg/I or more Free Ammonia (as N) 1.2 mg/I or less Irrigation, Industrial Cooling, E pH between 6.0 to 8.5 Controlled Waste disposal Electrical Conductivity at 250C micro mhos/cm Max.2250. Sodium absorption Ratio Max. 26 Boron Max. 2mg/I Below- Not Meeting A, B, C, D & E Criteria E Source: Central Pollution Control Board 83 | Page QJ 闐 m CL 吋 0O ,也. Q) buo Ln 00 CD (D N 0 C CD U') 0 c 0 c U') LO 0 c c C) C) CD CD Z .2 cý Z .2 Z .2 Z .2 -o- Ln CD - - -2 m m (o co E x x x X M C) c:) LO CD M U') M M C) r- m CD C) 0 c> 0 c; 0 Ln c; c; CD cý cý C) C) CD CO ,,;t CD Lo CD cs eli z z z z z z z c:) c; (0 0 A m 0 cn CD 00 CO cli c; z z z z z z Cl CS 0 z 0 12 M(D C> m m M m m m m C) CD < < < N < 1* < < < < 14- M: CD = m m - = - m = = - = 4) l D- LO CD o- CO CL C> M E E E E E E E E E E E 2 0 E E E 0 0 2 E m LO (D 0) C) C) U) Cl) M m C-i ш � � а � � 105. pH for all the surface water samples was found within the drinking water limits (6.5 to 8.5) as promulgated by Bureau of Indian Standards (IS: 10500) as observed from Table 36. 106. BOD was observed to be less than 0.2 in SW-1 & SW-2. Faecal coliform and total coliform was present in all the water samples indicating the risk of other more harmful pathogens and the presence of human or animal faecal contamination in the surface water, so adequate disinfection has been proposed in the current project in WTP. 87 1 P a g e 5.7 Ecology Baseline 5.7.1 Forest 107. The existing 300 mm pipeline (233 m) is passing through Birhu forest. Birhu forest is a protected medium dense forest of approximately 9.6 Ha under Khunti division and is predominantly covered by Shorea Robusta (Sal) trees. Around 235 sq. m of area of Birhu forest is required for upgrading the existing pipeline. Sal tree has been planted by the forest department in this land and communities dwelling nearby to the forest collect fuel wood (dry leaves and bushes) from the forest. During the application filed for NOC, the divisional forest officer mentioned that no major or endangered species were found in this forest area. The proposed alignment will not involve felling of any trees. 5.7.2 Terrestrial Ecology 108. In KNP are, the vegetation contains herb, shrub, tree, climber and grass. The dominant category is trees which covers 59 species. Butea monosperma, is the most dominant species in KNP, followed by Ziziphus mauritiana (Ber). Major fauna reported in KNP area are Macaca mulatta (monkeys), Presbytia entellus (grey langur), Pteropus ginganteus (Indian flying fox) and Vulpesbengalensis (fox). As per forest department, no endangered species have been reported in KNP. 5.7.3 Aquatic Ecology Baseline 109. The aquatic ecology in Tajna River near intake wells mainly comprises of Diatoms, followed by Chlorophyceae and blue- greens. Desmids and Dinophyceae. Zooplankton present is represented by 12 genera of rotifers, 6 of protozoa, 5 cladocerans and 2 of copepods. Major fish species reported in the river are Rohu, Catla, Mirka, etc. 88 | P a g e 6 SOCIAL PROFILE 110. This section outlines the social profile of the project impact area in terms of demography, livelihood, health and infrastructure. 6.1 Project Impact Area 111. The entire Project Impact Area (PIA) is within the KNP area. The Khunti Nagar Panchayat (KNP) is divided into 16 wards with the total of 7,245 houses. KNP is responsible for establishment and operation and maintenance of all basic amenities like water supply, sanitation, sewerage, and solid waste disposal. Khunti Nagar Panchayat is also responsible for holding public meeting, function, fairs, public awareness programs and implementation of all government schemes. 112. The socio-economic profile of PIA (Project Impact Area) is based on data from the secondary documents such as Census 2011, ULB records, and other pulished report and studies with an objective to understand the socio-economic background of the project area. 113. In addition, a census survey was carried out during the above mentioned period with an objective of gathering first-hand information on the following: Household characteristics, including social, economic and demographic profile Identification of non-titleholders Categorization and measurements of potential loss Inventory of affected assets Physical measurements of the affected assets/structures Assessment of potential economic impact, including temporary loss. 114. The census survey covered 100% structures affected within the proposed Right of Way (ROW) as per the Corridor of Impact (Col) of the DPR and drawings provided. 6.2 Socio Economic Profile 115. Khunti is a class Ill town and district headquarters of Khunti District, located at the central part of Jharkhand. Part of the South Chotanapur Commissionary, Khunti district was established on 12th September 2007, with 6 Blocks, and is 45 Km south of the state capital, Ranchi. The district is historically known as the center of activity of the Birsa movement. The town is spread over an area of 25.0 sq. km with total population of 36,390 as per Census of India 2011. National Highway 23 and SH 3 is major road crossing the town connecting link to other urban areas. Khunti is agriculture and forest product based town. Population 116. As per the data available from Census 2011, total population of the town is 36,390 in the year 2011 with average household size of five persons. The population of Khunti town is unevenly distributed 16 wards. Ward number 12 Hutubdug located in the east central part of 89 | P a g e the town has lowest population share in the town with 3.4% of population; whereas ward number 5 Khunti, located in west central side of the town has maximum population in the town i.e. 9.2 % of total. Table 37: Population, Area and Population Density of Khunti Town Year Area in sq. km Population Density -persons per sq. km 1971 11,743 455 1981 18,787 728 1991 24,183 937 2001 25.8 29,282 113 2011 25.8 36,390 1410 Source: Census of India 2011, KNP, 117. The total population of Khunti District is 5.3 Lakk as per Census 2011, whereas, the population of the Khunti Nagar Parishad is 36,390. Whereas, Khunti Nagar Parishad has total administration over 7,245 houses to which it supplies basic amenities like water and sewerage. Population Growth Rate 118. The average population growth rate of the Khunti Nagar Parishad has been 24.27% as per Census 2011. Figure 19: Population Growth Rate Total Population Decadal Growth Rate 70.00 40000.00 60.00 35000.00 30000.00 50.00 25000.00 40.00 20000.00 30.00 15000.00 20.00 10000.00 5000.00 10.00 0.00 0.00 1961 1971 1981 1991 2001 2011 1961-71 1971-81 1981-91 1991-2001 2001-11 Schedule Caste and Schedule Tribe Population 119. The Khunti Nagar Parishad has a sizable Scheduled caste and tribal population. As per Census 2011, Schedule Caste (SC) constitutes 4% while Schedule Tribe (ST) is 5% of total population in KNP. 29% of the total population falls under Minorities. 90 | P a g e Sex Ratio 120. In Khunti Nagar Parishad, sex ratio is of 960 against state average of 948 (i.e. 49% of females against the 51% of males to the total population). Moreover, Child Sex Ratio in Khunti Nagar Parishad is around 924 compared to Jharkhand state average of 948. Population of Children with age of 0-6 is 4,763 which is 13% of total population of Khunti (Nagar Parishad). Sex Ratio 49% 0 Male Population Female Population Figure 20: Gender Ratio Literacy Rate 121. Literacy rate of Khunti city was observed around 72% as per Census 2011 indicating an overall increase as compared to 2001. Of the total literate population, about 54% comprised male population while the rest 46% comprised female population as per Census 2011. The literacy rate in female population is 67% much lower than the literacy rates in males which is 77%. Figure 21: Literacy Rate in Khunti Nagar Panchayat 91| P a g e Literacy Rate 78% 76% f 74% - 72% 70% 68% 66% 64% 62% Total Male Female Workforce Participate Rate As per Census 2011, the total worker population was around 30% while the rest 70% comprised non worker population. Workers Population 0 Worker Population Non-Worker Population 70% Figure 22: Workforce Participation in Khunti Nagar Parishad 122. In 2011, out of the total population, about 11,052 persons were engaged in work or business activity. Of this 8,243 were males while 2,809 were females. In census survey, worker is defined as person who does business, job, service, and cultivator and labor activity. Of total 11,052 working population, 79% were engaged in Main Work while 21% of total workers were engaged in Marginal Work in 2011. Occupation Structure 92 | Page 123. In Khunti Nagar Parishad, majority (79%) of the total workers were involved in other activites, which involve government servants, municipal employees, teachers, factory workers, plantation workers, those engaged in trade, commerce, business, transport banking, mining, construction, political or social work, priests, entertainment artists, etc. Though in case of Khunti town, in this category the other workers are involved in the processing of primary activities only. The second highest is household industry workers which is 17%. Occupational Structure 4% Agriciltural Labours & Cultivators N Household Industry workers 79" Other Workers Figure 23: Occupation Distribution of Total Workers in Khunti NP, Census 2011 Economic Profile of the Study Area 124. Khunti is famous as the lac producer of the Jharkhand region. A large share of India's total lac is produced in this place. Lac is a natural polymer (resin) that is produced by a tiny insect called Kerria lacca (Kerr). This insect is specially grown on the shoots of several species of trees such as palas, kusum and ber. This agricultural profession of lac cultivation is a secondary source of income for many tribal in the Khunti region. And it is with the Government assistance and many other voluntary and NGO's that this cultivation has taken a new form and a new lease of life. Agriculture 125. The main crop grown in the district are paddy, maize black gram and Mustard. The district has also been identified as Agri-export Zone by Government of India, keeping in view the production of large quantities of green vegetables in the district. The climate of the district remains cool throughout the year with an average rainfall of 1050 mm to 1500 mm which is conducive for production of vegetables. However, there is urgent need for increasing the irrigation coverage in the district so that mono cropping at present may be transformed to multi cropping system in future. Peas, cauliflower, brinjal, tomato and french 93 | Page beans are supplied to other towns in Jharkhand and neighbouring States of Orissa, Chattisgarh and West Bengal. Basic infrastructure service 126. As per Census, 2011, there are 2 government allopathic hospitals run in the area with a strength of 30 beds and has very basic amenities and people are usually referred to nearby cities like Ranchi or Patna for better care. Other than that, there are 7 dispensaries, 1 T.B. Hospital and 1 Alternative hospital medicine centers in the town. 127. Although several public and private health facilities are available in the state, overall infrastructure for dispensing health related services require improvements. The incidence of malaria, typhoid and gastroenteritis disorders are common in the area. Education Facilities 128. There are 12 primary schools, 10 middle schools, 6 secondary schools, 6 senior secondary schools and 1 Arts, Science and Commerce College in Khunti Nagar Parishad (Source: census of India, 2011). Sanitation and Civic amenities 129. Throughout the PIA sanitation facility is poor to say the least. People however, have made own arrangement of individual toilet which is not hygienic. People of the clusters defecate in the open. In urban/ semi urban centres sanitation system is old and many households still use kuchcha or unsanitary latrines. Water Supply 130. Tube wells are the main source of drinking water in Khunti. The piped water supply system of Khunti is facing several problems at present. A low level of service in terms of low per capita water supply rate, short hours of supply, insufficient terminal pressure in the outlying areas, and non-uniform spatial supply rate are few examples of these problems. Most of the colonies do not receive municipal piped water supply. 131. Distribution network do not cover the entire town. Thus about 85 % area is not covered under the existing scheme. Ground water is the only alternative left. The quality of this water is also a cause of concern. Thus, quantity as well as quality of drinking water is the major issue obstructing the development and growth of the town. To supply adequate and safe drinking water, the proposed project is essential. 6.3 Town Management 132. Khunti town administration is structurally divided into two wings i.e. elective wing headed by chairperson and administrative wing headed by executive officer. In addition to 94 | P a g e nagar panchayat there are other parastatal bodies (e.g. Ward Office) working for sanitation related aspects. 133. The elective body is headed by Chairperson supported by vice-chairperson and 16 councilors, one for each of thel6 wards. Chairperson and vise-chairperson in KNP are selected by councilors. The tenure of the elected body of KNP is for five years.. The elective body is responsible for making policy decisions at town level for implementation of various town / citizen services including sanitation, and oversees the implementation process for successful execution of such schemes. As per Jharkhand Municipal Act, 2011, the Standing Committee shall consist of the Chairperson; the Vice- Chairperson, and three elected councilors to be elected by the Council. 134. Khunti Nagar Panchayatl9 (KNP)'s administrative body was constituted in the year 2008. It consists of 20 nos. of ward having total area of 25.8 Sq. Km. KNP is responsible to provide basic infrastructure including roads, drainage and sewerage, water supply, street lighting and services covering education, housing, poverty alleviation, slum improvement, urban forestry, environmental protection and conservation, primary health etc. KNP is headed by one executive officer and is responsible for operational planning and management of nagar panchayat. Other officials in the KNP such as municipal engineer, health officer, accounts officer etc. directly report to executive officer. 95 | P a g e 7 PUBLIC CONSULTATIONS AND DISCLOSURE 7.1 Identification of Stakeholders and Methods for Consultation 135. Consultation during project preparation as an integral part of the environment and social assessment process not only minimizes the risks but involves the public as stakeholders in project preparation process, promotes public understanding of the project leads to timely completion of the project. The ESMP prepared also incorporates the views of the project beneficiaries and Project Affected Persons (PAPs) in the design of the mitigation measures and a management plan. 136. The specific aims of the consultation process are to: Provide clear and accurate information about the project to the beneficiary community; Obtain the main concerns and perceptions of the public and their representatives regarding the project Obtain opinions and suggestions directly from the impacted communities on their preferred mitigation measures; and Identify local leaders with whom further dialogue can be continued in subsequent stages of the project. Improve project design and, thereby, minimize conflicts and delays in implementation Increase long term project sustainability and ownership 137. The primary stakeholders that were identified for the Khunti water supply project are the Khunti nagar Panchayat officials, representative of forest, water resource department and other relevant departments, PAPs and the direct beneficiaries. The secondary stakeholders include other individuals and groups, viz., the ULBs, other Governmental/Quasi-governmental departments, etc. The stakeholders identified, the social survey methods followed for collecting primary data and disclosure of the project are presented in the table below." 1 Given the socio-economic background of PAPs, most of them are engaged in their livelihood activities during the day. Therefore, despite repeated efforts to involve them in consultation process, only few attended. 96 | P a g e QJ 助 円 CL ト の Q) buo 00 0) 0 0 '0 0 4.. 0 0 U) 0 0 0 Jd CL cg ø 0 0 CL o- Process of Consultation 138. Consultation during the E&S Assessments: As a part of environmental and social impact assessment, public/stakeholder consultations were organized in Khunti. Furthermore, information pertaining to the sub-project including work schedule, procedures involved, finalization of project components with identification of impacts, entitled persons, mitigation measures and grievance redressal mechanisms was disseminated. Other stakeholders such as Forest, Water resource Department, PHED, the Land Revenue Department, National Highway Authority of India (NHAI) etc. were also contacted for face to face discussions (Refer Table no. 43). The outcomes of the initial consultations held during the month of January & February were incorporated, as appropriate, in the designs and mitigation plans. 139. Consultation on the draft ESIA, ESMP, STPP and ARAP: The draft ESIA was presented and explained to local community, stake holders, PAP and ULB members on 9th October 2017.The impacts arising due to the project, the mitigation measures and ESMP was discussed in detail. 99 | P a g e 凶“ 山 助 旧 C匕 ,叫 O ,叫 ш � � а г�1 � О � и и � и с ш U а � о и ш и � .� � а а ш � � и � о � о и � � ш � i � 'о � ш � о й � ш Q � >' � 0 Q �' С� й > � L� а �' � � f° - и 3 �3 � � ,о � с � � О � N �. . � � Ш N � f2 С � О _ � � U � � � U � U N и ш � о � с� ш � � о � � О �, � с� � A= Q) 0 4) a) >% buo 7u -o 0 CL (D U) c Q) 0 - (U 0 ø 0 U) 0 -5 2 to o (o L m o ø ø E 0- o (D ø E 0 m Lii E 0 0 o Q) 0) Ln (D c = o- (U 0 U) -J m 0 0) (D O- D- o- CL U) -0 Q) -0 (L) C: D- -0 L- 2 1=1 -0 E :ý -0 (o (D ø CD C7 U) N (U o- = :3 ý: -o 'rý LU 0 0 (D N U) 4- < FE :3 :t_, - ý: 0 o U) U) 0-,D M 0) con 0 0 m m-- -- - 1ý- 0 0 U) C. 0 > 0 (5-0 ý0 0 > D sol -0 Gol -u) -c) E m LM G) L- 0 c: m ý:, D- o < L-. 0-0 (D 0 0 m 2 D- 0ý 0 (n -0 U) ø ø ~ D- ø 0 = w E < o 0 _ ýD ø (D ID m 5, < (n z M> co o ý- o E < (n E :2 t5 0 (n ø -0 CJO L-. m > U) 0 =1 - o L- 0 0 7u- .2 o m = o < t5 = - -2 (D cý (D D- (D 0 E E (n 0 (D C Q) 0 U) m -0 0 o 0) -0 o- 0,= 0 - 0 m "FE E -0 CO ý- -= cl. 0 o- oL- ~ ý: C c U) 0 E 0 < 0 0 M LD Uj (5 0 m LL 0 ø (D (D 0 0 0 (D 0) E M -0 > ø a c > c: _-ý, 0 -0 > > o m (D 0 0 cg o- (n tý (n 0 (D Cn G) 0 2 Z 2 0 E E 0 (n D- U) 0 E U 50, o- o 13ý 0 0 0 z 0 0 0 0 EL 0 (D L c 0 0) >% CJO CDý 0) t5 =5 CL 2:1 0 4- 0 4- 0 E -t-, (D CM m CJO cn 7c 0) C.S o ýD 0 -t5 -0 CO cm 0 0 m CL 0 w E L-. c . E -0 0 G) -r- -o 0 C3) Q) 0 m E ø m -t5 m 0 (D 0 L 10 (o .0 0 E o m ø 0 ýD 0 -- 0 m < U) E LM 7.3 Summary of Public Consultation (Phase II) Observations 140. JUIDCo undertook a second phase of public consultation based on the advanced draft of the ESIA to seek inputs and acceptance of the proposed measures. The consultation was conducted at the District Collector Office, Khunti, the District Commissioner, ULB members, WRD , PAPs , Women Self Help Group were present. The summary of public consultation undertaken as part of ESIA is detailed below: The project does not require any land acquisition or any permanent impact to structures. Impacts are limited to non-title holders. The structure of only 2 non-title holders will be affected due to the project. There will be temporary loss of livelihood of 35 PAPs for approximate 20 days during the actual construction process. There is only one Schedule Tribe household to be affected. Assistance will be provided for the temporary impacts. The relevant provisions of the Entitlement Matrix (shown in section 12. 