Jhelum & Tawi Flood Recovery Project (Project ID: P154990) Procurement Summary I. General 1. Project Information: Project Name: Jhelum & Tawi Flood Recovery Project Country: India Project Code: P154990 2. Bank’s approval Date of the procurement Plan: Draft Procurement Plan dated April 24, 2015 Revision 0: Agreed by the Bank on April 25, 2015 Revision 1: March 30, 217 Revision 2: Feb 15 2019 3. Date of General Procurement Notice: September 01 2015 4. Period covered by this procurement plan: next 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Methods and Threshold Category Method of Procurement Threshold (US$ Equivalent) Goods and Non- ICB >3,000,000 consultant services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 500,000 DC As per Para 3.7 of the Bank Guidelines, wherever agreed and with prior agreement with the Bank Force Account As per Para 3.9 of Guidelines Framework As per Para 3.6 of Guidelines Agreements Works and Supply and ICB >40,000,000 Installation NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 1,000,000 carried out through a qualified local contractor selected through shopping (after inviting a minimum of three quotations in response to a written invitation with a minimum of 15 days’ notice period) Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines,  Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Information Technology: All contracts more than US$ 2.0 million equivalent; and • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent  The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. 2. Pre-qualification. Not applicable 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by Project Management Unit JTFRP, J&K, India All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Procurement Manual or Government Procurement Procedures and the Bank Guidelines, the latter shall prevail. 4. Any Other Special Procurement Arrangements: The bid evaluation will be carried out as per agreed timeline in the Procurement Manual.  National Competitive Bidding (NCB): Any contract exceeding shopping threshold shall be procured using NCB method. The model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. The following NCB provisions shall apply: i. Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding. ii. Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. For smaller packages (lesser than US$1 million for Works and US$ 500,000 for Goods), advertisement in state newspapers will be accepted with at least 15 days given for submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. At the Borrower's request, the Bank may agree to the Borrower's use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. vi. For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); vii. For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; viii. The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; ix. Government e-Marketplace (GeM)1 set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. x. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. xi. Two or three envelop system will not be used (expect when suing e- procurement system assessed and agreed by the Bank. xii. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety ("ESHS") risks and impacts.  Force Account: When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the project or a certain government agency has exclusive rights in certain type of works/supply, borrowers may use their own government departments’ personnel and equipment or government owned construction unit may be the only practical method, 1 Use of GeM will be allowed in lieu of RFQ as per following details: • up to INR 50,000 in catalogue mode (viz. any available item could be selected by IA without further competition), provided selected Item/Supplier meeting the requisite quality, specification and delivery period. • up to INR 3 Million from the Supplier having lowest price amongst at least three Suppliers meeting the requisite quality, specification and delivery period. The tools for online bidding and online reverse auction available on GeM may be used by the Purchaser. • up to INR equivalent of US$ 500,000 from the Supplier having lowest price and meeting the requisite quality, specification and delivery period after mandatorily obtaining bids from at least three Suppliers, using online bidding or reverse auction tool provided on GeM. provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the Bank on expenditure as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements: State level rate contracts will be examined by the Bank and if agreed, may also be used as framework agreements. Implementing agencies also have option to set-up new framework agreements as per paragraph 3.6 of Guidelines.  