PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Regional Economic Development Project (RED) Total Finance ($): USD 60,000,000 Project Number: P167428 Project Implementation agency Community Development and Investment Agency of the Kyrgyz Republic (ARIS) Date of the Procurement Plan February 5, 2020 Period covered by this Procurement Plan: September 2020 – December, 2026 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single- Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Kyrgyz Republic Regional Economic Development Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2021-03-03 2021-03-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167428 GPN Date: 2020-09-16 Project Name: Kyrgyz Republic Regional Economic Development Project Loan / Credit No: IDA / 65580 C Executing Agency(ies): ommunity Development and Investment Agency WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-W-RFQ-2021-1 / Improving Regional Economic Pending Request for Single Stage - One 2023-07- Office repair for Osh technical IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementat 2021-06-10 2021-07-23 Quotations Envelope 23 agricultural college Functions ion IDA-REDP-W-RFQ-2021-2 / Improving Regional Economic Pending Request for Single Stage - One 2022-07- Office repair of Laboratory IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementat 2021-06-10 2021-07-23 Quotations Envelope 23 ISTA Functions ion IDA-REDP-W-RFQ-2021-3 / Improving Regional Economic Pending Reconstruction of driving Request for Single Stage - One 2022-07- IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementat 2021-06-10 2021-07-16 fields for Osh technical Quotations Envelope 23 Functions ion agricultural college IDA-REDP-W-RFB-2021-4 / Catalyzing Investments for Pending Provision of tourism services Single Stage - One 2023-09- IDA / 65580 Tourism and Urban Post Request for Bids Open - National 0.00 Implementat 2021-06-10 2021-06-10 2021-07-15 2021-08-05 2021-08-22 and amenities (eg. rest stops) Envelope 11 Development ion along the main circuits IDA-REDP-W-RFQ-2021-8 / Improving Regional Economic Pending Request for Single Stage - One 2023-01- Office repair for Osh IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementat 2021-12-17 2022-01-22 Quotations Envelope 29 technological university Functions ion IDA-REDP-W-RFB-2021-6 / Suleiman-Too Museum and Complex upgrading and Uzgen Museum and grounds Catalyzing Investments for Pending Single Stage - Two 2023-11- upgrading (including infra, IDA / 65580 Tourism and Urban Prior Request for Bids Open - International 0.00 Implementat 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 Envelope 06 services, exhibition Development ion organization, museum site and visitor management plan etc.) IDA-REDP-W-RFB-2021-7 / Catalyzing Investments for Pending Abshir-Ata: Kara-Shoro Park Single Stage - One 2023-12- IDA / 65580 Tourism and Urban Post Request for Bids Open - National 0.00 Implementat 2021-06-13 2021-06-13 2021-08-01 2021-08-22 2021-09-11 Kyrgyz-Ata: infrastructure Envelope 20 Development ion improvement IDA-REDP-W-RFQ-2022-9 / Improving Regional Economic Pending Request for Single Stage - One 2023-07- Office repair of Interdistrict IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementat 2022-06-17 2022-07-30 Quotations Envelope 30 Laboratories Functions ion IDA-REDP-W-RFB-2021-5 / "Osh City downtown and key and Uzgen City urban regeneration (roads, parks Catalyzing Investments for Pending Single Stage - Two 2023-11- and other public spaces, IDA / 65580 Tourism and Urban Prior Request for Bids Open - International 0.00 Implementat 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 Envelope 06 utilities, etc.) (roads, parks Development ion and other public spaces, pedestrian bridges across river, utilities, etc.)" GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-GOODS-RFQ-2020- Improving Regional Economic Pending Request for Single Stage - One 1 / PCs for the office of IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2020-12-20 2021-02-16 2021-08-15 Quotations Envelope information market system Functions on