Resumen del plan de adquisiciones Procurement Plan 75. INVEST-H developed a procurement plan for project implementation. This plan has been agreed between the grant recipient and the Bank on October 20, 2014. An updated version was received on December 11, 2014 and is part of the Minutes of Negotiations. It will be published at SEPA within 30 days of Grant Effectiveness. The Procurement Plan will be updated annually in agreement with the Bank or as required to reflect the actual implementation needs and improvements in institutional capacity. 76. Frequency of Procurement Supervision: once per year. One out of five subcontracts procured by the operators will be subject to post review by the Bank. PROCUREMENT Honduras : Corredor Seco Food Security Project PLAN General Information Country: Honduras Bank’s Approval Date of the Original Procurement Plan: 2017-07-17 2021-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148737 GPN Date: Project Name: Corredor Seco Food Security Project Loan / Credit No: TF / 17904 Inversión Estratégica de Honduras Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-CSFSP-4-B-#TIT_LPN# / Adquisición de vehículos, tipo Monitoring, evaluation and Solicitud de TF / 17904 Posterior Open - National 77,000.00 53,834.12 Finalizado 2016-05-01 2017-03-01 2016-05-23 2016-06-13 2017-03-28 2016-06-30 2017-05-17 2016-07-18 2017-05-31 2016-08-15 2017-06-07 doble cabina, tracción en las project management ofertas cuatro ruedas (4x4) HN-INVEST-H-57207-GO- RFQ / Adquisición de Monitoring, evaluation and Solicitud de Single Stage - One Mobiliario para las Oficina TF / 17904 Posterior Open - National 1,000.00 804.13 Finalizado 2018-08-03 2018-08-31 2018-08-28 2018-09-20 2018-10-01 project management cotizaciones Envelope ACS-GAFSP (Sillas para la Oficina Central) HN-INVEST-H-57206-GO- RFQ / Adquisición de Equipo y Accesorios de Informática Monitoring, evaluation and Solicitud de Single Stage - One TF / 17904 Posterior Open - National 10,000.00 6,984.76 Firmado 2018-08-03 2018-10-01 2018-09-28 2018-10-31 para el Proyecto ACS-GAFSP project management cotizaciones Envelope (Laptop, accesorios, Tablet para M&E del proyecto) HN-INVEST-H-57198-GO- RFB / Adquisición de un Monitoring, evaluation and Solicitud de Single Stage - One Vehículo Pick Up, Doble TF / 17904 Posterior Open - National 32,000.00 31,595.37 Finalizado 2018-06-18 2018-06-26 2018-06-28 2018-07-26 2018-07-25 2018-08-02 2018-08-06 2018-08-17 2018-08-17 2018-09-16 2018-08-29 project management ofertas Envelope Cabina, tracción en las cuatro ruedas (4x4) HN-INVEST-H-84207-GO- RFQ / Adquisición de Equipo Monitoring, evaluation and Solicitud de Single Stage - One (Tablet) para Monitoreo y TF / 17904 Posterior Open - National 3,000.00 3,361.58 Finalizado 2018-11-16 2018-12-13 2018-12-17 2019-01-11 2019-01-23 project management cotizaciones Envelope Evaluación del Proyecto ACS- PROSASUR. HN-INVEST-H-149504-GO- RFB / Adquisición de un Monitoring, evaluation and Solicitud de Single Stage - One Ejecución Vehículo tipo PickUp, doble TF / 17904 Posterior Open - National 32,000.00 0.00 2020-01-13 2020-01-18 2020-02-17 2020-03-08 2020-03-18 2020-04-17 project management ofertas Envelope pendiente cabina, 4X4 para uso del Proyecto ACS PROSASUR HN-INVEST-H-149508-GO- RFQ / Adquisición Equipo y Monitoring, evaluation and Solicitud de Single Stage - One Ejecución Accesorios de Informática, TF / 17904 Posterior Open - National 9,000.00 0.00 2020-01-25 2020-02-25 2020-04-25 project management cotizaciones Envelope pendiente para uso del Proyecto ACS- PROSASUR. HN-INVEST-H-149509-GO- RFB / Adquisición de Equipo Monitoring, evaluation and Solicitud de Single Stage - One Ejecución TF / 17904 Posterior Open - National 34,000.00 0.00 2020-03-16 2020-03-21 2020-04-20 2020-05-12 2020-05-20 2020-07-04 para Monitoreo y Evaluación project management ofertas Envelope pendiente del Proyecto ACS-PROSASUR NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-INVEST-H-206357-CS- Selección basada CQS / Especialista en Monitoring, evaluation and TF / 17904 Previa en calificaciones Open - National 45,000.00 0.00 Cancelado 2020-11-25 2020-12-03 2020-12-18 2020-12-23 2021-01-17 2022-01-05 Adquisiciones para el Proyecto project management de consultores ACS-PROSASUR INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-CSFSP-9-CI-3CV / Contratación servicios de TF / 17904 Posterior Individual Limited 240,000.00 0.00 Cancelado 2016-06-30 2020-06-30 consultoría: _x000D_ Coordinador Regional HN-CSFSP-16-CI-3CV / Técnico Monitoreo y Monitoring, evaluation and TF / 17904 Posterior Individual Limited 159,700.00 26,774.69 Finalizado 2017-05-23 2018-06-26 2017-06-08 2017-07-10 2021-12-31 2018-07-09 Evaluación en