PROCUREMENT PLAN (Textual Part) Project information: Sri Lanka – Water Resources Management Project-P-166865 Project Implementation agency: Ministry of Mahaweli Development and Environment Date of the Procurement Plan: 24 June, 2019 Period covered by this Procurement Plan: 15 March 2020-30 Sep. 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. PROCUREMENT Sri Lanka : Sri Lanka Integrated Watershed and Water Resources Management Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2019-06-28 2021-06-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166865 GPN Date: 2020-07-28 Project Name: Sri Lanka Integrated Watershed and Water Resources Management Project Loan / Credit No: / , IDA / 66190, IDA / 66210 M Executing Agency(ies): inistry of Mahaweli Development and Environment WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LK-MOMDE-117185-CW- Component 4: Project Request for Single Stage - One 2019-11- RFQ / Refurbishment of PMU / Post Limited 45,311.47 38,887.42 Signed 2019-06-26 2019-06-18 2019-08-14 2019-09-04 Management Quotations Envelope 12 office (IWWRMP/PP/WORKS/01) LK-MOMDE-123620-CW-RFB / Improvements to Unnichchai LB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 923,033.71 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 0+000 to stn 13+725 Improvements Envelope 18 (IWWRMP- 2/WORKS/ID/OCBN/04-1) LK-MOMDE-124032-CW-RFB / Improvements to Unnichchai RB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 906,741.57 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 0+000 to stn 4+950 ( Improvements Envelope 01 IWWRMP- 2/WORKS/ID/OCBN/04-2 ) LK-MOMDE-124217-CW-RFB / Improvements to Unnichchai RB main channel from stn Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 887,640.45 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 4+950 to stn 10+000 ( Improvements Envelope 01 IWWRMP- 2/WORKS/ID/OCBN/04-3 ) LK-MOMDE-124409-CW-RFB / Rehabilititation of Panama Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 342,696.63 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Tank ( IWWRMP- Improvements Envelope 05 2/WORKS/ID/OCBN/07 ) LK-MOMDE-124659-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-03- Peramaduwa Scheme ( / Post Request for Bids Open - National 898,876.40 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Improvements Envelope 29 IWWRMP- 2/WORKS/ID/OCBN/17 ) LK-MOMDE-124666-CW-RFB / Improvements Viyadikulam Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 950,185.39 0.00 Canceled 2019-12-20 2020-01-03 2020-01-24 2020-02-23 2020-03-29 Spill ( IWWRMP- Improvements Envelope 29 2/WORKS/ID/OCBN/18-2 ) LK-MOMDE-124667-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-05- / Post Request for Bids Open - National 325,505.62 0.00 Canceled 2020-01-24 2020-02-07 2020-02-28 2020-03-29 2020-05-03 Abakolawewa Tank ( IWWRMP- Improvements Envelope 03 2/WORKS/ID/OCBN/19 ) LK-MOMDE-124683-CW-RFB / Rehabilititation of Karawita Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2019-11-25 2019-12-09 2019-12-30 2020-01-29 2020-03-04 tank ( IWWRMP- Improvements Envelope 04 2/WORKS/ID/OCBN/20 ) LK-MOMDE-125489-CW-RFB / Rehabilititation of Madiyawa Component 2: Infrastructure Single Stage - One 2021-04- / Post Request for Bids Open - National 464,775.28 0.00 Canceled 2019-12-23 2020-01-06 2020-01-27 2020-02-26 2020-04-01 Tank ( IWWRMP- Improvements Envelope 01 2/WORKS/ID/OCBN/23 ) LK-MOMDE-125508-CW-RFB / Rehabilititation of Component 2: Infrastructure Single Stage - One 2021-04- / Post Request for Bids Open - National 280,898.88 0.00 Canceled 2019-12-27 2020-01-10 2020-01-31 2020-03-01 2020-04-05 Mannankatiya Tank ( IWWRMP- Improvements Envelope 05 2/WORKS/ID/OCBN/27 ) LK-MOMDE-125511-CW-RFB / Rehabilititation of Main Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kimbulawana Oya / Post Request for Bids Open - National 347,780.90 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Improvements Envelope 18 Scheme (LBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-1 ) LK-MOMDE-125513-CW-RFB / Rehabilititation of Main Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kimbulawana Oya / Post Request for Bids Open - National 262,859.69 0.00 Canceled 2019-12-09 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Improvements Envelope 05 Scheme (RBMC) ( IWWRMP- 2/WORKS/ID/OCBN/28-2) LK-MOMDE-125515-CW-RFB / Rehabilititation of Maha Component 2: Infrastructure Single Stage - One 2021-03- / Post Request for Bids Open - National 896,067.42 0.00 Canceled 2019-12-09 2019-12-23 2020-01-13 2020-02-12 2020-03-18 Andara Wewa ( IWWRMP- Improvements Envelope 18 2/WORKS/ID/OCBN/29 ) LK-MOMDE-125834-CW-RFB / Improvement of Spillway Tail Component 2: Infrastructure Single Stage - One 2021-03- Canal of Kotmale Dam ( / Post Request for Bids Open - National 369,101.12 0.00 Canceled 2019-11-26 2019-12-10 2019-12-31 2020-01-30 2020-03-05 Improvements Envelope 05 IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-125839-CW-RFB / Repairs to gates of irrigation Component 2: Infrastructure Single Stage - One 2021-09- structures in Kalawewa Left / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2019-12-06 2019-12-20 2020-01-10 2020-02-09 2020-03-15 Improvements Envelope 16 Bank main canal (IWWRMP- 2/WORKS/MASL//OCBN/105) Page 1 LK-MOMDE-125846-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2020-11- Muthuiyankaddu Division - / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2019-11-15 2019-11-29 2019-12-20 2020-01-19 2020-02-23 Improvements Envelope 19 Package 01 (RB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-1 ) LK-MOMDE-125994-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Muthuiyankaddu Division - Improvements Envelope 20 (LB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-6 ) LK-MOMDE-125995-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-02- / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 Muthuiyankaddu Division - Improvements Envelope 18 (LB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-7 ) LK-MOMDE-126158-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Muthuiyankaddu Division - Improvements Envelope 25 (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) LK-MOMDE-126330-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2021-04- Muthuiyankaddu Division - / Post Request for Bids Open - National 674,157.30 0.00 Canceled 2020-04-17 2020-05-01 2020-05-22 2020-06-21 2020-07-26 Improvements Envelope 22 (RB/Track 04) ( IWWRMP- 2/WORKS/NPC/OCBN/200-10 ) LK-MOMDE-126332-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2021-05- Muthuiyankaddu Division - / Post Request for Bids Open - National 561,797.75 0.00 Canceled 2020-05-17 2020-05-31 2020-06-21 2020-07-21 2020-08-25 Improvements Envelope 22 (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200- 11) LK-MOMDE-126333-CW-RFB / Reconstruction of Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2021-05- Muthuiyankaddu Division - / Post Request for Bids Open - National 146,067.42 0.00 Canceled 2020-05-15 2020-05-29 2020-06-19 2020-07-19 2020-08-23 Improvements Envelope 20 (RB/Track 08) (IWWRMP- 2/WORKS/NPC/OCBN/200- 12) LK-MOMDE-126337-CW-RFB / Improvements of Muthuiyankaddu RB Main Component 2: Infrastructure Single Stage - One 2021-05- Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-05-20 2020-06-03 2020-06-24 2020-07-24 2020-08-28 Improvements Envelope 25 Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-13 ) LK-MOMDE-126338-CW-RFB / Improvements of Muthuiyankaddu LB Main Component 2: Infrastructure Single Stage - One 2021-07- Canal - Muthuiyankaddu / Post Request for Bids Open - National 84,269.66 0.00 Canceled 2020-07-20 2020-08-03 2020-08-24 2020-09-23 2020-10-28 Improvements Envelope 25 Division ( IWWRMP- 2/WORKS/NPC/OCBN/200-14 ) LK-MOMDE-126345-CW-RFB / Rehabilitation of Kalmadu Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 1,404,494.38 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 