Procurement Plan Metro Colombo Urban Development Project (P122735) Sri Lanka Credit/Grant #: 8145-LK I. General 1. Bank’s approval Date of the procurement Plan: Original 8th February 2012: Revision 28th March 2017 2. Date of General Procurement Notice: 29th August 2011 3. Period covered by this procurement plan: 31st December 2017 II. Goods and Works and Non-consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB (Works) Above US$ All 15,000,000 2. NCB (Works) Less US$ 10,000,000 First Contract only 3. Shopping (Works) Less US$ 500,000 First Contract only 4. ICB (Goods) Above US$ 4,000,000 All 5. NCB (Goods) Less US$ 1,000,000 First Contract only 6. Shopping (Goods) Less US$ 500,000 First Contract only 7. Force Account All 2. Prequalification. Bidders for identified procurements shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Procurement Guidelines. 3. Proposed Procedures for CDD Components: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Procurement Administration Manual, Metro Colombo Urban Development Project (MCUDP), December 2011 5. Any Other Special Procurement Arrangements: None March 28, 2017 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms Above US$ 2,000,000 All advertised internationally) 2. Single Source (Firms) All 3. Individual Consultants Above US$ 400,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None March 28, 2017 PROCUREMENT Sri Lanka : Metro Colombo Urban Development Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2017-02-08 2021-03-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122735 GPN Date: Project Name: Metro Colombo Urban Development Project Loan / Credit No: IBRD / 81450 Ministry of Megapolis and Western Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LK-MOMWD-1762-CW-RFB / SLLRDC/W/14 - Design & Component 1: Flood and Single Stage - Two 36,000,000.0 33,653,416. Under 2019-03- IBRD / 81450 Prior Request for Bids Open - International 2016-12-16 2017-02-09 2016-12-24 2017-01-02 2017-06-06 2017-02-27 2018-02-15 2017-03-30 2018-05-30 Building of new Mutwal Drainage Management Envelope 0 41 Review 29 Tunnel & Torrington Tunnel LK-MOMWD-1789-CW-RFB / SLLRDC/W/12 - Design & Component 1: Flood and Single Stage - Two 23,650,000.0 2019-03- Building of St Sebastian IBRD / 81450 Prior Request for Bids Open - International 0.00 Canceled 2016-09-20 2016-09-20 2016-09-20 2016-06-17 2016-11-03 2017-03-24 Drainage Management Envelope 0 07 Northlock gates & Pumping Station LK-MOMWD-1755-CW-RFB / SLLRDC/W/20 - Installation of Component 1: Flood and Single Stage - One 3,438,694.0 2018-09- IBRD / 81450 Post Request for Bids Open - National 3,816,793.00 Signed 2017-02-01 2018-05-25 2017-02-06 2017-03-08 2018-08-01 2017-04-07 2018-08-29 2017-05-12 2019-02-20 Flushing Gates for Water Drainage Management Envelope 5 07 Quality Improvement LK-MOMWD-1625-CW-RFB / SLLRDC/W/16/A - Kolonnawa Component 1: Flood and Single Stage - One 4,752,618.8 2019-02- IBRD / 81450 Post Request for Bids Open - National 1,307,692.00 Signed 2017-05-12 2018-04-06 2017-05-23 2017-06-20 2018-05-18 2017-07-24 2017-11-29 2019-01-28 Canal Diversion Scheme Stage Drainage Management Envelope 6 25 1 LK-MOMWD-1677-CW-RFB / SLLRDC/W/16-B - Kolonnawa Component 1: Flood and Single Stage - One 1,579,116.6 2018-10- IBRD / 81450 Post Request for Bids Open - National 3,000,000.00 Signed 2017-04-08 2017-04-13 2017-05-09 2017-06-13 2017-07-05 2017-07-17 2017-12-12 Canal Diversion Scheme Stage Drainage Management Envelope 1 10 II LK-MOMWD-1717-CW-RFB / SLLRDC/W/16/C - Component 1: Flood and Single Stage - One 5,615,951.4 2019-01- IBRD / 81450 Post Request for Bids Open - National 3,076,923.00 Signed 2017-04-17 2018-03-13 2017-04-24 2017-05-19 2018-05-08 2017-06-21 2018-05-31 2017-10-27 2018-10-23 Kolonnawa Canal Diversion Drainage Management Envelope 2 23 Scheme Stage III LK-MOMWD-1759-CW-RFB / Component 1: Flood and Single Stage - One 7,916,400.3 2018-08- SLLRDC/W/16-D - Kolonnawa IBRD / 81450 Post Request for Bids Open - National 7,076,923.00 Signed 2017-04-25 2018-05-15 2017-04-30 2017-05-30 2018-06-18 2017-06-29 2018-08-21 2017-08-25 2019-01-28 Drainage Management Envelope 0 18 Canal diversion stage IV LK-MOMWD-1605-CW-RFB / Component 1: Flood and Single Stage - One 1,274,967.2 2017-09- SLLRDC/W/05 - Madiwela East IBRD / 81450 Post Request for Bids Open - National 1,633,324.07 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-08-19 2016-09-30 2016-10-07 Drainage Management Envelope 2 18 Diversion Scheme Stage- 1 LK-MOMWD-1607-CW-RFB / SLLRDC/W/11- Improvements Component 1: Flood and Single Stage - One 2017-12- IBRD / 81450 Post Request for Bids Open - National 736,539.95 595,805.91 Signed 2016-09-19 2016-09-19 2016-10-04 2016-11-04 2016-11-01 2016-12-16 2016-12-16 to Madiwela East Diversion Drainage Management Envelope 11 Scheme Stage 11 LK-MOMWD-1376-CW-RFB / SLLRDC/W/19 - Component 1: Flood and Single Stage - One 1,929,864.7 2018-01- Improvements to Madiwela IBRD / 81450 Post Request for Bids Open - National 2,376,396.43 Signed 2016-09-05 2016-10-03 2016-11-02 2016-12-02 2016-12-07 2017-01-06 2016-12-27 Drainage Management Envelope 7 29 east Diversion Scheme Stage III LK-MOMWD-1623-CW-RFB / SLLRDC/W/9 - Construction Component 1: Flood and Single Stage - One 1,798,160.6 2018-07- IBRD / 81450 Post Request for Bids Open - National 4,725,000.00 Signed 2016-10-12 2016-10-17 2016-11-16 2016-12-16 2016-12-06 2017-04-18 2017-05-03 of Bank Protection works of St Drainage Management Envelope 0 06 Sebastian North Canal LK-MOMWD-1796-CW-RFB / SLLRDC/W/7/A - Conveyance Component 1: Flood and Single Stage - One 2017-05- IBRD / 81450 Post Request for Bids Open - National 507,165.00 390,878.50 Signed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-10-11 2016-07-21 Improvements to Wellawatta Drainage Management Envelope 15 Canal at Galle Road Bridge LK-MOMWD-10623-CW-RFB Under / SLLRDC/W/24 Plant Design, Component 1: Flood and Single Stage - Two 14,000,000.0 12,455,020. 