IDA-REDP-GOODS-RFQ-2021- 3 / Printing of materials for development of information market system and for Improving Regional Economic Pending MinAgri, Osh obl Request for Single Stage - One IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2021-08-10 2021-09-18 2021-12-17 administration and 7 Quotations Envelope Functions on laborotories, market fairs, 6 border control points, soil agrochemical map and its e- cadastre and 7 centers IDA-REDP-GOODS-RFQ-2021- 4 / Printing of education materials on veterinary, artificial insemination, Improving Regional Economic Pending mechanization and Request for Single Stage - One IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2021-08-10 2021-09-18 2021-12-17 electrification of agriculture Quotations Envelope Functions on for Osh agricolledge and printing education materials for Osh technological university Improving Regional Economic Pending IDA-REDP-GOODS-RFQ-2021- Request for Single Stage - One IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2021-12-15 2022-01-23 2022-04-23 5 / Tractor with equipment Quotations Envelope Functions on IDA-REDP-GOODS-RFQ-2022- Improving Regional Economic Pending 11 / Special vehicle for Request for Single Stage - One IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2022-02-23 2022-04-23 2022-10-20 testing points of expertise of Quotations Envelope Functions on crops Page 1 IDA-REDP-GOODS-RFB-2023- Improving Regional Economic Pending 15 / Goods for Single Stage - One IDA / 65580 Planning and Regulatory Post Request for Bids Open - National 0.00 Implementati 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 Implementation of acitivities Envelope Functions on suggested by the REDP IDA-REDP-GOODS-RFB-2023- Improving Regional Economic Pending Single Stage - One 16 / Goods for regional IDA / 65580 Planning and Regulatory Post Request for Bids Open - National 0.00 Implementati 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 Envelope online platform development Functions on IDA-REDP-GOODS-RFB-2022- 8 / Office equipment, furniture for laboratory (ISTA) for on testing points of Improving Regional Economic Pending expertise of crops; Office Single Stage - One IDA / 65580 Planning and Regulatory Post Request for Bids Open - International 0.00 Implementati 2022-02-23 2022-02-28 2022-04-11 2022-05-11 2022-06-15 2022-12-12 equipment, furniture for 7 Envelope Functions on sampling points for laboratory testing; Office equipment, furniture for 7 border control points and etc. IDA-REDP-GOODS-RFB-2021- Catalyzing Investments for Pending 7 / Goods for Branding, Single Stage - One IDA / 65580 Tourism and Urban Post Request for Bids Open - International 0.00 Implementati 2021-10-01 2021-10-06 2021-11-17 2021-12-17 2022-01-21 2022-04-21 marketing and promotion Envelope Development on activities for Osh region IDA-REDP-GOODS-RFB-2022- 12 / Abshir-Ata, Kara-Shoro Park, Kyrgyz-Ata: goods for Catalyzing Investments for Pending tourist infrastructure Single Stage - One IDA / 65580 Tourism and Urban Post Request for Bids Open - International 0.00 Implementati 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2023-04-30 upgrading and solid waste Envelope Development on management improvements ; Trucks and bins for Kyrgyz- Ata, Abshyr-Ata, Karashoroo IDA-REDP-GOODS-RFB-2022- 9 / Mechanization and Improving Regional Economic Pending Single Stage - One electrification of agriculture IDA / 65580 Planning and Regulatory Post Request for Bids Open - National 0.00 Implementati 2022-08-11 2022-08-11 2022-08-25 2022-08-28 2022-09-16 2022-12-15 Envelope for Osh technical agricultural Functions on college IDA-REDP-GOODS-RFQ-2022- Improving Regional Economic Pending 10 / Promotion materials for Request for Single Stage - One IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2022-06-26 2022-07-30 2022-11-06 National Stakeholders Quotations Envelope Functions on platform IDA-REDP-GOODS-RFB-2022- 13 / Furniture, goods and Catalyzing Investments for Pending Single Stage - One exibition equipment for IDA / 65580 Tourism and Urban Post Request for Bids Open - International 0.00 Implementati 2022-08-10 