Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: November 2015]: Revision 1 of Updated Procurement Plan, August 2016] 2. Date of General Procurement Notice: January, 2016 3. Period covered by this procurement plan: The procurement period of project covered from December 2017 to December 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of procurement Substantial risk Works (including turnkey, supply & installation of plant and 10.000.000USD equipment, and PPP) Goods, information technology and non-consulting services 2.000.000USD 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P147674 issued by PRAPS-BF 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domesti Review Comments No. Cost c by Bank US$ Preferen (Prior / million ce Post) (yes/no) Summary of the NCB 7.6 7 No Post (Works) Summary of the NCB 1.6 6 No Post (Goods) Summary of the RfQ 0.2 2 No Post (Works) January 10, 2018 Summary of the RfQ 0.5 9 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Substantial risk Consultants: firms 1.000.000USD Consultants: individuals 300.000USD 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.8 8 post number of contracts that will be let under QCBS, FBBS, LCBS Summary of 3 39 Post CQS, number of Individual contracts that consultant will be let under other methods January 10, 2018 PROCUREMENT Western Africa : Regional Sahel Pastoralism Support Project PLAN General Information Country: Western Africa Banks Approval Date of the Original Procurement Plan: 2018-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-03-04 Project ID: P147674 GPN Date: Project Name: Regional Sahel Pastoralism Support Project Loan / Credit No: IDA / 56510, IDA / 56520, IDA / D0650, IDA / D0640, IDA / 56490, IDA / 56500, IDA / D0660 Executing Agency(ies): Regional Sahel Pastoralism Support Project - Niger, Regional Sahel Pastoralism Support Project - Chad, Regional Sahel Pastoralism Support Project - Senegal, Inter-State Committee against Drought in the Sahel, Regional Sahel Pastoralism Support Project - Burkina Faso, Regional Sahel Pastoralism Support Project - Mali, Regional Sahel Pastoralism Support Project - Mauritania WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7788-CW-RFB / Travaux de constructions Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 400,000.00 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 bureaux DGSV & rehabilitation Envelope Implementation batiment UCP NE-PRAPS-NE-7808-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation Dosso NE-PRAPS-NE-7962-CW-RFQ / Project Management and Request for Single Stage - One Pending Rehabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation Tillaberi NE-PRAPS-NE-7963-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation Agadez NE-PRAPS-NE-7964-CW-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-04-22 2017-06-17 2017-08-16 Réhabilitation bureau d'Agadez Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7966-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-04-22 2017-06-17 2017-08-16 Institutional Support Quotations Envelope Implementation Maradi NE-PRAPS-NE-7968-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-04-17 2017-06-12 2017-08-11 Institutional Support Quotations Envelope Implementation Zinder NE-PRAPS-NE-7969-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 50,000.00 0.00 2017-04-25 2017-06-20 2017-08-19 Institutional Support Quotations Envelope Implementation Diffa NE-PRAPS-NE-7970-CW-RFQ / Request for Single Stage - One Pending Construction de 15 postes IDA / 56510 Animal Health Improvement Post Open - National 377,500.00 0.00 2017-05-27 2017-07-22 2018-01-18 Quotations Envelope Implementation é inaires départementaux vétr PRAPS-SN-05-TX / Recrutement d'une entreprise pour la construction et la réhabilitation Natural Resource Management Single Stage - Two Pending des forages pastoraux q é uipés IDA / 56520 Post Request for Bids Open - National 1,000,000.00 0.00 2017-10-02 2017-10-07 2017-11-18 2017-12-18 2018-01-22 2018-07-21 Enhancement Envelope Implementation de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 2 (KF et TC) TD-PRAPS-TD-9579-CW-RFQ / Natural Resource Management Request for Single Stage - One Pending Réhabilitation des tronçons de IDA / D0650 Post Limited 87,272.00 0.00 2017-03-15 2017-05-10 2017-11-06 Enhancement Quotations Envelope Implementation balises TD-PRAPS-TD-9637-CW-RFB / Construction de 4 marchés à Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 2,425,100.00 0.00 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 bétail et de 2 postes de sortie Envelope Implementation frontaliers TD-PRAPS-TD-9638-CW-RFB / Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Open - National 1,184,100.00 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Aménagement de 20 mares Enhancement Envelope Implementation TD-PRAPS-TD-9641-CW-RFB / Natural Resource Management Single Stage - One Pending Aménagement de 150 kilomètres IDA / D0650 Post Request for Bids Open - National 300,000.00 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Enhancement Envelope Implementation de tronçons balisés TD-PRAPS-TD-9644-CW-RFQ / Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 150,200.00 0.00 2017-10-07 2017-12-02 2018-05-31 Forage des postes de sortie Quotations Envelope Implementation TD-PRAPS-TD-9645-CW-RFB / Single Stage - One Pending Construction et réhabilitation des IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 2,003,600.00 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Envelope Implementation postes de vaccination TD-PRAPS-TD-9648-CW-RFB / Single Stage - One Pending Construction réhabilitation et IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 3,600,100.00 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Envelope Implementation é uipement de 12 forages q 01-T/PRAPS / réhabiliter clôture Project Management and Request for Single Stage - One IDA / 56490 Post Limited 15,000.00 18,108.92 Signed 2017-05-03 2017-06-05 2017-06-21 2017-08-16 2017-08-20 antenne de Fada Institutional Support Quotations Envelope REF 8 / Construction dans la Request for Single Stage - One Pending zone agro-écologique du Mali IDA / 56500 Market Access Facilitation Post Open - National 120,000.00 0.00 2017-06-06 2017-08-01 2018-01-28 Quotations Envelope Implementation Nord Est NE-PRAPS-NE-23108-CW-RFB Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 40,000.00 0.00 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 / Construction des locaux Institutional Support Envelope Implementation 119 / Construction de 15 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 377,500.00 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 é inaires départementaux vétr Envelope Implementation 120 / Contruction de 10 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Limited 251,200.00 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 communaux frontaliers Envelope Implementation 121 / Finalisation de 4 puits Natural Resource Management Request for Single Stage - One Pending pastoraux à Dosso IDA / 56510 Post Limited 80,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation (PAAPSSP/CTB) 122 / Fonçage de 4puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 176,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pastoaraux Tahoua (PAAPSSP) Enhancement Quotations Envelope Implementation 123 / Réhabilitation de 3 puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 88,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Dosso (PAAPSSP) Enhancement Quotations Envelope Implementation 124 / Rehabilitation batiment Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 DGPIA Enhancement Quotations Envelope Implementation 125 / Constructiondes 2 centres Request for Single Stage - One Pending IDA / 56510 Market Access Facilitation Post Limited 60,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 de collecte de lait Quotations Envelope Implementation 126 / Construction/réhabilitation Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 2,100,000.00 0.00 2018-02-13 2018-02-18 2018-04-01 2018-05-01 2018-06-05 2018-12-02 des marchés à bétail Envelope Implementation 127 / Réalisation d'une station de pompage dans la commune Natural Resource Management Single Stage - One Pending de N'Guimi dans la région de IDA / 56510 Post Request for Bids Open - National 170,000.00 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 Enhancement Envelope Implementation Diffa dans le cadre de programme d'urgrncr Diffa 2017 128 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 60,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tchinta 129 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 36,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tassara 130 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 72,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bermo 131 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 24,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Korgom 132 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ollélewa 133 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 48,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tenhiya 134 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tanout 135 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 84,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Magaria 136 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bandé 137 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bouné 138 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Alakos 139 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gamou 140 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gouré 141 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Guidiguir 142 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 24,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kéllé 143 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Takaya 144 / Réhabilitation des puits Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Pastoral Crisis Management Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Quotations Envelope Implementation Gudimouni 145 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Moa 146 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kanya Wamé Page 1 147 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTesker 148 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gueskérou 149 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Chétimari 150 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 36,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guigmi 151 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 72,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kablewa 152 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 24,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Foulatari 153 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 24,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guel Beyli 154 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 36,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Gourti 155 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 24,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Djeladjo 156 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 36,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Fillingué 157 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 36,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTchintaborak 158 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 12,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ingall 159 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 28,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Ingall 160 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 28,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Bermo 161 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 28,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Tchinta 162 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 28,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Abala 163 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 28,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune deTenhiya 164 / Réhabilitation des stations de pompage/forages pastoraux Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 56,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 dans la commune deTesker (site Enhancement Quotations Envelope Implementation de Tesker et Aborak) REF 1 / Réhabilitation de 19 Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 300,000.00 0.00 2017-11-22 2017-11-27 2018-01-08 2018-02-07 2018-03-14 2018-09-10 batiments Enhancement Envelope Implementation ML-PRAPS-ML-33832-CW-RFQ / Travaux d'aménagement et de gestion des pistes et des gîtes Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 79,000.00 0.00 2017-10-30 2017-12-25 2018-06-23 d'étapes dans les cercles de Enhancement Quotations Envelope Implementation Koutiala et Yorosso (région de Sikasso) ML-PRAPS-ML-33835-CW-RFQ Natural Resource Management Request for Single Stage - One Pending / Travaux d'aménagement de 3 IDA / 56500 Post Limited 105,000.00 0.00 2017-11-14 2018-01-09 2018-07-08 Enhancement Quotations Envelope Implementation périmètres pastoraux ML-PRAPS-ML-34689-CW-RFB Single Stage - One Pending / Réhabilitation dans la zone IDA / 56500 Market Access Facilitation Post Request for Bids Open - National 1,500,000.00 0.00 2018-03-31 2018-04-05 2018-05-17 2018-06-16 2018-07-21 2019-01-17 Envelope Implementation Delta central ML-PRAPS-ML-34760-CW-RFQ / Construction dans la zone agro- Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 140,000.00 0.00 2017-11-13 2018-01-08 2018-07-07 é ologique du Delta central de 7 c Quotations Envelope Implementation magasins MR-PRAPS-MR -35029-CW- RFB / construction en 2 lots de 7 Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 1,335,000.00 0.00 2017-12-28 2018-01-02 2018-02-13 2018-03-15 2018-04-19 2018-10-16 marchés a bétail dans plusieurs Envelope Implementation wilayas MR-PRAPS-MR -35030-CW- RFQ / réalisation d un puit Natural Resource Management Request for Single Stage - One Pending pastoral dans la localité de IDA / D0660 Post Open - National 28,500.00 0.00 2018-01-01 2018-02-26 2018-08-25 Enhancement Quotations Envelope Implementation teguelwezza commune de Kankossa 02-T/MOD1 / Réalisation de 111 forages pastoraux solaires et Natural Resource Management Single Stage - One Under IDA / 56490 Post Request for Bids Open - National 1,158,348.00 0.00 2017-12-04 2017-10-31 2017-12-18 2018-01-17 2017-12-15 2018-02-16 2018-04-01 2018-07-30 manuels dans les 6 régions du Enhancement Envelope Implementation PRAPS 05-T/MOD1 / Réalisation de 30 Natural Resource Management Single Stage - One Pending boulis et surcreusement de 5 IDA / 56490 Post Request for Bids Open - National 1,479,162.00 0.00 2018-09-28 2018-10-12 2018-11-11 2018-12-11 2019-01-24 2019-07-23 Enhancement Envelope Implementation mares 07-T/MOD1 / Construction de 9 Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 198,900.00 0.00 2019-02-10 2019-04-16 2019-08-14 é inaires cabinets vétr Quotations Envelope Implementation 09-T/MOD1 / Travaux de construction de 6 postes Single Stage - One Pending é inaires et 30 parcs de vétr IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 567,000.00 0.00 2017-12-04 2017-12-18 2018-01-17 2018-02-16 2018-04-01 2018-07-30 Envelope Implementation vaccination dans les 6 régions du PRAPS-BF 06-T/MOD1 / Single Stage - One Pending construction/réhabilitation et IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 523,200.00 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Envelope Implementation é uipement d'UTL et CCL q PRAPS-SN-01-TX / Réalisation Single Stage - Two Pending des travaux de construction de IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 240,000.00 0.00 2018-03-02 2018-03-07 2018-04-18 2018-05-03 2018-06-17 2018-09-15 Envelope Implementation 15 parcs a vaccination PRAPS-SN-02-TX-2018 / Réalisation des travaux de Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 16,000.00 0.00 2018-05-02 2018-06-27 2018-12-24 construction d'incinérateurs au Quotations Envelope Implementation niveau des 8 SDEL PRAPS-SN-03-TX-2018 / Réalisation des travaux de confection et de pose de bornes Natural Resource Management Request for Single Stage - One Pending IDA / 56520 Post Limited 20,000.00 0.00 2018-05-16 2018-07-11 2019-01-07 pour la matérialisation des Enhancement Quotations Envelope Implementation couloirs de transhumance Payar - Kahène PRAPS-SN-04-TX-2018 / Réalisation des travaux de construction et la réhabilitation Natural Resource Management Single Stage - Two Pending des forages pastoraux q é uipés IDA / 56520 Post Request for Bids Open - National 4,000,000.00 0.00 2018-01-17 2018-01-22 2018-03-05 2018-04-04 2018-05-09 2019-01-04 Enhancement Envelope Implementation de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 1 (SL, MT, LG) PRAPS-SN-05-TX-2018 / Réalisation des travaux Natural Resource Management Single Stage - Two Pending IDA / 56520 Post Request for Bids Open - National 400,000.00 0.00 2018-05-25 2018-05-30 2018-07-11 2018-08-10 2018-09-14 2019-01-12 d'aménagement de mares Enhancement Envelope Implementation pastorales PRAPS-SN-06-TX-2018 / Réalisation des travaux de Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 2,380,000.00 0.00 2018-05-11 2018-05-16 2018-06-27 2018-07-27 2018-08-31 2018-12-29 réhabilitation de 85 km de pistes Envelope Implementation rurales PRAPS-SN-07-TX-2018 / Réalisation des travaux de Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 1,900,000.00 0.00 2018-02-09 2018-02-14 2018-03-28 2018-04-27 2018-06-01 2018-09-29 construction de huit (08) Envelope Implementation marchés à bétail PRAPS-SN-08-TX-2018 / Single Stage - Two Pending Réalisation des travaux de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 448,000.00 0.00 2018-01-26 2018-01-31 2018-03-14 2018-04-13 2018-05-18 2018-11-14 Envelope Implementation construction des unités laitières PRAPS-SN-09-TX-2018 / Project Management and Request for Single Stage - One Pending Travaux de réaménagement des IDA / 56520 Post Limited 20,000.00 0.00 2018-01-22 2018-03-19 2018-04-03 Institutional Support Quotations Envelope Implementation bureaux du PRAPS BF-PRAPS-BF-45749-CW-RFB Project Management and Single Stage - One Pending / Construction du siège du IDA / 56490 Post Request for Bids Open - National 1,900,000.00 0.00 2017-06-19 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-22 Institutional Support Envelope Implementation PRAPS-BF ML-PRAPS-ML-46040-CW-RFQ / Réalisation des travaux Natural Resource Management Request for Single Stage - One Pending d'aménagement de 02 mares IDA / 56500 Post Limited 164,912.00 0.00 2018-03-17 2018-05-12 2018-11-08 Enhancement Quotations Envelope Implementation dans la zone d'intervention du Projet ML-PRAPS-ML-46041-CW-RFQ / Travaux de réhabilitation des Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 42,105.00 0.00 2018-03-10 2018-05-05 2018-11-01 infrastructures hydrauliques Enhancement Quotations Envelope Implementation d'accès à l'eau ML-PRAPS-ML-46042-CW-RFB / Réhabilitation de 03 marchés à bétail, construction et é uipement de 02 marchés à q bétail, construction de 05 aires Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 1,512,280.00 0.00 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 d'abattage, 03 té als de Enhancement Envelope Implementation boucherie, 10 magasins d'aliment bétail et 05 pistes d'accès aux marchés à bétail dans le Mali Nord Est PRAPS-SN-02-TX / Recrutement d'une entreprise pour les travaux Natural Resource Management Request for Single Stage - One Pending de construction de clôtures de IDA / 56520 Post Limited 30,000.00 0.00 2018-02-12 2018-04-09 2018-05-24 Enhancement Quotations Envelope Implementation pépinières communautaires (10 pépinières de 1/4 ha) Page 2 PRAPS-SN-12-TX-2018 / Recrutement d'une entreprise pour la réalisation de clôture de Natural Resource Management Single Stage - One Pending IDA / 56520 Post Request for Bids Open - National 140,000.00 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-12-01 mise en défens sur 200 ha (Dept Enhancement Envelope Implementation Linguère, Kanel, Bakel, Koumpentoum et Koungheul) PRAPS-SN-10-TX-2018 / Recrutement d'une entreprise Single Stage - Two Pending pour la construction et ou la IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 500,000.00 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2019-01-30 Envelope Implementation réhabilitation de mise aux normes d'aires d'abattage PRAPS-SN-11-TX-2018 / Recrutement d'une entreprise pour la réalisation des travaux de Single Stage - Two Pending construction de Magasins de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 280,000.00 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-10-02 Envelope Implementation Stockage et de Vente d'Aliment de Bétail (4 de 100T et 5 de 50 tonnes) ML-PRAPS-ML-48029-CW-RFB Natural Resource Management Single Stage - One Pending / Equipements et infrastructures IDA / 56500 Post Request for Bids Open - National 774,000.