Scheme Headworks ( IWWRMP- Improvements Envelope 22 2/WORKS/NPC/OCBN/201-1 ) LK-MOMDE-126347-CW-RFB / Rehabilitation of channel to kandawalai under RB cannel Component 2: Infrastructure Single Stage - One 2022-08- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2021-08-23 2021-09-06 2021-09-27 2021-10-27 2021-12-01 under Kalmadu Scheme ( Improvements Envelope 28 IWWRMP- 2/WORKS/NPC/OCBN/201-2 ) LK-MOMDE-126353-CW-RFB / Rehabilitation of channel to Puliyampokkanai under RB Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 cannel under Kalmadu Improvements Envelope 25 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-3 ) LK-MOMDE-126367-CW-RFB / Improvements of Spill & Component 2: Infrastructure Single Stage - One 2021-10- spilltail under Kalmadu / Post Request for Bids Open - National 337,078.65 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-5 ) LK-MOMDE-126371-CW-RFB / Rehabilitation of akkarayan kulam channel to Component 2: Infrastructure Single Stage - One 2021-02- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-02-14 2020-02-28 2020-03-20 2020-04-19 2020-05-24 kannagipuram under LB Improvements Envelope 18 cannel ( IWWRMP- 2/WORKS/NPC/OCBN/202-1 ) LK-MOMDE-126376-CW-RFB / Rehabilitation of akkarayan kulam channel to Akkarayan Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 under LB cannel & lift Improvements Envelope 21 irrigation ( IWWRMP- 2/WORKS/NPC/OCBN/202-2 ) LK-MOMDE-126378-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 kulam RB cannel ( IWWRMP- Improvements Envelope 03 2/WORKS/NPC/OCBN/202-3 ) Page 2 LK-MOMDE-126387-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2021-10- kulam spill & spilltail channel ( / Post Request for Bids Open - National 449,438.20 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 IWWRMP- 2/WORKS/NPC/OCBN/202-5 ) LK-MOMDE-126390-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One 2021-10- under Piramanthalaru Scheme / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Improvements Envelope 03 ( IWWRMP- 2/WORKS/NPC/OCBN/203-1 ) LK-MOMDE-126391-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-18 2019-12-02 2019-12-23 2020-01-22 2020-02-26 Piramanthalaru Irrigation Improvements Envelope 22 Scheme (phase 01) (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-126392-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2021-09- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2020-09-21 2020-10-05 2020-10-26 2020-11-25 2020-12-30 Piramanthalaru Irrigation Improvements Envelope 26 Scheme (phase 02) ( IWWRMP- 2/WORKS/NPC/OCBN/203-3 ) LK-MOMDE-126396-CW-RFB / Rehabilitation of Headworks Component 2: Infrastructure Single Stage - One 2021-10- under Kanagambikai Irrigation / Post Request for Bids Open - National 196,629.21 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 Improvements Envelope 21 Scheme (IWWRMP- 2/WORKS/NPC/OCBN/204-1) LK-MOMDE-126400-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Kanagambikai Scheme ( Improvements Envelope 26 IWWRMP- 2/WORKS/NPC/OCBN/204-2 ) LK-MOMDE-126410-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2020-12- of Kudamuruddy Tank ( / Post Request for Bids Open - National 421,348.31 0.00 Canceled 2019-12-19 2020-01-02 2020-01-23 2020-02-22 2020-03-28 Improvements Envelope 23 IWWRMP- 2/WORKS/NPC/OCBN/206-1) LK-MOMDE-126412-CW-RFB / Rehabilitation of Downstream under Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 Kudamuruddy Tank Irrigation Improvements Envelope 03 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/206-2) LK-MOMDE-126413-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2020-12- of Kariyalai Nagapaduwan / Post Request for Bids Open - National 1,123,595.51 0.00 Canceled 2019-12-16 2019-12-30 2020-01-20 2020-02-19 2020-03-25 Improvements Envelope 20 Tank ( IWWRMP- 2/WORKS/NPC/OCBN/207-1 ) LK-MOMDE-126416-CW-RFB / Rehabilitation of LB cannel Component 2: Infrastructure Single Stage - One 2021-10- under Kariyalai Nagapaduwan / Post Request for Bids Open - National 365,168.54 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements Envelope 25 Tank (IWWRMP- 2/WORKS/NPC/OCBN/207-2) LK-MOMDE-126417-CW-RFB / Rehabilitation of RB cannel Component 2: Infrastructure Single Stage - One 2021-10- under Kariyalai Nagapaduwan / Post Request for Bids Open - National 308,988.76 0.00 Canceled 2020-10-20 2020-11-03 2020-11-24 2020-12-24 2021-01-28 Improvements Envelope 25 Tank ( IWWRMP- 2/WORKS/NPC/OCBN/207-3 ) LK-MOMDE-126418-CW-RFB / Rehabilitation of Downstream under Vaneri Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-09-28 2020-10-12 2020-11-02 2020-12-02 2021-01-06 kulam Irrigation Scheme ( Improvements Envelope 03 IWWRMP- 2/WORKS/NPC/OCBN/208-1 ) LK-MOMDE-126420-CW-RFB / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2021-10- / Post Request for Bids Open - National 224,719.10 0.00 Canceled 2020-10-16 2020-10-30 2020-11-20 2020-12-20 2021-01-24 of Vaneri kulam ( IWWRMP- Improvements Envelope 21 2/WORKS/NPC/OCBN/208-2 ) LK-MOMDE-126422-CW-RFB / Rehabilitation of Dowstream infrastructure in Component 2: Infrastructure Single Stage - One 2020-11- / Post Request for Bids Open - National 112,359.55 0.00 Canceled 2019-11-22 2019-12-06 2019-12-27 2020-01-26 2020-03-01 Periyapandivirichan Kulam ( Improvements Envelope 26 IWWRMP- 2/WORKS/NPC/OCBN/209 ) LK-MOMDE-126382-CW-RFB / Rehabilitation of akkarayan Component 2: Infrastructure Single Stage - One 2022-07- / Post Request for Bids Open - National 842,696.63 0.00 Canceled 2021-07-16 2021-07-30 2021-08-20 2021-09-19 2021-10-24 kulam Headworks ( IWWRMP- Improvements Envelope 21 2/WORKS/NPC/OCBN/202-4 ) LK-MOMDE-163016-CW-RFB / Reconstruction of Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2022-02- / Post Request for Bids Open - National 589,887.64 0.00 Canceled 2021-02-16 2021-03-02 2021-03-23 2021-04-22 2021-05-27 Muthuiyankaddu Division - Improvements Envelope 21 (LB/Track 01) (IWWRMP- 2/WORKS/NPC/OCBN/200-9) LK-MOMDE-126361-CW-RFB / Rehabilitation of channel to kalmadu nagar under LB Component 2: Infrastructure Single Stage - One 2022-01- / Post Request for Bids Open - National 393,258.43 0.00 Canceled 2021-01-10 2021-01-24 2021-02-14 2021-03-16 2021-04-20 cannel under Kalmadu Improvements Envelope 15 Scheme ( IWWRMP- 2/WORKS/NPC/OCBN/201-4 ) LK-MOMDE-163051-CW-RFB / Rehablitation of tank Bund Pending (0.8km) including Rip Rap, Component 2: Infrastructure Single Stage - One 2024-03- IDA / 66210 Post Request for Bids Open - National 505,617.98 0.00 Implementat 2021-05-11 2021-12-07 2022-01-04 2022-02-03 2022-03-10 Spill and both sluice to Improvements Envelope 09 ion Meiyankal Tank (IWWRMP- 2/WORKS/EPC/OCBN/300) Page 3 LK-MOMDE-163052-CW-RFB / Rehabilitation of channels of Chadayanthalawa anicut, Kadukkayan anicut, Pending Component 2: Infrastructure Single Stage - One 2024-03- Neendakari anicut, and IDA / 66210 Post Request for Bids Open - National 226,320.22 0.00 Implementat 2021-05-17 2021-12-13 2022-01-10 2022-02-09 2022-03-16 Improvements Envelope 15 Weeramunai anicut in ion Chadayanthalawa Scheme (IWWRMP- 2/WORKS/EPC/OCBN/301) LK-MOMDE-163053-CW-RFB / Rehabilitation of Saliyapura Pending Component 2: Infrastructure Single Stage - One 2023-09- anicut of Paravipanchan IDA / 66210 Post Request for Bids Open - National 121,629.21 0.00 Implementat 2021-05-19 2021-12-15 2022-01-12 2022-02-11 2022-03-18 Improvements Envelope 09 scheme (IWWRMP- ion 2/WORKS/EPC/OCBN/302) LK-MOMDE-163054-CW-RFB / Improvements to canal Pending System (18km) inculuding Component 2: Infrastructure Single Stage - One 2024-03- IDA / 66210 Post Request for Bids Open - National 561,797.75 0.00 Implementat 2021-05-20 2021-12-16 2022-01-13 2022-02-12 2022-03-19 structures of Puluganawai- Improvements Envelope 18 ion Kankaniyar scheme (IWWRMP- 2/WORKS/EPC/OCBN/303) LK-MOMDE-163055-CW-RFB / Improvements of tank bund(1.5km), including