PROCUREMENT PLAN PERU INTEGRATED WATER RESOURCES MANAGEMENT IN TEN BASINS PROJECT P151851 I. General 1. Bank’s approval Date of the procurement Plan: Original, February 23, 2017 2. Date of General Procurement Notice: February 23, 2017 3. Period covered by this procurement plan: all the procurement process planned II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Below US$ 2 million None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Below US$ 10 million None 2. Project Operational/Procurement Manual: Procurement implementation details activities will be outlined in the Project Operational Manual (POM) 3. Any Other Special Procurement Arrangements: None 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 Description Estimated Package Domestic Review Comments Cost s Preferenc by Bank US$ e (Prior / Post) million (yes/no) Summary of the ICB (Goods) 25.2 5 No Prior Summary of the NCB (Works) 9.28 5 No Post Summary of the NCB (Goods) 3.16 4 No Post III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 350,000 All 2. Single Source (Firms) All 3. Individual Key personnel All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 350,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Description of Assignment Estimated Packages Review Comments Cost by Bank US$ million (Prior / Post) Summary of number of 15.95 10 Prior contracts that will be let under QCBS > US$ 350 mil Summary of number of 1.20 5 Post contracts that will be let under QCBS < US$ 350 mil PROCUREMENT Peru : Integrated Water Resources Management in Ten Basins PLAN General Information Country: Peru Banks Approval Date of the Original Procurement Plan: 2018-03-16 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-22 Project ID: P151851 GPN Date: Project Name: Integrated Water Resources Management in Ten Basins Loan / Credit No: IBRD / 87400 Executing Agency(ies): National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA) WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LPN 003 2018 ANA PGIRH BM / PERFORACIÓN E INSTALACIÓN DE 58 Component 1: Consolidating Single Stage - One Under IBRD / 87400 Post Request for Bids Open - National 2,205,593.00 0.00 2018-07-26 2018-08-08 2018-07-29 2018-08-28 2018-09-07 2018-09-26 2019-01-23 PIEZÓMETROS EN LOS IWRM at the National Level Envelope Implementation ACUÍFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LPI 002 ANA PGIRH / SUMINISTRO INSTALACION PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Prior Request for Bids Open - International 3,190,000.00 0.00 2018-07-31 2018-08-14 2018-10-15 2018-10-31 2018-11-15 2020-05-16 Y CAPACITACION DE 110 IWRM at the National Level Envelope Implementation SISTEMA MECANIZADOS DE AFOROS LPI 003 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DEL Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Prior Request for Bids Open - International 5,786,425.49 0.00 2018-07-06 2018-07-11 2018-09-13 2018-09-23 2018-10-25 2019-01-03 EQUIPAMIENTO PARA EL IWRM at the National Level Envelope Implementation SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 004 2018 ANA PGIRH / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE LOS Component 1: Consolidating Single Stage - One IBRD / 87400 Post Request for Bids Open - International 1,418,283.54 0.00 Canceled 2018-07-09 2018-07-14 2018-09-16 2018-09-26 2018-10-28 2019-01-11 SUBSISTEMAS PARA EL IWRM at the National Level Envelope SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE EQUIPAMIENTO PARA LA PLATAFORMA TECNOLÓGICA Component 1: Consolidating Single Stage - One Under IBRD / 87400 Post Request for Bids Open - National 100,250.00 0.00 2018-07-09 2018-08-10 2018-07-14 2018-09-16 2018-09-26 2022-08-25 2022-10-24 PARA LA ADQUISICIÓN, IWRM at the National Level Envelope Implementation DECODIFICACIÓN, INTEGRACIÓN Y DISTRIBUCIÓN DE DATOS DE LAS ESTACIONES AUTOMATICAS CON TELEMETRIA LPI 001 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Prior Request for Bids Open - International 7,874,768.00 0.00 2018-06-20 2018-06-29 2018-08-31 2018-09-21 2018-11-15 2019-11-15 Y CAPACITACIÓN DE 153 IWRM at the National Level Envelope Implementation ESTACIONES HIDROLÓGICAS CON 33 EHCA LPN 005 2018 ANA PGIRH BM / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE LOS Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Post Request for Bids Open - National 1,418,283.54 0.00 2018-07-19 2018-07-20 2018-08-20 2018-08-31 2018-09-20 2018-11-19 SUBSISTEMAS PARA EL IWRM at the National Level