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-06-07 2018-12-04 Enhancement Envelope Implementation d'abreuvement de forages ML-PRAPS-ML-48031-CW-RFB Natural Resource Management Single Stage - One Pending / Travaux de 11 forages grand IDA / 56500 Post Request for Bids Open - National 470,000.00 0.00 2018-06-12 2018-06-17 2018-07-29 2018-10-02 2019-03-31 Enhancement Envelope Implementation débit et 14 forages simples ML-PRAPS-ML-47899-CW-RFB / Travaux de réhabilitation de 5 Single Stage - One Pending é inaires, 5 SLPIA, 6 IDA / 56500 secteurs vétr Animal Health Improvement Post Request for Bids Open - National 240,350.00 0.00 2018-02-19 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Envelope Implementation Postes frontaliers, 1 Poste de contrôle frontalier et 15 UAPIA ML-PRAPS-ML-47901-CW-RFB Single Stage - One Pending / Travaux de construction de 31 IDA / 56500 Animal Health Improvement Post Request for Bids Open - National 652,631.00 0.00 2018-03-08 2018-03-13 2018-04-24 2018-05-24 2018-06-28 2018-12-25 Envelope Implementation Parcs de vaccination ML-PRAPS-ML-47903-CW-RFB / Réalisation du balisage de 245 km de pistes et gîtes d'étapes dans les cercles de Bankass et Natural Resource Management Single Stage - One Pending Koro (région de Mopti) et de 545 IDA / 56500 Post Request for Bids Open - National 443,509.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation km de pistes et gîtes d'étapes dans les cercles de Ténenkou et Niono (régions de Mopti et de Ségou) ML-PRAPS-ML-47905-CW-RFB / Réalisation de 14 Systèmes Hydrauliques Pastorales (SHPA) Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 1,719,298.00 0.00 2018-04-12 2018-04-17 2018-05-29 2018-06-28 2018-08-02 2019-01-29 dans les régions de Ségou, Enhancement Envelope Implementation Mopti, Tombouctou, Gao et Ménaka ML-PRAPS-ML-47907-CW-RFB / Réalisation des travaux de 11 mini Systèmes Hydraulique Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 578,947.00 0.00 2018-04-17 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Pastorales (SHPA) dans les Enhancement Envelope Implementation gites d'étapes des régions de Sikasso, Ségou, Mopti ML-PRAPS-ML-48014-CW-RFB / Réalisation des travaux de 23 forages dont les sites seront Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 201,754.00 0.00 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2018-11-26 déterminés à l'issu de la Enhancement Envelope Implementation validation des résultats de l'inventaire des points d'eau ML-PRAPS-ML-48011-CW-RFQ / Réhabilitation de trois bureaux Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 105,263.00 0.00 2018-02-28 2018-04-25 2018-10-22 pour les antennes régionales à Institutional Support Quotations Envelope Implementation (Kayes, Mopti, Gao) TD-PRAPS-TD-9573-CW-RFB / Single Stage - One Pending Construction de 30 parcs de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 601,080.00 0.00 2018-03-26 2018-03-31 2018-05-12 2018-07-16 2019-01-12 Envelope Implementation vaccination TD-PRAPS-TD-9582-CW-RFB / Natural Resource Management Single Stage - One Pending Construction de la première IDA / D0650 Post Request for Bids Limited 333,600.00 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation tranche des puits pastoraux TD-PRAPS-TD-9585-CW-RFB / Construction de 12 marchés à Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 1,175,000.00 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 bétail et de 5 postes de sortie Envelope Implementation frontaliers BF-PRAPS-BF-49891-CW-RFB / Réhabilitation 10 postes é inaires et 04 marchés à vétr Animal Health Improvement Single Stage - One Pending IDA / 56490 Post Request for Bids Open - National 670,531.00 0.00 2018-05-15 2018-05-29 2018-06-28 2018-07-19 2018-08-23 2018-12-21 bétail dans les régions de Market Access Facilitation Envelope Implementation l'antenne de Bobo-Dioulasso et de Fada N'Gourma 04-T/MOD1 / Construction 10 marchés à bétail et Single Stage - One Pending IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 1,383,864.00 0.00 2018-07-02 2018-07-16 2018-08-15 2018-09-14 2018-10-28 2019-03-27 construction/réhabilitation 10 Envelope Implementation aires d'abattage. 08-T/MOD2 / Sécurisation d'aires de pâture intervilageoise, Natural Resource Management Single Stage - One Pending de délimitation/balisage d'aires IDA / 56490 Post Request for Bids Open - National 1,475,167.00 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Enhancement Envelope Implementation de repôs, d'aménagement de pistes à bétail 03-T/MOD1 / Réhabilitation de é inaires dans la 08 postes vétr région du Sahel (Arbinda, Banh, Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 300,500.00 0.00 2018-05-01 2018-05-15 2018-06-14 2018-07-14 2018-08-27 2018-12-25 Baraboulé, Déou, Mansila, Envelope Implementation Marcoye, Nansoumbou, Tankougoumadié) BF-PRAPS-BF-51569-CW-RFB Single Stage - One Pending / Construction de 08 Postes IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 560,000.00 0.00 2018-06-12 2018-06-19 2018-07-19 2018-08-02 2018-08-30 2018-12-28 Envelope Implementation é inaires vétr GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7631-GO-RFB / Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 193,400.00 0.00 2017-02-23 2017-02-28 2017-04-11 2017-05-11 2017-06-15 2017-12-12 Acquisition matériel informatique Institutional Support Envelope Implementation NE-PRAPS-NE-7652-GO-RFQ / Production de certificat Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 40,000.00 0.00 2017-03-05 2017-04-30 2017-05-10 international de transhumance de Quotations Envelope Implementation la CEDEAO NE-PRAPS-NE-7653-GO-RFQ / Request for Single Stage - One Pending Fourniture et installation de IDA / 56510 Market Access Facilitation Post Limited 15,000.00 0.00 2017-03-10 2017-05-05 2017-07-04 Quotations Envelope Implementation Panneau Solaire pour la DGPIA NE-PRAPS-NE-7654-GO-RFQ / Project Management and Request for Single Stage - One Pending Confection des Panneaux et IDA / 56510 Post Limited 50,000.00 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation totems lumineux à Niamey NE-PRAPS-NE-7655-GO-RFQ / Productions des outils de collecte de données sur les Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-03-10 2017-05-05 2017-06-04 statistiques d'élevage ( Institutional Support Quotations Envelope Implementation commercialisation de bétail etc....) NE-PRAPS-NE-7658-GO-RFQ / Realisation, conception d'un Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-04-08 2017-06-03 2017-07-03 compendium sur deux ans de Institutional Support Quotations Envelope Implementation mise en RN en Suvre du PRAPS NE-PRAPS-NE-7659-GO-RFQ / impression d'un compendium sur Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 20,000.00 0.00 2017-04-22 2017-06-17 2017-07-07 deux ans de mise en RN en Institutional Support Quotations Envelope Implementation Suvre du PRAPS NE-PRAPS-NE-7660-GO-RFQ / Edition et diffusion des outils et Project Management and Request for Single Stage - One Pending manuels de sensibilisation sur IDA / 56510 Post Limited 50,000.00 0.00 2017-05-02 2017-06-27 2017-07-27 Institutional Support Quotations Envelope Implementation les maladies prioritaires et les maladies emergentes du betail NE-PRAPS-NE-7662-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-02-24 2017-04-21 2018-04-16 Telephone et flotte PRAPS Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7663-GO-RFQ / Project Management and Request for Single Stage - One Pending Fonctionnement véhicules et IDA / 56510 Post Limited 584,700.00 0.00 2017-02-24 2017-04-21 2017-10-18 Institutional Support Quotations Envelope Implementation motos (carburant,entretien,...) NE-PRAPS-NE-7664-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 50,000.00 0.00 2017-02-24 2017-04-21 2018-04-16 Fourniture et produit d'entretien Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7667-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 13,300.00 0.00 2017-02-24 2017-04-21 2018-04-16 Consommable bureau, journaux Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7670-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 18,000.00 0.00 2017-02-24 2017-04-21 2017-06-20 Edition journal du PRAPS Institutional Support Quotations Envelope Implementation TD-PRAPS-TD-8494-GO-RFB / Project Management and Single Stage - One Pending Acquisition d'un groupe IDA / D0650 Prior Request for Bids Limited 45,155.00 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Institutional Support Envelope Implementation é ectrogène l pour l'UCP TD-PRAPS-TD-8497-GO-RFB / Single Stage - One Pending Acquisition de 4 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 472,727.00 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Envelope Implementation doses de vaccin PPR PRAPS-SN-01-F / Acquisition Single Stage - Two Pending IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 162,000.00 0.00 2017-03-13 2017-03-18 2017-04-29 2017-05-14 2017-06-13 2017-07-13 de Vaccins PPCB, PPR et FVR Envelope Implementation BF-CILSS-8938-GO-RFQ / Impression de divers documents Project Management and Request for Single Stage - One Pending (notes des ETP-2, fiches IDA / D0640 Post Limited 80,000.00 0.00 2017-06-20 2017-08-15 2017-09-14 Institutional Support Quotations Envelope Implementation techniques, notes de plaidoyer, guide routier, plaquettes) PRAPS-SN-02-F / Acquisition de kit de diagnostic de Single Stage - Two Pending IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 150,000.00 0.00 2017-03-06 2017-03-11 2017-04-15 2017-05-15 2017-06-19 2017-08-03 laboratoire (PPR et FVR) et de Envelope Implementation matériel d'intervention PRAPS-SN-03-F / Recrutement d'un prestataire pour la confection de supports Animal Health Improvement Request for Single Stage - One Pending promotionnels (agendas, polos, IDA / 56520 Project Management and Post Limited 50,000.00 0.00 2017-03-11 2017-04-28 2017-05-28 Quotations Envelope Implementation pagnes, etc.) et Support de Institutional Support Communication (JML, JNE, autre com) PRAPS-SN-04-F / Acquisition Natural Resource Management Request for Single Stage - One Pending de 8 motos pour l'animation des IDA / 56520 Post Limited 30,000.00 0.00 2017-03-18 2017-05-07 2017-06-21 Enhancement Quotations Envelope Implementation UP Page 3 PRAPS-SN-05-F / Acquisition de matériel de lutte contre les Natural Resource Management Request for Single Stage - One Pending feux de brousse en vue de IDA / 56520 Post Limited 90,000.00 0.00 2017-07-29 2017-09-17 2017-11-01 Enhancement Quotations Envelope Implementation l'équipement de 30 comités de lutte contre les feux de brousse PRAPS-SN-06-F / Acquisition Natural Resource Management Request for Single Stage - One Pending IDA / 56520 Post Limited 80,000.00 0.00 2017-06-17 2017-08-12 2017-11-10 de motofaucheuses Enhancement Quotations Envelope Implementation PRAPS-SN-07-F / Acquisition de fournitures de bureau, de consommables informatiques et Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 40,000.00 0.00 2017-03-11 2017-04-30 2018-04-30 de Produits d'entretien de locaux Institutional Support Quotations Envelope Implementation administratifs et de petits matériels et outillages PRAPS-SN-09-F / Services de Project Management and Request for Single Stage - One Pending confection d'habillement pour le IDA / 56520 Post Limited 2,000.00 0.00 2017-03-25 2017-05-14 2017-06-14 Institutional Support Quotations Envelope Implementation personnel de service PRAPS-SN-11-F / Acquisition Project Management and Request for Single Stage - One Pending d'équipements de IDA / 56520 Post Limited 20,000.00 0.00 2017-03-11 2017-04-30 2017-06-15 Institutional Support Quotations Envelope Implementation Communication BF-CILSS-9090-GO-RFQ / Produire des dé itions de fin Project Management and Request for Single Stage - One IDA / D0640 Post Limited 50,000.00 7,364.49 Signed 2017-12-01 2017-10-12 2017-12-30 2017-12-01 2018-01-13 d'année (calendriers, Institutional Support Quotations Envelope plannings...) BF-CILSS-9091-GO-RFQ / Project Management and Request for Single Stage - One Acquisition de deux IDA / D0640 Post Limited 8,000.00 5,197.74 Signed 2018-03-05 2018-01-25 2018-04-09 2018-02-14 2018-04-19 Institutional Support Quotations Envelope rétroprojecteurs BF-CILSS-9092-GO-DIR / Project Management and Request for Single Stage - One Pending Acquisition de matériel de bureau IDA / D0640 Post Limited 3,500.00 0.00 2018-03-09 2018-04-09 2018-04-19 Institutional Support Quotations Envelope Implementation complémentaire BF-CILSS-9093-GO-RFQ / Project Management and Request for Single Stage - One Pending Acquisition de fournitures de IDA / D0640 Post Limited 20,000.00 0.00 2018-04-07 2018-05-12 2018-05-22 Institutional Support Quotations Envelope Implementation bureau PRAPS-SN-12-F / Achat de Mobilier (archivage et salon pour Project Management and Request for Single Stage - One Pending bureau coordonnateur et bureau IDA / 56520 Post Limited 20,000.00 0.00 2017-04-08 2017-05-28 2017-06-27 Institutional Support Quotations Envelope Implementation assistant sauvegarde environnemental et social) PRAPS-SN-13-F / Acquisition Project Management and Request for Single Stage - One Pending de Groupes Electrogènes UCP et IDA / 56520 Post Limited 30,000.00 0.00 2017-03-18 2017-05-07 2017-08-05 Institutional Support Quotations Envelope Implementation antennes PRAPS-SN-14-F / Acquisition Single Stage - One Pending é les en cas de crise de céra IDA / 56520 Pastoral Crisis Management Prior Request for Bids Open - National 648,000.00 0.00 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 2018-03-28 Envelope Implementation pastorale TD-PRAPS-TD-9182-GO-RFQ / Equipement de la salle des Project Management and Request for Single Stage - One Pending réunions du Ministère de IDA / D0650 Post Limited 36,360.00 0.00 2017-04-19 2017-06-14 2017-12-11 Institutional Support Quotations Envelope Implementation l'Elevage et des Productions Animales TD-PRAPS-TD-9999-GO-RFB / Project Management and Single Stage - One Pending Acquistion de 17 véhicules Tout IDA / D0650 Prior Request for Bids Open - International 1,644,600.00 0.00 2016-07-04 2016-07-09 2016-08-20 2016-09-19 2016-10-24 2017-04-22 Institutional Support Envelope Implementation Terrain et de 176 motocyclettes TD-PRAPS-TD-9998-GO-RFB / Project Management and Single Stage - One Pending Acqusitions des matériels IDA / D0650 Post Request for Bids Open - National 362,100.00 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Institutional Support Envelope Implementation informatiques TD-PRAPS-TD-9990-GO-RFB / Single Stage - One Pending Acquistion de 3 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Limited 500,000.00 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Envelope Implementation doses de vaccins PPCB 03-F/PRAPS / Acquérir 3 Single Stage - One é ectrogènes au profit groupes l IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 72,000.00 54,364.57 Signed 2017-04-03 2017-04-11 2017-04-08 2017-05-08 2017-05-24 2017-05-29 2017-05-24 2017-07-03 2017-10-13 2017-09-01 Envelope des antennes du PRAPS-BF 02-F/PRAPS / Duplication en Project Management and Request for Single Stage - One 1000 exemplaires la version IDA / 56490 Post Limited 6,000.00 2,739.84 Signed 2018-01-31 2018-01-25 2018-03-28 2018-02-28 2018-04-27 Institutional Support Quotations Envelope adaptée du guide genre Natural Resource Management 14-F/PRAPS / Fournitures et Enhancement Request for Single Stage - One Under consommables de bureau et IDA / 56490 Post Limited 20,000.00 0.00 2018-01-20 2017-12-29 2018-02-24 2018-03-26 Project Management and Quotations Envelope Implementation informatiques Institutional Support 15-F/PRAPS / Mobilier de Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 60,000.00 0.00 2018-10-22 2018-12-10 2019-02-08 bureau Institutional Support Quotations Envelope Implementation 13-F/PRAPS / Dispositif de Project Management and Request for Single Stage - One Under vidéoconférence au profit de IDA / 56490 Post Limited 38,000.00 0.00 2018-05-30 2017-12-18 2018-07-18 2018-09-16 Institutional Support Quotations Envelope Implementation l'UCP 12-F/PRAPS / 200 kits outils Request for Single Stage - One Pending pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 95,500.00 0.00 2019-06-24 2019-08-19 2019-10-18 Quotations Envelope Implementation de veille 10-F/PRAPS / Support de Single Stage - One Pending communication/formation adapté IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 122,400.00 0.00 2019-10-30 2019-11-04 2019-12-04 2020-01-03 2020-02-07 2020-04-07 Envelope Implementation é eveurs aux l 09-F/PRAPS / 1 véhicule 4x4 Project Management and Request for Single Stage - One Pending station wagon et 2 véhicules 4x4 IDA / 56490 Post Limited 183,000.00 0.00 2019-10-28 2019-12-23 2020-02-21 Institutional Support Quotations Envelope Implementation pick-up double cabine 05-F/PRAPS / Equiper Single Stage - One l'opérateur spécialisé (VSF-B) en IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 64,000.00 65,012.05 Completed 2016-01-08 2016-12-14 2016-01-22 2016-02-21 2017-01-24 2016-03-22 2017-02-13 2016-04-26 2017-06-23 2016-06-25 2017-08-25 Envelope véhicule 06-F/PRAPS / Production des Affiches et, dépliants (conception de 2 maquettes et impression de 2500 affiches et dépliants), Request for Single Stage - One IDA / 56490 Animal Health Improvement Post Limited 9,600.00 9,123.65 Completed 2017-05-26 2017-06-15 2017-07-21 2017-07-20 2017-08-20 2017-10-03 concevoir et produire des Quotations Envelope supports 'boites à images sur la santé animale et sur la conduite du troupeau REF 11 / Equipements et Project Management and Request for Single Stage - One Pending mobiliers de bureau pour les IDA / 56500 Post Limited 90,000.00 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation antennes régionales du Projet REF 12 / Achat d'un véhicule Request for Single Stage - One Pending spécialement q é uipé pour les IDA / 56500 Animal Health Improvement Post Limited 100,000.00 0.00 2017-02-28 2017-04-25 2017-10-22 Quotations Envelope Implementation interventions d'urgence REF 13 / Moquettes, rideaux et Project Management and Request for Single Stage - One Pending accessoires pour l'Unité de IDA / 56500 Post Limited 20,000.00 0.00 2017-05-21 2017-07-16 2018-01-12 Institutional Support Quotations Envelope Implementation Coordination du Projet REF 14 / Matériels Project Management and Request for Single Stage - One Pending informatiques pour les antennes IDA / 56500 Post Open - National 100,000.00 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation régionales REF 16 / Acquisition de 80 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 50,000.00 0.00 2017-03-22 2017-05-17 2017-11-13 smartphones Institutional Support Quotations Envelope Implementation REF 17 / Equipements de travail Request for Single Stage - One Pending pour les enquêteurs et les IDA / 56500 Market Access Facilitation Post Limited 50,000.00 0.00 2017-03-14 2017-05-09 2017-11-05 Quotations Envelope Implementation contrôleurs REF 19 / kit de semences Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 100,000.00 0.00 2017-03-25 2017-05-20 2017-11-16 é uipements fourragères et petits q Quotations Envelope Implementation Request for Single Stage - One Pending é inaires REF 22 / Trousses vétr IDA / 56500 Animal Health Improvement Post Limited 100,000.00 0.00 2017-03-30 2017-05-25 2017-11-21 Quotations Envelope Implementation REF 23 / 40 