2019-11- IBRD / 81450 Post Request for Bids Open - International Implementat 2017-03-24 2017-04-26 2017-03-31 2017-06-22 2017-08-10 2017-08-30 2018-06-26 2017-11-01 2018-08-17 Supply and Installation of Drainage Management Envelope 0 15 07 ion Pumping Station at Ambatale. LK-MOMWD-1375-CW-RFB / Component 1: Flood and Single Stage - One 2,138,419.7 2019-01- CMC/W/MD/4B - IBRD / 81450 Post Request for Bids Open - National 7,580,000.00 Signed 2017-04-30 2018-03-13 2017-05-05 2017-06-02 2017-06-30 2018-05-18 2017-08-31 2018-08-03 Drainage Management Envelope 5 25 Improvements to Norris Canal LK-MOMWD-1839-CW-RFB / UDA/W/1-B - Development of Component 1: Flood and Single Stage - One 2,977,944.9 2018-11- IBRD / 81450 Post Request for Bids Open - National 2,300,000.00 Signed 2017-04-28 2018-05-24 2017-05-09 2017-06-06 2017-07-03 2018-10-04 2017-08-14 2018-11-09 Bio-Diversity Park at Kotte Drainage Management Envelope 3 15 Rampart LK-MOMWD-1840-CW-RFB / UDA/W/4-C - Construction of Linear Park Along Beira Lake Component 1: Flood and Single Stage - One 2018-10- Phase III - Western Bank of IBRD / 81450 Post Request for Bids Open - National 2,100,000.00 791,905.90 Signed 2017-05-31 2017-06-09 2017-07-06 2017-08-03 2017-10-16 2017-09-14 2018-04-10 Drainage Management Envelope 03 West 1.25km- ( Along Army Head Quarter premises to Justice Akbar Mawatha ) LK-MOMWD-1836-CW-RFB / UDA/W/04-A - Construction of Linear Park AlongEastern Component 1: Flood and Single Stage - One 1,114,992.5 2016-12- IBRD / 81450 Post Request for Bids Open - National 1,500,285.01 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2015-08-11 Bank of East Beira Lake Phase Drainage Management Envelope 4 30 1 (Aitken Spence to Lotus Tower) Page 1 LK-MOMWD-1834-CW-RFB / UDA/W/03-B - Construction of bank protection works of Component 1: Flood and Single Stage - One 1,664,437.8 2016-12- Western Bank of west Beira IBRD / 81450 Post Request for Bids Open - National 2,307,979.05 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2015-10-14 Drainage Management Envelope 4 30 Lake - 1.05 km(Along Army Head quarters premises to Justice Akbar Mawatha) LK-MOMWD-1837-CW-RFB / UDA/W/04-D - Construction of Linear Park AlongEastern Component 1: Flood and Single Stage - One 1,619,346.6 2017-09- Bank of East Beira Lake Phase IBRD / 81450 Post Request for Bids Open - National 2,101,103.18 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-08 Drainage Management Envelope 9 15 11 Lotus Tower via Lake House Junction to Secretariat Station LK-MOMWD-1600-CW-RFB / CMC/W/MD/13 Micro Component 1: Flood and Single Stage - One 2,626,155.4 2017-11- IBRD / 81450 Post Request for Bids Open - National 3,364,292.73 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-08-15 2016-09-15 2016-09-15 Drainage improvements to Drainage Management Envelope 7 09 Devi Balika Junction LK-MOMWD-1604-CW-RFB / CMC/W/MD/12 - Component 1: Flood and Single Stage - One 1,088,141.2 2017-07- IBRD / 81450 Post Request for Bids Open - National 1,393,986.69 Signed 2016-09-15 2016-09-15 2016-09-16 2016-09-17 2016-08-04 2016-09-22 2016-09-28 Improvements to Kynsey Road Drainage Management Envelope 8 19 drain Component 2: Urban LK-MOMWD-1827-CW-RFB / development, infrastructure KUC/W/01 - Infrastructure Single Stage - One 1,065,008.4 2017-06- IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 1,381,849.06 Signed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-10-12 2016-09-14 Development in Kolonnawa Envelope 8 14 building for Metro Colombo Urban Council local authorities. LK-MOMWD-1813-CW-RFB / SLLRDC/W/3/A - Component 1: Flood and Single Stage - One 1,430,543.3 2016-09- Construction of Canal Bank IBRD / 81450 Post Request for Bids Open - National 1,982,829.89 Completed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2014-11-11 Drainage Management Envelope 0 20 protection of St Sebestian South Canal LK-MOMWD-1820-CW-RFB / CMC/W/MD/03 - Component 1: Flood and Single Stage - One 1,593,710.7 2016-09- IBRD / 81450 Post Request for Bids Open - National 2,208,990.98 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2014-12-05 Rehabilitation of Gregory's Drainage Management Envelope 1 21 Canal Component 2: Urban LK-MOMWD-1822-CW-RFB / development, infrastructure Single Stage - One 2016-11- CMC/W/3-A - Public IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 545,861.36 393,820.12 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2015-05-22 Envelope 20 Conveniences Package III building for Metro Colombo local authorities. Component 2: Urban LK-MOMWD-1832-CW-RFB / development, infrastructure Single Stage - One 1,518,821.0 2016-11- CMC/W/13/A - Construction IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 2,105,188.80 Completed 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2014-10-20 Envelope 3 20 of Beach Park at Crow Island building for Metro Colombo local authorities. Component 2: Urban LK-MOMWD-1824-CW-RFB / development, infrastructure SJKMC/W/03- Infrastructure Single Stage - One 2016-12- IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 584,432.97 421,648.21 