NILE EQUATORIAL LAKES SUBSIDIARY ACTION PROGRAM (NELSAP PROCUREMENT PLAN 1st May 2017 to April 2018 I. General 1. Project information: - Country borrower: Nile Basin Initiative/Nile Equatorial Lakes Subsidiary Action Program - Project Name: Nile Cooperation for Results Project - Loan/Credit No:- TF13766 - Project Implementing Agency (PIA): Nile Equatorial Lakes Subsidiary Action Program 2. Bank’s approvalDate of the procurement Plan: 3. Date of General Procurement Notice: N/A 4. Period covered by this procurement plan: 12 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] No Procurement Method Threshold Prior Review Comments (Goods and Works) in US Dollars Threshold in US Dollars 1 ICB (Goods) N/A N/A 2 LIB (Goods) N/A N/A 3 NCB (Goods and Non Consultants N/A N/A Services) 4 Shopping (Goods and Non ≤100,000 ≤100,000 Consultants Services) 5 ICB (Works) N/A 6 NCB (Works) N/A 7 Shopping (Works) N/A 8 ICB(Non-Consultant Services) N/A 2. Prequalification. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: : Guidelines for procurement under IBRD loans and IDA credits, NBI Procurement and Disposal Manual 5. Any Other Special Procurement Arrangements: N/A 6. Procurement Packages with Methods and Time Schedule: N/A III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: III. Selection of Consultants 2. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Ceiling Prior Review Comment Method Threshold 1. QCBS >= 1,000,000 2. QBS N/A 3. LCS ≤200,000 4. CQS N/A 5. SSS ≥ 100,000 6. IC ≥300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule PROCUREMENT Africa : AFCRI-Nile Cooperation for Results Project PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2020-03-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P130694 GPN Date: Project Name: AFCRI-Nile Cooperation for Results Project Loan / Credit No: TF / 13767 Executing Agency(ies): Nile Basin Initiative Secretariat WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-24732-GO-DIR / 1. Advancing Nile Basin- Pending software tools for TF / 13767 Wide Cooperation and Post Direct Selection Direct 5,000.00 0.00 Implementati 2018-02-05 2018-02-10 2018-03-17 2018-09-13 maintaining user community Analysis on portal and helpdesk UG-NBI-24733-GO-RFQ / 1. Advancing Nile Basin- Pending Request for Single Stage - One Printing the Corporate TF / 13767 Wide Cooperation and Post Limited 1,000.00 0.00 Implementati 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope Brochure Analysis on UG-NBI-24734-GO-RFQ / 1. Advancing Nile Basin- Pending Request for Single Stage - One Printing the NBI Corporate TF / 13767 Wide Cooperation and Post Limited 3,000.00 0.00 Implementati 2017-10-25 2017-11-24 2017-11-28 Quotations Envelope Report Analysis on UG-NBI-24249-GO-RFQ / 1. Advancing Nile Basin- Pending Request for Single Stage - One 5.1.1 - High end computing TF / 13767 Wide Cooperation and Post Limited 4,000.00 0.00 Implementati 2018-01-10 2018-02-22 2018-03-16 Quotations Envelope facility (server) Analysis on UG-NBI-24552-GO-RFQ / 1. Advancing Nile Basin- Request for Single Stage - One Printing 2018 NBI TF / 13767 Wide Cooperation and Post Limited 3,000.00 4,500.00 Signed 2017-11-25 2018-01-15 2018-01-19 2018-02-06 2019-01-05 Quotations Envelope Secretariat Calendars Analysis UG-NBI-24221-GO-DIR / 1. Advancing Nile Basin- 1.10.1.1 - Software tools for Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 5,000.00 0.00 Canceled 2017-11-24 2017-11-29 2018-01-10 2018-02-09 2018-03-16 2018-09-12 developing the integrated Proposals Envelope Analysis website and databases 1. Advancing Nile Basin- Pending UG-NBI-24247-GO-RFQ / Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 