ordinateurs Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 100,000.00 0.00 2017-04-14 2017-06-09 2017-12-06 portables et disques externes Institutional Support Quotations Envelope Implementation REF 25 / Ordinateur portable et accessoires, imprimante Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 10,000.00 0.00 2017-05-16 2017-07-11 2018-01-07 multifonction, photocopieuse et Institutional Support Quotations Envelope Implementation onduleur du PADEL-M NE-PRAPS-NE-23097-GO-RFQ Request for Single Stage - One Pending / Acquisition des kits de IDA / 56510 Animal Health Improvement Post Limited 27,000.00 0.00 2017-09-01 2017-10-27 2018-04-25 Quotations Envelope Implementation vaccination NE-PRAPS-NE-23100-GO-RFQ Request for Single Stage - One Pending / Equipements des 2 centres de IDA / 56510 Market Access Facilitation Post Limited 60,000.00 0.00 2017-10-20 2017-12-15 2018-06-13 Quotations Envelope Implementation collecte de lait NE-PRAPS-NE-23249-GO-RFQ Request for Single Stage - One Pending / Son de blé (1100 tonnes) région IDA / 56510 Pastoral Crisis Management Post Limited 616,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation de Tahoua avec depot sur site NE-PRAPS-NE-7610-GO-RFB / Project Management and Single Stage - One Pending Acquisition matériel roulant ( 26 IDA / 56510 Post Request for Bids Open - International 1,280,000.00 0.00 2017-02-27 2017-03-04 2017-04-15 2017-05-15 2017-06-19 2017-09-02 Institutional Support Envelope Implementation véhicules et 42 Moto) NE-PRAPS-NE-7640-GO-RFQ / Request for Single Stage - One Pending Equipement Vétr é inaire IDA / 56510 Animal Health Improvement Post Limited 100,000.00 0.00 2017-02-28 2017-04-25 2017-06-24 Quotations Envelope Implementation (matériels froid) NE-PRAPS-NE-7641-GO-RFQ / Equipements Vétr é inaires Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 83,000.00 0.00 2017-03-05 2017-04-30 2017-06-29 (Matériels de Prélvè ement et Kits Quotations Envelope Implementation de diagnostic ) NE-PRAPS-NE-23326-GO-RFQ / Tourteaux de graine (300 Request for Single Stage - One Pending tonnes) région de Tahoua ( IDA / 56510 Pastoral Crisis Management Post Limited 168,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation tonnes)de coton avec depot sur site NE-PRAPS-NE-23347-GO-RFQ / Fourniture des produits Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 658,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 é inaires et complexes vétr Quotations Envelope Implementation minéraux pour la DGPIA NE-PRAPS-NE-23327-GO-RFQ Request for Single Stage - One Pending / Son de blé région (1100 t) de IDA / 56510 Pastoral Crisis Management Post Limited 616,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation Zinder avec depot sur site NE-PRAPS-NE-23328-GO-RFQ / Tourteaux de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 168,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 (300t) région de Zinder avec Quotations Envelope Implementation depot sur site NE-PRAPS-NE-23330-GO-RFQ Request for Single Stage - One Pending / Son de blé région deDiffa (600) IDA / 56510 Pastoral Crisis Management Post Limited 336,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23333-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 112,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Diffa ( 200 tonnes)de coton avec Quotations Envelope Implementation depot sur site Page 4 NE-PRAPS-NE-23335-GO-RFQ Request for Single Stage - One Under / Son de blé région de Maradi IDA / 56510 Pastoral Crisis Management Post Limited 560,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site NE-PRAPS-NE-23336-GO-RFQ / Tourteaux de graine région Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 140,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 deMaradi ( 200 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23337-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Tillaberi IDA / 56510 Pastoral Crisis Management Post Limited 560,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site NE-PRAPS-NE-23338-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 140,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Tillaberi ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23339-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Dosso IDA / 56510 Pastoral Crisis Management Post Limited 448,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (800 tonnes) avec depot sur site NE-PRAPS-NE-23340-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 84,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Dosso ( 150 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23341-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Niamey IDA / 56510 Pastoral Crisis Management Post Limited 224,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (400 tonnes) avec depot sur site NE-PRAPS-NE-23343-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 140,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 Niamey ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23344-GO-RFQ / Son de blé région de Agadez ( Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 560,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 1000 tonnes)de coton avec depot Quotations Envelope Implementation sur site NE-PRAPS-NE-23345-GO-RFQ / Tourteau de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 168,000.00 0.00 2017-08-06 2017-10-01 2018-03-30 région d'Agadez (300 tonnes) Quotations Envelope Implementation avec depot sur site NE-PRAPS-NE-23045-GO-RFB Project Management and Single Stage - One Pending / Aquisition materiel informatique IDA / 56510 Post Request for Bids Open - National 193,400.00 0.00 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 Institutional Support Envelope Implementation et de communication 1 / Acquisition materiel roulant Project Management and Single Stage - One Pending IDA / 56510 Prior Request for Bids Open - International 1,280,000.00 0.00 2016-12-02 2016-12-07 2017-01-18 2017-02-17 2017-03-24 2017-09-20 (26véhicules et 50 Motos) Institutional Support Envelope Implementation 5 / Acquisition de vaccins et Request for Single Stage - One Pending diluants PPCB et diluants (6000 IDA / 56510 Animal Health Improvement Post Limited 655,000.00 0.00 2017-11-06 2018-01-01 2018-06-30 Quotations Envelope Implementation 000 doses) 6 / Edition guide ingénierie Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 7,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 sociale Enhancement Quotations Envelope Implementation 7 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 8,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tanout Enhancement Quotations Envelope Implementation 8 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Belbedji IDA / 56510 Post Limited 8,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gangara 9 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Kantche Enhancement Quotations Envelope Implementation 10 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 3,400.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Takaya Enhancement Quotations Envelope Implementation 11 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Magaria IDA / 56510 Post Limited 10,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Doungas 12 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 10,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Gouré Enhancement Quotations Envelope Implementation 13 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Boune Enhancement Quotations Envelope Implementation 14 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 4,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tesker Enhancement Quotations Envelope Implementation 15 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Agadez IDA / 56510 Post Limited 6,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Aderbissanet 16 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de INGAL Enhancement Quotations Envelope Implementation 17 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 6,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchiro-Arlit Enhancement Quotations Envelope Implementation 18 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Iférouane Enhancement Quotations Envelope Implementation 19 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 2,600.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de INATES Enhancement Quotations Envelope Implementation 20 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 9,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de say Enhancement Quotations Envelope Implementation 21 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 7,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Téra Enhancement Quotations Envelope Implementation 22 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 3,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tondikiwindi Enhancement Quotations Envelope Implementation 23 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 3,200.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Filingué Enhancement Quotations Envelope Implementation 24 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 2,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Bankilare Enhancement Quotations Envelope Implementation 25 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Guidan IDA / 56510 Post Limited 10,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Roumdji Madaroumfa 26 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 10,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mayayi Enhancement Quotations Envelope Implementation 27 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 15,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Dakoro Bermo Enhancement Quotations Envelope Implementation 28 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchinta-Konni Enhancement Quotations Envelope Implementation 29 / Acquisition matériel aratoire Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 6,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Abalak Quotations Envelope Implementation 30 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 7,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Bagaroua Enhancement Quotations Envelope Implementation 31 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 3,600.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tassara Enhancement Quotations Envelope Implementation 32 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Matankari Enhancement Quotations Envelope Implementation 33 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Dogon kirya IDA / 56510 Post Limited 5,600.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kieche 34 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 10,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Falmey-Boboy Enhancement Quotations Envelope Implementation 35 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 7,600.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Diffa Enhancement Quotations Envelope Implementation 36 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 5,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mainé Enhancement Quotations Envelope Implementation 37 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 4,400.00 0.00 2018-01-04 2018-03-01 2018-08-28 pour les sites de Goudoumaria Enhancement Quotations Envelope Implementation 38 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 35,275.00 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région D'Agagez Enhancement Quotations Envelope Implementation 39 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 17,455.00 0.00 2018-01-07 2018-03-04 2018-08-31 2 pour la région De Diffa Enhancement Quotations Envelope Implementation 40 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 10,185.00 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Dosso Enhancement Quotations Envelope Implementation 41 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 18,900.00 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Maradi Enhancement Quotations Envelope Implementation 42 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 30,000.00 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tahoua Enhancement Quotations Envelope Implementation 43 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 38,000.00 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tillaberi Enhancement Quotations Envelope Implementation 44 / Achat semence espèce 1,2 Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 73,000.00 0.00 2018-01-04 2018-03-01 2018-08-28 et 3 pour la région De Zinder Enhancement Quotations Envelope Implementation 46 / Acquisition et installation du Natural Resource Management Request for Single Stage - One Pending système de securité ( alarme IDA / 56510 Post Limited 40,000.00 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation incendie et vidéo surveillance) 47 / Achat matériel de collecte Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 56,000.00 0.00 2017-10-25 2017-12-20 2018-06-18 pour la DGSV Quotations Envelope Implementation 48 / Acquisition materiels Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 24,000.00 0.00 2017-10-27 2017-12-22 2018-06-20 d'archivage electronique Institutional Support Quotations Envelope Implementation 49 / Acquisition de logiciel pour Request for Single Stage - One Pending 5 postes ( Arc Gis logicel R et IDA / 56510 Pastoral Crisis Management Post Limited 18,000.00 0.00 2017-10-27 2017-12-22 2018-06-20 Quotations Envelope Implementation SPSS) 50 / Acquisition matériel Natural Resource Management Request for Single Stage - One Pending informatique et mobilier de IDA / 56510 Post Limited 40,000.00 0.00 2017-10-27 2017-12-22 2018-06-20 Enhancement Quotations Envelope Implementation bureau pour les 5 postes OSV NE-PRAPS-NE-30649-GO-RFQ Request for Single Stage - One Pending / Acquisition des kits de IDA / 56510 Animal Health Improvement Post Limited 27,000.00 0.00 2017-10-22 2017-12-17 2018-06-15 Quotations Envelope Implementation vaccination Page 5 NE-PRAPS-NE-30651-GO-RFQ / Réalisation de film sur la place Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 10,000.00 0.00 2017-10-15 2017-12-10 2018-06-08 des femmes et des jeune dans le Institutional Support Quotations Envelope Implementation pastoralisme REF 20 / Un ordinateur, 1 imprimante et photocopieur, 2 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 26,000.00 0.00 2017-03-24 2017-03-24 2017-03-24 bureaux, une armoire, fournitures Institutional Support Quotations Envelope Implementation de bureau ML-PRAPS-ML-31420-GO-RFB Single Stage - One Pending / Acquisition et Transport IDA / 56500 Pastoral Crisis Management Post Request for Bids Open - National 600,000.00 0.00 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Envelope Implementation d'aliment bétail NE-PRAPS-NE-30638-GO-DIR / Pending Acquisition de vaccins et diluants IDA / 56510 Animal Health Improvement Prior Direct Selection Direct 852,000.00 0.00 2017-11-09 2017-11-14 2017-12-16 2018-06-14 Implementation PPR (15 000 000 doses) NE-PRAPS-NE-34367-GO-RFQ Request for Single Stage - One Pending / Mise en place des incinérateurs IDA / 56510 Animal Health Improvement Post Limited 100,000.00 0.00 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope Implementation pour la gestion des déchets NE-PRAPS-NE-34385-GO-RFQ Request for Single Stage - One Pending / Acquisition /construction des IDA / 56510 Animal Health Improvement Post Limited 100,000.00 0.00 2017-11-11 2018-01-06 2018-07-05 Quotations Envelope Implementation parcs mobiles pour bovins 01-F/MOD1 / Equipement 111 Natural Resource Management Single Stage - One Pending forages solaires et manuels dans IDA / 56490 Post Request for Bids Open - National 947,800.00 0.00 2018-09-28 2018-10-19 2018-11-18 2018-12-09 2019-01-22 2019-05-22 Enhancement Envelope Implementation les régions du PRAPS-BF 17-F/PRAPS / Edition des manuels par compilation des Natural Resource Management Request for Single Stage - One Pending différentes règlementations IDA / 56490 Post Limited 11,400.00 0.00 2018-10-01 2018-11-26 2019-01-25 Enhancement Quotations Envelope Implementation existantes dans le domaine du pastoralisme MR-PRAPS-MR -43177-GO-DIR / Acquisition de médicaments Pending IDA / D0660 Pastoral Crisis Management Prior Direct Selection Direct 300,000.00 0.00 2018-01-29 2018-02-03 2018-03-10 2018-09-06 é inaires vétr pour le plan Implementation d'urgence. Animal Health Improvement 04-F/PRAPS / Acquisition de Natural Resource Management Request for Single Stage - One IDA / 56490 Post Limited 66,000.00 59,620.75 Completed 2017-04-07 2017-05-22 2017-06-18 2017-07-21 2017-08-02 2017-10-27 165 tablettes Enhancement Quotations Envelope Market Access Facilitation PRAPS-SN-01-F-2018 / Acquisition de matériel de froid Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 40,000.00 0.00 2018-02-21 2018-04-18 2018-06-02 complémentaire pour les services Quotations Envelope Implementation é inaires vétr PRAPS-SN-02-F-2018 / Single Stage - Two Pending Acquisition de vaccins (PPCB, IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 162,000.00 0.00 2018-02-02 2018-02-07 2018-03-21 2018-07-08 2018-10-06 Envelope Implementation PPR et FVR) PRAPS-SN-03-F-2018 / Recrutement d'un prestataire Animal Health Improvement Request for Single Stage - One Pending pour la confection de supports IDA / 56520 Project Management and Post Limited 40,000.00 0.00 2018-04-12 2018-06-07 2018-09-05 Quotations Envelope Implementation promotionnels (agendas, polos, Institutional Support etc.) PRAPS-SN-05-F-2018 / Fourniture et Installation Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 150,000.00 0.00 2018-02-24 2018-03-01 2018-04-12 2018-07-30 2018-10-28 d'équipements des centres de Envelope Implementation collectes, laiteries et fromagerie PRAPS-SN-07-F-2018 / Acquisition de groupes Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 90,000.00 0.00 2018-02-14 2018-04-11 2018-07-10 é ectrogènes pour les antennes l Institutional Support Quotations Envelope Implementation du PRAPS PRAPS-SN-08-F-2018 / Project Management and Request for Single Stage - One Pending Acquisition de mobilier IDA / 56520 Post Limited 20,000.00 0.00 2018-03-08 2018-05-03 2018-07-02 Institutional Support Quotations Envelope Implementation d'archivage PRAPS-SN-09-F-2018 / Acquisition de matériel Project Management and Request for Single Stage - One Pending informatique pour CONACILSS et IDA / 56520 Post Limited 30,000.00 0.00 2018-01-29 2018-03-26 2018-05-25 Institutional Support Quotations Envelope Implementation PRAPS ainsi que d'un kit de suivi environnement BF-CILSS-44411-GO-RFQ / Renouvellement de licence de la Project Management and Request for Single Stage - One IDA / D0640 Post Limited 8,000.00 7,492.24 Signed 2018-01-28 2018-01-23 2018-03-11 2018-02-14 2018-03-21 passerelle du système visio Institutional Support Quotations Envelope conférence BF-CILSS-44413-GO-RFQ / Project Management and Request for Single Stage - One Under Mise à jour de l'autocommutateur IDA / D0640 Post Limited 7,200.00 0.00 2018-01-29 2018-01-26 2018-03-05 2018-03-15 Institutional Support Quotations Envelope Implementation du CILSS BF-PRAPS-BF-44618-GO-RFB / Aliments de bétail pour approvisionner des magasins en stocks durgence (30 000 tonnes Single Stage - One Under IDA / 56490 Pastoral Crisis Management Prior Request for Bids Open - International 4,800,000.00 0.00 2018-02-15 2018-02-13 2018-03-01 2018-04-12 2018-04-26 2018-06-09 2018-08-08 aliment bétail) pour distribution Envelope Implementation SECNSA et SP-CVEL, DGEAP pour réponse à la contingence sécheresse BF-PRAPS-BF-44630-GO-RFB / Acquisition et transport sur sites de vivres pour distribution pour é Boutiques vente à prix modér/ Single Stage - One témoins SP CVEL pour IDA / 56490 Pastoral Crisis Management Prior Request for Bids Limited 3,099,000.00 0.00 Under Review 2018-02-15 2018-02-20 2018-04-03 2018-04-17 2018-05-31 2018-07-30 Envelope assistance aux sinistrés en réponse à la contingence conflits entre exploitants /scénaris de pire cas/DGEAP 07-F/PRAPS / Equipement Animal Health Improvement informatique, ordinateurs, 31 kits Project Management and solaires, 31 refrigérateurs ,31 Institutional Support Single Stage - One congelateur ,62 glacière, IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 