5 "Entitlement Matrix") were made known to the public and a Hindi version of the same would be distributed before mobilization of the contractor. Locals were also informed of skill development training. Khunti Nagar Panchayat is in the process of developing a plan to relocate the vendors during construction. People have raised the issue of noise and air pollution that would be generated during the construction phase and have requested for implementation of suitable mitigation measures. The participants stressed that majority of the labours to be employed during the construction and operation phase should be locals The participants suggested that the approved ESIA should be provided at ULB level. Water pipelines should be separated from the drainage lines to avoid any possible contamination. Free water points need to be considered. As informed by people, the contractor should keep a provision for employment of local persons (mainly women), in the project. Table 42: Key issues raised during consultation and response provided S.No Key Concerns Response provided Environmental 1 Community insisted on Community was informed by the PMU that the sharing the possible price of water tariff is still under consideration and ULBs the water point connection 109 | Page and the subsidy/benefits will decide on water charges. available to the poor. 2 People have raised the issue Adequate safe measures to mitigate of noise and air pollution that environmental impact have been assessed and would be generated during the made part of ESMP. ESMP will be made part of construction phase bid documents, so that the contractor is aware beforehand the mitigation measures to be implemented at site .Additional regular monitoring will be undertaken to oversee that all mitigation measures are properly implemented by contractor. Grievance cell will be created at ULB level as well as JUIDCO level, so that public can raise issues on any environmental concern that may arise due to construction activity. 3 People were concern All the present stakeholders were informed that regarding water quality during water quality will be maintained as per the operation phase. Indian standard. Monthly water quality test will be conducted to maintain the quality of water. Social 3 The community members Survey has been conducted to identify the stressed on proper PAPs. Further, the ARAP implementation identification and NGOs will conduct detailed verification of PAPs compensation for the PAPs. at implementation stage. The compensation will be provided as per the Entitlement Matrix and the community has been informed about the compensation. 4 The women were It was explained to the community members apprehensive about the that the daily water quality testing will be done quality of the water supplied to ensure compliance to IS: 10500:2012 at the and the maintenance of the WTP through a fully functional govt. approved pipelines. They suggested that laboratory. the water pipelines should be separated from the drainage lines to avoid any possible contamination. 5 Communities raised concern Traffic management plan will be made in on increase in traffic problems consultation with local authority and will be that may occur during the implemented by contractor to reduce the traffic construction phase impacts and local inconvenience 6 The participants stressed that Necessary directives will be given to Contractor majority of the labours to be for hiring the local work force. However, in case employed during the of unavailability of required labor force and construction and operation associated goods and services locally for the phase should be locals construction of civil works, because of a approved ESIA should be number of reasons such as worker 110 | Page provided at ULB level unavailability and lack of technical skills and capacity, the labour force (total or partial) may be brought in from outside the project area from nearby municipal towns and villages and sometimes from outside the state Disclosure of Project Information 141. The impacts of the project were disclosed to the local people who will be affected. Both positive and negative impacts of the project were disclosed. During public consultation sessions, the local people accepted that they were aware of the project as it was disclosed from time to time through local newspaper. 142. It was made known to the people that a resettlement information leaflet containing information on compensation, entitlement and resettlement management adopted for the project will be made available in the local language (Hindi) before mobilization of the contractor. The detailed information would also be available on the website of JUIDCO and the World Bank after approval of the World Bank. Grievance Redressal Mechanism 143. The Grievance Redressal Committee (GRC) at the state level has already been constituted. Consultation for the formation of GRC for this project at district/city level is being undertaken. Before the start of the process of civil contractor appointment, the GRC at project level will be formed in consultation with the PAPs and beneficiaries so that the grievances are resolved at the project site itself. Provision of further Consultations at Implementation Stage 144. The effectiveness of the implementation of an Environmental and Social Management Plan (ESMP) is directly related to the degree of continuing involvement of the people affected by the sub-project. Several additional rounds of consultation with the PAPs and local community will be undertaken during the sub-project implementation. A NGO responsible for ARAP implementation is entrusted with the task of conducting these consultations during implementation phase. This could involve agreements on assistance options, entitlement package and income restoration measures, accessibility and padestraian movement for the sub-project and inconvenience to the local community with respect to dust, noise safety, labour etc.. The consultation will continue throughout the sub- 111 | Page project implementation stage. The following set of activities will be undertaken for effective implementation of the plan: In case of any change in engineering alignment planning, the PAPs and other stakeholders will be consulted in selection of alternative alignment for minimization of resettlement impacts, development of mitigation measures, etc. During Implmentation an active feedback loop for citizen complaints on air, noise, dust pollution, and safety issues will be maintained and adequately addressed by the contractor and PIU. INcase of any changes to implmentation/ work schedules, closure of roads, interruption in utilities, the PIU and ULB will inform the affected people prior. Together with the NGO, the Project Implementation Unit (PIU) will conduct information dissemination sessions in the project area and will invite feedback from the PAPs in order to strengthen the Environmental and Social Management Plan implementation. During the implementation of ARAP, the NGO will organize public meetings and will inform the communities about the progress of the implementation of sub-project works, including awareness regarding health and sanitation issues related to water supply. Consultation and focus group discussions will be conducted with vulnerable groups like women, SCs, STs, and people living below poverty line to understand their specific needs that should be incorporated in ESMP/RAP/STPP. Women will be specially consulted during implementation stage. 112 | Page 8 ENVIRONMENTAL IMPACT ASSESSMENT 145. This chapter assesses key potential environmental impacts that are expected to occur during the project duration. The significance of the impacts has been assessed based on the methodology defined in Annexure XII. The expected impacts have been categorized into the following two phases: Construction phase Operation phase 8.1 Project Area of Influence 146. In the proposed sub-project, direct and/or indirect impacts are generated which are rather short-term. It is expected that most of the impacts are temporary in nature and will cease once the construction is completed. Table 43 shows the influence area of the proposed sub-project components. 113 | Page 付: 긔 아 b幻 rD 江 『》 「1 「ㅓ 山 助 门 亡匕 口 ,叫 尸月 8.2 Impacts due to project activity 8.2.1 Positive Impacts Construction Phase 147. The positive impacts of the project during construction phase are: Employment opportunities: With the construction of the proposed Project, there will be employment opportunities for both skilled and unskilled workers from Khunti. This will be beneficial both from the economic and social point of view. Economically, it means abundant unskilled labour will be used in production. Several workers including casual labourers, plumbers and engineers are expected to work on the site for a period of time. Semi-skilled, unskilled and formal employees are expected to obtain gainful employment during the period of construction. With labour intensive construction technologies, the project will provide employment for youths and provide support to the GoJ initiatives on creation of jobs. Creation of a market for construction: The Project will require materials, some of which will be sourced locally and some internationally. These include plant (pump sets, switch gear, instrumentation) pipes, valves, cement, sand and chemicals. This will provide a ready market for suppliers in and outside the project area Operation Phase Improved water quality will in turn reduce exposure to water borne diseases to the consumers. General hygiene in the served area could improve through use of acceptable water quality and enhanced availability (from 65 Ipcd to 155 Ipcd). Savings in time and effort: Piped water availability through household connections will save time and effort spent earlier in fetching water, especially for women. Household water connections and metering will help to reduce water wastage - currently estimated at 20 percent. Use of SCADA will reduce water wastage due to overflows at the ESRs, enhance equity and timeliness in water supply. Availability of potable drinking water will contribute to improved living standards within the sub-project area. Discontinuation of groundwater use and creating a new water supply system based on nearest surface water sources Recovering backwash water from treatment process 117 1 Page Improve water use efficiency and reduce water wastage at household level by recording and monitoring the water usage, and charging the consumers as per usage. Minimize unaccounted for water (UFW) losses using leak detection, and identifying unauthorized connections Using low-noise and energy efficient pumping systems 8.2.2 Negative Impacts 148. The precise environmental impacts and risks, and required mitigation measures under OP/BP 4.01; and OP 4.36 are described in the following sections of this ESIA. In particular, the Environmental and Social Management Plan (ESMP) will detail mitigation measure and also provides the institutional arrangement for their implementation including monitoring arrangements. 149. The impacts and subsequent mitigations presented here draw on a detailed field study carried out in Khunti. Information has been collected on a wide variety of variables required to anticipate and manage project impacts, including sensitive environmental receptors in the impacted area, expected effects of air and noise, impact of construction (e.g. on traffic and public safety). During operation of water supply system, the overall impact is expected to be positive, however to safeguard public health, it is imperative that regular monitoring of raw and treated water at the treatment plants, and in the distribution network be implemented to ensure that drinking water limits are not exceeded. The main impacts have been presented in Table 44. 118 | Page ( - C o o c=M M----- 2- o2 0 E 5c 0 . E~~ E > (u> o- o o o or må . oæ æ oæ rt o_ o E o - c m Io.om EE o E- m o - D- CL ø E a) c:¡~ - o zo Ivo -a- co E-m r o ~ ( E: -- -= 21 oroo - - eo s '0E '- g m - IDo o (1 -):- o> 3 o- m ø - 0 e rCL. E 0 o= m - o > o o o ina 0 0- cl ~ c - -5.(_ o a) Q) M (D c: C) - c:m o - E cn -L- c o c - _ - ø (n = ø o m- o E 0 O..O o.. y 3 CL -o N. r- = D c 0 5- c.9 o c:L-0 0 _ 2 2 E o - ø 2-U o Emæ r -Dg o - >o m ) =aA > (D P o .c - -o~~~~~ -,=2mo E-- I- s- a aon 2 a o E > Xo-=E o0 o > c-uo_ cn Z..-ZO0- _ æ L.- -. æcoæ æ-DO =- o j 8v- >oc~ 2-% v e~ c - 4) 0 ø sa 3a o O o ' O M. -L CL o .2 u) o Mco Z c _ - E '0 o 0 o - c-0 0 O r_ E > o- 25 -o U) 0 m- -0 Ec:-c= o o * --c -Voo - -o L--co o 00 z o-- ( 0-Q -0 E E m 0 - G (c 0 D L . ) , 0 -0. 0- : D( 0 E 0 )( 3 ) c D-cj 0)0 - = __ a c: o (n E O02 0ID< øX U QJ 助 円 CL O N 喝H QJ 助 门 C匕 ,叫 闪 ,叫 QJ 助 円 CL N N 喝H QJ 助 円 CL m N 喝H QJ 助 円 CL 寸 N 喝H 4-- 0) = ý0 _;, 0 0 Q) a) - - (o Q) ý0 0 U) Q) (D o 0 (u c 0 -0 :3 0 0 c 4- Q) -0 M 0 (n C) 0 > (D z -0, -0 (D buo 0 = (1) a) 0 ~ -o U) - C M 3) C) =3 L- - ø Q) CO OOD 0) 0 u C) E CO > mo > D- = Q) L- ø 0 0 -0 E 0 (D 0 L-. ~ ~ ~ L- o)- L Ln o 0 0 0 < C) o o (n C 0 -C ø u c: 0 0 0 -0 -0 ID 00 0 U) C 0 ø 0 a- E E u) 0 u> -o ø cn c) E LU 0 "- C. x 0 cn 06 C. 0 o__o -a,. 0 0 a> x c ø Å- In c 0) C) ýD =5 L-. 0 0 c:) o 0 ø 0 -0 CD -2 co m 0 5, CO cn -0 c: E 0 (D Z ý- U) > o o > U) C 0 0 L 0 E m > 0 Q-(o u) 0 M 0 o 0 0 0 E c ._ 0) CL :3 0) Q) = D- - c:) 0 ~ 0 - ý: a) > c c:) m cn_ c o 0 _; ýL- 0) U) -- jý c z m 0 (o (0 = r U) o 0 c 0(0 Z3 ý0 -2 Z3 C U) -0 c:) C-a C) -o 0 C C) I L- -D r- c-) (U r- m (1) U) 0 o o ø L ýr_ o- o > Q) r (D E jE -co c» -r (D a) r C. E CO CL.- E > E o 0 o- m Ln m 0 M 0 z 0 (n -o E ýl- LL U) a_ 0) E ø 0 25 (n 00<21= Lo -0 r- 0 r- 0 0 0 u) m m (D 0 0 0 CO 0 0 0 (n ø L-- c M =; (n ,_ m 0 m r E 0 M ý- 0 E E m -0 -0 G) ._ E 0 0 ø x 0 o- Q) -0 Q) 0 > 0 (o =3 0 0 m 0 a) C r- o U) m U) m o Z:: U) M U) m c: :3 -0 .ý= =3 ._ ._ m 0 > > ø m L-. 0 > 0 E 0 E m c L.- ._ (o > o o - : ø C» 2: 1-. 0 o- E (D m-- :3 5 C = ~ C E u) o ø E 0 0 o 0-ýý ø L- :3 w = M 0 (n M 4_ 0 ø W(D 0-0 0 C U) > v m 2ý m m Lo 0 m 0 0 0 LJ ø 0 C -o U) Lu 2 2 U) E G) c uj U)C» m E r--0 (0 ýý 0_ ~.Ln Ø (D > (D 0 m U) -IL) -0 0 D- = C (DJO E CL (D -0 E 0 z E m u) 0 X C 0 > 0 =s < 4) E -0 K E w E x 0 cg CL C 0 2 Q 0 E c 0 0 Z LU QJ 助 円 CL の N 喝H QJ 助 円 CL ト N 喝H QJ 助 円 CL co N 喝H QJ 助 円 CL の N 喝H 0 -o= G) (1) -04-- L- M-- ~ 0 0 0 = o >< -- c 0 G) w > 0 (0 c: U) Q) buo 0) n . L 0 Jý CL (D 0 CL -J (U :3 o. (D x U) 0 (D CO =3 = (1) (D C ý0 o -o - C CD 0-0 -0 N U) 0) 0 0 :ý^ 0 -U m U) 0 7L- ø CY 0 m - - 0 o 0 G) (D-a 0 0 0 0 0 &- ~ 4-- -o E ø -0 m 0 m = 05-0-0 ýD 0 a) ýD = = = = U) C c Q) o m c» M > 0 U) r- o cn - d > E 0- O-r 0 M -o :t:! 0) -- o- = - ø >, ~ 0 0 0 0 M C -o L- 0 m 0 c 0 o 0 > 0 o- C: 0) Q) (D o- r -0 E co '0 0 m (o E ø > 0 ø M 0 (D -0 o 0 (D 00-omr00 ma>E -L- E 0 M > m 0 G) 0 0 C. > -0 0-0 m r. 0 -0 ø E -0 0 M N 0 0 (> (L) ' (u Q) r_ u) o 0)0)0 u) (D - L-- o- D- 0 r (D a) m r- m L- ý (n o 0) 0 ø Cm C o Lý c 0 E E (62 45 o O-r r ø ,D ø L- o cn m (o 0 LO ýD ~ 0 E LO (o -0 m m N.E 0 c:) E., E _ m 2 ý5 CL o (D C 4-- 0 0_-o U) 0 r_ Mr o 0 0 0 m - ýF a) . U) - (o (o E -Ln ø L- 0 0 L D-øD ø o- (D w -0 o m K w o -o % 'E5 0 C) 0 cO E 0 0 0 0) 0 o 0 0 m o 0 E 0 0 o- 0 c-0 E -0 0 o a) j- - E 0 E ø- L 0 0 < 3' 0 U) 0) - ý:: 0 (D 0 0 =3 -0 -0 0 u) -0 E 0 '. L- o ýD :3 0 m E 0 N (D (D ø Q) 0 a) = 0 (D ø r4= -0 -0 -0 -0 -0 LL -J 0 cl L-. U) L.. Lo 4-- Q) (D 0 C) E (u E U, 0 CO o.- (D 2) 0 CL E - :ý^ ø -o- cn M ýD ý2 o CO CO a) -0 C0 M ø D- L- G) o C) (D c:) (D 0 (D (D ø CO C: 4-- m N 0 D U) m 0)o m u) -0 0 0) L- 4-- a) E -J 2 a) a) 3: = -~- n o ø (D cn U) U) M cm CL 0 m ø ý: M a) 0 0 o 0 ø CO 0 > N c> CO -0 o o m E cq 2 E .£ -ý, C0 0 0 o.- G) M 4-- o 4s >, -r- CL ø o- o-- 06 :ýý 0) CL 0 r- -0 U) = -- c: 0 ~ s.- = = 0, o- E 0 M (D :!:ý ~ ýD 0 ø 0) 0 0 0 0 -US L- 0 m c:) =3 r 0 U) ,D z (13 - -o -0 - M ~ C o c,,i cD 2 o Q> 0 C: >, ø 0 M L-- = to ýE,u~ a Mo 0 - 0 z .0 -iD m =5 G) m m -0 0 o- -0 x 0 0 0 X 4-- C M -0 J E (n > 02 o m ýi ýs < oý (n ø ø 0 m m -0 K LU 0 0 0 2 2 E o -0 (D 06 (D M ýD 0 0 0 劃: Q) 9 SOCIAL IMPACT ASSESSMENT (SIA) 9.1 SIA Methodology 150. The chapter deals with the approach and methodology adopted for collection of material and non-material socio-economic and cultural data and its analysis for understanding the various types of impact the project would bring about in the local social, cultural and economic fabric of the society. It also discusses the methods, tools and techniques used for screening and identifying the areas of concern for preparation of Resettlement Action Plan (RAP). With a view to comply with the applicable national and state laws, acts and guidelines and the World Bank OP 4.12, a conjunctive approach integrating the social, environmental and design aspects as well as intensive stakeholder consultations was adopted. 151. The project thus involves an integrated approach towards planning and design, incorporating close cooperation of the engineering, environment and social sector teams. The social assessment for impact analysis of the project was carried out through a series of complementary processes. Data for SIA was collected through various primary and secondary sources. 152. Primary data was collected through intensive survey to comprehend the broad baseline status and socio-economic profile of the local community and to establish the legal entitlement of the project affected families/people. Secondary data/information was collected from various agencies so as to ascertain/verify the ground realities and bring out the socio- economic characteristics, physical features and cultural set-up of the project area. Other secondary data was obtained from documents collected from JUIDCO, published articles and census publications. 9.2 Findings of Social Impact Assessment 9.2.1 Scope of Land Acquisition 153. According to JUIDCO, there is no need for land acquisition in the proposed Khunti Water supply project since the proposed project only entails change in the diameter of the pipelines in most part of the project area. The requisite land for laying down the water pipeline already lies with the Water supply Department/ULBs. 154. From the analysis of impacts, it is noted that only 2 private structures will be permanently affected due to the project work. In addition, there will be temporary impact on 135 | Page income for maximum 20 days of 35 vendors during the laying of Pipes.. The details of project impacts are discussed in the following section and the summary project impacts are presented in table below: Table 45: Summary Project Impacts SI. No. Impacts Number 1 Total land acquisition requirements (in Ha) Nil 2 Total private land acquisition requirements (in Ha) Nil 3 Total Govt. land acquisition requirements (in Ha) Nil 4 Total Number of land units/plots affected Nil 5 Total Number of private land units/plots affected Nil 6 Total Number of private Residential structures of TH Nil 7 Total Number of private Commercial structures of TH Nil 8 Total Number of private structures of NTH affected within the RoW 2 9 Total Number of Affected Families 2 10 Total Numbers of Persons affected 9 11 Total Number of Vulnerable households affected 1 12 Total Number of Mobile vendors affected Temporarily 35 13 Total Numbers of Persons Affected 157 14 Total Number of CPRs affected (Community and Religious) Nil Source: Census Survey, March, 2017 155. Thus, the sub-project is categorized as Category S2. 