Use of government Institutions and Enterprise: Government owned enterprise or institutions in India may be hired for its unique and exceptional nature if their participation is considered critical to the project implementation. In such cases, the conditions given in clauses 1.13 of Consultant Guidelines shall be satisfied and each case will be subject to prior review by the Bank. The works contracts up to cumulative amount of 37.5 million USD, would be directly executed by the J&K Projects Construction Corporation Ltd., which a Public Sector Undertaking. J&K Projects Construction Corporation Ltd. is executing projects of State as well as Central Government departments. 5. Summary of the Procurement Packages planned during the first 18 months and thereafter: Available on STEP III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Category Method of Procurement Threshold (US$ Equivalent) Consultants’ Services CQS Up to 500,000 SSS Up to 200,000 As per para 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines QCBS/QBS/FBS/LCS for all other cases (i) International shortlist >800,000 (ii) Shortlist may comprise national consultants only Up to 800,000  Prior Review by the Bank. The Bank will prior review the following contracts: o Consulting Services: All contracts more than US$ 1.0 million equivalent for firm; and o Consulting Services: All contracts more than US$ 300,000 equivalent for Individuals. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule: Available on STEP Use of e-procurement portal Procurement of goods works and non-consultancy services shall be conducted using the e- procurement portal www.jktenders.gov.in. All IAs shall use this e-procurement portal for procurement of goods works and non-consulting services. PROCUREMENT India : Jhelum and Tawi Flood Recovery Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-04-27 2019-12-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154990 GPN Date: 2016-11-18 Project Name: Jhelum and Tawi Flood Recovery Project Loan / Credit No: IDA / 56950 Executing Agency(ies): Roads and Building Department (R&B), Jammu and Kashmir WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CDII/1158 / Design and Built 300 bedded new Reconstruction and IPD/OT Block with Spinal Single Stage - Two IDA / 56950 strengthening of critical Prior Request for Bids Open - National 8,923,077.00 12,771,151.27 Signed 2017-06-15 2017-06-25 2017-07-25 2017-09-08 2017-10-03 2020-10-07 Care Centre at Bone & Envelope infrastructure Joint Hospital, Barzulla, Srinagar BRIDGES/KHANABAL / Design and Construction of two additional spans on Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 1,856,923.00 0.00 Canceled 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 either side of existing bridge bridges Envelope at Seer Nambal including the approaches, Anantnag BRIDGES/QAZIGUND / Design and Construction of Bridge (3x30 m) in place of Under Reconstruction of roads and Single Stage - Two 6x20 m washed away IDA / 56950 Post Request for Bids Open - National 1,273,846.00 0.00 Implementati 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 bridges Envelope submersible causeway at on Asajipora Kamad Sadoora road (km 4th), Kulgam BRIDGES/SHOPIAN / Design and Construction of Under Reconstruction of roads and Single Stage - Two Bridge(1x45 mtr) over nallah IDA / 56950 Post Request for Bids Open - National 490,769.00 0.00 Implementati 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 bridges Envelope Rambiara at Kumar Mohalla on Wachi, Shopian BRIDGES/BUDGAM / Design and Construction of Pending Reconstruction of roads and Single Stage - Two double lane Bridge(4x 35 IDA / 56950 Post Request for Bids Open - National 2,227,692.00 0.00 Implementati 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 bridges Envelope mtr Span) at Aripathan on Rutson Bridge, Budgam BRIDGES/BARAMULLA / Design and Construction of Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 476,923.00 0.00 