Rip Pending Component 2: Infrastructure Single Stage - One 2024-03- Rap and Sluice Structure to IDA / 66210 Post Request for Bids Open - National 168,539.33 0.00 Implementat 2021-05-03 2021-11-29 2021-12-27 2022-01-26 2022-03-02 Improvements Envelope 01 Puluganawai-Kankaniyar ion scheme (IWWRMP- 2/WORKS/EPC/OCBN/305) LK-MOMDE-224661-CW-RFB / Rehabilitation of Pending Muththuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-07- IDA / 66210 Post Request for Bids Open - National 365,168.54 0.00 Implementat 2021-03-15 2021-07-13 2021-08-10 2021-09-09 2021-10-14 Muththuiyankaddu Division - Improvements Envelope 11 ion (RB/Track 03) (IWWRMP- 2/WORKS/NPC/OCBN/200-1) LK-MOMDE-125851-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-07- IDA / 66210 Post Request for Bids Open - National 325,842.70 0.00 Implementat 2019-11-15 2021-07-08 2021-08-05 2021-09-04 2021-10-09 Muthuiyankaddu Division - Improvements Envelope 06 ion (RB/Track 07) ( IWWRMP- 2/WORKS/NPC/OCBN/200-2 ) LK-MOMDE-125854-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National 617,977.53 0.00 Implementat 2019-11-15 2021-08-12 2021-09-09 2021-10-09 2021-11-13 Muthuiyankaddu Division - Improvements Envelope 13 ion (RB/Track 05) ( IWWRMP- 2/WORKS/NPC/OCBN/200-3 ) LK-MOMDE-125855-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2023-05- IDA / 66210 Post Request for Bids Open - National 634,831.46 0.00 Implementat 2020-01-20 2021-08-11 2021-09-08 2021-10-08 2021-11-12 Muthuiyankaddu Division - Improvements Envelope 06 ion (RB/Track 01) ( IWWRMP- 2/WORKS/NPC/OCBN/200-4) LK-MOMDE-125856-CW-RFB / Rehabilitation of Pending Muthuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 831,460.67 0.00 Implementat 2020-01-20 2021-08-19 2021-09-16 2021-10-16 2021-11-20 Muthuiyankaddu Division - Improvements Envelope 17 ion (RB/Track 02) ( IWWRMP- 2/WORKS/NPC/OCBN/200-5) LK-MOMDE-126155-CW-RFB / Rehabilitation of Pending Muththuiyankaddu RB Canal - Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 464,831.46 0.00 Implementat 2021-03-15 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Muththuiyankaddu Division - Improvements Envelope 14 ion (RB/Track 06) (IWWRMP- 2/WORKS/NPC/OCBN/200-6) LK-MOMDE-163023-CW-RFB / Rehabilitation of Pending Muthuiyankaddu LB Canal - Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 589,887.64 0.00 Implementat 2021-06-16 2021-12-13 2022-01-10 2022-02-09 2022-03-16 Muthuiyankaddu Division - Improvements Envelope 11 ion (LB/Track 03) ( IWWRMP- 2/WORKS/NPC/OCBN/200-7) LK-MOMDE-163045-CW-RFB Pending / Rehabilitation of Kalmadu Component 2: Infrastructure Single Stage - One 2023-11- IDA / 66210 Post Request for Bids Open - National 1,619,101.12 0.00 Implementat 2020-11-18 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Scheme Headworks (IWWRMP- Improvements Envelope 17 ion 2/WORKS/NPC/OCBN/201-1) LK-MOMDE-163041-CW-RFB / Improvements of Spill & spill Pending Component 2: Infrastructure Single Stage - One 2022-11- tail under Kalmadu Scheme ( IDA / 66210 Post Request for Bids Open - National 291,011.24 0.00 Implementat 2020-11-16 2021-08-13 2021-09-10 2021-10-10 2021-11-14 Improvements Envelope 14 IWWRMP- ion 2/WORKS/NPC/OCBN/201-2 ) LK-MOMDE-163038-CW-RFB / Rehabilitation of Pending Downstream under Component 2: Infrastructure Single Stage - One 2022-08- IDA / 66210 Post Request for Bids Open - National 139,213.48 0.00 Implementat 2020-11-18 2021-08-16 2021-09-13 2021-10-13 2021-11-17 Piramanthalaru Irrigation Improvements Envelope 14 ion Scheme (phase 01) (IWWRMP- 2/WORKS/NPC/OCBN/203-2) LK-MOMDE-126401-CW-RFB Pending / Rehabilitation of Head works Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 1,500,000.00 0.00 Implementat 2021-07-01 2021-12-28 2022-01-25 2022-02-24 2022-03-31 in Periyamdu Tank ( IWWRMP- Improvements Envelope 31 ion 2/WORKS/NPC/OCBN/205 ) LK-MOMDE-163044-CW-RFB / Rehabilitation of Head works Pending Component 2: Infrastructure Single Stage - One 2023-04- of Kudamuruddy Tank ( IDA / 66210 Post Request for Bids Open - National 510,000.00 0.00 Implementat 2021-08-13 2022-01-10 2022-02-07 2022-03-09 2022-04-13 Improvements Envelope 13 IWWRMP- ion 2/WORKS/NPC/OCBN/206) LK-MOMDE-163059-CW-RFB / Rehabilitation of Head works Pending and Downstream Component 2: Infrastructure Single Stage - One 2023-05- IDA / 66210 Post Request for Bids Open - National 510,000.00 0.00 Implementat 2021-09-13 2022-02-10 2022-03-10 2022-04-09 2022-05-14 infrastructure of Kariyalai Improvements Envelope 15 ion Nagapaduwan Tank (IWWRMP- 2/WORKS/NPC/OCBN/207) Page 4 LK-MOMDE-163031-CW-RFB / Improvement of Spillway Tail Pending Canal and removing rock Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2020-06-29 2021-12-01 2021-12-29 2022-01-28 2022-03-04 boulders in Kotmale Dam ( Improvements Envelope 04 ion IWWRMP- 2/WORKS/MASL/OCBN/101 ) LK-MOMDE-163066-CW-RFB / Immediate improvement of Pending upper phephary of Polgolla Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 786,516.85 0.00 Implementat 2021-10-04 2021-11-08 2021-12-06 2022-01-05 2022-02-09 Dam - Phase I (IWWRMP- Improvements Envelope 09 ion 2/WORKS/MASL/OCBN/106- 1) LK-MOMDE-124090-CW-RFB / Improvements to Main Canal Pending Component 2: Infrastructure Single Stage - One 2023-06- (LB) of Huruluwewa Scheme ( IDA / 66210 Post Request for Bids Open - National 647,022.47 0.00 Implementat 2021-03-16 2021-09-27 2021-10-25 2021-11-24 2021-12-29 Improvements Envelope 22 IWWRMP- ion 2/WORKS/ID/OCBN/04-1) LK-MOMDE-124402-CW-RFB / Improvements to Pending Component 2: Infrastructure Single Stage - One 2023-06- Huruluwewa Main Canal (RB) IDA / 66210 Post Request for Bids Open - National 687,359.55 0.00 Implementat 2021-03-16 2021-09-27 2021-10-25 2021-11-24 2021-12-29 Improvements Envelope 22 (IWWRMP- ion 2/WORKS/ID/OCBN/04-2) LK-MOMDE-124408-CW-RFB / Improvements to (22 km) Pending Component 2: Infrastructure Single Stage - One 2023-07- Branch canal and structures of IDA / 66210 Post Request for Bids Open - National 815,235.96 0.00 Implementat 2021-03-16 2021-10-12 2021-11-09 2021-12-09 2022-01-13 Improvements Envelope 07 Illukuchenal Unit ( IWWRMP- ion 2/WORKS/ID/OCBN/05 ) LK-MOMDE-124412-CW-RFB / Rehabilitation of tank bund Pending (1.5 km) including Rip Rap Component 2: Infrastructure Single Stage - One 2024-01- IDA / 66210 Post Request for Bids Open - National 337,640.45 0.00 Implementat 2019-12-02 2021-10-04 2021-11-01 2021-12-01 2022-01-05 and sluice of Mahalindawewa Improvements Envelope 05 ion Tank ( IWWRMP- 2/WORKS/ID/OCBN/06) LK-MOMDE-124592-CW-RFB Pending / Rehabilititation of Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 369,932.58 0.00 Implementat 2019-12-16 2022-01-10 2022-02-07 2022-03-09 2022-04-13 Wadamunai Tank ( IWWRMP- Improvements Envelope 13 ion 2/WORKS/ID/OCBN/08 ) LK-MOMDE-124593-CW-RFB / Rehabilitation of Vahanery Pending Component 2: Infrastructure Single Stage - One 2023-04- Tank bund from Stn 0+000 to IDA / 66210 Post Request for Bids Open - National 551,604.19 0.00 Implementat 2019-12-16 2022-01-11 2022-02-08 2022-03-10 2022-04-14 Improvements Envelope 14 Stn 2+100 ( IWWRMP- ion 2/WORKS/ID/OCBN/09-1 ) LK-MOMDE-124671-CW-RFB / Improvements of Access Pending road of Vahanery tank form Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 775,000.00 0.00 Implementat 2019-12-27 2022-01-11 2022-02-08 2022-03-10 2022-04-14 Stn 0+000 to 7+683 Improvements Envelope 14 ion (Santhiyar road) ( IWWRMP- 2/WORKS/ID/OCBN/09-2 ) LK-MOMDE-124594-CW-RFB Pending / Rehabilitation of HaliEla Component 2: Infrastructure Single Stage - One 2022-12- IDA / 66210 Post Request for Bids Open - National 422,191.01 0.00 Implementat 2019-12-16 2021-09-09 2021-10-07 2021-11-06 2021-12-11 Tank ( IWWRMP- Improvements Envelope 11 ion 2/WORKS/ID/OCBN/10) LK-MOMDE-124595-CW-RFB Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National 1,216,044.94 0.00 Implementat 2019-12-02 2021-08-23 2021-09-20 