266,800.00 370,326.86 Signed 2017-04-19 2017-07-17 2017-04-24 2017-06-05 2017-09-04 2017-07-05 2017-09-13 2017-08-09 2017-12-18 2017-11-07 Envelope 124bouteilles de gaz, 35 Natural Resource Management smatphones, 35 power Bank, 50 Enhancement copteurs, qé uip. communicaion Market Access Facilitation 11-F/PRAPS / 100 Kits outils Request for Single Stage - One Under pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 95,500.00 0.00 2017-06-20 2017-05-22 2017-08-15 2017-10-14 Quotations Envelope Implementation de veille 08-F/PRAPS / 31 kits solaires - Request for Single Stage - One Pending acquisition, pose et installation IDA / 56490 Animal Health Improvement Post Limited 98,000.00 0.00 2017-11-15 2018-01-26 2018-03-12 Quotations Envelope Implementation de MOF-REF-1 / Acquisition de 43 Request for Single Stage - One motos au profit de la DGSV et de IDA / 56490 Animal Health Improvement Post Limited 99,000.00 94,702.76 Completed 2017-09-10 2017-09-05 2017-11-14 2017-10-30 2017-12-29 2017-12-28 Quotations Envelope VSF-B BF-PRAPS-BF-45936-GO-RFQ / 43 motos au profit des structures déconcentrées de collectes de Request for Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Limited 99,800.00 0.00 2018-05-19 2018-07-23 2018-09-21 données dans le cadre de la Quotations Envelope Implementation composante 4 (gestion des crises) BF-PRAPS-BF-45948-GO-RFB / 375 kits pour insertion socio- Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 187,000.00 0.00 2018-04-18 2018-04-23 2018-05-23 2018-06-13 2018-07-27 2018-09-25 professionnelle de la 1ère Envelope Implementation cohorte (C4) BF-PRAPS-BF-45979-GO-RFQ / Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 30,000.00 0.00 2018-03-26 2018-05-21 2018-07-20 Matériel de vaccination Quotations Envelope Implementation BF-PRAPS-BF-45989-GO-RFB / Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 336,000.00 0.00 2018-03-14 2018-04-04 2018-05-04 2018-05-25 2018-07-08 2018-09-06 Vaccins contre la PPR Envelope Implementation BF-PRAPS-BF-46005-GO-RFQ / Project Management and Request for Single Stage - One Pending Confection de goodies (publicité IDA / 56490 Post Limited 12,000.00 0.00 2018-02-26 2018-04-02 2018-05-02 Institutional Support Quotations Envelope Implementation par l'objet) BF-PRAPS-BF-46009-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 12,000.00 0.00 2018-06-17 2018-08-12 2019-02-08 Activité hors médias Institutional Support Quotations Envelope Implementation ML-PRAPS-ML-46243-GO-RFQ / Acquisition des semences, de boutures et d'éclats de souches é de diverses espèces/variéts Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 49,123.00 0.00 2018-03-30 2018-05-25 2018-11-21 d'herbacées et de ligneuses pour Enhancement Quotations Envelope Implementation les travaux de restauration des pâturages exondés et des bourgoutières ML-PRAPS-ML-46244-GO-RFQ / Acquisition de 11 Kiosques et Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 40,526.00 0.00 2018-09-30 2018-11-25 2019-05-24 11 kits pour la transformation de Quotations Envelope Implementation la viande ML-PRAPS-ML-46245-GO-RFQ / Acquisition de 11 tricycles Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 38,596.00 0.00 2018-10-13 2018-12-08 2019-06-06 motorisés pour le transport de la Quotations Envelope Implementation viande ML-PRAPS-ML-46327-GO-RFQ / Acquisition de 72 Smartphones Project Management and Request for Single Stage - One Pending pour la collecte et la remontée de IDA / 56500 Post Limited 26,526.00 0.00 2018-02-23 2018-04-20 2018-10-17 Institutional Support Quotations Envelope Implementation é enciée l'information géo réfr pour 31 cercles et 10 régions PRAPS-SN-04-F-2018 / Natural Resource Management Pending Acquisition de 4 motos pour IDA / 56520 Post Direct Selection Direct 10,000.00 0.00 2018-03-03 2018-03-08 2018-04-12 2018-06-11 Enhancement Implementation l'animation des UP PRAPS-SN-10-F-2018 / Acquisition de divers fournitures sous fore de contrats-cadres en Single Stage - One Pending trois lots separes Lot 1 produits IDA / 56520 Pastoral Crisis Management Post Request for Bids Open - National 670,000.00 0.00 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2019-05-30 Envelope Implementation veterinaires Lot 2 aliment de betail et Lot 3 betail ovins et caprins ML-PRAPS-ML-48894-GO-RFB / Acquisition de véhicules (4 Station wagon, 5 Pickups) Project Management and Single Stage - One Pending complémentaires pour améliorer IDA / 56500 Post Request for Bids Open - National 456,140.00 0.00 2018-03-12 2018-03-17 2018-04-28 2018-05-28 2018-07-02 2018-12-29 Institutional Support Envelope Implementation la mobilité des services techniques (DNSV, DNPIA) et de l'UCP TD-PRAPS-TD-49619-GO-DIR / Pending Acquisition de 15 millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 1,472,727.00 0.00 2018-06-10 2018-06-15 2018-07-20 2019-01-16 Implementation doses de vaccin contre la PPR BF-PRAPS-BF-44635-GO-DIR / Achat et transport sur sites de é inaires d'intervention produit vétr Pending IDA / 56490 Pastoral Crisis Management Post Direct Selection Direct 200,000.00 0.00 2018-02-15 2018-02-20 2018-04-07 2018-06-06 en réponse à la contingence Implementation é izooties/scénario du p pire/DGSV TD-PRAPS-TD-50122-GO-DIR / Pending Acquisition de six millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 654,545.00 0.00 2018-06-01 2018-06-06 2018-07-11 2019-01-07 Implementation doses de vaccin contre la PPCB Page 6 TD-PRAPS-TD-50137-GO-RFB / Project Management and Single Stage - One Pending Acquisition de 28 véhicules et IDA / D0650 Post Request for Bids Open - National 12,727,217.00 0.00 2018-04-04 2018-04-09 2018-05-21 2018-06-20 2018-07-25 2019-01-21 Institutional Support Envelope Implementation 176 motos TD-PRAPS-TD-50145-GO-RFQ / Acquisition des matériels et Request for Single Stage - One Pending IDA / D0650 Animal Health Improvement Post Limited 127,000.00 0.00 2018-04-15 2018-06-10 2018-12-07 chaine de froid et une chambre Quotations Envelope Implementation négative TD-PRAPS-TD-50430-GO-RFQ / Acquisition des groupes Project Management and Request for Single Stage - One Pending IDA / D0640 Post Limited 45,454.00 0.00 2018-03-25 2018-05-20 2018-11-16 é ectrogènes pour les antennes l Institutional Support Quotations Envelope Implementation régionales du PRAPS TD-PRAPS-TD-50439-GO-RFQ / Acquisition des qé uipements Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 305,454.00 0.00 2018-04-15 2018-06-10 2018-12-07 SIM Bétail (1 véhicule et 20 Quotations Envelope Implementation motos) TD-PRAPS-TD-50445-GO-RFB / é uipements Acquisition des q Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Limited 305,454.00 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 UAF en matériels de travail et Enhancement Envelope Implementation fournitures de bureau TD-PRAPS-TD-50451-GO-RFQ / Acquisition des matériels de Natural Resource Management Request for Single Stage - One Pending IDA / D0640 Post Limited 27,272.00 0.00 2018-04-04 2018-05-30 2018-11-26 travail de la Division d'Ingénierie Enhancement Quotations Envelope Implementation de Formation de NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7661-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 30,200.00 0.00 2017-02-24 2017-04-21 2018-04-16 Internet Institutional Support Quotations Envelope Implementation NE-PRAPS-NE-7665-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 150,000.00 0.00 2017-02-25 2017-04-22 2018-04-17 Assurance véhicule Institutional Support Quotations Envelope Implementation PRAPS-SN-10-F / Acquisition Project Management and Pending du logiciel MS Project et IDA / 56520 Prior Direct Selection Direct 30,000.00 0.00 2017-03-13 2017-03-18 2017-04-22 2017-05-22 Institutional Support Implementation formation des utilisateurs PRAPS-SN-08-F / Services d'entretiens et de maintenance Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 10,000.00 0.00 2016-12-30 2017-01-17 2018-01-17 du matériel informatique, du site Institutional Support Quotations Envelope Implementation web du PRAPS REF 28 / Appui à la production Natural Resource Management Request for Single Stage - One Pending des cartes des couloirs de IDA / 56500 Post Limited 50,000.00 0.00 2017-04-16 2017-06-11 2017-12-08 Enhancement Quotations Envelope Implementation transhumance REF 29 / Développement dune Project Management and Request for Single Stage - One Pending page Facebook et dune page IDA / 56500 Post Limited 4,000.00 0.00 2017-06-17 2017-08-12 2018-02-08 Institutional Support Quotations Envelope Implementation YouTube REF 30 / Conception et Project Management and Request for Single Stage - One Pending réalisation dun clip vidéo pour le IDA / 56500 Post Limited 40,000.00 0.00 2017-04-15 2017-06-10 2017-12-07 Institutional Support Quotations Envelope Implementation PRAPS NE-PRAPS-NE-7669-NC-DIR / Project Management and Pending IDA / 56510 Post Direct Selection Direct 72,864.00 0.00 2017-02-19 2017-02-24 2017-03-31 2018-03-26 Location Bureaux UCP/PRAPS Institutional Support Implementation NE-PRAPS-NE-7642-NC-DIR / Etablissement de 7 conventions Project Management and Pending IDA / 56510 Post Direct Selection Direct 20,000.00 0.00 2017-02-28 2017-03-05 2017-04-09 2017-10-06 avec les média locaux pour la Institutional Support Implementation vulgarisation des textes ML-PRAPS-ML-34772-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 50,000.00 0.00 2017-11-05 2017-12-31 2018-06-29 Diffusion de messages Institutional Support Quotations Envelope Implementation PRAPS-SN-06-F-2018 / Recrutement d'un prestataire Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 90,000.00 0.00 2018-03-19 2018-05-14 2019-05-14 pour la police d'assurance santé Institutional Support Quotations Envelope Implementation des agents du PRAPS ML-PRAPS-ML-47132-NC-RFQ / Conception, radialisation et diffusion des supports de communication sur les activités Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 70,175.00 0.00 2018-02-24 2018-04-21 2018-10-18 et les acquis du PRAPS- ML par Institutional Support Quotations Envelope Implementation : affichage, audio et audiovisuel, (film, sketchs, affiches, panneaux) REF 27 / Production des Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 50,000.00 0.00 2017-05-15 2017-07-10 2018-01-06 supports de vulgarisation Institutional Support Quotations Envelope Implementation 03-S/PRAPS / Assurance Project Management and Request for Single Stage - One IDA / 56490 Post Limited 40,000.00 0.00 Canceled 2017-04-22 2017-06-10 2017-07-16 maladie Institutional Support Quotations Envelope BF-PRAPS-BF-49968-NC-DIR / Project Management and Pending Assurance maladie du personnel IDA / 56490 Post Direct Selection Direct 41,600.00 0.00 2017-06-01 2017-06-08 2017-07-22 2018-07-22 Institutional Support Implementation du PRAPS-BF CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7700-CS-CQS / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de Consultant parcours(ingénerie sociale, Project Management and Pending IDA / 56510 Prior Qualification Open - National 1,500,000.00 0.00 2017-02-20 2017-03-13 2017-04-26 2017-05-26 2017-06-30 2018-06-25 aménagements pastoraux et Institutional Support Implementation Selection hydraulique pastorale ds les 7 régions avec une vingtaine d' ONG au niveau de Vingt sept zones NE-PRAPS-NE-7766-CS-CQS / Appui à la mise en place d'un Consultant disposititif adapté Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 40,000.00 0.00 2017-03-13 2017-04-03 2017-05-17 2017-06-16 2017-07-21 2017-09-19 d'approvisionnement et de Implementation Selection distribution d'aliments bétail en cas de crise pastorale NE-PRAPS-NE-7769-CS-CQS / Consultant Elaboration d'un document Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 20,000.00 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-26 2017-07-31 2017-08-30 d'evaluation d'une activité en Implementation Selection situation de crises pastorales PRAPS-SN-12-PI / Sélection d'un consultant individuel pour Consultant Pending l'étude de capitalisation des IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 40,000.00 0.00 2016-11-29 2017-02-09 2017-03-26 2017-04-25 2017-06-09 2017-10-07 Implementation activités de la cellule de lutte Selection contre le vol de bétail PRAPS-SN-04-PI / Sélection d'un cabinet pour l'étude sur les Consultant initiatives en cours pour la mise Natural Resource Management Pending IDA / 56520 Post Qualification Open - National 60,000.00 0.00 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-01 en place de pares feux dans le Enhancement Implementation Selection cadre de la lutte contre les feux de brousses PRAPS-SN-06-PI / Sélection é udes d'un cabinet pour les t Consultant Pending techniques en vue de la IDA / 56520 Market Access Facilitation Post Qualification Open - National 30,000.00 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2017-12-08 Implementation réhabilitation de 50 km de pistes Selection rurales PRAPS-SN-10-PI / Sélection Consultant Pending d'un cabinet pour les services IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 50,000.00 0.00 2017-08-28 2017-09-18 2017-11-01 2017-12-01 2018-01-05 2018-05-05 Implementation d'évaluation d'impact OSB Selection TD-PRAPS-TD-9404-CS-QBS / Recrutement d'un consultant Project Management and Quality Based Pending IDA / D0650 Post Open - National 28,000.00 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-27 pour les travaux de réhabilitation Institutional Support Selection Implementation des locaux de l'UCP 19-C/MODSIEGE / MOD pour la Consultant Project Management and Pending construction du siège de l'UCP IDA / 56490 Post Qualification Open - National 128,000.00 0.00 2017-03-09 2017-03-30 2017-04-27 2017-05-11 2017-06-08 2018-09-01 Institutional Support Implementation PRAPS Selection 43-C/PRAPS / Capitalisation Consultant des connaissances endogènes Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 30,000.00 0.00 2019-11-28 2019-12-12 2020-01-09 2020-01-23 2020-02-20 2020-03-21 sur les indicateurs de crise en Implementation Selection pastoralisme 07-C/PRAPS / Evaluation de Consultant l'intégration du pastoralisme dans Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 31,100.00 0.00 2017-06-23 2017-07-14 2017-08-11 2017-08-25 2017-09-22 2017-10-22 les instruments de gestion des Implementation Selection crises au Burkina Faso 37-C/PRAPS / Etude offre de formation professionnelle en lien avec le pastoralisme au profit des jeunes et capitalisation des Consultant Under activités connexes autour des IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 40,000.00 0.00 2017-06-16 2017-05-26 2017-07-07 2017-08-04 2017-06-17 2017-08-18 2017-07-21 2017-09-22 2017-09-22 Implementation infrastructures d'élevage, des Selection AGR l é igibles dans le PRAPS en relation avec le genre et les technologies adapté 46-C/PRAPS / Elaboration Consultant Natural Resource Management Pending é entiel technique des réfr IDA / 56490 Post Qualification Open - National 20,000.00 0.00 2019-11-29 2019-12-20 2020-01-17 2020-01-31 2020-02-28 2020-03-29 Enhancement Implementation infrastructures pastorales Selection REF 38 / Etudes pour 15 Consultant Natural Resource Management Pending schémas d'aménagement de IDA / 56500 Post Qualification Open - National 100,000.00 0.00 2017-04-18 2017-05-09 2017-06-22 2017-07-22 2017-08-26 2018-02-22 Enhancement Implementation terroirs Selection Consultant REF 39 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 70,000.00 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-17 2017-07-22 2018-01-18 des travaux daménagement Implementation Selection REF 40 / Evaluation des Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 100,000.00 0.00 2017-05-03 2017-05-24 2017-07-07 2017-08-04 2017-09-03 2017-10-08 2017-11-12 2018-11-12 superficies de pâturages Enhancement Based Selection Implementation Consultant é udes REF 42 / Réalisation des t Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 110,000.00 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2018-03-16 géophysiques Enhancement Implementation Selection é udes REF 44 / Réalisation des t Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 100,000.00 0.00 2017-05-04 2017-05-25 2017-07-08 2017-08-05 2017-09-04 2017-10-09 2017-11-13 2018-11-13 techniques Enhancement Based Selection Implementation REF 45 / Contrôle -surveillance Consultant Pending é uipements des travaux et q IDA / 56500 Market Access Facilitation Post Qualification Open - National 50,000.00 0.00 2017-04-25 2017-05-16 2017-06-29 2017-07-29 2017-09-02 2018-03-01 Implementation d'abreuvement Selection Consultant REF 46 / Contrôle des travaux Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 50,000.00 0.00 2017-05-18 2017-06-08 2017-07-22 2017-08-21 2017-09-25 2018-03-24 dans la zone mali NORD- EST Enhancement Implementation Selection Page 7 Consultant REF 63 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 100,000.00 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2018-03-08 fonds de roulement vaccins Implementation Selection Consultant REF 73 / Etudes d'identification Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 90,000.00 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 des travaux daménagement Enhancement Implementation Selection Consultant REF 74 / Aménagement dans Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 90,000.00 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la zone Centre du Mali Enhancement Implementation Selection REF 75 / Aménagement et Consultant Natural Resource Management Pending gestion durable des IDA / 56500 Post Qualification Open - National 100,000.00 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation bourgoutières Selection REF 76 / Aménagement et gestion durable des Consultant Natural Resource Management Pending bourgoutières dans les régions IDA / 56500 Post Qualification Open - National 100,000.00 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation de Tombouctou et de Gao Selection (régions du Nord-Mali) Consultant REF 78 / Réalisation des pare- Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 60,000.00 0.00 2017-06-22 2017-07-13 2017-08-26 2017-09-25 2017-10-30 2018-04-28 feu de sécurisation Enhancement Implementation Selection Consultant REF 80 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 100,000.00 0.00 2017-04-17 2017-05-08 2017-06-21 2017-07-21 2017-08-25 2018-02-21 fonds de roulement vaccins Implementation Selection NE-PRAPS-NE-7774-CS-CQS / Recrutement d'un bureau d'étude Consultant é ude, conception et suivi pour t Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 40,000.00 0.00 2017-03-22 2017-04-12 2017-05-26 2017-06-25 2017-07-30 2019-01-21 de travaux de construction de la Implementation Selection DGSV et Réhabilitation bureau UCP NE-PRAPS-NE-7779-CS-CQS / Recrutement d'un bureau Consultant d'études pour etude,conception Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 80,000.00 0.00 2017-02-21 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2018-12-23 et contrôle des 15 postes Implementation Selection départementaux et des 10 postes communauxfrontaliers* NE-PRAPS-NE-7702-CS-CQS / Consultant Convention de prestation avec un Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 50,000.00 0.00 2017-04-02 2017-04-23 2017-06-06 2017-07-06 2017-08-10 2018-08-05 Bureau pour organisation des Enhancement Implementation Selection usagers de parcours 53 / Recrutemnt d'un bureau Consultant d'étude pour Appui aux initiatives Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 35,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 communautaires à travers les Enhancement Implementation Selection CEP 58 / Identification, accords sociaux, géo réfré ence et Consultant Project Management and Pending préparation des DAO pour les IDA / 56510 Post Qualification Open - National 50,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation travaux de balisage en 2018 des Selection couloirs de passage 65 / Convention de prestation Consultant Project Management and Pending avec un bureau pour organisation IDA / 56510 Post Qualification Open - National 50,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation des usagers de parcours Selection 66 / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de parcours(ingénerie sociale, Consultant Pending aménagements pastoraux et IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 1,500,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation hydraulique pastorale ds les 7 Selection régions avec une vingtaine d' ONG au niveau de Vingt sept zones 68 / Recrutement d'un consultant firme pour Consultant Pending l'Elaboration d'un document IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 40,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation d'evaluation d'une activité en Selection situation de crises pastorales 80 / Recrutement d'un bureau Consultant d'étude pour t é ude, conception et Project Management and Under IDA / 56510 Post Qualification Open - National 40,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 suivi et contôle de batiment du Institutional Support Implementation Selection Projet 84 / Recrutement des ONG/OPEL pour le démarrage Consultant Pending du processus des accords partis IDA / 56510 Market Access Facilitation Post Qualification Open - National 70,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation pour la construction/réhabilitation Selection des marchés 85 / Recrutement d'un bureau d'études pour etude,conception Consultant Pending et contrôle des 15 postes IDA / 56510 Animal Health Improvement Post Qualification Open - National 80,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation départementaux et des 10 Selection postes communauxfrontaliers* Consultant 86 / Etude sur l'institution de Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 40,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 SVPP Implementation Selection 91 / Recrutement dun bureau detude pour Etudes de Consultant Pending faisabilité, préparation DAO, suivi IDA / 56520 Market Access Facilitation Post Qualification Open - National 100,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation et contrôle des quatorze centres Selection de collecte de lait 97 / recrutement dun bureau d'études pour la réalisation des etudes techniques et elaboration Quality And Cost- Pending IDA / 56510 Market Access Facilitation Post Open - National 100,000.00 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 des DAO relatifs a la Based Selection Implementation construction/rehabilitation des 29 marchés à bétail NE-PRAPS-NE-30657-CS-LCS / Recrutement d'un bureau d'étude pour etudes,suivi et contrôle des Project Management and Pending travaux de Réhabilitation du IDA / 56510 Post Least Cost Selection Open - National 70,000.00 0.00 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2018-10-08 Institutional Support Implementation batiment de la DGPIA et les locaux devant abriter les antennes régionales du PRAPS REF 47 / Recrutement de consultant chargé des t é udes Consultant Pending techniques pour la réalisation IDA / 56500 Market Access Facilitation Post Qualification Open - National 70,000.00 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-22 2017-09-26 2018-03-25 Implementation des Travaux dans la zone DELTA Selection CENTRAL ML-PRAPS-ML-31460-CS-CQS / RECRUTEMENT D'UNE ONG POUR LA CONDUITE DES Consultant Project Management and Pending ACTIVITÉS DE SAUVEGARDES IDA / 56500 Post Qualification Open - National 200,000.00 0.00 2017-10-25 2017-11-15 2017-12-29 2018-01-28 2018-03-04 2018-08-31 Institutional Support Implementation SOCIALES AUTOUR DES Selection INFRASTRUCTURES DU PRAPS ML-PRAPS-ML-33294-CS-CQS Consultant / Recrutement de consultant pour Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 120,000.00 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la réalisation des Travaux de Enhancement Implementation Selection sécurisation 18-C/PRAPS / Recrutement d'un opérateur en alphabétisation Consultant Under pour la formation des membres IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 Implementation des OP de la région de la Boucle Selection du Mouhoun 17-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Under IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région de l'Est 16-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2017-11-13 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région du Nord 03-C/MOD1 / Suivi-contrôle des travaux de construction de 5 Consultant Under é inaires et 30 parcs IDA / 56490 postes vétr Animal Health Improvement Post Qualification Open - National 63,000.00 0.00 2017-12-02 2018-01-15 2017-12-16 2018-01-20 2018-02-10 2018-03-17 2018-08-14 Implementation de vaccination dans les 6 régions Selection du PRAPS-BF 04-C/MOD1 / Maîtrise d'Suvre travaux de réalisation de 111 Consultant Natural Resource Management Under forages pastoraux solaires et IDA / 56490 Post Qualification Open - National 297,330.00 0.00 2017-12-29 2018-01-15 2018-01-19 2018-03-04 2018-04-03 2018-05-08 2018-10-05 Enhancement Implementation manuels dans les 6 régions du Selection PRAPS 05-C/MOD1 / Suivi-contrôle Consultant Pending travaux de réhabilitation de 25 IDA / 56490 Animal Health Improvement Post Qualification Open - National 22,500.00 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2018-12-20 Implementation é inaires postes vétr Selection 06-C/MOD1 / Etude/suivi 15 Pending marchés et 10 aires d'abattage à IDA / 56490 Market Access Facilitation Post Least Cost Selection Open - National 220,000.00 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2019-04-08 Implementation construire et à réhabiliter Consultant 02-C/MOD1 / Etude/suivi 30 Natural Resource Management Under IDA / 56490 Post Qualification Open - National 208,535.00 0.00 2018-09-21 2017-12-27 2018-10-12 2018-01-30 2018-11-25 2018-12-25 2019-01-29 2019-07-28 boulis et5 mares Enhancement Implementation Selection 08-C/MOD1 / Etude/suivi Quality And Cost- Under UTL/CCL à construire et IDA / 56490 Market Access Facilitation Post Open - National 34,300.00 0.00 2018-08-21 2017-05-29 2018-09-11 2018-10-25 2018-11-22 2017-10-06 2018-12-22 2017-10-06 2019-01-26 2017-10-06 2019-03-02 2019-07-30 Based Selection Implementation réhabiliter 11-C/MOD2 / Etudes s et suivi- contrôle Travaux de sécurisation de 25 aires de pâture inter- villageoise, de délimitation/balisage de 60 aires Natural Resource Management Quality And Cost- Pending IDA / 56490 Post Open - National 333,640.00 0.00 2018-08-22 2018-09-12 2018-10-26 2018-11-23 2018-12-23 2019-01-27 2019-03-03 2019-07-31 de repos, d'aménagement de 1 Enhancement Based Selection Implementation 000 km de pistes à bétail, et de récupération de 10 000 ha de terres dégradées par ONG/associatio 10-C/MOD1 / Etudes environnementales et sociales Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 13,720.00 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-22 2018-12-22 2019-01-26 2019-03-02 2019-06-30 UTL/CCL à construire et à Based Selection Implementation réhabiliter 01-C/MOD1 / Etude Consultant Natural Resource Management Pending environnemental et sociale 30 IDA / 56490 Post Qualification Open - National 86,890.00 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-24 2018-12-29 2019-05-28 Enhancement Implementation boulis et 5 mares Selection 41-C/MOD1 / Etudes environnementales et sociales 15 Consultant marchés à bétail et 10 aires Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 90,000.00 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 d'abattage à construire et Implementation Selection réhabiliter dans les régions d'intervention du PRAPS-BF 42-C/MOD1 / Etude environnementales et sociales 9 Quality And Cost- Pending é inaires privés à cabinets vétr IDA / 56490 Animal Health Improvement Post Open - National 11,700.00 0.00 2018-07-17 2018-08-07 2018-09-20 2018-10-18 2018-11-17 2018-12-22 2019-01-26 2019-07-25 Based Selection Implementation construire dans les régions d'intervention du PRAPS-BF Page 8 43-C/MOD1 / Etudes/suivi 9 é inaires privés à cabinets vétr Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 29,250.00 0.00 2018-05-14 2018-05-28 2018-07-02 2018-07-16 2018-07-30 2018-08-18 2018-09-22 2019-03-21 construire dans les régions Based Selection Implementation d'intervention du PRAPS-BF PRAPS-SN-09-PI / Sélection de consultant pour le développement Consultant Under de modules sur les crises IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 70,000.00 0.00 2016-12-07 2016-12-07 2017-02-04 2017-03-10 2017-04-10 2017-03-30 2017-05-31 2017-08-29 Implementation pastorales (SIGEL) et formation Selection des utilisateurs PRAPS-SN-02-PI-2018 / Sélection d'un consultant responsable du processus de Natural Resource Management Fixed Budget Pending é aluation participatif de la suivi v IDA / 56520 Post Open - National 60,000.00 0.00 2018-03-06 2018-03-27 2018-05-10 2018-06-07 2018-07-07 2018-08-11 2018-09-15 2019-09-15 Enhancement Selection Implementation mise en Suvre des plans de gestion et organisation des ateliers d'évaluation 21-C/PRAPS / Evaluation des Consultant performances du PRAPS et de la Project Management and Under IDA / 56490 Post Qualification Open - National 50,000.00 0.00 2017-01-27 2017-01-30 2017-02-17 2017-04-02 2017-03-27 2017-05-02 2017-04-19 2017-06-22 2017-08-03 responsable de la formulation du Institutional Support Implementation Selection PADEL-B Project Management and Quality And Cost- Pending 35-C/PRAPS / Auditeur externe IDA / 56490 Post Open - National 60,000.00 0.00 2019-04-15 2019-05-06 2019-06-10 2019-06-24 2019-07-15 2019-08-19 2019-10-02 2022-10-01 Institutional Support Based Selection Implementation Consultant MOF-REF-2 / Réalisation film Project Management and Pending IDA / 56490 Post Qualification Open - National 21,000.00 0.00 2016-06-09 2016-06-30 2016-08-13 2016-09-12 2016-10-17 2017-04-15 documentaire et spots Institutional Support Implementation Selection BF-PRAPS-BF-45594-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP dans la Selection région des Cascades BF-PRAPS-BF-45599-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région des Hauts Bassins BF-PRAPS-BF-45604-CS-CQS / Opérateur en Alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 6,400.00 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région du Sahel MOF-REF-11 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant Under l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 80,000.00 0.00 2016-08-02 2017-10-02 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Implementation dans l'antenne de Fada Enhancement Selection N'Gourma (Région de l'Est) Market Access Facilitation MOF-REF-12 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant Pending l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 91,000.00 0.00 2016-08-02 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Implementation dans l'antenne de Dori (régions Enhancement Selection du Sahel et du Nord) Market Access Facilitation MOF-REF-13 / ONG/association Animal Health Improvement pour l'ingénierie sociale du Pastoral Crisis Management Consultant PRAPS-BF dans l'antenne de Under IDA / 56490 Natural Resource Management Post Qualification Open - National 120,000.00 0.00 2016-08-02 2016-08-01 2016-08-23 2016-10-06 2016-11-05 2017-01-03 2017-07-02 Bobo-Dioulasso (régions des Implementation Enhancement Selection Hauts-Bassins, de la Boucle du Market Access Facilitation Mouhoun et des Cascades) 32-C/MOD1 / Etudes Quality And Cost- environnementales et sociales 9 IDA / 56490 Animal Health Improvement Post Open - National 100,000.00 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection é inaires cabinets vétr 09-C/MOD1 / Etudes/suivi 9 Quality And Cost- é inaires à cabinets vétr IDA / 56490 Animal Health Improvement Post Open - National 40,950.00 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection construction BF-PRAPS-BF-45926-CS-CQS / Consultant Project Management and Pending Suivi-contrôle de la construction IDA / 56490 Post Qualification Open - National 150,000.00 0.00 2017-06-26 2017-07-17 2017-08-14 2017-08-28 2017-10-02 2018-09-27 Institutional Support Implementation du siège du PRAPS-BF Selection BF-PRAPS-BF-46011-CS-CQS / Consultant Plan d'aménagement et de Natural Resource Management Pending IDA / 56490 Post Qualification Open - National 36,000.00 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 gestion (PAG) de la zone Enhancement Implementation Selection pastorale de Barani (48 924 ha) BF-PRAPS-BF-46012-CS-CQS / Plan d'aménagement et de Consultant Natural Resource Management Pending gestion (PAG) de la zone IDA / 56490 Post Qualification Open - National 36,000.00 0.00 2018-03-30 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 Enhancement Implementation pastorale de Sondré Est (16 459 Selection ha) ML-PRAPS-ML-46328-CS-CQS / Réalisation d'une té ude pour Consultant l'évaluation des superficies et de Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 35,087.00 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 la qualité des pâturages dans les Implementation Selection zones du Sahel Occidental, du Delta Central et du Mali Nord-Est ML-PRAPS-ML-46378-CS-CQS / Recrutement d'une ONG pour l'Appui au renforcement de Consultant capacité des membres des Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 63,158.00 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 organisations pastorales sur la Implementation Selection vie associative, l'exploitation et la maintenance des infrastructures pastorales ML-PRAPS-ML-46542-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux Consultant Natural Resource Management Pending d'aménagement de 4110 IDA / 56500 Post Qualification Open - National 144,211.00 0.00 2018-08-14 2018-09-04 2018-10-18 2018-11-17 2018-12-22 2019-06-20 Enhancement Implementation hectares de bourgoutières dans Selection les Régions de Ségou, Mopti, Tombouctou et Gao ML-PRAPS-ML-46560-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 300 Consultant Natural Resource Management Pending km de pare- feu autour des IDA / 56500 Post Qualification Open - National 22,105.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Enhancement Implementation zones de pâturages dans les Selection cercles de Bankass, Douentza et Youwarou (région de Mopti) ML-PRAPS-ML-46561-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 330 Consultant km de pare- feu autour des Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 30,395.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 zones de pâturages dans les Enhancement Implementation Selection cercles de Gao, Ansongo (région de Gao) et Niono (région de Ségou) ML-PRAPS-ML-47112-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 40,350.00 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection ML-PRAPS-ML-46757-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 40,350.00 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection BF-CILSS-46764-CS-CQS / Consultant Etude sur l'utilisation de Pending IDA / D0640 Pastoral Crisis Management Post Qualification Open - International 80,000.00 0.00 2018-03-08 2018-03-29 2018-05-12 2018-05-26 2018-06-16 2018-10-14 l'approche proxy calorique avec Implementation Selection les produits de l'élevage ML-PRAPS-ML-46972-CS-CQS Consultant / Etudes complémentaires de la Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 17,544.00 0.00 2018-05-22 2018-06-12 2018-07-26 2018-08-25 2018-09-29 2019-03-28 Stratégie Nationale d'hydraulique Enhancement Implementation Selection Pastorale ML-PRAPS-ML-46974-CS-CQS / Surveillance des travaux pour Consultant Pending les infrastructures marchandes et IDA / 56500 Market Access Facilitation Post Qualification Open - National 128,842.00 0.00 2018-05-29 2018-06-19 2018-08-02 2018-09-01 2018-10-06 2019-04-04 Implementation des magasins d'aliments bétail Selection dans la zone du Mali Nord Est ML-PRAPS-ML-47095-CS-CQS Consultant / Appui à l'élaboration des plans Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 52,632.00 0.00 2018-04-18 2018-05-09 2018-06-22 2018-07-22 2018-08-26 2019-02-22 de contingence communaux par Implementation Selection un bureau Consultant REF 41 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 50,000.00 0.00 2017-03-16 2017-04-06 2017-05-20 2017-06-19 2017-07-24 2018-01-20 des travaux Implementation Selection Consultant 40-C/PRAPS / Etude sur les IDA / 56490 Animal Health Improvement Post Qualification Open - National 34,000.00 0.00 Canceled 2017-03-31 2017-04-14 2017-05-05 2017-05-12 2017-06-16 2017-07-16 mandats sanitaires Selection TD-PRAPS-TD-50597-CS-QCBS / Recrutement d'un ingénieur Quality And Cost- Pending conseil pour la supervision et IDA / D0650 Market Access Facilitation Prior Open - National 2,545,454.00 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Based Selection Implementation contrôle des infrastructures pastorales INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-PRAPS-NE-7677-CS-INDV / Recrutement des 7 Assistants administratifs et financier, et 7 Project Management and Individual Consultant Pending IDA / 56510 Prior Open 235,200.00 0.00 2017-02-19 2017-04-09 2017-04-30 2017-06-04 2018-05-30 Assistants en suivi vé aluation Institutional Support Selection Implementation pour les antennes Régionales du PRAPS NE-PRAPS-NE-7680-CS-INDV / Project Management and Individual Consultant Pending IDA / 56510 Post Limited 20,000.00 0.00 2017-02-28 2017-03-05 2017-03-26 2017-04-30 2017-07-29 Création d'une base de données Institutional Support Selection Implementation NE-PRAPS-NE-7681-CS-INDV / Project Management and Individual Consultant Pending Renforcement des capacités en IDA / 56510 Post Limited 10,000.00 0.00 2017-06-19 2017-06-24 2017-07-15 2017-08-19 2017-09-18 Institutional Support Selection Implementation gestion et management NE-PRAPS-NE-7686-CS-INDV / Project Management and Individual Consultant Pending Conception et Réalisation du Site IDA / 56510 Post Limited 19,000.00 0.00 2017-02-19 2017-02-24 2017-03-17 2017-04-21 2017-05-12 Institutional Support Selection Implementation Web PRAPS NE-PRAPS-NE-7688-CS-INDV / Mise en place d'un reseau Project Management and Individual Consultant Pending IDA / 56510 Post Limited 27,000.00 0.00 2017-02-19 2017-02-24 2017-03-17 2017-04-21 2017-06-20 intranet et internet du MAG/EL ( Institutional Support Selection Implementation contribution) NE-PRAPS-NE-7695-CS-INDV / Project Management and Individual Consultant Pending Elaboration d'une strategie et IDA / 56510 Post Limited 24,000.00 0.00 2017-04-25 2017-04-30 2017-05-21 2017-06-25 2017-08-24 Institutional Support Selection Implementation d'un plan de communication NE-PRAPS-NE-7767-CS-INDV / Elaboration d'un document de Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Limited 15,000.00 0.00 2017-02-20 2017-02-25 2017-03-18 2017-04-22 2017-05-22 cadrage pour le financement des Selection Implementation AGR Page 9 NE-PRAPS-NE-7772-CS-INDV / Mise en place d'un système de Project Management and Individual Consultant Pending IDA / 56510 Post Limited 40,000.00 0.00 2017-02-26 2017-03-03 2017-03-24 2017-04-28 2017-05-28 documentation et d'archivage Institutional Support Selection Implementation Electronique NE-PRAPS-NE-7776-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 20,000.00 0.00 2017-02-20 2017-02-25 2017-03-18 2017-04-22 2017-05-22 pour l'analyse genre dans les Institutional Support Selection Implementation zones d'intervention du PRAPS NE-PRAPS-NE-7778-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 24,000.00 0.00 2017-02-20 2017-02-25 2017-03-18 2017-04-22 2017-05-22 pour l'elaboration de la strategie Institutional Support Selection Implementation genre NE-PRAPS-NE-7782-CS-INDV / Individual Consultant Pending Conception de model de marché IDA / 56510 Market Access Facilitation Post Limited 15,000.00 0.00 2017-05-22 2017-05-27 2017-06-17 2017-07-22 2017-08-21 Selection Implementation à betail PRAPS-SN-11-PI / Sélection d'un consultant pour l'étude sur la Individual Consultant Pending capitalisation des modèles de IDA / 56520 Pastoral Crisis Management Post Limited 10,000.00 0.00 2016-11-22 2017-01-17 2017-03-20 2017-04-24 2017-06-23 Selection Implementation gestion de magasins et boutiques pastorales BF-CILSS-9095-CS-CDS / t É ude comparative exportation de Individual Consultant Pending IDA / D0640 Market Access Facilitation Post Open 60,000.00 0.00 2018-01-28 2018-03-02 2018-03-09 2018-03-23 2018-06-21 viande versus exportation du Selection Implementation bétail sur pieds PRAPS-SN-02-PI / Sélection d'un consultant facilitateur dans Individual Consultant Pending le cadre de