Canceled 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 Bridge at Kalaban, bridges Envelope Baramulla BRIDGES/GANDERBAL / Under Design and Construction of Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 3,076,923.00 3,420,904.46 Implementati 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 two lane Bridge over Nallah bridges Envelope on Sindh at Wayil Ganderbal COLLEGES/BEMINA / Construction of (1) Humanities Block and Reconstruction and Single Stage - Two (2) Staff Room & Meeting IDA / 56950 strengthening of critical Post Request for Bids Open - National 1,538,462.00 0.00 Canceled 2018-07-31 2018-08-05 2018-09-16 2018-11-29 2019-01-03 2019-07-02 Envelope Halls Block infrastructure at Govt Degree College Bemina, Srinagar Page 1 RB/J/SCHOOLS/01 / Re- construction of 2 no. Class Rooms and allied infrastructure in Govt. Reconstruction and Middle School Chibba & 2 Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 124,608.00 0.00 Canceled 2018-08-20 2018-08-30 2018-10-03 2018-11-25 2019-01-10 2019-07-11 no. Class Rooms and allied Envelope infrastructure infrastructure in Govt. Middle School Dhoon in District Jammu under JTFRP. RB/J/SCHOOLS/02 / Reconstruction of schools: 1. Reconstruction and Single Stage - Two PS Gujjar Basti Karnaillay IDA / 56950 strengthening of critical Post Request for Bids Open - National 275,421.00 0.00 Canceled 2018-08-20 2018-08-30 2018-10-11 2018-12-09 2019-01-20 2019-10-24 Envelope chak, 2. MS Makwal, 3. infrastructure MS Pargwal RB/J/SCHOOLS/03 / Reconstruction of schools at Reconstruction and Single Stage - Two : 1. GMS Purana Pind, 2. IDA / 56950 strengthening of critical Post Request for Bids Open - National 253,711.00 0.00 Canceled 2018-08-20 2018-08-30 2018-10-11 2018-12-10 2019-01-14 2019-10-15 Envelope GHS Chak Majra, 3. GPS infrastructure Belicharana COLLEGES/ANANTNAG / Construction of Reconstruction and Single Stage - Two Administrative Block at Govt IDA / 56950 strengthening of critical Post Request for Bids Open - National 414,285.00 0.00 Canceled 2018-10-01 2018-10-06 2018-11-17 2019-01-30 2019-03-06 2019-09-02 Envelope Degree College for Women infrastructure Anantnag COLLEGES/BIJBEHARA / Construction of Additional Reconstruction and Under Single Stage - Two Classroom Block at Govt IDA / 56950 strengthening of critical Post Request for Bids Open - National 1,639,000.00 0.00 Implementati 2018-10-01 2018-10-06 2018-11-17 2019-01-30 2019-03-06 2019-09-02 Envelope Degree College, Bijbehara, infrastructure on Jammu and Kashmir SCHOOLS/SRINAGAR / (1) Construction of two Classrooms with allied works in Govt Middle School, Reconstruction and Single Stage - One Shivpora, Srinagar and (2) IDA / 56950 strengthening of critical Post Request for Bids Open - National 262,240.00 0.00 Canceled 2018-10-03 2018-10-08 2018-11-19 2018-12-19 2019-01-23 2019-07-22 Envelope Construction of two infrastructure Classrooms with allied works in Govt Middle School, Batwara, Srinagar SCHOOLS/PULWAMA / Construction of 4 Classrooms in Govt HS School Samboora, 4 Classrooms in Govt High School Dogripora, Reconstruction and Under 2 Classrooms in Govt P Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 775,657.00 0.00 Implementati 2018-10-03 2018-10-08 2018-11-19 2019-02-01 2019-03-08 2019-09-04 School Afghanipora, 2 Envelope infrastructure on Classrooms in Govt GMSchool Rakhi Litter and 2 Classrooms in Govt GMSchool Batpora Naina--- Pulwama Distt RB/J/BRIDGE/02 / Design & construction of 58m span motorable bridge over Ghordi Pending nallah & 50m span Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 2,310,725.00 0.00 Implementati 2018-10-30 2018-11-04 2018-12-16 2019-02-28 2019-04-04 2020-06-30 motorable bridgeover bridges Envelope on Barmeen nallah along with approach roads at Ramnagar in Udhampur District Page 2 RB/J/SCHOOLS/05 / construction of class rooms Reconstruction and & allied services in (a) HS Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 318,405.00 0.00 Canceled 2018-10-26 2018-10-31 2018-12-12 2019-02-24 2019-03-31 2019-12-26 SK Ber (b) MS Barian Envelope infrastructure Manyal ( c ) MS Upper Manta in udhampur district. RB/J/SCHOOLS/12 / construction of classrooms &allied services in (a)MS Reconstruction and Single Stage - Two Dhara J.W. Gali (b)PS IDA / 56950 strengthening of critical Post Request for Bids Open - National 233,329.00 