2021-10-20 2021-11-24 Akathimurippu Tank ( Improvements Envelope 24 ion IWWRMP- 2/WORKS/ID/OCBN/11) LK-MOMDE-124596-CW-RFB Pending / Rehabilitation of Pavatkulam Component 2: Infrastructure Single Stage - One 2022-10- IDA / 66210 Post Request for Bids Open - National 874,719.10 0.00 Implementat 2019-12-02 2021-07-30 2021-08-27 2021-09-26 2021-10-31 Tank ( IWWRMP- Improvements Envelope 31 ion 2/WORKS/ID/OCBN/12 ) LK-MOMDE-124642-CW-RFB Pending / Improvements to Mavilaru Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 522,646.07 0.00 Implementat 2020-02-03 2021-11-24 2021-12-22 2022-01-21 2022-02-25 Headworks (LB) ( IWWRMP- Improvements Envelope 25 ion 2/WORKS/ID/OCBN/13-1) LK-MOMDE-124649-CW-RFB Pending / Improvements to Mavilaru Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 412,247.19 0.00 Implementat 2020-02-06 2021-12-01 2021-12-29 2022-01-28 2022-03-04 Headworks (RB) ( IWWRMP- Improvements Envelope 04 ion 2/WORKS/ID/OCBN/13-2 ) LK-MOMDE-124655-CW-RFB Pending / Rehabilitation of Peramadu Component 2: Infrastructure Single Stage - One 2023-03- IDA / 66210 Post Request for Bids Open - National 595,505.62 0.00 Implementat 2021-03-22 2021-12-22 2022-01-19 2022-02-18 2022-03-25 Tank ( IWWRMP- Improvements Envelope 25 ion 2/WORKS/ID/OCBN/14) LK-MOMDE-124660-CW-RFB / Improvements to RB Main Pending canal from 0+000Km to Component 2: Infrastructure Single Stage - One 2023-02- IDA / 66210 Post Request for Bids Open - National 676,471.91 0.00 Implementat 2019-12-20 2021-11-22 2021-12-20 2022-01-19 2022-02-23 1+465Km of Viyadikulam Improvements Envelope 23 ion Scheme ( IWWRMP- 2/WORKS/ID/OCBN/15) LK-MOMDE-125494-CW-RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One 2022-12- Muhathankulam Scheme ( IDA / 66210 Post Request for Bids Open - National 629,213.48 0.00 Implementat 2019-12-23 2021-09-06 2021-10-04 2021-11-03 2021-12-08 Improvements Envelope 08 IWWRMP- ion 2/WORKS/ID/OCBN/17) LK-MOMDE-125506-CW-RFB / Rehabilitation of Pending Component 2: Infrastructure Single Stage - One 2022-10- Waduwawala Scheme ( IDA / 66210 Post Request for Bids Open - National 352,808.99 0.00 Implementat 2019-12-27 2021-07-20 2021-08-17 2021-09-16 2021-10-21 Improvements Envelope 21 IWWRMP- ion 2/WORKS/ID/OCBN/19 ) LK-MOMDE-225762-CW-RFB Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One 2023-04- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2021-07-28 2021-12-30 2022-01-27 2022-02-26 2022-04-02 Maruthankulam (IWWRMP- Improvements Envelope 03 ion 2/WORKS/NPC/OCBN/209) Page 5 LK-MOMDE-228195-CW-RFB Pending / Rehabilitation on Akkarayan Component 2: Infrastructure Single Stage - One 2023-10- IDA / 66210 Post Request for Bids Open - National 842,696.63 0.00 Implementat 2021-07-16 2022-01-12 2022-02-09 2022-03-11 2022-04-15 kulam Headworks (IWWRMP- Improvements Envelope 07 ion 2/WORKS/NPC/OCBN/202 LK-MOMDE-125529-CW-RFB / Improvements to Walawa RB Request for Bids - Under 41 km Main Canal from Component 2: Infrastructure Single Stage - One Works (without 2024-01- IDA / 66210 Post Request for Bids Open - National 2,302,251.70 0.00 Implementat 2019-11-22 2020-01-21 2021-05-03 2021-06-27 2021-05-31 2021-06-30 2021-08-04 0+000 km to 17+400 km ( Improvements Envelope prequalification) 31 ion IWWRMP- SPD 2/WORKS/MASL/OCBN/100- 1) LK-MOMDE-125831-CW-RFB / Improvements to Walawa RB 41 km Main Canal from Request for Bids - Under 23+400 km to 33+420 km Component 2: Infrastructure Single Stage - One Works (without 2024-03- IDA / 66210 Post Request for Bids Open - National 2,444,167.62 0.00 Implementat 2019-11-22 2019-12-20 2021-06-02 2021-06-27 2021-06-30 2021-07-30 2021-09-03 and 34+640km to 40+910 Improvements Envelope prequalification) 01 ion km ( IWWRMP- SPD 2/WORKS/MASL/OCBN/100-2 ) LK-MOMDE-125832-CW-RFB / Hydro Mechanical works of Request for Bids - Under Walawa RB Main Canal ( Component 2: Infrastructure Single Stage - One Works (without 2023-03- IDA / 66210 Post Request for Bids Open - National 332,261.49 0.00 Implementat 2019-11-29 2019-12-20 2021-06-09 2021-06-27 2021-07-07 2021-08-06 2021-09-10 IWWRMP- Improvements Envelope prequalification) 24 ion 2/WORKS/MASL/OCBN/100-3 SPD ) LK-MOMDE-125833-CW-RFB / Ecological Improvements Request for Bids - and Marking Reservation Under Component 2: Infrastructure Single Stage - One Works (without 2023-03- along Walawa RB Main Canal ( IDA / 66210 Post Request for Bids Open - National 422,232.84 0.00 Implementat 2019-11-29 2019-12-17 2021-06-09 2021-06-27 2021-07-07 2021-08-06 2021-09-10 Improvements Envelope prequalification) 24 IWWRMP- ion SPD 2/WORKS/MASL/OCBN/100-4 ) LK-MOMDE-125835-CW-RFB / Installation of Automated National Geodetic Survey Systems in Procurement Component 2: Infrastructure Single Stage - Two 2022-11- Kotmale & Randenigala Dams IDA / 66210 Prior Request for Bids Open - National Document - 2 1,623,595.51 0.00 Canceled 2019-11-19 2021-07-09 2021-08-06 2021-11-23 Improvements Envelope 23 for Dam Movement Envelope process Monitoring ( IWWRMP- (Non Bank-SPD) 2/WORKS/MASL//OCBN/102 ) LK-MOMDE-125836-CW-RFB National / Supply and Installation of Procurement Component 2: Infrastructure Single Stage - Two 2022-12- Gantry Crane for Polgolla IDA / 66210 Prior Request for Bids Open - National Document - 2 2,000,000.00 0.00 Canceled 2019-12-03 2021-07-23 2021-08-20 2021-12-07 Improvements Envelope 07 Barrage ( IWWRMP- Envelope process 2/WORKS/MASL//OCBN/103 ) (Non Bank-SPD) LK-MOMDE-125838-CW-RFB National / Supply and Installation of Procurement Component 2: Infrastructure Single Stage - Two 2022-11- Gantry Crane for Udawalawe IDA / 66210 Prior Request for Bids Open - National Document - 2 1,185,393.26 0.00 Canceled 2019-12-03 2021-07-12 2021-08-09 2021-11-26 Improvements Envelope 26 Dam ( IWWRMP- Envelope process 2/WORKS/MASL//OCBN/104 ) (Non Bank-SPD) LK-MOMDE-163036-CW-RFB National / Repairs to gates of irrigation Procurement Pending Component 2: Infrastructure Single Stage - One 2023-04- structures in Kalawewa Left IDA / 66210 Post Request for Bids Open - National Document - 1 449,438.20 0.00 Implementat 2020-07-06 2021-07-16 2021-08-13 2021-09-12 2021-10-17 Improvements Envelope 20 Bank main canal (IWWRMP- Envelope process ion 2/WORKS/MASL//OCBN/105) (Non Bank-SPD) LK-MOMDE-163026-CW-RFB National / Rehabilitation of Headworks Procurement Pending Component 2: Infrastructure Single Stage - One 2022-10- under Piramanthalaru Scheme IDA / 66210 Post Request for Bids Open - National Document - 1 327,865.17 0.00 Implementat 2020-08-31 2021-07-13 2021-08-10 2021-09-09 2021-10-14 Improvements Envelope 14 (IWWRMP- Envelope process ion 2/WORKS/NPC/OCBN/203-1) (Non Bank-SPD) LK-MOMDE-163046-CW-RFB National / Rehabilitation of Procurement Pending Downstream under Component 2: Infrastructure Single Stage - One 2022-10- IDA / 66210 Post Request for Bids Open - National Document - 1 224,719.10 0.00 Implementat 2020-09-21 2021-07-19 2021-08-16 2021-09-15 2021-10-20 Kanagambikai Scheme Improvements Envelope 20 Envelope process ion (IWWRMP- (Non Bank-SPD) 2/WORKS/NPC/OCBN/204) LK-MOMDE-125488-CW-RFB Request for Bids - / Rehabilitation of Haththota Pending Component 2: Infrastructure Single Stage - One Works (without 2023-03- Anicut Scheme (1st to 5th Km IDA / 66210 Post Request for Bids Open - National 341,337.08 0.00 Implementat 2019-12-23 2021-12-03 2021-12-31 2022-01-30 2022-03-06 Improvements Envelope prequalification) 06 canal) ( IWWRMP- ion SPD 2/WORKS/ID/OCBN/16-1) LK-MOMDE-234772-CW-RFB Request for Bids - / Rehabilititation of Haththota Pending Component 2: Infrastructure Single Stage - One Works (without 2023-01- Anicut Scheme (6th to 10th IDA / 66210 Post Request for Bids Open - National 314,971.91 0.00 Implementat 2021-07-01 2021-10-28 2021-11-25 2021-12-25 2022-01-29 Improvements Envelope prequalification) 29 Km canal) (IWWRMP- ion SPD 2/WORKS/ID/OCBN/16-2) LK-MOMDE-163064-CW-RFB Request for Bids - Pending / Rehabilitation of Component 2: Infrastructure Single Stage - One Works (without 2022-12- IDA / 66210 Post Request for Bids Open - National 840,000.00 0.00 Implementat 2021-07-21 2021-09-01 2021-09-29 2021-10-29 2021-12-03 Nithakaikulam (IWWRMP- Improvements Envelope prequalification) 03 ion 2/WORKS/NPC/OCBN/208) SPD LK-MOMDE-241092-CW-RFB National / Supply installation of Gantry Procurement Pending Component 2: Infrastructure Single Stage - Two 2022-11- Crane mechanism for Polgolla IDA / 66210 Post Request for Bids Open - National Document - 2 2,000,000.00 0.00 Implementat 2021-06-27 2021-07-16 2021-08-27 2021-10-24 2021-11-28 Improvements Envelope 28 Barrage (IWWRMP- Envelope process ion 2/WORKS/MASL/OCBN/103) (Non Bank-SPD) LK-MOMDE-241083-CW-RFB / Installation of Automated National Geodetic Survey Systems in Procurement Pending Component 2: Infrastructure Single Stage - Two 2022-11- Kotmale & Randenigala Dams IDA / 66210 Post Request for Bids Open - National Document - 2 1,623,595.51 0.00 Implementat 2021-06-25 2021-07-15 2021-08-26 2021-10-23 2021-11-27 Improvements Envelope 27 for Dam Movement Envelope process ion Monitoring (IWWRMP- (Non Bank-SPD) 2/WORKS/MASL/OCBN/102) LK-MOMDE-241095-CW-RFB National / Supply and Installation of Procurement Pending Component 2: Infrastructure Single Stage - Two 2022-11- Gantry Crane for Udawalawe IDA / 66210 Post Request for Bids Open - National Document - 2 1,185,393.26 0.00 Implementat 2021-06-25 2021-07-15 2021-08-26 2021-10-23 2021-11-27 Improvements Envelope 27 Dam (IWWRMP- Envelope process ion 2/WORKS/MASL/OCBN/104) (Non Bank-SPD) Page 6 LK-MOMDE-123594-CW-RFB National / Improvement to Bathalagoda Procurement Pending Component 2: Infrastructure Single Stage - One 2022-10- main bund road ch from 0 to IDA / 66210 Post Request for Bids Open - National Document - 1 122,134.83 0.00 Implementat 2019-11-15 2021-07-05 2021-08-02 2021-09-01 2021-10-06 Improvements Envelope 06 1+525 ( IWWRMP- Envelope process ion 2/WORKS/ID/OCBN/01-2 ) (Non Bank-SPD) LK-MOMDE-123596-CW-RFB National / Improvement to Bathalagoda Procurement Pending Component 2: Infrastructure Single Stage - One 2022-10- Anicut (Mechanical works) ( IDA / 66210 Post Request for Bids Open - National Document - 1 103,988.76 0.00 Implementat 2019-11-15 2021-07-08 2021-08-07 2021-09-06 2021-10-11 Improvements Envelope 11 IWWRMP- Envelope process ion 2/WORKS/ID/OCBN/01-3 ) (Non Bank-SPD) LK-MOMDE-123597-CW-RFB National / Improvement to Bathalagoda Procurement Pending Component 2: Infrastructure Single Stage - One 2022-07- main CHL road from 0+000 to IDA / 66210 Post Request for Bids Open - National Document - 1 179,606.74 0.00 Implementat 2021-06-27 2021-07-20 2021-08-17 2021-09-16 2021-10-21 Improvements Envelope 28 2+100 km ( IWWRMP- Envelope process ion 2/WORKS/ID/OCBN/01-4 ) (Non Bank-SPD) LK-MOMDE-123600-CW-RFB Request for Bids - / Rehabilitation of D1, D2, D4 Pending Component 2: Infrastructure Single Stage - One Works (without 2022-10- canals in Bathalagoda Scheme IDA / 66210 Post Request for Bids Open - National 321,657.30 0.00 Implementat 2019-11-19 2021-07-26 2021-08-23 2021-09-22 2021-10-27 Improvements Envelope prequalification) 27 ( IWWRMP- ion SPD 2/WORKS/ID/OCBN/02-1) LK-MOMDE-123602-CW-RFB National / Rehabilitation of D5, D7, D7 Procurement Pending Component 2: Infrastructure Single Stage - One 2022-11- RB canals in Bathalagoda IDA / 66210 Post Request for Bids Open - National Document - 1 231,629.21 0.00 Implementat 2019-11-19 2021-07-29 2021-08-28 2021-09-27 2021-11-01 Improvements Envelope 01 Scheme ( IWWRMP- Envelope process ion 2/WORKS/ID/OCBN/02-2 ) (Non Bank-SPD) LK-MOMDE-123572-CW-RFB National / Improvements to Procurement Pending Bathalagoda Anicut & Anicut Component 2: Infrastructure Single Stage - One 2022-10- IDA / 66210 Post Request for Bids Open - National Document - 1 411,123.60 0.00 Implementat 2019-11-15 2021-07-08 2021-08-07 2021-09-06 2021-10-11 inlet CHL road from CH0 to Improvements Envelope 11 Envelope process ion 3+775 (IWWRMP- (Non Bank-SPD) 2/WORKS/ID/OCBN/01-1) National LK-MOMDE-123606-CW-RFB Procurement Pending / Rehabilitation of Dewahuwa Component 2: Infrastructure Single Stage - One 2023-12- IDA / 66210 Post Request for Bids Open - National Document - 1 568,854.87 0.00 Implementat 2019-11-19 2021-09-22 2021-10-20 2021-11-19 2021-12-24 Scheme ( IWWRMP- Improvements Envelope 24 Envelope process ion 2/WORKS/ID/OCBN/03 ) (Non Bank-SPD) National LK-MOMDE-125496-CW-RFB Procurement Pending / Rehabilitation of Arawatta Component 2: Infrastructure Single Stage - One 2022-11- IDA / 66210 Post Request for Bids Open - National Document - 1 230,492.13 0.00 Implementat 2019-12-27 2021-08-09 2021-09-06 2021-10-06 2021-11-10 tank bund ( IWWRMP- Improvements Envelope 10 Envelope process ion 2/WORKS/ID/OCBN/18) (Non Bank-SPD) National LK-MOMDE-124591-CW-RFB Procurement Pending / Rehabilititation of Component 2: Infrastructure Single Stage - One 2023-12- IDA / 66210 Post Request for Bids Open - National Document - 1 725,466.29 0.00 Implementat 2019-11-14 2021-09-20 2021-10-20 2021-11-19 2021-12-24 Nagadeepa Tank ( IWWRMP- Improvements Envelope 24 Envelope process ion 2/WORKS/ID/OCBN/07) (Non Bank-SPD) LK-MOMDE-225755-CW-RFB / Improvement to Bund (1 National km), rip rap Protection, Procurement Pending Component 2: Infrastructure Single Stage - One 2024-07- Instrumentation and Toe filter IDA / 66210 Post Request for Bids Open - National Document - 1 3,132,932.58 0.00 Implementat 2021-06-30 2022-04-26 2022-05-26 2022-06-25 2022-07-30 Improvements Envelope 29 & drain of Senanayaka Envelope process ion Samudraya Reservoir (IWWRMP- (Non Bank-SPD) 2/WORKS/ID/OCBN/20) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-117380-GO-DIR / Procurement of Relevant Data and Maps for Component 1: Watershed and preparation of GIS maps / Post Direct Selection Direct 15,151.52 0.00 Canceled 2019-08-05 2019-08-13 2019-09-17 2020-01-15 Water Resources Planning including specific geographic locations/sub-watersheds (IWWRMP/PP/GOODS/01) LK-MOMDE-123586-GO-RFB / Procurement of Crew Cabs ( Component 2: Infrastructure Single Stage - One / Post Request for Bids Open - National 475,000.00 0.00 Canceled 2020-06-09 2020-06-23 2020-08-04 2020-09-03 2020-10-08 2021-04-06 IWWRMP- Improvements Envelope 2/GOODS/PMU/OCBN/3 ) LK-MOMDE-124216-GO-DIR / Purchasing of GIS Maps and Component 1: Watershed and / Post Direct Selection Direct 30,000.00 0.00 Canceled 2020-01-27 2020-02-10 2020-03-21 2020-09-17 Satellite Images ( IWWRMP- Water Resources Planning 1/GOODS/PMU/OCBN/6 ) LK-MOMDE-123574-GO-RFB Pending / Procurement of clay Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 675,000.00 0.00 Implementati 2022-01-24 2022-02-07 2022-03-07 2022-04-06 2022-05-11 2023-03-07 grouting machines ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/1 ) LK-MOMDE-124212-GO-RFB Pending / Procurement of computer Component 1: Watershed and Single Stage - One IDA / 66210 Post Request for Bids Open - National 60,000.00 0.00 Implementati 2022-02-23 2022-03-09 2022-04-06 2022-05-06 2022-06-10 2022-10-08 and accessories-1 ( IWWRMP- Water Resources Planning Envelope on 2/GOODS/PMU/OCBN/4 ) LK-MOMDE-124214-GO-RFB Pending / Procurement of Photocopy Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 Implementati 2022-03-25 2022-04-08 2022-05-06 2022-06-05 2022-07-10 2022-11-07 Machines-1 ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/5 ) LK-MOMDE-124219-GO-RFB Pending / Procurement of Office Component 1: Watershed and Single Stage - One IDA / 66210 Post Request for Bids Open - National 30,000.00 0.00 Implementati 2022-03-22 2022-04-11 2022-05-09 2022-06-08 2022-07-13 2022-11-10 Equipments-1 ( IWWRMP- Water Resources Planning Envelope on 2/GOODS/PMU/OCBN/7 ) LK-MOMDE-123581-GO-RFB Pending / Procurement of water weeds Component 2: Infrastructure Single Stage - One