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2015-07-28 Development in SJKMC Envelope 26 building for Metro Colombo Package III local authorities. LK-MOMWD-1761-CW-FCA / Component 1: Flood and 2017-09- SLLRDC/W/23 - Dredging of IBRD / 81450 Prior Force Account Direct 900,000.00 764,828.56 Completed 2016-09-20 2017-08-10 2016-09-20 2017-10-03 2016-09-20 2016-09-01 Drainage Management 01 Talangama Tank. LK-MOMWD-40497-CW-RFB / SLLRDC/W/12 - Design & Component 1: Flood and Single Stage - Two 23,650,000.0 12,969,360. Under 2019-06- building of St. sebastian IBRD / 81450 Prior Request for Bids Open - International 2018-01-11 2018-01-11 2018-01-11 2018-01-11 2018-01-15 2018-01-11 2017-03-24 Drainage Management Envelope 0 92 Review 30 nortlock gates & pumping station. LK-MOMWD-80060-CW-RFB / Construction of flood gate with culvert near Thalangama Component 1: Flood and Single Stage - One 1,465,912.3 2019-10- IBRD / 81450 Post Request for Bids Open - National 875,000.00 Signed 2018-11-19 2018-11-16 2018-11-26 2018-12-26 2018-01-18 2019-01-25 2019-03-29 2019-02-22 2019-05-06 tank and Construction of Drainage Management Envelope 5 20 culvert at Baudhaloka mawatha - MCUDP/PMU/W/01 LK-MOMWD-1786-CW-RFB / SLLRDC /W/18 - Supply of Component 1: Flood and Single Stage - One 2017-10- IBRD / 81450 Post Request for Bids Open - National 2,000,000.00 0.00 Canceled 2017-01-12 2017-01-17 2017-02-16 2017-03-18 2017-04-22 Real Time Integrated Flood Drainage Management Envelope 19 Management system LK-MOMWD-10527-CW-RFB / UDA/W/05 Repair and Component 1: Flood and 2018-09- IBRD / 81450 Post Direct Selection Direct 200,000.00 0.00 Canceled 2017-05-22 2017-06-21 2017-09-10 Renovation to McCallum Lock Drainage Management 10 Gates. LK-MOMWD-1777-CW-RFB / SLLRDC/W/13/ICB/2018- Component 1: Flood and Single Stage - One 10,770,000.0 6,884,132.8 2019-12- Design and Building of St. IBRD / 81450 Post Request for Bids Open - International Signed 2017-04-26 2018-03-22 2017-05-01 2017-07-24 2018-06-28 2017-10-01 2018-08-29 2017-12-01 2019-01-31 Drainage Management Envelope 0 2 05 Sebastian South Pumping Station LK-MOMWD-1374-CW-RFB / CMC/W/MD/4A - Component 1: Flood and Single Stage - One 2018-10- IBRD / 81450 Post Request for Bids Open - National 3,200,000.00 0.00 Canceled 2017-06-30 2017-07-10 2018-09-05 2017-08-07 2017-09-04 2017-10-13 Improvements to Saunders Drainage Management Envelope 16 Place Storm water system LK-MOMWD-143691-CW- Component 2: Urban FCA / MCUDP/W/02/2019 - development, infrastructure Procurement of Services for 2020-04- IBRD / 81450 rehabilitation and capacity Prior Force Account Direct 120,000.00 0.00 Canceled 2020-01-30 2020-02-06 2020-03-19 Measuring the International 18 building for Metro Colombo Roughness Index Value of local authorities. Roads LK-MOMWD-179997-CW- Component 2: Urban DIR / MCUDP/W/02/2020 - development, infrastructure Under 2020-11- Procurement of Measuring the IBRD / 81450 rehabilitation and capacity Post Direct Selection Direct 120,000.00 0.00 Implementat 2020-06-28 2020-09-24 2020-07-12 2020-08-30 28 International Roughness Index building for Metro Colombo ion Value of Roads local authorities. Page 2 GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-1670-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/06 - Procurement IBRD / 81450 Post Request for Bids Open - National 116,096.43 91,440.24 Signed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-22 2016-09-19 2018-06-26 Drainage Management Envelope of Workshop Tools LK-MOMWD-1691-GO-RFB / PMU/LA/G/01 - Procurement Component 1: Flood and Single Stage - One of Construction, Solid Waste IBRD / 81450 Post Request for Bids Open - National 1,660,500.98 1,533,958.12 Completed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-01-26 2016-09-19 2016-09-29 2016-09-19 2017-07-27 Drainage Management Envelope Management & Utility Support Vehicles LK-MOMWD-1760-GO-RFQ / SLLRDC/G/13 - Procurement Component 1: Flood and Request for Single Stage - One of Software for Geo technical IBRD / 81450 Post Open - International 18,000.00 23,109.31 Signed 2016-09-20 2016-09-20 2016-11-14 2016-09-20 Drainage Management Quotations Envelope Analysis, Geo slope, 2D Plaxis and 3D Plaxis LK-MOMWD-1763-GO-RFQ / SLLRDC/G/14 - Procurement Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - International 2,000.00 17,263.69 Completed 2016-09-25 2016-09-25 2018-01-17 2016-09-25 2018-06-19 of Microsoft Office 2013 & MS Drainage Management Quotations Envelope Project 2013 LK-MOMWD-1766-GO-RFQ / SLLRDC/G/12 - Procurement Component 1: Flood and Request for Single Stage - One of Software for Structural IBRD / 81450 Post Open - International 26,000.00 39,892.41 Completed 2016-09-20 2016-09-20 2018-11-09 2016-09-20 2019-07-11 Drainage Management Quotations Envelope Design, Prokon, SAP 2000 and Etab LK-MOMWD-1769-GO-RFQ / SLLRDC/G/11 - Procurement Component 1: Flood and Request for Single Stage - One of Auto CAD 2012, Auto CAD IBRD / 81450 Post Open - International 20,000.00 3,910.00 Signed 2016-09-20 2016-09-20 2016-11-02 2016-09-20 Drainage Management Quotations Envelope Civil 3D (Geometry Design) and Google Earth Pro LK-MOMWD-1924-GO-RFQ / SLLRDC/G/17 - Procurement Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - International 10,000.00 8,623.10 Signed 2016-09-26 2016-09-26 2016-11-14 2016-09-26 of Upgrading Arc GIS -10.3 Drainage Management Quotations Envelope Version LK-MOMWD-2473-GO-RFB / SLLRDC/G/4-A - Procurement Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 693,790.43 582,541.06 Completed 2016-10-10 