50678 Project Name: Wenchuan Earthquake Resconstruction Project (Sichuan Component) 6.800 Component: Health Component TTL: Mara. K. Wrick Subject: Tentative Procurement Plan for Good, Works and Consultancy Services Date: 1 2 3 5 6 8 9 10 12 13 14 15 16 Prior / District / Batch Building Reforcing Pre.Design Bidding Const. Start Const. End Ref. No. Municipal Con. No. Estimated Cost Proc. Method Post Remark County Number Area Area Complete Complete Date Date Review Sqm (RMB million) (US$ million) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) A) Construction of Works for Hospital, MCH Center and THC 326.40 48.00 1 CD DY One DY-C1 8.98 1.32 NCB/Works Prior 2009/04/01 2009/09/09 2009/09/29 2010/02/08 2 MY FC One FC-C1 2800 6276 14.04 2.06 NCB/Works Prior 2009/03/20 2009/09/09 2009/09/29 2010/01/08 3 MY YX One YX-C1 4800 2409 12.46 1.83 NCB/Works Prior 2009/03/21 2009/08/20 2009/09/09 2010/01/08 4 MY ST One ST-C1 12974 0 36.12 5.31 NCB/Works Prior 2009/04/05 2009/08/20 2009/09/09 2010/02/07 5 MY ZT One ZT-C1 2430 1026 4.30 0.63 NCB/Works Prior 2009/03/28 2009/08/20 2009/09/09 2010/01/08 6 MY YT One YT-C1 3500 0 10.88 1.60 NCB/Works Prior 2009/03/26 2009/08/20 2009/09/09 2010/01/08 7 NC LZ One LZ-C1 5072 3732 15.34 2.26 NCB/Works Prior 2009/03/13 2009/09/09 2009/09/29 2010/01/08 8 DY GH One GH-C1 7778 0 15.94 2.34 NCB/Works Prior 2009/02/25 2009/08/20 2009/09/09 2010/01/08 9 DY JY One JY-C1 17793 0 28.83 4.24 NCB/Works Prior 2009/03/20 2009/08/20 2009/09/09 2010/01/08 10 DY LJ One LJ-C1 9606 0 15.72 2.31 NCB/Works Prior 2009/03/20 2009/09/09 2009/09/29 2010/01/08 11 DY ZJ One ZJ-C1 21648 0 31.93 4.70 NCB/Works Prior 2009/03/30 2009/08/20 2009/09/09 2010/01/08 12 GY CX One CX-C1 12800 0 27.85 4.10 NCB/Works Prior 2009/04/30 2009/09/09 2009/09/29 2010/01/08 13 GY YB One YB-C1 2708 0 4.73 0.70 NCB/Works Prior 2009/04/05 2009/09/09 2009/09/29 2010/01/08 14 GY CT One CT-C1 10000 5700 30.52 4.49 NCB/Works Prior 2009/03/25 2009/08/20 2009/09/09 2010/01/08 15 GY WC One WC-C1 12800 700 25.46 3.74 NCB/Works Prior 2009/04/02 2009/09/09 2009/09/29 2010/01/08 16 YA SM One SM-C1 5688 0 16.92 2.49 NCB/Works Prior 2009/03/15 2009/09/09 2009/09/29 2010/01/08 17 YA LS One LS-C1 4911 0 10.12 1.49 NCB/Works Prior 2009/03/20 2009/09/09 2009/09/29 2010/01/08 18 YA BX One BX-C1 1200 0 5.93 0.87 NCB/Works Prior 2009/03/20 2009/09/09 2009/09/29 2010/01/08 19 BZ NJ One NJ-C1 6300 311 10.34 1.52 NCB/Works Prior 2009/03/20 2009/09/09 2009/09/29 2010/01/08 Project Name: Wenchuan Earthquake Resconstruction Project (Sichuan Component) 6.800 Component: Health Component TTL: Mara. K. Wrick Subject: Tentative Procurement Plan for Good, Works and Consultancy Services Date: 1 2 3 5 6 8 9 10 12 13 14 15 16 Prior / District / Batch Building Reforcing Pre.Design Bidding Const. Start Const. End Ref. No. Municipal Con. No. Estimated Cost Proc. Method Post Remark County