0.00 Canceled 2018-10-25 2018-10-30 2018-12-11 2019-02-23 2019-03-30 2019-12-25 Envelope Jabran & (c)GMS Khait infrastructure schools at Mendhar in poonch district RB/J/SCHOOLS/04 / construction of classrooms & allied services in (a)HS Reconstruction and Single Stage - Two Gurah Kalayal (b)HSS IDA / 56950 strengthening of critical Post Request for Bids Open - National 233,384.00 0.00 Canceled 2018-11-05 2018-11-10 2018-12-22 2019-03-06 2019-04-10 2020-01-05 Envelope Nagrota Gujru at Billawar infrastructure in Kathua district BRIDGES/KULGAM / Design and Construction of Under Reconstruction of roads and Single Stage - Two Bridge at Kulgam Chamgund IDA / 56950 Post Request for Bids Open - National 5,714,300.00 0.00 Implementati 2018-10-10 2018-10-15 2018-11-26 2019-02-08 2019-03-15 2019-09-11 bridges Envelope road km 1st RD700 (10x40 on Mt) RB/J/BRIDGE/03 / Design & construction of 43m span Pending steel Decked foot Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 204,229.00 0.00 Implementati 2018-11-10 2018-11-15 2018-12-27 2019-03-11 2019-04-15 2020-10-12 Bridge(truss type) over bridges Envelope on AnjiNallah at SukhalGhati in Reasi District J&K RB/J/SCHOOLS/06 / (i) construction of 2no.class rooms & alled services in GMS Prat(ii) construction of Reconstruction and 2no.class rooms & allied Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 203,698.00 0.00 Canceled 2018-11-15 2018-11-20 2019-01-01 2019-03-16 2019-04-20 2020-01-15 services in GPS Envelope infrastructure Rajgarh(iii)construction of 2no.class rooms & alled services in GMS Thichka in Rajouri District J&K SCHOOLS/SHOPIAN / Construction of (1) Two Classrooms in Govt Boys High School Nazneenpora, Reconstruction and Under (2)Two Classrooms in Govt Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 500,000.00 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 UP School Melhura and Envelope infrastructure on (3)Two Classrooms in Govt UP School Reban --- of Shopian Distt.... with allied works. SCHOOLS/KULGAM / Construction of (1) Two Classrooms in Govt Middle School Naikpora Reconstruction and Under Single Stage - Two and IDA / 56950 strengthening of critical Post Request for Bids Open - National 707,143.00 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Envelope (2) Four Classrooms in infrastructure on Govt Girls Higher Secondary School Yaripora --- of Kulgam District.... with allied works. Page 3 SCHOOLS/BUDGAM / Construction of (1) Four Classrooms in Govt Girls HrSec School Magam, Reconstruction and Single Stage - Two (2) Four Classrooms in IDA / 56950 strengthening of critical Post Request for Bids Open - National 292,857.00 0.00 Canceled 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Envelope Govt HrSec Narbal and infrastructure (3) Four Classrooms in Govt High School Sail. --- of Budgam Distt.... with allied works. SCHOOLS/QAZIGUND / Construction of (1) Four Classrooms in Govt Boys High School Verinag, Reconstruction and Single Stage - Two (2) Four Classrooms in IDA / 56950 strengthening of critical Post Request for Bids Open - National 478,571.00 0.00 Canceled 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Envelope Govt Hr Sec School Hakura infrastructure and (3) Four Classrooms in Govt Middle School Gundi Kilam. --- of Anantnag/Kulgam Distt.... SCHOOLS/SUMBAL with allied works. / Construction of (1) Two Classrooms in Govt Middle School Batipora, Naidkhai, (2) Two Classrooms in Reconstruction and Single Stage - Two Govt Boys Hr Sec School IDA / 56950 strengthening of critical Post Request for Bids Open - National 414,286.00 0.00 Canceled 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Envelope Nowgam and infrastructure (3) Four Classrooms in Govt Middle School Bakerpora, Banyari, ---of Bandipora Distt...with allied works. SCHOOLS/BANDIPORA / Construction of Four Reconstruction and Single Stage - One Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 174,286.00 0.00 Canceled 2018-11-01 2018-11-06 2018-12-18 2019-01-17 2019-02-21 2019-08-20 Envelope School Kulhama, Bandipora infrastructure District ... with allied works. SCHOOLS/KHANABAL-I / Construction of (1) Two Classrooms in Govt MS Arwani, (2) Two Classrooms in GMS Hafizabad (3)Two Reconstruction and Under Classrooms in GMS Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 682,129.00 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Subhanpora, (4) Four