l'élaboration du plan IDA / 56520 Animal Health Improvement Post Limited 16,000.00 0.00 2017-03-20 2017-03-25 2017-04-15 2017-05-20 2017-08-18 Selection Implementation de lutte contre la circulation des médicaments frauduleux PRAPS-SN-05-PI / Sélection d'un consultant individuel pour les services de formation des relais aux techniques de constitution et Natural Resource Management Individual Consultant Pending IDA / 56520 Post Limited 14,000.00 0.00 2017-07-10 2017-07-15 2017-08-05 2017-09-09 2017-11-08 d'utilisation rationnelle Enhancement Selection Implementation (valorisation) des ressources (réserves) fourragères dans 8 départements PRAPS-SN-08-PI / Formation de Pending formateurs sur les modules IDA / 56520 Market Access Facilitation Prior Direct Selection Direct 20,000.00 0.00 2017-04-10 2017-04-20 2017-06-24 2017-07-24 Implementation commercialisation PRAPS-SN-13-PI / Sélection d'un consultant individuel pour la Natural Resource Management Individual Consultant Pending facilitation de la mise en place de IDA / 56520 Post Limited 10,000.00 0.00 2017-03-27 2017-04-01 2017-04-22 2017-05-27 2017-07-26 Enhancement Selection Implementation cadres de concertation et é aboration de leur plan d'action l PRAPS-SN-14-PI / Sélection d'un consultant individuel pour la Natural Resource Management Individual Consultant Pending IDA / 56520 Post Limited 10,000.00 0.00 2017-06-05 2017-06-10 2017-07-01 2017-08-05 2017-09-04 formation des animateurs en Enhancement Selection Implementation animation pastorale TD-PRAPS-TD-9184-CS-INDV / Etude technique et t é at des lieux Individual Consultant Pending IDA / D0650 Animal Health Improvement Post Limited 32,400.00 0.00 2017-03-15 2017-03-20 2017-04-10 2017-05-15 2017-11-11 sur les infrastructures à Selection Implementation réhabiliter à la DGSV TD-PRAPS-TD-9187-CS-INDV / Individual Consultant Pending Etude relative à la création d'un IDA / D0650 Animal Health Improvement Post Limited 1,200.00 0.00 2017-03-10 2017-03-15 2017-04-05 2017-05-10 2017-11-06 Selection Implementation fonds de roulement vaccinal TD-PRAPS-TD-9188-CS-INDV / formulation pour une bonne Individual Consultant Pending gestion de chaine de froid au IDA / D0650 Animal Health Improvement Post Limited 36,000.00 0.00 2017-03-06 2017-03-11 2017-04-01 2017-05-06 2017-11-02 Selection Implementation é ations niveau des délg régionales TD-PRAPS-TD-9196-CS-INDV / Individual Consultant Pending IDA / D0650 Market Access Facilitation Post Limited 18,181.00 0.00 2017-03-07 2017-03-12 2017-04-02 2017-05-07 2017-11-03 Réalisation du diagnostic SIM B Selection Implementation TD-PRAPS-TD-9243-CS-INDV / Recrutement d'un consultant Natural Resource Management Individual Consultant Pending pour l'actualisation des IDA / D0650 Post Limited 54,550.00 0.00 2017-04-30 2017-05-05 2017-05-26 2017-06-30 2017-12-27 Enhancement Selection Implementation aménagements d'hydraulique pastorale TD-PRAPS-TD-9247-CS-INDV / Natural Resource Management Individual Consultant Pending Recrutement d'un consultant IDA / D0650 Post Limited 43,636.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-12-17 Enhancement Selection Implementation pour l'étude sur l'inventaire TD-PRAPS-TD-9253-CS-INDV / é onomique Etude de faisabilité c Natural Resource Management Individual Consultant Pending IDA / D0650 Post Limited 21,818.00 0.00 2017-04-30 2017-05-05 2017-05-26 2017-06-30 2017-12-27 et environnemental sur les Enhancement Selection Implementation stations pastorales BF-CILSS-9303-CS-INDV / Assistance technique du CIRAD Project Management and Under IDA / D0640 Post Direct Selection Direct 28,000.00 0.00 2017-11-26 2017-09-18 2017-12-06 2017-12-21 2018-12-16 à la coordination régionale du Institutional Support Implementation PRAPS BF-CILSS-9306-CS-CDS / t É ude sur l'utilisation de l'approche Individual Consultant Pending IDA / D0640 Pastoral Crisis Management Post Open 60,000.00 0.00 2018-01-25 2018-02-27 2018-03-06 2018-04-03 2018-09-30 proxy calorique avec les produits Selection Implementation de l'élevage BF-CILSS-9314-CS-CDS / Suivi Pending des flux et tracasseries, IDA / D0640 Market Access Facilitation Post Direct Selection Direct 56,000.00 0.00 2018-01-07 2018-01-17 2018-02-07 2018-07-17 Implementation enquêtes de satisfaction BF-CILSS-9322-CS-INDV / Appui aux pays pour la mise en Project Management and Individual Consultant IDA / D0640 Post Open 80,000.00 43,065.26 Signed 2017-11-16 2017-08-16 2017-12-14 2017-12-06 2017-12-19 2017-12-22 2017-12-29 2018-01-10 2018-04-28 Suvre des mesures de Institutional Support Selection sauvegarde sociale TD-PRAPS-TD-9374-CS-INDV / Natural Resource Management Individual Consultant Pending Audit des capacités des IDA / D0650 Post Limited 21,818.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-12-17 Enhancement Selection Implementation opérateurs pastoraux nationaux TD-PRAPS-TD-9379-CS-INDV / Etude d'impact de la sécurité Natural Resource Management Individual Consultant Pending IDA / D0650 Post Limited 36,363.00 0.00 2017-04-20 2017-04-25 2017-05-16 2017-06-20 2017-12-17 dans le corridor de la zone Enhancement Selection Implementation pastorale TD-PRAPS-TD-9398-CS-INDV / Etude de faisabilité technique de Individual Consultant Pending construction de 12 marchés à IDA / D0650 Market Access Facilitation Post Limited 43,636.00 0.00 2017-04-25 2017-04-30 2017-05-21 2017-06-25 2017-12-22 Selection Implementation bétail et de 5 portes de sorties frontaliers TD-PRAPS-TD-9402-CS-INDV / Individual Consultant Pending Recrutement d'un consultant IDA / D0650 Pastoral Crisis Management Post Limited 21,812.00 0.00 2017-06-30 2017-07-05 2017-07-26 2017-08-30 2018-02-26 Selection Implementation pour l'encadrement harmoniosé TD-PRAPS-TD-9452-CS-INDV / Project Management and Individual Consultant Pending Audit des comptes du PRAPS IDA / D0650 Prior Open 46,000.00 0.00 2017-03-08 2017-04-26 2017-05-17 2017-06-21 2017-12-18 Institutional Support Selection Implementation 2015 2016 ET 2017 TD-PRAPS-TD-9456-CS-INDV / Project Management and Individual Consultant Pending IDA / D0650 Post Limited 36,363.00 0.00 2017-04-17 2017-04-22 2017-05-13 2017-06-17 2017-12-14 Etude d'impact environnemental Institutional Support Selection Implementation TD-PRAPS-TD-9458-CS-INDV / Project Management and Individual Consultant Pending Etude de la gouvernance des IDA / D0650 Post Limited 29,090.00 0.00 2017-05-10 2017-05-15 2017-06-05 2017-07-10 2018-01-06 Institutional Support Selection Implementation organisations pastorales TD-PRAPS-TD-9987-CS-INDV / Formulation et recommandation Individual Consultant Pending pour une bonne gestion de IDA / D0650 Animal Health Improvement Post Limited 3,600.00 0.00 2016-12-15 2016-12-15 2016-12-15 2017-01-05 2017-07-04 Selection Implementation chaine de froid au niveau des é ations régionales délg TD-PRAPS-TD-9992-CS-INDV / Individual Consultant Pending Etude pour la mise en place d'un IDA / D0650 Animal Health Improvement Post Limited 12,000.00 0.00 2016-12-23 2016-12-28 2017-01-18 2017-02-22 2017-08-21 Selection Implementation fonds de roulement pour vaccins TD-PRAPS-TD-9996-CS-INDV / Project Management and Individual Consultant Pending IDA / D0650 Post Limited 36,363.00 0.00 2016-12-19 2016-12-24 2017-01-14 2017-02-18 2017-08-17 Etude de stratégie genre Institutional Support Selection Implementation TD-PRAPS-TD-10000-CS-INDV / Project Management and Individual Consultant Pending Audit des comptes du PRAPS IDA / D0650 Post Limited 46,000.00 0.00 2016-09-26 2016-10-01 2016-10-22 2016-11-26 2017-05-25 Institutional Support Selection Implementation 2015 2016 et 2017 39-C/PRAPS / Etat des lieux Individual Consultant IDA / 56490 Market Access Facilitation Post Limited 13,520.00 11,578.42 Signed 2017-05-10 2017-05-29 2017-05-15 2017-09-11 2017-06-05 2017-10-06 2017-07-10 2017-10-12 2017-08-24 UTL et CCL Selection 33-C/PRAPS / Développer Individual Consultant Pending IDA / 56490 Market Access Facilitation Post Limited 7,000.00 0.00 2018-06-12 2018-06-17 2018-07-08 2018-08-12 2018-10-11 plateforme SIM bétail Selection Implementation 38-C/PRAPS / Elaboration outils Individual Consultant de suivi et collecte de données IDA / 56490 Pastoral Crisis Management Post Limited 15,000.00 10,710.17 Completed 2017-07-07 2017-05-11 2017-07-12 2017-05-30 2017-08-02 2017-06-17 2017-09-06 2017-07-03 2017-10-06 2017-07-04 Selection sur le pastoralisme 12-C/PRAPS / Suivi de la Project Management and Individual Consultant construction du mur de clôture IDA / 56490 Post Limited 1,500.00 1,735.50 Signed 2017-04-28 2017-06-05 2017-05-03 2017-06-13 2017-05-24 2017-07-31 2017-06-21 2017-09-20 2017-08-20 Institutional Support Selection de l'antenne de Fada 44-C/PRAPS / Diagnostic du Project Management and Individual Consultant Pending leadership des OP féminines et IDA / 56490 Post Limited 10,000.00 0.00 2019-07-31 2019-08-05 2019-08-19 2019-09-02 2019-10-02 Institutional Support Selection Implementation mixtes dans le pastoralisme 45-C/PRAPS / Réaliser en français, dupliquer et diffuser des Project Management and Individual Consultant Pending é issions sur les bonnes m IDA / 56490 Post Limited 7,200.00 0.00 2019-06-05 2019-06-10 2019-06-24 2019-07-15 2019-08-14 Institutional Support Selection Implementation pratiques alimentaires et nutritionnelles 22-C/PRAPS / Stratégie genre Project Management and Individual Consultant IDA / 56490 Post Limited 11,000.00 10,372.26 Completed 2017-01-27 2017-01-03 2017-02-01 2017-01-16 2017-02-22 2017-02-13 2017-03-29 2017-02-16 2017-09-25 2017-07-04 du PRAPS-BF Institutional Support Selection REF 37 / Appui à la direction Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 20,000.00 0.00 2017-03-19 2017-03-24 2017-04-14 2017-05-19 2017-11-15 nationale de lhydraulique Enhancement Selection Implementation REF 43 / Formation des Individual Consultant Under membres des comités de gestion IDA / 56500 Market Access Facilitation Post Limited 70,000.00 0.00 2017-05-04 2017-07-14 2017-05-09 2017-05-16 2017-05-30 2018-01-09 2017-07-04 2017-12-31 Selection Implementation des infrastructures marchandes REF 48 / Mise en place de la Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Post Limited 20,000.00 0.00 2017-04-02 2017-04-07 2017-04-28 2017-06-02 2017-11-29 plateforme pastorale Selection Implementation REF 49 / Elaboration de Individual Consultant Pending lexercice simulation du plan de IDA / 56500 Pastoral Crisis Management Post Open 20,000.00 0.00 2017-04-02 2017-05-21 2017-06-11 2017-07-16 2018-01-12 Selection Implementation contingence REF 50 / Rédaction du manuel Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Prior Open 60,000.00 0.00 2017-07-06 2017-08-24 2017-09-14 2017-10-19 2018-04-17 de procédures des AGR Selection Implementation REF 51 / Assistance technique Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Prior Open 60,000.00 0.00 2017-07-06 2017-08-24 2017-09-14 2017-10-19 2018-04-17 à la mise en Suvre des AGR Selection Implementation REF 52 / Elaboration/adaptation de cadres de gestion Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Post Limited 20,000.00 0.00 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 environnementale et sociale pour Selection Implementation les différents types dAGR Page 10 REF 57 / Appui de lUCP à la planification pour les activités de Project Management and Individual Consultant Pending IDA / 56500 Post Open 30,000.00 0.00 2017-02-14 2017-04-04 2017-04-25 2017-05-30 2017-11-26 gestion de la plateforme Institutional Support Selection Implementation Wepmaping REF 58 / Etude diagnostique Individual Consultant Pending des OP des femmes pasteurs et IDA / 56500 Pastoral Crisis Management Post Open 20,000.00 0.00 2017-04-18 2017-06-06 2017-06-27 2017-08-01 2018-01-28 Selection Implementation agropasteurs REF 60 / Etudes d'identification des travaux daménagement des Natural Resource Management Individual Consultant Pending IDA / 56500 Post Open 20,000.00 0.00 2017-05-28 2017-07-16 2017-08-06 2017-09-10 2018-03-09 pistes de transhumance et des Enhancement Selection Implementation gîtes d'étapes REF 61 / Appui aux négociations/validation des Natural Resource Management Individual Consultant Pending accords sociaux des IDA / 56500 Post Limited 20,000.00 0.00 2017-06-19 2017-06-24 2017-07-15 2017-08-19 2018-02-15 Enhancement Selection Implementation aménagements et infrastructures pour 1 mois REF 62 / Elaboration des modules de formation des Individual Consultant Pending é inaires titulaires de mandat IDA / 56500 vétr Animal Health Improvement Post Limited 50,000.00 0.00 2017-08-04 2017-08-09 2017-08-30 2017-10-04 2018-04-02 Selection Implementation sanitaires et des chefs de poste vétré inaires REF 64 / Elaboration dun Project Management and Individual Consultant Pending manuel de procédures, IDA / 56500 Post Open 20,000.00 0.00 2017-05-08 2017-06-26 2017-07-17 2017-08-21 2018-02-17 Institutional Support Selection Implementation financières REF 65 / Consultant individuel National du Projet dAppui au Project Management and Individual Consultant Pending IDA / 56500 Post Limited 26,400.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 Développement de lElevage Institutional Support Selection Implementation intensif au Mali REF 66 / Etude de la rentabilité Project Management and Individual Consultant Pending des modèles délevage IDA / 56500 Post Limited 10,000.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 Institutional Support Selection Implementation modernes(PADEL-M) REF 67 / Etude de la Project Management and Individual Consultant Pending disponibilité des fonds de IDA / 56500 Post Limited 10,000.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 Institutional Support Selection Implementation financement (PADEL-M) REF 68 / Etude sur le répertoire Project Management and Individual Consultant Pending IDA / 56500 Post Limited 10,000.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 des grands acheteurs PADEL-M Institutional Support Selection Implementation REF 69 / Etude sur le répertoire et la cartographie des Project Management and Individual Consultant Pending IDA / 56500 Post Limited 10,000.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 é onomiques infrastructures c Institutional Support Selection Implementation (PADEL-M) REF 70 / Etude sur le répertoire et la cartographie synthétique Project Management and Individual Consultant Pending IDA / 56500 Post Limited 10,000.00 0.00 2017-03-29 2017-04-03 2017-04-24 2017-05-29 2017-11-25 des interventions du Ministère de Institutional Support Selection Implementation lElevage et de la Pêche REF 71 / Etudes CEGS (PADEL- Project Management and Individual Consultant Pending IDA / 56500 Post Limited 20,000.00 0.00 2017-08-06 2017-08-11 2017-09-01 2017-10-06 2018-04-04 M) Institutional Support Selection Implementation REF 72 / Etudes CPRP Project Management and Individual Consultant Pending IDA / 56500 Post Limited 25,000.00 0.00 2017-08-06 2017-08-11 2017-09-01 2017-10-06 2018-04-04 (PADELM) Institutional Support Selection Implementation REF 79 / Elaboration des Individual Consultant Pending modules de formation des IDA / 56500 Animal Health Improvement Post Open 50,000.00 0.00 2017-08-04 2017-09-22 2017-10-13 2017-11-17 2018-05-16 Selection Implementation é inaires vétr REF 81 / Manuel de procédures Project Management and Individual Consultant Pending IDA / 56500 Post Limited 20,000.00 0.00 2017-05-17 2017-05-22 2017-06-12 2017-07-17 2018-01-13 financières Institutional Support Selection Implementation REF 82 / Plan dintervention Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Post Limited 20,000.00 0.00 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 durgence Selection Implementation NE-PRAPS-NE-7682-CS-INDV / Project Management and Individual Consultant Pending Renforcement des Capacités en IDA / 56510 Post Direct 10,000.00 0.00 2017-03-21 2017-03-31 2017-04-21 2017-05-26 2017-06-23 Institutional Support Selection Implementation passation des marchés NE-PRAPS-NE-7690-CS-INDV / Project Management and Individual Consultant Pending Recrutement d'un consultant IDA / 56510 Post Open 40,000.00 0.00 2017-02-20 2017-04-10 2017-05-01 2017-06-05 2018-05-31 Institutional Support Selection Implementation pour appui en sauvegarde sociale NE-PRAPS-NE-30293-CS-INDV Individual Consultant Pending / Analyse du fonctionnement des IDA / 56510 Pastoral Crisis Management Post Limited 14,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Selection Implementation systèmes des centres pastoraux é udes 51 / Réalisation des t environnementales et sociales Project Management and Individual Consultant Pending IDA / 56510 Post Limited 6,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 pour les projets programmés du Institutional Support Selection Implementation PRAPS 52 / Recrutement des ONGs et Associations pour les Travaux de Natural Resource Management Individual Consultant Pending IDA / 56510 Post Open 6,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 CES/DRS et ensemencement Enhancement Selection Implementation é s par des espèces appéte 54 / Etude pour une proposition d'harmonisation des textes Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Limited 14,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 législatifs et réglementaires sur Selection Implementation le pastoralisme 56 / Création d'une base de Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 données Institutional Support Selection Implementation é udes 57 / Réalisation des t environnementales et sociales Project Management and Individual Consultant Pending IDA / 56510 Post Open 6,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 pour les projets programmés du Institutional Support Selection Implementation PRAPS 59 / Analyse du fonctionnement Individual Consultant Pending des systèmes des centres IDA / 56510 Pastoral Crisis Management Post Limited 14,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Selection Implementation pastoraux 60 / Recrutement d'un Project Management and Individual Consultant Pending consultant pour appui en IDA / 56510 Post Open 40,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation sauvegarde sociale 61 / Elaboration d'un document Project Management and Individual Consultant Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 de Planification operationnelle Institutional Support Selection Implementation 62 / Assistant tehnique Project Management and Individual Consultant Pending IDA / 56510 Post Open 50,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 internationnale Institutional Support Selection Implementation 63 / Conception des Individual Consultant Pending IDA / 56510 Animal Health Improvement Post Limited 10,300.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 communication en santé animale Selection Implementation 64 / Harmonisation des textes Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Open 30,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 réglementaires et législatifs Selection Implementation 67 / Evaluation et amélioration Natural Resource Management Individual Consultant Pending du FOSEL (cabinet IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Enhancement Selection Implementation internationnal) 69 / Etude pour l'élaboration du plan de passation de marchés en période de crises pastorales en Individual Consultant Pending situation d'urgence ( contrôle, IDA / 56510 Pastoral Crisis Management Post Limited 6,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Selection Implementation qualité, délai, réputation&) et une première sélection d'opérateur 70 / Recrutement d'un Bureau d'Etudes pour la réalisation de Individual Consultant Pending collecte des données sur les IDA / 56510 Pastoral Crisis Management Post Open 60,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Selection Implementation infrastructures/Équipements et les ressources pastorales. 