2,500.00 0.00 Implementati 2017-12-02 2018-01-21 2018-02-18 5.1.1.1 - Laptops Quotations Envelope Analysis on 1. Advancing Nile Basin- Pending UG-NBI-37577-GO-RFQ / Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 4,000.00 0.00 Implementati 2018-01-15 2018-03-12 2018-09-08 Printing of the NBI Strategy Quotations Envelope Analysis on UG-NBI-37654-GO-RFQ / 1. Advancing Nile Basin- Pending Request for Single Stage - One Printing of the State of TF / 13767 Wide Cooperation and Post Limited 1,000.00 0.00 Implementati 2018-01-09 2018-03-06 2018-09-02 Quotations Envelope knowledge brochure Analysis on Page 1 UG-NBI-24553-GO-RFQ / 1. Advancing Nile Basin- Request for Single Stage - One Printing the NBI Success TF / 13767 Wide Cooperation and Post Limited 1,500.00 0.00 Canceled 2018-01-20 2018-02-12 2018-03-09 Quotations Envelope Stories Analysis UG-NBI-37655-GO-RFQ / 1. Advancing Nile Basin- Request for Single Stage - One Procurement of Computer TF / 13767 Wide Cooperation and Post Limited 2,500.00 0.00 Canceled 2018-01-07 2018-03-04 2018-08-31 Quotations Envelope workstation/laptop Analysis UG-NBI-80192-GO-RFQ / 1. Advancing Nile Basin- Pending Activity 6.4.1.2 Printing of Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 5,000.00 0.00 Implementati 2018-10-23 2018-11-28 2018-12-20 communication products Quotations Envelope Analysis on (production cost, printing) UG-NBI-141069-GO-RFQ / Procurement of Office IT Equipment (High spec 1. Advancing Nile Basin- Pending Request for Single Stage - One computing facility (server) - TF / 13767 Wide Cooperation and Post Limited 26,000.00 0.00 Implementati 2019-11-04 2019-11-29 2020-01-15 Quotations Envelope $20,000; A3 printer color - Analysis on $4,000; Computer accessoires & one scanner - $2,000 UG-NBI-141064-GO-RFQ / W1.5.2.1-L6: Printing of 1. Advancing Nile Basin- Pending Knowledge & Information Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 2,000.00 0.00 Implementati 2019-11-30 2019-12-22 2020-01-10 products - from the basin- Quotations Envelope Analysis on wide hydrological monitoring system and using Remote UG-NBI-142438-GO-RFQ / W5.1.2.2-L2: Printing for knowledge and comm products on Climate Change: Long-term scenarios of 1. Advancing Nile Basin- Pending Request for Single Stage - One hydrology of the Nile Basin TF / 13767 Wide Cooperation and Post Limited 2,500.00 0.00 Implementati 2019-11-25 2019-12-22 2020-07-07 Quotations Envelope under selected climate Analysis on change projections made available for climate proofing medium to long term water resources planning and ad UG-NBI-142449-GO-RFQ / 1. Advancing Nile Basin- Pending Request for Single Stage - One W5.3.1.2-L4: Computer TF / 13767 Wide Cooperation and Post Limited 2,500.00 0.00 Implementati 2020-02-09 2020-03-14 2020-04-14 Quotations Envelope workstation/laptop Analysis on UG-NBI-152751-GO-RFQ / Activity C3.1.1.2 - Develop 1. Advancing Nile Basin- Pending NBI Corporate Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 3,700.00 0.00 Implementati 2020-01-13 2020-01-31 2020-07-29 Communication Products: Quotations Envelope Analysis on Printing NBI 2020 Wall calendars UG-NBI-152780-GO-RFQ / Activity C3.1.1.2 - Develop NBI Corporate 1. Advancing Nile Basin- Pending Request for Single Stage - One Communication Products: TF / 13767 Wide Cooperation and Post Limited 10,000.00 0.00 Implementati 2020-02-15 2020-03-06 2020-09-21 Quotations Envelope Printing copies of the Analysis on Benefits of Nile cooperation booklet UG-NBI-152743-GO-RFQ / Activity C3.1.1.2 - Develop 1. Advancing Nile Basin- Pending Request for Single Stage - One NBI Corporate TF / 13767 Wide Cooperation and Post Limited 6,000.00 0.00 