9.2.2 Influence on Society 156. Upgrading the Water supply and other urban infrastructure of the ULBs will have immense positive impact on the life of the under privileged in the urban areas. The development of the same would increase the well-being of the people in PIA. (a). Positive Impacts 157. The positive impacts on the population would be the followings: Improvement in overall water supply and sanitation services for Khunti Nagar Panchayat. Reduced incidence of water borne diseases and reduction in child mortality rate. Time savings for women. Surge in improved health, standard of living; personal hygiene. Improved services delivered by commercial establishments (restaurants), hospitals, businesses etc. due to availability of clean drinking water. (b). Adverse Impact 158. The adverse impacts to the population would be the followings: 136 | Page The structure of only 2 non-title holder with 9 PAPs will be affected due to the project. There will be temporary loss of livelihood of 35 vendors with 157 PAPs for approximate 20 days during the actual construction process. There is only one Schedule Tribe household to be affected. 9.3 Social Impact Mitigation Measures 159. No land acquisition will be undertaken for the project. Around 1650 m of pipeline will be upgraded and 130.758 km will be newly laid, The newly laid pipe will be within the RoW and there is no change in the character of land. The project involves loss of two structures of two non titleholders within the road Right of Way (RoW). Also at the time of laying of pipes is likely to cause loss of income for 35 street vendors temporarily. As per ESMF categorisation criteria Khunti Water Supply Project is categorised as S-2 and a separate Abbreviated Resettlement Action Plan (ARAP) is prepared. 160. Although, no need for compulsory land acquisition is identified, the construction of the raw water main would involve working within the forest area in Birhu Thana village under Khunti Nagar Panchayat. In order to ensure that the forest rights holders support the project and and their interests are protected throughout the project cycle, this Scheduled Tribe Participation Plan (STPP) has been prepared to meet the requirement of World Bank's Operation Policy on Indigenous People as well as Forest Rights Acts 2006 of India. 161. The Abbreviated Resettlement Action Plan and a Scheduled Tribe Participation Plan has been prepared as separate reports and will be disclosed along with this ESIA and ESMP. Abbreviated Resettlement Action Plan (ARAP) proposes a budget of INR 7.74 lakhs. However, no separate budget has been provisioned under Scheduled Tribe Participation Plan (STPP) as the implementation arrangements for ensuring participation of the forest dwellers remains the same as ESMP and ARAP. This has been included in the overall sub- project costs. 9.4 Gender issues and Action Plan 162. The Gender Development Index (GDI) value for India is very low and the socio- economic profile of the project area shows much lower socio-economic standing for women. The details have been discussed in table below: Table 46: Gender Data of Jharkhand and India Items Jharkhand India Gender Related Development Index (GDI) 0.558 0.590 GDI rank (out of 35) 29 122 Gender Empowerment Measure (GEM) 0.435 0.497 137 | Page GEM rank (out of 35) 26 Not Applicable Source: Jharkhand Factsheet 163. Further, the random interviews conducted for 200 households under the Khunti water supply sub-project indicated the following: a) Women play a major role in domestic water management and are typically responsible for collecting and storing water. The table below shows that in case of 84.36% households, women are responsible for managing household water requirements. Table 47: Present Accessibility in Khunti of Water for the Households For households without water supply Responsibility of managing water Women Men Both requirements 84.36% 12.80% 2.84% Within house <0.5km >0.5km to <1km 20.85% 38.86% 40.28% <=15 Mins >. to<25 >25 mins Time spent on fetching water mins 18.01% 1 37.44% Source: Survey from Jan to June, 2017 b) Women participation in decision-making regarding financial matters, education of child, healthcare of child, purchase of assets, day to day household activities, social function and marriages and land property was observed to be significantly low. The table below provides details of women involvement in various activities. Table 48:Women Participation in Khunti on Decision Making Dec ision making and participation at household le el Financial Education Healthcare of Purchase of Day-to-day Social Land matter of child child assets household function and property activities marriages Men 85.3% 9.8% 9.8% 60.8% 11.3% 60.8% 71.1% Women 4.4% 4.4% 4.4% 4.4% 4.4% 4.4% 4.4% Both 10.3% 85.8% 1 85.8% 34.8% 84.3% 34.8% 24.5% Source: Survey from Jan to June, 2017 c) The benefits of the project as envisaged by the women population are: i. Increased accessibility and better quality of the water ii. Reduced time spent on accessing the water. iii. Decreased cost of living leading to a better quality of life iv. Increased security of the women with infrastructural development of the urban areas, mainly house connections. v. Improvement in water quality leading to improvement in health and hygiene. 164. The project can improve the situation and create opportunities for them to equally access the project benefits by ensuring the following: 138 | Page i. Good quality of water supply will decrease the incidences of water borne diseases and will increase hygiene and sanitation. ii. Time saved by the women folk can be utilised for other productive activities that can help in generation of additional income. d) Women are largely involved in domestic work and have very low economic participation rate (i.e., productive or gainful employment). In the project, women are affected in a variety of ways. For example, they face hardship and stress due to scarcity of urban infrastructure and services such as water supply, drains and drainage, etc. e) In order to assess women's issues in connection with urban infrastructural project women were interviewed separately. The present scenario of the Khunti Nagar Panchayat as per the women FGD. (Annexure III: MINUTES OF THE CONSULTATION HELD ON 30TH OF MAY 2017 WITH SELF HELP GROUP OF THE KHUNTI NAGAR PANCHAYAT TO DISCUSS THE WATER SUPPLY SCHEME PROPOSED FOR WORLD BANK FUNDING) 139 | Page QJ 助 门 C匕 O 寸 ,叫 Actions to be Taken 165. The Vishakha Guidelines are a set of procedural guidelines for use in India in cases of sexual harassment. They are promulgated by the Indian Supreme Court in 1997 and was superseded in 2013 by 'The Sexual Harassment of Women at Workplace (Prevention, Prohibition and Redressal) Act, 2013'. The Jharkhand High Court in the Writ Petion (PIL) 5497 of 2011 had ordered the State of Jharkhand to strictly enforce the directions of the Honourable Supreme Court and also advised to enact legislation in tune Tamil Nadu Prohibition of Eve Teasing Act, 1998 and Delhi Prohibition of Eve Teasing Act, 1998. 166. As per the information of Jharkhand State Commission for Women (JSCW), around 10 Government organisations have confirmed the functioning of Anti sexual harassment cells till the December of 2016. The Sexual Harassment of Women at Workplace (Prevention, Prohibition and Redressal) Act 2013 under Vishaka Guidelines mentions an employer to set up an Internal Complaints Committee (ICC) at each office or branch with more than 10 employees of any gender. Inability to form such a cell can charge a sum of Rs 50,000 from the employer. JSCW had written letter to the chief secretary for prompt formation and functioning of such cells in all private as well as government departments for the sake of women employees. Involvement of an NGO member and a woman employee is mandatory in the cell also referred as ICC. But the formation of such cells in all the government and private offices is in process. 9.5 Labour Influx Management and Child Labour 167. The construction of civil works for which the required labor force and associated goods and services cannot be fully supplied locally for a number of reasons such as worker unavailability and lack of technical skills and capacity. In such cases, the labor force (total or partial) would need to be brought in from outside the project area from nearby municipal towns and villages and sometimes outside the state. This rapid migration of labor to the project area may affect the project area negatively in the terms of additional burden on public infrastructure such as local social and health services, utilities such as water and electricity, housing and social dynamics and thus impact on local communities. Other related issues could be increased risk of spread of communicable diseases, and increased rates of illicit behavior and crime. Some of the adverse environmental impacts are illegal waste disposal sites, inappropriate Wasterwater discharges, camp related noise, access roads and land use issues. Such adverse impacts may get amplified by local-level low capacity to manage and 1411 Page absorb the incoming labor force, and specifically when civil works are carried out in, or near, vulnerable communities and in other high-risk situations. 168. According to estimates, the labour demand (350 workers) for the project will be met through local labour, and a small fraction of 50-60 workers will be migrant. However these numbers are only indicative given the context of labour requriements in Jharkhand. The contactor, once on board would require to set up construction and labour camp for keeping the health and safety of workers and impacts of setting up such camps on the local community in consideration 169. As majority of labour under the project will consist of local population with only 15% labour/technicians coming from outside; therefore,chances of conflict between immigrant labour force and local community are rare. In this regard, directives will be issued to the contractor to manage the migrant labour. In addition to the above, there may be issues relating to child labour and safety and security of women.. A committee will be set up in each sub project district to look after the issues pertaining to child labour and ensure that children below 14 years are not employed in any of the sub-projects. While the sub project ESIAs would require to assess such potential issues linked to temporary project induced labour influx, the specific impacts can only be assessed once the contractor is appointed and decides to outsource labour. 170. Some of the risk factors identified are (i) weak institutional capacity of the implementing agency; (ii) many contractors without strong worker management and health and safety policies; (iv) pre-existing social conflicts or tensions; (v) weak local law enforcement, and (vi) prevalence of gender-based violence and social norms towards it in the community (vii) local prevalence of child and forced labor. (Viii) perception of insecurity by the local community due to illicit behavior or crimes including theft, physical assaults, substance abuse, human trafficking etc and (ix) limited availability of affordable accommodation and rents within Municipal area. 171. There are multiple and comprehensive Acts and Rules at both state and national level (Chapter 3) that set out the provisions for appropriate working conditions and for good labour management. However, multiplicity of laws and rules sometimes cause confusion in its applicability in a specific context. Further in case of contracted workers and Primary labor suppliers the enforcement weakens. 172. Hence, the contractor would require to develop sub project specific labour management procedures and mitigation measures in the C-ESMP before the start of works and monitor and update the labour management Plan as necessary during the course of the project. JUIDCO would develop a separate training module with the help of technical partner 142 | Page to build the capacity of JUIDCO, Supervision Consultants and Contractors in preparation and execution of this labour management Plan. 173. This Labor Management Plan would address specific activities that will be undertaken to minimize the impact on the local community, including elements such as * Communication and awareness plan on national labour and women harassment laws and its penal implications, leave provisions and other allowances for workers benefit, * Worker codes of conduct with respect to manual scavenging, engagement with local residents, child labor, nondiscrimination, harassment of coworkers including women and those belonging to SC and STs and other minority social groups. * Training programs on HIVIAIDS and other communicable diseases, etc. * Workers' Camp Management Plan addressing specific aspects of the establishment and operation of workers' camps provided the ULB is unable to cater to the demand for affordable housing for this additional workforce in terms of rentals, hostels, apartments etc. * Compliant handling Mechanism at the sub project level 174. The responsibilities for managing these adverse impacts is being clearly reflected as a contractual obligations of the Civil Works Contractor and Supervision Consultant, with appropriate mechanisms for addressing non-compliance. 143 | Page 144 | P a g e 10 ENVIRONMENT & SOCIAL MANAGEMENT PLAN 175. This section describes the management plan to be implemented to avoid or mitigate the anticipated negative environmental impacts and enhance the positive impacts of the sub- project activities. 10.1 Objectives of the ESMP 176. The objectives of the Environment and Social Management Plan (ESMP) are to: Provide a comprehensive listing of the various mitigation and monitoring measures that are to be implemented to avoid or reduce negative impacts and enhance postive impacts. Ensure compliance with the applicable National, and State Environment and Social laws and regulations as well as the World Bank's safeguard policies. Institutional arrangements that are and will be put in place by JMDP for the environmental and social compliance. Detail the plan for periodic monitoring of the effectiveness of the mitigation measures and residual impacts. Outline the capacity building plan for enhancing the capacities of the key stakeholders on environmental and social management. Detail the budget requirements for implementation of the ESMP. 10.2 Institutional Arrangement for ESMP Implementation 177. The key institutional arrangements and capacity for the implementation of the ESMP, their roles and responsibilities are outlined in this section. Table 49: Key institutions for EMP implementation Level Implementing institutions External institutions servicing the sub-project State JUIDCO - Project JUIDCO's Project Management Consultant Management Unit (PMU) (PMC) [already in place] Environmental Specialist Environmental Social Specialist Specialist Social Specialist Khunti JUIDCO - Project Contractor JUIDCO's ULB Implementation Unit (PIU) Environmental Construction level Environmental Health and Safety Supervision and Specialist Specialist Quality Control Social Specialist Social Specialist Consultant (CSQC Consultant) Environment, Social Health and Safety 145 | Page Specialist 178. JUIDCO-PMU: JUIDCO is the primary implementing agency for the JMDP under which the Khunti-WSS sub-project is being implemented. JUIDCO has established a Project Management Unit (PMU) for JMDP, which has a dedicated environment and social specialist. The JUIDCO-PMU will have ultimate responsibility and obligation to ensure ESMP implmentation and compliance. This role will include on-going identification and management of environmental impacts, monitoring social and environmental performance, ensuring availability of committed human resources and budget for ESMP implementation, periodic monitoring and reporting on ESMP performance. JUIDCO PMU will also carry out regular training on ESHS aspects especially for construction stage, orientation and experience sharing programs to enhance the knowledge and capacity of the project staff. The PMU will also put in place training programmes as per the ESMF for contractors staff on environment and social impacts in construction stage which include OHS management, maintainence of labour camp code of conduct and hygene,use of PPE, HIV prevention, gender, and maintaining hazard free work spaces JUIDCO-PMU will coordinate with Project Implementing Unit (PIU) at ULB level and Project Management Consultant (PMC) for effective monitoring of the ESMP. The JUIDCO PMU will draw support from safeguards specialists from the project management consultant's team if needed. 179. JUIDCO-PIU: The PIU located at the ULB level, this will be established and have a dedicated environment and social specialist to supervise and monitor the contractor's performance in implementing the ESMP. The PIU will assume direct responsibility for day- to-day project management, coordination and implementation of the sub project. The PIU will also supervise implementation of ESMP, and submit monthly progress reports to the PMU; and, will monitor the financial and physical progress of ESMP, adequacy of public consultation and compliant handling, and grievance redressal. It will also facilitate smooth coordination between the contractor, CSQC and the relevant government departments (ultilities, forest, traffic management etc.) for ESMP implementation. The PIU will also form the formal link between he ULB and JUIDCo, obtaining various clearances and approvals required and essential for project implementation, and reporting ESMP non compliance to the PMU. 180. CSQC Consultant: The CSQC Consultant ESHS specialist will undertake day to day supervision of the implementation of the ESMP, labour management, OHS and waste management provisions, including all mitigation, management and monitoring measures by the Contractor, will provide required on-site guidance for safeguards compliance, and, will report on safeguards compliance and non-compliance to the PIU. The scope of work for the CSQC ESHS specialist is attached in Annex XVIII 146 | Page 181. Contractor: The contractor will be responsible for implementation and adherence to all the mitigation measures, monitoring and inspection arrangements outlined in this ESMP associated with their respective activities. The contractor will be required to comply with the mitigation provisions, specifications, and drawings of the ESMP and with any related codes of conduct required by JUIDCO. The contractor selection process will include consideration of the capacities of the entities to ensure compliance to legal environmental and social requirements as well as adherence to the ESMP. The contract conditions will emphasize the obligations of the contractor on both these aspects. The contractor will put in place experienced specialist in the roles of Environmental Health and Safety; and Social as a part of the implementation team. State Pollution Control Board The state pollution control board (JSPCB) will provide Approvals for the WTP before start of Operation and Maintenance and conduct Monitoring of the effluent quality and ensure that it is according to the Standards laid down by CPCB/ CPHEEO. Khunti ULB: The ULB officers, engineers will form an integral part of the PIU. However, the ULB will also support the sub project implmentation in conducting information education and communication activities, addressing compliants, assistance in obtaining necessary government approvals for waste management, water withdrawal, and raw material requirements. 