Envelope Implementation SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 002 2018 ANA PGIRH BM / ADQUISICIÓN DE CATORCE Component 1: Consolidating (14) VEHÍCULOS PARA LA IWRM at the National Level Single Stage - One Pending IBRD / 87400 Post Request for Bids Open - National 592,732.00 0.00 2018-07-26 2018-07-31 2018-08-31 2018-09-05 2018-09-20 2018-10-20 SUPERVISIÓN, SEDE Component 3: General Project Envelope Implementation CENTRAL Y ADMINISTRACIÓN Adminstration DE LAS CUENCAS DEL PGIRH LPN 004 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE 141 Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Post Request for Bids Open - National 564,000.00 0.00 2018-07-31 2018-08-06 2018-09-05 2018-09-17 2018-10-04 2019-01-02 SENSORES CON SISTEMA DE IWRM at the National Level Envelope Implementation TELEMETRÍA PARA PIEZÓMETROS EN ICA Y TACNA LPI 005 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Component 1: Consolidating Single Stage - One Pending IBRD / 87400 Prior Request for Bids Open - International 3,200,000.00 0.00 2018-07-26 2018-07-31 2018-09-14 2018-09-19 2018-10-04 2018-12-28 Y CAPACITACIÓN DE IWRM at the National Level Envelope Implementation INSTRUMENTACIÓN DE PRESAS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SBCC 002 ANA MGRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TECNICOS PARA CONSTRUCCION DE 200 Component 1: Consolidating Quality And Cost- Under ESTRUCTURAS DE CONTROL IBRD / 87400 Post Open - National 125,000.00 0.00 2018-06-01 2018-06-08 2018-06-18 2018-06-23 2018-08-10 2018-07-08 2018-07-11 2018-07-13 2018-07-31 2018-10-14 IWRM at the National Level Based Selection Implementation Y MEDICION DE AGUA EN BLOQUES DE RIEGO EN DIECIOCHO SECTORES HIDRAULICO DE LA ZONA CENTRO DE LA COSTA DEL PERU SBCC 003 2018 ANA PGIRH / CONSULTORÍA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA CONSTRUCCIÓN DE 274 Component 1: Consolidating Quality And Cost- Under IBRD / 87400 Post Open - National 148,931.00 0.00 2018-06-15 2018-06-20 2018-07-23 2018-08-07 2018-08-16 2018-10-29 2018-11-16 2019-02-14 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level Based Selection Implementation DE AGUA EN BLOQUES DE RIEGO EN DOCE (12) SECTORES HIDRÁULICOS DE LA ZONA NORTE DE LA COSTA DEL PERÚ SBCC 001 ANA PGIRH / FORMULACIÓN DE LOS Component 2: Improving WRM Quality And Cost- PLANES DE GESTIÓN DE IBRD / 87400 Prior Open - International 5,955,217.00 0.00 Under Review 2018-06-01 2018-08-08 2018-06-06 2018-07-11 2018-10-08 2018-10-19 2018-10-26 2018-11-27 2020-11-26 in Selected Pilot River Basins Based Selection RECURSOS HDRICOS EN CUATRO CUENCAS SBCC 004 2018 ANA PGIRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA CONSTRUCCIÓN DE 337 Component 1: Consolidating Quality And Cost- Under IBRD / 87400 Post Open - National 155,680.00 0.00 2018-07-05 2018-07-17 2018-07-11 2018-08-08 2018-08-15 2018-09-12 2018-09-19 2018-09-27 2018-10-05 2019-01-03 ESTRUCTURAS DE MEDICIÓN IWRM at the National Level Based Selection Implementation DE AGUA EN BLOQUES DE RIEGO EN TREINTA (30) SECTORES HIDRÁULICOS DE LA ZONA SUR DE LA COSTA DEL PERÚ SBC 001 2018 ANA PGIRH BM / ESTUDIO DE LÍNEA BASE DEL PIP 302961 GESTIÓN Component 3: General Project Quality Based Under IBRD / 87400 Post Open - National 88,459.00 0.00 2018-07-23 2018-08-08 2018-07-25 2018-08-12 2018-09-11 2018-09-14 2018-09-17 2018-09-28 2018-12-27 INTEGRADA DE LOS Adminstration Selection Implementation RECURSOS HÍDRICOS EN DIEZ CUENCAS SBCC 005 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE Component 2: Improving WRM Quality And Cost- Pending RECURSOS HÍ DRICOS EN IBRD / 87400 Prior Open - International 1,809,400.00 0.00 2018-08-22 2018-09-06 2018-09-16 2018-10-16 2018-10-21 2018-10-24 2018-11-13 2020-11-02 in Selected Pilot River Basins Based Selection Implementation DOS CUENCAS PILOTO DE LA VERTIENTE DEL ATLÁNTICO: MAYO Y MANTARO SBCC 006 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN DE RECURSOS HIDRICOS EN DOS Component 2: Improving WRM Quality And Cost- Pending IBRD / 87400 Prior Open - International 2,151,920.00 0.00 2018-08-22 2018-09-06 2018-09-16 2018-10-16 2018-10-21 2018-10-24 2018-11-13 2020-05-06 CUENCAS PILOTO DE LA in Selected Pilot River Basins Based Selection Implementation VERTIENTE DEL ATLÁNTICO: PAMPAS-APURIMAC Y URUBAMBA-VILCANOTA INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCI-001 / III Administración Component 3: General Project Individual Consultant General del Proyecto IBRD / 