PROCUREMENT PLAN (Mandatory Requirements) Emergency Multi-Sector Rohingya Crisis Response Project (EMRCRP) Project Implementation Agencies: Ministry of Disaster Management and Relief (MoDMR) Department of Public Health Engineering (DPHE) Local Government Engineering Department (LGED) Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 revised November 2017 (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) Lottery in award of contracts shall not be allowed; 2) Bidders’ qualification[s]/experience requirement[s] shall be mandatory; 3) Bids shall not be rejected based on percentage above or below the estimated cost; 4) Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; 5) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; 6) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 7) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: formation and alteration of the bid/proposal evaluation committee shall be subject to Bank’s no objection. Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : Emergency Multi-Sector Rohingya Crisis Response Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2019-02-17 2021-09-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167762 GPN Date: Project Name: Emergency Multi-Sector Rohingya Crisis Response Project Loan / Credit No: / , IDA / D4190, IDA / D5900 Local Government Engineering Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Strengthening EMCRP/W3 / Relief Delivery of Basic Services, Administration and Resilient Infrastructure, Single Stage - One 2021-04- Distribution Center in Ukhya IDA / D4190 Post Request for Bids Open - National 240,000.00 228,105.67 Signed 2019-07-01 2020-03-01 2019-07-06 2019-07-21 2020-03-25 2019-08-30 2020-04-21 2019-10-11 2020-05-18 Emergency Response, and Envelope 13 Upazial of Cox's Bazar Gender-Based Viol ence District. Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W7 / Construction of Resilient Infrastructure, Single Stage - One 2020-11- Field Office (EE Cox's Bazar) IDA / D4190 Post Request for Bids Open - National 180,000.00 155,966.98 Signed 2019-07-25 2019-10-16 2019-07-30 2019-08-14 2019-11-12 2019-09-23 2019-11-24 2019-11-04 2019-12-10 Emergency Response, and Envelope 03 extension with renovation Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W10 / Construction Delivery of Basic Services, of 12 nos. new School cum Resilient Infrastructure, Single Stage - One 2021-09- Disaster shelter buildings in IDA / D4190 Post Request for Bids Open - National 6,020,000.00 347,830.11 Signed 2019-06-01 2019-10-01 2019-06-06 2019-06-21 2019-10-31 2019-07-31 2019-07-30 2019-09-11 2019-09-12 Emergency Response, and Envelope 10 Ukhya Upazial of Cox's Bazar Gender-Based Viol ence District. Prevention Component 1: Strengthening EMCRP/W13 / Improvement Delivery of Basic Services, of 8 Access Road to different Resilient Infrastructure, Single Stage - One 2,088,894.6 2021-05- camps of forcibly displaced IDA / D4190 Post Request for Bids Open - National 2,180,000.00 Signed 2019-08-01 2019-11-03 2019-08-06 2019-08-21 2019-12-04 2019-09-30 2019-12-24 2019-11-11 2020-01-29 Emergency Response, and Envelope 1 14 Myanmar nationals under Gender-Based Viol ence Cox's Bazar District: Prevention Component 1: Strengthening EMCRP/W14 / Improvement Delivery of Basic Services, of 7 Access Road to different Resilient Infrastructure, Single Stage - One 1,752,754.7 2021-05- camps of forcibly displaced IDA / D4190 Post Request for Bids Open - National 2,160,000.00 Signed 2019-08-10 2019-10-27 2019-08-15 2019-08-30 2019-11-27 2019-10-09 2019-12-04 2019-11-20 2020-01-14 Emergency Response, and Envelope 7 23 Myanmar nationals under Gender-Based Viol ence Cox's Bazar District: Prevention Component 1: Strengthening EMCRP/W4 / Construction of Delivery of Basic Services, Multipurpose Community and Under Resilient Infrastructure, Single Stage - One 2022-09- Service Center in Ukhya IDA / D4190 Post Request for Bids Open - National 3,434,667.00 0.00 Implementat 2020-11-20 2021-06-27 2020-11-25 2020-12-30 2021-07-27 2021-02-06 2021-03-20 Emergency Response, and Envelope 21 Upazial of Cox's Bazar ion Gender-Based Viol ence District. Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W15 / Construction Resilient Infrastructure, Single Stage - One 2,205,379.1 2022-07- of 4 RCC roads under Cox's IDA / D4190 Post Request for Bids Open - National 3,270,000.00 Signed 2020-09-20 2020-10-16 2020-09-24 2020-10-29 2020-11-23 2020-11-25 2021-02-01 2021-01-06 2021-03-10 Emergency Response, and Envelope 2 10 Bazar District: Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W16 / Construction Resilient Infrastructure, Single Stage - One 1,433,552.2 2022-07- of 4 RCC roads under Cox's IDA / D4190 Post Request for Bids Open - National 2,860,000.00 Signed 2020-09-20 2020-10-16 2020-09-25 2020-10-30 2020-11-23 2020-11-26 2021-02-01 2021-01-07 2021-03-10 Emergency Response, and Envelope 0 11 Bazar District: Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W19 / Improvementof Delivery of Basic Services, 10 roads roads and Resilient Infrastructure, Single Stage - One 2022-07- construction of culverts with IDA / D4190 Post Request for Bids Open - National 3,220,000.00 191,767.13 Signed 2020-09-10 2020-07-23 2020-09-14 2020-10-15 2020-08-26 2020-11-29 2020-09-06 2021-01-10 2020-11-04 Emergency Response, and Envelope 14 side drains under Cox's Gender-Based Viol ence Bazar District: Prevention Component 1: Strengthening EMCRP/W2 / Construction of Delivery of Basic Services, warehouse for firefighting Pending Resilient Infrastructure, Single Stage - One 2022-11- equipment and Satellite fire IDA / D4190 Post Request for Bids Open - National 240,000.00 0.00 Implementat 2021-01-15 2021-01-19 2021-02-16 2021-03-28 2021-05-09 Emergency Response, and Envelope 10 stations in Ukhya Upazial of ion Gender-Based Viol ence Cox's Bazar District. Prevention Component 1: Strengthening EMCRP/W5 / Construction of Delivery of Basic Services, internal road, footpath, Pending Resilient Infrastructure, Single Stage - One 2022-02- drainage and side slope IDA / D4190 Post Request for Bids Open - National 2,150,000.00 0.00 Implementat 2021-04-21 2021-04-25 2021-05-30 2021-07-09 2021-08-20 Emergency Response, and Envelope 16 protection in Ukhya Upazial of ion Gender-Based Viol ence Cox's Bazar District. Prevention Component 1: Strengthening EMCRP/W21 / Improvement Delivery of Basic Services, of 17 roads roads and Resilient Infrastructure, Single Stage - One 3,263,471.5 2022-12- construction of culverts with IDA / D4190 Post Request for Bids Open - National 3,190,000.00 Signed 2021-02-25 2021-03-18 2021-03-01 2021-04-05 2021-05-03 2021-05-15 2021-05-30 2021-06-26 2021-07-19 Emergency Response, and Envelope 4 28 side drains under Cox's Gender-Based Viol ence Bazar District: Prevention Component 1: Strengthening EMCRP/W6 / Rehabiliation of Delivery of Basic Services, blocked hilly chorra with Pending Resilient Infrastructure, Single Stage - One 2021-09- excavation of canalin Ukhya IDA / D4190 Post Request for Bids Open - National 60,000.00 0.00 Implementat 2021-03-30 2021-04-03 2021-04-24 2021-05-19 2021-06-30 Emergency Response, and Envelope 28 Upazial of Cox's Bazar ion Gender-Based Viol ence District. Prevention Component 1: Strengthening EMCRP/W8 / Construction of Delivery of Basic Services, 6 RCC Girder bridges at Resilient Infrastructure, Single Stage - One 1,409,281.9 2023-01- IDA / D4190 Post Request for Bids Open - National 2,780,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-29 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-10 different roads under Cox's Emergency Response, and Envelope 6 15 District. Gender-Based Viol ence Prevention Page 1 Component 1: Strengthening EMCRP/W20 / Improvement Delivery of Basic Services, of 11 roads roads and Resilient Infrastructure, Single Stage - One 3,308,124.3 2022-08- construction of culverts with IDA / D4190 Post Request for Bids Open - National 3,400,000.00 Signed 2020-10-20 2021-01-28 2020-10-24 2020-11-28 2021-03-02 2020-12-30 2021-03-16 2021-02-10 2021-04-13 Emergency Response, and Envelope 9 14 side drains under Cox's Gender-Based Viol ence Bazar District: Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W24 / Improvement Resilient Infrastructure, Single Stage - One 2,207,925.9 2023-01- of 7 roads under Cox's Bazar IDA / D4190 Post Request for Bids Open - National 3,350,000.00 Signed 2021-03-25 2021-03-18 2021-03-29 2021-05-03 2021-05-03 2021-06-12 2021-06-05 2021-07-24 2021-07-19 Emergency Response, and Envelope 6 25 District: Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W22 / Improvement Delivery of Basic Services, 15 Roads with culverts and Resilient Infrastructure, Single Stage - One 2,796,624.6 2023-02- IDA / D4190 Post Request for Bids Open - National 2,770,000.00 Signed 2021-04-20 2021-03-18 2021-04-24 2021-05-29 2021-05-03 2021-07-08 2021-06-05 2021-08-19 2021-07-19 side drain under Cox's Bazar Emergency Response, and Envelope 3 20 District Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W9 / Construction of Delivery of Basic Services, 4 RCC Girder bridges at Resilient Infrastructure, Single Stage - One 1,278,919.1 2023-01- IDA / D4190 Post Request for Bids Open - National 2,410,000.00 Signed 2020-09-20 2020-10-19 2020-09-24 2020-10-30 2020-11-23 2020-12-04 2021-02-01 2021-01-15 2021-03-10 different roads under Cox's Emergency Response, and Envelope 6 15 District. Gender-Based Viol ence Prevention EMCRP/W11 / Construction Component 1: Strengthening of 11 nos. new School cum Delivery of Basic Services, Disaster shelter buildings in Resilient Infrastructure, Single Stage - One 4,988,485.3 2022-11- IDA / D4190 Post Request for Bids Open - National 5,520,000.00 Signed 2020-07-24 2020-07-21 2020-07-28 2020-09-02 2020-09-22 2020-10-12 2020-10-08 2020-11-23 2020-12-13 Ukhya (9 nos.) and Teknaf Emergency Response, and Envelope 3 23 (2nos) Upazial of Cox's Bazar Gender-Based Viol ence District. Prevention Component 1: Strengthening EMCRP/W23 / Improvement Delivery of Basic Services, 18 Roads with culverts and Resilient Infrastructure, Single Stage - One 4,510,585.3 2023-02- IDA / D4190 Post Request for Bids Open - National 3,190,000.00 Signed 2021-04-20 2020-10-16 2021-04-24 2021-05-29 2020-11-23 2021-07-08 2021-03-04 2021-08-19 2021-04-29 side drain under Cox's Bazar Emergency Response, and Envelope 5 20 District Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W25 / Strengthening Resilient Infrastructure, Single Stage - One 1,774,351.5 2023-03- and widening of 10 roads IDA / D4190 Post Request for Bids Open - National 1,020,000.00 Signed 2021-05-26 2021-01-28 2021-05-30 2021-07-04 2021-03-02 2021-08-13 2021-03-16 2021-09-24 2021-04-15 Emergency Response, and Envelope 0 28 under Cox's Bazar Districts Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W18 / Improvement Delivery of Basic Services, of 8 roads roads and Resilient Infrastructure, Single Stage - One 2,055,922.9 2022-08- construction of culverts with IDA / D4190 Post Request for Bids Open - National 3,230,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-10 Emergency Response, and Envelope 3 14 side drains under Cox's Gender-Based Viol ence Bazar District: Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/W1 / Improvement fo Pending Resilient Infrastructure, Single Stage - One 2021-12- 6 nos. Hat Bazar under Cox's IDA / D4190 Post Request for Bids Open - National 360,000.00 0.00 Implementat 2021-03-10 2021-03-14 2021-04-13 2021-05-23 2021-07-04 Emergency Response, and Envelope 31 Bazar Districts: ion Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W17 / Improvement Delivery of Basic Services, of 8 roads and construction Resilient Infrastructure, Single Stage - One 2,236,005.8 2022-08- IDA / D4190 Post Request for Bids Open - National 2,890,000.00 Signed 2020-10-20 2020-10-16 2020-10-24 2020-11-29 2020-11-23 2020-12-30 2021-02-01 2021-02-10 2021-03-10 of culverts with side drains Emergency Response, and Envelope 1 14 under Cox's Bazar District: Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/W12 / Rehabiltiation Delivery of Basic Services, of 12 camp connecting roads Pending Resilient Infrastructure, Single Stage - One 2021-06- around/within forcibly IDA / D4190 Post Request for Bids Open - National 1,920,000.00 0.00 Implementat 2019-08-01 2019-08-05 2019-09-09 2019-10-19 2019-11-30 Emergency Response, and Envelope 02 displaced Myanmar