2022-08-15 2022-09-26 2022-10-26 2022-11-30 2023-05-29 Envelope Suleimqn-Too and Uzgen Development on museums IDA-REDP-GOODS-RFB-2022- 14 / Ensuring the product Catalyzing Investments for Pending development at the regional Single Stage - One IDA / 65580 Tourism and Urban Post Request for Bids Open - International 0.00 Implementati 2022-03-10 2022-03-13 2022-04-24 2022-05-24 2022-06-28 2022-12-25 level (fairs, exhibitions, PR, Envelope Development on media campaigns, cultural events, forums) IDA-REDP-GOODS-RFB-2021- 2 / Laboratory equipment (for 7 sampling points for laboratory testing, for 7 border control points, for 2 Improving Regional Economic Pending Single Stage - Two phytosanitary laboratories IDA / 65580 Planning and Regulatory Prior Request for Bids Open - International 0.00 Implementati 2021-12-12 2021-12-17 2022-01-28 2022-04-12 2022-05-17 2022-11-13 Envelope under GosStandard, food Functions on kaboratory (Sanepidnadzor), Venerinary Service and CoCommerse and small food laboratories etc... IDA-REDP-GOODS-RFQ-2021- Improving Regional Economic Pending Request for Single Stage - One 6 / Software for information IDA / 65580 Planning and Regulatory Post Open - National 0.00 Implementati 2021-12-12 2022-01-20 2022-04-20 Quotations Envelope market system Functions on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-CQS-2021-1 / Improving Regional Economic Consultant Pending Regional development IDA / 65580 Planning and Regulatory Post Qualification Open - National 0.00 2021-01-25 2021-01-31 2021-03-16 2021-04-15 2021-05-20 2021-08-18 Implementation platform implementation Functions Selection IDA-REDP-CS-CQS-2021-4 / Consulting company to Consultant Strengthening Agri-Food Pending conduct market studies. IDA / 65580 Post Qualification Open - National 0.00 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-15 2023-10-05 Supply Chains and SMEs Implementation Methodology for National Selection Stakeholders Platform IDA-REDP-CS-CQS-2021-5 / Survey on agribusiness value Consultant Strengthening Agri-Food Pending chain. Survey on diagnostic IDA / 65580 Post Qualification Open - National 0.00 2021-06-29 2021-06-30 2021-07-18 2021-08-17 2021-10-15 2022-01-13 Supply Chains and SMEs Implementation studies. Consulting company Selection for survey Page 2 IDA-REDP-CS-CQS-2021-10 / Consulting company for Development of design documentation and supervision of repair of the Improving Regional Economic Consultant Pending office of Osh technical IDA / 65580 Planning and Regulatory Post Qualification Open - National 0.00 2021-12-20 2021-12-25 2022-02-07 2022-03-21 2022-04-02 2022-10-18 Implementation agriculture college, (including Functions Selection driving fields) and office of Osh technological university, warehouses of seed farms and plemzavod etc... Catalyzing Investments for Consultant IDA-REDP-CS-CQS-2021-9 / Pending IDA / 65580 Tourism and Urban Post Qualification Open - International 0.00 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-03-06 Technical audit Implementation Development Selection IDA-REDP-CS-QCBS-2021-7 Catalyzing Investments for / Tech supervision Quality And Cost- Pending IDA / 65580 Tourism and Urban Post Open - International 0.00 2021-07-23 2021-08-07 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 SulaimanToo and the Uzgen Based Selection Implementation Development Museum IDA-REDP-CS-QCBS-2021-2 / Comprehensive assessment of SulaimanToo and Uzgen Catalyzing Investments for Quality And Cost- Pending museums complexes Detailed IDA / 65580 Tourism and Urban Post Open - International 0.00 2021-08-25 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-08-28 Based Selection Implementation designs and Construction Development Supervision for SulaimanToo and the Uzgen Museum IDA-REDP-CS-QCBS-2021-5 Implementation Support and Quality And Cost- Pending / Company for Preparation of IDA / 65580 Prior Open - International 0.00 2021-05-20 2021-06-10 2021-07-24 2021-08-21 2021-09-20 2021-10-25 2021-11-29 2022-11-29 Monitoring and Evaluation Based Selection Implementation future projects IDA-REDP-CS-QCBS-2021-8 / Company for Catalyzing