Number Area Area Complete Complete Date Date Review Sqm (RMB million) (US$ million) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) B) Procurement of Medical Equipment and Facilities for Hospital, MCH Center and THC 81.60 10.98 1 CD DY Two DY-G1 2.24 0.33 NCB/Goods Prior 2009/04/01 2009/06/30 2009/07/01 2010/01/08 2 MY FC Two FC-G1 3.51 0.30 Shopping Prior 2009/03/20 2009/06/01 2009/07/02 2010/01/08 3 MY YX Two YX-G1 3.11 0.46 NCB/Goods Prior 2009/03/21 2009/06/01 2009/07/03 2010/01/08 4 MY ST Two ST-G1 9.03 1.33 NCB/Goods Prior 2009/04/05 2009/07/01 2009/07/04 2010/02/07 5 MY ZT Two ZT-G1 1.07 0.16 Shopping Prior 2009/03/28 2009/06/01 2009/07/05 2010/01/08 6 MY YT Two YT-G1 2.72 0.40 NCB/Goods Prior 2009/03/26 2009/06/02 2009/07/06 2010/01/08 7 NC LZ Two LZ-G1 3.84 0.56 NCB/Goods Prior 2009/03/13 2009/07/01 2009/07/07 2010/01/08 8 DY GH Two GH-G1 3.98 0.59 NCB/Goods Prior 2009/02/25 2009/06/01 2009/07/08 2010/01/08 9 DY JY Two JY-G1 7.21 1.06 NCB/Goods Prior 2009/03/20 2009/06/01 2009/07/09 2010/01/08 10 DY LJ Two LJ-G1 3.93 0.58 NCB/Goods Prior 2009/03/20 2009/06/01 2009/07/10 2010/01/08 11 DY ZJ Two ZJ-G1 7.98 1.17 NCB/Goods Prior 2009/03/30 2009/06/01 2009/07/11 2010/01/08 12 GY CX Two CX-G1 6.96 1.02 NCB/Goods Prior 2009/04/30 2009/07/01 2009/07/12 2010/01/08 13 GY YB Two YB-G1 1.18 0.17 Shopping Prior 2009/04/05 2009/06/01 2009/07/13 2010/01/08 14 GY CT Two CT-G1 7.63 0.81 NCB/Goods Prior 2009/03/25 2009/06/01 2009/07/14 2010/01/08 15 GY WC Two WC-G1 6.36 0.73 NCB/Goods Prior 2009/04/02 2009/06/01 2009/07/15 2010/01/08 16 YA SM Two SM-G1 4.23 0.62 NCB/Goods Prior 2009/03/15 2009/06/01 2009/07/16 2010/01/08 17 YA LS Two LS-G1 2.53 0.18 Shopping Prior 2009/03/20 2009/06/01 2009/07/17 2010/01/08 18 YA BX Two BX-G1 1.48 0.12 Shopping Prior 2009/03/20 2009/06/01 2009/07/18 2010/01/08 19 BZ NJ Two NJ-G1 2.58 0.38 NCB/Goods Prior 2009/03/20 2009/06/01 2009/07/19 2010/01/08 Project Name: Wenchuan Earthquake Resconstruction Project (Sichuan Component) 6.800 Component: Health Component TTL: Mara. K. Wrick Subject: Tentative Procurement Plan for Good, Works and Consultancy Services Date: 1 2 3 5 6 8 9 10 12 13 14 15 16 Prior / District / Batch Building Reforcing Pre.Design Bidding Const. Start Const. End Ref. No. Municipal Con. No. Estimated Cost Proc. Method Post Remark County Number Area Area Complete Complete Date Date Review Sqm (RMB million) (US$ million) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) (mm/dd/yy) C) Consultancy services contracts EOI RFP Evaluation Start Date 1 PPMO TA-01 0.20 CQs/Service Prior 2009/03/28 2009/04/15 2009/04/30 2009/05/15 SUMMARY FOR HEALTH BATCH ONE 1 Retroactive financing contracts 0 0.00 2 NCB/Works contracts 19 48.00 3 NCB/Goods contracts 14 10.04 4 Shopping contracts 5 0.93 5 CQs/Service 1 0.20 6 Prior review contracts 38 59.18 7 Ex-post review contracts 0 0.00 8 Total 38 59.18