Envelope infrastructure on Classrooms in Govt HSS Arwani and (5)Four Classrooms in Govt Boys MS HP Tawella of Anantnag Distt...with allied works. SCHOOLS/KHANABAL-II / Construction of (1) Two Classrooms in Govt HS Jablipora (2) Two Classrooms in Govt HSS Reconstruction and Under Wanpoh (3)Two Classrooms Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 638,571.00 0.00 Implementati 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 in GMS Katriteng (4) Four Envelope infrastructure on Classrooms in Boys HSS Bijbehara & (5) Four Classrooms in Girls HSS Bijbehara of Anantnag Distt...with allied works. COLLEGES/AMARSINGH / Reconstruction and Under Construction of Science Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 1,617,650.00 0.00 Implementati 2018-11-20 2018-11-25 2019-01-06 2019-03-21 2019-04-25 2020-10-16 Block at Amarsingh College, Envelope infrastructure on Srinagar Page 4 SCHOOLS/BARAMULLA / Construction of Two Reconstruction and Single Stage - One Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 149,457.00 0.00 Canceled 2018-11-20 2018-11-25 2019-01-06 2019-02-05 2019-03-12 2020-03-11 Envelope School Galibal, Baramulla infrastructure District ... with allied works. SCHOOLS/GDA / Construction of (1)Two Classrooms in Govt PSchool Reconstruction and Qazipora Tangmarg, and (2) Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 381,564.00 0.00 Canceled 2018-11-20 2018-11-25 2019-01-06 2019-03-21 2019-04-25 2020-04-24 Four Classrooms in Govt HS Envelope infrastructure School Lalpora Kunzer .... of Baramulla District ... with allied works. COLLEGES/ANANTNAG-R / Construction of Reconstruction and Under Single Stage - Two Administrative Block at Govt IDA / 56950 strengthening of critical Post Request for Bids Open - National 378,571.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-06-26 2019-07-31 2020-07-30 Envelope Degree College for Women infrastructure on Anantnag COLLEGES/BEMINA-R / Construction of (1) Reconstruction and Under Humanities Block and (2) Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 1,571,430.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-06-26 2019-07-31 2021-01-21 Staff Room & Meeting Halls Envelope infrastructure on Block at Govt Degree College Bemina, Srinagar SCHOOLS/SRINAGAR-R / Construction of (1) two Classrooms with allied works Reconstruction and in Govt Middle School, Single Stage - One IDA / 56950 strengthening of critical Post Request for Bids Open - National 271,430.00 0.00 Canceled 2019-02-25 2019-03-02 2019-04-13 2019-05-13 2019-06-17 2020-06-16 Shivpora, Srinagar and Envelope infrastructure (2)two Classrooms with allied works in Govt Middle School, Batwara, Srinagar SCHOOLS/BUDGAM-R / Construction of (1) Four Classrooms in Govt Girls HrSec School Magam, (2) Reconstruction and Under Single Stage - Two Four Classrooms in Govt IDA / 56950 strengthening of critical Post Request for Bids Open - National 586,320.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-06-26 2019-07-31 2020-07-30 Envelope HrSec Narbal and (3) Four infrastructure on Classrooms in Govt High School Sail. --- of Budgam Distt.... with allied works. SCHOOLS/QAZIGUND-R-I / Construction of (1) Four Classrooms in Govt Boys Reconstruction and High School Verinag, and (2) Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 392,860.00 0.00 Canceled 2019-02-25 2019-03-02 2019-04-13 2019-06-26 2019-07-31 2020-07-30 Four Classrooms in Govt Hr Envelope infrastructure Sec School Hakura --- of Anantnag/Kulgam District.... with allied works. SCHOOLS/QAZIGUND-R-II / Construction of Four Reconstruction and Under Classrooms in Govt Middle Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 212,150.00 0.00 Implementati 2019-02-25 2019-03-02 2019-04-13 2019-06-26 2019-07-31 2020-07-30 School Gundi Kilam. --- of Envelope infrastructure on Kulgam District.... with allied works. SCHOOLS/GDA-R / Construction of (1)Two Classrooms in Govt PSchool Reconstruction and Under Qazipora Tangmarg, and (2) Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 361,564.00 0.00 Implementati 2019-03-15 2019-03-20 2019-05-01 2019-07-14 2019-08-18 2020-08-17 Four Classrooms in Govt HS Envelope infrastructure on School Lalpora Kunzer .... of Baramulla District ... with allied works. Page 5 BRIDGES/BARAMULLA-R / Under Design and Construction of