Procurement Plan Project Name: Myanmar Electric Power Project (P143988) I. General 2. Bank’s approval Date of the procurement Plan :Original August 27, 2013, Revised : September 22, 2016 3. Date of General Procurement Notice: October 23, 2013 4. Period covered by this procurement plan: Till December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement (US $ ) Works (Including turnkey supply and installation of plant and 2,000,000 equipment and PPP) ( 2 million) Goods, information technology and non-consulting services 1,000,000 ( 1million) Consultant firms 300,000 Consultant Individuals 200,000 Type of Market Approaches Thresholds Procurement (US $ in million) International National- National Comments Open RFQ (Shopping) Works (Including 3 and above Less than 3 Less than 1 Recommended to turnkey supply and advertise for 7 days for installation of plant RFQ above 0.5 and equipment and PPP) Goods, information 1 and above Less than 1 Less than 0.5 Recommended to technology and non- advertise for 7 days for consulting services RFQ above 0.05 Consultants (Firms) 0.1 and above Less than 0.1 Not CQS method may be applicable used up to 0.5. Use of full RFP mandatory for CQS above 0.3. Limits on market approaches do not apply to individual consultants. 2. Reference to (if any) Project Operational Manual (POM): TBD 3. Any Other Special Procurement Arrangements: N/A 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) 1 Summary of 0.32 1 No Post Shopping Goods 2 Summary of 4.2 1 No Prior the Goods (Direct Contracting) 5. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 0.5 7 Prior number of contracts that will be let under QCBS 2 Summary of 0.4 2 Post CQS number of contracts that will be let under other methods PROCUREMENT Myanmar : Electric Power Project PLAN General Information Country: Myanmar Banks Approval Date of the Original Procurement Plan: 2017-04-28 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-17 Project ID: P143988 GPN Date: Project Name: Electric Power Project Loan / Credit No: IDA / 53060 Executing Agency(ies): Electric Power Generation Enterprise WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MEPPSI-2 / Thaton 230/33 100 1. Combined Cycle Gas Turbine MVA Transformer and associated IDA / 53060 Prior Direct Selection Direct 4,200,000.00 4,200,000.00 Signed 2017-12-30 2018-01-04 2018-02-08 2018-05-11 2018-08-07 (CCGT) Power Plant switch yard extension 1. Combined Cycle Gas Turbine Request for Single Stage - One Pending MEPE-G3 / Gas Meters IDA / 53060 Post Open - National 500,000.00 0.00 2018-02-04 2018-04-01 2018-09-28 (CCGT) Power Plant Quotations Envelope Implementation G-04 / 33kV Energy Meters 1. Combined Cycle Gas Turbine Request for Single Stage - One Pending (27)Nos and 33kV Current IDA / 53060 Post Open - National 352,800.00 0.00 2018-04-30 2018-06-25 2018-12-22 (CCGT) Power Plant Quotations Envelope Implementation Transformers (24)Sets G-05 / 66kV Energy Meters and 1. Combined Cycle Gas Turbine Request for Single Stage - One Pending IDA / 53060 Post Open - National 487,000.00 0.00 2018-04-30 2018-06-25 2018-12-22 66kV Current Transformers (CCGT) Power Plant Quotations Envelope Implementation G-06 / Relay test set and Commisioning Tool, Transformer 1. Combined Cycle Gas Turbine Request for Single Stage - One Pending IDA / 53060 Post Open - National 484,000.00 0.00 2018-04-30 2018-06-25 2018-12-22 Oil purifier and Turbine Oil purifier (CCGT) Power Plant Quotations Envelope Implementation for Ywama & Thaton Power Plant G-07 / Battery Bank and Battery 1. Combined Cycle Gas Turbine Request for Single Stage - One Pending IDA / 53060 Post Open - National 495,000.00 0.00 2018-04-30 2018-06-25 2018-12-22 Charger (15)Sets (CCGT) Power Plant Quotations Envelope Implementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Combined Cycle Gas Turbine (CCGT) Power Plant Quality And Cost- CS-8 / Owners Engineer IDA / 53060 Prior Open - International N 0.00 2,386,634.36 Signed 2016-11-09 2016-11-18 2. Technical Assistance and Based Selection Advisory Services 1. Combined Cycle Gas Turbine MEPE-CS-02 / Myanmar Power (CCGT) Power Plant Quality And Cost- Sector Financial Analysis and IDA / 53060 Prior Open - International N 189,940.00 180,540.00 Signed 2015-06-22 2015-07-15 2. Technical Assistance and Based Selection Viability Action Plan Advisory Services 1. Combined Cycle Gas Turbine MEPE-CS-05 / Environmental (CCGT) Power Plant Quality And Cost- IDA / 53060 Prior Open - International N 500,000.00 753,655.72 Signed 2016-02-04 2016-06-24 and Social Safeguards 2. Technical Assistance and Based Selection Advisory Services 1. Combined Cycle Gas Turbine (CCGT) Power Plant Quality Based Under CS4 / TA on Electricity Tariffs IDA / 53060 Prior Open - International N 300,000.00 746,200.00 2016-09-01 2. Technical Assistance and Selection Implementation Advisory Services MEPP-CS-10 / TA on 2. Technical Assistance and Quality And Cost- Pending Independent Power Producer IDA / 53060 Prior Open - International 500,000.00 0.00 2018-01-29 2018-02-19 2018-04-04 2018-05-02 2018-06-01 2018-07-06 2018-08-10 2019-08-10 Advisory Services Based Selection Implementation (IPP) Administration MEPP-CS-11 / Environmental Consultant 2. Technical Assistance and Pending and Social Impact Assessment IDA / 53060 Post Qualification Open - International 200,000.00 0.00 2017-11-09 2017-12-09 2018-02-05 2018-03-07 2018-05-05 2018-11-01 Advisory Services Implementation TA Selection MEPP-CS-12 / Feasibility Study Consultant of Pilot Floating Solar Project for 2. Technical Assistance and IDA / 53060 Post Qualification Open - International 200,000.00 0.00 Canceled 2018-01-29 2018-02-19 2018-04-04 2018-05-04 2018-06-08 2018-12-05 Shwe Kyin Dam, and Zaung Tu Advisory Services Selection Dam INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 1. Combined Cycle Gas Turbine MEPE-CS-7 (Revised) / (CCGT) Power Plant Individual Consultant International Financial IDA / 53060 Prior Open N 0.00 85,500.00 Signed 2016-06-17 2016-08-01 2. Technical Assistance and Selection Management Specialist Advisory Services Page 2