2016-10-10 2016-10-10 2016-10-10 2015-09-15 2016-10-10 2016-02-08 2016-10-10 2017-05-20 of Construction Machinery & Drainage Management Envelope Equipment Package II LK-MOMWD-1923-GO-RFQ / Component 1: Flood and Request for Single Stage - One SLLRDC/G/08 - Procurement IBRD / 81450 Post Open - National 440,000.00 65,075.53 Completed 2016-10-01 2016-11-26 2017-05-31 2017-05-25 2017-09-15 Drainage Management Quotations Envelope of Computer Hardware LK-MOMWD-1606-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/15 - Procurement IBRD / 81450 Post Request for Bids Open - National 56,428.57 54,711.68 Completed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-08-04 2016-09-15 2016-12-07 2016-12-14 2017-08-18 Drainage Management Envelope of Generators LK-MOMWD-1754-GO-RFB / SLLRDC/G/03 - Procurement Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 420,000.00 78,654.30 Completed 2016-09-20 2016-09-20 2016-09-20 2016-09-20 2017-02-16 2016-09-20 2017-04-24 2016-09-20 2017-07-20 of Testing Equipment & Drainage Management Envelope Instruments Component 2: Urban LK-MOMWD-39993-GO-RFB development, infrastructure / SLLRDC/G/03-A Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 420,000.00 405,515.25 Signed 2017-12-18 2018-01-10 2018-01-15 2018-02-14 2018-04-09 2018-04-11 2019-04-08 2018-10-08 Procurement of Testing Envelope building for Metro Colombo Equipment and Instruments local authorities. LK-MOMWD-14361-GO-RFQ / SLLRDC/G/18-A - Supply and installation of equipment Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 40,000.00 28,910.24 Signed 2018-01-08 2018-05-28 2018-04-09 2018-08-20 and facilities for Center for Drainage Management Quotations Envelope Flood Control & Water Management. LK-MOMWD-40090-GO-RFQ / SLLRDC/G/18-G Supply and Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 150,000.00 122,619.56 Signed 2018-02-01 2019-02-15 2018-02-06 2018-03-20 2019-03-13 2018-04-19 2019-04-10 2018-05-24 2019-05-13 2018-11-20 installation of Rainfall gauges Drainage Management Envelope for RTC. LK-MOMWD-40334-GO-RFB / SLLRDC/G/18-K - Supply of Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 150,000.00 47,223.83 Completed 2017-12-25 2017-12-30 2018-02-10 2018-03-12 2019-01-21 2018-04-16 2019-01-29 2018-06-15 2019-03-12 software with related training Drainage Management Envelope to RTC LK-MOMWD-40339-GO-RFQ / SLLRDC/G/18-L - Supply of Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 37,000.00 31,110.05 Completed 2017-12-25 2018-02-19 2018-03-14 2018-08-18 2018-06-06 Acoustic Doppler Current Drainage Management Quotations Envelope Profiler for RTC system LK-MOMWD-40340-GO-RFQ / SLLRDC/G/18-M - Supply of Component 1: Flood and Request for Single Stage - One Telemetered automatic IBRD / 81450 Post Open - National 23,500.00 18,039.85 Completed 2017-12-21 2018-02-09 2018-03-14 2018-03-11 2018-08-10 Drainage Management Quotations Envelope weather station & water level measurement system for RTC LK-MOMWD-40346-GO-RFQ / SLLRDC/G/18-N - Supply of Component 1: Flood and Request for Single Stage - One Recording & Storage type IBRD / 81450 Post Open - National 25,000.00 22,280.26 Completed 2017-12-21 2018-02-09 2018-03-14 2018-03-11 2018-08-10 Drainage Management Quotations Envelope weather station & water level gauges LK-MOMWD-14408-GO-RFB / SLLRDC/G/18-D - Supply Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 65,500.00 0.00 Canceled 2017-09-16 2018-02-26 2018-06-28 and installation of central air Drainage Management Quotations Envelope conditioning for RTC LK-MOMWD-2474-GO-RFB / SLLRDC/G/4-B - Procurement Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 851,851.85 0.00 Canceled 2016-12-06 2016-12-11 2017-01-10 2017-02-09 2017-03-16 2017-09-12 of Construction Machinery & Drainage Management Envelope Equipment Package III Page 3 LK-MOMWD-100657-GO- RFQ / MCUDP/SLLRDC/G/18- Under Component 1: Flood and Request for Single Stage - One O - Supply of Ground IBRD / 81450 Post Open - National 40,000.00 0.00 Implementati 2019-02-28 2019-04-21 2019-08-19 Drainage Management Quotations Envelope Penetrating Radar (GPR) for on SLLRDC LK-MOMWD-14357-GO-RFQ / MCUDP/SLLRDC/G/18 - Component 1: Flood and Request for Single Stage - One Supply and installation of IBRD / 81450 Post Open - National 200,000.00 0.00 Canceled 2017-09-15 2018-02-26 2018-06-04 Drainage Management Quotations Envelope equipment & facilities for RTC centre. Component 2: Urban LK-MOMWD-1925-GO-RFB / development, infrastructure UDA/G/01 - Procurement of Single Stage - One IBRD / 81450 rehabilitation and capacity Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2017-01-18 2017-01-23 2017-03-06 2017-04-05 2017-05-10 2017-11-06 Transport and Utility Vehicles Envelope building for Metro Colombo for UDA local authorities. LK-MOMWD-2472-GO-RFB / Component 1: Flood and Single Stage - One SLLRDC/G/05 -Procurement IBRD / 81450 Post Request for Bids Open - National 640,000.00 0.00 Canceled 2016-12-08 2016-12-15 2017-01-14 2017-02-13 2017-03-09 2017-07-06 Drainage Management Envelope of Construction Plants. LK-MOMWD-40321-GO-RFQ / SLLRDC/G/18-J I Supply Component 1: Flood and Single Stage - One and installation of forecasting IBRD / 81450 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2019-06-03 2019-06-17 2019-07-17 2019-08-16 2019-09-20 2019-12-19 Drainage Management Envelope and control for SCADA - Phsae - I LK-MOMWD-40087-GO-RFQ / SLLRDC/G/18-F Supply and Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 132,000.00 0.00 Canceled 2019-06-03 2019-06-08 2019-07-08 2019-08-07 