PROCUREMENT PLAN Project information: Mozambique, Smallholder Irrigated Agriculture and Market Access Project, Grant Number D3510-MZ. Project Implementation agency: Ministry of Agriculture and Food Security-AIMU-Agriculture Investment Management Unit. Date of the Procurement Plan: April 5, 2019. Period covered by this Procurement Plan:18 (Eighteen months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Mozambique Procurement Regulations, Decree 5/2016 of March 8, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable . PROCUREMENT Mozambique : Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2019-04-25 2020-07-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164431 GPN Date: Project Name: Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 Loan / Credit No: IDA / D3510 Executing Agency(ies): NATIONAL INSTITUTE OF IRRIGATION WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-INIR-180497-CW-RFB / Chiverano Irrigation System Component 2-Smallholder Pending Single Stage - One Construction, 110 Ha, IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,000,000.00 0.00 Implementat 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 Envelope Mopeia District, Zambezia Management ion Province MZ-INIR-180508-CW-RFB / M´ziva Irrigation System Component 2-Smallholder Pending Single Stage - One Construction, 165 Ha, IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,300,000.00 0.00 Implementat 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 Envelope Nicoadala District, Zambezia Management ion Province MZ-INIR-180509-CW-RFB / Component 2-Smallholder Pending Acaboco Irrigation System Single Stage - One IDA / D3510 Irrigation Development and Post Request for Bids Open - National 2,500,000.00 0.00 Implementat 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 Construction, 314 Ha, Buzi Envelope Management ion District, Sofala Province MZ-INIR-174293-CW-RFB / Component 2-Smallholder Pending Five Irrigation System Single Stage - One IDA / D3510 Irrigation Development and Post Request for Bids Open - National 2,690,000.00 0.00 Implementat 2020-08-10 2020-08-15 2020-09-26 2020-10-26 2020-11-30 2021-05-29 Construction in Manica Envelope Management ion Province MZ-INIR-174295-CW-RFB / Component 2-Smallholder Pending Rehabilitating IRRIGA Request for Single Stage - One IDA / D3510 Irrigation Development and Post Limited 170,000.00 0.00 Implementat 2020-08-15 2020-10-10 2021-04-08 Project Office in Zambezia Quotations Envelope Management ion Province MZ-INIR-174296-CW-RFB / Component 2-Smallholder Pending Rehabilitating IRRIGA Request for Single Stage - One IDA / D3510 Irrigation Development and Post Limited 150,000.00 0.00 Implementat 2020-08-15 2020-10-10 2021-04-08 Project Office in Manica Quotations Envelope Management ion Province GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109235-GO-RFQ / Equipamento informático (16 Component 4- Project Under Request for Single Stage - One Computadores tipo Laptop, 6 IDA / D3510 Management and Monitoring Post Limited 78,900.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope Datashow, 6 Impressoras e 5 and Evaluation on Video Conferencias) MZ-INIR-109256-GO-RFQ / Component 4- Project Under Request for Single Stage - One Aquisição de 5 Smart TV IDA / D3510 Management and Monitoring Post Limited 7,500.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope (Televisores) and Evaluation on Page 1 MZ-INIR-129230-GO-RFQ / Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 950,000.00 393,283.34 Signed 2019-09-14 2019-09-23 2019-11-09 2019-12-03 2020-05-07 Purchase of Production Kits Capacity Building Quotations Envelope MZ-INIR-129114-GO-RFB / Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 300,000.00 236,899.15 Signed 2019-09-09 2019-12-16 2019-09-14 2020-01-08 2019-10-26 2020-02-06 2019-11-25 2020-02-27 2019-12-30 2020-03-06 2020-06-27 Purchase of 55 Motorcycles Capacity Building Envelope MZ-INIR-139505-GO-RFQ / Aquisition of computer Component 1-Institutional Request for Single Stage - One equipment for the IDA / D3510 Post Limited 100,000.00 112,209.52 Signed 2019-10-21 2019-11-14 2019-12-16 2019-12-17 2020-06-13 Capacity Building Quotations Envelope elaboration of the integrated agrarian survey MZ-INIR-140873-GO-RFQ / Acquisition of Protective Component 1-Institutional Request for Single Stage - One Material for Extension IDA / D3510 Post Limited 100,000.00 0.00 Canceled 2019-11-02 2019-12-28 2020-06-25 Capacity Building Quotations Envelope Technicians in Manica and Sofala Provinces MZ-INIR-109253-GO-RFB / Component 4- Project Single Stage - One Aquisicao de 6 Viaturas IDA / D3510 Management and Monitoring Post Request for Bids Open - National 240,000.00 0.00 Canceled 2019-04-11 2019-06-06 2019-04-16 2019-08-26 2019-05-28 2019-06-27 2019-08-01 2020-01-28 Envelope 4X4, Dupla Cabine. and Evaluation MZ-INIR-146499-GO-RFB / Acquisition of Protective Material for Extension Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 200,000.00 187,317.36 Signed 2019-11-28 2019-12-16 2019-12-03 2020-01-08 2020-01-14 2020-02-04 2020-02-13 2020-04-03 2020-03-19 2020-06-04 2020-09-15 Technicians in Manica, Capacity Building Envelope Sofala, Zambezia and Nampula Provinces MZ-INIR-146504-GO-RFB / Component 4- Project Purchase of 6 (six) 4x4 Single Stage - One IDA / D3510 Management