The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Jiangxi Farm Produce Distribution System Development (P147009) EAST ASIA AND PACIFIC | China | Agriculture and Food Global Practice | IBRD/IDA | Investment Project Financing | FY 2018 | Seq No: 5 | ARCHIVED on 30-Jan-2020 | ISR39362 | Implementing Agencies: People's Republic of China, Jiangxi Provincial Rural Social Development Bureau within Jiangxi Provincial Department of Agricultu Key Dates Key Project Dates Bank Approval Date: 15-Dec-2017 Effectiveness Date: 15-May-2018 Planned Mid Term Review Date: 11-Jan-2021 Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve the distribution systems of selected farm products in participating counties of Jiangxi. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Strengthening production logistics:(Cost $38.46 M) Component 2: Improving Distribution Logistics:(Cost $140.25 M) Component 3: Support Services for the Whole Distribution System:(Cost $0.45 M) Component 4: Project Management, Monitoring and Evaluation:(Cost $5.18 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO €Satisfactory €Satisfactory Overall Implementation Progress (IP) €Moderately Satisfactory €Moderately Satisfactory Overall Risk Rating €Substantial €Substantial Implementation Status and Key Decisions The pace of project implementation has quickened during the last six months after addressing key implementation bottlenecks and initiating project management systems. Six project counties have signed Risk Sharing Transfer agreements with Jiangxi Rural Commercial Bank under the Partial Credit Guarantee scheme. About 12 market facilitators have been hired in seven project counties. 116 villages now have village farmer information hubs (VFIH) and e-commerce platforms. Training and capacity building were imparted to 6554 farmers (including 2853 women farmers). FSRs have been finalized by all counties, except Anyuan and Taihe, where site selection and land approvals are pending. The preliminary designs for the proposed distribution logistics infrastructure have been completed by Yushan, Huichang, Jing’an, Longnan, and Pengze counties. Huichang has reached the bid-finalization stage while in Yushan, the first market distribution and logistics infrastructure is in the advanced stage of construction. 1/30/2020 Page 1 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance €Low €Low €Low Macroeconomic €Moderate €Moderate €Moderate Sector Strategies and Policies €Moderate €Moderate €Moderate Technical Design of Project or Program €Substantial €Substantial €Substantial Institutional Capacity for Implementation and €Substantial €Substantial €Substantial Sustainability Fiduciary €Moderate €Moderate €Moderate Environment and Social €Moderate €Moderate €Moderate Stakeholders €Moderate €Moderate €Moderate Other -- -- -- Overall €Substantial €Substantial €Substantial Results PDO Indicators by Objectives / Outcomes To improve the distribution system of selected farm products in participating counties of Jiangxi IN00768006 ►Farmers reached with agricultural assets or services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 31,110.00 35,994.00 225,000.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768007 €Farmers reached with agricultural assets or services - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6,202.00 12,240.00 37,300.00 IN00768008 ►Increased number of farmer cooperatives with service access provided by the Project financed markets (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 1/30/2020 Page 2 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Value 0.00 0.00 0.00 700.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768009 ►Increased producers  direct sales of farm produce through Project financed markets (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 Intermediate Results Indicators by Components Component 1: Strengthening production logistics IN00768010 ►Number of farmer cooperatives supported by the proposed Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 19.00 10.00 186.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 There has been a mistake in the methodology for data collection and reporting by CPMOs in the previous progress report. PPMO has since validated the results data and adjusted marginally downwards the Comments: achievement under this indicator in the current report. IN00768014 €New (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9.00 5.00 59.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768016 €Established (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.00 5.00 127.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768018 ►Number of farmers (person days) receiving training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7,500.00 6,554.00 88,600.00 1/30/2020 Page 3 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 There has been a mistake in the methodology for data collection and reporting by CPMOs in the previous progress report. PPMO has since validated the results data and adjusted marginally downwards the Comments: achievement under this indicator in the current report. IN00768020 €Males (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4,900.00 2,853.00 44,300.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768021 €Female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2,600.00 3,701.00 44,300.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768022 ►Number of certified farm products (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 21.00 28.00 155.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768023 ►Number of villages with farmer information hubs for the farmers (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 107.00 116.00 601.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768024 ►Incremental Amount of portfolio made through leverage of the partial guarantee ($million) (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.44 60.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 Component 2: Improving Distribution Logistics IN00768011 ►Number of markets/distribution centers constructed or rehabilitated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 1/30/2020 Page 4 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Value 0.00 0.00 0.00 8.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768015 €Rehabilitated (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768017 €New (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 IN00768019 ►Number of markets/distribution centers connected to provincial market information platform (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 Component 3: Support Services for the Whole Distribution System IN00768012 ►Number of person days for training of market/distribution center managers, staff and traders (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 180.00 11,900.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 Component 4: Project Management, Monitoring and Evaluation IN00768013 ►Percentage of residents in Project areas reporting that they are consulted about the Project (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Jan-2017 31-May-2019 31-Dec-2019 31-Dec-2023 1/30/2020 Page 5 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P147009 IBRD-88000 Effective USD 150.00 150.00 0.00 4.27 145.73 2.8% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147009 IBRD-88000 Effective 15-Dec-2017 05-Mar-2018 15-May-2018 31-Dec-2023 31-Dec-2023 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 1/30/2020 Page 6 of 7 The World Bank Implementation Status & Results Report Jiangxi Farm Produce Distribution System Development (P147009) 1/30/2020 Page 7 of 7