PROCUREMENT PLAN (Textual Part) Project information: Sri Lanka – Water Resources Management Project-P- 166865 Project Implementation agency: Ministry of Mahaweli Development and Environment Date of the Procurement Plan: 24 June, 2019 Period covered by this Procurement Plan: 15 March 2020-30 Sep. 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non- consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Sri Lanka : Sri Lanka Integrated Watershed and Water Resources Management Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2019-06-28 2021-04-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166865 GPN Date: 2020-07-28 Project Name: Sri Lanka Integrated Watershed and Water Resources Management Project Loan / Credit No: / , IDA / 66190, IDA / 66210 M Executing Agency(ies): inistry of Mahaweli Development and Environment WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LK-MOMDE-117185-CW- Component 4: Project Request for Single Stage - One 2019-11- RFQ / Refurbishment of PMU / Post Limited 45,311.47 38,887.42 Signed 2019-06-26 2019-06-18 2019-08-14 2019-09-04 Management Quotations Envelope 12 office (IWWRMP/PP/WORKS/01) LK-MOMDE-123620-CW-RFB / Improvements to Unnichchai LB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 923,033.71 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 0+000 to stn 13+725 Improvements Envelope 18 (IWWRMP- 2/WORKS/ID/OCBN/04-1) LK-MOMDE-124032-CW-RFB / Improvements to Unnichchai RB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 906,741.57 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 0+000 to stn 4+950 ( Improvements Envelope 01 IWWRMP- 2/WORKS/ID/OCBN/04-2 ) LK-MOMDE-124217-CW-RFB / Improvements to Unnichchai RB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 887,640.45 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 4+950 to stn 10+000 ( Improvements Envelope 01 IWWRMP- 2/WORKS/ID/OCBN/04-3 ) LK-MOMDE-124409-CW-RFB / Rehabilititation of Panama Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 342,696.63 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Tank ( IWWRMP- Improvements Envelope 05 2/WORKS/ID/OCBN/07 ) LK-MOMDE-124659-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-03- Peramaduwa Scheme ( / Post Request for Bids Open - National 898,876.40 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Improvements Envelope 29 IWWRMP- 2/WORKS/ID/OCBN/17 ) LK-MOMDE-124666-CW-RFB / Improvements Viyadikulam Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 950,185.39 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Spill ( IWWRMP- Improvements Envelope 29 2/WORKS/ID/OCBN/18-2 ) LK-MOMDE-124667-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-05- / Post Request for Bids Open - National 325,505.62 0.00 Canceled 2020-01-24 2020-02-07 2020-02-28 2020-03-29 2020-05-03 Abakolawewa Tank ( IWWRMP- Improvements Envelope 03 2/WORKS/ID/OCBN/19 ) LK-MOMDE-124683-CW-RFB / Rehabilititation of Karawita Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2019-11-25 2019-12-09 2019-12-30 2020-01-29 2020-03-04 tank ( IWWRMP- Improvements Envelope 04 2/WORKS/ID/OCBN/20 ) LK-MOMDE-125489-CW-RFB / Rehabilititation of Madiyawa Component 2: Infrastructure Single Stage - One 2021-04- / Post Request for Bids Open - National 464,775.28 0.00 Canceled 2019-12-23 2020-01-06 2020-01-27 2020-02-26 2020-04-01 Tank ( IWWRMP- Improvements Envelope 01 2/WORKS/ID/OCBN/23 ) LK-MOMDE-125508-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-04- / Post Request for Bids Open - National 280,898.88 0.00 Canceled 2019-12-27 2020-01-10 2020-01-31 2020-03-01 2020-04-05 Mannankatiya Tank ( IWWRMP- Improvements Envelope 05 2/WORKS/ID/OCBN/27 ) LK-MOMDE-125511-CW-RFB / Rehabilititation of Main Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kimbulawana Oya / Post Request for Bids Open - National 347,780.90 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Improvements Envelope 18 Scheme (LBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-1 ) LK-MOMDE-125513-CW-RFB / Rehabilititation of Main Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kimbulawana Oya / Post Request for Bids Open - National 262,859.69 0.00 Canceled 2019-12-09 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Improvements Envelope 05 Scheme (RBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-2) LK-MOMDE-125515-CW-RFB / Rehabilititation of Maha Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 896,067.42 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Andara Wewa ( IWWRMP- Improvements Envelope 18 2/WORKS/ID/OCBN/29 ) LK-MOMDE-125834-CW-RFB / Improvement of Spillway Tail Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kotmale Dam ( / Post Request for Bids Open - National 369,101.12 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Improvements Envelope 05 IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-125839-CW-RFB / Repairs to gates of irrigation Component 2: Infrastructure Single Stage - One 2021-09- structures in Kalawewa Left / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2019-12-06 2019-12-20 2020-01-10 2020-02-09 2020-03-15 Improvements Envelope 16 Bank main canal (IWWRMP- 2/WORKS/MASL//OCBN/105) Page 1 LK-MOMDE-125846-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2020-11- Muthuiyankaddu Division - / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2019-11-15 2019-11-29 2019-12-20 2020-01-19 2020-02-23 Improvements Envelope 19 Package 01 (RB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-1 ) LK-MOMDE-125994-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Muthuiyankaddu Division - Improvements Envelope 20 (LB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-6 ) LK-MOMDE-125995-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-02- / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Muthuiyankaddu Division - Improvements Envelope 18 (LB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-7 ) LK-MOMDE-126158-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Muthuiyankaddu Division - Improvements Envelope 25 (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) LK-MOMDE-126330-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2021-04- Muthuiyankaddu Division - / Post Request for Bids Open - National 674,157.30 0.00 Canceled 2020-04-17 2020-05-01 2020-05-22 2020-06-21 2020-07-26 Improvements Envelope 22 (RB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-10 ) LK-MOMDE-126332-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-05- Muthuiyankaddu Division - / Post Request for Bids Open - National 561,797.75 0.00 Canceled 2020-05-17 2020-05-31 2020-06-21 2020-07-21 2020-08-25 Improvements Envelope 22 (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200- 11) LK-MOMDE-126333-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2021-05- Muthuiyankaddu Division - / Post Request for Bids Open - National 146,067.42 0.00 Canceled 2020-05-15 2020-05-29 2020-06-19 2020-07-19 2020-08-23 Improvements Envelope 20 (RB/Track 08) (IWWRMP- 2/WORKS/NPC/OCBN/200- 12) LK-MOMDE-126337-CW-RFB / Improvements of Muthuiyankaddu RB Main Component 2: Infrastructure Single Stage - One 2021-05- Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-05-20 2020-06-03 2020-06-24 2020-07-24 2020-08-28 Improvements Envelope 25 Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-13 ) LK-MOMDE-126338-CW-RFB / Improvements of Muthuiyankaddu LB Main Component 2: Infrastructure Single Stage - One 2021-07- Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-07-20 2020-08-03 2020-08-24 2020-09-23 2020-10-28 Improvements Envelope 25 Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-14 ) LK-MOMDE-126345-CW-RFB / Rehabilitation of Kalmadu Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 1,404,494.38 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 Scheme Headworks ( IWWRMP- Improvements Envelope 22 2/WORKS/NPC/OCBN/201-1 ) LK-MOMDE-126347-CW-RFB / Rehabilitation of channel to kandawalai under RB cannel Component 2: Infrastructure Single Stage - One 2022-08- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2021-08-23 2021-09-06 2021-09-27 2021-10-27 2021-12-01 under Kalmadu Scheme ( Improvements Envelope 28 IWWRMP- 2/WORKS/NPC/OCBN/201-2 ) LK-MOMDE-126353-CW-RFB / Rehabilitation of channel to Puliyampokkanai under RB Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 cannel under Kalmadu Improvements Envelope 25 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-3 ) LK-MOMDE-126367-CW-RFB / Improvements of Spill & Component 2: Infrastructure Single Stage - One 2021-10- spilltail under Kalmadu / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-5 ) LK-MOMDE-126371-CW-RFB / Rehabilitation of akkarayan kulam channel to Component 2: Infrastructure Single Stage - One 2021-02- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 kannagipuram under LB Improvements Envelope 18 cannel ( IWWRMP- 2/WORKS/NPC/OCBN/202-1 ) LK-MOMDE-126376-CW-RFB / Rehabilitation of akkarayan kulam channel to Akkarayan Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 under LB cannel & lift Improvements Envelope 21 irrigation ( IWWRMP- 2/WORKS/NPC/OCBN/202-2 ) LK-MOMDE-126378-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 kulam RB cannel ( IWWRMP- Improvements Envelope 03 2/WORKS/NPC/OCBN/202-3 ) Page 2 LK-MOMDE-126387-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2021-10- kulam spill & spilltail channel ( / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 IWWRMP- 2/WORKS/NPC/OCBN/202-5 ) LK-MOMDE-126390-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One 2021-10- under Piramanthalaru Scheme / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Improvements Envelope 03 ( IWWRMP- 2/WORKS/NPC/OCBN/203-1 ) LK-MOMDE-126391-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 Piramanthalaru Irrigation Improvements Envelope 22 Scheme (phase 01) (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-126392-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2021-09- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2020-09-21 2020-10-05 2020-10-26 2020-11-25 2020-12-30 Piramanthalaru Irrigation Improvements Envelope 26 Scheme (phase 02) ( IWWRMP- 2/WORKS/NPC/OCBN/203-3 ) LK-MOMDE-126396-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One 2021-10- under Kanagambikai Irrigation / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 Scheme (IWWRMP- 2/WORKS/NPC/OCBN/204-1) LK-MOMDE-126400-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Kanagambikai Scheme ( Improvements Envelope 26 IWWRMP- 2/WORKS/NPC/OCBN/204-2 ) LK-MOMDE-126410-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2020-12- of Kudamuruddy Tank ( / Post Request for Bids Open - National 421,348.31 0.00 Canceled 2019-12-19 2020-01-02 2020-01-23 2020-02-22 2020-03-28 Improvements Envelope 23 IWWRMP- 2/WORKS/NPC/OCBN/206-1) LK-MOMDE-126412-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Kudamuruddy Tank Irrigation Improvements Envelope 03 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/206-2) LK-MOMDE-126413-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2020-12- of Kariyalai Nagapaduwan / Post Request for Bids Open - National 1,123,595.51 0.00 Canceled 2019-12-16 2019-12-30 2020-01-20 2020-02-19 2020-03-25 Improvements Envelope 20 Tank ( IWWRMP- 2/WORKS/NPC/OCBN/207-1 ) LK-MOMDE-126416-CW-RFB / Rehabilitation of LB cannel Component 2: Infrastructure Single Stage - One 2021-10- under Kariyalai Nagapaduwan / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements Envelope 25 Tank (IWWRMP- 2/WORKS/NPC/OCBN/207-2) LK-MOMDE-126417-CW-RFB / Rehabilitation of RB cannel Component 2: Infrastructure Single Stage - One 2021-10- under Kariyalai Nagapaduwan / Post Request for Bids Open - National 308,988.76 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements Envelope 25 Tank ( IWWRMP- 2/WORKS/NPC/OCBN/207-3 ) LK-MOMDE-126418-CW-RFB / Rehabilitation of Downstream under Vaneri Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 kulam Irrigation Scheme ( Improvements Envelope 03 IWWRMP- 2/WORKS/NPC/OCBN/208-1 ) LK-MOMDE-126420-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 of Vaneri kulam ( IWWRMP- Improvements Envelope 21 2/WORKS/NPC/OCBN/208-2 ) LK-MOMDE-126422-CW-RFB / Rehabilitation of Dowstream infrastructure in Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Periyapandivirichan Kulam ( Improvements Envelope 26 IWWRMP- 2/WORKS/NPC/OCBN/209 ) LK-MOMDE-126382-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2022-07- / Post Request for Bids Open - National 842,696.63 0.00 Canceled 2021-07-16 2021-07-30 2021-08-20 2021-09-19 2021-10-24 kulam Headworks ( IWWRMP- Improvements Envelope 21 2/WORKS/NPC/OCBN/202-4 ) LK-MOMDE-163016-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2022-02- / Post Request for Bids Open - National 589,887.64 0.00 Canceled 2021-02-16 2021-03-02 2021-03-23 2021-04-22 2021-05-27 Muthuiyankaddu Division - Improvements Envelope 21 (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) LK-MOMDE-126361-CW-RFB / Rehabilitation of channel to kalmadu nagar under LB Component 2: Infrastructure Single Stage - One 2022-01- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2021-01-10 2021-01-24 2021-02-14 2021-03-16 2021-04-20 cannel under Kalmadu Improvements Envelope 15 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-4 ) LK-MOMDE-163051-CW-RFB / Rehablitation of tank Bund Pending (0.8km) including Rip Rap, Component 2: Infrastructure Single Stage - One 2024-03- IDA / 66210 Post Request for Bids Open - National 505,617.98 0.00 Implementat 2021-05-11 2021-12-07 2022-01-04 2022-02-03 2022-03-10 Spill and both sluice to Improvements Envelope 09 ion Meiyankal Tank (IWWRMP- 2/WORKS/EPC/OCBN/300) Page 3 LK-MOMDE-163052-CW-RFB / Rehabilitation of channels of Chadayanthalawa anicut, Kadukkayan anicut, Pending Component 2: Infrastructure Single Stage - One 2024-03- Neendakari anicut, and IDA / 66210 Post Request for Bids Open - National 226,320.22 0.00 Implementat 2021-05-17 2021-12-13 2022-01-10 2022-02-09 2022-03-16 Improvements Envelope 15 Weeramunai anicut in ion Chadayanthalawa Scheme (IWWRMP- 2/WORKS/EPC/OCBN/301) LK-MOMDE-163053-CW-RFB / Rehabilitation of Saliyapura Pending Component 