147 | Page 182. The organogram of the project is presented in Error! Reference source not found. I I One each dedicated I I One each dedicated Environment & Social I Environment & Social Specialist (Full time) I Specialist (Full time) One each dedicated I 1 Dedicated EHSE & Environment & Social I Social specialist (Full Specialist (Full time) I time) I I 1 Dedicated EHSE (Full time) II I I II II I I II 183. The human resources in each of these institutions for EMP implementation will be as follows: Level Institution Human Resources State JUIDCO Full time dedicated 1 each Environment & Social Specialist PMU State + JUIDCO Full time dedicated 1 each Environment & Social Specialist Regional PMC Regional/ JUIDCO 1 dedicated Environment & Social Specialist ULB PlU Regional/ CSQC Full time Environment Social Health and Safety Specialist ULB Consultant Project Site Contractor Full time Environment Health and Safety Engineer 10.3 Project Commitments 184. As a part of the EMP, JUIDCO will commit to recognizing the environmental issues, social and livelihood impacts on the local communities at the individual sub-project sites. Overall, JUIDCO/PMC/the Contractor will not restrict or curtail the rights of local communities 148 | Page during the development of the sub-project other than for interventions that are necessary from the perspective of community health & safety. 10.4 Revisions to the ESMP 185. In case of any future changes in the sub-project design the ESMP will need to be updated to reflect the new scope of the activities. The environmental specialist in CSQC firm, and JUIDCO- PIU will identify any safeguard issues relating to the new design elements, and mitigation measures for the same. In case of substantial revisions, this will be finalised in consultation with the PMU. 10.5 Environmental and Social Management Plan 186. The ESMP presents a listing of the mitigation measures to be taken for each potential impact along with details on the responsible person, means of verification, timing and frequency of monitoring, supervision responsibility and reporting requirements. Before the start of construction work, the Project Engineer, contractor's team will carry out joint field verification of the ESMP. The efficacy of the mitigation measures suggested in the ESMP will be checked and if required, the Engineer will modify the ESMP and BoQs associated with the mitigation measures. Joint field verification of the ESMP and its provisons will be undertaken during the mobilization phase with PIU, Contractors team, and CSQC consultant to verify locations for sampling, monitoring and mitigation. Additionally, JUIDCO shall organize orientation sessions for all contractor staff of and field level implementation staff of Contractor and all consultants on environment and social management The ESMP is presented in Table 50. 149 | Page 回: QJ 助 门 C匕 ,叫 山 ,叫 QJ 助 円 CL N の 喝H QJ 助 円 CL m の 喝H QJ 助 门 C匕 寸 山 ,叫 QJ 助 円 CL い の 喝H QJ 助 门 C匕 口 山 ,叫 QJ 助 门 C匕 卜 山 ,叫 QJ 助 门 C匕 co 山 ,叫 QJ 助 门 C匕 自 山 ,叫 QJ 助 门 C匕 O 口 ,叫 QJ 助 门 C匕 ,叫 口 ,叫 QJ 助 円 CL N の 喝H QJ 助 円 CL m の 喝H QJ 助 门 C匕 寸 口 ,叫 QJ 助 円 CL い の 喝H QJ 助 门 C匕 口 口 ,叫 QJ 助 门 C匕 卜 口 ,叫 QJ 助 门 C匕 co 口 ,叫 回; 10.6 Environmental Monitoring 187. Monitoring will be required to ensure effectiveness of implementation of suggested mitigation measures by assessing the changes in environmental conditions. The monitoring scheduled for the construction and operation phases of the sub-project are presented in Table 51 and 170 1 P a g e 171| Page 目: し 助 円 CL m ト 喝H 심, 「 쑈 目! c (o 0 CL (.0 CO M o U) 0 0 A2 > 0 LL LL =5 M (D M x E CD U) cn cn CD LL U) m 0 r 0 0 m D- E -ý5 cn :, ýD U) 0 m ui > CO E D- 0 0 (D Q- Documentation and Record Keeping 188. Documentation and record keeping of requirements specified in ESMP will include the following databases and registers: i. Project level Management Information System (MIS) will be updated by JUIDCO's Environmental and Social Specialist pertaining to ESMP implmetation of Khunti Water Supply Project ii. Quarterly ESMP comlpaince, monitoring and verification report by PMU specialists and submitted to the World Bank. iii. End of Project report submitted by PMU to the World Bank which contains all aspects of ESMP compliance, and findings and addressal of all safeguard audit issues. iv. Monthly ESMP progress report submitted by CSQC consultant team to PMU and PIU. v. Monthly monitoring ESMP checklist/ verification report maintained by JUIDCO PIU and submitted to PMU ( according to format in Annex XII) vi. The ULB will submit quarterly compliance reports to PMU during the O&M phase according to the provisions listed in table 55 and 56 during the lifetime of the JMD project. In addition, the PIU will maintain a file comprising of the following documents: i. Legal register to track details of all NOCs, licenses and permits pertaining to the sub project ii. Database of all project impacted entities to be compensated as per the proposed entitlement framework as well as grievance records. iii. Labour camp monitoring checklist and accident/injury, compliance wih OHS arrangements iv. Record of all labour licences, registration of workers and labour camp establishment permit. v. Training register for contractor's team, and project staff vi. Environmental Quality (Air, Water, Soil, Ambient Noise) monitoring register vii. Waste management plan monitoring register viii. Tree plantation register ix. Environment and social audit findings and compliance reports JUIDCO-PMU is the primary agency responsible for ESMP implmentation and reporting to the World Bank. Hence the PMU shall coordinate all inputs from PIU, CSQC and submit the following environmental reporting documentation to World Bank pertaining to Khunti Water supply project: 178 | Page (a) Environmental & Social Monitoring Reports: 189. During Project Implementation, quarterly environmental monitoring reports will be submitted by PMU to the Bank for environmental and social progress of Khunti Water Supply during construction and operation phase of the project ( JMDP will finance 5 years O&M). The report will provide the following information: Background/context of the monitoring report (adequate information on the project, including physical progress of project activities, scope of monitoring report, reporting period, and the monitoring requirements including frequency of submission as agreed upon); Changes in project scope and adjusted safeguard measures, if applicable; Qualitative and quantitative environment and social monitoring. Monitoring parameters/indicators and methods based on the monitoring plan/program in the ESMP; Monitoring EHS compliance with WBG EHS Guidelines, and WBG, EBRD Worker accomodaton standards. Results of ambient environmental sampling (e.g., air quality and noise) and subsequent ambient sampling to be undertaken by contractors as specified in the ESMP (results to be compared to applicable standards); Monitoring of all mitigation measures listed in table 55 If noncompliance or any major gaps identified, include a corrective action plan; Records on disclosure of monitoring information to affected communities; Identification of key issues, or complaints from affected people, or recommendations for improvement; Monitoring adjustment measures recommended based on monitoring experience/trends and stakeholders suggestions. Information about actual institutional arrangement for implementing the monitoring program/plan provided or adjusted, as may be required; Information on occupational health and safety, injury, and accidents reported on site. Monitoring of all waste and debris management Proposed items of focus for the next report and due date. 179 | Page (b) Monthly Progress Report of Water Supply Khunti 190. The CSQC consultant shall, by no later than 10th of the following month, submit a brief progress report summarizing the physical and financial progress of the construction contract and the activities undertaken by the supervision team for the preceding month including progress made on ESMP as per the scope in Annex XVIII. The reports shall include the minutes of the monthly site coordination/stakeholder meetings and compliants handled and all verification of environment quality monitoring of water, air, noise and soil. (c) Sub-Project Completion Report: 191. The PMU will submit a sub-project Completion Report to World Bank after completion of construction phase i.e. by the end of 24 months. This will also include performance evaluation on the Contractor's implmentation of the ESMP and compliance with audit findings and any non-compliance issues raised. 10.7 Capacity Building and Training 192. The implementation of the ESMP will require a robust environmental, health and safety training plan which will ensure that the job specific training will be provided to the PIU and the ULB to encourage the implementation of environmentally sound practices and adherence to regulatory compliance requirements. This will help in minimising adverse environmental impacts and achieving performance beyond compliance. The same level of awareness and commitment will be imparted to the contractors and sub-contractors prior to the commencement of the project. The table below gives a brief overview of the capacity building and training plan. Table 53: Capacity Building and Training Plan Training program Key stakeholders Frequency of Methodology of participating training training Training program on PIU and ULB Annual Workshop, face to ESMP, ARAP ans representatives, face training. STPP compliance for Environment and provided by PIU and ULB officers Social specialist PIU, JUIDCO PMU Supervising Enginner safeguards staff ULB Training on ESMP, Contractor staff During contractor Orientation ARAP, STPP, Labour mobilization phase, Session & During influx management, prior to the construction OHS, use of PPE, and commencement of phase progress as emergency response work. required. measures for Contractor staff/labour On-site awareness program at 180 | P a g e construction site and at labour camp Provided by JUIDCO PMU safeguards staff, supported by CSQC and CSQC, Awareness program on Workers operating Prior to On-site awareness Environment Health and maintaining commencement of program at WTP and Safety WTP, intake, ESRs operations; During provided by management and and pipelines, the operations phase JUIDCO PMU implmentation of ESMP progress as required. safeguards staff for WTP, ESRs, Pipeline laying workers Stakeholder Engagement 193. The Project will establish a Community Disclosure and Grievance Redressal (CDGR) system to facilitate stakeholder engagement to be implemented during the execution of project. It is suggested that the system will be implemented by JUIDCO-PMU & PIU from support from appointed CSQC and RAP implementation support agency. The grievance mechanism should capture community grievance as well as worker's grievance. The CDGR must have various stakeholders and must meet regularly with PAPs to resolve the grievances. 194. The system will comprise of the following: An accessible and simple grievance redressal procedure: The grievance redressal procedure will outline the process and steps to be taken by the contractor, CSQC and PIU the key people responsible, and the upper limit to the time taken to resolve a conflict to the satisfaction of the complainant. In case there are grievances that have reached a stalemate, a third party mediation may be considered. The entire GR process will be disclosed to the community at individual project sites, and it should be JUIDCO's and its CSQC 's endeavour to get all complaints recorded in the grievances log, and be addressed in a consistent manner. Apart from this a Grievance redressal committee shall be constituted at the ULB level with representatives from PIU, other deparments and prominent citizens. Grievances could also be recorded by the aggrieved party with Deputy Project Director JUIDCO. A public consultation plan: This plan will detail out the range of awareness and communication initiatives that will be implemented by JUIDCO in order to transparently and proactively address stakeholder concerns during the implementation of project activity. 181 | Page 195. The Environmental and Social specialists of PIU will coordinate with the various government agencies, and ULBs to meet the ESMP's commitments to stakeholder engagement as follows: Interface between JUIDCO, ULB, contractors, sub-contractors, relevant line departments (forest, utilities, traffic police) and the local community. Disclosure of sub-project specific information including the ESIA and ESMP on ULB website and district library. Establish a mechanism to obtain, report and monitor all grievances from the local community. Regular engagement with all relevant local stakeholder groups identified in this report. 10.8 ESMP Budget 196. The indicative split up of capital and recurring cost for the environmental management for the project is presented in Table 54. It is important to mention that recurring cost for personnel to be hired for environmental management has not been reflected in the budget as it is considered as part of the project operations. Table 54: Indicative Budgetary allocation for ESMP implementation SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) A) Construction Phase (i) Environmental Mitigation Measures 1 Environment, i. Trainings to be provided to contractors Covered part Health and staff/workers with information pertaining to of ESMF Safety minimizing solid waste, camp site hygiene, usage training cost Awareness and of designated toilets; HIV prevention, gender, and Trainings occupational health and safety including usage of PPE, and maintaining Workplace EHS signage. ii. Training to WTP workers on EHS aspects and ESMP implementation 2 Tree cutting/ iii. Care will be taken to minimize the destruction or Covered part vegetation loss damage of trees. of Project iv. Re- planting of destroyed/ cut trees and shrubs in cost cleared areas where works are complete. 182 | Page SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) v. LPG provision shall be made available in labour camp so that no tree cutting is involved for fuel wood. 3 Interference work plan with clear responsibilities for each Covered part with any utilities department/ implementing agency should be of Project developed by JUIDCo to ensure smooth execution cost of any utility relocation. 4 Drainage i. Provision of adequate drainage and bunds/ Covered part management diversion dykes, water sprinkling etc. to prevent of Project soil/ raw material escape. cost 5 Maintaining i. Proper barricading should be provided at trenches Covered part Accessibility and work sites close to buildings, schools and of Project residential areas; cost ii. Provide walkways and metal sheets where required to maintain access across for people and vehicles; iii. Location for material piling and waste in areas where there is low potential for traffic congestion. 6 Dust Control i. Water sprinkling scour checks on slopes or when Covered working in loose soils part of ii. Wet all active construction areas as and when Project cost necessary to reduce dust. iii. Use tarpaulin sheets to cover sand and other loose material when transported by trucks 7 Emission Fit all heavy equipment and machinery with air Covered as control pollution control devices to meet criteria of CPCB. part of Ensure all vehicles meet PUC requirements. Project cost 8 Noise Pollution i. Minimize noise from construction equipment by Covered part control using vehicle silencers, fitting jack hammers with of Project noise- reducing mufflers, and portable street cost barriers the sound impact to surrounding sensitive receptors. 183 | Page SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) ii. Maintain maximum sound levels not exceeding 80 decibels (dB) when measured at a distance of 10 m or more from the vehicle/s. iii. Development of vegetation and landscaping around WTP 9 Construction i. Re-use of excavated materials in the works as far Covered part debris, and as feasible to reduce waste in landfill of Project solid waste ii. Properly dispose of the spoil in the identified landfill cost management approved by the ULB iii. Reuse of bituminous waste from road cutting and concrete waste from demolition of ESR for a back filling and leveling iv. Vehicles for transport of solid waste management and dumper bins wherever required v. Construction Waste from the Project is disposed at suitable sites and verification that disposal has been done in accordance with the waste management plan in Annex 10 Establishment As per specifications listed in Annex VII. Covered part of Labour camp of Project and ancillary cost facilities 11 Labour welfare i. At every workplace (construction camps, on site Covered part and hygiene on construction areas etc.) good and sufficient water of Project construction supply shall be maintained to avoid waterborne I cost site s water related / water-based diseases to ensure the health and hygiene of workers. ii. Adequate mobile toilets shall be provided at workplace for men and women iii. Medical and emergency care on site shall be provided to workers. 12 Labour Health i. Treatment of local and migrant workers which will 10 and Safety control the movement of disease vectors (through 184 | P a g e SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) contaminated water, mosquitoes and between people); ii. Provision of personal hygiene facilities in good condition with adequate water supply at all construction sites. iii. Ensure awareness raising on proper sanitation and personal hygiene to promote proper health. iv. HIV testing for labour and workers v. Workers should be provided with suitable personal protective equipment (PPE); vi. Provision of adequate sanitary facilities to workers. vii. Safety signage installation, and barricading along the work areas 13 Green Belt 2-3 rows of plantation in the periphery of WTP as per To be Plantation at CPCB guidance of green belt development covered Part WTP of Project cost 14 Miscellaneous 2.7 expenses for construction phase ESMP implementation. Sub-Total 12.7 (ii) Environmental Quality Monitoring 1 Air Quality PM10 pg /m3, PM2.5 pg/m3, SO2, NOX, CO 3.14 monitoring17 2 Water Quality Physical, chemical and biological 3.97 monitoring" 17Air Monitoring: Rs 4920 per sample, Continuous 16 months (8 months considered as rainy season) monitoring at proposed WTP & Labour Camp. 2 monitoring each during construction period at zone-1,2,3 &4 ,3 ESR locations and Inlet pump to WTP 18 Water Monitoring: Rs 8280 per sample; continuous drinking water monitoring at labour camp for 24 months, 2 monitoring at Tajna river near intake point during construction phase 185 | Page SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) 3 Noise Equivalent Day & 1.18 Monitoring Night Time Noise Levels (Occupational & Ambient)" 4 Drinking Water Grab sampling and analysis by using standard 1.98 Quality at methods Labour camp, construction camps and onsite Sub-Total 10.27 (Construction Phase) Total (i+ ii) 12.7+10.27= 22.97 B) Operation Phase () Environmental Quality Monitoring 1 Air monitoring PM10 pg /m3, PM2.5 pg/m3, S02, NOX, CO 0.39 per (2 location per annum 4 times a year) 2 Water quality pH, Cl, F,N03,TC,FC, Hardness,Turbidity 0.66 per monitoring BOD,COD,DO, Alkalnity, heavy metals and pesticides. annum (source and WTP (Both locations, quarterly) 3 Water Quality pH, Nitrite, Nitrate, Turbidity, Total 0.99 per Supplied to Alkalnity, Fluoride, Iron, Total coliform and Fecal annum consumers coliform etc. (follow IS:10500-2012) Monthly, one 19 Noise Monitoring: Rs 1980 per sample Continuous 24 months monitoring at proposed WTP & Labour Camp. 2 monitoring each during construction period at zone-1,2,3 &4 ,3 ESR locations and Inlet pump to WTP 186 | Page SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) water sample( each zone to be covered three times per annum) 4 Noise Equivalent Day & 0.23per monitoring (3 Night Time Noise Levels annum locations, 4 times a year) Sub-Total 2.27 lakhs/year 11.35 lakhs(5years) (iii) Environmental Mitigation 1 Environment, Trainings for WTP operator staff Covered part Health and Develop in-house guidelines on environment, health of ESMF Safety and safety management training cost Awareness and Trainings 2 Sludge Sludge from WTP will be dried, stabilized and Covered management transported to disposal site in Belahatti which is 6 km under O&M away from KNP, approximately 5.2 MT of dry sludge. cost20 3 Health, Safety i. Implementation of an emergency response plan Covered and Hygiene (EPR) under O&M for workers ii. Installation of fire hydrants/extinguishers within the cost proposed WTP and ancillary facilities and train workers on how use. iii. The design shall propose noise and vibration proofed systems installation. These shall be monitored during operation and if the values go above ambient or specifications, the necessary measures shall be undertaken which may include: 20 O&M cost budget of the Project = 10.04 Crore 187 | Page SI. Particular Mitigation /monitoring component Capital Cost No. (INR in Lakhs) iv. Personal protective equipment shall be provided 4 Storage and i. Proper ventilation, lighting, entry and exit facilities Covered handling of ii. Facility for isolation in the event of major chlorine under O&M Chlorine leakage cost iii. Personal protection and safety equipment for the operators in the chlorine plant iv. Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier 2 Waste Waste Management arrangement in staff quarters and Covered Management at WTP. under O&M cost 3 Noise and Ensure regular servicing of all machinery to prevent Vibration excess noise and vibration management 4. Greenbelt Maintaince of green belt developed as per CPCB Covered maintenance guideline of Green belt plantation under O&M cost 5 Environment, Covered health and under O&M safety training cost and ESMP evaluation 6 Housekeeping Housekeeping and record keeping of all ESMP Covered provisions under O&M cost (Operation phase) Sub-Total = 11.35 lakhs (5 years) 188 | Page ANNEXURE l: ENVIRONMENTAL AND SOCIAL SCREENING CHECKLIST -fttrT 4r envirnrimetal and social screening ižrg : ( m sta8, 4.m irFT environmental and social screening oor raat 2 1eTTivý raTr: iTA A A +l~ 4rtror f r 11It t) Týlýr 1- 4a1 19266i 189 Page Jharkljand NikfliciPal )ev*elop] ment Project Eiviroinmntal antd Social Screening Format Part A Name of the Deparment: Jharkiand Urban Infrastructure Development Company Ltd Name of the City/Municipality: Khunti Namrnes & Designuionli o/ te Oijk,er responsible: 1 Jull)CO iI-l'()1 moment SpYals4~ Social specialist t r 2 ULB City Engineer City Manager lfk' V 3 Consultant MaRS Planning and Engi nerin- Services Pv Ltd - Name oft hhepr npr Wter Su l1etf ame of the proposed site nke wR Proposed sub c poe¯t/ s e s Po t Trean1ent Pat Elevated Intake point/SiPWTP/R in n ain Distriiition Service Rcservoir main/distribut ion line etc. Currentiand t~uc of d ite L.nd Part B (Please tick mark -'in Ihe appropriate column and provide relevant information) SI. No Social Sereening Questions Probable social Impaets Yes N - - 0 Commnents/Remarks Is land in the possession ofMunicipality? J 1 What is the area? Area: 1. WTP: 4.88 A cre 2. ESR 2: 1.30 Acre 3. ESR 3: 2.05 Acre 4. ESR 4: 0.l0 Acre Is the current ownership status of the NOCReceived from coteed proposed site clear? Who is the current aulority dJharomkd Govt. 2 owner? Jharkhand Govt. is the current 3__ _m _ties o w n er. 3 Is therewatyTand 4 nsVcr forl i s,iies to be "- completed before using the site for 19 Officer an agpr PanchaYat Khunli 190 |P a g e 81. NI) Social Serceinäjg Puestio robahble ;Ocil fll m s L yes No a i~~tr, YiN- pr f>opO' ---- omments/Remark Wi t t be loss perelnnlial Crops 4 (ield ngi and/or ltit bearing and other trees Will t j ectdisplace - -- structures (Hoss Will the project dispic o>mmercial --- 6 structures (shops workshops. faetory and other establishments)? Wiltere loss tructures other than- 7 buildings? (CoMpound wall/gate/water tanks/ sljbs/ wells! septic tanks. etc. Are any cultural properties(iiaceof 8 worship, religioti. siructure. memorial, Monumten, cemetery, etc.) aflfected or displaced? Are rtymniunity opel (hand--p-- - 9 pump, weil, tap, chabutra, community hall etc.) afflected ordisplaced? Are any tellants running enterpirises orj-__ 10 operating from the structures that would be displaced? Are thereiny tenants residing in the- structures that woold be displaced? 12 rere residential squatters within the 1 - - - -- proposed site boundary? Are there commercial - _ 13 squatters/vendos/4awkers +vithin the Proposed site boundary? Will there be oss of incomes a - 14 livelihoods of employees of affected establishinenlts/ struct ures? 15 Will people lose accss t co, n m-- - facilities, services, or natural resources? 6 Will there be loss of exi acess to 9 -1 private properties and services? 17 Is there any Tribal co-ntnnity membes residing in group/cluster in elose proximity to the site? u v 18 Is tiere possiliy of - --- colflict/Grievances by the surrounding Méuef er P Napr Panhavat Khuniti 191 | P a g e E r. Aø .-l -clt 1wPonible Imlacts Yc1 ,T Poib i ad o a an e rn,e, njcaNtiri es i nwhic the~ area i laixorae accrdin~gh 20 r~lh~~ uhu-j lnt te.~ Ta-k- eitc r te lhc pq,et W,, !t I rinfluecey l pial 22 thl ie pojmxl Iniobe ijnise eni ~ f P w-IiaIKh r q v and water recure ava1abd2 P g and n ~rnn~ use Slaws and regultior P c uei'at other cimiie etel may incres I -a &4- Ofbieøer 3 e ~~NagerPanchayat Khrsi ud 192 | P a g e Afl ronmetal Aspeei~~~t~n~j~ ~ n Wk.l k,~ W(j~ 1ew~ p' r i (i' Dab:l ma (flrK71 C~~M WI t'aCustuctiOA debris Š Dåiposal $ WÈf ÈI/ l4T 1874 f(9 1 0602017 Wg 18g0 f(@ 07.06 2017 2 . 'bi ' t1i02 04 |4 PSag" 204 IP a g e 205 | Page ANNEXURE V: APPLICABLE ENVIRONMENTAL STANDARDS Applicable Standards - CPCB I. Drinking Water Standard Drinking water guideline as per IS 10500, 2012 has been presented in table below; S.No ICharacteristic T Acceptable Limit Permissible Limit General PaTrameters 1 Colour, Hazen units, Max 5 15 2 Odour Agreeable Agreeable 3 pH value 6.5-8.5 No Relaxation 4 Turbidity, NTU, Max 1 5 5 Total dissolved solids, mg/1 500 2000 6 Aluminium (as Al), mg/1, Max 0.03 0.2 7 Ammonia (as total ammonia-N)mg/l, 0.5 No relaxation Max 8 Anionic detergents (as MBAS) mg/I, 0.2 1.0 Max 9 Barium (as Ba), mg/, Max 0.7 No relaxation 10 Boron (as B), mg/1, Max 0.5 1 11 Calcium (as Ca), mg/1, Max 75 200 12 Chloramines (as C12), mg/I, Max 4 No relaxation 13 Chloride (as Cl), mg/l, Max 250 1000 14 Copper (as Cu), mg/, Max 0.5 1.5 15 Fluoride (as F) mg/, Max 1.0 1.5 16 Free residual chlorine, mg/1, Min 0.2 1 17 Iron (as Fe), mg/, Max 0.3 No relaxation 18 Magnesium (as Mg), mg/, Max 30 100 19 Manganese (as Mn), mg/I, Max 0.1 0.3 20 Mineral oil, mg/, Max 0.5 No relaxation 21 Nitrate (as N03), mg/, Max 45 No relaxation 22 Phenolic compounds (as C6H50H), 0.001 0.002 mg/1, Max 23 Selenium (as Se), mg/, Max 0.01 No relaxation 24 Silver (as Ag), mg/I, Max 0.1 No relaxation 25 Sulphate (as S04) mg/, Max 200 400 26 Sulphide (as H2S), mg/, Max 0.05 No relaxation 27 Total alkalinity as calcium - 200 600 carbonate, mg/, Max 28 Total hardness (as CaCO3), mg/I, 200 600 Max 29 Zinc (as Zn), mg/, Max 5 15 Concerning Toxic Substances 30 Cadmium (as Cd), mg/I, Max 0.003 No relaxation 31 Cyanide (as CN), mg/I, Max 0.05 No relaxation 32 Lead (as Pb), mg/I, Max 0.01 No relaxation 33 Mercury (as Hg), mg/I, Max 0.001 No relaxation 34 Molybdenum (as Mo), mg/I, Max 0.07 35 Nickel (as Ni), mg/, Max 0.02 36 Polychlorinated biphenyls, mg/I, * - 0.0005 No relaxation Max 37 Polynuclear aromatic hydro - 0.000 1 No relaxation carbons (as PAH), mg/, Max 38 Total arsenic (as As), mg/I, Max 0.01 0.05 206 | Page S.No Characteristic Acceptable Limit Permissible Limit 39 Total chromium (as Cr), mg/, Max 0.05 No relaxation 40 Bromoform, mg/I, Max 0.1 No relaxation 41 Dibromochloromethane, - 0.1 No relaxation mg/, Max 42 Bromodichloromethane, - 0.06 No relaxation mg/1, Max 43 Chloroform, mg/l, Max 0.2 No relaxation Concerning Radioactive Substances 44 Alpha emitters Bq/l, Max 0.1 No relaxation 45 Beta emitters Bq/l, Max 1.0 No relaxation Bacteriolo ical Quality of Drinking Waterl) 46 All water intended for drinking: a) E. coli or thermotolerant coliform bacteria2), 47 Treated water entering the distribution system: a) E. coli or thermotolerant coliform bacteria2) Shall not be detectable in any 100 ml sample b) Total coliform bacteria 48 Treated water in the distribution system: a) E. coli or thermotolerant coliform bacteria Shall not be detectable in any 100 ml sample b) Total coliform bacteria II. Surface Water Surface Water Quality criteria as per CPCB guidelines has been presented in table below Designated-Best-Use Class Criteria Drinking Water Source without A Total Coliforms Organism MPN/100ml shall conventional treatment but after be 50 or less disinfection pH between 6.5 and 8.5 Dissolved Oxygen 6mg/I or more Biochemical Oxygen Demand 5 days 200C 2mg/ or less Outdoor bathing (Organized) B Total Coliforms Organism MPN/100ml shall be 500 or less pH between 6.5 and 8.5 Dissolved Oxygen 5mg/I or more Biochemical Oxygen Demand 5 days 200C 3mg/ or less Drinking water source after C Total Coliforms Organism MPN/100ml shall conventional treatment and be 5000 or less disinfection pH between 6 to 9 Dissolved Oxygen 4mg/I or more Biochemical Oxygen Demand 5 days 200C 3mg/ or less Propagation of Wildlife and Fisheries D pH between 6.5 to 8.5 Dissolved Oxygen 4mg/I or more Free Ammonia (as N) 1.2 mg/I or less 207 | Page Designated-Best-Use Class Criteria Irrigation, Industrial cooling, Controlled E pH between 6.0 to 8.5 waste disposal Electrical Conductivity at 250C micro mhos/cm Max.2250 Sodium absorption Ratio Max. 26 Boron Max. 2mg/I Below- Not Meeting A, B, C, D & E Criteria E Source: Central Pollution Control Board III. DG Set Emission Standards Emission limits for new diesel engine up to 800 kW for generator set (Gen-set) application has been presented in table below: Power Emission Limits (glkW-hr) Smoke Limit (light Category NOx +HC CO PM absorption coefficient, m-1) Upto 19 KW 5 7.5 5 3.5 5 0.3 5 0.7 More than 19 5 4.7 5 3.5 5 0.3 5 0.7 KW upto 75 KW More than 75 5 4.0 3.5 5 0.2 5 0.7 KW upto 800 KW IV. Noise Levels The ambient noise quality standard as prescribed by CPCB in the Noise Rules 2000 has been provided in table below: Area Code Category of Area / Limits in dB A) Leq Zone Day Time Night Time A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence Zone 50 40 208 | Page Environmental Quality Standards - IFC EHS Guidelines V. Air Quality The ambient air quality guideline as provided in World Bank Group's General EHS Guidelines 2007 has been presented in table below: Parameter Averaging Period Guideline value in pglml Sulfur dioxide 24-hour 125 (Interim target-1) 50 (Interim target-2) (S02) 20 (guideline) 10 minute 500 (guideline Nitrogen dioxide 1-year 40 (guideline) (N02) 1-hour 200 (guideline) Particulate Matter 1-year 70 (Interim target-1) PM10 50 (Interim target-2) 30 (Interim target-3) 20 (guideline) 24-hour 150 (Interim target-1) 100 (Interim target-2) 75 (Interim target-3) 50 (guideline) Particulate Matter 1-year 35 (Interim target-1) PM2.5 25 (Interim target-2) 15 (Interim target-3) 10 (guideline 24-hour 75 (Interim target-1) 50 (Interim target-2) 37.5 (Interim target-3) 25 (guideline) Ozone 8-hour daily maximum 160 (Interim target-1) 100 (guideline) VI. Wastewater Sanitary wastewater from facilities may include effluents from domestic sewage, food service, and laundry facilities serving site employees. Miscellaneous wastewater from laboratories, medical infirmaries, water softening etc. may also be discharged to the sanitary wastewater treatment system. World Bank Group's General EHS Guidelines 2007 for sanitary wastewater quality has been presented in table below: Pollutants Pollutants Guideline Value pH pH 6-9 BOD mg/I 30 COD mg/I 125 Total nitrogen mg/I 10 Total phosphorus mg/1 2 Oil and grease mg/I 10 Total suspended solids Mg/I 50 Total coliform bacteria MPN / 100 ml 400 209 Page VII. Noise Level Guideline As per World Bank Group's General EHS Guidelines 2007, noise impacts should not exceed the levels presented in table or result in a maximum increase in background levels of 3 dB at the nearest receptor location off-site. Receptor One Hour LAeg (dBA) Daytime 07:00 - 22:00 Night time 22:00 - 07:00 Residential; institutional; 55 45 educational Industrial; commercial 70 70 210 | P a g e ANNEXURE VI: TOP SOIL MANAGEMENT Loss of topsoil is a long-term impact due to the following reasons: (i) site clearance (ii) temporary construction activities such as construction camps, material storage locations, diversion routes etc. The environmental measures for both these activities during all stages of construction activity are discussed in the subsequent sections. The top soil from all sites shall be stripped to a specified depth of 15 cm and stored in stock piles for reuse. A portion of temporarily acquired area and/or RoW edges will be earmarked for storing top soil. The locations for stacking will be pre-identified in consultation and with approval of JUIDCO. The following precautionary measures will be taken by the Contractor to preserve the stock piles till they are re-used: Stockpiles will be such that the slope doesn't exceed 1:2 (vertical to horizontal), and height is restricted to 2 m To retain soil and allow percolation of water, the edges of pile will be protected by silt fencing Multiple handling kept to a minimum to ensure that no compaction occurs Stockpiles shall be covered with empty gunny bags or will be planted with grasses to prevent the loss during rains Such stockpiled topsoil will be utilized for: * Covering reclamation sites or other disturbed areas * Top dressing and raising turfs * Filling up of tree pits * For developing compensatory plantation- * In the agricultural fields of farmers, acquired temporarily that needs to be restored * Residual top soil, if there is any, shall be utilized for the plantations works the utilization as far as possible shall be in the same area from where top soil was removed. The stripping, preservation and reuse shall be carefully inspected, closely supervised and properly recorded by JUIDCO 211| Page Annexure VII: Labour Camp Site Management Plan Introduction The scope of this plan pertains to the siting, development, management and restoration of construction and labour camps to avoid or mitigate impacts on the environment. According to estimates, the labour demand (350 workers) for the project will be met through local labour, and a small fraction of 50-60 workers will be migrant. Howver these numbers are only indicative given the context of labour requriements in Jharkhand. The contactor, once on board would require to set up construction and labour camp for keeping the health and safety of workers and impacts of setting up such camps on the local community in consideration accoding to the specifications in this plan. This plan is prepared in reference to the guidance provided in the ESMF on Labour camp siting and management, and the Workers accommodation: processes and standards (A guidance note by IFC and EBRD). The land for the labour camp accommodation and facilities has been made available by the consent of the ULB (Annex Ill) and will be located across 1 acre (0.4 Ha) at the WTP site. Most impacts ariding from operation of the camps would be managed by the contractor as they concern his staff. Responsibilities for managing these impacts have been clearly reflected as a contractual obligation, with appropriate mechanisms for addressing non- compliance. The contractor would also be requirde to develop specific labour management procedures and mitigation measures before the start of works and monitor and update the labour management plan as necessary during the project. JUIDCO would develop a separate training module with the help of technical partner to build the capacity of JUIDCO, Supervision Consultants and Contractors in preparation and execution of this labour management plan. This would address specific activities that will be undertaken to minimize the impact on the local community, including elements such as i. Communication and awareness plan on national labour and women harassment laws and its penal implications, leave provisions and other allowances for workers benefit, ii. Worker codes of conduct with respect to manual scavenging, engagement with residents, child labor, nondiscrimination, harassment of coworkers including women and those belonging to SC and STs and other minority social groups. iii. Training programs on HIV/AIDS and other communicable diseases, etc. iv. Compliant handling Mechanism at the sub project level 212 | Page Pre-Construction Stage 1. Siting: The contractor will work out arrangements for setting up his facilities during the duration of construction with the ULB and JUIDCo PIU. These arrangements shall be in the form of written agreement between the contractor and the ULB that would specify: a. Photograph of the proposed camp site in original condition; b. List the activities to be carried out in the site c. Environmental mitigation measures to be undertaken to prevent land, air, water and noise pollution d. Detailed layout plan for development of the construction and labour camp that shall indicate the various structures to be constructed in the camp including temporary, drainage and other facilities (as shown in figure below) gives a generic layout plan for a construction camp); and Restoration plan of camp site to previous camp conditions e. The arrangements will be verified by the JUIDCO PIU to enable redressal of grievances at a later stage of the project. Figure: Suggestive Layout Plan for Construction and Labour Camp Areas CRECHE SKILLED IN WORKERS LADY FRCT STORE IM, WIDE BRICK PAVING IN 1:6 FEMALE CHNAI LIK CEMENT WORKERS FENCING AS PER PLASTER DRAWNING NO, MESSD CONSTRUCTICN PLANTS DILE VEHICLE WAS-HGN OFFICEFAMILIES ONE BRICK THICK ZM. HIGH BRICK WALL TO PARKING SEPERET THE SPACES T MALE WORKERS AREA ENTEY 1. Setting up of labour and construction camps During the construction stage of the project, the construction contractor will construct and maintain necessary living accommodation, rest areas and ancillary facilities for labour such 213 | Page that the requirements of food, healthcare, merchandise, transport, and recreation can be ensured. Contractor shall follow all relevant provisions of the Factories Act, 1948 and the Building and the other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 for construction and maintenance of labour camp. The labour camp will be set up on an area of _approximately 1 acre near the current WTP site. The camp site and has been determined keeping in mind the site would not be located within or close to dense forest areas. The camp site and its associated facilities such as access roads do not involve forest clearance and do not negatively affect local wildlife. The Supervisor of the camp should take the attendance of the employee at each camp twice in a day (morning and evening) and should maintain the record. Further work hours of the workers should be maintained in accordance to the labour law and as mentioned in the labour licence. All workers should be provided with ID card and entry to the site should be through ID card only and should be ensured by security guard. Living accommodation and ancillary facilities should be provided to all the migrant workers employed for the complete duration of construction/maintenance period. The rooms of labour shall be well lighted and ventilated. Transportation to the labour from the camp to the working site should also be provided, along with the facilities and provisions to be provided for the labour are described below: a) Site barricading b) Clean Water Facility c) Clean kitchen area with provision of clean fuel like