2019-09-04 2019-12-03 installation of outlet physical Drainage Management Envelope model for pumping house. LK-MOMWD-117824-GO- RFQ / SLLRDC/G/18-K/VIII - Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Limited 960.00 1,112.18 Signed 2019-09-08 2019-09-26 2019-10-27 2019-10-28 2019-11-10 Supply and Delivery of Adobe Drainage Management Quotations Envelope Creative Cloud Suite (All Apps) LK-MOMWD-124028-GO- DIR / SLLRDC/G/18-J I - Under Component 1: Flood and Supply and Installation of IBRD / 81450 Post Direct Selection Direct 200,000.00 0.00 Implementati 2019-10-02 2019-06-03 2019-10-07 2019-11-16 2020-02-14 Drainage Management Forecasting and Control for on SCADA - Phase I LK-MOMWD-117806-GO- DIR / SLLRDC/G/18-K/III - Under Component 1: Flood and Supply and Delivery of Flo 2D IBRD / 81450 Post Direct Selection Direct 5,000.00 0.00 Implementati 2019-06-17 2019-06-04 2019-06-24 2019-07-22 2019-07-29 2019-08-28 Drainage Management Model Pro Subscription 5-Year on and Perpetual License LK-MOMWD-117812-GO- Under DIR / SLLRDC/G/18-K/V - Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 7,050.00 0.00 Implementati 2019-06-17 2019-06-04 2019-06-24 2019-07-22 2019-07-29 2019-08-28 Supply and Delivery of Drainage Management on Mathematica Software LK-MOMWD-117813-GO- DIR / SLLRDC/G/18-K/IV - Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 1,050.00 1,347.50 Signed 2019-06-17 2019-06-04 2019-06-24 2019-12-20 2019-07-29 2020-01-09 2019-08-28 Supply and Delivery of Drainage Management Highstock Developer License, Version 6 LK-MOMWD-117816-GO- Under DIR / SLLRDC/G/18-K/VII - Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 2,990.00 0.00 Implementati 2019-06-17 2019-06-04 2019-06-24 2019-07-22 2019-07-29 2019-08-28 Supply and Delivery of Drainage Management on Neurosolutions Pro License LK-MOMWD-117815-GO- DIR / SLLRDC/G/18-K/VI - Under Component 1: Flood and Supply and Delivery of Matlab IBRD / 81450 Post Direct Selection Direct 2,350.00 0.00 Implementati 2019-06-17 2019-06-04 2019-06-24 2019-07-22 2019-07-29 2019-08-28 Drainage Management Version R2017 with on DHIMatalab Toolbox LK-MOMWD-122409-GO- RFB / MCUDP/SLLRDC/G/18- Component 1: Flood and Q - Supply, Installation and IBRD / 81450 Post Direct Selection Direct 50,000.00 40,062.07 Signed 2019-10-02 2019-08-06 2019-10-07 2019-10-07 2019-11-16 2019-11-07 2020-02-14 Drainage Management Operation of Communication and Control for RTC System LK-MOMWD-117794-GO- Under RFB / SLLRDC/G/18-P - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 600,000.00 0.00 Implementati 2019-09-09 2019-10-14 2019-09-14 2020-03-04 2019-10-14 2019-11-13 2019-12-04 2020-03-03 Supply and Installation of Drainage Management Envelope on Compact X Band Radar Set LK-MOMWD-140119-GO- DIR / MCUDP/SLLRDC/G/18- G I - Procurement of Supply, Component 1: Flood and Installation, and Maintenance IBRD / 81450 Post Direct Selection Direct 33,500.00 28,933.59 Completed 2019-10-18 2019-10-21 2019-10-23 2019-10-22 2019-11-11 2020-01-14 2020-01-10 2020-06-09 Drainage Management of Automated Weather Stations with Accessories - Phase II. LK-MOMWD-140297-GO- DIR / MCUDP/SLLRDC/G/18-R Under - Procurement of Supply & Component 1: Flood and IBRD / 81450 Post Direct Selection Direct 200,000.00 0.00 Implementati 2019-11-13 2019-10-17 2019-11-18 2019-11-18 2019-12-07 2020-02-05 Installation of Communication Drainage Management on Network for Center for Urban Water LK-MOMWD-14365-GO-RFB / SLLRDC/G/18-B - Component 1: Flood and Request for Single Stage - One IBRD / 81450 Post Open - National 33,000.00 60,849.48 Signed 2019-12-28 2020-03-02 2020-11-30 2020-04-01 Procurement of Generator for Drainage Management Quotations Envelope RTC LK-MOMWD-117803-GO- Under RFB / SLLRDC/G/18-F - Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 50,000.00 0.00 Implementati 2019-11-07 2019-12-06 2019-11-17 2019-12-17 2020-01-16 2020-02-06 2020-03-07 Syatem for Real Time Data Drainage Management Envelope on Management LK-MOMWD-40295-GO-RFQ Under / SLLRDC/G/18-H Supply and Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-10-30 2020-02-10 2019-11-14 2019-12-14 2020-01-13 2020-01-27 2020-04-26 installation of Water level Drainage Management Envelope on gauges for RTC Page 4 LK-MOMWD-14368-GO-RFB / SLLRDC/G/18-C - Supply, installation and Under commissioning of IT facilities Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 800,000.00 0.00 Implementati 2019-11-25 2020-02-03 2019-11-30 2019-12-30 2020-01-29 2020-02-19 2020-05-19 including networking, Drainage Management Envelope on communication, data center facility and BMS for new RTC building. LK-MOMWD-144446-GO- RFQ / MCUDP/SLLDC/G/19 - Procurement of Supply, Component 3: Request for Single Stage - One IBRD / 81450 Post Limited 5,500.00 5,223.48 Signed 2019-11-17 2019-11-14 2019-12-22 2019-11-25 2020-01-05 Delivery and Installation of Implementation Support Quotations Envelope Renewal License for Autodesk AutoCAD Software LK-MOMWD-108647-GO- RFB / Purchasing of software Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 75,000.00 0.00 Canceled 2020-09-21 2020-09-26 2020-10-26 2020-11-16 2020-12-07 2021-01-06 with training related to RTC Drainage Management Envelope system - Phase II LK-MOMWD-180003-GO- DIR / MCUDP/SLLRDC/G/18- Pending Component 1: Flood and K/IX Procurement of Supply & IBRD / 81450 Post Direct Selection Direct 20,000.00 0.00 Implementati 2021-05-05 2021-05-12 2021-06-09 2021-07-09 Drainage Management Delivery of Mike Modelling on Package LK-MOMWD-117790-GO- RFB / SLLRDC/G/18-J II - Pending