and Monitoring Post Request for Bids Open - National 290,000.00 333,854.45 Signed 2019-11-29 2019-12-17 2019-12-04 2020-01-08 2020-01-15 2020-02-05 2020-02-14 2020-02-13 2020-03-20 2020-02-26 2020-09-16 double cab vehicles and one Envelope and Evaluation (01) Mini Bus MZ-INIR-166426-GO-RFQ / Supply and installation of integrated sound and video Under Component 1-Institutional Request for Single Stage - One system for the Consultative IDA / D3510 Post Limited 35,000.00 0.00 Implementati 2020-04-15 2020-04-08 2020-06-10 2020-12-07 Capacity Building Quotations Envelope Council of Meeting Room of on the Ministry of Agriculture and Rural Development MZ-INIR-109262-GO-RFQ / Component 4- Project Under Aquisição de Software de Request for Single Stage - One IDA / D3510 Management and Monitoring Post Limited 40,000.00 0.00 Implementati 2020-07-05 2020-06-10 2020-08-30 2021-02-26 Gestão Financeira Quotations Envelope and Evaluation on (Parametrização) MZ-INIR-180461-GO-RFQ / Under Acquisition of Information Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 20,000.00 0.00 Implementati 2020-07-18 2020-07-10 2020-09-12 2021-03-11 Equipment for the Fund Capacity Building Quotations Envelope on Mobilization Unit MZ-INIR-180512-GO-RFB / Acquisition and Installation Component 2-Smallholder Open - Single Stage - One Under of 6 Pivo Systems for IDA / D3510 Irrigation Development and Prior Request for Bids 2,750,000.00 0.00 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 International Envelope Review Irrigating 330ha, Chemba Management District, Sofala Province NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-129100-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Under Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 300,000.00 0.00 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2020-04-17 Based Selection Implementation Irrigation Systems Affected Management by IDAI Cyclone in Manica Province MZ-INIR-129103-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Under Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 0.00 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2020-03-16 Based Selection Implementation Irrigation Systems Affected Management by IDAI Cyclone in Sofala Province MZ-INIR-129104-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Under Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 0.00 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-01-03 2020-02-07 2020-03-13 2020-04-17 Based Selection Implementation Irrigation Systems Affected Management by IDAI Cyclone in Zambezia Province MZ-INIR-129111-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection and Feasibility Studies in Management Sofala Province. MZ-INIR-129110-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection and Feasibility Studies in Management Zambezia Province. MZ-INIR-129106-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection and Feasibility Studies in Management Nampula Province. MZ-INIR-129112-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection and Feasibility Studies in Management Manica Province. MZ-INIR-146515-CS-CQS / Contracting a company to Component 4- Project Consultant recruit technicians for the IDA / D3510 Management and Monitoring Post Qualification Open - National 100,000.00 0.00 Canceled 2019-12-23 2019-12-17 2020-01-13 2020-02-26 2020-03-27 2020-05-01 2020-10-28 IRRIGA Project at central and Evaluation Selection and provincial levels MZ-INIR-146523-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- Open - projects for IDA / D3510 Irrigation Development and Prior 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection International construction/rehabilitation of Management 750 hectares of irrigation systems in Nampula province and Supervision of the respective works Page 3 MZ-INIR-146521-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- Open - projects for IDA / D3510 Irrigation Development and Prior 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection International construction/rehabilitation of Management 750 hectares of irrigation systems in Zambezia province and Supervision of the respective works MZ-INIR-146520-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- Open - projects for IDA / D3510 Irrigation Development and Prior 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection International construction/rehabilitation of Management 750 hectares of irrigation systems in Manica province and Supervision of the respective works MZ-INIR-146518-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- Open - projects for IDA / D3510 Irrigation Development and Prior 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection International construction/rehabilitation of Management 750 hectares of irrigation systems in Sofala province and Supervision of the respective works MZ-INIR-183480-CS-CQS / Component 2-Smallholder Consultant Pending Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Qualification Limited 360,000.00 0.00 2020-07-30 2020-08-13 2020-09-12 2020-10-17 2021-04-15 Implementation System Supervision Management Selection MZ-INIR-180472-CS-QCBS / Component 2-Smallholder Five Irrigation System Quality And Cost- Pending IDA / D3510 Irrigation Development and Post Open - National 270,000.00 0.00 2020-08-31 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Supervision