Implementati 2020-01-12 2020-01-29 2020-08-05 Quotations Envelope Communication Products: Analysis on Printing corporate report UG-NBI-148213-GO-RFQ / 1. Advancing Nile Basin- Pending W1.8.1.1-L4: Printing of the Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 800.00 0.00 Implementati 2020-04-19 2020-05-28 2020-11-24 Water Qulity Baseline Quotations Envelope Analysis on document Page 2 UG-NBI-141077-GO-DIR / 1. Advancing Nile Basin- Pending W1.5.2.1-L3: Renewal of TF / 13767 Wide Cooperation and Post Direct Selection Direct 13,400.00 0.00 Implementati 2019-11-08 2019-11-13 2019-12-18 2020-12-18 Software license renewal Analysis on UG-NBI-163386-GO-RFQ / 1. Advancing Nile Basin- Pending W1.5.2.1-L3: Procurement of Request for Single Stage - One TF / 13767 Wide Cooperation and Post Limited 4,000.00 0.00 Implementati 2020-03-12 2020-04-07 2020-04-24 Additional 1 Scanner and 1 Quotations Envelope Analysis on Laptop. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Advancing Nile Basin- Under UG-NBI-22127-NC-RFB / Single Stage - One TF / 13767 Wide Cooperation and Post Request for Bids Limited 30,000.00 0.00 Implementati 2017-11-29 2018-03-12 2017-12-04 2018-03-13 2018-04-08 2018-06-07 2018-04-15 2018-06-08 2018-05-06 2018-09-15 IFMIS Software Envelope Analysis on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-80180-CS-QCBS / Activity 5.3.1.2 Consultancy 1. Advancing Nile Basin- Consultant firm for short-term river Open - Under TF / 13767 Wide Cooperation and Post Qualification 129,304.00 0.00 2019-03-20 2019-04-02 2019-04-10 2019-04-12 2019-05-24 2019-06-02 2019-05-28 2019-06-10 2019-12-07 flow forecasting expert International Implementation Analysis Selection support to development of river flow forecast INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-NBI-24551-CS-CDS / Graphic Designer (Long term Contract: Corporate report- 1. Advancing Nile Basin- 1200, Success Stories- 1200, Pending TF / 13767 Wide Cooperation and Post Direct Selection Direct 5,000.00 0.00 2016-12-20 2016-12-30 2017-03-05 2017-09-01 Nile News - 1200, Calendar Implementation Analysis - 800, Strategy document - 500 and Water Resources flyer - 100) UG-NBI-21887-CS-INDV / Consultant for regional and national training in Hydrodiplomacy, international law & 1. Advancing Nile Basin- Individual Pending negotiations: Consultant TF / 13767 Wide Cooperation and Post Consultant Open 6,000.00 0.00 2018-04-10 2018-05-10 2018-05-15 2018-05-28 2018-06-20 Implementation trainer for 6days ( 3-days Analysis Selection training, 2 preparations and 1 report) 10 meets in the countries and 1 regional meet- firm UG-NBI-22122-CS-INDV / 1. Advancing Nile Basin- Individual Pending 2.1.2.3 - Project/National TF / 13767 Wide Cooperation and Post Consultant Direct 15,181.00 0.00 2017-06-10 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Implementation Liason Officer Analysis Selection Page 3 UG-NBI-22129-CS-INDV / 1. Advancing Nile Basin- Individual Pending Salary for the Information TF / 13767 Wide Cooperation and Post Consultant Direct 29,400.00 0.00 2017-06-10 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Implementation Systems Specialist Analysis Selection UG-NBI-22120-CS-INDV / 1. Advancing Nile Basin- Individual 5.3.1.1 - Consultant- Senior Pending TF / 13767 Wide Cooperation and Post Consultant Open 21,950.00 0.00 2018-02-08 2018-03-29 2018-04-19 2018-05-24 2018-11-20 short-term river flow Implementation Analysis Selection forecasting expert 1. Advancing Nile Basin- Individual UG-NBI-37574-CS-INDV / Pending TF / 13767 Wide Cooperation and Post Consultant Open 24,000.00 0.00 2017-12-05 2018-01-23 2018-02-13 2018-03-20 2018-09-16 04 