82 / Recrutement d un consultant Etude diagnostique Individual Consultant Pending IDA / 56510 Market Access Facilitation Post Limited 14,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 sur le système de gestion Selection Implementation é uée délg des marchés bétail 83 / Recrutement d'un Project Management and Individual Consultant Pending consultant pour l'elaboration de la IDA / 56510 Post Open 24,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation strategie genre 87 / Recrutement d'un consultant individuel pour la conception des solutions NTIC Individual Consultant Pending IDA / 56510 Market Access Facilitation Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 pour la transmission des Selection Implementation données au suivi des marchés à Bétail 88 / Elaboration du plan Individual Consultant Pending IDA / 56510 Animal Health Improvement Post Open 30,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 d'urgence PPCB/PPR Selection Implementation 89 / Révision du plan de Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Limited 6,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 contingence Selection Implementation 92 / Etat de lieu des sites de Individual Consultant Under collecte des données sur la IDA / 56510 Pastoral Crisis Management Post Open 30,000.00 0.00 2017-09-29 2017-10-26 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Selection Implementation biomasse au Niger 93 / Recrutemnt d'un consultant pour l'Etude Diagnosque des observatoires de suivi de la vulnérabilité (OSV) et des Individual Consultant Pending systèmes communautaires IDA / 56510 Pastoral Crisis Management Post Limited 14,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Selection Implementation d'alerte précoces et des reponses (SCAP/RU) dans les Zones pastorales et agropastorales du Niger 95 / Appui internationale en Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Open 40,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 ingenierie sociale Selection Implementation 96 / Realisation des etudes sur les filieres d'elevage en vue la Project Management and Individual Consultant Pending preparation du terrain pour le IDA / 56510 Post Open 40,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation futur projet de developpement de l'elevage au Niger 98 / Etat de lieu et Individual Consultant Pending georeferencement des IDA / 56510 Pastoral Crisis Management Post Limited 100,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Selection Implementation realisations du PRAPS 101 / Recrutement dun consultant pour etat de lieux ( Individual Consultant Pending IDA / 56510 Pastoral Crisis Management Post Limited 20,000.00 0.00 2017-09-29 2017-10-04 2017-10-25 2017-11-29 2018-05-28 Evaluation du fonctionnement Selection Implementation des centres pastoraux) 102 / Etude de préparation de la note conceptuelle par un Project Management and Individual Consultant Pending Consultant International, IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation Spécialiste en Développement de Projet 103 / Contribution à lEtude de préparation de la note Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 conceptuelle par un Consultant Institutional Support Selection Implementation National, Agro-Eco/Eco Page 11 104 / Etude Analyse Economique du projet par Un Project Management and Individual Consultant Pending IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Consultant International Agro- Institutional Support Selection Implementation Economiste 105 / Un Consultant national Project Management and Individual Consultant Pending Spécialiste en GRN, IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation Récupération des Terres et RNA 106 / Un Consultant Individual Consultant Pending International, Spécialiste des IDA / 56510 Pastoral Crisis Management Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Selection Implementation Filières Cuir, Viande et Peau 107 / Un consultant National, Project Management and Individual Consultant Pending Spécialiste des Filières Cuir, IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation Viande et Peau 108 / Un Consultant Project Management and Individual Consultant Pending International, Analyse de la IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation Filière Lait 109 / Un consultant National, Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Spécialiste de la Filière Lait Institutional Support Selection Implementation 110 / Consultant International Etude Analyse de la Filière Project Management and Individual Consultant Pending IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Volaille (poulet de chair, poulet Institutional Support Selection Implementation bicyclette, pintade et Ruf) 111 / Consultant national Etude Analyse de la Filière Volaille Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 (poulet de chair, poulet Institutional Support Selection Implementation bicyclette, pintade et Ruf) 112 / Un Consultant International Project Management and Individual Consultant Pending IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 pour la Mécanisation Agricole Institutional Support Selection Implementation 113 / Un consultant National, Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Spécialiste des Filières Institutional Support Selection Implementation 114 / Un consultant National, Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Spécialiste des Filières Agricole Institutional Support Selection Implementation 115 / Un Consultant International Project Management and Individual Consultant Pending IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Spécialiste en Irrigation Institutional Support Selection Implementation 116 / Un consultant national Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 spécialiste en Irrigation Institutional Support Selection Implementation 117 / Un consultant International Project Management and Individual Consultant Pending pour la péparation du document IDA / 56510 Post Open 100,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Institutional Support Selection Implementation du projet 118 / Un consultant national Project Management and Individual Consultant Pending IDA / 56510 Post Open 20,000.00 0.00 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 juriste Institutional Support Selection Implementation NE-PRAPS-NE-30653-CS-INDV Individual Consultant Pending / Elaboration d'un plan de IDA / 56510 Pastoral Crisis Management Post Limited 10,000.00 0.00 2017-10-17 2017-10-22 2017-11-12 2017-12-17 2018-06-15 Selection Implementation contengence pastoral NE-PRAPS-NE-30655-CS-INDV / Elaboration des outils de Project Management and Individual Consultant Pending sensiblisation sur les maladies IDA / 56510 Post Limited 30,000.00 0.00 2017-10-19 2017-10-24 2017-11-14 2017-12-19 2018-06-17 Institutional Support Selection Implementation prioritaires du betail et les maladies emergentes NE-PRAPS-NE-30656-CS-INDV / Manuel sur les maladies Individual Consultant Under prioritaires du betail à l'intention IDA / 56510 Animal Health Improvement Post Limited 30,000.00 0.00 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2018-05-31 Selection Implementation des agents des services veterinaires NE-PRAPS-NE-30658-CS-INDV / PRISE EN COMPTE MSES Natural Resource Management Individual Consultant Pending IDA / 56510 Post Limited 7,500.00 0.00 2017-10-11 2017-10-16 2017-11-06 2017-12-11 2018-06-09 POUR 8 STATIONS DE Enhancement Selection Implementation POMPAGES NE-PRAPS-NE-30660-CS-INDV / Assistance Technique Project Management and Individual Consultant Pending IDA / 56510 Post Limited 50,000.00 0.00 2018-06-13 2018-06-18 2018-07-09 2018-08-13 2019-02-09 Internationale ( COSTAB) pour le Institutional Support Selection Implementation nouveau projet NE-PRAPS-NE-30661-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Under IDA / 56510 Post Open 20,000.00 0.00 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 National en CGES pour le Institutional Support Selection Implementation nouveau projet NE-PRAPS-NE-30662-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 20,000.00 0.00 2018-03-13 2018-03-18 2018-04-08 2018-05-13 2018-11-09 National en CPRP pour le Institutional Support Selection Implementation nouveau projet NE-PRAPS-NE-30663-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / 56510 Post Open 30,000.00 0.00 2018-01-09 2018-02-27 2018-03-20 2018-04-24 2018-10-21 Environnementaliste et social Institutional Support Selection Implementation pour le nouveau projet NE-PRAPS-NE-30664-CS-INDV Natural Resource Management Individual Consultant Pending / Recrutement d'un consultant IDA / 56510 Post Limited 10,500.00 0.00 2017-11-21 2017-11-26 2017-12-17 2018-01-21 2018-07-20 Enhancement Selection Implementation pour appui en formation REF 35 / Formation de 42 Pending VTMS et 200 chefs postes IDA / 56500 Animal Health Improvement Post Direct Selection Direct 50,000.00 0.00 2017-04-05 2017-04-15 2017-06-19 2017-12-16 Implementation é inaires vétr REF 31 / Réalisation EIES/NIES pour les Individual Consultant Pending IDA / 56500 Animal Health Improvement Post Open 100,000.00 0.00 2017-02-26 2017-04-16 2017-05-07 2017-06-11 2017-12-08 infrastructures de la composante Selection Implementation 1 REF 32 / Réalisation des EIES/NIES pour les Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 100,000.00 0.00 2017-02-28 2017-03-05 2017-03-26 2017-04-30 2017-10-27 infrastructures de la composante Enhancement Selection Implementation 2 REF 33 / Réalisation EIES/NIES pour les Market Access Facilitation Individual Consultant Pending IDA / 56500 Post Limited 100,000.00 0.00 2017-03-04 2017-03-09 2017-03-30 2017-05-04 2017-10-31 infrastructures de la composante Pastoral Crisis Management Selection Implementation 3 et 4 REF 36 / Formation 300 Pending IDA / 56500 Animal Health Improvement Post Direct Selection Direct 50,000.00 0.00 2017-04-20 2017-04-30 2017-07-04 2017-12-31 auxiliaires de santé animale Implementation REF 53 / Elaboration dun cadre Individual Consultant Pending juridique et institutionnel du SIM- IDA / 56500 Market Access Facilitation Post Open 10,000.00 0.00 2017-07-19 2017-07-19 2017-07-19 2017-07-19 2017-07-19 Selection Implementation B REF 59 / Formation de 30 Pending IDA / 56500 Market Access Facilitation Post Direct Selection Direct 50,000.00 0.00 2017-06-04 2017-06-14 2017-08-18 2018-02-14 agents et 50 marchands de bétail Implementation ML-PRAPS-ML-31402-CS-INDV / manuel de procédures, Individual Consultant Pending IDA / 56500 Animal Health Improvement Post Limited 20,000.00 0.00 2017-10-10 2017-10-15 2017-11-05 2017-12-10 2018-06-08 financières pour le paiement de Selection Implementation la prime à la vaccination ML-PRAPS-ML-31407-CS-INDV / Recrutement d'un consultant Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Post Limited 20,000.00 0.00 2017-10-09 2017-10-14 2017-11-04 2017-12-09 2018-06-07 pour l'élaboration d'un plan Selection Implementation d'intervention d'urgence ML-PRAPS-ML-31408-CS-INDV / Recrutement d'un consultant chargé de l'audit institutionnel et Project Management and Individual Consultant Pending IDA / 56500 Post Limited 12,000.00 0.00 2017-10-09 2017-10-14 2017-11-04 2017-12-09 2018-06-07 organisationnel des Institutional Support Selection Implementation Organisations de Producteurs (OP) du PADEL-M ML-PRAPS-ML-31409-CS-INDV / Recrutement d'un Consultant chargé de la préparation d'un Project Management and Individual Consultant Pending IDA / 56500 Post Limited 25,000.00 0.00 2017-11-07 2017-11-12 2017-12-03 2018-01-07 2018-07-06 projet d'accord-cadre entre le Institutional Support Selection Implementation PADEL -M et les institutions financières partenaires (IFP) ML-PRAPS-ML-31410-CS-INDV / Recrutement d'un consultant chargé de l'étude pour la création Individual Consultant Pending de l'unité de prévention et de IDA / 56500 Pastoral Crisis Management Post Limited 15,000.00 0.00 2017-10-09 2017-10-14 2017-11-04 2017-12-09 2018-06-07 Selection Implementation gestion des crises au Ministère de l'Elevage et de la Pèche pour le PADEL-M ML-PRAPS-ML-31411-CS-INDV / Recrutement d'un consultant chargé de l'Etude d'analyse de la place actuelle des femmes et Project Management and Individual Consultant Pending des jeunes (15-40 ans) dans les IDA / 56500 Post Limited 25,000.00 0.00 2017-10-09 2017-10-14 2017-11-04 2017-12-09 2018-06-07 Institutional Support Selection Implementation filières d'élevage, y compris l'aquaculture et proposition de leur meilleure implication pour le PADEL-M ML-PRAPS-ML-31412-CS-INDV / Recrutement d'un Consultant é ence chargé de L'Etude de réfr Project Management and Individual Consultant Pending IDA / 56500 Post Limited 15,000.00 0.00 2017-10-10 2017-10-15 2017-11-05 2017-12-10 2018-06-08 du Cadre de résultats du Projet Institutional Support Selection Implementation au Développement de l'Elevage au Mali ML-PRAPS-ML-31413-CS-CDS / Recrutement d'un consultant SPECIALISTE AGRICOLE Project Management and Pending chargé d'appuyer l'équipe IDA / 56500 Post Direct Selection Direct 20,000.00 0.00 2017-10-11 2017-10-21 2017-12-25 2018-06-23 Institutional Support Implementation malienne de préparation du projet lors de la phase d'évaluation du PADEL-M ML-PRAPS-ML-31415-CS-CDS / Recrutement d'un consultant Project Management and Pending IDA / 56500 Post Direct Selection Direct 65,000.00 0.00 2017-10-11 2017-10-21 2017-12-25 2018-06-23 pour l'Evaluation du personnel du Institutional Support Implementation PRAPS-ML ML-PRAPS-ML-31417-CS-INDV / Recrutement d'un Consultant pour la mise en place du Project Management and Individual Consultant Pending IDA / 56500 Post Limited 20,000.00 0.00 2017-10-17 2017-10-22 2017-11-12 2017-12-17 2018-06-15 Système de documentation et Institutional Support Selection Implementation é ectronique du d'archivage l PRAPS MALI ML-PRAPS-ML-33295-CS-INDV / Recrutement d'un consultant chargé d'Appui à l'UCP pour la Project Management and Individual Consultant Pending IDA / 56500 Post Limited 100,000.00 0.00 2017-04-10 2017-04-15 2017-05-06 2017-06-10 2017-12-07 planification des activités en Institutional Support Selection Implementation sauvegardes environnementale et sociale ML-PRAPS-ML-33816-CS-INDV / Recrutement d'un consultant Natural Resource Management Individual Consultant Pending IDA / 56500 Post Direct 20,000.00 0.00 2017-10-31 2017-11-10 2017-12-01 2018-01-05 2018-07-04 international pour appuyer la Enhancement Selection Implementation composante 2 du PRAPS MALI Page 12 NE-PRAPS-NE-30659-CS-INDV / Recrutement d'un consultant en Individual Consultant Pending sauvegarde environnementale et IDA / 56510 Pastoral Crisis Management Post Open 50,000.00 0.00 2017-10-17 2017-12-05 2017-12-26 2018-01-30 2018-07-29 Selection Implementation sociale dans la région de Tillabery NE-PRAPS-NE-34421-CS-INDV / Recrutement d'un consultant en Project Management and Individual Consultant Pending IDA / 56510 Post Open 50,000.00 0.00 2017-12-20 2018-02-07 2018-02-28 2018-04-04 2018-10-01 sauvegarde environnementale et Institutional Support Selection Implementation sociale dans la région de Dosso NE-PRAPS-NE-34422-CS-INDV / Recrutement d'un pour appui en Project Management and Individual Consultant Pending consultant en sauvegarde IDA / 56510 Post Open 50,000.00 0.00 2017-11-22 2018-01-10 2018-01-31 2018-03-07 2018-09-03 Institutional Support Selection Implementation environnementale et sociale dans la région de Tahoua NE-PRAPS-NE-34467-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending pour appui en sauvegarde IDA / 56510 Post Open 50,000.00 0.00 2017-11-29 2018-01-17 2018-02-07 2018-03-14 2018-09-10 Institutional Support Selection Implementation environnementale et sociale dans la region de Maradi NE-PRAPS-NE-34470-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending pour appui en sauvegarde IDA / 56510 Post Open 50,000.00 0.00 2017-12-12 2018-01-30 2018-02-20 2018-03-27 2018-09-23 Institutional Support Selection Implementation environnementale et sociale dans la région d'Agadez NE-PRAPS-NE-34474-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending pour appui en sauvegarde IDA / 56510 Post Open 50,000.00 0.00 2017-11-23 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Institutional Support Selection Implementation environnementale et sociale dans la région de Zinder NE-PRAPS-NE-34488-CS-INDV / Recrutement d'un Consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-11-06 2017-11-11 2017-12-02 2018-01-06 2018-07-05 pour la mise à jour Institutional Support Selection Implementation COSTAB/PTBA2018 NE-PRAPS-NE-34489-CS-INDV / Recrutement d'un Consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-11-06 2017-11-11 2017-12-02 2018-01-06 2018-07-05 PIMELAN, Appui à l'identification Institutional Support Selection Implementation du Projet NE-PRAPS-NE-34490-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / 56510 Post Limited 50,000.00 0.00 2017-11-07 2017-11-12 2017-12-03 2018-01-07 2018-07-06 é aluation du pour la préparation v Institutional Support Selection Implementation nouveau Projet NE-PRAPS-NE-34491-CS-INDV / recrutement d'un consultant Project Management and Individual Consultant Pending pour Appui Spécialisation en IDA / 56510 Post Limited 50,000.00 0.00 2017-11-10 2017-11-15 2017-12-06 2018-01-10 2018-07-09 Institutional Support Selection Implementation gestion des ressources en Afrique de l'Ouest au Sahel NE-PRAPS-NE-34492-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending pour appui Spécialisation, IDA / 56510 Post Limited 50,000.00 0.00 2017-11-03 2017-11-08 2017-11-29 2018-01-03 2018-07-02 Institutional Support Selection Implementation Facilitation Accé au marché en Afrique de l'Ouest au Sahel NE-PRAPS-NE-34493-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending Spécialiste de la gestion de crise IDA / 56510 Post Limited 50,000.00 0.00 2017-11-14 2017-11-19 2017-12-10 2018-01-14 2018-07-13 Institutional Support Selection Implementation pastorale en Afrique de l'Ouest au Sahel NE-PRAPS-NE-34494-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending pour appui en sauvegarde IDA / 56510 Post Limited 50,000.00 0.00 2017-12-19 2017-12-24 2018-01-14 2018-02-18 2018-08-17 Institutional Support Selection Implementation environnementale et sociale dans la région de Diffa BF-CILSS-36687-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Pending IDA / D0640 Post Open 5,000.00 0.00 2017-11-17 2017-12-09 2017-12-14 2017-12-24 2017-12-31 pour la formation sur le suivi Institutional Support Selection Implementation é aluation en zone de conflits v 15-C/PRAPS / Recrutement d'un Project Management and Individual Consultant consultant pour l'élaboration de la IDA / 56490 Post Limited 20,000.00 9,007.14 Completed 2017-11-13 2017-04-27 2017-11-27 2017-06-12 2017-12-11 2017-08-01 2018-01-15 2017-08-03 2018-02-14 2017-10-25 Institutional Support Selection plateforme web du PRAPS-BF 14-C/PRAPS / Recrutement d'un consultant en sauvegarde sociale pour appuyer le PRAPS dans la Project Management and Individual Consultant IDA / 56490 Post Limited 20,000.00 22,016.69 Signed 2017-11-13 2017-08-30 2017-11-27 2017-09-05 2017-12-11 2017-10-05 2018-01-15 2017-10-16 2018-03-16 prise en compte des questions Institutional Support Selection de sauvegarde sociale dans la mise en Suvre du projet 24-C/PRAPS / Recrutement d'un Project Management and Individual Consultant coordonnateur national pour le IDA / 56490 Post Direct 247,760.00 3,687.91 Signed 2017-11-13 2017-02-23 2017-11-19 2017-07-28 2017-11-20 2017-08-14 2017-11-22 2017-08-24 2022-11-16 Institutional Support Selection compte du PRAPS-BF 25-C/PRAPS / Recrutement d'un Spécialiste en Communication Project Management and Individual Consultant IDA / 56490 Post Direct 150,000.00 2,183.89 Signed 2017-11-13 2017-02-23 2017-11-19 2017-07-28 2017-11-20 2017-08-14 2017-11-22 2017-08-24 2022-11-21 pour le compte du PRAPS-BF et Institutional Support Selection du PADEL-B 26-C/PRAPS / Recrutement d'un Spécialiste en Gestion des Project Management and Individual Consultant IDA / 56490 Post Direct 134,000.00 1,935.98 Signed 2017-11-13 2017-02-23 2017-11-19 2017-07-28 2017-11-20 2017-08-14 2017-11-22 2017-08-24 2022-11-21 ressources naturelles pour le Institutional Support Selection compte du PRAPS-BF 27-C/PRAPS / Recrutement d'un Spécialiste en Gestion des Project Management and Individual Consultant IDA / 56490 Post Direct 134,000.00 1,935.98 Signed 2017-11-14 2017-02-23 2017-11-20 2017-07-28 2017-11-21 2017-08-14 2017-11-23 2017-08-24 2022-11-22 crises pastorales pour le compte Institutional Support Selection du PRAPS-BF 28-C/PRAPS / Recrutement d'un Spécialiste en Genre pour le Project Management and Individual