IDA / 66210 Post Request for Bids Open - National 845,000.00 0.00 Implementati 2021-07-09 2021-08-06 2021-09-03 2021-10-03 2021-11-07 2022-09-03 removers ( IWWRMP- Improvements Envelope on 2/GOODS/PMU/OCBN/2 ) Page 7 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-157171-NC-RFQ Pending / Conducting Asset Component 4: Project Request for Single Stage - One / Post Limited 2,808.99 0.00 Implementati 2020-05-30 2020-07-18 2020-08-17 verification and Valuation for Management Quotations Envelope on the PMU-IWWRMP Assets CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-116917-CS- INDV / Consultancy services Consultant Component 3: Multi-sector for Preparation of TOR for / Post Qualification Limited 9,090.91 0.00 Canceled 2019-07-25 2019-08-08 2019-09-07 2019-10-12 2020-04-09 Water Resources Planning River Basin Management Plan Selection (IWWRMP/PP/CONS/30) LK-MOMDE-120102-CS- QCBS / Consultancy service to finalize the Bid documents for Component 1: Watershed and Quality And Cost- / Post Open - National 12,121.21 0.00 Canceled 2019-09-16 2019-10-07 2019-11-20 2019-12-18 2020-01-17 2020-02-21 2020-03-27 2021-03-27 irrigation dam rehabilitation Water Resources Planning Based Selection of Component 1 (IWWRMP/PP/CONS/35) LK-MOMDE-121715-CS-CQS / Consultancy Service for Consultant preparation of Watershed Component 1: Watershed and / Post Qualification Open - National 15,151.52 0.00 Canceled 2019-07-17 2019-08-07 2019-09-20 2019-10-20 2019-11-24 2020-05-22 Management plans for Water Resources Planning Selection selected area (IWWRMP/PP/CONS/36) LK-MOMDE-121716-CS-CQS Consultant / Consultancy services for Component 2: Infrastructure / Post Qualification Open - National 30,303.03 0.00 Canceled 2019-09-15 2019-10-06 2019-11-19 2019-12-19 2020-01-23 2020-07-21 preparation of Risk Assesment Improvements Selection (IWWRMP/PP/CONS/37) LK-MOMDE-125891-CS- QCBS / Consultancy service for preparation of Watershed management plan for seven selected divisions -Nuwara Component 1: Watershed and Quality And Cost- / Post Open - International 1,348,314.61 0.00 Canceled 2019-12-05 2019-12-26 2020-02-08 2020-03-07 2020-04-06 2020-05-11 2020-06-15 2021-06-15 Eliya, Badulla, Walapnae & Water Resources Planning Based Selection Kandy (Delthota, Haguranketha and Pahatha Hewaheta) (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-125993-CS- QCBS / Consultancy Service for study and recommendation for back erosion of Rantambe dam spillway tail canal ,LB erosion Component 2: Infrastructure Quality And Cost- / Post Open - International 786,516.85 0.00 Canceled 2019-11-25 2019-12-16 2020-01-29 2020-02-26 2020-03-27 2020-05-01 2020-06-05 2021-06-05 of Victoria dam spillway tail Improvements Based Selection canal, Back Analysis for Victoria dam and Kotmale Dam grouting gallery inspection (IWWRMP- 2/CS/QCBS/7) LK-MOMDE-126757-CS- QCBS / Development of Basin Management plan for Walawa Component 1: Watershed and Quality And Cost- / Post Open - National 421,348.31 0.00 Canceled 2020-05-25 2020-06-15 2020-07-29 2020-08-26 2020-09-25 2020-10-30 2020-12-04 2021-12-04 & Ma Oya including the Water Resources Planning Based Selection stakeholder workshops (IWWRMP-1/CS/QCBS/5) LK-MOMDE-126759-CS- QCBS / Consultancy service for Expansion and Component 1: Watershed and Quality And Cost- / Post Open - National 561,797.75 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2023-05-10 enhancement of WMS/MASL Water Resources Planning Based Selection bulk water allocation model (IWWRMP-1/CS/QCBS/6) LK-MOMDE-138818-CS-CQS / Consultancy on improving reservoir capacity by dredging Consultant Component 1: Watershed and sand deposits - medium and / Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-01 2020-04-22 2020-06-05 2020-07-05 2020-08-09 2021-08-09 Water Resources Planning minor irrigation tanks within Selection the watershed (IWWRMP- 1/CS/CQS/2) LK-MOMDE-138828-CS-CQS / Establishment of policy and Consultant institutional arrangements for Component 2: Infrastructure / Post Qualification Open - National 112,359.55 0.00 Canceled 2020-04-14 2020-05-05 2020-06-18 2020-07-18 2020-08-22 2021-08-22 dam safety, and water Improvements Selection resources management (IWWRMP-2/CS/CQS/15) LK-MOMDE-138831-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 25,280.90 0.00 Canceled 2020-12-16 2021-01-06 2021-02-19 2021-03-21 2021-04-25 2022-04-25 Improvements social screening report for Selection rehabiliate dams & canals cluster VII (IWWRMP- 2/CS/CQS/18) LK-MOMDE-138832-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 25,280.90 0.00 Canceled 2019-12-13 2020-01-03 2020-02-16 2020-03-17 2020-04-21 2021-04-21 Improvements social screening report for Selection rehabilitate dams & canals cluster VIII (IWWRMP- 2/CS/CQS/19) Page 8 LK-MOMDE-138824-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-09-09 2020-09-30 2020-11-13 2020-12-13 2021-01-17 2021-07-16 Improvements social screening report for Selection rehabilitate dams & canals cluster IV ( IWWRMP- 2/CS/CQS/11) LK-MOMDE-138829-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-22 2020-06-26 2021-06-26 Improvements social screening report for Selection rehabiliate dams & canals cluster V (IWWRMP- 2/CS/CQS/16) LK-MOMDE-138830-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 22,471.91 0.00 Canceled 2019-12-09 2019-12-30 2020-02-12 2020-03-13 2020-04-17 2021-04-17 Improvements social screening report for Selection rehabilitate dams & canals cluster VI (IWWRMP- 2/CS/CQS/17) LK-MOMDE-138822-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2021-01-03 Improvements social screening report for Selection rehabilitate dams & canals cluster II (IWWRMP- 2/CS/CQS/9) LK-MOMDE-138835-CS-CQS / Feasibility study tocheck the Consultant Component 2: Infrastructure possibility of diverson of / Post Qualification Open - National 280,898.88 0.00 Canceled 2020-09-28 2020-10-19 2020-12-02 2021-01-01 2021-02-05 2022-02-05 Improvements Kaluganga Water to the CKD Selection area (IWWRMP-2/CS/CQS/22) LK-MOMDE-138823-CS-CQS / Consultancy service for Preparation of Environmental Social Management Consultant Component 2: Infrastructure Framework and Environmental / Post Qualification Open - National 56,179.78 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-04 2021-01-08 2021-07-07 Improvements social screening report for Selection rehabilitate dams & canals cluster III ( IWWRMP- 2/CS/CQS/10) LK-MOMDE-138836-CS-CQS / Preparation of guidline for Consultant Component 2: Infrastructure sustainable Dam safety and / Post Qualification Open - National 11,235.96 0.00 Canceled 2020-07-30 2020-08-20 2020-10-03 2020-11-02 2020-12-07 2021-12-07 Improvements Hydraulic Assets ( IWWRMP- Selection 2/CS/CQS/23 ) LK-MOMDE-138838-CS-CQS Consultant Component 2: Infrastructure / Risk assessment for all / Post Qualification Open - National 280,898.88 0.00 Canceled 2020-11-01 2020-11-22 2021-01-05 2021-02-04 2021-03-11 2022-03-11 Improvements identified dams Selection LK-MOMDE-162965-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed and Quality And Cost- / Post Open - National 280,898.88 0.00 Canceled 2020-10-29 2020-11-19 2021-01-02 2021-01-30 2021-03-01 2021-04-05 2021-05-10 2022-05-10 Upper Watershed Water Resources Planning Based Selection management intervention plan for cluster II (IWWRMP- 1/CS/QCBS/2) LK-MOMDE-138837-CS-CQS / preparation of O & M Consultant Manuals and Emergency Component 2: Infrastructure / Post Qualification Open - National 280,898.88 0.00 Canceled 2021-12-01 2021-12-22 2022-02-04 2022-03-06 2022-04-10 2023-04-10 Action plans for selected Improvements Selection dams ( IWWRMP- 2/CS/CQS/24 ) LK-MOMDE-162967-CS- QCBS / Consultancy service for preparation of Mahaweli Component 1: Watershed and Quality And Cost- / Post Open - National 224,719.10 0.00 Canceled 2021-02-01 2021-02-22 2021-04-07 2021-05-05 2021-06-04 2021-07-09 2021-08-13 2022-08-13 Upper