PROCUREMENT PLAN (Textual Part) Project information: Lebanon- Roads and Employment Project- P160223 Project Implementation agency: Council for Development and Reconstruction- CDR Date of the Procurement Plan: Initial plan of 22-Jan-19 Period covered by this Procurement Plan: From effectiveness Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Accounting Law of 1963 and Subsequent amendments, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable Other Relevant Procurement Information. Procurement methods and prior review thresholds Market approach Shortlist composed Goods, IT and non-consulting Works only of national services consultants Internatio Engineeri National nal and ng & Open Open Consulti Open Open national Construct internatio internatio ng national national ion nal (shoppi nal (shopping services supervisi ng) ) on US$ US$ US$ US$ US$ US$ US$ US$ Method ≥10,000,0 <10,000, ≤200,00 ≥1,000,00 < 1,000, < 300,00 Threshold ≤100,000 ≤500,000 00 000 0 0 000 0 s Proc. All RFB RFB RFQ RFB RFB RFQ QCBS Method methods Proc prior Firms >2,000,000 >15,000,000 >4,000,000 review Ind. >400,000 PROCUREMENT Lebanon : Roads and Employment Project PLAN General Information Country: Lebanon Bank’s Approval Date of the Original Procurement Plan: 2019-01-30 2021-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160223 GPN Date: 2019-02-13 Project Name: Roads and Employment Project Loan / Credit No: IBRD / 87050, TF / A4481 C Executing Agency(ies): ouncil for Development and Reconstruction WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PW001 / Works - Lot 1- Component 1: Roads Single Stage - One 15,583,129. 2021-12- Package 1 (Kesrouan and El TF / A4481 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-13 2020-03-05 2020-02-18 2020-03-12 2020-03-31 2020-06-30 2020-04-30 2020-07-29 2020-06-04 2020-09-22 Envelope 55 03 Metn) Maintenance Component 1: Roads PW002 / Works - Lot 1- Single Stage - One 7,521,113.7 2021-09- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-13 2020-03-05 2020-02-18 2020-03-12 2020-04-03 2020-06-30 2020-05-03 2020-07-29 2020-06-07 2020-09-14 Package 2 (Jbeil) Envelope 5 06 Maintenance Component 1: Roads Under PW003 / Works - Lot 2- Single Stage - One 2022-02- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-05-01 2020-11-06 2020-05-06 2020-11-24 2020-06-17 2020-12-18 2020-07-17 2021-03-10 2020-08-20 Package 1 (Aley and Chouf) Envelope 19 Maintenance ion Component 1: Roads Under PW004 / Works - Lot 2- Single Stage - One 2021-11- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-04-14 2020-11-06 2020-04-19 2020-11-24 2020-05-31 2020-12-17 2020-06-30 2020-08-04 Package 2 (Baabda and Zahle) Envelope 03 Maintenance ion PW005 / Works - Lot 3A- Component 1: Roads Single Stage - One 7,359,677.5 2020-12- Package 1 (Nabatiye and IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-20 2020-04-21 2020-02-25 2020-06-08 2020-04-20 2020-07-08 2020-05-20 2020-08-07 2020-07-03 2020-09-14 Envelope 0 30 Marjaayoun) Maintenance PW006 / Works - Lot 3A- Component 1: Roads Under Single Stage - One 2022-02- Package 2 (West Bekaa and IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-05-01 2020-11-06 2020-05-06 2020-11-24 2020-06-17 2020-12-18 2020-07-17 2020-08-20 Envelope 19 Rachaya and Hasbaya) Maintenance ion PW007 / Works - Lot 3B- Component 1: Roads Under Single Stage - One 2021-11- Package 1 (Sour and Bent IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-05-01 2020-11-06 2020-05-06 2020-11-24 2020-06-17 2020-12-18 2020-07-17 2021-03-11 2020-08-20 Envelope 19 Jbail) Maintenance ion Component 1: Roads Under PW008 / Works - Lot 3B- Single Stage - One 2022-02- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-05-01 2020-11-06 2020-05-06 2020-11-24 2020-06-17 2020-12-18 2020-07-17 2021-03-11 2020-08-20 Package 2 (Jezzine and Saida) Envelope 19 Maintenance ion Component 1: Roads PW009 / Works - Lot 4- Single Stage - One 6,762,501.7 2021-09- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-13 2020-03-05 