Consultant IDA / 56490 Post Direct 150,000.00 2,183.89 Signed 2017-11-14 2017-02-23 2017-11-20 2017-07-28 2017-11-21 2017-08-14 2017-11-23 2017-08-24 2022-11-22 compte du PRAPS-BF et du Institutional Support Selection PADEL-B 29-C/PRAPS / Recrutement d'un Spécialiste en Sauvegarde Project Management and Individual Consultant IDA / 56490 Post Direct 150,000.00 2,183.71 Signed 2017-11-14 2017-02-23 2017-11-20 2017-07-28 2017-12-11 2017-08-14 2017-12-26 2017-08-24 2022-12-25 environnementale pour le compte Institutional Support Selection du PRAPS-BF et du PADEL-B 30-C/PRAPS / Recrutement d'un Project Management and Individual Consultant Chef d'antenne pour le compte du IDA / 56490 Post Direct 134,000.00 1,935.98 Signed 2017-11-15 2017-02-23 2017-11-21 2017-07-28 2017-11-22 2017-08-14 2017-11-24 2017-08-24 2022-11-23 Institutional Support Selection PRAPS-BF à Bobo-Dioulasso 31-C/PRAPS / Recrutement d'un Project Management and Individual Consultant Chef d'antenne pour le compte du IDA / 56490 Post Direct 134,000.00 1,938.62 Signed 2017-11-15 2017-02-23 2017-11-21 2017-07-28 2017-11-22 2017-08-14 2017-11-24 2017-08-24 2022-11-23 Institutional Support Selection PRAPS-BF à Dori 23-C/PRAPS / Recrutement d'un Project Management and Individual Consultant Chef d'antenne pour le compte du IDA / 56490 Post Direct 134,000.00 1,935.98 Signed 2017-11-15 2017-02-23 2017-11-21 2017-07-28 2017-11-22 2017-08-14 2017-11-24 2017-08-24 2022-11-23 Institutional Support Selection PRAPS-BF à Fada 01-C/MOD / constitution des documents cadastraux des sites pour la construction et Animal Health Improvement réhabilitation des (19) Postes Natural Resource Management Individual Consultant Under IDA / 56490 Post Limited 50,000.00 0.00 2017-12-02 2017-08-23 2017-12-07 2017-12-21 2018-01-11 2018-02-10 é inaires vétr dont 7 de l'Antenne Enhancement Selection Implementation de Fada, (12) Postes vétr é inaires Market Access Facilitation de l'Antenne de Dori /sahel (Seyten 02-C/MOD / Constitution des documents cadastraux des sites pour la construction et Animal Health Improvement réhabilitation de (11) Postes Natural Resource Management Individual Consultant Under IDA / 56490 Post Limited 50,000.00 0.00 2017-12-02 2017-08-23 2017-12-07 2017-12-21 2018-01-25 2018-02-24 é inaires de l'Antenne de Bobo vétr Enhancement Selection Implementation /Hauts - Bassins-Boucle du Market Access Facilitation Mouhoun (Bérb é a, Satiri, Bama, Padema, Kolo MR-PRAPS-MR -43179-CS- INDV / Etudes d'impact Individual Consultant Pending environnemental de 12 forages IDA / D0660 Pastoral Crisis Management Post Limited 6,000.00 0.00 2018-01-30 2018-02-04 2018-02-25 2018-04-01 2018-09-28 Selection Implementation dans 4 wilayas pour le plan d'urgence MR-PRAPS-MR -43180-CS- INDV / Etude d'impact social de Individual Consultant Pending IDA / D0660 Pastoral Crisis Management Post Limited 6,000.00 0.00 2018-01-30 2018-02-04 2018-02-25 2018-04-01 2018-09-28 12 forages dans 4 wilayas pour le Selection Implementation plan d'urgence. BF-CILSS-44410-CS-INDV / Recrutement dun Consultant individuel pour la formation Project Management and Individual Consultant Under IDA / D0640 Post Open 6,000.00 0.00 2018-01-24 2018-01-20 2018-02-19 2018-02-24 2018-03-25 2018-04-04 régionale en Communication Institutional Support Selection Implementation axée sur les crises pastorales et la gestion des conflits ML-PRAPS-ML-47283-CS-INDV / Formation du personnel de Project Management and Individual Consultant Pending IDA / 56500 Post Open 20,000.00 0.00 2018-04-09 2018-05-28 2018-06-18 2018-07-23 2019-01-19 l'UCP et structures partenaires Institutional Support Selection Implementation en passation de marchés 36-C/PRAPS / Représentation Natural Resource Management de sketchs par THEATRE DE IDA / 56490 Post Direct Selection Direct 36,000.00 27,304.70 Signed 2017-09-14 2016-08-02 2017-09-24 2017-11-07 2017-10-03 2017-11-13 2017-11-02 Enhancement L'ESPOIR 13-C/PRAPS / Recrutement d'un consultant pour appuyer le Project Management and PRAPS-BF dans la 5ème IDA / 56490 Post Direct Selection Direct 10,986.00 10,324.18 Signed 2017-11-16 2017-10-09 2017-11-21 2017-10-17 2017-11-24 2017-11-13 2017-12-01 Institutional Support mission de suivi de la Banque Mondiale MOF-REF-14 / Etude sur le Individual Consultant IDA / 56490 Animal Health Improvement Post Direct 17,000.00 13,714.63 Signed 2017-03-31 2016-06-09 2017-04-28 2017-05-04 2017-05-05 2017-08-03 2017-06-02 2017-08-04 2017-07-02 mandat sanitaire. Selection BF-PRAPS-BF-46015-CS-INDV Project Management and Individual Consultant Pending / Base de données, archivage IDA / 56490 Post Limited 11,400.00 0.00 2018-09-19 2018-09-24 2018-10-15 2018-11-19 2019-01-03 Institutional Support Selection Implementation é ectronique l BF-PRAPS-BF-46335-CS-INDV / Opérateur en Alphabétisation Individual Consultant Under pour la formation des OP et IP de IDA / 56490 Market Access Facilitation Post Limited 6,400.00 0.00 2017-11-13 2017-10-02 2017-11-18 2017-10-26 2017-12-18 2018-01-31 2018-03-02 Selection Implementation la Région de la Boucle du Mouhoun ML-PRAPS-ML-46371-CS-INDV Individual Consultant Pending / Appui au renforcement des IDA / 56500 Pastoral Crisis Management Post Open 49,123.00 0.00 2018-08-28 2018-10-16 2018-11-06 2018-12-11 2019-06-09 Selection Implementation capacités des COFO ML-PRAPS-ML-46372-CS-INDV / Appui à l'élaboration de 110 Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 92,632.00 0.00 2018-04-21 2018-04-26 2018-05-17 2018-06-21 2018-12-18 conventions locales de Gestion Enhancement Selection Implementation des Ressources Naturelles ML-PRAPS-ML-46373-CS-INDV / Appui à l'élaboration de 80 Project Management and Individual Consultant Pending Accords sociaux sur les bonnes IDA / 56500 Post Limited 84,211.00 0.00 2018-05-29 2018-06-03 2018-06-24 2018-07-29 2019-01-25 Institutional Support Selection Implementation pratiques de gestion pour la prévention des conflits ML-PRAPS-ML-46374-CS-INDV / Appui à la formalisation de deux cadres de concertations inter Project Management and Individual Consultant Pending communautaires et IDA / 56500 Post Limited 14,035.00 0.00 2018-07-07 2018-07-12 2018-08-02 2018-09-06 2019-03-05 Institutional Support Selection Implementation transfrontaliers sur la transhumance et la gestion des parcours Page 13 ML-PRAPS-ML-46375-CS-INDV / Elaboration et la validation de 15 schémas communaux Individual Consultant Pending d'aménagement du territoire par IDA / 56500 Market Access Facilitation Post Limited 63,158.00 0.00 2018-04-03 2018-04-08 2018-04-29 2018-06-03 2018-11-30 Selection Implementation les collectivités territoriales dans les zones du Sahel occidental et du Delta Central ML-PRAPS-ML-46376-CS-INDV / Appui à la réalisation d'une é ude pour l'élaboration et la t Natural Resource Management Individual Consultant Pending validation de 5 schémas IDA / 56500 Post Limited 26,315.00 0.00 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 Enhancement Selection Implementation d'aménagement de terroirs par les collectivités territoriales dans la zone du Mali Nord-Est ML-PRAPS-ML-46563-CS-INDV / Appui à la diffusion des textes Natural Resource Management Individual Consultant Pending règlementaires et législatifs sur IDA / 56500 Post Limited 35,088.00 0.00 2018-07-22 2018-07-27 2018-08-17 2018-09-21 2019-03-20 Enhancement Selection Implementation le pastoralisme et l'accès aux ressources naturelles ML-PRAPS-ML-46564-CS-INDV / Formation et recyclage de 200 agents des services d'appui- Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 42,105.00 0.00 2018-07-09 2018-07-14 2018-08-04 2018-09-08 2019-03-07 conseil/ONG sur 4 thèmes Enhancement Selection Implementation relatifs à l'accès paisible aux ressources pastorales ML-PRAPS-ML-46565-CS-INDV / Elaboration et diffusion des Project Management and Individual Consultant Pending messages d'information, de IDA / 56500 Post Limited 14,035.00 0.00 2018-06-05 2018-06-10 2018-07-01 2018-08-05 2019-02-01 Institutional Support Selection Implementation sensibilisation et de formation des acteurs sur 4 supports PRAPS-SN-03-PI-2018 / Sélection d'un cabinet pour les Pending é udes techniques en vue de la t IDA / 56520 Market Access Facilitation Post Direct Selection Direct 240,000.00 0.00 2018-04-16 2018-04-26 2018-06-30 2018-12-27 Implementation réhabilitation de 215 km de pistes rurales PRAPS-SN-01-PI-2018 / Contractualisation avec ODVS pour l'opérationnalisation du Pending IDA / 56520 Animal Health Improvement Post Direct Selection Direct 30,000.00 0.00 2018-02-28 2018-03-10 2018-05-14 2019-05-14 dispositif déploiement des Implementation mandataires dans les zones pastorales ML-PRAPS-ML-46714-CS-INDV / Formation de 200 membres des comités de gestion sur la gestion et la maintenance durables des Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 56,140.00 0.00 2018-08-01 2018-08-06 2018-08-27 2018-10-01 2019-03-30 infrastructures/aménagements Enhancement Selection Implementation pastoraux et sur les aspects de Sauvegardes Environnementale et Sociale ML-PRAPS-ML-47114-CS-INDV / Appui à l'actualisation de la Natural Resource Management Individual Consultant Pending IDA / 56500 Post Limited 3,509.00 0.00 2018-03-26 2018-03-31 2018-04-21 2018-05-26 2018-11-22 cartographie des infrastructures Enhancement Selection Implementation d'hydraulique pastorale BF-CILSS-46752-CS-INDV / Recrutement d'un consultant Project Management and Individual Consultant Under IDA / D0640 Post Open 5,000.00 0.00 2018-02-05 2018-02-07 2018-03-10 2018-03-17 2018-03-31 2018-05-30 pour l'assistance en passation Institutional Support Selection Implementation des marchés BF-CILSS-46754-CS-CDS / Consultant pour l'élaboration de é ectronique la plateforme l Pending IDA / D0640 Market Access Facilitation Post Direct Selection Direct 25,000.00 0.00 2018-03-07 2018-03-17 2018-04-28 2018-08-26 régionale de diffusion des Implementation informations sur les marchés à bétail BF-CILSS-46759-CS-CDS / Appui à l'organisation des Pending ateliers nationaux de partage des IDA / D0640 Market Access Facilitation Post Direct Selection Direct 20,000.00 0.00 2018-03-15 2018-03-25 2018-04-29 2018-10-26 Implementation textes réglementaires sur le commerce du bétail BF-CILSS-46957-CS-CDS / Etude comparative sur Pending IDA / D0640 Market Access Facilitation Post Direct Selection Direct 60,000.00 0.00 2018-02-27 2018-03-09 2018-05-13 2018-09-10 l'exportation de betail vs Implementation exportation de carcasses ML-PRAPS-ML-46965-CS-INDV / Formation et recyclage de 50 Individual Consultant Pending agents des services techniques IDA / 56500 Market Access Facilitation Post Limited 31,579.00 0.00 2018-04-03 2018-04-08 2018-04-29 2018-06-03 2018-11-30 Selection Implementation et ONG sur les méthodes, outils et techniques ML-PRAPS-ML-46973-CS-INDV / Formation des membres de 25 Individual Consultant Pending comités de gestion des IDA / 56500 Market Access Facilitation Post Limited 43,860.00 0.00 2018-05-04 2018-05-09 2018-05-30 2018-07-04 2018-12-31 Selection Implementation infrastructures marchandes y compris les sauvegardes ML-PRAPS-ML-47091-CS-INDV / Formation de 55 bouchers sur Individual Consultant Pending IDA / 56500 Market Access Facilitation Post Limited 35,087.00 0.00 2018-07-02 2018-07-07 2018-07-28 2018-09-01 2019-02-28 la technique de découpe dans la Selection Implementation zone d'intervention du projet ML-PRAPS-ML-47092-CS-INDV / Appui à la structuration et à la Individual Consultant Pending IDA / 56500 Market Access Facilitation Post Limited 35,087.00 0.00 2018-08-06 2018-08-11 2018-09-01 2018-10-06 2019-04-04 mise en place de l'inter Selection Implementation profession bétail-viande ML-PRAPS-ML-47093-CS-INDV / Etude sur à la mise en place Project Management and Individual Consultant Pending IDA / 56500 Post Limited 26,315.00 0.00 2018-05-07 2018-05-12 2018-06-02 2018-07-07 2019-01-03 d'un système financier Institutional Support Selection Implementation décentralisé ML-PRAPS-ML-47097-CS-INDV / Organisation d'un atelier de mise à jour du plan de Individual Consultant Pending IDA / 56500 Pastoral Crisis Management Post Limited 10,526.00 0.00 2018-05-02 2018-05-07 2018-05-28 2018-07-02 2018-12-29 contingence aux crises Selection Implementation pastorales avec l'appui d'un consultant ML-PRAPS-ML-47098-CS-INDV / Formation des membres des comités de gestion de 10 Individual Consultant Pending magasins l'aliment bétail en IDA / 56500 Pastoral Crisis Management Post Limited 17,544.00 0.00 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 Selection Implementation gestion des stocks, hygiène et assainissement par un consultant ML-PRAPS-ML-47102-CS-INDV / Préparation et l'organisation de Project Management and Individual Consultant Pending IDA / 56500 Post Limited 52,631.00 0.00 2018-09-11 2018-09-16 2018-10-07 2018-11-11 2019-05-10 mission de revue à mi-parcours Institutional Support Selection Implementation du projet ML-PRAPS-ML-47103-CS-INDV / Elaboration d'un manuel de Project Management and Individual Consultant Pending bonnes pratiques IDA / 56500 Post Limited 12,281.00 0.00 2018-10-09 2018-10-14 2018-11-04 2018-12-09 2019-06-07 Institutional Support Selection Implementation environnementales dans le domaine du pastoralisme ML-PRAPS-ML-47104-CS-INDV / Formation des OP, collectivités Project Management and Individual Consultant Pending locales en sauvegarde IDA / 56500 Post Limited 52,632.00 0.00 2018-11-06 2018-11-11 2018-12-02 2019-01-06 2019-07-05 Institutional Support Selection Implementation environnementale et prévention et sensibilité aux conflits ML-PRAPS-ML-47105-CS-INDV / Appui au MEP pour la réalisation des té udes complémentaires afin d'actualiser des documents stratégiques Project Management and Individual Consultant Pending relatifs entre autres à la IDA / 56500 Post Limited 42,105.00 0.00 2018-03-31 2018-04-05 2018-04-26 2018-05-31 2018-11-27 Institutional Support Selection Implementation transhumance, aux règles d'accès aux ressources pastorales, à l'hydraulique pastorale, au processus politique de l'élevage, ML-PRAPS-ML-47106-CS-INDV / Renforcement des capacités de l'expert communication de l'UCP Project Management and Individual Consultant Pending IDA / 56500 Post Limited 4,210.00 0.00 2018-03-12 2018-03-17 2018-04-07 2018-05-12 2018-11-08 sur les techniques de mise Institutional Support Selection Implementation d'animation du site web, des pages Facebook et YouTube ML-PRAPS-ML-47108-CS-INDV / Formation sur l'administration d'une Organisation Socio- Project Management and Individual Consultant Pending Professionnelle féminine sur IDA / 56500 Post Limited 52,631.00 0.00 2018-04-05 2018-04-10 2018-05-01 2018-06-05 2018-12-02 Institutional Support Selection Implementation l'harmonisation des textes Réglementaires -documents archives ML-PRAPS-ML-33830-CS-CDS / Recrutement d'un consultant Natural Resource Management Pending IDA / 56500 Post Direct Selection Direct 20,000.00 0.00 2017-10-31 2017-11-10 2018-01-14 2018-07-13 international pour appuyer la Enhancement Implementation composante 2 du PRAPS MALI ML-PRAPS-ML-48018-CS-CDS / Mise à jour de la base des Pending données du SAP avec les IDA / 56500 Pastoral Crisis Management Post Direct Selection Direct 13,158.00 0.00 2018-03-02 2018-03-12 2018-05-16 2018-11-12 Implementation indicateurs pastoraux par un consultant TD-PRAPS-TD-9405-CS-INDV / Assistance technique pour appui Project Management and Individual Consultant Pending IDA / D0650 Post Limited 99,000.00 0.00 2018-05-15 2018-05-20 2018-06-10 2018-07-15 2019-01-11 à la mise en Suvre du projet Institutional Support Selection Implementation (planification et méthodologie) TD-PRAPS-TD-9189-CS-INDV / Elaboration d'un plan de Individual Consultant Pending IDA / D0650 Animal Health Improvement Post Limited 70,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 formation des agents des Selection Implementation é inaires services vétr TD-PRAPS-TD-9193-CS-INDV / Natural Resource Management Individual Consultant Pending Etude technique sur les ouvrages IDA / D0650 Post Limited 4,200.00 0.00 2018-06-15 2018-06-20 2018-07-11 2018-08-15 2019-02-11 Enhancement Selection Implementation dans les sables boulant TD-PRAPS-TD-9241-CS-INDV / recrutement d'un consultant Natural Resource Management Individual Consultant Pending international pour appui en IDA / D0650 Post Limited 18,181.00 0.00 2018-05-25 2018-05-30 2018-06-20 2018-07-25 2019-01-21 Enhancement Selection Implementation formation et organisation du dispositif AGRP TD-PRAPS-TD-50575-CS-INDV / Individual Consultant Pending Consultant pour la formation sur IDA / D0650 Animal Health Improvement Post Limited 81,818.00 0.00 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2018-10-27 Selection Implementation l'approche PPCB TD-PRAPS-TD-50582-CS-INDV / Supervision des travaux de Individual Consultant Pending IDA / D0650 Animal Health Improvement Post Limited 35,000.00 0.00 2018-05-31 2018-06-05 2018-06-26 2018-07-31 2019-01-27 réhabilitation des unités Selection Implementation é inaires vétr TD-PRAPS-TD-50587-CS-INDV / Consultant pour la formation des Natural Resource Management Individual Consultant Pending IDA / D0650 Post Limited 40,909.00 0.00 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 enquêteurs SPSA, PF, SISAAP Enhancement Selection Implementation et les antennes TD-PRAPS-TD-50593-CS-INDV / Natural Resource Management Individual Consultant Pending Consultation pour la formation de IDA / D0650 Post Limited 21,545.00 0.00 2018-05-15 2018-05-20 2018-06-10 2018-07-15 2019-01-11 Enhancement Selection Implementation l'équipe SIPSA et les 5 antennes Page 14 TD-PRAPS-TD-50603-CS-INDV / Natural Resource Management Individual Consultant Pending Etude de réhabilitation des IDA / D0650 Post Limited 36,641.00 0.00 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 Enhancement Selection Implementation périmètres pastoraux TD-PRAPS-TD-50606-CS-INDV / Natural Resource Management Individual Consultant Pending IDA / D0650 Post Direct 21,000.00 0.00 2018-06-05 2018-06-15 2018-07-06 2018-08-10 2019-02-06 Inventaire de l'espace pastorale Enhancement Selection Implementation TD-PRAPS-TD-50607-CS-INDV / Individual Consultant Pending Consultant pour la formation sur IDA / D0650 Pastoral Crisis Management Post Limited 81,818.00 0.00 2018-04-15 2018-04-20 2018-05-11 2018-06-15 2018-12-12 Selection Implementation l'approche LEGS TD-PRAPS-TD-50757-CS-INDV / Individual Consultant Pending Consultant pour la formation des IDA / D0640 Pastoral Crisis Management Post Limited 54,545.00 0.00 2018-04-20 2018-04-25 2018-05-16 2018-06-20 2018-12-17 Selection Implementation formateurs LEGS TD-PRAPS-TD-50759-CS-INDV / é aluation de la Consultant pour v Individual Consultant Pending IDA / D0650 Pastoral Crisis Management Post Limited 43,636.00 0.00 2018-09-14 2018-09-19 2018-10-10 2018-11-14 2019-05-13 réponse à la dernière crise Selection Implementation pastorale 2017-2018 TD-PRAPS-TD-50764-CS-INDV / Project Management and Individual Consultant Pending Consultant national de court IDA / D0650 Post Limited 21,818.00 0.00 2018-06-05 2018-06-10 2018-07-01 2018-08-05 2019-02-01 Institutional Support Selection Implementation terme pour le SIG TD-PRAPS-TD-50767-CS-INDV / Expert Ingénieur Génie Civil Project Management and Individual Consultant Pending IDA / D0650 Post Limited 21,818.00 0.00 2018-04-05 2018-04-10 2018-05-01 2018-06-05 2018-12-02 appui à la passation des Institutional Support Selection Implementation marchés TD-PRAPS-TD-50841-CS-INDV / Project Management and Individual Consultant Pending IDA / D0650 Post Limited 37,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 Consultant sauvegarde sociale Institutional Support Selection Implementation TD-PRAPS-TD-50854-CS-INDV / Project Management and Individual Consultant Pending é ence sur le genre IDA / D0650 Etude de réfr Post Limited 27,272.00 0.00 2018-02-28 2018-03-05 2018-03-26 2018-04-30 2018-10-27 Institutional Support Selection Implementation PRAPS-TD TD-PRAPS-TD-50867-CS-INDV / Etude pour l'évaluation et Project Management and Individual Consultant Pending IDA / D0650 Post Limited 27,272.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 l'actualisation de la situation de Institutional Support Selection Implementation é ence du PRAPS réfr Page 15