LPG d) Clean Living Facilities for Workers e) Sanitation Facilities f) Waste Management Facilities g) Rest and emergency area for workers at construction site h) Safe access road is required at camps i) Health Care Facilities j) Cr6che Facility & Play School k) Fire-fighting Facility a) Site Barricading and Safety Site should be completely barricaded from all the sides to prevent entry of outsiders and animals into the site with adequate marking, flags, reflectors etc. for safety of general traffic movement and pedestrians. Entry gate should be provided at the site and labour and construction camp which should be guarded by security guard. All workers should be issued ID cards and entry of outsiders shall be maintained in the register at the gate. Board should 214 | P a g e be displayed at the site and the labour camp, the name of project, capacity of project, authority carrying our projects, restriction of entry without authorization, no smoking zone and associated risks. Plant and machinery operation shall be restricted to 6:00 Am to 10:00 PM. b) Clean Water! Drinking Water Towards the provision and storage of drinking water at the construction camp, the contractor shall ensure the following provisions Potable water shall be provided for construction labour for drinking & cooking purpose. Clean water shall be provided for bathing, cleaning and washing purpose. Water quality testing for drinking water provided for workers shall be carried out on monthly basis. Water dispensers should be cleaned on monthly basis. Adequate water per person should be provided at site for drinking, cooking, bathing, cleaning and other use purpose Every water supply or storage shall be at a distance of not less than 15m from any wastewater / sewage drain or other source of pollution. Water sources within 15m proximity of toilet, drain or any source of pollution will not be used as a source of drinking water in the project. If bore well used as drinking water source, it shall be covered, the door shall be kept locked and opened only for cleaning or inspection, which shall be done at least once a month. There shall be a motor installed for extraction of water from well. In every site, adequate and suitable facilities for washing clothes and utensils shall be provided and maintained for the use of contract labour employed therein. Separate and adequate bathing shall be provided for the use of male and female workers. Such facilities shall be conveniently accessible and shall be kept in clean and hygienic conditions. c) Kitchen Area Provision of clean kitchen area for cooking and storage of eatables shall be provided. Clean fuels like LPG shall be provided for cooking purpose. Burning of firewood, garbage, paper and any other material for cooking or any other purpose shall strictly be prohibited at the site. Separate utensil washing area should be provided with proper drainage system. Kitchen waste should be daily cleaned and disposed of. Water storage facility at kitchen should be covered and cleaned on monthly basis. Kitchen area should be away from washing, toilets and bathing area. Wall surfaces adjacent to cooking areas are made of fire-resistant materials. Food preparation tables are also equipped with a smooth durable washable surface. 215 | Page d) Living Facility for the Workers Workers should be provided with proper bedding facility. Single bed should be provided to each worker and each bed should be at least 1 m apart from another. Double deck bedding should be avoided, in case provided, adequate fire-fighting facility should be provided. Bed linen should be washed regularly and should be applied with repellent and disinfectants so as to manage the diseases caused due to pests. Use of Long Lasting Impregnated Nets or use of Pyrethroids (in WHO class III - especially formulated for public health) for mosquito and vector control. Facilities for storage of personal belongings for workers should be provided in form of locker, shelf or cupboard. A separate storage area for the tools, boots, PPE should be provided. Proper ventilation through mechanical systems and lighting system should be ensured in construction camps. e) Sanitation and Toilet Facilities Sanitary arrangements, latrines and urinals shall be provided in every work place separately for male and female workers. The arrangements shall include: A latrine for every 15 females or part thereof (where female workers are employed). A latrine for every 10 males. Every latrine shall be under cover and so partitioned as to secure privacy, and shall have a proper door and fastenings. The latrines and urinals shall be adequately lighted and shall be maintained in a clean sanitary condition at all times and should have a proper drainage system; Water shall be provided in or near the latrines and urinals by storage in suitable containers. Hygiene in the camps should be maintained by providing good sanitation and cleaning facilities. Soak Pits can be provided only if labour camp is located away from river. Wastewater generated from these facilities should be disposed off through septic tanks and soak pit f) Waste and Wastewater Management in Labour Camp Kitchen waste water shall be disposed into soak pits located preferably at least 30 meters from any water body/ drinking water source. The capacity should be at least 1.3 times the maximum volume of wastewater discharged per day. The bottom of the pit should be filled with coarse gravel and the sides shored up with board, etc. to prevent erosion and collapse of the pit. 216 | Page Municipal waste will be generated from labour camp, and the contractor will comply with the Wastew management specifications in Annex VIII. Dustbins for recyclable and non-recyclable waste shall be provided in labour camp area. Recyclable waste shall be sold to authorized vendors and non-recyclable shall be disposed through authorized agency in area responsible for waste collection and management. The rejected waste should be disposed in a secured manner at the designated landfill site in belahatti. No dumping of waste/wastewater will take place on the surface/ ground. Hazardous waste or wastewater shall not be stored in unlined ponds. Wastewater generated from the washing/cleaning area after passing through oil & grease trap and curing area shall be re-used for water sprinkling and wheel washing. Wastewater from construction site should not be allowed to accumulate at site as standing water may lead to breeding of mosquitoes. Wastewater generated from labour camp will not be directed into river but should be treated and disposed off through septic tank (designed following Indian standard code of practice for installation of septic tanks IS: 2470) and soak pit/leach pit to meet the CPCB standards of class E. Wherever septic tanks are not provided mobile toilets with anaerobic digestion facility shall be provided and no domestic waste shall be discharged to any water body. Temporary storm water drainage system should also be provided at camp site and construction site to drain the storm water and prevent accumulation of storm water at site and thus breeding of mosquitoes/flies Solid wastes generated in the kitchen shall be reused if recyclable or disposed in land fill sites per waste management plan in Annex VIll All used oils, lubricants and machine oils will be stored in leak proof containers, and shall be placed on paved surface and disposed as per waste management plan in Annex VII. Authorised vendors from Jharkhand Pollution control board will collect the waste oils, lubricants. As the project is located within the urban area of Khunti, and is a short distance from a large city such as Ranchi, the contractor will have access to healthcare facilities and clinics. Any bio- medical waste generated at the labour camp is likely to be minor, likely to be generated at first aid centre, and shall be disposed of following the Bio Medical Waste Disposal Rules, 201621 217 | Page Provision of Rest and Emergency Assembly areas The work place shall provide four suitable sheds, two for meals and two for rest (separately for men and women). The height of the shelter shall not be less than 3.Om from the floor level to the lowest part of the roof. These shall be kept clean. Emergency Assembly Area shall be demarcated as emergency collection area near the gate where all can assemble in case of fire, earthquake or calamity at the site. g) Safe Access Road Temporary paved surface shall be constructed to approach the labour camp from the site. If camps are located close to residential and commercial areas, the roads should be watered sufficiently. Trucks carrying construction material to be adequately covered to avoid the dust pollution and to avoid the material spillage. Movement shall not be hampered during monsoon season due to water logging. h) Medical and First Aid Facilities Medical facilities shall be provided to the labour at the construction camp. Visits of doctor shall be arranged twice a month wherein routine check-ups would be conducted for women and children. A separate room for medical check-ups and keeping of first aid facilities should be built. The site medical room should display awareness posters on safety facilitation hygiene and HIV/AIDS awareness. Ambulance/ 4-wheeler motorized vehicle shall be available at the site for carrying injured to the nearby hospital. Tie-ups should be made with nearby hospital to handle emergency, if any. Nos. of ambulance, doctors and nearby hospital shall be displayed in first-aid room, site office & labour camps. List of contact nos. of emergency personnel, hospitals, fire brigade and other emergency contact should be displayed at camp site, guard's room and first aid room. First Aid Box will be provided at every construction campsite and under the charge of a responsible person who shall always be readily available during working hours. He/she shall be adequately trained in administering first aid-treatment. Formal arrangement shall be prescribed to carry injured person or person suddenly taken ill to the nearest hospital. The first aid box shall contain the following. - 6 small sterilized dressings 218 | Page - medium size sterilized dressings - large size sterilized dressings - large sterilized burns dressings - 1 (30 ml) bottle containing 2 % alcoholic solution of iodine - 1 (30 ml) bottle containing salvolatile - 1 snakebite lancet - 1 (30 gms) bottle of potassium permanganate crystals - 1 pair scissors - Ointment for burns - A bottle of suitable surgical antiseptic solution - In case, the number of labour exceeds 50, double quantity should be provided. i) Cr6ches In case 20 or more women workers are employed, there shall be a room of reasonable size for use of children under the age of six years. The room should have adequate light and ventilation. A caretaker is to be appointed to look after the children. The use of the room shall be restricted to children, their mothers and the caretaker. j) Storage of Construction Material in Construction Camps Adequate secondary containment for fuel storage tanks and for the temporary storage of other fluids such as lubricating oils and hydraulic fluids. Impervious/paved surfaces should be used for refueling areas and other fluid transfer areas to avoid soil and water contamination due to spillage. Training workers on the correct transfer and handling of fuels and chemicals and the response to spills Provide portable spill containment and cleanup equipment on site and training in the equipment deployment All materials shall be stored in a barricaded area. In case of electrical equipment, danger signs shall be posted. The batch mix plant is to be located away from the residential area and not in the wind direction. Separate parking areas for vehicles and also workshop areas need to be provided. k) Firefighting arrangement The following precautions need to be taken: Demarcation of area susceptible to fires with cautionary signage; Portable fire extinguishers and/or sand baskets shall be provided at easily accessible locations in the event of fire Contractor shall educate the workers on usage of this equipment. 219 | Page During Construction Activities Construction camps shall be maintained free from litter/ garbage and in hygienic condition. It should be kept free from spillage of oil, grease or bitumen. Any spillage should be cleaned immediately to avoid pollution of soil, water stored or adjacent water bodies. The following precautions need to be taken in construction camps. Measures to ensure that no leaching of oil and grease into water bodies or underground water takes place. Wastewater should not be disposed into water bodies. Regular collection of solid wastes should be undertaken and should be disposed safely. All consumables as the first aid equipment, cleaning equipment for maintaining hygiene and sanitation should be recouped immediately. The debris/scrap generated during construction should be kept in a designated and barricaded area. The PIU will monitor the cleanliness of construction campsites and ensure that the sites are properly maintained throughout the period of the contract. A. Grievance Redressal System A complaint register and a complaint box should be provided at the site so any person from local community can register their complaint, if any due of the camp, workers and other facilities. The system shall be communicated to local communities through consultations. Open house meetings should be conducted with workers on monthly basis to identify their problems and issues if any related to health, hygiene, safety, comfort and other issues. Activities prohibited at site B. Activities which should be strictly prohibited at site shall include Open burning of wood, garbage and any other material at sit for cooking or any other purpose Disturbance to the local community. Adoption of any unfair means or getting indulgence in any criminal activity Non-compliance of the safety guidelines as communicated be safety officials and during the trainings Adoption and proper usage of PPEs all the time as required Operation of the plant and machinery between 10 pm to 6 am unless approved by team leader 220 | P a g e No animal (wild or domestic or bird) shall be harmed by any construction worker in any condition at site and nearby areas Cutting of tree without permission of team leader/authorized person No indigenous population shall be hurt or teased C. Post Construction/Decommissioning Stage After the completion of construction, all construction camp facilities, labour camps shall be dismantled and removed from the site. The site shall be restored to a condition in no way inferior to the condition prior to commencement of the works. Various activities to be carried out for site rehabilitation include: All temporary structures should be cleared Debris (rejected material), building debris, garbage, night soils and POL waste should be disposed suitably per the construction debris and waste management plan. All disposal pits or trenches should be filled in, disinfected and effectively sealed off. All the areas within the camp site should be levelled and spread over with stored top soil. Residual topsoil, if any will be distributed or spread evenly in plantation sites, on adjoining/near-by barren land or affected agricultural land adjacent to the RoW that has been impacted because any accidental spillage. Oil and fuel contaminated soil shall be removed and transported and buried in waste disposal areas. Underground water tank in a barren/non-agricultural land can be covered. However, in an agricultural land, the tank shall be removed. If the construction camp site is on an agricultural land, top soil can be spread so as to aid faster rejuvenation. Entire camp area should be left clean and tidy, in a manner keeping the adjacent lands neat and clear, to the entire satisfaction of landowner and JUIDCO. Proper documentation of rehabilitation site is necessary. This shall include the following: a) Photograph of rehabilitated site; b) Land owner consent letter for satisfaction in measures taken for rehabilitation of site; c) Undertaking from contractor; and d) Certification from Engineer in-charge of the PIU. 221 | Page ANNEXURE Vill: CONSTRUCTION DEBRIS AND WASTE MANAGEMENT PLAN I. Potential Sources of Waste Generation The expected solid waste as per JUIDCO to be generated during construction phase and their disposal method is provided in the table below: Table 55: Solid and Hazardous Waste- Construction Phase S. No Type of Waste Estimated Disposal Quantity Non-Hazardous waste This will be used to level low lying areas at approved site for fling purpose, construction of approach roads. If any Construction Debris and earth 3-5 tonnes per extra ras remane 1.mtra,rcs a extra material is remained, r dthen that should be disposed of to the approved debris disposal site Bituminous waste, concrete will be Re-use as back filling and levelling for other roads Concrete Waste from ESR 126.945 CUM Nnrccal at hl 2 and old WTP Non-recyclable waste shall be disposed at approved debris site in covered vehicles Used Oil from diesel A 5t To be disposed to JSPCB 3 generators and construction pro.nne and CPCB authorised machinery vendors Recyclable waste shall be sold to authorized vendors and non-recyclable shall be Packing waste containing 20 tonnes per dipsdtruhahoze 4 crbadwodecyerdisposed through authorized cardboard, wood etc. year aec nae epnil agency in area responsible for waste collection and management. Hazardous waste Waste and oil contaminated 0.5-1 ton per Collected and disposed 1 rags annum through CPCB/JSPCB approved recyclers 2 Bituminous Waste 190.4175 CUM Re-use as back filling and I_ leveling # - Indicates Hazardous waste * - The quantity will be for the entire construction period 222 | Page II. Design of Comprehensive Waste Management Plan The contractor should follow the specifications listed below: Categorization of waste into degradable, biodegradable and hazardous categories and list of different types of waste that falls in each of these categories. Estimates about the quantity of waste generated in each category and type of storage units required. Detail the provisions for storage and handling of waste until disposed. A plan of the respective camps / areas like construction camp, labour camp etc. to be submitted indicating in it the space allocated for storage and handling of wastes. Detail the precautions to be taken while storing, handling and disposing each type of waste, trainings to be imparted to workers to create awareness about waste management. Details of Debris disposal site at Belatti as defined in Annexure III: Allocation Letter for disposal of construction waste & land for labour/construction camps: The contractor will submit a copy of approved site identification report along with location plan on a village map showing the debris disposal sites, site, its survey no., access road, project stretch, distance from the project stretch, surrounding features and land use like residences, agricultural land, water bodies etc., photograph of the site showing the topography and other existing features. III. Precautions to be adopted during disposal of debris/waste material The contractor shall take the following precautions during transportation and disposal of debris/waste material: A register should be kept for recording the details of the waste generated and their disposal. The contractor will take full care to ensure that public or private properties are not damaged/ affected during the site clearance for disposal of debris and the traffic is not interrupted. All arrangements for transportation during dismantling and clearing debris, considered incidental to the work, will be implemented by contractor in a planned manner as approved and directed by JUIDCO. In the event of any accidental spill or spread of wastes onto adjacent parcels of land, the contractor will immediately remove all such waste material/s and restore the affected area to its original state to the satisfaction of JUIDCO. Contractor should ensure that any spoils/materials unsuitable shall not be disposed off near any water course; water body; agricultural land; natural habitats like grass 223 | Page lands, wet lands, flood plains, forests etc. pasture; eroded slopes; and in ditches, which may pollute the surrounding including water sources. Contractor should ensure effective water sprinkling during the handling and transportation of materials where dust is likely to be created. Contractor Materials having the potential to produce dust will not be loaded beyond the side and tail board level and will be covered with a tarpaulin in good condition. * Any diversion required for traffic during disposal of debris shall be provided with traffic control signals and barriers after discussion with the local body and as approved by JUIDCO. During the debris disposal, Contractor will take care of surrounding features and avoid any damage to trees and properties No hazardous and contagious waste material shall be disposed at such locations. IV. Waste Disposal from Construction and Labour Camp Concrete flooring and oil interceptors should be provided for workshops, vehicle washing and fuel handling area. Petroleum, oil and lubricants waste shall be stored safely in separate containers and should be disposed off by transfer only to recycler/ re-refiners possessing valid authorization from the Jharkhand State Pollution Control Board. Used lead batteries, if any, should be disposed as per the Batteries (Management and Handling) Rules 2001. Water separated and collected from oil interceptor should be reused for dust suppression. There should be a register to record the details of the oil wastes generated at the workshops and oil storage areas. The municipal waste from the labour camp will only be routed through proper collection and handover to local municipal body for further disposal. No incineration or burning of wastes shall be carried out. Discarded plastic bags, paper and paper products, bottles, packaging material, gunny bags, hessian, metal containers, strips and scraps of metal, PVC pipes, rubber and poly urethane foam, auto mobile spares, tubes, tires, belts, filters, waste oil, drums and other such materials shall be either reused or will be sold /given out for recycling. Wastewater will be treated through Septic tank and soak pit and the sludge should be cleared by municipal exhausters. 