87400 Prior Open 360,000.00 324,000.00 Signed 2017-12-28 2018-03-31 2018-03-12 2018-03-12 2018-03-15 2018-04-24 2018-04-18 2018-04-06 2018-10-15 Adminstration Selection III.a Director Ejecutivo SCI 003 ANA PGIRH / Component 3: General Project Individual Consultant IBRD / 87400 Prior Limited 202,500.00 0.00 Canceled 2018-05-22 2018-05-30 2018-05-23 2018-05-29 2018-05-31 2022-11-06 Especialista en Adquisiciones Adminstration Selection SCI 004 ANA PGIRH / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General Project Individual Consultant IBRD / 87400 Prior Limited 192,000.00 0.00 Canceled 2018-05-25 2018-06-01 2018-06-08 2018-06-12 2022-05-22 RECURSOS HÍDRICOS - Adminstration Selection COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 005 ANA PGIRH / Component 3: General Project Individual Consultant Under ESPECIALISTA EN AGUA IBRD / 87400 Post Limited 192,000.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-05-23 Adminstration Selection Implementation SUBTERRÁNEAS SCI 009 ANA PGIRH / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 72,000.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2021-05-28 GEOGRAFO - SIG Adminstration Selection Implementation SCI 010 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE TECNICO IBRD / 87400 Post Limited 71,460.00 0.00 2018-05-25 2018-06-01 2018-06-08 2018-06-12 2021-05-27 Adminstration Selection Implementation TALLERES SCI 011 ANA PGIRH / Component 2: Improving WRM Individual Consultant Under COORDINADOR TECNICO IBRD / 87400 Post Limited 184,140.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-05-23 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO URUBAMBA Page 2 SCI 012 ANA PGIRH / Component 2: Improving WRM Individual Consultant Under COORDINADOR TECNICO IBRD / 87400 Post Limited 184,140.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-05-23 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MAYO SCI 013 ANA PGIRH / Component 2: Improving WRM Individual Consultant Under COORDINADOR TECNICO IBRD / 87400 Post Limited 184,140.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-11-19 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO PAMPAS SCI 014 ANA PGIRH / Component 2: Improving WRM Individual Consultant Under COORDINADOR TECNICO IBRD / 87400 Post Limited 184,140.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-05-23 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MANTARO SCI 015 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 RECURSOS HIDRICOS in Selected Pilot River Basins Selection Implementation CUENCA PILOTO URUBAMBA SCI 017 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 RECURSOS HIDRICOS in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MAYO SCI 016 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 RECURSOS HIDRICOS in Selected Pilot River Basins Selection Implementation CUENCA PILOTO PAMPAS SCI 018 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 RECURSOS HIDRICOS in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MANTARO SCI 019 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 CULTURA DEL AGUA CUENCA in Selected Pilot River Basins Selection Implementation PILOTO URUBAMBA SCI 020 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 CULTURA DEL AGUA CUENCA in Selected Pilot River Basins Selection Implementation PILOTO MAYO SCI 021 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 CULTURA DEL AGUA CUENCA in Selected Pilot River Basins Selection Implementation PILOTO PAMPAS SCI 022 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 CULTURA DEL AGUA CUENCA in Selected Pilot River Basins Selection Implementation PILOTO MANTARO SCI 023 ANA PGIRH / ESPECIALISTA SOCIAL Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-11-28 AMBIENTAL CUENCA PILOTO in Selected Pilot River Basins Selection Implementation URUBAMBA SCI 024 ANA PGIRH / ESPECIALISTA SOCIAL Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-11-28 AMBIENTAL CUENCA PILOTO in Selected Pilot River Basins Selection Implementation MAYO SCI 025 ANA PGIRH / ESPECIALISTA SOCIAL Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-11-28 AMBIENTAL CUENCA PILOTO in Selected Pilot River Basins Selection Implementation PAMPAS SCI 026 ANA PGIRH / ESPECIALISTA SOCIAL Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-11-28 AMBIENTAL CUENCA PILOTO in Selected Pilot River Basins Selection Implementation MANTARO SCI 027 ANA PGIRH / ASESOR Component 3: General Project Individual Consultant EN GESTIÓN DE RECURSOS IBRD / 87400 Post Limited 286,200.00 0.00 Canceled 2018-05-25 2018-06-01 2018-06-08 2018-06-12 2022-11-18 Adminstration Selection HÍDRICOS SCI 029 ANA PGIRH / Component 3: General Project Individual Consultant Pending SECRETARIA DE LA IBRD / 87400 Post Limited 64,800.