months salary (Modeler) Implementation Analysis Selection UG-NBI-75891-CS-INDV / WI 6.2.1.1 Consultant: 1. Advancing Nile Basin- Individual international water law Open - Pending TF / 13767 Wide Cooperation and Post Consultant 44,820.00 0.00 2018-08-28 2018-09-17 2018-09-20 2018-09-28 2018-12-31 expert- prepare training International Implementation Analysis Selection modules and conduct training 1. Advancing Nile Basin- Individual UG-NBI-22082-CS-INDV / Pending TF / 13767 Wide Cooperation and Post Consultant Direct 2,700.00 0.00 2018-10-05 2018-10-15 2018-10-19 2018-10-25 2018-10-29 English-French Translation Implementation Analysis Selection UG-NBI-22086-CS-INDV / 1. Advancing Nile Basin- Individual Pending English-French translation TF / 13767 Wide Cooperation and Post Consultant Direct 1,000.00 0.00 2018-10-05 2018-10-15 2018-10-19 2018-10-24 2019-10-30 Implementation Consultant -2 Analysis Selection UG-NBI-24304-CS-INDV / 2.1.2.3   Impact evaluation Consultant - Monitoring 1. Advancing Nile Basin- Individual Pending and evaluating TF / 13767 Wide Cooperation and Post Consultant Open 13,004.00 0.00 2018-01-05 2018-01-30 2018-02-06 2018-02-20 2018-04-24 Implementation implemetation of NBI Analysis Selection Strategy, strategic plan, programs and projects UG-NBI-37525-CS-INDV / 1. Advancing Nile Basin- Individual 5.3.1.1 - Consultant: senior TF / 13767 Wide Cooperation and Post Consultant Open 21,950.00 0.00 Canceled 2018-01-12 2018-03-02 2018-03-23 2018-04-27 2018-10-24 short-term river flow Analysis Selection forecasting expert UG-NBI-24264-CS-INDV / 5.3.1.1 Consultant -Regional consultnat - WR analyst experience in river flow 1. Advancing Nile Basin- Individual forecasting - Develop and TF / 13767 Wide Cooperation and Post Consultant Open 33,702.00 0.00 Canceled 2018-01-25 2018-05-11 2018-02-19 2018-02-22 2018-03-01 2018-11-09 operationalize short-term to Analysis Selection seasonal river flow forecasting - Requirements elaboration and preliminary design UG-NBI-80184-CS-INDV / Activity 6.4.1.2: An 1. Advancing Nile Basin- Individual Individual Consultant to Under TF / 13767 Wide Cooperation and Post Consultant Open 23,800.00 0.00 2018-09-28 2019-04-02 2018-11-12 2018-11-26 2018-11-30 2019-02-28 support the assessment of Implementation Analysis Selection status of Nile Cooperation at 20yrs UG-NBI-80185-CS-INDV / Activity 1.5.2.1 Individual 1. Advancing Nile Basin- Individual Consultant to support Pending TF / 13767 Wide Cooperation and Post Consultant Open 35,420.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 generation of actual ET Implementation Analysis Selection esimates and derived water balance products UG-NBI-80186-CS-INDV / Activity 6.4.1.1 Individual 1. Advancing Nile Basin- Individual Under Consultant to develop TF / 13767 Wide Cooperation and Post Consultant Open 23,800.00 0.00 2018-10-09 2019-05-07 2018-11-27 2018-12-05 2018-12-12 2019-03-15 Implementation benchmarking methodology Analysis Selection and assessment document Page 4 UG-NBI-24224-CS-INDV / 5.1.1.1 - Consultant - senior expert (climate change governance, water 1. Advancing Nile Basin- Individual governance issues, to help in TF / 13767 Wide Cooperation and Post Consultant Open 20,820.00 0.00 Canceled 2018-01-10 2018-05-16 2018-02-06 2018-02-14 2018-02-25 2018-04-10 preparation of state of Analysis Selection knowledge report and design and faciliation of the CC- water experts meetings UG-NBI-21883-CS-INDV / 2.1.1.1 Consultant for technical support to NileSEC in fundraising and 1. Advancing Nile Basin- Individual specialized proposal TF / 13767 Wide Cooperation and Post Consultant Open 8,846.00 0.00 Canceled 2018-03-23 2018-04-20 