Salud y project management Nutrición Oficina Regional Page 1 HN-INVEST-H-74177-CS- INDV / Técnico en Monitoreo Monitoring, evaluation and TF / 17904 Posterior Individual Open 134,400.00 33,600.00 Firmado 2018-08-17 2018-08-15 2018-10-09 2018-10-22 2018-10-23 2018-10-23 2018-11-19 2018-11-19 2019-11-18 y Evaluación del Proyecto ACS- project management PROSASUR HN-INVEST-H-149523-CS- INDV / Técnico Junior en Monitoring, evaluation and Salvaguarda Social para TF / 17904 Posterior Individual Open 81,800.00 24,000.00 Firmado 2019-12-19 2020-01-06 2020-01-28 2020-03-02 2020-02-03 2020-03-02 2020-02-14 2020-03-09 2021-02-13 project management Oficina Regional del Proyecto ACS-PROSASUR HN-INVEST-H-149533-CS- Monitoring, evaluation and INDV / Asistente Técnico del TF / 17904 Posterior Individual Open 118,000.00 0.00 Cancelado 2019-12-19 2020-01-07 2020-02-03 2020-02-08 2020-02-19 2021-02-18 project management Proyecto ACS-PROSASUR HN-INVEST-H-149536-CS- INDV / Promotor Monitoring, evaluation and Infraestructura Rural para TF / 17904 Posterior Individual Open 60,000.00 0.00 En ejecución 2020-01-27 2021-01-18 2020-03-01 2020-03-06 2020-03-16 2021-03-16 project management Oficina Regional ACS- PROSASUR HN-INVEST-H-149541-CS- Monitoring, evaluation and Ejecución INDV / Consultor Nacional TF / 17904 Posterior Individual Open 10,000.00 0.00 2019-12-19 2020-01-26 2020-01-31 2020-02-06 2020-04-06 project management pendiente M&E- Sistematización HN-INVEST-H-149517-CS- INDV / Técnico en Monitoring, evaluation and Salvaguarda Ambiental para TF / 17904 Posterior Individual Open 81,800.00 24,000.00 Rescindido 2020-01-06 2020-01-10 2020-02-17 2020-03-02 2020-02-23 2020-03-02 2020-03-03 2020-03-09 2021-03-03 project management Oficina Regional del Proyecto ACS-PROSASUR HN-INVEST-H-192996-CS- INDV / Técnico en Monitoring, evaluation and Salvaguarda Ambiental para la TF / 17904 Posterior Individual Open 60,000.00 0.00 En ejecución 2020-09-16 2020-09-16 2020-10-14 2020-10-17 2020-10-23 2021-10-23 project management Oficina Regional de ACS- PROSASUR HN-INVEST-H-197257-CS- Food production and rural Selección directa CDS / Asesor Técnico TF / 17904 Posterior Direct 19,600.00 19,600.00 En ejecución 2020-10-23 2020-10-23 2020-10-23 2020-10-23 2020-11-01 2021-03-01 household income generation de consultores Principal Recursos Hídricos HN-INVEST-H-214665-CS- Monitoring, evaluation and INDV / Asistente Técnico del TF / 17904 Posterior Individual Open 118,000.00 0.00 Bajo Revision 2021-01-25 2021-03-02 2021-02-18 2021-02-23 2021-03-19 2022-03-19 project management Proyecto ACS- PROSASUR. HN-INVEST-H-216013-CS- INDV / Recontratación del Monitoring, evaluation and Ejecución TF / 17904 Posterior Individual Direct 34,200.00 0.00 2021-02-25 2021-03-01 2021-03-22 2021-03-31 2021-06-30 Coordinador General del project management pendiente Proyecto HN-INVEST-H-214651-CS- INDV / Especialista en Monitoring, evaluation and TF / 17904 Previa Individual Open 45,000.00 0.00 Cancelado 2021-01-18 2021-02-12 2021-02-16 2021-02-21 2021-03-17 2022-03-17 Adquisiciones para el Proyecto project management ACS-PROSASUR HN-INVEST-H-245651-CS- INDV / Coordinador General- Re-contratación por Monitoring, evaluation and Ejecución continuidad de servicios TF / 17904 Posterior Individual Direct 68,140.68 0.00 2021-07-26 2021-07-26 2021-07-26 2021-07-26 2022-06-30 project management pendiente Convenio de Donación TF017904(Wilmer Roberto Sánchez Barahona) HN-INVEST-H-245652-CS- INDV / Coordinador Regional- Re-contratación por Monitoring, evaluation and Ejecución continuidad de servicios TF / 17904 Posterior Individual Direct 36,000.00 0.00 2021-07-26 2021-07-26 2021-07-26 2021-07-26 2022-06-30 project management pendiente Convenio de Donación TF017904(Edwin Orlando Rodríguez) HN-INVEST-H-245657-CS- INDV / Técnico M&E con énfasis en Agronegocios-Re- Monitoring, evaluation and Ejecución contratación por continuidad TF / 17904 Posterior Individual Direct 26,400.00 0.00 2021-07-26 2021-07-26 2021-07-26 2021-07-26 2022-06-30 project management pendiente de servicios Convenio de Donación TF017904(Laura María Sosa Rodríguez) HN-INVEST-H-245659-CS- INDV / Coordinador Técnico- Re-contratación por Monitoring, evaluation and Ejecución continuidad de servicios TF / 17904 Posterior Individual Direct 60,000.00 0.00 2021-07-26 2021-07-26 2021-07-26 2021-07-26 2022-06-30 project management pendiente Convenio de Donación TF017904 (Elmer Mauricio Cruz) HN-INVEST-H-245660-CS- INDV / Especialista de Monitoring, evaluation and Ejecución TF / 17904 Previa Individual Limited 42,000.00 0.00 2021-08-04 2021-08-09 2021-08-21 2021-08-29 2022-07-04 Adquisiciones para el Proyecto project management pendiente ACS-PROSASUR (ACS-GAFSP) Page 2