224 | P a g e V. Disposal of bituminous waste At locations identified for disposal of residual bituminous wastes, the disposal will be carried out over a 60 mm thick layer of rammed clay so as to eliminate the possibility of leaching of wastes into the ground water. The Contractor will suitably dispose off unutilized non-toxic debris at pre-designated disposal sites, subject to the approval of JUIDCO. Debris generated from construction activities along the rivers and streams drainage channels shall be carefully disposed in such a manner that it does not flow into the surface water bodies or form puddles in the area. VI. Disposal of non-bituminous waste Non-bituminous wastes may be dumped in in barren lands, only after approval of JUIDCO/ULB Local tree species suitable for such re-habitation work shall be selected in consultation with local community. VII. CRITERIA FOR LAND SELECTION FOR DISPOSAL OF CONSTRUCTION OF DEBRIS For disposal of debris, dumping sites need to be selected. The criteria for selection of dumping sites include: No residential areas are located downwind side of these locations * Dumping sites are located at least 1000 m away from sensitive locations; * Dumping sites do not contaminate any water sources, rivers etc.; and * Dumping sites have adequate capacity equal to the amount of debris generated; * Permission from the Village Panchayat and other regulatory authority are to be obtained for the dumping site selected. Sites should be chosen so that it can be suitably rehabilitated * Productive lands are to be avoided; and * Available waste lands shall be given preference VIII. DOCUMENTATION AND BOOKKEEPING The designated disposal site approved by ULB only can be used as disposal site. The contractor should keep record of type and quantity of material disposed daily and capacity of disposal site. Stringent action & penalties should be imposed off on contractor for dumping of materials in locations other than the pre-identified locations. Grievance Redressal mechanism should be in place for taking note and action on such complaints. 225 | Page ANNEXURE IX: OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT PLAN Assessment and Control of Occupational Health Risks The Contractor shall carry out a Health Risk Assessment (HRA) of all construction activities for all chemical, physical, biological, ergonomic, emergency situations and psychological health hazards associated with work at the construction site having risks assessed as medium or high on the Risk Assessment Matrix based on which control measures should be selected, implemented and documented. On site and off site emergency management plan shall be developed to effectively handle them. i. The environmental and occupational health and safety aspects and related emergency preparedness response can include incidence such as collapse of structure, trench, explosion, and other occupational accidents. ii. The selection of controls should take account of the control hierarchy, i.e. Elimination, Substitution, Engineering, Procedural and lastly Personal Protective Equipment. iii. Contractor shall develop the onsite emergency plan considering the potential environmental, occupational health and safety emergency at site and activities involved, and submit a copy of this plan to PlU and CSQC consultant before the start of the work. (this is also applicable for the operational phase of the water treatment plant) iv. Construction staff shall be trained in the nature of the occupational risk, hazards and the specified controls and responses. v. All records of emergency preparedness plan with emergency contact numbers, mock drills and corrective preventive action record after emergency is occurred vi. The accident and incident records and emergency preparedness drill reports shall form part of quarterly report to the PMU vii. Contractor shall be responsible to handle emergency condition and shall be liable to compensate the damage against accident, if any occurs at site. 226 | Page I. Chemical Hazards The Contractor shall identify, assess and control all hazardous chemicals involved in the construction, including building materials, proprietary chemical products, fumes, dusts and gases emitted because of cutting and welding and sanding/grinding. II. Physical Hazards The Contractor shall assess the risks associated with physical hazards and eliminate them or control them to as low as reasonably practicable, applying the principles outlined below: 1. Noise For operations under noisy conditions, the Contractor shall establish procedures in compliance with the Noise Guideline provided in "The Noise Pollution (Regulation And Control) Rules, 2000". The Contractor shall reduce noise from construction equipment by measures such as: Selecting machinery that has inherent noise reduction features; Periodic monitoring of sound levels and regular maintenance of equipment; Contractor shall conduct periodic monitoring of sound pressure at least once each quarter. 2. Vibration Where exposure to vibration may affect part or all of the body, for example in the use of pneumatic drills, the Contractor shall ensure that exposures are assessed and eliminated or controlled. 3. Climatic Stress For operations under extreme climatic conditions, the Contractor shall establish procedures in compliance with the relevant standards. Ill. Biological Hazards Where insects, mites and animals, moulds, yeasts, fungi, bacteria and viruses are present in the working environment, exposures to pathogenic biological agents shall be controlled such that diseases and ill health effects are prevented. 1. Malaria 227 | Page When construction takes place in areas where malaria occurs, a comprehensive risk based malaria control program shall be in place encompassing all aspects of malaria prevention programs. Use of malaria prophylaxis is a must, comparable with wearing safety shoes and hard hats. The four components of malaria prophylaxis are: Awareness * Be aware of the risk of malaria in the work locations or sites visited; * Be aware of the signs and symptoms and know how long it takes to develop the illness after being bitten. Bite Prevention - Avoid being bitten by mosquitoes by: * Wearing long sleeved shirts and trousers when outdoors; * Using insect repellent (preferably containing the active ingredient DEET) and; * Using air conditioning whenever available or mosquito nets at bedtime in the absence of air-conditioning. Chemoprophylaxis - comply when advised by a competent health professional: * Take anti-malarial drugs (chemoprophylaxis) when appropriate, to prevent infection from developing into clinical disease. Although highly effective, note that anti-malarial drugs do not guarantee 100% protection; * Medications are safe to use if taken according to medical advice. Diagnosis and Treatment * Early diagnosis and treatment can prevent fatalities. Seek immediate diagnosis and treatment if a fever and/or flu-like symptoms develop one week or more after entering and up to 3 months after departure from a risk area; * Inform your doctor of recent travel to a malaria risk area; * Owner should closely monitor performance of these Malaria control programs. 2. Legionella bacteria Water systems may support the growth of legionella bacteria. These bacteria can enter the human body when contaminated water is inhaled as a spray, and may cause infection in the form of Pontiac Fever or Legionnaires 'disease. Known sources of legionella-contaminated water on construction sites, which may lead to infection, include: Domestic water storage tanks; Pipe work including dead legs and intermittently used water services; Personal and safety showers, pipe work and heads; Fire water and other water storage tanks; Water supplies used for suppressing road dust etc.; Water cooling systems for air conditioners; Water jetting equipment 228 | Page The Contractor shall appoint a competent person to assess the risk of legionella and to implement the control measures. 3. Pest and Insect Control Typical pests are flies, mosquitoes, rats and snakes. Effective cleaning and good housekeeping of worksite and worker's camps is the basis of any pest control programme. In addition to providing Long Lasting Impregnated Nets. The Contractor shall employ a specialist subcontractor to provide a pest control service for the worksite and workers camp, to the Contractor's specification. IV. Ergonomic Hazards The use of good manual handling and lifting techniques for construction materials minimises back and other related injuries. The Contractor shall therefore instruct workers in correct posture and lifting techniques. V. Psychological Hazards 1. Work Plan and Organisation The Contractor needs to be assured that all relevant and appropriate good working practices are being followed. To plan the work so as to maximise efficiency and so as to optimise human efforts the following shall be considered: Work cycles/shift work, taking account of local legislation Circadian (daily) rhythms of the working population 2. Working Hours and Working Cycles Regular long working hours and shift work can promote fatigue. Fatigue can lead to reduced mental function and vigilance. As a result there will be an increased likelihood of accidents and ill health. Most construction activities carry a safety risk and this shall not be aggravated by serious fatigue because of excessive overtime. As a minimum the Contractor shall follow local legislation and ILO/UN recommendations on maximum working hours. The Contractor shall assess all the risks associated with the extended working hours and shift cycles and shall agree with the Owner the working hours and working cycles to be applied on the specific project. The Contractor shall set up a system to monitor that Subcontractors are also following the agreed working cycles. 229 | Page VI. Monitoring of Health Performance and Incident Reporting & Investigation The Contractor shall have health monitoring systems in place. A medical file shall be kept for each employee. This file should include details of the pre-employment fitness to work assessment, details of any subsequent first aid treatments or clinic visits, and details of any medical surveillance that may be undertaken. The Contractor shall monitor: Occupational illness cases and frequency; First aid treatment cases; Number of individuals' undergoing medical surveillance; Number of health audits; Number of health-related training courses; There may be a requirement to monitor and report specific illnesses, if required by the specific health management plan. Contractors shall investigate health incidents and non-accidental deaths, involving their staff in the same way as they are expected to investigate and report safety incidents. VII. Fitness to Work The Contractor shall identify all worker groups whose specific work or working conditions require a minimum fitness for duty standard. VIII. Local Health Facilities and Medical Emergency Response The Contractor shall provide access to suitably equipped and staffed hospitals. The Contractor shall provide medical centre and first aid arrangements that comply with the Medical Emergency Guidelines. Particular attention shall be paid to ensuring that the required first aid response times are achieved and should be verified by drills. The Contractor shall develop a site-specific plan based on the health risk assessment, which describes the response to various medical emergency scenarios and medical evacuation procedures. The Contractor shall arrange for regular drills to practice and learn from the various emergency scenarios. IX. General Health and Safety 1. Drinking Water Drinking water standards should meet those in the latest edition of Guidelines for Drinking Water Quality - WHO. The Contractor shall provide sufficient potable water calculated at 30 litres per person per day, plus at least five days' emergency supply. 230 | P a g e 2. Garbage Collection The Contractor shall provide a suitable system for garbage collection and disposal. Spillage of refuse should be prevented. Arrangement shall be made for a daily collection of food wastes for collection of refuse from living quarters and work sites not less than twice weekly. A sufficient number of fly-proof and rodent proof bins or containers shall be supplied to all food establishments, and to camp areas and work sites to maintain cleanliness. Bins shall be cleaned immediately after being emptied. Disposal of garbage shall meet local legislative requirements and public health standards. X. Emergency preparedness and response planning The 'On-site emergency plan' to be prepared by contractor and shall include minimum the following information: Site Locations Name, Designation & Contact Numbers of the organization, nearby hospitals, fire agencies etc. and key personnel including their assigned responsibilities in case of an emergency. Site Layout Diagram showing location of fire extinguishers, emergency collection area and fire alarm Identification of Potential Emergencies Situations/ preventive measures / control & response measures Medical services / first aid List of emergency equipment including fire extinguishers, fire suits etc. 231 | Page 232 | Page ANNEXURE X: GENERAL GUIDELINES FOR CHLORINATION PLANTS INCLUDING, HANDLING STORAGE AND SAFETY OF CHLORINE CYLINDERS AND DRUMS This Indian Standard (Part 1) was adopted by the Indian Standards Institution on 31 May 1983, after the draft finalized by the Public Health Engineering Equipment Sectional Committee had been approved by the Civil Engineering Division Council. Chlorine cylinders and drums with liquid chlorine can rapture at temperatures of over 70'C due to building up of internal pressure. Chlorine gas damages the lungs and attacks the mucous membranes. Therefore, special precautions are required to be observed when working with chlorine gas apparatus and chlorine containers. In the formulation of this standard due weightage has been given to international co- ordination among the standards and practices prevailing in different countries in addition to relating it to the practices in the field in this country. For the purpose of deciding whether a particular requirement of this standard is complied with, the final value, observed or calculated, expressing the result of a test or analysis, shall be rounded off in accordance with IS : 2-1960*. The number of significant plates retained in the round of value should be the same as that of the specified value in this standard. INSTALLATION Chlorination Equipment and Container Room Chlorine gas units and cylinders shall be housed in separate rooms, easily accessible, close to the point of application and convenient for truck loading and safe container handling. The floor shall be flat and at least 150 mm above the surrounding ground and drainage shall be adequate. The height of the container room should be at least 4'0 m. Under no circumstances such units shall be housed in basement or below ground level since the chlorine gas is heavy and settles into depressions. The exits shall lead directly out in the open and the doors shall open outward. The hinges of the doors should be of parliamentary type. At least two exits shall be provided in each such rooms. Adequate arrangements for air circulation and cross ventilation shall be made in the rooms. Air entry shall be from above and air exit shall be from below. Exhaust fans shall be provided at floor level. Natural ventilation and means of cross ventilation that allows change in approximate 10 minutes is desirable. For small installation, provision of ventilator openings 'at the bottom, one opposite the other is adequate. 