Procurement Plan for Shared Infrastructure for Solar Parks Project I. General 1. Project information: Country : India Borrower : Republic of India Project Name : Shared Infrastructure for solar Parks Project Loan No. : Project Implementing : IREDA, RUMSL Agency (PIA), etc. 2. Bank’s approval Date of the procurement Plan Original : March 9, 2017 3. Date of General Procurement Notice: February 9, 2017 4. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. World Bank review of procurement: The World Bank will prior review (thresholds are based on “Substantial” rating, will be modified if risk rating is changed after assessment by Bank during the project implementation) the following contracts: a) Works including turnkey Supply & Installation of Plant and Equipment and PPP: All contracts more than US$ 10 million equivalent b) Goods, Information Technology and Non-consulting Services: All contracts more than US$ 2 million equivalent First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of LIB, single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18 months implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on Technical Specifications will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Domestic preference is allowed only for Procurement of Goods and Information Technology and not for procurement of Works. Method Threshold Category Method of Procurement (US$ Equivalent) Works International Competitive Bidding > 40,000,000 (ICB) Up to 40,000,000 (with NCB National Competitive Bidding (NCB) conditions) Shopping Up to 100,000 As per paragraph 3.7 of Direct Contracting (DC) Guidelines Public-Private Partnership (PPP) for As per paragraph 3.14 of Works Guidelines As per paragraph 3.9 of Force Account Guidelines As per paragraph 3.6 of Framework Agreement (FA) Guidelines Goods International Competitive Bidding > 3,000,000 and non- (ICB) consultan Limited International Bidding (LIB) wherever agreed by Bank t services National Competitive Bidding (NCB) Up to 3,000,000 (with NCB (NCS) conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA)1 As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines 2. Prequalification. Pre-qualification is not envisaged for any package under the Project. 1/ DGS&D rate contracts may be used as framework agreement (FA) subject to the conditions mentioned under NCB conditions 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Implementation Plan: Not Applicable 5. Retroactive Financing : The project will be seeking retroactive financing, not exceeding US$ 20 million for financing expenditures incurred , in respect of payments for project-related work during project preparation, on or after May 1, 2016. This includes payments to consultants for various preparatory studies, Procurement of goods and works under the project, training and exposure visits (under technical assistance part) and eligible expenditure incurred prior to loan signing. 6. NCB Condition: National competition for the procurement of goods and works according to the established thresholds will be conducted in accordance with paragraphs 3.3 & 3.4 of Section III of the Guidelines and the following provisions: a) Only the model bidding documents for NCB agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) Rate contracts entered into by Directorate General of Supplies and Disposals (DGS&D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures; h) Use of DGS&D rate contracts as Framework Agreement must be reflected in the procurement plan agreed by the Bank for particular goods. Before issuing the purchasing order, the Bank will have to advise the government on carrying out a price analysis on the specific good that is intended to be purchased. If after this due diligence the borrower concludes [and Bank agrees] that the DGS&D rate contract is not suitable, then the borrower will have to proceed using NCB or shopping depending on the value. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders [in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders]. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. i) Two or three envelope system will not be used (except when using e- procurement system assessed and agreed by the Bank). 7. Procurement Packages with Methods and Time Schedule as per Table A [attached below] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: a) Consultancy Services for selection of firms : All contracts more than US$ 1.0 million equivalent; b) Consultancy services for selection of individuals: All contracts above US$ 0.3 million. c) First contract issued by implementing agency [IA] will be subject to prior review irrespective of their value. In addition, the justifications for all contracts to be issued on the basis of single-source or direct contracting will be subject to prior review. The above thresholds are for the initial 18-month implementation period; based on the procurement performance of the project these thresholds may be subsequently modified by Bank. In case of Post Review contracts, the inputs of Bank on TORs will be obtained by project. The procurement plan will be subsequently updated annually (or at any other time if required) and will reflect any change in prior review thresholds. The World Bank will carry out an annual ex-post procurement review of the procurement falling below the prior review thresholds provided above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the loan. Selection Method Method Threshold (USD) Consultants’ Selection Based on Consultants’ Up to 300,000 Services Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ for all other cases Quality-Based Selection (QBS)/ Selection under a Fixed Budget (FBS) (i) International shortlist > 800,000 (ii) Shortlist may comprise national Up to 800,000 consultants only 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: First consultancy selection shall be prior reviewed irrespective of threshold. Refer to sl. No. 4 under Section-II of the procurement plan 4. Consultancy Assignments with Selection Methods and Time Schedule as per Table A [attached below] Table A Procurement Plan of Project Implementing State/Agency (RUMSL) Procurement Plan period: (for first 18 months of the project) (Note : The procurement plan will be revised during the course of implementation of the project, based on Project needs) Rewa Solar Park: Mandsaur Solar Park: PROCUREMENT India : Shared Infrastructure for Solar Parks Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-06-29 2021-03-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154283 GPN Date: 2017-02-09 Project Name: Shared Infrastructure for Solar Parks Project Loan / Credit No: IBRD / 87370, TF / A4639 R Executing Agency(ies): ewa Ultra Mega Solar Limited WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1: Shared IN-RUMSL-19473-CW-RFB / Infrastructure for Solar Parks Contract for construction of (estimated total project cost: Single Stage - One 13,853,575.4 2017-06- 33/220 kV pooling substation IBRD / 87370 Prior Request for Bids Open - National 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2016-07-13 2017-06-29 2017-06-29 2017-06-29 US$198 million of which IBRD Envelope 8 29 along with 220 kV DCDS Loan: US$75 million and CTF transmission line Loan: US$23 million) Component 1: Shared IN-RUMSL-19520-CW-RFB / Infrastructure for Solar Parks Contractor to construct (estimated total project cost: Single Stage - One 13,853,575.4 9,227,020.5 2017-12- 33/220 kV pooling substation IBRD / 87370 Prior Request for Bids Open - National Signed 2017-06-29 2017-06-30 2017-06-29 2017-06-30 2017-06-29 2016-07-08 2017-06-29 2017-06-30 2017-06-29 2016-09-19 US$198 million of which IBRD Envelope 8 1 26 along with 220 kV DCDS Loan: US$75 million and CTF transmission line Loan: US$23 million) Component 1: Shared IN-RUMSL-19620-CW-RFB / Infrastructure for Solar Parks Contract for supply