2018-04-23 2018-04-30 2018-06-25 development, Analysis Selection international/regional consultant for 15 days, 2 engagements UG-NBI-22000-CS-INDV / 6.2.1.1 A consultant to develop Inventory of relevant existing national committees 1. Advancing Nile Basin- Individual and their mandates TF / 13767 Wide Cooperation and Post Consultant Open 18,616.00 0.00 Canceled 2018-01-19 2018-02-13 2018-02-18 2018-04-10 2018-06-05 (including convening power) Analysis Selection and establish their capacity gaps in relation to trans boundary water cooperation UG-NBI-24288-CS-INDV / 6.2.1.2 Stakeholder 1. Advancing Nile Basin- Individual Database Regional consultant TF / 13767 Wide Cooperation and Post Consultant Open 24,468.00 0.00 Canceled 2018-02-05 2018-03-08 2018-03-14 2018-03-22 2018-05-10 - Support to trans boundary Analysis Selection units, to improve coordination UG-NBI-21875-CS-INDV / 2.1.1.1 Consultant for 1. Advancing Nile Basin- Individual developing resource TF / 13767 Wide Cooperation and Post Consultant Open 12,222.00 0.00 Canceled 2018-03-05 2018-03-30 2018-04-06 2018-04-15 2018-07-27 mobilisation strategy - Analysis Selection international consultant for 20 days UG-NBI-80193-CS-INDV / Acivity 5.1.1.1 inidividual 1. Advancing Nile Basin- Individual Pending consultant to support the TF / 13767 Wide Cooperation and Post Consultant Open 22,820.00 0.00 2018-09-28 2018-11-16 2018-11-20 2018-11-30 2019-02-20 Implementation development of the CC Analysis Selection projections datasets 1. Advancing Nile Basin- Individual UG-NBI-85799-CS-QCBS / Pending TF / 13767 Wide Cooperation and Post Consultant Open 8,412.00 0.00 2019-03-12 2019-04-04 2019-04-10 2019-04-15 2019-04-23 IPSAS Trainer Implementation Analysis Selection UG-NBI-80188-CS-INDV / 1. Advancing Nile Basin- Individual Pending Graphic Designer - Long TF / 13767 Wide Cooperation and Post Consultant Direct 2,700.00 0.00 2018-10-03 2018-10-13 2018-10-15 2018-10-19 2019-10-18 Implementation term Contract Analysis Selection UG-NBI-105712-CS-INDV / 1. Advancing Nile Basin- Individual Pending Procure an Asset TF / 13767 Wide Cooperation and Post Consultant Limited 4,000.00 0.00 2019-04-04 2019-04-09 2019-04-20 2019-05-03 2019-05-20 Implementation Revaluation consultant Analysis Selection UG-NBI-105717-CS-CDS / 1. Advancing Nile Basin- Under Procurement of Phase 2 - TF / 13767 Wide Cooperation and Post Direct Selection Direct 31,056.00 0.00 2019-03-14 2019-09-26 2019-03-24 2019-04-05 2019-05-30 Implementation IPSAS Consultant Analysis Page 5 UG-NBI-141079-CS-INDV / Consultant: international leader water quality expert; prepare water quality baseline report : 1. Advancing Nile Basin- Individual Pending Activity W1.8.1.1-L1: Develop TF / 13767 Wide Cooperation and Post Consultant Open 30,502.00 0.00 2020-01-29 2020-02-29 2020-03-10 2020-03-25 2020-10-03 Implementation a first joint report on the Analysis Selection baseline, quality standards and concept of the water quality monitoring for the river. UG-NBI-142496-CS-INDV / National- Graphic Designer: C3.1.1.2-L6 - Corporate report: 3600, Nile Newsletter:1200 & Wall 1. Advancing Nile Basin- Individual Calendars - 200; C5.1.2.2-L2- Pending TF / 13767 Wide Cooperation and Prior Consultant Direct 7,700.00 0.00 2019-11-04 2019-11-14 2019-12-05 2020-01-09 2020-06-30 CC Docs - 1000; W5.1.2.1-L6 Implementation Analysis Selection - Basin Monitoring Bulletin & Tech. note from ET Assessment: 1500; W1.8.1.1- L4 - WQ Comm. pdts - $200 UG-NBI-152649-CS-INDV / Activity 6.4.1.1.    