233 | Page Separate and reasonably gas tight enclosers openings to the outdoor shall be provided for housing the chlorine feeding equipment in large installations (where tonne containers are used). These enclosers shall be vented to the upper atmosphere and equipped with positive means of exhaust ( near the floor level, at the centre of the room or opposite to the entrance) capable of a complete air change within 2 to 4 minutes in an emergency. A satisfactory ventilation scheme involves a combination of fresh air and exhaust system, consisting of fans that force the fresh air into the enclose through openings near the ceiling with exhaust fans to clear away any chlorine contaminated air near the floor level. The design of exhaust system shall not include the natural ventilation that may be available. Rooms for chlorine containers in which more than 200 kg chlorine is stored shall be separated from the chlorine gas apparatus room and shall be accessible., only from outside: Containers shall rest securely on cradles or on a level rack equipped with adequate safety block to prevent rolling and be slightly elevated from the floor to keep them dry. The temperature in the installation room shall be within the range of +4 to + 400C. The chlorine gas containers and chlorine gas pipes shall not be exposed to direct heat radiations and shall be protected from sun rays. Electrical installations inside the chlorine gas rooms shall be limited to the absolute minimum required. While laying electrical wiring and fixtures adequate safety precautions shall be observed during their installation of ensuring safe use of electricity (see IS : 732- 1963* and IS : 5216-1969t ). The following information shall be indicated prominantly on the outside entry door: - "Chlorine gas dosing apparatus room" "Smoking and handling naked flame prohibited "Admission restricted". HANDLING Ordinarily a plant labourer can handle up to 100-kg cylinder when aided by small hand cart. Heavy containers shall be handled with the aim of mechanical contrivance, such as trucks, monorails, cranes or other such equipment. Chlorine gas containers shall not be bumped, dropped or rolled on the ground and no object shall be allowed to strike them with force. Use of mechanical lifting devices is recommended. For lifting one tonne container, the capacity of the mechanical device should be about 2 tonne-. STORAGE 234 | P a g e All plants, particularly small- ones, should keep on hand at all times sufficient supply of chlorine cylinders or drums. Special consideration shall be given to requirements of monsoon seasons. Cylinders shall conform to IS: 7681-1975* and the provisions of IS: 8198 (Part 6 )-1979t for filling, inspection, testing, maintenance. And use -of containers for storage and transportation of liquefied chlorine in cylinders shall be observed. Cylinders shall be stored vertically so that a leaking container, if found, Can be removed with the least possible handling of others. Tonne containers shall be stored on the sides all the time horizontally with suitable rollers or saddles. Tonne containers are equipped with two values each with an internal eduction pipe. A removable hood is provided to protect the valves from inj4ry during shipment and handling. In placing tonne containers in position for use, the two valves shall be in vertical alignment. The eduction pipes then permit the upper valve to discharge gas and the lower valve liquid chlorine. No other objects except chlorine gas storing containers shall be kept in the room. SAFETY All operating and storing rooms for chlorine gas appliances and containers shall be fire proof. Chlorine storage rooms should preferably be provided with chlorine gas alarm device which gives out an acoustic or an optical signal when the chlorine gas concentration is reached, the set value for which is 1'0 mg chlorine per cubic metre of air in case of a person working in the room and 20 mg chlorine per cubic metre of air when no human being is inside the room. The sensor for alarm device shall be placed not higher than 300 mm above the floors of the room. A bottle of ammonia is essential to detect leaks, etc, in case alarm device is not provided. Cylinder as well as chlorine shall be tested at every shift period for leaks, first by trying to detect the sharp irritating smell of chlorine, then by passing over each cylinder and around each valve and pipe connections, a rod with a small cotton-wool swab tied on the end, dipped in an aqueous solution of ammonia. If chlorine is, present in the air, the swab will appear to smoke due to formation of white cloud of ammonium chlorine. If the leak appears to be heavy, all persons not directly concerned should leave the area and the operator should put on his mask and make a thorough search of the leak. NOTE - In tracing a leak, always work down-stream that is start at the cylinder and work down along the Jirie of flow until the leak is found. 235 | Page Safety equipment, like gas masks, rubber gloves, aprons shall be housed in easily accessible (unlocked) cupboard placed outside the chlorination room. NOTE - Faulty gas mask is' worse than none at all. Hence these shall be tested frequently and canisters shall be changed at proper intervals. First aid box and eye wash fountain shall be provided outside chlorinator room. The provisions shall be made for emergency disposal of chlorine from leaking containers. The proportions of alkali and water recommended for this purpose are given in Table 1. TABLE 1 RECOMMENDED ALKALINE SOLUTIONS FOR ABSORBING CHLORINE CONTAINER CAUSTIC SODA SODA Asr Hi YDRATEt LIME CAMACITY J --k -,---- 100% Water kg Water kg Water k& ks 1 1 45 57 ISO 136 450 57 570 67 85 275 204 680 85 850 1000 115 3 640 2272 9090 115 1150 NoTE - When chlorine is to be absorbed in hydrated lime, the solution should be continuously and vigorously agitated. Water shall never be applied to the chlorine leak to stop it, as it will only make it worse. When a chlorine leak occurs, the ventilation system should be operated immediately before any person enters the chlorination room. NOTE - Ventilation system should be controlled from outside. The exhaust pipe of the apparatus shall lead to the open through the shortest path and the outlet of this exhaust pipe shall not be readily accessible. In case of fire: the cylinders and drums containing' chlorine shall be protected by spraying with water since the containers' can burst at temperatures of over 700C. Source of pressurized water shall be provided adjacent to the chlorination room. Fusible plug, a safety device, shall be provided over all cylinders' and containers designed to melt or soften between 70 to 750C to preclude a build-up of hydrostatic pressure resulting from thermal expansion due to fire and other hazardous conditions. Before disconnecting the flexible leads from containers to gas headers, the cylinder valves should be closed first and then the gas under pressure should be drawn from the header and flexible leads before the header valve is closed. 236 | Page Solvents, such as petroleum, hydrocarbons or alcohols should not be used for cleaning parts which come in contact with chlorine. The safe solvents are chloroform or carbon tetrachloride. Grease should never be used where it comes in contact with chlorine. 22 No direct flame should 'be applied to the chlorine cylinder when heating becomes necessary. The protective hood over the valve should always be kept in place except when the cylinders are in use In addition to this, the relevant provisions of IS4263-1967 shall also be observed as far as possible. 22 Code for safety for chlorine 237 | Page ANNEXURE XI: ESMP MONITORING REPORT BY PIU Name of Sub-Project: Name of ULB: The components taken up for town are detailed in the following Table. Package Particulars Status Date of Date of Award Completion The status of Environmental and Social Management Plan (ESMP) for the month year are presented in the following sections PERMISSIONS/CONSENTS/CLEARANCES/APPROVALS: S.no Particulars Competent Status (applied/obtained) Authority 1. Forest 2 Railways 3 National Highway 4 Irrigation Department 5 NOC for water abreaction from source 6 CTO (batching plant) 7 CTE (batching plant) 8 Ground water extraction for construction activity 9 Establishment of DG-set (as per Air Act, 1981.) 10 PUC certificates 11 Labour License (as per Labour Act 1970) 12 Labour Registration (as per BOC Act -1996) 13 Certificate of Employing Labour (as per BOC Act -1996) I. FIELD VISITS & TRAINING CONDUCTED 238 | Page Date Sites Visited Persons Met Remarks Field Visit/ Training II. COMPLIANCE TO EM P23 Particulars Complied Compliance to EMP Pre-Construction Phase Construction Phase 0 Monitoring Requirements & O Specifications Ill. REDRESS OF GRIEVANCES/ COMPLIANT HANDLING Sub Project Registers No. of Grievances Action Taken Maintained received in the month IV. LABOUR REGISTRATION AND RECORDS Sub Project Labour Total labor M/F Local/Migrant license registered/working obtained on the project on (no. of the date of labour) inspection V. ACCIDENTS ON SITE Project Site Total accidents Fatal/serious FIR available Action taken in project injury/Disability site/camps etc. this months 23lnsert Construction Stage EMP table here and provide compliance status, and Recommendations for each EMP measures and environment monitoring reports 239 | Page VI. TEMPORARY IMPACTS ON STRUCTURES AND LIVELIHOODS Sr. Total affected identified so PAH identified this ARAP/RAP/SMP Received No far. month approved so far entitlement so far. VII. DESIGN CHANGES Design New scope Environmental Mitigation Cost of Parameter of work Impacts/Risks measures mitigation (if Applicable) VIII. ENVIRONMENTAL MONITORING VERIFICATION (A) Air Quality Monitoring Ambient Air Monitoring Time-period of Monitoring: S.No Location of Observed NAAQS Standard Compliance Mitigation sampling Value (B) Water Quality Monitoring Time-period of Monitoring: S.No Location of Observed IS:10500 Values Compliance Mitigation sampling Value (C) Ambient Noise Monitoring Time-period of Monitoring: S.No Location of Observed CPCB Values Compliance Mitigation sampling Value IX. WASTE MANAGEMENT PLAN VERIFICATION 240 | P a g e S. Waste Type Quantity Disposal Method/ Reuse site No 1 Excavated Soil 2 Domestic Solid Waste 3 Construction debris 4 Hazardous Waste 5 Labour Camp Waste X. TREE PLANTED S.No Location Species Quantity Survival (%) Panted XI. SUMMARY AND CONCLUSIONS EMP monitoring being done daily on the critical issues and following improvements/ positive developments are observed. S. No Issues/Deviations Compliance Corrective actions to Compliance status last be taken status during this visit visit 1 2 3 4. 5 6. 7 8 241 | Page ANNEXURE XII: ENVIRONMENT IMPACT ASSESSMENT METHODOLOGY Impact Description An impact is any change to a resource or receptor brought about by the presence of a project component or by the execution of a project related activity. The impacts have been characterized into the following Adverse or beneficial; Direct or indirect; Short, medium, or long-term in duration; and permanent or temporary; Affecting a local, regional or global scale; including trans-boundary; Table A: Impact Characteristics S.No. Impact Characteristics Definition 1 Adverse Causes adverse change from the baseline, or introduces a new undesirable factor. 2 Beneficial Causes improvement on the baseline or introduces a positive change. 3 Direct Impact Impacts that result from a direct interaction between a proposed project activity and the receiving environment/receptors 4 Indirect Impact Impacts that result from other activities that are encouraged to happen as a consequence of the proposed project Impact Severity Impact severity is a function of the extent, duration, and, sensitivity of the receptor. The definition of extent, duration and sensitivity to consider for determining impact severity has been presented in B Table B: Parameters to consider for impact severity S.No Classification Description 1 Extent Evaluation of the area of occurrence/influence of environmental impact; Extent can be defined as limited (within 2 km radius of the site); local (within 5 km radius of the site); regionally (district wide, nationally or internationally). 242 | Page 2 Duration Defines the time which a receptor will be affected. Temporary (<1 year); short term (1 - 5 years); medium term (5 - 10 years); long term (>10); or permanent. 3 Sensitivity of High sensitivity: Entire community affected (more than 100 receptor households affected), presence of world heritage and important cultural sites, presence of water body used by community within 50 m of project footprint, presence of ecologically sensitive area, national park or wild life sanctuary within 2 km of project site. Medium sensitivity: More than 50 and less than 100 houses affected, presence of forest area within 5 km, presence of water body used by community within 50-100 m of project footprint. Low sensitivity: No displacements, no potential for stakeholder conflict, less than 50 household affected, water body used by community present within 500 m of project footprint, no livelihood impact. Based on the above table, impact severity is calculated as presented below: Very low: Environmental changes are within the existing limits of natural variations. Low: Environmental changes exceed the existing limits of natural variations. Natural environment is completely self-recoverable. Medium: Environmental changes exceed the existing limits of natural variations and results in damage to specific environmental components. Natural environment remains self-recoverable. High: Environmental changes result in significant disturbance to specific environmental components and ecosystems. Certain environmental components lose self-recovering ability. Probability of occurrence The probability of occurrence of an impact is described below: Unlikely - The impact is unlikely to occur. Likely - The impact is likely to occur under most conditions. Definite - The impact will occur. Impact Significance Impact significance is determined from an impact significance matrix (Table) which compares severity of the impact with probability of its occurrence. 243 | Page Table C: Impact significance Probability of occurrence Unlikely Likely Definite Severity Very low Negligible Negligible Minor Low Negligible Minor Minor Medium Minor Moderate Moderate High Minor Major Major Impact significance criteria are as follows: Major: These denote that the impact is unacceptable and further mitigation measures must be implemented to reduce the significance. Moderate: Impacts in this region are considered tolerable but efforts must be made to reduce the impact to levels that are as low as reasonably practical. Minor: Impacts in this region are considered acceptable. Negligible: Impacts in this region are almost not felt. 244 | P a g e ANNEXURE XIV: FOREST NOC APPLICATION AND MAP OF PIPELINE 3TW 4:f mq rr a f 1 (e .si'èirw # we,) 3T%f T 2006 RT 3 ~ m qf T tú - 1;; 0.000 Z; 1" ý3fzh.- -M T;ZTC J wi ff 2006 m 1 Qf245 -dP a g:- (2) irfe# W f4Ä-'U (2 '4-¿#wrd Wýf~ ~ ~~~~~i 2 T4 - Zkp 19.e "Tr- 14. (rs) e-5 -r3 Vm/,rh iR- (Tr) Zý- eAe , 3d ()1:50.00m 'R T" ý*r4.ef 5 1d e# W NI ,3 «f rr :- Ji A " : O (3) Y< tof W ',4 cw# 446M._%"16 2 WT w zb-g-qR oki4 " i4 3 i fk fåf5 Tjrt ur c -r p pr 4 -4 g ~ s 4 t-a--t ý sf s í;JT n ýz fýf jf 5>pmT-n 5 0 umaga y# r -cge gTCgT vf~h were vrt (fan i* ) 4 Týl Wl ~ ò wiq/rjzt4 wfg ,IT- 245 |P ag e (T 2.2 (4) ) nn ~fi tåmimT) (1) ,-,n (2) (3) (4) nnUfà 10f (2 e a 2 3 u.gå-A -<» T 2 T 5 (5) ~nT f~Rm 2~¥ -fl~4 ~ .................. T........... ..........-............ 246 1 Pra gfe r r 38 .00 ale ea 247 | P a g e 11 ANNEXURE XV: NOC ISSUED UNDER FRA, 2006, SECTION 3 (2) (FOR REPLACEMENT OF PIPELINE IN 0.0235 HA OF FOREST LAND) E-ma5Il:dfokhMnd@?jgmaiLeom, Xift ~ r'r4i f~T 4 0.235 to 1g4 -4t 3~ T -t9 W- 740 Mf - 07.06.17 UW 4 zpT 'fW-192 C~T-28.06.17 'O2 O 2006 ZbeTer 3 (2) 4;1 CM 4 Ta F f4% «TrT-@-239 R ' 10-3845 4 v4 r 4 i 0235 ko j b-qT_ ( 3Mf~r~ & ii1a) 30 2f0-206 4 -T 3 (2) * 3tr n I r 4 m 1) 'r n u fr ü 44 4 4r ff fT # f awa1 aTfen 1980 * m Tr fT 2) wrt * m w4 My # r f4frr n 3) t p eTga/ àmwè 5) 'ýR 451 43- f - ëdww )r 6) f (Divertion) fN rà -4w n amrø5T f rr41 148 r A L p 248 |P ag e 12 ANNEXURE XVI: JUSTIFICATION OF POINT NO. 5 OF FOREST NOC NOC was provided by District Forest Officer( DFO) on 3.7.2017. Point number 5 of the NOC stated that no excavation work can be undertaken inside forest land.As the project required excavation activity inside forest for laying of pipeline, JUIDCO requested for clarification of the same from the DFO. DFO, Khunti on letter dated 28.07.2017 clarified that excavation activity can be undertaken 235 sqm of forest land for laying of pipeline - W1 lhaT 1 ti- qWTq*i- 1110 fkiE- 03,0717 -M 3MV W*r- 1007 f i- 26,07 17 W4frK4 WVr5- 1110 tqtrF- 03.07.17 9m t*40r1 *T-r 3&pW itRt A41i. 2006 'it W 3TMrt 9rM W44f0 uWrM * aYM 4 *,haT- f4% WMte- V6- 259 Z R# 10- 384s 4 T Wj4 4t V 00235 to at1drr 41 ifr 249 Page ANNEXURE XVII: NO OBJECTION FROM WATER RESOURCES DEPARTMENT FOR WATER WITHDRAWAL FROM EXISTING INTAKE POINT i o LtdiKhunti/WS/204/2015-282 |ii 27.02.2016 2048 8 14 MLD 2 *lma ti ? d A 3 f 3sh 'pdg m;ra - I 14~ 250i Tal 250 |P a g e ANNEXURE XVIII: SCOPE OF WORK FOR SAFEGUARDS SUPERVISION 1. The CSQC team will include a suitably qualified Environment Social Health and safety Specialist (ESHS) to undertake the day-to-day supervision of contractors in all matters concerning compliance with the ESMP, and the occupational health, safety (OHS), Waste Management, Labour Camp Management and Labour influx and child labour etc... 2. The PIU's safeguards officers will provide independent oversight and inputs to the CSQC Consultant with regard to all aspects of environmental and social compliance, for the CSQC Consultant to have addressed on the project through their role. 3. The JMDP PMU will undertake at least quarterly inspections of the construction sites, accompanied by the CSQC safeguard specialists. The Environment and Social Specialist shall prepare a joint quarterly report to be agreed by all parties clearly identifying actions to be taken to improve safeguards compliance. 4. Prior to any contractor commencing civil works the CSQC ESHS specialist shall in consultation with the PMU: * Review and Clear the Contractor's ESMP to ensure that it meets that it meets the requirements of: (i) the respective ESMPs; (ii) fully complies with relevant national laws, including any conditions of consent; (iii) meets the World Bank's Environmental, Health and Safety (EHS), and applicable IFC industry Sector Guidelines and environmental and social safeguards policies of WBG * Review and Clear the Contractor's OHS Plan. This shall be consistent with the projects ESMP OHS requirements, as well as the World Bank's EHS guidelines, and applicable IFC industry Sector Guidelines. 5. The environmental and social specialist of PIU shall report to the PMU environemal and social specialists if any changes to project design or construction methods which would trigger an update to the Project ESMP, RAP and STPP. Changes to works or methods should be assessed against the existing Project Area of Influence (PAl), Corridor of direct impact (Col) and whether there is a likely public interest aspect to the changes. If either the PAl (geographically, socially or environmentally) has changed or Col has changed substantially or if there is a public interest element to the changes then the safeguard instruments shall be updated. 251 | Page 6. CSQC shall regularly update JUIDCO PlU and PMU on progress with the contractor's applications for permits or consents as relevant under local laws or regulations. 7. CSQC shall Supervisethe management of the Contractors labour in all matters concerning occupational health, safety and care of the works and workers, including HIV/AIDS prevention, gender based violence (GBV). 8. CSQC shall ensure that the contractor is adhering to the day-to-day requirements of the ESMP, the environmental and social safeguard requirements under Gol laws (including conditions of consent), and the World Bank's occupational health, environmental and social safeguards policies. 9. CSQC shall ensure that any workers camps are established and managed in accordance with the recommendations of the ESMP and the guidance contained in the IFC Guidance Note on Worker's Accommodation. 10. CSQC shall issue instructions to the Contractor to address any ESMP non- compliance issues. 11. CSQC shall submit monthly progress report and support PIU in preparation of quarterly safeguard progress reports in an agreed format covering all aspects of the project supervision, including project progress, testing results, occupational health and safety, ESMP compliance, incidents, near misses, summary of grievances / complaints and actions taken, upcoming or potential issues to be any consultation undertaken, relevant training, and compliance with permits and consents. 12. CSQC shall provide support to contractor, PIU to consult with the communities and stakeholders in accordance with the consultation plan in the ESMP 252 | Page