in Manica Based Selection Implementation Management Province MZ-INIR-180481-CS-CQS / Component 2-Smallholder Consultant Pending Environmental Audit of IDA / D3510 Irrigation Development and Post Qualification Limited 90,000.00 0.00 2020-08-31 2020-09-14 2020-10-14 2020-11-18 2021-05-17 Implementation PROIRRI irrigations Management Selection MZ-INIR-180484-CS-CQS / Component 2-Smallholder Consultant Resettlement Action Plan Pending IDA / D3510 Irrigation Development and Post Qualification Limited 50,000.00 0.00 2020-08-31 2020-09-14 2020-10-14 2020-11-18 2021-05-17 (PAR) for the Chirimonio - Implementation Management Selection ACABOCO Irrigation MZ-INIR-180476-CS-QCBS / Component 2-Smallholder Quality And Cost- Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Open - National 360,000.00 0.00 Canceled 2020-07-20 2020-07-15 2020-08-10 2020-09-23 2020-10-21 2020-11-20 2020-12-25 2021-01-29 2022-01-29 Based Selection System Supervision Management INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109288-CS-INDV / Individual Component 1-Institutional Especialista em Procurement IDA / D3510 Prior Consultant Open 90,000.00 0.00 Canceled 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 Capacity Building (baseado em Maputo) Selection Page 4 MZ-INIR-129523-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Acaboco IDA / D3510 Irrigation Development and Post Direct Selection Direct 45,000.00 50,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-30 2019-12-16 Irrigation System Works Management Completion Project, 316 ha, Buzi District, Sofala Province MZ-INIR-129528-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Mziva and IDA / D3510 Irrigation Development and Post Direct Selection Direct 90,000.00 90,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-18 2019-12-16 Chiverano Irrigation System Management Works Completion Project, Zambeze Province MZ-INIR-139499-CS-INDV / Component 3-Agriculture Individual Hire a consultant to boost IDA / D3510 Intensification and Market Post Consultant Limited 30,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 the 2019/2020 agricultural Linkages Selection company in Manica Province MZ-INIR-139496-CS-INDV / Hire a consultant to boost Component 3-Agriculture Individual the 2019/2020 agricultural IDA / D3510 Intensification and Market Post Consultant Limited 35,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 company in Sofala and Linkages Selection Zambezia Provinces MZ-INIR-140872-CS-CDS / Service provider for the preparation of PEDSA II Component 2-Smallholder and PNISA II as part of the IDA / D3510 Irrigation Development and Post Direct Selection Direct 300,000.00 0.00 Canceled 2019-12-10 2019-12-20 2020-02-23 2020-08-21 institutional support to Management DPCI. Services performed via UN system. Individual MZ-INIR-150739-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Limited 72,000.00 0.00 Canceled 2019-12-22 2020-02-11 2019-12-27 2020-02-13 2020-01-17 2020-02-21 2020-08-19 Procurement Specialist Capacity Building Selection MZ-INIR-153140-CS-CDS / Service Provider for Component 3-Agriculture Operation of da Paz IDA / D3510 Intensification and Market Post Direct Selection Direct 180,000.00 199,447.47 Signed 2020-01-26 2020-01-17 2020-02-05 2020-01-22 2020-04-10 2020-03-30 2020-10-07 Irrigation in Zambezia Linkages Province Individual MZ-INIR-167041-CS-INDV / Component 1-Institutional Under IDA / D3510 Prior Consultant Open 72,000.00 0.00 2020-05-18 2020-05-05 2020-07-06 2020-07-27 2020-08-31 2021-02-27 Procurement Specialist Capacity Building Implementation Selection MZ-INIR-175070-CS-CDS / Organising and Building Component 3-Agriculture Under Capacity of Producers and IDA / D3510 Intensification and Market Post Direct Selection Direct 100,000.00 0.00 2020-06-30 2020-06-30 2020-07-10 2020-09-13 2021-03-12 Implementation Establishing Market Linkages Linkages in Manica Province MZ-INIR-178882-CS-INDV / Individual Component 1-Institutional Under Monitoring and Evaluation IDA / D3510 Post Consultant Limited 57,600.00 0.00 2020-07-13 2020-06-24 2020-07-18 2020-08-08 2020-09-12 2021-03-11 Capacity Building Implementation Specialist Selection MZ-INIR-178865-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 144,000.00 0.00 Under Review 2020-07-13 2020-06-24 2020-07-18 2020-08-08 2020-09-12 2021-03-11 Capacity Building Coordinator Selection MZ-INIR-178878-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 0.00 Under Review 2020-07-13 2020-06-24 2020-07-18 2020-08-08 2020-09-12 2021-03-11 Capacity Building Environment Management Selection Page 5 MZ-INIR-178874-CS-INDV / Individual Component 1-Institutional Under Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 0.00 2020-07-13 2020-06-24 2020-07-18 2020-08-08 2020-09-12 2021-03-11 Capacity Building Implementation Finance Management Selection Individual MZ-INIR-178872-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Limited 72,000.00 0.00 2020-07-13 2020-06-24 2020-07-18 2020-08-08 2020-09-12 2021-03-11 P4R Unit Coordinator Capacity Building Implementation Selection Individual MZ-INIR-109291-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Direct 36,000.00 0.00 Canceled 2019-05-23 2019-06-02 2019-06-23 2019-07-28 2020-01-24 Procurement Assistant Capacity Building Selection Page 6