Watershed Water Resources Planning Based Selection management intervention plan for cluster III (IWWRMP- 1/CS/QCBS/3) LK-MOMDE-162968-CS- QCBS / Consultancy Service development of best practices Component 1: Watershed and Quality And Cost- for water management using / Post Open - National 56,179.78 0.00 Canceled 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2021-10-07 Water Resources Planning Based Selection native , herbal, economical important species (IWWRMP- 1/CS/QCBS/4) LK-MOMDE-138839-CS-CQS / Consultancy Service for Consultant Component 4: Project Development for Project / Post Qualification Open - National 14,044.94 0.00 Canceled 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-05-23 Management Website (IWWRMP- Selection 4/CS/CQS/26) LK-MOMDE-162972-CS- QCBS / Consultancy service for development for Component 1: Watershed and Quality And Cost- / Post Open - National 56,179.78 0.00 Canceled 2020-09-29 2020-10-20 2020-12-03 2020-12-31 2021-01-30 2021-03-06 2021-04-10 2022-04-10 integrated design proposal for Water Resources Planning Based Selection upper periphary of Polgolla reservoir (IWWRMP- 1/CS/QCBS/5) LK-MOMDE-162975-CS-CQS / Consultancy service for Consultant Component 1: Watershed and Expansion and enhancement / Post Qualification Open - International 561,795.75 0.00 Canceled 2020-11-02 2020-11-23 2021-02-06 2021-03-08 2021-04-19 2022-04-19 Water Resources Planning of WMS/MASL bulk water Selection allocation model Page 9 LK-MOMDE-162963-CS- QCBS / Consultancy service for preparation of Component 1: Watershed and Quality And Cost- Pending Implementation support IDA / 66190 Post Open - National 955,056.18 0.00 2021-08-18 2021-10-28 2021-12-11 2022-01-10 2022-02-09 2022-03-02 2022-04-06 2023-04-06 Water Resources Planning Based Selection Implementation Upper Mahaweli Watershed management plan (IWWRMP- 1/CS/QCBS/1) LK-MOMDE-240780-CS-CQS / Consultancy service for Consultant development for integrated Component 1: Watershed and Pending IDA / 66190 Post Qualification Open - National 44,943.82 0.00 2021-09-23 2021-12-14 2022-02-10 2022-04-11 2022-05-16 2022-11-12 design proposal for upper Water Resources Planning Implementation Selection periphary of Polgolla reservoir (IWWRMP-1/CS/CQS/2) LK-MOMDE-138819-CS-CQS / Development Groundwater Management plans for Malwathoya, Deduru Oya, Kumbukkan Oya, MathuruOya, Consultant Component 1: Watershed and Pending Mee Oya, Maa Oya, Kelani IDA / 66190 Post Qualification Open - National 140,449.44 0.00 2021-08-19 2021-09-09 2021-11-06 2022-01-05 2022-02-09 2023-02-09 Water Resources Planning Implementation basin and Jaffna Peninsula Selection (WRB) by considering the real- time data on water quality, quantity, etc.(IWWRMP- 1/CS/CQS/3) LK-MOMDE-138820-CS-CQS / Development of Consultant Groundwater Data & Component 1: Watershed and Pending IDA / 66190 Post Qualification Open - National 56,179.78 0.00 2022-04-14 2022-06-22 2022-08-19 2022-10-18 2022-11-22 2023-11-22 Information System for WRB Water Resources Planning Implementation Selection covering entire country (IWWRMP-1/CS/CQS/4) LK-MOMDE-118633-CS- QCBS / Consultancy Service for the Evaluation and Recommendation for the Kotmale Dam grouting gallery Component 2: Infrastructure Quality And Cost- Pending inspection work, LB erosion of IDA / 66210 Post Open - International 1,601,123.60 0.00 2021-12-24 2022-02-24 2022-04-09 2022-05-07 2022-06-06 2022-07-11 2022-08-15 2023-08-15 Improvements Based Selection Implementation spillway tail canal of Victoria Dam, Back Analysis for the Victoria Dam and back erosion of spillway tail canal of the Rantambe LK-MOMDE-118622-CS- QCBS / Consultancy Services for Study on cracks in intake Component 2: Infrastructure Quality And Cost- Pending sluice tower and dam stability IDA / 66210 Post Open - International 842,696.63 0.00 2022-01-18 2022-02-18 2022-04-03 2022-05-01 2022-05-31 2022-07-05 2022-08-09 2023-08-09 Improvements Based Selection Implementation in Senanayaka Samudraya Headworks ( IWWRMP- 2/CS/QCBS/6 ) LK-MOMDE-162977-CS-CQS / Consultancy service for Preparation of Environmental Consultant Social Management Plan and Component 2: Infrastructure Pending IDA / 66210 Post Qualification Open - National 84,269.00 0.00 2021-06-30 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-05-11 Environmental and Social Improvements Implementation Selection Screening report for rehabilitate dams & canals in NPC (IWWRMP-2/CS/CQS/7) LK-MOMDE-138821-CS-CQS / Consultancy service for Preparation of Environmental Consultant Social Management Plan and Component 2: Infrastructure Pending IDA / 66210 Post Qualification Open - National 56,179.78 0.00 2021-06-30 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-05-05 Environmental and Social Improvements Implementation Selection Screening report for rehabilitate dams & canals in EPC (IWWRMP-2/CS/CQS/8) LK-MOMDE-138825-CS-CQS / Consultancy Service for preparation of Livelihood Consultant Component 2: Infrastructure Pending Support Assistance Plan (LSA) IDA / 66210 Post Qualification Open - National 56,179.78 0.00 2021-09-23 2021-10-14 2021-11-27 2021-12-27 2022-01-31 2022-07-30 Improvements Implementation for the period of Cultivation Selection forgo of selected dams (IWWRMP-2/CS/CQS/9) LK-MOMDE-138826-CS-CQS / Consultancy Service for inspection, identification of Consultant Component 2: Infrastructure Pending defects and repair works of IDA / 66210 Post Qualification Open - National 84,269.66 0.00 2021-07-28 2021-08-18 2021-10-01 2021-10-31 2021-12-05 2022-06-03 Improvements Implementation syphone from 3+950 km to Selection 4+330 km of walawa RB main canal (IWWRMP-2/CS/CQS/10) LK-MOMDE-138827-CS-CQS / Consultancy service for Consultant Component 2: Infrastructure Pending design of Bridge at 4+000 km IDA / 66210 Post Qualification Open - National 28,089.89 0.00 2021-08-13 2021-09-03 2021-10-17 2021-11-16 2021-12-21 2022-06-19 Improvements Implementation of walawa RB main canal Selection (IWWRMP-2/CS/CQS/11) LK-MOMDE-138834-CS-CQS / Feasibility Study for Construction of Poonery Tank Consultant and Barrages including Component 2: Infrastructure Pending IDA / 66210 Post Qualification Open - National 252,808.99 0.00 2022-02-01 2022-02-22 2022-04-07 2022-05-07 2022-06-11 2023-06-11 Investigation, Detailed Design, Improvements Implementation Selection BD preparation, EIA and Social assessment (IWWRMP- 2/CS/CQS/13) LK-MOMDE-121717-CS-CQS Consultant / Preparation of Management Component 4: Project Pending IDA / 66210 Post Qualification Open - National 12,121.21 0.00 2022-02-01 2022-02-15 2022-04-07 2022-05-07 2022-06-11 2022-12-08 Information System Management Implementation Selection (IWWRMP/PP/CONS/15) LK-MOMDE-240803-CS- QCBS / Preparation of O & M Manuals, Emergency Action Component 2: Infrastructure Quality And Cost- Pending plans for selected dams and IDA / 66210 Post Open - National 505,617.98 0.00 2022-03-16 2022-05-12 2022-06-25 2022-07-25 2022-08-24 2022-09-14 2022-10-19 2023-10-19 Improvements Based Selection Implementation Risk assessment for all identified dams (IWWRMP- 2/CS/QCBS/16) INDIVIDUAL CONSULTANTS Page 10 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMDE-113221-CS- INDV / Consultancy services for Environmental Social Individual Impact Assessment for Component 2: Infrastructure / Post Consultant Limited 9,090.91 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-03 2019-06-17 2019-06-03 2019-08-16 Rehabilitation of Elahara Improvements Selection scheme, Haththota scheme and Arawatta Tank (IWWRMP/PP/CONS/01) LK-MOMDE-113250-CS- INDV / Consultancy services for Environmental Social Impact Assessment for Individual Component 2: Infrastructure Rehabilitation of Hali Ela / Post Consultant Limited 12,121.21 3,593.15 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-28 2019-06-07 2019-06-02 2019-06-15 2019-06-03 2019-08-14 Improvements Tank, Akathimuripu