2: Infrastructure Single Stage - One 2023-09- anicut of Paravipanchan IDA / 66210 Post Request for Bids Open - National 121,629.21 0.00 Implementat 2021-05-19 2021-12-15 2022-01-12 2022-02-11 2022-03-18 Improvements Envelope 09 scheme (IWWRMP- ion 2/WORKS/EPC/OCBN/302) LK-MOMDE-163054-CW-RFB / Improvements to canal Pending System (18km) inculuding Component 2: Infrastructure Single Stage - One 2024-03- IDA / 66210 Post Request for Bids Open - National 561,797.75 0.00 Implementat 2021-05-20 2021-12-16 2022-01-13 2022-02-12 2022-03-19 structures of Puluganawai- Improvements Envelope 18 ion Kankaniyar scheme (IWWRMP- 2/WORKS/EPC/OCBN/303) LK-MOMDE-163055-CW-RFB / Improvements of tank bund(1.5km), including Rip Pending Component 2: Infrastructure Single Stage - One 2024-03- Rap and Sluice Structure to IDA / 66210 Post Request for Bids Open - National 168,539.33 0.00 Implementat 2021-05-03 2021-11-29 2021-12-27 2022-01-26 2022-03-02 Improvements Envelope 01 Puluganawai-Kankaniyar ion scheme (IWWRMP- 2/WORKS/EPC/OCBN/305) LK-MOMDE-224661-CW-RFB / Rehabilitation of Pending Muththuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-07- IDA / 66210 Post Request for Bids Open - National 365,168.54 0.00 Implementat 2021-03-15 2021-07-13 2021-08-10 2021-09-09 2021-10-14 Muththuiyankaddu Division - Improvements Envelope 11 ion (RB/Track 03) (IWWRMP- 2/WORKS/NPC/OCBN/200-1) LK-MOMDE-125851-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-07- IDA / 66210 Post Request for Bids Open - National 325,842.70 0.00 Implementat 2019-11-15 2021-07-08 2021-08-05 2021-09-04 2021-10-09 Muthuiyankaddu Division - Improvements Envelope 06 ion (RB/Track 07) ( IWWRMP- 2/WORKS/NPC/OCBN/200-2 ) LK-MOMDE-125854-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National 617,977.53 0.00 Implementat 2019-11-15 2021-08-12 2021-09-09 2021-10-09 2021-11-13 Muthuiyankaddu Division - Improvements Envelope 13 ion (RB/Track 05) ( IWWRMP- 2/WORKS/NPC/OCBN/200-3 ) LK-MOMDE-125855-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2023-05- IDA / 66210 Post Request for Bids Open - National 634,831.46 0.00 Implementat 2020-01-20 2021-08-11 2021-09-08 2021-10-08 2021-11-12 Muthuiyankaddu Division - Improvements Envelope 06 ion (RB/Track 01) ( IWWRMP- 2/WORKS/NPC/OCBN/200-4) LK-MOMDE-125856-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 831,460.67 0.00 Implementat 2020-01-20 2021-08-19 2021-09-16 2021-10-16 2021-11-20 Muthuiyankaddu Division - Improvements Envelope 17 ion (RB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-5) LK-MOMDE-126155-CW-RFB / Rehabilitation of Pending Muththuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 464,831.46 0.00 Implementat 2021-03-15 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Muththuiyankaddu Division - Improvements Envelope 14 ion (RB/Track 06) (IWWRMP- 2/WORKS/NPC/OCBN/200-6) LK-MOMDE-163023-CW-RFB / Rehabilitation of Pending Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 589,887.64 0.00 Implementat 2021-06-16 2021-12-13 2022-01-10 2022-02-09 2022-03-16 Muthuiyankaddu Division - Improvements Envelope 11 ion (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-7) LK-MOMDE-163045-CW-RFB Pending / Rehabilitation of Kalmadu Component 2: Infrastructure Single Stage - One 2023-11- IDA / 66210 Post Request for Bids Open - National 1,619,101.12 0.00 Implementat 2020-11-18 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Scheme Headworks (IWWRMP- Improvements Envelope 17 ion 2/WORKS/NPC/OCBN/201-1) LK-MOMDE-163041-CW-RFB / Improvements of Spill & spill Pending Component 2: Infrastructure Single Stage - One 2022-11- tail under Kalmadu Scheme ( IDA / 66210 Post Request for Bids Open - National 291,011.24 0.00 Implementat 2020-11-16 2021-08-13 2021-09-10 2021-10-10 2021-11-14 Improvements Envelope 14 IWWRMP- ion 2/WORKS/NPC/OCBN/201-2 ) LK-MOMDE-163026-CW-RFB / Rehabilitation of Headworks Pending Component 2: Infrastructure Single Stage - One 2022-09- under Piramanthalaru Scheme IDA / 66210 Post Request for Bids Open - National 327,865.17 0.00 Implementat 2020-08-31 2021-06-28 2021-07-26 2021-08-25 2021-09-29 Improvements Envelope 29 (IWWRMP- ion 2/WORKS/NPC/OCBN/203-1) LK-MOMDE-163038-CW-RFB / Rehabilitation of Pending Downstream under Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 139,213.48 0.00 Implementat 2020-11-18 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Piramanthalaru Irrigation Improvements Envelope 14 ion Scheme (phase 01) (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-163046-CW-RFB / Rehabilitation of Pending Downstream under Component 2: Infrastructure Single Stage - One 2022-09- IDA / 66210 Post Request for Bids Open - National 224,719.10 0.00 Implementat 2020-09-21 2021-06-18 2021-07-16 2021-08-15 2021-09-19 Kanagambikai Scheme Improvements Envelope 19 ion (IWWRMP- 2/WORKS/NPC/OCBN/204) LK-MOMDE-126401-CW-RFB Pending / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 1,500,000.00 0.00 Implementat 2021-07-01 2021-12-28 2022-01-25 2022-02-24 2022-03-31 in Periyamdu Tank ( IWWRMP- Improvements Envelope 31 ion 2/WORKS/NPC/OCBN/205 ) Page 4 LK-MOMDE-163044-CW-RFB / Rehabilitation of Head works Pending Component 2: Infrastructure Single Stage - One 2023-04- of Kudamuruddy Tank ( IDA / 66210 Post Request for Bids Open - National 510,000.00 0.00 Implementat 2021-08-13 2022-01-10 2022-02-07 2022-03-09 2022-04-13 Improvements Envelope 13 IWWRMP- ion 2/WORKS/NPC/OCBN/206) LK-MOMDE-163059-CW-RFB / Rehabilitation of Head works Pending and Downstream Component 2: Infrastructure Single Stage - One 2023-05- IDA / 66210 Post Request for Bids Open - National 510,000.00 0.00 Implementat 2021-09-13 2022-02-10 2022-03-10 2022-04-09 2022-05-14 infrastructure of Kariyalai Improvements Envelope 15 ion Nagapaduwan Tank (IWWRMP- 2/WORKS/NPC/OCBN/207) LK-MOMDE-163064-CW-RFB Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 840,000.00 0.00 Implementat 2021-07-21 2022-01-19 2022-02-16 2022-03-18 2022-04-22 Nithakaikulam (IWWRMP- Improvements Envelope 22 ion 2/WORKS/NPC/OCBN/208) LK-MOMDE-125529-CW-RFB / Improvements to Walawa RB Pending 41 km Main Canal from Component 2: Infrastructure Single Stage - One 2024-01- IDA / 66210 Post Request for Bids Open - National 2,302,251.70 0.00 Implementat 2019-11-22 2021-05-03 2021-05-31 2021-06-30 2021-08-04 0+000 km to 17+400 km ( Improvements Envelope 31 ion IWWRMP- 2/WORKS/MASL/OCBN/100- 1) LK-MOMDE-125831-CW-RFB / Improvements to Walawa RB 41 km Main Canal from Pending 23+400 km to 33+420 km Component 2: Infrastructure Single Stage - One 2024-02- IDA / 66210 Post Request for Bids Open - National 2,444,167.62 0.00 Implementat 2019-11-22 2021-05-06 2021-06-03 2021-07-03 2021-08-07 and 34+640km to 40+910 Improvements Envelope 03 ion km ( IWWRMP- 2/WORKS/MASL/OCBN/100-2 ) LK-MOMDE-125832-CW-RFB / Hydro Mechanical works of Pending Walawa RB Main Canal ( Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 332,261.49 0.00 Implementat 2019-11-29 2021-05-06 2021-06-03 2021-07-03 2021-08-07 IWWRMP- Improvements Envelope 18 ion 2/WORKS/MASL/OCBN/100-3 ) LK-MOMDE-125833-CW-RFB / Ecological Improvements and Marking Reservation Pending Component 2: Infrastructure Single Stage - One 2023-03- along Walawa RB Main Canal ( IDA / 66210 Post Request for Bids Open - National 422,232.84 0.00 Implementat 2019-11-29 2021-05-17 2021-06-14 2021-07-14 2021-08-18 Improvements Envelope 01 IWWRMP- ion 2/WORKS/MASL/OCBN/100-4 ) LK-MOMDE-163031-CW-RFB / Improvement of Spillway Tail Pending Canal and removing rock Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2020-06-29 2021-12-01 2021-12-29 2022-01-28 2022-03-04 boulders in Kotmale Dam ( Improvements Envelope 04 ion IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-125835-CW-RFB / Installation of Automated Geodetic Survey Systems in Pending Component 2: Infrastructure Single Stage - Two 2022-09- Kotmale & Randenigala Dams IDA / 66210 Post Request for Bids Open - National 1,623,595.51 0.00 Implementat 2019-11-19 2021-05-10 2021-06-07 2021-09-24 Improvements Envelope 24 for Dam Movement ion Monitoring ( IWWRMP- 2/WORKS/MASL//OCBN/102 ) LK-MOMDE-125836-CW-RFB / Supply and Installation of Pending Component 2: Infrastructure Single Stage - Two 2022-10- Gantry Crane for Polgolla IDA / 66210 Post Request for Bids Open - National 2,000,000.00 0.00 Implementat 2019-12-03 2021-05-24 2021-06-21 2021-10-08 Improvements Envelope 08 Barrage ( IWWRMP- ion 2/WORKS/MASL//OCBN/103 ) LK-MOMDE-125838-CW-RFB / Supply and Installation of Pending Component 2: Infrastructure Single Stage - Two 2022-10- Gantry Crane for Udawalawe IDA / 66210 Post Request for Bids Open - National 1,185,393.26 0.00 Implementat 2019-12-03 2021-06-11 2021-07-09 2021-10-26 Improvements Envelope 26 Dam ( IWWRMP- ion 2/WORKS/MASL//OCBN/104 ) LK-MOMDE-163036-CW-RFB / Repairs to gates of irrigation Pending Component 2: Infrastructure Single Stage - One 2023-04- structures in Kalawewa Left IDA / 66210 Post Request for Bids Open - National 449,438.20 0.00 Implementat 2020-07-06 2021-07-01 2021-07-29 2021-08-28 2021-10-02 Improvements Envelope 05 Bank main canal (IWWRMP- ion 2/WORKS/MASL//OCBN/105) LK-MOMDE-163066-CW-RFB / Immediate improvement of Pending upper phephary of Polgolla Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 786,516.85 0.00 Implementat 2021-10-04 2021-11-08 2021-12-06 2022-01-05 2022-02-09 Dam - Phase I (IWWRMP- Improvements Envelope 09 ion 2/WORKS/MASL/OCBN/106- 1) LK-MOMDE-123572-CW-RFB / Improvements to Pending Bathalagoda Anicut & Anicut Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 397,191.01 0.00 Implementat 2019-11-15 2021-09-21 2021-10-19 2021-11-18 2021-12-23 inlet CHL road from CH0 to Improvements Envelope 23 ion 3+775 (IWWRMP- 2/WORKS/ID/OCBN/01-1) LK-MOMDE-123594-CW-RFB / Improvement to Bathalagoda Pending Component 2: Infrastructure Single Stage - One 2022-10- main bund road ch from 0 to IDA / 66210 Post Request for Bids Open - National 122,134.83 0.00 Implementat 2019-11-15 2021-10-21 2021-11-18 2021-12-18 2022-01-22 Improvements Envelope 29 1+525 ( IWWRMP- ion 2/WORKS/ID/OCBN/01-2 ) LK-MOMDE-123596-CW-RFB / Improvement to Bathalagoda Pending Component 2: Infrastructure Single Stage - One 2022-10- Anicut (Mechanical works) ( IDA / 66210 Post Request for Bids Open - National 110,505.62 0.00 Implementat 2019-11-15 2021-10-28 2021-11-14 2021-12-14 2022-01-18 Improvements Envelope 25 IWWRMP- ion 2/WORKS/ID/OCBN/01-3 ) LK-MOMDE-123597-CW-RFB / Improvement to Bathalagoda Pending Component 2: Infrastructure Single Stage - One 2022-10- main CHL road from 0+000 to IDA / 66210 Post Request for Bids Open - National 179,606.74 0.00 Implementat 2019-11-15 2021-09-23 2021-10-21 2021-11-20 2021-12-25 Improvements Envelope 01 2+100 km ( IWWRMP- ion 2/WORKS/ID/OCBN/01-4 ) Page 5 LK-MOMDE-123600-CW-RFB / Rehabilitation of D1, D2, D4 Pending Component 2: Infrastructure Single Stage - One 2023-01- canals in Bathalagoda Scheme IDA / 66210 Post Request for Bids Open - National 259,662.92 0.00 Implementat 2019-11-19 2021-10-14 2021-11-11 2021-12-11 2022-01-15 Improvements Envelope 15 ( IWWRMP- ion 2/WORKS/ID/OCBN/02-1) LK-MOMDE-123602-CW-RFB / Rehabilitation of D5, D7, D7 Pending Component 2: Infrastructure Single Stage - One 2022-12- RB canals in Bathalagoda IDA / 66210 Post Request for Bids Open - National 205,505.62 0.00 Implementat 2019-11-19 2021-09-28 2021-10-26 2021-11-25 2021-12-30 Improvements Envelope 30 Scheme ( IWWRMP- ion 2/WORKS/ID/OCBN/02-2 ) LK-MOMDE-123606-CW-RFB Pending / Rehabilitation of Dewahuwa Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 579,550.56 0.00 Implementat 2019-11-19 2021-09-22 2021-10-20 2021-11-19 2021-12-24 Scheme ( IWWRMP- Improvements Envelope 24 ion 2/WORKS/ID/OCBN/03 ) LK-MOMDE-124090-CW-RFB / Improvements to Main Canal Pending Component 2: Infrastructure Single Stage - One 2023-06- (LB) of Huruluwewa Scheme ( IDA / 66210 Post Request for Bids Open - National 647,022.47 0.00 Implementat 2021-03-16 2021-09-27 2021-10-25 2021-11-24 2021-12-29 Improvements Envelope 22 IWWRMP- ion 2/WORKS/ID/OCBN/04-1) LK-MOMDE-124402-CW-RFB / Improvements to Pending Component 2: Infrastructure Single Stage - One 2023-06- Huruluwewa Main Canal (RB) IDA / 66210 Post Request for Bids Open - National 687,359.55 0.00 Implementat 2021-03-16 2021-09-27 2021-10-25 2021-11-24 2021-12-29 Improvements Envelope 22 (IWWRMP- ion 2/WORKS/ID/OCBN/04-2) LK-MOMDE-124408-CW-RFB / Improvements to (22 km) Pending Component 2: Infrastructure Single Stage - One 2023-07- Branch canal and structures of IDA / 66210 Post Request for Bids Open - National 815,235.96 0.00 Implementat 2021-03-16 2021-10-12 2021-11-09 2021-12-09 2022-01-13 Improvements Envelope 07 Illukuchenal Unit ( IWWRMP- ion 2/WORKS/ID/OCBN/05 ) LK-MOMDE-124412-CW-RFB / Rehabilitation of tank bund Pending (1.5 km) including Rip Rap Component 2: Infrastructure Single Stage - One 2024-01- IDA / 66210 Post Request for Bids Open - National 337,640.45 0.00 Implementat 2019-12-02 2021-10-04 2021-11-01 2021-12-01 2022-01-05 and sluice of Mahalindawewa Improvements Envelope 05 ion Tank ( IWWRMP- 2/WORKS/ID/OCBN/06) LK-MOMDE-124591-CW-RFB Pending / Rehabilititation of Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 725,466.29 0.00 Implementat 2019-11-14 2021-09-20 2021-10-18 2021-11-17 2021-12-22 Nagadeepa Tank ( IWWRMP- Improvements Envelope 22 ion 2/WORKS/ID/OCBN/07) LK-MOMDE-124592-CW-RFB Pending / Rehabilititation of Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 369,932.58 0.00 Implementat 2019-12-16 2022-01-10 2022-02-07 2022-03-09 2022-04-13 Wadamunai Tank ( IWWRMP- Improvements Envelope 13 ion 2/WORKS/ID/OCBN/08 ) LK-MOMDE-124593-CW-RFB / Rehabilitation of Vahanery Pending Component 2: Infrastructure Single Stage - One 2023-04- Tank bund from Stn 0+000 to IDA / 66210 Post Request for Bids Open - National 551,604.19 0.00 Implementat 2019-12-16 2022-01-11 2022-02-08 2022-03-10 2022-04-14 Improvements Envelope 14 Stn 2+100 ( IWWRMP- ion 2/WORKS/ID/OCBN/09-1 ) LK-MOMDE-124671-CW-RFB / Improvements of Access Pending road of Vahanery tank form Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 775,000.00 0.00 Implementat 2019-12-27 