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2022-11-21 Adminstration Selection Implementation JEFATURA SCI 031 ANA PGIRH / CHOFER Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 54,000.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2022-11-21 DE JEFATURA Adminstration Selection Implementation SCI 035 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE SOPORTE IBRD / 87400 Post Limited 36,000.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 Adminstration Selection Implementation TECNICO SCI 036 ANA PGIRH / Component 3: General Project Individual Consultant Pending SECRETARIA DE IBRD / 87400 Post Limited 54,000.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2022-11-21 Adminstration Selection Implementation ADMINISTRACION Y FINANZAS SCI 037 ANA PGIRH / CHOFER Component 3: General Project Individual Consultant Pending DE ADMINISTRACIÓN Y IBRD / 87400 Post Limited 48,600.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2022-11-21 Adminstration Selection Implementation FINANZAS SCI 038 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE DE IBRD / 87400 Post Limited 103,500.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 Adminstration Selection Implementation ADQUISICIONES 1 SCI 039 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE DE IBRD / 87400 Post Limited 103,500.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 Adminstration Selection Implementation ADQUISICIONES 2 SCI 040 ANA PGIRH / CHOFER Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 48,600.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2022-11-21 DE ADQUISICIONES Adminstration Selection Implementation Page 3 SCI 041 ANA PGIRH / Component 3: General Project Individual Consultant Under ESPECIALISTA EN IBRD / 87400 Post Limited 194,076.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-11-19 Adminstration Selection Implementation CONTABILIDAD SCI 042 ANA PGIRH / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 67,500.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2021-05-28 ASISTENTE DE CONTABILIDAD Adminstration Selection Implementation SCI 043 ANA PGIRH / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 155,250.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-11-19 ESPECIALISTA FINANCIERO Adminstration Selection Implementation SCI 044 ANA PGIRH / Component 3: General Project Individual Consultant Under IBRD / 87400 Post Limited 194,076.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-11-19 ESPECIALISTA EN TESORERIA Adminstration Selection Implementation SCI 045 ANA PGIRH / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 67,500.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 ASISTENTE DE TESORERIA Adminstration Selection Implementation SCI 046 ANA PGIRH / Component 3: General Project Individual Consultant Pending ESPECIALISTA EN CONTROL IBRD / 87400 Post Limited 155,250.00 0.00 2018-05-28 2018-06-04 2018-06-11 2018-06-13 2022-11-19 Adminstration Selection Implementation PATRIMONIAL Y ALMACEN SCI 047 ANA PGIRH / TECNICO Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 40,500.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 DE ARCHIVO Adminstration Selection Implementation SCI 048 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE EN SERVICIOS IBRD / 87400 Post Limited 40,500.00 0.00 2018-05-29 2018-06-06 2018-06-13 2018-06-15 2021-05-30 Adminstration Selection Implementation GENERALES Y ARCHIVO SCI 049 ANA PGIRH / Component 2: Improving WRM Individual Consultant Pending ASISTENTE ADMINISTRATIVO IBRD / 87400 Post Limited 33,600.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO URUBAMBA SCI 050 ANA PGIRH / Component 2: Improving WRM Individual Consultant Pending ASISTENTE ADMINISTRATIVO IBRD / 87400 Post Limited 33,600.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MAYO SCI 051 ANA PGIRH / Component 2: Improving WRM Individual Consultant Pending ASISTENTE ADMINISTRATIVO IBRD / 87400 Post Limited 33,600.