1. Advancing Nile Basin- Individual Pending Undertake Assessments of TF / 13767 Wide Cooperation and Post Consultant Open 26,150.00 0.00 2020-01-06 2020-01-29 2020-02-04 2020-02-10 2020-05-29 Implementation good practice in financing Analysis Selection transboundary investments UG-NBI-152650-CS-INDV / 1. Advancing Nile Basin- Individual Pending Activity C2.1.1d.1 Develop TF / 13767 Wide Cooperation and Post Consultant Open 11,652.00 0.00 2020-02-07 2020-03-04 2020-03-10 2020-03-20 2020-04-30 Implementation proposals for new projects Analysis Selection UG-NBI-152723-CS-INDV / Activity 2.1.2.3. Monitoring and evaluating 1. Advancing Nile Basin- Individual implementation of NBI Under TF / 13767 Wide Cooperation and Post Consultant Open 19,410.00 0.00 2020-02-10 2020-02-17 2020-03-05 2020-03-10 2020-03-15 2020-05-05 Strategy, strategic plan, Implementation Analysis Selection programs and projects: BWP Mid-term Evaluation Consultant; 1.5 Man-month; UG-NBI-142427-GO-RFQ / 1. Advancing Nile Basin- Individual Pending W1.8.1.1-L4: Editing Services TF / 13767 Wide Cooperation and Post Consultant Open 1,000.00 0.00 2020-01-26 2020-02-19 2020-02-24 2020-02-28 2020-03-27 Implementation - water quality baseline Analysis Selection UG-NBI-148522-CS-INDV / 6.2.1.1: Consultant to 1. Advancing Nile Basin- Individual support regional and TF / 13767 Wide Cooperation and Post Consultant Open 20,150.00 0.00 Canceled 2020-02-10 2020-03-04 2020-03-10 2020-03-15 2020-09-11 national training in Analysis Selection Negotiation skills and conflict resolution UG-NBI-156704-CS-CDS / C3.1.1.2-L7: Long term 1. Advancing Nile Basin- Pending Consultant to translate TF / 13767 Wide Cooperation and Post Direct Selection Direct 3,000.00 0.00 2020-02-07 2020-02-12 2020-02-17 2020-06-30 Implementation multiple reports for a year- Analysis (English/Arabic/English) UG-NBI-142489-CS-INDV / C3.1.1.2-L1 - Consultant 1: 1. Advancing Nile Basin- Individual Pending International Consultant - TF / 13767 Wide Cooperation and Post Consultant Direct 9,750.00 0.00 2020-01-27 2020-02-06 2020-02-10 2020-02-14 2020-06-30 Implementation Graphic Designer (Benefits Analysis Selection of Cooperation Booklet) UG-NBI-142500-CS-INDV / C3.1.1.2-L7: Long term 1. Advancing Nile Basin- Individual Pending Consultant to translate TF / 13767 Wide Cooperation and Post Consultant Direct 5,000.00 0.00 2019-11-04 2019-11-14 2019-11-15 2019-11-20 2020-06-06 Implementation multiple reports for a year- Analysis Selection (French) Page 6 UG-NBI-142493-CS-INDV / C3.1.1.2-L2: Consultant 2: 1. Advancing Nile Basin- Individual Pending National Consultant - Editor TF / 13767 Wide Cooperation and Post Consultant Direct 1,500.00 0.00 2020-02-03 2020-02-13 2020-02-17 2020-02-26 2020-06-30 Implementation (Benefits of Cooperation Analysis Selection Booklet) UG-NBI-163123-CS-INDV / W6.2.1.1-L1: Consultant to 1. Advancing Nile Basin- Individual support regional and Pending TF / 13767 Wide Cooperation and Post Consultant Open 16,000.00 0.00 2020-03-20 2020-04-14 2020-04-17 2020-04-22 2020-05-22 national training in Implementation Analysis Selection Negotiation skills and conflict resolution UG-NBI-163435-CS-INDV / W6.2.1.1-L2: Consultant to support Terms of Reference 1. Advancing Nile Basin- Individual Pending Preparation for the regional TF / 13767 Wide Cooperation and Post Consultant Open 3,000.00 0.00 2020-03-06 2020-03-25 2020-03-27 2020-04-03 2020-04-09 Implementation and national trainer in Analysis Selection Negotiation skills and conflict resolution UG-NBI-163462-CS-INDV / 1. Advancing Nile Basin- Individual S2.1.2-L2: An Individual Pending TF / 13767 Wide Cooperation and Post Consultant Limited 10,000.00 0.00 2020-03-06 2020-03-11 2020-03-15 2020-03-22 2020-04-15 Consultant to support Assets Implementation Analysis Selection revaluation Page 7