2022-01-11 2022-02-08 2022-03-10 2022-04-14 Stn 0+000 to 7+683 Improvements Envelope 14 ion (Santhiyar road) ( IWWRMP- 2/WORKS/ID/OCBN/09-2 ) LK-MOMDE-124594-CW-RFB Pending / Rehabilitation of HaliEla Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 422,191.01 0.00 Implementat 2019-12-16 2021-09-09 2021-10-07 2021-11-06 2021-12-11 Tank ( IWWRMP- Improvements Envelope 11 ion 2/WORKS/ID/OCBN/10) LK-MOMDE-124595-CW-RFB Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National 1,216,044.94 0.00 Implementat 2019-12-02 2021-08-23 2021-09-20 2021-10-20 2021-11-24 Akathimurippu Tank ( Improvements Envelope 24 ion IWWRMP- 2/WORKS/ID/OCBN/11) LK-MOMDE-124596-CW-RFB Pending / Rehabilitation of Pavatkulam Component 2: Infrastructure Single Stage - One 2022-10- IDA / 66210 Post Request for Bids Open - National 874,719.10 0.00 Implementat 2019-12-02 2021-07-30 2021-08-27 2021-09-26 2021-10-31 Tank ( IWWRMP- Improvements Envelope 31 ion 2/WORKS/ID/OCBN/12 ) LK-MOMDE-124642-CW-RFB Pending / Improvements to Mavilaru Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 522,646.07 0.00 Implementat 2020-02-03 2021-11-24 2021-12-22 2022-01-21 2022-02-25 Headworks (LB) ( IWWRMP- Improvements Envelope 25 ion 2/WORKS/ID/OCBN/13-1) LK-MOMDE-124649-CW-RFB Pending / Improvements to Mavilaru Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 412,247.19 0.00 Implementat 2020-02-06 2021-12-01 2021-12-29 2022-01-28 2022-03-04 Headworks (RB) ( IWWRMP- Improvements Envelope 04 ion 2/WORKS/ID/OCBN/13-2 ) LK-MOMDE-124655-CW-RFB Pending / Rehabilitation of Peramadu Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 595,505.62 0.00 Implementat 2021-03-22 2021-12-22 2022-01-19 2022-02-18 2022-03-25 Tank ( IWWRMP- Improvements Envelope 25 ion 2/WORKS/ID/OCBN/14) LK-MOMDE-124660-CW-RFB / Improvements to RB Main Pending canal from 0+000Km to Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 676,471.91 0.00 Implementat 2019-12-20 2021-11-22 2021-12-20 2022-01-19 2022-02-23 1+465Km of Viyadikulam Improvements Envelope 23 ion Scheme ( IWWRMP- 2/WORKS/ID/OCBN/15) LK-MOMDE-125488-CW-RFB Pending / Rehabilitation of Haththota Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 600,425.69 0.00 Implementat 2019-12-23 2021-12-03 2021-12-31 2022-01-30 2022-03-06 Anicut Scheme ( IWWRMP- Improvements Envelope 06 ion 2/WORKS/ID/OCBN/16) LK-MOMDE-125494-CW-RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One 2022-12- Muhathankulam Scheme ( IDA / 66210 Post Request for Bids Open - National 629,213.48 0.00 Implementat 2019-12-23 2021-09-06 2021-10-04 2021-11-03 2021-12-08 Improvements Envelope 08 IWWRMP- ion 2/WORKS/ID/OCBN/17) Page 6 LK-MOMDE-125496-CW-RFB Pending / Rehabilitation of Arawatta Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National 169,151.69 0.00 Implementat 2019-12-27 2021-08-09 2021-09-06 2021-10-06 2021-11-10 tank bund ( IWWRMP- Improvements Envelope 10 ion 2/WORKS/ID/OCBN/18) LK-MOMDE-125506-CW-RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One 2022-10- Waduwawala Scheme ( IDA / 66210 Post Request for Bids Open - National 352,808.99 0.00 Implementat 2019-12-27 2021-07-20 2021-08-17 2021-09-16 2021-10-21 Improvements Envelope 21 IWWRMP- ion 2/WORKS/ID/OCBN/19 ) LK-MOMDE-225755-CW-RFB / Improvement to Bund (1 km), rip rap Protection, Pending Component 2: Infrastructure Single Stage - One 2023-07- Instrumentation and Toe filter IDA / 66210 Post Request for Bids Open - National 1,685,393.26 0.00 Implementat 2021-06-30 2022-04-26 2022-05-24 2022-06-23 2022-07-28 Improvements Envelope 28 & drain of Senanayaka ion Samudraya Reservoir (IWWRMP- 2/WORKS/ID/OCBN/20) LK-MOMDE-225762-CW-RFB Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2021-07-28 2021-12-30 2022-01-27 2022-02-26 2022-04-02 Maruthankulam (IWWRMP- Improvements Envelope 03 ion 2/WORKS/NPC/OCBN/209) LK-MOMDE-228195-CW-RFB Pending / Rehabilitation on Akkarayan Component 2: Infrastructure Single Stage - One 2023-10- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2021-07-16 2022-01-12 2022-02-09 2022-03-11 2022-04-15 kulam Headworks (IWWRMP- Improvements Envelope 07 ion 2/WORKS/NPC/OCBN/202 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-117380-GO-DIR / Procurement of Relevant Data and Maps for Component 1: Watershed and preparation of GIS maps / Post Direct Selection Direct 15,151.52 0.00 Canceled 2019-08-05 2019-08-13 2019-09-17 2020-01-15 Water Resources Planning including specific geographic locations/sub-watersheds (IWWRMP/PP/GOODS/01) LK-MOMDE-123586-GO-RFB / Procurement of Crew Cabs ( Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 475,000.00 0.00 Canceled 2020-06-09 2020-06-23 2020-08-04 2020-09-03 2020-10-08 2021-04-06 IWWRMP- Improvements Envelope 2/GOODS/PMU/OCBN/3 ) LK-MOMDE-124216-GO-DIR / Purchasing of GIS Maps and Component 1: Watershed and / Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-01-27 2020-02-10 2020-03-21 2020-09-17 Satellite Images ( IWWRMP- Water Resources Planning 1/GOODS/PMU/OCBN/6 ) LK-MOMDE-123574-GO-RFB Pending / Procurement of clay Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 675,000.00 0.00 Implementati 2022-01-24 2022-02-07 2022-03-07 2022-04-06 2022-05-11 2023-03-07 grouting machines ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/1 ) LK-MOMDE-123581-GO-RFB Pending / Procurement of water weeds Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 845,000.00 0.00 Implementati 2021-07-09 2021-07-23 2021-08-20 2021-09-19 2021-10-24 2022-08-20 removers ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/2 ) LK-MOMDE-124212-GO-RFB Pending / Procurement of computer Component 1: Watershed and Single Stage - One IDA / 66210 Post Request for Bids Open - National 60,000.00 0.00 Implementati 2022-02-23 2022-03-09 2022-04-06 2022-05-06 2022-06-10 2022-10-08 and accessories-1 ( IWWRMP- Water Resources Planning Envelope on 2/GOODS/PMU/OCBN/4 ) LK-MOMDE-124214-GO-RFB Pending / Procurement of Photocopy Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 Implementati 2022-03-25 2022-04-08 2022-05-06 2022-06-05 2022-07-10 2022-11-07 Machines-1 ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/5 ) LK-MOMDE-124219-GO-RFB Pending / Procurement of Office Component 1: Watershed and Single Stage - One IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 Implementati 2022-03-22 2022-04-11 2022-05-09 2022-06-08 2022-07-13 2022-11-10 Equipments-1 ( IWWRMP- Water Resources Planning Envelope on 2/GOODS/PMU/OCBN/7 ) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-157171-NC-RFQ Pending / Conducting Asset Component 4: Project Request for Single Stage - One / Post Limited 2,808.99 0.00 Implementati 2020-05-30 2020-07-18 2020-08-17 verification and Valuation for Management Quotations Envelope on the PMU-IWWRMP Assets CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-116917-CS- INDV / Consultancy services Consultant Component 3: Multi-sector for Preparation of TOR for / Post Qualification Limited 9,090.91 0.00 Canceled 2019-07-25 2019-08-08 2019-09-07 2019-10-12 2020-04-09 Water Resources Planning River Basin Management Plan Selection (IWWRMP/PP/CONS/30) LK-MOMDE-120102-CS- QCBS / Consultancy service to finalize the Bid documents for Component 1: Watershed and Quality And Cost- / Post Open - National 12,121.21 0.00 Canceled 2019-09-16 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2021-03-27 irrigation dam rehabilitation Water Resources Planning Based Selection of Component 1 (IWWRMP/PP/CONS/35) Page 7 LK-MOMDE-121715-CS-CQS / Consultancy Service for Consultant preparation of Watershed Component 1: Watershed and / Post Qualification Open - National 15,151.52 0.00 Canceled 2019-07-17 2019-08-07 2019-09-20 2019-10-20 2019-11-24 2020-05-22 Management plans for Water Resources Planning Selection selected area (IWWRMP/PP/CONS/36) LK-MOMDE-121716-CS-CQS Consultant / Consultancy services for Component 2: Infrastructure / Post Qualification Open - National 30,303.03 0.00 Canceled 2019-09-15 2019-10-06 2019-11-19 2019-12-19 2020-01-23 2020-07-21 preparation of Risk Assesment Improvements Selection (IWWRMP/PP/CONS/37) LK-MOMDE-125891-CS- QCBS / Consultancy service for preparation of Watershed management plan for seven selected divisions -Nuwara Component 1: Watershed and Quality And Cost- / Post Open - International 1,348,314.61 0.00 Canceled 2019-12-05 2019-12-26 2020-02-08 2020-03-07 2020-04-06 2020-05-11 2020-06-15 2021-06-15 Eliya, Badulla, Walapnae & Water Resources Planning Based Selection Kandy (Delthota, Haguranketha and Pahatha Hewaheta) (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-125993-CS- QCBS / Consultancy Service for study and recommendation for back erosion of Rantambe dam spillway tail canal ,LB erosion Component 2: Infrastructure Quality And Cost- / Post Open - International 786,516.85 0.00 Canceled 2019-11-25 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2021-06-05 of Victoria dam spillway tail Improvements Based Selection canal, Back Analysis for Victoria dam and Kotmale Dam grouting gallery inspection (IWWRMP- 2/CS/QCBS/7) LK-MOMDE-126757-CS- QCBS / Development of Basin Management plan for Walawa Component 1: Watershed and Quality And Cost- / Post Open - National 421,348.31 0.00 Canceled 2020-05-25 2020-06-15 2020-07-29 2020-08-26 2020-09-25 2020-10-30 2020-12-04 2021-12-04 & Ma Oya including the Water Resources Planning Based Selection stakeholder workshops (IWWRMP-1/CS/QCBS/5) LK-MOMDE-126759-CS- QCBS / Consultancy service for Expansion and Component 1: Watershed and Quality And Cost- / Post Open - National 561,797.75 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2023-05-10 enhancement of WMS/MASL Water Resources Planning Based Selection bulk water allocation model (IWWRMP-1/CS/QCBS/6) LK-MOMDE-138818-CS-CQS / Consultancy on improving reservoir capacity by dredging Consultant Component 1: Watershed and sand deposits - medium and / Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-05 2020-08-09 2021-08-09 Water Resources Planning minor irrigation tanks within Selection the watershed (IWWRMP- 1/CS/CQS/2) LK-MOMDE-138828-CS-CQS / Establishment of policy and Consultant institutional arrangements for Component 2: Infrastructure / Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-14 2020-05-05 2020-06-18 2020-07-18 2020-08-22 2021-08-22 dam safety, and water Improvements Selection resources management (IWWRMP-2/CS/CQS/15) LK-MOMDE-138831-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 25,280.90 0.00 Canceled 2020-12-16 2021-01-06 2021-02-19 2021-03-21 2021-04-25 2022-04-25 Improvements social screening report for Selection rehabiliate dams & canals cluster VII (IWWRMP- 2/CS/CQS/18) LK-MOMDE-138832-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 25,280.90 0.00 Canceled 2019-12-13 2020-01-03 2020-02-16 2020-03-17 2020-04-21 2021-04-21 Improvements social screening report for Selection rehabilitate dams & canals cluster VIII (IWWRMP- 2/CS/CQS/19) LK-MOMDE-138824-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-09-09 2020-09-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 Improvements social screening report for Selection rehabilitate dams & canals cluster IV ( IWWRMP- 2/CS/CQS/11) LK-MOMDE-138829-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-22 2020-06-26 2021-06-26 Improvements social screening report for Selection rehabiliate dams & canals cluster V (IWWRMP- 2/CS/CQS/16) LK-MOMDE-138830-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 22,471.91 0.00 Canceled 2019-12-09 2019-12-30 2020-02-12 2020-03-13 2020-04-17 2021-04-17 Improvements social screening report for Selection rehabilitate dams & canals cluster VI (IWWRMP- 2/CS/CQS/17) Page 8 LK-MOMDE-138822-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2021-01-03 Improvements social screening report for Selection rehabilitate dams & canals cluster II (IWWRMP- 2/CS/CQS/9) LK-MOMDE-138835-CS-CQS / Feasibility study tocheck the Consultant Component 2: Infrastructure possibility of diverson of / Post Qualification Open - National 280,898.88 0.00 Canceled 2020-09-28 2020-10-19 2020-12-02 2021-01-01 2021-02-05 2022-02-05 Improvements Kaluganga Water to the CKD Selection area (IWWRMP-2/CS/CQS/22) LK-MOMDE-138823-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-04 2021-01-08 2021-07-07 Improvements social screening report for Selection rehabilitate dams & canals cluster III ( IWWRMP- 2/CS/CQS/10) LK-MOMDE-138836-CS-CQS / Preparation of guidline for Consultant Component 2: Infrastructure sustainable Dam safety and / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-07-30 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-12-07 Improvements Hydraulic Assets ( IWWRMP- Selection 2/CS/CQS/23 ) LK-MOMDE-138838-CS-CQS Consultant Component 2: Infrastructure Pending / Risk assessment for all / Post Qualification Open - National 280,898.88 0.00 2020-11-01 2020-11-22 2021-01-05 2021-02-04 2021-03-11 2022-03-11 Improvements Implementation identified dams Selection LK-MOMDE-162963-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed and Quality And Cost- Pending / Post Open - National 337,078.65 0.00 2020-06-16 2020-07-07 2020-08-20 2020-09-17 2020-10-17 2020-11-21 2020-12-26 2021-12-26 Upper Watershed Water Resources Planning Based Selection Implementation management intervention plan for cluster I (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-162965-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed and Quality And Cost- Pending / Post Open - National 280,898.88 0.00 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2022-05-10 Upper Watershed Water Resources Planning Based Selection Implementation management intervention plan for cluster II (IWWRMP- 1/CS/QCBS/2) LK-MOMDE-138837-CS-CQS / preparation of O & M Consultant Manuals and Emergency Component 2: Infrastructure Pending / Post Qualification Open - National 280,898.88 0.00 2021-12-01 2021-12-22 2022-02-04 2022-03-06 2022-04-10 2023-04-10 Action plans for selected Improvements Implementation Selection dams ( IWWRMP- 2/CS/CQS/24 ) LK-MOMDE-138834-CS-CQS / Feasibility Study for Construction of Pooneryn Consultant Tank and Barrages including Component 2: Infrastructure Pending / Post Qualification Open - National 252,808.99 0.00 2020-09-20 2020-10-11 2020-11-24 2020-12-24 2021-01-28 2022-01-28 Investigation, Detailed Design, Improvements Implementation Selection BD preparation, EIA and Social assessment (IWWRMP- 2\/CS/CQS/21) LK-MOMDE-162967-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed and Quality And Cost- Pending / Post Open - National 224,719.10 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-05 2021-06-04 2021-07-09 2021-08-13 2022-08-13 Upper Watershed Water Resources Planning Based Selection Implementation management intervention plan for cluster III (IWWRMP- 1/CS/QCBS/3) LK-MOMDE-138820-CS-CQS / Development of Consultant Component 1: Watershed and Pending Groundwater Data & / Post Qualification Open - National 56,179.78 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-11-08 Water Resources Planning Implementation Information System for WRB Selection (IWWRMP-1/CS/CQS/4) LK-MOMDE-138825-CS-CQS / Consultancy Service for Consultant Component 2: Infrastructure Pending preparation of Livelihood / Post Qualification Open - National 56,179.78 0.00 2020-09-06 2020-09-27 2020-11-10 2020-12-10 2021-01-14 2021-07-13 Improvements Implementation Support Assistance Plan (LSA) Selection ( IWWRMP-2/CS/CQS/12 ) LK-MOMDE-162968-CS- QCBS / Consultancy Service development of best practices Component 1: Watershed and Quality And Cost- Pending for water management using / Post Open - National 56,179.78 0.00 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2021-10-07 Water Resources Planning Based Selection Implementation native , herbal, economical important species (IWWRMP- 1/CS/QCBS/4) LK-MOMDE-138819-CS-CQS / Development Groundwater Consultant management plans & legal Component 1: Watershed and Pending / Post Qualification Open - National 140,449.44 0.00 2020-09-25 2020-10-16 2020-11-29 2020-12-29 2021-02-02 2022-02-02 framework for basins and Water Resources Planning Implementation Selection national level (WRB) (IWWRMP- 1/CS/CQS/3) LK-MOMDE-121717-CS-CQS Consultant / Preparation of Management Component 4: Project Pending / Post Qualification Open - National 12,121.21 0.00 2020-10-01 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-08-07 Information System Management Implementation Selection (IWWRMP/PP/CONS/15) LK-MOMDE-138839-CS-CQS / Consultancy Service for Consultant Component 4: Project Pending Development for Project / Post Qualification Open - National 14,044.94 0.00 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-05-23 Management Implementation Website (IWWRMP- Selection 4/CS/CQS/26) LK-MOMDE-138827-CS-CQS / Consultancy service for Consultant Component 2: Infrastructure Pending design of Bridge at 4+000 km / Post Qualification Open - National 28,089.89 0.00 2020-10-20 2020-11-10 2020-12-24 2021-01-23 2021-02-27 2021-08-26 Improvements Implementation of walawa RB main canal Selection (IWWRMP-2\/CS/CQS/14) Page 9 LK-MOMDE-138821-CS-CQS / Consultancy service for Preparation of Environmental Consultant Component 2: Infrastructure Pending Social Management / Post Qualification Open - National 56,179.78 0.00 2020-08-21 2020-09-11 2020-10-25 2020-11-24 2020-12-29 2021-06-27 Improvements Implementation Framework and Environmental Selection social screening report for rehabiliate dams & canals EPC LK-MOMDE-138826-CS-CQS / Consultancy Service for inspection, identification of Consultant Component 2: Infrastructure Pending defects and repair works of / Post Qualification Open - National 84,269.66 0.00 2020-09-20 2020-10-11 2020-11-24 2020-12-24 2021-01-28 2021-07-27 Improvements Implementation syphone from 3+950 km to Selection 4+330 km of walawa RB main canal (IWWRMP-2/CS/CQS/13) LK-MOMDE-162972-CS- QCBS / Consultancy service for development for Component 1: Watershed and Quality And Cost- Pending / Post Open - National 56,179.78 0.00 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2022-04-10 integrated design proposal for Water Resources Planning Based Selection Implementation upper periphary of Polgolla reservoir (IWWRMP- 1/CS/QCBS/5) LK-MOMDE-118633-CS- QCBS / Consultancy Service for study and recommendation for back erosion of Rantambe dam spillway tail canal ,LB erosion Component 2: Infrastructure Quality And Cost- Pending / Post Open - International 1,202,448.09 0.00 2020-11-19 2020-12-10 2021-01-23 2021-02-20 2021-03-22 2021-04-26 2021-05-31 2022-05-31 of Victoria dam spillway tail Improvements Based Selection Implementation canal, Back Analysis for Victoria dam and Kotmale Dam grouting gallery inspection (IWWRMP/PP/CONS/31) LK-MOMDE-118622-CS- QCBS / Consultancy Services for Feasibility study on Safety Component 2: Infrastructure Quality And Cost- Pending / Post Open - International 842,696.63 0.00 2020-11-02 2020-11-23 2021-01-06 2021-02-03 2021-03-05 2021-04-09 2021-05-14 2022-05-14 of Senanayaka Samudraya Improvements Based Selection Implementation Headworks (IWWRMP/PP/CONS/33) LK-MOMDE-162975-CS-CQS / Consultancy service for Consultant Component 1: Watershed and Pending Expansion and enhancement / Post Qualification Open - International 561,795.75 0.00 2020-11-02 2020-11-23 2021-02-06 2021-03-08 2021-04-19 2022-04-19 Water Resources Planning Implementation of WMS/MASL bulk water Selection allocation model LK-MOMDE-162977-CS-CQS / Consultancy service for Preparation of Environmental Consultant Social Management Component 2: Infrastructure Pending / Post Qualification Open - National 84,269.00 0.00 2020-08-30 2020-09-20 2020-11-03 2020-12-03 2021-01-07 2021-03-08 Framework and Environmental Improvements Implementation Selection social screening report for rehabilitation of dams & canals NPC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-113221-CS- INDV / Consultancy services for Environmental Social Individual Impact Assessment for Component 2: Infrastructure / Post Consultant Limited 9,090.91 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-03 2019-06-17 2019-06-03 2019-08-16 Rehabilitation of Elahara Improvements Selection scheme, Haththota scheme and Arawatta Tank (IWWRMP/PP/CONS/01) LK-MOMDE-113250-CS- INDV / Consultancy services for Environmental Social Impact Assessment for Individual Component 2: Infrastructure Rehabilitation of Hali Ela / Post Consultant Limited 12,121.21 3,593.15 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-02 2019-06-15 2019-06-03 2019-08-14 Improvements Tank, Akathimuripu Tank, Selection Madiyawa Tank and Waduwala Scheme (IWWRMP/PP/CONS/02) LK-MOMDE-113252-CS- Individual INDV / Consultancy services Component 2: Infrastructure / Post Consultant Limited 6,060.61 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 for Aquatic Survey Improvements Selection (IWWRMP/PP/CONS/03) LK-MOMDE-116871-CS- INDV / Consultancy service for Preparation of Operation manual for river basin planning and management, Individual Component 2: Infrastructure customized to the selected / Post Consultant Limited 24,242.42 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 Improvements river basins (Walawa including Selection the Walawa RB preparation of ESMP, Kalawewa and