2020-02-18 2020-03-12 2020-03-31 2020-06-30 2020-04-30 2020-08-07 2020-06-04 2020-09-14 Package 1 (Akkar) Envelope 5 03 Maintenance PW010 / Works - Lot 4- Component 1: Roads Single Stage - One 9,435,675.0 2021-10- Package 2 (Minieh- Dinnieh IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-20 2020-04-21 2020-03-01 2020-06-08 2020-04-25 2020-07-08 2020-05-25 2020-10-06 2020-07-03 2020-12-09 Envelope 0 02 and Zgharta) Maintenance Component 1: Roads Under PW011 / Works - Lot 5- Single Stage - One 2022-02- IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-04-14 2020-11-06 2020-04-19 2020-11-24 2020-05-31 2020-12-17 2020-06-30 2021-03-11 2020-08-04 Package 1 (Tripoli and Koura) Envelope 03 Maintenance ion PW012 / Works - Lot 5- Component 1: Roads Single Stage - One 10,343,732. 2022-01- Package 2 (Batroun and IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National Signed 2020-02-20 2020-04-21 2020-02-25 2020-06-08 2020-04-20 2020-07-08 2020-05-20 2020-08-07 2020-07-03 2020-09-14 Envelope 60 02 Bcharre) Maintenance PW013 / Works - Lot 6- Component 1: Roads Under Single Stage - One 2022-02- Package 1 (Hermel and IBRD / 87050 Rehabilitation and Prior Request for Bids Open - National 0.00 Implementat 2020-04-14 2020-11-06 2020-04-19 2020-11-24 2020-05-31 2020-12-17 2020-06-30 2021-03-11 2020-08-04 Envelope 03 Baalbek) Maintenance ion GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSH001 / 10 vehicles Four Component 2: Improving Wheels Drive, for the Ministry Single Stage - One IBRD / 87050 Road Emergency Response Post Request for Bids Open - International 0.00 Canceled 2018-04-01 2018-04-01 2019-01-17 2019-01-31 2019-02-21 2019-02-21 2019-04-07 2019-03-12 2019-06-20 2019-10-18 of Public Works and Transport Envelope Capacity (MoPWT). PSH005 / 5 salt spreaders For Component 2: Improving Single Stage - One the Ministry of Public Works IBRD / 87050 Road Emergency Response Post Request for Bids Open - International 627,135.59 Signed 2018-12-03 2019-01-20 2019-02-14 2019-02-12 2019-03-31 2019-03-19 2019-04-30 2019-06-20 2019-06-27 2019-08-23 2019-12-24 Envelope and Transport (MoPWT) Capacity PSH003 / 15 Wheel loaders, Component 2: Improving Single Stage - One for the Ministry of Public IBRD / 87050 Road Emergency Response Post Request for Bids Limited 2,274,615.90 Signed 2018-04-01 2018-12-20 2018-04-06 2019-01-11 2018-05-18 2019-02-22 2018-06-17 2019-03-14 2018-07-22 2019-06-12 2019-01-18 Envelope Works and Transport (MoPWT) Capacity PSH004 / 10 Snow blowers Component 2: Improving Single Stage - One for the Ministry of Public TF / A4481 Road Emergency Response Post Request for Bids Open - International 1,202,166.60 Signed 2018-12-03 2019-01-20 2019-02-14 2019-02-12 2019-03-31 2019-03-18 2019-04-30 2019-05-17 2019-06-27 2019-07-26 2020-02-22 Envelope Works and Transport (MoPWT) Capacity PSH001RE / 10 Vehicles Four Component 2: Improving Wheels Drive, for the Ministry Single Stage - One IBRD / 87050 Road Emergency Response Post Request for Bids Open - International 351,000.00 Signed 2019-04-11 2019-04-11 2019-05-20 2019-05-23 2019-06-20 2019-06-20 2019-08-04 2019-08-01 2019-10-17 2019-10-15 2020-02-14 of Public Works and Transport Envelope Capacity (MoPWT) PSH006 / Kaspersky endpoint Component 3: Capacity Pending Request for Single Stage - One security for Business IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-20 Quotations Envelope (Antivirus) Support on Page 1 PSH007 / Cisco WebEx 3/5 Component 3: Capacity Pending years One user license for Request for Single Stage - One IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-20 meetings (above 1 hr Quotations Envelope Support on duration) up to 25 participants PSH008 / Cisco ASA5508 Component 3: Capacity Pending Request for Single Stage - One Firepower IPS 3 years IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-20 Quotations Envelope (Firewall) Support on Component 3: Capacity Pending Request for Single Stage - One PSH009 / AutoCAD renewal IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-11-09 2020-12-04 Quotations Envelope Support on Component 3: Capacity Pending Request for Single Stage - One PSH010 / ESRI Arc GIS online IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-25 Quotations Envelope Support on Component 3: Capacity Pending PSH011 / Exchange Request for Single Stage - One IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-20 certificates (for Email) Quotations Envelope Support on Component 3: Capacity Pending Request for Single Stage - One PSH012 / A0 Plotter for PMU IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-09 Quotations Envelope Support on PSH013 / 4 PC’s with 30” Component 3: Capacity Pending screens (to replace existing 4 Request for Single Stage - One IBRD / 87050 Building and Implementation Post Limited 0.00 Implementati 2020-09-28 2020-10-26 2020-11-20 old PC’s out of 8 PMU PC’s) Quotations Envelope Support on for PMU only 4  x $ 1100 NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FC003 / Design consultant Component 1: Roads No 3. Lot 3=171.90KM, ACE Least Cost IBRD / 87050 Rehabilitation and Post Open - National 404,972.84 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-02 2019-01-02 2019-06-24 (Associated Consulting Selection Maintenance Engineers) FC004 / Design consultant Component 1: Roads No 4, Lot 4=86.4KM, ACE Least Cost IBRD / 87050 Rehabilitation and Post Open - National 171,203.96 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-09 2019-01-09 2019-07-01 (Associated Consulting Selection Maintenance Engineers) FC005 / Design consultant Component 1: Roads Least Cost No 5, Lot 5=131.20KM, Team IBRD / 87050 Rehabilitation and Post Open - National 287,165.45 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-17 2019-01-17 2019-07-09 Selection International Maintenance FC006 / Design consultant Component 1: Roads Least Cost No 6, Lot 6=140.1KM, Team IBRD / 87050 Rehabilitation and Post Open - National 301,202.20 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-17 2019-01-17 2019-07-09 Selection International Maintenance FC007 / Supervision Component 1: Roads Quality And Cost- consultant No 1, Lot IBRD / 87050 Rehabilitation and Prior Open - International 531,316.80 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-10-06 2019-09-27 2020-12-01 2021-09-26 Based Selection 1=144.9KM Maintenance FC008 / Supervision Component 1: Roads Quality And Cost- consultant No 2, Lot IBRD / 87050 Rehabilitation and Prior Open - International 720,859.62 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-10-06 2019-09-27 2020-11-10 2021-09-26 Based Selection 2=165KM Maintenance FC009 / Supervision Component 1: Roads Quality And Cost- consultant No 3, Lot IBRD / 87050 Rehabilitation and Prior Open - International 936,583.20 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-11-01 2019-09-27 2020-12-09 2021-09-26 Based Selection 3=171.90KM Maintenance FC010 / Supervision Component 1: Roads Quality And Cost- consultant No 4. Lot IBRD / 87050 Rehabilitation and Prior Open - International 761,443.20 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-11-01 2019-09-27 2020-12-30 2021-09-26 Based Selection 4=86.4KM Maintenance FC011 / Supervision Component 1: Roads Quality And Cost- consultant No 5, Lot IBRD / 87050 Rehabilitation and Prior Open - International 1,209,600.00 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-11-01 2019-09-27 2020-12-07 2021-09-26 Based Selection 5=131.20KM Maintenance FC012 / Supervision Component 1: Roads Quality And Cost- consultant No 6, Lot IBRD / 87050 Rehabilitation and Prior Open - International 515,390.40 Signed 2018-03-13 2018-06-21 2018-08-13 2019-02-26 2019-11-20 2019-04-27 2020-02-05 2019-06-26 2020-06-03 2019-08-17 2020-11-04 2019-09-27 2020-12-01 2021-09-26 Based Selection 6=140.1KM Maintenance FC001 / Design consultant Component 1: Roads No 1, Lot 1=144.9KM , Dar El Least Cost IBRD / 87050 Rehabilitation and Post Open - National 155,549.50 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-09 