100459 Phu Ly 19 October 2015 Cr.5031-VN Medium Citites Development Project-Phu Ly city subproject Revised/ update Procurement Plan for the remaining packages of the project Cost Bid Bid Cost Bid/ Contra Estimate/ Docs/ Docs/ Estimate/ Contract Proposa ct Revie TOR/R TOR/R Contract Contract Contract price Selection l duratio Description w by FP FP Signing Remark No. price (million Method submiss n WB prepara approva (mm/yy) (thousan VND) ion (month d USD) tion l s) (mm/yy) (mm/yy) (mm/yy) I Component 2: Environmental sanitation improvement Construction of Lam Ha 2 Revised the cost of the regulation lake, lower the package: increased compared road Ä?T493 and to the PP cleared by the Bank. construction of the Reason: There are some PL2-01 embankment on the North 6.857,0 142.634,0 NCB Post 10/15 11/15 12/15 12/15 20 additional items leading to side of Chau Giang river revisions in designing. (section from outlet of Lac Update the implementation Trang II pumping station to progress. Chau Giang bridge) II Component 4: Project management support and technical assistance Asset management and Is is separated from package PL4-13A 172,0 3.574,0 CQS Post 10/15 11/15 11/15 12/15 18 capacity building PL4-13. TOR of PL4-13A and Ces of both packages have Procurement of equipment been cleared by the Bank at PL4-13B and GIS database for asset 122,0 2.544,0 NCB Post 02/2016 03/2016 03/2016 04/2016 04 NOL dated 12 Oct. 2015. management Update the implementation Cost Bid Bid Cost Bid/ Contra Estimate/ Docs/ Docs/ Estimate/ Contract Proposa ct Contract Revie TOR/R TOR/R Contract Contract price Selection l duratio Description w by FP FP Signing Remark No. price (million Method WB prepara approva submiss (mm/yy) n (thousan VND) ion (month d USD) tion l s) (mm/yy) (mm/yy) (mm/yy) progress. TOR+CE have been reviewed by PMU+consultant; awaiting response from the Bank. Final evaluation of the PL4-10 72,0 1.492,0 CQS Post 10/16 10/16 11/16 12/16 09 Revised the name of the project package. Update the cost + implementation duration. Equipment for activities of Update the implementation teaching, studying and progress. PL4-21 97,0 2.018,0 Shopping Post 12/2015 01/2016 01/2016 02/2016 02 living of Luong Khanh Thien secondary school Followed the proposed training plan + CE. Expect to be non- Trainings for PMU and PL4-24 21,0 436,0 SOEs N/A 15 continuously implemented concerning agencies under SOE method for 15 months.