Mahalindawewa) (IWWRMP/PP/CONS/06) LK-MOMDE-116883-CS- INDV / Consultancy for Individual Preparation of guideline for Component 1: Watershed and / Post Consultant Limited 12,121.21 8,274.72 Signed 2019-08-01 2019-07-01 2019-08-06 2019-05-03 2019-08-27 2019-07-09 2019-10-01 2019-07-15 2020-03-29 Sustainable Watershed Water Resources Planning Selection Management (IWWRMP/PP/CONS/08) LK-MOMDE-116900-CS- INDV / Short-term Individual Component 4: Project assignment for Personal / Post Consultant Limited 3,030.30 0.00 Canceled 2019-05-30 2019-05-08 2019-06-04 2019-06-18 2019-07-09 2020-01-05 Management Assistant Selection (IWWRMP/PP/CONS/17) Page 10 LK-MOMDE-116901-CS- INDV / Consultancy services for Environmental Social Individual Impact Assesment for Component 2: Infrastructure / Post Consultant Limited 12,121.21 2,756.51 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-09 2019-06-07 2019-05-27 2019-06-17 2019-05-30 2019-08-16 Rehabilitation of Improvements Selection Muththuiyankaddu irrigation scheme (IWWRMP/PP/CONS/18) LK-MOMDE-116902-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Rehabilitation of Periyamadu Component 2: Infrastructure Pending / Post Consultant Limited 24,242.42 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2019-12-29 Tank and Kariyalai Improvements Implementation Selection Nagarpaduwan Tank & irrigation scheme and Periyapandivirichchan scheme (IWWRMP/PP/CONS/19) LK-MOMDE-116903-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Rehabilitation of Component 2: Infrastructure Pending / Post Consultant Limited 27,272.73 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 Akkarayankulam irrigation Improvements Implementation Selection scheme, Kudamuruthy Tank and Vannerikulam headworks & irrigation scheme (IWWRMP/PP/CONS/20) LK-MOMDE-116906-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Component 2: Infrastructure Rehabilitation of Dewahuwa / Post Consultant Limited 12,121.21 1,875.18 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-09 2019-05-27 2019-06-19 2019-06-03 2019-08-18 Improvements tank & scheme and Selection Baththalagoda Anicut & scheme (IWWRMP/PP/CONS/22) LK-MOMDE-116907-CS- INDV / Consultancy services for Environmental Social Individual Impact Assessment for Component 2: Infrastructure / Post Consultant Limited 21,212.12 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-04-09 2019-06-07 2019-04-10 2019-06-17 2019-06-03 2019-08-16 Rehabilitation of Huruluwewa Improvements Selection irrigation scheme, Karawita Tank & Ambakolawewa Tank (IWWRMP/PP/CONS/23) LK-MOMDE-116909-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Vahanery Individual Component 2: Infrastructure Dam, Panama Tank, / Post Consultant Limited 24,242.42 14,236.74 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-28 2019-06-11 2019-05-28 2019-06-25 2019-06-03 2019-09-23 Improvements Unnichchai scheme, Selection Nagadeepa Tank, Illukuchenal & Senanayake Samudraya Reservoir (IWWRMP/PP/CONS/24) LK-MOMDE-116910-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Pavatkulam Individual Component 2: Infrastructure Tank, Muhathankulam / Post Consultant Limited 24,242.42 13,898.79 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-11 2019-05-28 2019-06-25 2019-05-30 2019-09-23 Improvements Scheme, Viyadhikulam Selection irrigation scheme, Peramadu Tank & Scheme and Mavilaru Headworks (IWWRMP/PP/CONS/25) LK-MOMDE-116911-CS- INDV / Consultancy service Individual for preparation of Livelihood Component 2: Infrastructure / Post Consultant Limited 18,181.82 0.00 Canceled 2019-07-09 2019-07-14 2019-08-04 2019-09-08 2020-03-06 Support Assistance Plan (LSA) Improvements Selection - Walawa (IWWRMP/PP/CONS/26) LK-MOMDE-116912-CS- INDV / Consultancy services for Environmental Social Individual Component 2: Infrastructure Impact Assesment for / Post Consultant Limited 9,090.91 3,736.75 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-15 2019-06-11 2019-05-24 2019-06-25 2019-06-20 2019-08-24 Improvements Rehabilitation of Kothmale Selection Dam & irrigation scheme (IWWRMP/PP/CONS/27) LK-MOMDE-116914-CS- INDV / Individual Consultancy services to prepare mechanical specification, Individual Component 2: Infrastructure Estimation & Bid documents / Post Consultant Limited 9,090.91 11,032.96 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-28 2019-06-17 2019-06-03 2020-06-16 Improvements for Gantry crane Polgolla, Selection Udawalawe and Gate Automation for Bowatenna (IWWRMP/PP/CONS/28) LK-MOMDE-116896-CS- INDV / Short-term Individual Component 4: Project assignment for Procurement / Post Consultant Limited 3,030.30 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-12-14 Management Assistant Selection (IWWRMP/PP/CONS/16) LK-MOMDE-116904-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Individual Component 2: Infrastructure Piramanthalaru Kulam / Post Consultant Limited 27,272.27 8,299.72 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-24 2019-06-17 2019-05-30 2019-08-16 Improvements irrigation scheme, Selection Kanagambikaikulam irrigation scheme and Kalmadu tank irrigation scheme (IWWRMP/PP/CONS/21) Page 11 LK-MOMDE-121767-CS- INDV / Individual consultancy services for preparation and Individual reviewing the RFP of study & Component 2: Infrastructure / Post Consultant Open 60,000.00 0.00 Canceled 2019-07-28 2019-09-15 2019-10-06 2019-11-10 2020-05-08 recommendation for selected Improvements Selection MASL Dams (Rantambe, Victoria, Kothmale) (IWWRMP/PP/CONS/32) LK-MOMDE-121782-CS- INDV / Consultancy for Individual Preparation of guideline for Component 2: Infrastructure / Post Consultant Limited 12,121.21 0.00 Canceled 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 sustainable Dam safety and Improvements Selection Hydraulic Assert (IWWRMP/PP/CONS/07) LK-MOMDE-138929-CS- INDV / Consultancy services Individual Component 2: Infrastructure for Preparation of TOR for / Post Consultant Limited 8,426.97 0.00 Canceled 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-07-29 Improvements River Basin Management Plan Selection (IWWRMP-2/CS/IC/20) LK-MOMDE-162970-CS- INDV / Consultancy service for Preparation of Environmental Social Management Framework and Individual Component 2: Infrastructure Pending Environmental social / Post Consultant Limited 11,235.96 0.00 2020-08-03 2020-08-08 2020-08-15 2020-08-29 2020-11-27 Improvements Implementation screening report for Selection Rehabilitation of Wadamunai tank & Lunugamwehera Reservoir (IWWRMP- 2/CS/QCBS/15) LK-MOMDE-118665-CS- INDV / Training program on Individual Procurement (Evaluation of Component 4: Project Pending / Post Consultant Limited 6,060.61 0.00 2020-11-15 2020-11-20 2020-12-11 2021-01-15 2021-01-22 Consultancy, Goods and Management Implementation Selection Works) (IWWRMP/PP/CONS/41) LK-MOMDE-184063-CS- INDV / Short-term Individual Component 4: Project assignment for Personal IDA / 66190 Post Consultant Limited 2,500.00 0.00 Under Review 2020-07-15 2020-07-15 2020-07-18 2020-07-15 2020-08-01 2020-09-05 2021-03-04 Management Assistant Selection (IWWRMP/PP/CONS/17) Page 12