2019-01-09 2019-07-01 Handassah, Nazih Taleb & Selection Maintenance Partners. FC002 / Design consultant Component 1: Roads No 2, Lot 2=165KM, Dar El Least Cost TF / A4481 Rehabilitation and Post Open - National 198,352.25 Signed 2018-03-15 2018-03-15 2018-03-15 2018-06-13 2018-06-13 2018-09-05 2018-09-05 2018-09-19 2018-09-19 2018-10-16 2018-09-26 2019-01-09 2019-01-09 2019-07-01 Handassah Nazih Taleb & Selection Maintenance Partners FC013 / Supervision Component 1: Roads Quality And Cost- consultant No 7, Lot IBRD / 87050 Rehabilitation and Prior Open - International 863,393.57 Signed 2018-03-01 2018-07-02 2018-03-22 2019-10-14 2019-11-20 2019-11-11 2020-02-05 2019-12-11 2020-06-03 2020-01-15 2020-11-06 2020-02-19 2020-12-30 2022-02-18 Based Selection 3B=80.2KM Maintenance FC016 RE / Preparation of a Component 3: Capacity Program of Action for the Quality And Cost- Under IBRD / 87050 Building and Implementation Prior Open - International 0.00 2019-11-20 2019-11-25 2019-12-20 2019-12-27 2020-02-18 2021-02-18 2020-03-29 2020-04-28 2020-06-02 2020-07-07 2022-01-04 Improvement of the Safety of Based Selection Implementation Support The Roads in Lebanon Page 2 FC019 / Support to Farmers Component 4: Support to UN Agencies Pending Engaged in Crop and IBRD / 87050 farmers engaged in crop and Prior Direct 0.00 2021-04-20 2022-06-30 (Direct) Implementation Livestock Production livestock production INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Capacity Individual IC002 / Procurement officer, IBRD / 87050 Building and Implementation Prior Consultant Direct 211,618.00 Signed 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2018-02-12 2018-02-12 2023-01-05 Simon Moawad Support Selection Component 3: Capacity Individual FC017A / Road Safety Audit IBRD / 87050 Building and Implementation Post Consultant Open 34,025.04 Signed 2018-07-16 2019-02-13 2018-12-10 2019-05-29 2019-03-18 2019-09-25 2019-03-25 2019-12-16 2019-09-14 (Team Leader) Support Selection Component 3: Capacity Individual FC017B / Road Safety Audit IBRD / 87050 Building and Implementation Post Consultant Open 10,543.43 Signed 2018-07-16 2019-02-13 2018-12-10 2019-05-29 2019-03-18 2019-09-25 2019-03-25 2019-12-16 2019-09-14 (Team Member) Support Selection Component 3: Capacity Individual IC009 / Senior Environement IBRD / 87050 Building and Implementation Post Consultant Direct 0.00 Canceled 2018-11-05 2018-11-15 2019-01-09 2019-03-02 2019-08-29 & Social officer Support Selection Component 3: Capacity Individual IC001 / Project Coordinator IBRD / 87050 Building and Implementation Post Consultant Open 102,663.00 Signed 2018-04-30 2018-04-30 2018-07-02 2019-01-14 2018-11-05 2019-01-15 2018-11-19 2019-01-31 2021-11-22 Support Selection Component 3: Capacity Individual IC006 / Contract IBRD / 87050 Building and Implementation Post Consultant Open 41,063.00 Signed 2018-04-30 2018-04-30 2018-07-02 2019-01-14 2018-11-05 2019-04-15 2018-11-19 2019-01-17 2023-11-23 Administrator Specialist Support Selection Component 3: Capacity Individual IC008 / Environment & Social IBRD / 87050 Building and Implementation Post Consultant Open 99,000.00 Signed 2018-04-30 2019-02-13 2018-07-02 2019-09-25 2018-11-05 2019-11-05 2018-11-19 2019-12-02 2021-11-22 officer Support Selection Component 3: Capacity Individual IC003 / Traffic Road Safety Under IBRD / 87050 Building and Implementation Post Consultant Open 0.00 2020-05-24 2020-11-26 2020-12-10 2020-12-31 2021-02-01 2021-12-31 Expert Implementation Support Selection Component 3: Capacity Individual IC005 / Occupational Health Under IBRD / 87050 Building and Implementation Post Consultant Open 0.00 2020-05-24 2020-11-26 2020-12-15 2021-01-05 2021-02-09 2022-12-01 and Safety Specialist Implementation Support Selection Component 3: Capacity FC018 / CS for Updating the Pending IBRD / 87050 Building and Implementation Post Direct Selection Direct 0.00 2021-02-11 2021-02-12 2021-02-16 2021-03-15 ESMF Related to the REP Implementation Support Page 3