Reconstruction of roads and Single Stage - Two IDA / 56950 Post Request for Bids Open - National 428,570.00 0.00 Implementati 2019-03-15 2019-03-20 2019-05-01 2019-07-14 2019-08-18 2020-08-17 Bridge at Kalaban, bridges Envelope on Baramulla SCHOOLS/BARAMULLA-R / Construction of Two Reconstruction and Single Stage - One Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 149,457.00 0.00 Canceled 2019-03-22 2019-03-27 2019-05-08 2019-06-07 2019-07-12 2020-07-11 Envelope School Galibal, Baramulla infrastructure District ... with allied works. SCHOOLS/SUMBAL-R / Construction of (1) Two Classrooms in Govt Middle School Batipora, Naidkhai, (2) Two Classrooms in Govt Reconstruction and Under Single Stage - Two Boys Hr Sec School Nowgam IDA / 56950 strengthening of critical Post Request for Bids Open - National 543,761.00 0.00 Implementati 2019-03-22 2019-03-27 2019-05-08 2019-07-21 2019-08-25 2020-08-24 Envelope and (3) Four Classrooms in infrastructure on Govt Middle School Bakerpora, Banyari, ---of Bandipora Distt...with allied works. SCHOOLS/BANDIPORA-R / Construction of Four Reconstruction and Under Single Stage - One Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 212,331.00 0.00 Implementati 2019-03-22 2019-03-27 2019-05-08 2019-06-07 2019-07-12 2020-07-11 Envelope School Kulhama, Bandipora infrastructure on District ... with allied works. SCHOOLS/BARAMULLA-R2 / Construction of Two Reconstruction and Single Stage - Two Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 149,457.00 0.00 Canceled 2019-06-25 2019-06-30 2019-08-11 2019-10-24 2019-11-28 2020-11-27 Envelope School Galibal, Baramulla infrastructure District ... with allied works. COLLEGES/WOMENS_M.A ROAD / Construction of Reconstruction and Single Stage - Two Additional Classroom Block IDA / 56950 strengthening of critical Post Request for Bids Open - National 2,071,430.00 0.00 Canceled 2019-06-25 2019-06-30 2019-08-11 2019-10-24 2019-11-28 2021-05-21 Envelope at Govt College for Women, infrastructure M.A Road, Srinagar COLLEGES/WOMENS_M.A ROAD-2 / Construction of Reconstruction and Under Single Stage - Two Additional Classroom Block IDA / 56950 strengthening of critical Post Request for Bids Open - National 2,071,430.00 0.00 Implementati 2019-09-10 2019-09-15 2019-10-27 2020-01-09 2020-02-13 2021-08-06 Envelope at Govt College for Women, infrastructure on M.A Road, Srinagar R&B/FES/BUILDING / Construction of Reconstruction and Under Administrative Block and Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 2,857,150.00 0.00 Implementati 2019-09-30 2019-10-05 2019-11-16 2020-01-29 2020-03-04 2020-08-31 Store Building at the Fire Envelope infrastructure on and Emergency Headquarters Srinagar SCHOOLS/BARAMULLA-R2- 2 / Construction of Two Reconstruction and Pending Single Stage - Two Classrooms in Govt Middle IDA / 56950 strengthening of critical Post Request for Bids Open - National 149,457.00 0.00 Implementati 2019-12-14 2019-12-19 2020-01-30 2020-04-13 2020-05-18 2021-05-18 Envelope School Galibal, Baramulla infrastructure on District ... with allied works. SCHOOLS/QAZIGUND-R-I-2 / Construction of (1) Four Classrooms in Govt Boys Reconstruction and Pending High School Verinag, and (2) Single Stage - Two IDA / 56950 strengthening of critical Post Request for Bids Open - National 392,860.00 0.00 Implementati 2019-12-14 2019-12-19 2020-01-30 2020-04-13 2020-05-18 2021-05-18 Four Classrooms in Govt Hr Envelope infrastructure on Sec School Hakura --- of Anantnag/Kulgam District.... with allied works. Page 6 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CDII/ROADS CONST / Consultancy Services for Preparation of Detailed Reconstruction of roads and Quality And Cost- Under IDA / 56950 Prior Open - National 1,068,538.00 0.00 2017-11-30 2017-12-10 2018-01-23 2018-02-06 2018-02-16 2018-03-23 2018-04-27 2019-04-27 Project Report for Roads bridges Based Selection Implementation and Bridges Works in Jammu & Kashmir INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CDII/18883 / Consultancy Services (Structural & Architectural & for Reconstruction and monitoring during execution) IDA / 56950 strengthening of critical Post Direct Selection Direct 145,659.00 147,124.13 Signed 2017-04-27 2017-05-12 2017-06-22 2018-12-14 --- for works of Higher infrastructure Education Deptt and Fire & Emergency Services Deptt Page 7