Investments for Quality And Cost- Pending Branding,marketing and IDA / 65580 Tourism and Urban Post Open - International 0.00 2021-09-23 2021-09-28 2021-11-14 2021-12-04 2021-12-24 2022-01-14 2022-02-10 2022-10-06 Based Selection Implementation promotion activities for Osh Development region IDA-REDP-CS-LCS-2021-1 / Implementation Support and Least Cost Pending IDA / 65580 Post Open - International 0.00 2021-10-15 2021-11-05 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-04-26 2026-08-23 Project audit (financial audit) Monitoring and Evaluation Selection Implementation IDA-REDP-CS-QCBS-2021-9 / Tourism Product Catalyzing Investments for development at the regional Quality And Cost- Pending IDA / 65580 Tourism and Urban Post Open - International 0.00 2022-07-23 2022-08-13 2022-09-26 2022-10-24 2022-11-23 2022-12-28 2023-02-01 2023-07-01 level (fairs, exhibitions, PR, Based Selection Implementation Development media campaigns, cultural events, forums) IDA-REDP-CS-QCBS-2021-6 Catalyzing Investments for Quality And Cost- Pending / Osh City Construction IDA / 65580 Tourism and Urban Post Open - International 0.00 2021-07-23 2021-08-13 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection Implementation Supervision Services Development IDA-REDP-CS-QCBS-2021- 10 / Сonsulting company for M&E to conduct a baseline survey, focus group interviews, etc. collect Implementation Support and Quality And Cost- Pending IDA / 65580 Prior Open - International 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2024-04-20 quantitive and qualitative data Monitoring and Evaluation Based Selection Implementation through the project and then at closing provide the summary with the impact results IDA-REDP-CS-QCBS-2021-3 / Support to department of Improving Regional Economic Quality And Cost- Pending Tourism and regional/local IDA / 65580 Planning and Regulatory Prior Open - International 0.00 2021-06-20 2021-07-11 2021-08-24 2021-09-21 2021-10-21 2021-11-25 2021-12-30 2022-05-29 Based Selection Implementation tourism agencies for Functions improved statistics and data collection IDA-REDP-CS-QCBS-2021- 11 / Consulting company to identify specific supply chain Strengthening Agri-Food Quality And Cost- Pending IDA / 65580 Post Open - International 0.00 2021-07-23 2021-07-28 2021-09-01 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2022-04-09 actors for participation and Supply Chains and SMEs Based Selection Implementation the competitive selection of sub-projects IDA-REDP-CS-QCBS-2021-1 / Training in hospitality Catalyzing Investments for industry for tour guides, tour Quality And Cost- Pending IDA / 65580 Tourism and Urban Prior Open - International 0.00 2021-08-25 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-03-06 operators and accomodation Based Selection Implementation Development managers/staff; Technical support in business planning IDA-REDP-CS-CQS-2021-2 / Improving Regional Economic Consultant Development of Visitors Pending IDA / 65580 Planning and Regulatory Post Qualification Open - National 0.00 2021-06-17 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-01-08 Management Plans for Kyrgyz- Implementation Functions Selection Ata, Abshyr-Ata, Karashoroo IDA-REDP-CS-QCBS-2021-4 / Consulting company for feasibilty studies for SPS Improving Regional Economic Quality And Cost- Pending investments and design of IDA / 65580 Planning and Regulatory Post Open - International 0.00 2021-07-17 2021-08-07 2021-09-20 2021-10-18 2021-11-17 2021-12-22 2022-01-26 2022-07-25 Based Selection Implementation technical specifications for Functions equipment of laboratories, centers and points IDA-REDP-CS-CQS-2021-3 / Improving Regional Economic Consultant Development of Visitors Pending IDA / 65580 Planning and Regulatory Post Qualification Open - International 0.00 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-02-04 Management Plans for Implementation Functions Selection Suleiman Too and Uzgen IDA-REDP-CS-CQS-2021-7 / Desing for tourism site tourism services and Catalyzing Investments for Consultant Pending amenities (eg Desing Abshir- IDA / 65580 Tourism and