nations ion Gender-Based Viol ence under Cox's Bazar District Prevention Component 1: Strengthening National Delivery of Basic Services, EMCRP/W26 / Improvement Procurement Resilient Infrastructure, Single Stage - One 1,981,314.3 2023-04- of 09 nos Roads under Cox's IDA / D4190 Post Request for Bids Open - National Document - 1 2,514,400.00 Signed 2021-08-11 2021-03-18 2021-08-14 2021-09-04 2021-05-03 2021-09-11 2021-06-05 2021-10-16 2021-07-19 Emergency Response, and Envelope 7 14 Bazar District Envelope process Gender-Based Viol ence (Non Bank-SPD) Prevention GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, EMCRP/G-04 / Procurement Resilient Infrastructure, Single Stage - One of 10000 + 1000 Liter water / Post Request for Bids Open - National 2,408,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 Emergency Response, and Envelope tender for FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-05 / Procurement Resilient Infrastructure, Single Stage - One of Fire and Rescue Vehicle IDA / D4190 Post Request for Bids Open - National 2,744,000.00 2,654,506.42 Completed 2019-02-20 2019-05-28 2019-02-25 2019-03-12 2019-07-02 2019-04-21 2019-08-20 2019-05-26 2019-10-10 2019-09-23 2019-10-10 Emergency Response, and Envelope (medium) for FSCD Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-06 / Procurement Delivery of Basic Services, of Towing Vehicle ( Pick up Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 2,974,000.00 6,032,998.51 Signed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-09 2019-05-26 2019-10-10 2019-09-23 2019-10-10 type with CAF and Water ) for Emergency Response, and Envelope FSCD Gender-Based Viol ence Prevention Page 2 Component 1: Strengthening Delivery of Basic Services, EMCRP/G-07 / Procurement Resilient Infrastructure, Single Stage - One of Fire Fighting portable IDA / D4190 Post Request for Bids Open - National 397,000.00 372,622.94 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2020-06-25 Emergency Response, and Envelope pump ( Small) for FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-10 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 361,000.00 349,065.04 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-07-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 of Ambulance for FSCD Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-11 / Procurement Resilient Infrastructure, Single Stage - One / Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 of Rescue Boat for FSCD Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-12 / Procurement Resilient Infrastructure, Single Stage - One of Fire Fighting Turn Table for IDA / D4190 Post Request for Bids Open - National 1,746,000.00 0.00 Canceled 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-07-02 2019-04-21 2019-05-26 2019-09-23 Emergency Response, and Envelope FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-08 / Procurement Resilient Infrastructure, Single Stage - One of Fire Service Command IDA / D4190 Post Request for Bids Open - National 255,000.00 189,293.33 Completed 2019-02-20 2019-05-28 2019-02-25 2019-05-30 2019-03-12 2019-06-25 2019-04-21 2019-08-30 2019-05-26 2019-09-12 2019-09-23 2019-09-12 Emergency Response, and Envelope Vehicle for FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-01 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 81,000.00 0.00 Canceled 2019-07-01 2019-07-06 2019-07-21 2019-08-30 2019-10-11 2020-02-08 of Motorcycles Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-02 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 1,075,000.00 70,758.90 Signed 2019-07-10 2019-04-30 2019-07-15 2019-05-29 2019-07-30 2019-05-30 2019-09-08 2019-07-30 2019-10-20 2019-08-21 2020-04-17 of Solar Street Light Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03 / Supply and Delivery of Basic Services, installation of Early Steamer Resilient Infrastructure, Single Stage - One / Post Request for Bids Open - National 2,239,000.00 0.00 Canceled 2019-07-13 2019-07-18 2019-08-02 2019-09-11 2019-10-23 2020-04-20 Emission Lightening Emergency Response, and Envelope Protection System Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03A / Supply and Delivery of Basic Services, installation of 90 nos. Early Resilient Infrastructure, Single Stage - One Steamer Emission Lightening IDA / D4190 Post Request for Bids Open - National 537,314.00 411,717.06 Signed 2019-04-25 2019-04-30 2019-04-30 2019-05-29 2019-05-24 2019-05-30 2019-06-23 2019-07-11 2019-08-04 2019-07-30 2020-08-03 Emergency Response, and Envelope Protection System in Rohingya Gender-Based Viol ence Camps Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-12A / Procurement Resilient Infrastructure, Single Stage - One of 1 no. Fire Fighting Turn IDA / D4190 Post Request for Bids Open - National 1,746,000.00 1,638,365.11 Signed 2019-07-30 2019-10-28 2019-08-04 2019-08-24 2019-11-20 2019-10-03 2019-12-26 2019-11-07 2020-02-02 2020-05-05 Emergency Response, and Envelope Table for FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-04A / Procurement Resilient Infrastructure, Single Stage - One of 5 nos. 10000 +1000 Liter IDA / D4190 Post Request for Bids Open - National 2,408,000.00 2,350,486.60 Completed 2019-07-30 2019-07-27 2019-08-04 2019-08-24 2019-08-20 2019-10-03 2019-10-07 2019-11-07 2019-11-04 2020-05-05 2019-11-04 Emergency Response, and Envelope Water Tender Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-11A / Procurement Resilient Infrastructure, Single Stage - One of 6 nos. Rescue Boat for IDA / D4190 Post Request for Bids Open - National 1,499,000.00 0.00 Canceled 2019-07-30 2019-09-03 2019-08-04 2019-08-24 2019-11-26 2019-10-03 2019-11-07 2020-05-05 Emergency Response, and Envelope FSCD Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-1 / Procurement of Resilient Infrastructure, IDA / D4190 Post Direct Selection Direct 68,823.00 68,688.89 Completed 2020-06-07 2018-12-11 2020-06-12 2020-01-13 2020-07-19 2020-06-20 2020-10-17 2020-06-20 34 Motorcycle under EMCRP Emergency Response, and Gender-Based Viol ence Prevention EMCRP/COVID19/G-22 / Component 1: Strengthening Procurement of soap, hand Delivery of Basic Services, sanitizer and disinfectant Resilient Infrastructure, spray for prevention of COVID- IDA / D4190 Post Direct Selection Direct 5,978.00 4,660.05 Completed 2020-05-27 2020-05-19 2020-05-30 2020-05-31 2020-07-04 2020-05-31 2020-07-19 2020-08-30 Emergency Response, and 19 infections in cyclone Gender-Based Viol ence shelters in Cox's Bazar Prevention District. Component 1: Strengthening Delivery of Basic Services, Pending EMCRP/G-13 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 6,000.00 0.00 Implementati 2021-05-10 2021-05-14 2021-05-29 2021-05-31 2021-07-12 2021-09-10 of Computer and accessories Emergency Response, and Envelope on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Pending EMCRP/G-14 / Printers and Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 18,000.00 0.00 Implementati 2021-05-10 2021-05-14 2021-05-29 2021-06-23 2021-08-04 2021-10-03 Photocopy Machines Emergency Response, and Envelope on Gender-Based Viol ence Prevention Page 3 Component 1: Strengthening Delivery of Basic Services, Pending EMCRP/G-15 / Office Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 12,000.00 0.00 Implementati 2021-02-16 2021-02-20 2021-03-07 2021-04-01 2021-05-13 2021-07-12 Furniture Emergency Response, and Envelope on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Pending EMCRP/G-16 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 60,000.00 0.00 Implementati 2020-11-30 2020-12-04 2020-12-24 2021-01-14 2021-02-25 2021-04-26 of Stationery Emergency Response, and Envelope on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Under EMCRP/G-11B / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 1,499,000.00 0.00 Implementati 2020-10-15 2020-10-08 2020-10-18 2020-11-22 2021-01-04 2021-01-09 2021-02-20 2021-08-19 of 6 rescue boats for FSCD Emergency Response, and Envelope on Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-09 / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 255,000.00 0.00 Canceled 2020-08-15 2020-08-27 2020-08-20 2020-09-24 2020-09-21 2020-11-03 2020-10-05 2020-12-15 2021-06-28 of Command Vehicle Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/G-09_ / Procurement Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 255,000.00 187,462.92 Signed 2020-10-30 2020-10-21 2020-11-04 2020-11-22 2020-11-05 2020-12-07 2020-12-30 2021-01-11 2021-01-14 2021-07-10 of two command vehicles Emergency Response, and Envelope Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/G-03B / Supply and Delivery of Basic Services, Installation of 268 nos Early Pending Resilient Infrastructure, Single Stage - One Steamer Emission Lightening IDA / D4190 Post Request for Bids Open - National 1,764,240.00 0.00 Implementati 2021-09-14 2021-09-19 2021-10-17 2021-11-07 2021-12-12 2022-12-12 Emergency Response, and Envelope Protection System in different on Gender-Based Viol ence Rohingya camps Prevention NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, EMCRP/GBV/S2 / Gender Resilient Infrastructure, UN Agencies Based Violance Management IDA / D4190 Prior Direct 8,480,000.00 7,999,951.00 Signed 2019-08-01 2019-07-11 2019-08-06 2019-10-16 2019-10-07 2019-11-12 2021-11-30 Emergency Response, and (Direct) Firm Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/NS-01 / Transport Resilient Infrastructure, Single Stage - One IDA / D4190 Post Request for Bids Open - National 180,000.00 173,906.51 Signed 2019-06-01 2019-11-28 2019-06-06 2019-07-06 2020-01-02 2019-08-05 2020-01-15 2019-09-16 2020-02-04 2022-02-01 rental expenses Emergency Response, and Envelope Gender-Based Viol ence Prevention CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening Delivery of Basic Services, EMCRP/ME/S2 / Monitoring Consultant Resilient Infrastructure, and Evaluation Consultancy IDA / D4190 Post Qualification Open - National 480,000.00 621,765.16 Signed 2019-02-13 2019-05-23 2019-03-06 2019-05-22 2019-04-19 2019-08-19 2019-05-19 2019-12-10 2019-06-30 2019-12-15 2021-12-16 Emergency Response, and Services Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/CIA/S3 / Cumulative Consultant Resilient Infrastructure, Impact Assessment IDA / D4190 Post Qualification Open - National 490,000.00 483,492.42 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-12-31 2019-05-19 2020-01-29 2019-06-30 2020-03-03 2020-03-26 Emergency Response, and Consultancy Services Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/CA/S5 / Delivery of Basic Services, Consultant Communication and Resilient Infrastructure, IDA / D4190 Post Qualification Open - National 360,000.00 353,785.40 Signed 2019-02-13 2019-06-15 2019-03-06 2019-07-17 2019-04-19 2019-10-28 2019-05-19 2020-01-29 2019-06-30 2020-03-05 2021-12-16 Awareness Consultancy Emergency Response, and Selection Services Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Consultant EMCRP/IA/S4 / Appointment Resilient Infrastructure, Pending IDA / D4190 Post Qualification Open - National 20,000.00 0.00 2022-01-02 2022-01-07 2022-03-03 2022-05-02 2022-06-13 2022-09-11 of Internal Audit Firm Emergency Response, and Implementation Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/FS/S7 / Delivery of Basic Services, Consultancy Services for Resilient Infrastructure, Quality And Cost- Feasibility Study of Resilient IDA / D4190 Prior Open - International 3,396,000.00 2,429,875.88 Signed 2020-09-15 2020-09-15 2020-10-15 2020-09-17 2020-12-28 2021-04-27 2021-01-27 2021-03-02 2021-03-28 2021-05-10 2021-05-11 2021-07-27 2021-06-22 2021-09-07 2022-02-17 Emergency Response, and Based Selection Infrastructure Development Gender-Based Viol ence Project (RIDP) Prevention INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 Component 1: Strengthening Delivery of Basic Services, EMCRP/DS/S1 / Design and Resilient Infrastructure, Supervision Consultancy IDA / D4190 Prior Direct Selection Direct 1,650,000.00 1,616,870.20 Signed 2019-02-13 2019-05-23 2019-02-23 2019-05-05 2019-04-19 2019-10-23 2022-01-31 Emergency Response, and Service for EMCRP Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SPS/S2 / Senior Resilient Infrastructure, / Post Consultant Limited 240,000.00 205,711.06 Signed 2019-03-25 2019-05-01 2019-04-04 2019-05-01 2019-04-25 2019-06-16 2019-06-06 2019-06-27 2022-02-15 