of three (estimated total project cost: Single Stage - One 1,700,717.6 2017-12- IBRD / 87370 Post Request for Bids Open - National 2,484,928.08 Completed 2017-06-30 2016-06-03 2017-06-30 2017-06-30 2016-06-28 2017-06-30 2016-07-13 2017-06-30 2016-09-26 33/220 kV, 100 MVA step up US$198 million of which IBRD Envelope 3 27 transformer. Loan: US$75 million and CTF Loan: US$23 million) Component 1: Shared IN-RUMSL-19621-CW-RFB / Infrastructure for Solar Parks Contract for supply of nine (estimated total project cost: Single Stage - One 5,438,951.1 2017-12- IBRD / 87370 Post Request for Bids Open - National 7,115,924.28 Completed 2017-06-30 2016-05-23 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2016-07-15 2017-06-30 2016-11-30 33/220 kV, 100 MVA step up US$198 million of which IBRD Envelope 2 27 transformer. Loan: US$75 million and CTF Loan: US$23 million) IN-RUMSL-19622-CW-RFB / Contract to design, manufacture, test, deliver, Component 1: Shared install, complete and Infrastructure for Solar Parks commission certain facilities, (estimated total project cost: Single Stage - One 3,530,227.4 Under 2017-12- viz. 33/220 kV pooling IBRD / 87370 Prior Request for Bids Open - National 5,139,098.95 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-15 US$198 million of which IBRD Envelope 2 Review 27 substation consisting Loan: US$75 million and CTF installation of 3X100 MVA Loan: US$23 million) transformers at Rewa along with 220 kV DCDS transmission line IN-RUMSL-19623-CW-RFB / Contract to design, manufacture, test, deliver, Component 1: Shared install, complete and Infrastructure for Solar Parks commission certain facilities, (estimated total project cost: Single Stage - One 3,300,101.3 Under 2017-12- viz. 33/220 kV pooling IBRD / 87370 Prior Request for Bids Open - National 4,831,180.48 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-15 US$198 million of which IBRD Envelope 6 Review 27 substation consisting Loan: US$75 million and CTF installation of 3X100 MVA Loan: US$23 million) transformers, Rewa along with 220 kV DCDS transmission line IN-RUMSL-19624-CW-RFB / Contract to design, manufacture, test, deliver, Component 1: Shared install, complete and Infrastructure for Solar Parks commission certain facilities, (estimated total project cost: Single Stage - One 3,689,253.5 Under 2017-12- viz. 33/220 kV pooling IBRD / 87370 Prior Request for Bids Open - National 5,348,837.24 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2017-06-30 2016-07-08 2017-06-30 2017-06-30 2017-06-30 2016-12-15 US$198 million of which IBRD Envelope 1 Review 27 substation consisting Loan: US$75 million and CTF installation of 3X100 MVA Loan: US$23 million) transformers, Rewa along with 220 kV DCDS transmission line IN-RUMSL-188629-CW-RFB / Development of Nine 33/2220 kV substations for 1500 MW Component 1: Shared Solar parks in Madhya Pradesh Infrastructure for Solar Parks - two substations for 550 MW (estimated total project cost: Single Stage - Two 25,400,000.0 2022-05- IBRD / 87370 Prior Request for Bids Open - National 0.00 Canceled 2020-08-17 2020-08-19 2020-10-03 2020-10-24 2020-11-07 Agar Solar Park, three US$198 million of which IBRD Envelope 0 31 substations for 450 MW Loan: US$75 million and CTF Shajapur Solar Park, and three Loan: US$23 million) substations for 500 MW Neemuch Solar Park IN-RUMSL-190687-CW-RFB / Contract for supply of Component 1: Shared fourteen 33/220 kV 110 MVA Infrastructure for Solar Parks Under and three 33/220 kV 50 MVA (estimated total project cost: Single Stage - Two 14,000,000.0 2022-04- IBRD / 87370 Prior Request for Bids Open - National 0.00 Implementat 2020-09-07 2021-01-06 2020-09-09 2021-01-22 2020-10-24 2020-11-07 2020-11-21 step-up transformers for 550 US$198 million of which IBRD Envelope 0 05 ion MW Agar Solar Park, 450 MW Loan: US$75 million and CTF Shajapur Solar Park, and 500 Loan: US$23 million) MW Neemuch Solar Park IN-RUMSL-190742-CW-RFB / Component 1: Shared Contract for construction of Infrastructure for Solar Parks Under transmission lines from eight (estimated total project cost: Single Stage - Two 10,000,000.0 2022-04- IBRD / 87370 Prior Request for Bids Open - National 0.00 Implementat 2020-09-07 2021-01-18 2020-09-09 2021-02-11 2020-10-24 2020-11-07 2020-11-21 33/220kV substations to ISTS US$198 million of which IBRD Envelope 0 05 ion substations for Agar, Shajapur Loan: US$75 million and CTF and Neemuch Solar Park Loan: US$23 million) Page 1 IN-RUMSL-191683-CW-RFB / Development of Eight 33/2220 kV substations for Component 1: Shared 1500 MW Solar parks in Infrastructure for Solar Parks Madhya Pradesh - two Under (estimated total project cost: Single Stage - Two 25,400,000.0 2022-06- substations for 550 MW Agar IBRD / 87370 Prior Request for Bids Open - National 0.00 Implementat 2020-09-10 2020-12-23 2020-09-12 2021-01-28 2020-10-27 2020-11-17 2020-12-01 US$198 million of which IBRD Envelope 0 14 Solar Park, three substations ion Loan: US$75 million and CTF for 450 MW Shajapur Solar Loan: US$23 million) Park, and three substations for 500 MW Neemuch Solar Park GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Shared IN-RUMSL-19552-GO-RFB / Infrastructure for Solar Parks Contract for supply of nine (estimated total project cost: Single Stage - One 33/220 kV, 100 MVA step up IBRD / 87370 Post Request for Bids Open - National 7,115,924.28 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-12-26 US$198 million of which IBRD Envelope transformer for 750 MW of Loan: US$75 million and CTF Rewa Project Loan: US$23 million) Component 1: Shared IN-RUMSL-19554-GO-RFB / Infrastructure for Solar Parks Contract for supply of three (estimated total project cost: Single Stage - One 33/220 kV, 100 MVA IBRD / 87370 Post Request for Bids Open - National 2,484,928.08 0.00 Canceled 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-06-29 2017-12-26 US$198 million of which IBRD Envelope transformer for Mandsaur Loan: US$75 million and CTF Solar Project Loan: US$23 million) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RUMSL-121568-CS-LCS / Component 2 - Technical Survey for Identification of Assistance (Estimated Cost: Least Cost Under available ravine land for solar TF / A4639 Post Open - National 43,000.00 0.00 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-26 2020-01-23 2019-09-23 2019-10-07 2019-10-16 2019-10-30 2020-03-28 US$2 million of which CTF Selection Implementation project in 3 selected districts Grant:US$2 million) of the state IN-RUMSL-121569-CS-LCS / Component 2 - Technical Base line survey of Land in Assistance (Estimated Cost: Least Cost Under TF / A4639 Post Open - National 43,000.00 0.00 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-29 2020-01-23 2019-09-26 2019-10-10 2019-10-17 2019-10-31 2020-03-29 Sagar district for new solar US$2 million of which CTF Selection Implementation projects/parks Grant:US$2 million) IN-RUMSL-121572-CS-QCBS Component 2 - Technical / Preparing a Business Plan Assistance (Estimated Cost: Quality And Cost- TF / A4639 Post Open - National 43,000.00 152,725.18 Signed 2019-08-12 2019-12-26 2019-08-12 2020-01-15 2019-08-14 2020-01-23 2019-09-13 2020-06-22 2019-09-27 2020-07-16 2019-10-04 2020-07-16 2019-10-18 2020-12-31 2020-04-15 for RUMSL and Institutional US$2 million of which CTF Based Selection Capacity Building of RUMSL Grant:US$2 million) IN-RUMSL-121574-CS-QCBS / Planning publicity, Component 2 - Technical communication strategies and Assistance (Estimated Cost: Quality And Cost- Under TF / A4639 Post Open - National 200,000.00 0.00 2019-08-12 2019-12-15 2019-08-12 2020-01-15 2019-08-16 2020-01-23 2019-09-20 2019-10-04 2019-10-14 2019-10-30 2021-10-29 media plan for RUMSL's US$2 million of which CTF Based Selection Implementation existing, ongoing and future Grant:US$2 million) project IN-RUMSL-121576-CS-QCBS Component 2 - Technical / Management System for Assistance (Estimated Cost: Quality And Cost- Under TF / A4639 Post Open - National 200,000.00 0.00 2019-08-12 2019-12-26 2019-08-12 2019-08-20 2019-09-19 2019-10-03 2019-10-10 2019-10-24 2020-03-12 managing large solar parks US$2 million of which CTF Based Selection Implementation and projects Grant:US$2 million) IN-RUMSL-125718-CS-LCS / Component 2 - Technical Refurbishment of existing Assistance (Estimated Cost: Least Cost RUMSL website to make it TF / A4639 Post Open - National 36,000.00 15,264.40 Signed 2019-08-12 2019-12-15 2019-08-12 2020-01-15 2019-08-19 2020-01-23 2019-09-17 2020-06-22 2019-10-01 2020-07-16 2019-10-12 2020-09-01 2019-10-24 2020-10-05 2020-03-22 US$2 million of which CTF Selection dynamic and more user Grant:US$2 million) friendly IN-RUMSL-126037-CS-LCS / Component 2 - Technical Power system assessment and Assistance (Estimated Cost: Least Cost Pending TF / A4639 Post Open - National 28,570.00 0.00 2019-08-12 2019-08-12 2019-08-27 2019-09-25 2019-10-09 2019-10-17 2019-10-31 2020-02-28 planning for renewable energy US$2 million of which CTF Selection Implementation integration in MP Grant:US$2 million) IN-RUMSL-182192-CS-QCBS / Environment and Social Component 2 - Technical Baseline Survey for Assistance (Estimated Cost: Quality And Cost- Identification of Land for TF / A4639 Post Open - National 71,000.00 0.00 Canceled 2020-07-14 2020-11-16 2020-07-14 2020-08-13 2020-08-13 2020-08-20 2020-08-27 2020-09-10 2021-02-07 US$2 million of which CTF Based Selection Proposed Solar Park in Cluster Grant:US$2 million) – 1. Morena, 2. Chattarpur, District in Madhya Pradesh IN-RUMSL-182192-CS-QCBS- 2 / Environment and Social Component 2 - Technical Baseline Survey for Assistance (Estimated Cost: Quality And Cost- Identification of Land for TF / A4639 Post Open - National 71,000.00 0.00 Under Review 2021-01-28 2021-01-22 2021-01-28 2021-01-30 2021-02-24 2021-03-03 2021-03-11 2021-03-28 2021-08-15 US$2 million of which CTF Based Selection Proposed Solar Park in Cluster Grant:US$2 million) – 1. Morena, 2. Chattarpur, District in Madhya Pradesh INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 IN-RUMSL-129224-CS-INDV / Hiring of safeguards experts Component 2 - Technical to monitor and report on Individual Assistance (Estimated Cost: Pending safeguards/ESMP TF / A4639 Post Consultant Open 28,600.00 0.00 2019-09-05 2019-10-24 2019-11-14 2019-12-19 2020-06-16 US$2 million of which CTF Implementation implementation at various Selection Grant:US$2 million) solar parks (ongoing and pipeline) IN-RUMSL-216493-CS-INDV / Hiring of Environment Component 2 - Technical Individual Expert for implementation of Assistance (Estimated Cost: Pending TF / A4639 Post Consultant Open 46,285.00 0.00 2021-01-28 2021-02-24 2021-03-03 2021-03-17 2024-03-16 the Environmental Safeguards US$2 million of which CTF Implementation Selection for World Bank funded solar Grant:US$2 million) park projects. IN-RUMSL-217011-CS-INDV Component 2 - Technical / Hiring of Social Expert for Individual Assistance (Estimated Cost: Pending implementation of the Social TF / A4639 Post Consultant Open 46,285.00 0.00 2021-02-01 2021-02-26 2021-03-03 2021-03-17 2024-03-16 US$2 million of which CTF Implementation Safeguards for World Bank Selection Grant:US$2 million) funded solar park projects. Component 2 - Technical IN-RUMSL-225984-CS-INDV Individual Assistance (Estimated Cost: Pending / Hiring of Environment TF / A4639 Post Consultant Open 64,285.00 0.00 2021-03-23 2021-04-21 2021-04-28 2021-05-15 2024-05-14 US$2 million of which CTF Implementation Expert Selection Grant:US$2 million) Component 2 - Technical Individual IN-RUMSL-225994-CS-INDV Assistance (Estimated Cost: Pending TF / A4639 Post Consultant Open 64,285.00 0.00 2021-03-23 2021-04-21 2021-04-28 2021-05-15 2024-05-14 / Hiring of Social expert US$2 million of which CTF Implementation Selection Grant:US$2 million) Page 3