Urban Post Qualification Open - National 0.00 2021-06-29 2021-07-06 2021-08-19 2021-09-30 2021-10-12 2022-07-14 Implementation Ata: Kara-Shoro Park Kyrgyz- Development Selection Ata: infrastructure improvement) IDA-REDP-CS-CQS-2021-8 / Technical supervision for Catalyzing Investments for Consultant Pending tourism sites (infrastructure IDA / 65580 Tourism and Urban Post Qualification Open - National 0.00 2021-06-29 2021-07-06 2021-08-19 2021-09-30 2021-10-17 2022-04-15 Implementation improvement: Abshir-Ata, Development Selection park Kara-Shoro, Kyrgyz-Ata) Page 3 IDA-REDP-CS-CQS-2021-6 / Catalyzing Investments for Consultant Preparation of detailed design Pending IDA / 65580 Tourism and Urban Post Qualification Open - National 0.00 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-10 2022-01-13 packages for Osh and Uzgen Implementation Development Selection Design packages INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-IC-2021-11 / Improving Regional Economic Individual Pending Local consultant for review of IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2021-12-21 2022-01-23 2022-02-25 2022-03-22 2023-03-17 Implementation legal acts for exports 3 Functions Selection IDA-REDP-CS-IC-2021-12 / Improving Regional Economic Individual Pending Local consultant for review of IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 Implementation legal acts for exports 4 Functions Selection IDA-REDP-CS-IC-2021-13 / Consultant for Development Improving Regional Economic Individual Pending of legal documents of 7 IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 Implementation sampling points for laboratory Functions Selection testing IDA-REDP-CS-IC-2021-1 / Improving Regional Economic Individual Consultant for Regional Pending IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Economic Development Plan Implementation Functions Selection for Osh region IDA-REDP-CS-IC-2021-3 / Improving Regional Economic Individual Pending Consultant for sowtfare IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Implementation desing and on-job training Functions Selection IDA-REDP-CS-IC-2021-4 / Consultant for Development Improving Regional Economic Individual Pending of education materials for Osh IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Implementation technical agricultural college Functions Selection and Osh university IDA-REDP-CS-IC-2021-5 / International consultant for Improving Regional Economic Individual Pending MinAgri, Osh oblast IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Implementation administration and other Functions Selection stakeholders IDA-REDP-CS-IC-2021-6 / Local consultant for for Improving Regional Economic Individual Pending MinAgri, Osh oblast IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Implementation administration and other Functions Selection stakeholders 1 IDA-REDP-CS-IC-2021-7 / Local consultant for for Improving Regional Economic Individual Pending MinAgri, Osh oblast IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 Implementation administration and other Functions Selection stakeholders 2 IDA-REDP-CS-IC-2021-8 / Improving Regional Economic Individual International consultant for Pending IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 review of legal acts for Implementation Functions Selection exports IDA-REDP-CS-IC-2021-2 / Improving Regional Economic Individual Consultant for Development Pending IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2021-09-27 2021-10-27 2021-11-01 2021-12-31 2022-12-26 of the Regional tourism Implementation Functions Selection strategy for Osh region IDA-REDP-CS-IC-2021-10 / Improving Regional Economic Individual Pending Local consultant for review of IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 Implementation legal acts for exports 2 Functions Selection IDA-REDP-CS-IC-2021-9 / Improving Regional Economic Individual Pending Local consultant for review of IDA / 65580 Planning and Regulatory Post Consultant Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2021-05-01 Implementation legal acts for exports 1 Functions Selection Page 4