Component 1: Flood and Supply and installation of IBRD / 81450 Post Direct Selection Direct 400,000.00 0.00 Implementati 2021-05-20 2021-06-03 2021-07-08 2021-10-06 Drainage Management forecasting and control for on SCADA - Phase II LK-MOMWD-40332-GO-RFB Pending / SLLRDC/G/18-D - Supply Component 1: Flood and Single Stage - One IBRD / 81450 Post Request for Bids Open - National 250,000.00 0.00 Implementati 2021-04-29 2021-05-06 2021-06-05 2021-06-26 2021-07-10 2021-09-08 and installation of utility and Drainage Management Envelope on operational facilities for RTC LK-MOMWD-40083-GO-RFQ / SLLRDC/G/18-E Supply, Pending Component 1: Flood and Single Stage - One Installation and IBRD / 81450 Post Request for Bids Open - National 350,000.00 0.00 Implementati 2021-04-27 2021-05-04 2021-06-03 2021-07-03 2021-07-17 2021-10-15 Drainage Management Envelope Commissioning of Display on System for New RTC Building LK-MOMWD-206588-GO- RFQ / MCUDP/SLLDC/G/19-A Pending - Procurement of Supply, Component 3: Request for Single Stage - One IBRD / 81450 Post Limited 6,500.00 0.00 Implementati 2020-11-26 2020-12-06 2020-12-20 Delivery and Installation of Implementation Support Quotations Envelope on Renewal License for Autodesk AutoCAD Software LK-MOMWD-219478-GO- RFB / MCUDP/SLLDC/G/18- S/2021 - Procurement of Supply, Installation, Pending Component 1: Flood and Single Stage - One Commissioning and IBRD / 81450 Post Request for Bids Open - National 800,000.00 0.00 Implementati 2021-04-26 2021-05-03 2021-05-24 2021-06-14 2021-06-28 2021-09-26 Drainage Management Envelope Maintaining of Heating, on Ventilation and Air Conditioning (HVAC) System for RTC Building. NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-25530-NC-DIR / PMU/NC/01 Procurement Services for RTC Center Data Component 1: Flood and Integration and Forecasting IBRD / 81450 Post Direct Selection Direct 623,000.00 148,652.51 Signed 2017-08-21 2017-08-21 2017-08-21 2017-02-28 2020-06-30 Drainage Management from Computer Engineering Department of University of Moratuwa. LK-MOMWD-99203-NC-RFP / MCUDP/PMU/NC/02 - Component 1: Flood and Single Stage - One Procurement of a Payment IBRD / 81450 Post Request for Bids Limited 51,000.00 51,000.00 Signed 2019-02-27 2019-01-21 2019-03-02 2019-03-16 2019-03-19 2019-02-05 2019-04-12 2019-02-27 2020-04-11 Drainage Management Envelope Partner for Google Cloud Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-6554-CS-QCBS / PMU/C/16-A - Consultancy Services for Design Review, Construction Supervision and Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - International 1,000,000.00 1,742,015.24 Signed 2017-02-09 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-04-04 2017-07-17 2017-04-26 2017-08-21 2017-07-11 2018-08-21 Project Management for the Drainage Management Based Selection Design and Building of St. Sebestian North Lock Gates and Pumping Station LK-MOMWD-10544-CS- QCBS / PMU/C/59 Consultancy Services for Design Review, Contract Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - International 689,000.00 1,876,269.38 Signed 2017-03-27 2017-02-22 2017-03-27 2017-05-12 2017-07-04 2017-06-11 2017-08-18 2017-07-11 2017-11-01 2017-08-15 2017-11-23 2017-09-19 2018-07-16 2019-09-29 Management, and Drainage Management Based Selection Construction Supervision of Plant Design Supply and Installation of Pumping Station at Ambatale. LK-MOMWD-1598-CS-QCBS / PMU/C/32 - Consultancy Services for-Construction Supervision & Project Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - National 257,196.42 200,152.73 Signed 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-09-15 2016-06-03 2016-09-15 2016-07-21 2019-02-02 Management in Micro Drainage Management Based Selection Drainage Component (Drains from Kynsey Road & Devi Balika Junction) Page 5 LK-MOMWD-1715-CS-QCBS / PMU/C/38 - Consultancy Component 3: Quality And Cost- Services for Independent IBRD / 81450 Post Open - National 57,147.85 44,235.52 Signed 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-09-19 2016-06-30 2018-06-15 Implementation Support Based Selection Monitoring & Review of Social safeguards LK-MOMWD-1845-CS-QCBS / PMU/C/48 - Consultancy Component 1: Flood and Quality And Cost- Services for Design and IBRD / 81450 Post Open - International 305,343.51 908,154.60 Signed 2016-09-22 2016-09-22 2016-09-30 2016-10-31 2016-11-30 2016-12-15 2017-01-02 2017-09-22 2018-04-02 Drainage Management Based Selection Construction Management for Flushing Gates LK-MOMWD-1841-CS-QCBS / PMU/C/27 - Consultancy Services for Design Review Component 1: Flood and Quality And Cost- Under IBRD / 81450 Post Open - International 305,343.51 1,091,851.19 2016-09-26 2017-03-19 2016-12-21 2017-02-09 2018-03-15 2017-03-08 2018-05-02 2017-04-14 2018-08-27 2017-05-15 2018-10-04 2017-06-01 2018-12-18 2018-10-30 and Contract Management of Drainage Management Based Selection Implementation Kolonnawa Canal Diversion Scheme LK-MOMWD-1833-CS-QCBS / PMU/C/37 - Consultancy Services for Construction Component 1: Flood and Quality And Cost- Supervision and Project IBRD / 81450 Post Open - International 380,000.00 2,119,809.94 Signed 2016-09-21 2016-09-21 2016-09-21 2017-07-04 2016-09-21 2017-09-15 2016-10-03 2018-06-26 2016-11-01 2018-10-29 2016-12-01 2019-01-11 2018-08-30 Drainage Management Based Selection Management for the Construction of St. Sebestian South New Diversion LK-MOMWD-2525-CS-QCBS / PMU/C/04 - Consultancy Component 2: Urban Services for Infrastructure development, infrastructure Quality And Cost- Under