Procurement Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SDS/S4 / Social Resilient Infrastructure, / Post Consultant Limited 70,000.00 59,102.76 Signed 2019-04-10 2019-05-01 2019-04-20 2019-05-03 2019-05-11 2019-05-26 2019-06-22 2019-06-30 2021-11-30 Development Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/FSDS/S5 / Field Level Resilient Infrastructure, IDA / D4190 Post Consultant Limited 50,000.00 41,100.11 Signed 2019-07-30 2020-01-23 2019-08-09 2020-02-04 2019-08-30 2019-06-10 2019-10-11 2020-03-25 2021-11-30 Social Development Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/FENS/S7 / Field Level Resilient Infrastructure, / Post Consultant Limited 50,000.00 39,629.07 Signed 2019-08-01 2019-05-01 2019-08-11 2019-05-03 2019-09-01 2019-05-26 2019-10-13 2019-06-30 2021-11-30 Environment Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/GS/S8 / Gender Resilient Infrastructure, IDA / D4190 Post Consultant Limited 60,000.00 70,941.25 Signed 2019-08-25 2019-08-01 2019-09-04 2019-09-05 2019-09-25 2019-10-20 2019-11-06 2019-10-20 2021-11-30 Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/CS/S10 / Resilient Infrastructure, / Post Consultant Limited 60,000.00 30,034.25 Signed 2019-06-01 2019-05-01 2019-06-11 2019-05-03 2019-07-02 2019-05-26 2019-08-13 2019-06-30 2021-11-30 Communication Specialist Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/DCCS/S11 / Disaster Resilient Infrastructure, / Post Consultant Limited 40,000.00 34,796.15 Signed 2019-05-01 2019-05-01 2019-05-11 2019-05-03 2019-06-01 2019-05-26 2019-07-13 2019-06-30 2021-11-30 & Climate Change Specialis Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/IPP/INT-1/S12 / Individual Resilient Infrastructure, Procurement Panel IDA / D4190 Post Consultant Direct 80,000.00 80,190.00 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-18 2019-06-06 2019-04-30 2019-12-03 2021-01-20 Emergency Response, and International Member-1 Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/IPP/NAT-1/S14 / Individual Resilient Infrastructure, Procurement Panel National IDA / D4190 Post Consultant Direct 20,000.00 18,246.05 Completed 2019-04-01 2019-05-01 2019-04-11 2019-05-03 2019-05-02 2019-05-20 2019-06-06 2019-04-30 2019-12-03 2021-01-20 Emergency Response, and Member-3 Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual Resilient Infrastructure, EMCRP/GISE/S15 / GIS Expert IDA / D4190 Post Consultant Limited 40,000.00 58,380.21 Signed 2019-08-30 2019-05-30 2019-09-09 2019-06-11 2019-09-30 2019-08-20 2019-11-11 2019-10-20 2021-10-31 Emergency Response, and Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/MIS/S5A / Individual Individual Resilient Infrastructure, Consultancy Services of a MIS IDA / D4190 Post Consultant Direct 1,176.00 12,657.94 Signed 2020-02-16 2020-01-15 2020-02-26 2020-02-04 2020-03-02 2020-03-15 2020-04-06 2020-03-29 2020-10-03 Emergency Response, and Specialist for RAP Preparation Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/NAT-1/S14A / Delivery of Basic Services, Individual Member, National of 2- Resilient Infrastructure, IDA / D4190 Post Consultant Direct 28,236.00 25,014.58 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-04 2020-05-28 2021-02-09 member Independent Emergency Response, and Selection Procurement Panel Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/IPP/INT-1/12A / Delivery of Basic Services, Individual Chairman, 2-member Resilient Infrastructure, IDA / D4190 Post Consultant Direct 120,565.00 120,565.00 Completed 2020-03-01 2020-01-20 2020-03-09 2020-02-02 2020-03-14 2020-03-01 2020-03-24 2020-03-04 2020-05-28 2021-02-09 Procurement Panel Expert, Emergency Response, and Selection International Expert Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/STS/S1 / Senior Delivery of Basic Services, Individual Project Management Resilient Infrastructure, Pending IDA / D4190 Post Consultant Limited 240,000.00 0.00 2020-11-07 2020-11-12 2020-11-26 2021-01-07 2023-02-25 Specialist/Senior Technical Emergency Response, and Implementation Selection Specialist Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/FGS/S9 / Field Level Resilient Infrastructure, Pending IDA / D4190 Post Consultant Limited 50,000.00 0.00 2020-08-10 2020-08-12 2020-08-26 2020-10-07 2022-10-27 Gender Specialist Emergency Response, and Implementation Selection Gender-Based Viol ence Prevention Page 5 Component 1: Strengthening Delivery of Basic Services, Individual EMCRP/SENS/S6 / Senior Resilient Infrastructure, Pending IDA / D4190 Post Consultant Limited 70,000.00 0.00 2020-08-25 2020-08-31 2020-09-21 2020-11-02 2023-01-27 Environment Specialist Emergency Response, and Implementation Selection Gender-Based Viol ence Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/SFMS/S3 / Senior Individual Resilient Infrastructure, Under Financial Management IDA / D4190 Post Consultant Limited 170,000.00 0.00 2020-07-30 2021-01-19 2020-08-02 2020-08-16 2020-09-20 2023-03-10 Emergency Response, and Implementation Specialist Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/INT/S17 / Delivery of Basic Services, Individual Individual Consultancy Resilient Infrastructure, Pending IDA / D4190 Post Consultant Limited 200,720.00 0.00 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 Services for ICT Specialist Emergency Response, and Implementation Selection International Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ICT/S18 / Delivery of Basic Services, Individual Individual Consultancy Resilient Infrastructure, Pending IDA / D4190 Post Consultant Limited 72,000.00 0.00 2020-09-25 2020-09-28 2020-10-19 2020-11-16 2022-11-06 Services for ICT Specialist- Emergency Response, and Implementation Selection Local Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16 / Delivery of Basic Services, Individual Consultancy Services for Resilient Infrastructure, IDA / D4190 Post Consultant Limited 65,000.00 0.00 Canceled 2021-03-15 2021-02-10 2021-03-20 2021-04-04 2021-04-26 2023-10-13 Energy Specialist (Individual Emergency Response, and Selection Consultant) Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/D&S/S1 / Design Delivery of Basic Services, and Supervision Consulting Resilient Infrastructure, Pending IDA / D4190 Prior Direct Selection Direct 2,356,000.00 0.00 2021-02-15 2021-02-25 2021-05-01 2024-01-16 Services of EMCRP under Emergency Response, and Implementation additional financing. Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/M&E/S2 / Delivery of Basic Services, Consulting Services for Resilient Infrastructure, Pending Monitoring and Evaluation IDA / D4190 Post Direct Selection Direct 857,500.00 0.00 2021-02-15 2021-02-25 2021-05-01 2024-01-16 Emergency Response, and Implementation under EMCRP-AF under Gender-Based Viol ence additional Financing. Prevention Component 1: Strengthening Delivery of Basic Services, EMCRP/SPS/S2A / Individual Individual Resilient Infrastructure, Consultancy Services for IDA / D4190 Post Consultant Limited 76,900.00 95,579.82 Signed 2021-02-28 2021-02-22 2021-03-03 2021-03-15 2021-03-18 2021-03-22 2021-04-22 2021-05-03 2023-04-22 Emergency Response, and Senior Procurement Specialist Selection Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/NAT-1/S14 / Delivery of Basic Services, Individual Consultancy Services of Resilient Infrastructure, Pending IDA / D4190 Post Consultant Direct 25,000.00 0.00 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 Procurement Panel Member Emergency Response, and Implementation Selection (National) Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/IPP/INT-1/S12 / Delivery of Basic Services, Individual Consultancy Services of Resilient Infrastructure, Pending IDA / D4190 Post Consultant Direct 86,000.00 0.00 2021-02-28 2021-03-06 2021-03-13 2021-03-27 2021-05-26 Procurement Panel Member Emergency Response, and Implementation Selection (International) Gender-Based Viol ence Prevention Component 1: Strengthening EMCRP/AF/ES/S16. / Delivery of Basic Services, Individual Consultancy Services for Resilient Infrastructure, Under IDA / D5900 Post Consultant Limited 65,000.00 0.00 2021-09-01 2021-09-01 2021-09-06 2021-09-06 2021-09-20 2021-10-18 2024-04-15 Energy Specialist (Individual Emergency Response, and Implementation Selection Consultant). Gender-Based Viol ence Prevention Page 6