Tank, Selection Madiyawa Tank and Waduwala Scheme (IWWRMP/PP/CONS/02) LK-MOMDE-113252-CS- Individual INDV / Consultancy services Component 2: Infrastructure / Post Consultant Limited 6,060.61 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 for Aquatic Survey Improvements Selection (IWWRMP/PP/CONS/03) LK-MOMDE-116871-CS- INDV / Consultancy service for Preparation of Operation manual for river basin planning and management, Individual Component 2: Infrastructure customized to the selected / Post Consultant Limited 24,242.42 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-08-16 Improvements river basins (Walawa including Selection the Walawa RB preparation of ESMP, Kalawewa and Mahalindawewa) (IWWRMP/PP/CONS/06) LK-MOMDE-116883-CS- INDV / Consultancy for Individual Preparation of guideline for Component 1: Watershed and / Post Consultant Limited 12,121.21 8,274.72 Signed 2019-08-01 2019-07-01 2019-08-06 2019-05-03 2019-08-27 2019-07-09 2019-10-01 2019-07-15 2020-03-29 Sustainable Watershed Water Resources Planning Selection Management (IWWRMP/PP/CONS/08) LK-MOMDE-116900-CS- INDV / Short-term Individual Component 4: Project assignment for Personal / Post Consultant Limited 3,030.30 0.00 Canceled 2019-05-30 2019-05-08 2019-06-04 2019-06-18 2019-07-09 2020-01-05 Management Assistant Selection (IWWRMP/PP/CONS/17) LK-MOMDE-116901-CS- INDV / Consultancy services for Environmental Social Individual Impact Assesment for Component 2: Infrastructure / Post Consultant Limited 12,121.21 2,756.51 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-09 2019-06-07 2019-05-27 2019-06-17 2019-05-30 2019-08-16 Rehabilitation of Improvements Selection Muththuiyankaddu irrigation scheme (IWWRMP/PP/CONS/18) LK-MOMDE-116902-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Rehabilitation of Periyamadu Component 2: Infrastructure Pending / Post Consultant Limited 24,242.42 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2019-12-29 Tank and Kariyalai Improvements Implementation Selection Nagarpaduwan Tank & irrigation scheme and Periyapandivirichchan scheme (IWWRMP/PP/CONS/19) LK-MOMDE-116903-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Rehabilitation of Component 2: Infrastructure Pending / Post Consultant Limited 27,272.73 0.00 2019-08-30 2019-09-04 2019-09-25 2019-10-30 2020-04-27 Akkarayankulam irrigation Improvements Implementation Selection scheme, Kudamuruthy Tank and Vannerikulam headworks & irrigation scheme (IWWRMP/PP/CONS/20) LK-MOMDE-116906-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Individual Component 2: Infrastructure Rehabilitation of Dewahuwa / Post Consultant Limited 12,121.21 1,875.18 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-09 2019-05-27 2019-06-19 2019-06-03 2019-08-18 Improvements tank & scheme and Selection Baththalagoda Anicut & scheme (IWWRMP/PP/CONS/22) LK-MOMDE-116907-CS- INDV / Consultancy services for Environmental Social Individual Impact Assessment for Component 2: Infrastructure / Post Consultant Limited 21,212.12 9,340.87 Signed 2019-05-30 2019-05-08 2019-06-02 2019-04-09 2019-06-07 2019-04-10 2019-06-17 2019-06-03 2019-08-16 Rehabilitation of Huruluwewa Improvements Selection irrigation scheme, Karawita Tank & Ambakolawewa Tank (IWWRMP/PP/CONS/23) LK-MOMDE-116909-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Vahanery Individual Component 2: Infrastructure Dam, Panama Tank, / Post Consultant Limited 24,242.42 14,236.74 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-28 2019-06-11 2019-05-28 2019-06-25 2019-06-03 2019-09-23 Improvements Unnichchai scheme, Selection Nagadeepa Tank, Illukuchenal & Senanayake Samudraya Reservoir (IWWRMP/PP/CONS/24) Page 11 LK-MOMDE-116910-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Pavatkulam Individual Component 2: Infrastructure Tank, Muhathankulam / Post Consultant Limited 24,242.42 13,898.79 Signed 2019-05-30 2019-05-08 2019-06-04 2019-04-09 2019-06-11 2019-05-28 2019-06-25 2019-05-30 2019-09-23 Improvements Scheme, Viyadhikulam Selection irrigation scheme, Peramadu Tank & Scheme and Mavilaru Headworks (IWWRMP/PP/CONS/25) LK-MOMDE-116911-CS- INDV / Consultancy service Individual for preparation of Livelihood Component 2: Infrastructure / Post Consultant Limited 18,181.82 0.00 Canceled 2019-07-09 2019-07-14 2019-08-04 2019-09-08 2020-03-06 Support Assistance Plan (LSA) Improvements Selection - Walawa (IWWRMP/PP/CONS/26) LK-MOMDE-116912-CS- INDV / Consultancy services for Environmental Social Individual Component 2: Infrastructure Impact Assesment for / Post Consultant Limited 9,090.91 3,736.75 Signed 2019-05-30 2019-05-08 2019-06-04 2019-05-15 2019-06-11 2019-05-24 2019-06-25 2019-06-20 2019-08-24 Improvements Rehabilitation of Kothmale Selection Dam & irrigation scheme (IWWRMP/PP/CONS/27) LK-MOMDE-116914-CS- INDV / Individual Consultancy services to prepare mechanical specification, Individual Component 2: Infrastructure Estimation & Bid documents / Post Consultant Limited 9,090.91 11,032.96 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-28 2019-06-17 2019-06-03 2020-06-16 Improvements for Gantry crane Polgolla, Selection Udawalawe and Gate Automation for Bowatenna (IWWRMP/PP/CONS/28) LK-MOMDE-116896-CS- INDV / Short-term Individual Component 4: Project assignment for Procurement / Post Consultant Limited 3,030.30 0.00 Under Review 2019-05-30 2019-05-08 2019-06-02 2019-06-07 2019-06-17 2019-12-14 Management Assistant Selection (IWWRMP/PP/CONS/16) LK-MOMDE-116904-CS- INDV / Consultancy services for Environmental Social Impact Assesment for Rehabilitation of Individual Component 2: Infrastructure Piramanthalaru Kulam / Post Consultant Limited 27,272.27 8,299.72 Signed 2019-05-30 2019-05-08 2019-06-02 2019-05-23 2019-06-07 2019-05-24 2019-06-17 2019-05-30 2019-08-16 Improvements irrigation scheme, Selection Kanagambikaikulam irrigation scheme and Kalmadu tank irrigation scheme (IWWRMP/PP/CONS/21) LK-MOMDE-121767-CS- INDV / Individual consultancy services for preparation and Individual reviewing the RFP of study & Component 2: Infrastructure / Post Consultant Open 60,000.00 0.00 Canceled 2019-07-28 2019-09-15 2019-10-06 2019-11-10 2020-05-08 recommendation for selected Improvements Selection MASL Dams (Rantambe, Victoria, Kothmale) (IWWRMP/PP/CONS/32) LK-MOMDE-121782-CS- INDV / Consultancy for Individual Preparation of guideline for Component 2: Infrastructure / Post Consultant Limited 12,121.21 0.00 Canceled 2019-09-18 2019-09-23 2019-10-14 2019-11-18 2020-05-16 sustainable Dam safety and Improvements Selection Hydraulic Assert (IWWRMP/PP/CONS/07) LK-MOMDE-138929-CS- INDV / Consultancy services Individual Component 2: Infrastructure for Preparation of TOR for / Post Consultant Limited 8,426.97 0.00 Canceled 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-07-29 Improvements River Basin Management Plan Selection (IWWRMP-2/CS/IC/20) LK-MOMDE-118665-CS- INDV / Training program on Individual Procurement (Evaluation of Component 4: Project / Post Consultant Limited 6,060.61 0.00 Canceled 2020-11-15 2020-11-20 2020-12-11 2021-01-15 2021-01-22 Consultancy, Goods and Management Selection Works) (IWWRMP/PP/CONS/41) LK-MOMDE-184063-CS- INDV / Short-term Individual Component 4: Project assignment for Personal IDA / 66190 Post Consultant Limited 2,500.00 0.00 Under Review 2020-07-15 2020-07-15 2020-07-18 2020-07-15 2020-08-01 2020-09-05 2021-03-04 Management Assistant Selection (IWWRMP/PP/CONS/17) LK-MOMDE-162970-CS- INDV / Consultancy service for Preparation of Environmental Social Management Framework and Individual Component 2: Infrastructure Pending Environmental social IDA / 66210 Post Consultant Limited 11,235.96 0.00 2021-08-13 2021-08-18 2021-09-09 2021-10-14 2022-01-12 Improvements Implementation screening report for Selection Rehabilitation of Wadamunai tank & Lunugamwehera Reservoir (IWWRMP- 2/CS/IND/12) Page 12