Development in Local IBRD / 81450 rehabilitation and capacity Post Open - National 178,125.00 0.00 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 Based Selection Implementation Authorities- Sri building for Metro Colombo Jayawardanepura Kotte local authorities. Municipal Council LK-MOMWD-2526-CS-QCBS Component 2: Urban / PMU/C/06 - Consultancy development, infrastructure Services for Infrastructure Quality And Cost- Under IBRD / 81450 rehabilitation and capacity Post Open - National 107,765.62 77,801.52 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2016-10-11 2012-04-11 2016-10-11 2017-08-31 Development in Local Based Selection Implementation building for Metro Colombo authorities - Kolonnawa local authorities. Urban Council LK-MOMWD-23793-CS- QCBS / PMU/C/21-A - Consultancy Services for Design Review, Construction Component 1: Flood and Quality And Cost- IBRD / 81450 Prior Open - International 2,223,958.00 3,023,425.48 Under Review 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2017-08-04 2018-01-25 2017-08-04 2017-07-25 2020-01-21 Supervision & Project Drainage Management Based Selection Management for the Design & Building of New Mutwal Tunnel & Torrington Tunnel LK-MOMWD-1825-CS-QCBS / PMU/C/21-A - Consultancy Services for Design Review, Construction Supervision & Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - International 1,100,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-10-05 2016-10-31 2016-11-30 2016-12-15 2017-04-26 2017-01-02 2018-04-02 Project Management for the Drainage Management Based Selection Design & Building of New Mutwal Tunnel & Torrington Tunnel LK-MOMWD-1826-CS-QCBS / PMU/C/31 - Consultancy Services for the Construction Component 1: Flood and Quality And Cost- Supervision and Project IBRD / 81450 Post Open - National 483,000.00 336,185.00 Signed 2018-03-09 2016-11-21 2018-04-08 2018-05-22 2018-03-15 2018-06-21 2018-05-02 2018-07-21 2018-09-14 2018-08-18 2018-09-11 2018-09-22 2018-09-27 2019-12-21 Drainage Management Based Selection Management for the Improvements to Norris Canal - Stage I. LK-MOMWD-1838-CS-QCBS / PMU/C/07 - Consultancy Services for Project Component 1: Flood and Quality And Cost- Preparation and IBRD / 81450 Post Open - International 38,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2017-12-29 2018-06-29 Drainage Management Based Selection Implementation Management of Metro Colombo Real Time Control System LK-MOMWD-1835-CS-QCBS / PMU/C/45 - Consultancy Services of Management Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - International 1,000,000.00 0.00 Canceled 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-09-21 2016-10-03 2019-04-01 Consultant for flood & Drainage Management Based Selection Drainage Management Sub Projects LK-MOMWD-1823-CS-QCBS / PMU/C/16-A - Consultancy Services for Design Review, Construction Supervision and Component 1: Flood and Quality And Cost- IBRD / 81450 Post Open - International 1,000,000.00 0.00 Canceled 2016-09-21 2016-09-21 2017-03-27 2017-03-27 2017-03-27 2017-05-04 2017-05-25 2019-05-15 Project Management for the Drainage Management Based Selection Design and Building of St. Sebestian North Lock Gates and Pumping Station LK-MOMWD-10573-CS- QCBS / PMU/C/35 Consultancy Services for Component 1: Flood and Quality And Cost- Contract Management and IBRD / 81450 Post Open - National 206,000.00 0.00 Canceled 2017-04-24 2017-07-03 2018-10-17 2017-08-18 2017-09-15 2017-09-22 2017-10-19 2017-11-16 2018-11-20 Drainage Management Based Selection Construction Supervision of Improvements to Storm Water Drainage at Saunders Place. LK-MOMWD-86996-CS- QCBS / Consultancy services Component 3: Quality And Cost- for Independent monitoring & IBRD / 81450 Post Open - National 25,000.00 0.00 Canceled 2019-05-02 2019-06-01 2019-06-15 2019-07-13 2019-07-27 2019-08-17 2019-08-31 2020-06-26 Implementation Support Based Selection review of Environmental safeguards. (PMU/C/24-A) LK-MOMWD-80061-CS- QCBS / Consultancy services Component 3: Quality And Cost- for independent monitoring & IBRD / 81450 Post Open - National 60,000.00 0.00 Canceled 2019-06-03 2019-07-03 2019-07-17 2019-08-14 2019-08-28 2019-09-18 2019-10-02 2020-06-28 Implementation Support Based Selection review of social safeguards. (PMU/C/38-A) INDIVIDUAL CONSULTANTS Page 6 Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-MOMWD-1922-CS-INDV Component 2: Urban / PMU/C/42 - Individual development, infrastructure Individual Consultancy Services - IBRD / 81450 rehabilitation and capacity Post Consultant Open 21,428.57 16,722.42 Completed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2016-04-01 2017-04-03 2017-03-31 Engineering Consultant for building for Metro Colombo Selection Structural Designs. Eng. Mrs. local authorities. shyama Liyanage LK-MOMWD-1929-CS-INDV / PMU/C/52 - Procurement of Individual Component 1: Flood and Services of Individual IBRD / 81450 Post Consultant Open 49,285.71 38,461.57 Signed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2016-08-01 2017-08-01 Drainage Management Consultant for Micro Selection Tunnelling. LK-MOMWD-2257-CS-INDV / PMU/C/44 - Individual Individual Consultancy Services - Component 3: IBRD / 81450 Post Consultant Open 21,428.57 16,722.42 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2016-02-22 2017-02-21 2018-02-20 Engineering Consultant for Implementation Support Selection Procurement Contract & Claims. LK-MOMWD-2260-CS-INDV / PMU/C/55 - Individual Individual Consultancy Services - Component 3: IBRD / 81450 Post Consultant