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 in Selected Pilot River Basins Selection Implementation CUENCA PILOTO PAMPAS SCI 052 ANA PGIRH / Component 3: General Project Individual Consultant Pending ASISTENTE ADMINISTRATIVO IBRD / 87400 Post Limited 33,600.00 0.00 2018-06-04 2018-06-11 2018-06-19 2018-06-22 2022-06-01 Adminstration Selection Implementation CUENCA PILOTO MANTARO SCI 033 ANA PGIRH / Component 3: General Project Individual Consultant Pending ESPECIALISTA EN IBRD / 87400 Post Limited 155,250.00 0.00 2018-06-04 2018-06-11 2018-06-18 2018-06-22 2022-11-28 Adminstration Selection Implementation PRESUPUESTO SCI 002 ANA PGIRH / Component 3: General Project Individual Consultant Especialista en Administración y IBRD / 87400 Prior Limited 243,000.00 0.00 Canceled 2018-05-22 2018-05-29 2018-05-23 2018-05-29 2018-05-31 2018-11-09 Adminstration Selection Finanzas SCI 053 ANA PGIRH / Component 3: General Project Individual Consultant Under ESPECIALISTA EN IBRD / 87400 Prior Open 243,000.00 0.00 2018-06-14 2018-06-21 2018-07-02 2018-07-02 2018-07-03 2022-12-30 Adminstration Selection Implementation ADMINISTRACIÓN Y FINANZAS SCI 054 2018 ANA PGIRH / Component 3: General Project Individual Consultant Under ESPECIALISTA EN IBRD / 87400 Prior Open 202,500.00 0.00 2018-06-14 2018-06-21 2018-07-02 2018-07-02 2018-07-03 2022-12-30 Adminstration Selection Implementation ADQUISICIONES SCI 032 ANA PGIRH / ESPECIALISTA EN Component 3: General Project Individual Consultant Pending PLANIFICACION, IBRD / 87400 Prior Limited 216,000.00 0.00 2018-06-26 2018-07-02 2018-07-09 2018-07-12 2022-12-30 Adminstration Selection Implementation PRESUPUESTO Y EVALUACIÓN SCI 007-ANA-PGIRH / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Direct 192,000.00 0.00 2018-05-25 2018-06-04 2018-06-06 2018-06-08 2022-05-18 ESPECIALISTA AMBIENTAL Adminstration Selection Implementation SCI 028 2018 ANA PGIRH BM / Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 192,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 ESPECIALISTA AMBIENTAL Adminstration Selection Implementation SCI 030 2018 ANA PGIRH BM / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General Project Individual Consultant Pending IBRD / 87400 Post Limited 192,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 RECURSOS HÍDRICOS - Adminstration Selection Implementation COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 006 2018 ANA PGIRH BM / Component 3: General Project Individual Consultant Under ASESOR EN GESTIÓN DE IBRD / 87400 Prior Limited 286,200.00 0.00 2018-07-19 2018-08-02 2018-07-20 2018-08-07 2018-07-30 2018-07-31 2022-12-30 Adminstration Selection Implementation RECURSOS HÍDRICOS SCI 008 2018 ANA PGIRH BM / Component 3: General Project Individual Consultant Pending ESPECIALISTA EN GESTIÓN IBRD / 87400 Post Limited 192,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 Adminstration Selection Implementation DE RECURSOS HÍDRICOS SCI 059 2018 ANA PGIRH / ESPECIALISTA EN SISTEMAS Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 DE INFORMACIÓN CUENCA in Selected Pilot River Basins Selection Implementation PILOTO URUBAMBA SCI 060 2018 ANA PGIRH / ESPECIALISTA EN SISTEMAS Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 DE INFORMACIÓN CUENCA in Selected Pilot River Basins Selection Implementation PILOTO MANTARO SCI 061 2018 ANA PGIRH BM / ESPECIALISTA EN SISTEMAS Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 DE INFORMACIÓN CUENCA in Selected Pilot River Basins Selection Implementation PILOTO PAMPAS SCI 062 2018 ANA PGIRH BM / ESPECIALISTA EN SISTEMAS Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 151,200.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 DE INFORMACIÓN CUENCA in Selected Pilot River Basins Selection Implementation PILOTO MAYO Page 4 SCI 063 2018 ANA PGIRH BM / ASISTENTE TÉCNICO EN Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 SISTEMAS DE INFORMACIÓN in Selected Pilot River Basins Selection Implementation CUENCA PILOTO URUBAMBA SCI 064 2018 ANA PGIRH BM / ASISTENTE TÉCNICO EN Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 SISTEMAS DE INFORMACIÓN in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MANTARO SCI 065 2018 ANA PGIRH BM / ASISTENTE TÉCNICO EN Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 SISTEMAS DE INFORMACIÓN in Selected Pilot River Basins Selection Implementation CUENCA PILOTO MAYO SCI 034 2018 ANA PGIRH BM / ASISTENTE TÉCNICO EN Component 2: Improving WRM Individual Consultant Pending IBRD / 87400 Post Limited 96,000.00 0.00 2018-07-19 2018-07-20 2018-07-30 2018-07-31 2022-12-30 SISTEMAS DE INFORMACIÓN in Selected Pilot River Basins Selection Implementation CUENCA PILOTO PAMPAS Page 5