Open 50,000.00 0.00 Canceled 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2017-10-05 Engineering Consultant for Implementation Support Selection Quality Control & Quality Assurance(QAQC) LK-MOMWD-2261-CS-INDV / PMU/C/41 - Individual Individual Component 3: Consultancy Services - IBRD / 81450 Post Consultant Open 12,857.14 16,722.42 Completed 2016-10-05 2016-10-05 2016-10-05 2016-10-05 2017-01-23 2017-01-25 2018-04-20 Implementation Support Consultant for Land Selection Acquisitions. LK-MOMWD-2379-CS-INDV Individual / PMU/C/51 - Individual Component 3: IBRD / 81450 Post Consultant Open 17,142.85 13,733.90 Completed 2016-10-07 2016-10-07 2016-10-07 2016-10-07 2016-04-28 2017-04-28 2017-04-27 Consultancy Services - Implementation Support Selection Consultant for communication LK-MOMWD-2382-CS-INDV / PMU/C/56 - Individual Individual Consultancy Services - Component 1: Flood and IBRD / 81450 Post Consultant Open 73,714.28 55,852.88 Signed 2016-10-07 2016-10-07 2016-10-07 2016-10-07 2016-08-01 2017-07-05 Engineering Consultant for Drainage Management Selection Flood Control & Water Management. LK-MOMWD-10582-CS-INDV / PMU/C/58 Individual Individual Component 1: Flood and Consultancy Services - IBRD / 81450 Post Consultant Open 50,000.00 16,722.42 Completed 2017-03-27 2017-03-27 2017-04-20 2017-05-04 2017-05-02 2017-10-31 2018-04-30 Drainage Management Consultant for Quantity Selection Surveying. LK-MOMWD-1919-CS-INDV / PMU/C/12 - Individual Consultancy Services - Component 2: Urban Engineering Consultant for development, infrastructure Individual Infrastructure Development IBRD / 81450 rehabilitation and capacity Post Consultant Open 70,360.00 13,377.94 Signed 2016-09-26 2016-09-26 2016-09-26 2016-09-26 2017-01-16 2017-01-16 Component of MCUDP building for Metro Colombo Selection (Individual consultant was local authorities. selected in liaison with WB Officials through Interviews ) LK-MOMWD-39983-CS-INDV Component 2: Urban / PMU/C/42-A - Individual development, infrastructure Individual Consultancy Services - IBRD / 81450 rehabilitation and capacity Post Consultant Open 24,000.00 10,033.45 Signed 2017-12-18 2017-12-23 2017-12-28 2018-01-02 2017-12-15 2020-01-01 Engineering Consultant for building for Metro Colombo Selection Structural Designs. Eng. local authorities. Aravinda Kalugaldeniya LK-MOMWD-39985-CS-INDV Component 2: Urban / PMU/C/57 - Individual development, infrastructure Individual Consultancy Services - IBRD / 81450 rehabilitation and capacity Post Consultant Open 20,000.00 16,722.42 Completed 2017-12-18 2017-12-18 2017-12-18 2017-12-18 2017-01-23 2018-06-22 2018-04-20 Engineering Consultant for building for Metro Colombo Selection Contract Management local authorities. Eng. Jayawickrama LK-MOMWD-39987-CS-INDV / PMU/C/63 Individual Individual Consultancy Services - Component 1: Flood and IBRD / 81450 Post Consultant Open 31,000.00 2,184.13 Signed 2017-12-18 2017-12-18 2017-12-18 2017-12-18 2017-11-15 2020-06-30 Engineering Consultant for Drainage Management Selection Electro Mechanical. Eng. D.E.N. Rajapakshe LK-MOMWD-99192-CS-INDV / PMU/C/64 - Consultancy Individual Component 3: Under Services - Individual IBRD / 81450 Post Consultant Open 21,000.00 32,540.83 2019-02-08 2019-03-01 2019-03-08 2019-03-22 2020-03-21 Implementation Support Implementation Consultant for Contract Selection Management. LK-MOMWD-1928-CS-INDV / PMU/C/43 - Individual Individual Component 1: Flood and Consultancy Services - IBRD / 81450 Post Consultant Open 20,000.00 0.00 Canceled 2016-11-15 2017-01-03 2017-01-24 2017-02-28 2018-02-28 Drainage Management Engineering Consultant for Selection Geo technical; Designs LK-MOMWD-14355-CS-CDS / PMU/C/60 - Procurement of Component 1: Flood and services for RTC center data IBRD / 81450 Prior Direct Selection Direct 430,000.00 0.00 Canceled 2017-12-20 2017-12-30 2018-01-14 2020-06-30 Drainage Management integration and forecasting - Stage II LK-MOMWD-100654-CS- Individual INDV / MCUDP/PMU/C/58-A Component 1: Flood and IBRD / 81450 Post Consultant Open 20,500.00 0.00 Canceled 2019-06-03 2019-06-24 2019-07-01 2019-07-15 2020-06-09 Individual Consultant for Drainage Management Selection Quantity Surveying LK-MOMWD-122406-CS- CDS / MCUDP/PMU/C/38-A - Procurement of Consulting Component 3: IBRD / 81450 Post Direct Selection Direct 100,000.00 90,548.62 Signed 2019-07-15 2019-06-27 2019-07-25 2019-06-27 2019-08-30 2019-09-18 2020-02-26 Services for Independent Implementation Support Monitoring and Review of Safeguards Page 7 LK-MOMWD-122394-CS- INDV / MCUDP/PMU/C-65 - Component 2: Urban Procuremnt of Services of development, infrastructure Individual Individual Consultant for IBRD / 81450 rehabilitation and capacity Post Consultant Direct 15,500.00 20,230.69 Signed 2019-07-15 2019-06-28 2019-07-25 2019-07-18 2019-08-08 2019-09-17 2019-09-05 2019-10-01 2020-03-03 Nature Interpretation and building for Metro Colombo Selection Wetland Education Services at local authorities. Kotte Rampart LK-MOMWD-14371-CS-CDS / PMU/C/61 - Procurement of Component 1: Flood and srevices for Install and IBRD / 81450 Post Direct Selection Direct 250,000.00 0.00 Canceled 2017-09-18 2017-09-28 2018-07-30 2019-12-31 Drainage Management operation of communication for RTC system LK-MOMWD-14377-CS-CDS / PMU/C/62 - Procurement of Component 1: Flood and Pending IBRD / 81450 Post Direct Selection Direct 80,000.00 0.00 2020-09-14 2020-10-05 2020-11-25 2021-01-24 services for discharge Drainage Management Implementation measurement for RTC system Page 8